Professional Documents
Culture Documents
NR/L2/CIV/003/FormC:
Certificate of Design and Check for temporary works.
Temporary works 1
Description
Location
ELR Mileage
Asset Nr OS grid ref
Proposed Design Check (insert, I, II or III)
temporary works Category
Proposed works description
NR/L2/CIV/003/FormC:
Certificate of Design and Check for temporary works.
The designer is to confirm the temporary works methodology accords with that
envisaged by the Permanent Works Designer in the Form A, else list any variation
here with reasoning.
1.4 Temporary works
The Temporary Works Designer is to describe temporary works needed to facilitate
compliance with the DIA, such as the provision of temporary footbridges, hoardings,
alternative means of escape, phasing, and such like, where applicable.
The Temporary Works Designer is to consider impact from other disciplines on the
provision for temporary works, e.g., for services and other equipment supported on
temporary works.
The Temporary Works Designer is to review permanent works designs to ensure that
the Permanent Works Designer’s requirements for temporary works construction
methodology and sequencing have been accommodated, where applicable.
The Temporary Works Designer shall be satisfied that all temporary works designs
have been adequately designed and checked for stability at all times, so as not to
import risk of collapse during erection, use or deconstruction. This shall be
demonstrated to the satisfaction of the PE (B&C) and DPE.
1.5 Proposals for the staging of the Design and Design Check submissions
The designer is to confirm the temporary works staging accords with that envisaged
by the Permanent Works Designer in the FormA, else list any variation here with
reasoning.
1.6 Design criteria and design statement
1.6.1 General
The methodology that is to be adopted in the Design is to be stated here including
the proposed methods of analysis. Where relevant, reference is to be made to
NR/L2/CIV/003/F1990 to NR/L2/CIV/003/F1994 & NR/L2/CIV/003/F1997 and
decisions on the options/choices recorded.
NR/L2/CIV/003/FormC:
Certificate of Design and Check for temporary works.
Provide demonstration that such variations have been applied for and agreed in
accordance with NR standard NR/L2/CSG/STP001/04
NR/L2/CIV/003/FormC:
Certificate of Design and Check for temporary works.
NR/L2/CIV/003/FormC:
Certificate of Design and Check for temporary works.
16. A Geotechnical Design Report, which meets the requirements of BS EN 1997 and
NR/L3/CIV/071 is available. This Report justifies the selection of the Geotechnical
Design parameters and outlines any further work required for implementation.
Assumptions have been verified or measures for verification of assumptions have
been incorporated in the detailed design.
17. A plan of geotechnical related construction supervision and monitoring (including
details of items to be checked during construction or requiring maintenance or
monitoring) have been incorporated in the detailed design and meet the
requirements of BS EN 1997.
18. The Design complies with structure clearance and platform stepping distance
requirements.
19. Important Design matters not covered by standards are identified.
20. The proposals are economical and sustainable
21. The proposals have considered requirements for environmental and sustainable
development. The design has adequately considered the results and actions
required from the Environmental and Social Appraisal and the Environmental and
Social Management Plan, where required by NR/L2/ENV/015.
22. The proposed works will not compromise the structural robustness of any existing
structures.
23. The proposals have considered requirements for environmental and sustainable
development.
24. All materials specified in the design of structures are compatible with the intended
application and environment. This includes, but is not limited to:
fixing metallic structures to masonry with studs bonded with resin, grout or
other chemical bonding products
fixing design is to current standards and guidance
design and installation comply with manufacturer’s requirements, are
compatible with substrate and includes appropriate verification testing
building fabric design and associated fixings are appropriate for the
security risk and associated requirements
suitable and sufficient investigation, as far as reasonably practical, has
been carried out to determine that materials to be used will be compatible.
25. Design calculations have been completed where applicable and checked in
accordance with the Design Check Category(s) agreed in this submission
26. Design and design check calculations will be provided for incorporation into the
Project Health and Safety File.
27. The proposals have considered requirements for environmental and sustainable
development.
28. The selection of post-installed anchors in concrete and masonry meet the
requirements of BS 8539.
29. A completed IDC certificate has been provided with this design to comply with
NR/L2/RSE/02009 clause 15.3
OFFICIAL
NR/L2/CIV/003/FormC Issue 2, March 2022
NR/L2/CIV/003/FormC:
Certificate of Design and Check for temporary works.
