You are on page 1of 592

CARRIAGE COST

LOADING + Lead
Km 10 to Km UNLOADIN Distance(Km) TOTAL CARRIAGE
Sl. No. Name of Materials Unit Source upto 5 km Km 5 to Km 10 20 km and above G
20 COST

1 2 3 4 5 6 7 8 12 12 12
Lime , Stone dust, Building
Rates applicable on
1 Rubbish, Earth, Manure or Sludge Cum 137.24 10.34 8.59 7.10 0.00 50 487.8
compacted volume
and Excavated Rocks

Kochammaniyazhikom
i) Stone dust Cum General metal Industries 137.24 10.34 8.59 7.10 - 50.00 487.8
Kulappadam (20 km from end
Point)

Kochammaniyazhikom
General metal Industries
ii) Screening Material Cum 171.56 12.92 10.74 8.87 - 50.00 609.7
Kulappadam (20 km from end
Point)

Kochammaniyazhikom
General metal Industries
iii) Earth Cum 171.56 12.92 10.74 8.87 - 10.00 254.8
Kulappadam (20 km from end
Point)

2 Sand Stone agreegate and Soling


Stone

Kochammaniyazhikom
General metal Industries
i) Coarse Sand & Fine Sand Cum 137.24 10.34 8.59 7.10 - 50.00 487.8
Kulappadam (20 km from end
Point)

Kochammaniyazhikom
General metal Industries
ii) Stone Agreegate Cum 137.24 10.34 8.59 7.10 - 50.00 487.8
Kulappadam (20 km from end
Point)

Kochammaniyazhikom
ii) Stone Agreegate (Used in DBM, BC Cum General metal Industries 137.24 10.34 8.59 7.10 - 50.00 487.8
& RCC Works) Kulappadam (20 km from end
Point)

Kochammaniyazhikom
iii) Stone Chips Cum General metal Industries 137.24 10.34 8.59 7.10 - 50.00 487.8
Kulappadam (20 km from end
Point)

Kochammaniyazhikom
iv) Soling Stone Cum General metal Industries 161.47 12.16 10.11 8.33 - 50.00 573.2
Kulappadam (20 km from end
Point)

Kochammaniyazhikom
v) Boulder Cum General metal Industries 161.47 12.16 10.11 8.33 0.00 50.00 573.2
Kulappadam (20 km from end
Point)

Cement ,stone blocks, G.I., C.I.,


3 A.C. & C.C. pipes below 100 mm MT Vijayanagr 121.99 9.19 7.63 6.31 - 32.00 319.9
dia and other heavy materials

4 Steel MT Cochin 121.99 9.19 7.63 6.31 - 60.00 496.5


5 Bitumen MT Chennai 137.24 10.34 8.59 7.10 0.00 774.00 5626.4
6 Emulsion MT Chennai 137.24 10.34 8.59 7.10 0.00 774.00 5626.4
RCC pipes , A.C. pipes,
7 Vijayanagr 3333.21 251.08 208.65 172.35 - 32.00 8743.4
Unreinforced Cement pipes

10 Brick 1000 nos Vijayanagr 365.98 27.57 22.91 18.92 5.00 449.1
TMT BAR FOR August 2021 (SAIL RATEs)
Including GST (18%) Excluding GST
12 Meter
Sr. No. Bar Dia Per Piece Rate per Piece
weight (As SAIL June Per Kg. Rate Per Ton Rate Per Ton Rate
2021)

1 8 4.740 347 73.21 73,206.75 62,039.62


2 10 7.404 527 71.18 71,177.74 60,320.12
3 12 10.668 753 70.58 70,584.93 59,817.73
4 16 18.960 1336 70.46 70,464.14 59,715.37
5 20 29.628 2089 70.51 70,507.63 59,752.23
Average Rate up 100Km. Lead 60,329.01
Remarks
Basic Rate As
Cost Incl
SI. No. Description of Materials Unit Royalty Charges per 2021 with Carriage Cost
Carriage(Final rate)
CI
M-001 Stone Boulder of size 150 mm and below at Crusher Plant Cum 49.34 850 573.25 1472.59
M-002 Supply of quarried Stone 150-200 mm size for Hand Broken at site Cum 49.34 850 573.25 1472.59
M-003 Boulder with minimum size of 300 mm for Pitching at Site Cum 49.34 1372.04 573.25 1994.63
M-004 Coarse sand i) at source Quarry Koliwar/Sone sand Cum 156.25 1350 487.78 1994.03
M-005* Coarse sand ii) Equivalent to Koliwar / Sone Sand * Cum 156.25 1350 487.78 1994.03
M-006 Fine sand at Site Cum 156.25 900 487.78 1544.03
M-007 Moorum at Site Cum 40.00 769.74 487.78 1297.52
M-008 Gravel/Quarry spall at Site Cum 49.34 1142.69 487.78 1679.81
M-009 Granular Material or hard murum for GSB works at site Cum 49.34 1350 487.78 1887.12
M-010 Fly ash conforming to IS:3812 (Part II & I) at HMP Plant/Batching Plant/Crushing Mt 49.34 155.36 0 204.70
Plant
M-011 Filter media/Filter Material as per Table 300-3 (MoRT&H Specification) Cum 49.34 556 609.73 1215.07
M-012 Close graded Granular sub-base Material 53 mm to 9.5 mm/4.75mm Cum 49.34 1000 487.78 1537.12
M-013 Close graded Granular sub-base Material 37.5 mm to 9.5 mm Cum 49.34 1300 487.78 1837.12
M-014 Close graded Granular sub-base Material 26.5 mm to 9.5 mm Cum 49.34 1350 487.78 1887.12
M-015 Close graded Granular sub-base Material 9.5 mm to 4.75 mm Cum 49.34 1350 487.78 1887.12
M-016 Close graded Granular sub-base Material 9.5 mm to 2.36mm Cum 49.34 1350 487.78 1887.12
M-017 Close graded Granular sub-base Material 4.75mm to 2.36mm Cum 49.34 1400 487.78 1937.12
M-018 Close graded Granular sub-base Material 4.75mm to 75 micron Cum 49.34 1350 487.78 1887.12
M-019 Close graded Granular sub-base Material 2.36 mm & below Cum 49.34 1350 487.78 1887.12
M-020 Stone crusher dust finer than 3 mm with not more than 10% passing Cum 49.34 1350 487.78 1887.12
M-021 0.075
Coarsesieve.
graded Granular sub-base Material 2.36 mm & below Cum 49.34 1350 487.78 1887.12
M-022 Coarse graded Granular sub-base Material 4.75 mm to 75 micron Cum 49.34 1350 487.78 1887.12
M-023 Coarse graded Granular sub-base Material 4.75mm to 2.36 mm Cum 49.34 1350 487.78 1887.12
M-024 Coarse graded Granular sub-base Material 9.5mm to 4.75 mm Cum 49.34 1350 487.78 1887.12
M-025 Coarse graded Granular sub-base Material 26.5mm to 4.75 mm Cum 49.34 1350 487.78 1887.12
M-026 Coarse graded Granular sub-base Material 26.5 mm to 9.5 mm Cum 49.34 1350 487.78 1887.12
M-027 Coarse graded Granular sub-base Material 37.5 mm to 9.5 mm Cum 49.34 1350 487.78 1887.12
M-028 Coarse graded Granular sub-base Material 53 mm to 26.5 mm Cum 49.34 1350 487.78 1887.12
M-029 Aggregates below 5.6 mm at Quarry Cum 49.34 1350 487.78 1887.12
M-030 Aggregates 22.4 mm to 2.36 mm at Quarry Cum 49.34 1350 487.78 1887.12
M-031 Aggregates 22.4 mm to 5.6 mm at Quarry Cum 49.34 1350 487.78 1887.12
M-032 Aggregates 45 mm to 2.8 mm at Quarry Cum 49.34 1350 487.78 1887.12
M-033 Aggregates 45 mm to 22.4 mm at Quarry Cum 49.34 1350 487.78 1887.12
M-034 Aggregates 53 mm to 2.8 mm at Quarry Cum 49.34 1350 487.78 1887.12
M-035 Aggregates 53 mm to 22.4 mm(Grade III) at Quarry Cum 49.34 1350 487.78 1887.12
M-036 Aggregates 63 mm to 2.8 mm at Quarry Cum 49.34 1350 487.78 1887.12
M-037 Aggregates 63 mm to 45 mm (Grade II)at Quarry Cum 49.34 1350 487.78 1887.12
M-038 Aggregates 90 mm to 45mm(GradeI) at Quarry Cum 49.34 1350 487.78 1887.12
M-039 Aggregates 10 mm to 5 mm at Quarry Cum 49.34 1350 487.78 1887.12
M-040 Aggregates 11.2 mm to 0.09 mm (Key aggregate Type B) Cum 49.34 1350 487.78 1887.12
M-041 Aggregates 13.2 mm to 0.09 mm (Key aggregate Type A) Cum 49.34 1350 487.78 1887.12
M-042 Aggregates 13.2 mm to 5.6 mm at Quarry Cum 49.34 1350 487.78 1887.12
M-043 Aggregates 13.2 mm to 10 mm at Quarry Cum 49.34 1350 487.78 1887.12
M-044 Aggregates 20 mm to 10 mm at Quarry Cum 49.34 1350 487.78 1887.12
M-045 Aggregates 25 mm to10 mm at Quarry Cum 49.34 1350 487.78 1887.12
M-046 Aggregates 19 mm to 6 mm at Quarry Cum 49.34 1350 487.78 1887.12
M-047 Aggregates 37.5 mm to 19 mm at Quarry Cum 49.34 1350 487.78 1887.12
M-048 Aggregates 37.5 mm to 25 at Quarry Cum 49.34 1350 487.78 1887.12
M-049 Aggregates 6 mm nominal size at Quarry Cum 49.34 1350 487.78 1887.12
M-050 Aggregates 10 mm nominal size at Quarry Cum 49.34 1350 487.78 1887.12
M-051 Aggregates 13.2/12.5 mm nominal size at Quarry Cum 49.34 1350 487.78 1887.12
M-052 Aggregates 20 mm nominal size at Quarry Cum 49.34 1350 487.78 1887.12
M-053 Aggregates 25 mm nominal size at Quarry Cum 49.34 1350 487.78 1887.12
M-054 Aggregates 40 mm nominal size at Quarry Cum 49.34 1350 487.78 1887.12
M-055 Crushing of Stone aggregates (GSB Crusher Run) Cum 49.34 487.78 537.12
M-056 AC pipe 100 mm dia metre 59.13
M-057 Acrylic polymer bonding coat litre 236.3
M-058 Alluminium Paint litre 180.7
M-059 Aluminium alloy plate 2mm Thick sqm 8379.04
M-060 Aluminium alloy/galvanised steel tonne 46496.54 46,000.00 496.54
M-061 Aluminium sheeting fixed with encapsulated lens type reflective sheeting including sqm 7560.00
M-062 2%
Roadtowards lettering,
Aluminium cost Micro
Stud with of angle iron, cost
Prismatic lensofreflectors
drilling holes,
( 'thnuts, bolts etc.and each 169.19
signs as 100
shank) applicable
M-063 Barbed wire X 100 mm kg 66.72
M—064 Bearing (Cost of parts) nos 630
M-065 Bearing (Cast steel rocker bearing assembly of 250 tonne ) nos 55660.00
Bearing (Elastomeric bearing assembly consisting of 7 internal layers of elastomer cubic cm 0.59
M—066 bonded to 6 nos. internal
Taking elastomeric bearingreinforcing steel
of size 500 X 400 X 96mm, Overall nos 12915.00
laminates by thecubic
volume=19200 process @Rs
of vulcanisation)
M-067 Bearing (Forged steel cm 0.59/cucm=
roller bearing Rs 11328
of 250 tonne) nos 85008.00
M-068 Bearing (Pot type bearing assembly consisting of a metal piston supported by a MT 136.66
disc, PTFE pads providing sliding surfacesDoagainst stainless steel mating together nos 34165.00
with cast steel assemblies/ fabricated structural steel assemblies duly painted with
(a) Fixed POT-PTFE Bearing
all components output=250 tonne) MT 136.66
(b) Free POT-PTFE Bearing MT 146.43
(c) Guide Slide (L) POT-PTFE Bearing MT 156.19
(d) Guide Slide (T) POT-PTFE Bearing MT 151.31
M-069 Bearing (PTFE sliding plate bearing assembly of 80 tonnes ) nos 34788.00
M-070 Bearing (Supply of sliding plate bearing of 80 tonne) nos 34420.00
M—071 Bentonite kg 4.31
M-072 Binding wire kg 66.72
M-073 Bitumen ( Cationic Emulsion ) Jhansi tonne 51690.37 5626.37
M-074 Bitumen (60-70 grade) Bulked Mathura tonne 46556.37 5626.37
M—075 Bitumen (80-100 grade ) Bulked Mathura tonne 48006.37 5626.37
M-076 Bitumen (Cutback ) Marhura tonne 46556.37 5626.37
M-077 Bitumen (emulsion) Jhansi tonne 47662.37 5626.37
M-078 Bitumen (modified graded) Bulk Mathura (CRMB - 55) tonne 46896.37 5626.37
M—079 Brick 100A for - Patna Urban each 3.5 449.072
M-080 C.I. shoes for the pile kg 69.5
M-081 Cement OPC 43 Grade tonne 4940 319.9485
M-082 CGI Sheet 0.8 mm thick Kg 62.55
M—083 Cold twisted bars (HYSD Bars) — Fe S00 D Av. of M—10A tonne 46496.54 46,000.00 496.54
M-084 Coller (RCC) for joints 300 mm dia nos 76.45
M-085 Compressible Fibre Board (20mm thick) sqm 735.00
M-086 Connectors / Staples each 6.95
M-087 Copper Plate (12m long x 250mm wide) kg 389.2
M-088 Corrosion resistant Structural steel tonne 46496.54 46,000.00 496.54 44000.00
M-089 Corrugated sheet, 3 mm thick, "Thrie" beam section railing kg 72.28
Credit for excavated rock found suitable for use (add Royality @ I 319.7
M-090 30% of Rate) CLI
M-091 Curing compound litre 41.7
M-092 Delineators from ISI certified firm as per the standard drawing E'£I. h 382.25
M-093 given in IRCor- 79
Earth Cost compensation for earth taken from private land cum 45
Elastomeric slab seal expansion joint assembly manufactured by using
M-094 chloroprene, elastomer for elastomeric slab unit metre 27202.73
conforming to clause 915.1 of IRC: 83 (part II)
M-095 Epoxy compound with accessories for preparing epoxy mortar kg 764.5
M-096 Epoxy mortar kg 697.78
M-097 Epoxy primer kg 208.5
M-098 Epoxy resin-hardner mix for prime coat kg 378.00
M-099 Flag of red color cloth 600 x 600 mm each 118.00
M-100 Flowering Plants each 100.00
M-101 Galvanised MS flat clamp nos 27.8
M-102 Galvanised steel wire crates of mesh size 100 mm x 100 mm sqm 19.00
M-103 woven withstructural
Galvanised 4mm dia. steel
GI wire in 200
plate rolls mm
of required
wide, 6 size.
mm thick, 24 kg 63.00
M-104 m long
Geo grids sqm 236.00
M-105 Geomembrane sqm 89.00
M-106 Geonets sqm 210.00
M-107 Geotextile sqm 62.55
M-108 Geotextile filter fabric sqm 62.55
M-109 GI bolt 10 mm Dia nos 16.76
M-110 Spherical Dome Nut nos 1.00
M-111 Grass (Doob) kg 34.75
M-112 Grass (Fine) kg 34.75
M-113 HDPE pipes 75mm dia metre 234.00
M—114 HDPE pipes 90mm dia metre 252.00
M-115 Hedge plants each 25.00
M-116 Helical pipes 600mm diameter metre 1008.00
M-117 Hot applied thermoplastic compound (Sp. Gravity - 2.10) litre 166.8
M-118 HTS strand tonne 63806.54 63,310.00 496.54
M-119 Joint Sealant Compound kg 37.53
M-120 Jute netting, open weave, 2.5 cm square opening for seeding sqm 56.00
M-121 and
LDO Mulching
for steam curing litre 83.00
M-122 M.S. Clamps nos 41.7
M-123 M.S. Clamps kg 62.55
M—124 M.S.shoes @ 35 Kg per pile of 15 m kg 50.00
M-125 Mild Steel bars (Av-M6) tonne 63806.54 63,310.00 496.54
M-126 Modular strip/box seal expansion joint including anchorage catering to a metre 8400.00
M-127 horizontal movement
Modular strip/box sealbeyond 70 mm
expansion and
joint upto 140mm
catering assembly
to a horizontal comprising
movement of
beyond metre 8400.00
edge
140mm beams,
and central
upto beam,box/box
210mm 2 modules
seal chloroprene
joint seal,
assembly anchorage
containing 3 elements,
modules/cells
M-128 Nipples 12mm,300mm
support and control long all steel sections protected against corrosion
system, nos 26.41
and comprising of edge beams, two central beams, chloroprene seal, anchorage
M-129 Nuts
and and bolts
installed
elements, by theand
support manufacturer or hisallauthorised
control system, steel sections protected against kg 64.83
M-130 Paint
corrosion and installed by the manufacturer litre 235.22
M-131 or his authorised
Pavement Markingrepresentative
Paint litre 172.36
M-132 Paving Fabric sqm 80.73
M-133 Perforated geosynthetic pipe 150 mm dia metre 336.00
M-134 Perforated pipe of cement concrete, internal dia 100 mm metre 178.00
M-135 Pesticide kg 222.4
M-136 Pipes 200 mm dia, 2.5 m long for drainage metre 168.19
M-137 Plastic sheath, 1.25 mm thick for dowel bars sqm 41.7
M-138 Plastic tubes 50 mm dia, 1.2 m high nos 1124
M-139 Polymer braids metre 205
M-140 Pre moulded Joint filler, 25 mm thick for expansion joint. sqm 625.5
M-141 Pre-coated stone chips of 13.2 mm nominal size cum 1951.24
M-142 Preformed continuous chloroprene elastomer or closed cell foam sealing element M £'tre 948
M-143 with high tearasphalt
Pre-moulded strength, vulcanised
filler board in a single operation for the full length of a sqm 376.00
joint to ensure water
M-144 Pre-packed cement based polymer concrete of strength 45 Mpa k, 41
M-145 at 28 days
Primer (Wall) kg 288.00
M-146 Quick setting compound kg 103.00
M-147 Random Rubble Stone cum 611.6
M-148 RCC Pipe NP 4 heavy duty non presure pipe 1000 mm dia 'th metre 16478.7135 8743.3635 5925
spigot
RCC Pipe NP 4 heavy duty non presure pipe 1200 mm dia 'th 17792.2635
M-149 metre 8743.3635 6547
spigot
RCC Pipe NP 4 heavy duty non presure pipe 900 mm dia with 14990.0235
M-150 metre 8743.3635 5175
spigot
RCC Pipe NP 4 heavy duty non presure pipe 600 mm dia with 11954.2635
M-151 metre 8743.3635 3450
spigot
RCC Pipe NP 4 heavy duty non presure pipe 300 mm dia 10411.3635
M-152 metre 8743.3635 2358
M-153 Reflectorising glass beads kg 68.29
M-154 Reinforcement strips 60 mm wide 5 mm thick as per clause metre 1
M-155 3102. (Copper Strips)
Reinforcement strips 60 mm wide 5 mm thick as per clause metre 1
M156 3102. (Galvanised
Reinforcement carbon
strips 60 mmsteel strips)
wide 5 mm thick as per clause metre 1
M-157 3102. (Glass reinforced
Reinforcement strips 60 polymer/fibre
mm wide 5 mm reinforced
thick as polymer/polymeric
per clause strips) metre 1
M-158 3102. (Stainlessstrips
Reinforcement steel60
strips)
mm wide 5 mm thick as per clause metre 1
M-159 3102.
Rivets (Aluminium strips) each 6.00
M-160 Sand bags (Cost of sand and Empty cement bag) nos 8.48
M-161 Sapling 2 m high 25 mm dia each 300.00
M-162 Scrap tyres of size 900 x 20 nos 130.00
M-163 Seeds kg 84.00
M-164 Selected earth (Including royalty @ ‘33.0 per cum & CUM 222
M-165 compensation
Separation @ '1.81 of
Membrane perimpermeable
cum) plastic sheeting 125 sqm 16.68
M-166 micron thick
Sheathing duct metre 210.00
Shrubs each/
M-167 54.00
(sqft)
Sludge / Farm yard manure @ 0.18 cum per 100 sqm at site of I
M-168 work for turfing 300.00
CLI
M-169 Sodium vapour lamp (70 watt) each 4210.00
M-170 Square Rubble Coursed Stone cum 933.45
Steel circular hollow pole of standard specification for street
M-171 each 10000.00
lighting to mount light at 5 m height above deck level
Steel circular hollow pole of standard specification for street
M-172 each 15000.00
lighting to mount light at 9 m height above road level
M-173 Steel drum 300 mm dia 1.2 m high/empty bitumen drum nos 252
M-174 Steel helmet and cushion block on top of pile head during kg 135
M-175 driving.
Steel pipe 25 mm external dia as per IS:1239 metre 129.80
M-176 Steel pipe 50 mm external dia as per IS:1239 metre 232.28
M—177 Steel pipe 100 mm external dia as per IS:1239 metre 337.05
M-178 Steel wire rope 20 mm kg 44.78
M-179 Steel wire rope 40 mm kg 44.78
M-180 Strip seal expansion joint metre 8085
M-181 Structural Steel (Av. of M6, M8 & M9) tonne 63806.54 63,310.00 496.54
M-182 Super plastisizer admixture IS marked as per 9103-1999 kg 167.49
M—183 Synthetic Geogrids as per clause 3102.8 and approved design sqm 182.60
M-184 and specifications.
Through and bond stone each 59.77
M-185 Tie rods 20mm diameter (500mm length) @2.47 kg/m nos 1.50
M-186 Tiles size 300 x 300 mm and 25 mm thick each 33.15
M-187 Timber CUM 2500
M-188 Traffic cones with 150 mm reflective sleeve nos 640
M-189 Tube anchorage set complete with bearing plate, permanent nos 48.45
M-190 wedges
Unslakedetc
lime tonne 3753
Sub Analysis
M—191 Water KL 16.00
21.22
M-192 Water based cement paint litre 97.3
M-193 Welded steel wire fabric kg 66.72
M-194 Wire mesh 50mm x 50mm size of 3mm wire kg 66.72
M-195 Wooden ballies 2" Dia for bracing (Sai) each 21.89
M-196 Wooden ballies 8" Dia and 9 m long each 529.40
M-197 Wooden packing cum 1659
M-198 Wooden staff for fastening of flag 25 mm dia, 1.0 m long each 16
M-199 Silica fume kg 33.60
M-200 Synthetic Geogrids Ultimate tensile Strength 100kN/Metre. Sqm 278
M-201 Synthetic Geogrids Ultimate tensile Strength 150kN/Metre. Sqm 305.8
M-202 Synthetic Geogrids Ultimate tensile Strength 200kN/Metre. Sqm 417
M-203 Synthetic Geogrids Ultimate tensile Strength 250kN/Metre. Sqm 458.7
M-204 Synthetic Geogrids Ultimate tensile Strength 300kN/Metre. Sqm 486.5
M-205 Synthetic Geogrids Ultimate tensile Strength 350kN/Metre. Sqm 542.1
M-206 Synthetic Geogrids Ultimate tensile Strength 400kN/Metre. Sqm 583.8
M-207 Synthetic Geogrids Ultimate tensile Strength 500kN/Metre. Sqm 695
M-208 Synthetic Geogrids Ultimate tensile Strength 600kN/Metre. Sqm 764.5
M-209 Synthetic Geogrids Ultimate tensile Strength 700kN/Metre. Sqm 903.5
M-210 Synthetic Geogrids Ultimate tensile Strength 800kN/Metre. Sqm 984.12
M-211 Synthetic Geogrids Ultimate tensile Strength 900kN/Metre. Sqm 1168.99
M-212 Synthetic Geogrids Ultimate tensile Strength 1000kN/Metre. Sqm 1320.5
M-213 Synthetic Geogrids Ultimate tensile Strength 1100kN/Metre. Sqm 1390
M-214 Synthetic Geogrids Ultimate tensile Strength 1200kN/Metre. Sqm 1512.32
M-215 Explosive for blasting(Gelatine80%) Kg 81.90
M-216 Delay Detonators Nos 21
M-217 Electric Detonators @1 detonator for 1/2 gelatin stick of 125 Nos 21.00
M-218 gms each Fuse coil
Detonation Meter 19
M-219 3.7 mlong extension rod boom Hydraulic Drill jumbo Nos 10000
M-220 32 mm coupling sleeve boom Hydraulic Drill jumbo Nos 12000
M-221 Difter rod boom Hydraulic Drill jumbo Nos 15000
M-222 R32 sank adapter boom Hydraulic Drill jumbo Nos 13000
M-223 45 mm Dia Button Bit boom Hydraulic Drill jumbo Nos 3000
M-224 51mm Dia Button Bit Hydraulic Drill Jumbo Nos 5000
M-225 Steel Fiber tonne 46496.54
M-226 Microsilica Kg 32.00
M-227 Accelerator Kg 125
M-228 Wire mesh Kg 40.58
M-229 Bamboos (i) 75mmDia 6m to 8m long Meter 17.75
M-230 (ii) 100mm
Live Dia 6m to 8m long
Stake Stump Meter 1
(iii) 50mm Dia Hill Bamboc
M-231 Hard wood sticks Meter 100
M-232 Live Sods(0.6m Length) Nos 1
M-233 Live Sods(2.0 m Length) Nos 1
M-234 Coal Tar Epoxy Kg 1
M-235 Binding Material Meter 1
M-236 Spring post 700mm each 375
M-237 Spring post 450 mm each 350
M-238 Water Filled Barricades Work zone sheeting (Trapezoidal Shape each 2500
M-239 800mmto
GI Pipe 1001000mm
mm Diain Iength,700mm in height Meter 496
M-240 Bracket for G.I Pipe fixing Kg 1
M-241 Flange for G.I Pipe fixing Kg 1
M-242 Neem Cake Quintal 4000.00
M-243 Supplying sludge Cum 300.00
M-244 Contol Center Server Nos 1
M-245 Hot Standby Backup Server Nos 1
M-246 NAS Video Server with storage Minimum 70 TB Nos 1
M-247 Backup Video (Only Incidents) Server. Nos 1
M-248 Graphic Display(70" LED DLP IN 3X2 matrix) Set 1
M-249 Graphic Display Controller and software including Video Set 1
M-250 CCTV Monitoring Workstation Nos 1
M-251 Emergengy Telephone (1033)ConsoIe. Nos 1
M-252 VIDS-Workstation. Nos 1
M-253 Administrative Workstation Nos 1
M-254 ATMS Operator Workstation Nos 1
M-255 CCTV joystick Nos 1
M-256 Operations Laser Printer(Colour) Nos 1
M-257 Operations Laser Printer(Black) Nos 1
M-258 Rack 19" Nos 1
M—259 ATMS Control Room Software(integrated with Ls 1
M-260 VIDS,ATCC,VMS,MOS)
Video Management Software with atleast 150 VMS Lic Ls 1
M-261 Facility Monitoring System Controller Software Ls 1
M-262 Server & Database license Ls 1
M-263 Antivirus license Ls 1
M-264 PTZ Camera (including CCTV Controller) Set 1
M-265 Solar System with UPS, battery & 12mm Pole & Cabinet Set 1
M-266 VIDS Camera (including image Prossesing unit) Set 1
M—267 Warning amber lights with hooters, 72 Hrs solar backup,5m Set 1
M-268 poles and foundation
Cabinet Nos 1
M-269 12 m Pole (including manufacturing and galvanizing) Nos 1
M-270 Solar System with UPS & batteries Set 1
M-271 Equipment,Sensor unit, Processing unit, Solar power supply and Set 1
M-272 civil works
Solar forwith
System 4 Lanes
UPS , batteries. Set 1
M-273 VMS (Variable Message Sine-Mtype) Nos 1
M-274 Gantry(including Manufacturing and galvanizing) Nos 1
M-275 Solar System with UPS, battery and Cabinet for M type VMS Set 1
M-276 Uninterruptible Power supply (UPS)for Server Rack(10KVA) Set 1
M-277 Uninterruptible Power supply (UPS) for TMC (30KVA) Set 1
M-278 Power Distribution Board (Essential & CriticalSupply) Set 1
M-279 MOS sensor Equipment (including MOS Controller) Set 1
M-280 Cabinet Nos 1
M-281 Pole Nos 1
M-282 Steel fence for protection Set 1
M-283 24 CoreArmoured OFC + all accessories Meter 29
M-284 40 mm PLB HDPE duct as per latest TSEC specification +aII Meter 1
M-285 accessories
Trenching of 1.8 meters,Laying & Back filling for PLB HDPE duct Meter 1
M-286 Bi- Axial Extruded Geogrids of Minimum Tensile Strengh 15kN/m sqm 1
M-287 Bi- Axial Extruded Geogrids of Minimum Tensile Strengh 20kN/m sqm 1
M-288 Bi- Axial Extruded Geogrids of Minimum Tensile Strengh 30kN/m sqm 1
M-289 Bi- Axial Extruded Geogrids of Minimum Tensile Strengh 40kN/m sqm 1
M-290 Geosynthetic Drainage composite (tensile strength of 18 Kn/m) sqm 175
M-291 Geosynthetic Drainage composite (tensile strength of 13.5 sqm 150
M-292 Waste Plastic (as per IRC:SP:98-2013) tonne 5000
M293 RCC Pipe NP 4 heavy duty non presure pipe 1500 mm dia meter 1
M294 Acrylic noise barrier sheet Sqm 90
M295 Silt Fence Sheet Sqm 250
M296 Fully Threaded Hot Dip galvanised geotechnical bars with casing' Lm 1
M297 Centralizer No 1
M298 Bearing Plate 200mm x 200mm x 10mm No 1
M299 Spherical dome nut Nos. 1
M300 Fibre Reinforcement tonne 1
M301 Geotextile Sqm 1
M302 Polyvinyl Chloride Pipe (PVC)-90 mm meter 300
M303 Polyvinyl Chloride Pipe (PVC)-110 mm meter 350
M304 Polyvinyl Chloride Pipe (PVC)-135 mm meter 400
M305 Steel/Iron Scraps Kg. 1
M306 Aluminium sheeting fixed with encapsulated lens type reflective sheeting including sqm 1
M307 2% towards lettering (Class-C Type XI- 2mm
Geocell sqm 120
thick)
M308 Geosynthetics mat sqm 50
M309 Natural geotextile sqm 25
M310 Fabric Form mattress sqm 1
M311 Non-Woven Geotextile sqm 1
M312 Sr. Road Safety/Auditor/ Team Leader for Road Safety Audit Month 100000
M313 Traffic Planner for Road Safety Audit Month 75000
Boarding & Loading and Per Diem for Site Visits (During Road
M314 Days 3500
Safety Audit)
M315 Transportation at site and Head Office (During Road Safety No. of Trip 1200
M316 Audit)travel to Site (During Road Safety Audit)
Duty Days 2000
M317 Collection of Road accident data and analysis of fatal and grievously injured No. of Copies 5000
M318 accident with
Submission ofblack spot identification
GAP report (During
(For Road Safety Audit) No. of Copies 7000
Road Safety Audit)
M319 Road Safety Audit Reports on all activities which were planned, No. of Copies 7000
M320 actually executed
Submission and
of Audit planned
Report for the
of work next
zone quarter.
safety (for Road Safety No. of Copies 15000
M321 Audit)
Workshop Report for Road Safety Audit No. of Copies 4500
M322 Final Safety Report (for road safety Audit) No. of Copies 25000
M-323 Cement Fly Ash Brick (Conforming to IS 12894, size= 230 X 110 X 70 mm, weight each 5.008
of oneBlock
Paver brick=(Excluding
3Kg, composition:
GST ) Fly ash= 60%,
Coarse sand= 30%, Cement= 10%) including carriage of sand
(i) M -35 Grade and 60 mm thickness (a) White sqm 506.66

M-324
(b) Red sqm 515.69
M-324 (C) Yellow sqm 531.88
(ii) M-40 Grade and 80mm thickness (a) White sqm 581.43
(b) Red sqm 596.64
(C) Yellow sqm 615.88
M-325 Kerb-Stone Block- M30 Grade (Size 375mm x 300mm 150 ) each 79.00
M-326 inclusive
Autoclavedof Aerated
OH & CPConcrete (AAC) Block cum 2457.20
M-327 Bitumen grade VG 40 (30/40) packed Mathura MT 44020.00
MR01 Construction of restaurant, workshop, first aid room, shop etc. Sqm 1
MR02 in truck parking
Providing area booth
Telephone complete as peras
complete drg.
perand direction ofand
specifications the Engineer. Nos. 1
MR03 direction of
Providing & Engineer.
fixing tube well, complete as per drawing and Nr. 1
MR04 additional
Providing aspecifictions.
Drinking Water Kiosk complete as per drawing & Nr. 1
MR05 specification.
Providing and fixing of litter bins in Truck lay Bye locations Nr. 1
MR06 complete as per
Construction drawing
of toilet orprovided
block as directed byfittings
with the engineer.
and fixtures complete in truck Nr. 1
MR07 parking area complete
Construction as per
of Open lined U -drg. and
Drain in truck laybye area Meter 1
direction of
complete the Engineer.
MR08 Providing as shown
shelters in bus
for drawing and technical
passengers specification
as per drawing and clause 309. Nr. 1
MR09 MORT&H Specifications section 300, 1500, 1600 and 1700.
Providing & fixing guard railing with tubular steel sections at foot path / medians / Meter 1
MR10 islands etc at
Toll Booth including
Tollplazafoundation concrete and painting with approved paint etc. all Nr. 1
complete as per drawing & MORT&H Specifications Clauses 808, 300, 1500, 1700
MR11 Barrier
& 1900.gates at Tollplaza For 3.2 m wide toll lane Nr. 1
MR12 Barrier gates at Tollplaza For 4.5 m wide toll lane Nr. 1
MR13 Canopy Sqm 1
MR14 Canopy Lights Halide lamps 150 watt Nr. 1
MR15 Canopy Lights Halogen lamps 1000 watt Nr. 1
MR16 Loading Unloading Platform Sqm 1
MR17 Traffic Aid Post at Toll Plaza Nr. 1
MR18 Medical Aid Post at Toll Plaza Nr. 1
MR19 Vehicle Rescue Post at Toll Plaza Nr. 1
MR20 Ambulances at Toll Plaza Nr. 1
MR21 Cranesat Toll Plaza Nr. 1
MR22 Electronic Toll Connection (ETC lanes) at Toll Plaza Nr. 1
MR23 Intercom facility at Toll Plaza Nr. 1
MR24 Weigh Bridge Nr. 1
MR25 Car Parking area Sqm 1
MR26 Generator room Sqm 1
MR27 Base Maintainance Camp Sqm 1
MR28 Toll plaza equipment Lane 1
MR29 Electrification And Air conditioning for toll Booth and toll Plaza LS 1
MR30 Bull nose crash barrier Nr. 1
MR31 Standby Generator at Toll Plaza Nr. 1
MR32 CCTV camera installed at each booth Nr. 1
MR33 T1for Toll Road Start Nr. 1
MR34 T2 for Toll Gate 1 Km Nr. 1
MR35 T3 for Toll Gate 500 m and toll rates Nr. 1
MR36 T4 for exempt vehicles at Toll Plaza Nr. 1
MR37 T5 for pictorial description of toll rates Nr. 1
MR38 T6 for over size vehicle lane direction sign at Toll Plaza Nr. 1
MR39 T7 near the Toll booths displaying Toll Rates, exempt vehicles Nr. 1
MR40 andfor
T8 complaint telephone
Toll Road End number & address Nr. 1
MR41 Picnic Area at Rest Area Sqm 1
MR42 Petrol Pump & Pepairing Shop at Rest Area Sqm 1
MR43 Buffer Zone at Rest Area Sqm 1
MR44 Traffic blinker Signal (L.E.D.) Nr 1
MR4S PVC Roof Sheet at FOB Sqm 1
MR46 Cost of Water Quality Monitoring Nos. 1
MR47 Cost of Soil Quality Monitoring Nos. 1
MR48 Cost of Ambient Air Quality Nos. 1
MR49 Cost of Ambient Noise Monitoring 24 hour continuous Nos. 1
MR50 Consent to Establish (CTE) Nos. 1
MR51 Consent to Operate (CTO) Nos. 1
MR52 Compliance submission for Consent to Establish (CTE) Nos. 1
MR53 Compliance submission for Consent to Operate (CTO) Nos. 1
MR54 Cost of Environmental Workshop Nos. 1
PM1001 Dozer - 240 HP Hour 6,586.65
PM1002 Dozer - 175 HP Hour 5,087.25
PM1003 Dozer - 90 HP Hour 3,502.80
PM2001 Motor Grader 4.3 metre blade Hour 5,991.00
PM2002 Motor Grader 3.7 metre blade Hour 5,497.00
PM2003 Motor Grader 3.35 metre blade Hour 4796
PM3003 Hydraulic Excavator of 1.2 cum bucket Hour 3,420.00
PM3004 Hydraulic Excavator of 1.1 cum bucket Hour 3,074.00
PM3005 Hydraulic Excavator of 0.9 cum bucket Hour 2,782.00
PM4001 Jack Hammer (attachment of Hydraulic Excavator) Hour 216.30
PM5001 Front End loader 3.1 cum bucket capacity Hour 4,279.80
PM5002 Front End loader 2.1 cum bucket capacity Hour 2,640.75
PM5003 Backhoe-loader 1 cum bucket capacity Hour 1112
PM6001 Tipper-18 Cum Hour 2,883.30
PM6002 Tipper-14 Cum Hour 2,556.75
PM6003 Tipper-10 Cum Hour 2,274.30
PM6004 Tipper-5.5 Cum Hour 1,731.45
PM7001 Vibratory Soil Compactor (10 tonne) Hour 903.5
PM8001 Smooth Wheeled Roller 8 tonne Hour 417
PM9001 Tandem Roller Hour 1668
PM9002 Mini Tandem Roller hour 1,437.45
Vibratory
PM10001 Pneumatic Road Roller Hour 2,562.00
road Roller
PM11001 Water Tanker (16 KL) Hour 1,501.00
PM11002 Water Tanker (12 KL) Hour 1,327.00
PM11003 Water Tanker (6 KL) Hour 1005
PM12001 Tractor-Trolly Hour 1876.5
PM13001 Rotavator Hour 16.80
PM14001 Ripper Hour 22.05
PM15001 Air Compressor -250 cfm Hour 614.25
PM15002 Air Compressor -500 cfm Hour 2,752.05
PM16001 Integrated Stone Crusher Stone (3 Stage) 250 TPH Hour 15,481.20
PM17001 Wet Mix Plant - 250 TPH Capacity Hour 921.90
PM17002 Wet Mix Plant - 200 TPH Capacity Hour 612.15
PM17003 Wet Mix Plant - 100 TPH Capacity Hour 585.90
PM18001 Hotmix Plant - 200 TPH Capacity Hour 14,634.90
PM18002 Hotmix Plant - 160 TPH Capacity Hour 10,338.30
PM18003 Hotmix Plant - 120 TPH capacity Hour 8,372.70
PM19001 Batching and Mixing Plant - 240 cum Capacity Hour 6,313.65
PM19002 Batching and Mixing Plant - 120 cum Capacity Hour 4,104.45
PM20001 Mobile Concrete Batching / Mixing Plant Hour 983.85
PM21001 Concrete Mixer - 0.4/0.28 cum Hour 511.35
PM21002 Concrete Mixer - 1 cum Hour 551.25
PM22001 Generator 725 KVA Hour 11,596.20
PM22002 Generator 500 KVA Hour 8,022.00
PM22003 Generator 400 KVA Hour 6,470.10
PM22004 Generator 250 KVA Hour 3475
PM22005 Generator 125 KVA Hour 2,390.85
PM22006 Generator 100 KVA Hour 2,041.20
PM22007 Generator 62.5 KVA Hour 1,312.50
PM22008 Generator 33 KVA Hour 753.90
PM22009 Generator 15 KVA Hour 425.25
PM23001 Mechanical Broom Hydraulic Hour 500.4
PM24001 Bitumen Pressure Distributor Hour 1,729.35
PM25001 Emulsion Pressure Distributor Hour 1112
PM26001 Bitumen Boiler Oil Fired Hour 743.40
PM27001 Mastic Cooker Hour 1042.5
PM28001 Paver Finisher Mechanical Hour 1112
PM29001 Paver Finisher Hydrostatic with sensor control -240 HP Hour 9,233.70
PM29002 Paver Finisher Hydrostatic with sensor control -170 HP Hour 2,362.50
PM30001 Paver Finisher Concrete with 300 HP Motor Hour 28,108.50
PM30002 Paver Finisher Concrete with 241 HP Motor Hour 18,201.75
PM30003 Paver Finisher Concrete with 118 HP Motor Hour 4,517.10
PM31001 Texture Curing Machine (TCM) - upto 18 m Hour 4,830.00
PM31002 Texture Curing Machine (TCM) - upto 9 m Hour 3,807.30
PM32001 Hydraulic Chip Spreader Hour 2,220.75
PM33001 Pot-Hole Repair Machine Hour 1,796.55
PM34001 Transit Mixer - 6 Cum Hour 2,413.95
PM35001 Concrete Pump Hour 1,341.90
PM36001 Boom Placer Hour 4,401.60
PM37001 Kerb Casting Machine Hour 1,957.20
PM38001 Piling Rig with Bentonite Pump Hour 19,747.35
PM39001 Pneumatic Sinking Plant Hour 6,920.55
PM40001 Road marking machine Hour 1,951.95
PM41001 Mobile Slurry Seal Equipment Hour 3,998.40
PM42001 Joint Cutting Machine Hour 511.35
PM43001 Bar Bending & Cutting Machine Hour 528.15
PM44001 Needle Vibrator Hour 590.10
PM45001 Jack Hammer for air compressor Hour 11.55
PM46001 Plate Compactor Hour 597.45
PM47001 Milling Machine with 1 meter Drum Width Hour 4,784.85
PM47002 Milling Machine with 1.2 meter Drum Width Hour 5,592.30
PM47003 Milling Machine With 1.3 meter Drum Width Hour 8,006.25
PM47004 Milling Machine With 2 meter Drum Width Hour 11,982.60
PM48001 Cold in Situ recycling of bitumen's pavement with foam Hour 30,811.20
PM49001 bitumen technologyof WMM/GSB/Sub grade
In situ stabilisation Hour 26,741.40
PM50001 Cement spreader Hour 8,300.25
PM51001 Mobile cold recycling mixing plant Hour 22,397.55
PM52001 Hot in place recycling Hour 108,654.00
PM53001 Pre heater unit for hot in place recycling Hour 1,271.55
PM54001 Single boom Hydraulic Drill Jumbo Hour 5,420.10
PM55001 Two boom Hydraulic Drill Jumbo Hour 8,220.45
PM56001 Three boom Hydraulic Drill Jumbo Hour 12,007.80
PM57001 Hydraulic Rock bolt drill Hour 7,787.85
PM58001 Rotating Telehandlers Hour 1,207.50
PM59001 Shotcrete Machine Hour 1,830.15
PM60001 Grouting machine Hour 798.00
PM61001 Dewatering Pump 10 HP Hour 328.65
PM61002 Concrete cutting machine Hour 1251
PM62001 Crawler mounted Crane 35 tonne capacity Hour 6,330.45
PM62002 Crawler mounted Crane 80 tonne capacity Hour 6,580.35
PM62003 Crawler mounted Crane 100 tonne capacity Hour 9,978.15
PM63001 Mobile Hydraulic Crane 3 tonne capacity Hour 1,083.60
PM63002 Mobile Hydraulic Crane 5 tonne capacity Hour 1,128.75
PM63003 Mobile Hydraulic Crane 10 tonne capacity Hour 1,240.05
PM63004 Mobile Hydraulic Crane 15 tonne capacity Hour 1,278.90
PM63005 Mobile Hydraulic Crane 20 tonne capacity Hour 1,584.45
PM63006 Mobile Hydraulic Crane 35 toone capacity Hour 2,394.00
PM64001 Concrete Bucket Hour 153.30
PM65001 Prestressing Jack with Pump & Access Hour 559.65
PM66001 Boat to carry atleast 20 persons hour 975.45
PM67001 Crane with grab 0.75 cum capacity hour 1,094.10
PM68001 Epoxy Injection gun hour 380.10
PM69001 Induction, deinduction and erection of plant and equipment including all hour 10,073.70
PM70001 components and40
Jack for Lifting accessories forcapacity.
tonne lifting pneumatic hour 378.00
method of well sinking.
PM71001 Vibrating Pile driving hammer complete with power unit and hour 18,571.35
accessories.
Per
PM72001 Tipper 18 Cum ( Surface Road) 5.88 As per Carriage Rate
Tonne Km.
PM72002 Tipper-18 Cum (Unsurfaced Gravelled Road) excluding OH & t.km 7.15 Do
PM72003 CP
Tipper-18 Cum (Katcha Track) excluding OH & CP t.km 14.30 Do
PM73001 Tipper -14 Cum (Surface Road) excluding OH & CP t.km 6.68 Do
PM73002 Tipper -14 Cum (Unsurfaced Gravelled Road) excluding OH & t.km 8.12 Do
PM73003 CP
Tipper -14 Cum (Katcha Track) excluding OH & CP t.km 16.23 Do
PM74001 Tipper -10 Cum (Surface Road) excluding OH & CP t.km 8.25 Do
PM74002 Tipper -10 Cum (Unsurfaced Gravelled Road) excluding OH & t.km 10.03 Do
PM74003 CP
Tipper -10 Cum (Katcha Track) excluding OH & CP t.km 20.06 Do
PM75001 Tipper- 5.5 Cum (Surface Road) excluding OH & CP t.km 11.31 Do
PM75002 Tipper- 5.5 Cum (Unsurfaced Gravelled Road) excluding OH t.km 13.74 Do
PM75003 & CP 5.5 Cum (Katcha Track) excluding OH & CP
Tipper- t.km 27.48 Do
PM76001 Transit Mixer - 6 Cum excluding OH & CP t.km 12.77 Do
PM77001 Loading and unloading of stone boulder / stone aggregates / sand / kanker / cum 0.00 Do
PM77002 moorum (Using
Loading and by 18 cum
unloading capacity
of stone Tipper
boulder & aggregates / sand / kanker /
/ stone cum 0.00 Do
3.1 Cum capacity
moorum (Using Loader)
by 14 cum excluding
capacity OH & CP
Tipper & aggregates /
PM77003 Loading and unloading of stone boulder / stone cum 0.00 Do
2.1
sandCum capacity
/ kanker Loader) (Using
/ moorum excluding OHcum
by 10 & CPcapacity Tipper & 1.0 Cum capacity
PM77004 Loading and unloading of stone boulder / stone aggregates / sand / kanker / cum 0.00 Do
Loader)
moorum excluding
(Using byOH & CPcapacity Tipper &
5 cum
PM77005 Loading and Unloading of Cement or Steel by Manual Means tonne 0.00 Do
1.0
and Cum capacity Loader) excluding OH & CP
Stacking
PM78001 Centrifugal water pump Hour 329.00
PM79001 Shredding Machine Hour 416.00
PM80001 Mobile Bridge Inspection Unit (MBIU) hour 6,887.00
PM81001 Network Survey Vehicle (NSV) With SUV hour 6,415.00
PM82001 Falling weight deflectometer (FWD) Equipment With SUV hour 3,128.00
PM83001 Retroreflectometer testing equipment with Vehicle With SUV hour 1,709.00
PM84001 Sport utility vehicle (SUV) hour 1,221.00
PM85001 Automatic Vehicle Counter Classifier (ATCC) System hour 74.00
PM90001 WMM Paver finisher hour 1810.00
PM90002 6.5 KVA Generator set hour 304.00
PM90003 Sensor Paver Finisher(158 BHP) hour 3958.00

Approved
S.No. Description of Labour Unit
Rate
1 2 3 4
L-01 Blacksmith (IInd class) day 679
L-02 Blacksmith (Ist class)/ Welder/Plumber/Electrician day 738
L-03 Blaster (Stone cutter) day 511.52
L-04 Carpenter I Class day 738
L-05 Chiseller (Head Mazdoor) day 617
L-06 Driller (Jumper) day 558
L-07 Diver day 738
L-08 Fitter day 738
L-09 Mali day 511.52
L-10 Mason (IInd class) day 679
L-11 Mason (Ist class) day 738
L-12 Mate / Supervisor day 617
L-13 Mazdoor day 511.52
L-14 Mazdoor/Dresser (Semi Skilled) day 617
L-15 Mazdoor/Dresser/Sinker (Skilled) day 565.73
L-16 Medical Officer day 1077.25
L-17 Operator(grouting) day 738
L-18 Painter I class day 679
L-19 Para medical personnel day 622.72
L-20 Heavy Plant Operator day 626.89
L-21 Light Plant Operator. day 514.3
L-22 Heavy Vehicle Driver. day 1459.5
L-23 Light Vehicle Driver. day 676.93
L-24 Helper day 558
L-25 Black smith day 679
Basic Rate As per
2016 SOR

748.79
748.79
987.08
1303.77
1303.77
863.77
553.77
822.08
903.77
111.77
400
1325.57
1383.77
1383.77
1313.77
1343.77
1253.77
1253.77
1303.77
968.77
1136.27
1253.77
1253.77
1298.77
1318.77
1353.77
1353.77
1353.77
1353.77
1303.77
1378.77
1328.77
1349.22
1323.77
1321.93
1314.43
1262.79
1247.79
1403.77
1338.77
1353.77
1338.77
1303.77
1403.77
1318.77
1403.77
1370.44
1353.77
1403.77
1403.77
1303.77
1403.77
1353.77
1362.79

42.54
170
130
7980.04

7560.00
169.19
48
630
5145.00
0.59
12915.00
6310.00
136.66
34165.00
136.66
146.43
156.19
151.31
34788.00
10933.11
3.1
48
46064.00
40930.00
42380.00
40930.00
42036.00
41270.00
5.48
50
5700
45

55.00
735.00
5
280
52
230

30
275
159

27202.73

550
502
150
378.00
118.00
100.00
20
19.00
126.00
236.00
89.00
210.00
45
45
15.96
1.00
25
25
234.00
252.00
25.00
1008
120

27
56.00
83
30
45
50.00

8400.00
8400.00
19
61.74
224.02
124
76.89
336.00
178.00
160
160.18
30
1124
205
450
1403.77
948
376.00
41
288.00
103
440
5565
6510
4494
2310
1200
65.04

6.00
8.48
300.00
130.00
84.00
159.71
12
210.00

54.00

300.00

4210
889.00

10000

15000

123.62
221.22
321
42.65
42.65
159.51
330.00
43
1.50
23.85

46.14
2700
16.00

70
48
48
20.85
504.19

32.00
200
220
300
330
350
390
420
500
550
650
708
841
950
1000
1088
78
6,273.00
4,845.00
3,336.00
5,907.00
5,419.00
2100
3,293.00
2,965.00
2,689.00
206.00
4,076.00
2,515.00
800
2,746.00
2,435.00
2,166.00
1,649.00
650
200
1150
1,369.00
2,440.00
1,440.00
1,270.00
200
1250
16
21
585
2621
14744
878
583
558
13938
9846
7974
6013
3909
937
487
525
11044
7640
6162
2500
2277
1944
1250
718
405
200
1647
800
708
750
1500
8794
6971
26770
17335
4302
4600
3626
2115
1711
2299
1278
4192
1864
18807
6591
1859
3808
487
503
562
11
569
4557
5326
7625
11412
29344
25468
7905
21331
103480
1211
5162
7829
11436
7417
1150
1743
760
313
900
6029
6267
9503
1032
1075
1181
1218
1509
2280
146
533
929
1042
362
9594
360
17687
448
487
368
487
407
368
487
487
368
448
487
407
368
368
407
775
1050
448
448
451
370
1050
487
900
448
(A) Usage Rates of Plant and Machinery
Power
Sl. No. Description of Machine Activity Unit Rate
(in HP)
P&M-001 Dozer - 240 HP Spreading Cutting Clearing 6587 Hour 6,586.65
P&M-002 Dozer - 175 HP Spreading Cutting Clearing 5087 Hour 5,087.25
P&M-003 Dozer - 90 HP Spreading Cutting Clearing 3503 Hour 3,502.80
P&M-004 Motor Grader 4.3 metre blade Clearing Scarifying Spreading GSB WMM 5991 Hour 5,991.00
P&M-005 Motor Grader 3.7 metre blade Clearing Scarifying Spreading GSB WMM 5497 Hour 5,497.00
P&M-006 Motor Grader 3.35 metre blade Clearing Scarifying Spreading GSB WMM 4796 Hour 4,796.00
P&M-007 Hydraulic Excavator of 1.2 cum bucket Soil Ordinary Soil Marshy Soil Unsuitable 3420 Hour 3,420.00
P&M-008 Hydraulic Excavator of 1.1 cum bucket Soil Ordinary Soil Marshy Soil Unsuitable 3074 Hour 3,074.00
P&M-009 Hydraulic Excavator of 0.9 cum bucket Soil Ordinary Soil Marshy Soil Unsuitable 2782 Hour 2,782.00
P&M-010 Jack Hammer (attachment of Hydraulic Excavator) For Drilling Purpose 216 Hour 206.00
P&M-011 Front End loader 3.1 cum bucket capacity Soil loading, Aggregate loading, etc. 4280 Hour 4,279.80
P&M-012 Front End loader 2.1 cum bucket capacity Soil loading, Aggregate loading, etc. 2641 Hour 2,640.75
P&M-013 Backhoe-loader 1 cum bucket capacity Soil loading, Aggregate loading, etc. 1112 Hour 1,112.00
P&M-014 Tipper-18 Cum Transpotation of Soil, GSB,WMM, Hotmix etc. 2883 Hour 2,883.30
P&M-015 Tipper-14 Cum Transpotation of Soil, GSB,WMM, Hotmix etc. 2557 Hour 2,556.75
P&M-016 Tipper-10 Cum Transpotation of Soil, GSB,WMM, Hotmix etc. 2274 Hour 2,274.30
P&M-017 Tipper-5.5 Cum Transpotation of Soil, GSB,WMM, Hotmix etc. 1731 Hour 1,731.45
P&M-018 Vibratory Soil Compactor (10 tonne) Earth/Soil, GSB, WMM 904 Hour 903.50
P&M-019 Smooth Wheeled Roller 8 tonne Soil Compaction BM Compaction 417 Hour 417.00
P&M-020 Tandem Roller Rolling of Asphalt Surface 1668 Hour 1,668.00
P&M-021 Mini Tandem Roller Earth/Soil 1437 Hour 1,437.45
P&M-022 Pneumatic Road Roller Rolling of Asphalt Surface 2562 Hour 2,562.00
P&M-023 Water Tanker (16 KL) Water Transport. 1501 Hour 1,501.00
P&M-024 Water Tanker (12 KL) Water Transport. 1327 Hour 1,327.00
P&M-025 Water Tanker (6 KL) Water Transport. 1005 Hour 1,005.00
P&M-026 Tractor-trolley Pulling, Tranportation,etc. 1877 Hour 1,876.50
P&M-027 Rotavator Scarifying 17 Hour 16.80
P&M-028 Ripper Scarifying 22 Hour 22.05
P&M-029 Air Compressor -250 cfm General Purpose 614 Hour 614.25
P&M-030 Air Compressor -500 cfm General Purpose 2752 Hour 2,752.05
P&M-031 Integrated Stone Crusher Stone (3 Stage) 250 TPH Crushing of Spalls 15481 Hour 15,481.20
P&M-032 Wet Mix Plant - 250 TPH Capacity Wet Mix 922 Hour 921.90
P&M-033 Wet Mix Plant - 200 TPH Capacity Wet Mix 612 Hour 612.15
P&M-034 Wet Mix Plant - 100 TPH Capacity Wet Mix 586 Hour 585.90
P&M-035 Hotmix Plant - 200 TPH Capacity DBM / BM / BC / Premix etc. 14635 Hour 14,634.90
P&M-036 Hotmix Plant - 160 TPH Capacity DBM / BM / BC / Premix etc. 10338 Hour 10,338.30
P&M-037 Hotmix Plant - 120 TPH capacity DBM / BM / BC / Premix etc. 8373 Hour 8,372.70
P&M-038 Batching and Mixing Plant - 240 cum Capacity Concrete Mixing 6314 Hour 6,313.65
P&M-039 Batching and Mixing Plant - 120 cum Capacity Concrete Mixing 4104 Hour 4,104.45
P&M-040 Mobile Concrete Batching / Mixing Plant Concrete Mixing 984 Hour 983.85
P&M-041 Concrete Mixer - 0.4/0.28 cum Concrete Mixing 511 Hour 511.35
P&M-042 Concrete Mixer - 1 cum Concrete Mixing 551 Hour 551.25
P&M-043 Generator 725 KVA Generation of Electric Energy 11596 Hour 11,596.20
P&M-044 Generator 500 KVA Generation of Electric Energy 8022 Hour 8,022.00
P&M-045 Generator 400 KVA Generation of Electric Energy 6470 Hour 6,470.10
P&M-046 Generator 250 KVA Generation of Electric Energy 3475 Hour 3,475.00
P&M-047 Generator 125 KVA Generation of Electric Energy 2391 Hour 2,390.85
P&M-048 Generator 100 KVA Generation of Electric Energy 2041 Hour 2,041.20
P&M-049 Generator 62.5 KVA Generation of Electric Energy 1313 Hour 1,312.50
P&M-050 Generator 33 KVA Generation of Electric Energy 754 Hour 753.90
P&M-051 Generator 15 KVA Generation of Electric Energy 425 Hour 425.25
P&M-052 Mechanical Broom Hydraulic Surface Cleaning 500 Hour 500.40
P&M-053 Bitumen Pressure Distributor Applying bitumen tack coat 1729 Hour 1,729.35
P&M-054 Emulsion Pressure Distributor Applying bitumen tack coat 1112 Hour 1,112.00
P&M-055 Bitumen Boiler Oil Fired Bitumen Spraying 743 Hour 743.40
P&M-056 Mastic Cooker Mastic Wearing Coat 1043 Hour 1,042.50
P&M-057 Paver Finisher Mechanical Paving of WMM 1112 Hour 1,112.00
P&M-058 Paver Finisher Hydrostatic with sensor control -240 HP Paving of DBM/BM/BC/ Premix etc. 9234 Hour 9,233.70
P&M-059 Paver Finisher Hydrostatic with sensor control -170 HP Paving of DBM/BM/BC/ Premix etc. 2363 Hour 2,362.50
P&M-060 Paver Finisher Concrete with 300 HP Motor Paving of Concrete Surface 28109 Hour 28,108.50
P&M-061 Paver Finisher Concrete with 241 HP Motor Paving of Concrete Surface 18202 Hour 18,201.75
P&M-062 Paver Finisher Concrete with 118 HP Motor Paving of Concrete Surface 4517 Hour 4,517.10
P&M-063 Texture Curing Machine (TCM) - upto 18 m Texturing of Concrete Surface 4830 Hour 4,830.00
P&M-064 Texture Curing Machine (TCM) - upto 9 m Texturing of Concrete Surface 3807 Hour 3,807.30
P&M-065 Hydraulic Chip Spreader Surface Dressing 2221 Hour 2,220.75
P&M-066 Pot-Hole Repair Machine Repair of pot-holes 1797 Hour 1,796.55
P&M-067 Transit Mixer - 6 Cum Mix to Site Transportation of Concrete 2414 Hour 2,413.95
P&M-068 Concrete Pump Pumping of Concrete 1342 Hour 1,341.90
P&M-069 Boom Placer Pumping of Concrete 4402 Hour 4,401.60
P&M-070 Kerb Casting Machine Kerb Making 1957 Hour 1,957.20
P&M-071 Piling Rig with Bentonite Pump Piling in foundation 19747 Hour 19,747.35
P&M-072 Pneumatic Sinking Plant Sinking Purpose 6921 Hour 6,920.55
P&M-073 Road marking machine Road Marking 1952 Hour 1,951.95
P&M-074 Mobile Slurry Seal Equipment Mixing and laying slurry seat 3998 Hour 3,998.40
P&M-075 Joint Cutting Machine Cutting Purpose 511 Hour 511.35
P&M-076 Bar Bending & Cutting Machine Bar Cutting & Bending 528 Hour 528.15
P&M-077 Needle Vibrator Concrete pouring 590 Hour 590.10
P&M-078 Jack Hammer for air compressor General Purpose 12 Hour 11.55
P&M-079 Plate Compactor Compaction 597 Hour 597.45
P&M-080 Milling Machine with 1 meter Drum Width Milling of bitumen surface 4785 Hour 4,784.85
P&M-081 Milling Machine with 1.2 meter Drum Width Milling of bitumen surface 5592 Hour 5,592.30
P&M-082 Milling Machine With 1.3 meter Drum Width Milling of bitumen surface 8006 Hour 8,006.25
P&M-083 Milling Machine With 2 meter Drum Width Milling of bitumen surface 11983 Hour 11,982.60
P&M-084 Cold in Situ recycling of bitumen's pavement with foam bitumen technology Recycling of bitumen surface 30811 Hour 30,811.20
P&M-085 In situ stabilisation of WMM/GSB/Sub grade Stabilisation of WMM/GSB/Sub grade 26741 Hour 26,741.40
P&M-086 Cement spreader Spreading 8300 Hour 8,300.25
P&M-087 Mobile cold recycling mixing plant Recycling of bitumen surface 22398 Hour 22,397.55
P&M-088 Hot in place recycling Recycling of bitumen surface 108654 Hour 108,654.00
P&M-089 Pre heater unit for hot in place recycling Recycling of bitumen surface 1272 Hour 1,271.55
P&M-090 Single boom Hydraulic Drill Jumbo Drilling Purpose 5420 Hour 5,420.10
P&M-091 Two boom Hydraulic Drill Jumbo Drilling Purpose 8220 Hour 8,220.45
P&M-092 Three boom Hydraulic Drill Jumbo Drilling Purpose 12008 Hour 12,007.80
P&M-093 Hydraulic Rock bolt drill Drilling Purpose 7788 Hour 7,787.85
P&M-094 Rotating Telehandlers General Purpose 1208 Hour 1,207.50
P&M-095 Shotcrete Machine Concreting Purpose 1830 Hour 1,830.15
P&M-096 Grouting machine Grouting Purpose 798 Hour 798.00
P&M-097 Dewatering Pump 10 HP Dewatering 329 Hour 328.65
P&M-098 Concrete cutting machine Concrete cutting Purpose 1251 Hour 1,251.00
P&M-099 Crawler mounted Crane 35 tonne capacity Lifting Purpose 6330 Hour 6,330.45
P&M-100 Crawler mounted Crane 80 tonne capacity Lifting Purpose 6580 Hour 6,580.35
P&M-101 Crawler mounted Crane 100 tonne capacity Lifting Purpose 9978 Hour 9,978.15
P&M-102 Mobile Hydraulic Crane 3 tonne capacity Lifting Purpose 1084 Hour 1,083.60
P&M-103 Mobile Hydraulic Crane 5 tonne capacity Lifting Purpose 1129 Hour 1,128.75
P&M-104 Mobile Hydraulic Crane 10 tonne capacity Lifting Purpose 1240 Hour 1,240.05
P&M-105 Mobile Hydraulic Crane 15 tonne capacity Lifting Purpose 1279 Hour 1,278.90
P&M-106 Mobile Hydraulic Crane 20 tonne capacity Lifting Purpose 1584 Hour 1,584.45
P&M-107 Mobile Hydraulic Crane 35 toone capacity Lifting Purpose 2394 Hour 2,394.00
P&M-108 Concrete Bucket For Purring Concrete 153 Hour 153.30
P&M-109 Prestressing Jack with Pump & Access (400 tonne) Stressing of Steel Wires/Stands 560 Hour 559.65
P&M-110 Boat to carry atleast 20 persons General Purpose 975 hour 975.45
P&M-111 Crane with grab 0.75 cum capacity Lifting Purpose 1094 hour 1,094.10
P&M-112 Epoxy Injection gun - 380 hour 380.10
Induction, deinduction and erection of plant and equipment including all
P&M-113 Well sinking 10074 hour 10,073.70
components and accessories for pneumatic method of well sinking.
P&M-114 Jack for Lifting 40 tonne lifting capacity. Lifting Purpose 378 hour 378.00
P&M-115 Vibrating Pile driving hammer complete with power unit and accessories. Pile driving 18571 hour 18,571.35
Per Tonne
P&M-116 Tipper-18 Cum (Surface Road) excluding OH & CP Transportation of Soil, GSB,WMM, Hotmix etc. 6 6.18
Km.
Per Tonne
P&M-117 Tipper-18 Cum (Unsurfaced Gravelled Road) excluding OH & CP Transportation of Soil, GSB,WMM, Hotmix etc. 7 7.51
Km.
Per Tonne
P&M-118 Tipper-18 Cum (Katcha Track) excluding OH & CP Transportation of Soil, GSB,WMM, Hotmix etc. 14 15.02
Km.
Per Tonne
P&M-119 Tipper -14 Cum (Surface Road) excluding OH & CP Transportation of Soil, GSB,WMM, Hotmix etc. 7 7.01
Km.
Per Tonne
P&M-120 Tipper -14 Cum (Unsurfaced Gravelled Road) excluding OH & CP Transportation of Soil, GSB,WMM, Hotmix etc. 8 8.52
Km.
Per Tonne
P&M-121 Tipper -14 Cum (Katcha Track) excluding OH & CP Transportation of Soil, GSB,WMM, Hotmix etc. 16 17.05
Km.
Per Tonne
P&M-122 Tipper -10 Cum (Surface Road) excluding OH & CP Transportation of Soil, GSB,WMM, Hotmix etc. 8 8.66
Km.
Per Tonne
P&M-123 Tipper -10 Cum (Unsurfaced Gravelled Road) excluding OH & CP Transportation of Soil, GSB,WMM, Hotmix etc. 10 10.53
Km.
Per Tonne
P&M-124 Tipper -10 Cum (Katcha Track) excluding OH & CP Transportation of Soil, GSB,WMM, Hotmix etc. 20 21.06
Km.
Per Tonne
P&M-125 Tipper- 5.5 Cum (Surface Road) excluding OH & CP Transportation of Soil, GSB,WMM, Hotmix etc. 11 11.87
Km.
Per Tonne
P&M-126 Tipper- 5.5 Cum (Unsurfaced Gravelled Road) excluding OH & CP Transportation of Soil, GSB,WMM, Hotmix etc. 14 14.43
Km.
Per Tonne
P&M-127 Tipper- 5.5 Cum (Katcha Track) excluding OH & CP Transportation of Soil, GSB,WMM, Hotmix etc. 27 28.86
Km.
Per Tonne
P&M-128 Transit Mixer - 6 Cum excluding OH & CP Mix to Site Transportation of Concrete 13 13.41
Km.
Loading and unloading of stone boulder / stone aggregates / sand / kanker /
P&M-129 moorum (Using by 18 cum capacity Tipper & 3.1 Cum capacity Loader) - 0 Cum 92.72
excluding OH & CP.
Loading and unloading of stone boulder / stone aggregates / sand / kanker /
P&M-130 moorum (Using by 14 cum capacity Tipper & 2.1 Cum capacity Loader) - 0 Cum 92.81
excluding OH & CP
P&M-131 Loading and unloading of stone boulder / stone aggregates / sand / kanker / - 0 Cum 118.14
P&M-132 moorum (Using
Loading and by 10 cum
unloading capacity
of stone Tipper
boulder & 1.0
/ stone Cum capacity
aggregates / sandLoader)
/ kanker / - 0 Cum 117.36
P&M-133 moorum (Using
Loading and by 5 cumof capacity
Unloading Cement Tipper
or Steel&by
1.0Manual
Cum capacity Loader)
Means and Stacking - 0 tonne 562.10
P&M-134 Centrifugal water pump Water Pumping 329 Hour 329.00
P&M-135 Shredding Machine Shredding of waste Plastic 416 Hour 416.00
P&M-136 Mobile Bridge Inspection Unit (MBIU) For Inspection of Bridge 6887 hour 6,887.00
P&M-137 Network Survey Vehicle (NSV) With SUV For Pavement Inspection/Survey Purpose 6415 hour 6,415.00
P&M-138 Falling weight deflectometer (FWD) Equipment With SUV For Testing Purpose 3128 hour 3,128.00
P&M-139 Retroreflectometer testing equipment with Vehicle With SUV For Testing Retro reflection 1709 hour 1,709.00
P&M-140 Sport utility vehicle (SUV) General Purpose 1221 hour 1,221.00
P&M-141 Automatic Vehicle Counter Classifier (ATCC) System Traffic Counting 74 hour 74.00
P&M-142 Boring Machine hour 5,000.00
(B) Labour
Sl. No. Description of Labour Unit Rate
L-01 Blacksmith (IInd class) day 679.00
L-02 Blacksmith (Ist class)/ Welder/ Plumber/ Electrician day 738.00
L-03 Blaster (Stone cutter) day 511.52
L-04 Carpenter I Class day 738.00
L-05 Chiseller (Head Mazdoor) day 617.00
L-06 Driller (Jumper) day 558.00
L-07 Diver day 738.00
L-08 Fitter day 738.00
L-09 Mali day 511.52
L-10 Mason (IInd class) day 679.00
L-11 Mason (Ist class) day 738.00
L-12 Mate / Supervisor day 617.00
L-13 Mazdoor day 511.52
L-14 Mazdoor/Dresser (Semi Skilled) day 617.00
L-15 Mazdoor/Dresser/Sinker (Skilled) day 565.73
L-16 Medical Officer day 1,077.25
L-17 Operator(grouting) day 738.00
L-18 Painter I class day 679.00
L-19 Para medical personnel day 622.72
L-20 Black smith day 679.00

(C) Materials
Sl. No. Description Unit Rate
M-001 Stone Boulder of size 150 mm and below at Cruser Plant cum 1472.59

M-002 Supply of quarried stone 150 - 200 mm size for Hand Broken at site cum 1472.59

M-003 Boulder with minimum size of 300 mm for Pitching at Site cum 1994.63

M-004 Coarse sand at Mixing Plant cum 1994.03

M-005 Coarse sand at Site cum 1994.03

M-006 Fine sand at Site cum 1544.03

M-007 Moorum at Site cum 1297.52

M-008 Gravel/Quarry spall at Site Cum 1679.81

M-009 Granular Material or hard murrum for GSB works at Site Cum 1887.12

M-010 Fly ash conforming to IS: 3812 ( Part II & I) atHMP Plant / Batching Plant / Crushing Plant MT 204.70

M-011 Filter media/Filter Material as per Table 300-3 (MoRT&H Specification) at Site Cum 1215.07

M-013 Close graded Granular sub-base Material 37.5 mm to 9.5 mm cum 1837.12
M-014 Close graded Granular sub-base Material 26.5 mm to 9.5 mm cum 1887.12
M-015 Close graded Granular sub-base Material 9.5 mm to 4.75 mm cum 1887.12
M-016 Close graded Granular sub-base Material 9.5 mm to 2.36 mm cum 1887.12
M-017 Close graded Granular sub-base Material 4.75mm to 2.36 mm cum 1937.12
M-018 Close graded Granular sub-base Material 4.75mm to 75 micron mm cum 1887.12
M-019 Close graded Granular sub-base Material 2.36 mm cum 1887.12
M-020 Stone crusher dust finer than 3mm with not more than 10% passing 0.075 sieve. cum 1887.12
M-021 Coarse graded Granular sub-base Material 2.36 mm & below cum 1887.12
M-022 Coarse graded Granular sub-base Material 4.75mm to 75 micron mm cum 1887.12
M-023 Granular sub-base Material 4.75 mm to 2.36 mm cum 1887.12
M-024 Granular sub-base Material 9.5 mm to 4.75 mm cum 1887.12
M-025 Coarse graded Granular sub-base Material 26.5 mm to 4.75 mm cum 1887.12
M-026 Granular sub-base Material 26.5 mm to 9.5 mm cum 1887.12
M-027 Coarse graded Granular sub-base Material 37.5 mm to 9.5 mm cum 1887.12
M-028 Granular sub-base Material 53 mm to 26 .5mm cum 1887.12
M-029 Aggregates below 5.6 mm cum 1887.12
M-030 Aggregates 22.4 mm to 2.36 mm cum 1887.12
M-031 Aggregates 22.4 mm to 5.6 mm cum 1887.12
M-032 Aggregates 45 mm to 2.8 mm cum 1887.12
M-033 Aggregates 45 mm to 22.4 mm cum 1887.12
M-034 Aggregates 53 mm to 2.8 mm cum 1887.12
M-035 Aggregates 53 mm to 22.4 mm cum 1887.12
M-036 Aggregates 63 mm to 2.8 mm cum 1887.12
M-037 Aggregates 63 mm to 45 mm cum 1887.12
M-038 Aggregates 90 mm to 45 mm cum 1887.12
M-039 Aggregates 10 mm to 5 mm cum 1887.12
M-040 Aggregates 11.2 mm to 0.09 mm cum 1887.12
M-041 Aggregates 13.2 mm to 0.09 mm cum 1887.12
M-042 Aggregates 13.2 mm to 5.6 mm cum 1887.12
M-043 Aggregates 13.2 mm to 10 mm cum 1887.12
M-044 Aggregates 20 mm to 10 mm cum 1887.12
M-045 Aggregates 25 mm to 10 mm cum 1887.12
M-046 Aggregates 19 mm to 6 mm cum 1887.12
M-047 Aggregates 37.5 mm to 19 mm cum 1887.12
M-048 Aggregates 37.5 mm to 25 mm cum 1887.12
M-049 Aggregates 6 mm nominal size cum 1887.12
M-050 Aggregates 10 mm nominal size cum 1887.12
M-051 Aggregates 13.2/12.5 mm nominal size cum 1887.12
M-052 Aggregates 20 mm nominal size cum 1887.12
M-053 Aggregates 25 mm nominal size cum 1887.12
M-054 Aggregates 40 mm nominal size cum 1887.12
M-055 Crushing of stone aggregates (GSB Crusher Run) cum 537.12
M-056 AC pipe 100 mm dia metre 59.13
M-057 Acrylic polymer bonding coat litre 236.30
M-058 Alluminium Paint litre 180.70
M-059 Aluminium alloy plate 2mm Thick sqm 8379.04
M-060 Aluminium alloy/galvanised steel tonne 46496.54
Aluminium sheeting fixed with encapsulated lens type reflective sheeting including 2% towards lettering, cost of angle iron, cost of drilling holes,
M-061 sqm 7560.00
nuts, bolts etc.and signs as applicable
M-062 Aluminium studs 100 x 100 mm fitted with lense reflectors nos 169.19
M-063 Barbed wire kg 66.72
M-064 Bearing (Cost of parts) nos 630.00
M-065 Bearing (Cast steel rocker bearing assembly of 250 tonne ) nos 55660.00
Bearing (Elastomeric bearing assembly consisting of 7 internal layers of elastomer bonded to 6 nos. internal reinforcing steel laminates by the cubic cm 0.59
M-066 process of vulcanisation,)
Taking elastomeric bearing of size 500 X 400 X 96mm, Overall nos 12915.00
volume=19200 cubic cm @Rs 0.59/cucm= Rs 11328
M-067 Bearing (Forged steel roller bearing of 250 tonne nos 85008.00
Bearing (Pot type bearing assembly consisting of a metal piston supported by a disc, PTFE pads providing sliding surfaces against stainless steel MT 136.66
mating together with cast steel assemblies/fabricated structural steel assemblies duly painted with all components
Do nos 34165.00
(a) Fixed POT-PTFE Bearing MT 136.66
M-068 (b) Free POT-PTFE Bearing MT 146.43
(c) Guide Slide (L) POT-PTFE Bearing MT 156.19
(d) Guide Slide (T) POT-PTFE Bearing MT 151.31
M-069 Bearing (PTFE sliding plate bearing assembly of 80 tonnes ) nos 34788.00
M-070 Bearing (Supply of sliding plate bearing of 80 tonne) nos 34420.00
M-071 Bentonite kg 4.31
M-072 Binding wire kg 66.72
M-073 Bitumen ( Cationic Emulsion ) tonne 51690.37
M-074 Bitumen (60-70 grade)VG-40 tonne 46556.37
M-075 Bitumen (80-100 grade )VG-40 tonne 48006.37

M-076 Bitumen (Cutback ) tonne 46556.37

M-077 Bitumen (emulsion) tonne 47662.37


M-078 Bitumen (modified graded) tonne 46896.37
M-079 Brick each 3.50
M-080 C.I.shoes for the pile kg 69.50
M-081 Cement tonne 4940.00
M-082 CGI Sheet (0.8 mm thick) kg 62.55
M-083 Cold twisted bars (HYSD Bars) tonne 46496.54
M-084 Coller for joints 300 mm dia nos 76.45
M-085 Compressible Fibre Board(20mm thick) sqm 735.00
M-086 Connectors/ Staples each 6.95
M-087 Copper Plate(12m long x 250mmwide) kg 389.20
M-088 Corrosion resistant Structural steel tonne 44000.00
M-089 Corrugated sheet, 3 mm thick, "Thrie" beam section railing kg 72.28
M-090 Credit for excavated rock found suitable for use cum 319.70
M-091 Curing compound liter 41.70
M-092 Delineators from ISI certified firm as per the standard drawing given in IRC - 79 each 382.25
M-093 Earth Cost or compensation for earth taken from private land cum 45.00
Elastomeric slab seal expansion joint assembly manufactured by using chloroprene, elastomer for elastomeric slab unit conforming to clause 915.1
M-094 metre 27202.73
of IRC: 83 (part II),
M-095 Epoxy compound with accessories for preparing epoxy mortar kg 764.50
M-096 Epoxy mortar kg 697.78
M-097 Epoxy primer kg 208.50
M-098 Epoxy resin-hardner mix for prime coat kg 378.00
M-099 Flag of red color cloth 600 x 600 mm each 118.00
M-100 Flowering Plants each 100.00
M-101 Galvanised MS flat clamp nos 27.80
M-102 Galvanised steel wire crates of mesh size 100 mm x 100 mm woven with 4mm dia. GI wire in rolls of required size. sqm 19.00
M-103 Galvanised structural steel plate 200 mm wide, 6 mm thick, 24 m long kg 63.00
M-104 Geo grids sqm 236.00
M-105 Geomembrane sqm 89.00
M-106 Geonets sqm 210.00
M-107 Geotextile sqm 62.55
M-108 Geotextile filter fabric sqm 62.55
M-109 GI bolt 10 mm Dia nos 16.76
M-110 Grouting pump with agitator hour 798.00
M-111 Grass (Doob) kg 34.75
M-112 Grass (Fine) kg 34.75
M-113 HDPE pipes 75mm dia metre 234.00
M-114 HDPE pipes 90mm dia metre 252.00
M-115 Hedge plants each 25.00
M-116 Helical pipes 600mm diameter metre 1008.00
M-117 Hot applied thermoplastic compound litre 166.80

M-118 HTS strand tonne 63806.54

M-119 Joint Sealant Compound kg 37.53


M-120 Jute netting, open weave, 2.5 cm square opening for seeding and Mulching sqm 56.00
M-121 LDO for steam curing litre 83.00
M-122 M.S. Clamps nos 41.70
M-123 M.S. Clamps kg 62.55
M-124 M.S.shoes @ 35 Kg per pile of 15 m kg 50.00
M-125 Mild Steelstrip/box
Modular bars seal expansion joint including anchorage catering to a horizontal movement beyond 70 mm and upto 140mm assembly tonne 63806.54
M-126 comprising of edgeseal
Modular strip/box beams, centraljoint
expansion beam,2 modules
catering chloroprene
to a horizontal seal, anchorage
movement elements,
beyond 140mm support
and and control
upto 210mm system,
box/box seal all steel
joint sections
assembly protected3
containing metre 8400.00
M-127 against corrosion
modules/cells andand installedofbyedge
comprising the manufacturer or his beams,
beams, two central authorised representative
chloroprene seal, anchorage elements, support and control system, all steel metre 8400.00
M-128 sections protected against corrosion and installed by the manufacturer or his authorised representative
Nipples 12mm nos 26.41
M-129 Nuts and bolts kg 64.83
M-130 Paint litre 235.22
M-131 Pavement Marking Paint litre 172.36
M-132 Paving Fabric sqm 80.73
M-133 Perforated geosynthetic pipe 150 mm dia metre 336.00
M-134 Perforated pipe of cement concrete, internal dia 100 mm metre 178.00
M-135 Pesticide kg 222.40
M-136 Pipes 200 mm dia, 2.5 m long for drainage metre 168.19
M-137 Plastic sheath, 1.25 mm thick for dowel bars sqm 41.70
M-138 Plastic tubes 50 cm dia, 1.2 m high nos 1124.00
M-139 Polymer braids metre 205.00
M-140 Pre moulded Joint filler,25 mm thick for expansion joint. sqm 625.50
M-141 Pre-coated stone chips of 13.2 mm nominal size cum 1951.24
Preformed continuous chloroprene elastomer or closed cell foam sealing element with high tear strength, vulcanised in a single operation for the full
M-142 metre 948.00
length of a joint to ensure water tightness.
M-143 Pre-moulded asphalt filler board sqm 376.00
M-144 Pre-packed cement based polymer concrete of strength 45 Mpa at 28 days kg 41.00
M-145 Primer kg 288.00
M-146 Quick setting compound kg 103.00
M-147 Random Rubble Stone cum 611.60
M-148 RCC Pipe NP 4 heavy duty non presure pipe 1000 mm dia metre 5925.00
M-149 RCC Pipe NP 4 heavy duty non presure pipe 1200 mm dia metre 6547.00
RCC Pipe NP 4 heavy duty non presure pipe 1500 mm dia metre 7800.00
M-150 RCC Pipe NP 4 heavy duty non presure pipe 900 mm dia metre 5175.00
M-151 RCC Pipe NP 4 heavy duty non presure pipe 600 mm dia metre 3450.00
M-152 RCC Pipe NP 4 heavy duty non presure pipe 300 mm dia metre 2358.00
M-153 Reflectorising glass beads kg 68.29
M-154 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Copper Strips) metre 1.00
M-155 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Galvanised carbon steel strips) metre 1.00
M-156 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Glass reinforced polymer/fibre reinforced polymer/polymeric strips) metre 1.00
M-157 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Stainless steel strips) metre 1.00
M-158 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. Aluminium strips) metre 1.00
M-159 Rivets each 6.00
M-160 Sand bags (Cost of sand and Empty cement bag) nos 8.48
M-161 Sapling 2 m high 25 mm dia each 300.00
M-162 Scrap tyres of size 900 x 20 nos 130.00
M-163 Seeds kg 84.00
M-164 Selected earth cum 222.00
M-165 Separation Membrane of impermeable plastic sheeting 125 micron thick sqm 16.68
M-166 Sheathing duct metre 210.00
M-167 Shrubs each 54.00
M-168 Sludge / Farm yard manure @ 0.18 cum per 100 sqm at site of work for turfing cum 300.00
M-169 Sodium vapour lamp each 4210.00
M-170 Square Rubble Coursed Stone cum 933.45
Ashlar masonry ( first sort ) Plain ashlar cum 933.45
M-171 Steel circular hollow pole of standard specification for street lighting to mount light at 5 m height above deck level each 10000.00
M-172 Steel circular hollow pole of standard specification for street lighting to mount light at 9 m height above road level each 15000.00
M-173 Plastic barrels nos 150.00
M-173 Steel drum 300 mm dia 1.2 m high/empty bitumen drum nos 252.00
M-174 Steel helmet and cushion block on top of pile head during driving. kg 135.00
M-175 Steel pipe 25 mm external dia as per IS:1239 metre 129.80
M-176 Steel pipe 50 mm external dia as per IS:1239 metre 232.28
M-177 Steel pipe 100 mm external dia as per IS:1239 metre 337.05
M-178 Steel wire rope 20 mm kg 44.78
M-179 Steel wire rope 40 mm kg 44.78
M-180 Strip seal expansion join metre 8085.00
M-181 Structural Steel tonne 63806.54
M-182 Super plastisizer admixture IS marked as per 9103-1999 kg 167.49
Corrosion Inhibiting Admixture kg 70.00
M-183 Synthetic Geogrids as per clause 3102.8 and approved design and specifications. sqm 182.60
M-184 Through and bond stone each 59.77
M-185 Tie rods 20mm diameter nos 1.50
M-186 Tiles size 300 x 300 mm and 25 mm thick each 33.15
M-187 Timber cum 2500.00
M-188 Traffic cones with 150 mm reflective sleeve nos 640.00
M-189 Tube anchorage set complete with bearing plate, permanent wedges etc nos 48.45
M-190 Unstaked lime tonne 3753.00
M-191 Water KL 16.00
M-192 Water based cement paint litre 97.30
M-193 Welded steel wire fabric kg 66.72
M-194 Wire mesh 50mm x 50mm size of 3mm wire kg 66.72
M-195 Wooden ballies 2" Dia for bracing each 21.89
M-196 Wooden ballies 8" Dia and 9 m long each 529.40
M-197 Wooden packing cum 1659.00
M-198 Wooden staff for fastening of flag 25 mm dia, one m long each 16.00
M-199 Silica Fume Kg 33.60
M-200 Synthetic Geogrid Ultimate tensile strength- 100 kN/m sqm 278.00
M-201 Synthetic Geogrid Ultimate tensile strength- 150 kN/m sqm 305.80
M-202 Synthetic Geogrid Ultimate tensile strength- 200 kN/m sqm 417.00
M-203 Synthetic Geogrid Ultimate tensile strength- 250 kN/m sqm 458.70
M-204 Synthetic Geogrid Ultimate tensile strength- 300 kN/m sqm 486.50
M-205 Synthetic Geogrid Ultimate tensile strength- 350 kN/m sqm 542.10
M-206 Synthetic Geogrid Ultimate tensile strength- 400 kN/m sqm 583.80
M-207 Synthetic Geogrid Ultimate tensile strength- 500 kN/m sqm 695.00
M-208 Synthetic Geogrid Ultimate tensile strength- 600 kN/m sqm 764.50
M-209 Synthetic Geogrid Ultimate tensile strength- 700 kN/m sqm 903.50
M-210 Synthetic Geogrid Ultimate tensile strength- 800 kN/m sqm 984.12
M-211 Synthetic Geogrid Ultimate tensile strength- 900 kN/m sqm 1168.99
M-212 Synthetic Geogrid Ultimate tensile strength- 1000 kN/m sqm 1320.50
M-213 Synthetic Geogrid Ultimate tensile strength- 1100 kN/m sqm 1390.00
M-214 Synthetic Geogrid Ultimate tensile strength- 1200 kN/m sqm 1512.32
M-215 Explosives for blasting Kg 81.90
M-216 Delay Detonators for Nos. 21.00
M-217 Electric Detonators Nos. 21.00
M-218 Detonation fuse coil Meter 19.00
M-219 3.7 m long extension rod boom Hydraulic Drill Jumbo Nos 10000.00
M-220 32 mm coupling sleeve boom Hydraulic Drill Jumbo Nos 12000.00
M-221 Difter rod boom Hydraulic Drill Jumbo Nos 15000.00
M-222 R32 shank adapter boom Hydraulic Drill Jumbo Nos 13000.00
M-223 45 mm dia Button Bit boom Hydraulic Drill Jumbo Nos 3000.00
M-224 51 mm dia button bit boom Hydraulic Drill Jumbo Nos 5000.00
M-225 Steel Fiber tonne 46496.54
M-226 Microsilica Kg 32.00
M-227 Accelerator Kg 125.00
M-228 Wiremesh Kg 40.58
M-229 Bamboos Meter 17.75
M-230 Live Stake Stump Meter 1.00
M-231 Hard wood sticks Nos. 100.00
M-232 Live Sods (0.6m Length) Nos. 1.00
M-233 Live Sods ( 2m Length) tonne 1.00
M-234 Coal Tar Epoxy Kg. 1.00
M-235 Binding Material Meter 1.00
M-236 Spring post 700 mm each 375.00
M-237 Spring post 450 mm each 350.00
M-238 Water Filled Barricades Work zone sheeting (Trapezoidal Shape 800 mm to 1000 mm in length, 700 mm in height) each 2500.00
M-239 GI Pipe 100 mm Dia Meter 496.00
M-240 Bracket for GI pipe fixing Kg 1.00
M-241 Flange for GI pipe fixing Kg 1.00
M-242 Neem Cake Quintal 4000.00
M-244 Control Centre Server Nos. 1.00
M-245 Hot Standby Backup Server Nos. 1.00
M-246 NAS Video Server with storage Minimum 70 TB Nos. 1.00
M-247 Backup Video (Only Incidents) Server Nos. 1.00
M-248 Graphic Display (70" LED DLP in 3x2 matrix) Set 1.00
M-249 Graphic Display Controller and software including Video Switches Set 1.00
M-250 CCTV Monitoring Workstation Nos. 1.00
M-251 Emergency Telephone (1033) console Nos. 1.00
M-252 VIDS- Workstation Nos. 1.00
M-253 Administrative Workstation Nos. 1.00
M-254 ATMS Operator Workstation Nos. 1.00
M-255 CCTV Joystick Nos. 1.00
M-256 Operations Laser Printer (Colour) Nos. 1.00
M-257 Operations Laser Printer (Black) Nos. 1.00
M-258 Rack 19" Nos. 1.00
M-259 ATMS Control Room Software (integrated with VIDS, ATCC, VMS, MOS) LS 1.00
M-260 Video Management Software with atleast 150 VMS Lic. LS 1.00
M-261 Facility Monitoring System Controller Software LS 1.00
M-262 Server & Database license LS 1.00
M-263 Antivirus license LS 1.00
M-264 PTZ Camera (including CCTV Controller) Set 1.00
M-265 Solar System with UPS, battery & 12m Pole & Cabinet Set 1.00
M-266 VIDS Camera (including Image Processing unit) Set 1.00
M-267 Warning amber lights with hooters, 72 Hrs solar backup, 5m poles and foundation Set 1.00
M-268 Cabinet Nos. 1.00
M-269 12 m Pole (including manufacturing and galvanizing) Nos. 1.00
M-270 Solar System with UPS & batteries Set 1.00
M-271 Equipment, Sensor unit, Processing unit, Solar power supply and civil works for 4 Lanes Set 1.00
M-272 Solar System with UPS, batteries Set 1.00
M-273 VMS (Variable Message Sign - M type) Nos. 1.00
M-274 Gantry (including manufacturing and galvanizing) Nos. 1.00
M-275 Solar System with UPS, battery and cabinet for M type VMS Set 1.00
M-276 Uninterruptible Power Supply (UPS) For Server Rack (10 KVA) Set 1.00
M-277 Uninterruptible Power Supply (UPS) For TMC (30 KVA) Set 1.00
M-278 Power Distribution Board (Essential & Critical Supply) Set 1.00
M-279 MOS sensor Equipment (including MOS Controller) Set 1.00
M-280 Cabinet Nos. 1.00
M-281 Pole Nos. 1.00
M-282 Steel fence for protection Set 1.00
M-283 24 Core Armoured OFC + all accessories Meter 29.00
M-284 40 mm PLB HDPE duct as per latest TSEC specifications + all accessories Meter 1.00
M-285 Trenching of 1.8 meters, Laying & Backfilling for PLB HDPE duct Meter 1.00
M-286 Bi-Axial Extruded GeoGrids of Minimum Tensile Strength 15 kN/m sqm 1.00
M-287 Bi-Axial Extruded GeoGrids of Minimum Tensile Strength 20 kN/m sqm 1.00
M-288 Bi-Axial Extruded GeoGrids of Minimum Tensile Strength 30 kN/m sqm 1.00
M-289 Bi-Axial Extruded GeoGrids of Minimum Tensile Strength 40 kN/m sqm 1.00
M-290 Geosynthetic Drainage Composite ( tensile strength of 18 kN/m) sqm 175.00
M-291 Geosynthetic Drainage Composite (tensile strength of 13.5 kN/ m) sqm 150.00
M-292 Waste Plastic (as per IRC:SP:98-2013) tonne 5000.00
M293 RCC Pipe NP 4 heavy duty non presure pipe 1500 mm dia meter 1.00
M294 Acrylic noise barrier sheet Sqm 90.00
M295 Silt Fence Sheet Sqm 250.00
M296 Fully Threaded Hot Dip galvanised geotechnical bars with casing' Lm 1.00
M297 Centralizer No 1.00
M298 Bearing Plate 200mm x 200mm x 10mm No 1.00
M299 Spherical dome nut Nos. 1.00
M300 Fibre Reinforcement tonne 1.00
M301 Geotextile Sqm 1.00
M302 Polyvinyl Chloride Pipe (PVC)-90 mm meter 300.00
M303 Polyvinyl Chloride Pipe (PVC)-110 mm meter 350.00
M304 Polyvinyl Chloride Pipe (PVC)-135 mm meter 400.00
M305 Steel/Iron Scraps Kg. 1.00
M307 Geocell sqm 80.00
M308 Geosynthetics mat sqm 50.00
M309 Natural geotextile sqm 25.00
M310 Fabric Form mattress sqm 1.00
M311 Non-Woven Geotextile sqm 1.00
M312 Sr. Road Safety/Auditor/ Team Leader for Road Safety Audit Month 100000.00
M313 Traffic Planner for Road Safety Audit Month 75000.00
M314 Boarding & Loading and Per Diem for Site Visits (During Road Days 3500.00
M315 Safety Audit) at site and Head Office (During Road Safety
Transportation No. of Trip 1200.00
M316 Audit)
Duty travel to Site (During Road Safety Audit) Days 2000.00
Collection of Road accident data and analysis of fatal and grievously injured accident with black spot identification (During
M317 Road Safety Audit) No. of Copies 5000.00
M318 Submission of GAP report (For Road Safety Audit) No. of
7000.00
Copies
M319 Road Safety Audit Reports on all activities which were planned, No. of
actually executed and planned for the next quarter. 7000.00
Copies
M320 Submission of Audit Report of work zone safety (for Road Safety No. of
Audit) 15000.00
Copies
M321 Workshop Report for Road Safety Audit No. of
4500.00
Copies
M322 Final Safety Report (for road safety Audit) No. of
25000.00
Copies
M-323 Cement Fly Ash Brick (Conforming to IS 12894, size= 230 X 110 X 70 mm, weight of one brick= 3Kg, composition: Fly ash= 60%, Coarse sand= each 5.01
30%,
PaverCement= 10%) including
Block (Excluding GST ) carriage of sand
(i) M -35 Grade and 60 mm thickness (a) White sqm 506.66

M-324
(b) Red sqm 515.69
M-324 (C) Yellow sqm 531.88
(ii) M-40 Grade and 80mm thickness (a) White sqm 581.43
(b) Red sqm 596.64
(C) Yellow sqm 615.88
M-325 Kerb-Stone Block- M30 Grade (Size 375mm x 300mm 150 ) each 79.00
M-326 inclusive
Autoclavedof OH & CPConcrete (AAC) Block
Aerated cum 2457.20
M-327 Bitumen grade VG 40 (30/40) packed Ex Fatuha. MT 44020.00
Core tube (drilling bit) No. 2000.00
Core tube (drilling pipe) No. 2000.00
Core tube (Inner rod) No. 2000.00

(D) Lead Details


Lead (Km.)
Loading &
Unsurfaced unloading
Total
Gravelled Surface Road charges
Road
L1 Lead from Mixing Plant to working site 30 10 20 Included
L2 Lead for Earthwork borrow area to site 1 0 1 Included
Lead for Moorum/ Natural Granular material borrow area
L3 2 1 1 Included
to site
L4 Lead for fly ash from source to site 0 - - Included
L5 Lead for Sand from source to site 50 50 0 Included
L6 Lead for Sand from source to Plant 50 50 0 Included
L7 Lead for Aggregate from Quarry to working site 50 50 0 Included
L8 Lead for Aggregate from Quarry to Plant 50 50 0 Included
L9 Lead for Bitumen from source to Plant 0 0 0 Included
L10 Lead for HT Strands from source to Plant 0 - - Included

(E) Overheads & Contractors profit

Overheads for Road Works 8% 10% 12%


Contractors profit for Road Works 10% 10% 10%
Overheads for Bridge Works 20% 20% 20%
Overheads for Bridge Works (Rehabilitation) 30% 30% 30%
Contractors profit for Bridge Works 10% 10% 10%
Overheads for Road Tunnel Works 25% 25% 25%
Contractors profit for RoadTunnel Works 10% 10% 10%
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
CHAPTER-1
CARRIAGE OF MATERIALS
Loading and unloading of stone boulder / stone aggregates / sand /
kanker / moorum. (Placing tipper at loading point, loading with front
1.01
end loader, dumping, turning for return trip, excluding time for haulage
and return trip)
(i) Tipper-5.5 Cum cum 139.00 142.00
(ii) Tipper-10 Cum cum 128.00 130.00
(iii) Tipper-14 Cum cum 110.00 112.00
(iv) Tipper-18 Cum cum 110.00 112.00
1.02 Loading and Unloading of Boulders by Manual Means cum 455.00 464.00
Loading and Unloading of Cement or Steel by Manual Means and
1.03 tonne 668.00 680.00
stacking.
1.04 Cost of Haulage Excluding Loading and Unloading
(i) Surfaced Road
Tipper-5.5 Cum tonne.km 14.00 14.00
Tipper-10 Cum tonne.km 10.00 10.00
Tipper-14 Cum tonne.km 8.00 8.00
Tipper-18 Cum tonne.km 7.00 7.00
(ii) Unsurfaced Gravelled Road
Tipper-5.5 Cum tonne.km 17.00 17.00
Tipper-10 Cum tonne.km 13.00 13.00
Tipper-14 Cum tonne.km 10.00 10.00
Tipper-18 Cum tonne.km 9.00 9.00
(iii) Katcha Track and Track in river bed / nallah bed and choe bed.
Tipper-5.5 Cum tonne.km 34.00 35.00
Tipper-10 Cum tonne.km 25.00 25.00
Tipper-14 Cum tonne.km 20.00 21.00
Tipper-18 Cum tonne.km 18.00 18.00
(iv) Katcha Track in hilly area.. tonne.km 71.00 72.00
(v) Transit Mixture tonne.km 16.00 16.00
Hand Broken Stone Aggregates 63 mm nominal size (Supply of
quarried stone, hand breaking into coarse aggregate 63 mm nominal
1.05 cum 2,880.00 2,933.00
size (passing 80 mm and retained on 50 mm sieve) and stacking as
directed)
1.06 Crushing of stone aggregates (Nominal size)

Crushing of stone aggregates 40 mm nominal size (Crushing of stone


boulders of 150 mm size in an integrated stone crushing unit of 200
(i) tonnes per hour capacity comprising of primary and secondary cum 2,662.00 2,711.00
crushing units, belt conveyor and vibrating screens to obtain stone
aggregates of 40 mm nominal size.)

Crushing of stone aggregates 20 mm nominal size (Crushing of stone


boulders of 150 mm size in an integrated stone crushing unit of 200
(ii) tonnes per hour capacity comprising of primary and secondary cum 2,898.00 2,951.00
crushing units, belt conveyor and vibrating screens to obtain stone
aggregates of 20 mm nominal size.)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

Crushing of stone aggregates 10 mm nominal size. (Crushing of stone


boulders of 150 mm size in an integrated stone crushing unit of 250
(iii) tonnes per hour capacity comprising of primary and secondary cum 2,480.00 2,526.00
crushing units, belt conveyor and vibrating screens to obtain stone
aggregates of different nominal size

Crushing of stone aggregates Dust (Crushing of stone boulders of


150 mm size in an integrated stone crushing unit of 200 tonnes per
(iv) cum 610.00 622.00
hour capacity comprising of primary and secondary crushing units,
belt conveyor and vibrating screens to obtain stone aggregates of .)

Crushing of stone boulders of 150 mm size in an integrated stone


crushing unit of 250 tonnes per hour capacity comprising of primary
1.07 cum 1,689.00 1,720.00
and secondary crushing units, belt conveyor and vibrating screens to
obtain crusher run (all in aggregate) for GSB.

CHAPTER-2
SITE CLEARANCE
Cutting of trees, excluding removal of stumps and roots of trees
(Cutting of trees, trunks and branches excluding removal of stumps
2.01 (A)
and roots of trees and stacking of serviceable material with all lifts and
up to a lead of 1000 mtrs )
(i) Girth from 300 mm to 600 mm each 523.00 548.00
(ii) Girth from 600 mm to 900 mm each 750.00 796.00
(iii) Girth from 900 mm to 1800 mm each 1,458.00 1,517.00
(iv) Girth above 1800 mm each 2,859.00 3,008.00
Cutting of Trees, including Cutting of Trunks, Branches and Removal
(Removal of stumps, roots, stacking of serviceable material with all
2.01 (B)
lifts and up to a lead of 1000 metres and earth filling in the
depression/pit.)
(i) Girth from 300 mm to 600 mm each 586.00 605.00
(ii) Girth from 600 mm to 900 mm each 784.00 807.00
(iii) Girth from 900 mm to 1800 mm each 942.00 968.00
(iv) Girth above 1800 mm each 1,170.00 1,210.00
2.02 Clearing Grass and Removal of Rubbish hectare 31,850.00 32,440.00
Clearing and Grubbing Road Land .(Clearing and grubbing road land
including uprooting rank vegetation, grass, bushes, shrubs, saplings
and trees girth up to 300 mm, removal of stumps of trees cut earlier
2.03 and disposal of unserviceable materials and stacking of serviceable
material to be used or auctioned up to a lead of 1000 metres including
removal and disposal of top organic soil not exceeding 150 mm in
thickness.)
(i) By Manual Means:-
A In area of light jungle hectare 368,018.00 374,833.00
B In area of thorny jungle hectare 399,868.00 407,273.00
(ii) By Mechanical Meansby by Dozer
A In area of light jungle hectare 169,012.00 173,678.00
B In area of thorny jungle hectare 180,656.00 185,515.00
(iii) By Mechanical Means using by motor Grader
A In area of light jungle hectare 150,498.00 158,032.00
B In area of thorny jungle hectare 157,672.00 166,120.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

Dismantling of Structures (Dismantling of existing structures like


culverts, bridges, retaining walls and other structure comprising of
masonry, cement concrete, wood work, steel work, including T&P and
2.04
scaffolding wherever necessary, sorting the dismantled material,
disposal of unserviceable material and stacking the serviceable
material with all lifts and lead of 1000 metres)

(i) Lime /Cement Concrete


I By Manual Means
A Lime Concrete, cement concrete grade M-10 and below cum 1,043.00 1,062.00
B Cement Concrete Grade M-15 & M-20 cum 1,170.00 1,192.00
C Prestressed / Reinforced cement concrete grade M-20 & above cum 2,409.00 2,454.00
II By Mechanical Means for items No. 2.04( b) & ( c)
A Cement Concrete Grade M-15 & M-20 cum 986.00 1,005.00
B Prestressed / Reinforced cement concrete grade M-20 & above cum 1,356.00 1,382.00
(ii)Dismantling Brick / Tile work
A In lime mortar cum 713.00 726.00
B In cement mortar cum 841.00 856.00
C In mud mortar cum 662.00 674.00
D Dry brick pitching or brick soling cum 637.00 648.00
(iii) Dismantling Stone Masonry
A Rubble stone masonry in lime mortar cum 764.00 778.00
B Rubble stone masonry in cement mortar. cum 841.00 856.00
C Rubble Stone Masonry in mud mortar. cum 713.00 726.00
D Dry rubble masonry cum 688.00 700.00
E Dismantling stone pitching/ dry stone spalls. cum 662.00 674.00
Dismantling boulders laid in wire crates including opening of crates
F cum 713.00 726.00
and stacking dismantled materials.
II By Mechanical Means for items No. 2.04 (iii)
Dismantling Brick / Tile work/ rubble masonary/ pitching/ etc by
A cum 213.00 225.00
mechanical means
Wood work wrought framed and fixed in frames of trusses upto a
(iv) cum 1,330.00 1,355.00
height of 5 m above plinth level
Steel work in all types of sections upto a height of 5 m above plinth
(v)
level excluding cutting of rivet.
A Including dismembering tonne 2,763.00 2,815.00
B Excluding dismembering. tonne 2,008.00 2,046.00
C Extra over item No( V ) A and( V ) B for cutting rivets. tonne 19.00 19.00
(vi) Scraping of bricks dismantled from brick work including stacking.
1000
A In lime/Cement mortar 2.00 2.00
numbers
1000
B In mud mortar 1.00 1.00
numbers
(vii) Scraping of Stone from dismantled stone masonry
A In cement and lime mortar cum 892.00 908.00
B In Mud mortar cum 191.00 195.00
(viii) Scarping plaster in lime or cement mortar from brick/ stone masonry sqm 32.00 33.00

Removing all type of hume pipes and stacking within a lead of 1000
(ix)
metres including earthwork and dismantling of masonry works.
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
A Up to 600 mm dia metre 1,186.00 1,335.00
B Above 600 mm to 900 mm dia metre 1,447.00 1,573.00
C Above 900 mm metre 1,707.00 1,811.00

Dismantling of Flexible Pavements (Dismantling of flexible pavements


2.05 and disposal of dismantled materials up to a lead of 1000 metres,
stacking serviceable and unserviceable materials separately)
I By Manual Means
A Bituminous courses cum 1,328.00 1,352.00
B Granular courses cum 1,009.00 1,028.00
II By Mechanical Means
A Bituminous course cum 514.00 537.00
B Granular courses cum 65.00 71.00
Dismantling of Cement Concrete Pavement (Dismantling of cement
concrete pavement by mechanical means using pneumatic tools,
breaking to pieces not exceeding 0.02 cum in volume and stock piling
2.06 cum 934.00 991.00
at designated locations and disposal of dismantled materials up to a
lead of 1000 metres, stacking serviceable and unserviceable
materials separately)
Dismantling Guard Rails (Dismantling guard rails by manual means
and disposal of dismantled material with all lifts and up to a lead of
2.07 metre 109.00 111.00
1000 metres, stacking serviceable materials and unserviceable
materials separately.)
Dismantling Kerb Stone (Dismantling kerb stone by manual means
2.08 and disposal of dismantled material with all lifts and up to a lead of metre 41.00 41.00
1000 metre)
Dismantling Kerb Stone channel (Dismantling kerb stone channel by
2.09 manual means and disposal of dismantled material with all lifts and up metre 52.00 53.00
to a lead of 1000 metre)
Dismantling Kilometre Stone (Dismantling of kilometre stone including
2.10 cutting of earth, foundation and disposal of dismantled material with
all lifts and lead upto 1000 m and back filling of pit.)
A 5th KM stone each 812.00 827.00
B Ordinary KM Stone each 541.00 551.00
C Hectometre Stone each 108.00 110.00
Dismantling of Fencing (Dismantling of barbed wire fencing/ wire
mesh fencing including posts, foundation concrete, back filling of pit
2.11 by manual means including disposal of dismantled material with all metre 96.00 98.00
lifts and up to a lead of 1000 metres, stacking serviceable material
and unserviceable material separately. )

Dismantling of CI Water Pipe Line (Dismantling of CI water pipe line


600 mm dia including disposal with all lifts and lead upto 1000 metres
2.12 metre 265.00 270.00
and stacking of serviceable material and unserviceable material
separately under supervision of concerned department)

Removal of Cement Concrete Pipe of Sewer Gutter (Removal of


cement concrete pipe of sewer gutter 1500 mm dia under the
supervision of concerned department including disposal with all lifts
2.13 metre 405.00 413.00
and up to a lead of 1000 metres and stacking of serviceable and
unserviceable material separately but excluding earth excavation and
dismantling of masonry works.)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

Removal of Telephone / Electric Poles and Lines (Removal of


telephone / Electric poles including excavation and dismantling of
2.14 foundation concrete and lines under the supervision of concerned each 384.00 391.00
department, disposal with all lifts and up to a lead of 1000 metres and
stacking the serviceable and unserviceable material separately)

CHAPTER-3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Excavation in Soil by Manual Means. (Excavation for roadway in soil
3.01 using manual means including loading in truck for carrying of cut earth cum 397.00 405.00
to embankment site with all lifts and lead upto1000 metres.)

Excavation in ordinary rock by manual means (Excavation in ordinary


rock using manual means including loading in a truck and carrying of
3.02 cum 530.00 540.00
excavated material to embankment site with in all lifts and leads upto
1000 metres )
Excavation in Soil with Dozer with lead upto 1000 metres
(EExcavation for road way in soil by mechanical means including
cutting and transporting the earth to site of embankment/dumping
3.03 cum 182.00 193.00
area with lead upto 1000 metres, including trimming bottom and side
slopes in accordance with requirements of lines, grades and cross
sections.)
Excavation in Ordinary Rock with Dozer with lead upto 1000 metres
(Excavation for roadway in ordinary rock by deploying a dozer,
including cutting and transporting the earth to site of
3.04 cum 274.00 294.00
embankment/dumping area with lead upto 1000 metres, trimming
bottom and side slopes in accordance with the requirements of lines,
grades and cross sections.)
Excavation in Hard Rock (requiring blasting) with disposal upto 1000
metres (Excavation for roadway in hard rock (requiring blasting) by
drilling, blasting and breaking, trimming of bottom and side slopes in
3.05 cum 717.00 748.00
accordance with requirements of lines, grades and cross sections,
loading and disposal of cut road with in all lifts and leads upto 1000
metres )

Excavation in Soil using Hydraulic Excavator and Tippers with


disposal upto 1000 metres. (Excavation for roadwork in soil with
hydraulic excavator including cutting and loading in tippers, trimming
3.06 cum 97.00 112.00
bottom and side slopes, in accordance with requirements of lines,
grades and cross sections, and transporting to the embankment
location within all lifts and lead upto 1000m)

Excavation in Ordinary Rock using Hydraulic Excavator and Tippers


with disposal upto 1000 metres. (Excavation for roadwork in soil with
hydraulic excavator including cutting and loading in tippers, trimming
3.07 cum 659.00 706.00
bottom and side slopes, in accordance with requirements of lines,
grades and cross sections, and transporting to the embankment
location within all lifts and lead upto 1000m.)

Excavation in Hard Rock (blasting prohibited) (Excavation for


roadwork in Hard Rock (blasting prohibited) with hydraulic excavator
including cutting and loading in tippers, trimming bottom and side
3.08
slopes, in accordance with requirements of lines, grades and cross
sections, and transporting to the embankment location within all lifts
and lead upto 1000 m.)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
A Mechanised cum 705.00 768.00
B Manual Method cum 2,016.00 2,053.00
Excavation in Hard Rock (controlled blasting) with disposal upto
1000 metres (EExcavation for roadway in hard rock (requiring
blasting) by drilling, blasting and breaking, trimming of bottom and
3.09 cum 753.00 768.00
side slopes in accordance with requirements of lines, grades and
cross sections, loading and disposal of cut road with in all lifts and
leads upto 1000 metres )

Excavation in Marshy Soil (Excavation for roadwork in Marshy Soil


with hydraulic excavator including cutting and loading in tippers,
3.10 trimming bottom and side slopes, in accordance with requirements of cum 209.00 220.00
lines, grades and cross sections, and transporting to the embankment
location within all lifts and lead upto 1000 m.)

Removal of Unserviceable Soil with Disposal upto 1000 metres


(Removal of unserviceable soil including excavation, loading and
3.11 cum 99.00 104.00
disposal upto 1000 metres lead but excluding replacement by suitable
soil which shall be paid separately as per clause 305..)

Pre-splitting of Rock Excavation Slopes (Carrying out excavation in


hard rock to achieve a specified slope of the rock face by controlled
use of explosives and blasting accessories in properly aligned and
3.12 sqm 207.00 211.00
spaced drill holes, collection of the excavated rock by a dozer, loading
in tipper by a front end loader and disposing of the material with all
lifts and lead upto 1000 m, all as specified in clause No. 303)

Excavation for Structures (Earth work in excavation of foundation of


structures as per drawing and technical specification, including setting
out, construction of shoring and bracing, removal of stumps and other
3.13
deleterious matter, dressing of sides and bottom, backfilling the
excavation earth to the extent required and utilising the remaining
earth locally for road work.)

(i) Ordinary soil


A Manual Means (Depth upto 3 m) cum 510.00 519.00
B Mechanical Means (Depth upto 3 m) cum 96.00 101.00
(ii) Ordinary rock (not requiring blasting)
A Manual Means (Depth upto 3 m) cum 637.00 649.00
B Mechanical Means cum 688.00 738.00
(iii) Hard rock ( requiring blasting )
A Mechanical Means cum 390.00 406.00
(iv) Hard rock ( blasting prohibited )
A Mechanical Means cum 1,240.00 1,339.00
(v) Marshy soil
A Manual means ( upto 3 m depth) cum 1,364.00 1,389.00
B Mechanical Means cum 474.00 494.00
Scarifying the existing granular road surface to a depth of 50 mm and
3.14 disposal of scarified material within all lifts and leads upto 1000
metres.
Scarifying Existing Granular Surface to a Depth of 50 mm by Manual
(i) sqm 69.00 70.00
Means
(ii) By Mechanical Means using Hydraulic excavator sqm 6.00 7.00
(iii) By Mechanical Means using Motor Grader sqm 8.00 8.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Scarifying the existing bituminous surface to a depth of 50 mm and
3.15 disposal of scarified material within all lifts and leads upto 1000
metres.
(i) By Mechanical Means using Hydraulic excavator sqm 7.00 8.00
(ii) By Mechanical Means using Motor Grader sqm 8.00 9.00
Embankment Construction with Material Obtained from Borrow Pits
(Construction of embankment with approved material obtained from
3.16 borrow pits with all lifts and leads, transporting to site, spreading, cum 236.00 254.00
grading to required slope and compacting to meet requirement of
table 300-2)
Construction of Embankment with Material Deposited from Roadway
Cutting (Construction of embankment with approved materials
3.17 deposited at site from roadway cutting and excavation from drain and cum 75.00 85.00
foundation of other structures graded and compacted to meet
requirement of table 300-2)
Rate per Cum after adding royalty Rs 33.00/ cum cum 108.00 118.00
Construction of Subgrade and Earthen Shoulders (Construction of
subgrade and earthen shoulders with approved material obtained
3.18 from borrow pits with all lifts & leads, transporting to site, spreading, cum 240.00 259.00
grading to required slope and compacted to meet requirement of table
No. 300-2)

Construction of Subgrade and Earthen Shoulders with Material


Deposited from Roadway Cutting(Construction of embankment with
3.19 approved materials deposited at site from roadway cutting and cum 88.00 101.00
excavation from drain and foundation of other structures graded and
compacted to meet requirement of table 300-2.)

Rate per Cum after adding royalty Rs 33.00/ cum cum 121.00 134.00
3.20 Compacting Original Ground
Compacting original ground supporting subgrade (Loosening of the
ground upto a level of500 mm below the subgrade level, watered,
Case-I cum 123.00 139.00
graded and compacted in layers to meet requirement of table 300-2
for subgrade construction.)
Case-II :Compacting original ground supporting embankment cum 135.00 152.00
Stripping and Storing Top Soil (Stripping, storing of top soil by road
side at 15 m internal and re-application on embankment slopes, cut
3.21 cum 120.00 130.00
slopes and other areas in localities where the available embankment
material is not conducive to plant growth)

Stripping, storing and re-laying top soil from borrow areas in


agriculture fields. (Stripping of top soil from borrow areas located in
3.22 agriculture fields, storing at a suitable place, spreading and re-laying cum 218.00 230.00
after taking the borrow earth to maintain fertility of the agricultural
field, finishing it to the required levels and satisfaction of the farmer.)

Turfing with Sods (Furnishing and laying of the live sods of perennial
turf forming grass on embankment slope, verges or other locations
3.23 sqm 314.00 368.00
shown on the drawing or as directed by the engineer including
preparation of ground, fetching of rods and watering)

Seeding and Mulching (Preparation of seed bed on previously laid top


soil, furnishing and placing of seeds, fertilizer, mulching material,
3.24 applying bituminous emulsion at the rate of0.23 litres per sqm and sqm 936.00 1,098.00
laying and fixing jute netting, including watering for 3 months all as
per clause 308)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Surface Drains in Soil (Construction of unlined surface drains of
average cross sectional area 0.40 sqm in soil to specified lines,
3.25 grades, levels and dimensions to the requirement of clause 301 and
309. Excavated material to be used in embankment within a lead of50
metres (average lead 25 metres))
A Mechanical means metre 101.00 102.00
B Manual Means metre 311.00 316.00
Surface Drains in Ordinary Rock (Construction of unlined surface
drain of average cross sectional area 0.4 sqm in ordinary rock to
3.26 specified lines, grades, levels and dimensions as per approved design
and to the requirement of clause 301 to 309. Excavated material to be
used in embankment at site.)
A Mechanical Means metre 128.00 131.00
B Manual Means metre 424.00 432.00
Surface Drains in Hard Rock (Rate per metre may be worked out
3.27 metre
based on quantity of hard rock as per design.)

Sub Surface Drains with Perforated Pipe (Construction of subsurface


drain with perforated pipe of 100 mm internal diameter of metal/
asbestos cement/ cement concrete/PVC, closely jointed, perforations
3.28 ranging from 3 mm to 6 mm depending upon size of material 682.00 695.00
surrounding the pipe, with 150 mm bedding below the pipe and 300
mm cushion above the pipe, cross section of excavation 450 x 550
mm. Excavated material to be utilised in roadway at site )

Aggregate Sub- Surface Drains (Construction of aggregate sub


3.29 surface drain 300 mm x 450 mm with aggregates conforming to table metre 290.00 296.00
300-4, excavated material to be utilised in roadway )

Underground Drain at Edge of Pavement (Construction of an


underground drain 1 m x 1 m (inside dimensions) lined with RCC-20
3.30 metre 5,437.00 5,437.00
cm thick and covered with RCC slab10 cm in thickness on urban
roads)

Preparation and Surface Treatment of formation. (Preparation and


surface treatment of formation by removing mud and slurry, watering
3.31 to the extent needed to maintain the desired moisture content, sqm 6.00 6.00
trimming to the required line, grade, profile and rolling with 8-10 tonne
smooth wheeled roller, complete as per clause 310.)

Excavation in Hilly Areas in Hard Rock Requiring Blasting (Excavation


in hilly areas in hard rock requiring blasting, by mechanical means
3.32 cum 147.00 160.00
including trimming of slopes and disposal of cut material with all lifts
and lead upto 1000 metres.)

Work in Urban Roads (The cost of earth work in urban roads


3.33
inhabited area will be comparatively higher due to following reasons:)

Embankment Construction with Fly ash/Pond ash available from coal


or lignite burning Thermal Plants as waste material. (Construction of
embankment with fly ash conforming to table 1 of IRC: SP: 58
3.34 cum 125.00 141.00
obtained from coal or lignite burning thermal power stations as waste
material, spread and compacted in layer of 200mm thickness each at
OMC, all as specified in IRC: SP: 58 and as per approved plans.)

CHAPTER-4
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS

4.01 Granular Sub-base with Close Graded Material (Table:- 400-1)

Plant Mix Method (Construction of granular sub-base by providing


close graded Material, mixing in a mechanical mix plant at OMC,
carriage of mixed Material to work site, spreading in uniform layers
A
with motor grader on prepared surface and compacting with vibratory
power roller to achieve the desired density, complete as per clause
401 )
(i) for grading- I Material cum 3,767.00 3,900.00
(ii) for grading- II Material cum 3,767.00 3,900.00
(iii) for grading-III Material cum 3,767.00 3,900.00
(iv) for grading-IV Material cum 3,767.00 3,900.00
(v) for grading-V Material cum 3,767.00 3,900.00
(vi) for grading-VI Material cum 3,767.00 3,900.00

By Mix in Place Method (Construction of granular sub-base by


providing close graded material, spreading in uniform layers with
B motor grader on prepared surface, mixing by mix in place method with
rotavator at OMC, and compacting with vibratory roller to achieve the
desired density, complete as per clause 401)

(i) for grading- I Material cum 3,268.00 3,338.00


(ii) for grading- II Material cum 3,268.00 3,338.00
(iii) for grading-III Material cum 3,267.50 3,338.20
(iv) for grading-IV Material cum 3,268.00 3,338.00
(v) for grading-V Material cum 3,268.00 3,338.00
(vi) for grading-VI Material cum 3,268.00 3,338.00

Using Crusher Run Method (Construction of granular sub-base by


providing close graded material, spreading in uniform layers with
C motor grader on prepared surface, mixing by mix in place method with
rotavator at OMC, and compacting with vibratory roller to achieve the
desired density, complete as per clause 401)

(i) for grading- I Material cum 3,687.00 3,841.00


(ii) for grading- II Material cum 3,687.00 3,841.00
(iii) for grading-III Material cum 3,687.00 3,841.00
(iv) for grading-IV Material cum 3,687.00 3,841.00
(v) for grading-V Material cum 3,687.00 3,841.00
(vi) for grading-VI Material cum 3,687.00 3,755.00
4.02 Lime Stabilisation for Improving Subgrade
A By Manual Means

Laying and spreading available soil in the subgrade on a prepared


surface, pulverising, mixing the spread soil in place with rotavator with
3 % slaked lime having minimum content of 70% of CaO, grading with 743.00 550.00 596.00
motor grader and compacting with the road roller at OMC to the
desired density to form a layer of improved sub grade)

B By Mechanical Means
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

Laying and spreading available soil in the sub-grade on a prepared


surface, pulverising, mixing the spread soil in place with Soil Stabilizer
& Binder Spreader with 2 per cent slaked lime using Binder spreader
(i) cum 896.00 948.00
Machine, having minimum content of 70 per cent of CaO, grading
with motor grader and compacting with the road roller at OMC to the
desired density to form a layer of improved sub grade

Laying and spreading available soil in the sub-grade on a prepared


surface, pulverising, mixing the spread soil in place with Soil Stabilizer
with 2 per cent slaked lime mannualy spreaded having minimum
(ii) cum 823.00 874.00
content of 70 per cent of CaO, grading with motor grader and
compacting with the road roller at OMC to the desired density to form
a layer of improved sub grade

4.03 Cement Stabilisation for Improving Subgrade


A By Manual Means
Laying and spreading available soil in the sub-grade on a prepared
surface, pulverising, mixing the spread soil in place with Soil Stabilizer
& Binder Spreader with 2 per cent cement using Binder spreader
cum 599.00 646.00
Machine, grading with motor grader and compacting with the road
roller at OMC to the desired density to form a layer of improved sub
grade
B By Mechanical Means
Laying and spreading available soil in the sub-grade on a prepared
surface, pulverising, mixing the spread soil in place with Soil Stabilizer
& Binder Spreader with 2 per cent cement using Binder spreader
(i) cum 945.00 998.00
Machine, grading with motor grader and compacting with the road
roller at OMC to the desired density to form a layer of improved sub
grade

Laying and spreading available soil in the sub-grade on a prepared


surface, pulverising, mixing the spread soil in place with Soil Stabilizer
(ii) with 2 per cent cement mannualy spreaded, grading with motor cum 873.00 924.00
grader and compacting with the road roller at OMC to the desired
density to form a layer of improved sub grade

4.04 Cement Stabilisation for Improving Embankment


A By Manual Means

Laying and spreading available soil in the emabankment on a


prepared surface, pulverising, mixing the spread soil in place with
rotavator with 3 % slaked lime having minimum content of 70% of cum 505.00 546.00
CaO, grading with motor grader and compacting with the road roller at
OMC to the desired density to form a layer of improved sub grade)

B By Mechanical Means

Laying and spreading available soil in the emabankment on a


prepared surface, pulverising, mixing the spread soil in place with Soil
Stabilizer & Binder Spreader with 2 per cent slaked lime using
(i) cum 852.00 899.00
Binder spreader Machine, having minimum content of 70 per cent of
CaO, grading with motor grader and compacting with the road roller at
OMC to the desired density to form a layer of improved sub grade
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

Laying and spreading available soil in the emabankment n a prepared


surface, pulverising, mixing the spread soil in place with Soil Stabilizer
with 2 per cent slaked lime mannualy spreaded having minimum
(ii) cum 779.00 825.00
content of 70 per cent of CaO, grading with motor grader and
compacting with the road roller at OMC to the desired density to form
a layer of improved sub grade

Laying and spreading available soil in the emabankment n a prepared


surface, pulverising, mixing the spread soil in place with Soil Stabilizer
& Binder Spreader with 2 per cent cement using Binder spreader
(iii) cum 894.00 942.00
Machine, grading with motor grader and compacting with the road
roller at OMC to the desired density to form a layer of improved sub
grade

Laying and spreading available soil in the emabankment on a


prepared surface, pulverising, mixing the spread soil in place with Soil
(iv) Stabilizer with 2 per cent cement mannualy spreaded, grading with cum 821.00 868.00
motor grader and compacting with the road roller at OMC to the
desired density to form a layer of improved sub grade

Lime Treated Soil for Sub- Base (Providing, laying and spreading soil
on a prepared sub grade, pulverising, mixing the spread soil in place
with rotavator with 3 % slaked lime with minimum content of 70% of
4.05 cum 679.00 718.00
CaO, grading with motor grader and compacting with the road roller at
OMC to achieve at least 98%of the max dry density to form a layer of
sub base.)
Cement Treated Soil Sub Base/ Base (Providing, laying and
spreading soil on a prepared sub grade, pulverising, adding the
designed quantity of cement to the spread soil, mixing in place with
4.06 cum 856.00 898.00
rotavator, grading with the motor grader and compacting with the road
roller at OMC to achieve the desired unconfined compressive strength
and to form a layer of sub-base/base.)

Cement Treated Crushed Rock or combination as per clause 403 and


table 400.4 in Sub base/ Base (Providing, laying and spreading
Material on a prepared sub grade, adding the designed quantity of
4.07 cement to the spread Material, mixing in place with rotavator, grading
with the motor grader and compacting with the road roller at OMC to
achieve the desired unconfined compressive strength and to form a
layer of sub-base/base.)

(i) For Sub-Base course cum 3,493.00 3,725.00


(ii) For Base course cum 3,508.00 3,594.00

Cement Treated Crushed Stone Sub base (Construction of granular


sub-base by providing graded Material, mixing with cement in a
mechanical mix plant at OMC, carriage of mixed Material to work site,
4.08
spreading in uniform layers with Mechanical Paver on prepared
surface and compacting with vibratory power roller to achieve the
desired density, complete as per clause 401 )

A Plant Mix Method (Using by Mechanical Paver)


(i)
Cement Treated Crushed Stone Sub base (Grading-III Material) cum 4,167.00 4,321.00
(ii)
Cement Treated Crushed Stone Sub base (Grading-IV Material) cum 4,167.00 4,321.00
B By Mix in Place Method ((Using by Soil Stabilizer)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
(i)
Cement Treated Crushed Stone Sub base (Grading-III Material) cum 4,039.00 4,141.00
(ii)
Cement Treated Crushed Stone Sub base (Grading-IV Material) cum 4,039.00 4,141.00

Making 50 mm x 50 mm Furrows (Making 50 mm x 50 mm furrows,


25mm deep, 450 to the center line of the road and at one metre
4.09 interval in the existing thin bituminous wearing coarse including
sweeping and disposal of excavated material within 1000 metres
lead)
(i) 25mm deep furrow cutting sqm 8.00 8.00
(ii) 50mm deep furrow cutting sqm 16.00 17.00
Inverted Choke (Construction of inverted choke by providing, laying,
spreading and compacting screening B type/ coarse sand of specified
4.10 cum 3,040.00 3,117.00
grade in uniform layer on a prepared surface with motor grader and
compacting with power roller etc)
Water Bound Macadam (Providing, laying, spreading and compacting
stone aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand packing,
4.11 rolling with vibratory roller 8-10 tonnes in stages to proper grade and
camber, applying and brooming requisite type of screening/ binding
Materials to fill up the interstices of coarse aggregate, watering and
compacting to the required density.)
A By Manual Means
Grading- I (Using Screening Crushable type such as Moorum or
(i)
Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 3,936.00 4,039.00
(b) Using Screening Type-A (13.2mm Agg.) cum 3,842.00 3,944.00
(c) Using Screening Type-B (11.2mm Agg.) cum 4,022.00 4,124.00
Grading- II (Using Screening Crushable type such as Moorum or
(ii)
Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 3,936.00 4,039.00
(b) Using Screening Type-B (11.2mm Agg.) cum 4,022.00 4,127.00
B By Mechanical Means:
Grading- I (Using Screening Crushable type such as Moorum or
(i)
Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 3,668.00 3,764.00
(b) Using Screening Type-A (13.2mm Agg.) cum 3,575.00 3,669.00
Grading- II (Using Screening Crushable type such as Moorum or
(ii)
Gravel)
(a) Using Screening Crushable type such as Moorum or Gravel cum 3,668.00 3,764.00
(b) Using Screening Type-B (11.2mm Agg.) cum 3,754.00 3,849.00

Crushed Cement Concrete Sub-base / Base (Breaking and crushing


of material obtained by breaking damaged cement concrete slabs to
size range not exceeding 75 mm as specified in table 400.9
4.12 transporting the aggregates obtained from breaking of cement cum 856.00 954.00
concrete slabs at a lead of L km., laying and compacting the same as
sub base/ base course, constructed as WBM to clause 404 except the
use of screening or binding Material.)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Penetration Coat Over Top Layer of Crushed Cement Concrete Base
(Spraying of bitumen over cleaned dry surface of crushed cement
concrete base at the rate of 25 kg per 10 sqm by a bitumen pressure
4.13 sqm 40.00 41.00
distributor, spreading of key aggregates at the rate of 0.13 cum per 10
sqm by a mechanical gritter and rolling the surface as per clause
506.3.8)
4.14 Wet Mix Macadam laying
Wet Mix Macadam laying Using Mechanical Paver (Providing, laying,
spreading and compacting graded stone aggregate to wet mix
macadam specification including premixing the Material with water at
A OMC in mechanical mix plant carriage of mixed Material by tipper to cum 3,425.00 3,497.00
site, laying in uniform layers with paver in sub- base / base course on
well prepared surface and compacting with vibratory roller to achieve
the desired density.)
Wet Mix Macadam laying using by Grader (Providing, laying,
spreading and compacting graded stone aggregate to wet mix
macadam specification including premixing the Material with water at
B OMC in mechanical mix plant carriage of mixed Material by tipper to cum 3,418.00 3,480.00
site, laying in uniform layers with paver in sub- base / base course on
well prepared surface and compacting with vibratory roller to achieve
the desired density.)
Cement Treated Crushed Stone Base (Plant Mix Method) (Providing,
laying, spreading and compacting graded stone aggregate to wet mix
macadam specification including premixing the Material with water at
4.15 OMC in mechanical mix plant carriage of mixed Material by tipper to cum 4,134.00 4,233.00
site, laying in uniform layers with paver in sub- base / base course on
well prepared surface and compacting with vibratory roller to achieve
the desired density.)
Construction of Median and Island with Soil Taken from Roadway
Cutting (Construction of Median and Island above road level with
4.16 approved material deposited at site from roadway cutting and cum 433.00 447.00
excavation for drain and foundation of other structures, spread,
graded and compacted as per clause 407)
Construction of Median and Island with Soil Taken from Borrow Areas
(Construction of median and Island above road level with approved
4.17 cum 305.00 320.00
material brought from borrow pits, spread, sloped and compacted as
per clause 408)
4.18 Construction of Shoulders
A Earthen Shoulders
B Hard Shoulders
C Paved shoulders

Footpaths and Separators (Construction of footpath/separator by


providing a 150 mm compacted granular sub base as per clause 401
4.19 and 25 mm thick cement concrete grade M15, over laid with precast sqm 1,183.00 1,208.00
concrete tiles in cement mortar 1:3 including provision of all drainage
arrangements but excluding kerb channel..)

Crusher Run Macadam Base (Providing crushed stone aggregate,


depositing on a prepared surface by hauling vehicles, spreading and
4.20
mixing with a motor grader, watering and compacting with a vibratory
roller to clause 417 to form a layer of sub-base/Base)

A By Mix in Place Method


(i) For 53 mm maximum size cum 3,268.00 3,334.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
(ii) For 45 mm maximum size cum 3,268.00 3,334.00
B By Mixing Plant :
(i) For 53 mm maximum size cum 3,250.00 3,316.00
(ii) For 45 mm maximum size cum 3,250.00 3,316.00

Lime, Fly ash stabalised soil sub-base (Construction of Sub-base


using lime - fly ash admixture with granular soil, free from organic
matter/ deleterious material or clayey silts and low plasticity clays
having PI between 5 and 20 and liquid limit less than 25 and
commercial dry lime, slaked at site or pre-slaked with CaO content not
4.21 cum 868.00 944.00
less than 50%, fly ash to conform to gradation as per clause 4.3 of
IRC: 88, lime + fly ash content ranging between 10 to 30%, the
minimum un-confined compressive strength and CBR value after 28
days curing and 4 days soaking to be 7.5kg/sq, cm and 25%
respectively, all as specified in IRC: 88 )

Granular crack relief layer (Granular crack relief layer using


Mechanical paver (Providing,laying, spreading and compacting
graded stone aggregate to granular crack relief layer as per IRC SP -
4.22 37 including premixing the material with water at OMC in mechanical cum
mix plant carriage of mixed material by tipper to site, laying in uniform
layers with paver over base course on well prepared surface and
compacting with vibratory roller to achieve the desired density.))

CHAPTER-5
BASES AND SURFACE COURSES (BITUMINOUS)
5.01 Prime coat
A Prime Coat over WMM/WBM
Providing and applying primer coat with bitumen emulsion on
prepared surface of granular Base including clearing of road surface
(i) sqm 42.00 42.00
and spraying primer at the rate of 0.60 kg/sqm using mechanical
means
Providing and applying primer coat with cutback MC 30 bitumen
emulsion on prepared surface of granular Base including clearing of
(ii) sqm 35.00 36.00
road surface and spraying primer at the rate of 0.60 to 0.90 kg/sqm
using mechanical means.

B Prime Coat over Stabilized soil bases/Crusher Run Macadam

Providing and applying primer coat with SS1 grade bitumen emulsion
on prepared surface of granular Base including clearing of road
(i) sqm 53.00 54.00
surface and spraying primer at the rate of 0.90 to 1.20 kg/sqm using
mechanical means.
Providing and applying primer coat with cutback MC 70 bitumen
emulsion on prepared surface of granular Base including clearing of
(ii) sqm 52.00 53.00
road surface and spraying primer at the rate of 0.90 to 1.20 kg/sqm
using mechanical means.
5.02 Tack coat on Bituminous surfaces
Tack Coat on Bituminous surfaces (Providing and applying tack coat
with bitumen emulsion using emulsion pressure distributor at the rate
(i) sqm 12.00 12.00
of 0.20 to 0.30 kg per sqm on the prepared bituminous surface
cleaned with mechanical broom.)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

Tack Coat on Granular surfaces treated with primer (Providing and


applying tack coat with bitumen emulsion using emulsion pressure
(ii) distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared sqm 15.00 15.00
bituminous surface cleaned with mechanical broom.)

Tack Coat on Cement concrete pavement (Providing and applying


tack coat with bitumen emulsion using emulsion pressure distributor at
(iii) the rate of 0.30 to 0.35 kg per sqm on the prepared bituminous sqm 18.00 18.00
surface cleaned with mechanical broom.)

5.03 Bituminous Macadam

Bituminous Macadam -I ( 40 mm nominal size ) (Providing and laying


bituminous macadam with higher capacity hot mix plant using crushed
aggregates of specified grading premixed with bituminous binder,
(i) cum 8,243.00 8,474.00
transported to site, laid over a previously prepared surface with paver
finisher to the required grade, level and alignment and rolled as per
clauses 501.6 and 501.7 to achieve the desired compaction)

Bituminous Macadam -II ( 19 mm nominal size ) (Providing and laying


bituminous macadam with higher capacity hot mix plant using crushed
aggregates of specified grading premixed with bituminous binder,
(ii) cum 8,721.00 8,961.00
transported to site, laid over a previously prepared surface with paver
finisher to the required grade, level and alignment and rolled as per
clauses 501.6 and 501.7 to achieve the desired compaction)

5.04 Dense Graded Bituminous Macadam

Dense Graded Bituminous Macadam-I (Providing and laying dense


graded bituminous macadam with higher capacity batch type HMP
using crushed aggregates of specified grading, premixed with
bituminous binder @ 4.0 per cent by weight of total mix and filler,
(i) transporting the hot mix to work site, laying with a hydrostatic paver cum 10,028.00 10,296.00
finisher with sensor control to the required grade, level and alignment,
rolling with smooth wheeled, vibratory and tandem rollers to achieve
the desired compaction as per MoRTH specification clause No. 505
complete in all respects)

Dense Graded Bituminous Macadam-II (Providing and laying dense


graded bituminous macadam with higher capacity batch type HMP
using crushed aggregates of specified grading, premixed with
bituminous binder @ 4.5 per cent by weight of total mix and filler,
(ii) transporting the hot mix to work site, laying with a hydrostatic paver cum 10,648.00 10,928.00
finisher with sensor control to the required grade, level and alignment,
rolling with smooth wheeled, vibratory and tandem rollers to achieve
the desired compaction as per MoRTH specification clause No. 505
complete in all respects.)

5.05 Bituminous Concrete


Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

Bituminous Concrete Grading -I (Providing and laying bituminous


concrete with higher capacity batch type hot mix plant using crushed
aggregates of specified grading, premixed with bituminous binder @
5.2 per cent of mix and filler, transporting the hot mix to work site,
(i) cum 11,830.00 12,143.00
laying with a hydrostatic paver finisher with sensor control to the
required grade, level and alignment, rolling with smooth wheeled,
vibratory and tandem rollers to achieve the desired compaction as per
MORTH specification clause No. 507 complete in all respects)

Bituminous Concrete Grading -II (Providing and laying bituminous


concrete with higher capacity batch type hot mix plant using crushed
aggregates of specified grading, premixed with bituminous binder @
5.4 per cent of mix and filler, transporting the hot mix to work site,
(ii) cum 12,138.00 12,456.00
laying with a hydrostatic paver finisher with sensor control to the
required grade, level and alignment, rolling with smooth wheeled,
vibratory and tandem rollers to achieve the desired compaction as per
MORTH specification clause No. 507 complete in all respects)

Surface Dressing (Providing and laying surface dressing as wearing


course in single coat using crushed stone aggregates of specified size
5.06
on a layer of bituminous binder laid on prepared surface and rolling
with 8-10 tonne smooth wheeled steel roller)
Case -I :-19 mm nominal chipping size sqm 116.00 118.00
Case - II 13 mm nominal size chipping sqm 90.00 92.00

Open - Graded Premix Surfacing Providing, laying and rolling of open


- graded premix surfacing of 20 mm thickness composed of 13.2 mm
to 5.6 mm aggregates using Viscocity grade bitumen to required line,
5.07 grade and level to serve as wearing course on a previously prepared sqm 173.00 177.00
base, including mixing in a suitable hot mix plant of appropriate
capacity not less than 200 tonnes/hour, laying and rolling with a
smooth wheeled roller, finished to required level and grades.

Close Graded Premix Surfacing/Mixed Seal Surfacing (Mechanical


means using HMP of appropriate capacity not less than 75
tonnes/hour. Providing, laying and rolling of close-graded premix
surfacing material of 20 mm thickness composed of 11.2 mm to 0.09
5.08 mm (Type-a) or 13.2 mm to 0.09 mm (Type-b) aggregates using
penetration grade bitumen to the required line, grade and level to
serve as wearing course on a previously prepared base, including
mixing in a suitable plant, laying and rolling with a Smooth wheeled
roller 8-10 tonne capacity, and finishing to required level and grade. )

(i) Type A sqm 213.00 219.00


(ii) Type B sqm 196.00 202.00
Seal Coat (Providing and laying seal coat sealing the voids in a
5.09 bituminous surface laid to the specified levels, grade and cross fall
using Type A and B seal coats)
(i) Case - I : Type A sqm 86.00 88.00
Case - II : Type B (Providing and laying of premix sand seal coat with
HMP of appropriate capacity not less than 75 tonnes/ hours using
(ii) sqm 58.00 60.00
crushed stone chipping 6.7 mm size and penetration bitumen of
suitable grade.)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

Supply of Stone Aggregates for Pavement Courses (Supply of stone


aggregates from approved sources confirming to the physical
requirement, specified in the respective specified clauses, including
royalties, fees rents, collection, transportation, stacking and testing
and measured in cum as per clause 520 Competitive market rates to
5.10 cum - -
be ascertained. Alternatively, rates for stone crushing given in chapter
1may be adopted, if found economical. In case for supply of
aggregates at site are not available, nearest crusher site may be
ascertained. Loading and un-loading charges and cost of carriage
may be added to these rates to arrive at the cost at site.)

Mastic Asphalt (Providing and laying 25 mm thick mastic asphalt


wearing course with paving grade bitumen meeting the requirements
given in table 500-39, prepared by using mastic cooker and laid to
required level and slope after cleaning the surface, including providing
antiskid surface with bitumen precoated fine-grained hard stone
5.11 sqm 1,625.00 1,655.00
chipping of 13.2 mm nominal size at the rate of 0.005cum per 10 sqm
and at an approximate spacing of 10 cm center to center in both
directions, pressed into surface when the temperature of surfaces not
less than 1000C, protruding 1 mm to 4 mm over mastic surface, all
complete as per clause 516.)

Slurry Seal Providing and laying slurry seal consisting of a mixture of


fine aggregates, portland cement filler, bituminous emulsion and
5.12 water on a road surface including cleaning of surface, mixing of slurry
seal in a suitable mobile plant, laying and compacting to provide even
riding surface)
(i) 2-3 mm thickness sqm 54.00 55.00
(ii) 4-6 mm thickness sqm 87.00 89.00
(iii) 6-8 mm thickness sqm 107.00 109.00

Recycling of Bituminous Pavement with Central Recycling Plant


(Recycling pavement by cold milling of exiting bituminous layers,
planning the surface after cold milling, reclaiming excavated material
to the extent of 30 % of the required quantity, hauling and stock piling
5.13 the reclaimed material near the central recycling plant after carrying
out necessary checks and evaluation, adding fresh material including
rejuvenators as required, mixing in a hot mix plant, transporting and
laying at site and compacting to the required grade, level and
thickness, all as specified in clause 519.)

A (i) Using by bituminous Macadam Grading- I cum 8,880.00 9,306.00


A (ii) Using by bituminous Macadam Grading- II cum 8,344.00 8,763.00
B (i) Using by Dense Graded bituminous Macadam Grading- I cum 9,024.00 9,903.00

B (ii) Using by Dense Graded bituminous Macadam Grading- II cum 9,482.00 9,989.00
C (i) Using by bituminous concrete Grading- I cum 10,366.00 10,863.00
C (ii) Using by bituminous concrete Grading- II cum 10,459.00 10,895.00
5.14 Fog Spray
Providing and applying low viscosity bitumen emulsion for sealing
(i) cracks less than 3 mm wide or incipient fretting or disintegration in an sqm 44.00 44.00
existing bituminous surfacing.
1.In case it is decided by the engineer to blind the fog spray, the
(ii) sqm 20.00 21.00
following may be added
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Bituminous Cold Mix ( Including Gravel Emulsion) (Providing, laying
and rolling of bituminous cold mix on prepared base consisting of a
mixture of unheated mineral aggregate and emulsified or cutback
5.15
bitumen, including mixing in a plant of suitable type and capacity,
transporting, laying, compacting and finishing to specified grades and
levels.)
Using bitumen emulsion and 9.5 mm or 13.2 mm nominal size
(i) cum 14,587.00 14,952.00
aggregate
Using bitumen emulsion and 19 mm or 26.5 mm nominal size
(ii) cum 14,587.00 14,952.00
aggregate
Using cutback bitumen and 9.5 mm or 13.2 mm nominal size
(iii) cum 10,816.00 11,111.00
aggregate
Using cutback bitumen and 19 mm or 26.5 mm nominal size
(iv) cum 10,816.00 11,111.00
aggregate
Sand Asphalt Base Course (Providing, laying and rolling sand-asphalt
base course composed of sand, mineral filler and bituminous binder
on a prepared sub-grade or sub-base to the lines, levels, grades and
5.16 cum 11,051.00 11,348.00
cross sections as per the drawings including mixing in a plant of
suitable type and capacity, transporting, laying, compacting and
finishing.)
5.17 Crack Prevention Courses

Stress Absorbing Membrane (SAM) crack width less than 6 mm


(Providing and laying of a stress absorbing membrane over a cracked
road surface, with crack width below 6 mm after cleaning with a
mechanical broom, using modified binder complying with IRC:SP: 53,
(i) sqm 75.00 77.00
sprayed at the rate of 9 kg per 10 sqm and spreading 5.6 mm crushed
stone aggregates @ 0.11 cum per 10 sqm with hydraulic chip
spreader, sweeping the surface for uniform spread of aggregates and
surface finished to conform to clause 902..)

Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm


(Providing and laying of a stress absorbing membrane over a cracked
road surface, with crack width 6 to 9 mm after cleaning with a
mechanical broom, using modified binder complying with IRC:SP: 53,,
(ii) sqm 87.00 88.00
sprayed at the rate of 11 kg per 10 sqm and spreading 11.2 mm
crushed stone aggregates @ 0.12 cum per 10 sqm, sweeping the
surface for uniform spread of aggregates and surface finished to
conform to clause 902.)

Stress Absorbing Membrane (SAM) crack width above 9 mm and


cracked area above 50 % (Providing and laying a single coat of a
stress absorbing membrane over a cracked road surface, with crack
width above 9 mm and cracked area above 50 % after cleaning with a
(iii) mechanical broom, using modified binder complying with IRC:SP: 53,, sqm 113.00 116.00
sprayed at the rate of 15 kg per 10 sqm and spreading 11.2 mm
crushed stone aggregates @ 0.12 cum per 10 sqm, sweeping the
surface for uniform spread of aggregates and surface finished to
conform to clause 902.)

