You are on page 1of 1

J BARCELA CONSTRUCTION

33-4 Purok 3 Buntong Palay, Brgy. Silangan


San Mateo Rizal
Contact No.: 09323750027
O9278104226
joelbarcela1977@gmail.com Quotation
To Kekatamu Corporation Date 2-May-23
Attention Arch. Adrian Maliwat Duration
Project Masonry Works & Tubular Grills
Subject Supply of Labor and Tools
Location Christine Village Pasig City

Gentleman,
I am pleased to submit herewith my proposal to undertake additional works
for masonry and installation door jambs & panel.

No. Item Unit Qty Labor Cost


A CHB Laying
Double Wall @ shower room sq.m 27.00 6,750.00
Double Wall @ Hallway sq.m 20.25 5,062.50
Double Wall @ Façade sq.m 39.42 17,776.73
Column Corners ln.m 144 28,800.00
Sub-total 58,389.23
B Plastering
Double Wall @ shower room sq.m 32.40 8,100.00
Double Wall @ Hallway sq.m 24.3 6,075.00
Double Wall @ Façade sq.m 47.304 11,826.00
Column Corners sq.m 144 36,000.00
Cantiliver Beam Exterior Part ln.m 95.82 23,955.00
Plastering of Window Edges ln.m 269.56 40,434.00
Sub-total 126,390.00

C Carpentry
Installation of Door Jambs set 32 35,200.00

Installation of Door Panel and Knobs set 32 48,000.00


Sub-total 83,200.00

Direct Cost 267,979.23


Vat 5% 13,398.96
Total Cost 281,378.19

Submitted by: Conformed by:

You might also like