Rafi Bhai Slab Work Estimation.

G Singaram
Pillar holes ₹ 36,000
pudding work ₹ 12,000
miller charges ₹ 10,000
centring ₹ 97,500
salaq iron ₹ 240,000
cement ₹ 120,000
kankar 12mm ₹ 45,000
Sand Godari ₹ 80,000
kankar 40mm ₹ 15,000
bendadu stone ₹ 18,000
Moram ₹ 120,000
electric work ₹ 11,000
oil penda plaster,covering ₹ 2,000
dr fixit liquid ₹ 3,000
lift and millar ₹ 30,000
mestri work slab day ₹ 10,000
bricks ₹ 16,000
labour charges ₹ 210,000
sides and shuttering ₹ 12,000
transportation ₹ 10,000
miscellenous ₹ 10,000
septic tank and watertank ₹ 40,000
₹ 1,147,500