Case - IV : Bitumen Impregnated Geotextile (Providing and laying a


bitumen impregnated geotextile layer after cleaning the road surface,
(iv) geotextile conforming to requirements of clause 708.2, laid over a sqm 146.00 148.00
tack coat with 1.05 kg per sqm of paving grade bitumen 80 - 100
penetration and constructed to the requirement of clause 708.3.4)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Recipe Cold Mix (Providing and laying of premix of crushed stone
aggregates and emulsion binder, mixed in a batch type cold mixing
5.18 plant, laid over prepared surface, by paver finisher, rolled with a
pneumatic tyred roller initially and finished with a smooth steel wheel
roller, all as per clause 518.3)
(i) 75 mm thickness cum 10,204.00 10,496.00
(ii) 40 mm thickness cum 13,124.00 13,471.00
(iii) 25 mm thickness cum 14,748.00 15,126.00
5.19 Bituminous Concrete with waste plastic

Bituminous Concrete Grading -I with waste plastic(Providing and


laying bituminous concrete with higher capacity batch type hot mix
plant using crushed aggregates of specified grading, premixed with
bituminous binder @ 5.2 per cent of mix and filler, transporting the
(i) hot mix to work site, laying with a hydrostatic paver finisher with cum 11,368.00 11,686.00
sensor control to the required grade, level and alignment, rolling with
smooth wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MORTH specification clause No. 507 complete in
all respects)

Bituminous Concrete Grading -II with waste plastic (Providing and


laying bituminous concrete with higher capacity batch type hot mix
plant using crushed aggregates of specified grading, premixed with
bituminous binder @ 5.4 per cent of mix and filler, transporting the
(ii) hot mix to work site, laying with a hydrostatic paver finisher with cum 11,618.00 11,942.00
sensor control to the required grade, level and alignment, rolling with
smooth wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MORTH specification clause No. 507 complete in
all respects)

CHAPTER-6
CEMENT CONCRETE PAVEMENTS
Dry Lean Cement Concrete Sub- base (Construction of dry lean
cement concrete Sub- base over a prepared sub-grade with coarse
and fine aggregate conforming to IS: 383, the size of coarse
aggregate not exceeding 25 mm, aggregate cement ratio not to
exceed 15:1, aggregate gradation after blending to be as per table
6.01 600-1, cement content not to be less than 150 kg/ cum, optimum cum 5,073.00 5,273.00
moisture content to be determined during trial length construction,
concrete strength not to be less than 10 Mpa at 7 days, mixed in a
batching plant, transported to site, laid with a paver with electronic
sensor, compacting with 8-10 tonnes vibratory roller, finishing and
curing.)

Cement Concrete Pavement (Construction of un-reinforced, dowel


jointed, plain cement concrete pavement over a prepared sub base
with 43 grade cement @ 400 kg per cum, coarse and fine aggregate
conforming to IS 383, maximum size of coarse aggregate not
exceeding 25 mm, mixed in a batching and mixing plant as per
approved mix design, transported to site, laid with a fixed form or slip
6.02 cum 8,796.00 9,010.00
form paver, spread, compacted and finished in a continuous operation
including provision of contraction, expansion, construction and
longitudinal joints, joint filler, separation membrane, sealant primer,
joint sealant, debonding strip, dowel bar, tie rod, admixtures as
approved, curing compound, finishing to lines and grades as per
drawing )
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

Transition section between rigid and flexible pavement (Due to


change in the properties of materials and type of construction, a
gradual changeover from rigid pavement to flexible pavement is
desirable to avoid any damage at the butting joint. After provision of
6.03
an expansion joint in the cement concrete slab, the thickness of slab
should be tapered to 10 cm over a length of 3 m towards the flexible
pavement. The deficiency of thickness caused due to tapering of the
slab should be made up by the asphaltic layers.)

Construction of Base/Sub-base of pavement with lean concrete - fly


ash. (Construction of Base/sub-base using cement, sand, fly ash and
coarse aggregates proportioned as per table 4 of IRC: 74/1979 and
with water content ratio, slump and compressive strength as defined
6.04 in the said table, mix prepared in a batching and mixing plant and cum 5,048.00 5,258.00
compacted with a vibratory roller 8-10 tonnes capacity within the time
limit laid down vide clause 7.6.3 of IRC: 74-1979, construction joints
properly formed at the end of day's work, cured for 14 days, all as
specified in IRC: 74-1979 and as per approved plans.)

Cement - Fly ash concrete pavement. (Construction reinforced-


reinforced, dowel jointed, plain cement concrete pavement over a
prepared sub base with 43 grade cement, coarse and fine aggregate
conforming to IS 383, maximum size of coarse aggregate not
exceeding 25 mm, replacing cement by fly ash to the extent of 15%
and sand by 10%, mixed in a batching and mixing plant as per
6.05 approved mix design, transported to site, laid with a fixed form or slip cum 8,232.00 8,437.00
form paver, spread, compacted and finished in a continuous operation
including provision of contraction, expansion, construction and
longitudinal joints, joint filler, separation membrane, sealant primer,
joint sealant, debonding strip, dowel bar, tie rod, admixtures as
approved, curing compound, finishing to lines and grades as per
drawing )

Thin White topping(Construction of thin white topping with plain


cement concrete pavment over existing surface with approve grade
cement @ 400 kg per cum and as per IRC SP-76, coarse and fine
aggregate conforming to IS 383, maximum size of fine aggregate not
exceeding 25 mm, mixed in a batching and mixing plant as per
6.06 cum 8,362.00 8,548.00
approved mix design, transported to site, laid with a fixed form or slip
form paver, spread, compacted and finished in a continuous operation
including provision of contraction joint, joint filler, sealant primer, joint
sealant, admixture as approved, curing compound, finishing to lines
etc. and grades as per drawing.)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

Cement- Fly ash Thin White topping(Construction of thin white


topping with plain cement concrete pavment over existing surface with
approve grade cement @ 340 kg per cum and Fly ash as per IRC SP-
76, coarse and fine aggregate conforming to IS 383, maximum size of
fine aggregate not exceeding 25 mm, mixed in a batching and mixing
6.07 cum 7,859.00 8,036.00
plant as per approved mix design, transported to site, laid with a fixed
form or slip form paver, spread, compacted and finished in a
continuous operation including provision of contraction joint, joint filler,
sealant primer, joint sealant, admixture as approved, curing
compound, finishing to lines etc. and grades as per drawing.)

CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH

Sub- Surface Drain with Geotextiles (Construction of sub surface


drain 200 mm dia using geotextiles treated with carbon black with
physical properties as given in clause 702.2.3 formed in to a stable
7.01 metre 1,008.00 1,026.00
network and a planar geocomposite structure, joints wrapped with
geotextile to prevent ingress of soil, all as per clause 702 and
approved drawings including excavation and backfilling)

Laying Paving Fabric Beneath a Pavement Overlay (Providing and


laying paving fabric with physical requirements as per Table 700-16
over a tack coat of paving grade Bitumen 80-100 penetration, laid at
the rate of 1 kg per sqm over thoroughly cleaned and repaired surface
7.02 sqm 165.00 168.00
to provide a water resistant membrane and crack retarding layer.
Paving fabric to be free of wrinkling and folding and to be laid before
cooling of tack coat, brooming and rolling of surface with pneumatic
roller to maximise paving fabric contact with pavement surface)

Laying Boulder Apron in Crates of Synthetic Geogrids (Providing,


preparing and laying of geogrid crated apron 1 m x 5 m, 600 mm thick
including excavation and backfilling with baffles at 1 metre interval,
made with geogrids having characteristics as per clause 703.2, joining
sides with connectors/ring staples, top corners to be tie tensioned,
placing of suitable cross interval ties in layers of 300 mm connecting
7.03 opposite side with lateral braces and tied with polymer braids to avoid cum 7,184.00 7,317.00
bulging, constructed as per clause 703.3. filled with stone with
minimum size of 200 mm and specific gravity not less than 2.65,
packed with stone spalls, keyed to the foundation recess in case of
sloping ground and laid over a layer of geotextile to prevent migration
of fines, all as per clause 703 and laid as per clause 2503.3 and
approved design.)

Reinforced Earth Retaining Wall (Reinforced earth retaining walls


have four main components as under: a) Excavation for foundation,
foundation concrete and cement concrete grooved seating in the
7.04 foundation for facing elements (facia material). b) Facia material and
its placement. c) Assembling, joining with facing elements and laying
of the reinforcing elements. d) Earthfill with granular material which is
to be retained by the wall.)

(i) Assembling, joining and laying of reinforcing elements. Sqm


A With reinforcing element of steel / Aluminium strips / polymeric strips.
Type 1 1.Galvanised carbon steel strips metre 9.00 9.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Type 2 2.Copper Strips metre 9.00 9.00
Type 3 3.Aluminium Strips metre 9.00 9.00
Type 4 4.Stainless steel strips metre 9.00 9.00
Type 5 5.Glass reinforced polymer/fibre reinforced polymer/polymeric strips metre 9.00 9.00
B With reinforcing elements of synthetic geogrids sqm 250.00 255.00
(ii) Facing elements of RCC sqm 2,230.00 2,280.00
7.05 Bi-axial extruded high modulus polypropylene geogrid
Supplying & laying of bi-axial extruded high modulus polypropylene
geogrid conforming to MORT&H specification for base/sub-base
reinforcement having minimum tensile strength 15kN/m in the
(i) longitudinal and transverse direction, with 5kN/m and 7kN/m tensile sqm 12.00 13.00
strength at 2% and 5% strain respectively in the longitudinal and
transverse direction, junction efficiency not less than 95% and with
38mm X 38mm mesh opening.
Supplying & laying of bi-axial extruded high modulus polypropylene
geogrid conforming to MORT&H specification for base/sub-base
reinforcement having minimum tensile strength 20kN/m in the
(ii) longitudinal and transverse direction, with 7kN/m and 14kN/m tensile sqm 12.00 13.00
strength at 2% and 5% strain respectively in the longitudinal and
transverse direction, junction efficiency not less than 95% and with
38mm X 38mm mesh opening.

Supplying & laying of bi-axial extruded high modulus polypropylene


geogrid conforming to MORT&H specification for base/sub-base
reinforcement having minimum tensile strength 30kN/m in the
(iii) longitudinal and transverse direction, with 10.5kN/m and 21kN/m sqm 12.00 13.00
tensile strength at 2% and 5% strain respectively in the longitudinal
and transverse direction, junction efficiency not less than 95% and
with 38mm X 38mm mesh opening.

Supplying & laying of bi-axial extruded high modulus polypropylene


geogrid coforming to MORT&H specification for base/sub-base
reinforcement having minimum tensile strength 40kN/m in the
(iv) longitudinal and transverse direction, with 14kN/m and 28kN/m tensile sqm 12.00 13.00
strength at 2% and 5% strain respectively in the longitudinal and
transverse direction, junction efficiency not less than 95% and with
38mm X 38mm mesh opening.

Supplying and laying high strength flexible geogrids (HSFG) as soil


reinforcement / basal reinforcement as per MORTH 3100 and IRC
113, made of high tenacity polyester core with polyethylene coating
7.06
with minimum Long Term Design Strength (LTDS) of more than 50%
of ultimate tensile strength at 30 degree Celcius corresponding to 12
% strain etc. complete and as directed by Engineer - In - Charge.

(i) Synthetic Geogrid Ultimate tensile strength- 100 kN/m sqm 411.00 418.00
(ii) Synthetic Geogrid Ultimate tensile strength- 150 kN/m sqm 451.00 459.00
(iii) Synthetic Geogrid Ultimate tensile strength- 200 kN/m sqm 610.00 622.00
(iv) Synthetic Geogrid Ultimate tensile strength- 250 kN/m sqm 670.00 683.00
(v) Synthetic Geogrid Ultimate tensile strength- 300 kN/m sqm 710.00 724.00
(vi) Synthetic Geogrid Ultimate tensile strength- 350 kN/m sqm 790.00 805.00
(vii) Synthetic Geogrid Ultimate tensile strength- 400 kN/m sqm 850.00 866.00
(viii) Synthetic Geogrid Ultimate tensile strength- 500 kN/m sqm 1,010.00 1,029.00
(ix) Synthetic Geogrid Ultimate tensile strength- 600 kN/m sqm 1,110.00 1,131.00
(x) Synthetic Geogrid Ultimate tensile strength- 800 kN/m sqm 1,426.00 1,452.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
(xi) Synthetic Geogrid Ultimate tensile strength- 900 kN/m sqm 1,691.00 1,723.00
(xii) Synthetic Geogrid Ultimate tensile strength- 1000 kN/m sqm 1,909.00 1,945.00
(xiii) Synthetic Geogrid Ultimate tensile strength- 1100 kN/m sqm 2,009.00 2,046.00
(xiv) Synthetic Geogrid Ultimate tensile strength- 1200 kN/m sqm 2,185.00 2,225.00

Supplying & laying of drainage composite for use behind walls,


between two different fills, alongside drains of road, below concrete
lining of canals etc. Geocomposite for planar drainage, realized by
thermobonding a draining core in extruded monofilaments with two
filtering nonwoven geotextiles that may also be working as separation
or protecting layers. The draining three dimensional core will have a
“W” configuration as longitudinal parallel channels. Minimum
thickness to be 7.2mm, with two filtering UV stabilized polypropylene
7.07 sqm 240.00 244.00
nonwoven geotextile of minimum thickness of 0.75 mm having pores
of 150 micron and tensile strength of 8.0 kN/m that will be working as
separation or protecting layer, geocomposite having in plane flow
capacity of 2.1 L / (m.s) at hydraulic gradient of 1.0 & 20 kpa pressure
and tensile strength of 18 kN/m , with mass per unit area of 740 gsm,
supplied in the form of roll for easy transportation to site of work as
per detailed specification all complete as per directions of Engineer in
charge.

Supplying & laying of drainage composite for use behind walls,


between two different fills, alongside drains of road, below concrete
lining of canals etc. having thermobonding a draining core - HDPE
geonet comprises of two sets of parallel overlayed ribs integrally
connected to have a rhomboidal shape with a polyethylene film and a
nonwoven geotextile having mass per unit area 130 g/m2 and tensile
7.08 strength of 8.0 kN/m that will be working as separation or protecting sqm 207.00 211.00
layer, geocomposite having in plane flow capacity of 0.7 L / (m.s) at
hydraulic gradient of 1.0 & 20 kPa pressure and tensile strength of
13.5 kN/ m , with mass per unit area of 830 gsm, at easily accessible
location including top and bottom, with all leads and lifts, manpower
and machinery, materials, labour etc. complete and as directed by
Engineer - In - Charge.

Reinforced cement concrete crash Barrier with frication slab(Provision


of an Reinforced cement concrete crash barrier with friction slab at
the approaches to bridge structures, Constructed with M-40 grade
7.09 concrete with HYSD reinforcement conforming to IRC:112 and as per metre 16,292.00 16,438.00
dimensions in the approved drawings at locations directed by the
Engineers, all specified(Area-0.185 sqm/meter) below frication slab
and (Area-1.032 sqm/meter) crash Barrier with frication slab.)

In-site Soil reinforcement for slope restoration and protection work


(Soil Nailing)(With fully threaded hot-dip galvanised solid geotechnical
bars as soil nails (galvanization minimum 500 grams per sqm) of
miniimum 25 mm diameter, having yield strength>670N/mm2 and
Running
7.10 tensile strength> 800N/mm2 as per technical specifications and 4,240.00 4,318.00
metre
drawings etc. complete including drilling, flusing, grouting and all
supply and installation of all the components listed as per technical
specifications and drawings etc. and considering all lead, lift and
machinery.)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

Horizontal Drainage Boring(Horizontal Drainage Boring methods on


the types of sandy soil/ cohesive soil and drilling length including cost
7.11
of all materials, machinary, labour and all other ancillary operations
etc.,(Nominal Diameter of drilling pipe- 90mm))

(i) Drilling length below bed level upto 50.0 Meter


Running
A Sandy Soil/ Cohesive Soil 2,946.00 3,001.00
metre
Running
B Gravelly soil 4,100.00 4,176.00
metre
Running
C Rubble / Cobble Stone 5,485.00 5,586.00
metre
Running
D Soft Rock 4,469.00 4,552.00
metre
(ii) Drilling length below bed level from 50.0 Meter- 80 meter
Running
A Sandy Soil/ Cohesive Soil 3,450.00 3,514.00
metre
Running
B Gravelly soil 4,847.00 4,936.00
metre
Running
C Rubble / Cobble Stone 6,516.00 6,636.00
metre
Running
D Soft Rock 5,272.00 5,370.00
metre
Horizontal Drainage Boring(Nomonal Diameter of drilling pipe- 110
mm)(Horizontal Drainage Boring methods on the types of sandy soil/
7.12 cohesive soil and drilling length including cost of all materials,
machinary, labour and all other ancillary operations etc.,(Nominal
Diameter of drilling pipe- 90mm))
(i) Drilling length below bed level upto 50.0 Meter
Running
A Sandy Soil/ Cohesive Soil 3,870.00 3,942.00
metre
Running
B Gravelly soil 5,004.00 5,096.00
metre
Running
C Rubble / Cobble Stone 6,300.00 6,416.00
metre
Running
D Soft Rock 5,271.00 5,368.00
metre
(ii) Drilling length below bed level from 50.0 Meter- 80 meter
Running
A Sandy Soil/ Cohesive Soil 4,550.00 4,635.00
metre
Running
B Gravelly soil 5,911.00 6,020.00
metre
Running
C Rubble / Cobble Stone 7,446.00 7,584.00
metre
Running
D Soft Rock 6,218.00 6,333.00
metre
Horizontal Drainage Boring(Nomonal Diameter of drilling pipe- 135
mm)(Horizontal Drainage Boring methods on the types of sandy soil/
7.13 cohesive soil and drilling length including cost of all materials,
machinary, labour and all other ancillary operations etc.,(Nominal
Diameter of drilling pipe- 90mm))
(i) Drilling length below bed level upto 50.0 Meter
Running
A Sandy Soil/ Cohesive Soil 4,591.00 4,676.00
metre
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Running
B Gravelly soil 5,945.00 6,055.00
metre
Running
C Rubble / Cobble Stone 6,779.00 6,904.00
metre
Running
D Soft Rock 5,945.00 6,055.00
metre
(ii) Drilling length below bed level from 50.0 Meter- 80 meter
Running
A Sandy Soil/ Cohesive Soil 5,401.00 5,501.00
metre
Running
B Gravelly soil 7,038.00 7,169.00
metre
Running
C Rubble / Cobble Stone 8,063.00 8,212.00
metre
Running
D Soft Rock 7,038.00 7,656.00
metre
Selected fill behind Reinforced Earth Wall Complete as per drawing
7.14
and Technical specification
A Granular Material cum 2,804.00 2,872.00
B Sandy Material cum 1,911.00 1,957.00

Providing and laying of filter media with granular materials/stone


crused aggregates satisfying the requirements laid down in clause
2504.2.2. of MoRT&H specification to a thickness of not less than 600
7.15 mm with smallar size towards the soil and bigger size towards the wall sqm 2,255.00 2,297.00
provided over the entire surface behind abutment, wing wall and
return wall to the full height compacted to a firm condition complete as
per drawing and Technical specifications.

Supplying & laying of drainage composite for use behind walls with
7.16
Geosynthetic drainage composite

Supplying & laying of drainage composite for use behind walls,


between two different fills, alongside drains of road, below concrete
lining of canals etc. Geocomposite for planar drainage, realized by
thermobonding a draining core in extruded monofilaments with two
filtering nonwoven geotextiles that may also be working as separation
or protecting layers. The draining three dimensional core will have a
“W” configuration as longitudinal parallel channels. Minimum
thickness to be 7.2mm, with two filtering UV stabilized polypropylene
A sqm 240.00 244.00
nonwoven geotextile of minimum thickness of 0.75 mm having pores
of 150 micron and tensile strength of 8.0 kN/m that will be working as
separation or protecting layer, geocomposite having in plane flow
capacity of 2.1 L / (m.s) at hydraulic gradient of 1.0 & 20 kpa pressure
and tensile strength of 18 kN/m , with mass per unit area of 740 gsm,
supplied in the form of roll for easy transportation to site of work as
per detailed specification all complete as per directions of Engineer in
charge.
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

Supplying & laying of drainage composite for use behind walls,


between two different fills, alongside drains of road, below concrete
lining of canals etc. having thermobonding a draining core - HDPE
geonet comprises of two sets of parallel overlayed ribs integrally
connected to have a rhomboidal shape with a polyethylene film and a
nonwoven geotextile having mass per unit area 130 g/m2 and tensile
B strength of 8.0 kN/m that will be working as separation or protecting sqm 207.00 211.00
layer, geocomposite having in plane flow capacity of 0.7 L / (m.s) at
hydraulic gradient of 1.0 & 20 kPa pressure and tensile strength of
13.5 kN/ m , with mass per unit area of 830 gsm, at easily accessible
location including top and bottom, with all leads and lifts, manpower
and machinery, materials, labour etc. complete and as directed by
Engineer - In - Charge.

Geocell for Slope protection(Furnishing and installing of the Geocell


for slope protection including fixing and anchoring of cells in the
7.17 ground, preparation of ground, filling of cells with specified materials, sqm 114.00 117.00
seeding, watering and all other items to be complete the work as per
these specifications drawing or as directed by the Engineer.)

Geosynthtics mat on the slope(Furnishing and installing of the


Geosynthetics mat for control of erosion of slopes including suppling
7.18 and laying the mat, spreading soil and seeding to promote the design sqm 75.00 77.00
of vegetation, watering and all other items to be complete the work as
per these specifications drawing or as directed by the Engineer.)

Natural Geotextile on the slope(Furnishing and installing of the natural


Geotextile for control of erosion of slopes including suppling and
laying the natural Geotextile, spreading soil and seeding to promote
7.19 sqm 43.00 43.00
the design of vegetation, watering and all other items to be complete
the work as per these specifications drawing or as directed by the
Engineer.)
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES

Cast in Situ Cement Concrete M20 kerb (Construction of cement


concrete kerb with top and bottom width 115 and 165 mm
respectively, 250 mm high in M 20 grade PCC on M-10 grade
8.01
foundation 150 mm thick, foundation having 50 mm projection beyond
kerb stone, kerb stone laid with kerb laying machine, foundation
concrete laid manually, all complete as per clause 408)

A Using Concrete Batching and Mixing Plant


(i) PCC M15 for Kerb base metre 239.00 244.00
(ii) PCC M20 for Kerb (Cast in Situ) metre 306.00 312.00

Cast in Situ Cement Concrete M 20 Kerb with Channel (Construction


of cement concrete kerb with channel with top and bottom width 115
and 165 mm respectively, 250 mm high in M 20 grade PCC on M10
8.02 grade foundation 150 mm thick, kerb channel 300 mm wide, 50 mm
thick in PCC M20 grade, sloped towards the kerb, kerb stone with
channel laid with kerb laying machine, foundation concrete laid
manually, all complete as per clause 408)

A Using Concrete Batching and Mixing Plant


Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
(i) PCC M15 for Kerb base metre 249.00 253.00
(ii) PCC M20 for Kerb (Cast in Situ) metre 412.00 421.00
Printing new letter and figures of any shade (Printing new letter and
8.03 figures of any shade with synthetic enamel paint black or any other
approved colour to give an even shade)
Hindi ( Matras commas and the like not to be measured and paid for cm height
(i) 1.60 1.60
Half letter shall be counted as half ) per letter
cm height
(ii) English and Roman 0.90 1.00
per letter

Retro- reflectorised Traffic signs (Providing and fixing of retro-


reflectorised cautionary, mandatory and informatory sign as per
IRC :67 made of encapsulated lens type reflective sheeting vide
clause 801.3, fixed over aluminium sheeting, 1.5 mm thick supported
8.04
on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to
the ground by means of properly designed foundation with M15 grade
cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level
as per approved drawing)

( i ) 120 cm equilateral triangle each 8,800.00 8,969.00


( ii ) 90 cm equilateral triangle each 6,325.00 6,448.00
( iii ) 75 cm equilateral triangle each 5,353.00 5,458.00
( iv ) 60 cm equilateral triangle each 4,558.00 4,648.00
( v ) 120 cm circular each 13,403.00 13,657.00
(vi ) 90 cm circular each 8,914.00 9,085.00
( vii ) 75cm circular each 7,151.00 7,290.00
( viii ) 60 cm circular each 5,708.00 5,820.00
( ix) 90 cm x 75 cm rectangular each 9,267.00 9,444.00
( x) 80 mm x 60 mm rectangular each 7,498.00 7,643.00
( xi) 60 cm x 50 cm rectangular each 5,865.00 5,980.00
( xii) 60 cm x 45 cm rectangular each 5,593.00 5,702.00
( xiii) 60 cm x 60 cm square each 6,409.00 6,534.00
( xiv) 120 cm high octagon each 13,965.00 14,229.00
( xv) 90 cm high octagon each 9,231.00 9,407.00
( xvi) 75 cm high octagon each 7,371.00 7,513.00
Direction and Place Identification signs upto 0.9 sqm size board.
(Providing and erecting direction and place identification retro-
reflectorised sign asper IRC:67 made of encapsulated lens type
reflective sheeting vide clause 801.3, fixed over aluminium sheeting, 2
8.05 mm thick with area not exceeding 0.9 sqm supported on a mild steel sqm 12,996.00 13,243.00
single angle iron post 75 x 75 x 6 mm firmly fixed to the ground by
means of properly designed foundation with M15 grade cement
concrete 45 x 45 x 60 cm, 60 cm below ground level as per approved
drawing)

Direction and Place Identification signs with size more than 0.9 sqm
size board. (Providing and erecting direction and place identification
retro- reflectorised sign asper IRC :67 made of encapsulated lens
type reflective sheeting vide clause 801.3, fixed over aluminium
8.06 sheeting, 2 mm thick with area exceeding 0.9 sqm supported on a sqm 13,806.00 14,069.00
mild steel angle iron post 75 mm x 75 mm x 6 mm, 2 Nos. firmly fixed
to the ground by means of properly designed foundation with M 15
grade cement concrete45 cm x 45 cm x 60 cm, 60 cm below ground
level as per approved drawing)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

Overhead Signs (Providing and erecting overhead signs with a


corrosion resistant aluminium alloy sheet reflectorised with high
intensity retro-reflective sheeting of encapsulated lense type with
8.07 vertical and lateral clearance given in clause 802.2 and 802.3 and
installed as per clause 802.7 over a designed support system of
aluminium alloy or galvanised steel trestles and trusses of sections
and type as per structural design requirements and approved plans)

A Truss and Vertical Support tonne 74,693.00 76,076.00


B Aluminium alloy plate for over head sign sqm 10,150.00 10,338.00
Painting Two Coats on New Concrete Surfaces (Painting two coats
8.08 after filling the surface with synthetic enamel paint in all shades on sqm 93.00 95.00
new plastered concrete surfaces)
Painting on Steel Surfaces (Providing and applying two coats of ready
8.09 mix paint of approved brand on steel surface after through cleaning of sqm 93.00 95.00
surface to give an even shade)
Painting on Wood Surfaces (Providing and applying two coats of
8.10 ready mix paint of approved brand on wood surface after through sqm 102.00 104.00
cleaning of surface to give an even shade)

Painting Lines, Dashes, Arrows etc on Roads in Two Coats on New


Work (Painting lines, dashes, arrows etc on roads in two coats on
8.11 new work with ready mixed road marking paint conforming to IS:164
on bituminous surface, including cleaning the surface of all dirt, dust
and other foreign matter, demarcation at site and traffic control )

(i) Over 10 cm in width sqm 175.00 178.00


(ii) Up to 10 cm in width sqm 146.00 148.00

Painting Lines, Dashes, Arrows etc on Roads in Two Coats on Old


Work (Painting lines, dashes, arrows etc on roads in two coats on old
8.12 work with ready mixed road marking paint confirming to IS: 164 on
bituminous surface, including cleaning the surface of all dirt, dust and
other foreign matter, demarcation at site and traffic control )

(i) Over 10 cm in width sqm 123.00 125.00


(ii) Up to 10 cm in width sqm 134.00 136.00

Road Marking with Hot Applied Thermoplastic Compound with


Reflectorising Glass Beads on Bituminous Surface (Providing and
laying of hot applied thermoplastic compound 2.5 mm thick including
8.13 sqm 557.00 567.00
reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5
mm is exclusive of surface applied glass beads as per IRC:35 .The
finished surface to be level, uniform and free from streaks and holes.)

Kilo Metre Stone (Reinforced cement concrete M15grade kilometre


8.14 stone of standard design as per IRC:8-1980, fixing in position
including painting and printing etc)
(i) 5th kilometre stone (precast) each 6,885.00 7,022.00
(ii) Ordinary Kilometer stone (Precast) each 3,834.00 3,914.00
(iii) Hectometer stone (Precast) each 1,114.00 1,137.00
Road Delineators (Supplying and installation of delineators (road way
indicators, hazard markers, object markers), 80-100 cm high above
ground level, painted black and white in 15 cm wide stripes, fitted with
8.15 each 521.00 530.00
80 x 100 mm rectangular or 75 mm dia circular reflectorised panels at
the top, buried or pressed into the ground and confirming toIRC-79
and the drawings.)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Boundary pillar (Reinforced cement concrete M15 grade boundary
8.16 pillars of standard design as per IRC:25-1967, fixed in position each 1,173.00 1,194.00
including finishing and lettering but excluding painting)

G.I Barbed wire Fencing 1.2 metre high (Providing and fixing 1.2
metres high GI barbed wire fencing with 1.8 m angle iron posts 40
mm x 40 mm x 6 mm placed every 3 metres center to center founded
in M15 grade cement concrete, 0.6 metre below ground level, every
8.17 metre 349.00 355.00
15th post, last but one end post and corner post shall be strutted on
both sides and end post on one side only and provided with 9
horizontal lines and 2 diagonals interwoven with horizontal wires,
fixed with GI staples, turn buckles etc complete as per clause 808 )

G.I Barbed wire Fencing 1.8 metre high (Providing and fixing 1.8
metres high GI barbed wire fencing with 2.4 m angle iron posts 50
mm x 50 mm x 6 mm placed every 3 metres center to center founded
in M15 grade cement concrete, 0.6 metre below ground level, every
8.18 metre 577.00 588.00
15th post, last but one end post and corner post shall be strutted on
both sides and end post on one side only and provided with 12
horizontal lines and 2 diagonals interwoven with horizontal wires,
fixed with GI staples, turn buckles etc complete as per clause 808 )

Fencing with welded steel wire Fabric 75 mm x 50 mm (Suggestive)


(Providing 1.20 metre high fencing with angle iron posts 50 mm x 50
mm x 6 mm at 3 metre center to center with 0.40 metre embedded in
8.19 M15 grade cement concrete, corner, end and every 10th post to be
strutted, provided with welded steel wire fabric of 75 mm x 50 mm
mesh or 75 mm x 25 mm mesh and fixed to iron posts by flat iron 50 x
5 mm and bolts etc. complete in all respects.)

(i)75 mm x 50 mm mesh metre 837.00 853.00


(ii)75 mm x 25 mm mesh metre 1,213.00 1,235.00

Tubular Steel Railing on Medium Weight steel channel ( ISMC series)


100 mm x 50 mm (Providing, fixing and erecting 50 mm dia steel pipe
8.20 railing in 3 rows duly painted on medium weight steel channels (ISMC metre 2,212.00 2,226.00
series) 100 mm x 50 mm, 1.2 metres high above ground, 2 m centre
to centre, complete as per approved drawings)

Tubular Steel Railing on Precast RCC posts, 1.2 m high above


ground level (Providing, fencing and erecting 50 mm dia painted steel
8.21 pipe railing in 3 rows on precast M20 grade RCC vertical posts1.8 metre 5,260.00 5,382.00
metres high (1.2 m above GL) with 3 holes 50 mm dia for pipe, fixed 2
metres centre to, complete as per approved drawing)

8.22 Reinforced Cement Concrete Crash Barrier

Provision of an Reinforced cement concrete crash barrier at the


edges of the road, approaches to bridge structures and medians,
constructed with reinforcement conforming ti conforming Mort&h
specification and as per details given IRC-5(Fig-5, B) including dowel
A
bars 25 mm dia, 450 mm long at expansion joints filled with pre-
moulded asphalt filler board etc.., as per approved drawing and at
location directed by the engineer, all as specified {area-0.243
sqm/meter, single face

(i) M 25 grade concrete metre 3,100.00 3,112.00


Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
(ii) M 30 grade concrete metre 3,133.00 3,146.00

Provision of an Reinforced cement concrete new jersy crash barrier at


the media, constructed with reinforcement conforming ti conforming
Mort&h specification and as per details given IRC-119 (Fig-26,)
B including dowel bars 25 mm dia, 450 mm long at expansion joints
filled with pre-moulded asphalt filler board etc.., as per approved
drawing and at location directed by the engineer, all as specified
{area-0.261 sqm/meter, double face

(i) M 25 grade concrete metre 3,328.00 3,342.00


(ii) M 30 grade concrete metre 3,364.00 3,378.00
8.23 Metal Beam Crash Barrier

Type - A, "W" : Metal Beam Crash Barrier (Providing and erecting a


"W" metal beam crash barrier comprising of 3 mm thick corrugated
sheet metal beam rail, 70 cm above road/ground level, fixed on ISMC
series channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to
A centre, 1.8 m high, 1.1 m below ground/road level, all steel parts and metre 3,909.00 3,982.00
fitments to be galvanised by hot dip process, all fittings to conform to
IS:1367 and IS:1364, metal beam rail to be fixed on the vertical post
with a spacer of channel section 150 x 75 x 5 mm, 330 mm long
complete as per clause 811)

Type - B, "THRIE" : Metal Beam Crash Barrier (Providing and erecting


a "Thrie" metal beam crash barrier comprising of 3 mm thick
corrugated sheet metal beam rail, 85 cm above road/ground level,
fixed on ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2
B m centre to centre, 2 m high with 1.15 m below ground level, all steel metre 4,909.00 5,000.00
parts and fitments to be galvanised by hot dip process, all fittings to
conform to IS:1367 and IS:1364, metal beam rail to be fixed on the
vertical post with a space of channel section 150 x 75 x 5 mm, 546
mm long complete as per clause 811)

Road Traffic Signals electrically operated (Since it is a ready made


item commercially produced and erected by specialised firm in the
8.24 electrical and electronic field, rate may be taken based on market
enquiry from firms specialised in this field and ISI certified for the
approved design and drawing.)

Flexible Crash Barrier, Wire Rope Safety Barrier (Providing and


erecting a wire rope safety barrier with vertical posts of medium
weight RS Joist (ISMB series) 100 mm x 75 mm (11.50 kg/m), 1.50 m
long 0.85 m above ground and 0.65 m below ground level, split at the
bottom for better grip, embedded in M 15 grade cement concrete 450
x 450 x 450 mm, 1.50 m center to center and with 4 horizontal steel
8.25 wire rope 40 mm dia and anchored at terminal posts 15 m apart. metre 2,779.00 2,831.00
Terminal post to be embedded in M 15
gradecementconcretefoundation2400 x 450 x 900 mm (depth),
strengthened by a strut of RS joist 100 x 75 mm, 2 m long at 450
inclination and a tie 100 x 8 mm, 1.50 m long at the bottom, all
embedded in foundation concrete as per approved design and
drawing, rate excluding excavation and cement concrete.)

8.26 Anti - Glare Devices in Median


Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Plantation (Plantation of shrubs and plants of approved species in the
median. apart from cutting off glare from vehicle coming from opposite
A direction, these plants provide a pleasant envoirenment and are eco-
friendly. The rate for this item is available in the chapter 11 on
horticulture. )

Anti - Glare Screen with 25 mm steel pipe framework fixed with


circular and rectangular vans (Providing and erecting an anti - glare
screen with 25 mm dia vertical pipes fabricated and framed in the
form of panels of one metre length and 1.75 mtr height fixed with
B circular vane 250 mm dia at top and rectangular vane 600 x 300 mm metre 3,550.00 3,617.00
at the middle, made out of steel sheet of 3 mm thickness, end vertical
pipes of the panel made larger for embedding in foundation concrete,
applying 2 coats of paint on all exposed surfaces, all as per approved
design and drawings.)

Anti - Glare Screen with Rectangular Vane of MS sheet (Providing


and erecting anti - glare screen with rectangular vanes of size 750 x
500 mm made from MS sheet, 3 mm thick and fixed on MS angle 50 x
50 x 6 mm at an angle of 450 to the direction of flow of traffic, 1.5 m
C metre 1,283.00 1,307.00
center to center, top edge of the screen 1.75 m above ground level,
vertical post firmly embedded in cement concrete foundation 0.60 m
below ground level, applying 2 coats of paint on exposed faces, all
complete as per approved design and drawings)

Street Lighting (Providing and erecting street light mounted on a steel


circular hollow pole of standard specifications for street lighting, 9 m
8.27 high spaced 40 m apart, 1.8 m overhang on both sides if fixed in the
median and on one side if fixed on the footpath, fitted with sodium
vapour lamp and fixed firmly in concrete foundation.)

(i) For Fixing in Median each 25,042.00 25,508.00


(ii) For fixing in Footpath each 24,938.00 25,401.00
Lighting on Bridges (Providing and fixing lighting on bridges, mounted
on steel hollow circular poles of standard specifications, 5 m high
8.28 each 17,740.00 18,069.00
fixed on parapets with cement concrete, 20 m apart and fitted with
sodium vapour lamp)

Cable Duct Across the Road (Providing and laying of a reinforced


cement concrete pipe duct, 300 mm dia, across the road (new
construction), extending from drain to drain in cuts and toe of slope to
toe of slope in fills, constructing head walls at both ends, providing a
minimum fill of granular material over top and sides of RCC pipe as
8.29 per IRC:98-1997, bedded on a 0.3 m thick layer of granular material
free of rock pieces, outer to outer distance of pipe at least half dia of
pipe subject to minimum 450 mm in case of double and triple row
ducts, joints to be made leak proof, invert level of duct to be above
higher than ground level to prevent entry of water and dirt, all as per
IRC: 98 - 1997 and approved drawings.)

(i) Single Row for one utility service metre 3,754.00 3,824.00
(ii) Double Row for two utility services metre 7,362.00 7,637.00
(iii) Triple Row for three utility services metre 11,269.00 11,478.00
Highway Patrolling and Traffic Aid Post (It is proposed to locate one
8.30
Traffic Aid Post every 50-60 km of the highway. )
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

Items related to under pass/ subway/ overhead bridge/ overhead foot


bridge (The items involved for underpass/ subway/ overhead bridge/
overhead foot bridge are earthwork, plain cement concrete,
8.31
plastering, painting, information sign etc. The rates for these items are
available in respective chapters which can be adopted for the
quantities derived from the approved designs and drawings)

Traffic Control System and Communication system (Providing a traffic


control centre and communication system including
telecommunication facilities and related accessories, CCTV, radar,
vehicle detection camera, central computer system These are
8.32 specialised item of telecommunication system and are the commercial
products. The designer is required to contact the manufacturers to
ascertain market prices. In case of civil works required to be executed
for these installations, pricing may be done as per rates in relevant
chapters for quantities derived approved design and drawing.)

Gantry Mounted Variable Message Sign board (Providing and


erecting gantry mounted variable message sign board electronically
operated capable of flashing the desired message over a designed
8.33
support system of aluminium alloy or galvanised steel, erected as per
approved design and drawings and with lateral clearance as per
clause 802.3)
(i) Gantry Support System tonne 71,517.00 72,841.00
Message Display (Message display board 6 sqm electronically
(ii) operated with complete electronic fitments for flashing the pre-
determined messages.)
8.34 Traffic Impact Attenuators at Abutments and Piers

With Scrap Tyres (Provision and installation of traffic attenuators at


abutment/pier of flyovers bridges using scrap tyres of size 100 x 20
A sqm 1,414.00 1,440.00
retrieved from trucks laid in 2 rows and 4 tiers, one above the other
and tied with 20 mm wire rope as per approved design and drawings.)

Using Plastic/Steel Barrel, Filled with Sand (Provision and installation


of traffic impact attenuator at abutment/pier of flyovers bridges using
B plastic/steel barrels 0.60 m dia and 1.0 m in height, filled with sand in
three rows and tied with20 mm steel wire rope as per approved
design and drawings)
Plastic barrels sqm 1,763.00 1,796.00
Steel barrels sqm 2,066.00 2,104.00

With HI - DRO cell Sandwich (Patented) ((In this patented HI - DRO


C cell system, water gets discharged from plastic tubes on impact over a sqm 6,745.00 6,870.00
pre-determined time, thus absorbing the energy))
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

Solar Powered Road Marker (Solar Stud)(Supplying of Solar Raised


Pavement Markers made of polycarbonate molded body with circular
shape, solar powered,LED self illumination in active mode, 360
degree illumination and reflective panels with micro prismatic lens
capable of providing total internal reflection of the light entering the
lens face in passive mode. The marker shall support a load of 20000
kg tested in accordance to ASTM D 4280. The marker should be
resistant to dust and water ingress according to IP 65 standards and
should withstand temperatures in the range of 0 C to 70 C. Color of
lighting could be provided in red or yellow (amber) as per requirement
8.35 each 234.00 238.00
and typical frequency of blinking is 1 Hz. There should be current
losses of less than 20 microamperes at 2.4 V in sleepcharging mode
to enhance the life of the marker and a full charge should provide for
a minimum autonomy of 50 hours. The height, width and length of the
marker shall not be less than 10 mm x 100 mm x 100 mm. Also, the
surface diameter of the marker shall not be less than 100 mm
respectively. The weight of the marker shall not exceed 0.5
Kilograms. Fixing will be by drilling holes on the road for the shanks to
go inside, without nails and using epoxy resin based adhesive and
complete as directed by the engineer.)

Traffic Cone (Provision of red fluorescent with white reflective sleeve


traffic cone made of low density polyethylene (LDPE) material with a
8.36 each 768.00 783.00
square base of 390 x 390 x 35 mm and a height of 770 mm, 4 kg in
weight, placed at 1.5 m interval, all as per BS 873)

8.37 Roadside Amenities


Rest Areas (Providing plainly furnished accommodation for rest
rooms, dormitories, restaurants, stalls, shops, petrol pump, telephone
booth, first aid room, traffic aid post, police assistance booth,
A including electricity, toilet and sewerage system Pricing may be done
based on current plinth area rates approved by PWD/CPWD/MES for
a particular zone. Area is required to be assessed for specific location
as per actual site conditions)
Parking areas and Bus Laybyes for Trucks, Buses and Light vehicles
(Pricing of parking areas may be done for the quantities of various
B items based on the approved dimensions and pavement design for a
particular terrain and soil. Rates for items may be from respective
chapters.)

C Lawn (Providing a lawn planted with grass and its maintenance )

Rumble Strips (Provision of 15 nos rumble strips covered with premix


bituminous carpet, 15-20 mm high at center, 250 mm wide placed at 1
8.38 sqm 192.00 195.00
m center to center at approved locations to control speed, marked
with white strips of road marking paint.)
Policeman Umbrella (Provision of a 2 m high (floor to roof) umbrella
for traffic policeman at road crossings, where necessary, installed on
a raised platform, built on a central support of a steel pipe 100 mm
8.39 each 7,610.00 7,752.00
dia, roof made of 25 mm dia steel pipe to provide covered area of 3
sqm, roofed with CGI sheets, all steel parts to be given 2 coats of
paint)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

High Mast Pole Lighting at Interchanges and Flyovers (Providing and


erecting a high mast pole lighting with 30 m high hot dip galvanised
mast designed to withstand forces exerted with wind speeds of 180
km per hour with 3 seconds gust, as per IS:875 (Part 3) - 1978, fitted
with a base flange, door at the base of mast with heavy duty internal
lock, lantern carriage, suitable winching arrangement for safe
working load of 750 kg and high powered electrically driven power
tools for raising and lowering of lantern carriage, flexible 8 core
electric cable, lightening conductor, earthing terminal, and fixing 2
8.40
nos aviation obstruction lights on top of the mast, all complete as per
approved design and drawings This is a specialised work and is
generally done by firms who specialise in such jobs. The detailed
designs and estimates are submitted by the firms alongwith their
tender for checks by the Department. The cost of this work is required
to be worked out based on approved design, drawings and estimate
of the lowest tender. A separate contract for this work is concluded as
the contractors for road and bridge works generally donot undertake
such jobs.)

Toll Plaza (The construction, operation and maintenance of Toll


8.41 Plaza can be broken into separate items of work as under based on
the approved design and drawings:-)

Safety Devices and signs in Construction Zones (Provision and fixing


of traffic signs for limited period at suitable locations in construction
zone comprising of warning zone, approach transition zone, working
zone and terminal transition zone with a minimum distance of 60 cm
from the edge of the kerb in case of kerbed roads and 2 to 3 m from
8.42 the edge of the carriageway in case of un-kerbed roads, the bottom
edge of the lowest sign plate to be not less than 2 m above the road
level, fixed on 60 mm x 60 mm x 6 mm angle iron post, founded and
installed as per approved design and drawings, removed and
disposed of after completion of construction work, all as per
IRC:SP:55-2001)

Portable Barricade in Construction Zone (Installation of a steel


portable barricade with horizontal rail 300 mm wide, 2.5 m in length
fitted on a 'A' frame made with 45 x 45 x 5 mm angle iron section, 1.5
8.43 each 3,963.00 4,111.00
m in height, horizontal rail painted (2 coats) with yellow and white
stripes, 150 mm in width at an angle of 450, 'A' frame painted with 2
coats of yellow paint, complete as per IRC:SP:55-2001 )

8.44 Permanent Type Barricade in Construction Zone

With Steel Components (Construction of a permanent type barricade


made of steel components, 1.5 m high from road level, fitted with 3
A horizontal rails 200 mm wide and 4 m long on 50 x 50 x 5 mm angle each 6,270.00 6,386.00
iron vertical support, painted with yellow and white strips, 150 mm in
width at an angle of450, complete as per IRC:SP:55-2001 )

With Wooden Components (Construction of a permanent type


barricade made of wooden components, 1.5 m high from road level,
fitted with 3 horizontal planks 200 mm wide and 3.66 m long on 100 x
B each 1,776.00 1,809.00
100mm wooden vertical post, painted with yellow and white striups,
150 mm in width at an angle of450, complete as per IRC:SP:55-2001
)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
With Bricks (Construction of a permanent type barricade made with
brick work in mud mortar, 1.5 m high, 4 m long, 600 mm thick,
C each 12,735.00 12,971.00
plastered with cement mortar 1:6, painted with yellow and white
strips)

Drum Delineator in Construction Zone (Provision of metal drum/empty


bitumen drum delineator, 300 mm in diameter, 800 mm high, filled
8.45 with earth for stability, painted in circumferential strips of alternate each 807.00 822.00
black and white 100 mm wide fitted with reflectors 3 Nos of 7.5 cm
dia, all as per IRC:SP:55-2001)

Water Filled Barricades Work zone sheeting (Providing water filled


barricades made up of LDPE to segregate the vehicular movement
and workzone as per IRC SP 55 shall be in Trapezoidal Shape 800
mm to 1000 mm in length, 700 mm in height for Major Roads and
8.46 each 3,129.00 3,187.00
expressway and 500 mm tall for other roads with interlocking
arrnagements, To be placed 0.5 m from the edge of the carriageway
for expressway and 0.3 m for other roads. It should have reboubdable
workzone sheeting as per ASTM D 4956 S2.)

Providing Tubular Marker made up of Polyurethane used to divide


opposing lanes of road users shall be flexible in nature. Tubular
maker having minimum height 450 mm shall be having minimum 75
8.47 each 575.00 586.00
mm Reboundable workzone retroreflective sheeting as per ASTM
4956 S2. Application of Tubular Marker Shall be done as per IRC SP
55.
Providing Tubular Marker made up of Polyurethane used to divide
opposing lanes of road users shall be flexible in nature. Tubular
maker having minimum height 700 mm shall be having minimum 75
8.48 each 605.00 616.00
mm Reboundable workzone retroreflective sheeting as per ASTM
4956 S2. Application of Tubular Marker Shall be done as per IRC SP
55.
Flagman (Positioning of a smart flagman with a yellow vest and a
8.49 yellow cap and a red flag 600 x 600 mm securely fastened to a staff 1 each 796.00 811.00
m in length for guiding the traffic)

Advanced Traffic Management Systems (ATMS) work shall cover


design, supply, installation, commissioning and/or operation and
maintenance of Advance Traffic Management Systems (which is one
of the components of Intelligent Transport Systems - ITS). The
system would include out-door equipment including emergency call
boxes, variable message sign systems, meteorological data system,
8.50
close circuit TV camera (CCTV) system, traffic counting and
classification system and transmission system. The indoor equipment
would comprise a large display board, central computer (with Network
Management System - NMS), CCTV monitor system, call centre
system or management of emergency call boxes housed in a control
centre with uninterrupted power supply.

A Traffic Management Command Centre Equipment


Control Centre Server Nos. 1.00 1.00
Hot Standby Backup Server Nos. 1.00 1.00
NAS Video Server with storage Minimum 70 TB Nos. 1.00 1.00
Backup Video (Only Incidents) Server Nos. 1.00 1.00
Graphic Display (70" LED DLP in 3x2 matrix) Nos. 1.00 1.00
Graphic Display Controller and software including Video Switches Nos. 1.00 1.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
CCTV Monitoring Workstation Nos. 1.00 1.00
Emergency Telephone (1033) console Nos. 1.00 1.00
VIDS- Workstation Nos. 1.00 1.00
Administrative Workstation Nos. 1.00 1.00
ATMS Operator Workstation Nos. 1.00 1.00
CCTV Joystick Nos. 1.00 1.00
Operations Laser Printer (Colour) Nos. 1.00 1.00
Operations Laser Printer (Black) Nos. 1.00 1.00
Rack 19" Nos. 1.00 1.00
B Advanced Traffic Management Systems (ATMS) Software
ATMS Control Room Software (integrated with VIDS, ATCC, VMS,
Nos. 1.00 1.00
MOS)
Video Management Software with atleast 150 VMS Lic. Nos. 1.00 1.00
Facility Monitoring System Controller Software Nos. 1.00 1.00
Server & Database license Nos. 1.00 1.00
Antivirus license Nos. 1.00 1.00
C PTZ Closed Circuit Television System
PTZ Camera (including CCTV Controller) Set 1.00 1.00
Solar System with UPS, battery & 12m Pole & Cabinet Set 1.00 1.00
D Video Incident Detection System Equipment (VIDS)
VIDS Camera (including Image Processing unit) Set 1.00 1.00
Warning amber lights with hooters, 72 Hrs solar backup, 5m poles
Set 1.00 1.00
and foundation
Cabinet Nos. 1.00 1.00
12 m Pole (including manufacturing and galvanizing) Nos. 1.00 1.00
Solar System with UPS & batteries Set 1.00 1.00
E Automatic Traffic Counters-cum-classifier System Equipment (ATCC)
Equipment, Sensor unit, Processing unit, Solar power supply Set 1.00 1.00
Solar System with UPS, batteries Set 1.00 1.00
F Variable Message Sign Equipment (VMS)
VMS (Variable Message Sign - M type) Nos. 1.00 1.00
Gantry (including manufacturing and galvanizing) Nos. 1.00 1.00
Solar System with UPS, battery and cabinet for M type VMS Set 1.00 1.00
G UPS and Power system
Uninterruptible Power Supply (UPS) For Server Rack (10 KVA) Set 1.00 1.00
Uninterruptible Power Supply (UPS) For TMC (30 KVA) Set 1.00 1.00
Power Distribution Board (Essential & Critical Supply) Set 1.00 1.00
H Meteorological Observation System (MOS)
MOS sensor Equipment (including MOS Controller) Set 1.00 1.00
Cabinet Nos. 1.00 1.00
Pole Nos. 1.00 1.00
Steel fence for protection Set 1.00 1.00
I Digital Transmission System (DTS)
24 Core Armoured OFC + all accessories Meter 29.00 29.00
40 mm PLB HDPE duct as per latest TSEC specifications + all
Meter 1.00 1.00
accessories
Trenching of 1.8 meters, Laying & Backfilling for PLB HDPE duct Meter 1.00 1.00
8.51 Fiber Reinforced Cement Concrete New Jersy Crash Barrier
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

Provision of an Reinforced cement concrete crash barrier at the


edges of the road, approaches to bridge structures and medians,
constructed with Reinforced Cement Concrete with fiber steel and as
Linear
A per details given IRC -5 (Fig.-5, b) including dowel bars 25 mm dia, 3,007.00 3,016.00
metre
450 mm long at expansion joints filled with premoulded asphalt filler
board etc., as per approved drawing and at locations directed by the
Engineer, all as specified. (Area-0.243 Sqm. /Meter, Single Face)

Provision of an Reinforced cement concrete crash barrier at the


edges of the road, approaches to bridge structures and medians,
constructed with Reinforced Cement Concrete with fiber steel and as
Linear
B per details given IRC -5 (Fig.-5, b) including dowel bars 25 mm dia, 3,228.00 3,238.00
metre
450 mm long at expansion joints filled with premoulded asphalt filler
board etc., as per approved drawing and at locations directed by the
Engineer, all as specified. (Area-0.261 Sqm. /Meter, Double Face)

CHAPTER-9
CULVERTS & BOX CELL

Excavation for Structures (Earth work in excavation of foundation of


structures as per drawing and technical specification, including
9.01 setting out, construction of shoring and bracing, removal of stumps
and other deleterious matter, dressing of sides and bottom and
backfilling with approved material.)

I Ordinary soil
A Manual Means
(i) upto 3 m depth cum 223.00 227.00
(ii) 3 m to 6 m depth cum 287.00 292.00
(iii) Above 6 m depth cum 382.00 389.00
B Mechanical Means
(i) Depth upto 3 m cum 111.00 117.00
(ii) Depth 3 m to 6 m cum 123.00 129.00
(iii) Depth above 6m cum 137.00 144.00
II Ordinary rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m cum 319.00 324.00
B Mechanical Means cum 681.00 732.00
III Hard rock ( requiring blasting )
A Manual Means cum 703.00 716.00
B Mechanical Means cum 344.00 352.00
IV Hard rock ( blasting prohibited )
A Mechanical Means cum 913.00 1,033.00
V Marshy soil
(i) upto 3 m depth
A Manual means cum 1,232.00 1,255.00
B Mechanical Means cum 417.00 433.00
Sand Filling in Foundation Trenches as per Drawing & Technical
9.02 cum 2,922.00 2,989.00
Specification

Plain cement concrete 1:3:6 nominal mix in foundation with crushed


9.03 stone aggregate 40 mm nominal size mechanically mixed, placed in cum 5,537.00 5,656.00
foundation and compacted by vibration including curing for 14 days.
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Laying Reinforced Cement Concrete Pipe NP4/prestrssed concrete
pipe on first class bedding in single row . (Laying Reinforced cement
concrete pipe NP4/prestrssed concrete pipe for culverts on first class
9.04 bedding of granular material in single row including fixing collar with
cement mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head walls and
parapets . )
A 1000 mm dia metre 8,233.00 8,385.00
B 1200 mm dia metre 9,159.00 9,328.00
C 1500 mm dia metre 10,628.00 11,025.00
Laying Reinforced Cement Concrete Pipe NP 4 /prestrssed concrete
pipe on first class bedding in double row . (Laying Reinforced cement
concrete pipe NP4 /prestrssed concrete pipe for culverts on first class
9.05 bedding of granular material in double row including fixing collar with
cement mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head walls and
parapets . )
A 1000 mm dia metre 17,093.00 17,410.00
B 1200 mm dia metre 18,990.00 19,342.00
C 1500 mm dia metre 22,389.00 22,804.00
Plain/Reinforced Cement Concrete in Open Foundation complete as
9.06
per Drawing and Technical Specifications.
A PCC Grade M15
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 7,309.00 7,506.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 7,682.00 7,870.00
B PCC Grade M20
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 7,756.00 7,948.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 8,129.00 8,326.00
C RCC Grade M20
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 7,799.00 7,991.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 8,195.00 8,393.00
D PCC Grade M25
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 8,119.00 8,318.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 8,488.00 8,692.00
E RCC Grade M25
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 8,337.00 8,540.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 8,734.00 8,942.00
Supplying, Fitting and Placing un-coated HYSD bar Reinforcement in
9.07 tonne 60,866.00 62,082.00
Foundation complete as per Drawing and Technical Specifications.

CHAPTER-10
MAINTENANCE OF ROADS

Restoration of Rain Cuts (Restoration of rain cuts with soil, moorum,


gravel or a mixture of these, clearing the loose soil, benching for 300
10.01 mm width, laying fresh material in layers not exceeding 250 mm and cum 177.00 182.00
compacting with plate compactor or power rammers to restore the
original alignment, levels and slopes)

Maintenance of Earthen Shoulder (filling with fresh soil) (Making up


loss of material/ irregularities on shoulder to the design level by
10.02 sqm 116.00 119.00
adding fresh approved soil and compacting it with appropriate
equipment.)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Maintenance of Earth Shoulder (stripping excess soil) (Stripping
10.03 excess soil from the shoulder surface to achieve the approved level sqm 44.00 45.00
and compacting with plate compactor)

Filling Pot- holes and Patch Repairs with open - graded Premix
surfacing, 20mm. (Removal of all failed material, trimming of
completed excavation to provide firm vertical faces, cleaning of
10.04 surface, painting of tack coat on the sides and base of excavation as sqm 182.00 186.00
per clause 503, back filling the pot holes with hot bituminous material
as per clause 510, compacting, trimming and finishing the surface to
form a smooth continuous surface, all as per clause 3004.2)

Filling Pot- holes and Patch Repairs with - Bituminous concrete,


40mm. (Removal of all failed material, trimming of completed
excavation to provide firm vertical faces, cleaning of surface,
10.05 painting of tack coat on the sides and base of excavation as per
clause 503, back filling the pot holes with hot bituminous material as
per clause 504, compacting, trimming and finishing the surface to
form a smooth continuous surface, all as per clause 3004.2)

(i) for grading I Material sqm 487.00 497.00


(ii) for grading II Material sqm 487.00 497.00
Crack Filling (Filling of crack using slow - curing bitumen emulsion
10.06 metre 5.00 5.00
and applying crusher dust in case crack are wider than 3mm.)
Dusting (Applying crusher dust to areas of road where bleeding of
10.07 sqm 4.00 4.00
excess bitumen has occurred.)
10.08 A Fog Seal (ref item 5.14) sqm 44.00 44.00
B Crack Prevention courses. (ref item 5.17)
(i) Stress Absorbing Membrane (SAM) crack width less than 6 mm sqm 75.00 77.00

(ii) Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm sqm 87.00 88.00
Stress Absorbing Membrane (SAM) crack width above 9 mm and
(iii) sqm 113.00 116.00
cracked area above 50 %
(iv) Bitumen Impregnated Geotextile sqm 146.00 148.00
C Slurry Seal (ref item 5.12)
(i) 5 mm thickness sqm 87.00 89.00
(ii) 3 mm thickness sqm 54.00 55.00
(iii) 1.5 mm thickness sqm 54.00 55.00
D Surface Dressing for maintance works. (ref item 5.06)
(i) 19 mm nominal chipping size sqm 116.00 118.00
(ii) 13 mm nominal size chipping sqm 90.00 92.00

Repair of joint Grooves with Epoxy Mortar Repair of spalled joint


10.09 grooves of contraction joints, longitudinal joints and expansion joints metre 1,044.00 1,063.00
in concrete pavements using epoxy mortar or epoxy concrete)

Repair of old Joints Sealant (Removal of existing sealant and re


10.10 sealing of contraction, longitudinal or expansion joints in concrete metre 49.00 49.00
pavement with fresh sealant material)
Hill Side Drain Clearance (Removal of earth from the choked hill side
10.11 metre 64.00 65.00
drain and disposing it on the valley side manually)
Land Slide Clearance in soil (Clearance of land slides in soil and
10.12 ordinary rock by a bull-dozer 175 HP and disposal of the same on the cum 107.00 109.00
valley side)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Land slide Clearance in Hard Rock Requiring Blasting (Clearing of
10.13 land slide in hard rock requiring blasting for 50% of the boulders and cum 169.00 172.00
disposal of the same on the valley side.)

Snow Clearance on Roads with Dozer (Snow clearance from road


10.14 cum 7.00 7.00
surface by a bull- dozer 165 Hp and disposing it on the valley side)

Snow Clearance on Roads with Snow Blowers (Snow clearance from


10.15 cum 10.00 11.00
road surface by a snow blower and disposing on the valley side.)
10.16 Replacement of metel beam crash barrier

Type- A, "W" : Metal Beam Crash Barrier Replacement of "W" metal


beam crash barrier comprising of 3mm thick corrugated sheet metal
beam rail, 70 cm above road / ground level, fixing on ISMC series
channel vertical post, 150x75x5 mm spaced 2m centre to centre,
Running
A 1.8m high, 1.1m below ground/road level, all steel parts and fitments 3,003.00 3,005.00
Metre
to be galvanised by hot dip process, all fittings to confirm to IS: 1367
and IS: 1364, metal beam rail to be fixed on the vertical post with a
spacer of channel section 150x75x5 mm, 330mm long complete as
per clause 811

Type- B, "Thrie" : Metal Beam Crash Barrier Replacement of "Thrie"


metal beam crash barrier comprising of 3mm thick corrugated sheet
metal beam rail, 85 cm above road / ground level, fixing on ISMC
series channel vertical post, 150x75x5 mm spaced 2m centre to
Running
B centre, 2m high, 1.15m below ground/road level, all steel parts and 4,004.00 4,096.00
Metre
fitments to be galvanised by hot dip process, all fittings to confirm to
IS: 1367 and IS: 1364, metal beam rail to be fixed on the vertical post
with a spacer of channel section 150x75x5 mm, 546mm long
complete as per clause 811

Network Survey Vehicle (NSV) attached with SUV(Data collection of


longitudinal profiling (International Roughness Index), Transverse
profiling (Rut Depth), Pavement Texture in term of Mean Profile
10.17 Depth, Road Geometry Data(cross slope, gradient, curvature), GPS KM 450.00 458.00
coordinates (X,Y,Z) viz. longitude, latitude & altitude, video imaging
for Roadside furniture/ Road Assets and Video imaging for Pavement
Surface Distresses and reports.)

10.18 Falling weight deflectometer (FWD) KM 450.00 458.00


10.19 Road Retro reflectometer attached with SUV KM 4,133.00 4,209.00
10.20 Automatic Vehicle Counter Classifier(ATCC) Location 147,706.00 147,706.00
CHAPTER-11
HORTICULTURE
Spreading of Sludge Farm Yard Manure or/and good Earth
(Spreading of sludge farm yard manure or/ and good earth in required
11.01 cum 42.00 43.00
thickness (cost of sludge, farm- yard manure or/and good earth to be
paid for separately))
Grassing with ' Doobs' Grass (Grassing with 'Doobs' grass including
watering and maintenance of the lawn for 30 days or more till the
11.02
grass forms a thick lawn free from weeds and fit for moving including
supplying good earth if needed)
(i) In rows 15 cm apart in either direction sqm 58.00 59.00
(ii) In rows 7.5 cm apart in either direction sqm 106.00 108.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

Making Lawns including Ploughing and Dragging with 'Swagha'


Breaking of Clod (Making lawns including ploughing and breaking of
11.03 clod, removal of rubbish, dressing and supplying doobs grass roots sqm 58.00 59.00
and planting at 15 cm apart, including supplying and spreading of
farm yard manure at rate of 0.18 cum per 100 sqm)

Maintenance of Lawns or Turfing of Slopes (Maintenance of lawns or


11.04 Turfing of slopes (rough grassing) for a period of one year sqm 260.00 265.00
including watering etc)

Turfing Lawns with Fine Grassing including Ploughing, Dressing


(Turfing lawns with fine grassing including ploughing, dressing
11.05 including breaking of clods, removal of rubbish, dressing and sqm 66.00 67.00
supplying doobs grass roots at 10 cm apart, including supplying and
spreading of farm yard manure at rate of0.6 cum per 100 sqm)

11.06 Maintenance of Lawns with Fine Grassing for the First Year sqm 314.00 320.00

a) Planting Permanent Hedges including Digging of Trenches


(Planting permanent hedges including digging of trenches, 60 cm
11.07 wide and 45 cm deep, refilling the excavated earth mixed with metre 315.00 321.00
farmyard manure, supplied at the rate of 4.65 cum per 100 metres
and supplying and planting hedge plants at 30 cm apart)

(b) Maintenance of Hedge for one year metre 285.00 290.00


11.08 a) Planting Flowering Plants and Shrubs in Central Verge km 113,387.00 115,487.00
Maintenance of Flowering Plants and Shrubs in Central Verge for one
(b) km 354,852.00 361,423.00
Year

Planting of Trees and their Maintenance for one Year (Planting of


trees by the road side (Avenue trees) in 0.60 m dia holes, 1 m deep
11.09 dug in the ground, mixing the soil with decayed farm yard/sludge each 1,748.00 1,780.00
mannure, planting the saplings, backfilling the trench, watering,
fixing the tree guard and maintaining the plants for one year)

Renovation Lawns including, Weeding, Forking the Ground, Top


Dressing with Forked Soil (Renovation lawns including, weeding,
forking the ground, top dressing with forked soil, watering and
11.10 maintenance the lawns, for 30 days or more, till the grass forms a sqm 26.00 26.00
thick lawn, free from weeds, and fit for moving and disposal of
rubbish as directed, including supplying good earth, if needed but
excluding the cost of well decayed farm yard manure)

Supply at Site Well Decayed Farm Yard Manure (Supply at site of


11.11 work well decayed farm yard manure, from any available source, cum 356.00 363.00
approved by the engineer in charge including screening and stacking)

Supply at Site of Work/ Store - Deoiled Neem Cake (Supply at site of


11.12 quintal 4,752.00 4,840.00
work/ store- deoiled neem cake duly packed in used gunny bags)

11.13 Supplying Sludge (Supplying sludge duly stacked at site/ store) cum 356.00 363.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

Half Brick Circular Tree Guard, in 2nd class Brick, internal diametre
1.25 metres, and height 1.2 metres, above ground and 0.20 metre
below ground (Half brick circular tree guard, in 2nd class brick,
internal diametre 1.25 metres, and height 1.2 metres, above ground
11.14 each 1,478.00 1,506.00
and 0.20 metre below ground, bottom two courses laid dry, and top
three courses in cement mortar 1:6 ( 1 cement 6 sand) and the
intermediate courses being in dry honey comb masonry, as per
design complete)

Edging with 2nd class Bricks, laid dry lengthwise (Edging with 2nd
class bricks, laid dry lengthwise, including excavation, refilling,
11.15 metre 29.00 29.00
consolidation, with a hand packing and spreading nearly surplus
earth within a lead of 50 metres)

Making Tree Guard 53 cm dia and 1.3 m high as per design from
empty bitumen drum (Making tree guard 53 cm dia and 1.3 m high as
per design from empty bitumen drum, slit suitably to permit sun and
11.16 each 686.00 699.00
air, (supplied by the department at stock issue rate) including
providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with rivets,
complete in all respect)

Making Tree Guard 53 cm dia and 2 metres high as per design from
empty bitumen drums (Making tree guard 53 cm dia and 2 metres
high as per design from empty bitumen drums, slit suitably to permit
11.17 sun and air, ( supplied by the department at stock issue rate) each 1,262.00 1,285.00
including providing and fixing four legs 40 cm long of 30 x 3 mm MS
riveted to tree guard and providing and fixing 2 nos MS sheet rings 50
x 0.5 mm with rivets complete in all respects)

Wrought Iron and Mild Steel Welded Work (Wrought iron and mild
steel welded work) (using angles, square bars, tees and channel
grills, grating frames, gates and tree guards of any size and design
11.18 quintal 11,635.00 11,851.00
etc. including cost of screens and welding rods or bolts and nuts
complete fixed in position but without the cost of excavation and
concrete for fixing which will be paid separately)

Tree Guard with MS Iron (Providing and fixing MS iron tree guard 60
cm dia and 2 metre high above ground level formed of 4 Nos (25 x 6
mm) and 8 Nos (25 x 3 mm) vertical MS riveted to 3 Nos (25 x 6 mm) each tree
11.19 2,932.00 2,987.00
iron rings in two halves, bolted together with 8 mm dia and 30 mm guard
long bolts including painting two coats with paint of approved brand
over a coat of priming, complete in all respects.)

Tree Guard with MS Angle Iron and Steel Wire (Providing and fixing
tree guard 0.60 metre square, 2.00 metre high fabricated with MS each tree
11.20 3,847.00 3,919.00
angle iron 30 x 30 x 3 mm, MS iron 25 x 3 mm and steel wire3 mm guard
dia welded and fabricated as per design in two halves bolted together)

Compensatory Afforestation (Planting trees as compensatory


afforestation at the rate of 290 trees per hectare at a spacing of 6 m
by grubbing and leveling the ground upto a depth of 150 mm, digging
11.21 hectare 239,972.00 244,416.00
holes 0.9 m dia, 1 m deep, mixing farm yard/sludge manure with soil,
planting of sapling 2 m high with 25 cm dia stem, backfilling the hole
and watering)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

Rain Water Harvesting Constructing rain water harvesting recharge


trench cum recharge shaft / well including grating passage joining
storm water drain and trench having brick walls, RCC cover slab and
filled with layers of filter media (size 75 mm to 100 mm), grating
having brick walls and CC 1:2:4 base and PVC pipe shaft packed with
11.21 No. 131,945.00 133,253.00
gravel, provided with wire screen and bottom plug complete as per
Drawing, direction of the Engineer and MORT&H Specifications
sections 300, 1000, 1300, 1500, 1600 & 1700. (Dimension of rain
water harvesting pit 6.5 m depth, 2.10 meter inner dia, wall width 375
mm and top slab thickness 150 mm)

CHAPTER-12
FOUNDATIONS

Excavation for Structures (Earth work in excavation of foundation of


structures as per drawing and technical specification, including
12.01 setting out, construction of shoring and bracing, removal of stumps
and other deleterious matter, dressing of sides and bottom and
backfilling with approved material.)

I Ordinary soil
A Manual Means
(i) upto 3 m depth cum 248.00 248.00
(ii) 3 m to 6 m depth cum 319.00 319.00
(iii) Above 6 m depth cum 425.00 425.00
B Mechanical Means
(i) Depth upto 3 m cum 123.00 128.00
(ii) Depth 3 m to 6 m cum 136.00 141.00
(iii) Depth above 6m cum 152.00 158.00
II Ordinary rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m cum 354.00 354.00
B Mechanical Means cum 757.00 798.00
III Hard rock ( requiring blasting )
A Manual Means cum 380.00 389.00
IV Hard rock ( blasting prohibited )
A Mechanical Means cum 1,015.00 1,043.00
V Marshy soil
(i) upto 3 m depth
A Manual means cum 1,369.00 1,369.00
B Mechanical Means cum 463.00 472.00
VI Back Filling in Marshy Foundation Pits cum 1,180.00 1,180.00
Filling Annular Space Around Footing in Rock (Lean cement concrete
12.02 cum 6,152.00 6,170.00
1:3:6 nominal mix. Rate may be taken as per items 12.4.)
Sand Filling in Foundation Trenches as per Drawing & Technical
12.03 cum 3,259.00 3,275.00
Specification

PCC 1:3:6 in Foundation, Plain cement concrete 1:3:6 nominal mix in


foundation with crushed stone aggregate 40 mm nominal size
12.04 cum 6,152.00 6,170.00
mechanically mixed, placed in foundation and compacted by vibration
including curing for 14 days.

Brick masonry work in cement mortar 1:3 in foundation complete


12.05 excluding pointing and plastering, as per drawing and technical cum 6,061.00 6,098.00
specifications
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
12.06 A Cement mortar1:3 (1cement :3 sand) cum 6,765.00 6,765.00
B Cement mortar1:2 (1cement :2 sand) cum 7,517.00 7,517.00
C Cement mortar1:4 (1cement :4 sand) cum 6,244.00 6,244.00
D Cement mortar1:6 (1cement :6 sand) cum 6,056.00 6,056.00
Stone masonry work in cement mortar 1:3 in foundation complete as
12.07
drawing and Technical Specification
(a) Square Rubble Coursed rubble masonry( first sort ) cum 6,604.00 6,604.00
(b) Random Rubble Masonry cum 5,926.00 5,926.00
Plain/Reinforced cement concrete in open foundation complete as
12.08
per drawing and technical specifications
A PCC Grade M15
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 7,678.00 7,728.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 8,070.00 8,118.00
B PCC Grade M20
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 8,148.00 8,197.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 8,540.00 8,587.00
C RCC Grade M20
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 8,550.00 8,599.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 8,966.00 9,014.00
D PCC Grade M25
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 8,525.00 8,575.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 8,917.00 8,965.00
E RCC Grade M25
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 8,759.00 8,808.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 9,175.00 9,222.00
F PCC Grade M30
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 8,561.00 8,610.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 8,953.00 9,000.00
G RCC Grade M30
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 8,878.00 8,927.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 9,294.00 9,342.00
H RCC Grade M35
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 9,089.00 9,139.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 9,506.00 9,553.00
I RCC Grade M40
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 9,547.00 9,596.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 9,963.00 10,010.00
J RCC Grade M45
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 9,744.00 9,794.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 10,161.00 10,208.00
WELL FOUNDATION(Providing and constructing temporary island 16
12.09
m diameter for construction of well foundation for 8m dia. Well.)

A Assuming depth of water 1.0 m and height of island to be 1.25m. each 319,415.00 319,415.00
B Assuming depth of water 4.0 m and height of island 4.5 m. each 1,091,423.00 1,091,423.00
Providing and constructing one span service road to reach island
C metre 4,599.00 4,599.00
location from one pier location to another pier location

Providing and laying cutting edge of mild steel weighing 40 kg per


12.10 metre for well foundation complete as per drawing and technical tonne 135,715.00 135,757.00
specification.
Plain/Reinforced cement concrete, in well foundation complete as per
12.11
drawing and technical specification
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
A Well curb
(i) RCC M20 Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 9,113.00 9,113.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 9,519.00 9,519.00
(ii) RCC M25 Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 9,766.00 9,766.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 10,172.00 10,172.00
(iii) RCC M30Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 9,904.00 9,904.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 10,310.00 10,310.00
(iv) RCC M35 Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 10,148.00 10,148.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 10,554.00 10,554.00
(v) RCC M40Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 10,675.00 10,675.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 11,081.00 11,081.00
B Well steining
(I) PCC M15 Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 7,810.00 7,810.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 8,208.00 8,208.00
(ii) PCC M20 Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 8,306.00 8,306.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 8,704.00 8,704.00
(iii) RCC M20 Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 8,354.00 8,354.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 8,726.00 8,726.00
(iv) PCC M25 Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 8,706.00 8,706.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 9,104.00 9,104.00
(v) RCC M25 Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 8,952.00 8,952.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 9,324.00 9,324.00
(vi) PCC M30 Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 8,743.00 8,743.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 9,141.00 9,141.00
(vii) RCC M30 Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 9,079.00 9,079.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 9,451.00 9,451.00
(viii) RCC M35 Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 9,302.00 9,302.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 9,674.00 9,674.00
(ix) RCC M40 Grade
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 9,786.00 9,786.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 10,158.00 10,158.00
C Bottom Plug
(i) PCC Grade M20
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 7,961.00 7,961.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 8,392.00 8,392.00
(ii) PCC Grade M25
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 8,342.00 8,342.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 8,773.00 8,773.00
(iii) PCC Grade M30
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 8,378.00 8,378.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 8,809.00 8,809.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
(iv) PCC Grade M35
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 8,771.00 8,771.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 9,202.00 9,202.00
D Intermediate plug
(i) Grade M20 PCC
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 7,583.00 7,583.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 7,993.00 7,993.00
(ii) Grade M25 PCC
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 7,946.00 7,946.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 8,356.00 8,356.00
(iii) Grade M30 PCC
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 7,981.00 7,981.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 8,390.00 8,390.00
E Top plug
(i) Grade M15 PCC
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 7,384.00 7,432.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 7,760.00 7,806.00
(ii) Grade M20 PCC
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 7,836.00 7,883.00
Case II With Batching Plant, Transit Mixer and Manual placing 8,212.00 8,258.00
(iii) Grade M25 PCC
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 8,199.00 8,246.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 8,575.00 8,621.00
(iv) Grade M30 PCC
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 8,233.00 8,280.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 8,609.00 8,655.00
F Well cap
(i) RCC Grade M20
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 8,197.00 8,246.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 8,568.00 8,616.00
(ii) RCC Grade M25
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 8,763.00 8,812.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 9,134.00 9,181.00
(iii) RCC Grade M30
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 8,882.00 8,931.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 9,253.00 9,301.00
(iv) RCC Grade M35
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 9,089.00 9,139.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 9,465.00 9,512.00
(v) RCC M40 Grade cum
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 9,551.00 9,600.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 9,922.00 9,969.00
(vi) RCC M40 Grade cum
Case I With Batching Plant, Transit Mixer and Concrete Pump cum 9,748.00 9,798.00
Case II With Batching Plant, Transit Mixer and Manual placing cum 10,120.00 10,167.00

Sinking of 6 m external diameter well ( other than pneumatic method


of sinking ) through all types of strata namely sandy soil, clayey soil
12.12
and rock as shown against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned from bed level.

A Sandy soil
(i) Depth below bed level upto 3.0 M metre 5,651.00 5,651.00
(ii) Beyond 3m upto 10m depth metre 7,858.00 7,858.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
(iii) Beyond 10m upto 20m
a Add for every additional meter depth of sinking metre 10,379.00 10,379.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 19,471.00 19,471.00
Add 20% of cost for Kentledge including supports, loading
b metre 3,894.00 3,894.00
arrangement and Labour .
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 46,262.00 46,262.00
Add 20% of cost for Kentledge including supports, loading
b metre 9,253.00 9,253.00
arrangement and Labour .
B Clayey soil ( 6m dia. Well )
(i) Depth below bed level upto 3.0 M metre 7,841.00 7,841.00
(ii) Beyond 3m upto 10m depth metre 17,499.00 17,499.00
(iii) Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of
a metre 23,112.00 23,112.00
sinking for the previous meter
b Add for dewatering @ 5% of cost, if required. metre 1,156.00 1,156.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 43,352.00 43,352.00
b Add 5% of cost for dewatering of the cost, if required metre 2,168.00 2,168.00
Add 25% of cost for Kentledge including supports, loading
c metre 10,838.00 10,838.00
arrangement and Labour ).
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 102,998.00 102,998.00
b Add 5% of cost for dewatering, if required metre 5,150.00 5,150.00
Add 20% of cost for Kentledge including supports, loading
c metre 20,600.00 20,600.00
arrangement and Labour).
C Soft rock (6m dia well )
Extra over item no. 12.12 (A) & (B) irrespective of depth for sinking in
(i) metre 43,682.00 43,682.00
Soft Rock
D Hard rock (6m dia well )
Extra over item no. 12.12 (A) & (B) irrespective of depth for sinking in
(i) metre 44,573.00 44,573.00
Soft Rock
E Bouldery strata(6m dia well )
Extra over item no. 12.12 (A) & (B) irrespective of depth for sinking in
(i) metre 32,480.00 32,480.00
rock bouldery strata

Sinking of 7 m external diameter well ( other than pneumatic method


of sinking ) through all types of strata namely sandy soil, clayey soil
12.13
and rock as shown against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned from bed level.

A Sandy soil
(i) Depth below bed level upto 3.0 M metre 16,510.00 16,510.00
(ii) Beyond 3m upto 10m depth metre 10,859.00 10,859.00
(iii) Beyond 10m upto 20m metre 14,342.00 14,342.00
a Add for every additional meter depth of sinking metre 717.00 717.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 26,902.00 26,902.00
Add 20% of cost for Kentledge including supports, loading
b metre 5,381.00 5,381.00
arrangement and Labour) .
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 63,918.00 63,918.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Add 20% of cost for Kentledge including supports, loading
b metre 12,784.00 12,784.00
arrangement, and Labour etc.
B Clayey soil ( 7m dia. Well )
(I) Depth below bed level upto 3.0 M metre 10,859.00 10,859.00
(ii) Beyond 3m upto 10m depth metre 17,448.00 17,448.00
(iii) Beyond 10 m upto 20 m
a Add for every additional meter depth of sinking metre 23,043.00 23,043.00
b Add for dewatering @ 5% of cost, if required. metre 1,152.00 1,152.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 43,222.00 43,222.00
b Add 5% of cost for dewatering on the cost, if required metre 2,161.00 2,161.00
Add 25% of cost for Kentledge including supports, loading
c metre 10,806.00 10,806.00
arrangement and Labour ).
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 102,691.00 102,691.00
b Add 5% of cost for dewatering, if required metre 5,135.00 5,135.00
Add 20% of cost for Kentledge including supports, loading
c metre 20,538.00 20,538.00
arrangement and Labour).
C Soft rock (7 m dia well )
Extra over item no. 12.13 (A) & (B) irrespective of depth for sinking in
(i) metre 55,683.00 55,683.00
Soft Rock
D Hard rock (7 m dia well )
Extra over item no. 12.13(A) & (B) irrespective of depth for sinking in
(i) metre 57,401.00 57,401.00
Soft Rock
E Bouldery strata(7 m dia well )
Extra over item no. 12.13 (A) & (B) irrespective of depth for sinking in
(i) metre 80,118.00 80,118.00
rock bouldery strata

Sinking of 8 m external diameter well ( other than pneumatic method


of sinking ) through all types of strata namely sandy soil, clayey soil
12.14
and rock as shown against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned from bed level.

A Sandy soil
(i) Depth below bed level upto 3.0 M metre 10,065.00 10,065.00
(ii) Beyond 3m upto 10m depth metre 12,272.00 12,272.00
(iii) Beyond 10m upto 20m
a Add for every additional meter depth of sinking metre 16,206.00 16,206.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 30,395.00 30,395.00
Add 20% of cost for Kentledge including supports, loading
b metre 6,079.00 6,079.00
arrangement and Labour .
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 72,214.00 72,214.00
Add 20% of cost for Kentledge including supports, loading
b metre 14,443.00 14,443.00
arrangement, and Labour etc.
B Clayey soil ( 8m dia. Well )
(i) Depth upto 3.0 M metre 13,261.00 13,261.00
(ii) Beyond 3m upto 10m depth metre 18,472.00 18,472.00
(iii) Beyond 10 m upto 20 m
a Add for every additional meter depth of sinking metre 24,397.00 24,397.00
b Add for dewatering @ 5% of cost, if required. metre 1,220.00 1,220.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 45,763.00 45,763.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
b Add 5% of cost for dewatering on the cost, if required metre 2,288.00 2,288.00
Add 25% of cost for Kentledge including supports, loading
c metre 11,441.00 11,441.00
arrangement and Labour ).
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 108,726.00 108,726.00
b Add 5% of cost for dewatering, if required metre 5,436.00 5,436.00
Add 20% of cost for Kentledge including supports, loading
c metre 21,745.00 21,745.00
arrangement and Labour).
C Soft rock (8 m dia well )
Extra over item no. 12.14 (A) & (B) irrespective of depth for sinking in
(i) metre 69,278.00 69,278.00
Soft Rock
D Hard rock (8 m dia well )
Extra over item no. 12.14 (A) & (B) irrespective of depth for sinking in
(i) metre 73,385.00 73,385.00
Soft Rock
E Bouldery strata(8 m dia well )
Extra over item no. 12.14 (A) & (B) irrespective of depth for sinking in
(i) metre 101,693.00 101,693.00
rock bouldery strata

Sinking of 9 m external diameter well ( other than pneumatic method


of sinking ) through all types of strata namely sandy soil, clayey soil
12.15
and rock as shown against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned from bed level.

A Sandy soil
(i) Depth below bed level upto 3.0 M metre 10,276.00 10,276.00
(ii) Beyond 3m upto 10m depth metre 13,489.00 13,489.00
(iii) Beyond 10m upto 20m
a Add for every additional meter depth of sinking metre 17,816.00 17,816.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 33,419.00 33,419.00
Add 20% of cost for Kentledge including supports, loading
b metre 6,684.00 6,684.00
arrangement and Labour .
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 79,397.00 79,397.00
Add 20% of cost for Kentledge including supports, loading
b metre 15,880.00 15,880.00
arrangement, and Labour etc.
B Clayey soil ( 9m dia. Well )
(i) Depth below bed level upto 3.0 M metre 14,064.00 14,064.00
(ii) Beyond 3m upto 10m depth metre 19,917.00 19,917.00
(iii) Beyond 10 m upto 20 m
a Add for every additional meter depth of sinking metre 26,305.00 26,305.00
b Add for dewatering @ 5% of cost, if required. metre 1,315.00 1,315.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 49,341.00 49,341.00
b Add 5% of cost for dewatering on the cost, if required metre 2,467.00 2,467.00
Add 25% of cost for Kentledge including supports, loading
c metre 12,335.00 12,335.00
arrangement and Labour ).
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 117,228.00 117,228.00
b Add 5% of cost for dewatering, if required metre 5,862.00 5,862.00
Add 20% of cost for Kentledge including supports, loading
c metre 23,445.00 23,445.00
arrangement and Labour).
C Soft rock (9 m dia well )
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Extra over item no. 12.15 (A) & (B) irrespective of depth for sinking in
(i) metre 84,470.00 84,470.00
Soft Rock
D Hard rock (9 m dia well )
Extra over item no. 12.15(A) & (B) irrespective of depth for sinking in
(i) metre 76,144.00 76,144.00
Soft Rock
E Bouldery strata (9 m dia well )
Extra over item no. 12.15 (A) & (B) irrespective of depth for sinking in
(i) metre 125,927.00 125,927.00
rock bouldery strata

Sinking of 10 m external diameter well ( other than pneumatic method


of sinking ) through all types of strata namely sandy soil, clayey soil
12.16
and rock as shown against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned from bed level.

A Sandy soil
(i) Depth below bed level upto 3.0 M metre 12,077.00 12,077.00
(ii) Beyond 3m upto 10m depth metre 14,293.00 14,293.00
(iii) Beyond 10m upto 20m
a Add for every additional meter depth of sinking metre 18,877.00 18,877.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 35,408.00 35,408.00
Add 20% of cost for Kentledge including supports, loading
b metre 7,082.00 7,082.00
arrangement and Labour .
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 84,126.00 84,126.00
Add 20% of cost for Kentledge including supports, loading
b metre 16,825.00 16,825.00
arrangement, and Labour etc.
B Clayey soil (10m dia. Well )
(i) Depth below bed level upto 3.0 M metre 16,139.00 16,139.00
(ii) Beyond 3m upto 10m depth metre 20,163.00 20,163.00
(iii) Beyond 10 m upto 20 m
a Add for every additional meter depth of sinking metre 26,630.00 26,630.00
b Add for dewatering @ 5% of cost, if required. metre 1,332.00 1,332.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 49,951.00 49,951.00
'b Add 5% of cost for dewatering on the cost, if required metre 2,498.00 2,498.00
Add 25% of cost for Kentledge including supports, loading
c metre 12,488.00 12,488.00
arrangement and Labour ).
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 118,675.00 118,675.00
b Add 5% of cost for dewatering, if required metre 5,934.00 5,934.00
Add 20% of cost for Kentledge including supports, loading
c 23,735.00 23,735.00
arrangement and Labour).
C Soft rock (10 m dia well )
Extra over item no. 12.16 (A) & (B) irrespective of depth for sinking in
(i) metre 101,257.00 101,257.00
Soft Rock
D Hard rock (10 m dia well )
Extra over item no. 12.16 (A) & (B) irrespective of depth for sinking in
(i) metre 96,900.00 96,900.00
Soft Rock
E Bouldery strata (10 m dia well )
Extra over item no. 12.16 (A) & (B) irrespective of depth for sinking in
(i) metre 152,820.00 152,820.00
rock bouldery strata
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

Sinking of 11 m external diameter well ( other than pneumatic method


of sinking ) through all types of strata namely sandy soil, clayey soil
12.17
and rock as shown against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned from bed level.

A Sandy soil
(i) Depth from bed level upto 3.0 M metre 26,992.00 26,992.00
(ii) Beyond 3m upto 10m depth metre 23,450.00 23,450.00
(iii) Beyond 10m upto 20m
a Add for every additional meter depth of sinking metre 30,969.00 30,969.00
(iv) Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of
a metre 58,091.00 58,091.00
sinking for the previous meter
Add 20% of cost for Kentledge including supports, loading
b metre 11,618.00 11,618.00
arrangement and Labour .
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 138,015.00 138,015.00
Add 20% of cost for Kentledge including supports, loading
b metre 27,603.00 27,603.00
arrangement, and Labour etc.
B Clayey soil (11 m dia. Well )
(i) Depth from bed level upto 3.0 M metre 26,559.00 26,559.00
(ii) Beyond 3m upto 10m depth metre 41,983.00 41,983.00
(iii) Beyond 10 m upto 20 m
a Add for every additional meter depth of sinking metre 55,446.00 55,446.00
b Add for dewatering @ 5% of cost, if required. metre 2,772.00 2,772.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 104,002.00 104,002.00
b Add 5% of cost for dewatering on the cost, if required metre 5,200.00 5,200.00
Add 25% of cost for Kentledge including supports, loading
c metre 26,001.00 26,001.00
arrangement and Labour ).
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 247,093.00 247,093.00
b Add 5% of cost for dewatering, if required metre 12,355.00 12,355.00
Add 20% of cost for Kentledge including supports, loading
c metre 49,419.00 49,419.00
arrangement and Labour).
C Soft rock (11 m dia well )
Extra over item no. 12.17(A) & (B) irrespective of depth for sinking in
(i) metre 119,640.00 119,640.00
Soft Rock
D Hard rock (11 m dia well )
Extra over item no. 12.17 (A) & (B) irrespective of depth for sinking in
(i) metre 112,786.00 112,786.00
Soft Rock
E Bouldery strata (11 m dia well )
Extra over item no. 12.17 (A) & (B) irrespective of depth for sinking in
(i) metre 182,373.00 182,373.00
rock bouldery strata

Sinking of 12 m external diameter well ( other than pneumatic method


of sinking ) through all types of strata namely sandy soil, clayey soil
12.18
and rock as shown against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned from bed level.

A Sandy soil
(i) I) Depth below bed level upto 3.0 M metre 57,135.00 57,135.00
(ii) Beyond 3m upto 10m depth metre 65,191.00 65,191.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
(iii) Beyond 10m upto 20m
a Add for every additional meter depth of sinking metre 86,097.00 86,097.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 161,496.00 161,496.00
Add 20% of cost for Kentledge including supports, loading
b metre 32,299.00 32,299.00
arrangement and Labour .
(v) Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of
a metre 383,691.00 383,691.00
sinking for the previous meter
Add 20% of cost for Kentledge including supports, loading
b metre 76,738.00 76,738.00
arrangement, and Labour etc.
B Clayey soil (12 m dia. Well )
(i) Depth below bed level upto 3.0 M metre 64,314.00 64,314.00
(ii) Beyond 3m upto 10m depth metre 101,308.00 101,308.00
(iii) Beyond 10 m upto 20 m
a Add for every additional meter depth of sinking metre 133,796.00 133,796.00
b Add for dewatering @ 5% of cost, if required. metre 6,690.00 6,690.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 250,967.00 250,967.00
b Add 5% of cost for dewatering on the cost, if required metre 12,548.00 12,548.00
Add 25% of cost for Kentledge including supports, loading
c metre 62,742.00 62,742.00
arrangement and Labour ).
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 596,260.00 596,260.00
b Add 5% of cost for dewatering, if required metre 29,813.00 29,813.00
Add 20% of cost for Kentledge including supports, loading
c metre 119,252.00 119,252.00
arrangement and Labour).
C Soft rock (12 m dia well )
Extra over item no. 12.18 (A) & (B) irrespective of depth for sinking in
(i) metre 139,619.00 139,619.00
Soft Rock
D Hard rock (12 m dia well )
Extra over item no. 12.18 (A) & (B) irrespective of depth for sinking in
(i) metre 130,048.00 130,048.00
Soft Rock
E Bouldery strata (12 m dia well )
Extra over item no. 12.18 (A) & (B) irrespective of depth for sinking in
(i) metre 214,586.00 214,586.00
rock bouldery strata

Sinking of Twin D Type well ( other than pneumatic method of


sinking ) through all types of strata namely sandy soil, clayey soil and
12.19
rock as shown against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned from bed level.

A Sandy soil
(i) Depth from bed level upto 3.0 M metre 12,888.00 12,888.00
(ii) Beyond 3m upto 10m depth metre 13,898.00 13,898.00
(iii) Beyond 10m upto 20m
a Add for every additional meter depth of sinking metre 18,355.00 18,355.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 34,429.00 34,429.00
Add 20% of cost for Kentledge including supports, loading
b metre 6,886.00 6,886.00
arrangement and Labour .
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 81,797.00 81,797.00
Add 20% of cost for Kentledge including supports, loading
b metre 16,359.00 16,359.00
arrangement, and Labour etc.
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
B Clayey soil (Twin D Type Well )
(i) Depth below bed level upto 3.0 M metre 15,265.00 15,265.00
(ii) Beyond 3m upto 10m depth metre 22,365.00 22,365.00
(iii) Beyond 10 m upto 20 m
a Add for every additional meter depth of sinking metre 29,538.00 29,538.00
b Add for dewatering @ 5% of cost, if required. metre 1,477.00 1,477.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 55,406.00 55,406.00
b Add 5% of cost for dewatering on the cost, if required metre 2,770.00 2,770.00
Add 25% of cost for Kentledge including supports, loading
c metre 13,852.00 13,852.00
arrangement and Labour ).
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 131,638.00 131,638.00
b Add 5% of cost for dewatering, if required metre 6,582.00 6,582.00
Add 20% of cost for Kentledge including supports, loading
c metre 26,328.00 26,328.00
arrangement and Labour).
C Soft rock (Twin D Type well )
Extra over item no. 12.19 (A) & (B) irrespective of depth for sinking in
(i) metre 85,138.00 85,138.00
Soft Rock
D Hard rock (Twin D Type well )
Extra over item no. 12.19(A) & (B) irrespective of depth for sinking in
(i) metre 83,722.00 83,722.00
Soft Rock
E Bouldery strata (Twin D Type well )
Extra over item no. 12.19 (A) & (B) irrespective of depth for sinking in
(i) metre 61,745.00 61,745.00
rock bouldery strata

Pneumatic sinking of wells with equipment of approved design,


drawing and specifications worked by competent and trained
personnel and comprising of compression and decompression
chambers, reducers, two air locks separately for men and plant &
materials, arrangement for supply of fresh air to working chambers,
check valves, exhaust valves, shafts made from steel plates of riveted
12.20 construction not less than 6 mm thick to withstand an air pressure of 183,813.00 183,889.00
0.50 MPa, controlled blasting of hard rock where required, staircases
and 1 m wide landing plateforms with railing, arrangement for
compression and decompression, electric lighting of 50 V maximum,
proper rooms for rest and medical examinations and compliance with
safety precautions as per IS:4138, all as per clause1208.8 of MoRTH
Specifications.

Sand filling in wells complete as per drawing and technical


12.21 cum 2,658.00 2,658.00
specifications
Providing steel liner 10 mm thick for curbs and 6mm thick for steining
12.22 tonne 123,384.00 123,384.00
of wells including fabricating and setting out as per detailed drawing

Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement


complete as per drawing and technical specifications and removal of
12.23 metre 11,676.00 11,708.00
excavated earth with all lifts and lead upto 1000 m. (Pile diameter-750
mm)
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement
complete as per drawing and technical specifications and removal of
12.24 metre 15,689.00 15,747.00
excavated earth with all lifts and lead upto 1000 m. (Pile diameter-
1000 mm)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement
complete as per drawing and technical specifications and removal of
12.25 metre 20,776.00 20,860.00
excavated earth with all lifts and lead upto 1000 m. (Pile diameter-
1200 mm)
Bored cast-in-situ M35 grade R.C.C. Pile excluding Reinforcement
complete as per Drawing and Technical Specifications and removal of
12.26 metre 29,263.00 29,394.00
excavated earth with all lifts and lead upto 1000 m. (Pile diameter-
1500 mm)
Driven cast-in-place vertical M35 grade R.C.C. piles excluding
12.27 reinforcement complete as per drawing and & Technical Specification metre 8,729.00 8,751.00
(Pile diameter - 750 mm)
Driven cast-in-place vertical M35 grade R.C.C. piles excluding
12.28 reinforcement complete as per drawing and & Technical Specification metre 13,471.00 13,510.00
(Pile diameter - 1000 mm)
Driven cast-in-place vertical M35 grade R.C.C. piles excluding
12.29 reinforcement complete as per drawing and & Technical Specification metre 19,758.00 19,815.00
(Pile diameter - 1500 mm)
Driven precast vertical M35 grade R.C.C. piles excluding
12.30 reinforcement complete as per drawing and & Technical Specification metre 5,108.00 5,118.00
(Pile Diameter=500 mm)
Driven precast vertical M35 grade R.C.C. piles excluding
12.31 reinforcement complete as per drawing and & Technical Specification metre 8,012.00 8,034.00
(Pile Diameter=750 mm)
Driven precast vertical M35 grade R.C.C. piles excluding
12.32 reinforcement complete as per drawing and & Technical Specification metre 13,061.00 13,100.00
(Pile Diameter=1000 mm)
Driven precast vertical M35 grade R.C.C. piles excluding
12.33 reinforcement complete as per drawing and & Technical Specification metre 4,083.00 4,088.00
(Size of pile - 300 mm x 300 mm)
Driven precast vertical M35 grade R.C.C. piles excluding
12.34 reinforcement complete as per drawing and & Technical Specification metre 6,082.00 6,095.00
(Size of pile - 500 mm x 500 mm)
Driven precast vertical M35 grade R.C.C. piles excluding
12.35 reinforcement complete as per drawing and & Technical Specification metre 9,913.00 9,942.00
(Size of pile - 750 mm x 750 mm)
Driven vertical steel piles complete as per drawing and & Technical
12.36 Specification (Section of the pile - H Section steel column 400 x 250 metre 9,721.00 9,721.00
mm (ISHB Series) )
Driven vertical steel piles complete as per drawing and & Technical
12.37 Specification (Section of the pile - H Section steel column 450 x 250 metre 10,894.00 10,894.00
mm (ISHB Series) )
Pile load test on single vertical pile in accordance with IS:2911(Part-
12.38
IV)
a) Initial and routine load test tonne 300.00 300.00
b) Lateral load test tonne 500.00 500.00
Dismantling of Reinforced Concrete Pile head complete as per
12.39 cum 1,933.00 1,977.00
Drawing and Technical Specification
Cement concrete for reinforced concrete in pile cap complete as per
12.40
drawing and Technical Specification
A RCC Grade M20
(i) With Batching Plant, Transit Mixer and Concrete Pump cum 7,856.00 7,856.00
(ii) With Batching Plant, Transit Mixer and Manual placing cum 7,903.00 7,903.00
B RCC Grade M25
(i) With Batching Plant, Transit Mixer and Concrete Pump cum 8,422.00 8,422.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
(ii) With Batching Plant, Transit Mixer and Manual placing cum 8,469.00 8,469.00
C RCC Grade M30
(i) With Batching Plant, Transit Mixer and Concrete Pump cum 8,541.00 8,541.00
(ii) With Batching Plant, Transit Mixer and Manual placing cum 8,588.00 8,588.00
D RCC Grade M35
(i) With Batching Plant, Transit Mixer and Concrete Pump cum 8,751.00 8,751.00
(ii) With Batching Plant, Transit Mixer and Manual placing cum 8,798.00 8,798.00
E RCC Grade M40
(i) With Batching Plant, Transit Mixer and Concrete Pump cum 9,209.00 9,209.00
(ii) With Batching Plant, Transit Mixer and Manual placing cum 9,256.00 9,256.00
F RCC Grade M45
(i) With Batching Plant, Transit Mixer and Concrete Pump cum 9,406.00 9,406.00
(ii) With Batching Plant, Transit Mixer and Manual placing cum 9,453.00 9,453.00
12.41 Levelling course for Pile cap
(i) With Batching Plant, Transit Mixer and Concrete Pump cum 7,383.00 7,431.00
(ii) With Batching Plant, Transit Mixer and Manual placing cum 7,760.00 7,805.00
Supplying, fitting and placing un-coated HYSD bar reinforcement in
12.42 tonne 68,094.00 68,191.00
foundation complete as per drawing and technical specifications

Supplying, fitting and placing un-coated Mild steel reinforcement


12.43 tonne 92,085.00 92,182.00
complete in foundation as per drawing and technical specification
CHAPTER-13
SUB-STRUCTURE
Brick masonry work in 1:3 in sub-structure complete excluding
13.01 cum 5,734.00 5,773.00
pointing and plastering, as per drawing and technical specifications
Pointing with cement mortar (1:3 ) on brick work in substructure as per
13.02 sqm 102.00 102.00
Technical specifications
Plastering with cement mortar (1:3 ) on brick work in sub-structure as
13.03 sqm 187.00 186.00
per Technical specifications
Stone masonry work in cement mortar 1:3 for substructure complete
13.04
as per drawing and Technical Specifications
A Random Rubble Masonry cum 7,544.00 7,616.00
B Coursed rubble masonry (first sort ) cum 8,050.00 8,123.00
C Ashlar masonry ( first sort ) cum 10,002.00 10,075.00
Plain/Reinforced cement concrete in sub-structure complete as per
13.05
drawing and technical specifications
A PCC Grade M15
(p) Height upto 5m cum 8,121.00 8,174.00
B PCC Grade M20
(p) Height upto 5m cum 8,618.00 8,670.00
C PCC Grade M25
(p) Height upto 5m
With Batching Plant, Transit Mixer and Concrete Pump cum 9,017.00 9,069.00
(q) Height 5m to 10m
With Batching Plant, Transit Mixer and Concrete Pump cum 9,345.00 9,399.00
(r) Height above 10m
With Batching Plant, Transit Mixer and Concrete Pump cum 9,755.00 9,812.00
D PCC Grade M30
(p) Height upto 5m
With Batching Plant, Transit Mixer and Concrete Pump cum 9,055.00 9,107.00
(q) Height 5m to 10m
With Batching Plant, Transit Mixer and Concrete Pump cum 9,384.00 9,438.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
(r) Height above 10m
With Batching Plant, Transit Mixer and Concrete Pump cum 9,796.00 9,852.00
E RCC Grade M20
(p) Height upto 5m
With Batching Plant, Transit Mixer and Concrete Pump cum 8,666.00 8,718.00
(q) Height 5m to 10m
With Batching Plant, Transit Mixer and Concrete Pump cum 8,981.00 9,035.00
(r) Height above 10m
With Batching Plant, Transit Mixer and Concrete Pump cum 9,375.00 9,447.00
F RCC Grade M25
(p) Height upto 5m
With Batching Plant, Transit Mixer and Concrete Pump cum 9,264.00 9,316.00
(q) Height 5m to 10m
With Batching Plant, Transit Mixer and Concrete Pump cum 9,567.00 9,621.00
(r) Height above 10m
With Batching Plant, Transit Mixer and Concrete Pump cum 10,022.00 10,078.00
G RCC Grade M30
(p) Height upto 5m
With Batching Plant, Transit Mixer and Concrete Pump cum 9,390.00 9,442.00
(q) Height 5m to 10m
With Batching Plant, Transit Mixer and Concrete Pump cum 9,655.00 9,709.00
(r) Height above 10m
With Batching Plant, Transit Mixer and Concrete Pump cum 10,030.00 10,086.00
H RCC Grade M35
(p) Height upto 5m
With Batching Plant, Transit Mixer and Concrete Pump cum 9,614.00 9,666.00
(q) Height 5m to 10m
With Batching Plant, Transit Mixer and Concrete Pump cum 9,824.00 9,877.00
(r) Height above 10m
With Batching Plant, Transit Mixer and Concrete Pump cum 10,138.00 10,193.00
I RCC Grade M40
(p) Height upto 5m
With Batching Plant, Transit Mixer and Concrete Pump cum 10,097.00 10,150.00
(q) Height 5m to 10m
With Batching Plant, Transit Mixer and Concrete Pump cum 10,318.00 10,371.00
(r) Height above 10m
With Batching Plant, Transit Mixer and Concrete Pump cum 10,648.00 10,703.00
J RCC Grade M45
(p) Height upto 5m
With Batching Plant, Transit Mixer and Concrete Pump cum 10,306.00 10,359.00
(q) Height 5m to 10m
With Batching Plant, Transit Mixer and Concrete Pump cum 10,531.00 10,585.00
(r) Height above 10m
With Batching Plant, Transit Mixer and Concrete Pump cum 10,869.00 10,924.00
K RCC Grade M50
(p) Height upto 5m
With Batching Plant, Transit Mixer and Concrete Pump cum 11,147.00 11,199.00
(q) Height 5m to 10m
With Batching Plant, Transit Mixer and Concrete Pump cum 11,390.00 11,444.00
(r) Height above 10m
With Batching Plant, Transit Mixer and Concrete Pump cum 11,755.00 11,810.00
Supplying, fitting and placing HYSD bar reinforcement in sub-
13.06 tonne 68,419.00 68,517.00
structure complete as per drawing and technical specifications
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

Supplying, fitting and placing Mild steel reinforcement complete in


13.07 tonne 92,411.00 92,508.00
sub-structure as per drawing and technical specification

Providing weep holes in Brick masonry/Plain/Reinforced concrete


abutment, wing wall/return wall with 100 mm dia AC pipe, extending
13.08 each 172.00 172.00
through the full width of the structure with slope of 1V :20H towards
drawing foce. Complete as per drawing and Technical specifications

Back filling behind abutment, wing wall and return wall complete as
13.09
per drawing and Technical specification
A Granular material cum 3,688.00 3,688.00
B Sandy material cum 3,146.00 3,146.00

Providing and laying of Filter media with granular materials/stone


crushed aggregates satisfying the requirements laid down in clause
2504.2.2. of MoRTH specifications to a thickness of not less than 600
13.10 mm with smaller size towards the soil and bigger size towards the wall cum 2,506.00 2,506.00
and provided over the entire surface behind abutment, wing wall and
return wall to the full height compacted to a firm condition complete as
per drawing and Technical Specification.

Supplying & laying of drainage composite for use behind walls,


between two different fills, alongside drains of road, below concrete
lining of canals etc. Geocomposite for planar drainage, realized by
thermobonding a draining core in extruded monofilaments with two
filtering nonwoven geotextiles that may also be working as separation
or protecting layers. The draining three dimensional core will have a
“W” configuration as longitudinal parallel channels. Minimum
thickness to be 7.2mm, with two filtering UV stabilized polypropylene
13.11 sqm 266.00 266.00
nonwoven geotextile of minimum thickness of 0.75 mm having pores
of 150 micron and tensile strength of 8.0 kN/m that will be working as
separation or protecting layer, geocomposite having in plane flow
capacity of 2.1 L / (m.s) at hydraulic gradient of 1.0 & 20 kpa pressure
and tensile strength of 18 kN/m , with mass per unit area of 740 gsm,
supplied in the form of roll for easy transportation to site of work as
per detailed specification all complete as per directions of Engineer in
charge.
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

Supplying & laying of drainage composite for use behind walls,


between two different fills, alongside drains of road, below concrete
lining of canals etc. having thermobonding a draining core - HDPE
geonet comprises of two sets of parallel overlayed ribs integrally
connected to have a rhomboidal shape with a polyethylene film and a
nonwoven geotextile having mass per unit area 130 g/m2 and tensile
13.12 strength of 8.0 kN/m that will be working as separation or protecting sqm 230.00 230.00
layer, geocomposite having in plane flow capacity of 0.7 L / (m.s) at
hydraulic gradient of 1.0 & 20 kPa pressure and tensile strength of
13.5 kN/ m , with mass per unit area of 830 gsm, at easily accessible
location including top and bottom, with all leads and lifts, manpower
and machinery, materials, labour etc. complete and as directed by
Engineer - In - Charge.

Supplying, fitting and fixing in position true to line and level cast steel
rocker bearing conforming to IRC: 83(Pt.-1) section IX and clause tonne
13.13 301.00 301.00
2003 of MoRTH specifications complete including all accessories as capacity
per drawing and Technical Specifications.

Supplying, fitting and fixing in position true to line and level forged
steel roller bearing conforming to IRC: 83(Pt.-1) section IX and clause tonne
13.14 458.00 458.00
2003 of MoRTH specifications complete including all accessories as capacity
per drawing and Technical Specifications.

Supplying, fitting and fixing in position true to line and level sliding
plate bearing with PTFE surface sliding on stainless steel complete
tonne
13.15 including all accessories as per drawing and Technical Specifications 593.00 593.00
capacity
and BS: 5400, section 9.1 & 9.2 (for PTFE) and clause 2004 of
MoRTH Specifications.

Supplying, fitting and fixing in position true to line and level


elastomeric bearing conforming to IRC: 83 (Part-II) section IX and cubic
13.16 1.00 1.00
clause 2005 of MoRTH specifications complete including all centimetre
accessories as per drawing and Technical Specifications.

Supplying, fitting and fixing in position true to line and level sliding
plate bearing with stainless steel plate sliding on stainless steel plate tonne
13.17 584.00 584.00
with mild steel matrix complete including all accessories as per capacity
drawing and Technical Specifications.

Supplying, fitting and fixing in position true to line and level POT-
PTFE bearing consisting of a metal piston supported by a disc or
unreinforced elastomer confined within a metal cylinder, sealing
rings, dust seals, PTFE surface sliding against stainless steel mating
tonne
13.18 surface, completre assembly to be of cast steel/fabricated structural 188.00 188.00
capacity
steel, metal and elastomer elements to be as per IRC: 83 part-I & II
respectively and other parts conforming to BS: 5400, section 9.1 &
9.2 and clause 2006 of MoRTH Specifications complete asper
drawing and approved technical specifications.

13.19 Protection to substructure by using coal tar epoxy sqm 342.00 342.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Providing structural steel for sub-structure complete as per drawing
13.20 tonne 166,698.00 166,698.00
and technical specifications
CHAPTER-14
SUPER-STRUCTURE
Furnishing and Placing Reinforced/Prestressed cement concrete in
14.01
super-structure as per drawing and Technical Specification
A RCC Grade M20
Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 9,370.00 9,426.00
(q) Height 5m to 10m cum 9,761.00 9,818.00
(r) Height above 10m cum 10,151.00 10,211.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 9,761.00 9,818.00
(q) Height 5m to 10m cum 10,151.00 10,211.00
(r) Height above 10m cum 10,542.00 10,604.00
B RCC Grade M25
Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 10,023.00 10,078.00
(q) Height 5m to 10m cum 10,441.00 10,498.00
(r) Height above 10m cum 10,858.00 10,918.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 10,441.00 10,498.00
(q) Height 5m to 10m cum 10,858.00 10,918.00
(r) Height above 10m cum 11,276.00 11,338.00
C RCC Grade M 30
Using Batching Plant, Transit Mixer and Concrete Pump.
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 10,161.00 10,216.00
(q) Height 5m to 10m cum 10,584.00 10,642.00
(r) Height above 10m cum 11,007.00 11,067.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 10,584.00 10,642.00
(q) Height 5m to 10m cum 11,007.00 11,067.00
(r) Height above 10m cum 11,431.00 11,493.00
D RCC/PSC Grade M35
Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 18-28% of (a+b+c)
(p) Height upto 5m cum 10,231.00 10,286.00
(q) Height 5m to 10m cum 10,665.00 10,722.00
(r) Height above 10m cum 11,098.00 11,157.00
(ii) For T-beam & slab, 23-33% of (a+b+c)
(p) Height upto 5m cum 10,665.00 10,722.00
(q) Height 5m to 10m cum 11,098.00 11,157.00
(r) Height above 10m cum 11,532.00 11,593.00
(iii) For box girder and balanced cantilever, 38-58% of cost of concrete.
(p) Height upto 5m cum 11,965.00 12,029.00
(q) Height 5m to 10m cum 12,832.00 12,901.00
(r) Height above 10m cum 13,700.00 13,772.00
E RCC/PSC Grade M-40
Using Batching Plant, Transit Mixer and Concrete Pump
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
(i) For solid slab super-structure, 18-28% of (a+b+c)
(p) Height upto 5m cum 10,750.00 10,804.00
(q) Height 5m to 10m cum 11,205.00 11,262.00
(r) Height above 10m cum 11,661.00 11,720.00
(ii) For T-beam & slab, 23-33% of (a+b+c)
(p) Height upto 5m cum 11,205.00 11,262.00
(q) Height 5m to 10m cum 11,661.00 11,720.00
(r) Height above 10m cum 12,116.00 12,178.00
(iii) For box girder and balanced cantilever, 38-58% of cost of concrete.
(p) Height upto 5m cum 12,572.00 12,636.00
(q) Height 5m to 10m cum 13,483.00 13,551.00
(r) Height above 10m cum 14,394.00 14,467.00
F RCC/PSC Grade M-45
For solid slab/voided slab super-structure, 16-26% of cost of
(i)
concrete (a+b+c)
(p) Height upto 5m cum 10,788.00 10,842.00
(q) Height 5m to 10m cum 11,253.00 11,309.00
(r) Height above 10m cum 11,718.00 11,776.00
For I-beam & slab including launching of precast girders by launching
(ii)
truss upto 40 m span, 21-31% of cost of concrete.
(p) Height upto 5m cum 11,253.00 11,309.00
(q) Height 5m to 10m cum 11,718.00 11,776.00
(r) Height above 10m cum 12,183.00 12,244.00
For cast-in-situ box girder, segmental construction and balanced
(iii)
cantilever, 36-56% of cost of concrete.
(p) Height upto 5m cum 12,648.00 12,711.00
(q) Height 5m to 10m cum 13,578.00 13,646.00
(r) Height above 10m cum 14,508.00 14,580.00
G PSC Grade M-50
For cast-in-situ box girder, segmental construction and balanced
(i)
cantilever, 35-55% of cost of concrete
(p) Height upto 5m cum 13,587.00 13,649.00
(q) Height 5m to 10m cum 14,594.00 14,660.00
(r) Height above 10m cum 15,600.00 15,671.00
H PSC Grade M- 55
For cast-in-situ box girder, segmental construction and balanced
(i)
cantilever, 35-55% of cost of concrete
(p) Height upto 5m cum 13,728.00 13,790.00
(q) Height 5m to 10m cum 14,745.00 14,812.00
(r) Height above 10m cum 15,762.00 15,833.00
I PSC Grade M- 60
For cast-in-situ box girder, segmental construction and balanced
(i)
cantilever, 35-55% of cost of concrete
(p) Height upto 5m cum 14,066.00 14,129.00
(q) Height 5m to 10m cum 15,108.00 15,175.00
(r) Height above 10m cum 16,150.00 16,222.00
J PSC Grade M- 65
For cast-in-situ box girder, segmental construction and balanced
(i)
cantilever, 35-55% of cost of concrete
(p) Height upto 5m cum 14,140.00 14,202.00
(q) Height 5m to 10m cum 15,187.00 15,254.00
(r) Height above 10m cum 16,234.00 16,306.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

Supplying, fitting and placing HYSD bar reinforcement in super-


14.02 tonne 68,745.00 68,843.00
structure complete as per drawing and technical specifications

High tensile steel wires/strands including all accessories for stressing,


14.03 stressing operations and grouting complete as per drawing and tonne 150,058.00 150,058.00
Technical Specifications
Providing and laying Cement concrete wearing coat M-30 grade
14.04 including reinforcement complete as per drawing and Technical cum 13,724.00 13,778.00
Specifications

Mastic Asphalt (Providing and laying 12 mm thick mastic asphalt


wearing course on top of deck slab excluding prime coat with paving
grade bitumen meeting the requirements given in table 500-39,
prepared by using mastic cooker and laid to required level and slope
after cleaning the surface, including providing antiskid surface with
14.05 bitumen precoated fine grained hard stone chipping of 9.5 mm sqm 574.00 574.00
nominal size at the rate of 0.005cum per 10 sqm and at an
approximate spacing of 10 cm center to center in both directions,
pressed into surface when the temperature of surfaces not less than
100 deg. C, protruding 1 mm to 4 mm over mastic surface, all
complete as per clause 516.)

Construction of precast RCC railing of M30 Grade, aggregate size


not exceeding 12 mm, true to line and grade, tolurence of vertical
RCC post not to exceed 1 in 500, centre to centre spacing between
14.06 metre 2,097.00 2,103.00
vertical post not to exceed 2000 mm, leaving adequate space
between vertical post for expansion, complete as per approved
drawings and technical specifications.

Construction of RCC railing of M30 Grade in-situ with 20 mm nominal


size aggregate, true to line and grade, tolurence of vertical RCC post
not to exceed 1 in 500, centre to centre spacing between vertical
14.07 metre 2,047.00 2,053.00
post not to exceed 2000 mm, leaving adequate space between
vertical post for expansion, complete as per approved drawings and
technical specifications.

Providing, fitting and fixing mild steel railing complete as per drawing
14.08 metre 4,246.00 4,246.00
and Technical Specification
14.09 Drainage Spouts complete as per drawing and Technical specification each 4,779.00 4,779.00
PCC M15 Grade leveling course below approach slab complete as
14.10 cum
per drawing and Technical specification
(i) PCC Grade M15 with Batching Plant and Concrete Pump cum 7,384.00 7,432.00
(ii) PCC Grade M15 with Batching Plant and Manual placing cum 7,760.00 7,806.00
Reinforced cement concrete approach slab including reinforcement
14.11 cum 12,146.00 11,625.00
and formwork complete as per drawing and Technical specification

Providing anti-corrosive treatment to HYSD reinforcement with Fusion


14.12 Bonded Epoxy Coating (FBEC) (To be taken as per the prevailing tonne To be noted To be noted
market rates.)
Precast - pretensioned Girders (Providing, precasting, transportation
14.13 and placing in position precast pretensioned concrete girders as per cum 34,915.00 47,719.00
drawing and technical specifications)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
14.14 Providing and fixing Helical pipes in voided concrete slabs metre 1,591.00 1,591.00

Crash Barriers (The rate analysis for rigid crash barrier in reinforced
cement concrete, semi-rigid crash barrier with metal beam and
14.15
flexible crash barrier with wire ropes have been made and included in
chapter-8 on Traffic and Transportation.)
Painting on concrete surface (Providing and applying 2 coats of water
based cement paint to unplastered concrete surface after cleaning the
14.16 Sqm 107.00 107.00
surface of dirt, dust, oil, grease, efflorescence and applying paint @
of 1 litre for 2 Sq.m. )
14.17 Filler joint
Providing & fixing 2 mm thick corrugated copper plate in expansion
(i) metre 2,417.00 2,417.00
joint complete as per drawing & Technical Specification.

Providing & fixing 20 mm thick compressible fibre board in expansion


(ii) metre 255.00 255.00
joint complete as per drawing & Technical Specification.

Providing and fixing in position 20 mm thick premoulded joint filler in


expansion joint for fixed ends of simply supported spans not
(iii) exceeding 10 m to cater for a horizontal movement upto 20 mm, metre 266.00 266.00
covered with sealant complete as per drawing and technical
specifications.

Providing and filling joint sealing compound as per drawings and


(iv) metre 44.00 44.00
technical specifications with coarse sand and 6% bitumen by weight

Asphaltic Plug joint (Providing and laying of asphaltic plug joint to


provide for horizontal movement of 25 mm and vertical movement of 2
mm, depth of joint varying from 75 mm to 100 mm, width varying
from 500 mm to 750 mm (in traffic direction), covered with a closure
14.18 plate of 200mm x 6mm of wieldable structural steel conforming to IS: metre 1,569.00 1,569.00
2062, asphaltic plug to consist of polymer modified bitumen binder,
carefully selected single size aggregate of 12.5 mm nominal size and
a heat resistant foam caulking/backer rod, all as per approved
drawings and specifications.)

Elastomeric Slab Steel Expansion Joint (Providing and laying of an


elastomeric slab steel expansion joint, catering to right or skew (less
than 20 deg., moderately curved with maximum horizontal movement
upto 50 mm, complete as per approved drawings and standard
14.19 metre 37,794.00 37,794.00
specifications to be installed by the manufacturer/supplier or their
authorised representative ensuring compliance to the manufacturer's
instructions for installation and clause 2605 of MoRTH specifications
for road & bridge works..)

Compression Seal Joint (Providing and laying of compression seal


joint consisting of steel armoured nosing at two edges of the joint gap
suitably anchored to the deck concrete and a preformed chloroprene
14.20 metre 4,567.00 4,567.00
elastomer or closed cell foam joint sealer compressed and fixed into
the joint gap with special adhesive binder to cater for a horizontal
movement upto 40 mm and vertical movement of 3 mm.)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Strip Seal Expansion Joint (Providing and laying of a strip seal
expansion joint catering to maximum horizontal movement upto 70
mm, complete as per approved drawings and standard specifications
14.21 metre 11,281.00 11,281.00
to be installed by the manufacturer/supplier or their authorised
representative ensuring compliance to the manufacturer's instructions
for installation.)

Modular Strip / Box Seal Joint (Providing and laying of a modular strip
Box steel expansion joint including anchorage catering to a horizontal
movement beyond 70 mm and upto 140mm, complete as per
14.22 metre 11,173.00 11,173.00
approved drawings and standard specifications to be installed by the
manufacturer/supplier or their authorised representative ensuring
compliance to the manufacturer's instructions for installation.)

Modular Strip / Box Seal Joint (Providing and laying of a modular strip
box seal expansion joint catering to a horizontal movement beyond
140mm and upto 210mm, complete as per approved drawings and
14.23 metre 11,194.00 11,194.00
standard specifications to be installed by the manufacturer/supplier or
their authorised representative ensuring compliance to the
manufacturer's instructions for installation.)

Painting two coats after filling the surface with synthetic enamel paint
14.24 Nos. 208.00 208.00
bridge No. and span arrangements as per as directed by Engineer.

Bipolar corrosion inhibiting admixture in concrete for protection of


reinforced steel from corrosion(Admix polydentate, bipolar, migratory,
14.25 intergal non nitrate base concrete penetrating corrosion inhibiting cum 277.00 277.00
admixture at dosage of 3Kg per cu.m. of concrete as per
manufactures specification. Inhibitor should conforms to following-)

Providing structural steel for super-structure complete as per drawing


14.26 tonne 174,295.00 174,295.00
and technical specifications
CHAPTER-15
BOX CELL STRUCTURE

Excavation for Structures (Earth work in excavation of foundation of


structures as per drawing and technical specification, including
15.01 setting out, construction of shoring and bracing, removal of stumps
and other deleterious matter, dressing of sides and bottom and
backfilling with approved material.)

I Ordinary soil
A Manual Means
(i) Depth upto 3 m cum 248.00 248.00
(ii) Depth 3 m to 6 m cum 319.00 319.00
(iii) Depth above 6 m cum 425.00 425.00
B Mechanical Means
(i) Depth upto 3 m cum 123.00 128.00
(ii) Depth 3 m to 6 m cum 136.00 141.00
(iii) Depth above 6m cum 152.00 40,036.27
II Ordinary rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m cum 354.00 354.00
B Mechanical Means cum 757.00 798.00
III Hard rock ( requiring blasting )
A Manual Means cum 380.00 389.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
IV Hard rock ( blasting prohibited )
A Mechanical Means cum 1,015.00 1,043.00
V Marshy soil
(i) upto 3 m depth
A Manual means cum 1,369.00 1,369.00
B Mechanical Means cum 463.00 472.00
VI Back Filling in Marshy Foundation Pits cum 1,180.00 1,180.00
Filling Annular Space Around Footing in Rock (PCC-15 nominal mix.
15.02 cum 8,121.00 8,168.00
Rate may be taken as per items 15.11)
Sand Filling in Foundation Trenches as per Drawing & Technical
15.03 cum 3,259.00 3,275.00
Specification
Brick masonry work in cement mortar 1:3 in foundation complete
15.04 excluding pointing and plastering, as per drawing and technical cum 6,061.00 6,098.00
specifications
15.05 A Cement mortar1:3 (1cement :3 sand) cum 6,765.00 6,765.00
B Cement mortar1:2 (1cement :2 sand) cum 7,517.00 7,517.00
C Cement mortar1:4 (1cement :4 sand) cum 6,244.00 6,244.00
D Cement mortar1:6 (1cement :6 sand) cum 6,056.00 6,056.00
Stone masonry work in cement mortar 1:3 in foundation complete as
15.06
drawing and Technical Specification
(a) Square Rubble Coursed rubble masonry( first sort ) cum 6,604.00 6,604.00
(b) Random Rubble Masonry cum 5,926.00 5,926.00
Brick masonry work in cement mortar 1:3 in sub-structure complete
15.07 excluding pointing and plastering, as per drawing and technical cum 5,734.00 5,773.00
specifications
Pointing with cement mortar (1:3) on brick work in sub-structure as
15.08 Sqm 102.00 102.00
per Technical specification.
Plastering with cement mortar (1:3 ) on brick work in sub-structure as
15.09 Sqm 196.00 195.00
per Technical Specification
Stone masonry work in cement mortar 1:3 in sub-structure complete
15.10
as per drawing and Technical Specification
A Random Rubble Masonray cum 6,351.00 6,423.00
B Coursed Rubble Masonary cum 7,442.00 7,514.00
C Ashlar Masonary cum 9,160.00 9,232.00
Plain/Reinforced cement concrete, in open foundation complete as
15.11
per drawing and technical specification
A PCC Grade M15
Case I PCC Grade M15 using batching plant and concrete pump cum 8,121.00 8,168.00
Case II PCC Grade M15 using batching plant and manual placing cum 8,536.00 8,586.00
B PCC Grade M20
Case I PCC Grade M20 using batching plant and concrete pump cum 8,618.00 8,670.00
Case II PCC Grade M20 using batching plant and manual placing cum 9,032.00 9,082.00
C RCC Grade M20
Case I RCC Grade M20 using batching plant and concrete pump cum 8,666.00 8,718.00
Case II RCC Grade M20 using batching plant and manual placing cum 9,106.00 9,156.00
D PCC Grade M25
Case I PCC Grade M25 using batching plant and concrete pump cum 9,017.00 9,069.00
Case II PCC Grade M25 using batching plant and manual placing cum 9,432.00 9,482.00
E RCC Grade M25
Case I RCC Grade M25 using batching plant and concrete pump cum 9,264.00 9,316.00
Case II RCC Grade M25 using batching plant and manual placing cum 9,704.00 9,754.00
F PCC Grade M30
Case I PCC Grade M30 using batching plant and concrete pump cum 9,055.00 9,107.00
Case II PCC Grade M30 using batching plant and manual placing cum 9,469.00 9,520.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
G RCC Grade M30
Case I RCC Grade M30 using batching plant and concrete pump cum 9,390.00 9,442.00
Case II RCC Grade M30 using batching plant and manual placing cum 9,831.00 9,881.00
H RCC Grade M35
Case I RCC Grade M35 using batching plant and concrete pump cum 9,614.00 9,666.00
Case II RCC Grade M35 using batching plant and manual placing cum 10,054.00 10,104.00
I RCC Grade M40
Case I RCC Grade M40 using batching plant and concrete pump cum 10,097.00 10,150.00
Case II RCC Grade M40 using batching plant and manual placing cum 10,794.00 10,893.00
Plain/Reinforced cement concrete for wall & slab etc. complete as per
15.12
drawing and technical specification
A RCC Grade M20
With Batching Plant, Transit Mixer and Concrete Pump cum 9,847.00 9,907.00
B RCC Grade M25
With Batching Plant, Transit Mixer and Concrete Pump cum 10,527.00 10,587.00
C RCC Grade M30
With Batching Plant, Transit Mixer and Concrete Pump cum 10,671.00 10,701.00
D RCC Grade M35
With Batching Plant, Transit Mixer and Concrete Pump cum 10,925.00 10,984.00
E RCC Grade M40
With Batching Plant, Transit Mixer and Concrete Pump cum 11,474.00 11,534.00
Supplying, fitting and placing un-coated HYSD bar reinforcement in
15.13 MT 68,094.00 68,191.00
foundation complete as per drawing and technical specifications

Providing weep holes in Brick masonry/Plain/ Reinforced concrete


abutment, wing wall/ return wall with 100 mm dia AC pipe, extending
15.14 Number 172.00 172.00
through the full width of the structure with slope of 1V :20H towards
drawing foce. Complete as per drawing and Technical Specifications

PCC M15 Grade leveling course below approach slab complete as


15.15
per drawing and Technical specification
Case I PCC Grade M15 using batching plant and concrete pump cum 7,384.00 7,426.00
Case II PCC Grade M15 using batching plant and manual placing cum 7,760.00 7,806.00
Reinforced cement concrete approach slab including reinforcement
15.16 cum 12,113.00 12,167.00
and formwork complete as per drawing and Technical specification

15.17 Drainage Spouts complete as per drawing and Technical specification Number 875.00 875.00

Providing and laying Cement concrete wearing coat M-30 grade


15.18 including reinforcement complete as per drawing and Technical cum 13,746.00 13,777.00
Specifications
15.19 Mastic Asphalt

Providing and laying 12 mm thick mastic asphalt wearing course on


top of deck slab excluding prime coat with paving grade bitumen
meeting the requirements given in table 500-39, prepared by using
mastic cooker and laid to required level and slope after cleaning the
surface, including providing antiskid surface with bitumen precoated
sqm 574.00 574.00
fine grained hard stone chipping of 9.5 mm nominal size at the rate of
0.005cum per 10 sqm and at an approximate spacing of 10 cm center
to center in both directions, pressed into surface when the
temperature of surfaces not less than 100 deg. C, protruding 1 mm to
4 mm over mastic surface, all complete as per clause 516.

15.20 Crash Barriers for Bridge


Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
The rate analysis for semi rigid crash barrier with metal beam and
flexible crash barrier with wire ropes have been made and included in
chapter-8 on Traffic and Transportation. The rate analysis for rigid
crash barrier in reinforced cement concrete,
have been made and included in chapter-14 on Super-structure
15.21 Painting on concrete surface
Providing and applying 2 coats of water based cement paint to
unplastered concrete surface after cleaning the surface of dirt, dust, sqm 107.00 107.00
oil, grease, efflorescence and applying paint @ of 1 litre for 2 Sq.m.
15.22 Filler joint
Providing & fixing 2 mm thick corrugated copper plate in expansion Running
(i) 2,417.00 2,417.00
joint complete as per drawing & Technical Specification. Metre

Providing & fixing 20 mm thick compressible fibre board in expansion Running


(ii) 255.00 255.00
joint complete as per drawing & Technical Specification. Metre

Providing and fixing in position 20 mm thick premoulded joint filler in


expansion joint for fixed ends of simply supported spans not
Running
(iii) exceeding 10 m to cater for a horizontal movement upto 20 mm, 266.00 266.00
Metre
covered with sealant complete as per drawing and technical
specifications.
Providing and filling joint sealing compound as per drawings and
Running
(iv) technical specifications with coarse sand and 6 per cent bitumen by 44.00 44.00
Metre
weight
Back filling behind abutment, wing wall and return wall complete as
15.23
per drawing and Technical Specification
A Granular material cum 3,688.00 3,688.00
B Sandy material cum 3,146.00 3,146.00

Providing and laying of Filter media with granular materials/stone


crushed aggregates satisfying the requirements laid down in clause
2504.2.2. of MoRTH specifications to a thickness of not less than 600
15.24 mm with smaller size towards the soil and bigger size towards the wall cum 2,506.00 2,506.00
and provided over the entire surface behind abutment, wing wall and
return wall to the full height compacted to a firm condition complete as
per drawing and Technical Specification.

Painting with synthetic enamel paint bridge No. and span


15.25
arrangements
Painting two coats after filling the surface with synthetic enamel paint
Number 208.00 208.00
bridge No. and span arrangements as per as directed by Engineer.
CHAPTER-16
RIVER TRAINING AND PROTECTION WORKS
Providing and laying boulders apron on river bed for protection
16.01 against scour with stone boulders weighing not less than 40 kg each
complete as per drawing and Technical specification.
A Boulder laid dry without wire crates. cum 3,932.00 3,932.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Boulder apron laid in wire crates (Providing and laying of boulder
apron laid in wire crates made with 4mm dia GI wire conforming to IS:
16.02 280 & IS:4826 in 100mm x 100mm mesh (weaved diagonally) cum 3,761.00 3,761.00
including 10% extra for laps and joints laid with stone boulders
weighing not less than 40 kg each.)

Cement concrete blocks (size 0.5 x 0.5 x 0.5 m) (Providing and laying
of apron with cement concrete blocks of size 0.5x0.5x0.5 m cast in-
16.03 cum 8,231.00 8,280.00
situ and made with nominal mix of M-15 grade cement concrete with a
minimum cement content of 250 kg/cum as per IRC: 21-2000.)

Providing and laying Pitching on slopes laid over prepared filter media
16.04 including boulder apron laid dry in front of toe of embankment
complete as per drawing and Technical specifications
A Stone/Boulder cum 3,932.00 3,932.00
Cement Concrete blocks of size 0.3x0.3 x0.3 m cast in cement
B cum 8,231.00 8,280.00
concrete of Grade M15
Providing and laying Filter material underneath pitching in slopes
16.05 cum 2,827.00 2,827.00
complete as per drawing and Technical specification

Geotextile Filter (Laying of a geotextile filter between pitching and


embankment slopes on which pitching is laid to prevent escape of the
16.06 embankment material through the voids of the stone pitching/cement sqm 30.00 30.00
concrete blocks as well as to allow free movement of water without
creating any uplift head on the pitching.)

Toe protection (A toe wall for toe protection can either be in dry rubble
masonry in case of dry rubble pitching or pitching with stones in wire
crates or it can be in PCC M15 nominal mix if cement concrete block
16.07 have been used for pitching . Rates for toe wall can be adopted from
respective clauses depending upon approved design. The rate for
excavation for foundation, dry rubble masonry and PCC M15 have
been analysed and given in respective chapters.)

Providing and laying Flooring complete as per drawing and Technical


16.08
specifications laid over cement concrete bedding.
A Rubble stone laid in cement mortar 1:3 cum 8,600.00 8,616.00
B Cement Concrete blocks Grade M15 cum 10,314.00 10,381.00
Dry rubble Flooring, Construction of dry rubble flooring at cross
16.09 cum 4,618.00 4,618.00
drainage works for relatively less important works.

16.10 Curtain wall complete as per drawing and Technical specification


A Stone masonry in cement mortar (1:3) cum 6,604.00 6,604.00
B Cement concrete Grade M15 cum 7,678.00 7,728.00
Flexible Apron :Construction of flexible apron 1 m thick comprising of
16.11 loose stone boulders weighing not less than 40 kg beyond curtain cum 4,057.00 4,057.00
wall.
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

Gabian Structure for Retaining Earth (Providing and construction of a


gabain structure for retaining earth with segments of wire crates of
size 7 m x 3 m x 0.6 m each divided into 1.5 m compartments by
cross netting, made from 4 mm galvanised steel wire @ 32 kg per 10
16.12 sqm having minimum tensile strength of 300 Mpa conforming to cum 3,602.00 3,602.00
IS:280 and galvanizing coating conforming to IS:4826, woven into
mesh with double twist, mesh size not exceeding 100 x 100 mm,
filled with boulders with least dimension of 200 mm, all loose ends to
be tied with 4 mm galvanised steel wire)

Gabian Structure for Erosion Control, River Training Works and


Protection works (Providing and constructing gabain structures for
erosion control, river training works and protection works with wire
crates of size 2 m x 1 m x 0.3 m each divided into 1m compartments
by cross netting, made from 4 mm galvanised steel wire @ 32 kg per
16.13 cum 3,773.00 3,773.00
10 sqm having minimum tensile strength of 300 Mpa conforming to
IS:280 and galvanizing coating conforming to IS:4826, woven into
mesh with double twist, mesh size not exceeding 100 mm x 100 mm,
filled with boulders with least dimension of 200 mm, all loose ends to
be securely tied with 4 mm galvanised steel wire.)

Providing & making Gabion structure with Mechanically Woven


Double Twisted Hexagonal Shaped Wire mesh Gabion Boxes as per
IS 16014:2012, MORT&H Clause 2500, of required size, Mesh Type
10x12 (D=100 mm with tolerance of ± 2%) Zinc coated, Mesh wire
diameter 3.0 mm, mechanically edged/selvedged with partitions at
16.14 cum 3,534.00 3,534.00
every 1m interval and shall have minimum 10 numbers of openings
per meter of mesh perpendicular to twist, tying with lacing wire of
diameter 2.2 mm, supplied @3% by weight of Gabion boxes, filled
with boulders with least dimension of 200 mm, as per drawing, all
complete as per direction of Engineer-in-charge.

Laying of a fine aggregate concrete grade M30 filled fabric form for
16.15 erosion protection of embankments (Embankment Erosion Protection cum 1,105.00 1,110.00
using Fine Aggregate Concrete Filled Fabric Form Mattress system)
CHAPTER-17
REPAIR AND REHABILITATION

Removal of existing cement concrete wearing coat including its


disposal complete as per Technical specification without causing any
17.01 detrimental effect to any part of the bridge structure and removal of sqm 300.00 300.00
dismantled material with all lifts and lead upto 1000m(Thickness 75
mm)

Removal of existing asphaltic wearing coat comprising of 50 mm thick


17.02 asphaltic concrete laid over 12 mm thick mastic asphalt including sqm 232.00 232.00
disposal with all lift and lead upto 1000m.

Guniting concrete surface with cement mortar applied with


17.03 compressor after cleaning surface and spraying with epoxy complete sqm 1,525.00 1,525.00
as per Technical specification
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

Providing and inserting nipples with approved fixing compound after


drilling holes for grouting as per Technical specifications including
17.04 each 224.00 224.00
subsequent cutting/removal and sealing of the hole as necessary of
nipples after completion of grouting with Cement/Epoxy

Sealing of cracks/porous concrete by injection process through


17.05
nipples/Grouting complete as per Technical specification.
A Cement Grout kg 285.00 285.00
B Cement mortar (1:1) Grouting kg 281.00 281.00

Patching of damaged concrete surface with polymer concrete and


curing compounds, initiator and promoter, available in present
17.06 sqm 2,196.00 2,196.00
formulations, to be applied as per instructions of manufacturer and as
approved by the Engineer.

Sealing of crack / porous concrete with Epoxy Grout by injection


17.07 kg 1,418.00 1,418.00
through nipples complete as per clause 2803.1.
Applying epoxy mortar over leached, honey combed and spalled
17.08 concrete surface and exposed steel reinforcement complete as per sqm 557.00 557.00
Technical specification

Removal of defective concrete, cleaning the surface thoroughly,


applying the shotcrete mixture mechanically with compressed air
under pressure, comprising of cement, sand, coarse aggregates,
water and quick setting compound in the proportion as per clause
17.09 sqm 638.00 638.00
2807.1., sand and coarse aggregates conforming to IS: 383 and table
1 of IS: 9012 respectively, water cement ratio ranging from 0.35 to
0.50, density of gunite not less than 2000 kg/cum, strength not less
than 25 Mpa and workmanship conforming to clause 2807.6.

Applying pre-packed cement based polymer mortar of strength 45


17.10 sqm 202.00 202.00
Mpa at 28 days for replacement of spalled concrete
17.11 Eproxy bonding of new concrete to old concrete sqm 526.00 526.00

Providing external prestressing with high tensile steel wires/strands


including drilling for passage of prestessing steel, all accessories for
17.12 tonne 426,592.00 426,592.00
stressing and stressing operation and grouting complete as per
drawing and Technical specification

Providing external prestressing with high tensile steel wires/strands


including drilling for passage of prestessing steel, all accessories for
17.13 tonne 414,038.00 414,038.00
stressing and stressing operation and grouting complete as per
drawing and Technical specification

Providing external prestressing with high tensile steel wires/strands


including drilling for passage of prestessing steel, all accessories for
17.14 tonne 378,259.00 378,259.00
stressing and stressing operation and grouting complete as per
drawing and Technical specification

17.15 Replacement of bearings complete as per Technical specification each 84,446.00 84,446.00
17.16 Rectification of bearings as per Technical specifications each 5,753.00 5,753.00
17.17 Replacement of Expansion Joints complete as per drawings metre 4,595.00 4,613.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
17.18 Replacement of damaged concrete railing. metre 652.00 652.00
17.19 Replacement of crash barrier. metre 1,035.00 1,035.00
17.20 Replacement of damaged mild steel railing metre 575.00 575.00

Repair of crash barrier (Repair of concrete crash barrier with cement


concrete of M-30 grade by cutting and trimming the damaged portion
17.21 metre 407.00 409.00
to a regular shape, cleaning the area to be repaired thoroughly,
applying cement concrete after erection of proper form work.)

Repair of RCC Railing (Carrying out repair of RCC M30 railing to bring
17.22 metre 222.00 223.00
it to the original shape.)
Repair of steel Railing (Repair of steel railing to bring it to the original
17.23 metre 416.00 416.00
shape)
Mobile Bridge Inspection Unit (MBIU) Inspection of bridge by using of
17.24 km 55,382.00 55,382.00
Mobile Bridge Inspection Unit (MBIU)
CHAPTER-18
TUNNEL WORK
Excavation for Portal in Ordinary Rock with hydraulic excavator
including cutting and loading in tippers, trimming bottom and side
18.01 slopes, in accordance with requirements of lines, grades and cross Cum 854.00
sections, and disposal of excavated materials including all lifts and
lead upto 1000 m

Excavation for Portal in Hard Rock (blasting prohibited) with hydraulic


excavator including cutting and loading in tippers, trimming bottom
18.02 and side slopes, in accordance with requirements of lines, grades and Cum 880.00
cross sections, and and disposal of excavated materials including all
lifts and lead upto 1000m

Excavation for portal in soil with hydraulic excavator including cutting


and loading in tippers, trimming bottom and side slopes, in
18.03 accordance with requirements of lines, grades and cross sections, Cum 129.00
and and disposal of excavated materials including all lifts and lead
upto 1000m

Excavation for tunnel by using drilling & blasting methods in all types
of rock including cost of all materials,machinery, labour, scaling
18.04 excavated surface, marking, ventilation, lighting, drainage, removing Cum 1,744.00
and hauling the excavated muck outside tunnel upto specified dump
area and all other ancillary operations etc.

Dewatering in tunnel by pumping out water collected by natural


drainage inside tunnel including providing sump wherever necessary,
18.05 558.00
cost of all materials, machinery, labour, drainage and all other
ancillary operations etc., complete.
Providing , Fitting and Placing of Ribs including Fabrication,
Erection,Temporary fixture, Handling of material inside fabrication
18.06 tonne 128,101.00
workshop, final matching, field welding and complete as per Drawing
and Technical Specifications.

Shotcreting to upper bench / lower bench with steel fiber reinforced


18.07 shotcrete (SFRS) , shotcrete compressive strength shall be 25 cum 19,530.00
N/mm2 and complete as per Drawing and Technical Specifications.

Shotcreting to upper bench / lower bench with welded wiremesh ,


18.08 shotcrete compressive strength shall be 25 N/mm2 and complete as cum 16,354.00
per Drawing and Technical Specifications.
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Providing and fixing 25 mm diameter 3 meter long steel rock bolts
including drilling 45 mm dia holes, plate, nuts, cement grout, cost of
18.09 all materials, machinery, labour, ventilation, lighting, drainage and all Nos. 2,761.00
other ancillary operations etc. complete as per Drawing and Technical
Specifications.
Providing and fixing 32 mm diameter 7 meter long steel rock bolts
including drilling 51 mm dia holes, plate, nuts, cement grout, cost of
18.10 all materials, machinery, labour, ventilation, lighting, drainage and all Nos. 7,011.00
other ancillary operations etc. complete as per Drawing and Technical
Specifications.

Grouting cement slurry in grout holes under specified pressure for


consolidation / contact grouting including cost of all materials,
18.11 machinery, labour, redrilling wherever necessary, ventilation,lighting, tonne 19,547.00
drainage and other ancillary operations etc. complete as per Drawing
and Technical Specifications.

Mass Concrete for Tunnel (Furnishing and Placing Reinforced cement


18.12
concrete in Tunnel Work as per drawing and Technical Specificatio.)
A RCC Grade M20
(i) With Batching Plant, Transit Mixer and Manual placing Cum 11,523.00
B RCC Grade M25
(i) With Batching Plant, Transit Mixer and Manual placing Cum 12,316.00
C RCC Grade M30
(i) With Batching Plant, Transit Mixer and Manual placing Cum 12,484.00
D RCC Grade M35
(i) With Batching Plant, Transit Mixer and Manual placing Cum 12,780.00
E RCC Grade M40
(i) With Batching Plant, Transit Mixer and Manual placing Cum 13,421.00
F RCC Grade M45
(i) With Batching Plant, Transit Mixer and Manual placing Cum 13,699.00
G RCC Grade M50
(i) With Batching Plant, Transit Mixer and Manual placing Cum 14,813.00
H RCC Grade M55
(i) With Batching Plant, Transit Mixer and Manual placing Cum 14,965.00
I RCC Grade M60
(i) With Batching Plant, Transit Mixer and Manual placing Cum 15,272.00
J RCC Grade M65
(i) With Batching Plant, Transit Mixer and Manual placing Cum 15,351.00
Supplying, fitting and placing HYSD bar reinforcement in Tunnel Work
18.13 tonne 72,100.00
complete as per drawing and technical specifications
CHAPTER-19
ENVIRONMENTAL MANAGEMENT & BIO ENGINEERING
19.01 Noise Barrier
(i) Masonry wall cum 5,637.00 5,811.00
(ii) Galvanized steel plain sheet sqm 143.00 146.00
(iii) Acrylic noise barrier sheet sqm 264.00 269.00
Construction of bamboo crib wall complete as per drawing and
19.02 Rm. 424.00 432.00
Technical specification.
Construction of Fascines with a bundle of sticks complete as per
19.03 Rm. 481.00 490.00
drawing and Technical specification.
Contruction and laying of brush Layers across the slope complete as
19.04 Sqm. 110.00 112.00
per drawing and Technical specification.
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project

Construction of vegetative Palisades in Rills using hard wood cutting


19.05 Rm. 406.00 414.00
complete as per drawing and Technical specification.
Laying of Palisades in Slopes complete as per drawing and
19.06 Sqm. 110.00 112.00
Technical specification.
Dust suppressionSprinkling of water in the sellement and working
19.07 KL 189.00 193.00
area as per instruction of Engineer.
Water Quality Monitoring (Grab Sample as per the monitoring
19.08 No. 3,208.00 3,267.00
locations mention in the EIA/EMP report or one sample/10 km length.)

