TRIANGLE BUILDERS

P.O Peringandoor
PH : 9388426494,9061134369

FACTORY MESS HALL


Description No L B D Qty

1 Removing old tiled roof


2 35.00 3.50 245.000 M²
TOTAL 245.000
245.00 M² @ 300.00 /-M² 73,500.00
Removing old brick work
2

partition wall 4 3.81 0.25 2.5 9.525


TOILET door 2 0.9 0.25 2.5 1.125
toilet walll 2 7.96 0.25 2.5 9.950
toilet walll 4 2.54 0.25 2.5 6.350
wash area 1 6 0.6 0.6 2.160
TOTAL 26.950 M³
26.95 m³ @ 1800.00 /- m³ 48,510.00
3 Removing RCC roof
toilet roof 1 9 3 0.1 2.700
lintel 2 7.96 0.24 0.15 0.573
lintel 4 2.54 0.15 0.15 0.229
TOTAL 3.502 M³
3.50 M³ @ 3000.00 /-M³ 10,505.16
4 Removing floor concrete
passage 1 44 1 0.075 3.300
toilet 1 7.96 2.54 0.075 1.516
floor 1 34.32 3.81 0.075 9.807
TOTAL 77.687 M³
77.69 M³ @ 500.00 /-M³ 38,843.38
5 Removing rr foundation
toilet 2 7.96 0.6 0.6 5.731
TOTAL 5.731 M³
5.73 m³ @ 600.00 /- m³ 3,438.72

Page 1 of 12 06/01/2023
6 Removing old plastering
4 34.32 2.50 343.200
8 4.00 2.50 80.000
TOTAL 423.200
423.20 M² @ 70.00 /-M² 29,624.00
EARTH work for toilet wall
7
1 7.96 0.6 0.6 2.866
2.87 M³ @ 450.00 /-M³ 1,289.52

RR foundation for toilet


8 wall
1 7.96 0.6 0.6 2.866
2.87 M³ @ 3500.00 /-M³ 10,029.60

9 Brick work
upper wall on lintel 2 34.32 0.2 0.45 6.178
upper wall on lintel 3 4 0.2 0.45 1.080
toilet 1 7.96 0.2 2.6 4.139
TOTAL 7.258 M³
7.26 M³ @ 9000.00 /-M³ 65,318.40
10 RCC lintel
2 34.32 0.24 0.15 2.471
3 4 0.24 0.15 0.432
2 4 0.2 0.24 0.384
TOTAL 3.287 M³
3.29 M³ @ 14000.00 /-M³ 46,018.56
11 Rainforcement for lintel
2 34.32 4 0.395 108.451
3 4 4 0.395 18.960
1 0.7 360 0.222 55.944
1 7.96 4 0.395 12.577
2 4 4 0.888 28.416
TOTAL 224.348 kg
224.35 kg @ 96.00 /-kg 21,537.41

CC 1:3:6 using 20mm


broken stone including
12 watering curing etc

Page 2 of 12 06/01/2023
mess hall 1 34.32 3.81 0.075 9.807
wash area 1 6 1.2 0.075 0.540
TOTAL 10.347 m2
10.35 M³ @ 8000.00 /- M³ 82,775.52

Plastering with CM 1:4, 12


13 mm thick 1 coat

4 34.32 2.80 384.384


compound wall 1 73.00 1.50 109.500
4 3.81 2.80 42.672
TOTAL 536.556 m2
536.56 M² @ 400.00 /- M² 214,622.40
Roofing with GP tubular
roof members and GI
powder coated trafford
14 sheet including necessary
overlap etc complete

1 32.3 1.5 48.450


TOTAL 48.450 M²
48.45 M² @ 1400.00 /-M² 67,830.00
Roofing with GP tubular
roof members and GI
powder coated trafford
sand witch sheet including
15 necessary overlap etc
complete

