23/03/2023, 07:56 Small or Deep Excavation

Small or Deep Excavation


Print

Category: Excavation Hits: 19596

Task / Description Slow   Ave   Fast    Units


 Hydraulic Excavator, 0.3m3 bucket, Sand/Soil 6.7  8.4  9.9   m3/hr

 Hydraulic Excavator, 0.3m3 bucket, Gravel Beds 3.2  4.5  5.0   m3/hr

 Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk 3.3  4.1  5.2   m3/hr

 Hydraulic Excavator, 0.3m3 bucket, Hard Ground 3.3  4.1  5.2   m3/hr

 Hydraulic Excavator, 0.4m3 bucket, Sand/Soil 8.2  10.0  11.7   m3/hr

 Hydraulic Excavator, 0.4m3 bucket, Gravel Beds 7.1  8.7  10.2   m3/hr

 Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk 6.5  8.3  9.4   m3/hr

 Hydraulic Excavator, 0.4m3 bucket, Hard Ground 6.3  7.7  9.1   m3/hr

 Hydraulic Excavator, 0.5m3 bucket, Sand/Soil 12.2  13.3  15.4   m3/hr

 Hydraulic Excavator, 0.5m3 bucket, Gravel Beds 10.2  11.1  12.9   m3/hr

 Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk 9.7  10.5  12.1   m3/hr

 Hydraulic Excavator, 0.5m3 bucket, Hard Ground 6.1  6.7  7.7   m3/hr