You are on page 1of 2

YOUR GUIDE TO OBTAINING

AN ELECTRICAL CONNECTION
There are three primary utility providers that supply electrical power in Ras Al Khaimah. They are the
Federal Electricity and Water Authority (FEWA), Utico and Al Ghail Power LLC. Below is a simple step-by-
step guide designed to walk you through the process of connecting your electricity through the power
provider that fits your needs.

APPOINT A FEWA-LICENSED CONSULTANT


1 Your first step is to appoint 1. Drawings for lighting
a consultant from a list of 2. Power layout
FEWA-authorised consultants. 3. Calculation of load
Your consultant will prepare 4. Single line diagram
the following: 5. Setting layout plan

OBTAIN APPROVALS ON THE DRAWINGS


2 Once the drawings are prepared, your consultant will submit the drafts to RAK FTZ for
preliminary approval. After RAK FTZ’s approval, your consultant will submit the drawings
to FEWA for the final approval.

INSTALL ELECTRICAL WIRING


3 After the final approval on the drawings has been obtained, your contractor can begin
installing the electrical wiring and complete a RAK FTZ electrical connection form.

YOUR GUIDE TO OBTAINING AN ELECTRICAL CONNECTION 1/2


YOUR GUIDE TO OBTAINING AN ELECTRICAL CONNECTION

CONNECTION REQUESTED FROM

FEWA UTICO OR AL GHAIL


OBTAIN A SUBMIT
4 NO-OBJECTION 4 DOCUMENTATION
CERTIFICATE (NOC) TO RAK FTZ
FROM RAK FTZ FOR After completion of the electrical
THE ELECTRICAL wiring, you will submit the following
documents to RAK FTZ:
CONNECTION
1. Documents and drawings
After completion of the electrical
stamped by contractor
wiring, you can request an
2. Drawing approval from FEWA
electricity connection NOC from
3. Passport copy and Emirates ID
RAK FTZ, addressed to FEWA.
4. Trade licence & lease agreement
The NOC can be requested via
with RAK FTZ
email at sc@rakftz.com or via
5. An official letter on company
phone at +971 7 204 11 11 letterhead addressed to RAK FTZ,
requesting an NOC for laying
SUBMIT
5
11KV cable from the power utility
DOCUMENTATION to the location

TO FEWA
COLLECT NOC
After receiving the NOC, you will
submit the following documents
5 AND SUBMIT TO
to FEWA in order to set up an ap- POWER PROVIDER
pointment for electrical connection: After receiving the NOC from RAK
1. NOC from RAK FTZ FTZ, you can submit it to the power
2. Documents and drawings provider to set up an appointment
stamped by contractor for electrical connection.
3. Drawing approval from FEWA
4. Passport copy and Emirates ID
5. Trade licence & lease agreement
with RAK FTZ

RAK FREE TRADE ZONE AUTHORITY GOVERNMENT OF RAS AL KHAIMAH


Call: +971 7 2041111 Visit: www.rakftz.com Follow: / rakftz

YOUR GUIDE TO OBTAINING AN ELECTRICAL CONNECTION 2/2

You might also like