Professional Documents
Culture Documents
BILL OF QUANTITY
Harga Satuan Jumlah Harga
No Description Qty Unit Code
(Rp) (Rp)
II Pekerjaan Baru
1 Skylight Roof 3mm (FUMIRA) Type G680 41,60 ml 303.800 12.638.080 D 1008
2 Plafond gymsum t = 9 mm + rangka hollow galvanis 19,20 m2 169.030 3.245.376 E 1007
3 Kolom dan Balok Praktis 18,30 m' 137.661 2.519.196 B 1030
4 Dinding Bata 5,23 m2 145.099 758.868 C 1006
5 Plester 10,46 m2 79.233 828.777 C 1007
6 Aci 10,46 m2 36.975 386.759 C 1009
7 Cat Exterior (Dulux Weathershield) 5,23 m2 45.448 237.693 G 1001
TOTAL I 29.410.022
II Pekerjaan Baru
1 Atap Zincalume FUMIRA G680 183,84 m2 269.069 49.465.645 D 1029
2 Skylight Roof 3mm (FUMIRA) Type G680 10,60 ml 303.800 3.220.280 D 1008
3 Nok Atap 7,20 ml 186.200 1.340.640 D 1007
4 Flashing Tepi 13,20 ml 171.500 2.263.800 D 1006
TOTAL II 66.087.232
1
Project : PEKERJAAN RENOVASI ENGINEERING
Location : PT. Fajar Surya Wisesa
No : 01/CPK-BQ/FP/UHN-DOM/V/2023
Rev : 1
BILL OF QUANTITY
Harga Satuan Jumlah Harga
No Description Qty Unit Code
(Rp) (Rp)
III PHOTO NO. 3 (Pekerjaan Pengecetan)
Pekerjaan Bongkaran
1 Kupas Cat Existing 5 plong 238,50 m2 20.137 4.802.675 G 1006
2 Bongkaran Jendela Kayu 0,84 m2 123.970 104.135 A 1048
3 Buang Bekas Bongkaran 1,00 m3 122.220 122.220 A 1015
Pekerjaan Baru
1 Plamir Tembok Existing 238,50 m2 27.597 6.581.885 C 1015
2 Cat Interior 238,50 m2 37.191 8.870.054 G 1004
II Pekerjaan Baru
1 Atap Zincalume FUMIRA G680 200,26 m2 269.069 53.883.758 D 1029
2 Skylight Roof 3mm (FUMIRA) Type G680 18,80 ml 303.800 5.711.440 D 1008
TOTAL IV 68.696.268
TOTAL V 18.718.767
2
Project : PEKERJAAN RENOVASI ENGINEERING
Location : PT. Fajar Surya Wisesa
No : 01/CPK-BQ/FP/UHN-DOM/V/2023
Rev : 1
BILL OF QUANTITY
Harga Satuan Jumlah Harga
No Description Qty Unit Code
(Rp) (Rp)
II Pekerjaan Baru
1 Atap Zincalume FUMIRA G680 4 plong 144,00 m2 269.069 38.745.936 D 1029
2 Flashing Tepi 24,00 ml 171.500 4.116.000 D 1006
3 Pasang CNP 125x50x 20x2.3 216,80 Kg 26.411 5.725.905 B 1041
4 Cat CNP 216,80 kg 2.853 618.530 B 1052
5 Mur and bolt 12% 26,02 kg 26.411 687.109 B 1050
6 Rangka Talang + Cat 48,00 ml 475.398 22.819.104 D 1014
7 Talang Baru 48,00 m' 249.900 11.995.200 D 1010
8 Pipa down spot 4"type AW (9 titik) 45,00 m1 197.385 8.882.325 D 1020
9 Elbow 4" 18,00 bh 133.375 2.400.750 D 1025
TOTAL VI 106.647.398
II Pekerjaan Baru
1 Pemadatan 28,88 m2 13.109 378.522 A 1018
2 Plastic cor 28,88 m2 3.530 101.929 A 1029
3 Dowel Chemical (D16-600) 36,00 titik 126.773 4.563.828 B 1067
4 Wiremesh double layer M8 28,88 m2 211.288 6.100.941 B 1058
5 Concreate K-400 Tie beam keliling (30x40cm) 2,58 m3 1.242.934 3.206.770 B 1023
6 Rebar 6D16 + 2D10, D13 – 150 439,17 kg 16.903 7.423.347 A 1033
7 Concrete K400 (tebal = 20cm) 5,78 m3 1.242.934 7.177.944 B 1023
8 Plester beam (camprotan) 8,60 m2 79.233 681.404 C 1007
9 Finish arsir 28,88 m2 42.365 1.223.289 B 1031
10 Cutter beton (sealant) 21,50 ml 25.211 542.037 A 1017
11 Aspal/sealant dilatasi 21,50 ml 55.000 1.182.500
3
Project : PEKERJAAN RENOVASI ENGINEERING
Location : PT. Fajar Surya Wisesa
No : 01/CPK-BQ/FP/UHN-DOM/V/2023
Rev : 1
BILL OF QUANTITY
Harga Satuan Jumlah Harga
No Description Qty Unit Code
(Rp) (Rp)
II Pekerjaan Baru
1 Pemadatan 19,69 m2 13.109 258.051 A 1018
2 Plastic cor 19,69 m2 3.530 69.488 A 1029
3 Dowel Chemical (D16-600) 48,00 titik 126.773 6.085.104 B 1067
4 Wiremesh double layer M8 19,69 m2 211.288 4.159.204 B 1058
5 Concreate K-400 Tie beam keliling (30x40cm) 3,42 m3 1.242.934 4.250.834 B 1023
6 Rebar 6D16 + 2D10, D13 – 150 582,16 kg 16.903 9.840.250 A 1033
7 Concrete K400 (tebal = 20cm) 3,94 m3 1.242.934 4.893.431 B 1023
8 Plester beam (camprotan) 11,40 m2 79.233 903.256 C 1007
9 Finish arsir 19,69 m2 42.365 833.955 B 1031
10 Cutter beton (sealant) 28,50 ml 25.211 718.514 A 1017
11 Aspal/sealant dilatasi 28,50 ml 55.000 1.567.500
JUMLAH 398.786.601
PPN 11% 43.866.526
GRAND TOTAL ( INCLUDE PPN & PPH ) 442.653.127