Project: Shree Krishan Higher Secondary School Development Work 2078/079

Address:- Kharipati, Bhaktapur


Sub Work:-Playground Protection and Boundry demarkation Work
Length Width Height
S.N Description of Work No Quantity Unit Rate (Rs) Cost ( Rs) Remarks
m m m

Clearing Grass and removal and dressing and levelling the construction
surface cleraing grass/top soil removal meters inside the periphery of the
1 area, including cutting and filling of samll undolations. By manual Means
(201)

1 31.5 11.5 362.25


1 9 5 45
407.25 Sq.m 10.24 4,170.24

Earthwork in excavation of foundation for boundry wall including removal


2 of stumps and other deterious matter and backfinning with approved
Marerial as per Technical specification by manual means(907)

1 62.2 0.6 0.3 11.196 Cu.m 60.21 674.11

Providing and laying flat brick soiling complete as per Technical


3 Specifications. (H15)

1 62.2 0.23 14.306 Sq.m 823.4 11,779.56

Providing and laying Brick Masonary Work in cement mortar(1:4) in the


required area and above of the existing Stone Masonary Wall complete
4 excluding pointing and plastering , as per Drawing and Technical
Specification (2500)

1 34.7 0.23 0.3 2.3943


1 62.2 0.23 0.45 6.4377

Estimated By: Checked By: Approved By:


Length Width Height
S.N Description of Work No Quantity Unit Rate (Rs) Cost ( Rs) Remarks
m m m
8.832 Cu.m 17790.82 157,128.52

Providing and Laying of Plain Cement Concrete(M15) for Ploe


5
Jamming as per Technical Specification and wherever required (2000)

40 0.23 0.23 0.45 0.9522 Cu.m 12730.79 12,122.26

Providing and Laying of Plain Cement Concrete(M15) over the brick


5
wall as per Technical Specification and wherever required (2000)

1 96.5 0.23 0.075 1.664625 Cu.m 12730.79 21,191.99

Providing and Laying different size of Black Iron Angle ( Making


6
Frame;8'3"*4.75') as per instruction of the site Engineer (151)

Vertical Post ( 50*50*5) 13 6 3.8 (kg/m) 296.4


Horizontal Post ( 40*40*5) 32 6 3 (kg/m) 576
872.4 Kg 150 130,860.00

Providing and Laying G. I wire mesh (10 S.W.G.G.I) of 2"*2" mesh


7
size as per instruction of the site Engineer in the frame (295)

1 96.5 1.4 135.1 Sq.m 641.7 86,693.67

Providing and Applying 1 coat primer and 1 coat of enamel paint in


8
the iron angles as per instruction of site engineer (231)

1 96.5 0.3 28.95


1 76.5 0.2 15.3
44.25 Sq.m 25 1,106.25
Total Cost 425,726.60
15% Contingency 63,858.99
Total Cost after adding Contingency 489,585.59

Estimated By: Checked By: Approved By:


Project: Shree Krishan Higher Secondary School Development Work 2078/079
Address:- Kharipati, Bhaktapur
Sub Work:-Playground Protection and Boundry demarkation Work Near New School
Length Width Height
S.N Description of Work No Quantity Unit Rate (Rs) Cost ( Rs) Remarks
m m m

Providing and Laying of Plain Cement Concrete(M15) for Ploe


1
Jamming as per Technical Specification and wherever required (2000)

13 0.23 0.23 0.3 0.20631 Cu.m 12730.79 2,626.49

Providing and Laying different size of Black Iron Angle ( Making


2
Frame;8'3"*4.75') as per instruction of the site Engineer (151)

Vertical Post ( 50*50*5) 4 6 3.8 (kg/m) 91.2


Horizontal Post ( 40*40*5) 6 6 3 (kg/m) 108
199.2 Kg 150 29,880.00

Providing and Laying G. I wire mesh (10 S.W.G.G.I) of 2"*2" mesh


3
size as per instruction of the site Engineer in the frame (295)

