P.T. ATMINDO

Our Reference Date


JL. SEI BELUMAI NO. 30 KM 2.4
31OF23.559E 16/05/2023 DESA DAGANG KELAMBIR T.G. MORAWA
Our Client Number 20362 DELI SERDANG
Indonesia

INQUIRY

Dear Sirs,

Please let us have your best quotation with proforma invoice, packaging included, for the following material :

CAPEX 2024

N Quantity Unit Article


6 1 Set Complete unit of 40TPH Water Tube Steam Boiler with Superheater
Steam Evaporation at MCR: 40,000KG/HR
Design Steam Pressure:- 25 bar
Normal Steam Working Pressure:- 21 Bar
Steam Condition at Boiler Outlet:- Superheated Steam 60OC
Water Inlet temperature;- 90 OC
Draft System :- Balanced draft
Fuel: - Palm Kernel Shell, Palm Fibre
Burning Method : Pneumatic Spreader
Grate Type: Fixed pin Hole Grate
Location of Boiler:- In-door
Boiler Efficiency:- About 65% (GCV)
Overload Capacity:- 110%
Blowdown system: Automatic Time -based
Superheater vent:- Automatic vent
Scope of Work :
1. Supply One(1) Boiler unit complete
2. All Supporting Steel Structure, columns, Casing plates, access platforms and
Ladders
3. All flue gas and air ducts, dampers and expansion pieces
4. All fans complete with motor for Induced Draft, Forced draft, Secondary air and Fuel
feeder
5. All Refractory and Castables, Firebricks and Insulation Bricks
6. Boiler Mountings, Valves, and Fittings
7. Set of Fixed pin Hole Grate
8. Boiler Furnace inspection/Manual firing doors and ash doors
9. Two(2) Units Feed water Pump each having a capacity of 130% MCR (Electrically
driven)
10. Automatic Feed Water Regulator to provide Water level control within the Boiler
11. Electrical Panel complete with Mimic Diagram, Starters, and Isolators for all motors
wiring from Boiler Panel to all instruments & Equipments
12. Mild Steel Chimney
13. Multi Cyclone Dust Collector
14. One(1) Air Compressor
15. One unit Stainless Steel Sampling Cooler
16. Feed Water Piping from Feed Water Pump to Boiler
17. All Drain and blow down piping
18. Boiler Chemicals for initial dring and boil out of boiler

UBS Banque
IBAN CH32 0026 0260 1232 2261 X
SWIFT/BIC UBSWCHZH80A
1/2
Square des Places, 3
CH-1700 Fribourg
SUISSE
SODIMEX FR S.A. TVA: CHE301-532-672
EORI:DE205942345260326
+41 26 4255840
sodimexfr@socfin.com

Our Reference Date


31OF23.559E 16/05/2023
Our Client Number

19. Rotary Steam Blower


20. Auto-blowdown, timer based
21. All Dust & Ash Removal Conveyors

22.Superheater Auto-Vent
23. Boiler Site Installation work.
24. Main Power supply cable to the Boiler electrical control Panel
25. Installation & Commissioning of Softener Plant
26.All Civil work designs for Boiler & Boiler House building (Excluding installation)

7 1 Set Boiler House Building/ Structure

8 1 Set Critical spares for the Boiler

Thank you to send us your quotation as soon as possible.


INCOTERMS : CFR FREETOWN

DESTINATION : Sierra Leone

MAIN REMARKS : - the delivery time


- the option
- a possible discount
Your offer should inform us on :
- the unit and total prices
- the packing details: weight, volume, dimensions
- the country of origin
Thank you very much and best regards,

Patricia ASES
Tél.
E-mail pas@socfin.com

UBS Banque
IBAN CH32 0026 0260 1232 2261 X
SWIFT/BIC UBSWCHZH80A
2/2

You might also like