2 36 4 288.000
TOTAL 288.000 m2

288.00 M² @ 2400.00 /- M² 691,200.00


16 PVC GUTTERS
east and west side 2 34.00 68.000
north and south side 1 32.00 32.000
TOTAL 100.000 m
100.00 M @ 340.00 /- m 34,000.00
15 mm th cement board for
17 passage

passage 1 35.00 1.80 63.000


TOTAL 63.000 M²
63.00 M² @ 1300.00 /- M² 81,900.00

Page 3 of 12 06/01/2023
Gate gi tubular members
18 with gi mesh

1 5.7 1.5 8.550

TOTAL 8.550 M²
8.55 M² @ 1600.00 /- M² 13,680.00
Floor finishing
19

mess hall 1 34.32 4.00 137.280


wash area 1 6.00 1.20 7.200
TOTAL 144.480 M²
144.48 M² @ 1100.00 /- M² 158,928.00
Dadoing Walls with glazed
20 tiles

toilet wll tile 1 7.96 2.10 16.716


wash basin 1 6.00 1.00 6.000
TOTAL 22.716 M²
22.72 M² @ 1000.00 /- m² 22,716.00
BASIN PANNEL WORK FOR
21 ROOM PARTITION

2 3.81 2.40 18.288


TOTAL 18.288 M²
18.29 M² @ 1800.00 /- M² 32,918.40
Aluminium partion work
22

passage 1 3.81 1.20 4.572


fixed 1 1.20 1.50 1.800

TOTAL 6.372 M²
6.37 M² @ 2900.00 /- M² 18,478.80
Aluminium window work
23

mess hall 2 1.50 1.20 3.600


TOTAL 3.600 m²
3.60 m² @ 3500.00 /- m² 12,600.00
Aluminium door work
24
3 0.90 2.10 5.670
TOTAL 5.670 m²
5.67 m² @ 3900.00 /- m² 22,113.00
Pvc door work
25

Page 4 of 12 06/01/2023
2 0.90 2.10 3.780
TOTAL 3.780 m²
3.78 m² @ 1450.00 /- m² 5,481.00
26 Stainless steel wash basin
1 3.00 3.000
3.00 @ 15000.00 /- 45,000.00
27 SINK TAP
3 4.00 12.000
12.00 @ 1200.00 /- NOS 14,400.00
28 110 mm pvc went coul
1 2.00 2.000
2.00 @ 200.00 /- NOS 400.00
29 110 mm pvc pipe
1 5.00 5.000
5.00 @ 500.00 /- m 2,500.00
25 dia mm pvc pipe
29
1 25.00 25.000
25.00 @ 200.00 /- M 5,000.00

30
60 mm pvc pipe

1 25.00 25.000
25.00 @ 400.00 /- m 10,000.00
31 steel graitings
3 5.00 15.000
15.00 @ 200.00 /- m 3,000.00
Paving block
32

passage 1 35.00 1.10 38.500


1 32.00 1.30 41.600
80.100
80.10 m² @ 900.00 /- m² 72,090.00
White cement washing 1
33 coat as per item no

SAME AS PLASTERING 536.556 m²


536.556 m²
536.56 m² @ 30.00 /- m² 16,096.68
Painting with ready mixed
34 plastic emulsion 2 coat

Page 5 of 12 06/01/2023
SAME AS WHITE WASHING 536.556 m²

536.556
536.56 m² @ 90.00 /- m² 48,290.04
35 ENAMAL PAINTING
1 5.7 1.5 8.550
passage 1 35.00 1.5 52.500
TOTAL 61.050 m²
61.05 m² @ 120.00 /-M² 7,326.00
GRAND TOTAL 2,031,960.59

Page 6 of 12 06/01/2023
72

Page 7 of 12 06/01/2023
Page 8 of 12 06/01/2023
Page 9 of 12 06/01/2023
Page 10 of 12 06/01/2023
Page 11 of 12 06/01/2023
.

Page 12 of 12 06/01/2023

You might also like