Soil Quality Monitoring (Grab Sample as per the monitoring locations


19.09 No. 7,128.00 7,260.00
mention in the EIA/EMP report or one sample/10 km length.

Ambient Air Quality Monitoring 24 hrs continuous for location as


19.1 mention in the EIA/EMP report or one monitoring location within 10 No. 2,970.00 3,025.00
km radius.

Ambient Noise Monitoring 24 hour continuous (To be carried out as


19.11 No. 2,376.00 2,420.00
per the location mention in the EIA/EMP report.
19.12 Consent Approvals (Once)
(i) Consent to Establish (CTE) No. 118,800.00 121,000.00
(ii) Consent to Operate (CTO) No. 118,800.00 121,000.00
19.13 Compliance submission for Consent Approvals (Half Yearly).
(i) compliance submission for Consent to Establish (CTE) No. 14,256.00 14,520.00
(ii) compliance submission for Consent to Operate (CTO) No. 14,256.00 14,520.00
19.14 Environmental Clearance Compliance (Half Yearly) No. 29,700.00 30,250.00
19.15 Environmental Workshops (Half Yearly) No. 29,700.00 30,250.00
Pollution prevention, Silt fencing on eirther side of the streams and
19.16 rivers including erection and maintenance for entire construction 395.00 402.00
phase.

Road Safety Audit during Construction Period & Maintenance Period


including collection of Road accident data and analysis of fatal and
grievously injured accident with black spot identification report,
submission of GAP report, Road Safety Audit Reports on all activities
19.17
which were planned, actually executed and planned for the next
quarter report, Submission of audit report of work zone safety,
workshop report and Final Safety report complete as per IRC-SP-88
and directed by engineer.

A Upto 50.00 Kilometer Km. 2,203,918.00 2,244,732.00


B Between 50.00 Km. to 100.00 Km. Km. 2,920,045.00 2,974,120.00
C More than 100 Km. Km. 3,636,171.00 3,703,508.00
Road Safety Audit during Maintenance Period including collection of
Road accident data and analysis of fatal and grievously injured
accident with black spot identification report, submission of GAP
report, Road Safety Audit Reports on all activities which were
19.18
planned, actually executed and planned for the next quarter report,
submission of audit report of work zone safety (Maintenance work),
workshop report and Final Safety report complete as per IRC-SP-88
and directed by engineer.
A Upto 50.00 Kilometer Km. 1,325,095.00 1,349,634.00
B Between 50.00 Km. to 100.00 Km. Km. 1,553,785.00 1,582,559.00
C More than 100 Km. Km. 1,782,475.00 1,815,484.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

145.00
133.00
114.00
114.00
472.00
693.00

15.00
11.00
9.00
8.00

18.00
13.00
10.00
9.00

36.00
26.00
21.00
19.00
73.00
17.00

2,987.00

2,760.00

3,005.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

2,572.00

633.00

1,751.00

587.00
951.00
1,685.00
3,369.00

667.00
905.00
1,082.00
1,347.00
33,030.00

381,648.00
414,678.00

222,818.00
237,801.00

194,263.00
202,275.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

1,081.00
1,214.00
2,498.00

1,058.00
1,442.00

740.00
872.00
687.00
660.00

792.00
872.00
739.00
713.00
687.00
739.00

285.00

1,380.00

2,866.00
2,083.00
20.00

2.00

1.00

925.00
198.00
34.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
1,468.00
1,687.00
2,124.00

1,377.00
1,047.00

623.00
91.00

1,078.00

113.00

42.00

54.00

842.00
561.00
112.00

99.00

275.00

420.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

398.00

412.00

550.00

238.00

357.00

822.00

130.00

742.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
850.00
2,090.00

863.00

281.00

133.00

236.00

528.00
125.00

661.00
775.00

445.00

1,520.00

1,415.00
589.00

72.00
8.00
10.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

10.00
10.00

305.00

100.00

133.00

312.00

124.00

157.00

157.00

170.00

150.00

281.00

544.00

1,616.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

104.00
322.00

133.00
440.00

708.00

301.00

5,437.00

8.00

202.00

176.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

4,138.00
4,138.00
4,138.00
4,138.00
4,138.00
4,138.00

3,430.00
3,430.00
3,430.37
3,430.00
3,430.00
3,430.00

4,102.00
4,102.00
4,102.00
4,102.00
4,102.00
3,820.00

717.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

1,076.00

1,000.00

768.00

1,127.00

1,052.00

654.00

1,013.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

937.00

1,057.00

981.00

832.00

1,015.00

3,691.00
3,709.00

4,612.00

4,612.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
4,307.00

4,307.00

8.00
17.00

3,223.00

3,998.00
3,901.00
4,087.00

3,998.00
4,087.00

3,927.00
3,830.00

3,927.00
4,016.00

1,156.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

42.00

3,609.00

3,595.00

4,476.00

485.00

382.00

1,240.00

3,410.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
3,410.00

3,443.00
3,443.00

1,093.00

44.00

37.00

55.00

54.00

13.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

16.00

19.00

8,611.00

9,105.00

10,463.00

11,107.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

12,360.00

12,680.00

122.00
95.00

180.00

223.00
206.00

91.00

61.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

1,685.00

57.00
92.00
112.00

9,465.00
9,079.00
10,259.00

10,258.00
11,434.00
11,265.00

45.00

21.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

15,255.00

15,255.00

11,343.00

11,343.00

11,565.00

78.00

90.00

118.00

151.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

10,717.00
13,751.00
15,438.00

11,926.00

12,188.00

5,637.00

9,326.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

5,638.00

8,689.00

8,785.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

8,193.00

1,045.00

171.00

7,450.00

9.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
9.00
9.00
9.00
9.00
259.00
2,351.00

13.00

13.00

13.00

13.00

426.00
467.00
633.00
695.00
737.00
820.00
882.00
1,048.00
1,151.00
1,479.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
1,754.00
1,980.00
2,084.00
2,266.00

249.00

215.00

16,728.00

4,397.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

3,055.00

4,252.00

5,688.00

4,635.00

3,578.00

5,026.00

6,757.00

5,467.00

4,013.00

5,189.00

6,533.00

5,466.00

4,719.00

6,130.00

7,722.00

6,448.00

4,761.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
6,166.00

7,030.00

6,166.00

5,601.00

7,299.00

8,362.00

7,795.00

2,964.00
2,012.00

2,339.00

249.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

215.00

119.00

78.00

44.00

249.00
322.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
259.00
434.00

1.60

1.00

9,152.00
6,586.00
5,577.00
4,753.00
13,925.00
9,271.00
7,442.00
5,946.00
9,636.00
7,802.00
6,108.00
5,826.00
6,673.00
14,508.00
9,599.00
7,670.00

13,506.00

14,338.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

77,459.00
10,526.00

97.00

97.00

105.00

182.00
151.00

128.00
139.00

578.00

7,206.00
4,026.00
1,166.00

540.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

1,219.00

362.00

599.00

869.00
1,258.00

2,248.00

5,567.00

3,126.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
3,159.00

3,356.00
3,392.00

4,054.00

5,091.00

2,882.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

3,683.00

1,331.00

25,973.00
25,864.00

18,399.00

3,893.00
7,917.00
11,686.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

6,868.00

1,467.00

1,828.00
2,143.00

6,995.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

242.00

797.00

199.00

7,893.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

4,262.00

6,502.00

1,842.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

13,207.00

837.00

3,245.00

596.00

627.00

826.00

1.00
1.00
1.00
1.00
1.00
1.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00

1.00
1.00
1.00
1.00
1.00

1.00
1.00

1.00
1.00
1.00
1.00
1.00

1.00
1.00

1.00
1.00
1.00

1.00
1.00
1.00

1.00
1.00
1.00
1.00

29.00
1.00
1.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

3,025.00

3,248.00

231.00
297.00
396.00

146.00
162.00
181.00

330.00
766.00

730.00
395.00

1,195.00

1,278.00
511.00
3,087.00

5,819.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

8,538.00
9,498.00
11,430.00

17,726.00
19,694.00
23,219.00

7,805.00
8,176.00

8,254.00
8,639.00

8,299.00
8,708.00

8,631.00
9,012.00

8,857.00
9,266.00

63,391.00

189.00

122.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

46.00

191.00

510.00
510.00

5.00

5.00
45.00

78.00

90.00

118.00
151.00

92.00
57.00
57.00

122.00
95.00

1,082.00

50.00

66.00

111.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

175.00

8.00

11.00

3,077.00

4,188.00

466.00

467.00
4,286.00
147,706.00

44.00

61.00
110.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

60.00

270.00

68.00

326.00

327.00

296.00
117,587.00

367,994.00

1,812.00

27.00

370.00

4,928.00

370.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

1,533.00

30.00

711.00

1,309.00

12,066.00

3,041.00

3,991.00

248,860.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

136,980.00

248.00
319.00
425.00

157.00
173.00
194.00

354.00
821.00

429.00

1,087.00

1,369.00
547.00
1,180.00

6,235.00

3,328.00

6,235.00

6,249.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
6,765.00
7,517.00
6,244.00
6,056.00

6,604.00
5,926.00

7,892.00
8,282.00

8,361.00
8,751.00

8,764.00
9,178.00

8,739.00
9,129.00

8,972.00
9,387.00

8,775.00
9,164.00

9,092.00
9,506.00

9,303.00
9,717.00

9,760.00
10,174.00

9,958.00
10,372.00

319,415.00
1,091,423.00

4,599.00

135,841.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

9,113.00
9,519.00

9,766.00
10,172.00

9,904.00
10,310.00

10,148.00
10,554.00

10,675.00
11,081.00

7,810.00
8,208.00

8,306.00
8,704.00

8,354.00
8,726.00

8,706.00
9,104.00

8,952.00
9,324.00

8,743.00
9,141.00

9,079.00
9,451.00

9,302.00
9,674.00

9,786.00
10,158.00

7,961.00
8,392.00

8,342.00
8,773.00

8,378.00
8,809.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

8,771.00
9,202.00

7,583.00
7,993.00

7,946.00
8,356.00

7,981.00
8,390.00

7,589.00
7,964.00

8,040.00
8,415.00

8,403.00
8,778.00

8,280.00
8,812.00

8,410.00
8,780.00

8,976.00
9,346.00

9,096.00
9,465.00

9,303.00
9,676.00

9,764.00
10,134.00

9,962.00
10,331.00

5,651.00
7,858.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

10,379.00

19,471.00
3,894.00

46,262.00
9,253.00

7,841.00
17,499.00

23,112.00
1,156.00

43,352.00
2,168.00
10,838.00

102,998.00
5,150.00
20,600.00

43,682.00

44,573.00

32,480.00

16,510.00
10,859.00
14,342.00
717.00

26,902.00
5,381.00

63,918.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
12,784.00

10,859.00
17,448.00

23,043.00
1,152.00

43,222.00
2,161.00
10,806.00

102,691.00
5,135.00
20,538.00

55,683.00

57,401.00

80,118.00

10,065.00
12,272.00

16,206.00

30,395.00
6,079.00

72,214.00
14,443.00

13,261.00
18,472.00

24,397.00
1,220.00

45,763.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
2,288.00
11,441.00

108,726.00
5,436.00
21,745.00

69,278.00

73,385.00

101,693.00

10,276.00
13,489.00

17,816.00

33,419.00
6,684.00

79,397.00
15,880.00

14,064.00
19,917.00

26,305.00
1,315.00

49,341.00
2,467.00
12,335.00

117,228.00
5,862.00
23,445.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
84,470.00

76,144.00

125,927.00

12,077.00
14,293.00

18,877.00

35,408.00
7,082.00

84,126.00
16,825.00

16,139.00
20,163.00

26,630.00
1,332.00

49,951.00
2,498.00
12,488.00

118,675.00
5,934.00
23,735.00

101,257.00

96,900.00

152,820.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

26,992.00
23,450.00

30,969.00

58,091.00

11,618.00

138,015.00
27,603.00

26,559.00
41,983.00

55,446.00
2,772.00

104,002.00
5,200.00
26,001.00

247,093.00
12,355.00
49,419.00

119,640.00

112,786.00

182,373.00

57,135.00
65,191.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

86,097.00

161,496.00
32,299.00

383,691.00

76,738.00

64,314.00
101,308.00

133,796.00
6,690.00

250,967.00
12,548.00
62,742.00

596,260.00
29,813.00
119,252.00

139,619.00

130,048.00

214,586.00

12,888.00
13,898.00

18,355.00

34,429.00
6,886.00

81,797.00
16,359.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

15,265.00
22,365.00

29,538.00
1,477.00

55,406.00
2,770.00
13,852.00

131,638.00
6,582.00
26,328.00

85,138.00

83,722.00

61,745.00

184,140.00

2,658.00

123,384.00

11,837.00

15,976.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

21,190.00

29,909.00

8,823.00

13,639.00

20,000.00

5,151.00

8,108.00

13,231.00

4,103.00

6,136.00

10,035.00

9,721.00

10,894.00

300.00
500.00
2,006.00

7,856.00
7,903.00

8,422.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
8,469.00

8,541.00
8,588.00

8,751.00
8,798.00

9,209.00
9,256.00

9,406.00
9,453.00

7,588.00
7,963.00

68,383.00

92,375.00

5,946.00

102.00

193.00

7,907.00
8,413.00
10,365.00

8,347.00

8,844.00

9,243.00

9,579.00

8,739.00

9,281.00

9,618.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

10,040.00

8,892.00

9,215.00

9,635.00

9,490.00

9,800.00

10,266.00

9,616.00

9,887.00

10,272.00

9,840.00

10,054.00

10,376.00

10,323.00

10,549.00

10,886.00

10,532.00

10,762.00

11,107.00

11,373.00

11,621.00

11,993.00

68,709.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

92,701.00

172.00

3,688.00
3,146.00

2,506.00

266.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

230.00

301.00

458.00

593.00

1.00

584.00

188.00

342.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
166,698.00

9,615.00
10,016.00
10,417.00

10,016.00
10,417.00
10,817.00

10,268.00
10,696.00
11,124.00

10,696.00
11,124.00
11,551.00

10,406.00
10,839.00
11,273.00

10,839.00
11,273.00
11,706.00

10,472.00
10,916.00
11,360.00

10,916.00
11,360.00
11,803.00

12,247.00
13,135.00
14,022.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

10,991.00
11,457.00
11,922.00

11,457.00
11,922.00
12,388.00

12,854.00
13,785.00
14,717.00

11,025.00
11,500.00
11,975.00

11,500.00
11,975.00
12,451.00

12,926.00
13,876.00
14,827.00

13,863.00
14,890.00
15,916.00

14,003.00
15,041.00
16,078.00

14,342.00
15,404.00
16,467.00

14,415.00
15,483.00
16,551.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

69,035.00

150,058.00

13,950.00

574.00

2,121.00

2,072.00

4,246.00

4,779.00

7,589.00
7,964.00

11,794.00

To be noted

60,659.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
1,591.00

107.00

2,417.00

255.00

266.00

44.00

1,569.00

37,794.00

4,567.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

11,281.00

11,173.00

11,194.00

208.00

277.00

174,295.00

248.00
319.00
425.00

157.00
173.00
40,782.81

354.00
821.00

429.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

1,087.00

1,369.00
547.00
1,180.00
8,347.00

3,328.00

6,249.00

6,765.00
7,517.00
6,244.00
6,056.00

6,604.00
5,926.00

5,946.00

102.00

203.00

6,714.00
7,805.00
9,523.00

8,347.00
8,760.00

8,844.00
9,256.00

8,892.00
9,330.00

9,243.00
9,655.00

9,490.00
9,928.00

9,281.00
9,693.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

9,616.00
10,054.00

9,840.00
10,278.00

10,323.00
11,224.00

10,104.00

10,784.00

10,898.00

11,182.00

11,731.00

68,383.00

172.00

7,589.00
7,964.00

12,336.00

875.00

13,949.00

574.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

107.00

2,417.00

255.00

266.00

44.00

3,688.00
3,146.00

2,506.00

208.00

3,932.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

3,761.00

8,448.00

3,932.00
8,448.00

2,827.00

30.00

8,672.00
10,601.00

4,618.00

6,604.00
7,892.00

4,057.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

3,602.00

3,773.00

3,534.00

1,125.00

300.00

232.00

1,525.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

224.00

285.00
281.00

2,196.00

1,418.00

557.00

638.00

202.00

526.00

426,592.00

413,981.00

378,259.00

84,446.00
5,753.00
4,675.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
652.00
1,035.00
575.00

415.00

225.00

416.00

55,382.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

6,159.00
149.00
274.00
439.00

499.00

114.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project

421.00

114.00

197.00

3,326.00

7,392.00

3,080.00

2,464.00

123,200.00
123,200.00

14,784.00
14,784.00
30,800.00
30,800.00

409.00

2,285,545.00
3,028,194.00
3,770,844.00

1,374,173.00
1,611,333.00
1,848,493.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
CHAPTER-1

CARRIAGE OF MATERIALS

Reference to Quantity For Quantity For Quantity For Amount Amount Amount
Rate Remarks/
Sr No MORT&H Description Unit Large Medium Small (Rs.) Large (Rs.) Medium (Rs.) Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project

1.01 A Loading and unloading of stone boulder / stone


aggregates / sand / kanker / moorum.
Placing tipper at loading point, loading with front end
loader, dumping, turning for return trip, excluding
time for haulage and return trip
Unit = cum
Taking output = 5.5 cum cum cum
Time required for
i) Positioning of tipper at loading point Min 1.000 1.000 1.000
ii) Loading by front end loader 1 cum bucket Min 6.633 6.633 6.633
capacity
iii) Maneuvering, reversing, dumping and turning for Min 2.000 2.000 2.000
return
iv) Waiting time, unforeseen contingencies etc Min 4.000 4.000 4.000
Total Min 13.633 13.633 13.633
a) Machinery
Tipper 5.5 cum capacity hour 0.227 0.227 0.227 1,731.45 393.04 393.04 393.04 P&M-017
Front end-loader 1 cum bucket capacity hour 0.227 0.227 0.227 1,112.00 252.42 252.42 252.42 P&M-013
Total cost Excluding OH & CP 645.46 645.46 645.46
b) Overhead Charges @ 8% on @ 10% on @ 12% on
(a) (a) (a) 51.64 64.55 77.46
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 69.71 71.00 72.29
Cost for 5.5 cum = a+b+c 766.81 781.01 795.21
Rate per cum = (a+b+c)/5.5 139.42 142.00 144.58
Say 139.00 142.00 145.00
Note Unloading will be by tipping.
1.01 B Loading and unloading of stone boulder / stone
aggregates / sand / kanker / moorum.
Placing tipper at loading point, loading with front end
loader, dumping, turning for return trip, excluding
time for haulage and return trip
Unit = cum
Taking output = 10 cum cum cum
Time required for
i) Positioning of tipper at loading point Min 1.000 1.000 1.000
ii) Loading by front end loader 1 cum bucket Min 12.060 12.060 12.060
capacity
iii) Maneuvering, reversing, dumping and turning for Min 2.000 2.000 2.000
return
iv) Waiting time, unforeseen contingencies etc Min 4.000 4.000 4.000
Total Min 19.060 19.060 19.060
a) Machinery
Tipper 10 cum capacity hour 0.318 0.318 0.318 2,274.30 723.23 723.23 723.23 P&M-016
Front end-loader 1 cum bucket capacity hour 0.318 0.318 0.318 1,112.00 353.62 353.62 353.62 P&M-013
Total cost Excluding OH & CP 1076.84 1076.84 1076.84
b) Overhead Charges @ 8% on @ 10% on @ 12% on
(a) (a) (a) 86.15 107.68 129.22
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 116.30 118.45 120.61
Cost for 10 cum = a+b+c 1,279.29 1,302.98 1,326.67
Rate per cum = (a+b+c)/10 127.93 130.30 132.67
Say 128.00 130.00 133.00
Note Unloading will be by tipping.

1.01 C Loading and unloading of stone boulder / stone


aggregates / sand / kanker / moorum.
Placing tipper at loading point, loading with front end
loader, dumping, turning for return trip, excluding
time for haulage and return trip
Unit : cum
Taking output = 14.00 cum cum cum
Time required for
i) Positioning of tipper at loading point Min 1.000 1.000 1.000
ii) Loading by front end loader 2.1 cum bucket Min 8.029 8.029 8.029
capacity
iii) Maneuvering, reversing, dumping and turning for Min 2.000 2.000 2.000
return
iv) Waiting time, unforeseen contingencies etc Min 4.000 4.000 4.000
Total Min 15.029 15.029 15.029
a) Machinery
Tipper 14 cum capacity hour 0.250 0.250 0.250 2,556.75 639.19 639.19 639.19 P&M-015
Front end-loader 2.1 cum bucket capacity hour 0.250 0.250 0.250 2,640.75 660.19 660.19 660.19 P&M-012
Total cost Excluding OH & CP 1299.38 1299.38 1299.38
b) Overhead Charges @ 8% on @ 10% on @ 12% on
(a) (a) (a) 103.95 129.94 155.93
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 140.33 142.93 145.53
Cost for 14 cum = a+b+c 1,543.66 1,572.24 1,600.83
Reference to Quantity For Quantity For Quantity For Amount Amount Amount
Rate Remarks/
Sr No MORT&H Description Unit Large Medium Small (Rs.) Large (Rs.) Medium (Rs.) Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project

Rate per cum = (a+b+c)/14 110.26 112.30 114.35


Say 110.00 112.00 114.00
Note Unloading will be by tipping.

1.01 D Loading and unloading of stone boulder / stone


aggregates / sand / kanker / moorum.
Placing tipper at loading point, loading with front end
loader, dumping, turning for return trip, excluding
time for haulage and return trip
Unit : cum
Taking output = 18 cum cum cum
Time required for
i) Positioning of tipper at loading point Min 1.00 1.00 1.00
ii) Loading by front end loader 3.1 cum bucket Min 7.00 7.00 7.00
capacity
iii) Maneuvering, reversing, dumping and turning for Min 2.00 2.00 2.00
return
iv) Waiting time, unforeseen contingencies etc Min 4.00 4.00 4.00
Total Min 14.00 14.00 14.00
a) Machinery
Tipper 18 cum capacity hour 0.23 0.23 0.23 2,883.30 671.81 671.81 671.81 P&M-014
Front end-loader 3.1 cum bucket capacity hour 0.23 0.23 0.23 4,279.80 997.19 997.19 997.19 P&M-011
Total cost Excluding OH & CP 1669.00 1669.00 1669.00
b) Overhead Charges @ 8% on @ 10% on @ 12% on
(a) (a) (a) 133.52 166.90 200.28
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 180.25 183.59 186.93
Cost for 18 cum = a+b+c 1,982.77 2,019.49 2,056.21
Rate per cum = (a+b+c)/18 110.15 112.19 114.23
Say 110.00 112.00 114.00
Note Unloading will be by tipping.

1.02 Loading and Unloading of Boulders by Manual


Means
Unit = cum
Taking output = 10 cum cum cum
a) Labour
Mate day 0.055 0.055 0.055 617.00 33.65 33.65 33.65 L-12
Mazdoor for loading and unloading day 1.364 1.364 1.364 511.52 697.53 697.53 697.53 L-13
b) Machinery
Tipper 10 Cum capacity hour 1.364 1.364 1.364 2,274.30 3,102.15 3,102.15 3,102.15 P&M-016
Total cost Excluding OH & CP 3833.33 3833.33 3833.33
b) Overhead Charges @ 8% on @ 10% on @ 12% on
(a) (a) (a) 306.67 383.33 460.00
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 414.00 421.67 429.33
Cost for 10 cum = a+b+c+d 4,553.99 4,638.33 4,722.66
Rate per cum = (a+b+c+d)/10 455.40 463.83 472.27
Say 455.00 464.00 472.00
Note Unloading will be by tipping.

1.03 Loading and Unloading of Cement or Steel by


Manual Means and Stacking.
Unit = tonne
Taking output = 18 tonne tonne tonne
a) Labour
Mate day 0.144 0.144 0.144 617.00 88.85 88.85 88.85 L-12
Mazdoor for loading and unloading day 3.600 3.600 3.600 511.52 1,841.47 1,841.47 1,841.47 L-13
b) Machinery
Truck 18 tonne capacity hour 3.600 3.600 3.600 2,274.30 8,187.48 8,187.48 8,187.48 P&M-016
Total cost Excluding OH & CP 10117.80 10117.80 10117.80
b) Overhead Charges @ 8% on @ 10% on @ 12% on
(a) (a) (a) 809.42 1,011.78 1,214.14
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 1,092.72 1,112.96 1,133.19
Cost for 18 tonnes = a+b+c+d 12,019.95 12,242.54 12,465.13
Rate per tonnes = (a+b+c+d)/18 667.77 680.14 692.51
Say 668.00 680.00 693.00

1.04 (i) Cost of Haulage Excluding Loading and Unloading

A Case-I : Surfaced Road


Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit : t.km
Taking output 10 tonnes load and lead 10 km = 100 t.km t.km t.km

Speed with load : 25 km / hour.


Speed while Returning empty : 35 km / hour.
a) Machinery.
i) Tipper 10 tonne capacity P&M-017
Time taken for onward haulage with load hour 0.400 0.400 0.400 1,731.45 692.58 692.58 692.58 P&M-017
Reference to Quantity For Quantity For Quantity For Amount Amount Amount
Rate Remarks/
Sr No MORT&H Description Unit Large Medium Small (Rs.) Large (Rs.) Medium (Rs.) Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project

Time taken for empty return trip. hour 0.286 0.286 0.286 1,731.45 494.70 494.70 494.70 P&M-017
Total cost Excluding OH & CP 1187.28 1187.28 1187.28
b) Overhead Charges @ 8% on @ 10% on @ 12% on
(a) (a) (a) 94.98 118.73 142.47
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 128.23 130.60 132.98
cost for 100 t km = a+b+c 1,410.49 1,436.61 1,462.73
Rate per t.km = (a+b+c)/100 14.10 14.37 14.63
Say 14.00 14.00 15.00
B Case-I : Surfaced Road
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit : t.km
Taking output 18 tonnes load and lead 10 km = 180 t.km t.km t.km

Speed with load : 25 km / hour.


Speed while Returning empty : 35 km / hour.
a) Machinery.
i) Tipper 18 tonne capacity P&M-016
Time taken for onward haulage with load hour 0.400 0.400 0.400 2,274.30 909.72 909.72 909.72 P&M-016
Time taken for empty return trip. hour 0.286 0.286 0.286 2,274.30 649.80 649.80 649.80 P&M-016
Total cost Excluding OH & CP 1559.52 1559.52 1559.52
b) Overhead Charges @ 8% on @ 10% on @ 12% on
(a) (a) (a) 124.76 155.95 187.14
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 168.43 171.55 174.67
cost for 180 t km = a+b+c 1,852.71 1,887.02 1,921.33
Rate per t.km = (a+b+c)/180 10.29 10.48 10.67
Say 10.00 10.00 11.00

C Case-I : Surfaced Road


Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit : t.km
Taking output 25 tonnes load and lead 10 km = 250 t.km t.km t.km

Speed with load : 25 km / hour.


Speed while Returning empty : 35 km / hour.
a) Machinery.
i) Tipper 25 tonne capacity P&M-015
Time taken for onward haulage with load hour 0.400 0.400 0.400 2,556.75 1,022.70 1,022.70 1,022.70 P&M-015
Time taken for empty return trip. hour 0.286 0.286 0.286 2,556.75 730.50 730.50 730.50 P&M-015
Total cost Excluding OH & CP 1753.20 1753.20 1753.20
b) Overhead Charges @ 8% on @ 10% on @ 12% on
(a) (a) (a) 140.26 175.32 210.38
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 189.35 192.85 196.36
cost for 250 t km = a+b+c 2,082.80 2,121.37 2,159.94
Rate per t.km = (a+b+c)/250 8.33 8.49 8.64
Say 8.00 8.00 9.00

D Case-I : Surfaced Road


Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit : t.km
Taking output 32 tonnes load and lead 10 km = 320 t.km t.km t.km

Speed with load : 25 km / hour.


Speed while Returning empty : 35 km / hour.
a) Machinery.
i) Tipper 32 tonne capacity P&M-014
Time taken for onward haulage with load hour 0.400 0.400 0.400 2,883.30 1,153.32 1,153.32 1,153.32 P&M-014
Time taken for empty return trip. hour 0.286 0.286 0.286 2,883.30 823.80 823.80 823.80 P&M-014
Total cost Excluding OH & CP 1977.12 1977.12 1977.12
b) Overhead Charges @ 8% on @ 10% on @ 12% on
(a) (a) (a) 158.17 197.71 237.25
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 213.53 217.48 221.44
cost for 320 t km = a+b+c 2,348.82 2,392.32 2,435.81
Rate per t.km = (a+b+c)/320 7.34 7.48 7.61
Say 7.00 7.00 8.00

1.04 (ii) A Case-II : Unsurfaced Gravelled Road


Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit : t.km
Taking output 10 tonnes load and lead 10 km = 100 t.km t.km t.km

Speed with load : 20 km / hour


Speed for empty return trip : 30 km / hour
a)Machinery
Tipper 10 tonnes capacity P&M-017
Reference to Quantity For Quantity For Quantity For Amount Amount Amount
Rate Remarks/
Sr No MORT&H Description Unit Large Medium Small (Rs.) Large (Rs.) Medium (Rs.) Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project

Time taken for onward hanlage with load hour 0.500 0.500 0.500 1,731.45 865.73 865.73 865.73 P&M-017
Time taken for empty return trip hour 0.333 0.333 0.333 1,731.45 577.15 577.15 577.15 P&M-017
Total cost Excluding OH & CP 1442.88 1442.88 1442.88
b) Overhead Charges @ 8% on @ 10% on @ 12% on
(a) (a) (a) 115.43 144.29 173.15
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 155.83 158.72 161.60
Cost for 100 t .km = a+b+c 1,714.14 1,745.88 1,777.62
Rate per t.Km = (a+b+c)/100 17.14 17.46 17.78
Say 17.00 17.00 18.00
1.04 (ii) B Case-II : Unsurfaced Gravelled Road
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit : t.km
Taking output 18 tonnes load and lead 10 km = 180 t.km t.km t.km

Speed with load : 20 km / hour


Speed for empty return trip : 30 km / hour
a)Machinery
Tipper 18 tonnes capacity P&M-016
Time taken for onward hanlage with load hour 0.500 0.500 0.500 2,274.30 1,137.15 1,137.15 1,137.15 P&M-016
Time taken for empty return trip hour 0.333 0.333 0.333 2,274.30 758.10 758.10 758.10 P&M-016
Total cost Excluding OH & CP 1895.25 1895.25 1895.25
b) Overhead Charges @ 8% on @ 10% on @ 12% on
(a) (a) (a) 151.62 189.53 227.43
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 204.69 208.48 212.27
Cost for 180 t .km = a+b+c 2,251.56 2,293.25 2,334.95
Rate per t.Km = (a+b+c)/180 12.51 12.74 12.97
Say 13.00 13.00 13.00

1.04 (ii) C Case-II : Unsurfaced Gravelled Road


Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit : t.km
Taking output 25 tonnes load and lead 10 km = 250 t.km t.km t.km

Speed with load : 20 km / hour


Speed for empty return trip : 30 km / hour
a)Machinery
Tipper 25 tonnes capacity P&M-015
Time taken for onward hanlage with load hour 0.500 0.500 0.500 2,556.75 1,278.38 1,278.38 1,278.38 P&M-015
Time taken for empty return trip hour 0.333 0.333 0.333 2,556.75 852.25 852.25 852.25 P&M-015
Total cost Excluding OH & CP 2130.63 2130.63 2130.63
b) Overhead Charges @ 8% on @ 10% on @ 12% on
(a) (a) (a) 170.45 213.06 255.68
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 230.11 234.37 238.63
Cost for 250 t .km = a+b+c 2,531.18 2,578.06 2,624.93
Rate per t.Km = (a+b+c)/250 10.12 10.31 10.50
Say 10.00 10.00 10.00

1.04 (ii) D Case-II : Unsurfaced Gravelled Road


Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit : t.km
Taking output 32 tonnes load and lead 10 km = 320 t.km t.km t.km

Speed with load : 20 km / hour


Speed for empty return trip : 30 km / hour
a)Machinery
Tipper 32 tonnes capacity P&M-014
Time taken for onward hanlage with load hour 0.500 0.500 0.500 2,883.30 1,441.65 1,441.65 1,441.65 P&M-014
Time taken for empty return trip hour 0.333 0.333 0.333 2,883.30 961.10 961.10 961.10 P&M-014
Total cost Excluding OH & CP 2402.75 2402.75 2402.75
b) Overhead Charges @ 8% on @ 10% on @ 12% on
(a) (a) (a) 192.22 240.28 288.33
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 259.50 264.30 269.11
Cost for 320 t .km = a+b+c 2,854.47 2,907.33 2,960.19
Rate per t.Km = (a+b+c)/320 8.92 9.09 9.25
Say 9.00 9.00 9.00

1.04 (iii) A Case-III : Katcha Track and Track in river bed /


nallah bed and choe bed.
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit : t.km
Taking output 10 tonnes load and lead 10 km = 100 t.km t.km t.km

Speed with load : 10 km / hour


Speed while returning empty : 15 km / hour
Reference to Quantity For Quantity For Quantity For Amount Amount Amount
Rate Remarks/
Sr No MORT&H Description Unit Large Medium Small (Rs.) Large (Rs.) Medium (Rs.) Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project

a) Machinery
I) Tipper 10 tonnes capacity P&M-017
Time taken for onward haulage hour 1.000 1.000 1.000 1,731.45 1,731.45 1,731.45 1,731.45 P&M-017
Time taken for empty return trip hour 0.667 0.667 0.667 1,731.45 1,154.30 1,154.30 1,154.30 P&M-017
Total cost Excluding OH & CP 2885.75 2885.75 2885.75
b) Overhead Charges @ 8% on @ 10% on @ 12% on
(a) (a) (a) 230.86 288.58 346.29
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 311.66 317.43 323.20
Cost for 100 t .km = a+b+c 3,428.27 3,491.76 3,555.24
Rate per t.Km = (a+b+c)/100 34.28 34.92 35.55
Say 34.00 35.00 36.00
1.04 (iii) B Case-III : Katcha Track and Track in river bed /
nallah bed and choe bed.
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit : t.km
Taking output 18 tonnes load and lead 10 km = 180 t.km t.km t.km

Speed with load : 10 km / hour


Speed while returning empty : 15 km / hour
a) Machinery
I) Tipper 18 tonnes capacity P&M-016
Time taken for onward haulage hour 1.000 1.000 1.000 2,274.30 2,274.30 2,274.30 2,274.30 P&M-016
Time taken for empty return trip hour 0.667 0.667 0.667 2,274.30 1,516.20 1,516.20 1,516.20 P&M-016
Total cost Excluding OH & CP 3790.50 3790.50 3790.50
b) Overhead Charges @ 8% on @ 10% on @ 12% on
(a) (a) (a) 303.24 379.05 454.86
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 409.37 416.96 424.54
Cost for 180 t .km = a+b+c 4,503.11 4,586.51 4,669.90
Rate per t.Km = (a+b+c)/180 25.02 25.48 25.94
Say 25.00 25.00 26.00

1.04 (iii) C Case-III : Katcha Track and Track in river bed /


nallah bed and choe bed.
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit : t.km
Taking output 25 tonnes load and lead 10 km = 250 t.km t.km t.km

Speed with load : 10 km / hour


Speed while returning empty : 15 km / hour
a) Machinery
I) Tipper 18 tonnes capacity P&M-015
Time taken for onward haulage hour 1.000 1.000 1.000 2,556.75 2,556.75 2,556.75 2,556.75 P&M-015
Time taken for empty return trip hour 0.667 0.667 0.667 2,556.75 1,704.50 1,704.50 1,704.50 P&M-015
Total cost Excluding OH & CP 4261.25 4261.25 4261.25
b) Overhead Charges @ 8% on @ 10% on @ 12% on
(a) (a) (a) 340.90 426.13 511.35
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 460.22 468.74 477.26
Cost for 250 t .km = a+b+c 5,062.37 5,156.11 5,249.86
Rate per t.Km = (a+b+c)/250 20.25 20.62 21.00
Say 20.00 21.00 21.00

1.04 (iii) D Case-III : Katcha Track and Track in river bed /


nallah bed and choe bed.
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit : t.km
Taking output 32 tonnes load and lead 10 km = 320 t.km t.km t.km

Speed with load : 10 km / hour


Speed while returning empty : 15 km / hour
a) Machinery
I) Tipper 32 tonnes capacity P&M-014
Time taken for onward haulage hour 1.000 1.000 1.000 2,883.30 2,883.30 2,883.30 2,883.30 P&M-014
Time taken for empty return trip hour 0.667 0.667 0.667 2,883.30 1,922.20 1,922.20 1,922.20 P&M-014
Total cost Excluding OH & CP 4805.50 4805.50 4805.50
b) Overhead Charges @ 8% on @ 10% on @ 12% on
(a) (a) (a) 384.44 480.55 576.66
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 518.99 528.61 538.22
Cost for 320 t .km = a+b+c 5,708.93 5,814.66 5,920.38
Rate per t.Km = (a+b+c)/320 17.84 18.17 18.50
Say 18.00 18.00 19.00

1.04 (iv) Case-IV : Katcha Track in hilly area.


Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit : t.km
Reference to Quantity For Quantity For Quantity For Amount Amount Amount
Rate Remarks/
Sr No MORT&H Description Unit Large Medium Small (Rs.) Large (Rs.) Medium (Rs.) Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project

Taking output 10 tonnes load and lead 10 km = 100 t.km t.km t.km

Speed with load : 5 km / hour


Speed while returning empty : 7 km / hour
a) Machinery
I) Tipper 10 tonnes capacity P&M-017
Time taken for onward haulage hour 2.000 2.000 2.000 1,731.45 3,462.90 3,462.90 3,462.90 P&M-017
Time taken for empty return trip hour 1.429 1.429 1.429 1,731.45 2,473.50 2,473.50 2,473.50 P&M-017
Total cost Excluding OH & CP 5936.40 5936.40 5936.40
b) Overhead Charges @ 8% on @ 10% on @ 12% on
(a) (a) (a) 474.91 593.64 712.37
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 641.13 653.00 664.88
Cost for 100 t .km = a+b+c 7,052.44 7,183.04 7,313.64
Rate per t.Km = (a+b+c)/100 70.52 71.83 73.14
Say 71.00 72.00 73.00

1.04 (v) Case-V : Transit Mixture


Haulage of concrete by Transit mixture excluding
cost of loading, unloading and stacking.

Unit : t.km
Taking output 15 tonnes load and lead 10 km = 150 t.km t.km t.km

Speed with load : 20 km / hour


Speed while returning empty : 30 km / hour
a) Machinery
I) Transit Mixture 6 cum capacity P&M-067
Time taken for onward hanlage with load hour 0.500 0.500 0.500 2,413.95 1,206.98 1,206.98 1,206.98 P&M-067
Time taken for empty return trip hour 0.333 0.333 0.333 2,413.95 804.65 804.65 804.65 P&M-067
Total cost Excluding OH & CP 2011.63 2011.63 2011.63
b) Overhead Charges @ 8% on @ 10% on @ 12% on
(a) (a) (a) 160.93 201.16 241.40
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 217.26 221.28 225.30
Cost for 150 t .km = a+b+c 2,389.81 2,434.07 2,478.32
Rate per t.Km = (a+b+c)/150 15.93 16.23 16.52
Say 16.00 16.00 17.00

1.05 Hand Broken Stone Aggregates 63 mm nominal size

Supply of quarried stone, hand breaking into coarse


aggregate 63 mm nominal size (passing 80 mm and
retained on 50 mm sieve) and stacking as
directed
Unit : cum
Taking output 1.0 cum cum cum
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Mazdoor day 1.500 1.500 1.500 511.52 767.28 767.28 767.28 L-13
b) Material
Supply of quarried stone 150 - 200 mm size cum 1.100 1.100 1.100 1,472.59 1,619.85 1,619.85 1,619.85 M-002
Total cost Excluding OH & CP 2424.15 2424.15 2424.15
b) Overhead Charges @ 8% on @ 10% on @ 12% on
(a) (a) (a) 193.93 242.41 290.90
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 261.81 266.66 271.50
Rate per cum = a+b+c+d 2,879.89 2,933.22 2,986.55
2,879.89 2,933.22 2,986.55
Say 2,880.00 2,933.00 2,987.00
1.06 Crushing of stone aggregates (Nominal size)
Crushing of stone boulders of 150 mm size in an
integrated stone crushing unit of 250 tonnes per
hour capacity comprising of primary and secondary
crushing units, belt conveyor and vibrating screens
to obtain stone aggregates of different nominal size.

Unit : cum
Taking Output = 1125 tonne tonne tonne (750 cum)

a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mazdoor Skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
b) Material
Stone Boulder of size 150 mm and below cum 750.000 750.000 750.000 1,472.59 1,104,442.95 1,104,442.95 1,104,442.95 M-001
c) Machinery
Integrated stone crusher of 250 TPH including belt Hour
conveyor and vibrating screens 6.000 6.000 6.000 15,481.20 92,887.20 92,887.20 92,887.20 P&M-031
Generator 725 KVA Hour 6.000 6.000 6.000 11,596.20 69,577.20 69,577.20 69,577.20 P&M-043
Front end loader 3.1 cum bucket capacity at quarry Hour
and crusher 5.515 5.515 5.515 4,279.80 23,603.10 23,603.10 23,603.10 P&M-011
Reference to Quantity For Quantity For Quantity For Amount Amount Amount
Rate Remarks/
Sr No MORT&H Description Unit Large Medium Small (Rs.) Large (Rs.) Medium (Rs.) Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project

Tipper 14 cum capacity for loading at quarry site Hour


5.515 5.515 5.515 2,556.75 14,100.48 14,100.48 14,100.48 P&M-015
Tipper 14 cum capacity for transportation within 1
km t.km 1125.000 1125.000 1125.000 7.01 7,889.40 7,889.40 7,889.40 P&M-119
d) Cost for 750 cum = (a+b+c) 1,316,898.35 1,316,898.35 1,316,898.35
e) Crushing Pattern
40 mm (tonne) 22.71% 255.488 255.488 255.488
20 mm (tonne) 23.00% 258.750 258.750 258.750
10 mm (tonne) 25.86% 290.925 290.925 290.925
Dust (tonne) 28.43% 319.838 319.838 319.838
f) % Cost distribution { (d) x (f) / (e ) x 1.5 }
40 mm Cum 28.98% 28.98% 28.98% 2,240.64 2,240.64 2,240.64 Basic Cost
20 mm Cum 31.95% 31.95% 31.95% 2,439.12 2,439.12 2,439.12 Basic Cost
10 mm Cum 30.75% 30.75% 30.75% 2,087.89 2,087.89 2,087.89 Basic Cost
Dust Cum 8.32% 8.32% 8.32% 513.85 513.85 513.85 Basic Cost
g) Overhead Charges
40 mm @ 8% on (f) @ 10% on (f) @ 12% on
(f) 179.25 224.06 268.88
20 mm 0.080 0.100 0.120 195.13 243.91 292.69
10 mm 0.080 0.100 0.120 167.03 208.79 250.55
Dust 0.080 0.100 0.120 41.11 51.39 61.66
h) Contractor's profit @ 10% on @ 10% on @ 10% on
(f+g) (f+g) (f+g)
40 mm 241.99 246.47 250.95
20 mm 263.43 268.30 273.18
10 mm 225.49 229.67 233.84
Dust 55.50 56.52 57.55
i) Rate per cum = (f+g+h)
40 mm 2,661.88 2,711.17 2,760.46
20 mm 2,897.68 2,951.34 3,005.00
10 mm 2,480.41 2,526.35 2,572.28
Dust 610.45 621.76 633.06
Say 2,662.00 2,711.00 2,760.00
Say 2,898.00 2,951.00 3,005.00
Say 2,480.00 2,526.00 2,572.00
Say 610.00 622.00 633.00
Note: The average density of 1.5 tonne/cum is only a
reference density in this Data Book.

1.7 Crushing of stone aggregates (GSB Crusher Run)

Crushing of stone boulders of 150 mm size in an


integrated stone crushing unit of 250 tonnes per
hour capacity comprising of primary and secondary
crushing units, belt conveyor and vibrating screens
to obtain crusher run (all in aggregate) for GSB.

Unit : cum
Taking Output = 1125 tonne tonne tonne (750 cum)

a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mazdoor Skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
b) Material
Stone Boulder of size 150 mm and below cum 750.000 750.000 750.000 1,472.59 1,104,442.95 1,104,442.95 1,104,442.95 M-001
c) Machinery
Integrated stone crusher of 250 TPH including belt
conveyor and vibrating screens (for producing
crusher run production capacity will increas by 30%) Hour 4.615 4.615 4.615 15,481.20 71,445.74 71,445.74 71,445.74 P&M-031

Generator 725 KVA Hour 4.615 4.615 4.615 11,596.20 53,516.46 53,516.46 53,516.46 P&M-043
Front end loader 3.1 cum bucket capacity at quarry
and crusher Hour 5.515 5.515 5.515 4,279.80 23,603.10 23,603.10 23,603.10 P&M-011
Tipper 14 cum capacity for loading at quarry site
Hour 5.515 5.515 5.515 2,556.75 14,100.48 14,100.48 14,100.48 P&M-015
Tipper 14 cum capacity for transportation within 1
km t.km 1125.000 1125.000 1125.000 7.01 7,889.40 7,889.40 7,889.40 P&M-119

d) Overheads @ 8% on (a+b+c) @ 8% on @ 10% on @ 12% on


(a+b+c) (a+b+c) (a+b+c) 102,351.69 127,939.61 153,527.54

e) Contractors profit @ 10% on (a+b+c+d) @ 10% on @ 10% on @ 10% on


(a+b+c+d) (a+b+c+d) (a+b+c+d) 138,174.78 140,733.58 143,292.37
Cost for 900 cum = (a+b+c+d+e) 1,519,922.62 1,548,069.34 1,576,216.05
Rate per cum = (a+b+c+d+e)/900 1,688.80 1,720.08 1,751.35
Say 1,689.00 1,720.00 1,751.00
Note: Considering Crushed volume will be 1.2 times the
volume of boulder
CHAPTER-2
SITE CLEARANCE
Quantity Amount (Rs.)
Ref.to
Rate Remarks
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project /Input ref.
Specification Project Project Project Project

2.01 201 A Cutting of trees, excluding removal of stumps and roots


of trees
Cutting of trees stacking of serviceable material with all
lifts and up to a lead of 1000 metres.
(i) Girth from 300 mm to 600 mm
Unit = Each
Taking output = 40 nos
a) Labour
Mate day 0.960 0.960 0.960 617.00 592.32 592.32 592.32 L-12
Mazdoors day 24.000 24.000 24.000 511.52 12,276.48 12,276.48 12,276.48 L-13
b) Machinery
Tipper
(i) 18 cum capacity hour 1.600 2,883.30 4,613.28 P&M-014
(ii) 14 cum capacity hour 2.000 2,556.75 5,113.50 P&M-015
(iii) 10 cum capacity hour 2.667 2,274.30 6,064.80 P&M-016
Sundries @ 1% of lobour cost (a) 128.69 128.69 128.69
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 1,408.86 1,811.10 2,287.47
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 1,901.96 1,992.21 2,134.98
Rate for each tree = (a+b+c+d)/40 523.04 547.86 587.12
Say 523.00 548.00 587.00
(ii) Girth from 600 mm to 900 mm
Unit = Each
Taking output = 30 nos
a) Labour
Mate day 1.080 1.080 1.080 617.00 666.36 666.36 666.36 L-12
Mazdoors day 27.000 27.000 27.000 511.52 13,811.04 13,811.04 13,811.04 L-13
b) Machinery
Tipper
(i) 18 cum capacity hour 1.500 2,883.30 4,324.95 P&M-014
(ii) 14 cum capacity hour 2.000 2,556.75 5,113.50 P&M-015
(iii) 10 cum capacity hour 3.750 2,274.30 8,528.63 P&M-016
Sundries @ 1% of lobour cost (a) 144.77 144.77 144.77
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 1,515.77 1,973.57 2,778.10
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 2,046.29 2,170.92 2,592.89
Rate for each tree = (a+b+c+d)/30 750.31 796.01 950.73
Say 750.00 796.00 951.00
(iii) Girth from 900 mm to 1800 mm
Unit = Each
Taking output = 25 nos
a) Labour
Mate day 2.000 2.000 2.000 617.00 1,234.00 1,234.00 1,234.00 L-12
Mazdoors day 50.000 50.000 50.000 511.52 25,576.00 25,576.00 25,576.00 L-13
b) Machinery
Tipper
(i) 18 cum capacity hour 1.250 2,883.30 3,604.13 P&M-014
(ii) 14 cum capacity hour 1.667 2,556.75 4,261.25 P&M-015
(iii) 10 cum capacity hour 3.125 2,274.30 7,107.19 P&M-016
Sundries @ 1% of lobour cost (a) 268.10 268.10 268.10
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 2,454.58 3,133.94 4,102.23
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 3,313.68 3,447.33 3,828.75
Rate for each tree = (a+b+c+d)/25 1,458.02 1,516.82 1,684.65
Say 1,458.00 1,517.00 1,685.00
(iv) Girth above 1800 mm
Unit = Each
Taking output = 20 nos
a) Labour
Mate day 3.200 3.200 3.200 617.00 1,974.40 1,974.40 1,974.40 L-12
Mazdoors day 80.000 80.000 80.000 511.52 40,921.60 40,921.60 40,921.60 L-13
b) Machinery
Tipper
(i) 18 cum capacity hour 1.667 2,883.30 4,805.50 P&M-014
(ii) 14 cum capacity hour 2.500 2,556.75 6,391.88 P&M-015
(iii) 10 cum capacity hour 5.000 2,274.30 11,371.50 P&M-016
Quantity Amount (Rs.)
Ref.to
Rate Remarks
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project /Input ref.
Specification Project Project Project Project

Sundries @ 1% of lobour cost (a) 428.96 428.96 428.96


c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 3,850.44 4,971.68 6,563.58
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 5,198.09 5,468.85 6,126.00
Rate for each tree = (a+b+c+d)/20 2,858.95 3,007.87 3,369.30
Say 2,859.00 3,008.00 3,369.00
All the serviceable material resulting from tree cutting
Note: would be handed over to the employer for the all above
items.
2.01 201 B Removal of stumps and roots including backfilling with
suitable material to required compaction

Removal of stumps, roots, stacking of serviceable


material with all lifts and up to a lead of 1000 metres
and earth filling in the depression/pit.

(i) Girth from 300 mm to 600 mm


Unit = Each
Taking output = 40 nos
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoors day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 5.000 3,420.00 17,100.00 P&M-007
(ii) 1.1 cum bucket capacity hour 5.500 3,074.00 16,907.00 P&M-008
(iii) 0.9 cum bucket capacity hour 6.500 2,782.00 18,083.00 P&M-009
Tipper
(i) 18 cum capacity hour 0.727 2,883.30 2,096.95 P&M-014
(ii) 14 cum capacity hour 1.000 2,556.75 2,556.75 P&M-015
(iii) 10 cum capacity hour 1.333 2,274.30 3,032.40 P&M-016
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 1,578.65 2,000.00 2,598.19
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 2,131.18 2,199.99 2,424.98
Rate for each tree = (a+b+c+d)/40 586.07 605.00 666.87
Say 586.00 605.00 667.00
(ii) Girth from 600 mm to 900 mm
Unit = Each
Taking output = 30 nos
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoors day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 5.000 3,420.00 17,100.00 P&M-007
(ii) 1.1 cum bucket capacity hour 5.500 3,074.00 16,907.00 P&M-008
(iii) 0.9 cum bucket capacity hour 6.500 2,782.00 18,083.00 P&M-009
Tipper
(i) 18 cum capacity hour 0.750 2,883.30 2,162.48 P&M-014
(ii) 14 cum capacity hour 1.000 2,556.75 2,556.75 P&M-015
(iii) 10 cum capacity hour 1.500 2,274.30 3,411.45 P&M-016
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 1,583.89 2,000.00 2,643.68
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 2,138.26 2,199.99 2,467.43
Rate for each tree = (a+b+c+d)/30 784.03 806.66 904.73
Say 784.00 807.00 905.00
(iii) Girth from 900 mm to 1800 mm
Unit = Each
Taking output = 25 nos
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoors day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 5.000 3,420.00 17,100.00 P&M-007
(ii) 1.1 cum bucket capacity hour 5.500 3,074.00 16,907.00 P&M-008
(iii) 0.9 cum bucket capacity hour 6.500 2,782.00 18,083.00 P&M-009
Tipper
Quantity Amount (Rs.)
Ref.to
Rate Remarks
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project /Input ref.
Specification Project Project Project Project

(i) 18 cum capacity hour 0.758 2,883.30 2,184.32 P&M-014


(ii) 14 cum capacity hour 1.000 2,556.75 2,556.75 P&M-015
(iii) 10 cum capacity hour 1.471 2,274.30 3,344.56 P&M-016
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 1,585.64 2,000.00 2,635.65
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 2,140.62 2,199.99 2,459.94
Rate for each tree = (a+b+c+d)/25 941.87 968.00 1,082.37
Say 942.00 968.00 1,082.00
(iv) Girth above 1800 mm
Unit = Each
Taking output = 20 nos
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoors day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 5.000 3,420.00 17,100.00 P&M-007
(ii) 1.1 cum bucket capacity hour 5.500 3,074.00 16,907.00 P&M-008
(iii) 0.9 cum bucket capacity hour 6.500 2,782.00 18,083.00 P&M-009
Tipper
(i) 18 cum capacity hour 0.714 2,883.30 2,059.50 P&M-014
(ii) 14 cum capacity hour 1.000 2,556.75 2,556.75 P&M-015
(iii) 10 cum capacity hour 1.429 2,274.30 3,249.00 P&M-016
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 1,575.66 2,000.00 2,624.18
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 2,127.14 2,199.99 2,449.24
Rate for each tree = (a+b+c+d)/20 1,169.92 1,210.00 1,347.08
Say 1,170.00 1,210.00 1,347.00
All the serviceable material resulting from girth removal
Note: would be handed over to the employer for the all above
items.
2.02 201 Clearing Grass and Removal of Rubbish
Clearing grass and removal of rubbish up to a distance
of 50 metres outside the periphery of the area .

By Manual Means
Unit = Hectare
Taking output = 1 Hectare
a) Labour
Mate day 2.000 2.000 2.000 617.00 1,234.00 1,234.00 1,234.00 L-12
Mazdoor day 50.000 50.000 50.000 511.52 25,576.00 25,576.00 25,576.00 L-13
b) Overhead charges @ 8% on (a) @ 10% on @ 12% on
(a) (a) 2,144.80 2,681.00 3,217.20
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 2,895.48 2,949.10 3,002.72
Rate per Hectare = a+b+c 31,850.28 32,440.10 33,029.92
Say 31,850.00 32,440.00 33,030.00
2.03 201 Clearing and Grubbing Road Land .
Clearing and grubbing road land including uprooting
rank vegetation, grass, bushes, shrubs, saplings and
trees girth up to 300 mm, removal of stumps of trees
cut earlier and disposal of unserviceable materials and
stacking of serviceable material to be used or
auctioned, up to a lead of 1000 metres including
removal and disposal of top organic soil not exceeding
150 mm in thickness.

Unit = Hectare
Taking output = 1 Hectare
(i) By Manual Means:-
A In area of light jungle
a) Labour
Mate day 6.000 6.000 6.000 617.00 3,702.00 3,702.00 3,702.00 L-12
Mazdoor day 150.000 150.000 150.000 511.52 76,728.00 76,728.00 76,728.00 L-13
b) Machinery
Tractor-trolley hour 122.222 122.222 122.222 1,876.50 229,349.58 229,349.58 229,349.58 P&M-026
b) Overhead charges @ 8% on (a) @ 10% on @ 12% on
(a) (a) 24,782.37 30,977.96 37,173.55
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 33,456.19 34,075.75 34,695.31
Rate per Hectare = a+b+c+d 368,018.14 374,833.30 381,648.45
Quantity Amount (Rs.)
Ref.to
Rate Remarks
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project /Input ref.
Specification Project Project Project Project

Say 368,018.00 374,833.00 381,648.00


B In area of thorny jungle
a) Labour
Mate day 8.000 8.000 8.000 617.00 4,936.00 4,936.00 4,936.00 L-12
Mazdoor day 200.000 200.000 200.000 511.52 102,304.00 102,304.00 102,304.00 L-13
b) Machinery
Tractor-trolley hour 122.222 122.222 122.222 1,876.50 229,349.58 229,349.58 229,349.58 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 26,927.17 33,658.96 40,390.75
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 36,351.67 37,024.85 37,698.03
Rate per Hectare = a+b+c+d 399,868.42 407,273.40 414,678.37
Say 399,868.00 407,273.00 414,678.00
2.03 (ii) By Mechanical Means using Dozer
A In area of light jungle
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Dozer
(i) Dozer (240HP) hour 5.952 6,586.65 39,203.74 P&M-001
(ii) Dozer (175 HP) hour 7.692 5,087.25 39,131.13 P&M-002
(iii) Dozer (90 HP) hour 13.889 3,502.80 48,650.39 P&M-003
Tipper
For transportation to dumping yard considering lead @
1km
(i) 18 cum capacity t.km 1500.000 6.18 9,267.75 P&M-117
(ii) 14 cum capacity t.km 1500.000 7.01 10,519.20 P&M-120
(iii) 10 cum capacity t.km 1500.000 8.66 12,996.00 P&M-123
Loading & unloading charges for disposed of grabbed
material
(i) Using by 18 cum capacity Tipper & 3.1 Cum cum 1000.000 P&M-129
capacity Loader 92.72 92,722.35
(ii) Using by 14 cum capacity Tipper & 2.1 Cum cum 1000.000 P&M-130
capacity Loader 92.81 92,812.50
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 1000.000 P&M-131
Loader 118.14 118,140.00
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 11,381.30 14,353.52 21,703.05
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 15,364.75 15,788.87 20,256.18
Rate per Hectare = a+b+c+d 169,012.29 173,677.62 222,818.03
Say 169,012.00 173,678.00 222,818.00
2.03 B In area of thorny jungle
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Dozer
(i) Dozer (240HP) hour 7.440 6,586.65 49,004.68 P&M-001
(ii) Dozer (175 HP) hour 9.615 5,087.25 48,913.91 P&M-002
(iii) Dozer (90 HP) hour 17.361 3,502.80 60,812.11 P&M-003
Tipper
For transportation to dumping yard considering lead
@ 1km
(i) 18 cum capacity t.km 1500.000 6.18 9,267.75 P&M-117
(ii) 14 cum capacity t.km 1500.000 7.01 10,519.20 P&M-120
(iii) 10 cum capacity t.km 1500.000 8.66 12,996.00 P&M-123
Loading & unloading charges for disposed of grabbed
material
(i) Using by 18 cum capacity Tipper & 3.1 Cum cum 1000.000 P&M-129
capacity Loader 92.72 92,722.35
(ii) Using by 14 cum capacity Tipper & 2.1 Cum cum 1000.000 P&M-130
capacity Loader 92.81 92,812.50
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 1000.000 P&M-131
Loader 118.14 118,140.00
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 12,165.37 15,331.80 23,162.46
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 16,423.26 16,864.98 21,618.30
Rate per Hectare = a+b+c+d 180,655.81 185,514.79 237,801.27
Say 180,656.00 185,515.00 237,801.00
2.03 (iii) By Mechanical Means using Motor Grader
Quantity Amount (Rs.)
Ref.to
Rate Remarks
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project /Input ref.
Specification Project Project Project Project

A In area of light jungle


a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Motor Grader
(i) Motor grader 4.30 metre blade hour 4.032 5,991.00 24,155.71 P&M-004
(ii) Motor grader 3.70 metre blade hour 4.864 5,497.00 26,737.41 P&M-005
(iii) Motor grader 3.35 metre blade hour 5.423 4,796.00 26,008.71 P&M-006
Tipper
For transportation to dumping yard considering lead
@ 1km
(i) 18 cum capacity t.km 1500.000 6.18 9,267.75 P&M-117
(ii) 14 cum capacity t.km 1500.000 7.01 10,519.20 P&M-120
(iii) 10 cum capacity t.km 1500.000 8.66 12,996.00 P&M-123
Loading & unloading charges for disposed of grabbed
material
(i) Using by 18 cum capacity Tipper & 3.1 Cum cum 1000.000 P&M-129
capacity Loader 92.72 92,722.35
(ii) Using by 14 cum capacity Tipper & 2.1 Cum cum 1000.000 P&M-130
capacity Loader 92.81 92,812.50
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 1000.000 P&M-131
Loader 118.14 118,140.00
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 10,134.56 13,060.53 18,921.71
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 13,681.66 14,366.58 17,660.26
Rate per Hectare = a+b+c+d 150,498.23 158,032.42 194,262.88
Say 150,498.00 158,032.00 194,263.00
2.03 B In area of thorny jungle
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Motor Grader
(i) Motor grader 4.30 metre blade hour 5.040 5,991.00 30,194.64 P&M-004
(ii) Motor grader 3.70 metre blade hour 6.080 5,497.00 33,421.76 P&M-005
(iii) Motor grader 3.35 metre blade hour 6.779 4,796.00 32,512.08 P&M-006
Tipper
For transportation to dumping yard considering lead
@ 1km
(i) 18 cum capacity t.km 1500.000 6.18 9,267.75 P&M-117
(ii) 14 cum capacity t.km 1500.000 7.01 10,519.20 P&M-120
(iii) 10 cum capacity t.km 1500.000 8.66 12,996.00 P&M-123
Loading & unloading charges for disposed of grabbed
material
(i) Using by 18 cum capacity Tipper & 3.1 Cum cum 1000.000 P&M-129
capacity Loader 92.72 92,722.35
(ii) Using by 14 cum capacity Tipper & 2.1 Cum cum 1000.000 P&M-130
capacity Loader 92.81 92,812.50
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 1000.000 P&M-131
Loader 118.14 118,140.00
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 10,617.68 13,728.97 19,702.11
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 14,333.86 15,101.86 18,388.64
Rate per Hectare = a+b+c+d 157,672.48 166,120.49 202,275.04
Say 157,672.00 166,120.00 202,275.00
2.04 202 Dismantling of Structures
Dismantling of existing structures like culverts, bridges,
retaining walls and other structure comprising of
masonry, cement concrete, wood work, steel work,
including T&P and scaffolding wherever necessary,
sorting the dismantled material, disposal of
unserviceable material and stacking the serviceable
material with all lifts and lead of 1000 metres

Unit = cum
Taking output = 1.25 cum
(i) Lime /Cement Concrete
I By Manual Means
A Lime Concrete, cement concrete grade M-10 and
below
Quantity Amount (Rs.)
Ref.to
Rate Remarks
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project /Input ref.
Specification Project Project Project Project

a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor for dismantling and loading day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Tractor-trolley (considering 15 min loading time) hour 0.299 0.299 0.299 1,876.50 561.07 561.07 561.07 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 87.78 109.73 131.67
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 118.51 120.70 122.89
Cost for 1.25 cum = a+b+c+d 1,303.56 1,327.70 1,351.84
Rate per cum = (a+b+c+d)/ 1.25 1,042.85 1,062.16 1,081.47
Say 1,043.00 1,062.00 1,081.00
2.04 B Cement Concrete Grade M-15 & M-20
a) Labour
Mate day 0.050 0.050 0.050 617.00 30.85 30.85 30.85 L-12
Mazdoor for dismantling and loading day 1.250 1.250 1.250 511.52 639.40 639.40 639.40 L-13
b) Machinery
Tractor-trolley (considering 15 min loading time) hour 0.299 0.299 0.299 1,876.50 561.07 561.07 561.07 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 98.51 123.13 147.76
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 132.98 135.45 137.91
Cost for 1.25 cum = a+b+c+d 1,462.81 1,489.90 1,516.99
Rate per cum = (a+b+c+d)/ 1.25 1,170.25 1,191.92 1,213.59
Say 1,170.00 1,192.00 1,214.00
2.04 C Prestressed / Reinforced cement concrete grade M-20
& above
a) Labour
Mate day 0.150 0.150 0.150 617.00 92.55 92.55 92.55 L-12
Blacksmith day 0.250 0.250 0.250 679.00 169.75 169.75 169.75 L-02
Mazdoor for dismantling, loading and unloading day 3.500 3.500 3.500 511.52 1,790.32 1,790.32 1,790.32 L-13
b) Machinery
Tractor-trolley (considering 15 min loading time) hour 0.257 0.257 0.257 1,876.50 482.26 482.26 482.26 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 202.79 253.49 304.19
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 273.77 278.84 283.91
Cost for 1.25 cum = a+b+c+d 3,011.44 3,067.21 3,122.97
Rate per cum = (a+b+c+d)/ 1.25 2,409.15 2,453.76 2,498.38
Say 2,409.00 2,454.00 2,498.00
2.04 II By Mechanical Means
A Cement Concrete Grade M-15 & M-20
Unit = cum
Taking output = 1.25 cum
a) Labour
Mate day 0.020 0.020 0.020 617.00 12.34 12.34 12.34 L-12
Mazdoor for loading and unloading & Pneumatic day 0.500 0.500 0.500 L-13
breaker 511.52 255.76 255.76 255.76

b) Machinery
Air Compressor 250 cfm hour 0.6250 0.625 0.625 614.25 383.91 383.91 383.91 P&M-029
Pneumatic breaker @ 1 cum per hour hour 1.250 1.250 1.250 206.00 257.50 257.50 257.50 P&M-010
Tipper
For transportation to dumping yard considering lead @
1 km
(i) 18 cum capacity t.km 1.875 6.18 11.58 P&M-117
(ii) 14 cum capacity t.km 1.875 7.01 13.15 P&M-120
(iii) 10 cum capacity t.km 1.875 8.66 16.25 P&M-123
Loading & unloading charges for disposed of material

(i) Using by 18 cum capacity Tipper & 3.1 Cum cum 1.250 P&M-129
capacity Loader 92.72 115.90
(ii) Using by 14 cum capacity Tipper & 2.1 Cum cum 1.250 P&M-130
capacity Loader 92.81 116.02
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 1.250 P&M-131
Loader 118.14 147.68
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 82.96 103.87 128.81
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 112.00 114.25 120.22
Cost for 1.25 cum = a+b+c+d 1,231.95 1,256.79 1,322.46
Rate per cum = (a+b+c+d)/ 1.25 985.56 1,005.43 1,057.97
Quantity Amount (Rs.)
Ref.to
Rate Remarks
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project /Input ref.
Specification Project Project Project Project

Say 986.00 1,005.00 1,058.00


2.04 B Prestressed / reinforced cement concrete grade M-20
& above
Unit = cum
Taking output = 1.25 cum
a) Labour
Mate day 0.036 0.036 0.036 617.00 22.21 22.21 22.21 L-12
Mazdoor with Pneumatic breaker and for loading and day 0.910 0.910 0.910 L-13
unloading 511.52 465.48 465.48 465.48
Blacksmith day 0.250 0.250 0.250 679.00 169.75 169.75 169.75 L-01

b) Machinery
Air Compressor 250 cfm hour 0.625 0.625 0.625 614.25 383.91 383.91 383.91 P&M-029
Pneumatic breaker @ 1 cum per hour hour 1.250 1.250 1.250 206.00 257.50 257.50 257.50 P&M-010
Tipper
For transportation to dumping yard considering lead @
1 km
(i) 18 cum capacity t.km 1.875 6.18 11.58 P&M-117
(ii) 14 cum capacity t.km 1.875 7.01 13.15 P&M-120
(iii) 10 cum capacity t.km 1.875 8.66 16.25 P&M-123
Loading & unloading charges for disposed of material

(i) Using by 18 cum capacity Tipper & 3.1 Cum cum 1.250 P&M-129
capacity Loader 92.72 115.90
(ii) Using by 14 cum capacity Tipper & 2.1 Cum cum 1.250 P&M-130
capacity Loader 92.81 116.02
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 1.250 P&M-131
Loader 118.14 147.68
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 114.11 142.80 175.53
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 154.04 157.08 163.83
Cost for 1.25 cum = a+b+c+d 1,694.49 1,727.90 1,802.13
Rate per cum = (a+b+c+d)/ 1.25 1,355.59 1,382.32 1,441.71
Say 1,356.00 1,382.00 1,442.00
2.04 (ii) Dismantling Brick / Tile work
By Manual Means
A In lime mortar
a) Labour
Mate day 0.020 0.020 0.020 617.00 12.34 12.34 12.34 L-12
Mazdoor for dismantling, loading and unloading day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 1,876.50 482.26 482.26 482.26 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 60.03 75.04 90.04
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 81.04 82.54 84.04
Cost for 1.25 cum = a+b+c+d 891.43 907.94 924.44
Rate per cum = (a+b+c+d)/ 1.25 713.14 726.35 739.56
Say 713.00 726.00 740.00
2.04 B In cement mortar
a) Labour
Mate day 0.030 0.030 0.030 617.00 18.51 18.51 18.51 L-12
Mazdoor for dismantling, loading and unloading day 0.750 0.750 0.750 511.52 383.64 383.64 383.64 L-13
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 1,876.50 482.26 482.26 482.26 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 70.75 88.44 106.13
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 95.52 97.29 99.05
Cost for 1.25 cum = a+b+c+d 1,050.68 1,070.14 1,089.59
Rate per cum = (a+b+c+d)/ 1.25 840.54 856.11 871.67
Say 841.00 856.00 872.00
2.04 C In mud mortar
a) Labour
Mate day 0.016 0.016 0.016 617.00 9.87 9.87 9.87 L-12
Mazdoor for dismantling and loading day 0.400 0.400 0.400 511.52 204.61 204.61 204.61 L-13
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 1,876.50 482.16 482.16 482.16 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 55.73 69.66 83.60
Quantity Amount (Rs.)
Ref.to
Rate Remarks
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project /Input ref.
Specification Project Project Project Project

d) Contractor's profit @ 10% on @ 10% on @ 10% on


(a+b+c) (a+b+c) (a+b+c) 75.24 76.63 78.02
Cost for 1.25 cum = a+b+c+d 827.60 842.93 858.26
Rate per cum = (a+b+c+d)/ 1.25 662.08 674.34 686.60
Say 662.00 674.00 687.00
2.04 D Dry brick pitching or brick soling
a) Labour
Mate day 0.014 0.014 0.014 617.00 8.64 8.64 8.64 L-12
Mazdoor for Dismantling, loading and unloading day 0.350 0.350 0.350 511.52 179.03 179.03 179.03 L-13
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 1,876.50 482.16 482.26 482.16 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 53.59 66.99 80.38
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 72.34 73.69 75.02
Cost for 1.25 cum = a+b+c+d 795.75 810.62 825.23
Rate per cum = (a+b+c+d)/ 1.25 636.60 648.49 660.18
Say 637.00 648.00 660.00
2.04 (iii) Dismantling Stone Masonry
I By Manual Means
A Rubble stone masonry in lime mortar
a) Labour
Mate day 0.024 0.024 0.024 617.00 14.81 14.81 14.81 L-12
Mazdoor for dismantling, loading and unloading. day 0.600 0.600 0.600 511.52 306.91 306.91 306.91 L-13
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 1,876.50 482.26 482.16 482.16 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 64.32 80.39 96.47
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 86.83 88.43 90.03
Cost for 1.25 cum = a+b+c+d 955.13 972.69 990.38
Rate per cum = (a+b+c+d)/ 1.25 764.10 778.15 792.30
Say 764.00 778.00 792.00
2.04 B Rubble stone masonry in cement mortar.
a) Labour
Mate day 0.030 0.030 0.030 617.00 18.51 18.51 18.51 L-12
Mazdoor for dismantling, loading and unloading. day 0.750 0.750 0.750 511.52 383.64 383.64 383.64 L-13
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 1,876.50 482.26 482.16 482.16 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 70.75 88.43 106.12
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 95.52 97.27 99.04
Cost for 1.25 cum = a+b+c+d 1,050.68 1,070.01 1,089.47
Rate per cum = (a+b+c+d)/ 1.25 840.54 856.01 871.57
Say 841.00 856.00 872.00
2.04 C Rubble Stone Masonry in mud mortar.
a) Labour
Mate day 0.020 0.020 0.020 617.00 12.34 12.34 12.34 L-12
Mazdoor for dismantling, loading and unloading. day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 1,876.50 482.16 482.26 482.16 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 60.02 75.04 90.03
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 81.03 82.54 84.03
Cost for 1.25 cum = a+b+c+d 891.30 907.94 924.32
Rate per cum = (a+b+c+d)/ 1.25 713.04 726.35 739.45
Say 713.00 726.00 739.00
2.04 D Dry rubble masonry
a) Labour
Mate day 0.018 0.018 0.018 617.00 11.11 11.11 11.11 L-12
Mazdoor for dismantling, loading and unloading. day 0.450 0.450 0.450 511.52 230.18 230.18 230.18 L-13
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 1,876.50 482.26 482.16 482.16 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 57.88 72.34 86.81
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 78.14 79.58 81.03
Cost for 1.25 cum = a+b+c+d 859.58 875.37 891.29
Rate per cum = (a+b+c+d)/ 1.25 687.66 700.30 713.03
Quantity Amount (Rs.)
Ref.to
Rate Remarks
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project /Input ref.
Specification Project Project Project Project

Say 688.00 700.00 713.00


2.04 E Dismantling stone pitching/ dry stone spalls.
a) Labour
Mate day 0.016 0.016 0.016 617.00 9.87 9.87 9.87 L-12
Mazdoor for dismantling, loading and unloading. day 0.400 0.400 0.400 511.52 204.61 204.61 204.61 L-13
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 1,876.50 482.16 482.16 482.16 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 55.73 69.66 83.60
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 75.24 76.63 78.02
Cost for 1.25 cum = a+b+c+d 827.60 842.93 858.26
Rate per cum = (a+b+c+d)/ 1.25 662.08 674.34 686.60
Say 662.00 674.00 687.00
2.04 F Dismantling boulders laid in wire crates including
opening of crates and stacking dismantled materials.

a) Labour
Mate day 0.020 0.020 0.020 617.00 12.34 12.34 12.34 L-12
Mazdoor for dismantling, loading and unloading day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 1,876.50 482.16 482.26 482.16 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 60.02 75.04 90.03
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 81.03 82.54 84.03
Cost for 1.25 cum = a+b+c+d 891.30 907.94 924.32
Rate per cum = (a+b+c+d)/ 1.25 713.04 726.35 739.45
Say 713.00 726.00 739.00
II By Mechanical Means
2.04 A Dismantling Brick / Tile work/ rubble masonary/
pitching/ etc by mechanical means
Unit = cum
Taking output = 20 cum
a) Labour
Mate day 0.008 0.008 0.008 617.00 4.94 4.94 4.94 L-12
Mazdoor day 0.200 0.200 0.200 511.52 102.30 102.30 102.30 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 0.523 3,420.00 1,788.66 P&M-007
(ii) 1.1 cum bucket capacity hour 0.603 3,074.00 1,853.62 P&M-008
(iii) 0.9 cum bucket capacity hour 0.843 2,782.00 2,345.23 P&M-009
Tipper
For transportation to dumping yard considering lead @
1km
(i) 18 cum capacity t.km 30.000 6.18 185.36 P&M-117
(ii) 14 cum capacity t.km 30.000 7.01 210.38 P&M-120
(iii) 10 cum capacity t.km 30.000 8.66 259.92 P&M-123
Loading & unloading time
(i) 18 cum capacity hour 0.523 2,883.30 1,507.97 P&M-014
(ii) 14 cum capacity hour 0.603 2,556.75 1,541.72 P&M-015
(iii) 10 cum capacity hour 0.843 2,274.30 1,917.23 P&M-016
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 287.14 371.30 555.55
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 387.64 408.43 518.52
Cost for 20 cum = a+b+c+d 4,263.99 4,492.69 5,703.69
Rate per cum = (a+b+c+d)/ 20 213.20 224.63 285.18
Say 213.00 225.00 285.00
2.04 (iv) Wood Work wrought framed and fixed in frames of
trusses upto a height of 5 m above plinth level

Unit = Cum
Taking output = 1.25 Cum
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Carpenter day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-04
Mazdoor for dismantling, loading and unloading. day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 1,876.50 482.16 482.16 482.16 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 111.98 139.97 167.96
Quantity Amount (Rs.)
Ref.to
Rate Remarks
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project /Input ref.
Specification Project Project Project Project

d) Contractor's profit @ 10% on @ 10% on @ 10% on


(a+b+c) (a+b+c) (a+b+c) 151.17 153.97 156.77
Cost for 1.25 cum = a+b+c+d 1,662.84 1,693.63 1,724.43
Rate per cum = (a+b+c+d)/ 1.25 1,330.27 1,354.91 1,379.54
Say 1,330.00 1,355.00 1,380.00
2.04 (v) Steel Work in all types of sections upto a height of 5 m
above plinth level excluding cutting of rivet.

Unit = tonne
Taking output = 1 tonne
A Including dismembering
a) Labour
Mate day 0.140 0.140 0.140 617.00 86.38 86.38 86.38 L-12
Blacksmith day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-02
Mazdoor for dismantling, loading and unloading day 2.500 2.500 2.500 511.52 1,278.80 1,278.80 1,278.80 L-13
Add 2.5 per cent of cost of labour for gas cutting,
ropes, pulleys etc. 51.10 51.10 51.10
b) Machinery
Tractor-trolley hour 0.123 0.123 0.123 1,876.50 230.81 230.81 230.81 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 186.09 232.61 279.13
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 251.22 255.87 260.52
Rate per tonne = a+b+c+d 2,763.40 2,814.57 2,865.75
Say 2,763.00 2,815.00 2,866.00
2.04 B Excluding dismembering.
a) Labour
Mate day 0.100 0.100 0.100 617.00 61.70 61.70 61.70 L-12
Mazdoor for dismantling, loading and unloading day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
Blacksmith day 0.500 0.500 0.500 679.00 339.50 339.50 339.50 L-02
Add 2.5 per cent of cost of labour for gas cutting,
35.61 35.61 35.61
ropes, pulleys etc.
b) Machinery
Tractor-trolley hour 0.123 0.123 0.123 1,876.50 230.81 230.81 230.81 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 135.25 169.07 202.88
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 182.59 185.97 189.35
Rate per tonne = a+b+c+d 2,008.50 2,045.69 2,082.89
Say 2,008.00 2,046.00 2,083.00
2.04 C Extra over item No( v ) A and( v ) B for cutting rivets.

Unit = each
Taking output = 10 rivets
a) Labour
Mate day 0.010 0.010 0.010 617.00 6.17 6.17 6.17 L-12
Blacksmith day 0.130 0.130 0.130 679.00 88.27 88.27 88.27 L-02
Mazdoor day 0.130 0.130 0.130 511.52 66.50 66.50 66.50 L-13
b) Overhead charges @ 8% on (a) @ 10% on @ 12% on
(a) (a) 12.88 16.09 19.31
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 17.38 17.70 18.03
Cost for 10 rivets = a+b+c 191.19 194.73 198.28
Rate for each rivet = ( a+b+c)/10 19.12 19.47 19.83
Say 19.00 19.00 20.00
2.04 (vi) Scraping of Bricks Dismantled from Brick Work
including Stacking.
Unit = numbers 1000.00
Taking output = 1000 numbers
A In lime/Cement mortar
a) Labour
Mate day 0.140 0.140 0.140 617.00 86.38 86.38 86.38 L-12
Mazdoor day 3.500 3.500 3.500 511.52 1,790.32 1,790.32 1,790.32 L-13
b) Overhead charges @ 8% on (a) @ 10% on @ 12% on
(a) (a) 150.14 187.67 225.20
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 202.68 206.44 210.19
Rate per 1000 Nos = a+b+c 2.23 2.27 2.31
Say 2.00 2.00 2.00
2.04 B In mud mortar
a) Labour
Mate day 0.050 0.050 0.050 617.00 30.85 30.85 30.85 L-12
Quantity Amount (Rs.)
Ref.to
Rate Remarks
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project /Input ref.
Specification Project Project Project Project

Mazdoor day 1.250 1.250 1.250 511.52 639.40 639.40 639.40 L-13
b) Overhead charges @ 8% on (a) @ 10% on @ 12% on
(a) (a) 53.62 67.03 80.43
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 72.39 73.73 75.07
Rate per1000 Nos = a+b+c 0.80 0.81 0.83
Say 1.00 1.00 1.00
2.04 (vii) Scraping of Stone from Dismantled Stone Masonry

Unit = cum
Taking output = 1 cum
A In cement and lime mortar
a) Labour
Mate day 0.056 0.056 0.056 617.00 34.55 34.55 34.55 L-12
Mazdoor day 1.400 1.400 1.400 511.52 716.13 716.13 716.13 L-13
b) Overhead charges @ 8% on (a) @ 10% on @ 12% on
(a) (a) 60.05 75.07 90.08
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 81.07 82.57 84.08
Rate per cum = a+b+c 891.81 908.32 924.84
Say 892.00 908.00 925.00
2.04 B In Mud mortar
a) Labour
Mate day 0.012 0.012 0.012 617.00 7.40 7.40 7.40 L-12
Mazdoor day 0.300 0.300 0.300 511.52 153.46 153.46 153.46 L-13
b) Overhead charges @ 8% on (a) @ 10% on @ 12% on
(a) (a) 12.87 16.09 19.30
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 17.37 17.69 18.02
Rate per cum = a+b+c 191.10 194.64 198.18
Say 191.00 195.00 198.00
2.04 (viii) Scarping Plaster in Lime or Cement Mortar from Brick/
Stone Masonry
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Mazdoor for scarping and loading day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
b) Machinery
Tractor-trolley hour 0.308 0.308 0.308 1,876.50 578.59 578.59 578.59 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 217.87 272.34 326.81
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 294.13 299.57 305.02
Cost for 100 sqm = a+b+c+d 3,235.38 3,295.30 3,355.21
Rate per sqm = (a+b+c+d)/100 32.35 32.95 33.55
Say 32.00 33.00 34.00
2.04 (ix) Removing all type of Hume Pipes and Stacking within a
lead of 1000 metres including Earthwork and
Dismantling of Masonry Works.

A Up to 600 mm dia
Unit = metre
Taking output = 15 metre
a) Labour
Mate day 0.084 0.094 0.105 617.00 51.83 58.00 64.79 L-12
Mazdoor day 2.088 2.346 2.617 511.52 1,068.05 1,200.03 1,338.65 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 2.176 3,420.00 7,441.92 P&M-007
(ii) 1.1 cum bucket capacity hour 2.693 3,074.00 8,278.28 P&M-008
(iii) 0.9 cum bucket capacity hour 3.235 2,782.00 8,999.77 P&M-009
Tipper
For loading & Unloding Time & For transportation of
excess material to dumping yard considering lead @
1km
(i) 18 cum capacity hour 2.226 2,883.30 6,418.23 P&M-014
(ii) 14 cum capacity hour 2.743 2,556.75 7,013.17 P&M-015
(iii) 10 cum capacity hour 3.285 2,274.30 7,471.08 P&M-016
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 1,198.40 1,654.95 2,144.91
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 1,617.84 1,820.44 2,001.92
Quantity Amount (Rs.)
Ref.to
Rate Remarks
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project /Input ref.
Specification Project Project Project Project

Rate for 15 metre = a+b+c+d 17,796.27 20,024.86 22,021.11


Rate per metre = (a+b+c+d)/15 1,186.42 1,334.99 1,468.07
Say 1,186.00 1,335.00 1,468.00
B Above 600 mm to 900 mm dia
Unit = metre
Taking output = 15 metre
a) Labour
Mate day 0.094 0.104 0.115 617.00 57.70 64.08 70.77 L-12
Mazdoor day 2.338 2.597 2.868 511.52 1,195.93 1,328.16 1,466.78 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 2.676 3,420.00 9,151.92 P&M-007
(ii) 1.1 cum bucket capacity hour 3.193 3,074.00 9,815.28 P&M-008
(iii) 0.9 cum bucket capacity hour 3.735 2,782.00 10,390.77 P&M-009
Tipper for Loading & unloading
For loading & Unloding Time & For transportation of
excess material to dumping yard considering lead @
1km
(i) 18 cum capacity hour 2.726 2,883.30 7,859.88 P&M-014
(ii) 14 cum capacity hour 3.243 2,556.75 8,291.54 P&M-015
(iii) 10 cum capacity hour 3.785 2,274.30 8,608.23 P&M-016
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 1,461.23 1,949.91 2,464.39
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 1,972.67 2,144.90 2,300.09
Rate for 15 metre = a+b+c+d 21,699.33 23,593.87 25,301.03
Rate per metre = (a+b+c+d)/15 1,446.62 1,572.92 1,686.74
Say 1,447.00 1,573.00 1,687.00
C Above 900 mm
Unit = metre
Taking output = 15 metre
a) Labour
Mate day 0.104 0.114 0.135 617.00 63.87 70.25 83.11 L-12
Mazdoor day 2.588 2.847 3.368 511.52 1,323.81 1,456.04 1,722.54 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.176 3,420.00 10,861.92 P&M-007
(ii) 1.1 cum bucket capacity hour 3.693 3,074.00 11,352.28 P&M-008
(iii) 0.9 cum bucket capacity hour 4.735 2,782.00 13,172.77 P&M-009
Tipper for Loading & unloading
For loading & Unloding Time & For transportation of
excess material to dumping yard considering lead @
1km
(i) 18 cum capacity hour 3.226 2,883.30 9,301.53 P&M-014
(ii) 14 cum capacity hour 3.743 2,556.75 9,569.92 P&M-015
(iii) 10 cum capacity hour 4.785 2,274.30 10,882.53 P&M-016
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 1,724.09 2,244.85 3,103.31
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 2,327.52 2,469.33 2,896.43
Rate for 15 metre = a+b+c+d 25,602.74 27,162.67 31,860.69
Rate per metre = (a+b+c+d)/15 1,706.85 1,810.84 2,124.05
Say 1,707.00 1,811.00 2,124.00
Note 1. The excavation of earth, dismantling of stone
masonry work in head walls and protection works is not
included which is to be measured and paid separately.

2. Credit for retrieved stone from masonry work may be


taken as per actual availability.
2.05 202 Dismantling of Flexible Pavements
Dismantling of flexible pavements and disposal of
dismantled materials up to a lead of 1000 metres,
stacking serviceable and unserviceable materials
separately
Unit = cum
Taking output = 1 cum
(i) By Manual Means
A Bituminous courses
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Mazdoor for dismantling, loading and unloading day 1.500 1.500 1.500 511.52 767.28 767.28 767.28 L-13
b) Machinery
Quantity Amount (Rs.)
Ref.to
Rate Remarks
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project /Input ref.
Specification Project Project Project Project

Tractor-trolley hour 0.167 0.167 0.167 1,876.50 313.38 313.38 313.38 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 89.41 111.77 134.12
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 120.71 122.94 125.18
Rate per cum = a+b+c+d 1,327.80 1,352.39 1,376.98
Say 1,328.00 1,352.00 1,377.00
2.05 B Granular courses
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor for dismantling, loading and unloading. day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Tractor-trolley hour 0.167 0.167 0.167 1,876.50 313.38 313.38 313.38 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 67.97 84.96 101.95
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 91.75 93.45 95.15
Rate per cum = a+b+c+d 1,009.30 1,027.99 1,046.68
Say 1,009.00 1,028.00 1,047.00
2.05 Dismantling of flexible pavements and disposal of
dismantled materials up to a lead of 1000 metres,
stacking serviceable and unserviceable materials
separately
(ii) By Mechanical Means
A Bituminous courses
Unit = cum
Taking output = 20 cum
a) Labour
Mate day 0.024 0.027 0.033 617.00 14.81 16.66 20.36 L-12
Mazdoor for dismantling, loading and unloading day 0.588 0.667 0.833 511.52 300.77 341.18 426.10 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity considering output 85 hour 2.353 P&M-007
sqm/8.5 cum per hour 3,420.00 8,047.26
(ii) 1.1 cum bucket capacity considering output 75 hour 2.667 P&M-008
sqm/7.5 cum per hour 3,074.00 8,198.36
(iii) 0.9 cum bucket capacity considering output 60 hour 3.333 P&M-009
sqm/6 cum per hour 2,782.00 9,272.41
Tipper for transportation
(i) 18 cum capacity t.km 46.000 6.18 284.21 P&M-117
(ii) 14 cum capacity t.km 46.000 7.01 322.59 P&M-120
(iii) 10 cum capacity t.km 46.000 8.66 398.54 P&M-123
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 691.76 887.88 1,214.09
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 933.88 976.67 1,133.15
Rate for 20 metre = a+b+c+d 10,272.70 10,743.34 12,464.65
Rate per metre = (a+b+c+d)/20 513.63 537.17 623.23
Say 514.00 537.00 623.00
B Granular courses
Unit = cum
Taking output = 250 cum
a) Labour
Mate day 0.029 0.033 0.046 617.00 17.72 20.41 28.54 L-12
Mazdoor for dismantling, loading and unloading day 0.718 0.827 1.156 511.52 367.35 423.06 591.46 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 2.873 3,420.00 9,824.39 P&M-007
(ii) 1.1 cum bucket capacity hour 3.308 3,074.00 10,169.64 P&M-008
(iii) 0.9 cum bucket capacity hour 4.625 2,782.00 12,867.06 P&M-009
Tipper for transportation
(i) 18 cum capacity t.km 575.000 6.18 3,552.64 P&M-117
(ii) 14 cum capacity t.km 575.000 7.01 4,032.36 P&M-120
(iii) 10 cum capacity t.km 575.000 8.66 4,981.80 P&M-123
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 1,100.97 1,464.55 2,216.26
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 1,486.31 1,611.00 2,068.51
Rate for 250 metre = a+b+c+d 16,349.38 17,721.03 22,753.64
Rate per metre = (a+b+c+d)/250 65.40 70.88 91.01
Say 65.00 71.00 91.00
2.06 202 Dismantling of Cement Concrete Pavement
Quantity Amount (Rs.)
Ref.to
Rate Remarks
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project /Input ref.
Specification Project Project Project Project

Dismantling of cement concrete pavement by


mechanical means using pneumatic tools, breaking to
pieces not exceeding 0.02 cum in volume and stock
piling at designated locations and disposal of
dismantled materials up to a lead of 1000 metres,
stacking serviceable and unserviceable materials
separately

Unit = cum
Taking output = 60 cum
a) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 6.841 3,420.00 23,396.22 P&M-007
(ii) 1.1 cum bucket capacity hour 8.048 3,074.00 24,739.55 P&M-008
(iii) 0.9 cum bucket capacity hour 9.121 2,782.00 25,374.62 P&M-009
Jack Hammer hour 6.841 9.145 12.161 206.00 1,409.25 1,883.96 2,505.23 P&M-010
Air Compressor 250 cfm with 2 leads of pneumatic hour 2.880 2.880 2.880 P&M-029
breaker @ 1 cum per hour 614.25 1,769.04 1,769.04 1,769.04
Pneumatic breaker hour 5.760 5.760 5.760 206.00 1,186.56 1,186.56 1,186.56 P&M-010
Concrete Joint Cutting Machine hour 8.000 8.000 8.000 1,251.00 10,008.00 10,008.00 10,008.00 P&M-098
Tipper
For transportation to dumping yard considering lead @
1km
(i) 18 cum capacity t.km 180.000 6.18 1,112.13 P&M-117
(ii) 14 cum capacity t.km 180.000 7.01 1,262.30 P&M-120
(iii) 10 cum capacity t.km 180.000 8.66 1,559.52 P&M-123
For Loading & unloading charges for disposed of
grabbed material
(i) Using by 18 cum capacity Tipper & 3.1 Cum cum 72.000 P&M-129
capacity Loader 92.72 6,676.01
(ii) Using by 14 cum capacity Tipper & 2.1 Cum cum 72.000 P&M-130
capacity Loader 92.81 6,682.50
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 72.000 P&M-131
Loader 118.14 8,506.08
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 3,773.26 4,914.05 6,302.12
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 5,093.91 5,405.46 5,881.98
Cost for 60 cum = a+b+c+d 56,032.98 59,460.03 64,701.75
Rate per cum = (a+b+c+d)/ 60 933.88 991.00 1,078.36
Say 934.00 991.00 1,078.00
2.07 202 Dismantling of Guard Rails
Dismantling guard rails by manual means and disposal
of dismantled material with all lifts and up to a lead of
1000 metres, stacking serviceable materials and
unserviceable materials separately.

Unit = running metre


Taking output = 1 metre
a) Labour
Mate day 0.006 0.006 0.006 617.00 3.70 3.70 3.70 L-12
Mazdoor including loading and unloading day 0.150 0.150 0.150 511.52 76.73 76.73 76.73 L-13
b) Machinery
Tractor-trolley hour 0.006 0.006 0.006 1,876.50 11.26 11.26 11.26 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 7.34 9.17 11.00
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 9.90 10.09 10.27
Rate per metre = a+b+c+d 108.93 110.94 112.96
108.93 110.94 112.96
2.08 202 Dismantling of Kerb Stone Say 109.00 111.00 113.00
Dismantling kerb stone by manual means and disposal
of dismantled material with all lifts and up to a lead of
1000 metre
Unit = running metre
Taking output = 10 metre
a) Labour
Mate day 0.006 0.006 0.006 617.00 3.70 3.70 3.70 L-12
Mazdoor including loading and unloading day 0.150 0.150 0.150 511.52 76.73 76.73 76.73 L-13
b) Machinery
Tractor-trolley hour 0.139 0.139 0.139 1,876.50 260.83 260.83 260.83 P&M-026
Quantity Amount (Rs.)
Ref.to
Rate Remarks
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project /Input ref.
Specification Project Project Project Project

c) Overhead charges @ 8% on @ 10% on @ 12% on


(a+b) (a+b) (a+b) 27.30 34.13 40.95
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 36.86 37.54 38.22
Cost for 10 m = a+b+c+d 405.42 412.93 420.44
Rate per metre = (a+b+c+d)/10 40.54 41.29 42.04
Say 41.00 41.00 42.00
2.09 202 Dismantling of Kerb Stone Channel
Dismantling kerb stone channel by manual means and
disposal of dismantled material with all lifts and up to a
lead of 1000 metre
Unit = running metre
Taking output = 10 metre
a) Labour
Mate day 0.009 0.009 0.009 617.00 5.55 5.55 5.55 L-12
Mazdoor including loading and unloading day 0.225 0.225 0.225 511.52 115.09 115.09 115.09 L-13
b) Machinery
Tractor-trolley hour 0.170 0.170 0.170 1,876.50 319.01 319.01 319.01 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 35.17 43.97 52.76
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 47.48 48.36 49.24
Cost for 10 m = a+b+c+d 522.30 531.98 541.65
Rate per metre = (a+b+c+d)/10 52.23 53.20 54.16
Say 52.00 53.00 54.00
2.10 202 Dismantling of Kilometre Stone
Dismantling of kilometre stone including cutting of
earth, foundation and disposal of dismantled material
with all lifts and lead upto 1000 m and back filling of pit.

Unit = Each
Taking output = one KM stone
A 5th KM stone
Quantity of cement concrete = 0.392 cum
a) Labour
Mate day 0.030 0.030 0.030 617.00 18.51 18.51 18.51 L-12
Mazdoor day 0.750 0.750 0.750 511.52 383.64 383.64 383.64 L-13
b) Machinery
Tractor-trolley hour 0.150 0.150 0.150 1,876.50 281.48 281.48 281.48 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 54.69 68.36 82.04
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 73.83 75.20 76.57
Rate for one 5th KM stone = a+b+c+d 812.15 827.19 842.23
Say 812.00 827.00 842.00
B Ordinary KM Stone
Quantity of cement concrete = 0.269 cum
a) Labour
Mate day 0.020 0.020 0.020 617.00 12.34 12.34 12.34 L-12
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
b) Machinery
Tractor-trolley hour 0.100 0.100 0.100 1,876.50 187.65 187.65 187.65 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 36.46 45.58 54.69
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 49.22 50.13 51.04
Rate for one ordinary KM stone = a+b+c+d 541.43 551.46 561.48
Say 541.00 551.00 561.00
C Hectometre Stone
Quantity of cement concrete = 0.048 cum
a) Labour
Mate day 0.004 0.004 0.004 617.00 2.47 2.47 2.47 L-12
Mazdoor day 0.100 0.100 0.100 511.52 51.15 51.15 51.15 L-13
b) Machinery
Tractor-trolley hour 0.020 0.020 0.020 1,876.50 37.53 37.53 37.53 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 7.29 9.12 10.94
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 9.84 10.03 10.21
Rate for one Hectometre stone = a+b+c+d 108.29 110.29 112.30
Say 108.00 110.00 112.00
2.11 202 Dismantling of Fencing
Quantity Amount (Rs.)
Ref.to
Rate Remarks
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project /Input ref.
Specification Project Project Project Project

Dismantling of barbed wire fencing/ wire mesh fencing


including posts, foundation concrete, back filling of pit
by manual means including disposal of dismantled
material with all lifts and up to a lead of 1000 metres,
stacking serviceable material and unserviceable
material separately.

Unit = running metre


Taking output = 30 metres
a) Labour
Mate day 0.150 0.150 0.150 617.00 92.55 92.55 92.55 L-12
Mazdoor including loading and unloading day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Blacksmith day 0.750 0.750 0.750 679.00 509.25 509.25 509.25 L-02
b) Machinery
Tractor-trolley hour 0.150 0.150 0.150 1,876.50 281.48 281.48 281.48 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 193.43 241.78 290.14
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 261.13 265.96 270.80
Cost for 30 metres = a+b+c+d 2,872.39 2,925.58 2,978.77
Rate per metre = (a+b+c+d)/30 95.75 97.52 99.29
Say 96.00 98.00 99.00
2.12 202 Dismantling of CI Water Pipe Line
Dismantling of CI water pipe line 600 mm dia including
disposal with all lifts and lead upto 1000 metres and
stacking of serviceable material and unserviceable
material separately under supervision of concerned
department

Unit = running metre


Taking output = 10 metres
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
Plumber day 0.250 0.250 0.250 738.00 184.50 184.50 184.50 L-02
b) Machinery
Truck 10 tonne capacity hour 0.250 0.250 0.250 1,731.45 432.86 432.86 432.86 P&M-017
Light Crane 3 tonne capacity hour 0.500 0.500 0.500 1,083.60 541.80 541.80 541.80 P&M-102
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 178.53 223.16 267.79
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 241.01 245.47 249.94
Cost for 10 metres = a+b+c+d 2,651.10 2,700.19 2,749.29
Rate per metre = (a+b+c+d)/10 265.11 270.02 274.93
Say 265.00 270.00 275.00
Note The rate analysis does not include any excavation in
earth or dismantling of masonry works which are to be
measured and paid separately.

2.13 202 Removal of Cement Concrete Pipe of Sewer Gutter

Removal of cement concrete pipe of sewer gutter 1500


mm dia under the supervision of concerned department
including disposal with all lifts and up to a lead of 1000
metres and stacking of serviceable and unserviceable
material separately but excluding earth excavation and
dismantling of masonry works.

Unit = running metre


Taking output = 10 metres
a) Labour
Mate day 0.100 0.100 0.100 617.00 61.70 61.70 61.70 L-12
Mazdoor day 2.500 2.500 2.500 511.52 1,278.80 1,278.80 1,278.80 L-13
b) Machinery
Crane 5 tonne capacity hour 0.300 0.300 0.300 1,128.75 338.63 338.63 338.63 P&M-103
Truck flat body 10 tonne hour 1.000 1.000 1.000 1,731.45 1,731.45 1,731.45 1,731.45 P&M-017
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 272.85 341.06 409.27
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 368.34 375.16 381.98
Cost for 10 metres = a+b+c+d 4,051.76 4,126.80 4,201.83
Rate per metre = (a+b+c+d)/10 405.18 412.68 420.18
Say 405.00 413.00 420.00
Quantity Amount (Rs.)
Ref.to
Rate Remarks
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project /Input ref.
Specification Project Project Project Project

Note The rate analysis does not include any excavation in


earth or dismantling of masonry works which are to be
measured and paid separately.

2.14 202 Removal of Telephone / Electric Poles and Lines

Removal of telephone / Electric poles including


excavation and dismantling of foundation concrete and
lines under the supervision of concerned department,
disposal with all lifts and up to a lead of 1000 metres
and stacking the serviceable and unserviceable
material separately

Unit = each
Taking output = 30 Nos
a) Labour
Mate day 0.480 0.480 0.480 617.00 296.16 296.16 296.16 L-12
Mazdoor day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-13
Electrician/Lineman day 2.000 2.000 2.000 738.00 1,476.00 1,476.00 1,476.00 L-02
b) Machinery
Tractor-trolley hour 1.500 1.500 1.500 1,876.50 2,814.75 2,814.75 2,814.75 P&M-026
c) Overhead charges for large @ 10% on @ 12% on
Project @ 8% (a+b) (a+b) 776.17 970.21 1,164.25
on (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 1,047.83 1,067.23 1,086.64
Cost for 30 poles = a+b+c+d 11,526.11 11,739.55 11,953.00
Rate per pole = (a+b+c+d)/30 384.20 391.32 398.43
Say 384.00 391.00 398.00
All the serviceable material resulting from removal of
Note: Telephone / Electric Poles and Lines would be handed
over to the employer.
CHAPTER-3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

3.01 301 Excavation in Soil by Manual Means .

Excavation for roadway in soil using manual means


including loading in truck for carrying of cut earth to
embankment site with all lifts and lead upto1000 metres.

Unit = cum
Taking output = 120 cum
a) Labour
Mate day 1.800 1.800 1.800 617.00 1,110.60 1,110.60 1,110.60 L-12
Mazdoor day 45.000 45.000 45.000 511.52 23,018.40 23,018.40 23,018.40 L-13
b) Machinery
Truck 5.5 cum capacity hour 9.236 9.236 9.236 1,731.45 15,992.30 15,992.30 15,992.30 P&M-017
@ 8% on @ 10% on @ 12% on 3,209.70 4,012.13 4,814.56
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 4,333.10 4,413.34 4,493.59
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost of 120 cum = a+b+c+d 47,664.11 48,546.78 49,429.44
Rate per cum = (a+b+c+d)/120 397.20 404.56 411.91
Say 397.00 405.00 412.00
Note In case there is a situation where the cross-section is of
cut and fill and cut earth is required to be used in
embankment in the immediate vicinity, the item of carriage
in the truck shall be omitted.

3.02 301 Excavation in Ordinary Rock by Manual Means


Excavation in ordinary rock using manual means including
loading in a truck and carrying of excavated material to
embankment site with in all lifts and leads upto 1000
metres
Unit = cum
Taking output = 120 cum
a) Labour
Mate day 2.800 2.800 2.800 617.00 1,727.60 1,727.60 1,727.60 L-12
Mazdoor day 70.000 70.000 70.000 511.52 35,806.40 35,806.40 35,806.40 L-13
b) Machinery
Truck 5.5 cum capacity hour 9.236 9.236 9.236 1,731.45 15,992.30 15,992.30 15,992.30 P&M-017
@ 8% on @ 10% on @ 12% on 4,282.10 5,352.63 6,423.16
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 5,780.84 5,887.89 5,994.95
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 120 cum = a+b+c+d 63,589.25 64,766.83 65,944.40
Rate per cum = (a+b+c+d)/120 529.91 539.72 549.54
Say 530.00 540.00 550.00
Note In case there is a situation where the cross-section is of
cut and fill and cut earth is required to be used in
embankment in the immediate vicinity, the item of carriage
in the truck shall be omitted.

3.03 301
Excavation in Soil with Dozer with lead upto 1000 metres

Excavation for road way in soil by mechanical means


including cutting and transporting the earth to site of
embankment/dumping area with lead upto 1000 metres,
including trimming bottom and side slopes in accordance
with requirements of lines, grades and cross sections.

Unit = cum
Taking output = 500 cum 800 Tonne
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Dozer
Dozer (240HP) hour 3.731 6,586.65 24,577.05 P&M-001
Dozer (175 HP) hour 5.342 5,087.25 27,175.48 P&M-002
Dozer (90 HP) hour 8.621 3,502.80 30,196.55 P&M-003
Tipper
(i) 18 cum capacity t.km 800.000 6.18 4,942.80 P&M-117
(ii) 14 cum capacity t.km 800.000 7.01 5,610.24 P&M-120
(iii) 10 cum capacity t.km 800.000 8.66 6,931.20 P&M-123
Loading & unloading charges
(i) Using by 18 cum capacity Tipper & 3.1 Cum capacity cum 500.000 92.72 46,361.18 P&M-129
Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum capacity cum 500.000 92.81 46,406.25 P&M-130
Loader
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 500.000 118.14 59,070.00 P&M-131
Loader

@ 8% on @ 10% on @ 12% on 6,113.38 7,972.82 11,608.07


c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 8,253.06 8,770.10 10,834.20
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 500 cum = a+b+c+d 90,783.67 96,471.09 119,176.23
Rate per cum = (a+b+c+d)/500 181.57 192.94 238.35
Say 182.00 193.00 238.00
3.04 301 Excavation in Ordinary Rock with Dozer with lead upto
1000 metres

Excavation for roadway in ordinary rock by deploying a


dozer, including cutting and transporting the earth to site
of embankment/dumping area with lead upto 1000
metres, trimming bottom and side slopes in accordance
with the requirements of lines, grades and cross sections.

Unit = cum
Taking output = 300 cum 720 Tonne
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Dozer
Dozer (240HP) hour 4.688 6,586.65 30,878.22 P&M-001
Dozer (175 HP) hour 6.667 5,087.25 33,916.70 P&M-002
Dozer (90 HP) hour 10.714 3,502.80 37,529.00 P&M-003
Tipper
For transportation considering lead @ 1km
(i) 18 cum capacity t.km 720.000 6.18 4,448.52 P&M-117
(ii) 14 cum capacity t.km 720.000 7.01 5,049.22 P&M-120
(iii) 10 cum capacity t.km 720.000 8.66 6,238.08 P&M-123
For Loading & unloading charges
(i) Using by 18 cum capacity Tipper & 3.1 Cum capacity cum 360.000 92.72 33,380.05 P&M-129
Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum capacity cum 360.000 92.81 33,412.50 P&M-130
Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 360.000 118.14 42,530.40 P&M-131
Loader
@ 8% on @ 10% on @ 12% on 5,539.44 7,291.46 10,420.04
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 7,478.24 8,020.61 9,725.37
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 300 cum = a+b+c+d 82,260.66 88,226.68 106,979.09
Rate per cum = (a+b+c+d)/300 274.20 294.09 356.60
Say 274.00 294.00 357.00
3.05 301 Excavation in Hard Rock (requiring blasting) with
disposal upto 1000 metres

Excavation for roadway in hard rock (requiring blasting)


by drilling, blasting and breaking, trimming of bottom and
side slopes in accordance with requirements of lines,
grades and cross sections, loading and disposal of cut
road with in all lifts and leads upto 1000 metres

Unit = cum
Taking output = 180 cum 360 Tonne
a) Labour
Mate day 0.210 0.210 0.210 617.00 129.57 129.57 129.57 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Driller day 2.000 2.000 2.000 558.00 1,116.00 1,116.00 1,116.00 L-06
Blaster day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-03
b) Machinery
Air Compressor 250 cfm hour 27.500 27.500 27.500 614.25 16,891.88 16,891.88 16,891.88 P&M-029
hour 55.000 55.000 55.000 11.55 635.25 635.25 635.25 P&M-078
Pneumatic breaker for drilling holes (@ 4.5 m per hour)

Dozer
Dozer (240HP) hour 3.375 6,586.65 22,229.94 P&M-001
Dozer (175 HP) hour 4.800 5,087.25 24,418.80 P&M-002
Dozer (90 HP) hour 7.714 3,502.80 27,021.60 P&M-003
Tipper
For transportation considering lead @ 1km
(i) 18 cum capacity t.km 360.000 7.51 2,703.09 P&M-117
(ii) 14 cum capacity t.km 360.000 8.52 3,068.10 P&M-120
(iii) 10 cum capacity t.km 360.000 10.53 3,790.50 P&M-123
For loading & unloading charges
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

(i) Using by 18 cum capacity Tipper & 3.1 Cum capacity cum 216.000 92.72 20,028.03 P&M-129
Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum capacity cum 216.000 92.81 20,047.50 P&M-130
Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 216.000 118.14 25,518.24 P&M-131
Loader
c) Materials
Small dia.Explosive at 0.40 kg / cum for 180 cum ( 180 x kg 73.800 73.800 73.800 81.90 6,044.22 6,044.22 6,044.22 M-215
0.40 )
Explosive at 0.20 kg / cum for secondary blast @ 5%of the
total volume ( 180 x 0.2x5% )
Electric detonators at 1 per hole for main blast holes no 103.000 103.000 103.000 21.00 2,163.00 2,163.00 2,163.00 M-217
(21x3+20*2)=103 nos
Ordinary detonators @ 1 per hole for 10 secondary no 10.000 10.000 10.000 21.00 210.00 210.00 210.00 M-216
holes( required for 5% of the total quantity @ 0.6 m per
hole for I cum )
Detonating fuse coil m 320.000 320.000 320.000 19.00 6,080.00 6,080.00 6,080.00 M-218
Credit for excavated rock found suitable for use @ 50 per cum 90.000 90.000 90.000 319.70 28,773.00 28,773.00 28,773.00 M-090
cent quantity blasted
@ 8% on @ 10% on @ 12% on 8,693.31 11,123.98 14,404.28
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 11,735.97 12,236.37 13,444.00
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 180 cum = a+b+c+d+e 129,095.71 134,600.10 147,883.98
Rate per cum = (a+b+c+d+e)/180 717.20 747.78 821.58
Say 717.00 748.00 822.00
Note 1. The quality and availability of rock shall be checked
before affording credit.

2. In case some rock is issued to the contractor at site, the


item of carriage shall be reduced/restricted to that extent.

3.06 301 Excavation in Soil using Hydraulic Excavator and Tippers


with Disposal upto 1000 metres.

Excavation for roadwork in soil with hydraulic excavator


including cutting and loading in tippers, trimming bottom
and side slopes, in accordance with requirements of lines,
grades and cross sections, and transporting to the
embankment location within all lifts and lead upto 1000m

Unit = cum
Taking output = 350 cum
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.926 3,420.00 13,426.67 P&M-007
(ii) 1.1 cum bucket capacity hour 5.024 3,074.00 15,442.79 P&M-008
(iii) 0.9 cum bucket capacity hour 6.321 2,782.00 17,584.99 P&M-009
Tipper
For transportation considering lead @ 1 km
(i) 18 cum capacity t.km 525.000 6.18 3,243.71 P&M-117
(ii) 14 cum capacity t.km 525.000 7.01 3,681.72 P&M-120
(iii) 10 cum capacity t.km 525.000 8.66 4,548.60 P&M-123
For loading & unloading time
(i) 18 cum capacity hour 3.926 2,883.30 11,319.62 P&M-014
(ii) 14 cum capacity hour 5.024 2,556.75 12,844.29 P&M-015
(iii) 10 cum capacity hour 6.321 2,274.30 14,375.82 P&M-016
@ 8% on @ 10% on @ 12% on 2,282.10 3,250.50 4,445.47
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 3,080.83 3,575.55 4,149.11
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 350 cum = a+b+c+d 33,889.13 39,331.05 45,640.19
Rate per cum = (a+b+c+d)/350 96.83 112.37 130.40
Say 97.00 112.00 130.00
3.07 301
Excavation in Ordinary Rock using Hydraulic Excavator
and Tippers with Disposal upto 1000 metres.

Excavation for roadwork in Ordinary Rock with hydraulic


excavator including cutting and loading in tippers, trimming
bottom and side slopes, in accordance with requirements
of lines, grades and cross sections, and transporting to the
embankment location within all lifts and lead upto 1000m

Unit = cum
Taking output = 60 cum 120 Tonne
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator for Jack Hammer
(i) 1.2 cum bucket capacity hour 6.982 3,420.00 23,878.44 P&M-007
(ii) 1.1 cum bucket capacity hour 8.214 3,074.00 25,249.84 P&M-008
(iii) 0.9 cum bucket capacity hour 8.727 2,782.00 24,278.51 P&M-009
Jack Hammer hour 6.982 8.214 8.727 206.00 1,438.25 1,692.06 1,797.82 P&M-010
Tipper
For transportation considering lead @ 1km
(i) 18 cum capacity t.km 120.000 6.18 741.42 P&M-117
(ii) 14 cum capacity t.km 120.000 7.01 841.54 P&M-120
(iii) 10 cum capacity t.km 120.000 8.66 1,039.68 P&M-123
For loading & unloading charges for disposed of grabbed
material
(i) Using by 18 cum capacity Tipper & 3.1 Cum capacity cum 72.000 92.72 6,676.01 P&M-129
Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum capacity cum 72.000 92.81 6,682.50 P&M-130
Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 72.000 118.14 8,506.08 P&M-131
Loader
@ 8% on @ 10% on @ 12% on 2,661.63 3,500.21 4,339.00
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 3,593.19 3,850.23 4,049.73
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 60 cum = a+b+c+d 39,525.14 42,352.58 44,547.02
Rate per cum = (a+b+c+d)/60 658.75 705.88 742.45
Say 659.00 706.00 742.00
3.08 301 Excavation in Hard Rock (blasting prohibited)

Excavation for roadwork in Hard Rock (blasting


prohibited) with hydraulic excavator including cutting and
loading in tippers, trimming bottom and side slopes, in
accordance with requirements of lines, grades and cross
sections, and transporting to the embankment location
within all lifts and lead upto 1000m

A Unit = cum
Taking output = 50 cum 100 Tonne
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator for Jack Hammer
(i) 1.2 cum bucket capacity hour 8.533 3,420.00 29,184.00 P&M-007
(ii) 1.1 cum bucket capacity hour 10.039 3,074.00 30,859.89 P&M-008
(iii) 0.9 cum bucket capacity hour 11.378 2,782.00 31,652.98 P&M-009
Jack Hammer hour 8.533 10.039 11.378 206.00 1,757.87 2,068.08 2,343.82 P&M-010
Tipper
For transportation considering lead @ 1km
(i) 18 cum capacity t.km 100.000 6.18 617.85 P&M-117
(ii) 14 cum capacity t.km 100.000 7.01 701.28 P&M-120
(iii) 10 cum capacity t.km 100.000 8.66 866.40 P&M-123
For loading & unloading charges for disposed of grabbed
material
(i) Using by 18 cum capacity Tipper & 3.1 Cum capacity cum 60.000 92.72 5,563.34 P&M-129
Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum capacity cum 60.000 92.81 5,568.75 P&M-130
Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 60.000 118.14 7,088.40 P&M-131
Loader
Credit for excavated rock found suitable for use @ 50 per cum 25.000 25.000 25.000 319.70 -7,992.50 -7,992.50 -7,992.50 M-090
cent of excavated quantity
@ 8% on @ 10% on @ 12% on 2,373.34 3,174.17 4,139.44
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 3,204.01 3,491.59 3,863.47
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 50 cum = a+b+c+d 35,244.11 38,407.45 42,498.21
Rate per cum = (a+b+c+d)/50 704.88 768.15 849.96
Say 705.00 768.00 850.00
3.08 B Manual Method
Unit = cum
Taking output = 16 cum
a) Labour
Mate day 1.640 1.640 1.640 617.00 1,011.88 1,011.88 1,011.88 L-12
Mazdoor including loading in truck day 16.000 16.000 16.000 511.52 8,184.32 8,184.32 8,184.32 L-13
Chiseller day 24.000 24.000 24.000 617.00 14,808.00 14,808.00 14,808.00 L-05
Blacksmith (IInd class) day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-01
b) Machinery
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

Tipper 5.5 cum capacity, 1 trip per hour. hour 2.900 2.900 2.900 1,731.45 5,021.21 5,021.21 5,021.21 P&M-017
Credit for excavated rock found suitable for use @ 50 per cum 8.000 8.000 8.000 319.70 -2,557.60 -2,557.60 -2,557.60 M-090
cent of excavated
@ 8% on @ 10% on @ 12% on 2,171.74 2,714.68 3,257.62
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 2,931.85 2,986.15 3,040.44
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 16 cum = a+b+c+d 32,250.40 32,847.63 33,444.86
Rate per cum = (a+b+c+d)/16 2,015.65 2,052.98 2,090.30
Say 2,016.00 2,053.00 2,090.00
Note
1. Credit is considered for 50 per cent of quantity of work.

2. Loading for disposal will be done manually, being small


quantity.
3. In case some rock is issued to contractor at site, the
item of carriage shall be omitted to the extent of quantity
issued to the contractor.

3.09 301 Excavation in Hard Rock (controlled blasting) with


disposal upto 1000 metres

Excavation for roadway in hard rock (requiring blasting)


by drilling, blasting and breaking, trimming of bottom and
side slopes in accordance with requirements of lines,
grades and cross sections, loading and disposal of cut
road with in all lifts and leads upto 1000 metres

Unit = cum
Taking output = 180 cum 360 Tonne
a) Labour
Mate day 0.210 0.210 0.210 617.00 129.57 129.57 129.57 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Driller day 2.000 2.000 2.000 558.00 1,116.00 1,116.00 1,116.00 L-06
Blaster day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-03
b) Machinery
Air Compressor 250 cfm hour 27.500 27.500 27.500 614.25 16,891.88 16,891.88 16,891.88 P&M-029
hour 55.000 55.000 55.000 11.55 635.25 635.25 635.25 P&M-078
Pneumatic breaker for drilling holes (@ 4.5 m per hour)

Dozer
Dozer (240HP) hour 3.375 6,586.65 22,229.94 P&M-001
Dozer (175 HP) hour 4.320 5,087.25 21,976.92 P&M-002
Dozer (90 HP) hour 7.714 3,502.80 27,021.60 P&M-003
Tipper
For transportation considering lead @ 1km
(i) 18 cum capacity t.km 360.000 7.51 2,703.09 P&M-117
(ii) 14 cum capacity t.km 360.000 8.52 3,068.10 P&M-120
(iii) 10 cum capacity t.km 360.000 10.53 3,790.50 P&M-123
For loading & unloading charges
(i) Using by 18 cum capacity Tipper & 3.1 Cum capacity cum 216.000 92.72 20,028.03 P&M-129
Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum capacity cum 216.000 92.81 20,047.50 P&M-130
Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 216.000 118.14 25,518.24 P&M-131
Loader
c) Materials
Small dia.Explosive at 0.40 kg / cum for 180 cum ( 180 x kg 73.800 73.800 73.800 81.90 6,044.22 6,044.22 6,044.22 M-215
0.40 )
Explosive at 0.20 kg / cum for secondary blast @ 5%of the
total volume ( 180 x 0.2x5% )
Electric detonators at 1 per hole for main blast holes no 103.000 103.000 103.000 21.00 2,163.00 2,163.00 2,163.00 M-217
(21x3+20*2)=103 nos
Ordinary detonators @ 1 per hole for 10 secondary no 10.000 10.000 10.000 21.00 210.00 210.00 210.00 M-216
holes( required for 5% of the total quantity @ 0.6 m per
hole for I cum )
Detonating fuse coil m 320.000 320.000 320.000 19.00 6,080.00 6,080.00 6,080.00 M-218
Credit for excavated rock found suitable for use @ 50 per cum 90.000 90.000 90.000 319.70 28,773.00 28,773.00 28,773.00 M-090
cent quantity blasted
Add 5 per cent of cost of a+b+c towards muffling
arrangements to guard against any rock fly off during 5,433.32 5,439.89 6,001.78
blasting
@ 8% on @ 10% on @ 12% on 9,127.98 11,423.78 15,124.50
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 12,322.77 12,566.15 14,116.20
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 180 cum = a+b+c+d+e 135,550.49 138,227.70 155,278.18
Rate per cum = (a+b+c+d+e)/180 753.06 767.93 862.66
Say 753.00 768.00 863.00
Note 1. The quality and availability of rock shall be checked
before affording credit.
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

2. In case some rock is issued to the contractor at site, the


item of carriage shall be reduced/restricted to that extent.

3.10 301
Excavation in Marshy Soil using Hydraulic Excavator and
Tippers with Disposal upto 1000 metres.

Excavation for roadwork in Marshy Soil with hydraulic


excavator including cutting and loading in tippers, trimming
bottom and side slopes, in accordance with requirements
of lines, grades and cross sections, and transporting to the
embankment location within all lifts and lead upto 1000m

Unit = cum
Taking output = 325 cum 487.5 Tonne
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 8.506 3,420.00 29,091.11 P&M-007
(ii) 1.1 cum bucket capacity hour 9.796 3,074.00 30,113.44 P&M-008
(iii) 0.9 cum bucket capacity hour 13.695 2,782.00 38,100.81 P&M-009
Tipper
For transportation to dumping yard considering lead @
1km
(i) 18 cum capacity t.km 487.500 6.18 3,012.02 P&M-117
(ii) 14 cum capacity t.km 487.500 7.01 3,418.74 P&M-120
(iii) 10 cum capacity t.km 487.500 8.66 4,223.70 P&M-123
For loading & unloading time
(i) 18 cum capacity hour 8.506 2,883.30 24,525.85 P&M-014
(ii) 14 cum capacity hour 9.796 2,556.75 25,046.37 P&M-015
(iii) 10 cum capacity hour 13.695 2,274.30 31,147.61 P&M-016
@ 8% on @ 10% on @ 12% on 4,573.21 5,911.47 8,881.00
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 6,173.84 6,502.62 8,288.93
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 325 cum = a+b+c+d 67,912.23 71,528.84 91,178.25
Rate per cum = (a+b+c+d)/325 208.96 220.09 280.55
Say 209.00 220.00 281.00
3.11 301 Removal of Unserviceable Soil with Disposal upto 1000
metres
Removal of unserviceable soil including excavation,
loading and disposal upto 1000 metres lead but excluding
replacement by suitable soil which shall be paid separately
as per clause 305.
Unit = cum
Taking output = 415 cum 622.5 Tonne
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 4.769 3,420.00 16,309.98 P&M-007
(ii) 1.1 cum bucket capacity hour 5.492 3,074.00 16,882.41 P&M-008
(iii) 0.9 cum bucket capacity hour 7.678 2,782.00 21,360.20 P&M-009
Tipper
For transportation to dumping yard considering lead @
1km
(i) 18 cum capacity t.km 622.500 6.18 3,846.12 P&M-117
(ii) 14 cum capacity t.km 622.500 7.01 4,365.47 P&M-120
(iii) 10 cum capacity t.km 622.500 8.66 5,393.34 P&M-123
For loading & unloading time
(i) 18 cum capacity hour 4.769 2,883.30 13,750.46 P&M-014
(ii) 14 cum capacity hour 5.492 2,556.75 14,041.67 P&M-015
(iii) 10 cum capacity hour 7.678 2,274.30 17,462.08 P&M-016
@ 8% on @ 10% on @ 12% on 2,755.42 3,582.57 5,370.22
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 3,719.82 3,940.83 5,012.20
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 415 cum = a+b+c+d 40,917.99 43,349.15 55,134.23
Rate per cum = (a+b+c+d)/415 98.60 104.46 132.85
Say 99.00 104.00 133.00
3.12 303 Presplitting of Rock Excavation Slopes
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

Carrying out excavation in hard rock to achieve a specified


slope of the rock face by controlled use of explosives and
blasting accessories in properly aligned and spaced drill
holes, collection of the excavated rock by a dozer, loading
in tipper by a front end loader and disposing of the
material with all lifts and lead upto 1000 m, all as specified
in clause No. 303

Taking output = 400 sqm( 120 cum considering 300 mm


average depth of excavation over the existing rock face)

Unit = Sqm
Taking output = 400 sqm 240 Tonne
a) Labour
Mate day 0.210 0.210 0.210 617.00 129.57 129.57 129.57 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Driller day 2.000 2.000 2.000 558.00 1,116.00 1,116.00 1,116.00 L-06
Blaster day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-03
b) Machinery
Air Compressor 250 cfm hour 17.000 17.000 17.000 614.25 10,442.25 10,442.25 10,442.25 P&M-029
hour 34.000 34.000 34.000 11.55 392.70 392.70 392.70 P&M-078
Pneumatic breaker for drilling holes (@ 4.5 m per hour)

Dozer
(i) Dozer (240HP) hour 1.875 6,586.65 12,349.97 P&M-001
(ii) Dozer (175 HP) hour 2.400 5,087.25 12,209.40 P&M-002
(iii) Dozer (90 HP) hour 4.286 3,502.80 15,012.00 P&M-003
Tipper
For transportation considering lead @ 1km
(i) 18 cum capacity t.km 240.000 6.18 1,482.84 P&M-117
(ii) 14 cum capacity t.km 240.000 7.01 1,683.07 P&M-120
(iii) 10 cum capacity t.km 240.000 8.66 2,079.36 P&M-123
For Loading & unloading charges
(i) Using by 18 cum capacity Tipper & 3.1 Cum capacity cum 144.000 92.72 13,352.02 P&M-129
Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum capacity cum 144.000 92.81 13,365.00 P&M-130
Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 144.000 118.14 17,012.16 P&M-131
Loader
c) Materials
Small dia.Explosive at 0.40 kg / cum for 400 cum ( 400 x kg 49.200 49.200 49.200 81.90 4,029.48 4,029.48 4,029.48 M-215
0.40 )
Explosive at 0.20 kg / cum for secondary blast @ 5%of the
total volume ( 400 x 0.2x5% )
Electric detonators at 1 per hole for main blast holes no 69.000 69.000 69.000 21.00 1,449.00 1,449.00 1,449.00 M-217
(21x3+20*2)=103 nos
Ordinary detonators @ 1 per hole for 10 secondary no 7.000 7.000 7.000 21.00 147.00 147.00 147.00 M-216
holes( required for 5% of the total quantity @ 0.6 m per
hole for I cum )
Detonating fuse coil m 213.000 213.000 213.000 19.00 4,047.00 4,047.00 4,047.00 M-218
Credit for excavated rock found suitable for use @ 50 per cum 60.000 60.000 60.000 319.70 19,182.00 19,182.00 19,182.00 M-090
cent quantity blasted
@ 8% on @ 10% on @ 12% on 5,582.58 6,985.49 9,204.12
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 7,536.48 7,684.04 8,590.51
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 400 Sqm = a+b+c+d+e 82,901.33 84,524.44 94,495.58
Rate per cum = (a+b+c+d+e)/400 207.25 211.31 236.24
Say 207.00 211.00 236.00
Note 1. The quality and availability of rock shall be checked
before affording credit.

2. In case some rock is issued to the contractor at site, the


item of carriage shall be reduced/restricted to that extent.

3.13 304 Excavation for Structures


Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps
and other deleterious matter, dressing of sides and
bottom, backfilling the excavation earth to the extent
required and utilising the remaining earth locally for road
work.
(i) Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means (Depth upto 3 m)
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
@ 8% on (a) @ 10% on (a) @ 12% on (a) 343.17 428.96 514.75
b) Overhead charges
@ 10% on @ 10% on @ 10% on 463.28 471.86 480.44
c) Contractor's profit (a+b) (a+b) (a+b)
Cost for 10 cum = a+b+c 5,096.04 5,190.42 5,284.79
Rate per cum = (a+b+c)/10 509.60 519.04 528.48
Say 510.00 519.00 528.00
Note Cost of dewatering may be added where required upto 10
per cent of labour cost Assessment for dewatering shall
be made as per site conditions..

3.13 B Mechanical Means (Depth upto 3 m)


Unit = cum
Taking output = 330 cum
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Hydraulic Excavator
For excavation & Backfill
(i) 1.2 cum bucket capacity hour 4.627 3,420.00 15,824.29 P&M-007
(ii) 1.1 cum bucket capacity hour 5.329 3,074.00 16,380.39 P&M-008
(iii) 0.9 cum bucket capacity hour 7.450 2,782.00 20,725.16 P&M-009
Tipper
For transportation of excess material to dumping yard
considering lead @ 1km
(i) 18 cum capacity t.km 198.000 6.18 1,223.34 P&M-117
(ii) 14 cum capacity t.km 198.000 7.01 1,388.53 P&M-120
(iii) 10 cum capacity t.km 198.000 8.66 1,715.47 P&M-123
For loading & Unloding Time
(i) 18 cum capacity hour 1.851 2,883.30 5,336.39 P&M-014
(ii) 14 cum capacity hour 2.131 2,556.75 5,449.65 P&M-015
(iii) 10 cum capacity hour 2.980 2,274.30 6,777.17 P&M-016
@ 8% on @ 10% on @ 12% on 2,133.89 2,750.82 4,020.89
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 2,880.75 3,025.90 3,752.83
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 330 cum = a+b+c+d 31,688.26 33,284.88 41,281.13
Rate per cum = (a+b+c+d)/330 96.03 100.86 125.09
Say 96.00 101.00 125.00
3.13 (ii) Ordinary Rock (not requiring blasting)
A Manual Means (Depth upto 3 m)
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.400 0.400 0.400 617.00 246.80 246.80 246.80 L-12
Mazdoor day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-13
@ 8% on (a) @ 10% on (a) @ 12% on (a) 428.96 536.20 643.44
b) Overhead charges
@ 10% on @ 10% on @ 10% on 579.10 589.82 600.54
c) Contractor's profit (a+b) (a+b) (a+b)
Cost for 10 cum = a+b+c 6,370.06 6,488.02 6,605.98
Rate per cum = (a+b+c)/10 637.01 648.80 660.60
Say 637.00 649.00 661.00
Note Cost of dewatering upto 10 per cent of labour cost may
be added, where required. Assessment for dewatering
shall be made as per site conditions..

3.13 B Mechanical Means


Unit = cum
Taking output = 50 cum
a) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Machinery
Hydraulic Excavator
For excavation , backfilling & loading
(i) 1.2 cum bucket capacity hour 7.127 3,420.00 24,373.74 P&M-007
(ii) 1.1 cum bucket capacity hour 8.352 3,074.00 25,674.12 P&M-008
(iii) 0.9 cum bucket capacity hour 9.380 2,782.00 26,094.39 P&M-009
Jack Hammer hour 5.818 6.845 7.273 206.00 1,198.55 1,410.05 1,498.18 P&M-010
Tipper
For transportation to dumping yard considering lead @
1km
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

(i) 18 cum capacity t.km 40.000 6.18 247.14 P&M-117


(ii) 14 cum capacity t.km 40.000 7.01 280.51 P&M-120
(iii) 10 cum capacity t.km 40.000 8.66 346.56 P&M-123
For loading & unloading time
(i) 18 cum capacity hour 0.523 2,883.30 1,509.28 P&M-014
(ii) 14 cum capacity hour 0.603 2,556.75 1,541.31 P&M-015
(iii) 10 cum capacity hour 0.843 2,274.30 1,916.78 P&M-016
@ 8% on @ 10% on @ 12% on 2,314.98 3,051.46 3,775.74
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 3,125.23 3,356.61 3,524.02
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 50 cum = a+b+c+d 34,377.52 36,922.67 38,764.27
Rate per cum = (a+b+c+d)/50 687.55 738.45 775.29
Say 688.00 738.00 775.00
3.13 (iii) Hard Rock ( requiring blasting )
A Mechanical Means

Carrying out excavation in hard rock to achieve a specified


slope of the rock face by controlled use of explosives and
blasting accessories in properly aligned and spaced drill
holes, collection of the excavated rock by a dozer, loading
in tipper by a front end loader and disposing of the
material with all lifts and lead upto 1000 m, all as specified
in clause No. 303

Unit = cum
Taking output = 120 cum
a) Labour
Mate day 0.210 0.210 0.210 617.00 129.57 129.57 129.57 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Driller day 2.000 2.000 2.000 558.00 1,116.00 1,116.00 1,116.00 L-06
Blaster day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-03
b) Machinery
hour 17.000 17.000 17.000 637.35 10,834.95 10,834.95 10,834.95 P&M-029 +
P&M-078 x 2
Air Compressor 250 cfm

hour 34.000 34.000 34.000 11.55 392.70 392.70 392.70 P&M-078


Pneumatic breaker for drilling holes (@ 4.5 m per hour)

Hydraulic Excavator for Jack Hammer & backfilling ,


loading
(i) 1.2 cum bucket capacity hour 3.537 3,420.00 12,095.15 P&M-007
(ii) 1.1 cum bucket capacity hour 4.174 3,074.00 12,829.77 P&M-008
(iii) 0.9 cum bucket capacity hour 5.411 2,782.00 15,052.75 P&M-009
hour 1.024 1.280 1.365 11.55 11.83 14.78 15.77 P&M-078
Jack Hammer (consider 5% of the volume for dressing)

Tipper
For transportation considering lead @ 1km
(i) 18 cum capacity t.km 96.000 6.18 593.14 P&M-117
(ii) 14 cum capacity t.km 96.000 7.01 673.23 P&M-120
(iii) 10 cum capacity t.km 96.000 8.66 831.74 P&M-123
For loading & unloading time
(i) 18 cum capacity hour 1.005 2,883.30 2,897.82 P&M-014
(ii) 14 cum capacity hour 1.157 2,556.75 2,959.32 P&M-015
(iii) 10 cum capacity hour 1.618 2,274.30 3,680.21 P&M-016
c) Materials
Small dia.Explosive at 0.40 kg / cum for 120 cum ( 120 x kg 49.200 49.200 49.200 81.90 4,029.48 4,029.48 4,029.48 M-215
0.40 )
Explosive at 0.20 kg / cum for secondary blast @ 5%of the
total volume ( 120 x 0.2x5% )
Electric detonators at 1 per hole for main blast holes no 69.000 69.000 69.000 21.00 1,449.00 1,449.00 1,449.00 M-217
(21x3+20*2)=103 nos
Ordinary detonators @ 1 per hole for 10 secondary no 7.000 7.000 7.000 21.00 147.00 147.00 147.00 M-216
holes( required for 5% of the total quantity @ 0.6 m per
hole for I cum )
Detonating fuse coil m 213.000 213.000 213.000 19.00 4,047.00 4,047.00 4,047.00 M-218
@ 8% on @ 10% on @ 12% on 3,152.49 4,028.52 5,206.63
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 4,255.86 4,431.38 4,859.52
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 120 cum = a+b+c+d+e 46,814.41 48,745.14 53,454.77
Rate per cum = (a+b+c+d+e)/120 390.12 406.21 445.46
Say 390.00 406.00 445.00
3.13 (iv) Hard Rock ( blasting prohibited )
Unit = cum
Taking output = 35 cum
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery

Hydraulic Excavator used for Jack hammer & loading

(i) 1.2 cum bucket capacity hour 9.571 3,420.00 32,731.79 P&M-007
(ii) 1.1 cum bucket capacity hour 11.244 3,074.00 34,564.06 P&M-008
(iii) 0.9 cum bucket capacity hour 13.783 2,782.00 38,344.31 P&M-009
Jack Hammer hour 8.960 10.541 12.800 206.00 1,845.76 2,171.48 2,636.80 P&M-010
Tipper
For transportation to dumping yard considering lead @
1km
(i) 18 cum capacity t.km 28.000 6.18 173.00 P&M-117
(ii) 14 cum capacity t.km 28.000 7.01 196.36 P&M-120
(iii) 10 cum capacity t.km 28.000 8.66 242.59 P&M-123
For loading & unloading
(i) 18 cum capacity hour 0.244 2,883.30 704.33 P&M-014
(ii) 14 cum capacity hour 0.281 2,556.75 718.78 P&M-015
(iii) 10 cum capacity hour 0.393 2,274.30 894.25 P&M-016
@ 8% on @ 10% on @ 12% on 2,922.18 3,872.31 5,182.84
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 3,944.95 4,259.54 4,837.32
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 35 cum = a+b+c+d 43,394.41 46,854.92 53,210.51
Rate per cum = (a+b+c+d)/35 1,239.84 1,338.71 1,520.30
Say 1,240.00 1,339.00 1,520.00
3.13 (v) Marshy soil
Unit = cum
Taking output = 10 cum
A Manual means ( upto 3 m depth)
a) Labour
Mate/Supervisor day 0.400 0.400 0.400 617.00 246.80 246.80 246.80 L-12
Mazdoor day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-13
b) Machinery
Tractor-trolley hour 2.670 2.670 2.670 1,876.50 5,010.26 5,010.26 5,010.26 P&M-026
c) Material
Selected earth for refilling cum 5.000 5.000 5.000 222.00 1,110.00 1,110.00 1,110.00 M-164
@ 8% on @ 10% on @ 12% on 918.58 1,148.23 1,377.87
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 1,240.08 1,263.05 1,286.01
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 10 cum = a+b+c+d+e 13,640.92 13,893.53 14,146.14
Rate per cum = ( a+b+c+d+e)/ 10 1,364.09 1,389.35 1,414.61
Say 1,364.00 1,389.00 1,415.00
Note 1. Cost of dewatering @ 30 per cent of (a), may be
added, where required Assessment for dewatering shall
be made as per site conditions.
2. Shoring & strutting 20 per cent of (a), where required
may be added

3. It is assumed that Marshy Soil will be available upto 3 m


depth only. For deeper excavation below 3 m depth, refer
analysis in item (i) to (iv) for ordinary soil

3.13 B Mechanical Means


Unit = cum
Taking output = 260 cum
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 10.256 3,420.00 35,075.57 P&M-007
(ii) 1.1 cum bucket capacity hour 11.811 3,074.00 36,308.20 P&M-008
(iii) 0.9 cum bucket capacity hour 16.513 2,782.00 45,939.17 P&M-009
Tipper
For transportation to dumping yard considering lead @
1km
(i) 18 cum capacity t.km 639.600 6.18 3,951.77 P&M-117
(ii) 14 cum capacity t.km 639.600 7.01 4,485.39 P&M-120
(iii) 10 cum capacity t.km 639.600 8.66 5,541.49 P&M-123
For loading & unloading
(i) 18 cum capacity hour 10.256 2,883.30 29,571.17 P&M-014
(ii) 14 cum capacity hour 11.811 2,556.75 30,198.76 P&M-015
(iii) 10 cum capacity hour 16.513 2,274.30 37,555.52 P&M-016
c) Material
Selected earth for refilling cum 156.000 156.000 156.000 222.00 34,632.00 34,632.00 34,632.00 M-164
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

@ 8% on @ 10% on @ 12% on 8,301.34 10,616.05 14,904.53


c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 11,206.80 11,677.66 13,910.89
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 260 cum = a+b+c+d 123,274.84 128,454.26 153,019.79
Rate per cum = (a+b+c+d)/260 474.13 494.05 588.54
Say 474.00 494.00 589.00
3.14 305.4.3 Scarifying the existing granular road surface to a depth of
50 mm and disposal of scarified material within all lifts and
leads upto 1000 metres.
(i) Scarifying Existing Granular Surface to a Depth of 50 mm
by Manual Means
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor including loading and unloading day 5.000 5.000 5.000 511.52 2,557.60 2,557.60 2,557.60 L-13
b) Machinery
Tractor-trolley hour 1.670 1.670 1.670 1,876.50 3,133.76 3,133.76 3,133.76 P&M-026
@ 8% on @ 10% on @ 12% on 465.18 581.48 697.77
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 627.99 639.62 651.25
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 100 sqm = a+b+c+d 6,907.93 7,035.85 7,163.78
Rate per sqm = (a+b+c+d)/100 69.08 70.36 71.64
Say 69.00 70.00 72.00
Note In case material is to be reused at site, transportation cost
catered above for disposal shall be deleted.
3.14 305.4.3 (ii) By Mechanical Means using Hydraulic excavator
Unit = sqm
Taking output = 6000 sqm
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 4.309 3,420.00 14,736.59 P&M-007
(ii) 1.1 cum bucket capacity hour 4.962 3,074.00 15,254.46 P&M-008
(iii) 0.9 cum bucket capacity hour 6.938 2,782.00 19,300.60 P&M-009
Tipper
For transportation to dumping yard considering lead @
1km
(i) 18 cum capacity t.km 600.000 6.18 3,707.10 P&M-117
(ii) 14 cum capacity t.km 600.000 7.01 4,207.68 P&M-120
(iii) 10 cum capacity t.km 600.000 8.66 5,198.40 P&M-123
For loading & unloading
(i) 18 cum capacity hour 4.309 2,883.30 12,423.98 P&M-014
(ii) 14 cum capacity hour 4.962 2,556.75 12,687.65 P&M-015
(iii) 10 cum capacity hour 6.938 2,274.30 15,778.34 P&M-016
@ 8% on @ 10% on @ 12% on 2,512.31 3,268.60 4,897.62
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 3,391.62 3,595.46 4,571.12
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 6000 sqm = a+b+c+d 37,307.79 39,550.05 50,282.28
Rate per sqm = (a+b+c+d)/6000 6.22 6.59 8.38
Say 6.00 7.00 8.00
3.14 305.4.3 (iii) By Mechanical Means using Motor Grader
Unit = sqm
Taking output = 12500 sqm
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Motor Grader
(i) Motor grader 4.30 metre blade hour 3.064 5,991.00 18,354.78 P&M-004
(ii) Motor grader 3.70 metre blade hour 3.676 5,497.00 20,209.56 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.720 4,796.00 17,842.26 P&M-006
Tipper
For transportation to dumping yard considering lead @
1km
(i) 18 cum capacity t.km 1250.000 6.18 7,723.13 P&M-117
(ii) 14 cum capacity t.km 1250.000 7.01 8,766.00 P&M-120
(iii) 10 cum capacity t.km 1250.000 8.66 10,830.00 P&M-123
For Loading & unloading charges
(i) Using by 18 cum capacity Tipper & 3.1 Cum capacity cum 625.000 92.72 57,951.47 P&M-129
Loader
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

(ii) Using by 14 cum capacity Tipper & 2.1 Cum capacity cum 625.000 92.81 58,007.81 P&M-130
Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 625.000 118.14 73,837.50 P&M-131
Loader
@ 8% on @ 10% on @ 12% on 6,765.25 8,751.96 12,365.52
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 9,133.08 9,627.15 11,541.15
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 12500 sqm = a+b+c+d 100,463.90 105,898.68 126,952.63
Rate per sqm = (a+b+c+d)/12500 8.04 8.47 10.16
Say 8.00 8.00 10.00
Note
In case material is to be reused at site, transportation cost
catered above for disposal shall be deleted.

3.15 305.4.3 Scarifying the existing bituminous surface to a depth of 50


mm and disposal of scarified material within all lifts and
leads upto 1000 metres.
(i) By Mechanical Means using Hydraulic excavator
Unit = sqm
Taking output = 6000 sqm 300
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 5.196 3,420.00 17,770.59 P&M-007
(ii) 1.1 cum bucket capacity hour 5.984 3,074.00 18,395.09 P&M-008
(iii) 0.9 cum bucket capacity hour 8.366 2,782.00 23,274.25 P&M-009
Tipper
For transportation to dumping yard considering lead @
1km
(i) 18 cum capacity t.km 690.000 6.18 4,263.17 P&M-117
(ii) 14 cum capacity t.km 690.000 7.01 4,838.83 P&M-120
(iii) 10 cum capacity t.km 690.000 8.66 5,978.16 P&M-123
For loading & unloading
(i) 18 cum capacity hour 5.196 2,883.30 14,981.85 P&M-014
(ii) 14 cum capacity hour 5.984 2,556.75 15,299.82 P&M-015
(iii) 10 cum capacity hour 8.366 2,274.30 19,026.82 P&M-016
@ 8% on @ 10% on @ 12% on 3,004.14 3,906.99 5,857.85
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 4,055.60 4,297.69 5,467.33
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 6000 sqm = a+b+c+d 44,611.55 47,274.62 60,140.61
Rate per sqm = (a+b+c+d)/6000 7.44 7.88 10.02
Say 7.00 8.00 10.00
3.15 305.4.3 (ii) By Mechanical Means using Motor Grader
Unit = sqm
Taking output = 12500 sqm
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Motor Grader
(i) Motor grader 4.30 metre blade hour 3.064 5,991.00 18,354.78 P&M-004
(ii) Motor grader 3.70 metre blade hour 3.676 5,497.00 20,209.56 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.720 4,796.00 17,842.26 P&M-006
Tipper
For transportation to dumping yard considering lead @
1km
(i) 18 cum capacity t.km 1437.500 6.18 8,881.59 P&M-117
(ii) 14 cum capacity t.km 1437.500 7.01 10,080.90 P&M-120
(iii) 10 cum capacity t.km 1437.500 8.66 12,454.50 P&M-123
For Loading & unloading charges
(i) Using by 18 cum capacity Tipper & 3.1 Cum capacity cum 625.000 92.72 57,951.47 P&M-129
Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum capacity cum 625.000 92.81 58,007.81 P&M-130
Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 625.000 118.14 73,837.50 P&M-131
Loader
@ 8% on @ 10% on @ 12% on 6,857.92 8,883.45 12,560.46
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 9,258.20 9,771.79 11,723.09
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 12500 sqm = a+b+c+d 101,840.16 107,489.71 128,954.01
Rate per sqm = (a+b+c+d)/12500 8.15 8.60 10.32
Say 8.00 9.00 10.00
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

3.16 305 Construction of Embankment with Material obtained from


Borrowpits

Construction of embankment with approved material


obtained from borrow pits with all lifts and leads,
transporting to site, spreading, grading to required slope
and compacting to meet requirement of table 300-2.