I confirm that the criteria specified in NR/L2/CIV/003 have been considered and
certify that reasonable professional skill and care have been used with the objective
of checking that this temporary works Design:-
(a) is submitted on behalf of
insert name and address of the organisation responsible for the Design,
(b) Meets with the indicative temporary works requirements described in the FormA
reference …………………………..
signed by
………………………………………………………..on……………………where
applicable
Insert name of Project Engineer and date
(c) complies with the Design standards, codes and methods stated in this
Certificate
A list of all applicable Design standards are to be provided with this detailed
design submission, in Appendix A1.2.
A list of all requirements for NR/L2/CIV/003/F1990 to F1997 have been
considered and the selected options/choice recorded on this detailed
design submission, in Appendix A1.3
(d) unless identified in 1.3 and 1.8, (i) the Design complies with all relevant standards
and is delivered in accordance with the CR-T, Requirements documents and (ii) the
deliverables identified within the CR-T/Requirements documents will be completed
and submitted in support of this submission.
(e) Where variations to NR and other standards are necessary, applications to
NR/L2/CSG/STP001/04 have been made and accepted by NR.
OFFICIAL
NR/L2/CIV/003/FormC Issue 2, March 2022
NR/L2/CIV/003/FormC:
Certificate of Design and Check for temporary works.
PART 2: CHECK
Checking organisation………….……………………..........................................................
I certify that reasonable professional skill and care have been used in checking the
Design identified in PART 1 of this Certificate, with the objective of checking that the
Design
(a) complies with Part 1 and Appendix A of this certificate
(a) complies with the Design standards, codes and methods stated in this
submission (including any stated variations) and with any additions stated in
PART 1 of this Certificate: the justification given for these additions is
acceptable.
I confirm that the Design was checked as stated below and that the Design Check
has been carried out with the level of independence specified in NR/L2/CIV/003 as
listed below.
Description of associated Description of Design Check
permanent works asset proposed temporary Category
works
Signed Title
OFFICIAL
NR/L2/CIV/003/FormC Issue 2, March 2022
NR/L2/CIV/003/FormC:
Certificate of Design and Check for temporary works.
NR/L2/CIV/003/FormC:
Certificate of Design and Check for temporary works.
Signed Title
Name (print) Date
To be signed by the Project Engineer (Building and Civil Engineering)
Signed Title
Name (print) Date
To be signed by other responsible person (if applicable)
OFFICIAL
NR/L2/CIV/003/Form C Issue 1
NR/L2/CIV/003/FormC:
Certificate of Design and Check for temporary works.
Document reference Revision
Page ... of ...
GRIP Stage Date
Signed Title
Name (Print) Date
To be signed by the Asset Manager (Structures)
Signed Title
Name (Print) Date
To be signed by the Asset Manager (Geotechnical)
Signed Title
Name (Print) Date
To be signed by the Asset Manager (Drainage)
Signed Title
Name (Print) Date
To be signed by the Asset Manager (Buildings)
Page 10 of 12
OFFICIAL
NR/L2/CIV/003/Form C Issue 1
NR/L2/CIV/003/FormC:
Certificate of Design and Check for temporary works.
Document reference Revision
Page ... of ...
GRIP Stage Date
APPENDIX A
A1.1 LIST OF BUILDINGS AND CIVILS ENGINEERING ASSETS AFFECTED BY THE
TEMPORARY WORKS
1. Asset No 1 (add description, ELR and mileage)
2. Asset No 2 (add description, ELR and mileage)
3. Asset No 3 (add description, ELR and mileage)
4. Asset No 4 (add description, ELR and mileage)
Provide details for each asset (or group of assets where applicable) by completing
the following boxed heading and A1.1 to A1.4.
Asset No 1
Description
Location
ELR Mileage
Asset Nr OS grid ref
Page 11 of 12
OFFICIAL
NR/L2/CIV/003/Form C Issue 1
NR/L2/CIV/003/FormC:
Certificate of Design and Check for temporary works.
Document reference Revision
Page ... of ...
GRIP Stage Date
Provide reports for all geotechnical investigation used to justify the design, including
the proposals for the verification on parameters used in the design whilst
undertaking execution of the works.
Page 12 of 12