Clearing Grass and removal and dressing and levelling the construction
surface cleraing grass/top soil removal meters inside the periphery of the
1 area, including cutting and filling of samll undolations. By manual Means
(201)
Clearing Grass and removal and dressing and levelling the construction
surface cleraing grass/top soil removal meters inside the periphery of the
1 area, including cutting and filling of samll undolations. By manual Means
(201)
1 23.5 38 893
893 Sq.m 10.24 9,144.32
1 62 0.3 18.6
Length Width Height
S.N Description of Work No Quantity Unit Rate (Rs) Cost ( Rs) Remarks
m m m
1 40 0.2 8
26.6 Sq.m 25 665.00
Total Cost 115,257.54
15% Contingency 17,288.63
Total Cost after adding Contingency 132,546.17
Project: Shree Krishan Higher Secondary School Development Work 2078/079
Address:- Kharipati, Bhaktapur
Sub Work:-Playground Protection and Boundry demarkation Work Near New School
Length Width Height
S.N Description of Work No Quantity Unit Rate (Rs) Cost ( Rs) Remarks
m m m