Unit = cum
Taking output = 450 cum
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 5.048 3,420.00 17,264.16 P&M-007
(ii) 1.1 cum bucket capacity hour 5.813 3,074.00 17,869.16 P&M-008
(iii) 0.9 cum bucket capacity hour 8.127 2,782.00 22,609.31 P&M-009
Tipper
For Transportation
(i) 18 cum capacity t.km 450x1.6 x L2 6.18 4,448.52 P&M-117
(ii) 14 cum capacity t.km 450x1.6 x L2 7.01 5,049.22 P&M-120
(iii) 10 cum capacity t.km 450x1.6 x L2 8.66 6,238.08 P&M-123
For Loading & unloading time
(i) 18 cum capacity hour 5.048 2,883.30 14,554.90 P&M-014
(ii) 14 cum capacity hour 5.813 2,556.75 14,862.39 P&M-015
(iii) 10 cum capacity hour 8.127 2,274.30 18,483.24 P&M-016
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 2.177 5,991.00 13,042.41 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.626 5,497.00 14,435.12 P&M-005
(iii) Motor grader 3.35 metre blade hour 2.929 4,796.00 14,047.48 P&M-006
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 8.364 1,501.00 12,554.36 P&M-023
(ii) 12 KL capacity hour 11.142 1,327.00 14,785.43 P&M-024
(iii) 6 KL capacity hour 22.314 1,005.00 22,425.57 P&M-025
Vibratory roller hour 2.184 2.184 2.184 2,562.00 5,595.41 5,595.41 5,595.41 P&M-022
c) Material
Cost of water (considering 5% additional moisture KL 36.000 36.000 36.000 16.00 576.00 576.00 576.00 M-191
required)
Compensation for earth taken from private land cum 450.000 450.000 450.000 45.00 20,250.00 20,250.00 20,250.00 M-093
@ 8% on @ 10% on @ 12% on 7,148.65 9,449.51 13,355.70
d) Overhead charges (a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on 9,650.68 10,394.46 12,465.32
e) Contractor's profit (a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 450 cum = a+b+c+d+e 106,157.49 114,339.11 137,118.51
Rate per cum = (a+b+c+d+e)/450 235.91 254.09 304.71
Say 236.00 254.00 305.00
Note Compensation for earth will vary from place to place and
will have to be assessed realistically as per particular
ground situation. In case earth is available from Govt.
land, compensation for earth will not be required. The
position is required to be clearly stated in the cost
estimate.
3.17 305 Construction of Embankment with Material Deposited from
Roadway Cutting

Construction of embankment with approved materials


deposited at site from roadway cutting and excavation
from drain and foundation of other structures graded and
compacted to meet requirement of table 300-2.

Unit = cum
Taking output = 450 cum
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 2.177 5,991.00 13,042.41 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.626 5,497.00 14,435.12 P&M-005
(iii) Motor grader 3.35 metre blade hour 2.929 4,796.00 14,047.48 P&M-006
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 5.864 1,501.00 8,801.86 P&M-023
(ii) 12 KL capacity hour 7.812 1,327.00 10,366.52 P&M-024
(iii) 6 KL capacity hour 15.644 1,005.00 15,722.22 P&M-025
Vibratory roller hour 2.184 2.184 2.184 2,562.00 5,596.60 5,596.60 5,596.60 P&M-022
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

c) Material
Cost of water (considering 5% additional moisture KL 36.000 36.000 36.000 16.00 576.00 576.00 576.00 M-191
required)
@ 8% on @ 10% on @ 12% on 2,284.25 3,151.04 4,377.42
d) Overhead charges (a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on 3,083.73 3,466.15 4,085.59
e) Contractor's profit (a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 450 cum = a+b+c+d+e 33,921.05 38,127.64 44,941.52
Rate per cum = (a+b+c+d+e)/450 75.38 84.73 99.87
Say 75.00 85.00 100.00
3.18 305 Construction of Subgrade and Earthen Shoulders
Construction of sub-grade and earthen shoulders with
approved material obtained from borrow pits with all lifts &
leads, transporting to site, spreading, grading to required
slope and compacted to meet requirement of table No.
300-2
Unit = cum
Taking output = 450 cum
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 5.048 3,420.00 17,264.16 P&M-007
(ii) 1.1 cum bucket capacity hour 5.813 3,074.00 17,869.16 P&M-008
(iii) 0.9 cum bucket capacity hour 8.127 2,782.00 22,609.31 P&M-009
Tipper
For Transportation
(i) 18 cum capacity t.km 450x1.75 x L2 6.18 4,865.57 P&M-117
(ii) 14 cum capacity t.km 450x1.75 x L2 7.01 5,522.58 P&M-120
(iii) 10 cum capacity t.km 450x1.75 x L2 8.66 6,822.90 P&M-123
For Loading & unloading time
(i) 18 cum capacity hour 5.048 2,883.30 14,554.90 P&M-014
(ii) 14 cum capacity hour 5.813 2,556.75 14,862.39 P&M-015
(iii) 10 cum capacity hour 8.127 2,274.30 18,483.24 P&M-016
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 2.177 5,991.00 13,042.41 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.626 5,497.00 14,435.12 P&M-005
(iii) Motor grader 3.35 metre blade hour 2.929 4,796.00 14,047.48 P&M-006
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 9.135 1,501.00 13,711.64 P&M-023
(ii) 12 KL capacity hour 12.210 1,327.00 16,202.67 P&M-024
(iii) 6 KL capacity hour 24.390 1,005.00 24,511.95 P&M-025
Vibratory roller 12 tonne hour 2.184 2.184 2.184 2,562.00 5,595.41 5,595.41 5,595.41 P&M-022
c) Material
Cost of water (considering 5% additional moisture KL 39.375 39.375 39.375 16.00 630.00 630.00 630.00 M-191
required)
Compensation for earth taken from private land cum 450.000 450.000 450.000 45.00 20,250.00 20,250.00 20,250.00 M-093
@ 8% on @ 10% on @ 12% on 7,278.92 9,643.97 13,682.72
d) Overhead charges (a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on 9,826.54 10,608.37 12,770.54
e) Contractor's profit (a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 450 cum = a+b+c+d+e 108,091.93 116,692.07 140,475.96
Rate per cum = (a+b+c+d+e)/450 240.20 259.32 312.17
Say 240.00 259.00 312.00
3.19 305 Construction of Subgrade and Earthen Shoulders with
Material Deposited from Roadway Cutting

Construction of embankment with approved materials


deposited at site from roadway cutting and excavation
from drain and foundation of other structures graded and
compacted to meet requirement of table 300-2.

Unit = cum
Taking output = 450 cum
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 2.177 5,991.00 13,042.41 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.626 5,497.00 14,435.12 P&M-005
(iii) Motor grader 3.35 metre blade hour 2.929 4,796.00 14,047.48 P&M-006
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 9.135 1,501.00 13,711.64 P&M-023
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

(ii) 12 KL capacity hour 12.210 1,327.00 16,202.67 P&M-024


(iii) 6 KL capacity hour 24.390 1,005.00 24,511.95 P&M-025
Vibratory roller hour 2.184 2.184 2.184 2,562.00 5,595.41 5,595.41 5,595.41 P&M-022
c) Material
Cost of water (considering 5% additional moisture KL 39.375 39.375 39.375 16.00 630.00 630.00 630.00 M-191
required)
@ 8% on @ 10% on @ 12% on 2,681.25 3,739.94 5,438.53
d) Overhead charges (a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on 3,619.69 4,113.93 5,075.96
e) Contractor's profit (a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 450 cum = a+b+c+d+e 39,816.59 45,253.27 55,835.52
Rate per cum = (a+b+c+d+e)/450 88.48 100.56 124.08
Say 88.00 101.00 124.00
3.20 305.3.4 Compacting Original Ground
Case-I
Compacting original ground supporting sub-grade

Loosening of the ground upto a level of 500 mm below the


sub-grade level, watered, graded and compacted in layers
to meet requirement of table 300-2 for sub-grade
construction.
Unit = cum
Taking output = 225 cum
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Motor grader for ripping (in two layers) & grading
(i) Motor grader 4.30 metre blade hour 2.192 5,991.00 13,132.27 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.637 5,497.00 14,495.59 P&M-005
(iii) Motor grader 3.35 metre blade hour 2.804 4,796.00 13,447.98 P&M-006
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 4.346 1,501.00 6,523.35 P&M-023
(ii) 12 KL capacity 5.775 1,327.00 7,663.43 P&M-024
(iii) 6 KL capacity 11.580 1,005.00 11,637.90 P&M-025
Vibratory roller hour 1.092 1.092 1.092 2,562.00 2,798.30 2,798.30 2,798.30 P&M-022
c) Material
Cost of water (considering 5% additional moisture KL 19.688 19.688 19.688 16.00 315.00 315.00 315.00 M-191
required)
@ 8% on @ 10% on @ 12% on 1,864.41 2,580.85 3,448.25
d) Overhead charges (a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on 2,516.95 2,838.94 3,218.36
e) Contractor's profit (a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 225 cum = a+b+c+d+e 27,686.48 31,228.30 35,401.99
Rate per cum = (a+b+c+d+e)/225 123.05 138.79 157.34
Say 123.00 139.00 157.00
Case-
II :Compacting original ground supporting embankment

Loosening, leveling and Compacting original ground


supporting embankment to facilitate placement of first
layer of embankment, scarified to a depth of 150 mm,
mixed with water at OMC and then compacted by rolling
so as to achieve minimum dry density as given in Table
300-2 for embankment construction.

Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Motor grader for ripping & grading
(i) Motor grader 4.30 metre blade hour 3.487 5,991.00 20,888.92 P&M-004
(ii) Motor grader 3.70 metre blade hour 4.197 5,497.00 23,068.78 P&M-005
(iii) Motor grader 3.35 metre blade hour 4.497 4,796.00 21,569.46 P&M-006
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 5.650 1,501.00 8,480.65 P&M-023
(ii) 12 KL capacity hour 7.513 1,327.00 9,969.75 P&M-024
(iii) 6 KL capacity hour 15.027 1,005.00 15,102.14 P&M-025
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
c) Material
Cost of water (considering 5% additional moisture KL 24.000 24.000 24.000 16.00 384.00 384.00 384.00 M-191
required)
@ 8% on @ 10% on @ 12% on 2,721.67 3,768.98 4,958.74
d) Overhead charges (a+b+c) (a+b+c) (a+b+c)
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

@ 10% on @ 10% on @ 10% on 3,674.25 4,145.88 4,628.16


e) Contractor's profit (a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 300 cum = a+b+c+d+e 40,416.76 45,604.66 50,909.77
Rate per cum = (a+b+c+d+e)/300 134.72 152.02 169.70
Say 135.00 152.00 170.00
3.21 305 Stripping and Storing Top Soil

Stripping, storing of top soil by road side at 15 m internal


and re-application on embankment slopes, cut slopes and
other areas in localities where the available embankment
material is not conducive to plant growth.

Unit = cum
Taking output = 250 cum
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Motor grader
(i) Motor grader 4.30 metre blade hour 1.680 5,991.00 10,065.52 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.027 5,497.00 11,140.16 P&M-005
(iii) Motor grader 3.35 metre blade hour 2.260 4,796.00 10,837.65 P&M-006
Hydraulic Excavator for reapplication
(i) 1.2 cum bucket capacity hour 2.804 3,420.00 9,590.48 P&M-007
(ii) 1.1 cum bucket capacity hour 3.230 3,074.00 9,927.51 P&M-008
(iii) 0.9 cum bucket capacity hour 4.515 2,782.00 12,560.71 P&M-009
Tipper
For transportation considering lead @ 1 km (20% of the
material needs to be transported)
(i) 18 cum capacity t.km 75.000 6.18 463.39 P&M-117
(ii) 14 cum capacity t.km 75.000 7.01 525.96 P&M-120
(iii) 10 cum capacity t.km 75.000 8.66 649.80 P&M-123

For loading (20% of the material needs to be transported)

(i) Using by 18 cum capacity Tipper & 3.1 Cum capacity cum 50.000 92.72 4,636.12 P&M-129
Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum capacity cum 50.000 92.81 4,640.63 P&M-130
Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 50.000 118.14 5,907.00 P&M-131
Loader
@ 8% on @ 10% on @ 12% on 2,023.34 2,677.05 3,658.96
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 2,731.50 2,944.75 3,415.03
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 250 sqm = a+b+c+d 30,046.55 32,392.25 37,565.35
Rate per sqm = (a+b+c+d)/250 120.19 129.57 150.26
Say 120.00 130.00 150.00
3.22 305 Stripping, Storing and Re-laying Top Soil from Borrow
Areas in Agriculture Fields.

Stripping of top soil from borrow areas located in


agriculture fields, storing at a suitable place, spreading
and re-laying after taking the borrow earth to maintain
fertility of the agricultural field, finishing it to the required
levels and satisfaction of the farmer.

Unit = cum
Taking output = 250 cum
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Motor grader
(i) Motor grader 4.30 metre blade hour 1.680 5,991.00 10,065.52 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.027 5,497.00 11,140.16 P&M-005
(iii) Motor grader 3.35 metre blade hour 2.260 4,796.00 10,837.65 P&M-006
Hydraulic Excavator for reapplication
(i) 1.2 cum bucket capacity hour 2.804 3,420.00 9,589.68 P&M-007
(ii) 1.1 cum bucket capacity hour 3.230 3,074.00 9,929.02 P&M-008
(iii) 0.9 cum bucket capacity hour 4.515 2,782.00 12,560.73 P&M-009
Tipper
For transportation
(i) 18 cum capacity t.km 250x1.6 x L2 6.18 2,471.40 P&M-117
(ii) 14 cum capacity t.km 250x1.6 x L2 7.01 2,805.12 P&M-120
(iii) 10 cum capacity t.km 250x1.6 x L2 8.66 3,465.60 P&M-123
For loading & unloading
(i) Using by 18 cum capacity Tipper & 3.1 Cum capacity cum 250.000 92.72 23,180.59 P&M-129
Loader
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

(ii) Using by 14 cum capacity Tipper & 2.1 Cum capacity cum 250.000 92.81 23,203.13 P&M-130
Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 250.000 118.14 29,535.00 P&M-131
Loader
@ 8% on @ 10% on @ 12% on 3,667.47 4,761.36 6,832.22
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 4,951.09 5,237.50 6,376.74
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 250 sqm = a+b+c+d 54,461.95 57,612.48 70,144.14
Rate per sqm = (a+b+c+d)/250 217.85 230.45 280.58
Say 218.00 230.00 281.00
3.23 307 Turfing with Sods
Furnishing and laying of the live sods of perennial turf
forming grass on embankment slope, verges or other
locations shown on the drawing or as directed by the
engineer including preparation of ground, fetching of sods
and watering.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Mazdoor for preparation of ground and fetching of sods

b) Machinery
Water tanker including watering for 3 months
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 15.096 1,501.00 22,659.10 P&M-023
(ii) 12 KL capacity hour 20.138 1,327.00 26,723.13 P&M-024
(iii) 6 KL capacity hour 40.246 1,005.00 40,447.23 P&M-025
Tractor-trolley hour 1.000 1.000 1.000 1,876.50 1,876.50 1,876.50 1,876.50 P&M-026
c) Material
Farm yard manure @ 0.18 cum per 100 sqm at site of cum 0.180 0.180 0.180 300.00 54.00 54.00 54.00 M-168
work
Cost of water KL 12.000 12.000 12.000 16.00 192.00 192.00 192.00 M-191
@ 8% on @ 10% on @ 12% on 2,111.22 3,045.42 5,301.40
d) Overhead charges (a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on 2,850.14 3,349.96 4,947.97
e) Contractor's profit (a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 31,351.55 36,849.61 54,427.70
Rate per 100 sqm = (a+b+c+d+e)/100 313.52 368.50 544.28
Say 314.00 368.00 544.00
3.24 308 Seeding and Mulching

Preparation of seed bed on previously laid top soil,


furnishing and placing of seeds, fertilizer, mulching
material, applying bituminous emulsion at the rate of 0.23
litres per sqm and laying and fixing jute netting, including
watering for 3 months all as per clause 308.

Unit = sqm
Taking output = 240 sqm
a) Labour
Mate day 0.400 0.400 0.400 617.00 246.80 246.80 246.80 L-12
Mazdoor day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-13
b) Machinery
Water tanker including watering for 3 months
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 106.613 1,501.00 160,026.11 P&M-023
(ii) 12 KL capacity hour 142.160 1,327.00 188,646.32 P&M-024
(iii) 6 KL capacity hour 284.291 1,005.00 285,712.46 P&M-025
Tractor-trolley hour 2.400 2.400 2.400 1,876.50 4,503.60 4,503.60 4,503.60 P&M-026
c) Material
Seeds kg 3.600 3.600 3.600 84.00 302.40 302.40 302.40 M-163
cum 0.430 0.430 0.430 300.00 129.00 129.00 129.00 M-168
Sludge/Farm yard manure @ 0.18 cum per 100 sqm

Bitumen Emulsion litre 55.200 55.200 55.200 47.66 2,630.96 2,630.96 2,630.96 M-077 /1000
Jute netting, open weave, 2.5 cm square opening sqm 264.000 264.000 264.000 56.00 14,784.00 14,784.00 14,784.00 M-120
Cost of water for 3 months KL 84.000 84.000 84.000 16.00 1,344.00 1,344.00 1,344.00 M-191
@ 8% on @ 10% on @ 12% on 15,126.57 21,770.23 37,772.21
d) Overhead charges (a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on 20,420.86 23,947.25 35,254.06
e) Contractor's profit (a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 240 sqm = a+b+c+d+e 224,629.51 263,419.76 387,794.69
Rate per sqm = (a+b+c+d+e)/240 935.96 1,097.58 1,615.81
Say 936.00 1,098.00 1,616.00
3.25 309 Surface Drains in Soil
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

Construction of unlined surface drains of average cross


sectional area 0.40 sqm in soil to specified lines, grades,
levels and dimensions to the requirement of clause 301
and 309. Excavated material to be used in embankment
within a lead of 1000 metres

Unit = metre
Taking output = 10 metres 4 Cum
A Mechanical means
a) Labour
Mate day 0.010 0.010 0.010 617.00 6.17 6.17 6.17 L-12
Mazdoor for dressing of bed and side of drain day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
b) Machinery
Hydraulic Excavator 0.9 cum bucket capacity hour 0.090 0.090 0.090 2,782.00 250.38 250.38 250.38 P&M-009
Tractor-trolley
Tractor-trolley for transportation & for loading & Unloding hour 0.246 0.246 0.246 1,876.50 461.62 461.62 461.62 P&M-026
Time

@ 8% on @ 10% on @ 12% on 67.68 84.60 101.53


c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 91.37 93.07 94.76
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 10 metres = a+b+c+d 1,005.11 1,023.72 1,042.33
Rate per metre = (a+b+c+d)/10 100.51 102.37 104.23
Say 101.00 102.00 104.00
3.25 B Manual Means
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Tractor-trolley
Tractor-trolley for transportation & for loading & Unloding hour 0.822 0.822 0.822 1,876.50 1,542.48 1,542.48 1,542.48 P&M-026
Time

@ 8% on @ 10% on @ 12% on 209.19 261.49 313.79


c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 282.41 287.64 292.87
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 10 metres = a+b+c+d 3,106.48 3,164.01 3,221.54
Rate per metre = (a+b+c+d)/10 310.65 316.40 322.15
Say 311.00 316.00 322.00
Note
Where lining of drain is provided, quantity shall be worked
out based on approved design and drawing and priced on
rate of cement concrete of approved grade or stone/brick
masonry as the case may be.

3.26 309 Surface Drains in Ordinary Rock


Construction of unlined surface drain of average cross
sectional area 0.4 sqm in ordinary rock to specified lines,
grades, levels and dimensions as per approved design
and to the requirement of clause 301 to 309. Excavated
material to be used in embankment at site within a lead of
1000 metres.
Unit = metre
Taking output = 10 metres 4 Cum
A Mechanical Means
a) Labour
Mate day 0.020 0.020 0.020 617.00 12.34 12.34 12.34 L-12
Mazdoor for dressing of bed and side of drain day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
b) Machinery
Hydraulic Excavator 0.9 cum bucket capacity hour 0.112 0.112 0.112 2,782.00 311.58 311.58 311.58 P&M-009
Tractor-trolley
Tractor-trolley for transportation & for loading & Unloding hour 0.267 0.267 0.267 1,876.50 501.03 501.03 501.03 P&M-026
Time

@ 8% on @ 10% on @ 12% on 86.46 108.07 129.69


c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 116.72 118.88 121.04
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 10 metres = a+b+c+d 1,283.88 1,307.66 1,331.43
Rate per metre = (a+b+c+d)/10 128.39 130.77 133.14
Say 128.00 131.00 133.00
3.26 B Manual Means
a) Labour
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Machinery
Tractor-trolley
Tractor-trolley for transportation & for loading & Unloding hour 1.044 1.044 1.044 1,876.50 1,959.90 1,959.90 1,959.07 P&M-026
Time

@ 8% on @ 10% on @ 12% on 285.48 356.85 428.12


c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 385.40 392.54 399.58
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 10 metres = a+b+c 4,239.38 4,317.89 4,395.36
Rate per metre = (a+b+c)/10 423.94 431.79 439.54
Say 424.00 432.00 440.00
3.27 309 Surface Drains in Hard Rock
Rate per metre may be worked out based on quantity of
hard rock as per design.
For rate of hard rock cutting, refer relevant item in this
chapter

3.28 309 Sub-Surface Drains with Perforated Pipe

Construction of subsurface drain with perforated pipe of


100 mm internal diameter of metal/ asbestos cement/
cement concrete/PVC, closely jointed, perforations
ranging from 3 mm to 6 mm depending upon size of
material surrounding the pipe, with 150 mm bedding below
the pipe and 300 mm cushion above the pipe, cross
section of excavation 450 x 550 mm. Excavated material
to be utilised in roadway at site.

Unit = metre
Taking output = 10 metres
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor for excavation and back filling day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
c) Material
metre 10.000 10.000 10.000 178.00 1,780.00 1,780.00 1,780.00 M-134
Perforated pipe of cement concrete, internal dia 100 mm

Crushed stone as per table 300-3 cum 2.400 2.400 2.400 1,215.07 2,916.17 2,916.17 2,916.17 M-011
d) Overhead charges @ 8% on (a+b+c) 459.51 574.39 689.27
e) Contractor's profit @ 10% on (a+b+c+d) 620.34 631.83 643.32
Cost for 10 metres = a+b+c+d+e 6,823.75 6,950.11 7,076.48
Rate per metre = (a+b+c+d+e)/10 682.37 695.01 707.65
Say 682.00 695.00 708.00
Note Type of pipe may be modified depending upon provision in
design.

3.29 309 Aggregate Sub-Surface Drains


Construction of aggregate sub surface drain 300 mm x
450 mm with aggregates conforming to table 300-4,
excavated material to be utilised in roadway.
Unit = metre
Taking output = 10 metres
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
day 1.500 1.500 1.500 511.52 767.28 767.28 767.28 L-13
Mazdoor for excavation and back filling with aggregates

b) Material
Crushed stone as per table 300-3 cum 1.350 1.350 1.350 1,215.07 1,640.35 1,640.35 1,640.35 M-011
@ 8% on @ 10% on @ 12% on 195.57 244.46 293.36
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 264.02 268.91 273.80
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 10 metres = a+b+c+d 2,904.24 2,958.02 3,011.81
Rate per metre = (a+b+c+d)/10 290.42 295.80 301.18
Say 290.00 296.00 301.00
3.30 309 Underground Drain at Edge of Pavement

Construction of an underground drain 1 m x 1 m (inside


dimensions) lined with RCC-20 cm thick and covered with
RCC slab10 cm in thickness on urban roads.

Unit = Running metre


Taking output = one metre
a) Earthwork in soil cum 1.500 1.500 1.500 101.00 151.50 151.50 151.50 Item No.- 3.13
cum 0.495 0.495 0.495 8,195.00 4,056.53 4,056.53 4,056.53 Item No.-
b) RCC work M-20 9.14 C
Case-II
c) Reinforcement tonne 0.020 0.020 0.020 62,082.00 1,229.22 1,229.22 1,229.22 Item No.- 9.16
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

Rate per metre = (a+b+c) Say 5,437.00 5,437.00 5,437.00


Rates for these items may be taken from chapters on
earth work and culvert respectively.

3.31 310
Preparation and Surface Treatment of Formation.

Preparation and surface treatment of formation by


removing mud and slurry, watering to the extent needed to
maintain the desired moisture content, trimming to the
required line, grade, profile and rolling with smooth
wheeled roller, complete as per clause 310.

Unit = sqm
Taking output = 3500 sqm 525 Cum
a) Labour
Mate day 0.280 0.280 0.280 617.00 172.76 172.76 172.76 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
b) Machinery
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 4.590 1,501.00 6,889.59 P&M-023
(ii) 12 KL capacity hour 6.130 1,327.00 8,134.51 P&M-024
(iii) 6 KL capacity hour 12.230 1,005.00 12,291.15 P&M-025
Vibratory roller hour 2.549 2.549 2.549 2,562.00 6,529.37 6,529.37 6,529.37 P&M-022
c) Material
Cost of water KL 18.000 18.000 18.000 16.00 288.00 288.00 288.00 M-191
@ 8% on @ 10% on @ 12% on 1,401.17 1,875.95 2,749.94
d) Overhead charges (a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on 1,891.57 2,063.54 2,566.61
e) Contractor's profit (a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 3500 sqm = a+b+c+d+e 20,807.31 22,698.98 28,232.67
Rate per sqm = (a+b+c+d+e)/3500 5.94 6.49 8.07
Say 6.00 6.00 8.00
3.32 313 Construction of Rock fill Embankment with all lifts and lead
upto 5 Km

Construction of rock fill embankment from roadway


excavation with broken hard rock fragments of size not
exceeding 300 mm laid in layers not exceeding 500 mm
thick including filling of surface voids with stone spalls,
blinding top layer with granular material, rolled with
vibratory road roller, all complete as per clause 313.

Unit = cum
Taking output = 500 cum
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Dozer
Dozer (240HP) hour 3.731 6,586.65 24,574.79 P&M-001
Dozer (175 HP) hour 4.808 5,087.25 24,459.50 P&M-002
Dozer (90 HP) hour 8.621 3,502.80 30,197.64 P&M-003

Tipper for transportation of rock considering lead @ 5 km

(i) 18 cum capacity t.km 4000.000 6.18 24,714.00 P&M-117


(ii) 14 cum capacity t.km 4000.000 7.01 28,051.20 P&M-120
(iii) 10 cum capacity t.km 4000.000 8.66 34,656.00 P&M-123
Water tanker (speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 3.757 1,501.00 5,639.26 P&M-023
(ii) 12 KL capacity hour 5.009 1,327.00 6,646.94 P&M-024
(iii) 6 KL capacity hour 10.018 1,005.00 10,068.09 P&M-025
Vibratory roller hour 2.427 2.427 2.427 2,562.00 6,218.45 6,218.45 6,218.45 P&M-022
c) Material
Cost of water (considering 5% additional moisture KL 16.000 16.000 16.000 16.00 256.00 256.00 256.00 M-191
required)
@ 8% on @ 10% on @ 12% on 4,955.10 6,616.83 9,831.89
d) Overhead charges (a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on 6,689.38 7,278.51 9,176.43
e) Contractor's profit (a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 500 cum = a+b+c+d+e 73,583.17 80,063.63 100,940.69
Rate per cum = (a+b+c+d+e)/500 147.17 160.13 201.88
Say 147.00 160.00 202.00
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

Note It is assumed that rock is available locally at site from


roadway cutting. In case, portion of the rock requires
breaking to acceptable size of 300 mm, breaking charges
will have to be added.

3.33 Work in Urban Roads

The cost of earth work in urban roads inhabited area will


be comparatively higher due to following reasons:

a) There is mixed traffic on urban roads like slow


moving hand and animal driven carts, rickshaws, cycles,
two/ three wheeler apart from the usual vehicular traffic
resulting into traffic jams. This causes loss of working time
which may be in the range of 10 -15 per cent

b) There is considerable disruption of traffic adversely


affecting the efficiency of the working parties including
machines due to congestion caused by pedestrian traffic,
local road side venders, parking of vehicles by the road
side, encroachments by the shopkeepers and local shops
who make use of the berms of the road in front of these
shops and unauthorised conversion of road berms into
mini local market The output of manpower and machines
is substantially reduced due to factors mentioned above.

c) Cost of living in urban areas is comparatively more


resulting into higher wages.

d) At times, work is executed during night time due to


heavy traffic during day time. This involves extra
expenditure by way of making arrangement for lighting
and special transport for working parties due to odd hour

In the light of above, the authorities engaged in preparing


the cost estimates may exercise their judgment and cater
for the additional cost to the extent of 2 to 3 per cent,
keeping in view the severity of factors mentioned above.
Supporting details for the extra cost based on the actual
conditions in specific cases will have to give in justification.

3.34 Suggestiv Embankment Construction with Flyash/Pond ash available


e from coal or lignite burning Thermal Plants as waste
material.

Construction of embankment with Flyash conforming to


table 1 of IRC: SP: 58 obtained from coal or lignite
burning thermal power stations as waste material, spread
and compacted in layers at OMC, all as specified in IRC:
SP: 58 and as per approved plans.

Cosidering Soil blanketing of 2 m either side for 4 lane


section
Unit = cum Fly Ash - 382.5
Taking output = 450 cum Soil - 67.5
a) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Machinery
Hydraulic Excavator
For borrow area soil
(i) 1.2 cum bucket capacity hour 0.757 3,420.00 2,588.94 P&M-007
(ii) 1.1 cum bucket capacity hour 0.872 3,074.00 2,680.53 P&M-008
(iii) 0.9 cum bucket capacity hour 1.219 2,782.00 3,391.26 P&M-009
Tipper
Transportation of borrow area soil
(i) 18 cum capacity t.km 67.5x1.6 x L2 6.18 667.28 P&M-117
(ii) 14 cum capacity t.km 67.5x1.6 x L2 7.01 757.38 P&M-120
(iii) 10 cum capacity t.km 67.5x1.6 x L2 8.66 935.71 P&M-123
Transportation of flyash
To be supplied by the Tharmal Power Plant including
loading and unloading
Loading & unloading
(i) 18 cum capacity hour 0.757 2,883.30 2,182.66 P&M-014
(ii) 14 cum capacity hour 0.872 2,556.75 2,229.49 P&M-015
(iii) 10 cum capacity hour 1.219 2,274.30 2,772.37 P&M-016
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 2.177 5,991.00 13,042.41 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.626 5,497.00 14,435.12 P&M-005
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

(iii) Motor grader 3.35 metre blade hour 2.929 4,796.00 14,047.48 P&M-006
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 11.911 1,501.00 17,878.41 P&M-023
(ii) 12 KL capacity hour 15.892 1,327.00 21,088.68 P&M-024
(iii) 6 KL capacity hour 31.783 1,005.00 31,941.92 P&M-025
Vibratory roller 12 tonne hour 2.184 2.184 2.184 2,562.00 5,595.41 5,595.41 5,595.41 P&M-022
c) Material
Cost of water (considering 5% additional moisture KL 51.300 51.300 51.300 16.00 820.80 820.80 820.80 M-191
required)
Compensation for earth taken from private land cum 67.500 67.500 67.500 45.00 3,037.50 3,037.50 3,037.50 M-093
@ 8% on @ 10% on @ 12% on 3,793.76 5,225.35 7,698.13
d) Overhead charges (a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on 5,121.58 5,747.89 7,184.92
e) Contractor's profit (a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 450 cum = a+b+c+d+e 56,337.34 63,226.75 79,034.09
Rate per cum = (a+b+c+d+e)/450 125.19 140.50 175.63
Say 125.00 141.00 176.00
Note
1.As flyash is available free of cost as waste material from
Thermal Plants, cost of material has not been added.

2.The earth cover on sides and intermediate layers of


earth sandwiching the flyash have been included in this
analysis.
CHAPTER-4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
4.01 401 Granular Sub-Base with Graded Material (Table:-
400-1)
A Plant Mix Method
Construction of granular sub-base by providing close
graded Material, mixing in a mechanical mix plant at
OMC, carriage of mixed Material to work site,
spreading in uniform layers with motor grader on
prepared surface and compacting with vibratory
power roller to achieve the desired density, complete
as per clause 401

Unit = cum
Taking output = 400 cum 840 tonne 2.10
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Wet mix plant
(i) 250 tonne per hour hour 4.480 921.90 4,130.11 P&M-032
(ii) 200 tonne per hour hour 5.600 612.15 3,428.04 P&M-033
(iii) 100 tonne per hour hour 11.200 585.90 6,562.08 P&M-034
Electric generator
(i) 125 KVA hour 4.480 2,390.85 10,711.01 P&M-047
(ii) 100 KVA hour 5.600 2,041.20 11,430.72 P&M-048
(iii) 62.5 KVA hour 11.200 1,312.50 14,700.00 P&M-049
Front end loader
(i) 3.1 Cum Capacity hour 9.502 4,279.80 40,666.66 P&M-011
(ii) 2.1 Cum Capacity hour 14.047 2,640.75 37,094.62 P&M-012
(iii) 1 Cum Capacity hour 29.371 1,112.00 32,660.55 P&M-013
Tipper
For transportation
(i) 18 cum capacity t.km 840 x L1 6.18 155,698.20 P&M-117
(ii) 14 cum capacity t.km 840 x L1 7.01 176,722.56 P&M-120
(iii) 10 cum capacity t.km 840 x L1 8.66 218,332.80 P&M-123
For loading & unloading Time
(i) 18 cum capacity hour 4.480 2,883.30 12,917.18 P&M-014
(ii) 14 cum capacity hour 5.600 2,556.75 14,317.80 P&M-015
(iii) 10 cum capacity hour 11.200 2,274.30 25,472.16 P&M-016
Motor grader
(i) Motor grader 4.30 metre blade hour 3.226 5,991.00 19,326.97 P&M-004
(ii) Motor grader 3.70 metre blade hour 3.891 5,497.00 21,388.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 4.339 4,796.00 20,809.84 P&M-006
Vibratory roller hour 2.589 2.589 2.589 2,562.00 6,633.02 6,633.02 6,633.02 P&M-022
c) Material
Close graded Granular sub-base Material as per
table 400-1
For Grading-I Material
53 mm to 26.5 mm @27.5 per cent cum 148.077 148.077 148.077 1,887.12 279,439.38 279,439.38 279,439.38 M-028
26.5 mm to 9.5 mm @ 22.5 per cent cum 121.154 121.154 121.154 1,887.12 228,632.22 228,632.22 228,632.22 M-014
9.5 mm to 4.75 mm @ 10% cum 53.846 53.846 53.846 1,887.12 101,614.32 101,614.32 101,614.32 M-015
4.75 mm below @ 40 per cent cum 215.385 215.385 215.385 1,887.12 406,457.28 406,457.28 406,457.28 M-018
Cost of water KL 67.200 67.200 67.200 16.00 1,075.20 1,075.20 1,075.20 M-191
OR
For Grading-II Material
26.5 mm to 9.5 mm @ 35 per cent cum 188.462 188.462 188.462 1,887.12 355,650.12 355,650.12 355,650.12 M-014
9.5 mm to 4.75 mm @ 12.5 % cum 67.308 67.308 67.308 1,887.12 127,017.90 127,017.90 127,017.90 M-015
4.75 mm below @ 52.5 per cent cum 282.692 282.692 282.692 1,887.12 533,475.19 533,475.19 533,475.19 M-018
Cost of water KL 67.200 67.200 67.200 16.00 1,075.20 1,075.20 1,075.20 M-191
OR
For Grading-III Material
26.5 mm to 9.5 mm @ 68 per cent cum 366.154 366.154 366.154 1,887.12 690,977.38 690,977.38 690,977.38 M-014
9.5 mm to 4.75 mm @ 12 % cum 64.615 64.615 64.615 1,887.12 121,937.19 121,937.19 121,937.19 M-015
4.75 mm below @ 20 per cent cum 107.692 107.692 107.692 1,887.12 203,228.64 203,228.64 203,228.64 M-018
Cost of water KL 67.200 67.200 67.200 16.00 1,075.20 1,075.20 1,075.20 M-191
OR
For Grading-IV Material
26.5 mm to 9.5 mm @ 64 per cent cum 344.615 344.615 344.615 1,887.12 650,331.65 650,331.65 650,331.65 M-014
9.5 mm to 4.75 mm @ 11 % cum 59.231 59.231 59.231 1,887.12 111,775.75 111,775.75 111,775.75 M-015
4.75 mm below @ 25 per cent cum 134.615 134.615 134.615 1,887.12 254,035.80 254,035.80 254,035.80 M-018
Cost of water KL 67.200 67.200 67.200 16.00 1,075.20 1,075.20 1,075.20 M-191
OR
For Grading-V Material
53 mm to 26.5 mm @27.5 per cent cum 148.077 148.077 148.077 1,887.12 279,439.38 279,439.38 279,439.38 M-028
26.5 mm to 9.5 mm @ 22.5 per cent cum 121.154 121.154 121.154 1,887.12 228,632.22 228,632.22 228,632.22 M-014
9.5 mm to 4.75 mm @ 12.50 % cum 67.308 67.308 67.308 1,887.12 127,017.90 127,017.90 127,017.90 M-015
4.75 mm below @ 37.5 per cent cum 201.923 201.923 201.923 1,887.12 381,053.70 381,053.70 381,053.70 M-018
Cost of water KL 67.200 67.200 67.200 16.00 1,075.20 1,075.20 1,075.20 M-191
OR
For Grading-VI Material
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
53 mm to 26.5 mm @12.5 per cent cum 67.308 67.308 67.308 1,887.12 127,017.90 127,017.90 127,017.90 M-028
26.5 mm to 9.5 mm @22.5 per cent cum 121.154 121.154 121.154 1,887.12 228,632.22 228,632.22 228,632.22 M-014
9.5 mm to 4.75 mm @ 22.5 % cum 121.154 121.154 121.154 1,887.12 228,632.22 228,632.22 228,632.22 M-015
4.75 mm below @ 42.5 per cent cum 228.846 228.846 228.846 1,887.12 431,860.86 431,860.86 431,860.86 M-018
Cost of water KL 67.200 67.200 67.200 16.00 1,075.20 1,075.20 1,075.20 M-191
4.01A (i) Rate per cum for grading-I Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 101,474.25 128,936.06 161,221.86
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 136,990.24 141,829.67 150,473.73
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 400 cum = a+b+c+d+e 1,506,892.66 1,560,126.33 1,655,211.06
Rate per cum = (a+b+c+d+e)/400 3,767.23 3,900.32 4,138.03
Say 3,767.00 3,900.00 4,138.00
4.01A (ii) Rate per cum for grading-II Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 101,474.25 128,936.06 161,221.86
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 136,990.24 141,829.67 150,473.73
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 400 cum = a+b+c+d+e 1,506,892.66 1,560,126.33 1,655,211.06
Rate per cum = (a+b+c+d+e)/400 3,767.23 3,900.32 4,138.03
Say 3,767.00 3,900.00 4,138.00
4.01A (iii) Rate per cum for grading-III Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 101,474.25 128,936.06 161,221.86
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 136,990.24 141,829.67 150,473.73
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 400 cum = a+b+c+d+e 1,506,892.66 1,560,126.33 1,655,211.06
Rate per cum = (a+b+c+d+e)/400 3,767.23 3,900.32 4,138.03
Say 3,767.00 3,900.00 4,138.00
4.01A (iv) Rate per cum for grading-IV Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 101,474.25 128,936.06 161,221.86
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 136,990.24 141,829.67 150,473.73
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 400 cum = a+b+c+d+e 1,506,892.66 1,560,126.33 1,655,211.06
Rate per cum = (a+b+c+d+e)/400 3,767.23 3,900.32 4,138.03
Say 3,767.00 3,900.00 4,138.00
4.01A (v) Rate per cum for grading-V Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 101,474.25 128,936.06 161,221.86
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 136,990.24 141,829.67 150,473.73
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 400 cum = a+b+c+d+e 1,506,892.66 1,560,126.33 1,655,211.06
Rate per cum = (a+b+c+d+e)/400 3,767.23 3,900.32 4,138.03
Say 3,767.00 3,900.00 4,138.00
4.01A (vi) Rate per cum for grading-VI Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 101,474.25 128,936.06 161,221.86
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 136,990.24 141,829.67 150,473.73
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 400 cum = a+b+c+d+e 1,506,892.66 1,560,126.33 1,655,211.06
Rate per cum = (a+b+c+d+e)/400 3,767.23 3,900.32 4,138.03
Say 3,767.00 3,900.00 4,138.00
Note Any one of the grading for material may be adopted
as per design
4.01 B By Mix in Place Method
Construction of granular sub-base by providing close
graded material, spreading in uniform layers with
motor grader on prepared surface, mixing by mix in
place method with front end loader at OMC, and
compacting with vibratory roller to achieve the
desired density, complete as per clause 401

Unit = cum
Taking output = 250 cum 525 tonne
a) Labour
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Machinery
Front end loader for mixing at stock pile location

(i) 3.1 Cum Capacity hour 4.464 4,279.80 19,105.03 P&M-011


(ii) 2.1 Cum Capacity hour 6.579 2,640.75 17,373.49 P&M-012
(iii) 1 Cum Capacity hour 13.889 1,112.00 15,444.57 P&M-013
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 3 km/hr )

(i) 16 KL capacity hour 9.538 1,501.00 14,316.54 P&M-023


(ii) 12 KL capacity hour 12.707 1,327.00 16,862.19 P&M-024
(iii) 6 KL capacity hour 25.414 1,005.00 25,541.07 P&M-025
Motor Grader
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
(i) Motor grader 4.30 metre blade hour 2.016 5,991.00 12,077.86 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.432 5,497.00 13,368.70 P&M-005
(iii) Motor grader 3.35 metre blade hour 2.712 4,796.00 13,006.75 P&M-006
Vibratory roller hour 1.618 1.618 1.618 2,562.00 4,145.32 4,145.32 4,145.32 P&M-022
c) Material
Close graded Granular sub-base Material as per
table 400-1
For Grading-I Material
53 mm to 26.5 mm @27.5 per cent cum 92.548 92.548 92.548 1,887.12 174,649.61 174,649.61 174,649.61 M-028
26.5 mm to 9.5 mm @ 22.5 per cent cum 75.721 75.721 75.721 1,887.12 142,895.14 142,895.14 142,895.14 M-014
9.5 mm to 4.75 mm @ 10% cum 33.654 33.654 33.654 1,887.12 63,508.95 63,508.95 63,508.95 M-015
4.75 mm below @ 40 per cent cum 134.615 134.615 134.615 1,887.12 254,035.80 254,035.80 254,035.80 M-018
Cost of water KL 42.000 42.000 42.000 16.00 672.00 672.00 672.00 M-191
OR
For Grading-II Material
26.5 mm to 9.5 mm @ 35 per cent cum 117.788 117.788 117.788 1,887.12 222,281.33 222,281.33 222,281.33 M-014
9.5 mm to 4.75 mm @ 12.5 % cum 42.067 42.067 42.067 1,887.12 79,386.19 79,386.19 79,386.19 M-015
4.75 mm below @ 52.5 per cent cum 176.683 176.683 176.683 1,887.12 333,421.99 333,421.99 333,421.99 M-018
Cost of water KL 42.000 42.000 42.000 16.00 672.00 672.00 672.00 M-191
OR
For Grading-III Material
26.5 mm to 9.5 mm @ 68 per cent cum 228.846 228.846 228.846 1,887.12 431,860.86 431,860.86 431,860.86 M-014
9.5 mm to 4.75 mm @ 12 % cum 40.385 40.385 40.385 1,887.12 76,210.74 76,210.74 76,210.74 M-015
4.75 mm below @ 20 per cent cum 67.308 67.308 67.308 1,887.12 127,017.90 127,017.90 127,017.90 M-018
Cost of water KL 42.000 42.000 42.000 16.00 672.00 672.00 672.00 M-191
OR
For Grading-IV Material
26.5 mm to 9.5 mm @ 64 per cent cum 215.385 215.385 215.385 1,887.12 406,457.28 406,457.28 406,457.28 M-014
9.5 mm to 4.75 mm @ 11 % cum 37.019 37.019 37.019 1,887.12 69,859.85 69,859.85 69,859.85 M-015
4.75 mm below @ 25 per cent cum 84.135 84.135 84.135 1,887.12 158,772.38 158,772.38 158,772.38 M-018
Cost of water KL 42.000 42.000 42.000 16.00 672.00 672.00 672.00 M-191
OR
For Grading-V Material
53 mm to 26.5 mm @27.5 per cent cum 92.548 92.548 92.548 1,887.12 174,649.61 174,649.61 174,649.61 M-028
26.5 mm to 9.5 mm @ 22.5 per cent cum 75.721 75.721 75.721 1,887.12 142,895.14 142,895.14 142,895.14 M-014
9.5 mm to 4.75 mm @ 12.50 % cum 42.067 42.067 42.067 1,887.12 79,386.19 79,386.19 79,386.19 M-015
4.75 mm below @ 37.5 per cent cum 126.202 126.202 126.202 1,887.12 238,158.56 238,158.56 238,158.56 M-018
Cost of water KL 42.000 42.000 42.000 16.00 672.00 672.00 672.00 M-191
OR
For Grading-VI Material
53 mm to 26.5 mm @12.5 per cent cum 42.067 42.067 42.067 1,887.12 79,386.19 79,386.19 79,386.19 M-028
26.5 mm to 9.5 mm @22.5 per cent cum 75.721 75.721 75.721 1,887.12 142,895.14 142,895.14 142,895.14 M-014
9.5 mm to 4.75 mm @ 22.5 % cum 75.721 75.721 75.721 1,887.12 142,895.14 142,895.14 142,895.14 M-015
4.75 mm below @ 42.5 per cent cum 143.029 143.029 143.029 1,887.12 269,913.04 269,913.04 269,913.04 M-018
Cost of water KL 42.000 42.000 42.000 16.00 672.00 672.00 672.00 M-191
4.01 B (i) Rate per cum for grading-I Material

d) Overhead charges @ 8% on @ 10% on @ 12% on 55,008.42 68,971.02 83,531.79


(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 74,261.37 75,868.12 77,963.00
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 250 cum = a+b+c+d+e 816,875.04 834,549.37 857,593.01
Rate per cum = (a+b+c+d+e)/250 3,267.50 3,338.20 3,430.37
Say 3,268.00 3,338.00 3,430.00
4.01 B (ii) Rate per cum for grading-II Material

d) Overhead charges @ 8% on @ 10% on @ 12% on 55,008.42 68,971.02 83,531.79


(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 74,261.37 75,868.12 77,963.00
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 250 cum = a+b+c+d+e 816,875.04 834,549.37 857,593.01
Rate per cum = (a+b+c+d+e)/250 3,267.50 3,338.20 3,430.37
Say 3,268.00 3,338.00 3,430.00
4.01 B (iii) Rate per cum for grading-III Material

d) Overhead charges @ 8% on @ 10% on @ 12% on 55,008.42 68,971.02 83,531.79


(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 74,261.37 75,868.12 77,963.00
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 250 cum = a+b+c+d+e 816,875.04 834,549.37 857,593.01
Rate per cum = (a+b+c+d+e)/250 3,267.50 3,338.20 3,430.37
Say, 3,267.50 3,338.20 3,430.37
4.01 B (iv) Rate per cum for grading-IV Material

d) Overhead charges @ 8% on @ 10% on @ 12% on 55,008.42 68,971.02 83,531.79


(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 74,261.37 75,868.12 77,963.00
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 250 cum = a+b+c+d+e 816,875.04 834,549.37 857,593.01
Rate per cum = (a+b+c+d+e)/250 3,267.50 3,338.20 3,430.37
Say 3,268.00 3,338.00 3,430.00
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
4.01 B (v) Rate per cum for grading-V Material

d) Overhead charges @ 8% on @ 10% on @ 12% on 55,008.42 68,971.02 83,531.79


(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 74,261.37 75,868.12 77,963.00
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 250 cum = a+b+c+d+e 816,875.04 834,549.37 857,593.01
Rate per cum = (a+b+c+d+e)/250 3,267.50 3,338.20 3,430.37
Say 3,268.00 3,338.00 3,430.00
4.01 B (vi) Rate per cum for grading-VI Material

d) Overhead charges @ 8% on @ 10% on @ 12% on 55,008.42 68,971.02 83,531.79


(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 74,261.37 75,868.12 77,963.00
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 250 cum = a+b+c+d+e 816,875.04 834,549.37 857,593.01
Rate per cum = (a+b+c+d+e)/250 3,267.50 3,338.20 3,430.37
Say 3,268.00 3,338.00 3,430.00
Note Any one of the grading for material may be adopted
as per design
4.01 C Using Crusher Run
Construction of granular sub-base using crusher run,
spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method
with rotavator at OMC, and compacting with
vibratory roller to achieve the desired density,
complete as per clause 401

Unit = cum
Taking output = 250 cum 525 tonne
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Front end loader for loading to Tipper
(i) 3.1 Cum Capacity hour 1.548 4,279.80 6,625.13 P&M-011
(ii) 2.1 Cum Capacity hour 2.283 2,640.75 6,028.83 P&M-012
(iii) 1 Cum Capacity hour 4.808 1,112.00 5,346.50 P&M-013
Tipper
For transportation
(i) 18 cum capacity t.km 525 x L1 6.18 97,311.38 P&M-117
(ii) 14 cum capacity t.km 525 x L1 7.01 110,451.60 P&M-120
(iii) 10 cum capacity t.km 525 x L1 8.66 136,458.00 P&M-123
For loading & unloading Time
(i) 18 cum capacity hour 1.548 2,883.30 4,463.35 P&M-014
(ii) 14 cum capacity hour 2.283 2,556.75 5,837.06 P&M-015
(iii) 10 cum capacity hour 4.808 2,274.30 10,934.83 P&M-016
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 3 km/hr )

(i) 16 KL capacity hour 9.538 1,501.00 14,316.54 P&M-023


(ii) 12 KL capacity hour 12.707 1,327.00 16,862.19 P&M-024
(iii) 6 KL capacity hour 25.414 1,005.00 25,541.07 P&M-025
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.016 5,991.00 12,078.63 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.432 5,497.00 13,368.19 P&M-005
(iii) Motor grader 3.35 metre blade hour 2.712 4,796.00 13,005.18 P&M-006
Vibratory roller hour 1.618 1.618 1.618 2,562.00 4,145.63 4,145.63 4,145.63 P&M-022
c) Material
Close graded Granular sub-base Material as per
table 400-1
For Grading-I Material
53 mm to 4.75 mm below cum 336.538 336.538 336.538 1,887.12 635,088.64 635,088.64 635,088.64 M-034
Cost of water KL 42.000 42.000 42.000 16.00 672.00 672.00 672.00 M-191
OR
For Grading-II Material
26.5 mm to 4.75 mm below cum 336.538 336.538 336.538 1,887.12 635,089.51 635,089.51 635,089.51 M-025
Cost of water KL 42.000 42.000 42.000 16.00 672.00 672.00 672.00 M-191
OR
For Grading-III Material
26.5 mm to 4.75 mm below cum 336.538 336.538 336.538 1,887.12 635,089.51 635,089.51 635,089.51 M-025
Cost of water KL 42.000 42.000 42.000 16.00 672.00 672.00 672.00 M-191
OR
For Grading-IV Material
26.5 mm to 4.75 mm below cum 336.538 336.538 336.538 1,887.12 635,089.51 635,089.51 635,089.51 M-025
Cost of water KL 42.000 42.000 42.000 16.00 672.00 672.00 672.00 M-191
OR
For Grading-V Material
53 mm to 4.75 mm below cum 336.538 336.538 336.538 1,887.12 635,089.51 635,089.51 635,089.51 M-034
Cost of water KL 42.000 42.000 42.000 16.00 672.00 672.00 672.00 M-191
OR
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
For Grading-VI Material
53 mm to 4.75 mm below cum 336.538 336.538 336.538 1,887.12 635,089.51 635,089.51 635,089.51 M-034
Cost of water KL 42.000 42.000 42.000 16.00 672.00 672.00 M-191
4.01C (i) Rate per cum for grading-I Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 62,066.23 79,358.07 99,878.21
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 83,789.41 87,293.88 93,219.67
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 250 cum = a+b+c+d+e 921,683.54 960,232.71 1,025,416.34
Rate per cum = (a+b+c+d+e)/250 3,686.73 3,840.93 4,101.67
Say 3,687.00 3,841.00 4,102.00
4.01C (ii) Rate per cum for grading-II Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 62,066.30 79,358.16 99,878.32
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 83,789.51 87,293.98 93,219.76
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 250 cum = a+b+c+d+e 921,684.58 960,233.76 1,025,417.41
Rate per cum = (a+b+c+d+e)/250 3,686.74 3,840.94 4,101.67
Say 3,687.00 3,841.00 4,102.00
4.01C (iii) Rate per cum for grading-III Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 62,066.30 79,358.16 99,878.32
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 83,789.51 87,293.98 93,219.76
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 250 cum = a+b+c+d+e 921,684.58 960,233.76 1,025,417.41
Rate per cum = (a+b+c+d+e)/250 3,686.74 3,840.94 4,101.67
Say 3,687.00 3,841.00 4,102.00
4.01C (iv) Rate per cum for grading-IV Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 62,066.30 79,358.16 99,878.32
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 83,789.51 87,293.98 93,219.76
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 250 cum = a+b+c+d+e 921,684.58 960,233.76 1,025,417.41
Rate per cum = (a+b+c+d+e)/250 3,686.74 3,840.94 4,101.67
Say 3,687.00 3,841.00 4,102.00
4.01C (v) Rate per cum for grading-V Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 62,066.30 79,358.16 99,878.32
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 83,789.51 87,293.98 93,219.76
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 250 cum = a+b+c+d+e 921,684.58 960,233.76 1,025,417.41
Rate per cum = (a+b+c+d+e)/250 3,686.74 3,840.94 4,101.67
Say 3,687.00 3,841.00 4,102.00
4.01C (vi) Rate per cum for grading-VI Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 62,066.30 77,582.88 93,018.81
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 83,789.51 85,341.16 86,817.56
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 250 cum = a+b+c+d+e 921,684.58 938,752.81 954,993.14
Rate per cum = (a+b+c+d+e)/250 3,686.74 3,755.01 3,819.97
Say 3,687.00 3,755.00 3,820.00
Note Any one of the grading for material may be adopted
as per design
4.02 A 402 Lime Stabilisation for Improving Sub-grade

Laying and spreading available soil in the sub-grade


on a prepared surface, pulverising, mixing the
spread soil in place with rotavator with 2 per cent
slaked lime having minimum content of 70 per cent
of CaO, grading with motor grader and compacting
with the road roller at OMC to the desired density to
form a layer of improved sub grade

Taking output = 300 cum 525 tonne


Unit = cum

A By Manual Means
a) Labour
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor for spraying lime day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 3,420.00 11,508.57 P&M-007
(ii) 1.1 cum bucket capacity hour 3.875 3,074.00 11,913.01 P&M-008
(iii) 0.9 cum bucket capacity hour 5.418 2,782.00 15,072.85 P&M-009
Tipper
For Transportation
(i) 18 cum capacity t.km 525 x L2 6.18 3,243.71 P&M-116
(ii) 14 cum capacity t.km 525 x L2 7.01 3,681.72 P&M-119
(iii) 10 cum capacity t.km 525 x L2 8.66 4,548.60 P&M-122
For loading & unloading Time
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
(i) 18 cum capacity hour 3.365 2,883.30 9,702.53 P&M-014
(ii) 14 cum capacity hour 3.875 2,556.75 9,908.45 P&M-015
(iii) 10 cum capacity hour 5.418 2,274.30 12,322.13 P&M-016
Tractor with ripper and rotavator attachments @ 250
cum per hour for mixing
P&M-026
hour 1.200 1.200 1.200 1,915.35 2,298.42 2,298.42 2,298.42 +P&M-027
+P&M-028

Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
Water tanker (speed @ 20km/hr and return speed 23.007
@ 30 km/hr and spreading speed @ 2.5 km/hr )

(i) 16 KL capacity hour 23.007 1,501.00 34,533.51 P&M-023


(ii) 12 KL capacity hour 30.676 1,327.00 40,707.05 P&M-024
(iii) 6 KL capacity hour 61.321 1,005.00 61,627.61 P&M-025
c) Material
Lime at site tonne 10.500 10.500 10.500 3,753.00 39,406.50 39,406.50 39,406.50 M-190
Cost of water including water for curing KL 99.750 99.750 99.750 16.00 1,596.00 1,596.00 1,596.00 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 45.00 13,500.00 13,500.00 13,500.00 M-093
d) Overhead charges @ 8% on @ 10% on @ 12% on 11,111.57 14,766.41 20,950.73
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 15,000.63 16,243.05 19,554.01
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 300 cum= a+b+c+d+e 165,006.88 178,673.51 215,094.14
Rate per cum =( a+b+c+d+e)/300 550.02 595.58 716.98
Say 550.00 596.00 717.00
4.02 B 402 (i) Lime Stabilisation for Improving Sub-grade

Laying and spreading available soil in the sub-grade


on a prepared surface, pulverising, mixing the
spread soil in place with Soil Stabilizer with 2 per
cent slaked lime using Binder spreader Machine,
having minimum content of 70 per cent of CaO,
grading with motor grader and compacting with the
road roller at OMC to the desired density to form a
layer of improved sub grade

Taking output = 300 cum 525 tonne


Unit = cum

By Mechanical Means
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 3,420.00 11,508.57 P&M-007
(ii) 1.1 cum bucket capacity hour 3.875 3,074.00 11,913.01 P&M-008
(iii) 0.9 cum bucket capacity hour 5.418 2,782.00 15,072.85 P&M-009
Tipper
For Transportation
(i) 18 cum capacity t.km 525 x L2 6.18 3,243.71 P&M-116
(ii) 14 cum capacity t.km 525 x L2 7.01 3,681.72 P&M-119
(iii) 10 cum capacity t.km 525 x L2 8.66 4,548.60 P&M-122
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2,883.30 9,702.53 P&M-014
(ii) 14 cum capacity hour 3.875 2,556.75 9,908.45 P&M-015
(iii) 10 cum capacity hour 5.418 2,274.30 12,322.13 P&M-016
Soil Stabilizer for mixing and pulverising with hour 2.667 2.667 2.667 26,741.40 71,310.40 71,310.40 71,310.40 P&M-085
capacity 1000 m2 per hour
Binder Spreader hour 2.667 2.667 2.667 8,300.25 22,134.00 22,134.00 22,134.00 P&M-086
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )

(i) 16 KL capacity hour 23.007 1,501.00 34,533.51 P&M-023


(ii) 12 KL capacity hour 30.676 1,327.00 40,707.05 P&M-024
(iii) 6 KL capacity hour 61.321 1,005.00 61,627.61 P&M-025
c) Material
Lime at site tonne 10.500 10.500 10.500 3,753.00 39,406.50 39,406.50 39,406.50 M-190
Cost of water including water for curing KL 99.750 99.750 99.750 16.00 1,596.00 1,596.00 1,596.00 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 45.00 13,500.00 13,500.00 13,500.00 M-093
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
d) Overhead charges @ 8% on @ 10% on @ 12% on 18,102.98 23,505.66 31,437.84
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 24,439.02 25,856.23 29,341.98
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 300 cum= a+b+c+d+e 268,829.26 284,418.53 322,761.80
Rate per cum =( a+b+c+d+e)/300 896.10 948.06 1,075.87
Say 896.00 948.00 1,076.00
4.02 B 402 (ii) Lime Stabilisation for Improving Sub-grade

Laying and spreading available soil in the sub-grade


on a prepared surface, pulverising, mixing the
spread soil in place with Soil Stabilizer with 2 per
cent slaked lime mannualy spreaded having
minimum content of 70 per cent of CaO, grading
with motor grader and compacting with the road
roller at OMC to the desired density to form a layer
of improved sub grade

Unit = cum
Taking output = 300 cum 525 tonne
By Mechanical Means
a) Labour
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor for spraying lime day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 3,420.00 11,508.57 P&M-007
(ii) 1.1 cum bucket capacity hour 3.875 3,074.00 11,913.01 P&M-008
(iii) 0.9 cum bucket capacity hour 5.418 2,782.00 15,072.85 P&M-009
Tipper
For Transportation
(i) 18 cum capacity t.km 525 x L2 6.18 3,243.71 P&M-116
(ii) 14 cum capacity t.km 525 x L2 7.01 3,681.72 P&M-119
(iii) 10 cum capacity t.km 525 x L2 8.66 4,548.60 P&M-122
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2,883.30 9,702.53 P&M-014
(ii) 14 cum capacity hour 3.875 2,556.75 9,908.45 P&M-015
(iii) 10 cum capacity hour 5.418 2,274.30 12,322.13 P&M-016
Soil Stabilizer for mixing and pulverising with hour 2.667 2.667 2.667 26,741.40 71,310.40 71,310.40 71,310.40 P&M-085
capacity 1000 m2 per hour
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )

(i) 16 KL capacity hour 23.007 1,501.00 34,533.51 P&M-023


(ii) 12 KL capacity hour 30.676 1,327.00 40,707.05 P&M-024
(iii) 6 KL capacity hour 61.321 1,005.00 61,627.61 P&M-025
c) Material
Lime at site tonne 10.500 10.500 10.500 3,753.00 39,406.50 39,406.50 39,406.50 M-190
Cost of water including water for curing KL 99.750 99.750 99.750 16.00 1,596.00 1,596.00 1,596.00 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 45.00 13,500.00 13,500.00 13,500.00 M-093
d) Overhead charges @ 8% on @ 10% on @ 12% on 16,632.53 21,667.60 29,232.17
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 22,453.92 23,834.36 27,283.35
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 300 cum= a+b+c+d+e 246,993.11 262,178.01 300,116.90
Rate per cum =( a+b+c+d+e)/300 823.31 873.93 1,000.39
Say 823.00 874.00 1,000.00
4.03 402 A Cement Stabilisation for Improving Sub-grade

Laying and spreading available soil in the sub-grade


on a prepared surface, pulverising, mixing the
spread soil in place with rotavator with 2 per cent
cement , gradingmotor grader and compacting with
the road roller at OMC to the desired density to form
a layer of improved sub grade.

Taking output = 300 cum 525 tonne


Unit = cum
A By Manual Means
a) Labour
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor for spraying lime day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 3,420.00 11,508.57 P&M-007
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
(ii) 1.1 cum bucket capacity hour 3.875 3,074.00 11,913.01 P&M-008
(iii) 0.9 cum bucket capacity hour 5.418 2,782.00 15,072.85 P&M-009
Tipper
For Transportation
(i) 18 cum capacity t.km 525 x L2 6.18 3,243.71 P&M-116
(ii) 14 cum capacity t.km 525 x L2 7.01 3,681.72 P&M-119
(iii) 10 cum capacity t.km 525 x L2 8.66 4,548.60 P&M-122
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2,883.30 9,702.53 P&M-014
(ii) 14 cum capacity hour 3.875 2,556.75 9,908.45 P&M-015
(iii) 10 cum capacity hour 5.418 2,274.30 12,322.13 P&M-016
Tractor with ripper and rotavator attachments @ 250
cum per hour for mixing
P&M-026
hour 1.200 1.200 1.200 1,915.35 2,298.42 2,298.42 2,298.42 +P&M-027
+P&M-028

Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
Water tanker (speed @ 20km/hr and return speed
@ 30 km/hr and spreading speed @ 2.5 km/hr )

(i) 16 KL capacity hour 23.007 1,501.00 34,533.51 P&M-023


(ii) 12 KL capacity 30.676 1,327.00 40,707.05 P&M-024
(iii) 6 KL capacity 61.321 1,005.00 61,627.61 P&M-025
c) Material
Cement at site tonne 10.500 10.500 10.500 4,940.00 51,870.00 51,870.00 51,870.00 M-081
Cost of water including water for curing KL 99.750 99.750 99.750 16.00 1,596.00 1,596.00 1,596.00 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 45.00 13,500.00 13,500.00 13,500.00 M-093
d) Overhead charges @ 8% on @ 10% on @ 12% on 12,108.65 16,012.76 22,446.35
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 16,346.68 17,614.03 20,949.92
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 300 cum= a+b+c+d+e 179,813.51 193,754.35 230,449.17
Rate per cum =( a+b+c+d+e)/300 599.38 645.85 768.16
Say 599.00 646.00 768.00
4.03 402 B Cement Stabilisation for Improving Sub-grade

(i) Laying and spreading available soil in the sub-grade


on a prepared surface, pulverising, mixing the
spread soil in place with Soil Stabilizer with 2 per
cent cement using Binder spreader Machine,
grading with motor grader and compacting with the
road roller at OMC to the desired density to form a
layer of improved sub grade

By Mechanical Means
Unit = cum
Taking output = 300 cum 525 tonne
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor for spraying lime day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 3,420.00 11,508.57 P&M-007
(ii) 1.1 cum bucket capacity hour 3.875 3,074.00 11,913.01 P&M-008
(iii) 0.9 cum bucket capacity hour 5.418 2,782.00 15,072.85 P&M-009
Tipper
For Transportation
(i) 18 cum capacity t.km 525 x L2 6.18 3,243.71 P&M-116
(ii) 14 cum capacity t.km 525 x L2 7.01 3,681.72 P&M-119
(iii) 10 cum capacity t.km 525 x L2 8.66 4,548.60 P&M-122
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2,883.30 9,702.53 P&M-014
(ii) 14 cum capacity hour 3.875 2,556.75 9,908.45 P&M-015
(iii) 10 cum capacity hour 5.418 2,274.30 12,322.13 P&M-016
Soil Stabilizer for mixing and pulverising with hour 2.667 2.667 2.667 26,741.40 71,310.40 71,310.40 71,310.40 P&M-085
capacity 1000 m2 per hour
Binder Spreader hour 2.667 2.667 2.667 8,300.25 22,134.00 22,134.00 22,134.00 P&M-086
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )

(i) 16 KL capacity hour 23.007 1,501.00 34,533.51 P&M-023


Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
(ii) 12 KL capacity hour 30.676 1,327.00 40,707.05 P&M-024
(iii) 6 KL capacity hour 61.321 1,005.00 61,627.61 P&M-025
c) Material
Cement at site tonne 10.500 10.500 10.500 4,940.00 51,870.00 51,870.00 51,870.00 M-081
Cost of water including water for curing KL 99.750 99.750 99.750 16.00 1,596.00 1,596.00 1,596.00 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 45.00 13,500.00 13,500.00 13,500.00 M-093
d) Overhead charges @ 8% on @ 10% on @ 12% on 19,100.06 24,752.01 32,933.46
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 25,785.08 27,227.22 30,737.89
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 300 cum= a+b+c+d+e 283,635.90 299,499.37 338,116.83
Rate per cum =( a+b+c+d+e)/300 945.45 998.33 1,127.06
Say 945.00 998.00 1,127.00
4.03 B 402 (ii) Cement Stabilisation for Improving Sub-grade

Laying and spreading available soil in the sub-grade


on a prepared surface, pulverising, mixing the
spread soil in place with Soil Stabilizer with 2 per
cent cement mannualy spreaded, grading with motor
grader and compacting with the road roller at OMC
to the desired density to form a layer of improved
sub grade

Taking output = 300 cum 525 tonne


Unit = cum

a) Labour
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor for spraying lime day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 3,420.00 11,508.57 P&M-007
(ii) 1.1 cum bucket capacity hour 3.875 3,074.00 11,913.01 P&M-008
(iii) 0.9 cum bucket capacity hour 5.418 2,782.00 15,072.85 P&M-009
Tipper
For Transportation
(i) 18 cum capacity t.km 525 x L2 6.18 3,243.71 P&M-116
(ii) 14 cum capacity t.km 525 x L2 7.01 3,681.72 P&M-119
(iii) 10 cum capacity t.km 525 x L2 8.66 4,548.60 P&M-122
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2,883.30 9,702.53 P&M-014
(ii) 14 cum capacity hour 3.875 2,556.75 9,908.45 P&M-015
(iii) 10 cum capacity hour 5.418 2,274.30 12,322.13 P&M-016
Soil Stabilizer for mixing and pulverising with hour 2.667 2.667 2.667 26,741.40 71,310.40 71,310.40 71,310.40 P&M-085
capacity 1000 m2 per hour
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )

(i) 16 KL capacity hour 23.007 1,501.00 34,533.51 P&M-023


(ii) 12 KL capacity hour 30.676 1,327.00 40,707.05 P&M-024
(iii) 6 KL capacity hour 61.321 1,005.00 61,627.61 P&M-025
c) Material
Cement at site tonne 10.500 10.500 10.500 4,940.00 51,870.00 51,870.00 51,870.00 M-081
Cost of water including water for curing KL 99.750 99.750 99.750 16.00 1,596.00 1,596.00 1,596.00 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 45.00 13,500.00 13,500.00 13,500.00 M-093
d) Overhead charges @ 8% on @ 10% on @ 12% on 17,629.61 22,913.95 30,727.79
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 23,799.98 25,205.35 28,679.27
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 300 cum= a+b+c+d+e 261,799.75 277,258.84 315,471.93
Rate per cum =( a+b+c+d+e)/300 872.67 924.20 1,051.57
Say 873.00 924.00 1,052.00
4.04 402 Lime Stabilisation in Embankment
Laying and spreading available soil in the sub-grade
on a prepared surface, pulverising, mixing the
spread soil in place with rotavator with 2 per cent
slaked lime having minimum content of 70 per cent
of CaO, grading with motor grader and compacting
with the road roller at OMC to the desired density to
form a layer of improved sub grade

A By Manual Means

Taking output = 300 cum 450 tonne


Unit = cum
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
a) Labour
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor for spraying lime day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 3,420.00 11,508.57 P&M-007
(ii) 1.1 cum bucket capacity hour 3.875 3,074.00 11,913.01 P&M-008
(iii) 0.9 cum bucket capacity hour 5.418 2,782.00 15,072.85 P&M-009
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L2 6.18 2,780.33 P&M-116
(ii) 14 cum capacity t.km 450 x L2 7.01 3,155.76 P&M-119
(iii) 10 cum capacity t.km 450 x L2 8.66 3,898.80 P&M-122
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2,883.30 9,702.53 P&M-014
(ii) 14 cum capacity hour 3.875 2,556.75 9,908.45 P&M-015
(iii) 10 cum capacity hour 5.418 2,274.30 12,322.13 P&M-016

P&M-026
Tractor with ripper and rotavator attachments @ 250
hour 1.200 1.200 1.200 1,915.35 2,298.42 2,298.42 2,298.42 +P&M-027
cum per hour for mixing
+P&M-028

Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )

(i) 16 KL capacity hour 19.720 1,501.00 29,599.72 P&M-023


(ii) 12 KL capacity hour 26.293 1,327.00 34,890.81 P&M-024
(iii) 6 KL capacity hour 52.557 1,005.00 52,819.79 P&M-025
c) Material
Lime at site tonne 9.000 9.000 9.000 3,753.00 33,777.00 33,777.00 33,777.00 M-190
Cost of water including water for curing KL 85.500 85.500 85.500 16.00 1,368.00 1,368.00 1,368.00 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 45.00 13,500.00 13,500.00 13,500.00 M-093
d) Overhead charges @ 8% on @ 10% on @ 12% on 10,211.20 13,546.44 19,112.91
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 13,785.12 14,901.08 17,838.72
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 300 cum= a+b+c+d+e 151,636.32 163,911.87 196,225.91
Rate per cum =( a+b+c+d+e)/300 505.45 546.37 654.09
Say 505.00 546.00 654.00
4.04 B 402 (i) Lime Stabilisation in Embankment

Laying and spreading available soil in the sub-grade


on a prepared surface, pulverising, mixing the
spread soil in place with Soil Stabilizer with 2 per
cent slaked lime using Binder spreader Machine,
having minimum content of 70 per cent of CaO,
grading with motor grader and compacting with the
road roller at OMC to the desired density to form a
layer of improved sub grade

Taking output = 300 cum 450 tonne


Unit = cum

By Mechanical Means
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor for spraying lime day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 3,420.00 11,508.57 P&M-007
(ii) 1.1 cum bucket capacity hour 3.875 3,074.00 11,913.01 P&M-008
(iii) 0.9 cum bucket capacity hour 5.418 2,782.00 15,072.85 P&M-009
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L2 6.18 2,780.33 P&M-116
(ii) 14 cum capacity t.km 450 x L2 7.01 3,155.76 P&M-119
(iii) 10 cum capacity t.km 450 x L2 8.66 3,898.80 P&M-122
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2,883.30 9,702.53 P&M-014
(ii) 14 cum capacity hour 3.875 2,556.75 9,908.45 P&M-015
(iii) 10 cum capacity hour 5.418 2,274.30 12,322.13 P&M-016
Soil Stabilizer for mixing and pulverising with hour 2.667 2.667 2.667 26,741.40 71,310.40 71,310.40 71,310.40 P&M-085
capacity 1000 m2 per hour
Binder Spreader hour 2.667 2.667 2.667 8,300.25 22,134.00 22,134.00 22,134.00 P&M-086
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )

(i) 16 KL capacity hour 19.720 1,501.00 29,599.72 P&M-023


(ii) 12 KL capacity hour 26.293 1,327.00 34,890.81 P&M-024
(iii) 6 KL capacity hour 52.557 1,005.00 52,819.79 P&M-025
c) Material
Lime at site tonne 9.000 9.000 9.000 3,753.00 33,777.00 33,777.00 33,777.00 M-190
Cost of water including water for curing KL 85.500 85.500 85.500 16.00 1,368.00 1,368.00 1,368.00 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 45.00 13,500.00 13,500.00 13,500.00 M-093
d) Overhead charges @ 8% on @ 10% on @ 12% on 17,202.61 22,285.69 29,600.02
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 23,223.52 24,514.26 27,626.69
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 300 cum= a+b+c+d+e 255,458.71 269,656.90 303,893.57
Rate per cum =( a+b+c+d+e)/300 851.53 898.86 1,012.98
Say 852.00 899.00 1,013.00
4.04 B 402 (ii) Lime Stabilisation in Embankment

Laying and spreading available soil in the sub-grade


on a prepared surface, pulverising, mixing the
spread soil in place with Soil Stabilizer with 2 per
cent slaked lime mannualy spreaded having
minimum content of 70 per cent of CaO, grading
with motor grader and compacting with the road
roller at OMC to the desired density to form a layer
of improved sub grade

Taking output = 300 cum 450 tonne


Unit = cum

By Mechanical Means
a) Labour
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor for spraying lime day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 3,420.00 11,508.57 P&M-007
(ii) 1.1 cum bucket capacity hour 3.875 3,074.00 11,913.01 P&M-008
(iii) 0.9 cum bucket capacity hour 5.418 2,782.00 15,072.85 P&M-009
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L2 6.18 2,780.33 P&M-116
(ii) 14 cum capacity t.km 450 x L2 7.01 3,155.76 P&M-119
(iii) 10 cum capacity t.km 450 x L2 8.66 3,898.80 P&M-122
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2,883.30 9,702.53 P&M-014
(ii) 14 cum capacity hour 3.875 2,556.75 9,908.45 P&M-015
(iii) 10 cum capacity hour 5.418 2,274.30 12,322.13 P&M-016
Soil Stabilizer for mixing and pulverising with hour 2.667 2.667 2.667 26,741.40 71,310.40 71,310.40 71,310.40 P&M-085
capacity 1000 m2 per hour
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )

(i) 16 KL capacity hour 19.720 1,501.00 29,599.72 P&M-023


(ii) 12 KL capacity hour 26.293 1,327.00 34,890.81 P&M-024
(iii) 6 KL capacity hour 52.557 1,005.00 52,819.79 P&M-025
c) Material
Lime at site tonne 9.000 9.000 9.000 3,753.00 33,777.00 33,777.00 33,777.00 M-190
Cost of water including water for curing KL 85.500 85.500 85.500 16.00 1,368.00 1,368.00 1,368.00 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 45.00 13,500.00 13,500.00 13,500.00 M-093
d) Overhead charges @ 8% on @ 10% on @ 12% on 15,732.16 20,447.63 27,394.35
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 21,238.41 22,492.40 25,568.06
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 300 cum= a+b+c+d+e 233,622.56 247,416.37 281,248.67
Rate per cum =( a+b+c+d+e)/300 778.74 824.72 937.50
Say 779.00 825.00 937.00
4.04 B 402 (iii) Cement Stabilisation in Embankment
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Laying and spreading available soil in the sub-grade
on a prepared surface, pulverising, mixing the
spread soil in place with Soil Stabilizer with 2 per
cent cement using Binder spreader Machine,
grading with motor grader and compacting with the
road roller at OMC to the desired density to form a
layer of improved sub grade

Taking output = 300 cum 450 tonne


Unit = cum

By Mechanical Means
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor for spraying lime day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 3,420.00 11,508.57 P&M-007
(ii) 1.1 cum bucket capacity hour 3.875 3,074.00 11,913.01 P&M-008
(iii) 0.9 cum bucket capacity hour 5.418 2,782.00 15,072.85 P&M-009
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L2 6.18 2,780.33 P&M-116
(ii) 14 cum capacity t.km 450 x L2 7.01 3,155.76 P&M-119
(iii) 10 cum capacity t.km 450 x L2 8.66 3,898.80 P&M-122
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2,883.30 9,702.53 P&M-014
(ii) 14 cum capacity hour 3.875 2,556.75 9,908.45 P&M-015
(iii) 10 cum capacity hour 5.418 2,274.30 12,322.13 P&M-016
Soil Stabilizer for mixing and pulverising with hour 2.667 2.667 2.667 26,741.40 71,310.40 71,310.40 71,310.40 P&M-085
capacity 1000 m2 per hour
Binder Spreader hour 2.667 2.667 2.667 8,300.25 22,134.00 22,134.00 22,134.00 P&M-086
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )

(i) 16 KL capacity hour 19.720 1,501.00 29,599.72 P&M-023


(ii) 12 KL capacity hour 26.293 1,327.00 34,890.81 P&M-024
(iii) 6 KL capacity hour 52.557 1,005.00 52,819.79 P&M-025
c) Material
Cement at site tonne 9.000 9.000 9.000 4,940.00 44,460.00 44,460.00 44,460.00 M-081
Cost of water including water for curing KL 85.500 85.500 85.500 16.00 1,368.00 1,368.00 1,368.00 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 45.00 13,500.00 13,500.00 13,500.00 M-093
d) Overhead charges @ 8% on @ 10% on @ 12% on 18,057.25 23,353.99 30,881.98
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 24,377.28 25,689.39 28,823.18
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 300 cum= a+b+c+d+e 268,150.11 282,583.33 317,055.02
Rate per cum =( a+b+c+d+e)/300 893.83 941.94 1,056.85
Say 894.00 942.00 1,057.00
4.04 B 402 (iv) Cement Stabilisation in Embankment

Laying and spreading available soil in the sub-grade


on a prepared surface, pulverising, mixing the
spread soil in place with Soil Stabilizer with 2 per
cent cement mannualy spreaded, grading with motor
grader and compacting with the road roller at OMC
to the desired density to form a layer of improved
sub grade

Taking output = 300 cum 450 tonne


Unit = cum

By Mechanical Means
a) Labour
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor for spraying lime day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 3,420.00 11,508.57 P&M-007
(ii) 1.1 cum bucket capacity hour 3.875 3,074.00 11,913.01 P&M-008
(iii) 0.9 cum bucket capacity hour 5.418 2,782.00 15,072.85 P&M-009
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L2 6.18 2,780.33 P&M-116
(ii) 14 cum capacity t.km 450 x L2 7.01 3,155.76 P&M-119
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
(iii) 10 cum capacity t.km 450 x L2 8.66 3,898.80 P&M-122
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2,883.30 9,702.53 P&M-014
(ii) 14 cum capacity hour 3.875 2,556.75 9,908.45 P&M-015
(iii) 10 cum capacity hour 5.418 2,274.30 12,322.13 P&M-016
Soil Stabilizer for mixing and pulverising with hour 2.667 2.667 2.667 26,741.40 71,310.40 71,310.40 71,310.40 P&M-085
capacity 1000 m2 per hour
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )

(i) 16 KL capacity hour 19.720 1,501.00 29,599.72 P&M-023


(ii) 12 KL capacity hour 26.293 1,327.00 34,890.81 P&M-024
(iii) 6 KL capacity hour 52.557 1,005.00 52,819.79 P&M-025
c) Material
Cement at site tonne 9.000 9.000 9.000 4,940.00 44,460.00 44,460.00 44,460.00 M-081
Cost of water including water for curing KL 85.500 85.500 85.500 16.00 1,368.00 1,368.00 1,368.00 M-191
Compensation for earth taken from private land cum 300.000 300.000 300.000 45.00 13,500.00 13,500.00 13,500.00 M-093
d) Overhead charges @ 8% on @ 10% on @ 12% on 16,586.80 21,515.93 28,676.31
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 22,392.18 23,667.53 26,764.56
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 300 cum= a+b+c+d+e 246,313.96 260,342.80 294,410.12
Rate per cum =( a+b+c+d+e)/300 821.05 867.81 981.37
Say 821.00 868.00 981.00
4.05 402 Lime Treated Soil for Sub- Base
Providing, laying and spreading soil on a prepared
sub grade, pulverising, mixing the spread soil in
place with rotavator with 3 per cent slaked lime with
minimum content of 70 per cent of CaO, grading
with motor grader and compacting with the road
roller at OMC to achieve at least 98 per cent of the
max dry density to form a layer of sub base.

Unit = cum
Taking output = 300 cum 525 tonne
a) Labour
Mate day 0.480 0.480 0.480 617.00 296.16 296.16 296.16 L-12
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Mazdoor day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 7.852 3,420.00 26,853.33 P&M-007
(ii) 1.1 cum bucket capacity hour 9.043 3,074.00 27,797.02 P&M-008
(iii) 0.9 cum bucket capacity hour 12.642 2,782.00 35,169.98 P&M-009
Tipper
For Transportation of Soil
(i) 18 cum capacity t.km 525 x L2 6.18 3,243.71 P&M-116
(ii) 14 cum capacity t.km 525 x L2 7.01 3,681.72 P&M-119
(iii) 10 cum capacity t.km 525 x L2 8.66 4,548.60 P&M-122
For loading & unloading
(i) 18 cum capacity hour 7.852 2,883.30 22,639.24 P&M-014
(ii) 14 cum capacity hour 9.043 2,556.75 23,119.72 P&M-015
(iii) 10 cum capacity hour 12.642 2,274.30 28,751.64 P&M-016
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022

P&M-026
Tractor with ripper and rotavator attachments @ 250
hour 1.200 1.200 1.200 1,915.35 2,298.42 2,298.42 2,298.42 +P&M-027
cum per hour for mixing
+P&M-028

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and spreading speed @ 2.5 km/hr )

(i) 16 KL capacity hour 0.365xL1+1. 1,501.00 18,187.62 P&M-023


167
(ii) 12 KL capacity hour 0.486xL1+1.5 1,327.00 21,412.47 P&M-024
56
(iii) 6 KL capacity hour 0.972xL1+3. 1,005.00 32,432.36 P&M-025
111

c) Material
Lime at site tonne 15.750 15.75 15.75 3,753.00 59,109.75 59,109.75 59,109.75 M-190
Compensation for earth taken from private land cum 300.000 300.00 300.00 45.00 13,500.00 13,500.00 13,500.00 M-093
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Cost of water KL 52.500 52.5 52.50 16.00 840.00 840.00 840.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on 13,715.23 17,807.48 24,303.70
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 18,515.55 19,588.23 22,683.45
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 300 cum = a+b+c+d+e 203,671.10 215,470.53 249,518.00
Rate per cum= (a+b+c+d+e)/300 678.90 718.24 831.73
Say 679.00 718.00 832.00
4.06 403 Cement Treated Soil Sub Base/ Base
Providing, laying and spreading soil on a prepared
sub grade, pulverising, adding the designed quantity
of cement to the spread soil, mixing in place with
rotavator, grading with the motor grader and
compacting with the road roller at OMC to achieve
the desired unconfined compressive strength and to
form a layer of sub-base/base.

Unit = cum
Taking output = 300 cum 525 tonne
For 4 per cent quantity of cement by weight of soil

a) Labour
Mate day 0.480 0.480 0.480 617.00 296.16 296.16 296.16 L-12
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Mazdoor day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 7.852 3,420.00 26,853.33 P&M-007
(ii) 1.1 cum bucket capacity hour 9.043 3,074.00 27,797.02 P&M-008
(iii) 0.9 cum bucket capacity hour 12.642 2,782.00 35,169.98 P&M-009
Tipper
For Transportation of Soil
(i) 18 cum capacity t.km 525 x L2 6.18 3,243.71 P&M-116
(ii) 14 cum capacity t.km 525 x L2 7.01 3,681.72 P&M-119
(iii) 10 cum capacity t.km 525 x L2 8.66 4,548.60 P&M-122
For loading & unloading
(i) 18 cum capacity hour 7.852 2,883.30 22,639.24 P&M-014
(ii) 14 cum capacity hour 9.043 2,556.75 23,119.72 P&M-015
(iii) 10 cum capacity hour 12.642 2,274.30 28,751.64 P&M-016
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
Tractor with ripper and rotavator attachments @ 250
cum per hour for mixing
P&M-026
hour 1.200 1.200 1.200 1,915.35 2,298.42 2,298.42 2,298.42 +P&M-027
+P&M-028

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and spreading speed @ 2.5 km/hr )

(i) 16 KL capacity hour 0.365xL1+1. 1,501.00 18,187.62 P&M-023


167
(ii) 12 KL capacity hour 0.486xL1+1.5 1,327.00 21,412.47 P&M-024
56
(iii) 6 KL capacity hour 0.972xL1+3. 1,005.00 32,432.36 P&M-025
111

c) Material
Cement at site (@ 4 per cent of 525 tonne) tonne 21.000 21.000 21.000 4,940.00 103,740.00 103,740.00 103,740.00 M-081
Compensation for earth taken from private land cum 300.000 300.000 300.000 45.00 13,500.00 13,500.00 13,500.00 M-093
Cost of water KL 52.500 52.500 52.500 16.00 840.00 840.00 840.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on 17,285.65 22,270.51 29,659.33
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 23,335.62 24,497.56 27,682.04
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 300 cum = a+b+c+d+e 256,691.84 269,473.13 304,502.47
Rate per cum= (a+b+c+d+e)/300 855.64 898.24 1,015.01
Say 856.00 898.00 1,015.00
4.07 403 Cement Treated Crushed Rock or combination as
per clause 403 and table 400.4in Sub base/ Base

Providing, laying and spreading Material on a


prepared sub grade, adding the designed quantity of
cement to the spread Material, mixing in place with
rotavator, grading with the motor grader and
compacting with the road roller at OMC to achieve
the desired unconfined compressive strength and to
form a layer of sub-base/base.
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Unit = cum
Taking output = 300 cum 660 tonne 630.00
Quantity of cement assumed as 4 per cent of
quantity of crushed rock by weight.
a) Labour
Mate day 0.480 0.480 0.480 617.00 296.16 296.16 296.16 L-12
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Mazdoor day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-13
b) Machinery
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
Tractor with ripper and rotavator attachments @ 250
cum per hour for mixing
P&M-026
hour 1.200 1.200 1.200 1,915.35 2,298.42 2,298.42 2,298.42 +P&M-027
+P&M-028

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and spreading speed @ 2.5 km/hr )

(i) 16 KL capacity hour 0.417xL1+1. 1,501.00 20,796.36 P&M-023


333
(ii) 12 KL capacity hour 0.556xL1+1.7 1,327.00 24,493.77 P&M-024
78
(iii) 6 KL capacity hour 1.111xL1+3. 1,005.00 37,070.43 P&M-025
556
c) Material
Cement at site @ 4 per cent by weight of crushed tonne 24.000 24.000 24.000 4,940.00 118,560.00 118,560.00 118,560.00 M-081
aggregate (600 tonne)
Grading of material for sub-base course
37.5 mm to 9.5 mm @ 55 per cent cum 211.538 222.115 211.200 1,837.12 388,622.20 408,053.31 388,000.40 M-013
9.5 mm to 4.75 mm @ 20 per cent cum 76.800 80.769 76.800 1,887.12 144,931.05 152,421.48 144,931.05 M-015
4.75 mm to 75 micron @ 25 per cent cum 96.000 100.962 96.000 1,887.12 181,163.82 190,526.85 181,163.82 M-018
Cost of water KL 60.000 60.000 60.000 16.00 960.00 960.00 960.00 M-191
or
Grading of material for Base course
45 mm to 22.4 mm@ 30 per cent cum 124.800 124.800 124.800 1,837.12 229,272.96 229,272.96 229,272.96 M-013
22.4 mm to 2.36 mm @ 40 per cent cum 19.200 19.200 19.200 1,887.12 36,232.76 36,232.76 36,232.76 M-015
2.36 mm to 75 micron@ 30 per cent cum 240.000 240.000 240.000 1,887.12 452,909.55 452,909.55 452,909.55 M-018
Cost of water KL 60.000 60.000 60.000 16.00 960.00 960.00 960.00 M-191
4.07 (i) For Sub-Base course
d) Overhead charges @ 8% on @ 10% on @ 12% on 70,568.01 92,362.95 107,863.71
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 95,266.81 101,599.25 100,672.79
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 300 cum = a+b+c+d+e 1,047,934.90 1,117,591.75 1,107,400.72
Rate per cum = (a+b+c+d+e)/300 3,493.12 3,725.31 3,691.34
Say 3,493.00 3,725.00 3,691.00
4.07 (ii) For Base course
d) Overhead charges @ 8% on @ 10% on @ 12% on 70,863.86 89,104.32 108,382.11
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 95,666.22 98,014.75 101,156.63
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 300 cum = a+b+c+d+e 1,052,328.37 1,078,162.24 1,112,722.96
Rate per cum = (a+b+c+d+e)/300 3,507.76 3,593.87 3,709.08
Say 3,508.00 3,594.00 3,709.00
Note Quantities of aggregates provided under 'c' above
are uncompacted quantities.
4.08 403 Cement Treated Crushed Stone Sub base
A Plant Mix Method
Construction of granular sub-base by providing
graded Material, mixing with cement in a mechanical
mix plant at OMC, carriage of mixed Material to work
site, spreading in uniform layers with Mechanical
Paver on prepared surface and compacting with
vibratory power roller to achieve the desired density,
complete as per clause 401

Laying Using Mechanical Paver


Unit = cum
Taking output = 250 cum 525 tonne
a) Labour
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Machinery
Wet mix plant
(i) 250 tonne per hour hour 2.800 921.90 2,581.32 P&M-032
(ii) 200 tonne per hour hour 3.500 612.15 2,142.53 P&M-033
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
(iii) 100 tonne per hour hour 7.000 585.90 4,101.30 P&M-034
Electric generator
(i) 125 KVA hour 2.800 2,390.85 6,694.38 P&M-047
(ii) 100 KVA hour 3.500 2,041.20 7,144.20 P&M-048
(iii) 62.5 KVA hour 7.000 1,312.50 9,187.50 P&M-049
Front end loader for loading to Tipper
(i) 3.1 Cum Capacity hour 5.939 4,279.80 25,417.40 P&M-011
(ii) 2.1 Cum Capacity hour 8.779 2,640.75 23,183.88 P&M-012
(iii) 1 Cum Capacity hour 18.357 1,112.00 20,412.62 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 525 x L1 6.18 97,311.38 P&M-116
(ii) 14 cum capacity t.km 525 x L1 7.01 110,451.60 P&M-119
(iii) 10 cum capacity t.km 525 x L1 8.66 136,458.00 P&M-122
For loading & unloading time
(i) 18 cum capacity hour 5.600 2,883.30 16,146.48 P&M-014
(ii) 14 cum capacity hour 6.300 2,556.75 16,107.53 P&M-015
(iii) 10 cum capacity hour 9.800 2,274.30 22,288.14 P&M-016
Mechanical Paver finisher hour 2.800 3.500 3.500 1,112.00 3,113.60 3,892.00 3,892.00 P&M-057
Vibratory roller hour 2.240 2.800 2.800 2,562.00 5,738.88 7,173.60 7,173.60 P&M-022
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )

(i) 16 KL capacity hour 10.715 1,501.00 16,083.22 P&M-023


(ii) 12 KL capacity hour 14.292 1,327.00 18,965.48 P&M-024
(iii) 6 KL capacity hour 28.583 1,005.00 28,725.92 P&M-025
c) Material
Cement at site tonne 13.125 13.125 13.125 4,940.00 64,837.50 64,837.50 64,837.50 M-081
Cost of water including water for curing KL 99.750 99.750 99.750 16.00 1,596.00 1,596.00 1,596.00 M-191
(i) For Grading-III Material
26.5mm to 9.5mm @ 68 % cum 228.846 228.846 228.846 1,887.12 431,860.57 431,860.57 431,860.57 M-014
9.5mm to 4.75mm @12% cum 40.385 40.385 40.385 1,887.12 76,211.47 76,211.47 76,211.47 M-015
4.75mm below @ 20% cum 67.308 67.308 67.308 1,887.12 127,018.48 127,018.48 127,018.48 M-018
OR
(ii) For Grading-IV Material
26.5mm to 9.5mm @ 64 % cum 215.385 215.385 215.385 1,887.12 406,458.01 406,458.01 406,458.01 M-014
9.5mm to 4.75mm @11% cum 37.019 37.019 37.019 1,887.12 69,859.41 69,859.41 69,859.41 M-015
4.75mm below @ 25% cum 84.135 84.135 84.135 1,887.12 158,773.10 158,773.10 158,773.10 M-018

(i) Rate per cum for Grading-III Material


d) Overhead charges @ 8% on @ 10% on @ 12% on 70,144.78 89,278.38 112,315.45
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 94,695.45 98,206.22 104,827.76
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 250 cum = a+b+c+d+e 1,041,649.91 1,080,268.45 1,153,105.32
Rate per cum = (a+b+c+d+e)/250 4,166.60 4,321.07 4,612.42
Say 4,167.00 4,321.00 4,612.00
(ii) Rate per cum for Grading-IV Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 70,144.78 89,278.38 112,315.45
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 94,695.45 98,206.22 104,827.76
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for hour cum = a+b+c+d+e 1,041,649.91 1,080,268.45 1,153,105.32
Rate per cum = (a+b+c+d+e)/hour 4,166.60 4,321.07 4,612.42
Say 4,167.00 4,321.00 4,612.00
4.08 403 Cement Treated Crushed Stone Sub base
B By Mix in Place Method
Construction of granular sub-base by providing
graded Material, mixing , carriage of mixed Material
to work site, spreading in uniform layers with motor
grader on prepared surface, mixing with cement at
OMC and compacting with vibratory power roller to
achieve the desired density, complete as per clause
401

Unit = cum
Taking output = 250 cum 525 tonne
By Mechanical Means
a) Labour
Mate day 0.400 0.400 0.400 617.00 246.80 246.80 246.80 L-12
Skilled mazdoor for alignment and geometrics day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Mazdoor for spraying lime day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Front end loader for mixing at stock pile location

(i) 3.1 Cum Capacity hour 4.464 4,279.80 19,106.25 P&M-011


(ii) 2.1 Cum Capacity hour 6.579 2,640.75 17,373.36 P&M-012
(iii) 1 Cum Capacity hour 13.889 1,112.00 15,444.44 P&M-013
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )

(i) 16 KL capacity hour 22.637 1,501.00 33,978.14 P&M-023


(ii) 12 KL capacity hour 30.183 1,327.00 40,052.84 P&M-024
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
(iii) 6 KL capacity hour 60.336 1,005.00 60,637.68 P&M-025
Soil Stabilizer for mixing and pulverising with hour 2.222 2.222 2.222 26,741.40 59,425.33 59,425.33 59,425.33 P&M-085
capacity 1000 m2 per hour
Binder Spreader hour 2.222 2.222 2.222 8,300.25 18,445.00 18,445.00 18,445.00 P&M-086
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.016 5,991.00 12,078.63 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.432 5,497.00 13,368.19 P&M-005
(iii) Motor grader 3.35 metre blade hour 2.712 4,796.00 13,005.18 P&M-006
Vibratory roller hour 1.618 1.618 1.618
c) Material
Cement at site tonne 13.125 13.125 13.125 4,940.00 64,837.50 64,837.50 64,837.50 M-081
Cost of water including water for curing KL 99.750 99.750 99.750 16.00 1,596.00 1,596.00 1,596.00 M-191
For Grading-III Material
26.5 mm to 9.5 mm @ 68 per cent cum 228.846 228.846 228.846 1,887.12 431,860.86 431,860.86 431,860.86 M-014
9.5 mm to 4.75 mm @ 12 % cum 40.385 40.385 40.385 1,887.12 76,210.74 76,210.74 76,210.74 M-015
4.75 mm below @ 20 per cent cum 67.308 67.308 67.308 1,887.12 127,017.90 127,017.90 127,017.90 M-018
OR
For Grading-IV Material
26.5 mm to 9.5 mm @ 64 per cent cum 215.385 215.385 215.385 1,887.12 406,457.28 406,457.28 406,457.28 M-014
9.5 mm to 4.75 mm @ 11 % cum 37.019 37.019 37.019 1,887.12 69,859.85 69,859.85 69,859.85 M-015
4.75 mm below @ 25 per cent cum 84.135 84.135 84.135 1,887.12 158,772.38 158,772.38 158,772.38 M-018
(i) Rate per cum for Grading-III Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 68,002.14 85,565.81 104,874.13
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 91,802.89 94,122.40 97,882.52
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for cum = a+b+c+d+e 1,009,831.81 1,035,346.36 1,076,707.71
Rate per cum = (a+b+c+d+e)/250 4,039.33 4,141.39 4,306.83
Say 4,039.00 4,141.00 4,307.00
(ii) Rate per cum for Grading-IV Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 68,002.14 85,565.81 104,874.13
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 91,802.89 94,122.40 97,882.52
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for day cum = a+b+c+d+e 1,009,831.81 1,035,346.36 1,076,707.71
Rate per cum = (a+b+c+d+e)/250 4,039.33 4,141.39 4,306.83
Say 4,039.00 4,141.00 4,307.00
Note * Though vibratory roller is required only for 3 hours
as per norms, but the same has to be available at
site for 6 hours as other machines for spreading and
mixing will take 6 hours. The usage rates of roller
have been multiplied with a factor of 0.65.

4.09 404.3.1 Making 50 mm x 50 mm Furrows


Making 50 mm x 50 mm furrows, 25mm/ 50mm
deep, 450 to the center line of the road and at one
metre interval in the existing thin bituminous wearing
coarse including sweeping and disposal of
excavated material within 1000 metres lead

Unit = sqm
Taking output = 30 m x 7 m = 210 sqm
(i) 25mm deep furrow cutting
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Tractor-trolley hour 0.200 0.200 0.200 1,876.50 375.30 375.30 375.30 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on 115.82 144.77 173.72
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 156.35 159.25 162.14
(a+b+c) (a+b+c) (a+b+c)
Cost for 210 sqm= a+b+c+d 1,719.87 1,751.72 1,783.57
Rate per sqm =(a+b+c+d)/210 8.19 8.34 8.49
Say 8.00 8.00 8.00
(ii) 50mm deep furrow cutting
a) Labour
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Mazdoor day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
b) Machinery
Tractor-trolley hour 0.400 0.400 0.400 1,876.50 750.60 750.60 750.60 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on 231.63 289.54 347.45
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 312.70 318.49 324.28
(a+b+c) (a+b+c) (a+b+c)
Cost for 210 sqm= a+b+c+d 3,439.74 3,503.43 3,567.13
Rate per sqm =(a+b+c+d)/210 16.38 16.68 16.99
Say 16.00 17.00 17.00
4.10 404.3.2 Inverted Choke
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Construction of inverted choke by providing, laying,
spreading and compacting screening B type/ coarse
sand of specified grade in uniform layer on a
prepared surface with motor grader and compacting
with power roller etc

Unit = cum
Taking output = 600 cum
a) Labour
Mate day 0.920 0.920 0.920 617.00 567.64 567.64 567.64 L-12
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Mazdoor day 21.000 21.000 21.000 511.52 10,741.92 10,741.92 10,741.92 L-13
b) Machinery
Motor Grader
(i) Motor grader 4.30 metre blade hour 4.839 5,991.00 28,988.71 P&M-004
(ii) Motor grader 3.70 metre blade hour 5.837 5,497.00 32,083.66 P&M-005
(iii) Motor grader 3.35 metre blade hour 6.508 4,796.00 31,212.43 P&M-006
Vibratory roller 8-10 tonnes @ 60 cum per hour hour 6.000 6.000 6.000 2,562.00 15,372.00 15,372.00 15,372.00 P&M-022
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )

(i) 16 KL capacity hour 0.75xL1+4.8 1,501.00 40,977.30 P&M-023

(ii) 12 KL capacity hour 1xL1+6.4 1,327.00 48,302.80 P&M-024


(iii) 6 KL capacity hour 2xL1+12.8 1,005.00 73,164.00 P&M-025
c) Material
Screening type 'B' or coarse sand cum 720.000 720.000 720.000 1,994.03 1,435,702.32 1,435,702.32 1,435,702.32 M-005
Cost of water KL 108.000 108.000 108.000 16.00 1,728.00 1,728.00 1,728.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on 122,816.75 154,562.98 188,354.37
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 165,802.61 170,019.28 175,797.41
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 600 cum = a+b+c+d+e 1,823,828.71 1,870,212.06 1,933,771.55
Rate per cum = ( a+b+c+d+e)/600 3,039.71 3,117.02 3,222.95
Say 3,040.00 3,117.00 3,223.00
4.11 404 Water Bound Macadam
Providing, laying, spreading and compacting stone
aggregates of specific sizes to water bound
macadam specification including spreading in
uniform thickness, hand packing, rolling with 3
wheeled steel/ vibratory roller in stages to proper
grade and camber, applying and brooming requisite
type of screening/ binding Materials to fill up the
interstices of coarse aggregate, watering and
compacting to the required density.

A By Manual Means
Unit = cum
Taking output = 360 Cum 756 tonne
a) Labour
Mate day 10.080 10.080 10.080 617.00 6,219.36 6,219.36 6,219.36 L-12
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Mazdoor day 250.000 250.000 250.000 511.52 127,880.00 127,880.00 127,880.00 L-13
b) Machinery

Vibratory roller hour 2.330 2.330 2.300 2,562.00 5,969.46 5,969.46 5,892.60 P&M-022
or
Smooth 3 wheeled steel roller @ 30cum/hour hour 4.660 4.660 4.600 417.00 1,943.22 1,943.22 1,918.20 P&M-019
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )

(i) 16 KL capacity hour 1xL1+3.84 1,501.00 50,793.84 P&M-023


(ii) 12 KL capacity hour 1.333xL1+5.1 1,327.00 59,860.97 P&M-024
2
(iii) 6 KL capacity hour 0.533xL1+1 1,005.00 26,361.15 P&M-025
0.24

c) Material ( Refer table 400 - 8, 9, 10 & 11)


4.11 A (i) Grading-I

Aggregate
Grading-I 63 mm to 45 mm/Gradeing-II 53mm to cum 435.600 435.600 435.600 1,887.12 822,030.82 822,030.82 822,030.82 M-037
22.4mm@ 0.91cum per 10 sqm for compacted
thickness of 75 mm

Stone Screening
Type A 13.2 mm for grading-I @ 0.12 cum per 10 cum 57.600 57.600 57.600 1,887.12 108,698.29 108,698.29 108,698.29 M-041
sqm
OR
Crushable type such as Moorum or Gravel for cum 105.590 105.590 105.590 1,297.52 137,005.24 137,005.24 137,005.24 M-007
grading-I & II @ 0.22 cum per 10 sqm
OR
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Type B 11.2 mm for grading-II @ 0.18 cum per 10 cum 86.400 86.400 86.400 1,887.12 163,047.44 163,047.44 163,047.44 M-040
sqm
Binding material
Binding Material @ 0.06cum per 10 sqm for grading I cum 28.800 28.800 28.800 1,297.52 37,368.60 37,368.60 37,368.60 M-007
material
Cost of water KL 144.000 144.000 144.000 16.00 2,304.00 2,304.00 2,304.00 M-191
4.11 A (a) Using Scrining Crushable type such as Moorum or
(i) Gravel
d) Overhead charges @ 8% on @ 10% on @ 12% on 95,411.68 120,171.31 140,173.37
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 128,805.77 132,188.45 130,828.48
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 360 cum = a+b+c+d+e 1,416,863.46 1,454,072.90 1,439,113.30
Rate per cum = (a+b+c+d+e)/360 3,935.73 4,039.09 3,997.54
Say 3,936.00 4,039.00 3,998.00
OR
4.11 A (b) Using Scrining Type-A (13.2mm agg.)
(i)
d) Overhead charges @ 8% on @ 10% on @ 12% on 93,147.12 117,340.62 136,776.54
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 125,748.62 129,074.68 127,658.10
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 360 cum = a+b+c+d+e 1,383,234.80 1,419,821.49 1,404,239.13
Rate per cum = (a+b+c+d+e)/360 3,842.32 3,943.95 3,900.66
Say 3,842.00 3,944.00 3,901.00
OR
4.11 A (c) Using Scrining Type-B (11.2mm agg.)
(i)
d) Overhead charges @ 8% on @ 10% on @ 12% on 97,495.06 122,775.53 143,298.44
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 131,618.33 134,146.37 133,745.21
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 360 cum = a+b+c+d+e 1,447,801.59 1,484,677.24 1,471,197.28
Rate per cum = (a+b+c+d+e)/360 4,021.67 4,124.10 4,086.66
Say 4,022.00 4,124.00 4,087.00
4.11 A (ii) Grading-II

Aggregate
Grading-II 53 mm to 22.4 mm @ 0.91 cum per 10 cum 435.600 435.600 435.600 1,887.12 822,030.82 822,030.82 822,030.82 M-035
sqm for compacted thickness of 75 mm

Stone Screening
Type b 11.2 mm for grading-II@ 0.18 cum per 10 cum 86.400 86.400 86.400 1,887.12 163,047.44 163,047.44 163,047.44 M-040
sqm
OR
Crushable type such as Moorum or Gravel for cum 105.590 105.590 105.590 1,297.52 137,005.24 137,005.24 137,005.24 M-007
grading II &III @ 0.22 cum per 10 sqm
Binding material
Binding Material @ 0.06cum per 10 sqm for grading cum 28.800 28.800 28.800 1,297.52 37,368.60 37,368.60 37,368.60 M-007
II material
Cost of water KL 144.000 144.000 144.000 16.00 2,304.00 2,304.00 2,304.00 M-191
4.11 A (a) Using Scrining Crushable type such as Moorum or
(ii) Gravel
d) Overhead charges @ 8% on @ 10% on @ 12% on 95,411.68 120,171.31 140,173.37
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 128,805.77 132,188.45 130,828.48
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 360 cum = a+b+c+d+e 1,416,863.46 1,454,072.90 1,439,113.30
Rate per cum = (a+b+c+d+e)/360 3,935.73 4,039.09 3,997.54
Say 3,936.00 4,039.00 3,998.00
OR
4.11 A (b) Using Scrining Type-A (13.2mm agg.)
(ii)
d) Overhead charges @ 8% on (a+b+c) 97,495.06 122,775.53 143,298.44
e) Contractor's profit @ 10% on (a+b+c+d) 131,618.33 135,053.09 133,745.21

Cost for 360 cum = a+b+c+d+e 1,447,801.59 1,485,583.96 1,471,197.28


Rate per cum = (a+b+c+d+e)/360 4,021.67 4,126.62 4,086.66
OR Say 4,022.00 4,127.00 4,087.00
( Anyone of the aggregate grading, screening and
binding material may be used as per design)

4.11 B By Mechanical Means:


Unit = cum
Taking output = 360 Cum 756 tonne
a) Labour
Mate day 0.680 0.680 0.680 617.00 419.56 419.56 419.56 L-12
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Mazdoor day 15.000 15.000 15.000 511.52 7,672.80 7,672.80 7,672.80 L-13
b) Machinery
Front end loader for mixing at stock pile location
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
(i) 3.1 Cum Capacity hour 6.429 4,279.80 27,513.00 P&M-011
(ii) 2.1 Cum Capacity hour 9.474 2,640.75 25,017.63 P&M-012
(iii) 1 Cum Capacity hour 20.000 1,112.00 22,240.00 P&M-013
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.903 5,991.00 17,393.23 P&M-004
(ii) Motor grader 3.70 metre blade hour 3.502 5,497.00 19,250.19 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.905 4,796.00 18,727.46 P&M-006
Vibratory roller hour 2.330 2.330 2.330 2,562.00 5,969.71 5,969.71 5,969.71 P&M-022
or
Smooth 3 wheeled steel roller hour 4.660 4.660 4.660 417.00 1,943.30 1,943.30 1,943.30 P&M-019
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )

(i) 16 KL capacity hour 33.840 1,501.00 50,793.84 P&M-023


(ii) 12 KL capacity hour 45.110 1,327.00 59,860.97 P&M-024
(iii) 6 KL capacity hour 90.250 1,005.00 90,701.25 P&M-025
c) Material ( Refer table 400 - 8, 9, 10 & 11 )

4.11 B (i) Grading-I

Aggregate
Grading-I 63 mm to 45/Grading-II 53 mm to 22.4mm cum 435.600 435.600 435.600 1,887.12 822,030.82 822,030.82 822,030.82 M-037
@ 0.91cum per 10 sqm for compacted thickness of
75 mm

Stone Screening
Type A 13.2 mm for grading-I @ 0.12 cum per 10 cum 57.600 57.600 57.600 1,887.12 108,698.29 108,698.29 108,698.29 M-041
sqm
OR
Crushable type such as Moorum or Gravel for cum 105.590 105.590 105.590 1,297.52 137,005.24 137,005.24 137,005.24 M-007
grading-I &II@ 0.22 cum per 10 sqm
OR
Type B 11.2mm for grading II @0.18 cum per 10sqm cum 86.400 86.400 86.400 1,887.12 163,047.44 163,047.44 163,047.44 M-040

Binding material
Binding Material @ 0.06cum per 10 sqm for grading I cum 28.800 28.800 28.800 1,297.52 37,368.60 37,368.60 37,368.60 M-007
material
Cost of water KL 144.000 144.000 144.000 16.00 2,304.00 2,304.00 2,304.00 M-191
4.11 B (a) Using Scrining Crushable type such as Moorum or
(i) Gravel
d) Overhead charges @ 8% on @ 10% on @ 12% on 88,923.65 111,997.43 137,701.70
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 120,046.92 123,197.17 128,521.59
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 360 cum = a+b+c+d+e 1,320,516.13 1,355,168.90 1,413,737.50
Rate per cum = (a+b+c+d+e)/360 3,668.10 3,764.36 3,927.05
Say 3,668.00 3,764.00 3,927.00
OR
4.11 B (b) Using Scrining Type-A (13.2mm agg.)
(i)
d) Overhead charges @ 8% on @ 10% on @ 12% on 86,659.09 109,166.73 134,304.87
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 116,989.77 120,083.41 125,351.21
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 360 cum = a+b+c+d+e 1,286,887.48 1,320,917.49 1,378,863.34
Rate per cum = (a+b+c+d+e)/360 3,574.69 3,669.22 3,830.18
Say 3,575.00 3,669.00 3,830.00
OR
4.11 B (c) Using Scrining Type-B (11.2mm agg.)
(i)
d) Overhead charges @ 8% on @ 10% on @ 12% on 91,007.02 114,601.65 140,826.77
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 122,859.48 126,061.81 131,438.32
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 360 cum = a+b+c+d+e 1,351,454.26 1,386,679.95 1,445,821.49
Rate per cum = (a+b+c+d+e)/360 3,754.04 3,851.89 4,016.17
Say 3,754.00 3,852.00 4,016.00
4.11 B (ii) Grading-II

Aggregate
Grading-II 53 mm to 22.4 mm @ 0.91 cum per 10 cum 435.600 435.600 435.600 1,887.12 822,030.82 822,030.82 822,030.82 M-035
sqm for compacted thickness of 75 mm

Stone Screening
Type B11.2 mm for grading-III @ 0.18 cum per 10 cum 86.400 86.400 86.400 1,887.12 163,047.44 163,047.44 163,047.44 M-040
sqm
OR
Crushable type such as Moorum or Gravel for cum 105.590 105.590 105.590 1,297.52 137,005.24 137,005.24 137,005.24 M-007
grading II &III @ 0.22 cum per 10 sqm
Binding material
Binding Material @ 0.06cum per 10 sqm for grading cum 28.800 28.800 28.800 1,297.52 37,368.60 37,368.60 37,368.60 M-007
II material
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Cost of water KL 144.000 144.000 144.000 16.00 2,304.00 2,304.00 2,304.00 M-191
4.11 B (a) Using Scrining Crushable type such as Moorum or
(ii) Gravel
d) Overhead charges @ 8% on @ 10% on @ 12% on 88,923.65 111,997.43 137,701.70
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 120,046.92 123,197.17 128,521.59
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 360 cum = a+b+c+d+e 1,320,516.13 1,355,168.90 1,413,737.50
Rate per cum = (a+b+c+d+e)/360 3,668.10 3,764.36 3,927.05
Say 3,668.00 3,764.00 3,927.00
OR
4.11 B (b) Using Scrining Type-A (13.2mm agg.)
(ii)
d) Overhead charges @ 8% on @ 10% on @ 12% on 91,007.02 113,758.78 140,826.77
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 122,859.48 125,977.53 131,438.32
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 360 cum = a+b+c+d+e 1,351,454.26 1,385,752.79 1,445,821.49
Rate per cum = (a+b+c+d+e)/360 3,754.04 3,849.31 4,016.17
Say 3,754.00 3,849.00 4,016.00
4.12 405 Crushed Cement Concrete Sub-base / Base
Breaking and crushing of material obtained by
breaking damaged cement concrete slabs to size
range not exceeding 75 mm as specified in table
400.9 transporting the aggregates obtained from
breaking of cement concrete slabs at a lead of L km.,
laying and compacting the same as sub base/ base
course, constructed as WBM to clause 404 except
the use of screening or binding Material.

Unit = cum
Taking output = 360 cum 720.000 Tonne
a) Labour
Mate day 4.160 4.160 4.160 617.00 2,566.72 2,566.72 2,566.72 L-12
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Mazdoor for crushing broken cement concrete day 102.000 102.000 102.000 511.52 52,175.04 52,175.04 52,175.04 L-13
pavement/slabs into aggregate
b) Machinery
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 2.903 5,991.00 17,393.23 P&M-004
(ii) Motor grader 3.70 metre blade hour 3.502 5,497.00 19,250.19 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.905 4,796.00 18,727.46 P&M-006
Vibratory roller 8 - 10 tonne@ 60 cum per hour hour 6.000 6.000 6.000 2,562.00 15,372.00 15,372.00 15,372.00 P&M-022
or
Smooth 3 wheeled steel roller @ 30cum/hr. hour 12.000 12.000 12.000 - - - - P&M-019
Front end loader for loading to Tipper
(i) 3.1 Cum Capacity hour 2.229 4,279.80 9,540.11 P&M-011
(ii) 2.1 Cum Capacity hour 3.288 2,640.75 8,681.92 P&M-012
(iii) 1 Cum Capacity hour 6.923 1,112.00 7,698.46 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 720 x L 6.18 133,455.60 P&M-116
(ii) 14 cum capacity t.km 720 x L 7.01 151,476.48 P&M-119
(iii) 10 cum capacity t.km 720 x L 8.66 187,142.40 P&M-122
For loading & unloading time hour
(i) 18 cum capacity hour 2.229 2,883.30 6,426.88 P&M-014
(ii) 14 cum capacity hour 3.288 2,556.75 8,406.59 P&M-015
(iii) 10 cum capacity hour 6.923 2,274.30 15,744.98 P&M-016
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 3 km/hr )

(i) 16 KL capacity hour 13.536 1,501.00 20,317.54 P&M-023


(ii) 12 KL capacity hour 18.038 1,327.00 23,936.43 P&M-024
(iii) 6 KL capacity hour 36.106 1,005.00 36,286.53 P&M-025
c) Material
Material available from dismantled concrete slab
after crushing / breaking and only carriage is
required to be provided
Cost of water KL 57.600 57.600 57.600 16.00 921.60 921.60 921.60 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on 20,744.01 28,391.84 40,532.00
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 28,004.42 31,231.03 37,829.86
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 360 cum = a+b+c+d+e 308,048.60 343,541.30 416,128.51
Rate per cum = (a+b+c+d+e)/360 855.69 954.28 1,155.91
Say 856.00 954.00 1,156.00
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Note 1. It is assumed that dismantling of concrete
slab/pavement has been considered separately.
Hence same is not added in this analysis. Only
labour for crushing the dismantled slab into
aggregate has been added. Carriage from stock pile
to work site has been provided with a lead of L km.

2. In case of breaking of slabs is done locally without


involvement of transportation, the provision of tipper,
front end loader and loading/unloading charges may
be deleted.
3. As three wheeled smooth steel rollers are
commonly in use, the same has been provided as an
alternative.
4.13 405.2 Penetration Coat Over Top Layer of Crushed
Cement Concrete Base
Spraying of bitumen over cleaned dry surface of
crushed cement concrete base at the rate of 25 kg
per 10 sqm by a bitumen pressure distributor,
spreading of key aggregates at the rate of 0.13 cum
per 10 sqm by a mechanical gritter and rolling the
surface as per clause 506.3.8

Unit = sqm
Taking output = 7500 sqm
a) Labour
Mate day 0.560 0.560 0.560 617.00 345.52 345.52 345.52 L-12
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Mazdoor day 12.000 12.000 12.000 511.52 6,138.24 6,138.24 6,138.24 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.232 2.232 2.232 500.40 1,116.89 1,116.89 1,116.89 P&M-052
Hydraulic self propelled chips spreader hour 5.140 5.140 5.140 2,220.75 11,414.66 11,414.66 11,414.66 P&M-065
Front end loader 1 cum bucket capacity hour 6.000 6.000 6.000 1,112.00 6,672.00 6,672.00 6,672.00 P&M-013
Tipper 10 tonne capacity hour 6.000 6.000 6.000 1,731.45 10,388.70 10,388.70 10,388.70 P&M-017
Vibratory roller 8 -10 tonnes hour 5.140 5.140 5.140 2,562.00 13,168.68 13,168.68 13,168.68 P&M-022
Bitumen pressure distributor @ 1750 sqm per hour hour 4.280 4.280 4.280 1,729.35 7,401.62 7,401.62 7,401.62 P&M-053

c) Material
Crushed stone aggregate 11.2 mm size cum 97.500 97.500 97.500 1,887.12 183,994.50 183,994.50 183,994.50 M-040
Bitumen (60-70 grade) tonne 0.250 0.250 0.250 46,556.37 11,639.09 11,639.09 11,639.09 M-074
d) Overhead charges @ 8% on @ 10% on @ 12% on 20,272.91 25,341.14 30,409.36
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 27,368.43 27,875.25 28,382.07
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 7500 sqm = a+b+c+d+e 301,052.70 306,627.75 312,202.80
Rate per sqm = (a+b+c+d+e)/7500 40.14 40.88 41.63
Say 40.00 41.00 42.00
Note Though vibratory roller is required only for 3 hours as
per norms, the same is required to be available at
site for 6 hours to match with other machines. The
usage rates of vibratory roller may be multiplied with
a factor of 0.65.

4.14 406 A Wet Mix Macadam (Plant Mix Method)


Providing, laying, spreading and compacting graded
stone aggregate to wet mix macadam specification
including premixing the Material with water at OMC
in mechanical mix plant carriage of mixed Material
by tipper to site, laying in uniform layers with paver in
sub- base / base course on well prepared surface
and compacting with vibratory roller to achieve the
desired density.

Laying Using Mechanical Paver


Unit = cum
Taking output = 225 cum 495 tonne
a) Labour
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Machinery
Wet mix plant
(i) 250 tonne per hour hour 2.640 921.90 2,433.82 P&M-032
(ii) 200 tonne per hour hour 3.300 612.15 2,020.10 P&M-033
(iii) 100 tonne per hour hour 6.600 585.90 3,866.94 P&M-034
Electric generator
(i) 125 KVA hour 2.640 2,390.85 6,311.84 P&M-047
(ii) 100 KVA hour 3.300 2,041.20 6,735.96 P&M-048
(iii) 62.5 KVA hour 6.600 1,312.50 8,662.50 P&M-049
Front end loader for loading to Tipper
(i) 3.1 Cum Capacity hour 2.640 4,279.80 11,298.67 P&M-011
(ii) 2.1 Cum Capacity hour 3.300 2,640.75 8,714.48 P&M-012
(iii) 1 Cum Capacity hour 6.600 1,112.00 7,339.20 P&M-013
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Tipper
For Transportation
(i) 18 cum capacity t.km 495 x L2 6.18 3,058.36 P&M-116
(ii) 14 cum capacity t.km 495 x L2 7.01 3,471.34 P&M-119
(iii) 10 cum capacity t.km 495 x L2 8.66 4,288.68 P&M-122
For loading & unloading time hour
(i) 18 cum capacity hour 5.280 2,883.30 15,223.82 P&M-014
(ii) 14 cum capacity hour 6.600 2,556.75 16,874.55 P&M-015
(iii) 10 cum capacity hour 9.900 2,274.30 22,515.57 P&M-016
Mechanical Paver finisher hour 2.640 3.300 3.300 1,112.00 2,935.68 3,669.60 3,669.60 P&M-057
Vibratory roller hour 2.1120 2.640 2.640 2,562.00 5,410.94 6,763.68 6,763.68 P&M-022
c) Material
Close graded Granular sub-base Material as per
table 400-1
For Grading-I Material
45 mm to 22.4 mm@ 30 per cent cum 95.192 95.192 95.192 1,887.12 179,639.02 179,639.02 179,639.02 M-033
22.4 mm to 2.36 mm @ 40 per cent cum 126.923 126.923 126.923 1,887.12 239,519.33 239,519.33 239,519.33 M-030
2.36 mm to 75 micron@ 30 per cent cum 95.192 95.192 95.192 1,887.12 179,639.02 179,639.02 179,639.02 M-019
Cost of water KL 59.400 59.400 59.400 16.00 950.40 950.40 950.40 M-191
Rate per cum
d) Overhead charges @ 8% on @ 10% on @ 12% on 51,889.59 65,019.65 79,086.35
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 70,050.95 71,521.61 73,813.93
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 225 cum = a+b+c+d+e 770,560.46 786,737.74 811,953.24
Rate per cum = (a+b+c+d+e)/225 3,424.71 3,496.61 3,608.68
Say 3,425.00 3,497.00 3,609.00
4.14 406 B Wet Mix Macadam (Mix in place Method)
Providing, laying, spreading and compacting graded
stone aggregate to wet mix macadam specification
including premixing the Material with water at OMC
in mechanical mix plant carriage of mixed Material
by tipper to site, laying in uniform layers with grader
in sub- base / base course on well prepared surface
and compacting with vibratory roller to achieve the
desired density.

Laying Using Grader


Unit = cum
Taking output = 225 cum 495 tonne
a) Labour
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Machinery
Wet mix plant
(i) 250 tonne per hour hour 2.640 921.90 2,433.82 P&M-032
(ii) 200 tonne per hour hour 3.300 612.15 2,020.10 P&M-033
(iii) 100 tonne per hour hour 6.600 585.90 3,866.94 P&M-034
Electric generator
(i) 125 KVA hour 2.640 2,390.85 6,311.84 P&M-047
(ii) 100 KVA hour 3.300 2,041.20 6,735.96 P&M-048
(iii) 62.5 KVA hour 6.600 1,312.50 8,662.50 P&M-049
Front end loader for loading to Tipper
(i) 3.1 Cum Capacity hour 2.640 4,279.80 11,298.67 P&M-011
(ii) 2.1 Cum Capacity hour 3.300 2,640.75 8,714.48 P&M-012
(iii) 1 Cum Capacity hour 6.600 1,112.00 7,339.20 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 495 x L2 6.18 3,058.36 P&M-116
(ii) 14 cum capacity t.km 495 x L2 7.01 3,471.34 P&M-119
(iii) 10 cum capacity t.km 495 x L2 8.66 4,288.68 P&M-122
For loading & unloading time
(i) 18 cum capacity hour 2.640 2,883.30 7,611.91 P&M-014
(ii) 14 cum capacity hour 3.300 2,556.75 8,437.28 P&M-015
(iii) 10 cum capacity hour 6.600 2,274.30 15,010.38 P&M-016
Motor Grader
(i) Motor grader 4.30 metre blade hour 1.815 5,991.00 10,873.67 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.189 5,497.00 12,032.93 P&M-005
(iii) Motor grader 3.35 metre blade hour 2.441 4,796.00 11,707.04 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,730.27 3,730.27 3,730.27 P&M-022
c) Material
Close graded Granular sub-base Material as per
table 400-1
For Grading-I Material
45 mm to 22.4 mm@ 30 per cent cum 95.192 95.192 95.192 1,887.12 179,639.60 179,639.60 179,639.60 M-033
22.4 mm to 2.36 mm @ 40 per cent cum 126.923 126.923 126.923 1,887.12 239,519.47 239,519.47 239,519.47 M-030
2.36 mm to 75 micron@ 30 per cent cum 95.192 95.192 95.192 1,887.12 179,639.60 179,639.60 179,639.60 M-019
Cost of water KL 59.400 59.400 59.400 16.00 950.40 950.40 950.40 M-191
Rate per cum
d) Overhead charges @ 8% on @ 10% on @ 12% on 51,781.33 64,709.04 78,786.37
(a+b+c) (a+b+c) (a+b+c)
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
e) Contractor's profit @ 10% on @ 10% on @ 10% on 69,904.80 71,179.95 73,533.95
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 225 cum = a+b+c+d+e 768,952.75 782,979.42 808,873.41
Rate per cum = (a+b+c+d+e)/225 3,417.57 3,479.91 3,594.99
Say 3,418.00 3,480.00 3,595.00
Note 1. Though vibratory roller is required only for 3 hours
as per norms, the same is required to be available at
site for 6 hours to match with other machines. The
usage rates of vibratory roller may be multiplied with
a factor of 0.65
2. As three wheeled smooth steel rollers are
commonly in use, the same has been provided as an
alternative which can be used if the thickness of
individual layer does not exceed 100 mm..

4.15 406 Cement Treated Crushed Stone Base (Plant Mix


Method)
Providing, laying, spreading and compacting graded
stone aggregate mixed with cement to crushed stone
treated base specification including premixing the
Material with water at OMC in mechanical mix plant
carriage of mixed Material by tipper to site, laying in
uniform layers with paver in sub- base / base course
on well prepared surface and compacting with
vibratory roller to achieve the desired density.

Laying Using Mechanical Paver


Unit = cum
Taking output = 225 cum 495 tonne
a) Labour
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Machinery
Wet mix plant
(i) 250 tonne per hour hour 2.640 921.90 2,433.82 P&M-032
(ii) 200 tonne per hour hour 3.300 612.15 2,020.10 P&M-033
(iii) 100 tonne per hour hour 6.600 585.90 3,866.94 P&M-034
Electric generator
(i) 125 KVA hour 2.640 2,390.85 6,311.84 P&M-047
(ii) 100 KVA hour 3.300 2,041.20 6,735.96 P&M-048
(iii) 62.5 KVA hour 6.600 1,312.50 8,662.50 P&M-049
Front end loader for loading to Tipper
(i) 3.1 Cum Capacity hour 2.640 4,279.80 11,298.67 P&M-011
(ii) 2.1 Cum Capacity hour 3.300 2,640.75 8,714.48 P&M-012
(iii) 1 Cum Capacity hour 6.600 1,112.00 7,339.20 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 495 x L2 6.18 3,058.36 P&M-116
(ii) 14 cum capacity t.km 495 x L2 7.01 3,471.34 P&M-119
(iii) 10 cum capacity t.km 495 x L2 8.66 4,288.68 P&M-122
For loading & unloading time
(i) 18 cum capacity hour 5.280 2,883.30 15,223.82 P&M-014
(ii) 14 cum capacity hour 5.940 2,556.75 15,187.10 P&M-015
(iii) 10 cum capacity hour 9.240 2,274.30 21,014.53 P&M-016
Vibratory roller hour 2.112 2.112 2.112 2,562.00 5,410.94 5,410.94 5,410.94 P&M-022
Mechanical Paver finisher hour 2.460 2.460 2.460 1,112.00 2,735.52 2,735.52 2,735.52 P&M-057
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )

(i) 16 KL capacity hour 0.722xL1+1. 1,501.00 35,112.89 P&M-023


733
(ii) 12 KL capacity hour 0.963xL1+2.3 1,327.00 41,402.40 P&M-024
1
(iii) 6 KL capacity hour 1.925xL1+4. 1,005.00 62,681.85 P&M-025
62
c) Material
Close graded Granular sub-base Material as per
table 400-1
For Grading-I Material
45 mm to 22.4 mm@ 30 per cent cum 95.192 95.192 95.192 1,887.12 179,639.02 179,639.02 179,639.02 M-033
22.4 mm to 2.36 mm @ 40 per cent cum 126.923 126.923 126.923 1,887.12 239,519.33 239,519.33 239,519.33 M-030
2.36 mm to 75 micron@ 30 per cent cum 95.192 95.192 95.192 1,887.12 179,639.02 179,639.02 179,639.02 M-021
Cost of cement @ 4% Tonne 19.800 19.800 19.800 4,940.00 97,812.00 97,812.00 97,812.00 M-081
Cost of water KL 163.350 163.350 163.350 16.00 2,613.60 2,613.60 2,613.60 M-191

d) Overhead charges @ 8% on @ 10% on @ 12% on 62,640.63 78,709.98 98,090.66


(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 84,564.85 86,580.98 91,551.28
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 225 cum = a+b+c+d+e 930,213.33 952,390.77 1,007,064.09
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Rate per cum = (a+b+c+d+e)/225 4,134.28 4,232.85 4,475.84
Say 4,134.00 4,233.00 4,476.00
4.16 408 Construction of Median and Island with Soil Taken
from Roadway Cutting
Construction of Median and Island above road level
with approved material deposited at site from
roadway cutting and excavation for drain and
foundation of other structures, spread, graded and
compacted as per clause 408

Unit = cum
Taking output = 21 cum 46.2 tonne

a) Labour
Mate day 0.240 0.240 0.240 617.00 148.08 148.08 148.08 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
b) Machinery
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )

(i) 16 KL capacity hour 0.018xL1+0. 1,501.00 816.54 P&M-023


004
(ii) 12 KL capacity hour 0.023xL1+0.0 1,327.00 922.27 P&M-024
05
(iii) 6 KL capacity hour 0.047xL1+0. 1,005.00 1,427.10 P&M-025
001
Plate compactor @ 3.5 cum per hour hour 6.000 6.000 6.000 597.45 3,584.70 3,584.70 3,584.70 P&M-079
c) Material
Cost of water KL 2.520 2.520 2.520 16.00 40.32 40.32 40.32 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on 612.70 776.45 992.32
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 827.15 854.09 926.16
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 21 cum = a+b+c+d+e 9,098.61 9,395.03 10,187.80
Rate per cum = (a+b+c+d+e)/21 433.27 447.38 485.13
Say 433.00 447.00 485.00
Note This analysis provides for median and island with
earthen top. In case the surface is required to be
turfed or planted with shrubs, the same is required to
be provided separately as per analysis given in the
chapter on horticulture. In case granular fill is
required to be paved, quantities of paving are
required to be calculated as per approved design
and paid separately.

4.17 408 Construction of Median and Island with Soil Taken


from Borrow Areas
Construction of median and Island above road level
with approved material brought from borrow pits,
spread, sloped and compacted as per clause 408

Unit = cum
Taking output = 21 cum 31.5 tonne

a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 0.236 3,420.00 807.12 P&M-007
(ii) 1.1 cum bucket capacity hour 0.271 3,074.00 833.05 P&M-008
(iii) 0.9 cum bucket capacity hour 0.379 2,782.00 1,054.38 P&M-009
Tipper
For Transportation
(i) 18 cum capacity t.km 31.5 x L2 6.18 194.62 P&M-116
(ii) 14 cum capacity t.km 31.5 x L2 7.01 220.90 P&M-119
(iii) 10 cum capacity t.km 31.5 x L2 8.66 272.92 P&M-122
For loading & unloading time
(i) 18 cum capacity hour 0.236 2,883.30 680.46 P&M-014
(ii) 14 cum capacity hour 0.271 2,556.75 692.88 P&M-015
(iii) 10 cum capacity hour 0.379 2,274.30 861.96 P&M-016
Water tanker (speed @ 20km/hr and return speed
@ 30 km/hr and spreading speed @ 2.5 km/hr )

(i) 16 KL capacity hour 0.018xL1+0. 1,501.00 813.54 P&M-023


002
(ii) 12 KL capacity hour 0.023xL1+0.0 1,327.00 919.61 P&M-024
03
(iii) 6 KL capacity hour 0.047xL1+0. 1,005.00 1,423.08 P&M-025
006
Plate compactor hour 1.400 1.400 1.400 597.45 836.43 836.43 836.43 P&M-079
c) Material
Compensation for earth taken from private land cum 21.000 21.000 21.000 45.00 945.00 945.00 945.00 M-093
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Cost of water KL 2.520 2.520 2.520 16.00 40.32 40.32 40.32 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on 431.19 556.06 780.78
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 582.11 611.67 728.73
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 21 cum = a+b+c+d+e 6,403.19 6,728.32 8,015.99
Rate per cum = (a+b+c+d+e)/21 304.91 320.40 381.71
Say 305.00 320.00 382.00
Note This analysis provides for median and island with
earthen top. In case the surface is required to be
turfed or planted with shrubs, the same is required to
be provided separately as per analysis given in the
chapter on horticulture. In case surface finish is of
hard type, the same may be provided separately as
per approved design.

4.18 408 Construction of Shoulders


A. Earthen Shoulders
The rate as applicable for sub-grade construction
may be adopted.
B. Hard Shoulders
Rate as applicable for sub-base and or base may be
adopted as per approved design.
C. Paved shoulders
The rate may be adopted as applicable for different
layers of pavement depending upon approved
design of paved shoulders.
4.19 410 Footpaths and Separators
Construction of footpath/separator by providing a
150 mm compacted granular sub base as per clause
401 and 25 mm thick cement concrete grade M15,
over laid with pre-cast concrete tiles in cement
mortar 1:3 including provision of all drainage
arrangements but excluding kerb channel..

Unit = sqm
Taking output = 300 sqm
a) Labour
Mate day 1.360 1.360 1.360 617.00 839.12 839.12 839.12 L-12
Mason day 4.000 4.000 4.000 738.00 2,952.00 2,952.00 2,952.00 L-11
Mazdoor day 30.000 30.000 30.000 511.52 15,345.60 15,345.60 15,345.60 L-13
b) Machinery
Vibratory roller hour 0.750 0.750 0.750 2,562.00 1,921.50 1,921.50 1,921.50 P&M-022
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and spreading speed @ 2.5 km/hr )

(i) 16 KL capacity hour 0.083xL1+0. 1,501.00 3,797.53 P&M-023


04
(ii) 12 KL capacity hour 0.111xL1+0.0 1,327.00 4,489.24 P&M-024
53
(iii) 6 KL capacity hour 0.222xL1+0. 1,005.00 6,800.84 P&M-025
107
Concrete mixer 0.4/0.28 cum per hour hour 6.000 6.000 6.000 511.35 3,068.10 3,068.10 3,068.10 P&M-041
c) Material
i) For Granular sub base material
53 mm to 26.5 mm @ 35 per cent cum 20.790 20.790 20.790 1,887.12 39,233.29 39,233.29 39,233.29 M-028
26.5 mm to 4.75 mm @ 45 per cent cum 26.730 26.730 26.730 1,887.12 50,442.80 50,442.80 50,442.80 M-025
2.36 mm below @ 20 per cent cum 11.880 11.880 11.880 1,887.12 22,419.02 22,419.02 22,419.02 M-019
ii) For cement concrete grade M15 7.5 cum
Aggregate 12 mm crushed @ 0.9 cum of concrete cum 6.750 6.750 6.750 1,887.12 12,738.08 12,738.08 12,738.08 M-051

Sand @ 0.45 cum/cum of concrete cum 3.380 3.380 3.380 1,994.03 6,739.82 6,739.82 6,739.82 M-005
Cement tonne 1.880 1.880 1.880 4,940.00 9,287.20 9,287.20 9,287.20 M-081
iii) For cement plaster 1:3
Sand cum 3.840 3.840 3.840 1,994.03 7,657.08 7,657.08 7,657.08 M-005
Cement tonne 1.830 1.830 1.830 4,940.00 9,040.20 9,040.20 9,040.20 M-081
iv) Pre-cast cement concrete tiles
Tiles size 300 x 300 mm and 25 mm thick each 3300.000 3300.000 3300.000 33.15 109,395.00 109,395.00 109,395.00 M-186
v) RCC pipes
Pipes 200 mm dia,2.5 m long for drainage metre 22.500 22.500 22.500 168.19 3,784.25 3,784.25 3,784.25 M-136
vi) Cost of water KL 12.000 12.000 12.000 16.00 192.00 192.00 192.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on 23,908.21 29,954.43 36,222.71
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 32,276.08 32,949.87 33,807.86
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 300 sqm = a+b+c+d+e 355,036.89 362,448.62 371,886.47
Rate per sqm = (a+b+c+d+e)/300 1,183.46 1,208.16 1,239.62
Say 1,183.00 1,208.00 1,240.00
4.20 410 Crusher Run Macadam Base
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Providing crushed stone aggregate, depositing on a
prepared surface by hauling vehicles, spreading and
mixing with a motor grader, watering and compacting
with a vibratory roller to clause 417 to form a layer of
sub-base/Base

Unit = cum
Taking output = 360 cum 720 tonne
A By Mix in Place Method
a) Labour
Mate day 0.480 0.480 0.480 617.00 296.16 296.16 296.16 L-12
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Mazdoor day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-13
b) Machinery
Tractor attached with rotavator @ 25 cum per hour

P&M-026
hour 12.000 12.000 12.000 1,915.35 22,984.20 22,984.20 22,984.20 +P&M-027
+P&M-028

Front end loader for mixing at stock pile location

(i) 3.1 Cum Capacity hour 6.429 4,279.80 27,513.00 P&M-011


(ii) 2.1 Cum Capacity hour 9.474 2,640.75 25,017.63 P&M-012
(iii) 1 Cum Capacity hour 20.000 1,112.00 22,240.00 P&M-013
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.903 5,991.00 17,393.23 P&M-004
(ii) Motor grader 3.70 metre blade hour 3.502 5,497.00 19,250.19 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.905 4,796.00 18,727.46 P&M-006
Vibratory roller hour 2.330 2.330 2.330 2,562.00 5,969.71 5,969.71 5,969.71 P&M-022
or
Smooth 3 wheeled steel roller hour 4.660 4.660 4.660
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )

(i) 16 KL capacity hour 8.460 1,501.00 12,698.46 P&M-023


(ii) 12 KL capacity hour 11.270 1,327.00 14,955.29 P&M-024
(iii) 6 KL capacity hour 22.570 1,005.00 22,682.85 P&M-025
c) Material
i) For 53 mm maximum size
63 mm to 45 mm @ 33 per cent cum 157.460 157.460 157.460 1,887.12 297,146.40 297,146.40 297,146.40 M-037
22.5 mm to 5.6 mm@ 32 per cent cum 151.060 151.060 151.060 1,887.12 285,068.82 285,068.82 285,068.82 M-031
Below 5.6 mm @ 35 per cent cum 166.680 166.680 166.680 1,887.12 314,545.68 314,545.68 314,545.68 M-029
Cost of water KL 36.000 36.000 36.000 16.00 576.00 576.00 576.00 M-191
Or
ii) For 45 mm maximum size
45 mm to 22.5 mm@ 5 per cent cum 24.120 24.120 24.120 1,887.12 45,517.41 45,517.41 45,517.41 M-047
22.4 mm to 5.6 mm@ 50 per cent cum 237.600 237.600 237.600 1,887.12 448,380.45 448,380.45 448,380.45 M-031
Below 5.6 mm@ 45 per cent cum 213.480 213.480 213.480 1,887.12 402,863.04 402,863.04 402,863.04 M-029
Cost of water KL 36.000 36.000 36.000 16.00 576.00 576.00 576.00 M-191
4.20 A (i) For 53 mm maximum size

d) Overhead charges @ 8% on @ 10% on @ 12% on 79,235.07 99,205.67 119,578.07


(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 106,967.34 109,126.24 111,606.20
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 360.0cum = a+b+c+d+e 1,176,640.72 1,200,388.66 1,227,668.21
Rate per cum = (a+b+c+d+e)/360 3,268.45 3,334.41 3,410.19
or Say 3,268.00 3,334.00 3,410.00
4.20 A (ii) For 45 mm maximum size

d) Overhead charges @ 8% on @ 10% on @ 12% on 79,235.07 99,205.67 119,578.07


(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 106,967.34 109,126.24 111,606.20
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 360.0cum = a+b+c+d+e 1,176,640.72 1,200,388.66 1,227,668.21
Rate per cum = (a+b+c+d+e)/360 3,268.45 3,334.41 3,410.19
Say 3,268.00 3,334.00 3,410.00
Note Any one of the aggregate grading may be adopted

4.20 B By Mixing Plant :


Unit = cum
Taking output = 225 Cum 450 tonne
a) Labour
Mate day 0.280 0.280 0.280 617.00 172.76 172.76 172.76 L-12
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
b) Machinery
Wet mix plant
(i) 250 tonne per hour hour 2.400 921.90 2,212.56 P&M-032
(ii) 200 tonne per hour hour 3.000 612.15 1,836.45 P&M-033
(iii) 100 tonne per hour hour 6.000 585.90 3,515.40 P&M-034
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Electric generator
(i) 125 KVA hour 2.400 2,390.85 5,738.04 P&M-047
(ii) 100 KVA hour 3.000 2,041.20 6,123.60 P&M-048
(iii) 62.5 KVA hour 6.000 1,312.50 7,875.00 P&M-049
Front end loader for loading to Tipper
(i) 3.1 Cum Capacity hour 2.400 4,279.80 10,271.52 P&M-011
(ii) 2.1 Cum Capacity hour 3.000 2,640.75 7,922.25 P&M-012
(iii) 1 Cum Capacity hour 6.000 1,112.00 6,672.00 P&M-013
Motor Grader
(i) Motor grader 4.30 metre blade hour 1.815 5,991.00 10,873.67 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.189 5,497.00 12,032.93 P&M-005
(iii) Motor grader 3.35 metre blade hour 2.441 4,796.00 11,707.04 P&M-006
Vibratory roller hour 2.400 2.400 2.400 2,562.00 6,148.80 6,148.80 6,148.80 P&M-022
Water tanker (speed @ 20km/hr and return speed
@ 30 km/hr and spreading speed @ 3.0 km/hr )

(i) 16 KL capacity hour 0.125xL1+0. 1,501.00 6,079.05 P&M-023


3
(ii) 12 KL capacity hour 0.167xL1+0.4 1,327.00 7,179.07 P&M-024

(iii) 6 KL capacity hour 0.333xL1+0. 1,005.00 10,843.95 P&M-025


8
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L2 6.18 2,780.33 P&M-116
(ii) 14 cum capacity t.km 450 x L2 7.01 3,155.76 P&M-119
(iii) 10 cum capacity t.km 450 x L2 8.66 3,898.80 P&M-122
For loading & unloading time
(i) 18 cum capacity hour 2.400 2,883.30 6,919.92 P&M-014
(ii) 14 cum capacity hour 3.000 2,556.75 7,670.25 P&M-015
(iii) 10 cum capacity hour 6.000 2,274.30 13,645.80 P&M-016
c) Material
Aggregate at site
i) For 53 mm maximum size
63 mm to 45 mm @ 33 per cent cum 98.400 98.400 98.400 1,887.12 185,692.91 185,692.91 185,692.91 M-037
22.5 mm to 5.6 mm@ 32 per cent cum 94.410 94.410 94.410 1,887.12 178,163.29 178,163.29 178,163.29 M-031
Below 5.6 mm @ 35 per cent cum 104.180 104.180 104.180 1,887.12 196,600.49 196,600.49 196,600.49 M-029
Cost of water KL 18.000 18.000 18.000 16.00 288.00 288.00 288.00 M-191
Or
ii) For 37.5 mm maximum size
45 mm to 22.5 mm@ 5 per cent cum 15.060 15.060 15.060 1,887.12 28,420.07 28,420.07 28,420.07 M-033
22.4 mm to 5.6 mm@ 50 per cent cum 148.500 148.500 148.500 1,887.12 280,237.78 280,237.78 280,237.78 M-031
Below 5.6 mm@ 45 per cent cum 133.430 133.430 133.430 1,887.12 251,798.84 251,798.84 251,798.84 M-029
Cost of water KL 18.000 18.000 18.000 16.00 288.00 288.00 288.00 M-191
4.20 B (i) For 53 mm maximum size

d) Overhead charges @ 8% on @ 10% on @ 12% on 49,246.09 61,662.14 75,463.09


(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 66,482.23 67,828.36 70,432.22
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 225cum = a+b+c+d+e 731,304.50 746,111.91 774,754.40
Rate per cum = (a+b+c+d+e)/225 3,250.24 3,316.05 3,443.35
Say 3,250.00 3,316.00 3,443.00
4.20 B (ii) For 37.5 mm maximum size

d) Overhead charges @ 8% on @ 10% on @ 12% on 49,246.09 61,662.14 75,463.09


(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 66,482.23 67,828.36 70,432.22
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 360.0cum = a+b+c+d+e 731,304.50 746,111.91 774,754.40
Rate per cum = (a+b+c+d+e)/360 3,250.24 3,316.05 3,443.35
Say 3,250.00 3,316.00 3,443.00
4.21 Suggestive Lime, Flyash Stabilised Soil Sub-Base

Construction of Sub-base using lime - Flyash


admixture with granular soil, free from organic
matter/ deleterious material or clayey silts and low
plasticity clays having PI between 5 and 20 and
liquid limit less than 25 and commercial dry lime,
slaked at site or pre-slaked with CaO content not
less than 50 per cent, Flyash to conform to gradation
as per clause 4.3 of IRC: 88-1984, lime + Flyash
content ranging between 10 to 30 per cent, the
minimum un-confined compressive strength and
CBR value after 28 days curing and 4 days soaking
to be 7.5kg/sq, cm and 25 per cent respectively, all
as specified in IRC: 88-1984.

Unit = cum
Taking output = 480 cum (720 tonne, density 1.50
t/cum)
Assumptions made
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Total mass taken for analysis = 720 t 720.00 Tonne
Lime + Flyash admixture @ 20 per cent = 0.2 x
720=144 t
Soil = 720 -144 = 576 t 576.00 Tonne
576 /1.6 = 360 cum 360.00 Cum
Lime + Flyash = 144 t 144.00 Tonne
Ratio Lime 4 : Flyash 16 49.40 Cum
Lime = 29 t 409.40 Cum
Flyash = 115 t
a) Labour
Mate day 0.280 0.280 0.280 617.00 172.76 172.76 172.76 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 4.038 3,420.00 13,810.29 P&M-007
(ii) 1.1 cum bucket capacity hour 4.650 3,074.00 14,295.61 P&M-008
(iii) 0.9 cum bucket capacity hour 6.502 2,782.00 18,087.42 P&M-009
Tipper
For transportation
(i) 18 cum capacity t.km 720 x L1 6.18 133,455.60 P&M-116
(ii) 14 cum capacity t.km 720 x L1 7.01 151,476.48 P&M-119
(iii) 10 cum capacity t.km 720 x L1 8.66 187,142.40 P&M-122
For Loading & unloading time
(i) 18 cum capacity hour 4.038 2,883.30 11,642.77 P&M-014
(ii) 14 cum capacity hour 4.650 2,556.75 11,888.89 P&M-015
(iii) 10 cum capacity hour 6.502 2,274.30 14,787.50 P&M-016

Tractor with disc harrows for pulverisation hour 6.000 6.000 6.000 1,876.50 11,259.00 11,259.00 11,259.00 P&M-026
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 3.302 5,991.00 19,782.28 P&M-004
(ii) Motor grader 3.70 metre blade hour 3.982 5,497.00 21,889.05 P&M-005
(iii) Motor grader 3.35 metre blade hour 4.441 4,796.00 21,299.04 P&M-006
Vibratory roller hour 6.000 6.000 6.000 2,562.00 15,372.00 15,372.00 15,372.00 P&M-022
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and spreading speed @ 2.5 km/hr )

(i) 16 KL capacity hour 0.3xL1+1.57 1,501.00 15,868.57 P&M-023


2
(ii) 12 KL capacity hour 0.4xL1+2.096 1,327.00 18,705.39 P&M-024

(iii) 6 KL capacity hour 0.8xL1+4.19 1,005.00 28,332.96 P&M-025


2
c) Material
Slaked Lime tonne 29.000 29.000 29.000 3,753.00 108,837.00 108,837.00 108,837.00 M-190
Compensation for earth taken from private source cum 360.000 360.000 360.000 45.00 16,200.00 16,200.00 16,200.00 M-093

Cost of water (considering 5% additional moisture KL 43.200 43.200 43.200 16.00 691.20 691.20 691.20 M-191
required)
d) Overhead charges @ 8% on @ 10% on @ 12% on 28,058.11 37,442.22 51,097.93
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 37,878.44 41,186.45 47,691.41
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 480 cum = a+b+c+d+e 416,662.86 453,050.90 524,605.46
Rate per cum= (a+b+c+d+e)/480 868.05 943.86 1,092.93
Say 868.00 944.00 1,093.00
Note 1.Compensation for earth will vary from place to
place and will have to be assessed realistically as
per particular ground situation. In case earth is
available from Govt. land, compensation for earth
will not be required. The position is required to be
clearly stated in the cost estimate.

2.Cost of Flyash has not been considered as same


will be available free of cost. Only carriage of Flyash
has been provided.
3.Lime + Flyash has been taken as 20 per cent of
total mass and ratio of lime and Flyash as 1:4 for
estimating purposes. Total quantities will be as per
approved design.
CHAPTER-5
BASES AND SURFACE COURSES (BITUMINOUS)
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
5.01 502 A Prime Coat over WMM/WBM
(i) Providing and applying primer coat with SS1 grade
bitumen emulsion on prepared surface of granular Base
including clearing of road surface and spraying primer at
the rate of 0.70 to 1.00 kg/sqm using mechanical means.

Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.083 2.083 2.083 500.40 1,042.33 1,042.33 1,042.33 P&M-052
Air compressor 250 cfm hour 2.083 2.083 2.083 614.25 1,279.48 1,279.48 1,279.48 P&M-029
Bitumen pressure distributor (Spraying width 4.5 m) P&M-053
hour 1.944 1.944 1.944 1,729.35 3,361.86 3,361.86 3,361.86
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 2.803 1,501.00 4,207.30 P&M-023
(ii) 12 KL capacity hour 3.727 1,327.00 4,945.73 P&M-024
(iii) 6 KL capacity hour 7.453 1,005.00 7,490.27 P&M-025
c) Material
SS1 grade Bitumen emulsion @ 0.85 kg per sqm tonne 4.900 4.900 4.900 47,662.37 233,545.62 233,545.62 233,545.62 M-077
Cost of water KL 10.500 10.500 10.500 16.00 168.00 168.00 168.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
19,574.16 24,541.54 29,755.19
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
26,425.12 26,995.70 27,771.51
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 7000 Sqm = a+b+c+d+e 290,676.27 296,952.66 305,486.66
Rate per Sqm = (a+b+c+d+e)/7000 41.53 42.42 43.64
Say 42.00 42.00 44.00
Note Bitumen primer has been provided @ 0.85 kg per sqm as
per clause 502.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and the actual quantity approved by the
Engineer after the preliminary trials referred to in clause
No. 502.4.3.

(ii) Providing and applying primer coat with cutback MC 30


bitumen emulsion on prepared surface of granular Base
including clearing of road surface and spraying primer at
the rate of 0.60 to 0.90 kg/sqm using mechanical means.

Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.083 2.083 2.083 500.40 1,042.50 1,042.50 1,042.50 P&M-052
Air compressor 250 cfm hour 2.083 2.083 2.083 614.25 1,279.69 1,279.69 1,279.69 P&M-029
Bitumen pressure distributor (Spraying width 4.5 m) hour 1.944 1.944 1.944 1,729.35 3,362.63 3,362.63 3,362.63 P&M-053
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity 0.073xL1+0.6 P&M-023
hour 1,501.00 4,207.30
13
(ii) 12 KL capacity 0.097xL1+0.81 P&M-024
hour 1,327.00 4,945.73
7
(iii) 6 KL capacity 0.194xL1+1.6 P&M-025
hour 1,005.00 7,490.27
33
c) Material
Cutback Bitumen MC 30 @ 0.6 kg per sqm tonne 4.200 4.200 4.200 46,556.37 195,536.76 195,536.76 195,536.76 M-076
Cost of water KL 10.500 10.500 10.500 16.00 168.00 168.00 168.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
16,533.54 20,740.77 25,194.27
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
22,320.28 22,814.85 23,514.65
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 7000 Sqm = a+b+c+d+e 245,523.10 250,963.32 258,661.15
Rate per Sqm = (a+b+c+d+e)/7000 35.07 35.85 36.95
Say 35.00 36.00 37.00
Note Bitumen primer has been provided @ 0.75 kg per sqm as
per clause 502.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and the actual quantity approved by the
Engineer after the preliminary trials referred to in clause
No. 502.4.3.

5.01 502 B Prime Coat over Stabilized soil bases/Crusher Run


Macadam
(i) Providing and applying primer coat with SS1 grade
bitumen emulsion on prepared surface of granular Base
including clearing of road surface and spraying primer at
the rate of 0.90 to 1.20 kg/sqm using mechanical means.

Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.083 2.083 2.083 500.40 1,042.33 1,042.33 1,042.33 P&M-052
Air compressor 250 cfm hour 2.083 2.083 2.083 614.25 1,279.48 1,279.48 1,279.48 P&M-029
Bitumen pressure distributor (Spraying width 4.5 m) hour 1.944 1.944 1.944 1,729.35 3,361.86 3,361.86 3,361.86 P&M-053
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity 0.073xL1+0.6 P&M-023
hour 1,501.00 4,207.30
13
(ii) 12 KL capacity 0.097xL1+0.81 P&M-024
hour 1,327.00 4,945.73
7
(iii) 6 KL capacity 0.194xL1+1.6 P&M-025
hour 1,005.00 7,490.27
33
c) Material
SS1 grade Bitumen emulsion @ 0.9 kg per sqm tonne 6.300 6.300 6.300 47,662.37 300,272.94 300,272.94 300,272.94 M-077
Cost of water KL 10.500 10.500 10.500 16.00 168.00 168.00 168.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
24,912.35 31,214.27 37,762.47
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
33,631.67 34,335.70 35,244.97
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 7000 Sqm = a+b+c+d+e 369,948.32 377,692.71 387,694.72
Rate per Sqm = (a+b+c+d+e)/7000 52.85 53.96 55.38
Say 53.00 54.00 55.00
Note Bitumen primer has been provided @ 1.05 kg per sqm as
per clause 502.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and the actual quantity approved by the
Engineer after the preliminary trials referred to in clause
No. 502.4.3.

(ii) Providing and applying primer coat with cutback MC 70


bitumen emulsion on prepared surface of granular Base
including clearing of road surface and spraying primer at
the rate of 0.90 to 1.20 kg/sqm using mechanical means.

Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.083 2.083 2.083 500.40 1,042.50 1,042.50 1,042.50 P&M-052
Air compressor 250 cfm hour 2.083 2.083 2.083 614.25 1,279.69 1,279.69 1,279.69 P&M-029
Bitumen pressure distributor (Spraying width 4.5 m) P&M-053
hour 1.944 1.944 1.944 1,729.35 3,362.63 3,362.63 3,362.63
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity 0.073xL1+0.6 P&M-023
hour 1,501.00 4,207.30
13
(ii) 12 KL capacity 0.097xL1+0.81 P&M-024
hour 1,327.00 4,945.73
7
(iii) 6 KL capacity 0.194xL1+1.6 P&M-025
hour 1,005.00 7,490.27
33
c) Material
Cutback Bitumen MC 70 @ 0.9 kg per sqm tonne 6.300 6.300 6.300 46,556.37 293,305.14 293,305.14 293,305.14 M-076
Cost of water KL 10.500 10.500 10.500 16.00 168.00 168.00 168.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
24,355.01 30,517.61 36,926.47
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
32,879.27 33,569.37 34,464.71
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 7000 Sqm = a+b+c+d+e 361,671.93 369,263.06 379,111.80
Rate per Sqm = (a+b+c+d+e)/7000 51.67 52.75 54.16
Say 52.00 53.00 54.00
Note Bitumen primer has been provided @ 1.05 kg per sqm as
per clause 502.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and the actual quantity approved by the
Engineer after the preliminary trials referred to in clause
No. 502.4.3.

5.02 503 (i) Tack Coat on Bituminous surfaces


Providing and applying tack coat with bitumen emulsion
using emulsion pressure distributor at the rate of 0.20 to
0.30 kg per sqm on the prepared bituminous surface
cleaned with mechanical broom.

Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.083 2.083 2.083 500.40 1,042.33 1,042.33 1,042.33 P&M-052
Air compressor 250 cfm hour 2.083 2.083 2.083 614.25 1,279.48 1,279.48 1,279.48 P&M-029
Emulsion Pressure Distributor (Spraying width 4.5 m) P&M-054
hour 1.944 1.944 1.944 1,112.00 2,161.73 2,161.73 2,161.73
c) Material
Bitumen emulsion @ 0.22 kg per sqm tonne 1.400 1.400 1.400 47,662.37 66,727.32 66,727.32 66,727.32 M-077
d) Overhead charges @ 8% on @ 10% on @ 12% on
5,782.66 7,228.33 8,673.99
(a+b+c) (a+b+c) (a+b+c)
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
e) Contractor's profit @ 10% on @ 10% on @ 10% on
7,806.59 7,951.16 8,095.73
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 7000 Sqm = a+b+c+d+e 85,872.52 87,462.75 89,052.98
Rate per Sqm = (a+b+c+d+e)/7000 12.27 12.49 12.72
Say 12.00 12.00 13.00
Note 1. Bitumen emulsion has been provided @ 0.25 kg per
sqm as per clause 503.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and actual quantity approved by the Engineer
after preliminary trials referred to in clause No. 503.4.3

5.02 503 (ii) Tack Coat on Granular surfaces treated with primer

Providing and applying tack coat with bitumen emulsion


using emulsion pressure distributor at the rate of 0.25 to
0.30 kg per sqm on the prepared bituminous surface
cleaned with mechanical broom.

Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.083 2.083 2.083 500.40 1,042.33 1,042.33 1,042.33 P&M-052
Air compressor 250 cfm hour 2.083 2.083 2.083 614.25 1,279.48 1,279.48 1,279.48 P&M-029
Emulsion Pressure Distributor (Spraying width 4.5 m) P&M-054
hour 1.944 1.944 1.944 1,112.00 2,161.73 2,161.73 2,161.73
c) Material
Bitumen emulsion @ 0.25 kg per sqm tonne 1.750 1.750 1.750 47,662.37 83,409.15 83,409.15 83,409.15 M-077
d) Overhead charges @ 8% on @ 10% on @ 12% on
7,117.21 8,896.51 10,675.81
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
9,608.23 9,786.16 9,964.09
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 7000 Sqm = a+b+c+d+e 105,690.53 107,647.76 109,604.99
Rate per Sqm = (a+b+c+d+e)/7000 15.10 15.38 15.66
Say 15.00 15.00 16.00
Note 1. Bitumen emulsion has been provided @ 0.275 kg per
sqm as per clause 503.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and actual quantity approved by the Engineer
after preliminary trials referred to in clause No. 503.4.3

2. An output of 7000 sqm has been considered in case of


prime coat and tack coat which can be covered by
bituminous courses on the same day.
5.02 503 (iii) Tack Coat on Cement concrete pavement
Providing and applying tack coat with bitumen emulsion
using emulsion pressure distributor at the rate of 0.30 to
0.35 kg per sqm on the prepared bituminous surface
cleaned with mechanical broom.

Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.083 2.083 2.083 500.40 1,042.33 1,042.33 1,042.33 P&M-052
Air compressor 250 cfm hour 2.083 2.083 2.083 614.25 1,279.48 1,279.48 1,279.48 P&M-029
Emulsion Pressure Distributor (Spraying width 4.5 m) P&M-054
hour 1.944 1.944 1.944 1,112.00 2,161.73 2,161.73 2,161.73
c) Material
Bitumen emulsion @ 0.3 kg per sqm tonne 2.100 2.100 2.100 47,662.37 100,090.98 100,090.98 100,090.98 M-077
d) Overhead charges @ 8% on @ 10% on @ 12% on
8,451.75 10,564.69 12,677.63
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
11,409.87 11,621.16 11,832.46
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 7000 Sqm = a+b+c+d+e 125,508.54 127,832.78 130,157.01
Rate per Sqm = (a+b+c+d+e)/7000 17.93 18.26 18.59
Say 18.00 18.00 19.00
Note 1. Bitumen emulsion has been provided @ 0.325 kg per
sqm as per clause 503.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and actual quantity approved by the Engineer
after preliminary trials referred to in clause No. 503.4.3

2. An output of 7000 sqm has been considered in case of


prime coat and tack coat which can be covered by
bituminous courses on the same day.
5.03 504 (i) Bituminous Macadam Grading - I
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Providing and laying bituminous macadam with higher
capacity hot mix plant using crushed aggregates of
specified grading premixed with bituminous binder,
transported to site, laid over a previously prepared
surface with paver finisher to the required grade, level
and alignment and rolled as per clauses 501.6 and 501.7
to achieve the desired compaction

Unit = cum
Taking output = 205 cum 451.00 tonnes
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Batch Type Hot Mix Plant
(i) HMP 200 TPH hour 3.007 14,634.90 44,007.14 P&M-035
(ii) HMP 160 TPH hour 3.758 10,338.30 38,851.33 P&M-036
(iii) HMP 120 TPH hour 5.011 8,372.70 41,955.60 P&M-037
Mechanical broom (2.1m sweeping width) hour 0.697 0.697 0.697 500.40 348.78 348.78 348.78 P&M-052
Air compressor 250 cfm hour 0.697 0.697 0.697 614.25 428.13 428.13 428.13 P&M-029
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.007 9,233.70 27,765.74 P&M-058
(ii) Paver (240HP) hour 3.758 9,233.70 34,700.24 P&M-058
(iii) Paver (174HP) hour 5.011 2,362.50 11,838.49 P&M-059
Electric generator
(i) 500 KVA hour 3.007 8,022.00 24,122.15 P&M-044
(ii) 400 KVA hour 3.758 6,470.10 24,314.64 P&M-045
(iii) 250 KVA hour 5.011 3,475.00 17,413.23 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 4.618 4,279.80 19,764.12 P&M-011
(ii) 2.1 Cum Capacity hour 6.826 2,640.75 18,025.76 P&M-012
(iii) 1 Cum Capacity hour 14.273 1,112.00 15,871.58 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 451 x L1 6.18 83,595.11 P&M-116
(ii) 14 cum capacity t.km 451 x L1 7.01 94,883.18 P&M-119
(iii) 10 cum capacity t.km 451 x L1 8.66 117,223.92 P&M-122
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.014 2,883.30 17,340.17 P&M-014
(ii) 14 cum capacity hour 7.516 2,556.75 19,216.53 P&M-015
(iii) 10 cum capacity hour 10.022 2,274.30 22,793.03 P&M-016
Smooth steel wheeled tandem roller for static and P&M-020
vibratory passaes hour 7.256 7.256 7.256 1,668.00 12,103.40 12,103.40 12,103.40
c) Material
i) Bitumen@ 3.3 per cent of mix tonne 14.883 14.883 14.883 46,556.37 692,898.47 692,898.47 692,898.47 M-074
weight of mix = 205 x 2.2 = 451 tonne
ii) Aggregate
Total weight of mix = 451.00 tonnes
Weight of bitumen = 14.88 tonnes
Weight of aggregate = 436.12 tonnes
Taking density of aggregate = 1.5 ton/cum
*Grading I ( 40 mm nominal size )
37.5 - 25 mm 15 per cent cum 43.612 43.612 43.612 1,887.12 82,301.21 82,301.21 82,301.21 M-048
25 - 10 mm 45 per cent cum 130.835 130.835 130.835 1,887.12 246,901.75 246,901.75 246,901.75 M-045
10 - 5 mm 25 per cent cum 72.686 72.686 72.686 1,887.12 137,167.43 137,167.43 137,167.43 M-039
5 mm and below15 per cent cum 14.537 14.537 14.537 1,887.12 27,433.11 27,433.11 27,433.11 M-029
* Any one of the alternative may be adopted as per
approved design
(i) for Grading I ( 40 mm nominal size )
d) Overhead charges @ 8% on @ 10% on @ 12% on
113,787.68 143,574.32 171,941.69
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
153,613.36 157,931.75 160,478.91
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Royalty of aggregate cum 247.133 247.133 247.133 - - - -
Cost for 205 cum = a+b+c+d+e 1,689,747.00 1,737,249.30 1,765,267.97
Rate per cum = (a+b+c+d+e)/205 8,242.67 8,474.39 8,611.06
Say 8,243.00 8,474.00 8,611.00
Note 1.Quantity of Bitumen has been taken for analysis
purpose. The actual quantity will depend upon job mix
formula.
2. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.

3. In case BM is laid over freshly laid tack coat, provision


of Mechanical broom and 2 mazdoors for the same shall
be deleted as the same has been included in the cost of
tack coat.
5.03 504 (ii) Bituminous Macadam Grading -II
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Providing and laying bituminous macadam with higher
capacity hot mix plant using crushed aggregates of
specified grading premixed with bituminous binder,
transported to site, laid over a previously prepared
surface with paver finisher to the required grade, level
and alignment and rolled as per clauses 501.6 and 501.7
to achieve the desired compaction

Unit = cum
Taking output = 205 cum 451.00 tonnes
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Batch Type Hot Mix Plant
(i) HMP 200 TPH hour 3.007 14,634.90 44,002.27 P&M-035
(ii) HMP 160 TPH hour 3.758 10,338.30 38,854.78 P&M-036
(iii) HMP 120 TPH hour 5.011 8,372.70 41,956.53 P&M-037
Mechanical broom (2.1m sweeping width) hour 0.976 0.976 0.976 500.40 488.39 488.39 488.39 P&M-052
Air compressor 250 cfm hour 0.976 0.976 0.976 614.25 599.51 599.51 599.51 P&M-029
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.007 9,233.70 27,765.74 P&M-058
(ii) Paver (240HP) hour 3.758 9,233.70 34,700.24 P&M-058
(iii) Paver (174HP) hour 5.011 2,362.50 11,838.49 P&M-059
Electric generator
(i) 500 KVA hour 3.007 8,022.00 24,119.48 P&M-044
(ii) 400 KVA hour 3.758 6,470.10 24,316.79 P&M-045
(iii) 250 KVA hour 5.011 3,475.00 17,413.61 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.125 4,279.80 21,936.04 P&M-011
(ii) 2.1 Cum Capacity hour 7.577 2,640.75 20,008.43 P&M-012
(iii) 1 Cum Capacity hour 15.842 1,112.00 17,616.75 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 451 x L1 6.18 83,595.11 P&M-116
(ii) 14 cum capacity t.km 451 x L1 7.01 94,883.18 P&M-119
(iii) 10 cum capacity t.km 451 x L1 8.66 117,223.92 P&M-122
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.014 2,883.30 17,339.21 P&M-014
(ii) 14 cum capacity hour 7.516 2,556.75 19,217.39 P&M-015
(iii) 10 cum capacity hour 10.022 2,274.30 22,793.29 P&M-016
Smooth steel wheeled tandem roller for static and P&M-020
vibratory passaes hour 10.159 10.159 10.159 1,668.00 16,944.76 16,944.76 16,944.76
c) Material
i) Bitumen@ 3.4 per cent of mix tonne 15.334 15.334 15.334 46,556.37 713,895.39 713,895.39 713,895.39 M-074
weight of mix = 205 x 2.2 = 451 tonne
ii) Aggregate
Total weight of mix = 451.00 tonnes
Weight of bitumen = 15.33 tonnes
Weight of aggregate = 435.67 tonnes
Taking density of aggregate = 1.5 ton/cum
Grading II(19 mm nominal size)
25 - 10 mm 40 per cent cum 116.178 116.178 116.178 1,887.12 219,241.43 219,241.43 219,241.43 M-045
10 - 5 mm 40 per cent cum 116.178 116.178 116.178 1,887.12 219,241.43 219,241.43 219,241.43 M-039
5 mm and below 20 per cent cum 58.089 58.089 58.089 1,887.12 109,620.72 109,620.72 109,620.72 M-029
* Any one of the alternative may be adopted as per
approved design
(ii) for Grading II(19 mm nominal size)
d) Overhead charges @ 8% on @ 10% on @ 12% on
120,396.70 151,818.17 181,805.22
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
162,535.54 166,999.99 169,684.87
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Royalty of aggregate cum 232.355 232.355 232.355 - - - -
Cost for 205 cum = a+b+c+d+e 1,787,890.96 1,836,999.86 1,866,533.56
Rate per cum = (a+b+c+d+e)/205 8,721.42 8,960.97 9,105.04
Say 8,721.00 8,961.00 9,105.00
Note *1.Quantity of Bitumen has been taken for analysis
purpose. The actual quantity will depend upon job mix
formula.
2. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.

3. In case BM is laid over freshly laid tack coat, provision


of Mechanical broom and 2 mazdoors for the same shall
be deleted as the same has been included in the cost of
tack coat.

5.04 505 A Dense Graded Bituminous Macadam Grading 1


Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Providing and laying dense graded bituminous macadam
with higher capacity batch type HMP using crushed
aggregates of specified grading, premixed with
bituminous binder @ 4.0 per cent by weight of total mix
and filler, transporting the hot mix to work site, laying with
a hydrostatic paver finisher with sensor control to the
required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the
desired compaction as per MoRTH specification clause
No. 505 complete in all respects.

Unit = cum
Taking output = 195 cum 450.45 tonnes 2.31
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.003 14,634.90 43,948.60 P&M-035
(ii) HMP 160 TPH hour 3.754 10,338.30 38,807.39 P&M-036
(iii) HMP 120 TPH hour 5.005 8,372.70 41,905.36 P&M-037
Mechanical broom (2.1m sweeping width) hour 0.663 0.663 0.663 500.40 331.90 331.90 331.90 P&M-052
Air compressor 250 cfm hour 0.663 0.663 0.663 614.25 407.41 407.41 407.41 P&M-029
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.003 9,233.70 27,728.80 P&M-058
(ii) Paver (240HP) hour 3.754 9,233.70 34,661.00 P&M-058
(iii) Paver (174HP) hour 5.005 2,362.50 11,824.31 P&M-059
Electric generator
(i) 500 KVA hour 3.003 8,022.00 24,090.07 P&M-044
(ii) 400 KVA hour 3.754 6,470.10 24,287.14 P&M-045
(iii) 250 KVA hour 5.005 3,475.00 17,392.38 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.138 4,279.80 21,990.96 P&M-011
(ii) 2.1 Cum Capacity hour 7.596 2,640.75 20,058.53 P&M-012
(iii) 1 Cum Capacity hour 15.882 1,112.00 17,660.86 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 450.45 x L1 6.18 83,493.16 P&M-116
(ii) 14 cum capacity t.km 450.45 x L1 7.01 94,767.47 P&M-119
(iii) 10 cum capacity t.km 450.45 x L1 8.66 117,080.96 P&M-122
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.006 2,883.30 17,317.10 P&M-014
(ii) 14 cum capacity hour 7.508 2,556.75 19,194.80 P&M-015
(iii) 10 cum capacity hour 10.010 2,274.30 22,765.74 P&M-016
Smooth steel wheeled tandem roller for static and P&M-020
vibratory passaes hour 9.663 9.663 9.663 1,668.00 16,118.19 16,118.19 16,118.19
c) Material
i) Bitumen@ 4 per cent of mix tonne 18.018 18.018 18.018 46,556.37 838,852.69 838,852.69 838,852.69 M-074
weight of mix = 195 x 2.31 = 450.450 tonne
ii) Aggregate
Total weight of mix = 450.45 tonnes
Weight of bitumen = 18.02 tonnes
Weight of aggregate = 432.43 tonnes
Taking density of aggregate = 1.5 ton/cum
Grading - I40 mm (Nominal Size)
37.5 - 25 mm 22 per cent cum 63.423 63.423 63.423 1,887.12 119,687.69 119,687.69 119,687.69 M-048
25 - 10 mm 13 per cent cum 37.477 37.477 37.477 1,887.12 70,724.54 70,724.54 70,724.54 M-045
10 -4.75 mm 19 per cent cum 54.775 54.775 54.775 1,887.12 103,366.64 103,366.64 103,366.64 M-039
4.75 mm and below 44 per cent cum 126.847 126.847 126.847 1,887.12 239,375.38 239,375.38 239,375.38 M-029
Filler @ 2 per cent of weight of aggregates. tonne 8.649 8.649 8.649 3,753.00 32,459.70 32,459.70 32,459.70 M-190
* Any one of the alternative may be adopted as per
approved design
Grading - I40 mm (Nominal Size)
d) Overhead charges @ 8% on @ 10% on @ 12% on
131,684.97 165,926.97 198,734.76
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
177,774.70 182,519.67 185,485.78
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Royalty of aggregate cum 227.748 227.748 227.748 - - - -
Cost for 195 cum = a+b+c+d+e 1,955,521.75 2,007,716.37 2,040,343.54
Rate per cum = (a+b+c+d+e)/195 10,028.32 10,295.98 10,463.30
Say 10,028.00 10,296.00 10,463.00
Note *1.Quantity of Bitumen has been taken for analysis
purpose. The actual quantity will depend upon job mix
formula.
2. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.

3. In case DBM is laid over freshly laid tack coat,


provision of mechanical broom and 2 mazdoors shall be
deleted as the same has been included in the cost of tack
coat.
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
4. The individual density for each size of aggregates to be
used for construction I.e. 37.5-25 mm, 25-10 mm etc.
should be found in the laboratory and accordingly the
quantities should be ammended for use in field. The
average density of 1.5 tonne/cum is only a reference
density in this Data Book.

5. The individual percentage of aggregates should be


calculated from the total weight of dry aggregates i.e..
excluding the weight of bitumen. The weight of filler will
also be 2 per cent by weight of dry aggregates.

5.04 505 B Dense Graded Bituminous Macadam Grading 2


Providing and laying dense graded bituminous macadam
with higher capacity batch type HMP using crushed
aggregates of specified grading, premixed with
bituminous binder @ 4.5 per cent by weight of total mix
and filler, transporting the hot mix to work site, laying with
a hydrostatic paver finisher with sensor control to the
required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the
desired compaction as per MoRTH specification clause
No. 505 complete in all respects.

Unit = cum
Taking output = 195 cum 450.45 tonnes 2.31
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.003 14,634.90 43,948.60 P&M-035
(ii) HMP 160 TPH hour 3.754 10,338.30 38,807.39 P&M-036
(iii) HMP 120 TPH hour 5.005 8,372.70 41,905.36 P&M-037
Mechanical broom (2.1m sweeping width) hour 0.663 0.663 0.663 500.40 331.90 331.90 331.90 P&M-052
Air compressor 250 cfm hour 0.663 0.663 0.663 614.25 407.41 407.41 407.41 P&M-029
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.003 9,233.70 27,728.80 P&M-058
(ii) Paver (240HP) hour 3.754 9,233.70 34,661.00 P&M-058
(iii) Paver (174HP) hour 5.005 2,362.50 11,824.31 P&M-059
Electric generator
(i) 500 KVA hour 3.003 8,022.00 24,090.07 P&M-044
(ii) 400 KVA hour 3.754 6,470.10 24,287.14 P&M-045
(iii) 250 KVA hour 5.005 3,475.00 17,392.38 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.112 4,279.80 21,876.40 P&M-011
(ii) 2.1 Cum Capacity hour 7.556 2,640.75 19,954.04 P&M-012
(iii) 1 Cum Capacity hour 15.799 1,112.00 17,568.85 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 450.45 x L1 6.18 83,493.16 P&M-116
(ii) 14 cum capacity t.km 450.45 x L1 7.01 94,767.47 P&M-119
(iii) 10 cum capacity t.km 450.45 x L1 8.66 117,080.96 P&M-122
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.006 2,883.30 17,317.10 P&M-014
(ii) 14 cum capacity hour 7.508 2,556.75 19,194.80 P&M-015
(iii) 10 cum capacity hour 10.010 2,274.30 22,765.74 P&M-016
Smooth steel wheeled tandem roller for static and P&M-020
vibratory passaes hour 9.663 9.663 9.663 1,668.00 16,118.19 16,118.19 16,118.19
c) Material
i) Bitumen@ 4.5 per cent of mix tonne 20.270 20.270 20.270 46,556.37 943,709.28 943,709.28 943,709.28 M-074
ii) Aggregate
Total weight of mix = 450.45 tonnes
Weight of bitumen = 20.27 tonnes
Weight of aggregate = 430.18 tonnes
Taking density of aggregate = 1.5 ton/cum
Grading - II19 mm (Nominal Size)
25 - 10 mm 30 per cent cum 86.036 86.036 86.036 1,887.12 162,360.43 162,360.43 162,360.43 M-045
10 - 5 mm 28 per cent cum 80.300 80.300 80.300 1,887.12 151,536.40 151,536.40 151,536.40 M-039
5 mm and below 40 per cent cum 114.715 114.715 114.715 1,887.12 216,480.57 216,480.57 216,480.57 M-029
Filler @ 2 per cent of weight of aggregates. cum 8.604 8.604 8.604 3,753.00 32,289.29 32,289.29 32,289.29 M-190
* Any one of the alternative may be adopted as per
approved design
Grading - II19 mm (Nominal Size)
d) Overhead charges @ 8% on @ 10% on @ 12% on
139,828.55 176,107.46 210,952.84
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
188,768.54 193,718.20 196,889.32
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Royalty of aggregate cum 289.654 289.654 289.654 - - - -
Cost for 195 cum = a+b+c+d+e 2,076,453.94 2,130,900.22 2,165,782.49
Rate per cum = (a+b+c+d+e)/195 10,648.48 10,927.69 11,106.58
Say 10,648.00 10,928.00 11,107.00
Note *1.Quantity of Bitumen has been taken for analysis
purpose. The actual quantity will depend upon job mix
formula.
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
2. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.

3. In case DBM is laid over freshly laid tack coat,


provision of mechanical broom and 2 mazdoors shall be
deleted as the same has been included in the cost of tack
coat.
4. The individual density for each size of aggregates to be
used for construction I.e. 37.5-25 mm, 25-10 mm etc.
should be found in the laboratory and accordingly the
quantities should be ammended for use in field. The
average density of 1.5 tonne/cum is only a reference
density in this Data Book.

5. The individual percentage of aggregates should be


calculated from the total weight of dry aggregates i.e..
excluding the weight of bitumen. The weight of filler will
also be 2 per cent by weight of dry aggregates.

5.05 507 A Bituminous Concrete Grading 1


Providing and laying bituminous concrete with higher
capacity batch type hot mix plant using crushed
aggregates of specified grading, premixed with
bituminous binder @ 5.2 per cent of mix and filler,
transporting the hot mix to work site, laying with a
hydrostatic paver finisher with sensor control to the
required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the
desired compaction as per MORTH specification clause
No. 507 complete in all respects

Unit = cum
Taking output = 191 cum 450.76 tonnes 2.36
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.005 14,634.90 43,978.85 P&M-035
(ii) HMP 160 TPH hour 3.756 10,338.30 38,834.10 P&M-036
(iii) HMP 120 TPH hour 5.008 8,372.70 41,934.20 P&M-037
Mechanical broom (2.1m sweeping width) hour 1.137 1.137 1.137 500.40 568.91 568.91 568.91 P&M-052
Air compressor 250 cfm hour 1.137 1.137 1.137 614.25 698.34 698.34 698.34 P&M-029
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.005 9,233.70 27,747.88 P&M-058
(ii) Paver (240HP) hour 3.756 9,233.70 34,684.86 P&M-058
(iii) Paver (174HP) hour 5.008 2,362.50 11,832.45 P&M-059
Electric generator
(i) 500 KVA hour 3.005 8,022.00 24,106.64 P&M-044
(ii) 400 KVA hour 3.756 6,470.10 24,303.85 P&M-045
(iii) 250 KVA hour 5.008 3,475.00 17,404.34 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.078 4,279.80 21,731.06 P&M-011
(ii) 2.1 Cum Capacity hour 7.506 2,640.75 19,821.47 P&M-012
(iii) 1 Cum Capacity hour 15.694 1,112.00 17,452.13 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 450.76 x L1 6.18 83,550.62 P&M-116
(ii) 14 cum capacity t.km 450.76 x L1 7.01 94,832.69 P&M-119
(iii) 10 cum capacity t.km 450.76 x L1 8.66 117,161.54 P&M-122
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.010 2,883.30 17,329.02 P&M-014
(ii) 14 cum capacity hour 7.513 2,556.75 19,208.01 P&M-015
(iii) 10 cum capacity hour 10.017 2,274.30 22,781.41 P&M-016
Smooth steel wheeled tandem roller for static and P&M-020
vibratory passaes hour 11.831 11.831 11.831 1,668.00 19,734.45 19,734.45 19,734.45
Pnumetic Tyre roller hour 2.404 3.005 4.007 2,562.00 6,159.18 7,698.98 10,265.31 P&M-022
c) Material
i) Bitumen@ 5.2 per cent of mix tonne 23.440 23.440 23.440 46,556.37 1,091,281.34 1,091,281.34 1,091,281.34 M-074
ii) Aggregate
Total weight of mix = 450.76 tonnes
Weight of bitumen = 23.44 tonnes
Weight of aggregate = 427.32 tonnes
Taking density of aggregate = 1.5 ton/cum
* Grading - I-19 mm (Nominal Size)
20 - 10 mm 38 per cent cum 108.255 108.255 108.255 1,887.12 204,290.51 204,290.51 204,290.51 M-044
10 - 5 mm 17 per cent cum 48.430 48.430 48.430 1,887.12 91,393.37 91,393.37 91,393.37 M-039
5 mm and below 40 per cent cum 122.499 122.499 122.499 1,887.12 231,170.69 231,170.69 231,170.69 M-029
Filler @ 2 per cent of weight of aggregates. cum 8.546 8.546 8.546 3,753.00 32,073.14 32,073.14 32,073.14 M-190
* Any one of the alternative may be adopted as per
approved design
* Grading - I-19 mm (Nominal Size)
d) Overhead charges @ 8% on @ 10% on @ 12% on
152,158.66 191,676.40 229,945.37
(a+b+c) (a+b+c) (a+b+c)
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
e) Contractor's profit @ 10% on @ 10% on @ 10% on
205,414.19 210,844.04 214,615.68
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Royalty of aggregate cum 287.730 287.730 287.730 - - - -
Cost for 191 cum = a+b+c+d+e 2,259,556.12 2,319,284.39 2,360,772.43
Rate per cum = (a+b+c+d+e)/191 11,830.14 12,142.85 12,360.07
Say 11,830.00 12,143.00 12,360.00
Note *1.Quantity of Bitumen has been taken for analysis
purpose. The actual quantity will depend upon job mix
formula.
2. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.

2. In case BC is laid over freshly laid tack coat, provision


of mechanical broom and 2 mazdoors shall be deleted as
the same has been included in the cost of tack coat.

3. The individual density for each size of aggregates to be


used for construction i.e. 37.5-25 mm, 25-10 mm etc.
should be found in the laboratory and accordingly the
quantities should be ammended for use in field. The
average density of 1.5 tonne/cum is only a reference
density in this Data Book.

4. The individual percentage of aggregates should be


calculated from the total weight of dry aggregates i.e..
excluding the weight of bitumen. The weight of filler will
also be 2 per cent by weight of dry aggregates.

5.05 507 B Bituminous Concrete Grading 2


Providing and laying bituminous concrete with higher
capacity batch type hot mix plant using crushed
aggregates of specified grading, premixed with
bituminous binder @ 5.4 per cent of mix and filler,
transporting the hot mix to work site, laying with a
hydrostatic paver finisher with sensor control to the
required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the
desired compaction as per MORTH specification clause
No. 507 complete in all respects

Unit = cum
Taking output = 191 cum 450.76 tonnes 2.36
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.005 14,634.90 43,978.85 P&M-035
(ii) HMP 160 TPH hour 3.756 10,338.30 38,834.10 P&M-036
(iii) HMP 120 TPH hour 5.008 8,372.70 41,934.20 P&M-037
Mechanical broom (2.1m sweeping width) hour 1.624 1.624 1.624 500.40 812.72 812.72 812.72 P&M-052
Air compressor 250 cfm hour 1.624 1.624 1.624 614.25 997.63 997.63 997.63 P&M-029
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.005 9,233.70 27,747.88 P&M-058
(ii) Paver (240HP) hour 3.756 9,233.70 34,684.86 P&M-058
(iii) Paver (174HP) hour 5.008 2,362.50 11,832.45 P&M-059
Electric generator
(i) 500 KVA hour 3.005 8,022.00 24,106.64 P&M-044
(ii) 400 KVA hour 3.756 6,470.10 24,303.85 P&M-045
(iii) 250 KVA hour 5.008 3,475.00 17,404.34 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.004 4,279.80 21,416.12 P&M-011
(ii) 2.1 Cum Capacity hour 7.378 2,640.75 19,483.45 P&M-012
(iii) 1 Cum Capacity hour 15.553 1,112.00 17,294.94 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 450.76 x L1 6.18 83,550.62 P&M-116
(ii) 14 cum capacity t.km 450.76 x L1 7.01 94,832.69 P&M-119
(iii) 10 cum capacity t.km 450.76 x L1 8.66 117,161.54 P&M-122
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.010 2,883.30 17,329.02 P&M-014
(ii) 14 cum capacity hour 7.513 2,556.75 19,208.01 P&M-015
(iii) 10 cum capacity hour 10.017 2,274.30 22,781.41 P&M-016
Smooth steel wheeled tandem roller for static and P&M-020
vibratory passaes hour 16.902 16.902 16.902 1,668.00 28,192.07 28,192.07 28,192.07
Pneumatic Tyre roller hour 2.404 3.005 4.007 2,562.00 6,159.18 7,698.98 10,265.31 P&M-022
c) Material
i) Bitumen@ 5.4 per cent of mix tonne 24.341 24.341 24.341 46,556.37 1,133,230.49 1,133,230.49 1,133,230.49 M-074
ii) Aggregate
Total weight of mix = 450.76 tonnes
Weight of bitumen = 24.34 tonnes
Weight of aggregate = 426.42 tonnes
Taking density of aggregate = 1.5 ton/cum
Grading - II-13 mm (Nominal Size)
13.2 - 10 mm 21 per cent cum 59.699 59.699 59.699 1,887.12 112,659.36 112,659.36 112,659.36 M-043
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
10 - 5 mm 17 per cent cum 48.327 48.327 48.327 1,887.12 91,199.00 91,199.00 91,199.00 M-039
5 mm and below 60 per cent cum 170.568 170.568 170.568 1,887.12 321,882.81 321,882.81 321,882.81 M-029
Filler @ 2 per cent of weight of aggregates. cum 8.528 8.528 8.528 3,753.00 32,005.58 32,005.58 32,005.58 M-190
* Any one of the alternative may be adopted as per
approved design
* Grading - I-19 mm (Nominal Size)
d) Overhead charges @ 8% on @ 10% on @ 12% on
156,114.98 196,619.49 235,898.77
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
210,755.22 216,281.44 220,172.19
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Royalty of aggregate cum 287.122 287.122 287.122 - - - -
Cost for 191 cum = a+b+c+d+e 2,318,307.45 2,379,095.79 2,421,894.08
Rate per cum = (a+b+c+d+e)/191 12,137.74 12,456.00 12,680.07
Say 12,138.00 12,456.00 12,680.00
Note *1.Quantity of Bitumen has been taken for analysis
purpose. The actual quantity will depend upon job mix
formula.
2. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.

3. In case BC is laid over freshly laid tack coat, provision


of mechanical broom and 2 mazdoors shall be deleted as
the same has been included in the cost of tack coat.

4. The individual density for each size of aggregates to be


used for construction i.e. 37.5-25 mm, 25-10 mm etc.
should be found in the laboratory and accordingly the
quantities should be ammended for use in field. The
average density of 1.5 tonne/cum is only a reference
density in this Data Book.

5. The individual percentage of aggregates should be


calculated from the total weight of dry aggregates i.e..
excluding the weight of bitumen. The weight of filler will
also be 2 per cent by weight of dry aggregates.

5.06 509 Surface Dressing


Providing and laying surface dressing as wearing course
in single coat using crushed stone aggregates of
specified size on a layer of bituminous binder laid on
prepared surface and rolling with 8-10 tonne smooth
wheeled steel roller

Unit = sqm
Taking output = 9000 sqm
5.06 Case -I :-19 mm nominal chipping size
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.679 2.679 2.679 500.40 1,340.36 1,340.36 1,340.36 P&M-052
Air compressor 250 cfm hour 2.679 2.679 2.679 614.25 1,645.31 1,645.31 1,645.31 P&M-029
Bitumen pressure distributor (Spraying width 4.5 m) P&M-053
hour 1.250 1.250 1.250 1,729.35 2,161.69 2,161.69 2,161.69
Hydraulic self propelled chip spreader hour 7.401 7.401 7.401 2,220.75 16,436.47 16,436.47 16,436.47 P&M-065
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 0.823 4,279.80 3,523.01 P&M-011
(ii) 2.1 Cum Capacity hour 1.216 2,640.75 3,211.72 P&M-012
(iii) 1 Cum Capacity hour 2.547 1,112.00 2,832.45 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 202.5 x L1 6.18 37,534.39 P&M-116
(ii) 14 cum capacity t.km 202.5 x L1 7.01 42,602.76 P&M-119
(iii) 10 cum capacity t.km 202.5 x L1 8.66 52,633.80 P&M-122
For loading & unloading time
(i) 18 cum capacity hour 8.224 2,883.30 23,713.66 P&M-014
(ii) 14 cum capacity hour 8.618 2,556.75 22,032.87 P&M-015
(iii) 10 cum capacity hour 9.948 2,274.30 22,625.84 P&M-016
Smooth steel wheeled tandem roller for static and P&M-020
vibratory passaes hour 5.973 5.973 5.973 1,668.00 9,963.17 9,963.17 9,963.17
Pnumetic Tyre roller hour 5.973 5.973 5.973 2,562.00 15,303.14 15,303.14 15,303.14 P&M-022
c) Material
Bitumen@ 1.20 kg per sqm tonne 10.800 10.800 10.800 46,556.37 502,808.81 502,808.81 502,808.81 M-074
Crushed stone chipping,19 mm nominal size @ 0.015 M-046
cum per sqm cum 135.000 135.000 135.000 1,887.12 254,761.62 254,761.62 254,761.62
d) Overhead charges @ 8% on @ 10% on @ 12% on
70,015.86 87,827.45 106,622.31
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
94,521.41 96,610.20 99,514.16
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 9000 sqm = a+b+c+d+e 1,039,735.50 1,062,712.19 1,094,655.74
Rate per sqm = (a+b+c+d+e)/9000 115.53 118.08 121.63
Say 116.00 118.00 122.00
5.06 509 Case - II 13 mm nominal size chipping
Unit = sqm
Taking output = 9000 sqm
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.679 2.679 2.679 500.40 1,340.36 1,340.36 1,340.36 P&M-052
Air compressor 250 cfm hour 2.679 2.679 2.679 614.25 1,645.31 1,645.31 1,645.31 P&M-029
Bitumen pressure distributor (Spraying width 4.5 m) P&M-053
hour 1.250 1.250 1.250 1,729.35 2,161.69 2,161.69 2,161.69
Hydraulic self propelled chip spreader hour 7.401 7.401 7.401 2,220.75 16,436.47 16,436.47 16,436.47 P&M-065
Front end loader for loading
(i) 3.1 Cum Capacity hour 0.544 4,279.80 2,329.73 P&M-011
(ii) 2.1 Cum Capacity hour 0.804 2,640.75 2,122.03 P&M-012
(iii) 1 Cum Capacity hour 1.688 1,112.00 1,876.50 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 135 x L1 6.18 25,022.93 P&M-116
(ii) 14 cum capacity t.km 135 x L1 7.01 28,401.84 P&M-119
(iii) 10 cum capacity t.km 135 x L1 8.66 35,089.20 P&M-122
For loading & unloading time
(i) 18 cum capacity hour 7.946 2,883.30 22,909.75 P&M-014
(ii) 14 cum capacity hour 8.205 2,556.75 20,977.85 P&M-015
(iii) 10 cum capacity hour 9.089 2,274.30 20,670.69 P&M-016
Smooth steel wheeled tandem roller for static and P&M-020
vibratory passaes hour 3.982 3.982 3.982 1,668.00 6,642.11 6,642.11 6,642.11
Pnumetic Tyre roller hour 3.982 3.982 3.982 2,562.00 10,201.88 10,201.88 10,201.88 P&M-022
c) Material
Bitumen@ 1.20 kg per sqm tonne 9.000 9.000 9.000 46,556.37 419,007.34 419,007.34 419,007.34 M-074
Crushed stone chipping,13 mm nominal size @ 0.015 M-051
cum per sqm cum 90.000 90.000 90.000 1,887.12 169,841.08 169,841.08 169,841.08
d) Overhead charges @ 8% on @ 10% on @ 12% on
54,683.62 68,478.46 82,910.31
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
73,822.89 75,326.30 77,382.96
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 9000 sqm = a+b+c+d+e 812,051.78 828,589.34 851,212.52
Rate per sqm = (a+b+c+d+e)/9000 90.23 92.07 94.58
Say 90.00 92.00 95.00
Note 1.Where the proposed aggregate fails to pass the
stripping test, an approved adhesion agent may be added
to the binder as per clause 510.2.4. Alternatively, chips
may be pre-coated as per clause 510.2.5

2.Input for the second coat, where required, will be the


same as per the Ist coat mentioned above
5.07 510 Open - Graded Premix Surfacing
Providing, laying and rolling of open - graded premix
surfacing of 20 mm thickness composed of 13.2 mm to
5.6 mm aggregates using Viscocity grade bitumen to
required line, grade and level to serve as wearing course
on a previously prepared base, including mixing in a
suitable hot mix plant of appropriate capacity not less
than 200 tonnes/hour, laying and rolling with a smooth
wheeled roller, finished to required level and grades.

Unit = cum 205 cum


Taking output = 10250 Sqm 483.80 tonnes
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.225 14,634.90 47,202.43 P&M-035
(ii) HMP 160 TPH hour 4.032 10,338.30 41,680.58 P&M-036
(iii) HMP 120 TPH hour 5.376 8,372.70 45,007.91 P&M-037
Mechanical broom (2.1m sweeping width) hour 1.220 1.220 1.220 500.40 610.61 610.61 610.61 P&M-052
Air compressor 250 cfm hour 1.220 1.220 1.220 614.25 749.53 749.53 749.53 P&M-029
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.225 9,233.70 29,781.76 P&M-058
(ii) Paver (240HP) hour 4.032 9,233.70 37,227.20 P&M-058
(iii) Paver (174HP) hour 5.376 2,362.50 12,699.75 P&M-059
Electric generator
(i) 500 KVA hour 3.225 8,022.00 25,873.62 P&M-044
(ii) 400 KVA hour 4.032 6,470.10 26,085.29 P&M-045
(iii) 250 KVA hour 5.376 3,475.00 18,680.06 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 4.942 4,279.80 21,150.62 P&M-011
(ii) 2.1 Cum Capacity hour 7.283 2,640.75 19,232.30 P&M-012
(iii) 1 Cum Capacity hour 15.375 1,112.00 17,097.00 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 483.8 x L1 6.18 89,674.75 P&M-116
(ii) 14 cum capacity t.km 483.8 x L1 7.01 101,783.78 P&M-119
(iii) 10 cum capacity t.km 483.8 x L1 8.66 125,749.30 P&M-122
For loading & unloading time
(i) 18 cum capacity hour 6.451 2,883.30 18,599.21 P&M-014
(ii) 14 cum capacity hour 8.063 2,556.75 20,615.93 P&M-015
(iii) 10 cum capacity hour 10.751 2,274.30 24,451.25 P&M-016
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Smooth steel wheeled tandem roller for static and P&M-020
vibratory passaes hour 18.141 18.141 18.141 1,668.00 30,258.50 30,258.50 30,258.50
c) Material
Bitumen @ 14.60 kg per 10 sqm tonne 14.965 14.965 14.965 46,556.37 696,716.09 696,716.09 696,716.09 M-074
Crushed stone chipping,13.2 mm to 5.6 mm @ 0.27 cum M-042
per 10 sqm cum 276.750 276.750 276.750 1,887.12 522,261.32 522,261.32 522,261.32
* Any one of the alternative may be adopted as per
approved design
d) Overhead charges @ 8% on @ 10% on @ 12% on
119,123.82 150,339.04 180,054.07
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
160,817.15 165,372.94 168,050.46
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10250 Sqm = a+b+c+d+e 1,768,988.66 1,819,102.36 1,848,555.10
Rate per Sqm = (a+b+c+d+e)/10250 172.58 177.47 180.35
Say 173.00 177.00 180.00
5.08 508 Close Graded Premix Surfacing/Mixed Seal Surfacing

Providing, laying and rolling of open - graded premix


surfacing of 20 mm thickness composed of 11.2 mm to
0.09 mm (Type-a) or 13.2 mm to 0.09 mm (Type-b)
aggregates using Viscocity grade bitumen to required
line, grade and level to serve as wearing course on a
previously prepared base, including mixing in a suitable
hot mix plant of appropriate capacity not less than 200
tonnes/hour, laying and rolling with a smooth wheeled
roller, finished to required level and grades.

Unit = cum 205 cum


Taking output = 10250 Sqm 483.80 tonnes
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.225 14,634.90 47,202.43 P&M-035
(ii) HMP 160 TPH hour 4.032 10,338.30 41,680.58 P&M-036
(iii) HMP 120 TPH hour 5.376 8,372.70 45,007.91 P&M-037
Mechanical broom (2.1m sweeping width) hour 1.220 1.220 1.220 500.40 610.61 610.61 610.61 P&M-052
Air compressor 250 cfm hour 1.220 1.220 1.220 614.25 749.53 749.53 749.53 P&M-029
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.225 9,233.70 29,781.76 P&M-058
(ii) Paver (240HP) hour 4.032 9,233.70 37,227.20 P&M-058
(iii) Paver (174HP) hour 5.376 2,362.50 12,699.75 P&M-059
Electric generator
(i) 500 KVA hour 3.225 8,022.00 25,873.62 P&M-044
(ii) 400 KVA hour 4.032 6,470.10 26,085.29 P&M-045
(iii) 250 KVA hour 5.376 3,475.00 18,680.06 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 3.225 4,279.80 13,803.78 P&M-011
(ii) 2.1 Cum Capacity hour 7.283 2,640.75 19,232.30 P&M-012
(iii) 1 Cum Capacity hour 15.375 1,112.00 17,097.00 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 483.8 x L1 6.18 89,674.75 P&M-116
(ii) 14 cum capacity t.km 483.8 x L1 7.01 101,783.78 P&M-119
(iii) 10 cum capacity t.km 483.8 x L1 8.66 125,749.30 P&M-122
For loading & unloading time
(i) 18 cum capacity hour 6.451 2,883.30 18,599.21 P&M-014
(ii) 14 cum capacity hour 8.063 2,556.75 20,615.93 P&M-015
(iii) 10 cum capacity hour 10.751 2,274.30 24,451.25 P&M-016
Smooth steel wheeled tandem roller for static and P&M-020
vibratory passaes hour 18.141 18.141 18.141 1,668.00 30,258.50 30,258.50 30,258.50
c) Material
Type - A
* Bitumen@ 22 kg per 10 sqm tonne 22.550 22.550 22.550 46,556.37 1,049,846.17 1,049,846.17 1,049,846.17 M-074
Stone crushed aggregates 11.2 mm to 0.09 @ 0.27 cum M-040
per 10 sqm cum 276.750 276.750 276.750 1,887.12 522,261.32 522,261.32 522,261.32
or
Type - B
Bitumen @ 19 kg per 10 sqm tonne 19.475 19.475 19.475 46,556.37 906,685.33 906,685.33 906,685.33 M-074
Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27 M-041
cum per 10 sqm cum 276.750 276.750 276.750 1,887.12 522,261.32 522,261.32 522,261.32
* Any one of the alternative may be adopted as per
approved design
Type - A
d) Overhead charges @ 8% on @ 10% on @ 12% on
146,786.47 185,652.05 222,429.68
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
198,161.74 204,217.25 207,601.03
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10250 Sqm = a+b+c+d+e 2,179,779.15 2,246,389.75 2,283,611.35
Rate per Sqm = (a+b+c+d+e)/10250 212.66 219.16 222.79
Say 213.00 219.00 223.00
Type - B
d) Overhead charges @ 8% on @ 10% on @ 12% on
135,333.61 171,335.96 205,250.38
(a+b+c) (a+b+c) (a+b+c)
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
e) Contractor's profit @ 10% on @ 10% on @ 10% on
182,700.37 188,469.56 191,567.02
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10250 Sqm = a+b+c+d+e 2,009,704.07 2,073,165.13 2,107,237.20
Rate per Sqm = (a+b+c+d+e)/10250 196.07 202.26 205.58
Say 196.00 202.00 206.00
5.09 511 Seal Coat
Providing and laying seal coat sealing the voids in a
bituminous surface laid to the specified levels, grade and
cross fall using Type A and B seal coats

(i) Case - I : Type A


Unit = sqm
Taking output = 10250 sqm 92.25 cum
a) Labour
Mate day 0.240 0.240 0.240 617.00 148.08 148.08 148.08 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 3.051 3.051 3.051 500.40 1,526.52 1,526.52 1,526.52 P&M-052
Air compressor 250 cfm hour 3.051 3.051 3.051 614.25 1,873.83 1,873.83 1,873.83 P&M-029
Bitumen pressure distributor (Spraying width 4.5 m) hour 2.847 2.847 2.847 1,729.35 4,923.84 4,923.84 4,923.84 P&M-053
Hydraulic self propelled chip spreader hour 8.429 8.429 8.429 2,220.75 18,719.32 18,719.32 18,719.32 P&M-065
Front end loader
(i) 3.1 Cum Capacity hour 0.563 4,279.80 2,407.39 P&M-011
(ii) 2.1 Cum Capacity hour 0.831 2,640.75 2,194.68 P&M-012
(iii) 1 Cum Capacity hour 1.741 1,112.00 1,935.51 P&M-013
Tipper
For loading time
(i) 18 cum capacity hour 0.563 2,883.30 1,623.30 P&M-014
(ii) 14 cum capacity hour 0.831 2,556.75 2,124.87 P&M-015
(iii) 10 cum capacity hour 1.741 2,274.30 3,958.57 P&M-016
For Transportation
(i) 18 cum capacity t.km 202.95 x L1 6.18 37,617.80 P&M-116
(ii) 14 cum capacity t.km 202.95 x L1 7.01 42,697.43 P&M-119
(iii) 10 cum capacity t.km 202.95 x L1 8.66 52,750.76 P&M-122
For unloading time
(i) 18 cum capacity hour 8.429 2,883.30 24,304.13 P&M-014
(ii) 14 cum capacity hour 8.429 2,556.75 21,551.55 P&M-015
(iii) 10 cum capacity hour 8.429 2,274.30 19,170.70 P&M-016
Smooth steel wheeled tandem roller for static and P&M-020
vibratory passaes hour 4.082 4.082 4.082 1,668.00 6,808.16 6,808.16 6,808.16
c) Material
Bitumen@ 9.80 kg per 10 sqm tonne 10.045 10.045 10.045 46,556.37 467,658.75 467,658.75 467,658.75 M-074
Crushed stone chipping of 6.7 mm size defined as 100 M-049
per cent passing 11.2 mm sieve and retained on 2.36 cum 92.250 92.250 92.250 1,887.12 174,087.11 174,087.11 174,087.11
mm sieve applied @ 0.09 cum per 10 sqm
d) Overhead charges @ 8% on @ 10% on @ 12% on
59,581.39 74,738.33 90,795.63
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
80,434.87 82,212.16 84,742.59
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Royalty of aggregate cum 92.250 92.250 92.250 - - - -
Cost for 10250 sqm = a+b+c+d+e 884,783.60 904,333.73 932,168.49
Rate per sqm = (a+b+c+d+e)/10250 86.32 88.23 90.94
Say 86.00 88.00 91.00
Note Since seal coat is provided immediately over the
bituminous layers, mechanical broom for clearing has not
been catered.
5.09 (ii) Case - II : Type B
Providing and laying of premix sand seal coat with HMP
of appropriate capacity not less than 200 tonnes/ hours
using crushed stone chipping 6.7 mm size and
penetration bitumen of suitable grade.

Unit = cum
Taking output = 7860 sqm 47.16 cum
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 0.314 14,634.90 4,601.21 P&M-035
(ii) HMP 160 TPH hour 0.393 10,338.30 4,062.95 P&M-036
(iii) HMP 120 TPH hour 0.524 8,372.70 4,387.29 P&M-037
Mechanical broom (2.1m sweeping width) hour 2.339 2.339 2.339 500.40 1,170.58 1,170.58 1,170.58 P&M-052
Air compressor 250 cfm hour 2.339 2.339 2.339 614.25 1,436.91 1,436.91 1,436.91 P&M-029
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 0.314 9,233.70 2,903.08 P&M-058
(ii) Paver (240HP) hour 0.393 9,233.70 3,628.84 P&M-058
(iii) Paver (174HP) hour 0.524 2,362.50 1,237.95 P&M-059
Electric generator
(i) 500 KVA hour 0.314 8,022.00 2,522.12 P&M-044
(ii) 400 KVA hour 0.393 6,470.10 2,542.75 P&M-045
(iii) 250 KVA hour 0.524 3,475.00 1,820.90 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 0.832 4,279.80 3,560.79 P&M-011
(ii) 2.1 Cum Capacity hour 1.230 2,640.75 3,248.81 P&M-012
(iii) 1 Cum Capacity hour 2.572 1,112.00 2,860.47 P&M-013
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Tipper
For Transportation
(i) 18 cum capacity t.km 103.752 x L1 6.18 19,230.95 P&M-116
(ii) 14 cum capacity t.km 103.752 x L1 7.01 21,827.76 P&M-119
(iii) 10 cum capacity t.km 103.752 x L1 8.66 26,967.22 P&M-122
For loading & unloading time
(i) 18 cum capacity hour 0.629 2,883.30 1,813.02 P&M-014
(ii) 14 cum capacity hour 0.786 2,556.75 2,009.61 P&M-015
(iii) 10 cum capacity hour 1.048 2,274.30 2,383.47 P&M-016
Smooth steel wheeled tandem roller for static and P&M-020
vibratory passaes hour 2.087 2.087 2.087 1,668.00 3,480.47 3,480.47 3,480.47
c) Material
Bitumen@ 6.80 kg per 10 sqm tonne 5.345 5.345 5.345 46,556.37 248,834.49 248,834.49 248,834.49 M-074
Crushed stone chipping of 6.7 mm size defined as M-049
passing 11.2 mm sieve and retained on 2.36 mm sieve cum 47.160 47.160 47.160 1,887.12 88,996.73 88,996.73 88,996.73
applied @ 0.06 cum per 10 sqm
* Any one of the alternative may be adopted as per
approved design
d) Overhead charges @ 8% on @ 10% on @ 12% on
30,777.57 38,740.91 46,769.49
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
41,549.72 42,615.01 43,651.52
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 7860 Sqm = a+b+c+d+e 457,046.87 468,765.06 480,166.72
Rate per Sqm. = (a+b+c+d+e)/7860 58.15 59.64 61.09
Say 58.00 60.00 61.00

5.10 520 Supply of Stone Aggregates for Pavement Courses

Supply of stone aggregates from approved sources


conforming to the physical requirement, specified in the
respective specified clauses, including royalties, fees
rents, collection, transportation, stacking and testing and
measured in cum as per clause 520

Competitive market rates to be as certained.


Alternatively, rates for stone crushing given in chapter 1
may be adopted, if found economical. In case for supply
of aggregates at site are not available, nearest crusher
site may be as certained. Loading and un-loading
charges and cost of carriage may be added to these rates
to arrive at the cost at site.

5.11 516 Mastic Asphalt


Providing and laying 25 mm thick mastic asphalt wearing
course with paving grade bitumen meeting the
requirements given in table 500-39, prepared by using
mastic cooker and laid to required level and slope after
cleaning the surface, including providing antiskid surface
with bitumen precoated finegrained hard stone chipping
of 13.2 mm nominal size at the rate of 0.005cum per 10
sqm and at an approximate spacing of 10 cm center to
center in both directions, pressed into surface when the
temperature of surfaces is not less than 1000C,
protruding 1 mm to 4 mm over mastic surface, all
complete as per clause 516.

Unit = sqm
Taking output = 35 sqm 2.0125 tonnes
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-13
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
b) Machinery
Mechanical broom (2.1m sweeping width) hour 0.010 0.010 0.010 500.40 5.00 5.00 5.00 P&M-052
Air compressor 250 cfm hour 0.010 0.010 0.010 614.25 6.14 6.14 6.14 P&M-029
Mastic cooker 1 tonne capacity hour 3.000 3.000 3.000 1,042.50 3,127.50 3,127.50 3,127.50 P&M-056
Bitumen boiler 1500 litres capacity hour 3.000 3.000 3.000 743.40 2,230.20 2,230.20 2,230.20 P&M-055
Tractor for towing and positioning of mastic cooker and P&M-026
bitumen boiler hour 1.000 1.000 1.000 1,876.50 1,876.50 1,876.50 1,876.50
c) Material
Base mastic (without coarse aggregates) = 60 per cent

Coarse aggregate (6.3mm to 13.2 mm) = 40 per cent .

Proportion of material required for mastic asphalt with


coarse aggregates (based on mix design done by CRRI
for a specific case)
I) Bitumen 85/25 or 30/40 @ 10.2 per cent by weight of M-327
mix. 2 x 10.2/100 = 0.204 tonne 0.205 0.205 0.205 44,020.00 9,036.21 9,036.21 9,036.21
ii) Fine aggregate passing 2.36mm and retained on M-019
0.075mm sieve @ 31.9 per cent by weight of mix = 2 x
31.9/100 = 0.638 tonnes = 0.638/1.625 = 0.39 cum 0.395 0.395 0.395 1,887.12 745.54 745.54 745.54

iii) Lime stone dust filler with calcium content not less M-190
than 80 per cent by weight @ 17.92 per cent by weight tonne 0.361 0.361 0.361 3,753.00 1,353.48 1,353.48 1,353.48
of mix = 2 x 17.92/100 = 0.36
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
iv) Coarse aggregates 6.3 mm to 13.2 mm @ 40 per cent M-042
by weight of mix = 2 x 40/100 = 0.8 MT = 0.8/1.456 = 0.55 cum 0.553 0.553 0.553 1,887.12 1,043.36 1,043.36 1,043.36

v) Pre-coated stone chips of 13.2 mm nominal size for M-051


skid resistance = 35 x 0.005/10 = 0.018 cum 0.018 0.018 0.018 1,887.12 33.97 33.97 33.97
vi) Bitumen for coating of chips @ 2 per cent by weight = M-327
0.018 x 1.456 x 2/100 = 0.0005 MT = 0.5kg kg 0.510 0.510 0.510 44,020.00 22,450.20 22,450.20 22,450.20

d) Overhead charges @ 8% on @ 10% on @ 12% on


3,828.84 4,786.05 5,743.26
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
5,168.94 5,264.66 5,360.38
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Royalty of aggregate cum 0.97 0.97 0.97 - - - -
Cost for 35 Sqm = a+b+c+d+e 56,858.30 57,911.23 58,964.16
Rate per Sqm = (a+b+c+d+e)/35 1,624.52 1,654.61 1,684.69
Say 1,625.00 1,655.00 1,685.00
Note 1.The rates for 50 mm & 40 mm thick layers may be
worked out on pro-rata basis.
2.Where tack coat is required to be provided before
laying mastic asphalt, the same is required to be
measured and paid separately.
3.The quantities of binder, filler and aggregates are for
estimating purpose. Exact quantities shall be as per mix
design.
4.This rate analysis is based on design made by CRRI for
a specific case and is meant for estimating purposes
only. Actual design is required to be done for each case.

5.12 512 Slurry Seal


Providing and laying slurry seal consisting of a mixture of
fine aggregates, portland cement filler, bituminous
emulsion and water on a road surface including cleaning
of surface, mixing of slurry seal in a suitable mobile plant,
laying and compacting to provide even riding surface

(i) 2-3 mm thickness (Type-I)


Unit = sqm
Taking output = 24000 sqm 60 cum 132.00
Taking density of 2.2 tonnes per cum
weight of mix = 176 tonnes
a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 7.143 7.143 7.143 500.40 3,574.29 3,574.29 3,574.29 P&M-052
Air compressor 250 cfm hour 7.143 7.143 7.143 614.25 4,387.50 4,387.50 4,387.50 P&M-029
Mobile slurry seal equipment hour 6.579 6.579 6.579 3,998.40 26,305.26 26,305.26 26,305.26 P&M-074
Front end loader
(i) 3.1 Cum Capacity hour 0.366 4,279.80 1,565.78 P&M-011
(ii) 2.1 Cum Capacity hour 0.541 2,640.75 1,427.43 P&M-012
(iii) 1 Cum Capacity hour 1.132 1,112.00 1,258.87 P&M-013
Tipper
Tipper for loading time
(i) 18 cum capacity hour 0.366 2,883.30 1,054.87 P&M-014
(ii) 14 cum capacity hour 0.541 2,556.75 1,382.03 P&M-015
(iii) 10 cum capacity hour 1.132 2,274.30 2,574.68 P&M-016
For Transportation
(i) 18 cum capacity t.km 132 x L1 7.51 39,645.38 P&M-117
(ii) 14 cum capacity t.km 132 x L1 8.52 44,998.80 P&M-120
(iii) 10 cum capacity t.km 132 x L1 10.53 55,594.00 P&M-123
Tipper for unloading time
(i) 18 cum capacity hour 6.579 2,883.30 18,969.08 P&M-014
(ii) 14 cum capacity hour 6.579 2,556.75 16,820.72 P&M-015
(iii) 10 cum capacity hour 6.579 2,274.30 14,962.50 P&M-016
Water tanker (speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 3 km/hr )
(i) 16 KL capacity hour 5.690 1,501.00 8,540.69 P&M-023
(ii) 12 KL capacity hour 7.597 1,327.00 10,081.22 P&M-024
(iii) 6 KL capacity hour 15.193 1,005.00 15,268.97 P&M-025
Pneumatic tyred roller with individual wheel load not P&M-022
exceeding 1.5 tonnes hour 5.263 5.263 5.263 2,562.00 13,484.21 13,484.21 13,484.21
c) Material
Residual Binder @ 13 per cent of mix 60 x 2.2 x 0.13 M-077
tonne 17.160 17.160 17.160 47,662.37 817,886.29 817,886.29 817,886.29
Fine aggregate 3 mm and below 85.5 per cent of total M-029
mix,60 x 2.2 x 0.855 = 112.860 tonnes. Taking cum 75.240 75.240 75.240 1,887.12 141,987.14 141,987.14 141,987.14
density1.5, = 112.860/1.5 = 75.240 cum
Filler @ 1.5 per cent of total mix = 60 x 2.2 x 0.15 tonne 1.980 1.980 1.980 3,753.00 7,430.94 7,430.94 7,430.94 M-190
Cost of water KL 12.000 12.000 12.000 16.00 192.00 192.00 192.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
87,057.28 109,315.04 132,971.90
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
117,527.32 120,246.54 124,107.11
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 24000 Sqm = a+b+c+d+e 1,292,800.53 1,322,711.92 1,365,178.17
Rate per Sqm = (a+b+c+d+e)/24000 53.87 55.11 56.88
Say 54.00 55.00 57.00
5.12 (ii) 4-6 mm thickness (Type-II)
Unit = sqm 176.000 tonne
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Taking output = 16000 sqm 80 cum
a) Labour
Mate day 0.240 0.240 0.240 617.00 148.08 148.08 148.08 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 4.762 4.762 4.762 500.40 2,382.86 2,382.86 2,382.86 P&M-052
Air compressor 250 cfm hour 4.762 4.762 4.762 614.25 2,925.00 2,925.00 2,925.00 P&M-029
Mobile slurry seal equipment hour 4.386 4.386 4.386 3,998.40 17,536.84 17,536.84 17,536.84 P&M-074
Front end loader
(i) 3.1 Cum Capacity hour 0.488 4,279.80 2,087.71 P&M-011
(ii) 2.1 Cum Capacity hour 0.721 2,640.75 1,903.24 P&M-012
(iii) 1 Cum Capacity hour 1.509 1,112.00 1,678.49 P&M-013
Tipper
Tipper for loading time
(i) 18 cum capacity hour 0.488 2,883.30 1,406.49 P&M-014
(ii) 14 cum capacity hour 0.721 2,556.75 1,842.70 P&M-015
(iii) 10 cum capacity hour 1.509 2,274.30 3,432.91 P&M-016
For Transportation
(i) 18 cum capacity t.km 176 x L1 7.51 29,734.03 P&M-117
(ii) 14 cum capacity t.km 176 x L1 8.52 33,749.10 P&M-120
(iii) 10 cum capacity t.km 176 x L1 10.53 41,695.50 P&M-123
Tipper for unloading time
(i) 18 cum capacity hour 4.386 2,883.30 12,646.05 P&M-014
(ii) 14 cum capacity hour 4.386 2,556.75 11,213.82 P&M-015
(iii) 10 cum capacity hour 4.386 2,274.30 9,975.00 P&M-016
Water tanker (speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 3 km/hr )
(i) 16 KL capacity hour 4.623 1,501.00 6,939.12 P&M-023
(ii) 12 KL capacity hour 6.174 1,327.00 8,192.90 P&M-024
(iii) 6 KL capacity hour 12.349 1,005.00 12,410.75 P&M-025
Pneumatic tyred roller with individual wheel load not P&M-022
exceeding 1.5 tonnes hour 3.509 3.509 3.509 2,562.00 8,989.47 8,989.47 8,989.47
c) Material
Residual Binder @ 10.5 per cent of mix = 80 x 2.2 x M-077
0.105=18.480 tonnes tonne 18.480 18.480 18.480 47,662.37 880,800.62 880,800.62 880,800.62
Fine aggregate 4.75 mm and below 88 per cent of total M-029
mix, 80x 2.2 x 0.88 = 154.880 tonnes. Taking density 1.5, cum 103.253 103.253 103.253 1,887.12 194,851.12 194,851.12 194,851.12
154.880/1.5=103.253
Filler @ 2 per cent of total mix = 80x 2.2 x 0.015 tonne 2.640 2.640 2.640 3,753.00 9,907.92 9,907.92 9,907.92 M-190
Cost of water KL 12.000 12.000 12.000 16.00 192.00 192.00 192.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
93,889.31 117,770.48 142,799.48
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
126,750.57 129,547.53 133,279.52
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 16000 Sqm = a+b+c+d+e 1,394,256.32 1,425,022.80 1,466,074.67
Rate per Sqm = (a+b+c+d+e)/16000 87.14 89.06 91.63
Say 87.00 89.00 92.00
5.12 (iii) 6-8 mm thickness (Type-III)
Unit = sqm
Taking output = 12000 sqm 84 cum 184.80
a) Labour
Mate day 0.280 0.280 0.280 617.00 172.76 172.76 172.76 L-12
Mazdoor day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 3.571 3.571 3.571 500.40 1,787.14 1,787.14 1,787.14 P&M-052
Air compressor 250 cfm hour 3.571 3.571 3.571 614.25 2,193.75 2,193.75 2,193.75 P&M-029
Mobile slurry seal equipment hour 3.289 3.289 3.289 3,998.40 13,152.63 13,152.63 13,152.63 P&M-074
Front end loader
(i) 3.1 Cum Capacity hour 0.512 4,279.80 2,192.09 P&M-011
(ii) 2.1 Cum Capacity hour 0.757 2,640.75 1,998.41 P&M-012
(iii) 1 Cum Capacity hour 1.585 1,112.00 1,762.42 P&M-013
Tipper
Tipper for loading time
(i) 18 cum capacity hour 0.512 2,883.30 1,476.81 P&M-014
(ii) 14 cum capacity hour 0.757 2,556.75 1,934.84 P&M-015
(iii) 10 cum capacity hour 1.585 2,274.30 3,604.55 P&M-016
For Transportation
(i) 18 cum capacity t.km 184.8 x L1 7.51 17,840.42 P&M-117
(ii) 14 cum capacity t.km 184.8 x L1 8.52 20,249.46 P&M-120
(iii) 10 cum capacity t.km 184.8 x L1 10.53 25,017.30 P&M-123
Tipper for unloading time
(i) 18 cum capacity hour 3.289 2,883.30 9,484.54 P&M-014
(ii) 14 cum capacity hour 3.289 2,556.75 8,410.36 P&M-015
(iii) 10 cum capacity hour 3.289 2,274.30 7,481.25 P&M-016
Water tanker (speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 3 km/hr )
(i) 16 KL capacity hour 4.090 1,501.00 6,139.09 P&M-023
(ii) 12 KL capacity hour 5.463 1,327.00 7,249.40 P&M-024
(iii) 6 KL capacity hour 10.927 1,005.00 10,981.64 P&M-025
Pneumatic tyred roller with individual wheel load not P&M-022
exceeding 1.5 tonnes hour 2.632 2.632 2.632 2,562.00 6,742.11 6,742.11 6,742.11
c) Material
Residual Binder @ 9 per cent of mix, 84 x 2.2 x 0.09 M-077
tonne 16.632 16.632 16.632 47,662.37 792,720.55 792,720.55 792,720.55
Fine aggregate 2.36 mm and below,89.5 per cent of M-029
total mix,84x 2.2 x 0.895 = 165.396 tonnes. Taking cum 110.264 110.264 110.264 1,887.12 208,081.74 208,081.74 208,081.74
density 1.5 ,165.396/1.5=110.264 cum
Filler @ 1.5 per cent of total mix = 84x 2.2 x 0.015 tonne 2.772 2.772 2.772 3,753.00 10,403.32 10,403.32 10,403.32 M-190
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Cost of water KL 12.000 12.000 12.000 16.00 192.00 192.00 192.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
86,092.77 107,886.91 130,544.86
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
116,225.24 118,675.60 121,841.86
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 12000 Sqm = a+b+c+d+e 1,278,477.60 1,305,431.62 1,340,260.51
Rate per Sqm = (a+b+c+d+e)/12000 106.54 108.79 111.69
Say 107.00 109.00 112.00
Note 1.Tack coat, if required to be provided, before laying
slurry seal may be measured and paid separately

5.13 519 Recycling of Bituminous Pavement with Central


Recycling Plant
Recycling pavement by cold milling of existing bituminous
layers, planning the surface after cold milling, reclaiming
excavated material to the extent of 30 per cent of the
required quantity, hauling and stock piling the reclaimed
material near the central recycling plant after carrying out
necessary checks and evaluation, adding fresh material
including rejuvenators as required, mixing in a hot mix
plant, transporting and laying at site and compacting to
the required grade, level and thickness, all as specified in
clause 519.

Unit = cum
Taking output = 120 Cum 276 tonnes
A (i) Using by Bituminous Macadam Grading-I
a) Labour
Mate day 0.280 0.280 0.280 617.00 172.76 172.76 172.76 L-12
Mazdoor day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
Mazdoor skilled day 3.000 3.000 3.000 565.73 1,697.19 1,697.19 1,697.19 L-15
b) Machinery
Milling Machine
Milling Machine with 2 meter Drum Width hour 5.926 11,982.60 71,008.89 P&M-083
Milling Machine with 1.3 meter Drum Width 9.117 8,006.25 72,992.98 P&M-082
Milling Machine with 1.2 meter Drum Width 9.877 5,592.30 55,235.15 P&M-081
Bitumen pressure distributor (Spraying width 4.5m) hour 0.667 0.667 0.667 1,729.35 1,152.90 1,152.90 1,152.90 P&M-053
Batch Type Hot Mix Plant
(i) HMP 200 TPH hour 1.840 14,634.90 26,928.22 P&M-035
(ii) HMP 160 TPH hour 2.300 10,338.30 23,778.09 P&M-036
(iii) HMP 120 TPH hour 3.067 8,372.70 25,676.28 P&M-037
Mechanical broom (2.1m sweeping width) hour 0.571 0.571 0.571 500.40 285.94 285.94 285.94 P&M-052
Air compressor 250 cfm hour 0.571 0.571 0.571 614.25 351.00 351.00 351.00 P&M-029
Paver Finisher hydrostatic with sensor control compatible
with the hot mix plant
(i) Paver (240HP) hour 1.840 9,233.70 16,990.01
(ii) Paver (240HP) hour 2.300 9,233.70 21,237.51
(iii) Paver (174HP) hour 3.067 2,362.50 7,245.00
Electric generator
(i) 500 KVA hour 1.840 8,022.00 14,760.48 P&M-044
(ii) 400 KVA hour 2.300 6,470.10 14,881.23 P&M-045
(iii) 250 KVA hour 3.067 3,475.00 10,656.67 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 1.868 4,279.80 7,994.67 P&M-011
(ii) 2.1 Cum Capacity hour 2.762 2,640.75 7,293.75 P&M-012
(iii) 1 Cum Capacity hour 5.775 1,112.00 6,421.80 P&M-013
Tipper
For Transportation Plant to Site
(i) 18 cum capacity t.km 276 x L1 7.51 62,171.16 P&M-117
(ii) 14 cum capacity t.km 276 x L1 8.52 70,566.30 P&M-120
(iii) 10 cum capacity t.km 276 x L1 10.53 87,181.50 P&M-123
Tipper for loading & unloading time
(i) 18 cum capacity hour 3.680 2,883.30 10,610.54 P&M-014
(ii) 14 cum capacity hour 4.600 2,556.75 11,761.05 P&M-015
(iii) 10 cum capacity hour 6.133 2,274.30 13,948.28 P&M-016
For Transportaion of Dismantle Material Site to Plant
For Transportation Plant to Site
(i) 18 cum capacity t.km 276 x L1 7.51 62,171.16 P&M-117
(ii) 14 cum capacity t.km 276 x L1 8.52 70,566.30 P&M-120
(iii) 10 cum capacity t.km 276 x L1 10.53 87,181.50 P&M-123
Tipper for loading
(i) 18 cum capacity hour 5.926 2,883.30 17,086.44 P&M-014
(ii) 14 cum capacity hour 9.117 2,556.75 23,309.89 P&M-015
(iii) 10 cum capacity hour 9.877 2,274.30 22,463.26 P&M-016
Smooth steel wheeled tandem roller for static and P&M-019
vibratory passaes hour 10.619 10.619 10.619 417.00 813.15 813.15 813.15
c) Material
i) Bitumen
A bitumen content is 3.3 per cent bitumen weight of mix.
For reclaimed material, fresh bitumen will be required to
the extent of 60 per cent of normal requirement.

In a mix of 276 tonnes, 82.8 tonne is reclaimed and


balance 193.2 tonne is fresh mix.
Bitumen required for reclaimed mix of 82.8 tonne @ 60 M-074
per cent = 82.8 x 0.60 x0.033 = 1.639 tonne 1.639 1.639 1.639 46,556.37 76,305.89 76,305.89 76,305.89
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Bitumen required for fresh mix of 193.2 tonnes = 193.2 x M-074
0.033 = 6.376 tonne 6.376 6.376 6.376 46,556.37 296,843.42 296,843.42 296,843.42
ii) Aggregates
Percentage of mix requiring fresh aggregates - 70 per
cent
Weight of fresh mix = 276 x 0.70 = 193.2 tonne
Weight of fresh aggregate in the mix = 193.2 x 0.967 =
186.824 tonne
Taking average density of 1.5 tonnes/cum, total volume
of aggregate = 124.550 cum.
Size wise requirement of fresh aggregates
Grading I (40 mm nominal size)
37.5 - 25 mm @ 15 per cent cum 18.683 18.683 18.683 1,887.12 35,257.12 35,257.12 35,257.12 M-048
25 - 10 mm @ 45 per cent cum 56.048 56.048 56.048 1,887.12 105,769.48 105,769.48 105,769.48 M-045
10- 5 mm @ 25 per cent cum 31.138 31.138 31.138 1,887.12 58,761.24 58,761.24 58,761.24 M-039
Below 5 mm @15 per cent cum 18.683 18.683 18.683 1,887.12 35,257.12 35,257.12 35,257.12 M-029
Credit for milled material for use (70%), considering 20 %
cost as salvage value of above average material rate of cum 124.550 124.550 124.550 -377.42 -47,008.24 -47,008.24 -47,008.24
aggregate
* Any one of the alternative may be adopted as per
approved design
d) Overhead charges @ 8% on @ 10% on @ 12% on
68,594.13 88,409.22 106,045.74
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
92,602.07 97,250.14 98,976.02
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 120 cum = a+b+c+d+e 1,065,631.05 1,116,759.75 1,135,744.49
Rate per cum = (a+b+c+d+e)/120 8,880.26 9,306.33 9,464.54
Say 8,880.00 9,306.00 9,465.00
A (ii) Using by Bituminous Macadam Grading-II
a) Labour
Mate day 0.280 0.280 0.280 617.00 172.76 172.76 172.76 L-12
Mazdoor day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
Mazdoor skilled day 3.000 3.000 3.000 565.73 1,697.19 1,697.19 1,697.19 L-15
b) Machinery
Milling Machine
Milling Machine with 2 meter Drum Width hour 5.926 738.00 4,373.39 P&M-083
Milling Machine with 1.3 meter Drum Width 9.117 738.00 6,728.35 P&M-082
Milling Machine with 1.2 meter Drum Width 9.877 558.00 5,511.37 P&M-081
Bitumen pressure distributor (Spraying width 4.5m) hour 0.667 0.667 0.667 1,729.35 1,152.90 1,152.90 1,152.90 P&M-053
Batch Type Hot Mix Plant
(i) HMP 200 TPH hour 1.840 14,634.90 26,928.22 P&M-035
(ii) HMP 160 TPH hour 2.300 10,338.30 23,778.09 P&M-036
(iii) HMP 120 TPH hour 3.067 8,372.70 25,676.28 P&M-037
Mechanical broom (2.1m sweeping width) hour 0.571 0.571 0.571 500.40 285.94 285.94 285.94 P&M-052
Air compressor 250 cfm hour 0.571 0.571 0.571 614.25 351.00 351.00 351.00 P&M-029
Paver Finisher hydrostatic with sensor control compatible
with the hot mix plant
(i) Paver (240HP) hour 1.840 9,233.70 16,990.01
(ii) Paver (240HP) hour 2.300 9,233.70 21,237.51
(iii) Paver (174HP) hour 3.067 2,362.50 7,245.00
Electric generator
(i) 500 KVA hour 1.840 8,022.00 14,760.48 P&M-044
(ii) 400 KVA hour 2.300 6,470.10 14,881.23 P&M-045
(iii) 250 KVA hour 3.067 3,475.00 10,656.67 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 2.196 4,279.80 9,398.44 P&M-011
(ii) 2.1 Cum Capacity hour 3.246 2,640.75 8,571.87 P&M-012
(iii) 1 Cum Capacity hour 6.787 1,112.00 7,547.14 P&M-013
Tipper
For Transportation Plant to Site
(i) 18 cum capacity t.km 276 x L1 7.51 62,171.16 P&M-117
(ii) 14 cum capacity t.km 276 x L1 8.52 70,566.30 P&M-120
(iii) 10 cum capacity t.km 276 x L1 10.53 87,181.50 P&M-123
Tipper for loading & unloading time
(i) 18 cum capacity hour 3.680 2,883.30 10,610.54 P&M-014
(ii) 14 cum capacity hour 4.600 2,556.75 11,761.05 P&M-015
(iii) 10 cum capacity hour 6.133 2,274.30 13,948.28 P&M-016
For Transportaion of Dismantle Material Site to Plant
For Transportation Plant to Site
(i) 18 cum capacity t.km 276 x L1 7.51 62,171.16 P&M-117
(ii) 14 cum capacity t.km 276 x L1 8.52 70,566.30 P&M-120
(iii) 10 cum capacity t.km 276 x L1 10.53 87,181.50 P&M-123
Tipper for loading
(i) 18 cum capacity hour 5.926 2,883.30 17,086.44 P&M-014
(ii) 14 cum capacity hour 9.117 2,556.75 23,309.89 P&M-015
(iii) 10 cum capacity hour 9.877 2,274.30 22,463.26 P&M-016
Smooth steel wheeled tandem roller for static and P&M-019
vibratory passaes hour 10.619 10.619 10.619 417.00 813.15 813.15 813.15
c) Material
i) Bitumen
A bitumen content is 3.4 per cent bitumen weight of mix.
For reclaimed material, fresh bitumen will be required to
the extent of 60 per cent of normal requirement.

In a mix of 276 tonnes, 82.8 tonne is reclaimed and


balance 193.2 tonne is fresh mix.
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Bitumen required for reclaimed mix of 82.8 tonne @ 60 M-074
per cent = 82.8 x 0.60 x0.034 = 1.689 tonne 1.689 1.689 1.689 46,556.37 78,633.71 78,633.71 78,633.71
Bitumen required for fresh mix of 193.2 tonnes = 193.2 x M-074
0.034 = 6.569 tonne 6.569 6.569 6.569 46,556.37 305,828.80 305,828.80 305,828.80
ii) Aggregates
Percentage of mix requiring fresh aggregates - 70 per
cent
Weight of fresh mix = 276 x 0.70 = 193.2 tonne
Weight of fresh aggregate in the mix = 193.2 x 0.966 =
186.631 tonne
Taking average density of 1.5 tonnes/cum, total volume
of aggregate = 124.421 cum.
Size wise requirement of fresh aggregates
Grading II (19 mm nominal size)
25 - 10 mm @ 40 per cent cum 49.768 49.768 49.768 1,887.12 93,919.10 93,919.10 93,919.10 M-045
10- 5 mm @ 40 per cent cum 49.768 49.768 49.768 1,887.12 93,919.10 93,919.10 93,919.10 M-039
Below 5 mm @20 per cent cum 24.884 24.884 24.884 1,887.12 46,959.55 46,959.55 46,959.55 M-029
Credit for milled material for use (70%), considering 20 %
cost as salvage value of above average material rate of cum 124.421 124.421 124.421 -377.42 -46,959.55 -46,959.55 -46,959.55
aggregate
* Any one of the alternative may be adopted as per
approved design
d) Overhead charges @ 8% on @ 10% on @ 12% on
64,264.76 83,022.03 101,547.69
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
86,757.43 91,324.24 94,777.84
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 120 cum = a+b+c+d+e 1,001,291.30 1,051,526.14 1,089,515.81
Rate per cum = (a+b+c+d+e)/120 8,344.09 8,762.72 9,079.30
Say 8,344.00 8,763.00 9,079.00
Using by Dense Graded Bituminous Macadam Grading-I
B (i)
a) Labour
Mate day 0.280 0.280 0.280 617.00 172.76 172.76 172.76 L-12
Mazdoor day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
Mazdoor skilled day 3.000 3.000 3.000 565.73 1,697.19 1,697.19 1,697.19 L-15
b) Machinery
Milling Machine
Milling Machine with 2 meter Drum Width hour 5.926 1,887.12 11,183.09 P&M-083
Milling Machine with 1.3 meter Drum Width 9.117 1,887.12 17,204.90 P&M-082
Milling Machine with 1.2 meter Drum Width 9.877 1,887.12 18,639.11 P&M-081
Bitumen pressure distributor (Spraying width 4.5m) hour 0.667 0.667 0.667 1,729.35 1,152.90 1,152.90 1,152.90 P&M-053
Batch Type Hot Mix Plant
(i) HMP 200 TPH hour 1.840 14,634.90 26,928.22 P&M-035
(ii) HMP 160 TPH hour 2.300 10,338.30 23,778.09 P&M-036
(iii) HMP 120 TPH hour 3.067 8,372.70 25,676.28 P&M-037
Mechanical broom (2.1m sweeping width) hour 0.571 0.571 0.571 500.40 285.94 285.94 285.94 P&M-052
Air compressor 250 cfm hour 0.571 0.571 0.571 614.25 351.00 351.00 351.00 P&M-029
Paver Finisher hydrostatic with sensor control compatible
with the hot mix plant
(i) Paver (240HP) hour 1.840 9,233.70 16,990.01
(ii) Paver (240HP) hour 2.300 9,233.70 21,237.51
(iii) Paver (174HP) hour 3.067 2,362.50 7,245.00
Electric generator
(i) 500 KVA hour 1.840 8,022.00 14,760.48 P&M-044
(ii) 400 KVA hour 2.300 6,470.10 14,881.23 P&M-045
(iii) 250 KVA hour 3.067 3,475.00 10,656.67 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 1.800 4,279.80 7,703.64 P&M-011
(ii) 2.1 Cum Capacity hour 2.300 2,640.75 6,073.73 P&M-012
(iii) 1 Cum Capacity hour 3.642 1,112.00 4,049.90 P&M-013
Tipper
For Transportation Plant to Site
(i) 18 cum capacity t.km 276 x L1 7.51 62,171.16 P&M-117
(ii) 14 cum capacity t.km 276 x L1 8.52 70,566.30 P&M-120
(iii) 10 cum capacity t.km 276 x L1 10.53 87,181.50 P&M-123
Tipper for loading & unloading time
(i) 18 cum capacity hour 3.680 2,883.30 10,610.54 P&M-014
(ii) 14 cum capacity hour 4.600 2,556.75 11,761.05 P&M-015
(iii) 10 cum capacity hour 6.133 2,274.30 13,948.28 P&M-016
For Transportaion of Dismantle Material Site to Plant
For Transportation Plant to Site
(i) 18 cum capacity t.km 276 x L1 7.51 62,171.16 P&M-117
(ii) 14 cum capacity t.km 276 x L1 8.52 70,566.30 P&M-120
(iii) 10 cum capacity t.km 276 x L1 10.53 87,181.50 P&M-123
Tipper for loading
(i) 18 cum capacity hour 5.926 2,883.30 17,086.44 P&M-014
(ii) 14 cum capacity hour 9.117 2,556.75 23,309.89 P&M-015
(iii) 10 cum capacity hour 9.877 2,274.30 22,463.26 P&M-016
Smooth steel wheeled tandem roller for static and P&M-019
vibratory passaes hour 10.619 10.619 10.619 417.00 813.15 813.15 813.15
c) Material
i) Bitumen
A bitumen content is 4 per cent bitumen weight of mix.
For reclaimed material, fresh bitumen will be required to
the extent of 60 per cent of normal requirement.
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
In a mix of 276 tonnes, 82.8 tonne is reclaimed and
balance 193.2 tonne is fresh mix.
Bitumen required for reclaimed mix of 82.8 tonne @ 60 M-074
per cent = 82.8 x 0.60 x0.04 = 1.987 tonne 1.987 1.987 1.987 46,556.37 92,507.51 92,507.51 92,507.51
Bitumen required for fresh mix of 193.2 tonnes = 193.2 x M-074
0.04 = 7.728 tonne 7.728 7.728 7.728 46,556.37 359,787.64 359,787.64 359,787.64
ii) Aggregates
Percentage of mix requiring fresh aggregates - 70 per
cent
Weight of fresh mix = 276 x 0.70 = 193.2 tonne
Weight of fresh aggregate in the mix = 193.2 x 0.96 =
185.472 tonne
Taking average density of 1.5 tonnes/cum, total volume
of aggregate = 123.648 cum.
Size wise requirement of fresh aggregates
Grading I (40 mm nominal size)
37.5 - 25 mm @ 22 per cent cum 27.203 18.683 18.683 1,887.12 51,334.58 35,257.12 35,257.12 M-048
25 - 10 mm @ 13 per cent cum 16.074 49.768 49.768 1,887.12 30,334.07 93,919.10 93,919.10 M-045
10- 4.75 mm @ 19 per cent cum 23.493 49.768 49.768 1,887.12 44,334.41 93,919.10 93,919.10 M-039
Below 4.75 mm @44 per cent cum 54.405 24.884 24.884 1,887.12 102,669.16 46,959.55 46,959.55 M-029
Filler @2% of Weight of aggregate tonne 5.520 5.520 5.520 3,753.00 20,716.56 20,716.56 20,716.56 M-190
Credit for milled material for use (70%), considering 20 %
cost as salvage value of above average material rate of cum 124.421 124.421 124.421 -452.06 -56,245.72 -56,245.72 -56,245.72
aggregate
* Any one of the alternative may be adopted as per
approved design
d) Overhead charges @ 8% on @ 10% on @ 12% on
70,524.96 95,271.89 116,445.77
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
95,208.69 104,799.08 108,682.71
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 120 cum = a+b+c+d+e 1,082,824.76 1,188,318.99 1,231,039.02
Rate per cum = (a+b+c+d+e)/120 9,023.54 9,902.66 10,258.66
Say 9,024.00 9,903.00 10,259.00
Using by Dense Graded Bituminous Macadam Grading-II
B (ii)
a) Labour
Mate day 0.280 0.280 0.280 617.00 172.76 172.76 172.76 L-12
Mazdoor day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
Mazdoor skilled day 3.000 3.000 3.000 565.73 1,697.19 1,697.19 1,697.19 L-15
b) Machinery
Milling Machine
Milling Machine with 2 meter Drum Width hour 5.926 166.80 988.46 P&M-083
Milling Machine with 1.3 meter Drum Width 9.117 1,008.00 9,189.94 P&M-082
Milling Machine with 1.2 meter Drum Width 9.877 25.00 246.93 P&M-081
Bitumen pressure distributor (Spraying width 4.5m) hour 0.667 0.667 0.667 1,729.35 1,152.90 1,152.90 1,152.90 P&M-053
Batch Type Hot Mix Plant
(i) HMP 200 TPH hour 1.840 14,634.90 26,928.22 P&M-035
(ii) HMP 160 TPH hour 2.300 10,338.30 23,778.09 P&M-036
(iii) HMP 120 TPH hour 3.067 8,372.70 25,676.28 P&M-037
Mechanical broom (2.1m sweeping width) hour 0.571 0.571 0.571 500.40 285.94 285.94 285.94 P&M-052
Air compressor 250 cfm hour 0.571 0.571 0.571 614.25 351.00 351.00 351.00 P&M-029
Paver Finisher hydrostatic with sensor control compatible
with the hot mix plant
(i) Paver (240HP) hour 1.840 9,233.70 16,990.01
(ii) Paver (240HP) hour 2.300 9,233.70 21,237.51
(iii) Paver (174HP) hour 3.067 2,362.50 7,245.00
Electric generator
(i) 500 KVA hour 1.840 8,022.00 14,760.48 P&M-044
(ii) 400 KVA hour 2.300 6,470.10 14,881.23 P&M-045
(iii) 250 KVA hour 3.067 3,475.00 10,656.67 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 2.127 4,279.80 9,103.13 P&M-011
(ii) 2.1 Cum Capacity hour 3.145 2,640.75 8,305.16 P&M-012
(iii) 1 Cum Capacity hour 6.575 1,112.00 7,311.40 P&M-013
Tipper
For Transportation Plant to Site
(i) 18 cum capacity t.km 276 x L1 7.51 62,171.16 P&M-117
(ii) 14 cum capacity t.km 276 x L1 8.52 70,566.30 P&M-120
(iii) 10 cum capacity t.km 276 x L1 10.53 87,181.50 P&M-123
Tipper for loading & unloading time
(i) 18 cum capacity hour 3.680 2,883.30 10,610.54 P&M-014
(ii) 14 cum capacity hour 4.600 2,556.75 11,761.05 P&M-015
(iii) 10 cum capacity hour 6.133 2,274.30 13,948.28 P&M-016
For Transportaion of Dismantle Material Site to Plant
For Transportation Plant to Site
(i) 18 cum capacity t.km 276 x L1 7.51 62,171.16 P&M-117
(ii) 14 cum capacity t.km 276 x L1 8.52 70,566.30 P&M-120
(iii) 10 cum capacity t.km 276 x L1 10.53 87,181.50 P&M-123
Tipper for loading
(i) 18 cum capacity hour 5.926 2,883.30 17,086.44 P&M-014
(ii) 14 cum capacity hour 9.117 2,556.75 23,309.89 P&M-015
(iii) 10 cum capacity hour 9.877 2,274.30 22,463.26 P&M-016
Smooth steel wheeled tandem roller for static and P&M-019
vibratory passaes hour 10.619 10.619 10.619 417.00 813.15 813.15 813.15
c) Material
i) Bitumen
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
A bitumen content is 4.5 per cent bitumen weight of mix.
For reclaimed material, fresh bitumen will be required to
the extent of 60 per cent of normal requirement.

In a mix of 276 tonnes, 82.8 tonne is reclaimed and


balance 193.2 tonne is fresh mix.
Bitumen required for reclaimed mix of 82.8 tonne @ 60 M-074
per cent = 82.8 x 0.60 x0.045 = 2.236 tonne 2.236 2.236 2.236 46,556.37 104,100.05 104,100.05 104,100.05
Bitumen required for fresh mix of 193.2 tonnes = 193.2 x M-074
0.045 =8.694 tonne 8.694 8.694 8.694 46,556.37 404,761.09 404,761.09 404,761.09
ii) Aggregates
Percentage of mix requiring fresh aggregates - 70 per
cent
Weight of fresh mix = 276 x 0.70 = 193.2 tonne
Weight of fresh aggregate in the mix = 193.2 x 0.955 =
184.506 tonne
Taking average density of 1.5 tonnes/cum, total volume
of aggregate = 123.004 cum.
Size wise requirement of fresh aggregates
Grading I (40 mm nominal size)
25 - 10 mm @ 30 per cent cum 36.901 36.901 36.901 1,887.12 69,637.11 69,637.11 69,637.11 M-045
10- 4.75 mm @ 28 per cent cum 34.441 34.441 34.441 1,887.12 64,994.63 64,994.63 64,994.63 M-039
Below 5 mm @40 per cent cum 49.202 49.202 49.202 1,887.12 92,849.48 92,849.48 92,849.48 M-029
Filler @2% of Weight of aggregate tonne 5.520 6.520 7.520 3,753.00 20,716.56 24,469.56 28,222.56 M-190
Credit for milled material for use (70%), considering 20 %
cost as salvage value of above average material rate of cum 123.004 123.004 123.004 -470.72 -57,900.25 -57,900.25 -57,900.25
aggregate
* Any one of the alternative may be adopted as per
approved design
d) Overhead charges @ 8% on @ 10% on @ 12% on
74,118.98 96,302.61 117,011.34
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
100,060.62 105,932.88 109,210.58
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 120 cum = a+b+c+d+e 1,137,850.57 1,198,692.33 1,230,994.11
Rate per cum = (a+b+c+d+e)/120 9,482.09 9,989.10 10,258.28
Say 9,482.00 9,989.00 10,258.00
C (i) Using by Bituminous Concrete Grading-I
a) Labour
Mate day 0.280 0.280 0.280 617.00 172.76 172.76 172.76 L-12
Mazdoor day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
Mazdoor skilled day 3.000 3.000 3.000 565.73 1,697.19 1,697.19 1,697.19 L-15
b) Machinery
Milling Machine
Milling Machine with 2 meter Drum Width hour 5.926 48.45 287.10 P&M-083
Milling Machine with 1.3 meter Drum Width 9.117 640.00 5,834.88 P&M-082
Milling Machine with 1.2 meter Drum Width 9.877 2,500.00 24,692.50 P&M-081
Bitumen pressure distributor (Spraying width 4.5m) hour 0.667 0.667 0.667 1,729.35 1,152.90 1,152.90 1,152.90 P&M-053
Batch Type Hot Mix Plant
(i) HMP 200 TPH hour 1.840 14,634.90 26,928.22 P&M-035
(ii) HMP 160 TPH hour 2.300 10,338.30 23,778.09 P&M-036
(iii) HMP 120 TPH hour 3.067 8,372.70 25,676.28 P&M-037
Mechanical broom (2.1m sweeping width) hour 0.571 0.571 0.571 500.40 285.94 285.94 285.94 P&M-052
Air compressor 250 cfm hour 0.571 0.571 0.571 614.25 351.00 351.00 351.00 P&M-029
Paver Finisher hydrostatic with sensor control compatible
with the hot mix plant
(i) Paver (240HP) hour 1.840 9,233.70 16,990.01
(ii) Paver (240HP) hour 2.300 9,233.70 21,237.51
(iii) Paver (174HP) hour 3.067 2,362.50 7,245.00
Electric generator
(i) 500 KVA hour 1.840 8,022.00 14,760.48 P&M-044
(ii) 400 KVA hour 2.300 6,470.10 14,881.23 P&M-045
(iii) 250 KVA hour 3.067 3,475.00 10,656.67 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 2.112 4,279.80 9,038.94 P&M-011
(ii) 2.1 Cum Capacity hour 3.122 2,640.75 8,244.42 P&M-012
(iii) 1 Cum Capacity hour 6.527 1,112.00 7,258.02 P&M-013
Tipper
For Transportation Plant to Site
(i) 18 cum capacity t.km 276 x L1 7.51 62,171.16 P&M-117
(ii) 14 cum capacity t.km 276 x L1 8.52 70,566.30 P&M-120
(iii) 10 cum capacity t.km 276 x L1 10.53 87,181.50 P&M-123
Tipper for loading & unloading time
(i) 18 cum capacity hour 3.680 2,883.30 10,610.54 P&M-014
(ii) 14 cum capacity hour 4.600 2,556.75 11,761.05 P&M-015
(iii) 10 cum capacity hour 6.133 2,274.30 13,948.28 P&M-016
For Transportaion of Dismantle Material Site to Plant
For Transportation Plant to Site
(i) 18 cum capacity t.km 276 x L1 7.51 62,171.16 P&M-117
(ii) 14 cum capacity t.km 276 x L1 8.52 70,566.30 P&M-120
(iii) 10 cum capacity t.km 276 x L1 10.53 87,181.50 P&M-123
Tipper for loading
(i) 18 cum capacity hour 5.926 2,883.30 17,086.44 P&M-014
(ii) 14 cum capacity hour 9.117 2,556.75 23,309.89 P&M-015
(iii) 10 cum capacity hour 9.877 2,274.30 22,463.26 P&M-016
Smooth steel wheeled tandem roller for static and P&M-019
vibratory passaes hour 10.619 10.619 10.619 417.00 813.15 813.15 813.15
c) Material
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
i) Bitumen
A bitumen content is 5.2 per cent bitumen weight of mix.
For reclaimed material, fresh bitumen will be required to
the extent of 60 per cent of normal requirement.

In a mix of 276 tonnes, 82.8 tonne is reclaimed and


balance 193.2 tonne is fresh mix.
Bitumen required for reclaimed mix of 82.8 tonne @ 60 M-074
per cent = 82.8 x 0.60 x0.052 =2.583 tonne 2.853 2.853 2.853 46,556.37 132,825.33 132,825.33 132,825.33
Bitumen required for fresh mix of 193.2 tonnes = 193.2 x M-074
0.052 = 10.046 tonne 10.046 10.046 10.046 46,556.37 467,705.30 467,705.30 467,705.30
ii) Aggregates
Percentage of mix requiring fresh aggregates - 70 per
cent
Weight of fresh mix = 276 x 0.70 = 193.2 tonne
Weight of fresh aggregate in the mix = 193.2 x 0.948=
183.154 tonne
Taking average density of 1.5 tonnes/cum, total volume
of aggregate = 122.102 cum.
Size wise requirement of fresh aggregates
Grading I (19 mm nominal size)
20 - 10 mm @ 38 per cent cum 46.399 46.399 46.399 1,887.12 87,560.17 87,560.17 87,560.17 M-045
10- 5 mm @ 17 per cent cum 20.757 20.757 20.757 1,887.12 39,171.66 39,171.66 39,171.66 M-039
Below 5 mm @43 per cent cum 52.504 52.504 52.504 1,887.12 99,081.25 99,081.25 99,081.25 M-029
Filler @2% of Weight of aggregate tonne 5.520 6.520 7.520 3,753.00 20,716.56 24,469.56 28,222.56 M-190
Credit for milled material for use (70%), considering 20 %
cost as salvage value of above average material rate of cum 122.102 122.102 122.102 -470.72 -57,475.67 -57,475.67 -57,475.67
aggregate
* Any one of the alternative may be adopted as per
approved design
d) Overhead charges @ 8% on @ 10% on @ 12% on
81,291.81 105,003.63 130,789.52
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
109,743.95 115,503.99 122,070.22
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 120 cum = a+b+c+d+e 1,243,942.52 1,303,550.02 1,372,025.47
Rate per cum = (a+b+c+d+e)/120 10,366.19 10,862.92 11,433.55
Say 10,366.00 10,863.00 11,434.00
C (ii) Using by Bituminous Concrete Grading-II
a) Labour
Mate day 0.280 0.280 0.280 617.00 172.76 172.76 172.76 L-12
Mazdoor day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
Mazdoor skilled day 3.000 3.000 3.000 565.73 1,697.19 1,697.19 1,697.19 L-15
b) Machinery
Milling Machine
Milling Machine with 2 meter Drum Width hour 5.926 1.00 5.93 P&M-083
Milling Machine with 1.3 meter Drum Width 9.117 1.00 9.12 P&M-082
Milling Machine with 1.2 meter Drum Width 9.877 1.00 9.88 P&M-081
Bitumen pressure distributor (Spraying width 4.5m) hour 0.667 0.667 0.667 1,729.35 1,152.90 1,152.90 1,152.90 P&M-053
Batch Type Hot Mix Plant
(i) HMP 200 TPH hour 1.840 14,634.90 26,928.22 P&M-035
(ii) HMP 160 TPH hour 2.300 10,338.30 23,778.09 P&M-036
(iii) HMP 120 TPH hour 3.067 8,372.70 25,676.28 P&M-037
Mechanical broom (2.1m sweeping width) hour 0.571 0.571 0.571 500.40 285.94 285.94 285.94 P&M-052
Air compressor 250 cfm hour 0.571 0.571 0.571 614.25 351.00 351.00 351.00 P&M-029
Paver Finisher hydrostatic with sensor control compatible
with the hot mix plant
(i) Paver (240HP) hour 1.840 9,233.70 16,990.01
(ii) Paver (240HP) hour 2.300 9,233.70 21,237.51
(iii) Paver (174HP) hour 3.067 2,362.50 7,245.00
Electric generator
(i) 500 KVA hour 1.840 8,022.00 14,760.48 P&M-044
(ii) 400 KVA hour 2.300 6,470.10 14,881.23 P&M-045
(iii) 250 KVA hour 3.067 3,475.00 10,656.67 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 2.107 4,279.80 9,017.54 P&M-011
(ii) 2.1 Cum Capacity hour 3.115 2,640.75 8,225.94 P&M-012
(iii) 1 Cum Capacity hour 6.513 1,112.00 7,242.46 P&M-013
Tipper
For Transportation Plant to Site
(i) 18 cum capacity t.km 276 x L1 7.51 62,171.16 P&M-117
(ii) 14 cum capacity t.km 276 x L1 8.52 70,566.30 P&M-120
(iii) 10 cum capacity t.km 276 x L1 10.53 87,181.50 P&M-123
Tipper for loading & unloading time
(i) 18 cum capacity hour 3.680 2,883.30 10,610.54 P&M-014
(ii) 14 cum capacity hour 4.600 2,556.75 11,761.05 P&M-015
(iii) 10 cum capacity hour 6.133 2,274.30 13,948.28 P&M-016
For Transportaion of Dismantle Material Site to Plant
For Transportation Plant to Site
(i) 18 cum capacity t.km 276 x L1 7.51 62,171.16 P&M-117
(ii) 14 cum capacity t.km 276 x L1 8.52 70,566.30 P&M-120
(iii) 10 cum capacity t.km 276 x L1 10.53 87,181.50 P&M-123
Tipper for loading
(i) 18 cum capacity hour 5.926 2,883.30 17,086.44 P&M-014
(ii) 14 cum capacity hour 9.117 2,556.75 23,309.89 P&M-015
(iii) 10 cum capacity hour 9.877 2,274.30 22,463.26 P&M-016
Smooth steel wheeled tandem roller for static and P&M-019
vibratory passaes hour 10.619 10.619 10.619 417.00 813.15 813.15 813.15
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
c) Material
i) Bitumen
A bitumen content is 5.4 per cent bitumen weight of mix.
For reclaimed material, fresh bitumen will be required to
the extent of 60 per cent of normal requirement.

In a mix of 276 tonnes, 82.8 tonne is reclaimed and


balance 193.2 tonne is fresh mix.
Bitumen required for reclaimed mix of 82.8 tonne @ 60 M-074
per cent = 82.8 x 0.60 x0.054 = 2.683 tonne 2.683 2.683 2.683 46,556.37 124,910.74 124,910.74 124,910.74
Bitumen required for fresh mix of 193.2 tonnes = 193.2 x M-074
tonne 10.433 10.433 10.433 46,556.37 485,722.62 485,722.62 485,722.62
0.054 =10.433
ii) Aggregates
Percentage of mix requiring fresh aggregates - 70 per
cent
Weight of fresh mix = 276 x 0.70 = 193.2 tonne
Weight of fresh aggregate in the mix = 193.2 x 0.946 =
182.767 tonne
Taking average density of 1.5 tonnes/cum, total volume
of aggregate = 121.845cum.
Size wise requirement of fresh aggregates
Grading II (13 mm nominal size)
13.2 - 10 mm @ 21 per cent cum 25.587 25.587 25.587 1,887.12 48,286.67 48,286.67 48,286.67 M-045
10- 5 mm @ 17 per cent cum 20.714 20.714 20.714 1,887.12 39,089.21 39,089.21 39,089.21 M-039
Below 5 mm @60 per cent cum 73.107 73.107 73.107 1,887.12 137,961.91 137,961.91 137,961.91 M-029
Filler @2% of Weight of aggregate tonne 5.520 5.520 5.520 3,753.00 20,716.56 20,716.56 20,716.56 M-190
Credit for milled material for use (70%), considering 20 %
cost as salvage value of above average material rate of cum 121.745 121.745 121.745 -470.72 -57,307.62 -57,307.62 -57,307.62
aggregate
* Any one of the alternative may be adopted as per
approved design
d) Overhead charges @ 8% on @ 10% on @ 12% on
82,051.25 105,023.45 128,100.47
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
110,769.18 115,525.80 119,560.44
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 120 cum = a+b+c+d+e 1,255,052.06 1,307,374.84 1,351,755.90
Rate per cum = (a+b+c+d+e)/120 10,458.77 10,894.79 11,264.63
Say 10,459.00 10,895.00 11,265.00

5.14 513 Fog Spray


Providing and applying low viscosity bitumen emulsion for
sealing cracks less than 3 mm wide or incipient fretting or
disintegration in an existing bituminous surfacing.

Unit = sqm
Taking output = 10500 Sqm
(i) a) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 3.125 3.125 3.125 500.40 1,563.75 1,563.75 1,563.75 P&M-052
Air compressor 250 cfm hour 3.125 3.125 3.125 614.25 1,919.53 1,919.53 1,919.53 P&M-029
Bitumen pressure distributor (Spraying width 4.5 m) P&M-053
tonne 2.917 2.917 2.917 1,729.35 5,043.94 5,043.94 5,043.94
c) Material
Bitumen emulsion @ 0.75 kg per sqm tonne 7.880 7.880 7.880 47,662.37 375,579.48 375,579.48 375,579.48 M-077
d) Overhead charges @ 8% on @ 10% on @ 12% on
30,857.22 38,571.53 46,285.84
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
41,657.25 42,428.68 43,200.11
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10500 Sqm = a+b+c+d+e 458,229.78 466,715.52 475,201.25
Rate per Sqm = (a+b+c+d+e)/10500 43.64 44.45 45.26
Say 44.00 44.00 45.00
(ii) 1.In case it is decided by the engineer to blind the fog
spray, the following may be added
a) Labour
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Mazdoor for precoating of grit day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
b) Material
Crushed stone grit 3 mm size @ 3.75 kg per sqm cum 26.250 26.250 26.250 1,887.12 49,536.98 49,536.98 49,536.98 M-023
Bitumen emulsion for precoating grit @ 2 per cent of M-077
grit,39.38 x 0.02 tonne 0.790 0.790 0.790 47,662.37 37,653.27 37,653.27 37,653.27
Cost for 10500 Sqm = a+b 89,335.05 89,335.05 89,335.05
Cost per qm 8.508 8.508 8.508
c) Overhead charges @ 8% on @ 10% on @ 12% on
14,293.61 17,867.01 21,440.41
(a+b+c) (a+b+c) (a+b+c)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
19,296.37 19,653.71 20,011.05
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10500 Sqm = a+b+c+d 212,260.09 216,190.83 220,121.57
Rate per Sqm = (a+b+c+d)/10500 20.22 20.59 20.96
Say 20.00 21.00 21.00
5.15 518 Bituminous Cold Mix (Including Gravel Emulsion)
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

Providing, laying and rolling of bituminous cold mix on


prepared base consisting of a mixture of unheated
mineral aggregate and emulsified or cutback bitumen,
including mixing in a plant of suitable type and capacity,
transporting, laying, compacting and finishing to specified
grades and levels.

Unit = cum
Taking output = 205 Cum 450 tonnes
(i) Using bitumen emulsion and 9.5 mm or 13.2 mm size
aggregate
Composition of mix (450 tonne) is assumed to be as
under:-
Bitumen Emulsion 8 percent By weight of total mix
Filler 2 per cent
Total aggregates 90 per cent
Proportion of aggregates
19 mm to 9.5 mm25 per cent
9.5 mm to 6 mm29 per cent
6 mm to 0.075 mm 36 per cent
a) Labour
Mate day 0.480 0.480 0.480 617.00 296.16 296.16 296.16 L-12
Mazdoor day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.000 14,634.90 43,904.70 P&M-035
(ii) HMP 160 TPH hour 3.750 10,338.30 38,768.63 P&M-036
(iii) HMP 120 TPH hour 5.000 8,372.70 41,863.50 P&M-037
Mechanical broom (2.1m sweeping width) hour 1.743 1.743 1.743 500.40 872.30 872.30 872.30 P&M-052
Air compressor 250 cfm hour 1.743 1.743 1.743 614.25 1,070.76 1,070.76 1,070.76 P&M-029
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.000 9,233.70 27,701.10 P&M-058
(ii) Paver (240HP) hour 3.750 9,233.70 34,626.38 P&M-058
(iii) Paver (174HP) hour 5.000 2,362.50 11,812.50 P&M-059
Electric generator
(i) 500 KVA hour 3.000 8,022.00 24,066.00 P&M-044
(ii) 400 KVA hour 3.750 6,470.10 24,262.88 P&M-045
(iii) 250 KVA hour 5.000 3,475.00 17,375.00 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 4.852 4,279.80 20,766.33 P&M-011
(ii) 2.1 Cum Capacity hour 6.923 2,640.75 18,282.12 P&M-012
(iii) 1 Cum Capacity hour 15.081 1,112.00 16,770.16 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L1 7.51 101,366.02 P&M-117
(ii) 14 cum capacity t.km 450 x L1 8.52 115,053.75 P&M-120
(iii) 10 cum capacity t.km 450 x L1 10.53 142,143.75 P&M-123
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.000 2,883.30 17,299.80 P&M-014
(ii) 14 cum capacity hour 7.500 2,556.75 19,175.63 P&M-015
(iii) 10 cum capacity hour 10.000 2,274.30 22,743.00 P&M-016
Smooth steel wheeled tandem roller for static and P&M-019
vibratory passaes hour 18.141 18.141 18.141 417.00 7,564.63 7,564.63 7,564.63
Pneumatic Tyre roller hour 2.569 3.000 4.000 2,562.00 6,581.58 7,686.00 10,248.00 P&M-022
c) Material
Bitumen emulsion @ 8 per cent tonne 36.000 36.000 36.000 47,662.37 1,715,845.36 1,715,845.36 1,715,845.36 M-077
Filler (lime)@ 2 per cent tonne 9.000 9.000 9.000 3,753.00 33,777.00 33,777.00 33,777.00 M-190
Aggregates size 19 to 9.5 mm - 450 x 0.25 x 1/1.5 cum 75.000 75.000 75.000 1,887.12 141,534.23 141,534.23 141,534.23 M-044
Aggregates size 9.5 to 6 mm - 450 x 0.29 x 1/1.5 cum 87.000 87.000 87.000 1,887.12 164,179.71 164,179.71 164,179.71 M-039
Aggregates size 6 to 0.075 mm - 450 x 0.36 x 1/1.5 M-029
cum 108.000 108.000 108.000 1,887.12 203,809.30 203,809.30 203,809.30
d) Overhead charges @ 8% on @ 10% on @ 12% on
201,363.54 253,321.41 304,597.76
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
271,840.78 278,653.55 284,291.24
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 205 cum = a+b+c+d+e 2,990,248.57 3,065,189.05 3,127,203.63
Rate per cum = (a+b+c+d+e)/205 14,586.58 14,952.14 15,254.65
Say 14,587.00 14,952.00 15,255.00
(Applicable to cases I to IV)
Note 1.Density of aggregates has been assumed 1.5 gms/cc

2. Tack coat where provided will be measured and paid


separately.

5.15 (ii) Using bitumen emulsion and 19 mm or 26.5 mm nominal


size aggregate
Composition of mix (450 tonne) is assumed to be as
under:-
Bitumen Emulsion 8 per cent
Filler2 per cent
Total aggregates 90 per cent
Proportion of aggregates
37.5 mm to 19 mm25 per cent
19 mm to 6 mm 30 per cent
6 mm to 0.075 mm 35 per cent
a) Labour
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Mate day 0.480 0.480 0.480 617.00 296.16 296.16 296.16 L-12
Mazdoor day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.000 14,634.90 43,904.70 P&M-035
(ii) HMP 160 TPH hour 3.750 10,338.30 38,768.63 P&M-036
(iii) HMP 120 TPH hour 5.000 8,372.70 41,863.50 P&M-037
Mechanical broom (2.1m sweeping width) hour 1.743 1.743 1.743 500.40 872.30 872.30 872.30 P&M-052
Air compressor 250 cfm hour 1.743 1.743 1.743 614.25 1,070.76 1,070.76 1,070.76 P&M-029
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.000 9,233.70 27,701.10 P&M-058
(ii) Paver (240HP) hour 3.750 9,233.70 34,626.38 P&M-058
(iii) Paver (174HP) hour 5.000 2,362.50 11,812.50 P&M-059
Electric generator
(i) 500 KVA hour 3.000 8,022.00 24,066.00 P&M-044
(ii) 400 KVA hour 3.750 6,470.10 24,262.88 P&M-045
(iii) 250 KVA hour 5.000 3,475.00 17,375.00 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 4.852 4,279.80 20,766.33 P&M-011
(ii) 2.1 Cum Capacity hour 6.923 2,640.75 18,282.12 P&M-012
(iii) 1 Cum Capacity hour 15.081 1,112.00 16,770.16 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L1 7.51 101,366.02 P&M-117
(ii) 14 cum capacity t.km 450 x L1 8.52 115,053.75 P&M-120
(iii) 10 cum capacity t.km 450 x L1 10.53 142,143.75 P&M-123
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.000 2,883.30 17,299.80 P&M-014
(ii) 14 cum capacity hour 7.500 2,556.75 19,175.63 P&M-015
(iii) 10 cum capacity hour 10.000 2,274.30 22,743.00 P&M-016
Smooth steel wheeled tandem roller for static and P&M-019
vibratory passaes hour 18.141 18.141 18.141 417.00 7,564.63 7,564.63 7,564.63
Pneumatic Tyre roller hour 2.569 3.000 4.000 2,562.00 6,581.58 7,686.00 10,248.00 P&M-022
c) Material
Bitumen emulsion @ 8 per cent tonne 36.000 36.000 36.000 47,662.37 1,715,845.36 1,715,845.36 1,715,845.36 M-077
Filler (lime)@ 2 per cent tonne 9.000 9.000 9.000 3,753.00 33,777.00 33,777.00 33,777.00 M-190
Aggregates size 37.5 to 19 mm - 450 x 0.25 x 1/1.5 M-047
cum 75.000 75.000 75.000 1,887.12 141,534.23 141,534.23 141,534.23
Aggregates size 19 to 6 mm - 450 x 0.3 x 1/1.5 cum 90.000 90.000 90.000 1,887.12 169,841.08 169,841.08 169,841.08 M-046
Aggregates size 6 to 0.075 mm - 450 x 0.35 x 1/1.5 M-029
cum 105.000 105.000 105.000 1,887.12 198,147.93 198,147.93 198,147.93
d) Overhead charges @ 8% on @ 10% on @ 12% on
201,363.54 253,321.41 304,597.76
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
271,840.78 278,653.55 284,291.24
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 205 cum = a+b+c+d+e 2,990,248.57 3,065,189.05 3,127,203.63
Rate per cum = (a+b+c+d+e)/205 14,586.58 14,952.14 15,254.65
Say 14,587.00 14,952.00 15,255.00
Note 1.Density of aggregates has been assumed 1.5 gms/cc

2. Tack coat where provided will be measured and paid


separately.
5.15 (iii) Using cutback bitumen and 9.5 mm or 13.2 mm nominal
size aggregate
Composition of mix (450 tonne) is assumed to be as
under:-
Cutback bitumen 5 per cent
Filler (lime) 2 per cent
Total aggregates 93 per cent
Proportion of aggregates
19 mm to 9.5 mm26 per cent
9.5 mm to 6 mm31 per cent
6 mm to 0.075 mm 36 per cent
a) Labour
Mate day 0.480 0.480 0.480 617.00 296.16 296.16 296.16 L-12
Mazdoor day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.000 14,634.90 43,904.70 P&M-035
(ii) HMP 160 TPH hour 3.750 10,338.30 38,768.63 P&M-036
(iii) HMP 120 TPH hour 5.000 8,372.70 41,863.50 P&M-037
Mechanical broom (2.1m sweeping width) hour 1.743 1.743 1.743 500.40 872.30 872.30 872.30 P&M-052
Air compressor 250 cfm hour 1.743 1.743 1.743 614.25 1,070.76 1,070.76 1,070.76 P&M-029
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.000 9,233.70 27,701.10 P&M-058
(ii) Paver (240HP) hour 3.750 9,233.70 34,626.38 P&M-058
(iii) Paver (174HP) hour 5.000 2,362.50 11,812.50 P&M-059
Electric generator
(i) 500 KVA hour 3.000 8,022.00 24,066.00 P&M-044
(ii) 400 KVA hour 3.750 6,470.10 24,262.88 P&M-045
(iii) 250 KVA hour 5.000 3,475.00 17,375.00 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.009 4,279.80 21,436.22 P&M-011
(ii) 2.1 Cum Capacity hour 7.154 2,640.75 18,891.52 P&M-012
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
(iii) 1 Cum Capacity hour 15.568 1,112.00 17,311.14 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L1 7.51 101,366.02 P&M-117
(ii) 14 cum capacity t.km 450 x L1 8.52 115,053.75 P&M-120
(iii) 10 cum capacity t.km 450 x L1 10.53 142,143.75 P&M-123
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.000 2,883.30 17,299.80 P&M-014
(ii) 14 cum capacity hour 7.500 2,556.75 19,175.63 P&M-015
(iii) 10 cum capacity hour 10.000 2,274.30 22,743.00 P&M-016
Smooth steel wheeled tandem roller for static and P&M-019
vibratory passaes hour 18.141 18.141 18.141 417.00 7,564.63 7,564.63 7,564.63
Pneumatic Tyre roller hour 2.569 3.000 4.000 2,562.00 6,581.58 7,686.00 10,248.00 P&M-022
c) Material
Cutback bitumen @ 5 per cent tonne 22.500 22.500 22.500 46,556.37 1,047,518.35 1,047,518.35 1,047,518.35 M-076
Filler (lime)@ 2 per cent tonne 9.000 9.000 9.000 3,753.00 33,777.00 33,777.00 33,777.00 M-190
Aggregates size 19 to 9.5 mm - 450 x 0.26 x 1/1.5 cum 78.000 78.000 78.000 1,887.12 147,195.60 147,195.60 147,195.60 M-044
Aggregates size 9.5 to 6 mm - 450 x 0..31 x 1/1.5 cum 93.000 93.000 93.000 1,887.12 175,502.45 175,502.45 175,502.45 M-039
Aggregates size 6 to 0.075 mm - 450 x 0.36 x 1/1.5 M-029
cum 108.000 108.000 108.000 1,887.12 203,809.30 203,809.30 203,809.30
d) Overhead charges @ 8% on @ 10% on @ 12% on
149,309.70 188,248.06 226,501.53
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
201,568.09 207,072.87 211,401.42
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 205 cum = a+b+c+d+e 2,217,249.03 2,277,801.52 2,325,415.66
Rate per cum = (a+b+c+d+e)/205 10,815.85 11,111.23 11,343.49
Say 10,816.00 11,111.00 11,343.00
Note 1.Density of aggregates has been assumed 1.5 gms/cc

2. Tack coat where provided will be measured and paid


separately.

5.15 (iv) Using cutback bitumen and 19 mm or 26.5 mm nominal


size aggregate
Composition of mix (450 tonne) is assumed to be as
under:-
Cutback bitumen 5 per cent
Filler2 per cent
Total aggregates 93 per cent
Proportion of aggregates
37.5 mm to 19 mm25 per cent
19 mm to 6 mm 30 per cent
6 mm to 0.075 mm 38 per cent
a) Labour
Mate day 0.480 0.480 0.480 617.00 296.16 296.16 296.16 L-12
Mazdoor day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.000 14,634.90 43,904.70 P&M-035
(ii) HMP 160 TPH hour 3.750 10,338.30 38,768.63 P&M-036
(iii) HMP 120 TPH hour 5.000 8,372.70 41,863.50 P&M-037
Mechanical broom (2.1m sweeping width) hour 1.743 1.743 1.743 500.40 872.30 872.30 872.30 P&M-052
Air compressor 250 cfm hour 1.743 1.743 1.743 614.25 1,070.76 1,070.76 1,070.76 P&M-029
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.000 9,233.70 27,701.10 P&M-058
(ii) Paver (240HP) hour 3.750 9,233.70 34,626.38 P&M-058
(iii) Paver (174HP) hour 5.000 2,362.50 11,812.50 P&M-059
Electric generator
(i) 500 KVA hour 3.000 8,022.00 24,066.00 P&M-044
(ii) 400 KVA hour 3.750 6,470.10 24,262.88 P&M-045
(iii) 250 KVA hour 5.000 3,475.00 17,375.00 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.009 4,279.80 21,436.22 P&M-011
(ii) 2.1 Cum Capacity hour 7.154 2,640.75 18,891.52 P&M-012
(iii) 1 Cum Capacity hour 15.568 1,112.00 17,311.14 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L1 7.51 101,366.02 P&M-117
(ii) 14 cum capacity t.km 450 x L1 8.52 115,053.75 P&M-120
(iii) 10 cum capacity t.km 450 x L1 10.53 142,143.75 P&M-123
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.000 2,883.30 17,299.80 P&M-014
(ii) 14 cum capacity hour 7.500 2,556.75 19,175.63 P&M-015
(iii) 10 cum capacity hour 10.000 2,274.30 22,743.00 P&M-016
Smooth steel wheeled tandem roller for static and P&M-019
vibratory passaes hour 18.141 18.141 18.141 417.00 7,564.63 7,564.63 7,564.63
Pneumatic Tyre roller hour 2.569 3.000 4.000 2,562.00 6,581.58 7,686.00 10,248.00 P&M-022
c) Material
Cutback bitumen on @ 5 per cent tonne 22.500 22.500 22.500 46,556.37 1,047,518.35 1,047,518.35 1,047,518.35 M-076
Filler (lime)@ 2 per cent tonne 9.000 9.000 9.000 3,753.00 33,777.00 33,777.00 33,777.00 M-190
Aggregates size 37.5 to 19 mm - 450 x 0.25 x 1/1.5 M-047
cum 75.000 75.000 75.000 1,887.12 141,534.23 141,534.23 141,534.23
Aggregates size 19 to 6 mm - 450 x 0.3 x 1/1.5 cum 90.000 90.000 90.000 1,887.12 169,841.08 169,841.08 169,841.08 M-046
Aggregates size 6 to 0.075 mm - 450 x0.38 x 1/1.5 cum 114.000 114.000 114.000 1,887.12 215,132.03 215,132.03 215,132.03 M-030
d) Overhead charges @ 8% on @ 10% on @ 12% on
149,309.70 188,248.06 226,501.53
(a+b+c) (a+b+c) (a+b+c)
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
e) Contractor's profit @ 10% on @ 10% on @ 10% on
201,568.09 207,072.87 211,401.42
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 205 cum = a+b+c+d+e 2,217,249.03 2,277,801.52 2,325,415.66
Rate per cum = (a+b+c+d+e)/205 10,815.85 11,111.23 11,343.49
Say 10,816.00 11,111.00 11,343.00
Note 1.Density of aggregates has been assumed 1.5 gms/cc

2. Tack coat where provided will be measured and paid


separately.
5.16 506 Sand Asphalt Base Course
Providing, laying and rolling sand-asphalt base course
composed of sand, mineral filler and bituminous binder
on a prepared sub-grade or sub-base to the lines, levels,
grades and cross sections as per the drawings including
mixing in a plant of suitable type and capacity,
transporting, laying, compacting and finishing.

Unit = cum
Taking output = 205 Cum 450 tonnes
a) Labour
Mate day 0.480 0.480 0.480 617.00 296.16 296.16 296.16 L-12
Mazdoor day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.000 14,634.90 43,904.70 P&M-035
(ii) HMP 160 TPH hour 3.750 10,338.30 38,768.63 P&M-036
(iii) HMP 120 TPH hour 5.000 8,372.70 41,863.50 P&M-037
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.000 9,233.70 27,701.10 P&M-058
(ii) Paver (240HP) hour 3.750 9,233.70 34,626.38 P&M-058
(iii) Paver (174HP) hour 5.000 2,362.50 11,812.50 P&M-059
Electric generator
(i) 500 KVA hour 3.000 8,022.00 24,066.00 P&M-044
(ii) 400 KVA hour 3.750 6,470.10 24,262.88 P&M-045
(iii) 250 KVA hour 5.000 3,475.00 17,375.00 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.044 4,279.80 21,589.05 P&M-011
(ii) 2.1 Cum Capacity hour 7.441 2,640.75 19,648.50 P&M-012
(iii) 1 Cum Capacity hour 15.664 1,112.00 17,418.60 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L1 7.51 101,366.02 P&M-117
(ii) 14 cum capacity t.km 450 x L1 8.52 115,053.75 P&M-120
(iii) 10 cum capacity t.km 450 x L1 10.53 142,143.75 P&M-123
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.000 2,883.30 17,299.80 P&M-014
(ii) 14 cum capacity hour 7.500 2,556.75 19,175.63 P&M-015
(iii) 10 cum capacity hour 10.000 2,274.30 22,743.00 P&M-016
Smooth steel wheeled tandem roller for static and P&M-019
vibratory passaes hour 18.141 18.141 18.141 417.00 7,564.63 7,564.63 7,564.63
c) Material
Composition of mix (450 tonne) is assumed to be as
under:-
Density 2.20 tonne per cum
Weight450 tonne
Bitumen5 per cent
Filler2 per cent
Sand of size 4.75 to 0.075 mm 93 per cent
Bitumen@ 5 per cent tonne 22.500 22.500 22.500 46,556.37 1,047,518.35 1,047,518.35 1,047,518.35 M-074
Filler (lime)@ 2 per cent tonne 9.000 9.000 9.000 3,753.00 33,777.00 33,777.00 33,777.00 M-190
Sand of size 4.75 to 0.075 mm - 450 x 0.93 x 1/1.5 cum 288.620 288.620 288.620 1,994.03 575,517.23 575,517.23 575,517.23 M-004
d) Overhead charges @ 8% on @ 10% on @ 12% on
152,560.75 192,261.84 230,932.68
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
205,957.01 211,488.02 215,537.17
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 205 cum = a+b+c+d+e 2,265,527.07 2,326,368.27 2,370,908.85
Rate per cum = (a+b+c+d+e)/205 11,051.35 11,348.14 11,565.41
Say 11,051.00 11,348.00 11,565.00
Note 1. Tack coat will be measured and paid separately

5.17 Crack Prevention Courses


(i) Stress absorbing membrane (SAM) crack width less than
6 mm
Providing and laying of a stress absorbing membrane
over a cracked road surface, with crack width below 6
mm after cleaning with a mechanical broom, using
modified binder complying with IRC:SP: 53, sprayed at
the rate of 9 kg per 10 sqm and spreading 5.6 mm
crushed stone aggregates @ 0.11 cum per 10 sqm with
hydraulic chip spreader, sweeping the surface for uniform
spread of aggregates and surface finished to conform to
clause 902.

Unit = sqm
Taking output = 10500 sqm
a) Labour
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Mazdoor day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 3.125 3.125 3.125 500.40 1,563.75 1,563.75 1,563.75 P&M-052
Air compressor 250 cfm hour 3.125 3.125 3.125 614.25 1,919.53 1,919.53 1,919.53 P&M-029
Bitumen pressure distributor (Spraying width 4.5 m) P&M-053
hour 2.917 2.917 2.917 1,729.35 5,043.94 5,043.94 5,043.94
Hydraulic Chip spreader hour 5.397 5.397 5.397 2,220.75 11,984.93 11,984.93 11,984.93 P&M-065
Smooth wheeled road roller 8-10 tonne hour 5.397 5.397 5.397 417.00 2,250.46 2,250.46 2,250.46 P&M-019
c) Material
Modified binder tonne 9.450 9.450 9.450 46,896.37 443,170.71 443,170.71 443,170.71 M-078
Crushed stone aggregates 5.6 mm size cum 105.000 105.000 105.000 1,887.12 198,147.93 198,147.93 198,147.93 M-049
d) Overhead charges @ 8% on @ 10% on @ 12% on
53,298.08 66,622.60 79,947.12
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
71,952.41 73,284.86 74,617.32
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10500 Sqm = a+b+c+d+e 791,476.54 806,133.51 820,790.48
Rate per Sqm = (a+b+c+d+e)/10500 75.38 76.77 78.17
Say 75.00 77.00 78.00
5.17 (ii) Stress absorbing membrane (SAM) with crack width 6
mm to 9 mm
Providing and laying of a stress absorbing membrane
over a cracked road surface, with crack width 6 to 9 mm
after cleaning with a mechanical broom, using modified
binder complying with IRC:SP: 53, sprayed at the rate of
11 kg per 10 sqm and spreading 11.2 mm crushed stone
aggregates @ 0.12 cum per 10 sqm, sweeping the
surface for uniform spread of aggregates and surface
finished to conform to clause 902.

Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Mazdoor day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 3.125 3.125 3.125 500.40 1,563.75 1,563.75 1,563.75 P&M-052
Air compressor 250 cfm hour 3.125 3.125 3.125 614.25 1,919.53 1,919.53 1,919.53 P&M-029
Bitumen pressure distributor (Spraying width 4.5 m) P&M-053
hour 2.917 2.917 2.917 1,729.35 5,043.94 5,043.94 5,043.94
Hydraulic Chip spreader hour 5.397 5.397 5.397 2,220.75 11,984.93 11,984.93 11,984.93 P&M-065
Smooth wheeled road roller 8-10 tonne hour 5.397 5.397 5.397 417.00 2,250.46 2,250.46 2,250.46 P&M-019
c) Material
Modified binder tonne 11.550 11.550 11.550 46,896.37 541,653.09 541,653.09 541,653.09 M-078
Crushed stone chipping 11.2 mm size cum 105.000 105.000 105.000 1,887.12 198,147.93 198,147.93 198,147.93 M-050
d) Overhead charges @ 8% on @ 10% on @ 12% on
61,176.67 76,470.84 91,765.01
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
82,588.51 84,117.93 85,647.34
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10500 Sqm = a+b+c+d+e 908,473.60 925,297.19 942,120.77
Rate per Sqm = (a+b+c+d+e)/10500 86.52 88.12 89.73
Say 87.00 88.00 90.00
5.17 (iii) Stress absorbing membrane (SAM) crack width above 9
mm and cracked area above 50 per cent

Providing and laying a single coat of a stress absorbing


membrane over a cracked road surface, with crack width
above 9 mm and cracked area above 50 per cent after
cleaning with a mechanical broom, using modified binder
complying with IRC:SP: 53, sprayed at the rate of 15 kg
per 10 sqm and spreading 11.2 mm crushed stone
aggregates @ 0.12 cum per 10 sqm, sweeping the
surface for uniform spread of aggregates and surface
finished to conform to clause 902.

Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 0.240 0.240 617.00 148.08 148.08 148.08 L-12
Mazdoor day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Machinery
Mechanical broom (2.1m sweeping width) hour 3.125 3.125 3.125 500.40 1,563.75 1,563.75 1,563.75 P&M-052
Air compressor 250 cfm hour 3.125 3.125 3.125 614.25 1,919.53 1,919.53 1,919.53 P&M-029
Bitumen pressure distributor (Spraying width 4.5 m) P&M-053
hour 2.917 2.917 2.917 1,729.35 5,043.94 5,043.94 5,043.94
Hydraulic Chip spreader hour 5.397 5.397 5.397 2,220.75 11,984.93 11,984.93 11,984.93 P&M-065
Smooth wheeled road roller 8-10 tonne hour 5.397 5.397 5.397 417.00 2,250.46 2,250.46 2,250.46 P&M-019
c) Material
Modified binder tonne 15.750 15.750 15.750 46,896.37 738,617.84 738,617.84 738,617.84 M-078
Crushed stone aggregates 11.2 mm size cum 126.000 126.000 126.000 1,887.12 237,777.51 237,777.51 237,777.51 M-050
d) Overhead charges @ 8% on @ 10% on @ 12% on
80,198.69 100,248.36 120,298.03
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
108,268.23 110,273.19 112,278.16
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10500 Sqm = a+b+c+d+e 1,190,950.50 1,213,005.14 1,235,059.77
Rate per Sqm = (a+b+c+d+e)/10500 113.42 115.52 117.62
Say 113.00 116.00 118.00
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Note In case 2nd coat is also required to be provided, material
provided for the 2nd coat shall be as per Table 500-43.

5.17 (iv) Case - IV : Bitumen impregnated geotextile


Providing and laying of premix of crushed stone
aggregates and emulsion binder, mixed in a batch type
cold mixing plant, laid over prepared surface, by paver
finisher, rolled with a pneumatic tyred roller initially and
finished with a smooth steel wheel roller, all as per clause
518.3

Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.280 0.280 0.280 617.00 172.76 172.76 172.76 L-12
Mazdoor day 5.000 5.000 5.000 511.52 2,557.60 2,557.60 2,557.60 L-13
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Machinery
Mechanical broom (2.1m sweeping width) hour 1.042 1.042 1.042 500.40 521.25 521.25 521.25 P&M-052
Air compressor 250 cfm hour 1.042 1.042 1.042 614.25 639.84 639.84 639.84 P&M-029
Bitumen pressure distributor (Spraying width 4.5 m) P&M-053
hour 0.972 0.972 0.972 1,729.35 1,681.31 1,681.31 1,681.31
Pneumatic roller hour 2.000 2.000 2.000 2,562.00 5,124.00 5,124.00 5,124.00 P&M-022
c) Material
Paving grade bitumen of 80 - 100 penetration @ 1.05 kg
per sqm tonne 3.680 3.680 3.680 48,006.37 176,663.45 176,663.45 176,663.45 M-075
Geotextile including 10 per cent for overlaps sqm 3850.000 3850.000 3850.000 62.55 240,817.50 240,817.50 240,817.50 M-107
d) Overhead charges @ 8% on @ 10% on @ 12% on
34,344.73 42,930.92 51,517.10
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
46,365.39 47,224.01 48,082.63
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 3500 Sqm = a+b+c+d+e 510,019.30 519,464.10 528,908.90
Rate per Sqm = (a+b+c+d+e)/3500 145.72 148.42 151.12
Say 146.00 148.00 151.00
NOTE As bitumen overlay construction shall follow closely the
fabric placement on the same day, an output of 3500 sqm
only has been considered for the analysis which will
cover a length of 500 m, of 7 m wide carriagway. This can
be conveniently overlaid by a bitumenious course in a
day

5.18 518.3 Recipe Cold Mix


Providing and laying of premix of crushed stone
aggregates and emulsion binder, mixed in a batch type
cold mixing plant, laid over prepared surface, by paver
finisher, rolled with a pneumatic tyred roller initially and
finished with a smooth steel wheel roller, all as per clause
518.3

Unit = cum
Taking output 205 Cum 450 tonnes
(i) 75 mm thickness
a) Labour
Mate day 0.480 0.480 0.480 617.00 296.16 296.16 296.16 L-12
Mazdoor day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.000 14,634.90 43,904.70 P&M-035
(ii) HMP 160 TPH hour 3.750 10,338.30 38,768.63 P&M-036
(iii) HMP 120 TPH hour 5.000 8,372.70 41,863.50 P&M-037
Electric generator
(i) 500 KVA hour 3.000 8,022.00 24,066.00 P&M-044
(ii) 400 KVA hour 3.750 6,470.10 24,262.88 P&M-045
(iii) 250 KVA hour 5.000 3,475.00 17,375.00 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.400 4,279.80 23,110.92 P&M-011
(ii) 2.1 Cum Capacity hour 8.027 2,640.75 21,197.37 P&M-012
(iii) 1 Cum Capacity hour 16.500 1,112.00 18,348.00 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L1 7.51 101,366.02 P&M-117
(ii) 14 cum capacity t.km 450 x L1 8.52 115,053.75 P&M-120
(iii) 10 cum capacity t.km 450 x L1 10.53 142,143.75 P&M-123
For loading & unloading time
(i) 18 cum capacity hour 6.000 2,883.30 17,299.80 P&M-014
(ii) 14 cum capacity hour 7.500 2,556.75 19,175.63 P&M-015
(iii) 10 cum capacity hour 10.000 2,274.30 22,743.00 P&M-016
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.000 9,233.70 27,701.10 P&M-058
(ii) Paver (240HP) hour 3.750 9,233.70 34,626.38 P&M-058
(iii) Paver (174HP) hour 5.000 2,362.50 11,812.50 P&M-059
Smooth steel wheeled tandem roller for static and P&M-019
vibratory passaes hour 11.831 11.831 11.831 417.00 4,933.61 4,933.61 4,933.61
Pnumetic Tyre roller hour 2.400 3.000 4.000 2,562.00 6,148.80 7,686.00 10,248.00 P&M-022
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 1.442 1,501.00 2,164.44 P&M-023
(ii) 12 KL capacity hour 1.923 1,327.00 2,551.82 P&M-024
(iii) 6 KL capacity hour 3.816 1,005.00 3,835.08 P&M-025
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
c) Material
Bitumen emulsion @ 45 litres per tonne tonne 20.250 20.250 20.250 46,556.37 942,766.51 942,766.51 942,766.51 M-074
Crushed stone aggregates 40 mm nominal size cum 297.000 297.000 297.000 1,887.12 560,475.56 560,475.56 560,475.56 M-054
Cost of water KL 6.000 6.000 6.000 16.00 96.00 96.00 96.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
140,859.11 177,829.96 214,001.52
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
190,159.80 195,612.95 199,734.75
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 205 cum = a+b+c+d+e 2,091,757.83 2,151,742.49 2,197,082.23
Rate per cum = (a+b+c+d+e)/205 10,203.70 10,496.30 10,717.47
Say 10,204.00 10,496.00 10,717.00
Note (Case I to III)
1. These mixes are considered suitable for minor repair
work and temporary road surface improvement.

2. In case concrete mixtures are required to be used for


mixing, a number of these will be needed to match the
capacity of road rollers.
3. Tack coat, where provided, will be measured and paid
separately.
5.18 (ii) 40 mm thickness
a) Labour
Mate day 0.480 0.480 0.480 617.00 296.16 296.16 296.16 L-12
Mazdoor day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.000 14,634.90 43,904.70 P&M-035
(ii) HMP 160 TPH hour 3.750 10,338.30 38,768.63 P&M-036
(iii) HMP 120 TPH hour 5.000 8,372.70 41,863.50 P&M-037
Electric generator
(i) 500 KVA hour 3.000 8,022.00 24,066.00 P&M-044
(ii) 400 KVA hour 3.750 6,470.10 24,262.88 P&M-045
(iii) 250 KVA hour 5.000 3,475.00 17,375.00 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.125 4,279.80 21,933.98 P&M-011
(ii) 2.1 Cum Capacity hour 7.553 2,640.75 19,944.61 P&M-012
(iii) 1 Cum Capacity hour 15.944 1,112.00 17,730.22 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L1 7.51 101,366.02 P&M-117
(ii) 14 cum capacity t.km 450 x L1 8.52 115,053.75 P&M-120
(iii) 10 cum capacity t.km 450 x L1 10.53 142,143.75 P&M-123
For loading & unloading time
(i) 18 cum capacity hour 6.000 2,883.30 17,299.80 P&M-014
(ii) 14 cum capacity hour 7.500 2,556.75 19,175.63 P&M-015
(iii) 10 cum capacity hour 10.000 2,274.30 22,743.00 P&M-016
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.000 9,233.70 27,701.10 P&M-058
(ii) Paver (240HP) hour 3.750 9,233.70 34,626.38 P&M-058
(iii) Paver (174HP) hour 5.000 2,362.50 11,812.50 P&M-059
Smooth steel wheeled tandem roller for static and P&M-019
vibratory passaes hour 11.831 11.831 11.831 417.00 4,933.61 4,933.61 4,933.61
Pnumetic Tyre roller hour 2.400 3.000 4.000 2,562.00 6,148.80 7,686.00 10,248.00 P&M-022
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 1.602 1,501.00 2,404.60 P&M-023
(ii) 12 KL capacity hour 2.136 1,327.00 2,834.47 P&M-024
(iii) 6 KL capacity hour 4.241 1,005.00 4,262.21 P&M-025
c) Material
Bitumen emulsion @ 70 litres per tonne tonne 31.500 31.500 31.500 46,556.37 1,466,525.69 1,466,525.69 1,466,525.69 M-074
Crushed stone aggregates 14 mm nominal size cum 287.000 287.000 287.000 1,887.12 541,604.33 541,604.33 541,604.33 M-051
Cost of water KL 6.000 6.000 6.000 16.00 96.00 96.00 96.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
181,175.21 228,221.74 274,565.19
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
244,586.53 251,043.92 256,260.84
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 205 cum = a+b+c+d+e 2,690,451.81 2,761,483.07 2,818,869.29
Rate per cum = (a+b+c+d+e)/205 13,124.16 13,470.65 13,750.58
Say 13,124.00 13,471.00 13,751.00
5.18 (iii) 25 mm thickness
a) Labour
Mate day 0.480 0.480 0.480 617.00 296.16 296.16 296.16 L-12
Mazdoor day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.000 14,634.90 43,904.70 P&M-035
(ii) HMP 160 TPH hour 3.750 10,338.30 38,768.63 P&M-036
(iii) HMP 120 TPH hour 5.000 8,372.70 41,863.50 P&M-037
Electric generator
(i) 500 KVA hour 3.000 8,022.00 24,066.00 P&M-044
(ii) 400 KVA hour 3.750 6,470.10 24,262.88 P&M-045
(iii) 250 KVA hour 5.000 3,475.00 17,375.00 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 4.576 4,279.80 19,585.53 P&M-011
(ii) 2.1 Cum Capacity hour 6.750 2,640.75 17,825.06 P&M-012
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
(iii) 1 Cum Capacity hour 14.211 1,112.00 15,802.11 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L1 7.51 101,366.02 P&M-117
(ii) 14 cum capacity t.km 450 x L1 8.52 115,053.75 P&M-120
(iii) 10 cum capacity t.km 450 x L1 10.53 142,143.75 P&M-123
For loading & unloading time
(i) 18 cum capacity hour 6.000 2,883.30 17,299.80 P&M-014
(ii) 14 cum capacity hour 7.500 2,556.75 19,175.63 P&M-015
(iii) 10 cum capacity hour 10.000 2,274.30 22,743.00 P&M-016
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.000 9,233.70 27,701.10 P&M-058
(ii) Paver (240HP) hour 3.750 9,233.70 34,626.38 P&M-058
(iii) Paver (174HP) hour 5.000 2,362.50 11,812.50 P&M-059
Smooth steel wheeled tandem roller for static and P&M-019
vibratory passaes hour 11.831 11.831 11.831 417.00 4,933.61 4,933.61 4,933.61
Pnumetic Tyre roller hour 2.400 3.000 4.000 2,562.00 6,148.80 7,686.00 10,248.00 P&M-022
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 1.807 1,501.00 2,712.31 P&M-023
(ii) 12 KL capacity hour 2.409 1,327.00 3,196.74 P&M-024
(iii) 6 KL capacity hour 4.788 1,005.00 4,811.94 P&M-025
c) Material
Bitumen emulsion @ 85 litres per tonne tonne 38.250 38.250 38.250 46,556.37 1,780,781.19 1,780,781.19 1,780,781.19 M-074
Crushed stone aggregates 6 mm nominal size cum 270.000 270.000 270.000 1,887.12 509,523.24 509,523.24 509,523.24 M-049
Cost of water KL 6.000 6.000 6.000 16.00 96.00 96.00 96.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
203,585.90 256,263.45 308,260.71
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
274,840.96 281,889.80 287,710.00
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 205 cum = a+b+c+d+e 3,023,250.60 3,100,787.80 3,164,810.00
Rate per cum = (a+b+c+d+e)/205 14,747.56 15,125.79 15,438.10
Say 14,748.00 15,126.00 15,438.00
15.19 A
Bituminous Concrete Grading I Using Waste Plastic
Providing and laying bituminous concrete with higher
capacity batch type hot mix plant using crushed
aggregates of specified grading, premixed with
bituminous binder @ 5.2 per cent of mix and filler,
transporting the hot mix to work site, laying with a
hydrostatic paver finisher with sensor control to the
required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the
desired compaction as per MORTH specification clause
No. 507 complete in all respects

Unit = cum
Taking output = 191 cum 450.76 tonnes
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.005 14,634.90 43,978.85 P&M-035
(ii) HMP 160 TPH hour 3.756 10,338.30 38,834.10 P&M-036
(iii) HMP 120 TPH hour 5.008 8,372.70 41,934.20 P&M-037
Mechanical broom (2.1m sweeping width) hour 1.137 1.137 1.137 500.40 568.91 568.91 568.91 P&M-052
Air compressor 250 cfm hour 1.137 1.137 1.137 614.25 698.34 698.34 698.34 P&M-029
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.005 9,233.70 27,747.88 P&M-058
(ii) Paver (240HP) hour 3.756 9,233.70 34,684.86 P&M-058
(iii) Paver (174HP) hour 5.008 2,362.50 11,832.45 P&M-059
Electric generator
(i) 500 KVA hour 3.005 8,022.00 24,106.64 P&M-044
(ii) 400 KVA hour 3.756 6,470.10 24,303.85 P&M-045
(iii) 250 KVA hour 5.008 3,475.00 17,404.34 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.078 4,279.80 21,731.00 P&M-011
(ii) 2.1 Cum Capacity hour 7.506 2,640.75 19,821.41 P&M-012
(iii) 1 Cum Capacity hour 15.694 1,112.00 17,452.08 P&M-013
Tipper
For Transportation Mix
(i) 18 cum capacity t.km 450.76 x L1 7.51 101,537.21 P&M-117
(ii) 14 cum capacity t.km 450.76 x L1 8.52 115,248.06 P&M-120
(iii) 10 cum capacity t.km 450.76 x L1 10.53 142,383.82 P&M-123
Loading & unloading time for Mix
(i) 18 cum capacity hour 6.010 2,883.30 17,329.02 P&M-014
(ii) 14 cum capacity hour 7.513 2,556.75 19,208.01 P&M-015
(iii) 10 cum capacity hour 10.017 2,274.30 22,781.41 P&M-016

Smooth steel wheeled tandem roller for static and P&M-019


vibratory passaes hour 11.831 11.831 11.831 417.00 4,933.61 4,933.61 4,933.61
Pnumetic Tyre roller hour 2.404 3.005 4.007 2,562.00 6,159.18 7,698.98 10,265.31 P&M-022
Shredding Machine hour 1.250 1.250 1.250 416.00 520.04 520.04 520.04 P&M-79001
c) Material
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
i) Bitumen@ 4.78 per cent of mix tonne 21.564 21.564 21.564 46,556.37 1,003,958.27 1,003,958.27 1,003,958.27 M-074
ii) Plastic @ 8 per cent of Bitumen tonne 1.875 1.875 1.875 5,000.00 9,375.81 9,375.81 9,375.81
iii) Aggregate
Total weight of mix = 450.760 tonnes
Weight of bitumen = 21.564 tonnes
Weight of Plastic = 1.875 tonnes
Weight of aggregate = 427.320 tonnes
Taking density of aggregate = 1.5 ton/cum
* Grading - I-19 mm (Nominal Size)
20 - 10 mm 38 per cent cum 108.255 108.255 108.255 1,887.12 204,289.61 204,289.61 204,289.61 M-045
10 - 5 mm 17 per cent cum 48.430 48.430 48.430 1,887.12 91,392.72 91,392.72 91,392.72 M-039
5 mm and below 43 per cent cum 122.499 122.499 122.499 1,887.12 231,169.82 231,169.82 231,169.82 M-029
Filler @ 2 per cent of weight of aggregates. tonnes 8.546 8.546 8.546 3,753.00 32,074.68 32,074.68 32,074.68 M-081
* Any one of the alternative may be adopted as per
approved design
* Grading - I-19 mm (Nominal Size)
d) Overhead charges @ 8% on @ 10% on @ 12% on
146,219.27 184,495.03 221,904.56
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
197,396.01 202,944.54 207,110.92
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 191 cum = a+b+c+d+e 2,171,356.13 2,232,118.42 2,277,948.67
Rate per cum = (a+b+c+d+e)/191 11,368.36 11,686.48 11,926.43
Say 11,368.00 11,686.00 11,926.00
Note *1.Quantity of Bitumen has been taken for analysis
purpose. The actual quantity will depend upon job mix
formula.
2. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.

2. In case BC is laid over freshly laid tack coat, provision


of mechanical broom and 2 mazdoors shall be deleted as
the same has been included in the cost of tack coat.

3. The individual density for each size of aggregates to be


used for construction i.e. 37.5-25 mm, 25-10 mm etc.
should be found in the laboratory and accordingly the
quantities should be ammended for use in field. The
average density of 1.5 tonne/cum is only a reference
density in this Data Book.

4. The individual percentage of aggregates should be


calculated from the total weight of dry aggregates i.e..
excluding the weight of bitumen. The weight of filler will
also be 2 per cent by weight of dry aggregates.

B
Bituminous Concrete Grading 2 Using Waste Plastic
Providing and laying bituminous concrete with higher
capacity batch type hot mix plant using crushed
aggregates of specified grading, premixed with
bituminous binder @ 5.4 per cent of mix and filler,
transporting the hot mix to work site, laying with a
hydrostatic paver finisher with sensor control to the
required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the
desired compaction as per MORTH specification clause
No. 507 complete in all respects

Unit = cum
Taking output = 191 cum 450.76 tonnes
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.005 14,634.90 43,978.85 P&M-035
(ii) HMP 160 TPH hour 3.756 10,338.30 38,834.10 P&M-036
(iii) HMP 120 TPH hour 5.008 8,372.70 41,934.20 P&M-037
Mechanical broom (2.1m sweeping width) hour 1.624 1.624 1.624 500.40 812.72 812.72 812.72 P&M-052
Air compressor 250 cfm hour 1.624 1.624 1.624 614.25 997.63 997.63 997.63 P&M-029
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.005 9,233.70 27,747.88 P&M-058
(ii) Paver (240HP) hour 3.756 9,233.70 34,684.86 P&M-058
(iii) Paver (174HP) hour 5.008 2,362.50 11,832.45 P&M-059
Electric generator
(i) 500 KVA hour 3.005 8,022.00 24,106.64 P&M-044
(ii) 400 KVA hour 3.756 6,470.10 24,303.85 P&M-045
(iii) 250 KVA hour 5.008 3,475.00 17,404.34 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 4.993 4,279.80 21,370.87 P&M-011
(ii) 2.1 Cum Capacity hour 7.362 2,640.75 19,441.48 P&M-012
(iii) 1 Cum Capacity hour 15.520 1,112.00 17,258.37 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 450.76 x L1 7.51 101,537.21 P&M-117
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
(ii) 14 cum capacity t.km 450.76 x L1 8.52 115,248.06 P&M-120
(iii) 10 cum capacity t.km 450.76 x L1 10.53 142,383.82 P&M-123
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.010 2,883.30 17,329.02 P&M-014
(ii) 14 cum capacity hour 7.513 2,556.75 19,208.01 P&M-015
(iii) 10 cum capacity hour 10.017 2,274.30 22,781.41 P&M-016
Smooth steel wheeled tandem roller for static and P&M-019
vibratory passaes hour 16.902 16.902 16.902 417.00 7,048.02 7,048.02 7,048.02
Pneumatic Tyre roller hour 2.404 3.005 4.007 2,562.00 6,159.18 7,698.98 10,265.31 P&M-022
Shredding Machine hour 1.298 1.298 1.298 416.00 540.05 540.05 540.05 P&M-79001
c) Material
i) Bitumen@ 4.97 per cent of mix tonne 22.394 22.394 22.394 46,556.37 1,042,572.05 1,042,572.05 1,042,572.05 M-074
ii) Plastic @ 8 per cent of Bitumen tonne 1.947 1.947 1.947 5,000.00 9,736.42 9,736.42 9,736.42
iii) Aggregate
Total weight of mix = 450.76 tonnes
Weight of bitumen = 22.39 tonnes
Weight of Plastic = 1.95 tonnes
Weight of aggregate = 426.42 tonnes
Taking density of aggregate = 1.5 ton/cum
Grading - II-13 mm (Nominal Size)
13.2 - 10 mm 21 per cent cum 59.699 99.498 99.498 1,887.12 112,658.71 187,764.52 187,764.52 M-043
10 - 5 mm 17 per cent cum 48.327 65.384 65.384 1,887.12 91,199.91 123,388.11 123,388.11 M-039
5 mm and below 60 per cent cum 170.568 113.712 113.712 1,887.12 321,882.03 214,588.02 214,588.02 M-029
Filler @ 2 per cent of weight of aggregates. tonnes 8.528 8.528 8.528 3,753.00 32,007.01 32,007.01 32,007.01 M-081
* Any one of the alternative may be adopted as per
approved design
* Grading - I-19 mm (Nominal Size)
d) Overhead charges @ 8% on @ 10% on @ 12% on
149,428.28 188,504.31 226,738.04
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
201,728.17 207,354.74 211,622.17
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 191 cum = a+b+c+d+e 2,219,009.91 2,280,902.19 2,327,843.90
Rate per cum = (a+b+c+d+e)/191 11,617.85 11,941.90 12,187.66
Say 11,618.00 11,942.00 12,188.00
Note *1.Quantity of Bitumen & Plastic have been taken for
analysis purpose. The actual quantity will depend upon
job mix formula.
2. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.

3. In case BC is laid over freshly laid tack coat, provision


of mechanical broom and 2 mazdoors shall be deleted as
the same has been included in the cost of tack coat.

4. The individual density for each size of aggregates to be


used for construction i.e. 37.5-25 mm, 25-10 mm etc.
should be found in the laboratory and accordingly the
quantities should be ammended for use in field. The
average density of 1.5 tonne/cum is only a reference
density in this Data Book.

5. The individual percentage of aggregates should be


calculated from the total weight of dry aggregates i.e..
excluding the weight of bitumen. The weight of filler will
also be 2 per cent by weight of dry aggregates.
CHAPTER-6
CEMENT CONCRETE PAVEMENTS
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium Small
(Rs.) Large Project Input ref.
Specification Project Project Project Project Project
6.01 601 Dry Lean Cement Concrete Sub- base
Construction of dry lean cement concrete Sub- base over a
prepared sub-grade with coarse and fine aggregate
conforming to IS: 383, the size of coarse aggregate not
exceeding 25 mm, aggregate cement ratio not to exceed 15:1,
aggregate gradation after blending to be as per table 600-1,
optimum moisture content to be determined during trial length
construction, concrete strength not to be less than 10 Mpa at 7
days, mixed in a batching plant, transported to site, laid with a
paver with electronic sensor, compacting with 8-10 tonnes
vibratory roller, finishing and curing.

Unit = cum
Taking output 450 cum
990 tonne
a) Labour
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Mazdoor day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
b) Machinery
Paver with electronic sensor
(i) Paver Finisher Concrete with 300 HP Motor hour 2.045 28,108.50 57,494.66 P&M-060
(ii) Paver Finisher Concrete with 241 HP Motor 3.000 18,201.75 54,605.25 P&M-061
(iii) Paver Finisher Concrete with 118 HP Motor 5.625 4,517.10 25,408.69 P&M-062
Vibratory roller 8-10 t capacity hour 2.045 3.000 5.625 2,562.00 5,240.45 7,686.00 14,411.25 P&M-022
Tipper
For Transportation
(i) 18 cum capacity t.km 990 x L1 6.18 183,501.45 P&M-116
(ii) 14 cum capacity t.km 990 x L1 7.01 208,280.16 P&M-119
(iii) 10 cum capacity t.km 990 x L1 8.66 257,320.80 P&M-122
For loading & unloading Time
(i) 18 cum capacity hour 4.545 2,883.30 13,104.60 P&M-014
(ii) 14 cum capacity hour 5.500 2,556.75 14,062.13 P&M-015
(iii) 10 cum capacity hour 10.625 2,274.30 24,164.44 P&M-016
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 1.509xL1+7.
1,501.00 78,825.02 P&M-023
245
(ii) 12 KL capacity hour 2.013xL1+9.6
1,327.00 92,956.35 P&M-024
6
(iii) 6 KL capacity hour 4.025xL1+1
1,005.00 140,770.35 P&M-025
9.32

c) Material
Concrete from sub-analysis of concrete Rate
(i) Using Batching Plant 240 Cum Capacity Sub-
Analysis of
cum 450.000 3,500.00 1,575,000.00
Concrete -
20.18 A
(ii) Using Batching Plant 240 Cum Capacity Sub-
Analysis of
cum 450.000 3,500.00 1,575,000.00
Concrete -
20.18 A
(iii) Using Batching Plant 120 Cum Capacity Sub-
Analysis of
cum 450.000 3,530.00 1,588,500.00
Concrete -
20.18 C
Cost of water (Curing) KL 217.350 217.350 217.350 16.00 3,477.60 3,477.60 3,477.60 M-191

d) Overhead charges @ 8% on @ 10% on @ 12% on


153,726.24 196,100.17 247,078.48
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
207,530.42 215,710.19 230,606.58
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 450 cum = a+b+c+d+e 2,282,834.66 2,372,812.06 2,536,672.41


Rate per cum = (a+b+c+d+e)/450 5,072.97 5,272.92 5,637.05
Say 5,073.00 5,273.00 5,637.00
Note Quantity provided for aggregate is for estimating purpose.
Exact quantity shall be as per mix design.
6.02 602 Cement Concrete Pavement
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium Small
(Rs.) Large Project Input ref.
Specification Project Project Project Project Project
Construction of un-reinforced, dowel jointed, plain cement
concrete pavement over a prepared sub base with 43 grade
cement @ 310 kg per cum, coarse and fine aggregate
conforming to IS 383, maximum size of coarse aggregate not
exceeding 25 mm, mixed in a batching and mixing plant as per
approved mix design, transported to site, laid with a fixed form
or slip form paver, spread, compacted and finished in a
continuous operation including provision of contraction,
expansion, construction and longitudinal joints, joint filler,
separation membrane, sealant primer, joint sealant, debonding
strip, dowel bar, tie rod, admixtures as approved, curing
compound, finishing to lines and grades as per drawing

Unit = cum
Taking output = 900 Cum 2070 Tonne
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.893 0.893 0.893 500.40 446.79 446.79 446.79 P&M-052
Air compressor 250 cfm hour 0.893 0.893 0.893 614.25 548.44 548.44 548.44 P&M-029
Paver with electronic sensor
(i) Paver Finisher Concrete with 300 HP Motor hour 4.091 28,108.50 114,991.87 P&M-060
(ii) Paver Finisher Concrete with 241 HP Motor 6.000 18,201.75 109,210.50 P&M-061
(iii) Paver Finisher Concrete with 118 HP Motor 11.250 4,517.10 50,817.38 P&M-062
Transit truck agitator
For Transportation Transit truck agitator 6 cum capacity t.km 2070 x L1 2070 x L1 2070 x L1 13.41 832,812.75 832,812.75 832,812.75 P&M-128
For unloding time hour 4.091 6.000 11.250 2,413.95 9,875.47 14,483.70 27,156.94 P&M-067
Concrete joint cutting machine hour 101.587 101.587 101.587 1,251.00 127,085.71 127,085.71 127,085.71 P&M-098
Texturing machine
Texturing machine (TCM) - upto 18 m hour 4.091 4,830.00 19,759.53 P&M-063
Texturing machine (TCM) - upto 18 m 6.000 4,830.00 28,980.00 P&M-063
Texturing machine (TCM) - upto 9 m 11.250 3,807.30 42,832.13 P&M-064
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 114.180 1,501.00 171,384.18 P&M-023
(ii) 12 KL capacity hour 152.250 1,327.00 202,035.75 P&M-024
(iii) 6 KL capacity hour 304.500 1,005.00 306,022.50 P&M-025
c) Material
Concrete from sub-analysis of concrete Rate
Sub-
Analysis of
(i) Using Batching Plant 240 Cum Capacity cum 900.000 5,083.00 4,574,700.00
Concrete -
20.19 A
Sub-
Analysis of
(ii) Using Batching Plant 240 Cum Capacity cum 900.000 5,083.00 4,574,700.00
Concrete -
20.19 A
Sub-
Analysis of
(iii) Using Batching Plant 120 Cum Capacity cum 900.000 5,126.00 4,613,400.00
Concrete -
20.19 C
36 mm mild steel dowel bars of grade S 240 tonne 9.170 9.170 9.170 63,806.54 585,106.01 585,106.01 585,106.01 M-125
12 mm deformed steel tie bars of grade S 415 tonne 1.051 1.051 1.051 46,496.54 48,867.87 48,867.87 48,867.87 M-083
Separation Membrane of impermeable plastic sheeting 125 sqm
micron thick (including 5% Overlap) 3150.000 3150.000 3150.000 16.68 52,542.00 52,542.00 52,542.00 M-165
Joint sealant kg 609.524 609.524 609.524 37.53 22,875.43 22,875.43 22,875.43 M-119
Sealant primer kg 100.003 100.003 100.003 37.53 3,753.11 3,753.11 3,753.11 M-119
Plastic sheath,1.25 mm thick for dowel bars sqm 155.735 155.735 155.735 41.70 6,494.15 6,494.15 6,494.15 M-137
Curing compound Liter 600.000 600.000 600.000 41.70 25,020.00 25,020.00 25,020.00 M-091
Cost of water (Curing) KL 472.500 472.500 472.500 16.00 7,560.00 7,560.00 7,560.00 M-191
Add 1 per cent of material for cost of miscellaneous materials
like tarpauline, Hessian cloth, metal cap, cotton / compressible
sponge and cradle for dowel bars, work bridges for men to
approach concrete surface without walking over it, cutting
53,269.19 53,269.19 53,656.19
blades and bites, minor equipments like scabbling machine,
threads, ropes, guide wires and any other unforeseen items.

d) Overhead charges @ 8% on @ 10% on @ 12% on


533,060.94 670,196.06 817,580.00
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
719,632.27 737,215.67 763,074.66
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 900 cum = a+b+c+d+e 7,915,954.95 8,109,372.38 8,393,821.29


Rate per cum = (a+b+c+d+e)/900 8,795.51 9,010.41 9,326.47
Say 8,796.00 9,010.00 9,326.00
Note The quantities for cement, coarse aggregate and fine
aggregates are for estimating only .The exact quantities will be
as per mix design.
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium Small
(Rs.) Large Project Input ref.
Specification Project Project Project Project Project
6.03 Suggestive Transition Section between Rigid and Flexible Pavement

Due to change in the properties of materials and type of


construction, a gradual changeover from rigid pavement to
flexible pavement is desirable to avoid any damage at the
butting joint. After provision of an expansion joint in the cement
concrete slab, the thickness of slab should be tapered to 10 cm
over a length of 3 m towards the flexible pavement. The
deficiency of thickness caused due to tapering of the slab
should be made up by the asphaltic layers.

The quantities of items should be worked out based on the


approved design and drawings and priced as per rates given
under respective clauses for cement concrete and asphaltic
work.
6.04 Suggestive Cement - Flyash Dry Lean Cement Concrete Sub- base

Construction of dry lean cement concrete Sub- base over a


prepared sub-grade with coarse and fine aggregate
conforming to IS: 383, the size of coarse aggregate not
exceeding 25 mm, replacing cement by fly ash to the extent of
20 per cent , aggregate cement ratio not to exceed 15:1,
aggregate gradation after blending to be as per table 600-1,
cement content not to be less than 120 kg/ cum, optimum
moisture content to be determined during trial length
construction, concrete strength not to be less than 10 Mpa at 7
days, mixed in a batching plant, transported to site, laid with a
paver with electronic sensor, compacting with 8-10 tonnes
vibratory roller, finishing and curing.

Unit = cum
Taking output 450 cum
990 tonne
a) Labour
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Mazdoor day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
b) Machinery
Paver with electronic sensor
(i) Paver Finisher Concrete with 300 HP Motor hour 2.045 28,108.50 57,494.66 P&M-060
(ii) Paver Finisher Concrete with 241 HP Motor 3.000 18,201.75 54,605.25 P&M-061
(iii) Paver Finisher Concrete with 118 HP Motor 5.625 4,517.10 25,408.69 P&M-062
Vibratory roller 8-10 t capacity hour 2.045 3.000 5.625 903.50 1,848.07 2,710.50 5,082.19 P&M-018
Tipper
For Transportation
(i) 18 cum capacity t.km 990 x L1 7.51 223,005.23 P&M-117
(ii) 14 cum capacity t.km 990 x L1 8.52 253,118.25 P&M-120
(iii) 10 cum capacity t.km 990 x L1 10.53 312,716.25 P&M-123
For loading & unloading Time
(i) 18 cum capacity hour 4.545 2,883.30 13,105.91 P&M-014
(ii) 14 cum capacity hour 5.500 2,556.75 14,062.13 P&M-015
(iii) 10 cum capacity hour 10.625 2,274.30 24,164.44 P&M-016
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 52.515 1,501.00 78,825.02 P&M-023
(ii) 12 KL capacity hour 70.050 1,327.00 92,956.35 P&M-024
(iii) 6 KL capacity hour 140.070 1,005.00 140,770.35 P&M-025
c) Material
Concrete from sub-analysis of concrete Rate
Sub-
Analysis of
(i) Using Batching Plant 240 Cum Capacity cum 450.000 3,399.00 1,529,550.00
Concrete -
20.18 B
Sub-
Analysis of
(ii) Using Batching Plant 240 Cum Capacity cum 450.000 3,399.00 1,529,550.00
Concrete -
20.18 B
Sub-
Analysis of
(iii) Using Batching Plant 120 Cum Capacity cum 450.000 3,428.00 1,542,600.00
Concrete -
20.18 D
Cost of water (Curing) KL 217.350 217.350 217.350 16.00 3,477.60 3,477.60 3,477.60 M-191

d) Overhead charges @ 8% on @ 10% on @ 12% on


152,979.26 195,541.43 247,098.45
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
206,522.00 215,095.57 230,625.22
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 205 cum = a+b+c+d+e 2,271,741.96 2,366,051.30 2,536,877.40


Rate per cum = (a+b+c+d+e)/450 5,048.32 5,257.89 5,637.51
Say 5,048.00 5,258.00 5,638.00
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium Small
(Rs.) Large Project Input ref.
Specification Project Project Project Project Project
Note Quantity provided for aggregate is for estimating purpose.
Exact quantity shall be as per mix design.
6.05 Suggestive Cement - Flyash Concrete Pavement.
Construction reinforced-reinforced, dowel jointed, plain cement
concrete pavement over a prepared sub base with 43 grade
cement, coarse and fine aggregate conforming to IS 383,
maximum size of coarse aggregate not exceeding 25 mm,
replacing cement by fly ash to the extent of 15 per cent and
sand by 10 per cent, mixed in a batching and mixing plant as
per approved mix design, transported to site, laid with a fixed
form or slip form paver, spread, compacted and finished in a
continuous operation including provision of contraction,
expansion, construction and longitudinal joints, joint filler,
separation membrane, sealant primer, joint sealant, debonding
strip, dowel bar, tie rod, admixtures as approved, curing
compound, finishing to lines and grades as per drawing

Unit = cum
Taking output = 900 Cum 2070 Tonne
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.893 0.893 0.893 500.40 446.79 446.79 446.79 P&M-052
Air compressor 250 cfm hour 0.893 0.893 0.893 614.25 548.44 548.44 548.44 P&M-029
Paver with electronic sensor
(i) Paver Finisher Concrete with 300 HP Motor hour 4.091 28,108.50 114,989.32 P&M-060
(ii) Paver Finisher Concrete with 241 HP Motor 6.000 18,201.75 109,210.50 P&M-061
(iii) Paver Finisher Concrete with 118 HP Motor 11.250 4,517.10 50,817.38 P&M-062
Transit truck agitator
For Transportation Transit truck agitator 6 cum capacity t.km 2070 x L1 2070 x L1 2070 x L1 13.41 832,812.75 832,812.75 832,812.75 P&M-128
For Unloding time hour 4.091 6.000 11.250 2,413.95 9,875.25 14,483.70 27,156.94 P&M-067
Concrete joint cutting machine . hour 101.587 101.587 101.587 511.35 51,946.67 51,946.67 51,946.67 P&M-075
Texturing machine . hour 4.091 6.000 11.250 4,830.00 19,759.09 28,980.00 54,337.50 P&M-063
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 114.180 1,501.00 171,384.18 P&M-023
(ii) 12 KL capacity hour 152.250 1,327.00 202,035.75 P&M-024
(iii) 6 KL capacity hour 304.500 1,005.00 306,022.50 P&M-025
c) Material
Concrete from sub-analysis of concrete Rate
Sub-
Analysis of
(i) Using Batching Plant 240 Cum Capacity cum 900.000 4,664.00 4,197,600.00
Concrete -
20.19 B
Sub-
Analysis of
(ii) Using Batching Plant 240 Cum Capacity cum 900.000 4,664.00 4,197,600.00
Concrete -
20.19 B
(iii) Using Batching Plant 120 Cum Capacity cum Sub-
Analysis of
900.000 4,650.00 4,185,000.00
Concrete -
20.19 D
36 mm mild steel dowel bars of grade S 240 tonne 9.170 9.170 9.170 63,806.54 585,106.01 585,106.01 585,106.01 M-125
12 mm deformed steel tie bars of grade S 415 tonne 1.051 1.051 1.051 46,496.54 48,867.87 48,867.87 48,867.87 M-083
Separation Membrane of impermeable plastic sheeting 125 sqm
micron thick (including 5% Overlap) 3150.000 3150.000 3150.000 16.68 52,542.00 52,542.00 52,542.00 M-165
Joint sealant kg 609.524 609.524 609.524 37.53 22,875.43 22,875.43 22,875.43 M-119
Sealant primer kg 100.003 100.003 100.003 208.50 20,850.60 20,850.60 20,850.60 M-097
Plastic sheath,1.25 mm thick for dowel bars sqm 155.735 155.735 155.735 41.70 6,494.15 6,494.15 6,494.15 M-137
Curing compound Liter 600.000 600.000 600.000 41.70 25,020.00 25,020.00 25,020.00 M-091
Cost of water (Curing) KL 472.500 472.500 472.500 16.00 7,560.00 7,560.00 7,560.00 M-191
Add 1 per cent of material for cost of miscellaneous materials
like tarpauline, Hessian cloth, metal cap, cotton / compressible
sponge and cradle for dowel bars, work bridges for men to
approach concrete surface without walking over it, cutting
61,748.48 62,135.50 62,845.74
blades and bites, minor equipments like scabbling machine,
threads, ropes, guide wires and any other unforeseen items.

d) Overhead charges @ 8% on @ 10% on @ 12% on


498,927.70 627,568.54 761,690.40
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
673,552.40 690,325.39 710,911.04
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 900 cum = a+b+c+d+e 7,409,076.36 7,593,579.33 7,820,021.44


Rate per cum = (a+b+c+d+e)/900 8,232.31 8,437.31 8,688.91
Say 8,232.00 8,437.00 8,689.00
Note The quantities for cement, coarse aggregate and fine
aggregates are for estimating only .The exact quantities will be
as per mix design.
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium Small
(Rs.) Large Project Input ref.
Specification Project Project Project Project Project
6.06 Suggestive Thin White topping

Construction of thin white topping with plain cement concrete


pavment over existing surface with approve grade cement @
400 kg per cum and as per IRC SP-76, coarse and fine
aggregate conforming to IS 383, maximum size of fine
aggregate not exceeding 25 mm, mixed in a batching and
mixing plant as per approved mix design, transported to site,
laid with a fixed form or slip form paver, spread, compacted
and finished in a continuous operation including provision of
contraction joint, joint filler, sealant primer, joint sealant,
admixture as approved, curing compound, finishing to lines etc.
and grades as per drawing.

Unit = cum
Taking output = 900 Cum 2070 Tonne
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.893 0.893 0.893 500.40 446.79 446.79 446.79 P&M-052
Air compressor 250 cfm hour 0.893 0.893 0.893 614.25 548.44 548.44 548.44 P&M-029
Paver with electronic sensor
(i) Paver Finisher Concrete with 300 HP Motor hour 4.091 28,108.50 114,989.32 P&M-060
(ii) Paver Finisher Concrete with 241 HP Motor 6.000 18,201.75 109,210.50 P&M-061
(iii) Paver Finisher Concrete with 118 HP Motor 11.250 4,517.10 50,817.38 P&M-062
Transit truck agitator
For Transportation Transit truck agitator 6 cum capacity t.km 2070 x L1 2070 x L1 2070 x L1 13.41 832,812.75 832,812.75 832,812.75 P&M-128
For Unloding time hour 4.091 6.000 11.250 2,413.95 9,875.25 14,483.70 27,156.94 P&M-067
Concrete joint cutting machine . hour 320.000 320.000 320.000 511.35 163,632.00 163,632.00 163,632.00 P&M-075
Texturing machine .
Texturing machine (TCm)- upto 18m hour 4.091 4,830.00 19,759.09 P&M-063
Texturing machine (TCm)- upto 18m hour 6.000 4,830.00 28,980.00 P&M-063
Texturing machine (TCm)- upto 9m hour 11.250 3,807.30 42,832.13 P&M-064
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 57.105 1,501.00 85,714.61 P&M-023
(ii) 12 KL capacity hour 76.140 1,327.00 101,037.78 P&M-024
(iii) 6 KL capacity hour 152.250 1,005.00 153,011.25 P&M-025
c) Material
Concrete from sub-analysis of concrete Rate
Sub-
Analysis of
(i) Using Batching Plant 240 Cum Capacity cum 900.000 5,083.00 4,574,700.00
Concrete -
20.19 A
Sub-
Analysis of
(ii) Using Batching Plant 240 Cum Capacity cum 900.000 5,083.00 4,574,700.00
Concrete -
20.19 A
(iii) Using Batching Plant 120 Cum Capacity cum Sub-
Analysis of
900.000 5,126.00 4,613,400.00
Concrete -
20.19 C
Joint sealant kg 609.524 609.524 609.524 37.53 22,875.43 22,875.43 22,875.43 M-119
Sealant primer kg 100.003 100.003 100.003 208.50 20,850.60 20,850.60 20,850.60 M-097
Fiber Reinforcement @9.25 kg Per Cum tonne 8.325 8.325 8.325 46,496.54 387,083.73 387,083.73 387,083.73 M-225
Curing compound Liter 600.000 600.000 600.000 41.70 25,020.00 25,020.00 25,020.00 M-091
Cost of water (Curing) KL 472.500 472.500 472.500 16.00 7,560.00 7,560.00 7,560.00 M-191
Add 1 per cent of material for cost of miscellaneous materials
like tarpauline, Hessian cloth, metal cap, cotton / compressible
sponge and cradle for dowel bars, work bridges for men to
approach concrete surface without walking over it, cutting
62,720.37 62,954.11 63,542.17
blades and bites, minor equipments like scabbling machine,
threads, ropes, guide wires and any other unforeseen items.

d) Overhead charges @ 8% on @ 10% on @ 12% on


506,780.61 635,836.51 770,131.06
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
684,153.82 699,420.16 718,788.99
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 900 cum = a+b+c+d+e 7,525,692.05 7,693,621.73 7,906,678.88


Rate per cum = (a+b+c+d+e)/900 8,361.88 8,548.47 8,785.20
Say 8,362.00 8,548.00 8,785.00
Note The quantities for cement, coarse aggregate and fine
aggregates are for estimating only .The exact quantities will be
as per mix design.
6.07 Suggestive Cement- Fly ash Thin White topping
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium Small
(Rs.) Large Project Input ref.
Specification Project Project Project Project Project

Construction of thin white topping with plain cement concrete


pavment over existing surface with approve grade cement @
340 kg per cum and Fly ash as per IRC SP-76, coarse and fine
aggregate conforming to IS 383, maximum size of fine
aggregate not exceeding 25 mm, mixed in a batching and
mixing plant as per approved mix design, transported to site,
laid with a fixed form or slip form paver, spread, compacted
and finished in a continuous operation including provision of
contraction joint, joint filler, sealant primer, joint sealant,
admixture as approved, curing compound, finishing to lines etc.
and grades as per drawing.

Unit = cum
Taking output = 900 Cum 2070 Tonne
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.893 0.893 0.893 500.40 446.79 446.79 446.79 P&M-052
Air compressor 250 cfm hour 0.893 0.893 0.893 614.25 548.44 548.44 548.44 P&M-029
Paver with electronic sensor
(i) Paver Finisher Concrete with 300 HP Motor hour 4.091 28,108.50 114,989.32 P&M-060
(ii) Paver Finisher Concrete with 241 HP Motor 6.000 18,201.75 109,210.50 P&M-061
(iii) Paver Finisher Concrete with 118 HP Motor 11.250 4,517.10 50,817.38 P&M-062
Transit truck agitator
For Transportation Transit truck agitator 6 cum capacity t.km 2070 x L1 2070 x L1 2070 x L1 13.41 832,812.75 832,812.75 832,812.75 P&M-128
For Unloding time hour 4.091 6.000 11.250 2,413.95 9,875.25 14,483.70 27,156.94 P&M-067
Concrete joint cutting machine . hour 320.000 320.000 320.000 511.35 163,632.00 163,632.00 163,632.00 P&M-075
Texturing machine .
Texturing machine (TCm)- upto 18m hour 4.091 4,830.00 19,759.09 P&M-063
Texturing machine (TCm)- upto 18m hour 6.000 4,830.00 28,980.00 P&M-063
Texturing machine (TCm)- upto 9m hour 11.250 3,807.30 42,832.13 P&M-064
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 57.105 1,501.00 85,714.61 P&M-023
(ii) 12 KL capacity hour 76.140 1,327.00 101,037.78 P&M-024
(iii) 6 KL capacity hour 152.250 1,005.00 153,011.25 P&M-025
c) Material
Concrete from sub-analysis of concrete Rate
Sub-
Analysis of
(i) Using Batching Plant 240 Cum Capacity cum 900.000 4,664.00 4,197,600.00
Concrete -
20.19 B
Sub-
Analysis of
(ii) Using Batching Plant 240 Cum Capacity cum 900.000 4,664.00 4,197,600.00
Concrete -
20.19 B
(iii) Using Batching Plant 120 Cum Capacity cum Sub-
Analysis of
900.000 4,650.00 4,185,000.00
Concrete -
20.19 D
Joint sealant kg 609.524 609.524 609.524 37.53 22,875.43 22,875.43 22,875.43 M-119
Sealant primer kg 100.003 100.003 100.003 208.50 20,850.60 20,850.60 20,850.60 M-097
Fiber Reinforcement @9.25 kg Per Cum tonne 8.325 8.325 8.325 46,496.54 387,083.73 387,083.73 387,083.73 M-225
Curing compound Liter 600.000 600.000 600.000 41.70 25,020.00 25,020.00 25,020.00 M-091
Cost of water (Curing) KL 472.500 472.500 472.500 16.00 7,560.00 7,560.00 7,560.00 M-191
Add 1 per cent of material for cost of miscellaneous materials
like tarpauline, Hessian cloth, metal cap, cotton / compressible
sponge and cradle for dowel bars, work bridges for men to
approach concrete surface without walking over it, cutting
58,949.37 59,183.11 59,258.17
blades and bites, minor equipments like scabbling machine,
threads, ropes, guide wires and any other unforeseen items.

d) Overhead charges @ 8% on @ 10% on @ 12% on


476,310.93 597,749.41 718,208.98
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
643,019.75 657,524.35 670,328.38
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 900 cum = a+b+c+d+e 7,073,217.30 7,232,767.82 7,373,612.20


Rate per cum = (a+b+c+d+e)/900 7,859.13 8,036.41 8,192.90
Say 7,859.00 8,036.00 8,193.00
Note The quantities for cement, coarse aggregate and fine
aggregates are for estimating only .The exact quantities will be
as per mix design.
CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
7.1 702 Sub-Surface Drain with Geotextiles
Construction of sub surface drain 200 mm dia using
geotextiles treated with carbon black with physical
properties as given in clause 702.2.3 formed in to a
stable network and a planar geocomposite structure,
joints wrapped with geotextile to prevent ingress of
soil, all as per clause 702 and approved drawings
including excavation and backfilling

Unit = Running metre


Taking output = one metre
a) Labour
Mate day 0.030 0.030 0.030 617.00 18.51 18.51 18.51 L-12
Mazdoor skilled day 0.250 0.250 0.250 565.73 141.43 141.43 141.43 L-15
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
b) Material
Geonets, geomembrane and geotextile to make
planar geocomposite stable network for sub surface
drain including wrapping of joints with 160 mm over
lapping with geotextile .
Geonets sqm 1.000 1.000 1.000 210.00 210.00 210.00 210.00 M-106
Geomembrane sqm 1.000 1.000 1.000 89.00 89.00 89.00 89.00 M-105
Geotextile sqm 2.000 2.000 2.000 62.55 125.10 125.10 125.10 M-107
Add 2 per cent cost of material for miscellaneous
items like synthetic cord 8.48 8.48 8.48
c) Overhead charges @ 8% on @ 10% on @ 12% on
67.86 84.83 101.79
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
91.61 93.31 95.01
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = a+b+c+d 1,007.76 1,026.42 1,045.09
Say 1,008.00 1,026.00 1,045.00
Note Surplus excavated material to be used at site. Hence
seprate cost for disposal not added.
7.2 708 Laying Paving Fabric Beneath a Pavement Overlay

Providing and laying paving fabric with physical


requirements as per Table 700-16 over a tack coat of
paving grade Bitumen 80-100 penetration, laid at the
rate of 1 kg per sqm over thoroughly cleaned and
repaired surface to provide a water resistant
membrane and crack retarding layer. Paving fabric to
be free of wrinkling and folding and to be laid before
cooling of tack coat, brooming and rolling of surface
with pneumatic roller to maximise paving fabric
contact with pavement surface

Unit = sqm
Taking output = 2800 sqm
a) Labour
Mate day 0.800 0.800 0.800 617.00 493.60 493.60 493.60 L-12
Mazdoor day 20.000 20.000 20.000 511.52 10,230.40 10,230.40 10,230.40 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 0.833 2.240 2.240 500.40 416.83 1,120.90 1,120.90 P&M-052
Pneumatic roller 14 tonnes 2000 sqm per hour hour 1.400 1.400 1.400 2,562.00 3,586.80 3,586.80 3,586.80 P&M-022
Bitumen pressure distributor (Spraying width 4.5 m)
hour 0.778 0.778 0.778 1,729.35 1,345.05 1,345.05 1,345.05 P&M-053
c) Material
Paving Fabric sqm 2940.0 2940.0 2940.0 80.73 237,359.43 237,359.43 237,359.43 M-132
Paving Bitumen 80-100 tonne 2.800 2.800 2.800 48,006.37 134,417.84 134,417.84 134,417.84 M-075
c) Overhead charges @ 8% on @ 10% on @ 12% on
31,028.00 38,855.40 46,626.48
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
41,887.79 42,740.94 43,518.05
(a+b+c) (a+b+c) (a+b+c)
Cost for 2800 sqm = a+b+c+d+e 460,765.74 470,150.36 478,698.55
Rate per sqm =(a+b+c+d+e)/2800 164.56 167.91 170.96
Say 165.00 168.00 171.00
7.3 703 Laying Boulder Apron in Crates of Synthetic Geogrids
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

Providing, preparing and laying of geogrid crated


apron 1 m x 5 m, 600 mm thick including excavation
and backfilling with baffles at 1 metre interval, made
with geogrids having characteristics as per clause
703.2, joining sides with connectors/ring staples, top
corners to be tie tensioned, placing of suitable cross
interval ties in layers of 300 mm connecting opposite
side with lateral braces and tied with polymer braids
to avoid bulging, constructed as per clause 703.3.
filled with stone with minimum size of 200 mm and
specific gravity not less than 2.65, packed with stone
spalls, keyed to the foundation recess in case of
sloping ground and laid over a layer of geotextile to
prevent migration of fines, all as per clause 703 and
laid as per clause 2503.3 and approved design.

Unit = cum
Taking output = 3 cum
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor skilled day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
Mazdoor day 1.500 1.500 1.500 511.52 767.28 767.28 767.28 L-13
b) Material
Geo grids sqm 21.000 21.000 21.000 236.00 4,956.00 4,956.00 4,956.00 M-104
Connectors/ Staples each 50.000 50.000 50.000 6.95 347.50 347.50 347.50 M-086
Polymer braids metre 20.000 20.000 20.000 205.00 4,100.00 4,100.00 4,100.00 M-139
Stones with minimum size of 200 mm cum 3.450 3.450 3.450 1,994.63 6,881.48 6,881.48 6,881.48 M-003
Stones spall for filling voids cum 0.450 0.450 0.450 1,679.81 755.92 755.92 755.92 M-008
c) Overhead charges @ 8% on @ 10% on @ 12% on
1,451.23 1,814.04 2,176.85
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,959.16 1,995.44 2,031.72
(a+b+c) (a+b+c) (a+b+c)
Cost for 3 cum = a+b+c+d 21,550.79 21,949.88 22,348.97
Rate per cum = (a+b+c+d)/ 3 7,183.60 7,316.63 7,449.66
Say 7,184.00 7,317.00 7,450.00
7.4 3100 Reinforced Earth Structures
Reinforced earth Structures have four main
components as under:
a) Excavation for foundation, foundation concrete
and cement concrete grooved seating in the
foundation for facing elements (facia material).

b) Facia material and its placement.


c) Assembling, joining with facing elements and
laying of the reinforcing elements.
d) Earth fill with granular material which is to be
retained by the wall.
Each component is analysed separately as under:

considering Average height of wall = 8 m.


7.4 3103 (i) Assembling, joining and laying of reinforcing
elements.
A With reinforcing element of steel / Aluminium strips /
polymeric strips.
Unit = Running Metre
Taking Output = 450 m
a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Material
@ Reinforcement strips 60 mm wide 5 mm thick as
per clause 3103. including 5% wastage
1.Galvanised carbon steel strips metre 472.500 472.500 472.500 1.00 472.50 472.50 472.50 M-155
Add 5 per cent of the cost of reinforcing elements
strip towards accessories like tie-strips, nuts and bolts
and loops/lugs for joining reinforcing elements with 47.25 47.25 47.25
the facia pannels, overlaps heat bonding or extension

or
2.Copper Strips metre 472.500 472.500 472.500 1.00 472.50 472.50 472.50 M-154
Add 5 per cent of the cost of reinforcing elements
strip towards accessories like tie-strips, nuts and bolts
and loops/lugs for joining reinforcing elements with 47.25 47.25 47.25
the facia pannels, overlaps heat bonding or extension

or
3.Aluminium Strips metre 472.500 472.500 472.500 1.00 472.50 472.50 472.50 M-158
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Add 5 per cent of the cost of reinforcing elements
strip towards accessories like tie-strips, nuts and bolts
and loops/lugs for joining reinforcing elements with 47.25 47.25 47.25
the facia pannels, overlaps heat bonding or extension

or
4.Stainless steel strips metre 472.500 472.500 472.500 1.00 472.50 472.50 472.50 M-157
Add 5 per cent of the cost of reinforcing elements
strip towards accessories like tie-strips, nuts and bolts
and loops/lugs for joining reinforcing elements with 47.25 47.25 47.25
the facia pannels, overlaps heat bonding or extension

or
5.Glass reinforced polymer/fibre reinforced
polymer/polymeric strips metre 472.500 472.500 472.500 1.00 495.00 495.00 495.00 M-156
Add 5 per cent of the cost of reinforcing elements
strip towards accessories like tie-strips, nuts and bolts
and loops/lugs for joining reinforcing elements with 49.50 49.50 49.50
the facia pannels, overlaps heat bonding or extension

@ Any one of the above alternative may be adopted


as per approved design.

Type 1 1.Galvanised carbon steel strips


c) Overhead charges @ 8% on @ 10% on @ 12% on
264.73 330.92 397.10
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
357.39 364.01 370.63
(a+b+c) (a+b+c) (a+b+c)
Cost of 450 m = a+b+c+d 3,931.29 4,004.10 4,076.90
Rate per metre =(a+b+c+d)/450 8.74 8.90 9.06
Say 9.00 9.00 9.00
Type 2 2.Copper Strips
c) Overhead charges @ 8% on @ 10% on @ 12% on
264.73 330.92 397.10
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
357.39 364.01 370.63
(a+b+c) (a+b+c) (a+b+c)
Cost of 450 m = a+b+c+d 3,931.29 4,004.10 4,076.90
Rate per metre =(a+b+c+d)/450 8.74 8.90 9.06
Say 9.00 9.00 9.00
Type 3 3.Aluminium Strips
c) Overhead charges @ 8% on @ 10% on @ 12% on
264.73 330.92 397.10
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
357.39 364.01 370.63
(a+b+c) (a+b+c) (a+b+c)
Cost of 450 m = a+b+c+d 3,931.29 4,004.10 4,076.90
Rate per metre =(a+b+c+d)/450 8.74 8.90 9.06
Say 9.00 9.00 9.00
Type 4 4.Stainless steel strips
c) Overhead charges @ 8% on @ 10% on @ 12% on
264.73 330.92 397.10
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
357.39 364.01 370.63
(a+b+c) (a+b+c) (a+b+c)
Cost of 450 m = a+b+c+d 3,931.29 4,004.10 4,076.90
Rate per metre =(a+b+c+d)/450 8.74 8.90 9.06
Say 9.00 9.00 9.00
Type 5 5.Glass reinforced polymer/fibre reinforced
polymer/polymeric strips
c) Overhead charges @ 8% on @ 10% on @ 12% on
266.71 333.39 400.07
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
360.06 366.73 373.40
(a+b+c) (a+b+c) (a+b+c)
Cost of 450 m = a+b+c+d 3,960.70 4,034.04 4,107.39
Rate per metre =(a+b+c+d)/450 8.80 8.96 9.13
Say 9.00 9.00 9.00
7.4(i) B With reinforcing elements of synthetic geogrids

Unit = sqm
Taking output 300 sqm
a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Material
Synthetic Geogrids as per clause 3100 and approved
design and specifications including 5% wastage. sqm 315.000 315.000 315.000 182.60 57,519.00 57,519.00 57,519.00 M-183

Add 5 per cent of the cost of reinforcing elements


(synthetic geogrids) for accessories like tie-strips,
nuts and bolts and loops/lugs for joining reinforcing
elements with the facia pannels, overlaps and other 2,875.95 2,875.95 2,875.95
protective elements for synthetic geogrids.
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
c) Overhead charges @ 8% on @ 10% on @ 12% on
5,054.75 6,318.44 7,582.12
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
6,823.91 6,950.28 7,076.65
(a+b+c) (a+b+c) (a+b+c)
Cost of 300 sqm of Synthetic geogrids = a+b+c+d
75,063.03 76,453.09 77,843.14
Rate per sqm = (a+b+c+d)/ 300 250.21 254.84 259.48
Say 250.00 255.00 259.00
7.4 3105 (ii) Facing elements of RCC
Unit = sqm
Taking output 200 sqm
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Machinery
i) For Casting yard
Light crane with lifting capacity upto 3 tonne ( For
hour 2.963 2.963 2.963 1,083.60 3,210.71 3,210.71 3,210.71 P&M-102
Lifting at casting yard)
ii) For transportation and placement at site
Light crane with lifting capacity upto 3 tonne for
loading & Unloading hour 5.926 5.926 5.926 1,083.60 6,421.41 6,421.41 6,421.41 P&M-102
Trailer 30 tonne capacity for transporting to site
t.km. 36 x 2.5 x L 36 x 2.5 x L 36 x 2.5 x L 6.18 16,681.95 16,681.95 16,681.95 P&M-116
Light crane with lifting capacity upto 3 tonne ( For
erection) 8.000 8.000 8.000 1,083.60 8,668.80 8,668.80 8,668.80 P&M-102
c) Material
Pre-cast RCC M-35 facing elements of size as per cum 36.000 6,925.00 249,300.00 Item No. -
design and 18 cm thick for 75 sqm. (Refer Item 12.8 cum 36.000 6,959.00 250,524.00 12.08 H
(H) Basic Cost of Labour, Material & Machinery ) cum 36.000 7,079.00 254,844.00 Case II
Formwork @ 4 per cent on cost of concrete i.e. cost
of material, labour and machinery 9,972.00 10,020.96 10,193.76

Non-Woven geotextile behind the fascia element to


Sqm 80.000 80.000 80.000 1.00 80.00 80.00 80.00 M-107
avoid leaching out of backfill material

tonnes 1.400 51,234.00 71,727.60


HYSD steel @ 7 kg / sqm (Refer Item 9.07 ,Basic Item No. -
tonnes 1.400 51,308.00 71,831.20
Cost of Labour, Material & Machinery ) 9.07
tonnes 1.400 51,454.00 72,035.60
Add 2 per cent of cost of facia pannels, for all
necessary temporary form work, scaffolding and
provision of loops/lugs for lifting of pannels and 4,986.00 5,010.48 5,096.88
joining the reinforcing elements.
d) Overhead charges @ 8% on @ 10% on @ 12% on
30,035.72 37,684.75 45,795.74
(a+b) (a+b) (a+b)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
40,548.22 41,453.23 42,742.69
(a+b+d) (a+b+d) (a+b+d)

Cost for 200 sqm = a+b+c+d+e 446,030.43 455,985.51 470,169.55


Rate per sqm = (a+b+c+d+e)/200 2,230.15 2,279.93 2,350.85
Say
2,230.00 2,280.00 2,351.00
Note 1.The specification and construction details to be adopted shall be as per section 3100 of MoRTH Specification.
2.Drainage arrangement shall be made as per approved design and drawings.
3.The quantity of filler media shall be calculated as per approved design and specifications and shall be priced separately.The rate for same to be adopted from chapter 9.
4.Excavation for foundation including foundation concrete and groove in the foundation for seating of bottom most facia panel and capping beam to be calculated as per design
and
5.The priced
earthseparately. The rates
fill to be retained forincluded
is not excavation andanalysis.
in this foundation
Theconcrete
same is shall
to bebe taken out
worked fromand
theprovided
chapter separately
9 culvert chapter
complete as per clause 305.
, 6.For compaction of Earthwork, attention is invited to clause 3106.5 of MoRTH Specification.
7.Length of reinforcing strips will vary with the height of wall and will be as per approved design and drawings.
8.The type of reinforcing elements to be adopted shall be as per approved design and specifications.
9.The market rate for supply of reinforcing elements and their accessories are to be ascertained from reputed firms in the field of earth reinforcement.
10.The earth fill material shall be clean, free draining, granular with high friction and low cohesion, non-corrosive, coarse grained with not 10 per cent of particles passing 75
micron sieve,beam
11.Capping free is
of to
anybedeleterious matter, as
priced separately chlorides, salts, acids,
per approved design.alkalies,
The ratemineral oil, fungus
for cement andshall
concrete microbes andfrom
be taken shallthe
be chapter
of specified PH value. in bridge section.
of sub-structure
12.The cost of reinforced earth retaining wall shall include following:
(i) Foundation concrete as per approved design.
(ii) Cost of facial pannels and their erection .
(iii) Cost of reinforcing elements including their fixing and joining with the facial pannels.
(iv) Drainage arrangement including filter media as per approved design and drawings.
13. The compacted earth filling to be retained shall form part of embankment.
14. Excavation for foundation including backfilling paid separately.

7.5 703 (i)


Supplying & laying of bi-axial extruded high modulus
polypropylene geogrid conforming to MORT&H
specification for base/sub-base reinforcement having
minimum tensile strength 15kN/m in the longitudinal
and transverse direction, with 5kN/m and 7kN/m
tensile strength at 2% and 5% strain respectively in
the longitudinal and transverse direction, junction
efficiency not less than 95% and with 38mm X 38mm
mesh opening.

Unit = Sqm
Taking output 300 Sqm
a) Labour
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Mazdoor (Skilled ) day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Material
Bi-Axial Extruded GeoGrids of Minimum Tensile
Strength 15 kN/m in the longitudinal and transverse sqm 300.00 300.00 300.00 1.00 300.00 300.00 300.00 M-286
direction
Add 10 % of the cost of reinforcing elements
(synthetic geogrids) for wastage and accessories like
tie-strips, nuts and bolts and loops/lugs for joining
reinforcing elements with the facia pannels, overlaps
and other protective elements for synthetic geogrids 30.00 30.00 30.00
and all other activities required to complete the item in
all respect including taxes and transportation.

c) Overhead charges @ 8% on @ 10% on @ 12% on


249.55 311.94 374.33
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
336.90 343.14 349.38
(a+b+c) (a+b+c) (a+b+c)
Cost for 300 sqm = a+b+c+d 3,705.87 3,774.50 3,843.13
Rate per sqm = (a+b+c+d)/300 12.35 12.58 12.81
Say 12.00 13.00 13.00

7.5 703 (ii) Supplying & laying of bi-axial extruded high modulus
polypropylene geogrid conforming to MORT&H
specification for base/sub-base reinforcement having
minimum tensile strength 20kN/m in the longitudinal
and transverse direction, with 7kN/m and 14kN/m
tensile strength at 2% and 5% strain respectively in
the longitudinal and transverse direction, junction
efficiency not less than 95% and with 38mm X 38mm
mesh opening.

Unit = Sqm
Taking output 300 Sqm
a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Mazdoor (Skilled ) day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Material
Bi-Axial Extruded GeoGrids of Minimum Tensile
Strength 20 kN/m in the longitudinal and transverse sqm 300.00 300.00 300.00 1.00 300.00 300.00 300.00 M-287
direction
Add 10 % of the cost of reinforcing elements
(synthetic geogrids) for wastage and accessories like
tie-strips, nuts and bolts and loops/lugs for joining
reinforcing elements with the facia pannels, overlaps
and other protective elements for synthetic geogrids 30.00 30.00 30.00
and all other activities required to complete the item in
all respect including taxes and transportation.

c) Overhead charges @ 8% on @ 10% on @ 12% on


249.55 311.94 374.33
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
336.90 343.14 349.38
(a+b+c) (a+b+c) (a+b+c)
Cost for 300 sqm = a+b+c+d 3,705.87 3,774.50 3,843.13
Rate per sqm = (a+b+c+d)/300 12.35 12.58 12.81
Say 12.00 13.00 13.00

7.5 703 (iii) Supplying & laying of bi-axial extruded high modulus
polypropylene geogrid conforming to MORT&H
specification for base/sub-base reinforcement having
minimum tensile strength 30kN/m in the longitudinal
and transverse direction, with 10.5kN/m and 21kN/m
tensile strength at 2% and 5% strain respectively in
the longitudinal and transverse direction, junction
efficiency not less than 95% and with 38mm X 38mm
mesh opening.

Details of Cost for 300 Sqm


Unit = Sqm
Taking output 300 Sqm
a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Mazdoor (Skilled ) day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Material
Bi-Axial Extruded GeoGrids of Minimum Tensile
Strength 30 kN/m in the longitudinal and transverse sqm 300.00 300.00 300.00 1.00 300.00 300.00 300.00 M-288
direction
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Add 10 % of the cost of reinforcing elements
(synthetic geogrids) for wastage and accessories like
tie-strips, nuts and bolts and loops/lugs for joining
reinforcing elements with the facia pannels, overlaps
and other protective elements for synthetic geogrids 30.00 30.00 30.00
and all other activities required to complete the item in
all respect including taxes and transportation.

c) Overhead charges @ 8% on @ 10% on @ 12% on


249.55 311.94 374.33
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
336.90 343.14 349.38
(a+b+c) (a+b+c) (a+b+c)
Cost for 300 sqm = a+b+c+d 3,705.87 3,774.50 3,843.13
Rate per sqm = (a+b+c+d)/300 12.35 12.58 12.81
Say 12.00 13.00 13.00

7.5 703 (iv) Supplying & laying of bi-axial extruded high modulus
polypropylene geogrid coforming to MORT&H
specification for base/sub-base reinforcement having
minimum tensile strength 40kN/m in the longitudinal
and transverse direction, with 14kN/m and 28kN/m
tensile strength at 2% and 5% strain respectively in
the longitudinal and transverse direction, junction
efficiency not less than 95% and with 38mm X 38mm
mesh opening.

Unit = Sqm
Taking output 300 Sqm
a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Mazdoor (Skilled ) day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Material
Bi-Axial Extruded GeoGrids of Minimum Tensile
Strength 40 kN/m in the longitudinal and transverse sqm 300.00 300.00 300.00 1.00 300.00 300.00 300.00 M-289
direction
Add 10 % of the cost of reinforcing elements
(synthetic geogrids) for wastage and accessories like
tie-strips, nuts and bolts and loops/lugs for joining
reinforcing elements with the facia pannels, overlaps
and other protective elements for synthetic geogrids 30.00 30.00 30.00
and all other activities required to complete the item in
all respect including taxes and transportation.

c) Overhead charges @ 8% on @ 10% on @ 12% on


249.55 311.94 374.33
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
336.90 343.14 349.38
(a+b+c) (a+b+c) (a+b+c)
Cost for 300 sqm = a+b+c+d 3,705.87 3,774.50 3,843.13
Rate per sqm = (a+b+c+d)/300 12.35 12.58 12.81
Say 12.00 13.00 13.00

7.6 703 Supplying and laying high strength flexible geogrids


(HSFG) as soil reinforcement / basal reinforcement as
per MORTH 3100 and IRC 113, made of high tenacity
polyester core with polyethylene coating with
minimum Long Term Design Strength (LTDS) of more
than 50% of ultimate tensile strength at 30 degree
Celcius corresponding to 12 % strain etc. complete
and as directed by Engineer - In - Charge.

Details of Cost for 300 Sqm


Unit = Sqm
Taking output 300 Sqm
b) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Beldar day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Skilled Beldar day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
a) Material
(i) Synthetic Geogrid Ultimate tensile strength- 100 kN/m
sqm 330.000 330.000 330.000 278.00 91,740.00 91,740.00 91,740.00 M-200
(ii) Synthetic Geogrid Ultimate tensile strength- 150 kN/m
sqm 330.000 330.000 330.000 305.80 100,914.00 100,914.00 100,914.00 M-201
(iii) Synthetic Geogrid Ultimate tensile strength- 200 kN/m
sqm 330.000 330.000 330.000 417.00 137,610.00 137,610.00 137,610.00 M-202
(iv) Synthetic Geogrid Ultimate tensile strength- 250 kN/m
sqm 330.000 330.000 330.000 458.70 151,371.00 151,371.00 151,371.00 M-203
(v) Synthetic Geogrid Ultimate tensile strength- 300 kN/m
sqm 330.000 330.000 330.000 486.50 160,545.00 160,545.00 160,545.00 M-204
(vi) Synthetic Geogrid Ultimate tensile strength- 350 kN/m
sqm 330.000 330.000 330.000 542.10 178,893.00 178,893.00 178,893.00 M-205
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
(vii) Synthetic Geogrid Ultimate tensile strength- 400 kN/m
sqm 330.000 330.000 330.000 583.80 192,654.00 192,654.00 192,654.00 M-206
(viii) Synthetic Geogrid Ultimate tensile strength- 500 kN/m
sqm 330.000 330.000 330.000 695.00 229,350.00 229,350.00 229,350.00 M-207
(ix) Synthetic Geogrid Ultimate tensile strength- 600 kN/m
sqm 330.000 330.000 330.000 764.50 252,285.00 252,285.00 252,285.00 M-208
(x) Synthetic Geogrid Ultimate tensile strength- 800 kN/m
sqm 330.000 330.000 330.000 984.12 324,759.60 324,759.60 324,759.60 M-210
(xi) Synthetic Geogrid Ultimate tensile strength- 900 kN/m
sqm 330.000 330.000 330.000 1,168.99 385,766.70 385,766.70 385,766.70 M-211
(xii) Synthetic Geogrid Ultimate tensile strength- 1000
kN/m sqm 330.000 330.000 330.000 1,320.50 435,765.00 435,765.00 435,765.00 M-212
(xiii) Synthetic Geogrid Ultimate tensile strength- 1100
kN/m sqm 330.000 330.000 330.000 1,390.00 458,700.00 458,700.00 458,700.00 M-213
(xiv) Synthetic Geogrid Ultimate tensile strength- 1200
kN/m sqm 330.000 330.000 330.000 1,512.32 499,065.60 499,065.60 499,065.60 M-214
@ Any one of the above alternative may be adopted
as per approved design.
Add 10 per cent of the cost of reinforcing elements
(synthetic geogrids) for wastage and accessories like
tie-strips, nuts and bolts and loops/lugs for joining
reinforcing elements with the facia pannels, overlaps
and other protective elements for synthetic geogrids
and all other activities required to complete the item in
all respect including taxes and transportation.

(i) Synthetic Geogrid Ultimate tensile strength- 100 kN/m


9,174.00 9,174.00 9,174.00
(ii) Synthetic Geogrid Ultimate tensile strength- 150 kN/m
10,091.40 10,091.40 10,091.40
(iii) Synthetic Geogrid Ultimate tensile strength- 200 kN/m
13,761.00 13,761.00 13,761.00
(iv) Synthetic Geogrid Ultimate tensile strength- 250 kN/m
15,137.10 15,137.10 15,137.10
(v) Synthetic Geogrid Ultimate tensile strength- 300 kN/m
16,054.50 16,054.50 16,054.50
(vi) Synthetic Geogrid Ultimate tensile strength- 350 kN/m
17,889.30 17,889.30 17,889.30
(vii) Synthetic Geogrid Ultimate tensile strength- 400 kN/m
19,265.40 19,265.40 19,265.40
(viii) Synthetic Geogrid Ultimate tensile strength- 500 kN/m
22,935.00 22,935.00 22,935.00
(ix) Synthetic Geogrid Ultimate tensile strength- 600 kN/m
25,228.50 25,228.50 25,228.50
(x) Synthetic Geogrid Ultimate tensile strength- 800 kN/m
32,475.96 32,475.96 32,475.96
(xi) Synthetic Geogrid Ultimate tensile strength- 900 kN/m
38,576.67 38,576.67 38,576.67
(xii) Synthetic Geogrid Ultimate tensile strength- 1000
kN/m 43,576.50 43,576.50 43,576.50
(xiii) Synthetic Geogrid Ultimate tensile strength- 1100
kN/m 45,870.00 45,870.00 45,870.00
(xiv) Synthetic Geogrid Ultimate tensile strength- 1200
kN/m 49,906.56 49,906.56 49,906.56
(i) c) Overhead charges @ 8% on @ 10% on @ 12% on
8,296.27 10,370.34 12,444.41
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
11,199.97 11,407.38 11,614.78
(a+b+c) (a+b+c) (a+b+c)
Cost for 300 sqm = a+b+c+d 123,199.66 125,481.14 127,762.61
Rate per sqm = (a+b+c+d)/300 410.67 418.27 425.88
Say 411.00 418.00 426.00
(ii) c) Overhead charges @ 8% on @ 10% on @ 12% on
9,103.59 11,379.48 13,655.38
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
12,289.84 12,517.43 12,745.02
(a+b+c) (a+b+c) (a+b+c)
Cost for 300 sqm = a+b+c+d 135,188.25 137,691.73 140,195.22
Rate per sqm = (a+b+c+d)/300 450.63 458.97 467.32
Say 451.00 459.00 467.00
(iii) c) Overhead charges @ 8% on @ 10% on @ 12% on
12,332.83 15,416.04 18,499.25
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
16,649.33 16,957.65 17,265.97
(a+b+c) (a+b+c) (a+b+c)
Cost for sqm sqm = a+b+c+d 183,142.58 186,534.11 189,925.64
Rate per sqm = (a+b+c+d)/300 610.48 621.78 633.09
Say 610.00 622.00 633.00
(iv) c) Overhead charges @ 8% on @ 10% on @ 12% on
13,543.80 16,929.75 20,315.70
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
18,284.13 18,622.73 18,961.32
(a+b+c) (a+b+c) (a+b+c)
Cost for 300 sqm = a+b+c+d 201,125.45 204,850.00 208,574.54
Rate per sqm = (a+b+c+d)/300 670.42 682.83 695.25
Say 670.00 683.00 695.00
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
(v) c) Overhead charges @ 8% on @ 10% on @ 12% on
14,351.11 17,938.89 21,526.67
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
19,374.00 19,732.78 20,091.56
(a+b+c) (a+b+c) (a+b+c)
Cost for 300 sqm = a+b+c+d 213,114.04 217,060.59 221,007.15
Rate per sqm = (a+b+c+d)/300 710.38 723.54 736.69
Say 710.00 724.00 737.00
(vi) c) Overhead charges @ 8% on @ 10% on @ 12% on
15,965.74 19,957.17 23,948.61
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
21,553.75 21,952.89 22,352.03
(a+b+c) (a+b+c) (a+b+c)
Cost for 300 sqm = a+b+c+d 237,091.20 241,481.78 245,872.36
Rate per sqm = (a+b+c+d)/300 790.30 804.94 819.57
Say 790.00 805.00 820.00
(vii) c) Overhead charges @ 8% on @ 10% on @ 12% on
17,176.71 21,470.88 25,765.06
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
23,188.55 23,617.97 24,047.39
(a+b+c) (a+b+c) (a+b+c)
Cost for 300 sqm = a+b+c+d 255,074.08 259,797.67 264,521.27
Rate per sqm = (a+b+c+d)/300 850.25 865.99 881.74
Say 850.00 866.00 882.00
(viii) c) Overhead charges @ 8% on @ 10% on @ 12% on
20,405.95 25,507.44 30,608.93
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
27,548.04 28,058.19 28,568.34
(a+b+c) (a+b+c) (a+b+c)
Cost for 300 sqm = a+b+c+d 303,028.41 308,640.05 314,251.69
Rate per sqm = (a+b+c+d)/300 1,010.09 1,028.80 1,047.51
Say 1,010.00 1,029.00 1,048.00
(ix) c) Overhead charges @ 8% on @ 10% on @ 12% on
22,424.23 28,030.29 33,636.35
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
30,272.72 30,833.32 31,393.93
(a+b+c) (a+b+c) (a+b+c)
Cost for 300 sqm = a+b+c+d 332,999.87 339,166.53 345,333.20
Rate per sqm = (a+b+c+d)/300 1,110.00 1,130.56 1,151.11
Say 1,110.00 1,131.00 1,151.00
(x) c) Overhead charges @ 8% on @ 10% on @ 12% on
28,802.00 36,002.50 43,203.00
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
38,882.70 39,602.75 40,322.80
(a+b+c) (a+b+c) (a+b+c)
Cost for 300 sqm = a+b+c+d 427,709.68 435,630.23 443,550.78
Rate per sqm = (a+b+c+d)/300 1,425.70 1,452.10 1,478.50
Say 1,426.00 1,452.00 1,479.00
(xi) c) Overhead charges @ 8% on @ 10% on @ 12% on
34,170.62 42,713.28 51,255.93
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
46,130.34 46,984.61 47,838.87
(a+b+c) (a+b+c) (a+b+c)
Cost for 300 sqm = a+b+c+d 507,433.75 516,830.68 526,227.60
Rate per sqm = (a+b+c+d)/300 1,691.45 1,722.77 1,754.09
Say 1,691.00 1,723.00 1,754.00
(xii) c) Overhead charges @ 8% on @ 10% on @ 12% on
38,570.47 48,213.09 57,855.71
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
52,070.14 53,034.40 53,998.66
(a+b+c) (a+b+c) (a+b+c)
Cost for 300 sqm = a+b+c+d 572,771.53 583,378.41 593,985.29
Rate per sqm = (a+b+c+d)/300 1,909.24 1,944.59 1,979.95
Say 1,909.00 1,945.00 1,980.00
(xiii) c) Overhead charges @ 8% on @ 10% on @ 12% on
40,588.75 50,735.94 60,883.13
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
54,794.82 55,809.54 56,824.26
(a+b+c) (a+b+c) (a+b+c)
Cost for 300 sqm = a+b+c+d 602,742.99 613,904.90 625,066.81
Rate per sqm = (a+b+c+d)/300 2,009.14 2,046.35 2,083.56
Say 2,009.00 2,046.00 2,084.00
(xiv) c) Overhead charges @ 8% on @ 10% on @ 12% on
44,140.93 55,176.16 66,211.39
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
59,590.25 60,693.77 61,797.30
(a+b+c) (a+b+c) (a+b+c)
Cost for 300 sqm = a+b+c+d 655,492.76 667,631.51 679,770.27
Rate per sqm = (a+b+c+d)/300 2,184.98 2,225.44 2,265.90
Say 2,185.00 2,225.00 2,266.00
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
7.7 704

Supplying & laying of drainage composite for use


behind walls, between two different fills, alongside
drains of road, below concrete lining of canals etc.
Geocomposite for planar drainage, realized by
thermobonding a draining core in extruded
monofilaments with two filtering nonwoven geotextiles
that may also be working as separation or protecting
layers. The draining three dimensional core will have
a “W” configuration as longitudinal parallel channels.
Minimum thickness to be 7.2mm, with two filtering UV
stabilized polypropylene nonwoven geotextile of
minimum thickness of 0.75 mm having pores of 150
micron and tensile strength of 8.0 kN/m that will be
working as separation or protecting layer,
geocomposite having in plane flow capacity of 2.1 L /
(m.s) at hydraulic gradient of 1.0 & 20 kpa pressure
and tensile strength of 18 kN/m , with mass per unit
area of 740 gsm, supplied in the form of roll for easy
transportation to site of work as per detailed
specification all complete as per directions of
Engineer in charge.

Unit = Sqm
Taking output 300 Sqm

a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Mazdoor (Skilled ) day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Material
Geosynthetic Drainage Composite (tensile strength of
18 kN/ m) sqm 300.00 300.00 300.00 175.00 52,500.00 52,500.00 52,500.00 M-290
Add 10 per cent of the cost of synthetic Composits for
wastage and accessories for joining sheets with the
facia pannels, overlaps and other protective elements
for synthetic Composits and other miscelleneus
5,250.00 5,250.00 5,250.00
activities required to complete the item in all respect
including transpotarion & takes.

c) Overhead charges @ 8% on @ 10% on @ 12% on


4,843.15 6,053.94 7,264.73
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
6,538.26 6,659.34 6,780.42
(a+b+c) (a+b+c) (a+b+c)
Cost for 300 sqm = a+b+c+d 71,920.83 73,252.70 74,584.57
Rate per sqm = (a+b+c+d)/300 239.74 244.18 248.62
Say 240.00 244.00 249.00

7.8 704 Supplying & laying of drainage composite for use


behind walls, between two different fills, alongside
drains of road, below concrete lining of canals etc.
having thermobonding a draining core - HDPE geonet
comprises of two sets of parallel overlayed ribs
integrally connected to have a rhomboidal shape with
a polyethylene film and a nonwoven geotextile having
mass per unit area 130 g/m2 and tensile strength of
8.0 kN/m that will be working as separation or
protecting layer, geocomposite having in plane flow
capacity of 0.7 L / (m.s) at hydraulic gradient of 1.0 &
20 kPa pressure and tensile strength of 13.5 kN/ m ,
with mass per unit area of 830 gsm, at easily
accessible location including top and bottom, with all
leads and lifts, manpower and machinery, materials,
labour etc. complete and as directed by Engineer - In
- Charge.

Unit = Sqm
Taking output 300 Sqm
a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Mazdoor (Skilled ) day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Material
Geosynthetic Drainage Composite (tensile strength of
13.5 kN/ m) sqm 300.00 300.00 300.00 150.00 45,000.00 45,000.00 45,000.00 M-291
Add 10 per cent of the cost of synthetic Composits for
wastage and accessories for joining sheets with the
facia pannels, overlaps and other protective elements
for synthetic Composits and other miscelleneus
4,500.00 4,500.00 4,500.00
activities required to complete the item in all respect
including transpotarion & takes.

c) Overhead charges @ 8% on @ 10% on @ 12% on


4,183.15 5,228.94 6,274.73
(a+b) (a+b) (a+b)
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
d) Contractor's profit @ 10% on @ 10% on @ 10% on
5,647.26 5,751.84 5,856.42
(a+b+c) (a+b+c) (a+b+c)
Cost for 300 sqm = a+b+c+d 62,119.83 63,270.20 64,420.57
Rate per sqm = (a+b+c+d)/300 207.07 210.90 214.74
Say 207.00 211.00 215.00
7.9 Suggestive Reinforced cement concrete crash Barrier with
frication slab

Provision of an Reinforced cement concrete crash


barrier with frication slab at the approaches to bridge
structures, Constructed with M-40 grade concrete with
HYSD reinforcement conforming to IRC:112 and as
per dimensions in the approved drawings and at
locations directed by the Engineers, all as specified.
(Area-0.185 sqm/meter) below frication slab and
(Area-1.032 sqm/meter) crash Barrier with frication
slab

Unit = Linear Meter


Taking output 10 m
(i) a) M 40 grade concrete
cum 0.550 8,070.00 4,438.50 Item No. -
PCC M 15 grade concrete (Area-0.185 sqm/meter)
cum 0.550 8,118.00 4,464.90 12.08 A
below frication slab
cum 0.550 8,282.00 4,555.10 Case II
cum 10.320 10,750.00 110,940.00 Item No. -
RCC M 40 grade concrete (Area-1.032 sqm/meter) cum 10.320 10,804.00 111,497.28 14.01 E
cum 10.320 10,991.00 113,427.12 Case II
b) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
c) Material
Fiber Steel (80kg/Cum) Tonne 0.826 0.826 0.826 46,496.54 38,406.15 38,406.15 38,406.15 M-225
d) Overhead charges @ 8% on @ 10% on @ 12% on
3,201.18 4,001.47 4,801.77
(b+c) (b+c) (b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
4,321.59 4,401.62 4,481.65
(b+c+d) (b+c+d) (b+c+d)

Cost for 10 sqm = a+b+c+d+e 162,916.02 164,380.02 167,280.39


Rate per sqm = (a+b+c+d+e)/10 16,291.60 16,438.00 16,728.04
Say 16,292.00 16,438.00 16,728.00
7.10

In-site Soil reinforcement for slope restoration and


protection work (Soil Nailing)(With fully threaded hot-
dip galvanised solid geotechnical bars as soil nails
(galvanization minimum 500 grams per sqm) of
miniimum 25 mm diameter, having yield
strength>670N/mm2 and tensile strength> 800N/mm2
as per technical specifications and drawings etc.
complete including drilling, flusing, grouting and all
supply and installation of all the components listed as
per technical specifications and drawings etc. and
considering all lead, lift and machinery.)

Unit = Running Meter


Taking output 6 m
a) Labour
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Skilled Mazdoor day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Semi Skilled Mazdoor day 2.000 2.000 2.000 617.00 1,234.00 1,234.00 1,234.00 L-14
Highly Skilled day 4.000 4.000 4.000 565.73 2,262.92 2,262.92 2,262.92 L-15
Driller day 1.000 1.000 1.000 558.00 558.00 558.00 558.00 L-06
Operator Grouting day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-17
b) Machinery
Air Compressor 250 cft hour 6.000 6.000 6.000 614.25 3,685.50 3,685.50 3,685.50 P&M-029
Tractor-trolley hour 3.000 3.000 3.000 1,876.50 5,629.50 5,629.50 5,629.50 P&M-026
Grouting pump with agitator hour 6.000 6.000 6.000 798.00 4,788.00 4,788.00 4,788.00 M-110
Drilling Machine hour 6.000 6.000 6.000 11.55 69.30 69.30 69.30 P&M-078
c) Material
Fully Threaded Hot Dip galvanized geotechnical bars
LM 6.000 6.000 6.000 1.00 6.00 6.00 6.00 M296
with casing'
Centralizer No. 3.000 3.000 3.000 1.00 3.00 3.00 3.00 M297
Bearing Plate 200mm x 200mm x 10mm No. 1.000 1.000 1.000 1.00 1.00 1.00 1.00 M298
Spherical Dome Nut No. 1.000 1.000 1.000 1.00 1.00 1.00 1.00 M299
Cement Tonne 0.300 0.300 0.300 4,940.00 1,482.00 1,482.00 1,482.00 M-081
Admixture kg 1.000 1.000 1.000 167.49 167.49 167.49 167.49 M-182
d) Overhead charges @ 8% on @ 10% on @ 12% on
1,713.08 2,141.36 2,569.63
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
2,312.66 2,355.49 2,398.32
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost of repair for10m = a+b+c+d 25,439.30 25,910.40 26,381.50


Cost of meter = (a+b+c+d+e)/6 4,239.88 4,318.40 4,396.92
Say 4,240.00 4,318.00 4,397.00
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
7.11 suggestive
Horizontal Drainage Boring(Horizontal Drainage
Boring methods on the types of sandy soil/ cohesive
soil and drilling length including cost of all materials,
machinary, labour and all other ancillary operations
etc.,(Nominal Diameter of drilling pipe- 90mm))

Nominal Diameter of drilling pipe- 90 mm.


Unit = Running Meter
(i) Drilling length below bed level upto 50.0 Meter
A Sandy Soil / Cohesive Soil
Taking output 32 m
a) Labour
For boring work
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73
For installation of pipe material
Mate day 0.030 0.030 0.030 617.00 18.51 18.51 18.51
Mazdoor day 0.400 0.400 0.400 511.52 204.61 204.61 204.61
Mazdoor skilled day 0.352 0.352 0.352 565.73 199.14 199.14 199.14
For both installation and removal of machinery and
equipment of boring works
Mate day 0.176 0.176 0.176 617.00 108.59 108.59 108.59
Mazdoor day 2.600 2.600 2.600 511.52 1,329.95 1,329.95 1,329.95
Mazdoor skilled day 1.800 1.800 1.800 565.73 1,018.31 1,018.31 1,018.31
For installation and removal of temporary stage in flat
terrain
Mate day 0.364 0.364 0.364 617.00 224.59 224.59 224.59
Mazdoor day 5.700 5.700 5.700 511.52 2,915.66 2,915.66 2,915.66
Mazdoor skilled day 3.400 3.400 3.400 565.73 1,923.48 1,923.48 1,923.48
b) Machinery
Boring Machine hour 8.000 8.000 8.000 5,000.00 40,000.00 40,000.00 40,000.00
Grout pump hour 8.000 8.000 8.000 798.00 6,384.00 6,384.00 6,384.00
Crawler Crane- 5 tonne (for installation and removal
hour 5.600 5.600 5.600 1,128.75 6,321.00 6,321.00 6,321.00
of machinery and equipment)
Crawler Crane- 5 tonne (for temporary stage) hour 3.600 3.600 3.600 1,128.75 4,063.50 4,063.50 4,063.50
c) Material
Polyvinyl Chloride Pipe (PVC) - 90 mm meter 32.960 32.960 32.960 300.00 9,888.00 9,888.00 9,888.00
Core tube (drilling bit) No. 0.416 0.416 0.416 2,000.00 832.00 832.00 832.00
Core tube (drilling pipe) No. 0.224 0.224 0.224 2,000.00 448.00 448.00 448.00
Core tube (Inner rod) No. 0.288 0.288 0.288 2,000.00 576.00 576.00 576.00
Geo-textile for wrapping the pipe including 5%
sqm 11.180 11.180 11.180 62.55 699.31 699.31 699.31
wastage
d) Overhead charges @ 8% on @ 10% on @ 12% on
6,348.29 7,935.37 9,522.44
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
8,570.20 8,728.90 8,887.61
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 32 meter = a+b+c+d+e 94,272.16 96,017.94 97,763.72


Rate per Meter = (a+b+c+d+e)/32 2,946.00 3,000.56 3,055.12
Say 2,946.00 3,001.00 3,055.00
B Gravelly Soil
Taking output 22 m
a) Labour
For boring work
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73
For installation of pipe material
Mate day 0.022 0.022 0.022 617.00 13.57 13.57 13.57
Mazdoor day 0.300 0.300 0.300 511.52 153.46 153.46 153.46
Mazdoor skilled day 0.242 0.242 0.242 565.73 136.91 136.91 136.91
For both installation and removal of machinery and
equipment of boring works
Mate day 0.176 0.176 0.176 617.00 108.59 108.59 108.59
Mazdoor day 2.600 2.600 2.600 511.52 1,329.95 1,329.95 1,329.95
Mazdoor skilled day 1.800 1.800 1.800 565.73 1,018.31 1,018.31 1,018.31
For installation and removal of temporary stage in flat
terrain
Mate day 0.364 0.364 0.364 617.00 224.59 224.59 224.59
Mazdoor day 5.700 5.700 5.700 511.52 2,915.66 2,915.66 2,915.66
Mazdoor skilled day 3.400 3.400 3.400 565.73 1,923.48 1,923.48 1,923.48
b) Machinery
Boring Machine hour 8.000 8.000 8.000 5,000.00 40,000.00 40,000.00 40,000.00
Grout pump hour 8.000 8.000 8.000 798.00 6,384.00 6,384.00 6,384.00
Crawler Crane- 5 tonne (for installation and removal
hour 5.600 5.600 5.600 1,128.75 6,321.00 6,321.00 6,321.00
of machinery and equipment)
Crawler Crane- 5 tonne (for temporary stage) hour 3.600 3.600 3.600 1,128.75 4,063.50 4,063.50 4,063.50
c) Material
Polyvinyl Chloride Pipe (PVC) - 90 mm meter 22.660 22.660 22.660 300.00 6,798.00 6,798.00 6,798.00
Core tube (drilling bit) No. 0.416 0.416 0.416 2,000.00 832.00 832.00 832.00
Core tube (drilling pipe) No. 0.224 0.224 0.224 2,000.00 448.00 448.00 448.00
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Core tube (Inner rod) No. 0.288 0.288 0.288 2,000.00 576.00 576.00 576.00
Geo-textile for wrapping the pipe including 5%
sqm 7.686 7.686 7.686 62.55 480.76 480.76 480.76
wastage
d) Overhead charges @ 8% on @ 10% on @ 12% on
6,074.14 7,592.68 9,111.22
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
8,200.09 8,351.95 8,503.80
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 22 meter = a+b+c+d+e 90,201.04 91,871.43 93,541.82


Rate per Meter = (a+b+c+d+e)/22 4,100.05 4,175.97 4,251.90
Say 4,100.00 4,176.00 4,252.00
C Rubble/Cobble Stone
Taking output 16 m
a) Labour
For boring work
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73
For installation of pipe material
Mate day 0.017 0.017 0.017 617.00 10.49 10.49 10.49
Mazdoor day 0.240 0.240 0.240 511.52 122.76 122.76 122.76
Mazdoor skilled day 0.176 0.176 0.176 565.73 99.57 99.57 99.57
For both installation and removal of machinery and
equipment of boring works
Mate day 0.176 0.176 0.176 617.00 108.59 108.59 108.59
Mazdoor day 2.600 2.600 2.600 511.52 1,329.95 1,329.95 1,329.95
Mazdoor skilled day 1.800 1.800 1.800 565.73 1,018.31 1,018.31 1,018.31
For installation and removal of temporary stage in flat
terrain
Mate day 0.364 0.364 0.364 617.00 224.59 224.59 224.59
Mazdoor day 5.700 5.700 5.700 511.52 2,915.66 2,915.66 2,915.66
Mazdoor skilled day 3.400 3.400 3.400 565.73 1,923.48 1,923.48 1,923.48
b) Machinery
Boring Machine hour 8.000 8.000 8.000 5,000.00 40,000.00 40,000.00 40,000.00
Grout pump hour 8.000 8.000 8.000 798.00 6,384.00 6,384.00 6,384.00
Crawler Crane- 5 tonne (for installation and removal
hour 5.600 5.600 5.600 1,128.75 6,321.00 6,321.00 6,321.00
of machinery and equipment)
Crawler Crane- 5 tonne (for temporary stage) hour 3.600 3.600 3.600 1,128.75 4,063.50 4,063.50 4,063.50
c) Material
Polyvinyl Chloride Pipe (PVC) - 90 mm meter 16.480 16.480 16.480 300.00 4,944.00 4,944.00 4,944.00
Core tube (drilling bit) No. 0.416 0.416 0.416 2,000.00 832.00 832.00 832.00
Core tube (drilling pipe) No. 0.224 0.224 0.224 2,000.00 448.00 448.00 448.00
Core tube (Inner rod) No. 0.288 0.288 0.288 2,000.00 576.00 576.00 576.00
Geo-textile for wrapping the pipe including 5%
sqm 5.590 5.590 5.590 62.55 349.65 349.65 349.65
wastage
d) Overhead charges @ 8% on @ 10% on @ 12% on
5,909.65 7,387.06 8,864.47
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
7,978.02 8,125.76 8,273.50
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 16 meter = a+b+c+d+e 87,758.25 89,383.40 91,008.55


Rate per Meter = (a+b+c+d+e)/16 5,484.89 5,586.46 5,688.03
Say 5,485.00 5,586.00 5,688.00
D Soft Rock
Taking output 20 m
a) Labour
For boring work
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73
For installation of pipe material
Mate day 0.020 0.020 0.020 617.00 12.34 12.34 12.34
Mazdoor day 0.280 0.280 0.280 511.52 143.23 143.23 143.23
Mazdoor skilled day 0.220 0.220 0.220 565.73 124.46 124.46 124.46
For both installation and removal of machinery and
equipment of boring works
Mate day 0.176 0.176 0.176 617.00 108.59 108.59 108.59
Mazdoor day 2.600 2.600 2.600 511.52 1,329.95 1,329.95 1,329.95
Mazdoor skilled day 1.800 1.800 1.800 565.73 1,018.31 1,018.31 1,018.31
For installation and removal of temporary stage in flat
terrain
Mate day 0.364 0.364 0.364 617.00 224.59 224.59 224.59
Mazdoor day 5.700 5.700 5.700 511.52 2,915.66 2,915.66 2,915.66
Mazdoor skilled day 3.400 3.400 3.400 565.73 1,923.48 1,923.48 1,923.48
b) Machinery
Boring Machine hour 8.000 8.000 8.000 5,000.00 40,000.00 40,000.00 40,000.00
Grout pump hour 8.000 8.000 8.000 798.00 6,384.00 6,384.00 6,384.00
Crawler Crane- 5 tonne (for installation and removal
hour 5.600 5.600 5.600 1,128.75 6,321.00 6,321.00 6,321.00
of machinery and equipment)
Crawler Crane- 5 tonne (for temporary stage) hour 3.600 3.600 3.600 1,128.75 4,063.50 4,063.50 4,063.50
c) Material
Polyvinyl Chloride Pipe (PVC) - 90 mm meter 20.600 20.600 20.600 300.00 6,180.00 6,180.00 6,180.00
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Core tube (drilling bit) No. 0.416 0.416 0.416 2,000.00 832.00 832.00 832.00
Core tube (drilling pipe) No. 0.224 0.224 0.224 2,000.00 448.00 448.00 448.00
Core tube (Inner rod) No. 0.288 0.288 0.288 2,000.00 576.00 576.00 576.00
Geo-textile for wrapping the pipe including 5%
sqm 6.988 6.988 6.988 62.55 437.10 437.10 437.10
wastage
d) Overhead charges @ 8% on @ 10% on @ 12% on
6,019.30 7,524.12 9,028.95
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
8,126.05 8,276.54 8,427.02
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 20 meter = a+b+c+d+e 89,386.58 91,041.89 92,697.19


Rate per Meter = (a+b+c+d+e)/20 4,469.33 4,552.09 4,634.86
Say 4,469.00 4,552.00 4,635.00
(ii) Drilling length from 50.0 Meter - 80 meter
A Sandy Soil / Cohesive Soil
Taking output 26.7 m
a) Labour
For boring work
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73
For installation of pipe material
Mate day 0.026 0.026 0.026 617.00 16.04 16.04 16.04
Mazdoor day 0.347 0.347 0.347 511.52 177.50 177.50 177.50
Mazdoor skilled day 0.294 0.294 0.294 565.73 166.32 166.32 166.32
For both installation and removal of machinery and
equipment of boring works
Mate day 0.176 0.176 0.176 617.00 108.59 108.59 108.59
Mazdoor day 2.600 2.600 2.600 511.52 1,329.95 1,329.95 1,329.95
Mazdoor skilled day 1.800 1.800 1.800 565.73 1,018.31 1,018.31 1,018.31
For installation and removal of temporary stage in flat
terrain
Mate day 0.364 0.364 0.364 617.00 224.59 224.59 224.59
Mazdoor day 5.700 5.700 5.700 511.52 2,915.66 2,915.66 2,915.66
Mazdoor skilled day 3.400 3.400 3.400 565.73 1,923.48 1,923.48 1,923.48
b) Machinery
Boring Machine hour 8.000 8.000 8.000 5,000.00 40,000.00 40,000.00 40,000.00
Grout pump hour 8.000 8.000 8.000 798.00 6,384.00 6,384.00 6,384.00
Crawler Crane- 5 tonne (for installation and removal
hour 5.600 5.600 5.600 1,128.75 6,321.00 6,321.00 6,321.00
of machinery and equipment)
Crawler Crane- 5 tonne (for temporary stage) hour 3.600 3.600 3.600 1,128.75 4,063.50 4,063.50 4,063.50
c) Material
Polyvinyl Chloride Pipe (PVC) - 90 mm meter 27.501 27.501 27.501 300.00 8,250.30 8,250.30 8,250.30
Core tube (drilling bit) No. 0.416 0.416 0.416 2,000.00 832.00 832.00 832.00
Core tube (drilling pipe) No. 0.224 0.224 0.224 2,000.00 448.00 448.00 448.00
Core tube (Inner rod) No. 0.288 0.288 0.288 2,000.00 576.00 576.00 576.00
Geo-textile for wrapping the pipe including 5%
sqm 9.328 9.328 9.328 62.55 583.47 583.47 583.47
wastage
d) Overhead charges @ 8% on @ 10% on @ 12% on
6,203.02 7,753.77 9,304.53
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
8,374.08 8,529.15 8,684.23
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 26.7 meter = a+b+c+d+e 92,114.83 93,820.66 95,526.49


Rate per Meter = (a+b+c+d+e)/26.7 3,449.99 3,513.88 3,577.77
Say 3,450.00 3,514.00 3,578.00
B Gravelly Soil
Taking output 18.3 m
a) Labour
For boring work
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73
For installation of pipe material
Mate day 0.019 0.019 0.019 617.00 11.72 11.72 11.72
Mazdoor day 0.263 0.263 0.263 511.52 134.53 134.53 134.53
Mazdoor skilled day 0.201 0.201 0.201 565.73 113.71 113.71 113.71
For both installation and removal of machinery and
equipment of boring works
Mate day 0.176 0.176 0.176 617.00 108.59 108.59 108.59
Mazdoor day 2.600 2.600 2.600 511.52 1,329.95 1,329.95 1,329.95
Mazdoor skilled day 1.800 1.800 1.800 565.73 1,018.31 1,018.31 1,018.31
For installation and removal of temporary stage in flat
terrain
Mate day 0.364 0.364 0.364 617.00 224.59 224.59 224.59
Mazdoor day 5.700 5.700 5.700 511.52 2,915.66 2,915.66 2,915.66
Mazdoor skilled day 3.400 3.400 3.400 565.73 1,923.48 1,923.48 1,923.48
b) Machinery
Boring Machine hour 8.000 8.000 8.000 5,000.00 40,000.00 40,000.00 40,000.00
Grout pump hour 8.000 8.000 8.000 798.00 6,384.00 6,384.00 6,384.00
Crawler Crane- 5 tonne (for installation and removal
hour 5.600 5.600 5.600 1,128.75 6,321.00 6,321.00 6,321.00
of machinery and equipment)
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Crawler Crane- 5 tonne (for temporary stage) hour 3.600 3.600 3.600 1,128.75 4,063.50 4,063.50 4,063.50
c) Material
Polyvinyl Chloride Pipe (PVC) - 90 mm meter 18.849 18.849 18.849 300.00 5,654.70 5,654.70 5,654.70
Core tube (drilling bit) No. 0.416 0.416 0.416 2,000.00 832.00 832.00 832.00
Core tube (drilling pipe) No. 0.224 0.224 0.224 2,000.00 448.00 448.00 448.00
Core tube (Inner rod) No. 0.288 0.288 0.288 2,000.00 576.00 576.00 576.00
Geo-textile for wrapping the pipe including 5%
sqm 6.394 6.394 6.394 62.55 399.94 399.94 399.94
wastage
d) Overhead charges @ 8% on @ 10% on @ 12% on
5,972.70 7,465.87 8,959.05
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
8,063.14 8,212.46 8,361.78
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 18.3 meter = a+b+c+d+e 88,694.55 90,337.04 91,979.53


Rate per Meter = (a+b+c+d+e)/18.3 4,846.70 4,936.45 5,026.20
Say 4,847.00 4,936.00 5,026.00
C Rubble/Cobble Stone
Taking output 13.3 m
a) Labour
For boring work
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73
For installation of pipe material
Mate day 0.014 0.014 0.014 617.00 8.64 8.64 8.64
Mazdoor day 0.213 0.213 0.213 511.52 108.95 108.95 108.95
Mazdoor skilled day 0.146 0.146 0.146 565.73 82.60 82.60 82.60
For both installation and removal of machinery and
equipment of boring works
Mate day 0.176 0.176 0.176 617.00 108.59 108.59 108.59
Mazdoor day 2.600 2.600 2.600 511.52 1,329.95 1,329.95 1,329.95
Mazdoor skilled day 1.800 1.800 1.800 565.73 1,018.31 1,018.31 1,018.31
For installation and removal of temporary stage in flat
terrain
Mate day 0.364 0.364 0.364 617.00 224.59 224.59 224.59
Mazdoor day 5.700 5.700 5.700 511.52 2,915.66 2,915.66 2,915.66
Mazdoor skilled day 3.400 3.400 3.400 565.73 1,923.48 1,923.48 1,923.48
b) Machinery
Boring Machine hour 8.000 8.000 8.000 5,000.00 40,000.00 40,000.00 40,000.00
Grout pump hour 8.000 8.000 8.000 798.00 6,384.00 6,384.00 6,384.00
Crawler Crane- 5 tonne (for installation and removal
hour 5.600 5.600 5.600 1,128.75 6,321.00 6,321.00 6,321.00
of machinery and equipment)
Crawler Crane- 5 tonne (for temporary stage) hour 3.600 3.600 3.600 1,128.75 4,063.50 4,063.50 4,063.50
c) Material
Polyvinyl Chloride Pipe (PVC) - 90 mm meter 13.699 13.699 13.699 300.00 4,109.70 4,109.70 4,109.70
Core tube (drilling bit) No. 0.416 0.416 0.416 2,000.00 832.00 832.00 832.00
Core tube (drilling pipe) No. 0.224 0.224 0.224 2,000.00 448.00 448.00 448.00
Core tube (Inner rod) No. 0.288 0.288 0.288 2,000.00 576.00 576.00 576.00
Geo-textile for wrapping the pipe including 5%
sqm 4.647 4.647 4.647 62.55 290.67 290.67 290.67
wastage
d) Overhead charges @ 8% on @ 10% on @ 12% on
5,835.57 7,294.47 8,753.36
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
7,878.02 8,023.91 8,169.80
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 13.3 meter = a+b+c+d+e 86,658.26 88,263.04 89,867.82


Rate per Meter = (a+b+c+d+e)/13.3 6,515.66 6,636.32 6,756.98
Say 6,516.00 6,636.00 6,757.00
D Soft Rock
Taking output 16.7 m
a) Labour
For boring work
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73
For installation of pipe material
Mate day 0.017 0.017 0.017 617.00 10.49 10.49 10.49
Mazdoor day 0.247 0.247 0.247 511.52 126.35 126.35 126.35
Mazdoor skilled day 0.184 0.184 0.184 565.73 104.09 104.09 104.09
For both installation and removal of machinery and
equipment of boring works
Mate day 0.176 0.176 0.176 617.00 108.59 108.59 108.59
Mazdoor day 2.600 2.600 2.600 511.52 1,329.95 1,329.95 1,329.95
Mazdoor skilled day 1.800 1.800 1.800 565.73 1,018.31 1,018.31 1,018.31
For installation and removal of temporary stage in flat
terrain
Mate day 0.364 0.364 0.364 617.00 224.59 224.59 224.59
Mazdoor day 5.700 5.700 5.700 511.52 2,915.66 2,915.66 2,915.66
Mazdoor skilled day 3.400 3.400 3.400 565.73 1,923.48 1,923.48 1,923.48
b) Machinery
Boring Machine hour 8.000 8.000 8.000 5,000.00 40,000.00 40,000.00 40,000.00
Grout pump hour 8.000 8.000 8.000 798.00 6,384.00 6,384.00 6,384.00
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Crawler Crane- 5 tonne (for installation and removal
hour 5.600 5.600 5.600 1,128.75 6,321.00 6,321.00 6,321.00
of machinery and equipment)
Crawler Crane- 5 tonne (for temporary stage) hour 3.600 3.600 3.600 1,128.75 4,063.50 4,063.50 4,063.50
c) Material
Polyvinyl Chloride Pipe (PVC) - 90 mm meter 17.201 17.201 17.201 300.00 5,160.30 5,160.30 5,160.30
Core tube (drilling bit) No. 0.416 0.416 0.416 2,000.00 832.00 832.00 832.00
Core tube (drilling pipe) No. 0.224 0.224 0.224 2,000.00 448.00 448.00 448.00
Core tube (Inner rod) No. 0.288 0.288 0.288 2,000.00 576.00 576.00 576.00
Geo-textile for wrapping the pipe including 5%
sqm 5.835 5.835 5.835 62.55 364.98 364.98 364.98
wastage
d) Overhead charges @ 8% on @ 10% on @ 12% on
5,928.82 7,411.03 8,893.24
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
8,003.91 8,152.13 8,300.35
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 16.7 meter = a+b+c+d+e 88,043.05 89,673.48 91,303.90


Rate per Meter = (a+b+c+d+e)/16.7 5,272.04 5,369.67 5,467.30
Say 5,272.00 5,370.00 5,467.00
7.12 suggestive
Horizontal Drainage Boring(Nomonal Diameter of
drilling pipe- 110 mm) (Horizontal Drainage Boring
methods on the types of sandy soil/ cohesive soil and
drilling length including cost of all materials,
machinary, labour and all other ancillary operations
etc.,(Nominal Diameter of drilling pipe- 90mm))

Nominal Diameter of drilling pipe- 110 mm.


Unit = Running Meter
(i) Drilling length below bed level upto 50.0 Meter
A Sandy Soil / Cohesive Soil
Taking output 24 m
a) Labour
For boring work
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73
For installation of pipe material
Mate day 0.048 0.048 0.048 617.00 29.62 29.62 29.62
Mazdoor day 0.940 0.940 0.940 511.52 480.83 480.83 480.83
Mazdoor skilled day 0.264 0.264 0.264 565.73 149.35 149.35 149.35
For both installation and removal of machinery and
equipment of boring works
Mate day 0.176 0.176 0.176 617.00 108.59 108.59 108.59
Mazdoor day 2.600 2.600 2.600 511.52 1,329.95 1,329.95 1,329.95
Mazdoor skilled day 1.800 1.800 1.800 565.73 1,018.31 1,018.31 1,018.31
For installation and removal of temporary stage in flat
terrain
Mate day 0.364 0.364 0.364 617.00 224.59 224.59 224.59
Mazdoor day 5.700 5.700 5.700 511.52 2,915.66 2,915.66 2,915.66
Mazdoor skilled day 3.400 3.400 3.400 565.73 1,923.48 1,923.48 1,923.48
b) Machinery
Boring Machine hour 8.000 8.000 8.000 5,000.00 40,000.00 40,000.00 40,000.00
Grout pump hour 8.000 8.000 8.000 798.00 6,384.00 6,384.00 6,384.00
Crawler Crane- 5 tonne (for installation and removal
hour 5.600 5.600 5.600 1,128.75 6,321.00 6,321.00 6,321.00
of machinery and equipment)
Crawler Crane- 5 tonne (for temporary stage) hour 3.600 3.600 3.600 1,128.75 4,063.50 4,063.50 4,063.50
c) Material
Polyvinyl Chloride Pipe (PVC) - 110 mm meter 24.720 24.720 24.720 350.00 8,652.00 8,652.00 8,652.00
Core tube (drilling bit) No. 0.416 0.416 0.416 2,000.00 832.00 832.00 832.00
Core tube (drilling pipe) No. 0.224 0.224 0.224 2,000.00 448.00 448.00 448.00
Core tube (Inner rod) No. 0.288 0.288 0.288 2,000.00 576.00 576.00 576.00
Geo-textile for wrapping the pipe including 5%
sqm 8.385 8.385 8.385 62.55 524.48 524.48 524.48
wastage
d) Overhead charges @ 8% on @ 10% on @ 12% on
6,254.43 7,818.04 9,381.65
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
8,443.48 8,599.84 8,756.20
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 24 meter = a+b+c+d+e 92,878.29 94,598.26 96,318.23


Rate per Meter = (a+b+c+d+e)/24 3,869.93 3,941.59 4,013.26
Say 3,870.00 3,942.00 4,013.00
B Gravelly Soil
Taking output 18 m
a) Labour
For boring work
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73
For installation of pipe material
Mate day 0.043 0.043 0.043 617.00 26.53 26.53 26.53
Mazdoor day 0.880 0.880 0.880 511.52 450.14 450.14 450.14
Mazdoor skilled day 0.198 0.198 0.198 565.73 112.01 112.01 112.01
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
For both installation and removal of machinery and
equipment of boring works
Mate day 0.176 0.176 0.176 617.00 108.59 108.59 108.59
Mazdoor day 2.600 2.600 2.600 511.52 1,329.95 1,329.95 1,329.95
Mazdoor skilled day 1.800 1.800 1.800 565.73 1,018.31 1,018.31 1,018.31
For installation and removal of temporary stage in flat
terrain
Mate day 0.364 0.364 0.364 617.00 224.59 224.59 224.59
Mazdoor day 5.700 5.700 5.700 511.52 2,915.66 2,915.66 2,915.66
Mazdoor skilled day 3.400 3.400 3.400 565.73 1,923.48 1,923.48 1,923.48
b) Machinery
Boring Machine hour 8.000 8.000 8.000 5,000.00 40,000.00 40,000.00 40,000.00
Grout pump hour 8.000 8.000 8.000 798.00 6,384.00 6,384.00 6,384.00
Crawler Crane- 5 tonne (for installation and removal
hour 5.600 5.600 5.600 1,128.75 6,321.00 6,321.00 6,321.00
of machinery and equipment)
Crawler Crane- 5 tonne (for temporary stage) hour 3.600 3.600 3.600 1,128.75 4,063.50 4,063.50 4,063.50
c) Material
Polyvinyl Chloride Pipe (PVC) - 110 mm meter 18.540 18.540 18.540 350.00 6,489.00 6,489.00 6,489.00
Core tube (drilling bit) No. 0.416 0.416 0.416 2,000.00 832.00 832.00 832.00
Core tube (drilling pipe) No. 0.224 0.224 0.224 2,000.00 448.00 448.00 448.00
Core tube (Inner rod) No. 0.288 0.288 0.288 2,000.00 576.00 576.00 576.00
Geo-textile for wrapping the pipe including 5%
sqm 6.289 6.289 6.289 62.55 393.38 393.38 393.38
wastage
d) Overhead charges @ 8% on @ 10% on @ 12% on
6,065.21 7,581.52 9,097.82
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
8,188.04 8,339.67 8,491.30
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 18 meter = a+b+c+d+e 90,068.41 91,736.35 93,404.28


Rate per Meter = (a+b+c+d+e)/18 5,003.80 5,096.46 5,189.13
Say 5,004.00 5,096.00 5,189.00
C Rubble/Cobble Stone
Taking output 14 m
a) Labour
For boring work
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73
For installation of pipe material
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68
Mazdoor day 0.840 0.840 0.840 511.52 429.68 429.68 429.68
Mazdoor skilled day 0.154 0.154 0.154 565.73 87.12 87.12 87.12
For both installation and removal of machinery and
equipment of boring works
Mate day 0.176 0.176 0.176 617.00 108.59 108.59 108.59
Mazdoor day 2.600 2.600 2.600 511.52 1,329.95 1,329.95 1,329.95
Mazdoor skilled day 1.800 1.800 1.800 565.73 1,018.31 1,018.31 1,018.31
For installation and removal of temporary stage in flat
terrain
Mate day 0.364 0.364 0.364 617.00 224.59 224.59 224.59
Mazdoor day 5.700 5.700 5.700 511.52 2,915.66 2,915.66 2,915.66
Mazdoor skilled day 3.400 3.400 3.400 565.73 1,923.48 1,923.48 1,923.48
b) Machinery
Boring Machine hour 8.000 8.000 8.000 5,000.00 40,000.00 40,000.00 40,000.00
Grout pump hour 8.000 8.000 8.000 798.00 6,384.00 6,384.00 6,384.00
Crawler Crane- 5 tonne (for installation and removal
hour 5.600 5.600 5.600 1,128.75 6,321.00 6,321.00 6,321.00
of machinery and equipment)
Crawler Crane- 5 tonne (for temporary stage) hour 3.600 3.600 3.600 1,128.75 4,063.50 4,063.50 4,063.50
c) Material
Polyvinyl Chloride Pipe (PVC) - 110 mm meter 14.420 14.420 14.420 350.00 5,047.00 5,047.00 5,047.00
Core tube (drilling bit) No. 0.416 0.416 0.416 2,000.00 832.00 832.00 832.00
Core tube (drilling pipe) No. 0.224 0.224 0.224 2,000.00 448.00 448.00 448.00
Core tube (Inner rod) No. 0.288 0.288 0.288 2,000.00 576.00 576.00 576.00
Geo-textile for wrapping the pipe including 5%
sqm 4.891 4.891 4.891 62.55 305.93 305.93 305.93
wastage
d) Overhead charges @ 8% on @ 10% on @ 12% on
5,939.08 7,423.85 8,908.62
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
8,017.76 8,166.24 8,314.71
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 14 meter = a+b+c+d+e 88,195.35 89,828.60 91,461.85


Rate per Meter = (a+b+c+d+e)/14 6,299.67 6,416.33 6,532.99
Say 6,300.00 6,416.00 6,533.00
D Soft Rock
Taking output 17 m
a) Labour
For boring work
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73
For installation of pipe material
Mate day 0.042 0.042 0.042 617.00 25.91 25.91 25.91
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Mazdoor day 0.870 0.870 0.870 511.52 445.02 445.02 445.02
Mazdoor skilled day 0.187 0.187 0.187 565.73 105.79 105.79 105.79
For both installation and removal of machinery and
equipment of boring works
Mate day 0.176 0.176 0.176 617.00 108.59 108.59 108.59
Mazdoor day 2.600 2.600 2.600 511.52 1,329.95 1,329.95 1,329.95
Mazdoor skilled day 1.800 1.800 1.800 565.73 1,018.31 1,018.31 1,018.31
For installation and removal of temporary stage in flat
terrain
Mate day 0.364 0.364 0.364 617.00 224.59 224.59 224.59
Mazdoor day 5.700 5.700 5.700 511.52 2,915.66 2,915.66 2,915.66
Mazdoor skilled day 3.400 3.400 3.400 565.73 1,923.48 1,923.48 1,923.48
b) Machinery
Boring Machine hour 8.000 8.000 8.000 5,000.00 40,000.00 40,000.00 40,000.00
Grout pump hour 8.000 8.000 8.000 798.00 6,384.00 6,384.00 6,384.00
Crawler Crane- 5 tonne (for installation and removal
hour 5.600 5.600 5.600 1,128.75 6,321.00 6,321.00 6,321.00
of machinery and equipment)
Crawler Crane- 5 tonne (for temporary stage) hour 3.600 3.600 3.600 1,128.75 4,063.50 4,063.50 4,063.50
c) Material
Polyvinyl Chloride Pipe (PVC) - 110 mm meter 17.510 17.510 17.510 350.00 6,128.50 6,128.50 6,128.50
Core tube (drilling bit) No. 0.416 0.416 0.416 2,000.00 832.00 832.00 832.00
Core tube (drilling pipe) No. 0.224 0.224 0.224 2,000.00 448.00 448.00 448.00
Core tube (Inner rod) No. 0.288 0.288 0.288 2,000.00 576.00 576.00 576.00
Geo-textile for wrapping the pipe including 5%
sqm 5.939 5.939 5.939 62.55 371.48 371.48 371.48
wastage
d) Overhead charges @ 8% on @ 10% on @ 12% on
6,033.67 7,542.08 9,050.50
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
8,145.45 8,296.29 8,447.13
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 17 meter = a+b+c+d+e 89,599.93 91,259.19 92,918.44


Rate per Meter = (a+b+c+d+e)/17 5,270.58 5,368.19 5,465.79
Say 5,271.00 5,368.00 5,466.00
(ii) Drilling length from 50.0 Meter - 80 meter
A Sandy Soil / Cohesive Soil
Taking output 20 m
a) Labour
For boring work
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73
For installation of pipe material
Mate day 0.045 0.045 0.045 617.00 27.77 27.77 27.77
Mazdoor day 0.900 0.900 0.900 511.52 460.37 460.37 460.37
Mazdoor skilled day 0.220 0.220 0.220 565.73 124.46 124.46 124.46
For both installation and removal of machinery and
equipment of boring works
Mate day 0.176 0.176 0.176 617.00 108.59 108.59 108.59
Mazdoor day 2.600 2.600 2.600 511.52 1,329.95 1,329.95 1,329.95
Mazdoor skilled day 1.800 1.800 1.800 565.73 1,018.31 1,018.31 1,018.31
For installation and removal of temporary stage in flat
terrain
Mate day 0.364 0.364 0.364 617.00 224.59 224.59 224.59
Mazdoor day 5.700 5.700 5.700 511.52 2,915.66 2,915.66 2,915.66
Mazdoor skilled day 3.400 3.400 3.400 565.73 1,923.48 1,923.48 1,923.48
b) Machinery
Boring Machine hour 8.000 8.000 8.000 5,000.00 40,000.00 40,000.00 40,000.00
Grout pump hour 8.000 8.000 8.000 798.00 6,384.00 6,384.00 6,384.00
Crawler Crane- 5 tonne (for installation and removal
hour 5.600 5.600 5.600 1,128.75 6,321.00 6,321.00 6,321.00
of machinery and equipment)
Crawler Crane- 5 tonne (for temporary stage) hour 3.600 3.600 3.600 1,128.75 4,063.50 4,063.50 4,063.50
c) Material
Polyvinyl Chloride Pipe (PVC) - 110 mm meter 20.600 20.600 20.600 350.00 7,210.00 7,210.00 7,210.00
Core tube (drilling bit) No. 0.416 0.416 0.416 2,000.00 832.00 832.00 832.00
Core tube (drilling pipe) No. 0.224 0.224 0.224 2,000.00 448.00 448.00 448.00
Core tube (Inner rod) No. 0.288 0.288 0.288 2,000.00 576.00 576.00 576.00
Geo-textile for wrapping the pipe including 5%
sqm 6.988 6.988 6.988 62.55 437.10 437.10 437.10
wastage
d) Overhead charges @ 8% on @ 10% on @ 12% on
6,128.30 7,660.38 9,192.46
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
8,273.21 8,426.42 8,579.63
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 20 meter = a+b+c+d+e 91,005.31 92,690.59 94,375.88


Rate per Meter = (a+b+c+d+e)/20 4,550.27 4,634.53 4,718.79
Say 4,550.00 4,635.00 4,719.00
B Gravelly Soil
Taking output 15 m
a) Labour
For boring work
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73
For installation of pipe material
Mate day 0.041 0.041 0.041 617.00 25.30 25.30 25.30
Mazdoor day 0.850 0.850 0.850 511.52 434.79 434.79 434.79
Mazdoor skilled day 0.165 0.165 0.165 565.73 93.35 93.35 93.35
For both installation and removal of machinery and
equipment of boring works
Mate day 0.176 0.176 0.176 617.00 108.59 108.59 108.59
Mazdoor day 2.600 2.600 2.600 511.52 1,329.95 1,329.95 1,329.95
Mazdoor skilled day 1.800 1.800 1.800 565.73 1,018.31 1,018.31 1,018.31
For installation and removal of temporary stage in flat
terrain
Mate day 0.364 0.364 0.364 617.00 224.59 224.59 224.59
Mazdoor day 5.700 5.700 5.700 511.52 2,915.66 2,915.66 2,915.66
Mazdoor skilled day 3.400 3.400 3.400 565.73 1,923.48 1,923.48 1,923.48
b) Machinery
Boring Machine hour 8.000 8.000 8.000 5,000.00 40,000.00 40,000.00 40,000.00
Grout pump hour 8.000 8.000 8.000 798.00 6,384.00 6,384.00 6,384.00
Crawler Crane- 5 tonne (for installation and removal
hour 5.600 5.600 5.600 1,128.75 6,321.00 6,321.00 6,321.00
of machinery and equipment)
Crawler Crane- 5 tonne (for temporary stage) hour 3.600 3.600 3.600 1,128.75 4,063.50 4,063.50 4,063.50
c) Material
Polyvinyl Chloride Pipe (PVC) - 110 mm meter 15.450 15.450 15.450 350.00 5,407.50 5,407.50 5,407.50
Core tube (drilling bit) No. 0.416 0.416 0.416 2,000.00 832.00 832.00 832.00
Core tube (drilling pipe) No. 0.224 0.224 0.224 2,000.00 448.00 448.00 448.00
Core tube (Inner rod) No. 0.288 0.288 0.288 2,000.00 576.00 576.00 576.00
Geo-textile for wrapping the pipe including 5%
sqm 5.241 5.241 5.241 62.55 327.82 327.82 327.82
wastage
d) Overhead charges @ 8% on @ 10% on @ 12% on
5,970.63 7,463.29 8,955.94
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
8,060.35 8,209.61 8,358.88
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 15 meter = a+b+c+d+e 88,663.84 90,305.76 91,947.68


Rate per Meter = (a+b+c+d+e)/15 5,910.92 6,020.38 6,129.85
Say 5,911.00 6,020.00 6,130.00
C Rubble/Cobble Stone
Taking output 11.7 m
a) Labour
For boring work
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73
For installation of pipe material
Mate day 0.038 0.038 0.038 617.00 23.45 23.45 23.45
Mazdoor day 0.817 0.817 0.817 511.52 417.91 417.91 417.91
Mazdoor skilled day 0.129 0.129 0.129 565.73 72.98 72.98 72.98
For both installation and removal of machinery and
equipment of boring works
Mate day 0.176 0.176 0.176 617.00 108.59 108.59 108.59
Mazdoor day 2.600 2.600 2.600 511.52 1,329.95 1,329.95 1,329.95
Mazdoor skilled day 1.800 1.800 1.800 565.73 1,018.31 1,018.31 1,018.31
For installation and removal of temporary stage in flat
terrain
Mate day 0.364 0.364 0.364 617.00 224.59 224.59 224.59
Mazdoor day 5.700 5.700 5.700 511.52 2,915.66 2,915.66 2,915.66
Mazdoor skilled day 3.400 3.400 3.400 565.73 1,923.48 1,923.48 1,923.48
b) Machinery
Boring Machine hour 8.000 8.000 8.000 5,000.00 40,000.00 40,000.00 40,000.00
Grout pump hour 8.000 8.000 8.000 798.00 6,384.00 6,384.00 6,384.00
Crawler Crane- 5 tonne (for installation and removal
hour 5.600 5.600 5.600 1,128.75 6,321.00 6,321.00 6,321.00
of machinery and equipment)
Crawler Crane- 5 tonne (for temporary stage) hour 3.600 3.600 3.600 1,128.75 4,063.50 4,063.50 4,063.50
c) Material
Polyvinyl Chloride Pipe (PVC) - 110 mm meter 12.051 12.051 12.051 350.00 4,217.85 4,217.85 4,217.85
Core tube (drilling bit) No. 0.416 0.416 0.416 2,000.00 832.00 832.00 832.00
Core tube (drilling pipe) No. 0.224 0.224 0.224 2,000.00 448.00 448.00 448.00
Core tube (Inner rod) No. 0.288 0.288 0.288 2,000.00 576.00 576.00 576.00
Geo-textile for wrapping the pipe including 5%
sqm 4.088 4.088 4.088 62.55 255.70 255.70 255.70
wastage
d) Overhead charges @ 8% on @ 10% on @ 12% on
5,866.56 7,333.20 8,799.84
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
7,919.86 8,066.52 8,213.18
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 11.7 meter = a+b+c+d+e 87,118.41 88,731.71 90,345.02


Rate per Meter = (a+b+c+d+e)/11.7 7,446.02 7,583.91 7,721.80
Say 7,446.00 7,584.00 7,722.00
D Soft Rock
Taking output 14.2 m
a) Labour
For boring work
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73
For installation of pipe material
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68
Mazdoor day 0.842 0.842 0.842 511.52 430.70 430.70 430.70
Mazdoor skilled day 0.156 0.156 0.156 565.73 88.25 88.25 88.25
For both installation and removal of machinery and
equipment of boring works
Mate day 0.176 0.176 0.176 617.00 108.59 108.59 108.59
Mazdoor day 2.600 2.600 2.600 511.52 1,329.95 1,329.95 1,329.95
Mazdoor skilled day 1.800 1.800 1.800 565.73 1,018.31 1,018.31 1,018.31
For installation and removal of temporary stage in flat
terrain
Mate day 0.364 0.364 0.364 617.00 224.59 224.59 224.59
Mazdoor day 5.700 5.700 5.700 511.52 2,915.66 2,915.66 2,915.66
Mazdoor skilled day 3.400 3.400 3.400 565.73 1,923.48 1,923.48 1,923.48
b) Machinery
Boring Machine hour 8.000 8.000 8.000 5,000.00 40,000.00 40,000.00 40,000.00
Grout pump hour 8.000 8.000 8.000 798.00 6,384.00 6,384.00 6,384.00
Crawler Crane- 5 tonne (for installation and removal
hour 5.600 5.600 5.600 1,128.75 6,321.00 6,321.00 6,321.00
of machinery and equipment)
Crawler Crane- 5 tonne (for temporary stage) hour 3.600 3.600 3.600 1,128.75 4,063.50 4,063.50 4,063.50
c) Material
Polyvinyl Chloride Pipe (PVC) - 110 mm meter 14.626 14.626 14.626 350.00 5,119.10 5,119.10 5,119.10
Core tube (drilling bit) No. 0.416 0.416 0.416 2,000.00 832.00 832.00 832.00
Core tube (drilling pipe) No. 0.224 0.224 0.224 2,000.00 448.00 448.00 448.00
Core tube (Inner rod) No. 0.288 0.288 0.288 2,000.00 576.00 576.00 576.00
Geo-textile for wrapping the pipe including 5%
sqm 4.961 4.961 4.961 62.55 310.31 310.31 310.31
wastage
d) Overhead charges @ 8% on @ 10% on @ 12% on
5,945.37 7,431.71 8,918.06
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
8,026.25 8,174.89 8,323.52
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 14.2 meter = a+b+c+d+e 88,288.77 89,923.75 91,558.72


Rate per Meter = (a+b+c+d+e)/14.2 6,217.52 6,332.66 6,447.80
Say 6,218.00 6,333.00 6,448.00
7.13 suggestive
Horizontal Drainage Boring(Nomonal Diameter of
drilling pipe- 135 mm)(Horizontal Drainage Boring
methods on the types of sandy soil/ cohesive soil and
drilling length including cost of all materials,
machinary, labour and all other ancillary operations
etc.,(Nominal Diameter of drilling pipe- 90mm))

Nominal Diameter of drilling pipe- 135 mm.


Unit = Running Meter
(i) Drilling length below bed level upto 50.0 Meter
A Sandy Soil / Cohesive Soil
Taking output 20 m
a) Labour
For boring work
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73
For installation of pipe material
Mate day 0.020 0.020 0.020 617.00 12.34 12.34 12.34
Mazdoor day 0.270 0.270 0.270 511.52 138.11 138.11 138.11
Mazdoor skilled day 0.220 0.220 0.220 565.73 124.46 124.46 124.46
For both installation and removal of machinery and
equipment of boring works
Mate day 0.176 0.176 0.176 617.00 108.59 108.59 108.59
Mazdoor day 2.600 2.600 2.600 511.52 1,329.95 1,329.95 1,329.95
Mazdoor skilled day 1.800 1.800 1.800 565.73 1,018.31 1,018.31 1,018.31
For installation and removal of temporary stage in flat
terrain
Mate day 0.364 0.364 0.364 617.00 224.59 224.59 224.59
Mazdoor day 5.700 5.700 5.700 511.52 2,915.66 2,915.66 2,915.66
Mazdoor skilled day 3.400 3.400 3.400 565.73 1,923.48 1,923.48 1,923.48
b) Machinery
Boring Machine hour 8.000 8.000 8.000 5,000.00 40,000.00 40,000.00 40,000.00
Grout pump hour 8.000 8.000 8.000 798.00 6,384.00 6,384.00 6,384.00
Crawler Crane- 5 tonne (for installation and removal
hour 5.600 5.600 5.600 1,128.75 6,321.00 6,321.00 6,321.00
of machinery and equipment)
Crawler Crane- 5 tonne (for temporary stage) hour 3.600 3.600 3.600 1,128.75 4,063.50 4,063.50 4,063.50
c) Material
Polyvinyl Chloride Pipe (PVC) - 135mm meter 20.600 20.600 20.600 400.00 8,240.00 8,240.00 8,240.00
Core tube (drilling bit) No. 0.416 0.416 0.416 2,000.00 832.00 832.00 832.00
Core tube (drilling pipe) No. 0.224 0.224 0.224 2,000.00 448.00 448.00 448.00
Core tube (Inner rod) No. 0.288 0.288 0.288 2,000.00 576.00 576.00 576.00
Geo-textile for wrapping the pipe including 5%
sqm 6.988 6.988 6.988 62.55 437.10 437.10 437.10
wastage
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
d) Overhead charges @ 8% on @ 10% on @ 12% on
6,183.69 7,729.61 9,275.53
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
8,347.98 8,502.57 8,657.16
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 20 meter = a+b+c+d+e 91,827.78 93,528.30 95,228.81


Rate per Meter = (a+b+c+d+e)/20 4,591.39 4,676.41 4,761.44
Say 4,591.00 4,676.00 4,761.00
B Gravelly Soil
Taking output 15 m
a) Labour
For boring work
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73
For installation of pipe material
Mate day 0.015 0.015 0.015 617.00 9.26 9.26 9.26
Mazdoor day 0.220 0.220 0.220 511.52 112.53 112.53 112.53
Mazdoor skilled day 0.165 0.165 0.165 565.73 93.35 93.35 93.35
For both installation and removal of machinery and
equipment of boring works
Mate day 0.176 0.176 0.176 617.00 108.59 108.59 108.59
Mazdoor day 2.600 2.600 2.600 511.52 1,329.95 1,329.95 1,329.95
Mazdoor skilled day 1.800 1.800 1.800 565.73 1,018.31 1,018.31 1,018.31
For installation and removal of temporary stage in flat
terrain
Mate day 0.364 0.364 0.364 617.00 224.59 224.59 224.59
Mazdoor day 5.700 5.700 5.700 511.52 2,915.66 2,915.66 2,915.66
Mazdoor skilled day 3.400 3.400 3.400 565.73 1,923.48 1,923.48 1,923.48
b) Machinery
Boring Machine hour 8.000 8.000 8.000 5,000.00 40,000.00 40,000.00 40,000.00
Grout pump hour 8.000 8.000 8.000 798.00 6,384.00 6,384.00 6,384.00
Crawler Crane- 5 tonne (for installation and removal
hour 5.600 5.600 5.600 1,128.75 6,321.00 6,321.00 6,321.00
of machinery and equipment)
Crawler Crane- 5 tonne (for temporary stage) hour 3.600 3.600 3.600 1,128.75 4,063.50 4,063.50 4,063.50
c) Material
Polyvinyl Chloride Pipe (PVC) - 135mm meter 15.450 15.450 15.450 400.00 6,180.00 6,180.00 6,180.00
Core tube (drilling bit) No. 0.416 0.416 0.416 2,000.00 832.00 832.00 832.00
Core tube (drilling pipe) No. 0.224 0.224 0.224 2,000.00 448.00 448.00 448.00
Core tube (Inner rod) No. 0.288 0.288 0.288 2,000.00 576.00 576.00 576.00
Geo-textile for wrapping the pipe including 5%
sqm 5.241 5.241 5.241 62.55 327.82 327.82 327.82
wastage
d) Overhead charges @ 8% on @ 10% on @ 12% on
6,005.36 7,506.71 9,008.05
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
8,107.24 8,257.38 8,407.51
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 15 meter = a+b+c+d+e 89,179.67 90,831.14 92,482.62


Rate per Meter = (a+b+c+d+e)/15 5,945.31 6,055.41 6,165.51
Say 5,945.00 6,055.00 6,166.00
C Rubble/Cobble Stone
Taking output 13 m
a) Labour
For boring work
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73
For installation of pipe material
Mate day 0.014 0.014 0.014 617.00 8.64 8.64 8.64
Mazdoor day 0.200 0.200 0.200 511.52 102.30 102.30 102.30
Mazdoor skilled day 0.143 0.143 0.143 565.73 80.90 80.90 80.90
For both installation and removal of machinery and
equipment of boring works
Mate day 0.176 0.176 0.176 617.00 108.59 108.59 108.59
Mazdoor day 2.600 2.600 2.600 511.52 1,329.95 1,329.95 1,329.95
Mazdoor skilled day 1.800 1.800 1.800 565.73 1,018.31 1,018.31 1,018.31
For installation and removal of temporary stage in flat
terrain
Mate day 0.364 0.364 0.364 617.00 224.59 224.59 224.59
Mazdoor day 5.700 5.700 5.700 511.52 2,915.66 2,915.66 2,915.66
Mazdoor skilled day 3.400 3.400 3.400 565.73 1,923.48 1,923.48 1,923.48
b) Machinery
Boring Machine hour 8.000 8.000 8.000 5,000.00 40,000.00 40,000.00 40,000.00
Grout pump hour 8.000 8.000 8.000 798.00 6,384.00 6,384.00 6,384.00
Crawler Crane- 5 tonne (for installation and removal
hour 5.600 5.600 5.600 1,128.75 6,321.00 6,321.00 6,321.00
of machinery and equipment)
Crawler Crane- 5 tonne (for temporary stage) hour 3.600 3.600 3.600 1,128.75 4,063.50 4,063.50 4,063.50
c) Material
Polyvinyl Chloride Pipe (PVC) - 135mm meter 13.390 13.390 13.390 400.00 5,356.00 5,356.00 5,356.00
Core tube (drilling bit) No. 0.416 0.416 0.416 2,000.00 832.00 832.00 832.00
Core tube (drilling pipe) No. 0.224 0.224 0.224 2,000.00 448.00 448.00 448.00
Core tube (Inner rod) No. 0.288 0.288 0.288 2,000.00 576.00 576.00 576.00
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Geo-textile for wrapping the pipe including 5%
sqm 4.542 4.542 4.542 62.55 284.10 284.10 284.10
wastage
d) Overhead charges @ 8% on @ 10% on @ 12% on
5,934.08 7,417.60 8,901.13
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
8,011.01 8,159.37 8,307.72
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 13 meter = a+b+c+d+e 88,121.14 89,753.02 91,384.89


Rate per Meter = (a+b+c+d+e)/13 6,778.55 6,904.08 7,029.61
Say 6,779.00 6,904.00 7,030.00
D Soft Rock
Taking output 15 m
a) Labour
For boring work
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73
For installation of pipe material
Mate day 0.015 0.015 0.015 617.00 9.26 9.26 9.26
Mazdoor day 0.220 0.220 0.220 511.52 112.53 112.53 112.53
Mazdoor skilled day 0.165 0.165 0.165 565.73 93.35 93.35 93.35
For both installation and removal of machinery and
equipment of boring works
Mate day 0.176 0.176 0.176 617.00 108.59 108.59 108.59
Mazdoor day 2.600 2.600 2.600 511.52 1,329.95 1,329.95 1,329.95
Mazdoor skilled day 1.800 1.800 1.800 565.73 1,018.31 1,018.31 1,018.31
For installation and removal of temporary stage in flat
terrain
Mate day 0.364 0.364 0.364 617.00 224.59 224.59 224.59
Mazdoor day 5.700 5.700 5.700 511.52 2,915.66 2,915.66 2,915.66
Mazdoor skilled day 3.400 3.400 3.400 565.73 1,923.48 1,923.48 1,923.48
b) Machinery
Boring Machine hour 8.000 8.000 8.000 5,000.00 40,000.00 40,000.00 40,000.00
Grout pump hour 8.000 8.000 8.000 798.00 6,384.00 6,384.00 6,384.00
Crawler Crane- 5 tonne (for installation and removal
hour 5.600 5.600 5.600 1,128.75 6,321.00 6,321.00 6,321.00
of machinery and equipment)
Crawler Crane- 5 tonne (for temporary stage) hour 3.600 3.600 3.600 1,128.75 4,063.50 4,063.50 4,063.50
c) Material
Polyvinyl Chloride Pipe (PVC) - 135mm meter 15.450 15.450 15.450 400.00 6,180.00 6,180.00 6,180.00
Core tube (drilling bit) No. 0.416 0.416 0.416 2,000.00 832.00 832.00 832.00
Core tube (drilling pipe) No. 0.224 0.224 0.224 2,000.00 448.00 448.00 448.00
Core tube (Inner rod) No. 0.288 0.288 0.288 2,000.00 576.00 576.00 576.00
Geo-textile for wrapping the pipe including 5%
sqm 5.241 5.241 5.241 62.55 327.82 327.82 327.82
wastage
d) Overhead charges @ 8% on @ 10% on @ 12% on
6,005.36 7,506.71 9,008.05
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
8,107.24 8,257.38 8,407.51
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 15 meter = a+b+c+d+e 89,179.67 90,831.14 92,482.62


Rate per Meter = (a+b+c+d+e)/15 5,945.31 6,055.41 6,165.51
Say 5,945.00 6,055.00 6,166.00
(ii) Drilling length from 50.0 Meter - 80 meter
A Sandy Soil / Cohesive Soil
Taking output 16.7 m
a) Labour
For boring work
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73
For installation of pipe material
Mate day 0.017 0.017 0.017 617.00 10.49 10.49 10.49
Mazdoor day 0.230 0.230 0.230 511.52 117.65 117.65 117.65
Mazdoor skilled day 0.184 0.184 0.184 565.73 104.09 104.09 104.09
For both installation and removal of machinery and
equipment of boring works
Mate day 0.184 0.184 0.184 617.00 113.53 113.53 113.53
Mazdoor day 2.800 2.800 2.800 511.52 1,432.26 1,432.26 1,432.26
Mazdoor skilled day 1.800 1.800 1.800 565.73 1,018.31 1,018.31 1,018.31
For installation and removal of temporary stage in flat
terrain
Mate day 0.364 0.364 0.364 617.00 224.59 224.59 224.59
Mazdoor day 5.700 5.700 5.700 511.52 2,915.66 2,915.66 2,915.66
Mazdoor skilled day 3.400 3.400 3.400 565.73 1,923.48 1,923.48 1,923.48
b) Machinery
Boring Machine hour 8.000 8.000 8.000 5,000.00 40,000.00 40,000.00 40,000.00
Grout pump hour 8.000 8.000 8.000 798.00 6,384.00 6,384.00 6,384.00
Crawler Crane- 5 tonne (for installation and removal
hour 5.600 5.600 5.600 1,128.75 6,321.00 6,321.00 6,321.00
of machinery and equipment)
Crawler Crane- 5 tonne (for temporary stage) hour 3.600 3.600 3.600 1,128.75 4,063.50 4,063.50 4,063.50
c) Material
Polyvinyl Chloride Pipe (PVC) - 135mm meter 17.201 17.201 17.201 400.00 6,880.40 6,880.40 6,880.40
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Core tube (drilling bit) No. 0.416 0.416 0.416 2,000.00 832.00 832.00 832.00
Core tube (drilling pipe) No. 0.224 0.224 0.224 2,000.00 448.00 448.00 448.00
Core tube (Inner rod) No. 0.288 0.288 0.288 2,000.00 576.00 576.00 576.00
Geo-textile for wrapping the pipe including 5%
sqm 5.835 5.835 5.835 62.55 364.98 364.98 364.98
wastage
d) Overhead charges @ 8% on @ 10% on @ 12% on
6,074.32 7,592.90 9,111.47
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
8,200.33 8,352.18 8,504.04
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 16.7 meter = a+b+c+d+e 90,203.60 91,874.03 93,544.47


Rate per Meter = (a+b+c+d+e)/16.7 5,401.41 5,501.44 5,601.47
Say 5,401.00 5,501.00 5,601.00
B Gravelly Soil
Taking output 12.5 m
a) Labour
For boring work
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73
For installation of pipe material
Mate day 0.013 0.013 0.013 617.00 8.02 8.02 8.02
Mazdoor day 0.188 0.188 0.188 511.52 96.17 96.17 96.17
Mazdoor skilled day 0.138 0.138 0.138 565.73 78.07 78.07 78.07
For both installation and removal of machinery and
equipment of boring works
Mate day 0.184 0.184 0.184 617.00 113.53 113.53 113.53
Mazdoor day 2.800 2.800 2.800 511.52 1,432.26 1,432.26 1,432.26
Mazdoor skilled day 1.800 1.800 1.800 565.73 1,018.31 1,018.31 1,018.31
For installation and removal of temporary stage in flat
terrain
Mate day 0.364 0.364 0.364 617.00 224.59 224.59 224.59
Mazdoor day 5.700 5.700 5.700 511.52 2,915.66 2,915.66 2,915.66
Mazdoor skilled day 3.400 3.400 3.400 565.73 1,923.48 1,923.48 1,923.48
b) Machinery
Boring Machine hour 8.000 8.000 8.000 5,000.00 40,000.00 40,000.00 40,000.00
Grout pump hour 8.000 8.000 8.000 798.00 6,384.00 6,384.00 6,384.00
Crawler Crane- 5 tonne (for installation and removal
hour 5.600 5.600 5.600 1,128.75 6,321.00 6,321.00 6,321.00
of machinery and equipment)
Crawler Crane- 5 tonne (for temporary stage) hour 3.600 3.600 3.600 1,128.75 4,063.50 4,063.50 4,063.50
c) Material
Polyvinyl Chloride Pipe (PVC) - 135mm meter 12.875 12.875 12.875 400.00 5,150.00 5,150.00 5,150.00
Core tube (drilling bit) No. 0.416 0.416 0.416 2,000.00 832.00 832.00 832.00
Core tube (drilling pipe) No. 0.224 0.224 0.224 2,000.00 448.00 448.00 448.00
Core tube (Inner rod) No. 0.288 0.288 0.288 2,000.00 576.00 576.00 576.00
Geo-textile for wrapping the pipe including 5%
sqm 4.367 4.367 4.367 62.55 273.16 273.16 273.16
wastage
d) Overhead charges @ 8% on @ 10% on @ 12% on
5,924.54 7,405.68 8,886.81
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
7,998.13 8,146.24 8,294.36
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 12.5 meter = a+b+c+d+e 87,979.43 89,608.67 91,237.92


Rate per Meter = (a+b+c+d+e)/12.5 7,038.35 7,168.69 7,299.03
Say 7,038.00 7,169.00 7,299.00
C Rubble/Cobble Stone
Taking output 10.8 m
a) Labour
For boring work
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73
For installation of pipe material
Mate day 0.012 0.012 0.012 617.00 7.40 7.40 7.40
Mazdoor day 0.171 0.171 0.171 511.52 87.47 87.47 87.47
Mazdoor skilled day 0.119 0.119 0.119 565.73 67.32 67.32 67.32
For both installation and removal of machinery and
equipment of boring works
Mate day 0.184 0.184 0.184 617.00 113.53 113.53 113.53
Mazdoor day 2.800 2.800 2.800 511.52 1,432.26 1,432.26 1,432.26
Mazdoor skilled day 1.800 1.800 1.800 565.73 1,018.31 1,018.31 1,018.31
For installation and removal of temporary stage in flat
terrain
Mate day 0.364 0.364 0.364 617.00 224.59 224.59 224.59
Mazdoor day 5.700 5.700 5.700 511.52 2,915.66 2,915.66 2,915.66
Mazdoor skilled day 3.400 3.400 3.400 565.73 1,923.48 1,923.48 1,923.48
b) Machinery
Boring Machine hour 8.000 8.000 8.000 5,000.00 40,000.00 40,000.00 40,000.00
Grout pump hour 8.000 8.000 8.000 798.00 6,384.00 6,384.00 6,384.00
Crawler Crane- 5 tonne (for installation and removal
hour 5.600 5.600 5.600 1,128.75 6,321.00 6,321.00 6,321.00
of machinery and equipment)
Crawler Crane- 5 tonne (for temporary stage) hour 3.600 3.600 3.600 1,128.75 4,063.50 4,063.50 4,063.50
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
c) Material
Polyvinyl Chloride Pipe (PVC) - 135mm meter 11.124 11.124 11.124 400.00 4,449.60 4,449.60 4,449.60
Core tube (drilling bit) No. 0.416 0.416 0.416 2,000.00 832.00 832.00 832.00
Core tube (drilling pipe) No. 0.224 0.224 0.224 2,000.00 448.00 448.00 448.00
Core tube (Inner rod) No. 0.288 0.288 0.288 2,000.00 576.00 576.00 576.00
Geo-textile for wrapping the pipe including 5%
sqm 3.773 3.773 3.773 62.55 236.00 236.00 236.00
wastage
d) Overhead charges @ 8% on @ 10% on @ 12% on
5,863.93 7,329.91 8,795.90
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
7,916.31 8,062.91 8,209.50
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 10.8 meter = a+b+c+d+e 87,079.38 88,691.96 90,304.54


Rate per Meter = (a+b+c+d+e)/10.8 8,062.91 8,212.22 8,361.53
Say 8,063.00 8,212.00 8,362.00
D Soft Rock
Taking output 12.5 m
a) Labour
For boring work
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73
For installation of pipe material
Mate day 0.013 0.040 0.040 617.00 8.02 24.68 24.68
Mazdoor day 0.188 0.842 0.842 511.52 96.17 430.70 430.70
Mazdoor skilled day 0.138 0.156 0.156 565.73 78.07 88.25 88.25
For both installation and removal of machinery and
equipment of boring works
Mate day 0.184 0.176 0.176 617.00 113.53 108.59 108.59
Mazdoor day 2.800 2.600 2.600 511.52 1,432.26 1,329.95 1,329.95
Mazdoor skilled day 1.800 1.800 1.800 565.73 1,018.31 1,018.31 1,018.31
For installation and removal of temporary stage in flat
terrain
Mate day 0.364 0.364 0.364 617.00 224.59 224.59 224.59
Mazdoor day 5.700 5.700 5.700 511.52 2,915.66 2,915.66 2,915.66
Mazdoor skilled day 3.400 3.400 3.400 565.73 1,923.48 1,923.48 1,923.48
b) Machinery
Boring Machine hour 8.000 8.000 8.000 5,000.00 40,000.00 40,000.00 40,000.00
Grout pump hour 8.000 8.000 8.000 798.00 6,384.00 6,384.00 6,384.00
Crawler Crane- 5 tonne (for installation and removal
hour 5.600 5.600 5.600 1,128.75 6,321.00 6,321.00 6,321.00
of machinery and equipment)
Crawler Crane- 5 tonne (for temporary stage) hour 3.600 3.600 3.600 1,128.75 4,063.50 4,063.50 4,063.50
c) Material
Polyvinyl Chloride Pipe (PVC) - 135mm meter 12.875 24.720 24.720 400.00 5,150.00 9,888.00 9,888.00
Core tube (drilling bit) No. 0.416 0.416 0.416 2,000.00 832.00 832.00 832.00
Core tube (drilling pipe) No. 0.224 0.224 0.224 2,000.00 448.00 448.00 448.00
Core tube (Inner rod) No. 0.288 0.288 0.288 2,000.00 576.00 576.00 576.00
Geo-textile for wrapping the pipe including 5%
sqm 4.367 4.961 4.961 62.55 273.16 310.31 310.31
wastage
d) Overhead charges @ 8% on @ 10% on @ 12% on
5,924.54 7,908.60 9,490.33
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
7,998.13 8,699.47 8,857.64
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 12.5 meter = a+b+c+d+e 87,979.43 95,694.12 97,434.01


Rate per Meter = (a+b+c+d+e)/12.5 7,038.35 7,655.53 7,794.72
Say 7,038.00 7,656.00 7,795.00
7.14 710.1.4 Selected fill behind Reinforced Earth Wall Complete
of IRC78 & as per drawing and Technical specification
2200
A Granular Material
Unit = Cum
Taking output 250 cum
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
(i) Motor grader 4.30 metre blade hour 1.210 5,991.00 7,249.11 P&M-004
(ii) Motor grader 3.70 metre blade hour 1.459 5,497.00 8,020.12 P&M-005
(iii) Motor grader 3.35 metre blade hour 1.627 4,796.00 7,803.09 P&M-006
Vibratory roller hour 1.214 1.214 1.214 903.50 1,096.85 1,096.85 1,096.85 P&M-018
Water tanker ( speed @ water tanker speed km/hr
and return speed @ 20 km/hr and spreading speed @
3.0 km/hr)
(i) 16 KL capacity 0.292xL1+0.
hour 1,501.00 13,849.73 P&M-023
467
(ii) 12 KL capacity 0.389xL1+0.6
hour 1,327.00 16,311.48 P&M-024
22
(iii) 6 KL capacity 0.778xL1+1.
hour 1,005.00 24,706.92 P&M-025
244
c) Material
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Cost of Water KL 42.000 42.000 42.000 16.00 672.00 672.00 672.00 M-191
Granular material cum 300.000 300.000 300.000 1,887.12 566,136.93 566,136.93 566,136.93 M-009
d) Overhead charges @ 8% on @ 10% on @ 12% on
47,210.50 59,336.40 72,185.09
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
63,734.17 65,270.04 67,372.75
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 250 sqm = a+b+c+d+e 701,075.90 717,970.44 741,100.24


Rate per sqm = (a+b+c+d+e)/250 2,804.30 2,871.88 2,964.40
Say 2,804.00 2,872.00 2,964.00
B Sandy Material
Unit = Cum
Taking output 450 cum
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
(i) Motor grader 4.30 metre blade hour 2.177 5,991.00 13,042.41 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.626 5,497.00 14,435.12 P&M-005
(iii) Motor grader 3.35 metre blade hour 2.929 4,796.00 14,047.48 P&M-006
Water tanker ( speed @ water tanker speed km/hr
and return speed @ 20 km/hr and spreading speed @
2.5 km/hr)
(i) 16 KL capacity 0.25xL1+0.8
hour 1,501.00 12,554.36 P&M-023
64
(ii) 12 KL capacity 0.333xL1+1.1
hour 1,327.00 14,785.43 P&M-024
52
(iii) 6 KL capacity 0.667xL1+2.
hour 1,005.00 22,425.57 P&M-025
304
Vibratory roller hour 2.184 2.184 2.184 903.50 1,973.24 1,973.24 1,973.24 P&M-018
c) Material
Cost of Water KL 36.000 36.000 36.000 16.00 576.00 576.00 576.00 M-191
Sand at Site cum 450.000 450.000 450.000 1,544.03 694,813.95 694,813.95 694,813.95 M-006
d) Overhead charges @ 8% on @ 10% on @ 12% on
57,922.59 72,765.62 88,189.04
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
78,195.50 80,042.18 82,309.77
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 450 sqm = a+b+c+d+e 860,150.45 880,463.94 905,407.45


Rate per sqm = (a+b+c+d+e)/450 1,911.45 1,956.59 2,012.02
Say 1,911.00 1,957.00 2,012.00
7.15 710.1.4.of
IRC:78 and
2504.2 Providing and laying of Filter media with granular
materials/stone crushed aggregates satisfying the
requirements laid down in clause 2504.2.2. of MoRTH
specifications to a thickness of not less than 600 mm
with smaller size towards the soil and bigger size
towards the wall and provided over the entire surface
behind abutment, wing wall and return wall to the full
height compacted to a firm condition complete as per
drawing and Technical Specification.

Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mazdoor for filling, watering, ramming etc. day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
Mazdoor (Skilled) day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
b) Material
Filter media of stone aggregate conforming to clause cum M-011
2504.2.2. of MoRTH specifications. 12.000 12.000 12.000 1,215.07 14,580.87 14,580.87 14,580.87
c) Machinery
Water Tanker of 6 KL capacity hour 0.060 0.060 0.060 1,005.00 60.30 60.30 60.30 P&M-025
d) Overhead charges @ 8% on @ 10% on @ 12% on
1,518.80 1,898.50 2,278.20
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
2,050.38 2,088.35 2,126.32
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 10 cum = a+b+c+d+e 22,554.16 22,971.83 23,389.50


Rate per cum = (a+b+c+d+e)/10 2,255.42 2,297.18 2,338.95
Say 2,255.00 2,297.00 2,339.00
7.16 704
Supplying & laying of drainage composite for use
behind walls with Geo synthetic Drainage Composite
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
7.16 A

Supplying & laying of drainage composite for use


behind walls, between two different fills, alongside
drains of road, below concrete lining of canals etc.
Geocomposite for drainage, realized by
thermobonding a draining core in extruded
monofilaments with two filtering nonwoven geotextiles
that may also be working as separation or protecting
layers. The draining three dimensional core will have
a “W” configuration as longitudinal parallel channels.
Minimum thickness to be 7.2mm, with two filtering UV
stabilized polypropylene nonwoven geotextile of
minimum thickness of 0.75 mm having pores of 150
micron and tensile strength of 8.0 kN/m that will be
working as separation or protecting layer,
geocomposite having in plane flow capacity of 2.1 L /
(m.s) at hydraulic gradient of 1.0 & 20 kpa pressure
and tensile strength of 18 kN/m , with mass per unit
area of 740 gsm, supplied in the form of roll for easy
transportation to site of work as per detailed
specification all complete as per directions of
Engineer in charge.

Unit = Sqm
Taking output 300 Sqm

a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Mazdoor (Skilled ) day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Material
Geosynthetic Drainage Composite (tensile strength of sqm 300.00 300.00 300.00 M-290
18 kN/ m) 175.00 52,500.00 52,500.00 52,500.00
Add 10 per cent of the cost of synthetic Composits for
wastage and accessories for joining sheets with the
facia pannels, overlaps and other protective elements
for synthetic Composits and other miscelleneus
5,250.00 5,250.00 5,250.00
activities required to complete the item in all respect
including transpotarion & takes.

d) Overhead charges @ 8% on @ 10% on @ 12% on


4,843.15 6,053.94 7,264.73
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
6,538.26 6,659.34 6,780.42
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 300 sqm= a+b+c+d+e 71,920.83 73,252.70 74,584.57


Rate per sqm = (a+b+c+d+e)/300 239.74 244.18 248.62
Say 240.00 244.00 249.00
7.16 B

Supplying & laying of drainage composite for use


behind walls, between two different fills, alongside
drains of road, below concrete lining of canals etc.
Geocomposite for drainage, realized by
thermobonding a draining core in extruded
monofilaments with two filtering nonwoven geotextiles
that may also be working as separation or protecting
layers. The draining three dimensional core will have
a “W” configuration as longitudinal parallel channels.
Minimum thickness to be 7.2mm, with two filtering UV
stabilized polypropylene nonwoven geotextile of
minimum thickness of 0.75 mm having pores of 150
micron and tensile strength of 8.0 kN/m that will be
working as separation or protecting layer,
geocomposite having in plane flow capacity of 2.1 L /
(m.s) at hydraulic gradient of 1.0 & 20 kpa pressure
and tensile strength of 18 kN/m , with mass per unit
area of 740 gsm, supplied in the form of roll for easy
transportation to site of work as per detailed
specification all complete as per directions of
Engineer in charge.

Unit = Sqm
Taking output 300 Sqm

a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Mazdoor (Skilled ) day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Material
Geosynthetic Drainage Composite (tensile strength of sqm 300.00 300.00 300.00 M-290
13.5 kN/ m) 150.00 45,000.00 45,000.00 45,000.00
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Add 10 per cent of the cost of synthetic Composits for
wastage and accessories for joining sheets with the
facia pannels, overlaps and other protective elements
for synthetic Composits and other miscelleneus
4,500.00 4,500.00 4,500.00
activities required to complete the item in all respect
including transpotarion & takes.

d) Overhead charges @ 8% on @ 10% on @ 12% on


4,183.15 5,228.94 6,274.73
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
5,647.26 5,751.84 5,856.42
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 300 sqm= a+b+c+d+e 62,119.83 63,270.20 64,420.57


Rate per sqm = (a+b+c+d+e)/300 207.07 210.90 214.74
Say 207.00 211.00 215.00
7.17 705 Geocell for Slope Protection

Furnishing and installing of the Geocell for Slope


Protection including fixing and anchoring of cells in
the ground ,preparation of ground, filling of cells with
specified materials, seeding,watering and all other
incidentals including all other items to complete the
work as per these specifications drawing or as
directed by the engineer.

Unit = Sqm
Taking output 100 Sqm

a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Mazdoor for preparation of ground and laying of the day 1.000 1.000 1.000 L-13
Geocell 511.52 511.52 511.52 511.52
Mazdoor (Skilled ) day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
b) Material
Geocell sqm 100.00 100.00 100.00 80.00 8,000.00 8,000.00 8,000.00 M-290
Add 10 per cent of the cost of Geocell for wastage,
overlaps and accessories for anchoring with the
ground, other protective elements for Geocell and
other miscelleneus activities required to complete the 800.00 800.00 800.00
item in all respect including transpotarion & takes.

d) Overhead charges @ 8% on @ 10% on @ 12% on


770.51 963.14 1,155.77
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
1,040.19 1,059.45 1,078.72
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 100 sqm= a+b+c+d+e 11,442.11 11,654.00 11,865.89


Rate per sqm = (a+b+c+d+e)/100 114.42 116.54 118.66
Say 114.00 117.00 119.00
Note For rate of soil filling, turfing/seeding, refer
relevant chapter-03
7.18 706 Geosynthetics mat on the slope

Furnishing and installing of the Geosynthetics mat for


control of erosion of slopes including supplying and
laying the mat, spreading soil and seeding to promote
the design of vegetation, watering and all other
incidentals including all other items to complete the
work as per these specifications drawing or as
directed by the engineer.

Unit = Sqm
Taking output 100 Sqm
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Mazdoor for preparation of ground and laying of the day 1.000 1.000 1.000 L-13
Geocell 511.52 511.52 511.52 511.52
Mazdoor (Skilled ) day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
b) Material
Geosynthetics mat sqm 100.00 100.00 100.00 50.00 5,000.00 5,000.00 5,000.00 M-290
Add 10 per cent of the cost of Geosynthetics mat for
wastage, overlaps and accessories for anchoring with
the ground, other protective elements for
Geosynthetics mat and other miscelleneus activities
500.00 500.00 500.00
required to complete the item in all respect including
transpotarion & takes.

d) Overhead charges @ 8% on @ 10% on @ 12% on


506.51 633.14 759.77
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
683.79 696.45 709.12
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 100 sqm= a+b+c+d+e 7,521.71 7,661.00 7,800.29


Rate per sqm = (a+b+c+d+e)/100 75.22 76.61 78.00
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Say 75.00 77.00 78.00
Note For rate of soil filling, turfing/seeding, refer
relevant chapter-03
7.19 707 Natural Geotextile on the slope

Furnishing and installing of the natural Geotextile for


control of erosion of slopes including suppling and
laying the natural Geotextile, spreading soil and
seeding to promote the design of vegetation, watering
and all other items to be complete the work as per
these specifications drawing or as directed by the
Engineer.

Unit = Sqm
Taking output 100 Sqm
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Mazdoor for preparation of ground and laying of the day 1.000 1.000 1.000 L-13
Geocell 511.52 511.52 511.52 511.52
Mazdoor (Skilled ) day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
b) Material
Natural geotextile sqm 100.00 100.00 100.00 25.00 2,500.00 2,500.00 2,500.00 M-290

Add 10 per cent of the cost of Natural geotextile for


wastage, overlaps and accessories for anchoring with
the ground, other protective elements for Natural
250.00 250.00 250.00
geotextile and other miscelleneus activities required
to complete the item in all respect including
transpotarion & takes.

d) Overhead charges @ 8% on @ 10% on @ 12% on


286.51 358.14 429.77
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
386.79 393.95 401.12
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 100 sqm= a+b+c+d+e 4,254.71 4,333.50 4,412.29


Rate per sqm = (a+b+c+d+e)/100 42.55 43.34 44.12
Say 43.00 43.00 44.00
Note For rate of soil filling, turfing/seeding, refer
relevant chapter-03
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
8.01 409 Cast in Situ Cement Concrete M20 Kerb

Construction of cement concrete kerb with top and


bottom width 115 and 165 mm respectively, 250 mm high
in M 20 grade on M-15 grade foundation 150 mm thick,
foundation having 50 mm projection beyond kerb stone,
kerb stone laid with kerb laying machine, foundation
concrete laid manually, all complete as per clause 409

Unit = Running metre


Taking output = 360 meter
Using Concrete Batching and Mixing Plant
(i) PCC M15 for Kerb base
Total Concrete = 11.610 Cum.
a) Labour
Mate day 0.240 0.240 0.240 617.00 148.08 148.08 148.08 L-12
Mason day 2.000 2.000 2.000 679.00 1,358.00 1,358.00 1,358.00 L-10
Mazdoor day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
b) Machinery
Transit truck agitator
For Transportation Transit truck agitator 6 cum capacity t.km. 26.703 x L 26.703 x L 26.703 x L 13.41 10,743.28 10,743.28 10,743.28 P&M-128
For loading & Unloding time hour 3.729 3.729 3.729 2,413.95 9,001.62 9,001.62 9,001.62 P&M-067
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and Curing speed @ 2 km/hr )
0.011xL1+0.
(i) 16 KL capacity hour 1,501.00 675.45 P&M-023
12
0.015xL1+0.1
(ii) 12 KL capacity hour 1,327.00 756.39 P&M-024
2
0.03xL1+0.1
(iii) 6 KL capacity hour 1,005.00 1,025.10 P&M-025
2
c) Material

Sub-Analysis
Concrete from sub-analysis of concrete Rate cum 11.610 11.610 11.610 4,176.00 48,483.36 48,483.36 48,483.36 of Concrete -
20.21

Cost of water KL 1.602 1.602 1.602 16.00 25.63 25.63 25.63 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
5,798.52 7,256.24 8,739.74
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
7,828.00 7,981.87 8,157.09
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 360 meter = a+b+c+d+e 86,108.03 87,800.56 89,727.98


Rate per metre = (a+b+c+d+e)/360 239.19 243.89 249.24
Say 239.00 244.00 249.00

(ii) PCC M20 for Kerb Cast in Situ


Total Concrete = 12.600 Cum.
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Mason day 0.500 0.500 0.500 679.00 339.50 339.50 339.50 L-10
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Kerb casting machine @ 120 metres/hour hour 3.000 3.000 3.000 1,957.20 5,871.60 5,871.60 5,871.60 P&M-070
Transit truck agitator
For Transportation Transit truck agitator 6 cum capacity t.km. 28.980 x L 28.980 x L 28.980 x L 13.41 11,659.38 11,659.38 11,659.38 P&M-128
For loading & Unloding time hour 3.140 3.140 3.140 2,413.95 7,579.80 7,579.80 7,579.80 P&M-067
Concrete cutting machine hour 6.000 6.000 6.000 1,251.00 7,506.00 7,506.00 7,506.00 P&M-098
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and Curing speed @ 2 km/hr )
0.042xL1+0.
(i) 16 KL capacity hour 1,501.00 2,071.38 P&M-023
12
0.056xL1+0.1
(ii) 12 KL capacity hour 1,327.00 2,388.60 P&M-024
2
0.113xL1+0.
(iii) 6 KL capacity hour 1,005.00 3,527.55 P&M-025
12
c) Material

Sub-Analysis
Concrete from sub-analysis of concrete Rate cum 12.600 12.600 12.600 4,518.00 56,926.80 56,926.80 56,926.80 of Concrete -
20.2

Cost of water KL 6.086 6.086 6.086 16.00 97.37 97.37 97.37 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
7,408.03 9,291.76 11,286.79
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
10,000.84 10,220.94 10,534.33
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 360 meter = a+b+c+d+e 110,009.24 112,430.29 115,877.66


Rate per metre = (a+b+c+d+e)/360 305.58 312.31 321.88
Say 306.00 312.00 322.00
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project

8.02 409 Cast in Situ Cement Concrete M 20 Kerb with Channel

Construction of cement concrete kerb with channel with


top and bottom width 115 and 165 mm respectively, 250
mm high in M 20 grade PCC on M15 grade foundation
150 mm thick, kerb channel 300 mm wide, 50 mm thick in
PCCM20 grade, sloped towards the kerb, kerb stone with
channel laid with kerb laying machine, foundation
concrete laid manually, all complete as per clause 409
Cement concrete of grade M20= 17.48 cum
Cement concrete of grade M10 for base = 23.18 cum
Total Concrete = 40.66 cum
Unit = Running metre
Taking output = 300 meter
Total Concrete = 9.675 Cum.
Using Concrete Batching and Mixing Plant
(i) PCC M15 for Kerb base
Total Concrete = 9.675 Cum.
a) Labour
Mate day 0.240 0.240 0.240 617.00 148.08 148.08 148.08 L-12
Mason day 2.000 2.000 2.000 679.00 1,358.00 1,358.00 1,358.00 L-10
Mazdoor day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
b) Machinery
Transit truck agitator
For Transportation Transit truck agitator 6 cum capacity t.km. 26.703 x L 26.703 x L 26.703 x L 13.41 10,743.28 10,743.28 10,743.28 P&M-128
For loading & Unloding time hour 3.108 3.108 3.108 2,413.95 7,501.35 7,501.35 7,501.35 P&M-067
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and Curing speed @ 2 km/hr )
0.009xL1+0.
(i) 16 KL capacity hour 1,501.00 555.37 P&M-023
1

(ii) 12 KL capacity hour 0.012xL1+0.1 1,327.00 610.42 P&M-024

0.025xL1+0.
(iii) 6 KL capacity hour 1,005.00 854.25 P&M-025
1
c) Material

Sub-Analysis
Concrete from sub-analysis of concrete Rate cum 9.675 9.675 9.675 4,176.00 40,402.80 40,402.80 40,402.80 of Concrete -
20.2

Cost of water KL 1.335 1.335 1.335 16.00 21.36 21.36 21.36 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
5,022.11 6,283.14 7,569.02
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
6,779.84 6,911.45 7,064.42
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 360 meter = a+b+c+d+e 74,578.27 76,025.96 77,708.65


Rate per metre = (a+b+c+d+e)/300 248.59 253.42 259.03
Say 249.00 253.00 259.00

(ii) PCC M20 for Kerb Cast in Situ


Total Concrete = 15.000 Cum.
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Mason day 0.500 0.500 0.500 679.00 339.50 339.50 339.50 L-10
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Kerb casting machine @ 90 metres/hour hour 3.333 3.333 3.333 1,957.20 6,524.00 6,524.00 6,524.00 P&M-070
Transit truck agitator
For Transportation Transit truck agitator 6 cum capacity t.km. 28.980 x L 28.980 x L 28.980 x L 13.41 11,659.38 11,659.38 11,659.38 P&M-128
For loading & Unloding time hour 3.500 3.500 3.500 2,413.95 8,448.83 8,448.83 8,448.83 P&M-067
Concrete cutting machine hour 5.000 5.000 5.000 1,251.00 6,255.00 6,255.00 6,255.00 P&M-098
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and Curing speed @ 2 km/hr )

(i) 16 KL capacity hour 0.05xL1+0.1 1,501.00 2,401.60 P&M-023

(ii) 12 KL capacity hour 0.067xL1+0.1 1,327.00 2,799.97 P&M-024

0.134xL1+0.
(iii) 6 KL capacity hour 1,005.00 4,140.60 P&M-025
1
c) Material

Sub-Analysis
Concrete from sub-analysis of concrete Rate cum 15.000 15.000 15.000 4,518.00 67,770.00 67,770.00 67,770.00 of Concrete -
20.21

Cost of water KL 7.245 7.245 7.245 16.00 115.92 115.92 115.92 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
8,325.02 10,446.11 12,696.21
(a+b+c) (a+b+c) (a+b+c)
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
11,238.78 11,490.72 11,849.80
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 360 meter = a+b+c+d+e 123,626.56 126,397.97 130,347.77


Rate per metre = (a+b+c+d+e)/300 412.09 421.33 434.49
Say 412.00 421.00 434.00
8.03 801 Printing New Letter and Figures of any Shade
Printing new letter and figures of any shade with
synthetic enamel paint black or any other approved
colour to give an even shade

Hindi ( Matras commas and the like not to be measured


(i)
and paid for Half letter shall be counted as half )

Details for 100 letters of 16 cm height i.e. 1600 cm 1600.00 Cm.


Unit = per cm height per letter
a) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Painter day 2.000 2.000 2.000 679.00 1,358.00 1,358.00 1,358.00 L-18
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Material
Paint Litre 0.700 0.700 0.700 235.22 164.65 164.65 164.65 M-130
Per Cm. Basic Cost of Labour & Material (a+b) 1.318 1.318 1.318
c) Overhead charges @ 8% on @ 10% on @ 12% on
168.66 210.82 252.99
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
227.69 231.90 236.12
(a+b+c) (a+b+c) (a+b+c)
Cost for 1600 cm = a+b+c+d 2,504.56 2,550.94 2,597.32
Rate per cm height per letter = (a+b+c+ d)/1600 1.57 1.59 1.62
Say 1.60 1.60 1.60
8.03 (ii) English and Roman
Hyphens and the like not to be measured and paid for
Detail for 100 letters of 16 cm height. i.e.1600 cm 1600.00 Cm.
Unit = per cm height per letter
a) Labour
Mate day 0.070 0.070 0.070 617.00 43.19 43.19 43.19 L-12
Painter Ist class day 1.250 1.250 1.250 679.00 848.75 848.75 848.75 L-18
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
b) Material
Paint Litre 0.500 0.500 0.500 235.22 117.61 117.61 117.61 M-130
Per Cm. Basic Cost of Labour & Material (a+b) 0.79 0.79 0.79
c) Overhead charges @ 8% on @ 10% on @ 12% on
101.22 126.53 151.84
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
136.65 139.18 141.71
(a+b+c) (a+b+c) (a+b+c)
Cost for 1600 cm = a+b+c+d 1,503.19 1,531.03 1,558.86
Rate per cm height per letter = (a+b+c +d)/1600 0.94 0.96 0.97
Say 0.90 1.00 1.00
8.04 801 Retro-Reflectorised Traffic Signs

Providing and fixing of retro- reflectorised cautionary,


mandatory and informatory sign as per IRC :67 made of
high intensity grade sheeting vide clause 801.3, 2mm
thick aluminium sheeting, 3mm/4mm thick Aluminum
composite material sheet depending on the size of the
sign fixed over back support frame of min 25x25x3mm
Angle mounted on a mild steel circular pipe 65 NB ,3.2
mm thicknness firmly fixed to the ground by means of
properly designed foundation with M25 grade cement
concrete 45 cm x 45 cm x 60 cm, 60 cm below ground
level as per approved drawing.

Unit = Each
Taking output = one traffic sign
i) Excavation for foundation cum 0.122 223.00 27.21
Item No. -
cum 0.122 227.00 27.69
9.01 A - (I)
cum 0.122 231.00 28.18
ii) Cement concrete M25 grade cum 0.122 8,734.00 1,061.18 Item No. -
cum 0.122 8,942.00 1,086.45 9.06 E, case -
cum 0.122 9,266.00 1,125.82 II
iii) Painting angle iron post two coats sqm 1.414 93.00 131.48
Item No. -
sqm 1.414 95.00 134.30
8.09
sqm 1.414 97.00 137.13
a) Labour (For fixing at site)
Mate day 0.010 0.010 0.010 617.00 6.17 6.17 6.17 L-12
Mazdoor day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
b) Material
Mild Steel 'L' Angle Back Support Frame 25 x 25 x 3mm kg 2.200 2.200 2.200 63.81 140.37 140.37 140.37 M-181/1000

Mild Steel circular pipe 65 NB ,3.2 mm thicknness,


kg 20.556 20.556 20.556 63.81 1,311.61 1,311.61 1,311.61 M-181/1000
3.6 meter height
Aluminium sheeting fixed with encapsulated lens type
reflective sheeting of size including lettering and signs as
applicable
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
(i) 120 cm equilateral triangle sqm 0.624 0.624 0.624 7,560.00 4,713.95 4,713.95 4,713.95 M-061
Add 1 per cent of cost material (b) towards cost of drilling
61.66 61.66 61.66
holes, nuts, bolts etc.
or
( ii ) 90 cm equilateral triangle sqm 0.351 0.351 0.351 7,560.00 2,651.60 2,651.60 2,651.60 M-061
Add 1 per cent of cost material (b) towards cost of drilling
41.04 41.04 41.04
holes, nuts, bolts etc.
or
(iii) 75 cm equilateral triangle sqm 0.244 0.244 0.244 7,560.00 1,841.39 1,841.39 1,841.39 M-061
Add 1 per cent of cost material (b) towards cost of drilling
32.93 32.93 32.93
holes, nuts, bolts etc.
or
(iv) 60 cm equilateral triangle sqm 0.156 0.156 0.156 7,560.00 1,178.49 1,178.49 1,178.49 M-061
Add 1 per cent of cost material (b) towards cost of drilling
26.30 26.30 26.30
holes, nuts, bolts etc.
or
(v) 120 cm circular sqm 1.131 1.131 1.131 7,560.00 8,550.16 8,550.16 8,550.16 M-061
Add 1 per cent of cost material (b) towards cost of drilling
100.02 100.02 100.02
holes, nuts, bolts etc.
or
(vi) 90 cm circular sqm 0.636 0.636 0.636 7,560.00 4,809.46 4,809.46 4,809.46 M-061
Add 1 per cent of cost material (b) towards cost of drilling
62.61 62.61 62.61
holes, nuts, bolts etc.
or
(vii) 75cm circular sqm 0.442 0.442 0.442 7,560.00 3,339.91 3,339.91 3,339.91 M-061
Add 1 per cent of cost material (b) towards cost of drilling
47.92 47.92 47.92
holes, nuts, bolts etc.
or
(viii) 60 cm circular sqm 0.283 0.283 0.283 7,560.00 2,137.54 2,137.54 2,137.54 M-061
Add 1 per cent of cost material (b) towards cost of drilling
35.90 35.90 35.90
holes, nuts, bolts etc.
or
( ix ) 90 cm x 75 cm rectangular sqm 0.675 0.675 0.675 7,560.00 5,103.00 5,103.00 5,103.00 M-061
Add 1 per cent of cost material (b) towards cost of drilling
65.55 65.55 65.55
holes, nuts, bolts etc.
or
(x) 80 mm x 60 mm rectangular sqm 0.480 0.480 0.480 7,560.00 3,628.80 3,628.80 3,628.80 M-061
Add 1 per cent of cost material (b) towards cost of drilling
50.81 50.81 50.81
holes, nuts, bolts etc.
or
(xi) 60 cm x 50 cm rectangular sqm 0.300 0.300 0.300 7,560.00 2,268.00 2,268.00 2,268.00 M-061
Add 1 per cent of cost material (b) towards cost of drilling
37.20 37.20 37.20
holes, nuts, bolts etc.
or
(xii) 60 cm x 45 cm rectangular sqm 0.270 0.270 0.270 7,560.00 2,041.20 2,041.20 2,041.20 M-061
Add 1 per cent of cost material (b) towards cost of drilling
34.93 34.93 34.93
holes, nuts, bolts etc.
or
(xiii ) 60 cm x 60 cm square sqm 0.360 0.360 0.360 7,560.00 2,721.60 2,721.60 2,721.60 M-061
Add 1 per cent of cost material (b) towards cost of drilling
41.74 41.74 41.74
holes, nuts, bolts etc.
or
(xiv) 120 cm high octagon sqm 1.193 1.193 1.193 7,560.00 9,018.59 9,018.59 9,018.59 M-061
Add 1 per cent of cost material (b) towards cost of drilling
104.71 104.71 104.71
holes, nuts, bolts etc.
or
(xv) 90 cm high octagon sqm 0.671 0.671 0.671 7,560.00 5,072.96 5,072.96 5,072.96 M-061
Add 1 per cent of cost material (b) towards cost of drilling
65.25 65.25 65.25
holes, nuts, bolts etc.
or
( xvi ) 75 cm high octagon sqm 0.466 0.466 0.466 7,560.00 3,522.89 3,522.89 3,522.89 M-061
Add 1 per cent of cost material (b) towards cost of drilling
49.75 49.75 49.75
holes, nuts, bolts etc.

c) Machinery
Tractor-trolley hour 0.010 0.010 0.010 1,876.50 18.77 18.77 18.77 P&M-026

(i) 120 cm equilateral triangle


d) Overhead charges @ 8% on @ 10% on @ 12% on
510.43 638.04 765.65
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
689.08 701.84 714.61
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 8,799.78 8,968.74 9,151.79


Say 8,800.00 8,969.00 9,152.00

( ii ) 90 cm equilateral triangle
d) Overhead charges @ 8% on @ 10% on @ 12% on
343.79 429.74 515.69
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
464.12 472.72 481.31
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 6,325.21 6,448.34 6,585.56


Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
Say 6,325.00 6,448.00 6,586.00

(iii) 75 cm equilateral triangle


d) Overhead charges @ 8% on @ 10% on @ 12% on
278.33 347.91 417.49
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
375.74 382.70 389.66
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 5,353.05 5,458.18 5,577.40


Say 5,353.00 5,458.00 5,577.00

(iv) 60 cm equilateral triangle


d) Overhead charges @ 8% on @ 10% on @ 12% on
224.77 280.96 337.15
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
303.44 309.05 314.67
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 4,557.65 4,648.05 4,752.54


Say 4,558.00 4,648.00 4,753.00

( v ) 120 cm circular
d) Overhead charges @ 8% on @ 10% on @ 12% on
820.40 1,025.50 1,230.60
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
1,107.54 1,128.05 1,148.56
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 13,402.77 13,656.97 13,925.26


Say 13,403.00 13,657.00 13,925.00

(vi) 90 cm circular
d) Overhead charges @ 8% on @ 10% on @ 12% on
518.15 647.69 777.23
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
699.50 712.46 725.41
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 8,914.39 9,085.47 9,270.64


Say 8,914.00 9,085.00 9,271.00

(vii) 75cm circular


d) Overhead charges @ 8% on @ 10% on @ 12% on
399.41 499.26 599.11
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
539.20 549.19 559.17
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 7,151.10 7,289.52 7,442.04


Say 7,151.00 7,290.00 7,442.00

(viii) 60 cm circular
d) Overhead charges @ 8% on @ 10% on @ 12% on
302.26 377.82 453.39
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
408.05 415.61 423.16
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 5,708.40 5,820.11 5,945.91


Say 5,708.00 5,820.00 5,946.00

( ix ) 90 cm x 75 cm rectangular
d) Overhead charges @ 8% on @ 10% on @ 12% on
541.87 677.33 812.80
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
731.52 745.07 758.61
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 9,266.60 9,444.20 9,635.89


Say 9,267.00 9,444.00 9,636.00

( x ) 80 mm x 60 mm rectangular
d) Overhead charges @ 8% on @ 10% on @ 12% on
422.75 528.44 634.13
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
570.72 581.28 591.85
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 7,497.74 7,642.58 7,801.52


Say 7,498.00 7,643.00 7,802.00

(xi) 60 cm x 50 cm rectangular
d) Overhead charges @ 8% on @ 10% on @ 12% on
312.80 391.00 469.20
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
422.28 430.10 437.92
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 5,864.94 5,979.55 6,108.25


Say 5,865.00 5,980.00 6,108.00
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
(xii) 60 cm x 45 cm rectangular
d) Overhead charges @ 8% on @ 10% on @ 12% on
294.47 368.09 441.71
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
397.54 404.90 412.26
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 5,592.81 5,702.37 5,826.04


Say 5,593.00 5,702.00 5,826.00

(xiii ) 60 cm x 60 cm square
d) Overhead charges @ 8% on @ 10% on @ 12% on
349.45 436.81 524.18
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
471.76 480.49 489.23
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 6,409.20 6,533.89 6,672.67


Say 6,409.00 6,534.00 6,673.00

(xiv) 120 cm high octagon


d) Overhead charges @ 8% on @ 10% on @ 12% on
858.25 1,072.81 1,287.37
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
1,158.63 1,180.09 1,201.55
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 13,964.84 14,229.44 14,508.14


Say 13,965.00 14,229.00 14,508.00

(xv) 90 cm high octagon


d) Overhead charges @ 8% on @ 10% on @ 12% on
539.44 674.30 809.16
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
728.24 741.73 755.22
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 9,230.55 9,407.48 9,598.51


Say 9,231.00 9,407.00 9,599.00

( xvi ) 75 cm high octagon


d) Overhead charges @ 8% on @ 10% on @ 12% on
414.19 517.74 621.29
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
559.16 569.52 579.87
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 7,370.65 7,513.14 7,669.73


Say 7,371.00 7,513.00 7,670.00
1.Any one area of aluminium sheeting given at (i) to (vii)
Note may be adopted as per site requirement and in
accordance with IRC : 67
2.Rate for excavation, cement concrete M-15 and
painting may be taken from respective chapters
3. The depth of foundation and quantity of cement
concrete in the foundation are indicative. These may be
increased for areas having higher wind velocities like in
coastal areas. This is applicable to all road signs and
directions boards.
Direction and Place Identification Signs upto 0.9 sqm
8.05 801
Size Board.

Providing and erecting direction and place identification


retro-reflectorised sign as per IRC :67 made of high
intensity grade sheeting vide clause 801.3, fixed over
aluminium sheeting, 2 mm thick or Aluminum composite
material sheet with overall thickness of 4mm with area
not exceeding 0.9 sqm fixed over back support frame of
min 35 x 35 x 3mm Angle mounted on a mild steel
circular pipe 65 NB, firmly fixed to the ground by means
of properly designed foundation with M25 grade cement
concrete 45 x 45 x 60 cm, 60 cm below ground level as
per approved drawing

Unit = sqm
Taking output = 0.9 sqm
i) Excavation for foundation cum 0.122 223.00 27.21
Item No. -
cum 0.122 227.00 27.69
9.01 A - (I)
cum 0.122 231.00 28.18
ii) Cement concrete M25 grade cum 0.122 8,734.00 1,061.18 Item No. -
cum 0.122 8,942.00 1,086.45 9.06 E, case -
cum 0.122 9,266.00 1,125.82 II
iii) Painting angle iron post two coats sqm 1.414 93.00 131.48
Item No. -
sqm 1.414 95.00 134.30
8.09
sqm 1.414 97.00 137.13
a) Labour (For fixing at site)
Mate day 0.008 0.008 0.008 617.00 4.94 4.94 4.94 L-12
Mazdoor day 0.200 0.200 0.200 511.52 102.30 102.30 102.30 L-13
b) Material
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project

Mild Steel 'L' Angle Back Support Frame 35 x 35 x 3mm kg 6.080 6.080 6.080 63.81 387.94 387.94 387.94 M-181/1000

Mild Steel circular pipe 65 NB ,3.2 mm thicknness,


kg 20.556 20.556 20.556 63.81 1,311.61 1,311.61 1,311.61 M-181/1000
3.6 meter height
Aluminium sheeting fixed with encapsulated lens type
sqm 0.900 0.900 0.900 7,560.00 6,804.00 6,804.00 6,804.00 M-061
reflective sheeting of size 0.9 sqm
Add 2 per cent of cost of materials for drilling holes,
170.07 170.07 170.07
nuts, bolts, fabrication etc.
c) Machinery
Tractor-trolley hour 0.020 0.020 0.020 1,876.50 37.53 37.53 37.53 P&M-026
d) Overhead charges @ 8% on @ 10% on @ 12% on
705.47 881.84 1,058.21
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
952.39 970.02 987.66
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 0.9 sqm =I+ii+ii+ a+b+c+d+e 11,696.11 11,918.70 12,155.39


Rate per sqm (for sign having area upto 0.9 sqm) =
12,995.68 13,243.01 13,505.99
(I+ii+iii+a+b+c+d+e)/0.90
Say 12,996.00 13,243.00 13,506.00

I) Lettering and arrow marks on sign board to be provided


Note separately as per actual requirement. Rates for these
items have been analysed separately

ii) Rate for excavation, cement concrete M-25 and


painting may be taken from respective chapters
Direction and Place Identification Signs with size more
8.06 801
than 0.9 sqm size Board.

Providing and erecting direction and place identification


retro-reflectorised sign as per IRC :67 made of High
Intensity grade sheeting lause 801.3, fixed over
aluminium sheeting, 2 mm thick or Aluminum composite
material sheet with overall thickness of 4 mm with area
exceeding 0.9 sqm fixed over back support frame of min
40 x 40 x 5 mm MS Angle mounted on two nos. of mild
steel circular pipe 65 NB ,3.2 mm thicknness and 4.5
meter total height firmly fixed to the ground by means of
properly designed foundation with M 25 grade cement
concrete 45 cm x 45 cm x 60 cm, 60 cm below ground
level as per approved drawing

Unit = sqm
Taking output = 1.5 sqm
i) Excavation for foundation cum 0.243 223.00 54.19
Item No. -
cum 0.243 227.00 55.16
9.01 A - (I)
cum 0.243 231.00 56.13
ii) Cement concrete M25 grade cum 0.243 8,734.00 2,122.36 Item No. -
cum 0.243 8,942.00 2,172.91 9.06 E, case -
cum 0.243 9,266.00 2,251.64 II
iii) Painting angle iron post two coats sqm 2.827 93.00 262.91
Item No. -
sqm 2.827 95.00 268.57
8.09
sqm 2.827 97.00 274.22
a) Labour (For fixing at site)
Mate day 0.012 0.012 0.012 617.00 7.40 7.40 7.40 L-12
Mazdoor day 0.300 0.300 0.300 511.52 153.46 153.46 153.46 L-13
b) Material
Mild Steel 'L' Angle Back Support Frame 40 x 40 x 5 mm kg 14.400 14.400 14.400 63.81 918.81 918.81 918.81 M-181/1000

Mild Steel circular pipe 65 NB ,3.2 mm thicknness,


kg 41.112 41.112 41.112 63.81 2,623.21 2,623.21 2,623.21 M-181/1000
3.6 meter height
Aluminium sheeting fixed with encapsulated lens type
sqm 1.500 1.500 1.500 7,560.00 11,340.00 11,340.00 11,340.00 M-061
reflective sheeting
Add 2 per cent of cost of materials for drilling holes,
297.64 297.64 297.64
nuts, bolts, fabrication etc.
c) Machinery
Tractor-trolley hour 0.020 0.020 0.020 1,876.50 37.53 37.53 37.53 P&M-026
d) Overhead charges @ 8% on @ 10% on @ 12% on
1,230.24 1,537.81 1,826.06
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
1,660.83 1,691.59 1,720.41
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 1.5 sqm =I+ii+ii+ a+b+c+d+e 20,708.60 21,104.08 21,506.53


Rate per sqm ( for sign having area more than 0.9 sqm) =
13,805.73 14,069.39 14,337.68
( i+ii+iii+a+b+c+d+e)/1.50
Say 13,806.00 14,069.00 14,338.00

i) Lettering and arrow marks on sign board to be provided


Note separately as per actual requirement. Rates for these
items have been analysed separately

ii) Rate for excavation, cement concrete M-15 and


painting may be taken from respective chapters
8.07 802 Overhead Signs
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project

Providing and erecting overhead signs with a corrosion


resistant 2mm thick aluminium alloy sheet reflectorised
with high intensity retro-reflective sheeting of
encapsulated lense type with vertical and lateral
clearance given in clause 802.2 and 802.3 and installed
as per clause 802.7 over a designed support system of
aluminium alloy or galvanised steel trestles and trusses
of sections and type as per structural design
requirements and approved plans & as per IRC :67

A Truss and Vertical Support


Unit = tonne
Taking output = 1 tonne
a) Labour
Mate day 0.240 0.240 0.240 617.00 148.08 148.08 148.08 L-12
Blacksmith day 2.000 2.000 2.000 738.00 1,476.00 1,476.00 1,476.00 L-02
Mazdoor including for handling & fixing at site. day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
b) Material
Aluminium alloy / galvanised steel including 2 per cent
tonne 1.020 1.020 1.020 46,496.54 47,426.48 47,426.48 47,426.48 M-060
wastage
Add 1 per cent on cost of material for nuts, bolts and
474.26 474.26 474.26
drilling and welding consumables
Add 15 per cent on cost of material for fabrication of
7,185.11 7,185.11 7,185.11
trusses as per approved design
c) Machinery
Crane 3 tonne capacity hour 3.000 3.000 3.000 1,083.60 3,250.80 3,250.80 3,250.80 P&M-102
Truck hour 0.500 0.500 0.500 1,731.45 865.73 865.73 865.73 P&M-017
d) Overhead charges @ 8% on @ 10% on @ 12% on
5,029.80 6,287.25 7,544.70
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
6,790.23 6,915.98 7,041.72
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Rate per tonne = (a+b+c+d+e) 74,692.57 76,075.77 77,458.96


Say 74,693.00 76,076.00 77,459.00
8.07 B Aluminium Alloy Plate for Over Head Sign
Unit = sqm
Taking output = 1 sqm
a) Labour
Mate day 0.020 0.020 0.020 617.00 12.34 12.34 12.34 L-12
Blacksmith day 0.100 0.100 0.100 738.00 73.80 73.80 73.80 L-02
Mazdoor day 0.150 0.150 0.150 511.52 76.73 76.73 76.73 L-13
b) Material
Aluminium alloy plate,2 mm thick, fixed with high intensity
sqm 1.000 1.000 1.000 8,379.04 8,379.04 8,379.04 8,379.04 M-059
grade sheeting vide clause 801.3
Miscellaneous
Add 1 per cent of cost of labour for lifting arrangement,
1.63 1.63 1.63
like ladders, pulleys, ropes etc
c) Overhead charges @ 8% on @ 10% on @ 12% on
683.48 854.35 1,025.22
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
922.70 939.79 956.88
(a+b+c) (a+b+c) (a+b+c)
Rate per sqm = (a+b+c+d) 10,149.72 10,337.68 10,525.64
Say 10,150.00 10,338.00 10,526.00
1. The cost of excavation and foundation concrete for
fixing of vertical support system to be worked out
Note
separately as per the approved drawing/design and to be
included in the estimate.
2. Lettering and arrow marks on sign board to be
provided separately as per actual requirement. Rates for
these items have been included separately in this
chapter.
8.08 803 Painting Two Coats on New Concrete Surfaces
Painting two coats after filling the surface with synthetic
enamel paint in all shades on new plastered concrete
surfaces
Unit = sqm
Taking output = 40 sqm 40 sqm
a) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Painter day 2.000 2.000 2.000 679.00 1,358.00 1,358.00 1,358.00 L-18
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Material
Paint conforming to requirement of clause 803.3. Litre 6.000 6.000 6.000 172.36 1,034.16 1,034.16 1,034.16 M-131
Add for scaffolding @ 1 per cent of labour cost where
19.44 19.44 19.44
required
Add @ 5 per cent cost of labour and materials to
prepare the surface by filling minuts roughness on the
148.89 148.89 148.89
surface and priming the surface before laying 2 coats of
painting.
Per Sqm Basic Cost of Labour & Material (a+b) 78.65 78.65 78.65

c) Overhead charges @ 8% on @ 10% on @ 12% on


251.68 314.60 377.52
(a+b) (a+b) (a+b)
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
d) Contractor's profit @ 10% on @ 10% on @ 10% on
339.77 346.06 352.36
(a+b+c) (a+b+c) (a+b+c)
Cost for 40 sqm = a+b+c+d 3,737.50 3,806.71 3,875.92
Rate per sqm = (a+b+c+d)/40 93.44 95.17 96.90
Say 93.00 95.00 97.00
8.09 803 Painting on Steel Surfaces
Providing and applying two coats of ready mix paint of
approved brand on steel surface after through cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.028 0.028 0.028 617.00 17.28 17.28 17.28 L-12
Painter day 0.450 0.450 0.450 679.00 305.55 305.55 305.55 L-18
Mazdoor day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
b) Material
Paint ready mixed approved brand. Litre 1.250 1.250 1.250 235.22 294.03 294.03 294.03 M-130
Add @ 1 per cent on cost of material for scaffolding 2.94 2.94 2.94

Add @ 5 per cent cost of labour and materials to


prepare the surface by filling minuts roughness on the
37.24 37.24 37.24
surface and priming the surface before laying 2 coats of
painting.
Per Sqm Basic Cost of Labour & Material (a+b) 78.49 78.49 78.49
c) Overhead charges @ 8% on @ 10% on @ 12% on
62.79 78.49 94.19
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
84.77 86.34 87.91
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm = a+b+c+d 932.47 949.74 967.01
Rate per sqm= (a+b+c+d)/10 93.25 94.97 96.70
Say 93.00 95.00 97.00
8.10 803 Painting on Wood Surfaces

Providing and applying two coats of ready mix paint of


approved brand on wood surface after thorough cleaning
of surface to give an even shade

Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.028 0.028 0.028 617.00 17.28 17.28 17.28 L-12
Painter day 0.500 0.500 0.500 679.00 339.50 339.50 339.50 L-18
Mazdoor day 0.200 0.200 0.200 511.52 102.30 102.30 102.30 L-13
b) Material
Paint ready mixed of approved brand. Litre 1.500 1.500 1.500 235.22 352.83 352.83 352.83 M-130
Add @ 1 per cent on cost of material for scaffolding 3.53 3.53 3.53

Add @ 5 per cent cost of labour and materials to


prepare the surface by filling minuts roughness on the
40.60 40.60 40.60
surface and priming the surface before laying 2 coats of
painting.
Per Sqm Basic Cost of Labour & Material (a+b) 85.60 85.60 85.60
c) Overhead charges @ 8% on @ 10% on @ 12% on
68.48 85.60 102.72
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
92.45 94.16 95.88
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm = a+b+c+d 1,016.97 1,035.80 1,054.64
Rate per sqm = (a+b+c+d)/10 101.70 103.58 105.46
Say 102.00 104.00 105.00
Painting Lines, Dashes, Arrows etc on Roads in Two
8.11 803
Coats on New Work

Painting lines, dashes, arrows etc on roads in two coats


on new work with ready mixed road marking paint
conforming to IS:164 on bituminous surface, including
cleaning the surface of all dirt, dust and other foreign
matter, demarcation at site and traffic control

(i) Over 10 cm in width


Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.084 0.084 0.084 617.00 51.83 51.83 51.83 L-12
Painter day 0.550 0.550 0.550 679.00 373.45 373.45 373.45 L-18
Mazdoor day 1.550 1.550 1.550 511.52 792.86 792.86 792.86 L-13
b) Material
Road marking Paint as per IS :164 Litre 1.480 1.480 1.480 172.36 255.09 255.09 255.09 M-131
Per Sqm Basic Cost of Labour & Material (a+b) 147.32 147.32 147.32
c) Overhead charges @ 8% on @ 10% on @ 12% on
117.86 147.32 176.79
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
159.11 162.05 165.00
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm = a+b+c+d 1,750.19 1,782.60 1,815.02
Rate per sqm= (a+b+c+d)/10 175.02 178.26 181.50
Say 175.00 178.00 182.00
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
8.11 (ii) Up to 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.068 0.068 0.068 617.00 41.96 41.96 41.96 L-12
Painter day 0.350 0.350 0.350 679.00 237.65 237.65 237.65 L-18
Mazdoor day 1.350 1.350 1.350 511.52 690.55 690.55 690.55 L-13
b) Material
Road marking paint Litre 1.480 1.480 1.480 172.36 255.09 255.09 255.09 M-131
Per Sqm Basic Cost of Labour & Material (a+b) 123.00 123.00 123.00
c) Overhead charges @ 8% on @ 10% on @ 12% on
98.02 122.53 147.03
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
132.33 134.78 137.23
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm = a+b+c+d 1,455.60 1,482.55 1,509.51
Rate per sqm = (a+b+c+d)/10 145.56 148.26 150.95
Say 146.00 148.00 151.00
Painting Lines, Dashes, Arrows etc on Roads in Two
8.12 803
Coats on Old Work

Painting lines, dashes, arrows etc on roads in two coats


on old work with ready mixed road marking paint
conforming to IS: 164 on bituminous surface, including
cleaning the surface of all dirt, dust and other foreign
matter, demarcation at site and traffic control

(i) Over 10 cm in width


Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.062 0.062 0.062 617.00 38.25 38.25 38.25 L-12
Painter Ist class day 0.300 0.300 0.300 679.00 203.70 203.70 203.70 L-18
Mazdoor day 1.250 1.250 1.250 511.52 639.40 639.40 639.40 L-13
b) Material
Road marking paint Litre 0.900 0.900 0.900 172.36 155.12 155.12 155.12 M-131
Per Sqm Basic Cost of Labour & Material (a+b) 104.00 104.00 104.00
c) Overhead charges @ 8% on @ 10% on @ 12% on
82.92 103.65 124.38
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
111.94 114.01 116.09
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm = a+b+c+d 1,231.34 1,254.14 1,276.94
Rate per sqm = (a+b+c+d)/10 123.13 125.41 127.69
Say 123.00 125.00 128.00
8.12 (ii) Up to 10 cm in width
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.068 0.068 0.068 617.00 41.96 41.96 41.96 L-12
Painter Ist class day 0.350 0.350 0.350 679.00 237.65 237.65 237.65 L-18
Mazdoor day 1.350 1.350 1.350 511.52 690.55 690.55 690.55 L-13
b) Material
Road marking Paint Litre 0.900 0.900 0.900 172.36 155.12 155.12 155.12 M-131
Per Sqm Basic Cost of Labour & Material (a+b) 113.00 113.00 113.00
c) Overhead charges @ 8% on @ 10% on @ 12% on
90.02 112.53 135.03
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
121.53 123.78 126.03
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm= a+b+c+d 1,336.84 1,361.59 1,386.35
Rate per sqm = (a+b+c+d)/10 133.68 136.16 138.63
Say 134.00 136.00 139.00

Road Marking with Hot Applied Thermoplastic Compound


8.13 803
with Reflectorising Glass Beads on Bituminous Surface

Providing and laying of hot applied thermoplastic


compound 2.5 mm thick including reflectorising glass
beads @ 250 gms per sqm area, thickness of 2.5 mm is
exclusive of surface applied glass beads as per
IRC:35 .The finished surface to be level, uniform and free
from streaks and holes.
Unit = sqm
Taking output = 600 sqm
a) Labour
Mate day 0.030 0.030 0.030 617.00 18.51 18.51 18.51 L-12
Mazdoor day 0.750 0.750 0.750 511.52 383.64 383.64 383.64 L-13
b) Machinery
Road marking machine @ 60 sqm per hour hour 10.000 10.000 10.000 1,951.95 19,519.50 19,519.50 19,519.50 P&M-073
Tractor-trolley hour 0.500 0.500 0.500 1,876.50 938.25 938.25 938.25 P&M-026
c) Material
Hot applied thermoplastic compound Litre 1500.000 1500.000 1500.000 166.80 250,200.00 250,200.00 250,200.00 M-117
Reflectorising glass beads kg 150.000 150.000 150.000 68.29 10,243.80 10,243.80 10,243.80 M-153
d) Overhead charges @ 8% on @ 10% on @ 12% on
22,504.30 28,130.37 33,756.44
(a+b+c) (a+b+c) (a+b+c)
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
30,380.80 30,943.41 31,506.01
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 600 sqm = a+b+c+d+e 334,188.80 340,377.48 346,566.16


Rate per sqm = a+b+c+d+e)/600 556.98 567.30 577.61
Say 557.00 567.00 578.00

1. A sealing primer may be applied in advance on cement


concrete pavement to ensure proper bonding. Any
Note
laitance and/or curing compound to be removed where
paint is required to be applied on concrete surface.

2.Cost of painter is already included in hire charges of


road marking machine.
8.14 804 Kilometre Stone
Reinforced cement concrete M15grade kilometre stone of
standard design as per IRC:8, fixing in position including
painting and printing etc
(i) 5th kilometre stone (precast)
Unit = Nos.
Taking output = 6 Nos.
a) M-15 grade of concrete cum 2.350 7,682.00 18,052.70
Item No. -
cum 2.350 7,870.00 18,494.50
9.06 Case II
cum 2.350 8,176.00 19,213.60
b) Steel reinforcement @ 5 kg per sqm kg 22.080 60.87 1,343.92
Item No. -
kg 22.080 62.08 1,370.77
9.07 / 1000
kg 22.080 63.39 1,399.67
c) Excavation in soil for foundation cum 1.680 223.00 374.64
Item No. -
cum 1.680 227.00 381.36
9.01 A(i)
cum 1.680 231.00 388.08
d) Painting two coats on concrete surface sqm 9.850 93.00 916.05
Item No. -
sqm 9.850 95.00 935.75
8.08
sqm 9.850 97.00 955.45
e) Lettering on km post (average 30 letters of 10 cm per cm
1800.000 1.60 2,880.00
height each) per letter
per cm Item No. -
1800.000 1.60 2,880.00
per letter 8.03
per cm
1800.000 1.60 2,880.00
per letter
Transportation and fixing
f) Labour
Mate day 0.264 0.264 0.264 617.00 162.89 162.89 162.89 L-12
Mason day 0.600 0.600 0.600 738.00 442.80 442.80 442.80 L-11
Mazdoor including loading/unloading day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
g) Machinery
Tractor-trolley hour 6.000 6.000 6.000 1,876.50 11,259.00 11,259.00 11,259.00 P&M-026
h) Overhead charges @ 8% on @ 10% on @ 12% on
1,194.70 1,493.38 1,792.06
(f+g) (f+g) (f+g)
i) Contractor's profit @ 10% on @ 10% on @ 10% on
1,612.85 1,642.72 1,672.59
(f+g+h) (f+g+h) (f+g+h)

Cost for 6 Nos. 5th km stone = a+b+c+ d+e +f+g+h +i 41,308.68 42,132.29 43,235.25

Rate for each 5th km stone = (a+b+c+ d+e +f+g+h


6,884.78 7,022.05 7,205.88
+i ) /6
Say 6,885.00 7,022.00 7,206.00
8.14 (ii) Ordinary kilometer stone (precast)
Unit = Nos.
Taking output = 14 Nos.
a) M-15 grade of concrete cum 3.770 7,682.00 28,961.14
Item No. -
cum 3.770 7,870.00 29,669.90
9.06 Case II
cum 3.770 8,176.00 30,823.52
b) Steel reinforcement @ 5 kg per sqm kg 26.320 60.87 1,601.99
Item No. -
kg 26.320 62.08 1,634.00
9.07 / 1000
kg 26.320 63.39 1,668.45
c) Excavation in soil for foundation cum 2.770 223.00 617.71
Item No. -
cum 2.770 227.00 628.79
9.01 A(i)
cum 2.770 231.00 639.87
d) Painting two coats on concrete surface sqm 11.410 93.00 1,061.13
Item No. -
sqm 11.410 95.00 1,083.95
8.08
sqm 11.410 97.00 1,106.77
e) Lettering on km post (average 30 letters of 10 cm per cm
1680.000 1.60 2,688.00
height each) per letter
per cm Item No. -
1680.000 1.60 2,688.00
per letter 8.03
per cm
1680.000 1.60 2,688.00
per letter
Transportation and fixing
f) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
g) Machinery
Tractor-trolley hour 6.000 6.000 6.000 1,876.50 11,259.00 11,259.00 11,259.00 P&M-026
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
h) Overhead charges @ 8% on @ 10% on @ 12% on
1,262.01 1,577.51 1,893.01
(f+g) (f+g) (f+g)
i) Contractor's profit @ 10% on @ 10% on @ 10% on
1,703.71 1,735.26 1,766.81
(f+g+h) (f+g+h) (f+g+h)
Cost for 14 Nos. ordinary km stone = (a+b+ c
53,670.77 54,792.49 56,361.51
+d+e+f+g+h+i)
Rate for each ordinary km stone = (a+b+ c
3,833.63 3,913.75 4,025.82
+d+e+f+g+h+j) /14
Say 3,834.00 3,914.00 4,026.00
8.14 (iii) Hectometer stone (precast)
Unit = Nos.
Taking output = 33 Nos.
a) M-15 grade of concrete cum 1.580 7,682.00 12,137.56
Item No. -
cum 1.580 7,870.00 12,434.60
9.06 Case II
cum 1.580 8,176.00 12,918.08
b) Steel reinforcement @ 5 kg per sqm kg 66.000 60.87 4,017.16
Item No. -
kg 66.000 62.08 4,097.41
9.07 / 1000
kg 66.000 63.39 4,183.81
c) Excavation in soil for foundation cum 1.390 223.00 309.97
Item No. -
cum 1.390 227.00 315.53
9.01 A(i)
cum 1.390 231.00 321.09
d) Painting two coats on concrete surface sqm 6.270 93.00 583.11
Item No. -
sqm 6.270 95.00 595.65
8.08
sqm 6.270 97.00 608.19
e) Lettering on km post (average 30 letters of 10 cm per cm
330.000 1.60 528.00
height each) per letter
per cm Item No. -
330.000 1.60 528.00
per letter 8.03
per cm
330.000 1.60 528.00
per letter
Transportation and fixing
f) Labour
Mate day 0.340 0.340 0.340 617.00 209.78 209.78 209.78 L-12
Mason day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-11
Mazdoor day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
g) Machinery
Tractor-trolley hour 6.000 6.000 6.000 1,876.50 11,259.00 11,259.00 11,259.00 P&M-026
h) Overhead charges @ 8% on @ 10% on @ 12% on
1,292.51 1,615.64 1,938.77
(f+g) (f+g) (f+g)
i) Contractor's profit @ 10% on @ 10% on @ 10% on
1,744.89 1,777.21 1,809.52
(f+g+h) (f+g+h) (f+g+h)
Cost for 33 Nos. Hectometer stone = (a+b +c +d+e+f+
36,769.62 37,520.46 38,463.88
g+h+i)
Rate for each Hectometer stone = (a+b +c +d+e+f+
1,114.23 1,136.98 1,165.57
g+h+i) / 33
Say 1,114.00 1,137.00 1,166.00
The rate for excavation, cement concrete, steel
Note reinforcement, painting and lettering may be taken from
respective chapters.
8.15 805 Road Delineators
Supplying and installation of delineators (road way
indicators, hazard markers, object markers), 80-100 cm
high above ground level, painted black and white in 15
cm wide strips, fitted with 80 x 100 mm rectangular or 75
mm dia circular reflectorised panels at the top, buried or
pressed into the ground and conforming toIRC-79 and
the drawings.
Unit = Each
Taking output= 30 Nos.
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor for fixing day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Material

Cost of approved type of delineators from ISI certified


each 30.000 30.000 30.000 382.25 11,467.50 11,467.50 11,467.50 M-092
firm as per the standard drawing given in IRC - 79

Add 10 per cent cost of material for installation 1,146.75 1,146.75 1,146.75
c) Overhead charges @ 8% on @ 10% on @ 12% on
1,052.04 1,315.05 1,578.05
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,420.25 1,446.55 1,472.85
(a+b+c) (a+b+c) (a+b+c)
Cost for 30 Nos. delineators = (a+b+ c+d) 15,622.73 15,912.04 16,201.35
Rate per delineators = (a+b+c+d) /30 520.76 530.40 540.05
Say 521.00 530.00 540.00
In case of soft ground, a proper foundation may be
provided as per approved design. In case foundation is
Note required to be provided, the items of excavation and
foundation concrete are required to be measured and
paid separately.
8.16 806 Boundary pillar
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project

Reinforced cement concrete M15 grade boundary pillars


of standard design as per IRC:25-1967, fixed in position
including finishing and lettering but excluding painting

Unit = Each
Taking output = 57 Nos.
a) M-15 grade of concrete cum 1.250 7,682.00 9,602.50
Item No. -
cum 1.250 7,870.00 9,837.50
9.06 Case II
cum 1.250 8,176.00 10,220.00
b) Steel reinforcement @ 5 kg per sqm kg 79.800 60.87 4,857.11
Item No. -
kg 79.800 62.08 4,954.14
9.07 / 1000
kg 79.800 63.39 5,058.60
c) Excavation in soil for foundation cum 10.720 223.00 2,390.56
Item No. -
cum 10.720 227.00 2,433.44
9.01 A(i)
cum 10.720 231.00 2,476.32
e) Lettering on km post (average 30 letters of 10 cm per cm
2280.000 1.60 3,648.00
height each) per letter
per cm Item No. -
2280.000 1.60 3,648.00
per letter 8.03
per cm
2280.000 1.60 3,648.00
per letter
Transportation and fixing
e) Labour
Mate day 0.570 0.570 0.570 617.00 351.69 351.69 351.69 L-12
Mazdoor day 14.250 14.250 14.250 511.52 7,289.16 7,289.16 7,289.16 L-13
f) Machinery
Tractor-trolley hour 6.000 6.000 6.000 1,876.50 11,259.00 11,259.00 11,259.00 P&M-026
g) Material
Stone spall cum 11.970 11.970 11.970 1,679.81 20,107.36 20,107.36 20,107.36 M-008
h) Overhead charges @ 8% on @ 10% on @ 12% on
3,120.58 3,900.72 4,680.87
(e+f+g) (e+f+g) (e+f+g)
i) Contractor's profit
@ 10% on @ 10% on @ 10% on
4,212.78 4,290.79 4,368.81
(e+f+g+h) (e+f+g+h) (e+f+g+h)

Cost for 57 Nos. boundary pillar = (a+b +c+d +e+ f+g+h+i


66,838.74 68,071.81 69,459.81
)

Rate for each boundary pillar = (a+b+c+d+e+ f+g+h+i)/57 1,172.61 1,194.24 1,218.59
Say 1,173.00 1,194.00 1,219.00
In case of soft ground, a proper foundation may be
provided as per approved design. In case foundation is
Note required to be provided, the items of excavation and
foundation concrete are required to be measured and
paid separately.
8.17 808 G.I Barbed Wire Fencing 1.2 Metre High

Providing and fixing 1.2 metres high GI barbed wire


fencing with 1.8 m angle iron posts 40 mm x 40 mm x 6
mm placed every 3 metres center to center founded in
M15 grade cement concrete, 0.6 metre below ground
level, every 15th post, last but one end post and corner
post shall be strutted on both sides and end post on one
side only and provided with 9 horizontal lines and 2
diagonals interwoven with horizontal wires, fixed with GI
staples, turn buckles etc complete as per clause 817

Unit = per running metre


Taking output = 30 metres
a) Labour
Mate day 0.090 0.090 0.090 617.00 55.53 55.53 55.53 L-12
Blacksmith day 0.250 0.250 0.250 738.00 184.50 184.50 184.50 L-02
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Material
Barbed wire 335 metres length @ 9.38 kg per 100 metres kg 31.420 31.420 31.420 66.72 2,096.34 2,096.34 2,096.34 M-063

MS angle iron 40 mm x 40mm x 6 mm, 23 metres in


kg 80.500 80.500 80.500 63.81 5,136.43 5,136.43 5,136.43 M-181/1000
length @ 3.5 kg per metre
Add for GI staple binding wire, drilling holes etc. @ 2 per
144.66 144.66 144.66
cent of the cost of material
c) Painting
sqm 2.110 93.00 196.23
Applying two coats of painting on exposed surface of Item No. -
sqm 2.110 95.00 200.45
angle iron posts ( Rate as per item no. 8.09) 8.09
sqm 2.110 97.00 204.67
d) Overhead charges @ 8% on @ 10% on @ 12% on
691.24 864.05 1,036.86
(a+b) (a+b) (a+b)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
933.17 950.45 967.74
(a+b+d) (a+b+d) (a+b+d)

Cost for 30 metres fencing = a+b+c+d+e 10,461.14 10,655.45 10,849.76


Rate per metre = (a+b+c+d+e)/30 348.70 355.18 361.66
Say 349.00 355.00 362.00
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project

Cost of excavation for foundation and foundation


concrete to be added separately in the cost estimate as
Note
per approved design. The rate for these items may be
taken from respective chapters.

8.18 808 G.I Barbed Wire Fencing 1.8 Metre High

Providing and fixing 1.8 metres high GI barbed wire


fencing with 2.4 m angle iron posts 50 mm x 50 mm x 6
mm placed every 3 metres center to center founded in
M15 grade cement concrete, 0.6 metre below ground
level, every 15th post, last but one end post and corner
post shall be strutted on both sides and end post on one
side only and provided with 12 horizontal lines and 2
diagonals interwoven with horizontal wires, fixed with GI
staples, turn buckles etc complete as per clause 808

Unit = per running metre


Taking output = 30 metres
a) Labour
Mate day 0.116 0.116 0.116 617.00 71.57 71.57 71.57 L-12
Blacksmith day 0.400 0.400 0.400 738.00 295.20 295.20 295.20 L-02
Mazdoor day 2.500 2.500 2.500 511.52 1,278.80 1,278.80 1,278.80 L-13
b) Material
Barbed wire 428 metres length @ 9.38 kg per 100 metres kg 40.150 40.150 40.150 66.72 2,678.81 2,678.81 2,678.81 M-063

MS angle iron 50 mm x 50 mm x 6 mm,33.8 metres in


kg 152.000 152.000 152.000 63.81 9,698.59 9,698.59 9,698.59 M-181 /1000
length @ 4.5 kg per metre
Add for GI staple, binding wire, drilling holes etc. @ 2
247.55 247.55 247.55
per cent of the cost of material
c) Painting
Applying two coats of painting on exposed surface of
sqm 3.960 93.00 368.28
angle iron posts ( Rate as per item no. 8.09) Item No. -
sqm 3.960 95.00 376.20 8.08
sqm 3.960 97.00 384.12
d) Overhead charges @ 8% on @ 10% on @ 12% on
1,141.64 1,427.05 1,712.46
(a+b) (a+b) (a+b)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
1,541.22 1,569.76 1,598.30
(a+b+d) (a+b+d) (a+b+d)

Cost for 30 metres fencing = a+b+c+d+e 17,321.66 17,643.53 17,965.40


Rate per metre fencing = (a+b+c +d+e)/30 577.39 588.12 598.85
Say 577.00 588.00 599.00

Cost of excavation for foundation and foundation


concrete to be added separately in the cost estimate as
Note
per approved design. The rate for these items may be
taken from respective chapters.

8.19 Suggest Fencing With Welded Steel Wire Fabric 75 mm x 50 mm


ive

Providing 1.20 metre high fencing with angle iron posts


50 mm x 50 mm x 6 mm at 3 metre center to center with
0.40 metre embedded in M15 grade cement concrete,
corner, end and every 10th post to be strutted, provided
with welded steel wire fabric of 75 mm x 50 mm mesh or
75 mm x 25 mm mesh and fixed to iron posts by flat iron
50 x 5 mm and bolts etc. complete in all respects.

Unit = Running metre


Taking output = 30 m
a) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Welder day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-02
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Material
i) Angle iron for posts 50 x 50 x 6 mm kg 106.000 106.000 106.000 63.81 6,763.49 6,763.49 6,763.49 M-181/1000
ii) Runner flat 50 x 5 mm kg 26.000 26.000 26.000 63.81 1,658.97 1,658.97 1,658.97 M-181/1000
iii) Welded steel wire fabric 75x50 mm mesh @ 4
kg 151.000 151.000 151.000 66.72 10,074.72 10,074.72 10,074.72 M-193
kg/sqm,4 x 30 x 1.2 + 5 per cent wastage
OR
Welded steel wire fabric 75 x 25 mm mesh @ 7.75
kg 293.000 293.000 293.000 66.72 19,548.96 19,548.96 19,548.96 M-103
kg/sqm, 7.75 x 30 x 1.2 + 5 per cent wastage
Add 2.5 per cent of cost of material for drilling holes in
angles, flats, splitting angle at bottom, nuts and bolts and
welded consumables
c) Machinery
Tractor-trolley hour 0.100 0.100 0.100 1,876.50 187.65 187.65 187.65 P&M-026
d) Painting
Applying two coats of painting on exposed surface of
sqm 8.000 93.00 744.00
angle iron posts ( Rate as per item no. 8.09) Item No. -
sqm 8.000 95.00 760.00 8.08
sqm 8.000 97.00 776.00
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
(i)75x50 mm mesh
e) Overhead charges @ 8% on @ 10% on @ 12% on
1,641.59 2,051.99 2,462.39
(a+b+c) (a+b+c) (a+b+c)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
2,216.15 2,257.19 2,298.23
(a+b+c+e) (a+b+c+e) (a+b+c+e)

Cost for 30 metre = a+b+c+d+e+f 25,121.66 25,589.10 26,056.53


Rate per metre = (a+b+c+d+e+f)/30 837.39 852.97 868.55
Say 837.00 853.00 869.00
(i)75x25 mm mesh
e) Overhead charges @ 8% on @ 10% on @ 12% on
2,399.53 2,999.42 3,599.30
(a+b+c) (a+b+c) (a+b+c)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
3,239.37 3,299.36 3,359.35
(a+b+c+e) (a+b+c+e) (a+b+c+e)

Cost for 30 metre = a+b+c+d+e+f 36,377.05 37,052.93 37,728.80


Rate per metre = (a+b+c+d+e+f)/30 1,212.57 1,235.10 1,257.63
Say 1,213.00 1,235.00 1,258.00

i) Adopt any one type of welded steel wire fabric 75 x 50


Note
mm or 75 x 25 mm as per approved design.

ii) The item of excavation and cement concrete in


foundation shall be measured and paid separately
Tubular Steel Railing on Medium Weight Steel Channel
8.20 808
( ISMC series) 100 mm x 50 mm
Providing, fixing and erecting 50 mm dia steel pipe railing
in 3 rows duly painted on medium weight steel channels
(ISMC series) 100 mm x 50 mm, 1.2 metres high above
ground, 2 m centre to centre, complete as per approved
drawings
Unit = Running metre
Taking output = 10metres
cum 1.296 223.00 289.01
Item No. -
i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x 0.6 cum 1.296 227.00 294.19
9.01 A(i)
cum 1.296 231.00 299.38
cum 0.648 7,682.00 4,977.94
ii) Foundation concrete M-15 grade PCC 6 x 0.6 x 0.6 x Item No. -
cum 0.648 7,870.00 5,099.76
0.3 9.06 Case II
cum 0.648 8,176.00 5,298.05
iii) Painting of pipe sqm 4.710 93.00 438.03
Item No. -
sqm 4.710 95.00 447.45
8.09
sqm 4.710 97.00 456.87
sqm 2.160 93.00 200.88
iv) Painting of channel section 6 nos,1.8 metres each 0.2 Item No. -
sqm 2.160 95.00 205.20
x 1.8 x 6 = 2.16 8.09
sqm 2.160 97.00 209.52
a) Labour (For fixing at site)
Mate day 0.010 0.010 0.010 617.00 6.17 6.17 6.17 L-12
Mazdoor day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
Plumber day 0.010 0.010 0.010 738.00 7.38 7.38 7.38 L-02
b) Material
Steel pipe 50 mm external dia as per IS:1239 metre 30.000 30.000 30.000 232.28 6,968.43 6,968.43 6,968.43 M-176

Medium weight steel channel (ISMC series) 100 mm x 50


kg 99.360 99.360 99.360 63.81 6,339.82 6,339.82 6,339.82 M-181/1000
mm,10.8 metres length @ 9.2 kg per metre

Add for drilling holes @ 2 per cent of cost of channels 126.80 126.80 126.80
c) Machinery
Tractor-trolley hour 0.040 0.040 0.040 1,876.50 75.06 75.06 75.06 P&M-026
d) Overhead charges @ 8% on @ 10% on @ 12% on
1,092.12 1,092.12 1,092.12
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
1,474.37 1,474.37 1,474.37
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e 22,123.88 22,264.63 22,481.84


Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10 2,212.39 2,226.46 2,248.18
Say 2,212.00 2,226.00 2,248.00
Tubular Steel Railing on Precast RCC Posts, 1.2 m High
8.21 808
Above Ground Level

Providing, fencing and erecting 50 mm dia painted steel


pipe railing in 3 rows on precast M20 grade RCC vertical
posts1.8 metres high (1.2 m above GL) with 3 holes 50
mm dia for pipe, fixed 2 metres centre to, complete as
per approved drawing

Unit = Running metre


Taking output = 10metres
cum 1.296 223.00 289.01
Item No. -
i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x 0.6 cum 1.296 227.00 294.19
9.01 A(i)
cum 1.296 231.00 299.38
cum 0.648 7,682.00 4,977.94
ii) Foundation concrete M - 15 grade PCC 6 x 0.6 x 0.6 x Item No. -
cum 0.648 7,870.00 5,099.76
0.3 9.06 A Case II
cum 0.648 8,176.00 5,298.05
cum 4.710 8,195.00 38,598.45 Item No. -
iii) RCC M - 20 for pre cast posts 6 nos of 1.8 metres
cum 4.710 8,393.00 39,531.03 9.06 C, Case
each
II
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project InputNo.
Item ref.-
Specification iii) RCC M - 20 for pre cast posts 6 nos of 1.8 metres Project Project Project
9.06 C, Case
each
cum 4.710 8,708.00 41,014.68 II
sqm 2.160 93.00 200.88
Item No. -
iv) Painting of pipe sqm 2.160 95.00 205.20
8.09
sqm 2.160 97.00 209.52
a) Labour
Mate day 0.010 0.010 0.010 617.00 6.17 6.17 6.17 L-12
Mazdoor day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
Plumber day 0.010 0.010 0.010 738.00 7.38 7.38 7.38 L-02
b) Material
Steel pipe 50 mm dia as per IS:1239 metre 30.000 30.000 30.000 232.28 6,968.43 6,968.43 6,968.43 M-176
c) Machinery
Tractor-trolley hour 0.040 0.040 0.040 1,876.50 75.06 75.06 75.06 P&M-026
d) Overhead charges @ 8% on @ 10% on @ 12% on
574.79 718.49 862.19
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
775.97 790.34 804.71
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e 52,601.96 53,823.94 55,673.45


Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10 5,260.20 5,382.39 5,567.34
Say 5,260.00 5,382.00 5,567.00
8.22 811 Reinforced Cement Concrete Crash Barrier

Provision of an Reinforced cement concrete crash barrier


at the edges of the road, approaches to bridge structures
and medians, constructed with reinforcement conforming
ti conforming Mort&h specification and as per details
given IRC-5(Fig-5, B) including dowel bars 25 mm dia,
450 mm long at expansion joints filled with pre-moulded
asphalt filler board etc.., as per approved drawing and at
location directed by the engineer, all as specified {area-
0.243 sqm/meter, single face

Unit = Linear metre


Taking output = 20 m
A (i) a) M 25 grade concrete
cum 4.860 10,172.00 49,435.92 Item No. -
M 25 grade concrete (Area-0.243 Sqm. /Meter) cum 4.860 10,172.00 49,435.92 12.11 A (ii)
cum 4.860 10,172.00 49,435.92 Case II
HYSD steel reinforcement including dowel bars tonne 0.194 60,866.00 11,808.00
Item No. -
tonne 0.194 62,082.00 12,043.91
9.07
tonne 0.194 63,391.00 12,297.85
b) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
c) Material
Pre-moulded asphalt filler board sqm 0.250 0.250 0.250 376.00 94.00 94.00 94.00 M-143
d) Overhead charges @ 8% on @ 10% on @ 12% on
50.42 63.02 75.62
(b+c) (b+c) (b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
68.06 69.32 70.58
(b+c+d) (b+c+d) (b+c+d)

Cost for 20 metre = a+b+c+d+e 61,992.60 62,242.37 62,510.18


Rate per metre = (a+b+c+d+e)/20 3,099.63 3,112.12 3,125.51
Say 3,100.00 3,112.00 3,126.00

A (ii) a) M 30 grade concrete


cum 4.860 10,310.00 50,106.60 Item No. -
M 30 grade concrete cum 4.860 10,310.00 50,106.60 12.11 A (iii)
cum 4.860 10,310.00 50,106.60 Case II
HYSD steel reinforcement including dowel bars tonne 0.194 60,866.00 11,808.00
Item No. -
tonne 0.194 62,082.00 12,043.91
9.07
tonne 0.194 63,391.00 12,297.85
b) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
c) Material
Pre-moulded asphalt filler board sqm 0.250 0.250 0.250 376.00 94.00 94.00 94.00 M-143
d) Overhead charges @ 8% on @ 10% on @ 12% on
50.42 63.02 75.62
(b+c) (b+c) (b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
68.06 69.32 70.58
(b+c+d) (b+c+d) (b+c+d)

Cost for 20 metre = a+b+c+d+e 62,663.28 62,913.05 63,180.86


Rate per metre = (a+b+c+d+e)/20 3,133.16 3,145.65 3,159.04
Say 3,133.00 3,146.00 3,159.00
i) Excavation and backfilling are incidental to work and
Note
not to be measured separately.
ii) If PCC required below crash barrier then it should be
measured & Paid separately.
iii) Rate for RCC M 25 may be taken from chapter-12 on
foundation.
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project

Provision of an Reinforced cement concrete new jersy


crash barrier at the media, constructed with
reinforcement conforming ti conforming Mort&h
specification and as per details given IRC-119 (Fig-26,)
B including dowel bars 25 mm dia, 450 mm long at
expansion joints filled with pre-moulded asphalt filler
board etc.., as per approved drawing and at location
directed by the engineer, all as specified {area-0.261
sqm/meter, double face
Unit = Linear metre
Taking output = 20 m
(i) a) M 25 grade concrete
M 25 grade concrete cum 5.220 10,172.00 53,097.84 Item No. -
5.220 10,172.00 53,097.84 12.11 A (ii)
5.220 10,172.00 53,097.84 Case II
HYSD steel reinforcement including dowel bars tonne 0.209 60,866.00 12,720.99
Item No. -
tonne 0.209 62,082.00 12,975.14
9.07
tonne 0.209 63,391.00 13,248.72
b) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
c) Material
Pre-moulded asphalt filler board sqm 0.250 0.250 0.250 376.00 94.00 94.00 94.00 M-143
d) Overhead charges @ 8% on @ 10% on @ 12% on
50.42 63.02 75.62
(b+c) (b+c) (b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
68.06 69.32 70.58
(b+c+d) (b+c+d) (b+c+d)

Cost for 20 metre = a+b+c+d+e 66,567.51 66,835.52 67,122.97


Rate per metre = (a+b+c+d+e)/20 3,328.38 3,341.78 3,356.15
Say 3,328.00 3,342.00 3,356.00

(ii) a) M 30 grade concrete


M 30 grade concrete cum 5.220 10,310.00 53,818.20 Item No. -
5.220 10,310.00 53,818.20 12.11 A (iii)
5.220 10,310.00 53,818.20 Case II
HYSD steel reinforcement including dowel bars tonne 0.209 60,866.00 12,720.99
Item No. -
tonne 0.209 62,082.00 12,975.14
9.07
tonne 0.209 63,391.00 13,248.72
b) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
c) Material
Pre-moulded asphalt filler board sqm 0.250 0.250 0.250 376.00 94.00 94.00 94.00 M-143
d) Overhead charges @ 8% on @ 10% on @ 12% on
50.42 63.02 75.62
(b+c) (b+c) (b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
68.06 69.32 70.58
(b+c+d) (b+c+d) (b+c+d)

Cost for 20 metre = a+b+c+d+e 67,287.87 67,555.88 67,843.33


Rate per metre = (a+b+c+d+e)/20 3,364.39 3,377.79 3,392.17
Say 3,364.00 3,378.00 3,392.00
i) Excavation and backfilling are incidental to work and
Note
not to be measured separately.
ii) If PCC required below crash barrier then it should be
measured & Paid separately.
iii) Rate for RCC M 25 may be taken from chapter-12 on
foundation.
8.23 811 Metal Beam Crash Barrier
A Type - A, "W" : Metal Beam Crash Barrier

Providing and erecting a "W" metal beam crash barrier


comprising of 3 mm thick corrugated sheet metal beam
rail, 70 cm above road/ground level, fixed on ISMC series
channel vertical post, 150 x 75 x 5 mm spaced 2 m
centre to centre, 1.8 m high, 1.1 m below ground/road
level, all steel parts and fitments to be galvanised by hot
dip process, all fittings to conform to IS:1367 and
IS:1364, metal beam rail to be fixed on the vertical post
with a spacer of channel section 150 x 75 x 5 mm, 330
mm long complete as per clause 811

Unit = Running metre


Taking output = 4.5 metre length
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Blacksmith day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-02
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Tractor-trolley hour 0.100 0.100 0.100 1,876.50 187.65 187.65 187.65 P&M-026
c) Material
Corrugated sheet,3 mm thick, "W" beam section
kg 41.210 41.210 41.210 72.28 2,978.66 2,978.66 2,978.66 M-089
railing,4.5 m in length
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
Channel post 150 x 75 x 5 mm,1.8 m long,3 Nos @ 16.4
kg 88.560 88.560 88.560 63.81 5,650.71 5,650.71 5,650.71 M-181/1000
kg per metre
Spacer 150 x 75 x 5 mm channel 0.33 m long,3 Nos @
kg 16.240 16.240 16.240 63.81 1,036.22 1,036.22 1,036.22 M-181/1000
16.4 kg per metre
Nuts and bolts kg 20.000 20.000 20.000 64.83 1,296.54 1,296.54 1,296.54 M-129
Add 25 per cent of the cost of material for fabrication,
2,740.53 2,740.53 2,740.53
nuts, bolts and washers etc.)
d) Overhead charges @ 8% on @ 10% on @ 12% on
1,184.63 1,480.78 1,776.94
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
1,599.25 1,628.86 1,658.48
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 4.5 metre = a+b+c+d+e 17,591.72 17,917.49 18,243.27


Rate per metre = (a+b+c+d+e)/4.5 3,909.27 3,981.67 4,054.06
Say 3,909.00 3,982.00 4,054.00
8.23 B Type - B, "THRIE" : Metal Beam Crash Barrier

Providing and erecting a "Thrie" metal beam crash barrier


comprising of 3 mm thick corrugated sheet metal beam
rail, 85 cm above road/ground level, fixed on ISMC series
channel vertical post, 150 x 75 x 5 mm spaced 2 m
centre to centre, 2 m high with 1.15 m below ground
level, all steel parts and fitments to be galvanised by hot
dip process, all fittings to conform to IS:1367 and
IS:1364, metal beam rail to be fixed on the vertical post
with a space of channel section 150 x 75 x 5 mm, 546
mm long complete as per clause 811

Unit = Running metre


Taking output = 4.5 metre length
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Blacksmith day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-02
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Tractor-trolley hour 0.100 0.100 0.100 1,876.50 187.65 187.65 187.65 P&M-026
c) Material
Corrugated sheet,3 mm thick, "Thrie" beam section
kg 72.940 72.940 72.940 72.28 5,272.10 5,272.10 5,272.10 M-089
railing,4.5 m in length
Channel post 150 x 75 x 5 mm, 2 m long,3 Nos @ 16.4
kg 98.400 98.400 98.400 63.81 6,278.56 6,278.56 6,278.56 M-181/1000
kg per metre

Spacer 150 x 75 x 5 mm channel 0.546 m long,3 Nos kg 26.860 26.860 26.860 63.81 1,713.84 1,713.84 1,713.84 M-181/1000
Nuts and bolts kg 30.000 30.000 30.000 64.83 1,944.81 1,944.81 1,944.81 M-129
Add 15 per cent of the cost of material for fabrication,
2,281.40 2,281.40 2,281.40
nuts, bolts and washers etc.)
d) Overhead charges @ 8% on @ 10% on @ 12% on
1,487.67 1,859.59 2,231.51
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
2,008.36 2,045.55 2,082.74
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 4.5 metre = a+b+c+d+e 22,091.94 22,501.05 22,910.16


Rate per metre= (a+b+c+d+e)/4.5 4,909.32 5,000.23 5,091.15
Say 4,909.00 5,000.00 5,091.00

In the case of median crash barrier, 'W' metal beam or


thrie beam section should be provided on both sides of
Note the vertical posts fixed in the median. Extra provision for
metal beam railing and spacer is required to be made
when fixed in the median depending on approved design.

8.24 811 Road Traffic Signals electrically operated

Since it is a ready made item commercially produced and


erected by specialised firm in the electrical and electronic
Note field, rate may be taken based on market enquiry from
firms specialised in this field and ISI certified for the
approved design and drawing.

Suggest
8.25 Flexible Crash Barrier, Wire Rope Safety Barrier
ive
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project

Providing and erecting a wire rope safety barrier with


vertical posts of medium weight RS Joist (ISMB series)
100 mm x 75 mm (11.50 kg/m), 1.50 m long 0.85 m
above ground and 0.65 m below ground level, split at the
bottom for better grip, embedded in M 15 grade cement
concrete 450 x 450 x 450 mm, 1.50 m center to center
and with 4 horizontal steel wire rope 40 mm dia and
anchored at terminal posts 15 m apart. Terminal post to
be embedded in M 15 grade cement concrete foundation
2400 x 450 x 900 mm (depth), strengthened by a strut of
RS joist 100 x 75 mm, 2 m long at 450 inclination and a
tie 100 x 8 mm, 1.50 m long at the bottom, all embedded
in foundation concrete as per approved design and
drawing, rate excluding excavation and cement concrete.

Unit = Running metre


Taking output = 15 metre
a) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
Blacksmith day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-02
b) Material
i) RS Joist 100 x 75 mm - 16.5 m @ 11.5 kg per metre kg 190.000 190.000 190.000 63.81 12,123.24 12,123.24 12,123.24 M-181/1000

ii) Struts - 2 Nos. for terminal posts,2 m long each 2 x 2 x


kg 46.000 46.000 46.000 63.81 2,935.10 2,935.10 2,935.10 M-181/1000
11.50
iii) Tie 2 Nos. of 8 mm steel plate,1.5 sqm each for
kg 188.400 188.400 188.400 63.81 12,021.15 12,021.15 12,021.15 M-181/1000
terminal posts @ 62.80 kg/sqm (2 x 1.5)

iv) Steel wire rope 40 mm, including 7.50 per cent extra
kg 65.000 65.000 65.000 44.78 2,910.86 2,910.86 2,910.86 M-179
for fixing at ends 15 x 4 x 1.075 @ 1 kg per m

Add 5 per cent of cost of material for drilling, gripping,


1,499.52 1,499.52 1,499.52
fixing, fabrication and welding consumables

c) Painting
Applying 2 coats of painting on exposed surface sqm 16.500 93.00 1,534.50
Item No. -
sqm 16.500 95.00 1,567.50
8.09
sqm 16.500 97.00 1,600.50
d) Machinery
Tractor-trolley hour 0.250 0.250 0.250 1,876.50 469.13 469.13 469.13 P&M-026
e) Overhead charges
@ 8% on @ 10% on @ 12% on
2,703.53 3,379.41 4,055.29
(a+b+d) (a+b+d) (a+b+d)

f) Contractor's profit
@ 10% on @ 10% on @ 10% on
3,649.76 3,717.35 3,784.94
(a+b+d+e) (a+b+d+e) (a+b+d+e)

Cost for 15 m = a+b+c+d+e+f 41,681.87 42,458.34 43,234.81


Rate per m = (a+b+c+d+e+f)/15 2,778.79 2,830.56 2,882.32
Say 2,779.00 2,831.00 2,882.00
The items of excavations and cement concrete works will
Note be measured and included separately as per the
approved designs and drawings.
Suggest
8.26 Anti-Glare Devices in Median
ive
A Plantation

Plantation of shrubs and plants of approved species in


the median. apart from cutting off glare from vehicle
coming from opposite direction, these plants provide a
pleasant envoirenment and are eco-friendly. The rate for
this item is available in the chapter 11 on horticulture.

Anti-glare screen with 25 mm steel pipe framework fixed


B
with circular and rectangular vans

Providing and erecting an anti - glare screen with 25 mm


dia vertical pipes fabricated and framed in the form of
panels of one metre length and 1.75 metre height fixed
with circular vane 250 mm dia at top and rectangular
vane 600 x 300 mm at the middle, made out of steel
sheet of 3 mm thickness, end vertical pipes of the panel
made larger for embedding in foundation concrete,
applying 2 coats of paint on all exposed surfaces, all as
per approved design and drawings.

Unit = Running metre


Taking output = one metre
a) Labour
Mate day 0.004 0.004 0.004 617.00 2.47 2.47 2.47 L-12
Mazdoor day 0.100 0.100 0.100 511.52 51.15 51.15 51.15 L-13
b) Material
i) 25 mm steel pipe metre 16.000 16.000 16.000 129.80 2,076.82 2,076.82 2,076.82 M-175
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
ii) MS sheet for 600 x 300 x 3 mm rectangular vane, one
kg 4.320 4.320 4.320 63.81 275.64 275.64 275.64 M-181/1000
number @ 24kg/sqm
iii) MS sheet for 250 mm dia circular vane 3 mm thick,4
kg 4.800 4.800 4.800 63.81 306.27 306.27 306.27 M-181/1000
numbers @ 24 kg/sqm
Add 5 per cent cost of material for fabrication, welding,
132.94 132.94 132.94
bending, nuts, bolts etc
c) Painting
Applying 2 coats of painting on exposed surface sqm 1.830 93.00 170.19
Item No. -
sqm 1.830 95.00 173.85
8.09
sqm 1.830 97.00 177.51
d) Overhead charges @ 8% on @ 10% on @ 12% on
227.62 284.53 341.43
(a+b) (a+b) (a+b)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
307.29 312.98 318.67
(a+b+d) (a+b+d) (a+b+d)

Rate per metre = a+b+c+d+e 3,550.39 3,616.65 3,682.91


Say 3,550.00 3,617.00 3,683.00

The items of excavation and cement concrete as per


Note
approved design to be measured and paid separately

8.26 C Anti-glare screen with rectangular vane of MS sheet

Providing and erecting anti - glare screen with


rectangular vanes of size 750 x 500 mm made from MS
sheet, 3 mm thick and fixed on MS angle 50 x 50 x 6 mm
at an angle of 450 to the direction of flow of traffic, 1.5 m
center to center, top edge of the screen 1.75 m above
ground level, vertical post firmly embedded in M-15
cement concrete foundation 0.60 m below ground level,
applying 2 coats of paint on exposed faces, all complete
as per approved design and drawings

Unit = Running metre


Taking output = 1.50 metre
a) Labour
Mate day 0.004 0.004 0.004 617.00 2.47 2.47 2.47 L-12
Mazdoor day 0.100 0.100 0.100 511.52 51.15 51.15 51.15 L-13
b) Material
i) Angle iron post,50 x 50 x 6 mm, length 2.35 m kg 10.580 10.580 10.580 63.81 675.07 675.07 675.07 M-181/1000
ii) MS sheet 3 mm thick @ 24 kg/sqm kg 9.000 9.000 9.000 63.81 574.26 574.26 574.26 M-181/1000
Add 5 per cent of cost of material for fabrication, nuts,
62.47 62.47 62.47
bolts etc
c) Machinery
Tractor-trolley hour 0.100 0.100 0.100 1,876.50 187.65 187.65 187.65 P&M-026
d) Painting
Applying 2 coats of painting on exposed surface sqm 0.850 93.00 79.05
Item No. -
sqm 0.850 95.00 80.75
8.09
sqm 0.850 97.00 82.45
e) Overhead charges @ 8% on @ 10% on @ 12% on
124.25 155.31 186.37
(a+b+c) (a+b+c) (a+b+c)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
167.73 170.84 173.94
(a+b+c+e) (a+b+c+e) (a+b+c+e)

Cost for 1.5 m = a+b+c+d+e+f 1,924.10 1,959.96 1,995.83


Rate per metre = (a+b+c+d+e+f)/1.50 1,282.73 1,306.64 1,330.55
Say 1,283.00 1,307.00 1,331.00
The items of excavation and cement concrete as per
approved design to be measured and paid separately.
Note
Rate of painting has been analaysed separately in this
chapter.
Suggest
8.27 Street Lighting
ive

Providing and erecting street light mounted on a steel


circular hollow pole of standard specifications for street
lighting, 10 m high spaced 40 m apart, 1.8 m overhang
on both sides if fixed in the median and on one side if
fixed on the footpath, fitted with sodium vapour lamp and
fixed firmly in concrete foundation.

Unit = Each
Taking output = one light
a) Labour
Mate day 0.030 0.030 0.030 617.00 18.51 18.51 18.51 L-12
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
Electrician day 0.250 0.250 0.250 738.00 184.50 184.50 184.50 L-02
b) Material
i) Steel circular hollow pole of standard specification for
street lighting to mount light at 10 m height above road each 1.000 1.000 1.000 15,000.00 15,000.00 15,000.00 15,000.00 M-172
level
ii) Sodium vapour lamp each 1.000 1.000 1.000 4,210.00 4,210.00 4,210.00 4,210.00 M-169
Add 5 per cent of cost of material for holder, electric
960.50 960.50 960.50
cable, insulation, ladder, scaffolding etc .
c) Painting
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
For Fixing in Median
sqm 5.750 93.00 534.75
Providing two coats of alluminium paint over steel circular Item No. -
sqm 5.750 95.00 546.25
hollow pipe with overhang on both sides 8.09
sqm 5.750 97.00 557.75
For fixing in Footpath
sqm 4.630 93.00 430.59
Providing two coats of alluminium paint over steel circular Item No. -
sqm 4.630 95.00 439.85
hollow pipe with overhang on one side 8.09
sqm 4.630 97.00 449.11
(i) For Fixing in Median
d) Overhead charges @ 8% on @ 10% on @ 12% on
1,650.34 2,062.93 2,475.51
(a+b) (a+b) (a+b)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
2,227.96 2,269.22 2,310.48
(a+b+d) (a+b+d) (a+b+d)

Rate per light for fixing in Median= a+b+c+d+e 25,042.32 25,507.67 25,973.01
Say 25,042.00 25,508.00 25,973.00
(ii) For fixing in Footpath
Rate per light for Fixing in Footpath = a+b+c+d+e 24,938.16 25,401.27 25,864.37
Say 24,938.00 25,401.00 25,864.00

The items of excavation and cement concrete foundation


will be measured and included separately in the estimate
Note
as per approved design and drawing. The rate for
painting has been analysed in this chapter.

Suggest
8.28 Lighting on Bridges
ive

Providing and fixing lighting on bridges, mounted on steel


hollow circular poles of standard specifications, 5 m high
fixed on parapets with cement concrete, 20 m apart and
fitted with sodium vapour lamp

Unit = Each
Taking output = one light
a) Labour
Mate day 0.020 0.020 0.020 617.00 12.34 12.34 12.34 L-12
Mazdoor day 0.400 0.400 0.400 511.52 204.61 204.61 204.61 L-13
Electrician day 0.200 0.200 0.200 738.00 147.60 147.60 147.60 L-02
b) Material

i) Steel circular hollow pole of standard specification for


each 1.000 1.000 1.000 10,000.00 10,000.00 10,000.00 10,000.00 M-171
street lighting to mount light at 5 m above deck level

ii) Sodium vapour lamp 70 watt each 1.000 1.000 1.000 4,210.00 4,210.00 4,210.00 4,210.00 M-169
Add 1 per cent of cost of material for holder, electric
142.10 142.10 142.10
cable, insulation, ladder, scaffolding etc
c) Painting
sqm 2.760 93.00 256.68
Providing two coats of alluminium paint over steel circular Item No. -
sqm 2.760 95.00 262.20
hollow pipe 8.09
sqm 2.760 97.00 267.72
d) Overhead charges @ 8% on @ 10% on @ 12% on
1,177.33 1,471.66 1,766.00
(a+b) (a+b) (a+b)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
1,589.40 1,618.83 1,648.26
(a+b+d) (a+b+d) (a+b+d)

Rate per light = a+b+c+d+e 17,740.06 18,069.34 18,398.63


Say 17,740.00 18,069.00 18,399.00

The items of cement concrete to be measured and paid


Note separately as per approved design. The rate for painting
has already been analysed in this chapter.

Suggest
8.29 Cable Duct Across the Road
ive

Providing and laying of a reinforced cement concrete


pipe duct, 300 mm dia, across the road (new
construction), extending from drain to drain in cuts and
toe of slope to toe of slope in fills, constructing head walls
at both ends, providing a minimum fill of granular material
over top and sides of RCC pipe as per IRC:98-1997,
bedded on a 0.3 m thick layer of granular material free of
rock pieces, outer to outer distance of pipe at least half
dia of pipe subject to minimum 450 mm in case of double
and triple row ducts, joints to be made leak proof, invert
level of duct to be above higher than ground level to
prevent entry of water and dirt, all as per IRC: 98 - 1997
and approved drawings.

(i) Single row for one utility service


Unit = Running metre
Taking output = 20metres
cum 2.360 15.07 35.57
a) Random Rubble masonry/Brick masonry in cement
cum 2.360 15.07 35.57 Err:509
mortar 1:6 for head wall both side
cum 2.360 15.07 35.57
b) Labour
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
Mate day 0.050 0.050 0.050 617.00 30.85 30.85 30.85 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
Mazdoor skilled day 0.250 0.250 0.250 565.73 141.43 141.43 141.43 L-15
c) Material
Reinforced Cement Concrete pipe 300 mm dia metre 20.000 20.000 20.000 2,358.00 47,160.00 47,160.00 47,160.00 M-152
Granular soil with PI less than 6 for bedding and sides of
cum 7.200 7.200 7.200 1,887.12 13,587.29 13,587.29 13,587.29 M-009
pipe (0.6 x 0.6 x 20 m)
Collar for joints 300 mm dia each 9.000 9.000 9.000 76.45 688.05 688.05 688.05 M-084

Sub-Analysis
Cement mortar 1:2 for joints (15.05B) cum 0.020 0.020 0.020 5,695.00 113.90 113.90 113.90 of Concrete -
20.01 B

d) Machinery
Tractor-trolley hour 0.500 0.500 0.500 1,876.50 938.25 938.25 938.25 P&M-026
e) Overhead charges
@ 8% on @ 10% on @ 12% on
5,053.70 6,317.13 7,580.55
(b+c+d) (b+c+d) (b+c+d)

f) Contractor's profit
@ 10% on @ 10% on @ 10% on
6,822.50 6,948.84 7,075.18
(b+c+d+e) (b+c+d+e) (b+c+d+e)

Cost for 20 metre = a+b+c+d+e+f 75,083.06 76,472.82 77,862.59


Rate per metre = (a+b+c+d+e+f)/20 3,754.15 3,823.64 3,893.13
Say 3,754.00 3,824.00 3,893.00
8.29 (ii) Double row for two utility services
Unit = Running metre
Taking output = 20metres
cum 3.370 15.07 50.79
a) Random Rubble brick/Brick masonry in cement mortar
cum 3.370 15.07 50.79 Err:509
1:6 for head wall both sides.
cum 3.370 15.07 50.79
b) Labour
Mate day 0.090 0.090 0.090 617.00 55.53 55.53 55.53 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
Mazdoor skilled day 0.250 0.250 0.250 565.73 141.43 141.43 141.43 L-15
c) Material
Reinforced Cement Concrete pipe 300 mm dia metre 40.000 40.000 40.000 2,358.00 94,320.00 94,320.00 94,320.00 M-152
Granular soil with PI less than 6 for bedding and sides of
cum 14.400 14.400 14.400 1,887.12 27,174.57 27,174.57 27,174.57 M-009
pipe (0.6 x 0.6 x 40 m)
Collar for joints 300 mm dia each 18.000 18.000 18.000 76.45 1,376.10 1,376.10 1,376.10 M-084

Sub-Analysis
Cement mortar 1:2 for joints cum 0.040 0.040 0.040 5,695.00 227.80 227.80 227.80 of Concrete -
20.01 B

d) Machinery
Tractor-trolley hour 1.000 1.000 1.000 1,876.50 1,876.50 1,876.50 1,876.50 P&M-026
e) Overhead charges
@ 8% on @ 10% on @ 12% on
10,095.60 12,619.50 15,143.40
(b+c+d) (b+c+d) (b+c+d)

f) Contractor's profit
@ 10% on @ 10% on @ 10% on
10,903.25 13,881.45 16,960.60
(b+c+d+e) (b+c+d+e) (b+c+d+e)

Cost for 20 metre = a+b+c+d+e+f 147,244.60 152,746.71 158,349.76


Rate per metre = (a+b+c+d+e+f)/20 7,362.23 7,637.34 7,917.49
Say 7,362.00 7,637.00 7,917.00
8.29 (iii) Triple Row for three utility services
Unit = Running metre
Taking output = 20 metres
cum 4.380 15.07 66.01
a) Random Rubble brick/Brick masonry in cement mortar
4.380 15.07 66.01 Err:509
1:6 for head wall both sides.
4.380 15.07 66.01
b) Labour
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
c) Material
Reinforced Cement Concrete pipe 300 mm dia metre 60.000 60.000 60.000 2,358.00 141,480.00 141,480.00 141,480.00 M-152
Granular soil with PI less than 6 for bedding and sides of
cum 21.600 21.600 21.600 1,887.12 40,761.86 40,761.86 40,761.86 M-009
pipe (0.6 x 0.6 x 60 m)
Collar for joints 300 mm dia each 27.000 27.000 27.000 76.45 2,064.15 2,064.15 2,064.15 M-084

Sub-Analysis
Cement mortar 1:2 for joints cum 0.060 0.060 0.060 5,695.00 341.70 341.70 341.70 of Concrete -
20.01 B

d) Machinery
Tractor-trolley hour 1.500 1.500 1.500 1,876.50 2,814.75 2,814.75 2,814.75 P&M-026
e) Overhead charges
@ 8% on @ 10% on @ 12% on
15,172.92 18,966.15 22,759.38
(b+c+d) (b+c+d) (b+c+d)

f) Contractor's profit
@ 10% on @ 10% on @ 10% on
20,483.44 20,862.76 21,242.08
(b+c+d+e) (b+c+d+e) (b+c+d+e)

Cost for 20 metre = a+b+c+d+e+f 225,383.83 229,556.38 233,728.94


Rate per metre = (a+b+c+d+e+f)/20 11,269.19 11,477.82 11,686.45
Say 11,269.00 11,478.00 11,686.00
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project

1.Inspection chamber at both ends is the responsibility of


Note
the agency who is laying the duct. Hence not included.

2.The rates for stone masonry / brick masonry and


cement mortar to be adopted from respective clauses.

Suggest
8.30 Highway Patrolling and Traffic Aid Post
ive
It is proposed to locate one Traffic Aid Post every 50-60
km of the highway.
The organisation and financial aspect are required to be
finalised in consultation with administrative and traffic
authorities .
Suggest Items Related to Underpass/ Subway/ Overhead Bridge/
8.31
ive Overhead Foot Bridge

The items involved for underpass/ subway/ overhead


bridge/ overhead foot bridge are earthwork, plain cement
concrete, plastering, painting, information sign etc. The
rates for these items are available in respective chapters
which can be adopted for the quantities derived from the
approved designs and drawings

Suggest
8.32 Traffic Control System and Communication System
ive

Providing a traffic control centre and communication


system including telecommunication facilities and related
accessories, CCTV, radar, vehicle detection camera,
central computer system

These are specialised item of telecommunication system


and are the commercial products. The designer is
required to contact the manufacturers to ascertain market
prices. In case of civil works required to be executed for
these installations, pricing may be done as per rates in
relevant chapters for quantities derived as per approved
design and drawing.

As regards the locations where such devices are required


to be installed, the traffic control authority should be
consulted to finalise the location
Suggest
8.33 Gantry Mounted Variable Message Sign Board
ive

Providing and erecting gantry mounted variable message


sign board electronically operated capable of flashing the
desired message over a designed support system of
aluminium alloy or galvanised steel, erected as per
approved design and drawings and with lateral clearance
as per clause 802.3

(i) Gantry Support System


Unit = tonne
Taking output=1 tonne
a) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
Blacksmith day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-02
b) Material
Alluminium alloy/galvanised steel including 5 per cent
tonne 1.050 1.050 1.050 46,496.54 48,821.37 48,821.37 1,731.45 M-060
wastage
Add 15 per cent of cost of material for fabrication and
7,323.21 7,323.21 259.72
erection.
Add 1 per cent of cost of material for nuts, bolts and
488.21 488.21 17.31
welding
c) Machinery
Truck 10 tonne hour 1.000 1.000 1.000 1,731.45 1,731.45 1,731.45 1,731.45 P&M-017
d) Overhead charges @ 8% on @ 10% on @ 12% on
4,815.95 6,019.93 669.00
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
6,501.53 6,621.93 624.40
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Rate per tonne = a+b+c+d+e 71,516.79 72,841.18 6,868.41


Say 71,517.00 72,841.00 6,868.00
8.33 (ii) Message Display
Message display board 6 sqm electronically operated
with complete electronic fitments for flashing the pre-
determined messages.
This is a specilised commercial product and the lumpsum
rate including erection at site is required to be as
certained from the market and including in the rate
analysis. The size of the board will vary depending upon
specific location.
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project

The rate for the gantry mounted variable sign would be


the addition of cost of gantry support system as per
approved design determined at (i) above and the cost of
message display board as certained from the market at
(ii) above
Suggest
8.34 Traffic Impact Attenuators at Abutments and Piers
ive
A With Scrap Tyres

Provision and installation of traffic attenuators at


abutment/pier of flyovers bridges using scrap tyres of size
100 x 20 retrieved from trucks laid in 2 rows and 4 tiers,
one above the other and tied with 20 mm wire rope as
per approved design and drawings.

Unit = sqm
Taking output = 20sqm
a) Labour
Mate day 0.070 0.070 0.070 617.00 43.19 43.19 43.19 L-12
Mazdoor day 1.500 1.500 1.500 511.52 767.28 767.28 767.28 L-13
Blacksmith day 0.250 0.250 0.250 738.00 184.50 184.50 184.50 L-02
b) Material
Scrap tyres of size 900 x 20 each 80.000 80.000 80.000 130.00 10,400.00 10,400.00 10,400.00 M-162
20 mm steel wire rope kg 150.000 150.000 150.000 44.78 6,717.38 6,717.38 6,717.38 M-178
Add 1 per cent of cost of wire rope for clamps etc. 67.17 67.17 67.17
c) Machinery
Tractor-trolley hour 3.000 3.000 3.000 1,876.50 5,629.50 5,629.50 5,629.50 P&M-026
d) Overhead charges @ 8% on @ 10% on @ 12% on
1,904.72 2,380.90 2,857.08
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
2,571.37 2,618.99 2,666.61
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 20 sqm = a+b+c+d+e 28,285.11 28,808.91 29,332.71


Rate per sqm = (a+b+c+d+e)/20 1,414.26 1,440.45 1,466.64
Say 1,414.00 1,440.00 1,467.00
8.34 B Using Plastic/Steel Barrel, Filled with Sand

Provision and installation of traffic impact attenuator at


abutment/pier of flyovers bridges using plastic/steel
barrels 0.60 m dia and 1.0 m in height, filled with sand in
three rows and tied with20 mm steel wire rope as per
approved design and drawings

Unit = sqm
Taking output = 20sqm
a) Labour
Mate day 0.130 0.130 0.130 617.00 80.21 80.21 80.21 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Blacksmith day 0.250 0.250 0.250 738.00 184.50 184.50 184.50 L-02
b) Material
Plastic barrels each 50.000 50.000 50.000 150.00 7,500.00 7,500.00 7,500.00 M-173
or
Steel barrels each 50.000 50.000 50.000 252.00 12,600.00 12,600.00 12,600.00 M-173
Sand cum 8.000 8.000 8.000 1,994.03 15,952.25 15,952.25 15,952.25 M-004
20 mm steel wire rope kg 15.000 15.000 15.000 44.78 671.74 671.74 671.74 M-178
Add 1 per cent of cost of wire rope for clamps etc. 6.72 6.72 6.72
c) Machinery
Tractor-trolley hour 2.000 2.000 2.000 1,876.50 3,753.00 3,753.00 3,753.00 P&M-026
d) Overhead charges @ 8% on @ 10% on @ 12% on
2,374.64 2,968.30 3,561.96
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
3,205.76 3,265.13 3,324.49
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 20 sqm = a+b+c+d+e 35,263.37 35,916.40 36,569.42


Rate per sqm = (a+b+c+d+e)/20 1,763.17 1,795.82 1,828.47
Say 1,763.00 1,796.00 1,828.00
d) Overhead charges @ 8% on @ 10% on @ 12% on
2,782.64 3,478.30 4,173.96
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
3,756.56 3,826.13 3,895.69
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 20 sqm = a+b+c+d+e 41,322.17 42,087.40 42,852.62


Rate per sqm = (a+b+c+d+e)/20 2,066.11 2,104.37 2,142.63
Say 2,066.00 2,104.00 2,143.00
8.34 C With HI - DRO cell Sandwich (Patented)
(In this patented HI - DRO cell system, water gets
discharged from plastic tubes on impact over a pre-
determined time, thus absorbing the energy)
Providing and installing a patentend HI - DRO cell system
as a traffic impact attenuators, using plastic tubes 50 cm
dia, 1.2 m in height, 25 mm opening at the top, placed in
three rows, filled with water and tied with a 20 mm steel
wire rope
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
Unit = sqm
Taking output = 10sqm
a) Labour
Mate day 0.100 0.100 0.100 617.00 61.70 61.70 61.70 L-12
Mazdoor day 2.500 2.500 2.500 511.52 1,278.80 1,278.80 1,278.80 L-13
b) Material
Plastic tubes 50 cm dia,1.2 m high each 40.000 40.000 40.000 1,124.00 44,960.00 44,960.00 44,960.00 M-138
Cost of water KL 12.000 12.000 12.000 16.00 192.00 192.00 192.00 M-191
20 mm steel wire rope kg 100.000 100.000 100.000 44.78 4,478.25 4,478.25 4,478.25 M-178
Add 1 per cent of cost of wire rope for clamps etc. 44.78 44.78 44.78
c) Machinery
Tractor-trolley hour 2.000 2.000 2.000 1,876.50 3,753.00 3,753.00 3,753.00 P&M-026
Water tanker6 KL capacity hour 2.000 2.000 2.000 1,005.00 2,010.00 2,010.00 2,010.00 P&M-025
d) Overhead charges @ 8% on @ 10% on @ 12% on
4,542.28 5,677.85 6,813.42
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
6,132.08 6,245.64 6,359.20
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 10 sqm = a+b+c+d+e 67,452.90 68,702.02 69,951.15


Rate per sqm = (a+b+c+d+e)/10 6,745.29 6,870.20 6,995.12
Say 6,745.00 6,870.00 6,995.00
Suggest
8.35 Solar Powered Road Marker ( Solar Stud)
ive
Supplying of Solar Raised Pavement Markers made of
polycarbonate molded body with circular shape, solar
powered,LED self illumination in active mode, 360
degree illumination and reflective panels with micro
prismatic lens capable of providing total internal reflection
of the light entering the lens face in passive mode. The
marker shall support a load of 20000 kg tested in
accordance to ASTM D 4280. The marker should be
resistant to dust and water ingress according to IP 65
standards and should withstand temperatures in the
range of 0 C to 70 C. Color of lighting could be provided
in red or yellow (amber) as per requirement and typical
frequency of blinking is 1 Hz. There should be current
losses of less than 20 microamperes at 2.4 V in
sleepcharging mode to enhance the life of the marker
and a full charge should provide for a minimum autonomy
of 50 hours. The height, width and length of the marker
shall not be less than 10 mm x 100 mm x 100 mm. Also,
the surface diameter of the marker shall not be less than
100 mm respectively. The weight of the marker shall not
exceed 0.5 Kilograms. Fixing will be by drilling holes on
the road for the shanks to go inside, without nails and
using epoxy resin based adhesive and complete as
directed by the engineer.

Unit = Nos
Taking output = 50Nos
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Material
Poly carbonate or ABS body and shall support a load of
13.635 Kg tested in accordance to ASTM D 4280 with
each 50.000 50.000 50.000 169.19 8,459.50 8,459.50 8,459.50 M-062
height not exceeding 20mm and width/length not
exceeding 130mm
Add 10 per cent of cost of material for fixing and
845.95 845.95 845.95
installation
c) Overhead charges @ 8% on @ 10% on @ 12% on
787.33 984.17 1,181.00
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,062.90 1,082.58 1,102.26
(a+b+c) (a+b+c) (a+b+c)
Cost for 50 studs = a+b+c+d 11,691.88 11,908.40 12,124.91
Rate per studs = (a+b+c+d)/50 233.84 238.17 242.50
Say 234.00 238.00 242.00
Suggest
8.36 Traffic Cone
ive

Provision of red fluorescent with white reflective sleeve


traffic cone made of low density polyethylene (LDPE)
material with a square base of 390 x 390 x 35 mm and a
height of 770 mm, 4 kg in weight, placed at 1.5 m
interval, all as per BS 873

Unit = Running metre


Taking output = 68 Nos.
a) Labour
Mate day 0.020 0.020 0.020 617.00 12.34 12.34 12.34 L-12
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
b) Material
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
Traffic cones with 150 mm reflective sleeve each 68.000 68.000 68.000 640.00 43,520.00 43,520.00 43,520.00 M-188
c) Machinery
Tractor-trolley hour 0.100 0.100 0.100 1,876.50 187.65 187.65 187.65 P&M-026
d) Overhead charges @ 8% on @ 10% on @ 12% on
3,518.06 4,397.58 5,277.09
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
4,749.38 4,837.33 4,925.28
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 68 Nos. = a+b+c+d+e 52,243.19 53,210.66 54,178.12


Rate per metre = (a+b+c+d+e)/68 768.28 782.51 796.74
Say 768.00 783.00 797.00
Suggest
8.37 Roadside Amenities
ive
A Rest areas
Providing plainly furnished accommodation for rest
rooms, dormitories, restaurants, stalls, shops, petrol
pump, telephone booth, first aid room, traffic aid post,
police assistance booth, including electricity, toilet and
sewerage system
Pricing may be done based on current plinth area rates
approved by PWD/CPWD/MES for a particular zone.
Area is required to be assessed for specific location as
per actual site conditions
Parking areas and bus laybyes for trucks, buses and light
B
vehicles

Pricing of parking areas may be done for the quantities of


various items based on the approved dimensions and
pavement design for a particular terrain and soil. Rates
for items may be from respective chapters.

C Lawn
Providing a lawn planted with grass and its maintenance

Pricing of lawn may be done as per rates given in the


chapter on horticulture for the quantities as per approved
dimensions in the drawings
Suggest
8.38 Rumble Strips
ive
Provision of 15 nos rumble strips covered with premix
bituminous carpet, 15-20 mm high at center, 250 mm
wide placed at 1 m center to center at approved locations
to control speed, marked with white strips of road
marking paint.
Unit = sqm
Taking output = 100 sqm (including gaps)
Sqm 26.250 173.00 4,541.25
Item No. -
Open - Graded Premix Surfacing Sqm 26.250 177.00 4,646.25
5.07
Sqm 26.250 180.00 4,725.00
Sqm 26.250 557.00 14,621.25
Road Marking with Hot Applied Thermoplastic Compound Item No. -
Sqm 26.250 567.00 14,883.75
with Reflectorising Glass Beads on Bituminous Surface 8.13
Sqm 26.250 578.00 15,172.50
19,162.50 19,530.00 19,897.50
191.63 195.30 198.98
Say 192.00 195.00 199.00

The rate per sqm of premix carpet and road marking may
be adopted from chapter 5 & 8 respectively for the
quantities calculated from approved drawings

Suggest
8.39 Policeman Umbrella
ive

Provision of a 2 m high (floor to roof) umbrella for traffic


policeman at road crossings, where necessary, installed
on a raised platform, built on a central support of a steel
pipe 100 mm dia, roof made of 25 mm dia steel pipe to
provide covered area of 3 sqm, roofed with CGI sheets,
all steel parts to be given 2 coats of paint

Unit = each
Taking output = one number
Earthwork cum
Cement Concrete cum
brick masonry or cum
stone masonry cum
Painting sqm 2.500 93.00 232.50
Item No. -
sqm 2.500 95.00 237.50
8.09
sqm 2.500 97.00 242.50
a) Labour
Mate day 0.090 0.090 0.090 617.00 55.53 55.53 55.53 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
Blacksmith (Ist class) day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-02
Welder day 0.250 0.250 0.250 738.00 184.50 184.50 184.50 L-02
b) Material
Steel pipe 100 mm dia metre 3.500 3.500 3.500 337.05 1,179.68 1,179.68 1,179.68 M-177
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
Steel pipe 25 mm dia metre 10.000 10.000 10.000 129.80 1,298.01 1,298.01 1,298.01 M-175
CGI sheets (0.8 mm) kg 8.000 8.000 8.000 62.55 500.40 500.40 500.40 M-082
Add 25 per cent of cost of material for fabrication 744.52 744.52 744.52
Add 2 per cent of cost of material for welding
59.56 59.56 59.56
consumables, J-hooks, washers etc.
c) Machinery
Tractor-trolley hour 0.500 0.500 0.500 1,876.50 938.25 938.25 938.25 P&M-026
d) Overhead charges @ 8% on @ 10% on @ 12% on
496.80 621.00 745.20
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
670.68 683.10 695.52
(a+b+c+d) (a+b+c+d) (a+b+c+d)

7,609.94 7,751.56 7,893.18


Rate per policeman umbrella = a+b+c+d+e Say 7,610.00 7,752.00 7,893.00

suggesti
8.40 High Mast Pole Lighting at Interchanges and Flyovers
ve

Providing and erecting a high mast pole lighting with 30


m high hot dip galvanised mast designed to withstand
forces exerted with wind speeds of 180 km per hour with
3 seconds gust, as per IS:875 (Part 3) - 1978, fitted with
a base flange, door at the base of mast with heavy duty
internal lock, lantern carriage, suitable winching
arrangement for safe working load of 750 kg and high
powered electrically driven power tools for raising and
lowering of lantern carriage, flexible 8 core electric cable,
lightening conductor, earthing terminal, and fixing 2 nos
aviation obstruction lights on top of the mast, all complete
as per approved design and drawings

This is a specialised work and is generally done by firms


who specialise in such jobs. The detailed designs and
estimates are submitted by the firms along with their
tender for checks by the Department. The cost of this
work is required to be worked out based on approved
design, drawings and estimate of the lowest tender. A
separate contract for this work is concluded as the
contractors for road and bridge works generally donot
undertake such jobs.

8.41 Toll Plaza

The construction, operation and maintenance of Toll


Plaza can be broken into separate items of work as
under based on the approved design and drawings:-

a) Provision of toll collection service lane to separate


different categories of vehicles for purpose of toll
collection. This involves considerable increase in carriage
way width
b) Provision of 2.5 m wide separators for different toll
collection service lanes for safety
c) Toll booths with integrated roof cover
d) Barrier gates for individual lanes
e) Provision of building to provide facility to toll plaza
personnel
f) Toll plaza office equipment and furniture
g) Water supply, electricity, sanitation, septic-tank
system and drainage
h) Telephone, intercomes, wireless communication
system
i) High mast lighting
j) Pavement marking
k) Overhead signs
l) Fixed message signs (Advance)
m) Variable message signs
n) Traffic cones and pylons
o) First aid post
p) Traffic aid post and security
The quantities for the above mentioned items may be
calculated from the approved design and drawings and
their rates adopted from respective chapters of the
Standard Data Book
8.42 Safety Devices and Signs in Construction Zones
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project

Provision and fixing of traffic signs for limited period at


suitable locations in construction zone comprising of
warning zone, approach transition zone, working zone
and terminal transition zone with a minimum distance of
60 cm from the edge of the kerb in case of kerbed roads
and 2 to 3 m from the edge of the carriageway in case of
un-kerbed roads, the bottom edge of the lowest sign
plate to be not less than 2 m above the road level, fixed
on 60 mm x 60 mm x 6 mm angle iron post, founded and
installed as per approved design and drawings, removed
and disposed of after completion of construction work, all
as per IRC:SP:55-2001

Unit = each
Taking output = one sign post
Following types of signs are required to be fixed in
construction zones for safety of traffic
a) Diversion one km ahead
b) Traffic sign ahead
c) Road ahead closed
d) Men at work
e) Road narrow
f) Single file traffic
g) Right lane diverted
h) Left lane diverted
i) Right lane closed
j) Left lane closed
k) Median closed
l) Diversion to other carriageway
m) Traffic signal ahead
n) Two way traffic
o) Un - even road
p) Slippery road
q) Loose chippings
r) Dual carriageway ends
s) Diversion
t) Do not enter
u) Road closed
v) Stop
w) Slow
x) One way
y) Give way
z) Overtaking prohibited
aa) Speed limit
bb) Weight limit
cc) Height and length limit
dd) No stopping or standing
ee) Any other warning or regulatory safety sign as per
site requirement and consistent with IRC:SP:55 and
IRC:67
The rate for traffic signs are already worked out and
given elsewhere in this chapter. The same may be
adopted.
suggesti
8.43 Portable Barricade in Construction Zone
ve

Installation of a steel portable barricade with horizontal


rail 300 mm wide, 2.5 m in length fitted on a 'A' frame
made with 45 x 45 x 5 mm angle iron section, 1.5 m in
height, horizontal rail painted (2 coats) with yellow and
white stripes, 150 mm in width at an angle of 450, 'A'
frame painted with 2 coats of yellow paint, complete as
per IRC:SP:55-2001

Unit = each
Taking output = one steel portable barricade
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
Painter day 0.500 0.500 0.500 679.00 339.50 339.50 339.50 L-18
Welder day 0.250 0.250 0.250 738.00 184.50 184.50 184.50 L-02
b) Material
Angle iron 45 x 45 x 5 mm kg 25.000 25.000 25.000 63.81 1,595.16 1,595.16 1,595.16 M-181 /1000
MS sheet 300 mm wide,2.5 m long and 2.6 mm thick kg 15.000 15.000 15.000 63.81 957.10 957.10 957.10 M-181 /1000
Paint litre 0.500 0.500 0.500 235.22 117.61 117.61 117.61 M-130
Add 2 per cent of cost of steel for welding consumables,
51.05 51.05 51.05
nuts & bolts and drilling holes
c) Overhead charges @ 8% on @ 10% on @ 12% on
271.80 339.75 407.70
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
293.54 373.72 456.62
(a+b+c) (a+b+c) (a+b+c)
Rate per barricade = a+b+c+d 3,962.82 4,110.95 4,261.80
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
Say 3,963.00 4,111.00 4,262.00
suggesti
8.44 Permanent Type Barricade in Construction Zone
ve
A With steel components

Construction of a permanent type barricade made of


steel components, 1.5 m high from road level, fitted with
3 horizontal rails 200 mm wide and 4 m long on 50 x 50 x
5 mm angle iron vertical support, painted with yellow and
white strips, 150 mm in width at an angle of450, complete
as per IRC:SP:55-2001

Unit = each
Taking output = one barricade
a) Labour
Mate day 0.048 0.048 0.048 617.00 29.62 29.62 29.62 L-12
Mazdoor day 0.300 0.300 0.300 511.52 153.46 153.46 153.46 L-13
Painter day 0.600 0.600 0.600 679.00 407.40 407.40 407.40 L-18
Welder day 0.300 0.300 0.300 738.00 221.40 221.40 221.40 L-02
b) Material
Angle iron 50 x 50 x 5 mm,2 m long,2 Nos. kg 15.000 15.000 15.000 63.81 957.10 957.10 957.10 M-181 /1000
MS sheet of 12 SWG,3 Nos of 200 mm width and 4 m
kg 50.000 50.000 50.000 63.81 3,190.33 3,190.33 3,190.33 M-181 /1000
length
Paint litre 1.000 1.000 1.000 235.22 235.22 235.22 235.22 M-130
Add 1 per cent of cost of steel for welding consumables,
82.95 82.95 82.95
nuts & bolts and drilling holes
c) Overhead charges @ 8% on @ 10% on @ 12% on
422.20 527.75 633.30
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
569.97 580.52 591.08
(a+b+c) (a+b+c) (a+b+c)
Rate per barricade = a+b+c+d 6,269.63 6,385.73 6,501.84
Say 6,270.00 6,386.00 6,502.00
8.44 B With wooden components

Construction of a permanent type barricade made of


wooden components, 1.5 m high from road level, fitted
with 3 horizontal planks 200 mm wide and 3.66 m long on
100 x 100mm wooden vertical post, painted with yellow
and white strips, 150 mm in width at an angle of450,
complete as per IRC:SP:55-2001

Unit = each
Taking output = one barricade
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Mazdoor day 0.300 0.300 0.300 511.52 153.46 153.46 153.46 L-13
Painter day 0.600 0.600 0.600 679.00 407.40 407.40 407.40 L-18
Carpenter day 0.600 0.600 0.600 738.00 442.80 442.80 442.80 L-04
b) Material
Timber cum 0.180 0.180 0.180 2,500.00 450.00 450.00 450.00 M-187
Add 1 per cent of cost of timber for nuts & bolts, nails,
4.50 4.50 4.50
etc.
c) Overhead charges @ 8% on @ 10% on @ 12% on
119.61 149.52 179.42
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
161.48 164.47 167.46
(a+b+c) (a+b+c) (a+b+c)
Rate per barricade = a+b+c+d 1,776.27 1,809.16 1,842.06
Say 1,776.00 1,809.00 1,842.00
8.44 C With bricks
Construction of a permanent type barricade made with
brick work in mud mortar, 1.5 m high, 4 m long, 600 mm
thick, plastered with cement mortar 1:6, painted with
yellow and white strips
Unit = each
Taking output = one barricade
a) Labour
Mate day 0.240 0.240 0.240 617.00 148.08 148.08 148.08 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Painter day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-18
Mason day 2.000 2.000 2.000 738.00 1,476.00 1,476.00 1,476.00 L-11
b) Material
Brick each 1800.000 1800.000 1800.000 3.50 6,300.00 6,300.00 6,300.00 M-079
Cement kg 22.000 22.000 22.000 4.94 108.68 108.68 108.68 M-081 /1000
Sand cum 0.090 0.090 0.090 1,994.03 179.46 179.46 179.46 M-005
Paint litre 1.250 1.250 1.250 235.22 294.03 294.03 294.03 M-130
c) Overhead charges @ 8% on @ 10% on @ 12% on
857.58 1,071.98 1,286.38
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,157.74 1,179.18 1,200.62
(a+b+c) (a+b+c) (a+b+c)
Rate per barricade = a+b+c+d 12,735.13 12,970.97 13,206.80
Say 12,735.00 12,971.00 13,207.00
suggesti
8.45 Drum Delineator in Construction Zone
ve
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project

Provision of metal drum/empty bitumen drum delineator,


300 mm in diameter, 800 mm high, filled with earth for
stability, painted in circumferential strips of alternate Red
and white 100 mm wide fitted with reflectors 3 Nos of 75
mm wide, all as per IRC:SP:55.

Unit = each
Taking output = one drum delineator
a) Labour
Mate day 0.020 0.020 0.020 617.00 12.34 12.34 12.34 L-12
Mazdoor day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
Painter day 0.250 0.250 0.250 679.00 169.75 169.75 169.75 L-18
b) Material
Steel drum 300 mm dia 1.2 m high/empty bitumen drum each 1.000 1.000 1.000 252.00 252.00 252.00 252.00 M-173
Paint litre 0.500 0.500 0.500 235.22 117.61 117.61 117.61 M-130
c) Overhead charges @ 8% on @ 10% on @ 12% on
54.37 67.96 81.55
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
73.39 74.75 76.11
(a+b+c) (a+b+c) (a+b+c)
Rate per drum delineator = a+b+c+d 807.34 822.29 837.24
Say 807.00 822.00 837.00
suggesti
8.46 Water Filled Barricades Work zone sheeting
ve

Providing water filled barricades made up of LDPE to


segregate the vehicular movement and workzone as per
IRC SP 55 shall be in Trapezoidal Shape 800 mm to
1000 mm in length, 700 mm in height for Major Roads
and expressway and 500 mm tall for other roads with
interlocking arrnagements, To be placed 0.5 m from the
edge of the carriageway for expressway and 0.3 m for
other roads. It should have reboubdable workzone
sheeting as per ASTM D 4956 S2.

Unit = each
Taking output = one drum delineator
a) Labour
Mate day 0.010 0.010 0.010 617.00 6.17 6.17 6.17 L-12
Mazdoor day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
b) Material
Water Filled Barricades Work zone sheeting each 1.000 1.000 1.000 2,500.00 2,500.00 2,500.00 2,500.00 M-238
c) Overhead charges @ 8% on @ 10% on @ 12% on
210.72 263.41 316.09
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
284.48 289.75 295.01
(a+b+c) (a+b+c) (a+b+c)
Rate per drum delineator = a+b+c+d 3,129.25 3,187.20 3,245.15
Say 3,129.00 3,187.00 3,245.00
suggesti
8.47 Tubular Marker/ Spring post 450 mm
ve

Providing Tubular Marker made up of Polyurethane used


to divide opposing lanes of road users shall be flexible in
nature. Tubular maker having height upto 450 mm shall
be having 75 mm Reboundable workzone retroreflective
sheeting as per ASTM 4956 S2. Application of Tubular
Marker Shall be done as per IRC SP 55

Unit = each
Taking output = one drum delineator
a) Labour
Mate day 0.010 0.010 0.010 617.00 6.17 6.17 6.17 L-12
Mazdoor day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
b) Material
Tubular Marker/ Spring post 450 mm each 1.000 1.000 1.000 350.00 350.00 350.00 350.00 M-237
c) Overhead charges @ 8% on @ 10% on @ 12% on
38.72 48.41 58.09
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
52.28 53.25 54.21
(a+b+c) (a+b+c) (a+b+c)
Rate per drum delineator = a+b+c+d 575.05 585.70 596.35
Say 575.00 586.00 596.00
suggesti
8.48 Tubular Marker/ Spring post 700 mm
ve

Providing Tubular Marker made up of Polyurethane used


to divide opposing lanes of road users shall be flexible in
nature. Tubular maker having minimum height 700 mm
shall be having minimum 75 mm Reboundable workzone
retroreflective sheeting as per ASTM 4956 S2.
Application of Tubular Marker Shall be done as per IRC
SP 55.

Unit = each
Taking output = one drum delineator
a) Labour
Mate day 0.010 0.010 0.010 617.00 6.17 6.17 6.17 L-12
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
Mazdoor day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
b) Material
Tubular Marker/ Spring post 700 mm each 1.000 1.000 1.000 375.00 375.00 375.00 375.00 M-236
c) Overhead charges @ 8% on @ 10% on @ 12% on
40.72 50.91 61.09
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
54.98 56.00 57.01
(a+b+c) (a+b+c) (a+b+c)
Rate per drum delineator = a+b+c+d 604.75 615.95 627.15
Say 605.00 616.00 627.00
suggesti
8.49 Flagman
ve

Positioning of a smart flagman with a yellow vest and a


yellow cap and a red flag 600 x 600 mm securely
fastened to a staff 1 m in length for guiding the traffic

Unit = each
Taking output = one flagman
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Material
Flag of red color cloth 600 x 600 mm each 1.000 1.000 1.000 118.00 118.00 118.00 118.00 M-099
Wooden staff for fastening of flag 25 mm dia, one m long each 1.000 1.000 1.000 16.00 16.00 16.00 16.00 M-198
c) Overhead charges @ 8% on @ 10% on @ 12% on
53.62 67.02 80.42
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
72.38 73.72 75.06
(a+b+c) (a+b+c) (a+b+c)
Rate per flagman = a+b+c+d 796.20 810.94 825.69
Say 796.00 811.00 826.00

Advanced Traffic Management Systems (ATMS) work


shall cover design, supply, installation, commissioning
and/or operation and maintenance of Advance Traffic
Management Systems (which is one of the components
of Intelligent Transport Systems - ITS). The system would
include out-door equipment including emergency call
boxes, variable message sign systems, meteorological
8.50 816 data system, close circuit TV camera (CCTV) system,
traffic counting and classification system and
transmission system. The indoor equipment would
comprise a large display board, central computer (with
Network Management System - NMS), CCTV monitor
system, call centre system or management of emergency
call boxes housed in a control centre with uninterrupted
power supply.

A Traffic Management Command Centre Equipment


Material
Control Centre Server Nos. 1.000 1.000 1.000 1.00 1.00 1.00 1.00 M-244
Hot Standby Backup Server Nos. 1.000 1.000 1.000 1.00 1.00 1.00 1.00 M-245
NAS Video Server with storage Minimum 70 TB Nos. 1.000 1.000 1.000 1.00 1.00 1.00 1.00 M-246
Backup Video (Only Incidents) Server Nos. 1.000 1.000 1.000 1.00 1.00 1.00 1.00 M-247
Graphic Display (70" LED DLP in 3x2 matrix) Set 1.000 1.000 1.000 1.00 1.00 1.00 1.00 M-248
Graphic Display Controller and software including Video
Set 1.000 1.000 1.000 1.00 1.00 1.00 1.00 M-249
Switches
CCTV Monitoring Workstation Nos. 1.000 1.000 1.000 1.00 1.00 1.00 1.00 M-250
Emergency Telephone (1033) console Nos. 1.000 1.000 1.000 1.00 1.00 1.00 1.00 M-251
VIDS- Workstation Nos. 1.000 1.000 1.000 1.00 1.00 1.00 1.00 M-252
Administrative Workstation Nos. 1.000 1.000 1.000 1.00 1.00 1.00 1.00 M-253
ATMS Operator Workstation Nos. 1.000 1.000 1.000 1.00 1.00 1.00 1.00 M-254
CCTV Joystick Nos. 1.000 1.000 1.000 1.00 1.00 1.00 1.00 M-255
Operations Laser Printer (Colour) Nos. 1.000 1.000 1.000 1.00 1.00 1.00 1.00 M-256
Operations Laser Printer (Black) Nos. 1.000 1.000 1.000 1.00 1.00 1.00 1.00 M-257
Rack 19" Nos. 1.000 1.000 1.000 1.00 1.00 1.00 1.00 M-258
Advanced Traffic Management Systems (ATMS)
B
Software
ATMS Control Room Software (integrated with VIDS,
Nos. 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-259
ATCC, VMS, MOS)

Video Management Software with atleast 150 VMS Lic. Nos. 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-260
Facility Monitoring System Controller Software Nos. 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-261
Server & Database license Nos. 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-262
Antivirus license Nos. 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-263
C PTZ Closed Circuit Television System
PTZ Camera (including CCTV Controller) Set 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-264
Solar System with UPS, battery & 12m Pole & Cabinet Set 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-265

D Video Incident Detection System Equipment (VIDS)


D1 VIDS Camera (including Image Processing unit) Set 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-266
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
Warning amber lights with hooters, 72 Hrs solar backup,
D2 Set 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-267
5m poles and foundation
D3 Cabinet Nos. 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-268
D4 12 m Pole (including manufacturing and galvanizing) Nos. 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-269
D5 Solar System with UPS & batteries Set 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-270
Automatic Traffic Counters-cum-classifier System
E
Equipment (ATCC)
Equipment, Sensor unit, Processing unit, Solar power
E1 Set 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-271
supply
E3 Solar System with UPS, batteries Set 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-272
F Variable Message Sign Equipment (VMS)
VMS (Variable Message Sign - M type) Nos. 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-273
Gantry (including manufacturing and galvanizing) Nos. 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-274
Solar System with UPS, battery and cabinet for M type
Set 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-275
VMS
G UPS and Power system
Uninterruptible Power Supply (UPS) For Server Rack (10
Set 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-276
KVA)

Uninterruptible Power Supply (UPS) For TMC (30 KVA) Set 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-277

Power Distribution Board (Essential & Critical Supply) Set 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-278
H Meteorological Observation System (MOS)
MOS sensor Equipment (including MOS Controller) Set 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-279
Cabinet Nos. 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-280
Pole Nos. 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-281
Steel fence for protection Set 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-282
I Digital Transmission System (DTS)
24 Core Armoured OFC + all accessories Km 1.000 1.000 1.00 29.00 29.00 29.00 29.00 M-283
40 mm PLB HDPE duct as per latest TSEC specifications
Km 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-284
+ all accessories
Trenching of 1.8 meters, Laying & Backfilling for PLB
Km 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-285
HDPE duct
Overhead and contractor profit will be add separately on
Note
Item no 8.50 .
Civil works required to be executed for these
installations, pricing may be done as per rates in relevant
chapters for quantities derived approved design and
drawing.)
suggesti Fiber Reinforced Cement Concrete new jersey crash
8.51
ve barrier

Provision of an Reinforced cement concrete crash barrier


at the edges of the road, approaches to bridge structures
and medians, constructed with Reinforced Cement
Concrete with fiber steel and as per details given IRC -5
A (Fig.-5, b) including dowel bars 25 mm dia, 450 mm long
at expansion joints filled with premoulded asphalt filler
board etc., as per approved drawing and at locations
directed by the Engineer, all as specified. (Area-0.243
Sqm. /Meter, Single Face)

Unit = Linear metre


Taking output = 20 m
(i) a) M 30 grade concrete
cum 4.860 10,310.00 50,106.60 Item No. -
M 30 grade concrete cum 4.860 10,310.00 50,106.60 12.11 A (iii)
cum 4.860 10,310.00 50,106.60 Case II
b) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
c) Material
Fiber Steel (35 Kg / Cum) tonne 0.170 0.170 0.170 46,496.54 7,904.41 7,904.41 7,904.41 M-143
d) Overhead charges @ 8% on @ 10% on @ 12% on
675.25 844.06 1,012.87
(b+c) (b+c) (b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
911.59 928.47 945.35
(b+c+d) (b+c+d) (b+c+d)

Cost for 20 metre = a+b+c+d+e 60,134.05 60,319.74 60,505.43


Rate per metre = (a+b+c+d+e)/20 3,006.70 3,015.99 3,025.27
Say 3,007.00 3,016.00 3,025.00

Provision of an Reinforced cement concrete crash barrier


at the edges of the road, approaches to bridge structures
and medians, constructed with Reinforced Cement
Concrete with fiber steel and as per details given IRC -5
B (Fig.-5, b) including dowel bars 25 mm dia, 450 mm long
at expansion joints filled with premoulded asphalt filler
board etc., as per approved drawing and at locations
directed by the Engineer, all as specified.(Area-0.261
Sqm. /Meter, Double Face)

Unit = Linear metre


Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
Taking output = 20 m
(i) a) M 30 grade concrete
cum 5.220 10,310.00 53,818.20 Item No. -
M 30 grade concrete cum 5.220 10,310.00 53,818.20 12.11 A (iii)
cum 5.220 10,310.00 53,818.20 Case II
b) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
c) Material
Fiber Steel (35 Kg / Cum) tonne 0.183 0.183 0.183 46,496.54 8,508.87 8,508.87 8,508.87 M-143
d) Overhead charges @ 8% on @ 10% on @ 12% on
723.61 904.51 1,085.41
(b+c) (b+c) (b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
976.87 994.96 1,013.05
(b+c+d) (b+c+d) (b+c+d)

Cost for 20 metre = a+b+c+d+e 64,563.74 64,762.73 64,961.72


Rate per metre = (a+b+c+d+e)/20 3,228.19 3,238.14 3,248.09
Say 3,228.00 3,238.00 3,248.00
CHAPTER-9
PIPE CULVERTS
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
9.01 304 Excavation for Structures
Earth work in excavation of foundation of structures as
per drawing and technical specification, including
setting out, construction of shoring and bracing,
removal of stumps and other deleterious matter,
dressing of sides and bottom and backfilling with
approved material.

I Ordinary soil
Unit = cum
Taking output = 10 cum
Manual Means
A (i) Depth upto 3 m
a) Labour
Mate day 0.140 0.140 0.140 617.00 86.38 86.38 86.38 L-12
Mazdoor day 3.500 3.500 3.500 511.52 1,790.32 1,790.32 1,790.32 L-13
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 187.670 187.670 187.670
b) Overhead charges @ 10% on
@ 8% on (a) @ 12% on (a) 150.14 187.67 225.20
(a)
c) Contractor's profit @ 10% on @ 10% on @ 10% on
202.68 206.44 210.19
(a+b) (a+b) (a+b)
Cost for 10 cum = a+b+c 2,229.52 2,270.81 2,312.09
Rate per cum = (a+b+c)/10 222.95 227.08 231.21
Say 223.00 227.00 231.00
Note
1. Cost of dewatering may be added where required
upto, 10 per cent of labour cost Assessment for
dewatering shall be made as per site conditions.

2.The excavated earth can be used partially for


backfilling of foundation pit and partly for road work
except for marshy soil. Hence cost of disposal has not
been added except for marshy soil. This remark is
common to all cases of item 12.1 excluding marshy
soil.

3.The cost of shoring and shuttering, where needed,


may be added @ 1 per cent on cost of excavation for
open foundation.
9.01 A (ii) Depth 3 m to 6 m
a) Labour
Mate/Supervisor day 0.180 0.180 0.180 617.00 111.06 111.06 111.06 L-12
Mazdoor day 4.500 4.500 4.500 511.52 2,301.84 2,301.84 2,301.84 L-13
b) Overhead charges @ 10% on
@ 8% on (a) @ 12% on (a) 193.03 241.29 289.55
(a)
c) Contractor's profit @ 10% on @ 10% on @ 10% on
260.59 265.42 270.24
(a+b) (a+b) (a+b)
Cost for 10 cum = a+b+c 2,866.53 2,919.61 2,972.69
Rate per cum = (a+b+c)/10 286.65 291.96 297.27
Say 287.00 292.00 297.00
Note Cost of dewatering may be added where required upto
15 per cent of labour cost. Assessment for dewatering
shall be done as per actual ground conditions.

9.01 A (iii) Depth above 6 m


a) Labour
Mate/Supervisor day 0.240 0.240 0.240 617.00 148.08 148.08 148.08 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
b) Overhead charges @ 10% on
@ 8% on (a) @ 12% on (a) 257.38 321.72 386.06
(a)
c) Contractor's profit @ 10% on @ 10% on @ 10% on
347.46 353.89 360.33
(a+b) (a+b) (a+b)
Cost for 10 cum = a+b+c 3,822.03 3,892.81 3,963.59
Rate per cum = (a+b+c)/10 382.20 389.28 396.36
Say 382.00 389.00 396.00
Note 1. Cost of dewatering may be added where required
upto 20 per cent of labour cost. Assessment for
dewatering shall be made as per site conditions..

9.01 B (i) Mechanical Means (Depth upto 3 m)


Unit = cum
Taking output = 330 cum
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Hydraulic Excavator
For excavation
(i) 1.2 cum bucket capacity hour 4.627 3,420.00 15,824.29 P&M-007
(ii) 1.1 cum bucket capacity hour 5.329 3,074.00 16,380.39 P&M-008
(iii) 0.9 cum bucket capacity hour 7.450 2,782.00 20,725.16 P&M-009
For backfilling (considering 60% of the excavated
material)
(i) 1.2 cum bucket capacity hour 2.776 3,420.00 9,494.57 P&M-007
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
(ii) 1.1 cum bucket capacity hour 3.197 3,074.00 9,828.23 P&M-008
(iii) 0.9 cum bucket capacity hour 4.470 2,782.00 12,435.10 P&M-009
Tipper for transportation of excess material to dumping
yard considering lead @ 1 km
(i) 18 cum capacity t-km 198.000 6.18 1,223.34 P&M-116
(ii) 14 cum capacity t-km 198.000 7.01 1,388.53 P&M-119
(iii) 10 cum capacity t-km 198.000 8.66 1,715.47 P&M-122
c) Overhead charges @ 8% on @ 10% on @ 12% on
2,466.54 3,188.68 4,699.84
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
3,329.83 3,507.54 4,386.52
(a+b+c) (a+b+c) (a+b+c)
Cost for 330 cum = a+b+c+d 36,628.18 38,582.97 48,251.69
Rate per cum = (a+b+c+d)/330 110.99 116.92 146.22
Say 111.00 117.00 146.00
9.01 B (ii) Mechanical Means (Depth 3 m to 6 m)
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Hydraulic Excavator
For excavation
(i) 1.2 cum bucket capacity hour 4.674 3,420.00 15,984.13 P&M-007
(ii) 1.1 cum bucket capacity hour 5.383 3,074.00 16,545.84 P&M-008
(iii) 0.9 cum bucket capacity hour 7.525 2,782.00 20,934.51 P&M-009
For backfilling (considering 60% of the excavated
material)
(i) 1.2 cum bucket capacity hour 2.804 3,420.00 9,590.48 P&M-007
(ii) 1.1 cum bucket capacity hour 3.230 3,074.00 9,927.51 P&M-008
(iii) 0.9 cum bucket capacity hour 4.515 2,782.00 12,560.71 P&M-009
Tipper for transportation of excess material to dumping
yard considering lead @ 1 km
(i) 18 cum capacity t-km 180.000 6.18 1,112.13 P&M-116
(ii) 14 cum capacity t-km 180.000 7.01 1,262.30 P&M-119
(iii) 10 cum capacity t-km 180.000 8.66 1,559.52 P&M-122

c) Overhead charges @ 8% on @ 10% on @ 12% on


2,478.11 3,202.53 4,721.32
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
3,345.44 3,522.78 4,406.57
(a+b+c) (a+b+c) (a+b+c)
Cost for 300 cum = a+b+c+d 36,799.88 38,750.56 48,472.22
Rate per cum = (a+b+c+d)/300 122.67 129.17 161.57
Say 123.00 129.00 162.00
9.01 B (iii) Mechanical Means (Depth above 6 m)
Unit = cum
Taking output = 270 cum
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Hydraulic Excavator
For excavation
(i) 1.2 cum bucket capacity hour 4.732 3,420.00 16,183.93 P&M-007
(ii) 1.1 cum bucket capacity hour 5.450 3,074.00 16,752.67 P&M-008
(iii) 0.9 cum bucket capacity hour 7.619 2,782.00 21,196.19 P&M-009
For backfilling (considering 60% of the excavated
material)
(i) 1.2 cum bucket capacity hour 2.839 3,420.00 9,710.36 P&M-007
(ii) 1.1 cum bucket capacity hour 3.270 3,074.00 10,051.60 P&M-008
(iii) 0.9 cum bucket capacity hour 4.571 2,782.00 12,717.71 P&M-009
Tipper for transportation of excess material to dumping
yard considering lead @ 1 km
(i) 18 cum capacity t-km 162.000 6.18 1,000.92 P&M-116
(ii) 14 cum capacity t-km 162.000 7.01 1,136.07 P&M-119
(iii) 10 cum capacity t-km 162.000 8.66 1,403.57 P&M-122
c) Overhead charges @ 8% on @ 10% on @ 12% on
2,494.78 3,222.99 4,752.85
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
3,367.96 3,545.29 4,435.99
(a+b+c) (a+b+c) (a+b+c)
Cost for 270 cum = a+b+c+d 37,047.55 38,998.23 48,795.91
Rate per cum = (a+b+c+d)/270 137.21 144.44 180.73
Say 137.00 144.00 181.00
9.01 II Ordinary Rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 5.000 5.000 5.000 511.52 2,557.60 2,557.60 2,557.60 L-13
b) Overhead charges @ 10% on
@ 8% on (a) @ 12% on (a) 214.48 268.10 321.72
(a)
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
c) Contractor's profit @ 10% on @ 10% on @ 10% on
289.55 294.91 300.27
(a+b) (a+b) (a+b)
Cost for 10 cum = a+b+c 3,185.03 3,244.01 3,302.99
Rate per cum = (a+b+c)/10 318.50 324.40 330.30
Say 319.00 324.00 330.00
Note Cost of dewatering upto 10 per cent of labour cost
may be added, where required. Assessment for
dewatering shall be made as per site conditions..