1 34 1.4 47.6 Sq.m 641.7 30,544.92

Providing and Applying 1 coat primer and 1 coat of enamel paint in


4
the iron angles as per instruction of site engineer (231)

1 33.5 0.3 10.05


1 24 0.2 4.8
14.85 Sq.m 25 371.25
Total Cost 63,422.66
15% Contingency 9,513.40
Total Cost after adding Contingency 72,936.06
Project: Shree Krishan Higher Secondary School Development Work 2078/079
Address:- Kharipati, Bhaktapur
Sub Work:-Playground Protection and Boundry demarkation Work Near New School
Length Width Height
S.N Description of Work No Quantity Unit Rate (Rs) Cost ( Rs) Remarks
m m m

Clearing Grass and removal and dressing and levelling the construction
surface cleraing grass/top soil removal meters inside the periphery of the
1 area, including cutting and filling of samll undolations. By manual Means
(201)

1 23.5 38 893
893 Sq.m 10.24 9,144.32

Providing and Laying of Plain Cement Concrete(M15) for Ploe


2
Jamming as per Technical Specification and wherever required (2000)

26 0.23 0.23 0.3 0.41262 Cu.m 12730.79 5,252.98

Providing and Laying different size of Black Iron Angle ( Making


2
Frame;8'3"*4.75') as per instruction of the site Engineer (151)

Vertical Post ( 50*50*5) 7 6 3.8 (kg/m) 159.6


Horizontal Post ( 40*40*5) 11 6 3 (kg/m) 198
357.6 Kg 150 53,640.00

Providing and Laying G. I wire mesh (10 S.W.G.G.I) of 2"*2" mesh


3
size as per instruction of the site Engineer in the frame (295)

1 62 1.4 86.8 Sq.m 641.7 55,699.56

Providing and Applying 1 coat primer and 1 coat of enamel paint in


4
the iron angles as per instruction of site engineer (231)

1 62 0.3 18.6
Length Width Height
S.N Description of Work No Quantity Unit Rate (Rs) Cost ( Rs) Remarks
m m m
1 40 0.2 8
26.6 Sq.m 25 665.00
Total Cost 115,257.54
15% Contingency 17,288.63
Total Cost after adding Contingency 132,546.17
Project: Shree Krishan Higher Secondary School Development Work 2078/079
Address:- Kharipati, Bhaktapur
Sub Work:-Playground Protection and Boundry demarkation Work Near New School
Length Width Height
S.N Description of Work No Quantity Unit Rate (Rs) Cost ( Rs) Remarks
m m m

Earthwork in excavation of foundation for pipe installation including


1 removal of stumps and other deterious matter and backfinning with
approved Marerial as per Technical specification by manual means(907)

1 53 0.6 2 63.6 Cu.m 60.21 3,829.36

Providing and Laying of Hume Pipe ;NP3(200mm) as per Technical


1
Specification and wherever required

1 53 53 R.m 3366.06 178,401.18

Providing and Laying different size of Black Iron Angle ( Making


2
Frame;8'3"*4.75') as per instruction of the site Engineer (151)

Vertical Post ( 50*50*5) 4 6 3.8 (kg/m) 91.2


Horizontal Post ( 40*40*5) 6 6 3 (kg/m) 108
199.2 Kg 150 29,880.00

Providing and Laying G. I wire mesh (10 S.W.G.G.I) of 2"*2" mesh


3
size as per instruction of the site Engineer in the frame (295)

1 34 1.4 47.6 Sq.m 641.7 30,544.92

Providing and Applying 1 coat primer and 1 coat of enamel paint in


4
the iron angles as per instruction of site engineer (231)

1 33.5 0.3 10.05


1 24 0.2 4.8
14.85 Sq.m 25 371.25
Length Width Height
S.N Description of Work No Quantity Unit Rate (Rs) Cost ( Rs) Remarks
m m m
Total Cost 239,197.35
15% Contingency 35,879.60
Total Cost after adding Contingency 275,076.95