Date: August 30, 2022

Project: Painting Works (Proscenium by Rockwell)


Location: Makati City
Project Duration: 30 Days
Contractor: JJFP Builders

Item Description Qty Unit Unit Cost Total Cost


1.00 48TH Floor
BULKHEAD IN AREA (M2) 25.71 sq.m 550.00 14,137.75
BULKHEAD IN AREA (M) 19.87 m 550.00 10,930.15
SLAB SOFFIT 211.97 sq.m 550.00 116,584.88
DRY CEILING 172.67 sq.m 550.00 94,966.03
RC WALL 190.93 sq.m 550.00 105,009.03
YTONG 496.92 sq.m 550.00 273,307.10
DRYWALL 221.29 sq.m 550.00 121,707.30

2.00 49TH Floor


BULKHEAD IN AREA (M2) 15.83 sq.m 550.00 8,704.85
BULKHEAD IN AREA (M) 14.55 m 550.00 8,004.15
SLAB SOFFIT 145.89 sq.m 550.00 80,241.70
DRY CEILING 117.33 sq.m 550.00 64,529.85
RC WALL 136.00 sq.m 550.00 74,801.65
YTONG 324.65 sq.m 550.00 178,555.30
DRYWALL 157.14 sq.m 550.00 86,428.65

₱ 1,237,908.38

Validity
10 Days from the date of quotation
Payment Terms
Downpayment 20% and 80% Progress Billing
Mobilization
3 days after receiving Downpayment

Prepared by: Engr Daniel Priela

Conformed by:
Date: August 30, 2022
Project: Painting Works (Proscenium by Rockwell)
Location: Makati City
Project Duration: 25 Days
Contractor: JJFP Builders

Item Description Qty Unit Unit Cost Total Cost


1.00 47TH Floor
BULKHEAD IN AREA (M2) 13.10 sq.m 550.00 7,202.53
BULKHEAD IN AREA (M) 9.98 m 550.00 5,491.48
SLAB SOFFIT 107.34 sq.m 550.00 59,035.08
DRY CEILING 87.35 sq.m 550.00 48,043.05
RC WALL 96.52 sq.m 550.00 53,086.55
YTONG 251.27 sq.m 550.00 138,197.40
DRYWALL 112.14 sq.m 550.00 61,677.00

₱ 372,733.08

Validity
10 Days from the date of quotation
Payment Terms
Downpayment 20% and 80% Progress Billing
Mobilization
3 days after receiving Downpayment

Prepared by: Engr Daniel Priela

Conformed by: