You are on page 1of 1

ARCHITECT

APEX CONSORTIUM
DRAWN SCALES
31, SARVODAYA COLONY, MEERUT.[U.P.] PROPOSED RESIDENCIAL BUILDING AT LKO FOOTING DETAIL
PH:0121-2970394 DESIGN
E-mail: apexcom.in@gmail.com
NO DATE CHANGES 154320 -ST -02
CHECKED DATE 03.09.2020

NOTES
GENERAL
G1. DO NOT SCALE THE DRAWING FOLLOW ONLY FIGURED
DIMENSIONS.
G2. ALL STRUCTURAL DRAWINGS SHOULD BE READ IN
CONJUCTION WITH RELEVANT ARCHITECTURAL DRAWINGS.
ANY DISCREPANCY OR AMBIGUITY IN EITHER SHOULD
BE BROUGHT TO THE NOTICE OF THE ARCHITECT.
DIMENSIONS DEPTH BOTTOM REINFORCEMENT TOP REINFORCEMENT TERRACE G3. ALL DIMENSIONS AND LEVELS ARE IN mm.

FTG.MK'D

OF RINGS
RELATIVE TO THIS LEVEL.
MAIN BARS CROSS BARS MAIN BARS CROSS BARS

3 SETS
LX LY D1 D2 (BY)
ROOF
(BX)
BEAM

10
CONCRETE
F1 12'-0" 12'-0" 12" 33" - - P.LVL. C1. USE CONCRETE GRADE M-25 FOR ALL RCC WORK

MIN.
24"
C2. ALL RCC. WORK SHALL BE CARRIED OUT AS PER

A
F2 10'-6" 10'-6" 12" 30" - - IS-456-2000. (REAFFIRMED 2005)

REINFORCING STEEL
8'-0" 8'-0" - - 9"
F3 12" 24" R1. ALL REINFORCEING STEEL WILL BE OF TESTED QUALITY
CONFORMING TO IS:1786 LATEST.

EQ.
R2. USE Fe 500 STEEL FOR ALL RFT. BARS

B
WITH CHARACTERSTIC STRENGTH OF 500 N/sq. mm.
F4 9'-0" 9'-0" 12" 21" - -
R3. REFER TO HIGH YEILD STRENGTH DEFORMED BARS

5'-6" MINIMUM
R4. CLEAR COVER TO MAIN REINFORCEMENT SHALL BE
F5 8'-0" 8'-0" 12" 21" - - * FOUNDATION 50 mm. ALL AROUND

LAP LENGTH
* COLUMNS 40 mm. ALL AROUND
* BEAMS 30 mm. ALL AROUND
* SLABS 20 mm. TOP & BOTTOM
F6 5'-0" 12'-0" 9" 21" - - * WALLS 25 mm. EARTH FACE
LAPPED HERE

A
* WALLS 20 mm. INNER FACE
R5. LAP LENGTH TO BE 50xDIA OF BAR MINIMUM.
F7 5'-0" 10'-0" 9" 21" - - BARS TO BE R6. LAPS SHALL BE STAGGERED AND NOT MORE THAN

5'-0"(min.)
50% OF BARS SHALL BE LAPPEDAT ONE PLACE.
R7. SLAB BARS IN SHORTER DIRECTION, SHALL BE
F8 5'-0" 10'-0" 9" 21" - - BELOW OF BARS IN LONGER DIRECTION.
R8. IN BEAMS, FIRST STIRRUP SHALL BE AT NO MORE THAN
BOTHWAYS 40 mm FROM FACE OF THE SUPPORTING MEMBER.

10'-0" 10'-0" - -

B
F9 12" 24" R9. IN BEAMS TOP BARS ARE NOT TO BE SPLICED IN THE
END QUARTERS OF THE SPAN, AND THE BOTTOM BARS

EQ.
ARE NOT TO BE SPLICED AT MIDDLE HALF OF THE SPAN.

CF1 AS/FDN PLAN 21" BRICK


B1. THE MINIMUM CRUSHING STRENGTH OF BRICKS SHALL

21"
BE 75 kg/ccm . ALL BRICKS SHALL BE SOUND, HARD,
CF2 AS/FDN PLAN 21" WELL BURNT WITH UNIFORM SIZE AND SHAPE.

MIN.
24"
4" B2. THE MORTAR USED SHALL CONFORM TO IS 2250.

A
FIRST FLR SLAB MORTAR MIX IN 230TH. WALLS SHALL BE IN 1:6 C.M.

CF3 AS/FDN PLAN 21" B3. MORTAR MIX IN 115TH WALLS SHALL BE IN 1:4 CM
WITH 2 BARS OF 6mm DIA IN EVERY FOURTH LAYER

OF RINGS
AND CONTINUED INTO THE INTERSECTING WALLS.

6"

3 SETS
CF4 AS/FDN PLAN P. C. C. (1:4:8) ROOF B4. IN CASE OF ALL NON-LOAD BEARING WALLS, COMING
18" UNDER THE SLABS OR BEAMS, THE LAST COURSE SHALL
BEAM

10
BOTHWAYS LIFT DETAIL BE BUILT AFTER THE FORMWORK OF THE SLAB OR BEAM,
IS REMOVED.

CF5 AS/FDN PLAN 18" CONSTRUCTION PRACTICE

MIN.
600
P1. IT IS MANDATORY TO REMOVE ALL LOOSE SOIL TILL

A
THE FIRM SOIL IS REACHED.
P2. BACK FILLING AROUND THE FOUNDATIONS SHALL BE
CARRIED OUT USING SOIL,SAND WITHOUT GRAVEL AND
PEBBLES.
P3. IT IS ADVISABLE TO ALLOW STANDING WATER IN THE
EXCAVATION TRENCHES FOR 24 HOURS. WHEN THE
L OF FOOTING
C L OF FOOTING
C SURFACE IS SEMIDRY, HAND RAMMING SHALL BE CARRIED

EQ.
OUT WITH AT LEAST 6 TO 8 PASSES.
L OF FOOTING
C

B
P4. BACK FILLING OF BASEMENT WALLS SHALL BE DONE
ONLY AFTER THE ROOF SLAB IS CASTED.
L OF FOOTING
C P5. IN NORMAL CIRCUMSTANCES AND WHERE ORDINARY
PORTLAND CEMENT IS USED, FORMS MAY GENERALLY BE
REMOVED AFTER THE EXPIRY OF THE FOLLOWING PERIODS
TY

LAP LENGTH
* WALLS, COLUMNS AND VERTICAL
FACES OF ALL MEMBERS 36 TO 48 HOURS
* SLABS (PROPS LEFT UNDER) 6 DAYS
* BEAM SOFFITS (PROPS LEFT UNDER)7 DAYS

A
* REMOVAL OF PROPS UNDER SLABS
B B LAPPED HERE -SPANNING UP TO 4500 7 DAYS
TX

B B C OF FOOTING

BX

BX
L A A C OF FOOTING -SPANNING OVER 4500 14 DAYS
BY

L BARS TO BE * REMOVAL OF PROPS UNDER BEAMS


LY

LY
LY

-SPANNING UP TO 6000 14 DAYS


-SPANNING OVER 6000 21 DAYS
3" (TYP.) P6. WHERE POSSIBLE, THE FORMWORK SHALL BE LEFT

COLUMN
LONGER, AS IT WOULD ASSIST CURING.
P7. THE CENTERING SUPPORTING THE OVERHANGING
BY STRUCTURAL MEMBERS SHALL NOT BE REMOVED UNTIL
BX BY SUFFICIENT BALANCING LOAD OVER THE BEARING HAS

B
BEEN ATTAINED BY BUILDING MASONRY OR OTHERWISE.

EQ.
P8. THE CENTERING OF CANTILEVER BEAMS & SLABS SHALL
LX BE REMOVED STARTING FROM OVERHANGING EDGE.
P9. UNLESS OTHERWISE INDICATED IN THE DRAWING,
LX CONSTRUCTION JOINTS IN FLOORS SHALL BE LOCATED
LX NEAR THE MID SPAN OF STRUCTURAL MEMBERS (SLABS,
SECONDARY BEAMS), UNLESS A SECONDARY BEAM

TYPICAL COMBINED FOOTING PLAN TYPICAL ONE SIDE FOOTING PLAN TYPICAL ISOLATED FOOTING PLAN
INTERSECTS A MAIN BEAM AT THIS POINT,IN WHICH CASE,

MIN.
THE JOINTS IN THE MAIN BEAMS SHALL BE OFFSET BY

24'
DISTANCE EQUAL TO TWICE THE WIDTH OF THAT
PLINTH LVL. A SECONDARY BEAM.
P10. WHILE POURING CONCRETE THE MAXIMUM FREE FALL
SHALL NOT BE MORE THAN 1500 mm. TO AVOID
SEGGREGATION.

SPECIFIC TO JOB

AS/SITE
P.L. P.L. SPL. NOTES.-
P.LVL.
AS PER ARCH

AS PER SITE

AS PER SITE
N.G.L. G.B. 2. SAFE BEARING CAPACITY OF SOIL HAS BEEN TAKEN
AS 120 KN/SQ.M. AT 1.5 MT. DEPTH AS TOLD.

A
G.B. G.B. STRUCTURAL CONSULTANTS
N.G.L. G.B. Er.JYOTI GUPTA
N.G.L. G.B. (B.Tech)

TX

5'-0"

OF RINGS
TY
5'-0"

5'-0"

3 SETS
3" (TYP.)
5'-0"

3" (TYP.)
18" (min)

10
D2
D2

D1
D2
D

Ld 18" (MIN.) Ld 18"(MIN.) Ld


D1

D1
4"

6"

BX P. C. C. (1:4:8)
6"

BX P. C. C. (1:4:8) COL.TIES
BX BY BY
BX LX x LY 4"
4" LX x LY 4"
4" LX x LY 4" A= 8 @ 4" c/c.
B= 8 @ 6" c/c.
SECTION B-B P. C. C. (1:4:8) SECTION B-B SECTION A-A (LEGGED AS PER SCHEDULE)
TYPICAL COLUMNS ELEVATION

You might also like