PT.

CAHAYA BAROKAH MAKMUR


CONTRACTOR, SUPPLIER, HEAVY EQUIPMENT RENTAL & MINING
SITE – SURYA CIPTA MAHAKAM

DAILY REPORT PRODUCTION


22 Juli 2022
HEALTH, SAFETY & ENVIRONMENT
1.1 Safety statistic
Safety Statistics Kepmen 555
Items Near Miss First Aid Medical Lost Time Property Cidera Cidera
Fire Case Mati / Fatality
Case Injuries Treatment Injury Damage Ringan Berat
Today - - - - - - - - -
MTD - - - - - - - - -
YTD - - - - 1 - - - -
1.2 HSE Issue

PRODUCTION PERFORMANCE
Plan Actual Month To Year To ACH / Day ACH/
Activity Plan Daily Ket
Monthly Daily Date Date % Month %
OB REMOVAL BCM 7.679 223.985 2.121 49.782 323.137 28% 22% 1 Fleet
COAL GETTING MT 243 7.091 0 4.698 10.909 0% 66% -
SR BCM/TON 32 32 0 11 30 0% 34% -
FUEL CONSMP PRO LTR 6.920 201.859 2.647 60.263 294.080 38% 30%
FR LTR/BCM 0,88 0,88 1,25 1,13 0,89 71% 78% -
FUEL CONSMP WP LTR 0 588 16.209
TOTAL FUEL CONSMP LTR 2.647 60.851 310.289

STOCK SOLAR LTR 18.988


Note

UNIT ACTIVITY
Shift Activity
ID
Day Night
E-31 Standby OB Removal
E-32 Standby Standby
E-33 OB Removal Standby
E20 Housing Cylinder Arm Stratch Housing Cylinder Arm Stratch
M11 Standby Standby
HD01 AC Hot AC Hot
HD02 OB Removal OB Removal
HD03 OB Removal OB Removal
HD05 OB Removal OB Removal
DT20 Standby Standby
DT22 Standby Standby
DT23 Standby Standby
DT26 Troubleshooting Standby
DT28 Standby Standby
DT30 Troubleshooting Troubleshooting
DT32 Standby Standby
DT34 Standby Standby
D02 Transmission Can't Shifting Transmission Can't Shifting
D16 Kontrak Expired Kontrak Expired
D11 Scrape Jalan dan Disposal Scrape Jalan dan Disposal
MG 02 Excel Bar Patah Excel Bar Patah
VB01 Standby Standby
WP03 Standby Pumping
WP05 Standby Standby

DEPARTEMEN ENGINEERING & QUALITY CONTROL


PT. CAHAYA BAROKAH MAKMUR
CONTRACTOR, SUPPLIER, HEAVY EQUIPMENT RENTAL & MINING
SITE – SURYA CIPTA MAHAKAM

EQUIPMENTS PERFORMANCE
WH PA % UA %
ID TYPE
Plan Daily MTD Plan Daily MTD Plan Daily MTD
E-31 DX520LAC 14 4,0 152,2 90% 100% 100% 67% 17% 29%
E-32 DX520LAC 14 0,0 82,7 90% 100% 95% 67% 0% 16%
E-33 DX520LAC 14 9,0 112,7 90% 100% 86% 67% 54% 21%
E20 ZX 470 14 0,0 0,0 90% 0% 0% 67% 0% 0%
M-11 PC 200 14 2,4 113,8 90% 100% 100% 67% 10% 22%
HD01 HD465-7R 14 0,0 87,3 90% 0% 91% 67% 0% 17%
HD02 HD465-7R 14 9,6 127,7 90% 100% 96% 67% 40% 24%
HD03 HD465-7R 14 8,9 130,3 90% 100% 100% 67% 37% 25%
HD05 HD465-7R 14 9,6 89,0 90% 100% 95% 67% 40% 17%
DT20 FM320TI 14 0,0 61,3 90% 100% 100% 67% 0% 14%
DT22 FM320TI 14 0,0 26,2 90% 100% 100% 67% 0% 6%
DT23 FM320TI 14 0,0 0,0 90% 100% 100% 67% 0% 0%
DT26 FM320TI 14 0,0 16,4 90% 100% 100% 67% 0% 4%
DT28 FM320TI 14 0,0 51,7 90% 100% 100% 67% 0% 11%
DT30 FM320TI 14 0,0 0,0 90% 0% 0% 67% 0% 0%
DT32 FM320TI 14 0,0 65,6 90% 100% 91% 67% 0% 14%
DT34 FM320TI 14 0,0 0,0 90% 100% 100% 67% 0% 0%
D02 D85 SS 14 0,0 0,0 90% 0% 13% 67% 0% 0%
D016 D85 SS 14 0,0 50,0 90% 0% 25% 67% 0% 11%
D011 D85 SS 14 10,6 138,5 90% 100% 67% 67% 44% 26%
MG 02 MG 705 14 0,0 81,5 90% 0% 78% 67% 0% 22%
VB01 Compact 14 0,0 0,0 90% 100% 100% 67% 0% 0%
WP03 Sykess 160 14 21,2 151,7 90% 100% 100% 67% 88% 29%
WP05 Sykess 220 14 0,0 0,0 90% 100% 100% 67% 0% 0%

Note

DELAYS
Actual Month To
Delays Shift Plan Daily Keterangan
Daily Date
Rain & Day Hujan Awal Shift, Hujan Jam 15.15, Hujan Jam 15.20
Hours 3 6 30
Slippery Night -
Day -
OTHERS Hours 4 0 0
Night -

Note
Curah Hujan :
1. Hujan Awal dan Akhir Shift I

DEPARTEMEN ENGINEERING & QUALITY CONTROL