Planeación de la producción de triciclos modelo AM-206

Indented Bill of Materials


Number per
Item name Level Indented BOM
parent
Triciclo 0 1 Triciclo
Ensamble de rueda frontal 1 1 Ensamble de rueda frontal
Ensamble de rueda trasera 1 1 Ensamble de rueda trasera
Rueda 2 2 Rueda
Manubrio 2 1 Manubrio
Sistema de freno 2 1 Sistema de freno

Distinct items 6

Minimum
Triciclo Lead time 1 Safety Stock 10 Lot size 1 0
quantity
Semana 1 2 3 4 5 6 7 8 9 10
Gross requirements 0 0 0 0 0 0 0 20 100 0
Scheduled receipts
On Hand Inventory 0 0 10 10 10 10 10 10 10 10 10
NET POQ Req 10 0 0 0 0 0 0 20 100 0
Planned receipts 10 0 0 0 0 0 0 20 100 0
Planned orders 0 0 0 0 0 0 20 100 0 0

Ensamble de Minimum
Lead time 1 Safety Stock 0 Lot size 1 0
rueda frontal quantity
Semana 1 2 3 4 5 6 7 8 9 10
Gross requirements 0 0 0 0 0 0 20 100 0 0
Scheduled receipts 0 0 0 0 0 0 0 0 0 0
On Hand Inventory 40 40 40 40 40 40 40 40 20 0 0
NET POQ Req 0 0 0 0 0 0 0 80 0 0
Planned receipts 0 0 0 0 0 0 0 80 0 0
Planned orders 0 0 0 0 0 0 80 0 0 0

Ensamble de Minimum
Lead time 1 Safety Stock 0 Lot size 1 0
rueda trasera quantity
Semana 1 2 3 4 5 6 7 8 9 10
Gross requirements 0 0 0 0 0 0 20 100 0 0
Scheduled receipts 0 0 0 0 0 0 0 0 0 0
On Hand Inventory 15 15 15 15 15 15 15 15 0 0 0
NET POQ Req 0 0 0 0 0 0 5 100 0 0
Planned receipts 0 0 0 0 0 0 5 100 0 0
Planned orders 0 0 0 0 0 5 100 0 0 0
Minimum
Rueda Lead time 1 Safety Stock 0 Lot size 1 0
quantity
Semana 1 2 3 4 5 6 7 8 9 10
Gross requirements 0 0 0 0 0 10 200 0 0 0
Scheduled receipts 0 0 0 0 0 0 0 0 0 0
On Hand Inventory 10 10 10 10 10 10 10 0 0 0 0
NET POQ Req 0 0 0 0 0 0 200 0 0 0
Planned receipts 0 0 0 0 0 0 200 0 0 0
Planned orders 0 0 0 0 0 200 0 0 0 0

Minimum
Manubrio Lead time 1 Safety Stock 0 Lot size 1 0
quantity
Semana 1 2 3 4 5 6 7 8 9 10
Gross requirements 0 0 0 0 0 5 100 0 0 0
Scheduled receipts 0 0 0 0 0 0 0 0 0 0
On Hand Inventory 20 20 20 20 20 20 20 15 0 0 0
NET POQ Req 0 0 0 0 0 0 85 0 0 0
Planned receipts 0 0 0 0 0 0 85 0 0 0
Planned orders 0 0 0 0 0 85 0 0 0 0

Minimum
Sistema de freno Lead time 1 Safety Stock 0 Lot size 1 0
quantity
Semana 1 2 3 4 5 6 7 8 9 10
Gross requirements 0 0 0 0 0 5 100 0 0 0
Scheduled receipts 0 0 0 0 0 0 0 0 0 0
On Hand Inventory 30 30 30 30 30 30 30 25 0 0 0
NET POQ Req 0 0 0 0 0 0 75 0 0 0
Planned receipts 0 0 0 0 0 0 75 0 0 0
Planned orders 0 0 0 0 0 75 0 0 0 0