Project

Location: Butig, Lanao Del Sur

Electrical Cost Estimates Electrical System Cost Estimates


No. Description Qty. Unit Average Consuption in (KW) Total KW (Approx.)/Peso (Approx.)

1 Housing (29 VIP, 29 Executive & 500 normal) 558 l.s 3 1674 50,000.00 27,900,000.00

2 Torogan Building 2-Storey 1 l.s 10 10 120,000.00 120,000.00

3 Government Offices 3-Storey 1 l.s 10 10 120,000.00 120,000.00

4 Two Storey Mall 1 l.s 25 25 180,000.00 180,000.00

5 Mosque 1 l.s 3 3 60,000.00 60,000.00

6 Torel Building 3-Storey 1 l.s 5 5 80,000.00 80,000.00

7 Open Park 1 l.s 5 5 250,000.00 250,000.00

8 Cultural Hub, Traing Center 2-Storey 1 l.s 5 5 80,000.00 80,000.00

9 Municipal Market 2- Storey 1 l.s 5 5 120,000.00 120,000.00

10 Food Terminal One Storey 1 l.s 5 5 80,000.00 80,000.00

11 3 Madrasha Building Two Storey 1 l.s 5 5 80,000.00 80,000.00

12 School Building 2-Storey 1 l.s 5 5 80,000.00 80,000.00

13 Gym Covered Court 1 l.s 5 5 80,000.00 80,000.00

14 Medical Clinic 1 l.s 5 5 60,000.00 60,000.00

15 Hospital 1 l.s 50 50 750,000.00 750,000.00

16 Health Center 1 l.s 5 5 80,000.00 80,000.00

17 Sport Complex 1 l.s 15 15 1,500,000.00 1,800,000.00

18 4- Security Tower Post 1 l.s 1 1 100,000.00 100,000.00

19 3- Bridges 1 l.s 5 5 240,000.00 240,000.00

20 Water System 1 l.s 5 5 50,000.00 50,000.00

Sub Total 32,310,000.00

21 11 KV Sub Station Construction 1 l.s 25,000,000.00

22 Distribution Lines, Transformers and Fittings 1 l.s 16,000,000.00

23 Low Voltage panels and Fittings 1 l.s 2,000,000.00

24 Miscellaneous 1 l.s 1,200,000.00

25 Design (Archieict and Engineers Work) 1 l.s 3,200,000.00

Total (Approx) 79,710,000.00