STEP 1. Circle the Relevant Area STEP 6. Fill out the JSA team details STEP 1 – Circle Relevant Area:
STEP 2. Write in the JSA Title STEP 7. Develop the procedure or Work
STEP 3. Write in the JSA Scope Instruction that includes the critical safe M3 Prefab Maritiem Other: KED MTC
STEP 4. Define the Job/equipment behaviors to ensure that you complete the
etc. job safely
STEP 5. List any Reference STEP 8. Check for other documents, sign
Materials used off and give the form to your Supervisor
Step 2 JSA Title: Painting
Date made: 10-Sep-2022 JSA Made by:Carlos Orasji Document (JSA) name: Sandblasting/Painters
Date revised: 29- Sep- 2022 JSA Approved by: HSE supervisor (Sherief Rodjan) Version: 2.0
STEP 6 – List the JSA Team Members:
Name Position Industry Job
Experience Experience
Carlos Orasji Fleet 14 6
Supervisor
Date made: 10-Sep-2022 JSA Made by:Carlos Orasji Document (JSA) name: Sandblasting/Painters
Date revised: 29- Sep- 2022 JSA Approved by: HSE supervisor (Sherief Rodjan) Version: 2.0
1 Site preparation and Poor planning • Supervisor and Supervisor and the
Inspection contractor shall conduct joint site Contractor
inspection to identify hazards.
• The overall cable layout shall be
prepared
2 Before connecting the Trip and fall hazard • Wear appropriate PPE Sandblasters and
air hoses • Remove all obstacle /cleanup painters
procedure/inspect the hoses
• Refer to the operation and service
manuals of the manufacturer
3 Sandblasting • High pressure • Physical check on hose condition Sandblasters
• Noise • Secure hoses and relief valve in safe
• Exposure to dust working condition
• Earing protection
• Protective clothing
• Functional test (Gradually turn on)
• Blasting hood
• Workers most wear the required PPE
• Adequate ventilation
Depressurize the system , by using
4 Coating • Leaks • Ensure the correct PPE is used
manometer(testpoint), Painters
• slips • Safety classes must be worn at all time
• eye injury • Check for correct setup, tighten all
fittings
• Ensure safety trigger lock is operational
and locked machine is turned of
• Use scaffold for spraying, not ladders
• Spill kit must be always available
• Adequate ventilation
•
Date made: 10-Sep-2022 JSA Made by:Carlos Orasji Document (JSA) name: Sandblasting/Painters
Date revised: 29- Sep- 2022 JSA Approved by: HSE supervisor (Sherief Rodjan) Version: 2.0
5 House keeping • Health hazard • Drinking location must be in Supervisor, contractor,
• Environmental pollution good hygienic conditions Sandblasters and
• Housekeeping must be done prior to Painters
closing of working permit
• All unused materials must be removed
from site daily and dispose of only in
an approved dumping area
SIGN OFF
(All personnel involved in performing the work shall enter their names below and sign to confirm they have read, understood, and will comply with
the conditions of the JSA).
Name Role in team (e.g., Company Signature Mobile #
driver)
Date revised: 29- Sep- 2022 JSA Approved by: HSE supervisor (Sherief Rodjan) Version: 2.0