Employer Requirements
Construction Progress Reporting
Document Number: 00-000000-000000-NEO-PCO-EMR-000005
2. Monthly Report
The Employer will issue a Project Calendar to the Contractor within 30 days of Project Award.
This Project Calendar will show the monthly report progress cut-off’s which shall occur on a Friday to
align with a weekly progress cut-off.
The CONTRACTOR shall submit a Monthly Progress Report to the Employer by COB on the 5th
working day following the monthly report progress cut-off.
3. Weekly Report
This CONTRACTOR Weekly Report progress cut-off shall occur on a Friday.
The CONTRACTOR shall submit a Weekly Progress Report to the Employer by COB on the 2nd
working day following the weekly report progress cut-off.
The Weekly Report shall include the following: