Professional Documents
Culture Documents
Rev. A B C
Index
First
Issue
Date 16.10.22 27.01.23 16.03.23
TABLE OF CONTENTS
■ For Approval
□ For Information
△
1
If you have comments on this document, please return it with your comments as soon as possible in order to avoid
the delay of schedule for witness test, delivery etc. which might be caused by late return.
△
1 Revised(P-1,2) 25.Jan.2023 M.Shichi K.Fukao T.Tsunematsu A.Wada
No.
Contents of revision Date of Rev. Prepared by Reviewed by Approved by
TGT 1 生管 1 試験 1
Prepared by QM Dept. M.SHICHI 12.DEC.2022
1 ポ技部 生技 1 倉庫 1
調達
2 ポ技部 1 鋳造 1 (製缶 G)
1
Reviewed by QM Dept. K.FUKAO 15.DEC.2022
PEG 工作 1 塗装 1
No.2 Pump 検査 1 輸送 1
Reviewed by T.TSUNEMATSU 15.DEC.2022
Design Dept. 九トリ 控え 1
Page - 3/15
TORISHIMA PUMP MFG. CO., LTD. INSPECTION AND TEST PLAN
Customer : MUTLAQ AL-GHOWARI CO.FOR CONTRACTING LIMITED Service : Main Pump
End User SALINE WATER CONVERSION CORPORATION Pump Size: CDM600x450
Product Number : PU0450618
Attended by
Item Location & Extent Test Procedure Accept Standards Form rd Remarks
3
Torishima Mutlaq SWCC
Party
Mill Certificate R
Material Specification Material Specification R R R Corrosion test report shall be submitted
Upper Half ISO 10474(3.1)
Volute Casing Liquid penetrant (PT)
Sealing surface ASME VIII Div.1 Appendix 7 Test Report S R R R
ASME V Article 6
Mill Certificate
Material Specification Material Specification R R R R Corrosion test report shall be submitted
Lower Half ISO 10474(3.1)
Volute Casing Liquid penetrant (PT)
Sealing surface ASME VIII Div.1 Appendix 7 Test Report S R R R
ASME V Article 6
Mill Certificate
Material Specification Material Specification R R R R Corrosion test report shall be submitted
ISO 10474(3.1)
Shaft
Ultrasonic testing(UT)
Full length ASME Sec. VIII,Div.2 3.3.4 Test Report S R R R
ASME V Article 5
Mill Certificate
Material Specification Material Specification R R R R Corrosion test report shall be submitted
ISO 10474(3.1)
Double Entry Liquid penetrant (PT)
All accessible surface ASME VIII Div.1 Appendix 7 Test Report S R R R
Impeller ASME V Article 6
ISO1940-1(JIS B 0905)
Static balance test ISO1940-1(JIS B 0905) Test Report S R R R
G2.5 or better
Mill Certificate
Casing Wear Ring Material Specification Material Specification R R R R Corrosion test report shall be submitted
ISO 10474(3.1)
Mill Certificate
Impeller Wear Ring Material Specification Material Specification R R R R Corrosion test report shall be submitted
ISO 10474(3.1)
Holding time 30 min. R
Hydrostatic pressure test No leaks Test Report S R R
Design Pressure X 1.5
ISO1940-1(JIS B 0905) △
1
Dynamic balance test ISO1940-1(JIS B 0905) Test Report S R R R
G2.5 or better
ISO 9906(2012) Grade 1 W W
Performance test ISO 9906(2012) Grade 1B Test Report S W Witness test for all pump
JIS B8302(2002)
ISO 9906(2012) Grade 1 S
NPSH test ≦NPSH3 (specified) Test Report W W W For first test pump only
JIS B8302(2002)
Pump bearing temp. JIS B8301(2000) JIS B8301 Test Report S
△ W
1 △ W
1
W For first test pump only
Shaft vibration ISO 10816-7(2009) ISO 10816-7(2009) Table B.1 Test Report S W W W For first test pump only
Assembled Pump For reference only at shop test
Noise JIS B8310(1985) (≦95B(A)at 1m from pomp unit Test Report S W W W Reference only
at site)
No harmful defect & deviation
Visual inspection In-house standard Test Report S R R R
from the drawing
Overall dimension check Drawing Within the tolerance Test Report S R R R
Dismantling inspection In-house standard No damage due to hit or scratch Test Report S R R R
Painting Inspection Check the dry film thickness Painting procedure Test Report S R R R
■ For Approval
□ For Information
If you have comments on this document, please return it with your comments as soon as possible in order to avoid
the delay of schedule for witness test, delivery etc. which might be caused by late return.
△
2 Revised(P-6,8) 16.Mar.2023 M.SHICHI M.YOSHINOUCHI T.TSUNEMATSU S.KANEKO
△
1 Revised(P-1,11) 27.Jan.2023 M.SHICHI K.FUKAO T.TSUNEMATSU A.WADA
No.
Contents of revision Date of Rev. Prepared by Reviewed by Approved by
TGT 1 生管 1 試験 1
Prepared by QM Dept. M.SHICHI 12.DEC.2022
1 ポ技部 生技 1 倉庫 1
2 ポ技部 2 鋳造 1 調達 1
Reviewed by QM Dept. K.FUKAO 15.DEC.2022
PEG 工作 1 塗装 1
No.2 Pump 品管 2 1 輸送 1
Reviewed by T.TSUNEMATSU 15.DEC.2022
Design Dept. 品管 3 1 控え 1
Page - 5/15
P-2
1. SCOPE
This procedure shall be applied to the shop test and inspection for the pump written on the cover.
2. APPLICABLE STANDARD
The following standards shall be applicable.
(1) JIS (Japanese Industrial Standards)
・ JIS B0905(1992) 「Rotating machines – Balance quality requirements of rigid rotors」
・ JIS B8301(2000) 「Rotodynamic pumps-Hydraulic performance acceptance tests-grades 1
and 2」
・ JIS B8302(2002) 「Measurement methods of pump discharge」
・ JIS B8310(1985) 「Methods of a-weighted sound pressure level measurement for pumps」
・ JIS B7505-1(2017) 「Aneroid pressure gauges-Part 1: Bourdon tube pressure gauges」
(2) ISO (International Organization for Standardization)
・ ISO 9906(2012)「Rotodynamic pumps – Hydraulic performance acceptance tests
- Grades 1, 2 and 3」
・ ISO 10816-7(2009)「Mechanical vibration – Evaluation of machine vibration by measurements
on non-rotating parts – Part 7: Rotordynamic pumps for industrial
applications, including measurements on rotating shafts」
・ ISO 1940-1(1986)「Mechanical vibration – Balance quality requirements of rigid rotors – Part 1:
Determination of permissible residual unbalance」
・ ISO 10474(1991) 「Steel and steel products – Inspection documents」
(3) ASME (American Society of Mechanical Engineers)
・ASME B16.5(2017)「Pipe Flanges and Flanged Fittings」
(4) Torishima in-house standard (TES)
Dwg.No. : QA2220575
Page - 6/15
P-3
4. TEST AND INSPECTION PROCEDURE
The tests and inspections given in paragraph 3 shall be carried out in accordance with the procedures and
judgments mentioned below.
pcs.
Part No. Part designation Material
(1 pump set)
*1
1021 UPPER HALF VOLUTE CASING A995 Gr.1B 1
*1
1022 LOWER HALF VOLUTE CASING A995 Gr.1B 1
*1
2100 SHAFT UNS S31803 1
*1
2340 DOUBLE ENTRY IMPELLER A995 Gr.1B 1
*1&*2 UNS S31803
5020.1 CASING WEARING RING 1
+WC Coating
*1&*2 UNS S31803
5020.2 CASING WEARING RING 1
+WC Coating
*1&*2
5030.1 IMPELLER WEARING RING UNS S31803 1
*1&*2
5030.2 IMPELLER WEARING RING UNS S31803 1
[Note]
1) Pitting Corrosion Test (marked with *1) shall be conducted in accordance with
ASTM G48 Method A.
2) Hardness test (marked with *2) shall be included in the Mill Certificate.
Dwg.No. : QA2220575
Page - 7/15
P-4
(2) Applicable standard
Non-destructive examination shall be carried out by qualified inspector who has been qualified in
accordance with JIS Z2305, ISO 9712, ASNT, SNT-TC-1A or other equivalent international
qualification code.
(3) Applicable parts and Method and Acceptance Criteria
Applicable parts and acceptance Criteria shall be in accordance with following table.
Acceptance
Test Applicable Parts /portion Procedure
Criteria
Sealing surface:
ASME ASME SEC.VIII
Liquid Penetrant UPPER HALF VOLUTE CASING
SEC.V,Art.6 Div.1,app.7
Testing(PT) LOWER HALF VOLUTE CASING
All accessible surface: ASME ASME SEC.VIII
DOUBLE ENTRY IMPELLER SEC.V,Art.6 Div.1,app.7
Dwg.No. : QA2220575
P-5
4.4 Static balance test
(1) Purpose
Static balance test shall be carried out to prevent abnormal vibration during operation by removing
the unbalance weight of the rotating parts to be balanced.
Applicable parts : DOUBLE ENTRY IMPELLER
(2) Applicable standard
Static balance test shall be carried out in accordance with JIS B0905(1992) (equivalent to ISO
1940-1(1986))and Torishima in-house standard(TES).
(3) Test equipment
The static balancer shall be used for this test.
(4) Test procedure
The unbalance weight shall be corrected by removing any unbalance portion.
(5) Acceptance criteria
Balance quality of DOUBLE ENTRY IMPELLER shall be G2.5 or better of JIS B0905(1992).
(equivalent to ISO 1940-1(1986))
Dwg.No. : QA2220575
P-6
(4) Test procedure
A) Test equipment
Test arrangement is shown as Fig.1. Equipment position, pipework arrangement and other shall
be determined according to circumstances.
B) Driver
The driver to be used for the test shall be one of the job motor,The speed shall be reduced not
less than 80% of the rated speed due to limitation of power of factory supply.
Translation of test result to rated speed shall be made in accordance with ISO 9906 as
mentioned in para,(k)(b).△
2
C) Testing liquid
The clean water at normal temperature (0℃ to 40℃) shall be used for this test.
D) Test point
A minimum of six (6) test points including the following test points, shall be taken for drawing
the H-Q,ShaftPower and Efficiency curves.
(a) Shutoff
3
(b) Min Flow :APPROX . 3710m /h
3
(c) AOR Min :APPROX . 4011m /h
3
(d) POR Min :APPROX . 4319m /h
3
(e) Rated :APPROX . 5760m /h
3
(f) POR Max :APPROX . 7404m /h
E) Total head (H)
The suction pressure and discharge pressure shall be measured with pressure transducers and
indicators. And total head shall be calculated from the following formula. Four static pressure
tapping shall be provided.
H = 106/ρg X (pd – ps) + Vd /2g - Vs /2g + z
2 2
Dwg.No. : QA2220575
P-7
I) Efficiency (η)
The pump efficiency shall be given from the following formula.
η = ( Pu / P ) X 100 (%)
3
Pu = (1/(60X10 ))ρgQH(kW)
Where, Pu : Water horse power (kW)
P : Shaft power (kW)
ρ : Density of test liquid (kg/m )
3
2
g : Gravitational acceleration (m/s )
3
Q : Rate of flow (m /min)
H : Total head (m)
J) Cavitation test
(a) Test point
Five (5) test points shall be taken at Min Flow,AOR Min.,POR Min.,POR Min.,Rated, and
Max.Flow
(b) Procedure
Cavitation test shall be carried out by controlling the pump suction valve and/or vacuum
tank pressure. Suction pressure shall be controlled to the corresponding pressure equal to
or less than the NPSH3 specified in the PUMP DATA SHEET. Then, the test shall be
performed by observing the pressure drop from normal operating condition(under the
enough NPSHA).
Pressure drop = ((Total head at normal operating - Total head at cavitation test) / Total head at
normal operating) X 100(%)
The NPSH3 shall be given from the following formula.
6 2
NPSH3=10 /ρg X (Pa - Pv) + hs + Vs /2g + Zs
ρ : Density of the test liquid (kg/m )
3
Where,
2
g : Gravitational acceleration (m/s )
Pa: Atmospheric pressure (MPa)
Pv: Vapor pressure (MPa)
hs: Suction head (m)
2
Vs /2g: Suction velocity head (m)
Zs: Suction potential head (m)
K) Correction of the test result
(a) The density of test liquid is different from specified density, thus the test results shall be
corrected by the following formula.
Correction of the test results (ISO 9906(2012) 6.1.1)
PT=P(ρSP/ρ)
Where, ρSP : Specified density (kg/m )
3
Dwg.No. : QA2220575
P-8
△
2 (b) The test results shall be corrected by the following formula when rotating speed is reduced.
Speed correction( ISO 9906(2012) 6.1.1)
QT = Q X (nSP / n)
2
HT = H X (nSP / n)
3
PT = P X (nSP / n)
2
NPSHT = NPSH X (nSP / n)
Where, nSP : Rated speed
n : Test speed
Subscript T : Translated
L) Running test
The items mentioned below shall be observed during the continuous operation of the pump at
the rated flow.
(a) Bearing temperature
The bearing temperature shall be measured by thermometer at bearing housing surface.
(b) Shaft vibration
Shaft vibration displacement shall be measured by vibration sensor at pump BEARING
SHELL portion on shaft as per ISO 10816-7 Annex B at Rated flow.
(c) Noise level
Noise level shall be measured at 1m from the pump unit surface by sound level meter. And
the measuring positions shall be decided according to JIS B8310(1985)” Methods of
a-weighted sound pressure level measurement for pumps”.
(5) Acceptance criteria (after correction of test results)
(a) Flow and total head:Customers Specification
Flow and total head shall satisfy the following mentioned below.
- Flow at the rated head shall lie between a range of -0%~+5% of the rated flow.
- Total head at the rated flow shall lie between a range of -0%~+3% of the rated
total head.
(b) Shutoff head:Customers Specification
Shutoff head shall be between a range of -4%~+5% of the expected maximum total
head(304m).
(c) H-Q curve:Customers Specification
Pumps shall have a continuously rising curve to shutoff.
(d) Shaft power:Customers Specification
Shaft power at the Rated flow shall not exceed +4% of the expected shaft power (5210kW).
(e) Efficiency : ISO 9906(2012) Grade 1B
The efficiency shall be judged from the measured H(Q)-curve where it is intersected by the
straight line passing through the specified duty point Q G, HG and zero of the QH-axis and
from where a vertical line intersects the η(Q)-curve. The pump efficiency shall be higher than
or at least equal to 0.97・ηG (ηG : guaranteed efficiency)
(f) Cavitation test
NPSH3 at the rated flow shall satisfy the specified NPSH3. As a condition, the total head
drop shall be within 3%.
(g) Pump bearing temperature:JIS B8301(2000) Annex 2 Table 1
Bearing temperature shall not exceed allowable temperature rise (ambient
temperature+40℃). However, shall not exceed allowable maximum temperature (75℃).
(h) Shaft Vibration : ISO 10816-7 Annex B Table B.1
Shaft vibration displacement at the Rated flow shall not exceed
0.33×0.295μm peak to peak.△ 2
Dwg.No. : QA2220575
P-9
(i) Noise level
Since pump noise level measurements at shop test have big influence of the noise from the
discharge valve and reflection noise from floor, noise level shall be measured for reference
only at shop test.
(Noise level shall not exceed 95 dB(A) at 1m from pump and motor at site.)
Dwg.No. : QA2220575
P-10
4.9 Dismantling inspection
(1) Purpose
After performance test, inside of the pump shall be checked that there is no damage due to hit or
scratch by operating.
(2) Applicable standard
Dismantling inspection shall be carried out in accordance with Torishima in-house standard (TES).
(3) Procedure
UPPER HALF VOLUTE CASING shall be dismantled and be checked visually..
(4) Acceptance criteria
There shall be no damage due to hit or scratch.
Dwg.No. : QA2220575
P-11
Dwg.No. : QA2220575