9.01 B Mechanical Means


Unit = cum
Taking output = 50 cum
a) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Machinery
Hydraulic Excavator
Excavator for excavation
(i) 1.2 cum bucket capacity hour 5.818 3,420.00 19,897.56 P&M-007
(ii) 1.1 cum bucket capacity hour 6.845 3,074.00 21,041.53 P&M-008
(iii) 0.9 cum bucket capacity hour 7.273 2,782.00 20,233.49 P&M-009
For loading
(i) 1.2 cum bucket capacity hour 0.872 3,420.00 2,982.24 P&M-007
(ii) 1.1 cum bucket capacity hour 1.005 3,074.00 3,089.37 P&M-008
(iii) 0.9 cum bucket capacity hour 1.405 2,782.00 3,908.71 P&M-009
Jack Hammer hour 5.818 6.845 7.273 206.00 1,198.51 1,410.07 1,498.24 P&M-010
Tipper
For transportation considering lead @ 1km
(i) 18 cum capacity t-km 75.000 6.18 463.39 P&M-116
(ii) 14 cum capacity t-km 75.000 7.01 525.96 P&M-119
(iii) 10 cum capacity t-km 75.000 8.66 649.80 P&M-122
For loading & unloading time
(i) 18 cum capacity hour 0.872 2,883.30 2,514.24 P&M-014
(ii) 14 cum capacity hour 1.005 2,556.75 2,569.53 P&M-015
(iii) 10 cum capacity hour 1.405 2,274.30 3,195.39 P&M-016
c) Overhead charges @ 8% on @ 10% on @ 12% on
2,293.16 3,024.51 3,731.31
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
3,095.77 3,326.96 3,482.55
(a+b+c) (a+b+c) (a+b+c)
Cost for 50 cum = a+b+c+d 34,053.47 36,596.53 38,308.09
Rate per cum = (a+b+c+d)/50 681.07 731.93 766.16
Say 681.00 732.00 766.00
9.01 301 & 302 III Hard Rock ( requiring blasting )
A Manual Means
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.350 0.350 0.350 617.00 215.95 215.95 215.95 L-12
Driller day 0.500 0.500 0.500 558.00 279.00 279.00 279.00 L-06
Blaster day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-03
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Air Compressor 250 cfm with 2 jack hammer for drilling. P&M-
15001+
hour 1.000 1.000 1.000 625.80 625.80 625.80 625.80 P&M-45001

c) Material
Explosives (Blasting Material) kg 3.500 3.500 3.500 81.90 286.65 286.65 286.65 M-215
Detonator electric each 14.000 14.000 14.000 21.00 294.00 294.00 294.00 M-217
d) Overhead charges @ 8% on @ 10% on @ 12% on
473.72 592.14 710.57
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
639.52 651.36 663.20
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10 cum = a+b+c+d+e 7,034.67 7,164.94 7,295.21
Rate per cum = (a+b+c+d+e)/10 703.47 716.49 729.52
Say 703.00 716.00 730.00
Note Cost of dewatering @ 10 per cent of (a+b) may be
added, where required Assessment for dewatering
shall be made as per site conditions.
9.01 301 & 302 III Hard Rock ( requiring blasting )
Carrying out excavation in hard rock to achieve a
specified slope of the rock face by controlled use of
explosives and blasting accessories in properly aligned
and spaced drill holes, collection of the excavated rock
by a dozer, loading in tipper by a front end loader and
disposing of the material with all lifts and lead upto
1000 m, all as specified in clause No. 303

B Mechanical Means
Unit = cum
Taking output = 120 cum
a) Labour
Mate day 0.210 0.210 0.210 617.00 129.57 129.57 129.57 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Driller day 2.000 2.000 2.000 558.00 1,116.00 1,116.00 1,116.00 L-06
Blaster day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-03
b) Machinery
Air compressor hour 6.000 6.000 6.000 614.25 3,685.50 3,685.50 3,685.50 P&M-029
Jack Hammer for drilling holes (@ 4.5 m per hour) P&M-078
hour 24.000 24.000 24.000 11.55 277.20 277.20 277.20
Jack Hammer (consider 5% of the volume for dressing) P&M-010
hour 1.024 1.024 1.024 206.00 210.94 210.94 210.94
Hydraulic Excavator
Excavator for excavation
(i) 1.2 cum bucket capacity hour 1.024 3,420.00 3,502.08 P&M-007
(ii) 1.1 cum bucket capacity hour 1.024 3,074.00 3,147.78 P&M-008
(iii) 0.9 cum bucket capacity hour 1.024 2,782.00 2,848.77 P&M-009
For loading
(i) 1.2 cum bucket capacity hour 2.094 3,420.00 7,160.89 P&M-007
(ii) 1.1 cum bucket capacity hour 2.411 3,074.00 7,412.54 P&M-008
(iii) 0.9 cum bucket capacity hour 3.371 2,782.00 9,378.66 P&M-009
Tipper
For transportation considering lead @ 1 km
(i) 18 cum capacity t-km 180.000 7.51 1,351.55 P&M-117
(ii) 14 cum capacity t-km 180.000 8.52 1,534.05 P&M-120
(iii) 10 cum capacity t-km 180.000 10.53 1,895.25 P&M-123
For loading & unloading time
(i) 18 cum capacity hour 2.094 2,883.30 6,037.13 P&M-014
(ii) 14 cum capacity hour 2.411 2,556.75 6,165.26 P&M-015
(iii) 10 cum capacity hour 3.371 2,274.30 7,667.11 P&M-016
c) Materials
Small dia.Explosive at 0.40 kg / cum for 120 cum ( 120 M-215
x 0.40 )
Explosive at 0.20 kg / cum for secondary blast @ 5%of kg 48.000 48.000 48.000 81.90 3,931.20 3,931.20 3,931.20
the total volume ( 120 x 0.2x5% )
Electric detonators at 1 per hole for main blast holes M-217
(21x3+20*2)=103 nos no 69.000 69.000 69.000 21.00 1,449.00 1,449.00 1,449.00
Ordinary detonators @ 1 per hole for 10 secondary M-216
holes( required for 5% of the total quantity @ 0.6 m per no 7.000 7.000 7.000 21.00 147.00 147.00 147.00
hole for I cum )
Detonating fuse coil m 213.000 213.000 213.000 19.00 4,047.00 4,047.00 4,047.00 M-218
d) Overhead charges @ 8% on @ 10% on @ 12% on
2,776.60 3,491.55 4,613.48
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
3,748.41 3,840.70 4,305.91
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 120 cum = a+b+c+d+e 41,232.51 42,247.73 47,365.03
Rate per cum = (a+b+c+d+e)/120 343.60 352.06 394.71
Say 344.00 352.00 395.00

9.01 IV Hard Rock ( blasting prohibited )


Unit = cum
Taking output = 35 cum
A Mechanical Means
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Jack Hammer hour 5.973 7.467 9.190 206.00 1,230.51 1,538.13 1,893.09 P&M-010
Hydraulic Excavator
Excavator for excavation
(i) 1.2 cum bucket capacity hour 5.973 3,420.00 20,428.80 P&M-007
(ii) 1.1 cum bucket capacity hour 7.467 3,074.00 22,952.53 P&M-008
(iii) 0.9 cum bucket capacity hour 9.190 2,782.00 25,565.87 P&M-009
For loading
(i) 1.2 cum bucket capacity hour 0.611 3,420.00 2,088.59 P&M-007
(ii) 1.1 cum bucket capacity hour 0.703 3,074.00 2,161.99 P&M-008
(iii) 0.9 cum bucket capacity hour 0.983 2,782.00 2,735.44 P&M-009
Tipper
For transportation to dumping yard considering lead @
1km
(i) 18 cum capacity t-km 52.500 6.18 324.37 P&M-116
(ii) 14 cum capacity t-km 52.500 7.01 368.17 P&M-119
(iii) 10 cum capacity t-km 52.500 8.66 454.86 P&M-122
For loading & unloading time
(i) 18 cum capacity hour 0.611 2,883.30 1,760.83 P&M-014
(ii) 14 cum capacity hour 0.703 2,556.75 1,798.20 P&M-015
(iii) 10 cum capacity hour 0.983 2,274.30 2,236.24 P&M-016

c) Overhead charges @ 8% on @ 10% on @ 12% on


2,152.44 2,989.14 4,074.95
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
2,905.79 3,288.06 3,803.28
(a+b+c) (a+b+c) (a+b+c)
Cost for 35 cum = a+b+c+d 31,963.73 36,168.63 41,836.13
Rate per cum = (a+b+c+d)/35 913.25 1,033.39 1,195.32
Say 913.00 1,033.00 1,195.00
9.01 V Marshy Soil
Unit = cum
Taking output = 10 cum
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Depth upto 3 m
A Manual means
a) Labour
Mate/Supervisor day 0.400 0.400 0.400 617.00 246.80 246.80 246.80 L-12
Mazdoor day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-13
b) Machinery
Tractor-trolley for removal. hour 2.670 2.670 2.670 1,876.50 5,010.26 5,010.26 5,010.26 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
829.78 1,037.23 1,244.67
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,120.20 1,140.95 1,161.69
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 cum = a+b+c+d 12,322.24 12,550.43 12,778.62
Rate per cum = ( a+b+c+d)/ 10 1,232.22 1,255.04 1,277.86
Say 1,232.00 1,255.00 1,278.00
Note 1. Cost of dewatering @ 30 per cent of (a), may be
added, where required Assessment for dewatering
shall be made as per site conditions.
2. Shoring & strutting 15 per cent of (a), where
required may be added
3. It is assumed that Marshy Soil will be available upto
3 m depth only. For deeper excavation below 3 m
depth, refer analysis in item12.1 (i) to (iv) for ordinary
soil
9.01 B Mechanical Means
Unit = cum
Taking output = 260 cum
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 8.506 3,420.00 29,091.11 P&M-007
(ii) 1.1 cum bucket capacity hour 9.796 3,074.00 30,113.44 P&M-008
(iii) 0.9 cum bucket capacity hour 13.695 2,782.00 38,100.81 P&M-009
Tipper
For transportation to dumping yard considering lead @
1km
(i) 18 cum capacity t-km 390.000 6.18 2,409.62 P&M-116
(ii) 14 cum capacity t-km 390.000 7.01 2,734.99 P&M-119
(iii) 10 cum capacity t-km 390.000 8.66 3,378.96 P&M-122
For loading & unloading time
(i) 18 cum capacity hour 8.506 2,883.30 24,525.85 P&M-014
(ii) 14 cum capacity hour 9.796 2,556.75 25,046.37 P&M-015
(iii) 10 cum capacity hour 13.695 2,274.30 31,147.61 P&M-016
c) Material
Selected earth for refilling cum 156.000 156.000 156.000 222.00 34,632.00 34,632.00 34,632.00 M-164
d) Overhead charges @ 8% on @ 10% on @ 12% on
7,295.58 9,306.30 12,935.47
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
9,849.04 10,236.93 12,073.11
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 260 cum = a+b+c+d 108,339.39 112,606.22 132,804.16
Rate per cum = (a+b+c+d)/260 416.69 433.10 510.79
Say 417.00 433.00 511.00
9.02 304 Sand Filling in Foundation Trenches as per Drawing &
Technical Specification
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading @ 30 mins per trip )

(i) 16 KL capacity 0.125xL1+0.1 P&M-023


hour 1,501.00 5,868.91
6
(ii) 12 KL capacity 0.167xL1+0.2 P&M-024
hour 1,327.00 6,930.92
13
(iii) 6 KL capacity 0.333xL1+0.4 P&M-025
hour 1,005.00 10,469.09
27
c) Material
Sand (assuming 20 per cent voids) at site cum 120.000 120.000 120.000 1,994.03 239,283.72 239,283.72 239,283.72 M-004
Water KL 18.000 18.000 18.000 16.00 288.00 288.00 288.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
19,678.15 24,703.88 30,069.24
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
26,565.50 27,174.27 28,064.62
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per 100 cum = a+b+c+d+e 292,220.47 298,917.00 308,710.87
Rate per cum = (a+b+c+d+e)/100 2,922.20 2,989.17 3,087.11
Say 2,922.00 2,989.00 3,087.00
9.03 2100 PCC 1:3:6 in Foundation
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Plain cement concrete 1:3:6 nominal mix in foundation
with crushed stone aggregate 40 mm nominal size
mechanically mixed, placed in foundation and
compacted by vibration including curing for 14 days.

Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mason day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-10
Mazdoor day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
b) Material
Plain cement concrete 1:3:6 nominal mix using Sub-
batching plant (Rate as sub-analysis) Analysis of
cum 15.000 15.000 15.000 4,238.00 63,570.00 63,570.00 63,570.00 Concrete -
20.02
Water KL 3.240 3.240 3.240 16.00 51.84 51.84 51.84 M-191
c) Machinery
Plate Compactor hour 1.000 1.000 1.000 597.45 597.45 597.45 597.45 P&M-079
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading @ 30 mins per trip )

(i) 16 KL capacity hour 0.825 1,501.00 1,238.33 P&M-023


(ii) 12 KL capacity hour 1.080 1,327.00 1,433.16 P&M-024
(iii) 6 KL capacity hour 2.160 1,005.00 2,170.80 P&M-025
d) Overhead charges @ 8% on @ 10% on @ 12% on
5,593.18 7,010.95 8,501.66
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
7,550.79 7,712.05 7,934.88
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 15 cum = a+b+c+d+e 83,058.66 84,832.53 87,283.71
Rate per cum = (a+b+c+d+e)/15 5,537.24 5,655.50 5,818.91
Say 5,537.00 5,656.00 5,819.00
Note Vibrator is a part of minor T & P which is already
included in overhead charges of the contractor.
9.04 2900 Laying Reinforced Cement Concrete Pipe NP4 /
Prestressed Concrete Pipe on First Class Bedding in
Single Row .
Laying Reinforced cement concrete pipe
NP4/prestressed concrete pipe for culverts on first
class bedding of granular material in single row
including fixing collar with cement mortar 1:2 but
excluding excavation, protection works, backfilling,
concrete and masonry works in head walls and
parapets .

Unit = metre
Taking output = 12.5 metres ( 5 pipes of 2.5 m length
each )
A 1000 mm dia
a) Labour
Mate day 0.100 0.100 0.100 617.00 61.70 61.70 61.70 L-12
Mason day 0.500 0.500 0.500 679.00 339.50 339.50 339.50 L-10
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Material
Sand at site cum 0.070 0.070 0.070 1,994.03 139.58 139.58 139.58 M-005
Cement at site tonne 0.050 0.050 0.050 4,940.00 247.00 247.00 247.00 M-081
RCC pipe NP-4 /prestressed concrete pipe including M-148
collar at site metre 12.500 12.500 12.500 5,925.00 74,062.50 74,062.50 74,062.50
Granular material passing 5.6 mm sieve for bedding M-009
cum 4.500 4.500 4.500 1,887.12 8,492.05 8,492.05 8,492.05
c) Machinery
Light Crane 3 tonnes capacity for placing of Hume P&M-102
pipe hour 2.083 2.083 2.083 1,083.60 2,257.50 2,257.50 2,257.50
d) Overhead charges @ 8% on @ 10% on @ 12% on
6,929.83 8,662.29 10,394.75
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
9,355.27 9,528.52 9,701.76
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 12.5 metres = a+b+c+d 102,907.98 104,813.68 106,719.38
Rate per metre = (a+b+c+d)/12.5 8,232.64 8,385.09 8,537.55
Say 8,233.00 8,385.00 8,538.00
Note 1. In case of cement craddle bedding, quantity of PCC
M15 is to be calculated as per design and priced
separately and added .
2. The rate analysis does not include excavation,
cement /masonry works in head walls, backfilling,
protection works and parapet walls. The same are to
be calculated as per approved design and drawings
and priced separately on rates available under
respective sections

9.04 B 1200 mm dia


a) Labour
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Mason day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-10
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Material
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Sand at site cum 0.090 0.090 0.090 1,994.03 179.46 179.46 179.46 M-005
Cement at site tonne 0.070 0.070 0.070 4,940.00 345.80 345.80 345.80 M-081
RCC pipe NP-4/prestressed concrete pipe including M-149
collar at site metre 12.500 12.500 12.500 6,547.00 81,837.50 81,837.50 81,837.50
Granular material passing 5-6 mm sieve for class M-009
bedding cum 5.000 5.000 5.000 1,887.12 9,435.62 9,435.62 9,435.62
c) Machinery
Light Crane 3 tonnes capacity for handling Hume pipe P&M-102
hour 2.083 2.083 2.083 1,083.60 2,257.50 2,257.50 2,257.50
d) Overhead charges @ 8% on @ 10% on @ 12% on
7,709.45 9,636.82 11,564.18
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
10,407.76 10,600.50 10,793.23
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 12.5 metres = a+b+c+d 114,485.37 116,605.47 118,725.57
Rate per metre= (a+b+c+d)/12.5 9,158.83 9,328.44 9,498.05
Say 9,159.00 9,328.00 9,498.00
Note 1. In case of cement craddle bedding, quantity of PCC
M15 is to be calculated as per design and priced
separately and added .
2. The rate analysis does not include excavation,
cement /masonry works in head walls, backfilling,
protection works and parapet walls. The same are to
be calculated as per approved design and drawings
and priced separately on rates available under
respective sections

9.04 C 1500 mm dia


a) Labour
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Mason day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-10
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Material
Sand at site cum 0.090 0.090 0.090 1,994.03 179.46 179.46 179.46 M-005
Cement at site tonne 0.070 0.070 0.070 4,940.00 345.80 345.80 345.80 M-081
RCC pipe NP-4/prestressed concrete pipe including M-149
collar at site metre 12.500 12.500 12.500 7,800.00 97,500.00 97,500.00 97,500.00
Granular material passing 5-6 mm sieve for class M-009
bedding cum 5.750 5.750 5.750 1,887.12 10,850.96 10,850.96 10,850.96
c) Machinery
Light Crane 3 tonnes capacity for handling Hume pipe P&M-102
hour 2.500 2.500 2.500 1,083.60 2,709.00 2,709.00 2,709.00
d) Overhead charges @ 8% on @ 10% on @ 12% on
9,111.80 11,389.75 13,667.70
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
9,840.74 12,528.73 15,307.82
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 12.5 metres = a+b+c+d 132,850.04 137,815.98 142,873.02
Rate per metre= (a+b+c+d)/12.5 10,628.00 11,025.28 11,429.84
Say 10,628.00 11,025.00 11,430.00
Note 1. In case of cement craddle bedding, quantity of PCC
M15 is to be calculated as per design and priced
separately and added .
2. The rate analysis does not include excavation,
cement /masonry works in head walls, backfilling,
protection works and parapet walls. The same are to
be calculated as per approved design and drawings
and priced separately on rates available under
respective sections

9.05 2900 Laying Reinforced Cement Concrete Pipe NP4 /


Prestressed Concrete Pipe on First Class Bedding in
Double Row .
Laying Reinforced cement concrete pipe NP4 /
prestressed concrete pipe for culverts on first class
bedding of granular material in double row including
fixing collar with cement mortar 1:2 but excluding
excavation, protection works, backfilling, concrete and
masonry works in head walls and parapets .

Unit = metre
Taking output = 12.5 metres ( 10 pipes of 2.5 m length
each in two rows.)
A 1000 mm dia
a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mason day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-10
Mazdoor day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
b) Material
Sand at site cum 0.140 0.140 0.140 1,994.03 279.16 279.16 279.16 M-005
Cement at site tonne 0.100 0.100 0.100 4,940.00 494.00 494.00 494.00 M-081
RCC pipe NP-4/prestressed concrete pipe including M-148
collar at site metre 25.000 25.000 25.000 5,925.00 148,125.00 148,125.00 148,125.00
Granular material passing 5.6 mm sieve for bedding M-009
cum 12.500 12.500 12.500 1,887.12 23,589.04 23,589.04 23,589.04
c) Machinery
Light Crane 3 tonnes capacity for handling Hume pipe P&M-102
hour 4.167 4.167 4.167 1,083.60 4,515.00 4,515.00 4,515.00
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
d) Overhead charges @ 8% on @ 10% on @ 12% on
14,388.05 17,985.07 21,582.08
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
19,423.87 19,783.58 20,143.28
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 12.5 metres = a+b+c+d 213,662.61 217,619.33 221,576.04
Rate per metre = (a+b+c+d)/12.5 17,093.01 17,409.55 17,726.08
Say 17,093.00 17,410.00 17,726.00
Note 1. In case of cement craddle bedding, quantity of PCC
M15 is to be calculated as per design and priced
separately and added .
2. The rate analysis does not include excavation,
cement /masonry works in head walls, backfilling,
protection works and parapet walls. The same are to
be calculated as per approved design and drawings
and priced separately on rates available under
respective sections

9.05 B 1200 mm dia


a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mason day 2.000 2.000 2.000 679.00 1,358.00 1,358.00 1,358.00 L-10
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
b) Material
Sand at site cum 0.180 0.180 0.180 1,994.03 358.93 358.93 358.93 M-005
Cement at site tonne 0.140 0.140 0.140 4,940.00 691.60 691.60 691.60 M-081
RCC pipe NP-4 /prestressed concrete pipe including M-149
collar at site metre 25.000 25.000 25.000 6,547.00 163,675.00 163,675.00 163,675.00
Granular material passing 5-6 mm sieve for class M-009
bedding cum 13.750 13.750 13.750 1,887.12 25,947.94 25,947.94 25,947.94
c) Machinery
Light Crane 3 tonnes capacity for handling Hume pipe P&M-102
hour 4.167 4.167 4.167 1,083.60 4,515.00 4,515.00 4,515.00
d) Overhead charges @ 8% on @ 10% on @ 12% on
15,985.04 19,981.30 23,977.56
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
21,579.81 21,979.43 22,379.06
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 12.5 metres = a+b+c+d 237,377.88 241,773.76 246,169.65
Rate per metre= (a+b+c+d)/12.5 18,990.23 19,341.90 19,693.57
Note 1. In case of cement craddle bedding, quantity of PCC
M15 is to be calculated as per design and priced Say 18,990.00 19,342.00 19,694.00
separately and added .
2. The rate analysis does not include excavation,
cement /masonry works in head walls, backfilling,
protection works and parapet walls. The same are to
be calculated as per approved design and drawings
and priced separately on rates available under
respective sections

9.05 C 1500 mm dia


a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mason day 2.000 2.000 2.000 679.00 1,358.00 1,358.00 1,358.00 L-10
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
b) Material
Sand at site cum 0.180 0.180 0.180 1,994.03 358.93 358.93 358.93 M-005
Cement at site tonne 0.140 0.140 0.140 4,940.00 691.60 691.60 691.60 M-081
RCC pipe NP-4 /prestressed concrete pipe including M-149
collar at site metre 25.000 25.000 25.000 7,800.00 195,000.00 195,000.00 195,000.00
Granular material passing 5-6 mm sieve for class M-009
bedding cum 15.625 15.625 15.625 1,887.12 29,486.30 29,486.30 29,486.30
c) Machinery
Light Crane 3 tonnes capacity for handling Hume pipe P&M-102
hour 5.000 5.000 5.000 1,083.60 5,418.00 5,418.00 5,418.00
d) Overhead charges @ 8% on @ 10% on @ 12% on
18,846.35 23,557.94 28,269.53
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
25,442.57 25,913.73 26,384.89
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 12.5 metres = a+b+c+d 279,868.31 285,051.05 290,233.80
Rate per metre= (a+b+c+d)/12.5 22,389.46 22,804.08 23,218.70
Say 22,389.00 22,804.00 23,219.00
Note 1. In case of cement craddle bedding, quantity of PCC
M15 is to be calculated as per design and priced
separately and added .
2. The rate analysis does not include excavation,
cement /masonry works in head walls, backfilling,
protection works and parapet walls. The same are to
be calculated as per approved design and drawings
and priced separately on rates available under
respective sections

9.06 1500, 1700 Plain/Reinforced Cement Concrete in Open Foundation


& 2100 complete as per Drawing and Technical Specifications.

A PCC Grade M15


Case I PCC Grade M15 using batching plant & Concrete
pump
Unit = cum
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis) Sub-
Analysis of
cum 30.000 30.000 30.000 4,176.00 125,280.00 125,280.00 125,280.00 Concrete -
20.03
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne- P&M-128
75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.694 0.694 2,413.95 1,569.07 1,676.35 1,676.35 P&M-067
Hydraulic Boom placer pump hour 0.650 0.694 0.694 4,401.60 2,861.04 3,056.67 3,056.67 P&M-069
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.6 P&M-023
hour 1,501.00 5,892.93
56
(ii) 12 KL capacity 0.146xL1+0.8 P&M-024
hour 1,327.00 6,973.39
75
(iii) 6 KL capacity 0.292xL1+1.7 P&M-025
hour 1,005.00 10,562.55
5
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 5594.000 5640.000 5759.000

d) Formwork @ 10 per cent on cost of concrete i.e.


16,779.54 16,917.88 17,276.79
cost of material, labour and machinery
e) Overhead charges @ 8% on @ 10% on @ 12% on
14,765.99 18,609.66 22,805.37
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
19,934.09 20,470.63 21,285.01
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 30 cum = a+b+c+d+e+f 219,275.02 225,176.94 234,135.10


Rate per cum = (a+b+c+d+e+f)/30 7,309.17 7,505.90 7,804.50
Say 7,309.00 7,506.00 7,805.00
Case II PCC Grade M15 using batching plant & manual placing

Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis) Sub-
Analysis of
cum 15.000 15.000 15.000 4,176.00 62,640.00 62,640.00 62,640.00 Concrete -
20.03
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne- P&M-128
37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19
km
For unloading hour 0.833 0.833 0.833 2,413.95 2,010.82 2,010.82 2,010.82 P&M-067
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.055xL1+0.3 P&M-023
hour 1,501.00 2,968.98
28
(ii) 12 KL capacity 0.073xL1+0.4 P&M-024
hour 1,327.00 3,487.36
38
(iii) 6 KL capacity 0.146xL1+0.8 P&M-025
hour 1,005.00 5,281.28
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 5879.000 5914.000 6033.000
d) Formwork @ 10 per cent on cost of concrete i.e.
cost of material, labour and machinery 8,817.81 8,869.65 9,049.04

e) Overhead charges @ 8% on @ 10% on @ 12% on


7,759.67 9,756.61 11,944.73
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
10,475.56 10,732.27 11,148.42
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 15 cum = a+b+c+d+e+f 115,231.15 118,055.02 122,632.59


Rate per cum = (a+b+c+d+e+f)/15 7,682.08 7,870.33 8,175.51
Say 7,682.00 7,870.00 8,176.00
9.06 B PCC Grade M20
Case I PCC Grade M20 using batching plant transit mixer &
Concrete pump
Unit = cum
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis) Sub-
Analysis of
cum 30.000 30.000 30.000 4,518.00 135,540.00 135,540.00 135,540.00 Concrete -
20.04
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.87 677.87 677.87 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne- P&M-128
75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.6 P&M-023
hour 1,501.00 5,892.93
56
(ii) 12 KL capacity 0.146xL1+0.8 P&M-024
hour 1,327.00 6,973.39
75
(iii) 6 KL capacity 0.292xL1+1.7 P&M-025
hour 1,005.00 10,562.55
5
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 5936.000 5972.000 6091.000
d) Formwork @ 10 per cent on cost of concrete i.e.
cost of material, labour and machinery 17,805.55 17,913.60 18,272.51

e) Overhead charges @ 8% on @ 10% on @ 12% on


15,668.88 19,704.96 24,119.72
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
21,152.99 21,675.45 22,511.73
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 30 cum = a+b+c+d+e+f 232,682.92 238,429.96 247,629.08


Rate per cum = (a+b+c+d+e+f)/30 7,756.10 7,947.67 8,254.30
Say 7,756.00 7,948.00 8,254.00
Case II PCC Grade M20 using batching plant transit mixer &
manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis) Sub-
Analysis of
cum 15.000 15.000 15.000 4,518.00 67,770.00 67,770.00 67,770.00 Concrete -
20.04
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne- P&M-128
37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19
km
For unloading hour 0.833 0.833 0.833 2,413.95 2,010.82 2,010.82 2,010.82 P&M-067
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.055xL1+0.3 P&M-023
hour 1,501.00 2,968.98
28
(ii) 12 KL capacity 0.073xL1+0.4 P&M-024
hour 1,327.00 3,487.36
38
(iii) 6 KL capacity 0.146xL1+0.8 P&M-025
hour 1,005.00 5,281.28
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6221.000 6256.000 6375.000
d) Formwork @ 10 per cent on cost of concrete i.e.
cost of material, labour and machinery 9,330.81 9,382.65 9,562.04

e) Overhead charges @ 8% on @ 10% on @ 12% on


8,211.11 10,320.91 12,621.89
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
11,085.00 11,353.00 11,780.43
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 15 cum = a+b+c+d+e+f 121,935.03 124,883.05 129,584.77


Rate per cum = (a+b+c+d+e+f)/15 8,129.00 8,325.54 8,638.98
Say 8,129.00 8,326.00 8,639.00
9.06 C RCC Grade M20
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Case I RCC Grade M20 using batching plant transit mixer &
Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis) Sub-
Analysis of
cum 30.000 30.000 30.000 4,533.00 135,990.00 135,990.00 135,990.00 Concrete -
20.05
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne- P&M-128
75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.6 P&M-023
hour 1,501.00 5,892.93
56
(ii) 12 KL capacity 0.146xL1+0.8 P&M-024
hour 1,327.00 6,973.39
75
(iii) 6 KL capacity 0.292xL1+1.7 P&M-025
hour 1,005.00 10,562.55
5
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 5969.000 6005.000 6124.000
d) Formwork @ 10 per cent on cost of concrete i.e.
cost of material, labour and machinery 17,904.16 18,012.21 18,371.12

e) Overhead charges @ 8% on @ 10% on @ 12% on


15,755.66 19,813.43 24,249.88
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
21,270.14 21,794.77 22,633.22
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 30 cum = a+b+c+d+e+f 233,971.55 239,742.45 248,965.44


Rate per cum = (a+b+c+d+e+f)/30 7,799.05 7,991.42 8,298.85
Say 7,799.00 7,991.00 8,299.00
Case II RCC Grade M20 using batching plant transit mixer &
manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis) Sub-
Analysis of
cum 15.000 15.000 15.000 4,533.00 67,995.00 67,995.00 67,995.00 Concrete -
20.05
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.420 0.420 0.420 617.00 259.14 259.14 259.14 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne- P&M-128
37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19
km
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.055xL1+0.3 P&M-023
hour 1,501.00 2,968.98
28
(ii) 12 KL capacity 0.073xL1+0.4 P&M-024
hour 1,327.00 3,487.36
38
(iii) 6 KL capacity 0.146xL1+0.8 P&M-025
hour 1,005.00 5,281.28
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6272.000 6306.000 6426.000
d) Formwork @ 10 per cent on cost of concrete i.e.
cost of material, labour and machinery 9,407.01 9,458.85 9,638.24

e) Overhead charges @ 8% on @ 10% on @ 12% on


8,278.17 10,404.73 12,722.48
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
11,175.53 11,445.21 11,874.31
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 15 cum = a+b+c+d+e+f 122,930.82 125,897.28 130,617.44


Rate per cum = (a+b+c+d+e+f)/15 8,195.39 8,393.15 8,707.83
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Say 8,195.00 8,393.00 8,708.00
9.06 D PCC Grade M25
Case I PCC Grade M25 using batching plant transit mixer &
Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis) Sub-
Analysis of
cum 30.000 30.000 30.000 4,793.00 143,790.00 143,790.00 143,790.00 Concrete -
20.06
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-11
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne- P&M-128
75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.6 P&M-023
hour 1,501.00 5,892.93
56
(ii) 12 KL capacity 0.146xL1+0.8 P&M-024
hour 1,327.00 6,973.39
75
(iii) 6 KL capacity 0.292xL1+1.7 P&M-025
hour 1,005.00 10,562.55
5
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6214.000 6250.000 6369.000
d) Formwork @ 10 per cent on cost of concrete i.e.
cost of material, labour and machinery 18,639.39 18,747.44 19,106.35

e) Overhead charges @ 8% on @ 10% on @ 12% on


16,402.66 20,622.18 25,220.38
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
22,143.59 22,684.40 23,539.03
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 30 cum = a+b+c+d+e+f 243,579.54 249,528.36 258,929.28


Rate per cum = (a+b+c+d+e+f)/30 8,119.32 8,317.61 8,630.98
Say 8,119.00 8,318.00 8,631.00
Case II PCC Grade M25 using batching plant transit mixer &
manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis) Sub-
Analysis of
cum 15.000 15.000 15.000 4,793.00 71,895.00 71,895.00 71,895.00 Concrete -
20.06
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne- P&M-128
37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19
km
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.055xL1+0.3 P&M-023
hour 1,501.00 2,968.98
28
(ii) 12 KL capacity 0.073xL1+0.4 P&M-024
hour 1,327.00 3,487.36
38
(iii) 6 KL capacity 0.146xL1+0.8 P&M-025
hour 1,005.00 5,281.28
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6496.000 6531.000 6650.000
d) Formwork @ 10 per cent on cost of concrete i.e.
cost of material, labour and machinery 9,743.39 9,795.23 9,974.62

e) Overhead charges @ 8% on @ 10% on @ 12% on


8,574.18 10,774.75 13,166.50
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
11,575.15 11,852.23 12,288.73
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Cost for 15 cum = a+b+c+d+e+f 127,326.63 130,374.50 135,176.06
Rate per cum = (a+b+c+d+e+f)/15 8,488.44 8,691.63 9,011.74
Say 8,488.00 8,692.00 9,012.00
9.06 E RCC Grade M25
Case I RCC Grade M25 using batching plant transit mixer &
Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis) Sub-
Analysis of
cum 30.000 30.000 30.000 4,945.00 148,350.00 148,350.00 148,350.00 Concrete -
20.07
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne- P&M-128
75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.6 P&M-023
hour 1,501.00 5,892.93
56
(ii) 12 KL capacity 0.146xL1+0.8 P&M-024
hour 1,327.00 6,973.39
75
(iii) 6 KL capacity 0.292xL1+1.7 P&M-025
hour 1,005.00 10,562.55
5
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6381.000 6417.000 6536.000
d) Formwork @ 10 per cent on cost of concrete i.e.
cost of material, labour and machinery 19,140.16 19,248.21 19,607.12

e) Overhead charges @ 8% on @ 10% on @ 12% on


16,843.34 21,173.03 25,881.40
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
22,738.51 23,290.33 24,155.97
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 30 cum = a+b+c+d+e+f 250,123.60 256,193.61 265,715.71


Rate per cum = (a+b+c+d+e+f)/30 8,337.45 8,539.79 8,857.19
Say 8,337.00 8,540.00 8,857.00
Case II RCC Grade M25 using batching plant transit mixer &
manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis) Sub-
Analysis of
cum 15.000 15.000 15.000 4,945.00 74,175.00 74,175.00 74,175.00 Concrete -
20.07
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.420 0.420 0.420 617.00 259.14 259.14 259.14 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne- P&M-128
37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19
km
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.055xL1+0.3 P&M-023
hour 1,501.00 2,968.98
28
(ii) 12 KL capacity 0.073xL1+0.4 P&M-024
hour 1,327.00 3,487.36
38
(iii) 6 KL capacity 0.146xL1+0.8 P&M-025
hour 1,005.00 5,281.28
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 7352.000 7390.000 7522.000
d) Formwork @ 10 per cent on cost of concrete i.e.
cost of material, labour and machinery 10,025.01 10,076.85 10,256.24

e) Overhead charges @ 8% on @ 10% on @ 12% on


8,822.01 11,084.53 13,538.24
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
11,909.71 12,192.99 12,635.69
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 15 cum = a+b+c+d+e+f 131,006.84 134,122.86 138,992.57


Rate per cum = (a+b+c+d+e+f)/15 8,733.79 8,941.52 9,266.17
Say 8,734.00 8,942.00 9,266.00
9.07 1600 Supplying, Fitting and Placing un-coated HYSD bar
Reinforcement in Foundation complete as per Drawing
and Technical Specifications.

Unit = MT
Taking output = 8 MT
a) Material
MS bars including 5 per cent overlaps and wastage M-083
tonne 8.400 8.400 8.400 46,496.54 390,570.97 390,570.97 390,570.97
Binding wire Kg 48.000 48.000 48.000 66.72 3,202.56 3,202.56 3,202.56 M-072
b) Labour for straightening, cutting, bending, shifting
to site, tying and placing in position

Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Blacksmith day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-20
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
c) Machinery
Cutting Machine & Bending Machine hour 5.333 5.333 5.333 528.15 2,816.62 2,816.62 2,816.62 P&M-076
Electric generator 15 KVA hour 5.333 5.333 5.333 425.25 2,267.86 2,267.86 2,267.86 P&M-051
Tipper
Tipper for Transportation
(i) 18 cum capacity t.km 8xL 6.18 1,482.84 P&M-116
(ii) 14 cum capacity t.km 8xL 7.01 1,683.07 P&M-119
(iii) 10 cum capacity t.km 8xL 8.66 2,079.36 P&M-122
Loading & Unloading Time hour
(i) 18 cum capacity hour 1.000 2,883.30 2,883.30 P&M-014
(ii) 14 cum capacity hour 1.280 2,556.75 3,272.64 P&M-015
(iii) 10 cum capacity hour 1.778 2,274.30 4,043.20 P&M-016
Light weight Crane
At cutting bending yard hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102
At site hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102
Per MT Basic Cost of Labour, Material & Machinery
(a+b+c) 51234.000 51308.000 51454.000

d) Overhead charges @ 8% on @ 10% on @ 12% on


32,789.67 41,046.04 49,395.27
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
44,266.05 45,150.64 46,102.25
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 8 MT (a+b+c+d) 486,926.55 496,657.09 507,124.78
Rate for per MT (a+b+c+d)/8 60,865.82 62,082.14 63,390.60
Say 60,866.00 62,082.00 63,391.00
CHAPTER- 10
MAINTENANCE OF ROADS
Quantity Amount (Rs.)
Ref.to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium Small
(Rs.) Large Project ref.
Specification Project Project Project Project Project

10.01 3002 Restoration of Rain Cuts


Restoration of rain cuts with soil, moorum, gravel
or a mixture of these, clearing the loose soil,
benching for 300 mm width, laying fresh material in
layers not exceeding 250 mm and compacting with
plate compactor or power rammers to restore the
original alignment, levels and slopes

Unit = cum
Taking output = 10 cum 10 Cum 12 tonne
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 0.007 3,420.00 23.94 P&M-007
(ii) 1.1 cum bucket capacity hour 0.008 3,074.00 24.59 P&M-008
(iii) 0.9 cum bucket capacity hour 0.012 2,782.00 33.38 P&M-009
Tipper
For transportation to dumping yard considering
lead @ 1km
(i) 18 cum capacity t.km 12 x L2 6.18 74.14 P&M-116
(ii) 14 cum capacity t.km 12 x L2 7.01 84.15 P&M-119
(iii) 10 cum capacity t.km 12 x L2 8.66 103.97 P&M-122
For loading & unloading
(i) 18 cum capacity hour 0.007 2,883.30 20.18 P&M-014
(ii) 14 cum capacity hour 0.008 2,556.75 20.45 P&M-015
(iii) 10 cum capacity hour 0.012 2,274.30 27.29 P&M-016
Plate compactor hour 0.500 0.500 0.500 597.45 298.73 298.73 298.73 P&M-079
d) Overhead charges @ 8% on @ 10% on @ 12% on 119.15 150.03 184.29
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 160.85 165.04 172.01
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10 cum = a+b+c+d 1,769.40 1,815.39 1,892.07
Rate per cum = (a+b+c+d)/10 176.94 181.54 189.21
Say 177.00 182.00 189.00
Note Only 75 per cent of fresh material has been
provided as 25 per cent can be retrieved at site
from earth that is flown down the slope in the form
of slurry and deposited at the foot of there in cuts

10.02 3003 Maintenance of Earthen Shoulder (filling with fresh


soil)
Making up loss of material/ irregularities on
shoulder to the design level by adding fresh
approved soil and compacting it with appropriate
equipment.
Unit = sqm
Taking output = 100 sqm
Assuming average thickness of filling to be 150
mm
Quantity of fresh material = 15 Cum 24 tonne
a) Labour
Mate day 0.180 0.180 0.180 617.00 111.06 111.06 111.06 L-12
Mazdoor day 4.500 4.500 4.500 511.52 2,301.84 2,301.84 2,301.84 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 0.011 3,420.00 37.62 P&M-007
(ii) 1.1 cum bucket capacity hour 0.012 3,074.00 36.89 P&M-008
(iii) 0.9 cum bucket capacity hour 0.017 2,782.00 47.29 P&M-009
Tipper
For transportation to dumping yard considering
lead @ 1km
(i) 18 cum capacity t.km 24 x L2 6.18 148.28 P&M-116
(ii) 14 cum capacity t.km 24 x L2 7.01 168.31 P&M-119
(iii) 10 cum capacity t.km 24 x L2 8.66 207.94 P&M-122
For loading & unloading
(i) 18 cum capacity hour 0.011 2,883.30 31.72 P&M-014
(ii) 14 cum capacity hour 0.012 2,556.75 30.68 P&M-015
(iii) 10 cum capacity hour 0.017 2,274.30 38.66 P&M-016
Plate compactor @ 25 sqm per hour hour 12.000 12.000 12.000 597.45 7,169.40 7,169.40 7,169.40 P&M-079
Quantity Amount (Rs.)
Ref.to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium Small
(Rs.) Large Project ref.
Specification Project Project Project Project Project

c) Overhead charges @ 8% on @ 10% on @ 12% on 783.99 981.82 1,185.14


(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 1,058.39 1,080.00 1,106.13
(a+b+c) (a+b+c) (a+b+c)
Cost for 100 sqm = a+b+c+d 11,642.31 11,879.99 12,167.47
Rate per sqm = (a+b+c+d)100 116.42 118.80 121.67
Say 116.00 119.00 122.00
10.03 3003 Maintenance of Earth Shoulder (stripping excess
soil)
Stripping excess soil from the shoulder surface to
achieve the approved level and compacting with
plate compactor
Unit = sqm
Taking output = 100 sqm
Assuming average depth of stripping as 75 mm

Quantity of earth cutting involved = 7.5 cum


a) Labour
Mate day 0.100 0.100 0.100 617.00 61.70 61.70 61.70 L-12
Mazdoor day 2.500 2.500 2.500 511.52 1,278.80 1,278.80 1,278.80 L-13
b) Machinery
Plate compactor @ 25 sqm per hour hour 4.000 4.000 4.000 597.45 2,389.80 2,389.80 2,389.80 P&M-079
c) Overhead charges @ 8% on @ 10% on @ 12% on 298.42 373.03 447.64
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 402.87 410.33 417.79
(a+b+c) (a+b+c) (a+b+c)
Cost for 100 sqm = a+b+c+d 4,431.60 4,513.66 4,595.73
Rate per sqm on = (a+b+c+d)100 44.32 45.14 45.96
Say 44.00 45.00 46.00
Note The earth stripped from earthen shoulders to be
dumped on the side slopes locally for disposal.

10.04 3004.2 Filling Pot-holes and Patch Repairs with open-


Graded Premix surfacing, 20mm.
Removal of all failed material, trimming of
completed excavation to provide firm vertical faces,
cleaning of surface, painting of tack coat on the
sides and base of excavation as per clause 503,
back filling the pot holes with hot bituminous
material as per clause 510, compacting, trimming
and finishing the surface to form a smooth
continuous surface, all as per clause 3004.2

Unit = Sqm 205 cum


Taking out put = 10250 sqm 405 tonne
a) Labour
Mate Day 3.760 3.760 3.760 617.00 2,319.92 2,319.92 2,319.92 L-12
Mazdoor Day 90.000 90.000 90.000 511.52 46,036.80 46,036.80 46,036.80 L-13
Mazdoor skilled Day 4.000 4.000 4.000 565.73 2,262.92 2,262.92 2,262.92 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 2.700 14,634.90 39,514.23 P&M-035
(ii) HMP 160 TPH hour 3.375 10,338.30 34,891.76 P&M-036
(iii) HMP 120 TPH hour 4.500 8,372.70 37,677.15 P&M-037
Mechanical broom (2.1m sweeping width) hour 3.051 3.051 3.051 500.40 1,526.52 1,526.52 1,526.52 P&M-052
Air compressor 250 cfm hour 3.051 3.051 3.051 614.25 1,873.83 1,873.83 1,873.83 P&M-029
Electric generator
(i) 500 KVA hour 2.700 8,022.00 21,659.40 P&M-044
(ii) 400 KVA hour 3.375 6,470.10 21,836.59 P&M-045
(iii) 250 KVA hour 4.500 3,475.00 15,637.50 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 2.700 4,279.80 11,555.46 P&M-011
(ii) 2.1 Cum Capacity hour 3.375 2,640.75 8,912.53 P&M-012
(iii) 1 Cum Capacity hour 4.500 1,112.00 5,004.00 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 405 x L 6.18 75,068.78 P&M-116
(ii) 14 cum capacity t.km 405 x L 7.01 85,205.52 P&M-119
(iii) 10 cum capacity t.km 405 x L 8.66 105,267.60 P&M-122
For loading & unloading time
(i) 18 cum capacity hour 2.700 2,883.30 7,784.91 P&M-014
(ii) 14 cum capacity hour 3.375 2,556.75 8,629.03 P&M-015
(iii) 10 cum capacity hour 4.500 2,274.30 10,234.35 P&M-016
Smooth steel wheeled tandem roller for static and 6,051.70 6,051.70 6,051.70 P&M-019
vibratory passaes hour 14.512 14.512 14.512 417.00
c) Material
Quantity Amount (Rs.)
Ref.to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium Small
(Rs.) Large Project ref.
Specification Project Project Project Project Project

Crushed stone aggregates nominal size 13.2mm 348,174.21 348,174.21 348,174.21 M-051
cum 184.500 184.500 184.500 1,887.12
Crushed stone aggregates nominal size 11.2mm 174,087.11 174,087.11 174,087.11 M-050
cum 92.250 92.250 92.250 1,887.12
Bitumen 80/100 tonne 14.970 14.970 14.970 48,006.37 718,655.37 718,655.37 718,655.37 M-075
Bitumen emulsion for tack coat including vertical 117,249.43 117,249.43 117,249.43 M-077
sides of pot hole. tonne 2.460 2.460 2.460 47,662.37
d) Overhead charges @ 8% on @ 10% on @ 12% on 125,905.65 157,771.32 191,047.01
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 169,972.62 173,548.46 178,310.54
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10250 sqm = a+b+c+d+e 1,869,698.86 1,909,033.03 1,961,415.96
Rate per sqm = (a+b+c+d+e)/10250 182.41 186.25 191.36
Say 182.00 186.00 191.00
10.05 3004.2 Filling Pot-holes and Patch Repairs with
Bituminous concrete, 40mm.
Removal of all failed material, trimming of
completed excavation to provide firm vertical faces,
cleaning of surface, painting of tack coat on the
sides and base of excavation as per clause 503,
back filling the pot holes with hot bituminous
material as per clause 504, compacting, trimming
and finishing the surface to form a smooth
continuous surface, all as per clause 3004.2

Unit = Sqm 196 cum


Taking out put = 4900 sqm 450 tonne
a) Labour
Mate Day 2.920 2.920 2.920 617.00 1,801.64 1,801.64 1,801.64 L-12
Mazdoor Day 70.000 70.000 70.000 511.52 35,806.40 35,806.40 35,806.40 L-13
Mazdoor skilled Day 3.000 3.000 3.000 565.73 1,697.19 1,697.19 1,697.19 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.000 14,634.90 43,904.70 P&M-035
(ii) HMP 160 TPH hour 3.750 10,338.30 38,768.63 P&M-036
(iii) HMP 120 TPH hour 5.000 8,372.70 41,863.50 P&M-037
Mechanical broom (2.1m sweeping width) hour 1.458 1.458 1.458 500.40 729.75 729.75 729.75 P&M-052
Air compressor 250 cfm hour 1.458 1.458 1.458 614.25 895.78 895.78 895.78 P&M-029
Electric generator
(i) 500 KVA hour 3.000 8,022.00 24,066.00 P&M-044
(ii) 400 KVA hour 3.750 6,470.10 24,262.88 P&M-045
(iii) 250 KVA hour 5.000 3,475.00 17,375.00 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 3.000 4,279.80 12,839.40 P&M-011
(ii) 2.1 Cum Capacity hour 3.750 2,640.75 9,902.81 P&M-012
(iii) 1 Cum Capacity hour 5.000 1,112.00 5,560.00 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L 6.18 83,409.75 P&M-116
(ii) 14 cum capacity t.km 450 x L 7.01 94,672.80 P&M-119
(iii) 10 cum capacity t.km 450 x L 8.66 116,964.00 P&M-122
For loading & unloading time
(i) 18 cum capacity hour 3.000 2,883.30 8,649.90 P&M-014
(ii) 14 cum capacity hour 3.750 2,556.75 9,587.81 P&M-015
(iii) 10 cum capacity hour 5.000 2,274.30 11,371.50 P&M-016
Smooth steel wheeled tandem roller for static and 5,786.02 5,786.02 5,786.02 P&M-019
vibratory passaes hour 13.875 13.875 13.875 417.00
c) Material
I) Bitumen tonne 23.890 23.890 23.890 48,006.37 1,146,872.20 1,146,872.20 1,146,872.20 M-075
ii) Bitumen emulsion for tack coat . tonne 1.180 1.180 1.180 47,662.37 56,241.60 56,241.60 56,241.60 M-077
iii) Aggregates
Grading I - 19mm(Nominal size)
20-10mm 35 per cent cum 108.255 108.255 108.255 1,887.12 204,290.51 204,290.51 204,290.51 M-044
10-5 mm 23 per cent cum 48.430 48.430 48.430 1,887.12 91,393.37 91,393.37 91,393.37 M-039
5mm and below40 per cent cum 122.499 122.499 122.499 1,887.12 231,170.69 231,170.69 231,170.69 M-029
Filler @ 2 percent of weight of aggregates tonne 8.546 8.546 8.546 3,753.00 32,073.14 32,073.14 32,073.14 M-190
Add 5 per cent for wastage 27,946.39 27,946.39 27,946.39
or
Grading-II 13mm (Nominal size)
13.2-10 mm 30 per cent cum 59.825 59.825 59.825 1,887.12 112,897.14 112,897.14 112,897.14 M-043
10-5 mm 25 per cent cum 48.430 48.430 48.430 1,887.12 91,393.37 91,393.37 91,393.37 M-024
5 mm and Below43 per cent cum 170.928 170.928 170.928 1,887.12 322,562.18 322,562.18 322,562.18 M-029
Filler 2 per cent tonne 8.546 8.546 8.546 3,753.00 32,073.14 32,073.14 32,073.14 M-190
Add 5 per cent for wastage 27,946.29 27,946.29 27,946.29
Any one of the above alternatives of aggregate i.e.
19mm or 13mm nominal size may be adopted as
per approved design.
Quantity Amount (Rs.)
Ref.to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium Small
(Rs.) Large Project ref.
Specification Project Project Project Project Project

10.05 (i) for grading I Material


d) Overhead charges @ 8% on @ 10% on @ 12% on 160,765.95 201,389.96 243,580.64
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 217,034.04 221,528.96 227,341.93
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 4900 cum = a+b+c+d+e 2,387,374.42 2,436,818.52 2,500,761.25
Rate per cum = (a+b+c+d+e)/4900 487.22 497.31 510.36
Say 487.00 497.00 510.00
10.05 (ii) for grading II Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 160,765.80 201,389.76 243,580.40
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 217,033.82 221,528.74 227,341.71
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 4900 cum = a+b+c+d+e 2,387,372.07 2,436,816.12 2,500,758.81
Rate per cum = (a+b+c+d+e)/4900 487.22 497.31 510.36
Say 487.00 497.00 510.00
Note For detailed working of quantities of aggregates,
refer item 5.8 of chapter 5
10.06 3004.3.3 Crack Filling

Filling of crack using slow - curing bitumen


emulsion and applying crusher dust in case crack
are wider than 3mm.
Unit = Running Meter
Taking out put = 500m
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Material
Slow-curing bitumen emulsion Kg 33.000 33.000 33.000 47.66 1,572.86 1,572.86 1,572.86 M-077/1000
Stone crusher dust cum 0.020 0.020 0.020 1,887.12 37.74 37.74 37.74 M-020
c) Overhead charges @ 8% on @ 10% on @ 12% on 171.74 214.68 257.62
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 231.85 236.15 240.44
(a+b+c) (a+b+c) (a+b+c)
Cost for 500sqm = a+b+c+d 2,550.40 2,597.63 2,644.86
Rate per meter = (a+b+c+d+e)/500 5.10 5.20 5.29
Say 5.00 5.00 5.00
10.07 3004.4 Dusting
Applying crusher dust to areas of road where
bleeding of excess bitumen has occurred.

Unit = Sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Material
Stone crusher dust finer than 3mm with not more 11,794.52 11,794.52 11,794.52 M-020
than 10 per cent passing 0.075 sieve. cum 6.250 6.250 6.250 1,887.12
c) Overhead charges @ 8% on @ 10% on @ 12% on 1,029.35 1,286.69 1,544.03
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 1,389.63 1,415.36 1,441.09
(a+b+c) (a+b+c) (a+b+c)
Cost for 3500sqm = a+b+c+d 15,285.90 15,568.97 15,852.04
Rate per meter = (a+b+c+d)/3500 4.37 4.45 4.53
Say 4.00 4.00 5.00
10.8 (A) Fog Seal
3004.3.2 sqm

(B) Crack Prevention courses.


3004.3.4

(i) Stress Absorbing Membrane (SAM) crack width


less than 6 mm sqm
(ii) Stress Absorbing Membrane (SAM) with crack
width 6 mm to 9 mm sqm
(iii) Stress Absorbing Membrane (SAM) crack width
above 9 mm and cracked area above 50 per cent sqm

(iv) Bitumen Impregnated Geotextile sqm


10.8 (C) Slurry Seal
3004.5
(i) 5 mm thickness sqm
(ii) 3 mm thickness sqm
(iii) 1.5 mm thickness sqm
Quantity Amount (Rs.)
Ref.to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium Small
(Rs.) Large Project ref.
Specification Project Project Project Project Project

10.8 (D) Surface Dressing for maintenance works.


3004.6
(i) 19 mm nominal chipping size sqm
(ii) 13 mm nominal size chipping sqm
Note The above mentioned items have already been
included in chapter 5.
10.09 3005.1 Repair of Joint Grooves with Epoxy Mortar
Repair of spalled joint grooves of contraction joints,
longitudinal joints and expansion joints in concrete
pavements using epoxy mortar or epoxy concrete

Unit = running metre


Taking output = 10 metres
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
Chiseller day 0.500 0.500 0.500 617.00 308.50 308.50 308.50 L-05
b) Material
Epoxy primer kg 2.500 2.500 2.500 208.50 521.25 521.25 521.25 M-097
Epoxy compound with accessories for preparing 7,645.00 7,645.00 7,645.00 M-095
epoxy mortar kg 10.000 10.000 10.000 764.50
c) Machinery
Air compressor 250 cfm for cleaning hour 0.050 0.050 0.050 614.25 30.71 30.71 30.71 P&M-029
d) Overhead charges @ 8% on @ 10% on @ 12% on 702.87 878.59 1,054.31
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 948.88 966.45 984.02
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10 metres = a+b+c+d+e 10,437.65 10,630.94 10,824.23
Rate per metre = (a+b+c+d+e)/10 1,043.77 1,063.09 1,082.42
Say 1,044.00 1,063.00 1,082.00
10.10 3005.2 Repair of old Joints Sealant
Removal of existing sealant and re sealing of
contraction, longitudinal or expansion joints in
concrete pavement with fresh sealant material

Unit = running metre


Taking output = 10 metres
a) Labour
Mate day 0.020 0.020 0.020 617.00 12.34 12.34 12.34 L-12
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
b) Material
Primer kg 0.250 0.250 0.250 288.00 72.00 72.00 72.00 M-145
Sealant kg 1.000 1.000 1.000 37.53 37.53 37.53 37.53 M-119
c) Machinery
Air compressor 250 cfm for cleaning hour 0.050 0.050 0.050 614.25 30.71 30.71 30.71 P&M-029
d) Overhead charges @ 8% on @ 10% on @ 12% on 32.67 40.83 49.00
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 44.10 44.92 45.73
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10 metres = a+b+c+d+e 485.11 494.09 503.08
Rate per metre = (a+b+c+d+e)/10 48.51 49.41 50.31
Say 49.00 49.00 50.00
10.11 3000 Hill Side Drain Clearance
Removal of earth from the choked hill side drain
and disposing it on the valley side manually

Unit = running metre


Taking output = 10 metres
Assuming muck causing choking of drain to be 0.2
cum per metre, quantity of earth to be removed for
10 metres = 2 cum
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Overhead charges @ 8% on @ 10% on @ 12% on 42.90 53.62 64.34
(a) (a) (a)
c) Contractor's profit @ 10% on @ 10% on @ 10% on 57.91 58.98 60.05
(a+b) (a+b) (a+b)
Cost for 10 metres = a+b+c 637.01 648.80 660.60
Rate per metre = (a+b+c)/10 63.70 64.88 66.06
Say 64.00 65.00 66.00
10.12 3000 Land Slide Clearance in soil
Clearance of land slides in soil and ordinary rock
by a bull-dozer D 80 A-12, 180 HP and disposal of
the same on the valley side
Unit = cum
Taking output = 100 cum
Quantity Amount (Rs.)
Ref.to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium Small
(Rs.) Large Project ref.
Specification Project Project Project Project Project

a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Dozer 175 HP hour 1.670 1.670 1.670 5,087.25 8,495.71 8,495.71 8,495.71 P&M-002
c) Overhead charges @ 8% on @ 10% on @ 12% on 722.55 903.19 1,083.83
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 975.45 993.51 1,011.57
(a+b+c) (a+b+c) (a+b+c)
Cost for 100 cum = a+b+c+d 10,729.91 10,928.61 11,127.31
Rate per cum = (a+b+c+d)/100 107.30 109.29 111.27
Say 107.00 109.00 111.00
Note Land Slide clearance involves pushing of loose
earth slided on the road surface from hill face on
the valley side. Since no cutting of original ground
is involved, the output of dozer has been taken as
60 cum per hour for soil, ordinary rock and blasted
hard rock. However, if there are objection to
disposing of earth on valley side, additional
resources for its disposal shall be considered as
per site conditions.

10.13 3000 Landslide Clearance in Hard Rock Requiring


Blasting
Clearing of land slide in hard rock requiring
blasting for 50 per cent of the boulders and
disposal of the same on the valley side.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.093 0.093 0.093 617.00 57.38 57.38 57.38 L-12
Mazdoor day 1.500 1.500 1.500 511.52 767.28 767.28 767.28 L-13
Driller day 0.750 0.750 0.750 558.00 418.50 418.50 418.50 L-06
Blaster day 0.070 0.070 0.070 511.52 35.81 35.81 35.81 L-03
b) Machinery
Dozer 175 HP hour 1.670 1.670 1.670 5,087.25 8,495.71 8,495.71 8,495.71 P&M-002
Air compressor 250 cfm with two jack hammer hour 2.500 2.500 2.500 614.25 1,535.63 1,535.63 1,535.63 P&M-029
c) Materials
Explosives kg 17.500 17.500 17.500 81.90 1,433.25 1,433.25 1,433.25 M-215
Electric Detonators @ 1 Detonator for 2 Gelatine 1,470.00 1,470.00 1,470.00 M-217
sticks of 125 gms each each 70.000 70.000 70.000 21.00
c) Overhead charges @ 8% on @ 10% on @ 12% on 1,137.08 1,421.35 1,705.63
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 1,535.06 1,563.49 1,591.92
(a+b+c) (a+b+c) (a+b+c)
Cost for 100 cum = a+b+c+d+e 16,885.70 17,198.40 17,511.09
Rate per cum = (a+b+c+d+e)/100 168.86 171.98 175.11
Say 169.00 172.00 175.00
Note Credit for the rock if found acceptable as
construction material shall be afforded
10.14 3000 Snow Clearance on Roads with Dozer
Snow clearance from road surface by a bull- dozer
165 Hp and disposing it on the valley side

Unit = cum
Taking output = 5000 cum
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Dozer 175 HP hour 5.880 5.880 5.880 5,087.25 29,913.03 29,913.03 29,913.03 P&M-002
c) Overhead charges @ 8% on @ 10% on @ 12% on 2,478.83 3,098.54 3,718.25
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 3,346.43 3,408.40 3,470.37
(a+b+c) (a+b+c) (a+b+c)
Cost for 5000 cum = a+b+c+d 36,810.69 37,492.37 38,174.05
Rate per cum = (a+b+c+d)/5000 7.36 7.50 7.63
Say 7.00 7.00 8.00
Note i) Labour provided will not be cutting the snow.
They will be guiding the dozer operator on the
alignment of the road as entire surface gets
covered with snow and the edges of the road are
not visible and for changing the blade angle. Also
they will keep a watch on the hill side for any
eventuality of avalanches, slide etc
Quantity Amount (Rs.)
Ref.to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium Small
(Rs.) Large Project ref.
Specification Project Project Project Project Project

10.15 3000 Snow Clearance on Roads with Snow Blowers

Snow clearance from road surface by a snow


blower and disposing on the valley side.
Unit = cum
Taking output = 3600 cum
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Snow blower equipment 175 HP @ 600 cum per 30,523.50 30,523.50 30,523.50 P&M-002
hour hour 6.000 6.000 6.000 5,087.25
c) Overhead charges @ 8% on @ 10% on @ 12% on 2,527.67 3,159.59 3,791.51
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 3,412.36 3,475.55 3,538.74
(a+b+c) (a+b+c) (a+b+c)
Cost for 3600 cum (a+b+c+d) 37,535.93 38,231.04 38,926.15
Rate per cum = (a+b+c+d)/3600 10.43 10.62 10.81
Say 10.00 11.00 11.00
10.16 811 Replacement of Metal Beam Crash Barrier
A Type - A, "W" : Metal Beam Crash Barrier

Replacement of "W" metal beam crash barrier


comprising of 3mm thick corrugated sheet metal
beam rail, 70 cm above road / ground level, fixing
on ISMC series channel vertical post, 150x75x5
mm spaced 2m centre to centre, 1.8m high, 1.1m
below ground/road level, all steel parts and
fitments to be galvanised by hot dip process, all
fittings to confirm to IS: 1367 and IS: 1364, metal
beam rail to be fixed on the vertical post with a
spacer of channel section 150x75x5 mm, 330mm
long complete as per clause 811

Unit = Running metre


Taking output = 4.5 metre length
a) Labour
Mate day 0.080 0.060 0.060 617.00 49.36 37.02 37.02 L-12
Blacksmith day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-02
Mazdoor day 1.500 1.000 1.000 511.52 767.28 511.52 511.52 L-13
b) Machinery
Tractor-trolley hour 0.100 0.100 0.100 1,876.50 187.65 187.65 187.65 P&M-026
c) Material
Corrugated sheet,3 mm thick, "W" beam section
kg 41.210 41.210 41.210 72.28 2,978.66 2,978.66 2,978.66 M-089
railing,4.5 m in length
Channel post 150 x 75 x 5 mm,1.8 m long,3 Nos @
kg 88.560 88.560 88.560 63.81 5,650.71 5,650.71 5,650.71 M-181/1000
16.4 kg per metre
Spacer 150 x 75 x 5 mm channel 0.33 m long,3
kg 16.240 16.240 16.240 63.81 1,036.22 1,036.22 1,036.22 M-181/1000
Nos @ 16.4 kg per metre
Nuts and bolts kg 20.000 20.000 20.000 64.83 1,296.54 1,296.54 1,296.54 M-129
Add 25 per cent of the cost of material for
2,740.53 2,740.53 2,740.53
fabrication, nuts, bolts and washers etc.)
Credit for salvage value of dismantled material kg 166.010 166.010 166.010 -26.47 -4,394.62 -4,394.62 -4,394.62
d) Overhead charges @ 8% on @ 10% on @ 12% on
1,206.08 1,480.78 1,776.94
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
1,628.20 1,628.86 1,658.48
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 4.5 metre = a+b+c+d+e 13,515.61 13,522.88 13,848.65
Rate per metre = (a+b+c+d+e)/4.5 3,003.47 3,005.08 3,077.48
Say 3,003.00 3,005.00 3,077.00
10.16 B Type - B, "THRIE" : Metal Beam Crash Barrier

Replacement of "Thrie" metal beam crash barrier


comprising of 3mm thick corrugated sheet metal
beam rail, 85 cm above road / ground level, fixing
on ISMC series channel vertical post, 150x75x5
mm spaced 2m centre to centre, 2m high, 1.15m
below ground/road level, all steel parts and
fitments to be galvanised by hot dip process, all
fittings to confirm to IS: 1367 and IS: 1364, metal
beam rail to be fixed on the vertical post with a
spacer of channel section 150x75x5 mm, 546mm
long complete as per clause 811

Unit = Running metre


Taking output = 4.5 metre length
Quantity Amount (Rs.)
Ref.to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium Small
(Rs.) Large Project ref.
Specification Project Project Project Project Project

a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Blacksmith day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-02
Mazdoor day 1.500 1.500 1.500 511.52 767.28 767.28 767.28 L-13
b) Machinery
Tractor-trolley hour 0.100 0.100 0.100 1,876.50 187.65 187.65 187.65 P&M-026
c) Material
Corrugated sheet,3 mm thick, "Thrie" beam section
kg 72.940 72.940 72.940 72.28 5,272.10 5,272.10 5,272.10 M-089
railing,4.5 m in length
Channel post 150 x 75 x 5 mm, 2 m long,3 Nos @
kg 98.400 98.400 98.400 63.81 6,278.56 6,278.56 6,278.56 M-181/1000
16.4 kg per metre
Spacer 150 x 75 x 5 mm channel 0.546 m long,3
kg 26.860 26.860 26.860 63.81 1,713.84 1,713.84 1,713.84 M-181/1000
Nos
Nuts and bolts kg 30.000 30.000 30.000 64.83 1,944.81 1,944.81 1,944.81 M-129
Add 15 per cent of the cost of material for
2,281.40 2,281.40 2,281.40
fabrication, nuts, bolts and washers etc.)
Credit for salvage value of dismantled material kg 166.010 166.010 166.010 -26.47 -4,394.62 -4,394.62 -4,394.62
d) Overhead charges @ 8% on @ 10% on @ 12% on
1,509.12 1,886.40 2,263.68
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
2,037.31 2,075.04 2,112.77
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 4.5 metre = a+b+c+d+e 18,015.82 18,430.83 18,845.84
Rate per metre= (a+b+c+d+e)/4.5 4,003.52 4,095.74 4,187.96
Say 4,004.00 4,096.00 4,188.00
10.17 Network Survey Vehicle (NSV) attached with SUV

Data collection of longitudinal profiling


(International Roughness Index), Transverse
profiling (Rut Depth), Pavement Texture in term of
Mean Profile Depth, Road Geometry Data(cross
slope, gradient, curvature), GPS coordinates
(X,Y,Z) viz. longitude, latitude & altitude, video
imaging for Roadside furniture/ Road Assets and
Video imaging for Pavement Surface Distresses
and reports.
Unit = Lane Kilometer
Taking output = 200 lane km
a) Labour
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mazdoor skilled day 9.000 9.000 9.000 565.73 5,091.57 5,091.57 5,091.57 L-15
b) Machinery
Network Survey Vehicle (NSV) hour 8.000 8.000 8.000 6,415.00 51,320.00 51,320.00 51,320.00 P&M-137
Network Survey Vehicle (NSV) Mobilization &
hour 15.000 15.000 15.000 1,221.00 18,315.00 18,315.00 18,315.00 P&M-140
demobilization
Add 1 Percent of cost of a+b for Miscellaneous
749.49 749.49 749.49
work
d) Overhead charges @ 8% on @ 10% on @ 12% on
6,055.85 7,569.82 9,083.78
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
8,175.40 8,326.80 8,478.20
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for200 Km = a+b+c+d+e 89,929.43 91,594.79 93,260.15
Rate per metre= (a+b+c+d+e)/200 449.65 457.97 466.30
Say 450.00 458.00 466.00
Note: (i) Average Distance has been considered
300 km for mobilization at working site and same
for demobilization
(ii) Speed of vehicle 40 Km/hr. has been
considered.
(iii) The survey speed shall be within 30 to 80
kmph.
10.18 Falling weight deflectometer (FWD)
Unit = Lane Kilometer
Taking output = 120 lane km
a) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Falling weight deflectometer (FWD) Equipment hour 8.000 8.000 8.000 3,128.00 25,024.00 25,024.00 25,024.00 P&M-138

Falling weight deflectometer (FWD) Equipment


hour 15.000 15.000 15.000 1,221.00 18,315.00 18,315.00 18,315.00 P&M-140
Mobilization & demobilization
Add 1 Percent of cost of a+b for Miscellaneous
450.02 450.02 450.02
work
d) Overhead charges @ 8% on @ 10% on @ 12% on
3,636.15 4,545.18 5,454.22
(a+b+c) (a+b+c) (a+b+c)
Quantity Amount (Rs.)
Ref.to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium Small
(Rs.) Large Project ref.
Specification Project Project Project Project Project

e) Contractor's profit @ 10% on @ 10% on @ 10% on


4,908.80 4,999.70 5,090.60
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 120 Km = a+b+c+d+e 53,996.77 54,996.71 55,996.65
Rate per metre= (a+b+c+d+e)/120 449.97 458.31 466.64
Say 450.00 458.00 467.00
Note: (i) Average Distance has been considered
300 km for mobilization at working site and same
for demobilization
(ii) Speed of vehicle 40 Km/hr. has been
considered.
10.19 Road Retroreflectometer attached with SUV
Unit = Lane Kilometer
Taking output = 50 lane km
a) Labour
Mate day 1.200 1.200 1.200 617.00 740.40 740.40 740.40 L-12
Mazdoor skilled day 20.000 20.000 20.000 565.73 11,314.60 11,314.60 11,314.60 L-15
Mazdoor day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-13
b) Machinery
Road Retro Reflectometer testing equipment with
hour 80.000 80.000 80.000 1,709.00 136,720.00 136,720.00 136,720.00 P&M-139
Vehicle With SUV
Road Retro Reflectometer attached with SUV
hour 15.000 15.000 15.000 1,221.00 18,315.00 18,315.00 18,315.00 P&M-140
Mobilization & Demobilization
Add 1 Percent of cost of a+b for Miscellaneous
1,722.05 1,722.05 1,722.05
work
d) Overhead charges @ 8% on @ 10% on @ 12% on
13,914.18 17,392.73 20,871.27
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
18,784.14 19,132.00 19,479.85
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 50 Km = a+b+c+d+e 206,625.58 210,451.97 214,278.37
Rate per metre= (a+b+c+d+e)/50 4,132.51 4,209.04 4,285.57
Say 4,133.00 4,209.00 4,286.00
Note: (i) Average Distance has been considered
300 km for mobilization at working site and same
for demobilization
(ii) Speed of vehicle 40 Km/hr. has been
considered.

10.20 Automatic Vehicle Counter Classifier (ATCC)


Unit = Per Location
Taking output = 1 Location
a) Labour
Mate day 1.696 1.696 1.696 617.00 1,046.43 1,046.43 1,046.43 L-12
Mazdoor skilled day 0.400 0.400 0.400 565.73 226.29 226.29 226.29 L-15
Mazdoor day 42.000 42.000 42.000 511.52 21,483.84 21,483.84 21,483.84 L-13
b) Machinery
Automatic Vehicle Counter Classifier (ATCC)
hour 168.000 168.000 168.000 74.00 12,432.00 12,432.00 12,432.00 P&M-141
Equipment etc.
Sport utility vehicle (SUV) including Mobilization &
hour 72.000 72.000 72.000 1,221.00 87,912.00 87,912.00 87,912.00 P&M-140
demobilization

Data processing and Report chargesAdd 1 Percent


Lsm 1,231.01 1,231.01 1,231.01
of cost of a+b as Miscellaneous work

d) Overhead charges @ 8% on @ 10% on @ 12% on


9,946.53 12,433.16 14,919.79
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
13,427.81 13,676.47 13,925.14
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 1 Location = a+b+c+d+e 147,705.90 150,441.20 153,176.49
Rate 1 Location= (a+b+c+d+e)/1 147,705.90 150,441.20 153,176.49
Say 147,706.00 150,441.00 153,176.00
Note: (i) Average Distance has been considered
300 km for mobilization at working site and same
for demobilization
(ii) Speed of vehicle 40 Km/hr. has been
considered.
CHAPTER-11
HORTICULTURE
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
11.1 307 Spreading of Sludge Farm Yard Manure or/and
good Earth
Spreading of sludge farm yard manure or/ and
good earth in required thickness (cost of sludge,
farm yard manure or/and good earth to be paid for
separately)
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Overhead charges @ 10% on @ 12% on
@ 8% on (a) 42.90 53.62 64.34
(a) (a)
c) Contractor's profit @ 10% on @ 10% on @ 10% on
57.91 58.98 60.05
(a+b) (a+b) (a+b)
Cost for 15 cum= a+b+c 637.01 648.80 660.60
Rate per cum = (a+b+c)/15 42.47 43.25 44.04
Say 42.00 43.00 44.00
11.2 307 Grassing with ' Doobs' Grass
Grassing with 'Doobs' grass including watering and
maintenance of the lawn for 30 days or more till the
grass forms a thick lawn free from weeds and fit for
moving including supplying good earth if needed

Unit = sqm
Taking output = 100 sqm
(i) In rows 15 cm apart in either direction
a) Labour
Mate day 0.070 0.070 0.070 617.00 43.19 43.19 43.19 L-12
Mazdoor for grassing day 0.750 0.750 0.750 511.52 383.64 383.64 383.64 L-13
Mazdoor for maintenance for 30 days day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Water tanker6 KL capacity hour 0.500 0.500 0.500 1,005.00 502.50 502.50 502.50 P&M-025
c) Material
Doob grass kg 100.000 100.000 100.000 34.75 3,475.00 3,475.00 3,475.00 M-111
d) Overhead charges @ 8% on @ 10% on @ 12% on
393.27 491.59 589.90
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
530.91 540.74 550.58
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 5,840.03 5,948.18 6,056.33
Rate per sqm= (a+b+c+d+e)/100 58.40 59.48 60.56
Say 58.00 59.00 61.00
11.2 (ii) In rows 7.5 cm apart in either direction
a) Labour
Mate day 0.090 0.090 0.090 617.00 55.53 55.53 55.53 L-12
Mazdoor for grassing. day 1.250 1.250 1.250 511.52 639.40 639.40 639.40 L-13
for maintenance for 30 days day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Water tanker6 KL capacity hour 0.750 0.750 0.750 1,005.00 753.75 753.75 753.75 P&M-025
c) Material
Doob grass kg 200.000 200.000 200.000 34.75 6,950.00 6,950.00 6,950.00 M-111
d) Overhead charges @ 8% on @ 10% on @ 12% on
712.82 891.02 1,069.22
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
962.30 980.12 997.94
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 10,585.32 10,781.34 10,977.37
Rate per sqm = (a+b+c+d+e)/100 105.85 107.81 109.77
Say 106.00 108.00 110.00
Note In the case of horticulture one mate has been
provided for every 10 mazdoors as maintenance of
grass and plants require more care.

11.3 307 Making Lawns including Ploughing and Dragging


with 'Swagha' Breaking of Clod
Making lawns including ploughing and breaking of
clod, removal of rubbish, dressing and supplying
doobs grass roots and planting at 15 cm apart,
including supplying and spreading of farm yard
manure at rate of 0.18 cum per 100 sqm

Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Mazdoor for preparation of ground day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
Mali for fetching doobs grass roots and grassing at L-09
15 cm apart day 1.000 1.000 1.000 511.52 511.52 511.52 511.52
b) Machinery
Water tanker6 KL capacity hour 0.500 0.500 0.500 1,005.00 502.50 502.50 502.50 P&M-025
Tractor with tipper hour 0.010 0.010 0.010 1,876.50 18.77 18.77 18.77 P&M-026
c) Material
Supply of farm yard manure at site of work cum 0.180 0.180 0.180 300.00 54.00 54.00 54.00 M-168
Fine grass kg 100.000 100.000 100.000 34.75 3,475.00 3,475.00 3,475.00 M-112
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
d) Overhead charges @ 8% on @ 10% on @ 12% on
388.37 485.46 582.55
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
524.29 534.00 543.71
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 5,767.22 5,874.02 5,980.82
Rate per sqm = (a+b+c+d+e)/100 57.67 58.74 59.81
Say 58.00 59.00 60.00
11.4 307 Maintenance of Lawns or Turfing of Slopes
Maintenance of lawns or Turfing of slopes (rough
grassing) for a period of one year including
watering etc
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.400 0.400 0.400 617.00 246.80 246.80 246.80 L-12
Mali day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-09
b) Machinery
Water tanker6 KL capacity hour 15.000 15.000 15.000 1,005.00 15,075.00 15,075.00 15,075.00 P&M-025
c) Material
Cost of water KL 90.000 90.000 90.000 16.00 1,440.00 1,440.00 1,440.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
1,750.16 2,187.70 2,625.24
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
2,362.72 2,406.47 2,450.22
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 25,989.88 26,471.17 26,952.46
Rate per sqm = (a+b+c+d+e)/100 259.90 264.71 269.52
Say 260.00 265.00 270.00
11.5 307 Turfing Lawns with Fine Grassing including
Ploughing, Dressing
Turfing lawns with fine grassing including
ploughing, dressing including breaking of clods,
removal of rubbish, dressing and supplying doobs
grass roots at 10 cm apart, including supplying and
spreading of farm yard manure at rate of0.6 cum
per 100 sqm

Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.100 0.100 0.100 617.00 61.70 61.70 61.70 L-12
Mazdoor for preparation of ground day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
Mali for fetching doobs grass roots hedges and L-09
grassing at 10 cm apart day 1.500 1.500 1.500 511.52 767.28 767.28 767.28
b) Machinery
Water tanker6 KL capacity hour 0.500 0.500 0.500 1,005.00 502.50 502.50 502.50 P&M-025
Tractor with tiller hour 0.010 0.010 0.010 1,876.50 18.77 18.77 18.77 P&M-026
c) Material
Supply of farm yard manure at site of work @ 0.6 M-168
cum per 100 sqm cum 0.600 0.600 0.600 300.00 180.00 180.00 180.00
Fine grass kg 100.000 100.000 100.000 34.75 3,475.00 3,475.00 3,475.00 M-112
d) Overhead charges @ 8% on @ 10% on @ 12% on
441.34 551.68 662.01
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
595.81 606.84 617.88
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 6,553.92 6,675.29 6,796.65
Rate per sqm = (a+b+c+d+e)/100 65.54 66.75 67.97
Say 66.00 67.00 68.00
11.6 307 Maintenance of Lawns with Fine Grassing for the
First Year
Maintenance of lawns with fine grassing for the first
year including watering etc
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.400 0.400 0.400 617.00 246.80 246.80 246.80 L-12
Mali day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-09
b) Machinery
Water tanker6 KL capacity hour 20.000 20.000 20.000 1,005.00 20,100.00 20,100.00 20,100.00 P&M-025
c) Material
Cost of water KL 60.000 60.000 60.000 16.00 960.00 960.00 960.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
2,113.76 2,642.20 3,170.64
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
2,853.58 2,906.42 2,959.26
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 31,389.34 31,970.62 32,551.90
Rate per sqm = (a+b+c+d+e)/100 313.89 319.71 325.52
Say 314.00 320.00 326.00
11.7 307 Planting and Maintaining of Permanent Hedges

(a) Planting permanent hedges including digging of


trenches
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Planting permanent hedges including digging of
trenches, 60 cm wide and 45 cm deep, refilling the
excavated earth mixed with farmyard manure,
supplied at the rate of 4.65 cum per 100 metres
and supplying and planting hedge plants at 30 cm
apart

Unit = Running metre


Taking output = 100metre
a) Labour
Mate day 0.560 0.560 0.560 617.00 345.52 345.52 345.52 L-12
Mazdoor for digging of trench 60 cm wide and 45 L-13
cm deep day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20
Mazdoor for refilling the excavated earth mixed L-13
with cow dung, preparation of ground and digging
of plant, from the nursery carriage to site and day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08
planting in position
b) Machinery
Water tanker6 KL capacity hour 0.500 0.500 0.500 1,005.00 502.50 502.50 502.50 P&M-025
c) Material
Cost of hedge plants 2 rows at 30 cm apart each 2x340 2x340 2x340 25.00 17,000.00 17,000.00 17,000.00 M-115
Supply of farm yard manure at site of work cum 4.670 4.670 4.670 300.00 1,401.00 1,401.00 1,401.00 M-168
Pesticide kg 0.250 0.250 0.250 222.40 55.60 55.60 55.60 M-135
Cost of water KL 3.000 3.000 3.000 16.00 48.00 48.00 48.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
2,121.11 2,651.39 3,181.67
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
2,863.50 2,916.53 2,969.56
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 metres = a+b+c+d+e 31,498.51 32,081.82 32,665.12
Rate per metre = a+b+c+d+e)/100 314.99 320.82 326.65
Say 315.00 321.00 327.00
(b) Maintenance of hedge for one year
Unit = Running metre
Taking output = 100 m
a) Labour
Mate day 1.200 1.200 1.200 617.00 740.40 740.40 740.40 L-12
Mazdoor day 30.000 30.000 30.000 511.52 15,345.60 15,345.60 15,345.60 L-13
b) Machinery
Water tanker6 KL capacity hour 5.000 5.000 5.000 1,005.00 5,025.00 5,025.00 5,025.00 P&M-025
c) Material
Manure sludge/Farm yard manure cum 2.000 2.000 2.000 300.00 600.00 600.00 600.00 M-168
Pesticide kg 0.500 0.500 0.500 222.40 111.20 111.20 111.20 M-135
Cost of water KL 30.000 30.000 30.000 16.00 480.00 480.00 480.00 M-191
Cost of hedge plants @ 10 per cent casualty each 68.000 68.000 68.000 25.00 1,700.00 1,700.00 1,700.00 M-115
d) Overhead charges @ 8% on @ 10% on @ 12% on
1,920.18 2,400.22 2,880.26
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
2,592.24 2,640.24 2,688.25
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 metres = a+b+c+d+e 28,514.61 29,042.66 29,570.71
Rate per metre = a+b+c+d+e)/100 285.15 290.43 295.71
Say 285.00 290.00 296.00
11.8 307 Planting and Maintaining of Flowering Plants and
Shrubs
(a) Planting flowering plants and shrubs in central
verge
Unit = Running metres
200 plants and 800 shrubs in two rows in one km
length of road where width of verge is 3m and
above.
Taking output = 1000 metres
a) Labour
Mate day 0.480 0.480 0.480 617.00 296.16 296.16 296.16 L-12
Mazdoor day 12.000 12.000 12.000 511.52 6,138.24 6,138.24 6,138.24 L-13
b) Machinery
Water tanker6 KL capacity hour 6.000 6.000 6.000 1,005.00 6,030.00 6,030.00 6,030.00 P&M-025
c) Material
Plants each 200.000 200.000 200.000 100.00 20,000.00 20,000.00 20,000.00 M-100
Shrubs each 800.000 800.000 800.000 54.00 43,200.00 43,200.00 43,200.00 M-167
Manure sludge/Farm yard manure cum 63.640 63.640 63.640 300.00 19,092.00 19,092.00 19,092.00 M-168
Pesticide kg 0.500 0.500 0.500 222.40 111.20 111.20 111.20 M-135
Cost of water KL 36.000 36.000 36.000 16.00 576.00 576.00 576.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
7,635.49 9,544.36 11,453.23
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
10,307.91 10,498.80 10,689.68
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per Km = (a+b+c+d+e) 113,387.00 115,486.76 117,586.52
Say 113,387.00 115,487.00 117,587.00
11.8 (b) Maintenance of flowering plants and shrubs in
central verge for one year
Unit = km
Taking output = one km
a) Labour
Mate day 14.600 14.600 14.600 617.00 9,008.20 9,008.20 9,008.20 L-12
Mazdoor day 365.000 365.000 365.000 511.52 186,704.80 186,704.80 186,704.80 L-13
b) Machinery
Water tanker6 KL capacity hour 90.000 90.000 90.000 1,005.00 90,450.00 90,450.00 90,450.00 P&M-025
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
c) Material
Manure Sludge / farm yard manure at site cum 10.000 10.000 10.000 300.00 3,000.00 3,000.00 3,000.00 M-168
Cost of water KL 180.000 180.000 180.000 16.00 2,880.00 2,880.00 2,880.00 M-191
Replacement of casualties @ 10 per cent
Plants each 20.000 20.000 20.000 100.00 2,000.00 2,000.00 2,000.00 M-100
Shrubs each 80.000 80.000 80.000 54.00 4,320.00 4,320.00 4,320.00 M-167
Pesticides kg 1.500 1.500 1.500 222.40 333.60 333.60 333.60 M-135
d) Overhead charges @ 8% on @ 10% on @ 12% on
23,895.73 29,869.66 35,843.59
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
32,259.23 32,856.63 33,454.02
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per Km for one year = (a+b+c+d+e) 354,851.56 361,422.89 367,994.21
Say 354,852.00 361,423.00 367,994.00
11.9 307 Planting of Trees and their Maintenance for one
Year
Planting of trees by the road side (Avenue trees) in
0.60 m dia holes, 1 m deep dug in the ground,
mixing the soil with decayed farm yard/sludge
manure, planting the saplings, backfilling the
trench, watering, fixing the tree guard and
maintaining the plants for one year

Unit = Each
Taking output = 10 trees
a) Labour
Mate day 0.680 0.680 0.680 617.00 419.56 419.56 419.56 L-12
Mazdoor for planting day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
Mazdoor for maintenance for one year day 15.000 15.000 15.000 511.52 7,672.80 7,672.80 7,672.80 L-13
b) Machinery
Water tanker6 KL capacity hour 2.000 2.000 2.000 1,005.00 2,010.00 2,010.00 2,010.00 P&M-025
c) Material
Sapling 2 m high 25 mm dia each 10.000 10.000 10.000 300.00 3,000.00 3,000.00 3,000.00 M-161
Farm yard manure cum 0.940 0.940 0.940 300.00 282.00 282.00 282.00 M-168
Pesticide kg 0.500 0.500 0.500 222.40 111.20 111.20 111.20 M-135
Cost of water KL 12.000 12.000 12.000 16.00 192.00 192.00 192.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
1,176.85 1,471.06 1,765.27
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
1,588.74 1,618.17 1,647.59
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10 trees = a+b+c+d+e 17,476.19 17,799.83 18,123.46
Rate per trees = (a+b+c+d+e)/10 1,747.62 1,779.98 1,812.35
Say 1,748.00 1,780.00 1,812.00
11.10 308
Renovation Lawns including, Weeding, Forking the
Ground, Top Dressing with Forked Soil

Renovation lawns including, weeding, forking the


ground, top dressing with forked soil, watering and
maintenance the lawns, for 30 days or more, till the
grass forms a thick lawn, free from weeds, and fit
for moving and disposal of rubbish as directed,
including supplying good earth, if needed but
excluding the cost of well decayed farm yard
manure

Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Machinery
Water tanker6 KL capacity hour 0.500 0.500 0.500 1,005.00 502.50 502.50 502.50 P&M-025
c) Material
Cost of water KL 3.000 3.000 3.000 16.00 48.00 48.00 48.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
172.73 215.91 259.09
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
233.18 237.50 241.82
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 2,565.01 2,612.51 2,660.01
Rate per sqm = (a+b+c+d+e) 25.65 26.13 26.60
Say 26.00 26.00 27.00
11.11 308.2
Supply at Site Well Decayed Farm Yard Manure
Supply at site of work well decayed farm yard
manure, from any available source, approved by
the engineer in charge including screening and
stacking
Unit = cum
Taking output = one cum
a) Material
a) Cost of well decayed farm yard manure duly M-168
screened, loading, carriage, unloading and cum 1.000 1.000 1.000 300.00 300.00 300.00 300.00
stacking at site
b) Overhead charges @ 10% on @ 12% on
@ 8% on (a) 24.00 30.00 36.00
(a) (a)
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
c) Contractor's profit @ 10% on @ 10% on @ 10% on
32.40 33.00 33.60
(a+b) (a+b) (a+b)
Rate per cum = (a+b+c) 356.40 363.00 369.60
Say 356.00 363.00 370.00
11.12 308.20 Supply at Site of Work/ Store-Deoiled Neem Cake

Supply at site of work/ store-deoiled neem cake


duly packed in used gunny bags
Unit = quintal
Taking output = one quintal
a) Cost, carriage, loading, unloading and M-242
stacking in store/site quintal 1.000 1.000 1.000 4,000.00 4,000.00 4,000.00 4,000.00
b) Overhead charges @ 10% on @ 12% on
@ 8% on (a) 320.00 400.00 480.00
(a) (a)
c) Contractor's profit @ 10% on @ 10% on @ 10% on
432.00 440.00 448.00
(a+b) (a+b) (a+b)
Rate per quintal = a+b+c 4,752.00 4,840.00 4,928.00
Say 4,752.00 4,840.00 4,928.00
11.13 308.2 Supplying Sludge
Supplying sludge duly stacked at site/ store
Unit = cum
Taking output = one cum
a) Cost of sludge including carriage, loading, M-168
unloading and stacking at site cum 1.000 1.000 1.000 300.00 300.00 300.00 300.00
b) Overhead charges @ 10% on @ 12% on
@ 8% on (a) 24.00 30.00 36.00
(a) (a)
c) Contractor's profit @ 10% on @ 10% on @ 10% on
32.40 33.00 33.60
(a+b) (a+b) (a+b)
Rate per cum = a+b+c 356.40 363.00 369.60
Say 356.00 363.00 370.00
11.14 New Half Brick Circular Tree Guard, in 2nd Class Brick,
internal diametre 1.25 metres, and height 1.2
metres, above ground and 0.20 metre below
ground
Half brick circular tree guard, in 2nd class brick,
internal diametre 1.25 metres, and height 1.2
metres, above ground and 0.20 metre below
ground, bottom two courses laid dry, and top three
courses in cement mortar 1:6 (1 cement 6 sand)
and the intermediate courses being in dry honey
comb masonry, as per design complete

Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.020 0.020 0.020 617.00 12.34 12.34 12.34 L-12
Mason day 0.250 0.250 0.250 738.00 184.50 184.50 184.50 L-11
Mazdoor day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
b) Material
Brick 2nd class including carriage each 230.000 230.000 230.000 3.50 805.00 805.00 805.00 M-079
Cement mortar 1:6 Sub-
Analysis of
cum 0.025 0.025 0.025 4,588.00 114.70 114.70 114.70 Concrete -
20.01 D
c) Overhead charges @ 8% on @ 10% on @ 12% on
99.55 124.44 149.33
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
134.40 136.89 139.38
(a+b+c) (a+b+c) (a+b+c)
Rate per tree Guard = a+b+c+d 1,478.37 1,505.75 1,533.13
Say 1,478.00 1,506.00 1,533.00
11.15 New Edging with 2nd Class Bricks, Laid Dry Lengthwise

Edging with 2nd class bricks, laid dry lengthwise,


including excavation, refilling, consolidation, with a
hand packing and spreading nearly surplus earth
within a lead of 50 metres

Unit = Metre
Taking output= 10 metres
a) Labour
Mate day 0.004 0.004 0.004 617.00 2.47 2.47 2.47 L-12
Mason day 0.050 0.050 0.050 738.00 36.90 36.90 36.90 L-11
Mazdoor day 0.050 0.050 0.050 511.52 25.58 25.58 25.58 L-13
b) Material
Brick 2nd class including carriage each 50.000 50.000 50.000 3.50 175.00 175.00 175.00 M-079
c) Overhead charges @ 8% on @ 10% on @ 12% on
19.20 23.99 28.79
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
25.91 26.39 26.87
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 metre = a+b+c+d 285.05 290.33 295.61
Rate per metre = (a+b+c+d)/10 28.51 29.03 29.56
Say 29.00 29.00 30.00
11.16 New Making Tree Guard 53 cm dia and 1.3 m High as
per Design from Empty Bitumen Drums
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Making tree guard 53 cm dia and 1.3 m high as per
design from empty bitumen drum, slit suitably to
permit sun and air, (supplied by the department at
stock issue rate) including providing and fixing 2
nos MS sheet rings 50 x 0.5 mm with rivets,
complete in all respect

Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.009 0.009 0.009 617.00 5.43 5.43 5.43 L-12
Blacksmith day 0.150 0.150 0.150 738.00 110.70 110.70 110.70 L-02
Mazdoor day 0.070 0.070 0.070 511.52 35.81 35.81 35.81 L-13
b) Material
Empty bitumen drum each 1.000 1.000 1.000 252.00 252.00 252.00 252.00 M-173
MS sheet 50 x 0.5 mm M-181 /
kg 0.650 0.650 0.650 63.81 41.47 41.47 41.47 1000
Rivets 6 mm dia and 10 mm in length each 22.000 22.000 22.000 6.00 132.00 132.00 132.00 M-159
d) Overhead charges @ 8% on @ 10% on @ 12% on
46.19 57.74 69.29
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
62.36 63.52 64.67
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate for each tree guard = a+b+c+d 685.96 698.67 711.37
Say 686.00 699.00 711.00
11.17 New Making Tree Guard 53 cm dia and 2 Metre High as
per Design from Empty Bitumen Drums

Making tree guard 53 cm dia and 2 metres high as


per design from empty bitumen drums, slit suitably
to permit sun and air, ( supplied by the department
at stock issue rate) including providing and
fixing four legs 40 cm long of 30 x 3 mm MS riveted
to tree guard and providing and fixing 2 nos MS
sheet rings 50 x 0.5 mm with rivets complete in all
respects

Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.016 0.016 0.016 617.00 9.87 9.87 9.87 L-12
Blacksmith day 0.200 0.200 0.200 738.00 147.60 147.60 147.60 L-02
Mazdoor day 0.200 0.200 0.200 511.52 102.30 102.30 102.30 L-13
b) Material
Empty bitumen drum each 1.500 1.500 1.500 252.00 378.00 378.00 378.00 M-173
MS sheet50 x 0.5 mm M-181 /
kg 0.650 0.650 0.650 63.81 41.47 41.47 41.47 1000
Rivets 6 mm dia and 10 mm in length each 50.000 50.000 50.000 6.00 300.00 300.00 300.00 M-159
MS plate30 x 3 mm M-181 /
kg 1.300 1.300 1.300 63.81 82.95 82.95 82.95 1000
c) Overhead charges @ 8% on @ 10% on @ 12% on
84.98 106.22 127.46
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
114.72 116.84 118.97
(a+b+c) (a+b+c) (a+b+c)
Rate for each tree guard = a+b+c+d 1,261.89 1,285.26 1,308.63
Say 1,262.00 1,285.00 1,309.00
11.18 New Wrought Iron and Mild Steel Welded Work
Wrought iron and mild steel welded work (using
angles, square bars, tees and channel grills,
grating frames, gates and tree guards of any size
and design etc. including cost of screens and
welding rods or bolts and nuts complete fixed in
position but without the cost of excavation and
concrete for fixing which will be paid separately

Unit = quintal
Taking output = one quintal
a) Labour
Mate day 0.180 0.180 0.180 617.00 111.06 111.06 111.06 L-12
Blacksmith/ welder for cutting to design and shape L-02
and jointing day 2.000 2.000 2.000 738.00 1,476.00 1,476.00 1,476.00
Mazdoor for fixing and helper for Blacksmith/welder L-13
day 2.500 2.500 2.500 511.52 1,278.80 1,278.80 1,278.80
b) Material
Angle, tees, channels etc quintal 1.050 1.050 1.050 6,380.65 6,699.69 6,699.69 6,699.69 M-181 / 10
Deduct the cost of scrap M-181 / 10/3
quintal 0.050 0.050 0.050 -2,126.88 -106.34 -106.34 -106.34
Add 5 per cent of cost of material for welding rods
and other welding accessories 334.98 334.98 334.98
c) Overhead charges @ 8% on @ 10% on @ 12% on
783.53 979.42 1,175.30
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,057.77 1,077.36 1,096.95
(a+b+c) (a+b+c) (a+b+c)
Rate per quintal = a+b+c+d 11,635.49 11,850.97 12,066.44
Say 11,635.00 11,851.00 12,066.00
11.19 New Tree Guard with MS Iron
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Providing and fixing MS iron tree guard 60 cm dia
and 2 metre high above ground level formed of 4
Nos (25 x 6 mm) and 8 Nos (25 x 3 mm) vertical
MS riveted to 3 Nos (25 x 6 mm) iron rings in two
halves, bolted together with 8 mm dia and 30 mm
long bolts including painting two coats with paint of
approved brand over a coat of priming, complete in
all respects.

Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.020 0.020 0.020 617.00 12.34 12.34 12.34 L-12
Blacksmith day 0.250 0.250 0.250 738.00 184.50 184.50 184.50 L-02
Mazdoor day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
b) Material
MS iron 25 x 6 mm M-181 /1000
kg 19.200 19.200 19.200 63.81 1,225.09 1,225.09 1,225.09
MS iron 25 x 3 mm M-181 /
kg 9.600 9.600 9.600 63.81 612.54 612.54 612.54 1000
Add 5 per cent of cost of material for riveting,
bolting and welding accessories 91.88 91.88 91.88
c) Machinery
Tractor-trolley hour 0.040 0.040 0.040 1,876.50 75.06 75.06 75.06 P&M-026
d) Painting
Painting two coats including priming sqm 1.770 93.00 164.61
Item No. -
sqm 1.770 95.00 168.15
8.09
sqm 1.770 97.00 171.69
e) Overhead charges @ 8% on @ 10% on @ 12% on
186.34 232.93 279.51
(a+b+c) (a+b+c) (a+b+c)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
251.56 256.22 260.88
(a+b+c+e) (a+b+c+e) (a+b+c+e)
Rate per tree guard =a+b+c+d+e+f 2,931.81 2,986.59 3,041.38
Say 2,932.00 2,987.00 3,041.00
Note 1 The items of excavation and concreting to be
measured and paid separately as per design .

2 . Rate of painting may be adopted from the


chapter as Traffic signs.
11.20 New Tree Guard with MS Angle Iron and Steel Wire

Providing and fixing tree guard 0.60 metre square,


2.00 metre high fabricated with MS angle iron 30 x
30 x 3 mm, MS iron 25 x 3 mm and steel wire3 mm
dia welded and fabricated as per design in two
halves bolted together

Unit = Each
Taking output = one
a) Labour
Mate day 0.030 0.030 0.030 617.00 18.51 18.51 18.51 L-12
Blacksmith day 0.250 0.250 0.250 738.00 184.50 184.50 184.50 L-02
Welder day 0.250 0.250 0.250 738.00 184.50 184.50 184.50 L-02
Mazdoor day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
b) Material
MS angle 30 x 30 x 3 mm M-181 /
kg 13.500 13.500 13.500 63.81 861.39 861.39 861.39 1000
MS iron 25 x 3 mm M-181 /
kg 18.000 18.000 18.000 63.81 1,148.52 1,148.52 1,148.52 1000
Steel wire 3 mm dia kg 6.000 6.000 6.000 66.72 400.32 400.32 400.32 M-194
Add 5 per cent of cost of material for riveting,
bolting and welding accessories 120.51 120.51 120.51
c) Machinery
Tractor-trolley hour 0.040 0.040 0.040 1,876.50 75.06 75.06 75.06 P&M-026
d) Painting
Painting two coats including priming sqm 1.500 93.00 139.50
Item No. -
sqm 1.500 95.00 142.50
8.09
sqm 1.500 97.00 145.50
e) Overhead charges @ 8% on @ 10% on @ 12% on
249.69 312.12 374.54
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
337.09 343.33 349.57
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Rate per tree guard = a+b+c+d+e+f 3,847.47 3,919.14 3,990.80


Say 3,847.00 3,919.00 3,991.00
11.21 New Compensatory Afforestation
Planting trees as compensatory afforestation at the
rate of 290 trees per hectare at a spacing of 6 m by
grubbing and leveling the ground upto a depth of
150 mm, digging holes 0.9 m dia, 1 m deep, mixing
farm yard/sludge manure with soil, planting of
sapling 2 m high with 25 cm dia stem, backfilling
the hole and watering

Unit = Hectare
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Taking output = one hectare
a) Labour
i) Planting
Mate day 1.000 1.000 1.000 617.00 617.00 617.00 617.00 L-12
Mazdoor day 25.000 25.000 25.000 511.52 12,788.00 12,788.00 12,788.00 L-13
ii) For Maintenance for one year
Mate day 5.000 5.000 5.000 617.00 3,085.00 3,085.00 3,085.00 L-12
Mazdoor day 50.000 50.000 50.000 511.52 25,576.00 25,576.00 25,576.00 L-13
b) Machinery
Dozer 80 HP @ 1000 sqm/hour hour 10.000 10.000 10.000 3,502.80 35,028.00 35,028.00 35,028.00 P&M-003
Water tanker6 KL capacity (for planting) hour 3.000 3.000 3.000 1,005.00 3,015.00 3,015.00 3,015.00 P&M-025
Water tanker6 KL capacity (for maintenance) hour 25.000 25.000 25.000 1,005.00 25,125.00 25,125.00 25,125.00 P&M-025
c) Material
Sapling 1 to 1.5 m high 2 cm dia stem M-161 x 0.8
each 290.000 290.000 290.000 240.00 69,600.00 69,600.00 69,600.00
Add 10 per cent of sapling M-161 x 0.8
each 29.000 29.000 29.000 240.00 6,960.00 6,960.00 6,960.00
Decayed farm yard/sludge manure (planting) cum 60.900 60.900 60.900 300.00 18,270.00 18,270.00 18,270.00 M-168
Decayed farm yard/sludge manure (maintenance) M-168
cum 4.000 4.000 4.000 300.00 1,200.00 1,200.00 1,200.00
Pesticides for planting kg 0.500 0.500 0.500 222.40 111.20 111.20 111.20 M-135
Pesticides for maintenance kg 1.500 1.500 1.500 222.40 333.60 333.60 333.60 M-135
Cost of water KL 18.000 18.000 18.000 16.00 288.00 288.00 288.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
16,159.74 20,199.68 24,239.62
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
21,815.65 22,219.65 22,623.64
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per hectare = a+b+c+d+e 239,972.20 244,416.13 248,860.06
Say 239,972.00 244,416.00 248,860.00
Note Cost of fencing to be provided as per size of plot
and approved design, measured and paid
separately
11.22 New Rain Water Harvesting Constructing rain water
harvesting

Rain Water Harvesting Constructing rain water


harvesting recharge trench cum recharge shaft /
well including grating passage joining storm water
drain and trench having brick walls, RCC cover
slab and filled with layers of filter media (size 75
mm to 100 mm), grating having brick walls and CC
1:2:4 base and PVC pipe shaft packed with gravel,
provided with wire screen and bottom plug
complete as per Drawing, direction of the Engineer
and MORT&H Specifications sections 300, 1000,
1300, 1500, 1600 & 1700. (Dimension of rain water
harvesting pit 6.5 m depth, 2.10 meter inner dia,
wall width 375 mm and top slab thickness 150 mm)

Unit = Number
Taking output = 10 Number
a) Material
cum 230.213 152.00 34,992.38 Item No.-
Excavation 12.01 (Rate taken from Item No.-12.01
cum 230.213 158.00 36,373.65 12.01 (I)
(I) B (iii) )
cum 230.213 194.00 44,661.32 B(iii)
cum 61.819 6,061.00 374,684.96
Brick Wall (2.5 meter) (Rate taken from Item No. - Item No.-
cum 61.819 6,098.00 376,972.26
12.05) 12.05
cum 61.819 6,249.00 386,306.93
cum 98.910 5,030.63 497,579.61
Brick Wall (Without Mortar -4 meter) (Rate taken Item No.-
cum 98.910 5,061.34 500,617.14
from Item No.-12.05 x 83%) 12.05
cum 98.910 5,186.67 513,013.53
cum 5.193 8,966.00 46,560.44
RCC M20 for Slab (Rate taken from Item No.12.08 Item No.-
cum 5.193 9,014.00 46,809.70
C, Case-II) 12.08C(ii)
cum 5.193 9,178.00 47,661.35
MT 0.415 68,094.00 28,259.01
Item No.-
Reinforcement (Rate taken from Item No.-12.42) MT 0.415 68,191.00 28,299.27
12.42
MT 0.415 68,383.00 28,378.95
b) Filter Material (Size from 75- 100 mm) cum 225.020 225.020 225.020 1,215.07 273,415.64 273,415.64 273,415.64 M-011
c) Add 1 per cent of the cost of (a+b) for other
miscelleneus (i.e Pipe etc) activities required to 12,554.92 12,624.88 12,934.38
complete the item in all respect.
@ 10% on @ 12% on
d) Overhead charges @ 8% on (b) 21,873.25 27,341.56 32,809.88
(b) (b)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 29,528.89 30,075.72 30,622.55
(b+d) (b+d) (b+d)
Cost for 10 Nos. = a+b+c+d+e 1,319,449.09 1,332,529.82 1,369,804.52
Rate per No. = (a+b+c+d+e)/10 131,944.91 133,252.98 136,980.45
Say 131,945.00 133,253.00 136,980.00
CHAPTER-12
FOUNDATIONS
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
12.01 304 Excavation for Structures
Earth work in excavation of foundation of structures
as per drawing and technical specification,
including setting out, construction of shoring and
bracing, removal of stumps and other deleterious
matter, dressing of sides and bottom and
backfilling with approved material.

I Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means
(i) Depth upto 3 m
a) Labour
Mate day 0.140 0.140 0.140 617.00 86.38 86.38 86.38 L-12
Mazdoor day 3.500 3.500 3.500 511.52 1,790.32 1,790.32 1,790.32 L-13
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 187.670 187.670 187.670
b) Overhead charges @ 20% on (a) @ 20% on (a) @ 20% on (a) 375.34 375.34 375.34
c) Contractor's profit @ 10% on @ 10% on @ 10% on
225.20 225.20 225.20
(a+b) (a+b) (a+b)
Cost for 10 cum = a+b+c 2,477.24 2,477.24 2,477.24
Rate per cum = (a+b+c)/10 247.72 247.72 247.72
Say 248.00 248.00 248.00
Note 1. Cost of dewatering may be added where
required upto, 10 per cent of labour cost
Assessment for dewatering shall be made as per
site conditions.
2.The excavated earth can be used partially for
backfilling of foundation pit and partly for road work
except for marshy soil. Hence cost of disposal has
not been added except for marshy soil. This
remark is common to all cases of item 12.1
excluding marshy soil.

3.The cost of shoring and shuttering, where


needed, may be added @ 1 per cent on cost of
excavation for open foundation.
12.01 (I) A (ii) Depth 3 m to 6 m

a) Labour
Mate/Supervisor day 0.180 0.180 0.180 617.00 111.06 111.06 111.06 L-12
Mazdoor day 4.500 4.500 4.500 511.52 2,301.84 2,301.84 2,301.84 L-13
b) Overhead charges @ 20% on (a) @ 20% on (a) @ 20% on (a) 482.58 482.58 482.58
c) Contractor's profit @ 10% on @ 10% on @ 10% on
289.55 289.55 289.55
(a+b) (a+b) (a+b)
Cost for 10 cum = a+b+c 3,185.03 3,185.03 3,185.03
Rate per cum = (a+b+c)/10 318.50 318.50 318.50
Say 319.00 319.00 319.00
Note Cost of dewatering may be added where required
upto 15 per cent of labour cost. Assessment for
dewatering shall be done as per actual ground
conditions.
12.01 (I) A (iii) Depth above 6 m

a) Labour
Mate/Supervisor day 0.240 0.240 0.240 617.00 148.08 148.08 148.08 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
b) Overhead charges @ 20% on (a) @ 20% on (a) @ 20% on (a) 643.44 643.44 643.44
c) Contractor's profit @ 10% on @ 10% on @ 10% on
386.06 386.06 386.06
(a+b) (a+b) (a+b)
Cost for 10 cum = a+b+c 4,246.70 4,246.70 4,246.70
Rate per cum = (a+b+c)/10 424.67 424.67 424.67
Say 425.00 425.00 425.00
Note 1. Cost of dewatering may be added where
required upto 20 per cent of labour cost.
Assessment for dewatering shall be made as per
site conditions..
12.01 (I) B Mechanical Means

Depth upto 3 m
Unit = cum
Taking output = 330 cum
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Hydraulic Excavator
For excavation
(i) 1.2 cum bucket capacity hour 4.627 3,420.00 15,824.29 P&M-007
(ii) 1.1 cum bucket capacity hour 5.329 3,074.00 16,380.39 P&M-008
(iii) 0.9 cum bucket capacity hour 7.450 2,782.00 20,725.16 P&M-009
For backfilling (considering 60% of the excavated
material)
(i) 1.2 cum bucket capacity hour 2.776 3,420.00 9,494.57 P&M-007
(ii) 1.1 cum bucket capacity hour 3.197 3,074.00 9,828.23 P&M-008
(iii) 0.9 cum bucket capacity hour 4.470 2,782.00 12,435.10 P&M-009
Tipper for transportation of excess material to
dumping yard considering lead @ 1 km
(i) 18 cum capacity t-km 198.000 6.18 1,223.34 P&M-116
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
(ii) 14 cum capacity t-km 198.000 7.01 1,388.53 P&M-119
(iii) 10 cum capacity t-km 198.000 8.66 1,715.47 P&M-122
c) Overhead charges @ 20% on @ 20% on @ 20% on
6,166.36 6,377.35 7,833.07
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
3,699.82 3,826.41 4,699.84
(a+b+c) (a+b+c) (a+b+c)
Cost for 330 cum = a+b+c+d 40,697.98 42,090.51 51,698.24
Rate per cum = (a+b+c+d)/330 123.33 127.55 156.66
Say 123.00 128.00 157.00
Note Cost of dewatering upto 5 per cent of (a+b) may
be added, where required. Assessment for
dewatering shall be made as per site conditions..

12.01 (I) B (ii) Depth 3 m to 6 m

Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Hydraulic Excavator
For excavation
(i) 1.2 cum bucket capacity hour 4.674 3,420.00 15,984.13 P&M-007
(ii) 1.1 cum bucket capacity hour 5.383 3,074.00 16,545.84 P&M-008
(iii) 0.9 cum bucket capacity hour 7.525 2,782.00 20,934.51 P&M-009
For backfilling (considering 60% of the excavated
material)
(i) 1.2 cum bucket capacity hour 2.804 3,420.00 9,590.48 P&M-007
(ii) 1.1 cum bucket capacity hour 3.230 3,074.00 9,927.51 P&M-008
(iii) 0.9 cum bucket capacity hour 4.515 2,782.00 12,560.71 P&M-009
Tipper for transportation of excess material to
dumping yard considering lead @ 1 km
(i) 18 cum capacity t-km 180.000 6.18 1,112.13 P&M-116
(ii) 14 cum capacity t-km 180.000 7.01 1,262.30 P&M-119
(iii) 10 cum capacity t-km 180.000 8.66 1,559.52 P&M-122

c) Overhead charges @ 20% on @ 20% on @ 20% on


6,195.27 6,405.05 7,868.87
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
3,717.16 3,843.03 4,721.32
(a+b+c) (a+b+c) (a+b+c)
Cost for 300 cum = a+b+c+d 40,888.76 42,273.34 51,934.52
Rate per cum = (a+b+c+d)/300 136.30 140.91 173.12
Say 136.00 141.00 173.00
Note Cost of dewatering upto 7.5 per cent of (a+b)
may be added, where required. Assessment for
dewatering shall be made as per site conditions..

12.01 (I) B (iii) Mechanical Means (Depth above 6 m)

Unit = cum
Taking output = 270 cum
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Hydraulic Excavator
For excavation
(i) 1.2 cum bucket capacity hour 4.732 3,420.00 16,183.93 P&M-007
(ii) 1.1 cum bucket capacity hour 5.450 3,074.00 16,752.67 P&M-008
(iii) 0.9 cum bucket capacity hour 7.619 2,782.00 21,196.19 P&M-009
For backfilling (considering 60% of the excavated
material)
(i) 1.2 cum bucket capacity hour 2.839 3,420.00 9,710.36 P&M-007
(ii) 1.1 cum bucket capacity hour 3.270 3,074.00 10,051.60 P&M-008
(iii) 0.9 cum bucket capacity hour 4.571 2,782.00 12,717.71 P&M-009
Tipper for transportation of excess material to
dumping yard considering lead @ 1 km
(i) 18 cum capacity t-km 162.000 6.18 1,000.92 P&M-116
(ii) 14 cum capacity t-km 162.000 7.01 1,136.07 P&M-119
(iii) 10 cum capacity t-km 162.000 8.66 1,403.57 P&M-122
c) Overhead charges @ 20% on @ 20% on @ 20% on
6,236.96 6,445.99 7,921.41
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
3,742.18 3,867.59 4,752.85
(a+b+c) (a+b+c) (a+b+c)
Cost for 270 cum = a+b+c+d 41,163.94 42,543.52 52,281.34
Rate per cum = (a+b+c+d)/270 152.46 157.57 193.63
Say 152.00 158.00 194.00
Note 1. Cost of dewatering upto 10 per cent of (a+b)
may be added, where required. Assessment for
dewatering shall be made as per site conditions..

2.Labour provided for excavation by mechanical


means includes that required for trimming of
bottom and side slopes.
12.01 II Ordinary Rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m
Unit = cum
Taking output = 10 cum
a) Labour
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 5.000 5.000 5.000 511.52 2,557.60 2,557.60 2,557.60 L-13
b) Overhead charges @ 20% on (a) @ 20% on (a) @ 20% on (a) @ 20% on (a) 536.20 536.20 536.20
c) Contractor's profit @ 10% on (a+b) @ 10% on @ 10% on @ 10% on
321.72 321.72 321.72
(a+b) (a+b) (a+b)
Cost for 10 cum = a+b+c 3,538.92 3,538.92 3,538.92
Rate per cum = (a+b+c)/10 353.89 353.89 353.89
Say 354.00 354.00 354.00
Note Cost of dewatering upto 10 per cent of labour cost
may be added, where required. Assessment for
dewatering shall be made as per site conditions..

12.01 B Mechanical Means


(II)
Unit = cum
Taking output = 50 cum
a) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Machinery
Hydraulic Excavator
Excavator for excavation
(i) 1.2 cum bucket capacity hour 5.818 3,420.00 19,898.18 P&M-007
(ii) 1.1 cum bucket capacity hour 6.845 3,074.00 21,041.28 P&M-008
(iii) 0.9 cum bucket capacity hour 7.273 2,782.00 20,232.73 P&M-009
For loading
(i) 1.2 cum bucket capacity hour 0.872 3,420.00 2,983.70 P&M-007
(ii) 1.1 cum bucket capacity hour 1.005 3,074.00 3,088.56 P&M-008
(iii) 0.9 cum bucket capacity hour 1.405 2,782.00 3,907.78 P&M-009
Jack Hammer hour 5.818 6.845 7.273 206.00 1,198.55 1,410.05 1,498.18 P&M-010
Tipper
For transportation considering lead @ 1km
(i) 18 cum capacity t-km 75.000 6.18 463.39 P&M-116
(ii) 14 cum capacity t-km 75.000 7.01 525.96 P&M-119
(iii) 10 cum capacity t-km 75.000 8.66 649.80 P&M-122
For loading & unloading time
(i) 18 cum capacity hour 0.872 2,883.30 2,515.47 P&M-014
(ii) 14 cum capacity hour 1.005 2,556.75 2,568.86 P&M-015
(iii) 10 cum capacity hour 1.405 2,274.30 3,194.63 P&M-016
c) Overhead charges @ 20% on @ 20% on @ 20% on
5,733.58 6,048.66 6,218.34
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
3,440.15 3,629.20 3,731.01
(a+b+c) (a+b+c) (a+b+c)
Cost for 50 cum = a+b+c+d 37,841.61 39,921.17 41,041.06
Rate per cum = (a+b+c+d)/50 756.83 798.42 820.82
Say 757.00 798.00 821.00
Note 1.Cost of dewatering upto 10 per cent of (a+b),
may be added, where required Assessment for
dewatering shall be made as per site conditions.

2.In case of rock, foundation beyond3 m is not dug


and hence not included.
12.01 III Hard Rock ( requiring blasting )
Carrying out excavation in hard rock to achieve a
specified slope of the rock face by controlled use of
explosives and blasting accessories in properly
aligned and spaced drill holes, collection of the
excavated rock by a dozer, loading in tipper by a
front end loader and disposing of the material with
all lifts and lead upto 1000 m, all as specified in
clause No. 303

A Manual Means
Unit = cum
Taking output = 120 cum
a) Labour
Mate day 0.210 0.210 0.210 617.00 129.57 129.57 129.57 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Driller day 2.000 2.000 2.000 558.00 1,116.00 1,116.00 1,116.00 L-06
Blaster day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-03
b) Machinery
Air compressor hour 6.000 6.000 6.000 614.25 3,685.50 3,685.50 3,685.50 P&M-029
Jack Hammer for drilling holes (@ 4.5 m per hour)
hour 24.000 24.000 24.000 11.55 277.20 277.20 277.20 P&M-078
Jack Hammer (consider 5% of the volume for
dressing) hour 1.024 1.205 1.280 206.00 210.94 248.17 263.68 P&M-010
Hydraulic Excavator
Excavator for excavation
(i) 1.2 cum bucket capacity hour 1.024 3,420.00 3,502.08 P&M-007
(ii) 1.1 cum bucket capacity hour 1.205 3,074.00 3,703.27 P&M-008
(iii) 0.9 cum bucket capacity hour 1.280 2,782.00 3,560.96 P&M-009
For loading
(i) 1.2 cum bucket capacity hour 2.094 3,420.00 7,160.89 P&M-007
(ii) 1.1 cum bucket capacity hour 2.411 3,074.00 7,412.54 P&M-008
(iii) 0.9 cum bucket capacity hour 3.371 2,782.00 9,378.66 P&M-009
Tipper
For transportation considering lead @ 1 km
(i) 18 cum capacity t-km 180.000 6.18 1,112.13 P&M-116
(ii) 14 cum capacity t-km 180.000 7.01 1,262.30 P&M-119
(iii) 10 cum capacity t-km 180.000 8.66 1,559.52 P&M-122
For loading & unloading time
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
(i) 18 cum capacity hour 2.094 2,883.30 6,037.13 P&M-014
(ii) 14 cum capacity hour 2.411 2,556.75 6,165.26 P&M-015
(iii) 10 cum capacity hour 3.371 2,274.30 7,667.11 P&M-016
c) Materials
Small dia.Explosive at 0.40 kg / cum for 120 cum M-215
( 120 x 0.40 )
Explosive at 0.20 kg / cum for secondary blast @ kg 49.200 49.200 49.200 81.90 4,029.48 4,029.48 4,029.48
5%of the total volume ( 120 x 0.2x5% )

Electric detonators at 1 per hole for main blast M-217


holes (21x3+20*2)=103 nos no 69.000 69.000 69.000 21.00 1,449.00 1,449.00 1,449.00
Ordinary detonators @ 1 per hole for 10 secondary M-216
holes( required for 5% of the total quantity @ 0.6 m no 7.000 7.000 7.000 21.00 147.00 147.00 147.00
per hole for I cum )
Detonating fuse coil m 213.000 213.000 213.000 19.00 4,047.00 4,047.00 4,047.00 M-218
d) Overhead charges @ 20% on @ 20% on @ 20% on
6,913.27 7,066.95 7,794.62
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
4,147.96 4,240.17 4,676.77
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 120 cum = a+b+c+d+e 45,627.60 46,641.84 51,444.51
Rate per cum = (a+b+c+d+e)/120 380.23 388.68 428.70
Say 380.00 389.00 429.00
Note Cost of dewatering @ 10 per cent of (a+b) may
be added, where required Assessment for
dewatering shall be made as per site conditions.

12.01 IV Hard Rock ( blasting prohibited )


Unit = cum
Taking output = 35 cum
A Mechanical Means
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Jack Hammer hour 5.973 6.788 7.467 206.00 1,230.51 1,398.30 1,538.13 P&M-010
Hydraulic Excavator
Excavator for excavation
(i) 1.2 cum bucket capacity hour 5.973 3,420.00 20,428.80 P&M-007
(ii) 1.1 cum bucket capacity hour 6.788 3,074.00 20,865.94 P&M-008
(iii) 0.9 cum bucket capacity hour 7.467 2,782.00 20,772.27 P&M-009
For loading
(i) 1.2 cum bucket capacity hour 0.611 3,420.00 2,088.59 P&M-007
(ii) 1.1 cum bucket capacity hour 0.703 3,074.00 2,161.99 P&M-008
(iii) 0.9 cum bucket capacity hour 0.983 2,782.00 2,735.44 P&M-009
Tipper
For transportation to dumping yard considering
lead @ 1km
(i) 18 cum capacity t-km 52.500 6.18 324.37 P&M-116
(ii) 14 cum capacity t-km 52.500 7.01 368.17 P&M-119
(iii) 10 cum capacity t-km 52.500 8.66 454.86 P&M-122
For loading & unloading time
(i) 18 cum capacity hour 0.611 2,883.30 1,760.83 P&M-014
(ii) 14 cum capacity hour 0.703 2,556.75 1,798.20 P&M-015
(iii) 10 cum capacity hour 0.983 2,274.30 2,236.24 P&M-016

d) Overhead charges @ 20% on @ 20% on @ 20% on


5,381.10 5,533.00 5,761.87
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
3,228.66 3,319.80 3,457.12
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 35 cum = a+b+c+d 35,515.26 36,517.81 38,028.33
Rate per cum = (a+b+c+d)/35 1,014.72 1,043.37 1,086.52
Say 1,015.00 1,043.00 1,087.00
Note 1. Cost of dewatering upto10 per cent of (a+b),
may be added, where required Assessment for
dewatering shall be made as per site conditions.

2.In case of rock, foundation beyond3 m is not dug


and hence not included.
12.01 V Marshy Soil
Unit = cum
Taking output = 10 cum
Depth upto 3 m
A Manual means
a) Labour
Mate/Supervisor day 0.400 0.400 0.400 617.00 246.80 246.80 246.80 L-12
Mazdoor day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-13
b) Machinery
Tractor-trolley for removal. hour 2.670 2.670 2.670 1,876.50 5,010.26 5,010.26 5,010.26 P&M-026
c) Overhead charges @ 20% on @ 20% on @ 20% on
2,074.45 2,074.45 2,074.45
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,244.67 1,244.67 1,244.67
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 cum = a+b+c+d 13,691.38 13,691.38 13,691.38
Rate per cum = ( a+b+c+d)/ 10 1,369.14 1,369.14 1,369.14
Say 1,369.00 1,369.00 1,369.00
Note 1. Cost of dewatering @ 30 per cent of (a), may
be added, where required Assessment for
dewatering shall be made as per site conditions.

2. Shoring & strutting 15 per cent of (a), where


required may be added
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
3. It is assumed that Marshy Soil will be available
upto 3 m depth only. For deeper excavation below
3 m depth, refer analysis in item12.1 (i) to (iv) for
ordinary soil
12.01 B Mechanical Means
(V)
Unit = cum
Taking output = 260 cum
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 8.506 3,420.00 29,091.11 P&M-007
(ii) 1.1 cum bucket capacity hour 9.796 3,074.00 30,113.44 P&M-008
(iii) 0.9 cum bucket capacity hour 13.695 2,782.00 38,100.81 P&M-009
Tipper
For transportation to dumping yard considering
lead @ 1km
(i) 18 cum capacity t-km 390.000 6.18 2,409.62 P&M-116
(ii) 14 cum capacity t-km 390.000 7.01 2,734.99 P&M-119
(iii) 10 cum capacity t-km 390.000 8.66 3,378.96 P&M-122
For loading & unloading time
(i) 18 cum capacity hour 8.506 2,883.30 24,525.85 P&M-014
(ii) 14 cum capacity hour 9.796 2,556.75 25,046.37 P&M-015
(iii) 10 cum capacity hour 13.695 2,274.30 31,147.61 P&M-016
c) Material
Selected earth for refilling cum 156.000 156.000 156.000 222.00 34,632.00 34,632.00 34,632.00 M-164
c) Overhead charges @ 20% on @ 20% on @ 20% on
18,238.95 18,612.60 21,554.18
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
10,943.37 11,167.56 12,932.51
(a+b+c) (a+b+c) (a+b+c)
Cost for 260 cum = a+b+c+d 120,377.10 122,843.15 142,257.59
Rate per cum = (a+b+c+d)/260 462.99 472.47 547.14
Say 463.00 472.00 547.00
Note 1. Cost of dewatering @ 20 per cent of (a+b)
may be added, where required
2. Shoring & strutting @ 10 per cent of (a+b),
where required may be added
3. It is assumed that Marshy Soil will be available
upto 3 m depth only. For deeper excavation below
3 m depth, refer analysis in item 12.1 (i) to (iv) for
ordinary soil
12.01 VI Back Filling in Marshy Foundation Pits
(VI)
Unit : Cum
Taking Output : 6 cum
a) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor for dressing sides, bottom and backfilling
day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Machinery
Tractor-trolley for transportation hour 2.000 2.000 2.000 1,876.50 3,753.00 3,753.00 3,753.00 P&M-026
c) Overhead charges @ 20% on @ 20% on @ 20% on
1,072.32 1,072.32 1,072.32
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
643.39 643.39 643.39
(a+b+c) (a+b+c) (a+b+c)
Cost for 6 cum = a+b+c+d 7,077.31 7,077.31 7,077.31
Rate per cum = (a+b+c+d)/6 1,179.55 1,179.55 1,179.55
Say 1,180.00 1,180.00 1,180.00
12.02 304
Filling Annular Space Around Footing in Rock
Unit = cum
Taking out put = 1 cum
Lean cement concrete 1:3:6 nominal mix. Rate Item No. -
may be taken as per item 12.4. Say 6,152.00 6,170.00 6,235.00
12.04
12.03 304 Sand Filling in Foundation Trenches as per
Drawing & Technical Specification
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Water tanker (speed @ 20km/hr and return speed
@ 30 km/hr and spreading @ 30 mins per trip )

(i) 16 KL capacity hour 4.500 1,501.00 6,754.50 P&M-023


(ii) 12 KL capacity hour 6.010 1,327.00 7,975.27 P&M-024
(iii) 6 KL capacity hour 11.990 1,005.00 12,049.95 P&M-025
c) Material
Sand (assuming 20 per cent voids) at site cum 120.000 120.000 120.000 1,994.03 239,283.72 239,283.72 239,283.72 M-004
Water KL 18.000 18.000 18.000 16.00 288.00 288.00 288.00 M-191
d) Overhead charges @ 20% on @ 20% on @ 20% on
49,372.48 49,616.64 50,431.57
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
29,623.49 29,769.98 30,258.94
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per 100 cum = a+b+c+d+e 325,858.39 327,469.81 332,848.39
Rate per cum = (a+b+c+d+e)/100 3,258.58 3,274.70 3,328.48
Say 3,259.00 3,275.00 3,328.00
12.04 2100 PCC 1:3:6 in Foundation
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Plain cement concrete 1:3:6 nominal mix in
foundation with crushed stone aggregate 40 mm
nominal size mechanically mixed, placed in
foundation and compacted by vibration including
curing for 14 days.

Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mason day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-10
Mazdoor day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
b) Material
Plain cement concrete 1:3:6 nominal mix using
batching plant (Rate as sub-analysis) Sub-Analysis
cum 15.000 15.000 15.000 4,238.00 63,570.00 63,570.00 63,570.00 of Concrete -
20.02

Water KL 3.240 3.240 3.240 16.00 51.84 51.84 51.84 M-191


c) Machinery
Plate Compactor hour 1.000 1.000 1.000 597.45 597.45 597.45 597.45 P&M-079
Water tanker (speed @ 20km/hr and return speed
@ 30 km/hr and spreading @ 30 mins per trip )

(i) 16 KL capacity
hour 0.023xL1+0.135 1,501.00 1,238.33 P&M-023
(ii) 12 KL capacity hour 0.03xL1+0.18 1,327.00 1,433.16 P&M-024
(iii) 6 KL capacity hour 0.06xL1+0.36 1,005.00 2,170.80 P&M-025
d) Overhead charges @ 20% on @ 20% on @ 20% on
13,982.94 14,021.91 14,169.43
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
8,389.76 8,413.14 8,501.66
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 15 cum = a+b+c+d+e 92,287.40 92,544.58 93,518.26
Rate per cum = (a+b+c+d+e)/15 6,152.49 6,169.64 6,234.55
Say 6,152.00 6,170.00 6,235.00
Note Vibrator is a part of minor T & P which is already
included in overhead charges of the contractor.

12.05 1300 Brick Masonry Work in Cement Mortar 1:3 in


Foundation complete excluding Pointing and
Plastering, as per Drawing and Technical
Specifications.
Unit = cum
Taking output = 5 cum
a) Material
Bricks Ist class each 2500.000 2500.000 2500.000 3.50 8,750.00 8,750.00 8,750.00 M-079
Cement mortar 1:3 (Rate as sub-analysis)
Sub-Analysis
cum 1.200 1.200 1.200 5,125.00 6,150.00 6,150.00 6,150.00 of Concrete -
20.01 (A)

Water for curing KL 2.415 2.415 2.415 16.00 38.64 38.64 38.64 M-191
b) Labour
Mate day 0.480 0.480 0.480 617.00 296.16 296.16 296.16 L-12
Mason day 4.000 4.000 4.000 679.00 2,716.00 2,716.00 2,716.00 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Water tanker (speed @ 20km/hr and return speed
@ 30 km/hr and spreading @ 30 mins per trip )

(i) 16 KL capacity
hour 0.017xL1+0.101 1,501.00 917.11 P&M-023
(ii) 12 KL capacity
hour 0.022xL1+0.134 1,327.00 1,053.64 P&M-024
(iii) 6 KL capacity
hour 0.045xL1+0.268 1,005.00 1,626.09 P&M-025
c) Overhead charges @ 20% on @ 20% on @ 20% on
4,592.01 4,619.32 4,733.81
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
2,755.21 2,771.59 2,840.29
(a+b+c) (a+b+c) (a+b+c)
Cost for 5 cum = a+b+c+d 30,307.29 30,487.51 31,243.15
Rate per cum (a+b+c+d)/5 6,061.46 6,097.50 6,248.63
Say 6,061.00 6,098.00 6,249.00

12.06 Sub- (A) Cement Mortar 1:3 (1 cement : 3 sand)


analysis

Unit = 1 cum
Taking output = 1 cum
Cement mortar 1:3 (Rate as sub-analysis) Sub-Analysis
of Concrete -
Cum 1.000 1.000 1.000 5,125.00 5,125.00 5,125.00 5,125.00 20.01 (A)

c) Overhead charges @ 20% on @ 20% on @ 20% on


1,025.00 1,025.00 1,025.00
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
615.00 615.00 615.00
(a+b+c) (a+b+c) (a+b+c)
Cost for 1 cum = a+b+c+d 6,765.00 6,765.00 6,765.00
Say 6,765.00 6,765.00 6,765.00
(B) Cement Mortar 1:2 (1 cement : 2 sand)
Unit = 1 cum
Taking output = 1 cum
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Cement mortar 1:2 (Rate as sub-analysis) Sub-Analysis
of Concrete -
Cum 1.000 1.000 1.000 5,695.00 5,695.00 5,695.00 5,695.00 20.01 (B)

c) Overhead charges @ 20% on @ 20% on @ 20% on


1,139.00 1,139.00 1,139.00
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
683.40 683.40 683.40
(a+b+c) (a+b+c) (a+b+c)
Cost for 1 cum = a+b+c+d 7,517.40 7,517.40 7,517.40
Say 7,517.00 7,517.00 7,517.00
(C) Cement Mortar 1:4 (1 cement : 4 sand)
Unit = 1 cum
Taking output = 1 cum
Cement mortar 1:4 (Rate as sub-analysis) Sub-Analysis
of Concrete -
Cum 1.000 1.000 1.000 4,730.00 4,730.00 4,730.00 4,730.00 20.01 (C)

c) Overhead charges @ 20% on @ 20% on @ 20% on


946.00 946.00 946.00
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
567.60 567.60 567.60
(a+b+c) (a+b+c) (a+b+c)
Cost for 1 cum = a+b+c+d 6,243.60 6,243.60 6,243.60
Say 6,244.00 6,244.00 6,244.00
(D) Cement Mortar1:6 (1cement :6 sand)
Unit = 1 cum
Taking output = 1 cum
Cement Mortar1:6 (Rate as sub-analysis) Sub-Analysis
of Concrete -
Cum 1.000 1.000 1.000 4,588.00 4,588.00 4,588.00 4,588.00 20.01 (D)

c) Overhead charges @ 20% on @ 20% on @ 20% on


917.60 917.60 917.60
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
550.56 550.56 550.56
(a+b+c) (a+b+c) (a+b+c)
Cost for 1 cum = a+b+c+d 6,056.16 6,056.16 6,056.16
Say 6,056.00 6,056.00 6,056.00
12.07 Stone Masonry Work in Cement Mortar 1:3 in
Foundation complete as per Drawing and
Technical Specifications.
Unit = cum
Taking output = 5 cum
(A) Square Rubble Coursed Rubble Masonry (first sort)

a) Material
Stone cum 5.500 5.500 5.500 933.45 5,133.98 5,133.98 5,133.98 M-170
Through and bond stone each 35.000 35.000 35.000 59.77 2,091.95 2,091.95 2,091.95 M-184
(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as sub-analysis)
Sub-Analysis
cum 1.500 1.500 1.500 5,125.00 7,687.50 7,687.50 7,687.50 of Concrete -
20.01 (A)

b) Labour
Mate day 0.660 0.660 0.660 617.00 407.22 407.22 407.22 L-12
Mason day 7.500 7.500 7.500 679.00 5,092.50 5,092.50 5,092.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Overhead charges @ 20% on @ 20% on @ 20% on
5,003.37 5,003.37 5,003.37
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
3,002.02 3,002.02 3,002.02
(a+b+c) (a+b+c) (a+b+c)
Cost for 5 cum = a+b+c+d 33,022.21 33,022.21 33,022.21
Rate per cum (a+b+c+d)/5 6,604.44 6,604.44 6,604.44
Say 6,604.00 6,604.00 6,604.00
(B) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.500 5.500 5.500 611.60 3,363.80 3,363.80 3,363.80 M-147
Through and bond stone each 35.000 35.000 35.000 59.77 2,091.95 2,091.95 2,091.95 M-184
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in sub-analysis)
Sub-Analysis
cum 1.550 1.550 1.550 5,125.00 7,943.75 7,943.75 7,943.75 of Concrete -
20.01 (A)

b) Labour
Mate day 0.600 0.600 0.600 617.00 370.20 370.20 370.20 L-12
Mason day 6.000 6.000 6.000 679.00 4,074.00 4,074.00 4,074.00 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Overhead charges @ 20% on @ 20% on @ 20% on
4,489.48 4,489.48 4,489.48
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
2,693.69 2,693.69 2,693.69
(a+b+c) (a+b+c) (a+b+c)
Cost for 5 cum = a+b+c+d 29,630.54 29,630.54 29,630.54
Rate per cum (a+b+c+d)/5 5,926.11 5,926.11 5,926.11
Say 5,926.00 5,926.00 5,926.00
Note The labour already considered in cement mortar
has been taken into account while proposing
labour for masonry works.
12.08 1500, Plain/Reinforced Cement Concrete in Open
1700 & Foundation complete as per Drawing and
2100 Technical Specifications.
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
A PCC Grade M15
Case I PCC Grade M15 using batching plant & Concrete
pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,176.00 125,280.00 125,280.00 125,280.00 of Concrete -
20.03

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity
hour 0.109xL1+0.656 1,501.00 5,892.93 P&M-023
(ii) 12 KL capacity
hour 0.146xL1+0.875 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity hour 0.292xL1+1.75 1,005.00 10,562.55 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 5594.000 5630.000 5749.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 6,711.82 6,755.03 6,898.60

e) Overhead charges @ 20% on @ 20% on @ 20% on


34,901.44 35,126.18 35,872.72
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
20,940.87 21,075.71 21,523.63
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 230,349.52 231,832.77 236,759.98
Rate per cum = (a+b+c+d+e+f)/30 7,678.32 7,727.76 7,892.00
Say 7,678.00 7,728.00 7,892.00
Case II PCC Grade M15 using batching plant & manual
placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 4,176.00 62,640.00 62,640.00 62,640.00 of Concrete -
20.03

Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity
hour 0.055xL1+0.328 1,501.00 2,968.98 P&M-023
(ii) 12 KL capacity
hour 0.073xL1+0.438 1,327.00 3,487.36 P&M-024
(iii) 6 KL capacity
hour 0.146xL1+0.875 1,005.00 5,281.28 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 5879.000 5914.000 6033.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 3,527.16 3,547.89 3,619.65

e) Overhead charges @ 20% on @ 20% on @ 20% on


18,341.21 18,449.04 18,822.17
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
11,004.73 11,069.42 11,293.30
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 121,052.01 121,763.64 124,226.33
Rate per cum = (a+b+c+d+e+f)/15 8,070.13 8,117.58 8,281.76
Say 8,070.00 8,118.00 8,282.00
12.08 B PCC Grade M20
Case I PCC Grade M20 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,518.00 135,540.00 135,540.00 135,540.00 of Concrete -
20.04

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity
hour 0.109xL1+0.656 1,501.00 5,892.93 P&M-023
(ii) 12 KL capacity
hour 0.146xL1+0.875 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity
hour 0.292xL1+1.750 1,005.00 10,562.55 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 5936.000 5972.000 6091.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 7,122.22 7,165.43 7,309.00

e) Overhead charges @ 20% on @ 20% on @ 20% on


37,035.52 37,260.26 38,006.80
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
22,221.31 22,356.15 22,804.08
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 244,434.44 245,917.70 250,844.90
Rate per cum = (a+b+c+d+e+f)/30 8,147.81 8,197.26 8,361.50
Say 8,148.00 8,197.00 8,361.00
Case II PCC Grade M20 using batching plant transit mixer
& manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 4,518.00 67,770.00 67,770.00 67,770.00 of Concrete -
20.04

Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity
hour 0.055xL1+0.328 1,501.00 2,968.98 P&M-023
(ii) 12 KL capacity
hour 0.073xL1+0.438 1,327.00 3,487.36 P&M-024
(iii) 6 KL capacity
hour 0.146xL1+0.875 1,005.00 5,281.28 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6221.000 6256.000 6375.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 3,732.36 3,753.09 3,824.85

e) Overhead charges @ 20% on @ 20% on @ 20% on


19,408.25 19,516.08 19,889.21
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
11,644.95 11,709.65 11,933.53
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 128,094.47 128,806.10 131,268.79
Rate per cum = (a+b+c+d+e+f)/15 8,539.63 8,587.07 8,751.25
Say 8,540.00 8,587.00 8,751.00
12.08 C RCC Grade M20
Case I RCC Grade M20 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,793.00 143,790.00 143,790.00 143,790.00 of Concrete -
20.06

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity
hour 0.109xL1+0.656 1,501.00 5,892.93 P&M-023
(ii) 12 KL capacity
hour 0.146xL1+0.875 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity hour 0.292xL1+1.75 1,005.00 10,562.55 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6229.000 6265.000 6384.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 7,473.66 7,516.88 7,660.45

e) Overhead charges @ 20% on @ 20% on @ 20% on


38,863.05 39,087.79 39,834.33
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
23,317.83 23,452.67 23,900.60
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 256,496.14 257,979.39 262,906.60
Rate per cum = (a+b+c+d+e+f)/30 8,549.87 8,599.31 8,763.55
Say 8,550.00 8,599.00 8,764.00
Case II RCC Grade M20 using batching plant transit mixer
& manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 4,793.00 71,895.00 71,895.00 71,895.00 of Concrete -
20.06

Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.420 0.420 0.420 617.00 259.14 259.14 259.14 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity
hour 0.055xL1+0.328 1,501.00 2,968.98 P&M-023
(ii) 12 KL capacity
hour 0.073xL1+0.438 1,327.00 3,487.36 P&M-024
(iii) 6 KL capacity
hour 0.146xL1+0.875 1,005.00 5,281.28 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6532.000 6566.000 6686.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 3,918.80 3,939.54 4,011.30

e) Overhead charges @ 20% on @ 20% on @ 20% on


20,377.78 20,485.61 20,858.74
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
12,226.67 12,291.36 12,515.24
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 134,493.37 135,205.00 137,667.69
Rate per cum = (a+b+c+d+e+f)/15 8,966.22 9,013.67 9,177.85
Say 8,966.00 9,014.00 9,178.00
12.08 D PCC Grade M25
Case I PCC Grade M25 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,793.00 143,790.00 143,790.00 143,790.00 of Concrete -
20.06

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity
hour 0.109xL1+0.656 1,501.00 5,892.93 P&M-023
(ii) 12 KL capacity
hour 0.146xL1+0.875 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity hour 0.292xL1+1.75 1,005.00 10,562.55 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6211.000 6247.000 6366.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 7,452.22 7,495.43 7,639.00

e) Overhead charges @ 20% on @ 20% on @ 20% on


38,751.52 38,976.26 39,722.80
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
23,250.91 23,385.75 23,833.68
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 255,760.04 257,243.30 262,170.50
Rate per cum = (a+b+c+d+e+f)/30 8,525.33 8,574.78 8,739.02
Say 8,525.00 8,575.00 8,739.00
Case II PCC Grade M25 using batching plant transit mixer
& manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 4,793.00 71,895.00 71,895.00 71,895.00 of Concrete -
20.06

Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity
hour 0.055xL1+0.328 1,501.00 2,968.98 P&M-023
(ii) 12 KL capacity
hour 0.073xL1+0.438 1,327.00 3,487.36 P&M-024
(iii) 6 KL capacity
hour 0.146xL1+0.875 1,005.00 5,281.28 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6496.000 6531.000 6650.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 3,897.36 3,918.09 3,989.85

e) Overhead charges @ 20% on @ 20% on @ 20% on


20,266.25 20,374.08 20,747.21
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
12,159.75 12,224.45 12,448.33
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 133,757.27 134,468.90 136,931.59
Rate per cum = (a+b+c+d+e+f)/15 8,917.15 8,964.59 9,128.77
Say 8,917.00 8,965.00 9,129.00
12.08 E RCC Grade M25
Case I RCC Grade M25 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,945.00 148,350.00 148,350.00 148,350.00 of Concrete -
20.07

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity
hour 0.109xL1+0.656 1,501.00 5,892.93 P&M-023
(ii) 12 KL capacity
hour 0.146xL1+0.875 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity hour 0.292xL1+1.75 1,005.00 10,562.55 P&M-025
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6381.000 6417.000 6536.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 7,656.06 7,699.28 7,842.85

e) Overhead charges @ 20% on @ 20% on @ 20% on


39,811.53 40,036.27 40,782.81
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
23,886.92 24,021.76 24,469.69
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 262,756.11 264,239.36 269,166.57
Rate per cum = (a+b+c+d+e+f)/30 8,758.54 8,807.98 8,972.22
Say 8,759.00 8,808.00 8,972.00
Case II RCC Grade M25 using batching plant transit mixer
& manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 4,945.00 74,175.00 74,175.00 74,175.00 of Concrete -
20.07

Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.420 0.420 0.420 617.00 259.14 259.14 259.14 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity
hour 0.055xL1+0.328 1,501.00 2,968.98 P&M-023
(ii) 12 KL capacity
hour 0.073xL1+0.438 1,327.00 3,487.36 P&M-024
(iii) 6 KL capacity
hour 0.146xL1+0.875 1,005.00 5,281.28 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6684.000 6718.000 6838.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 4,010.00 4,030.74 4,102.50

e) Overhead charges @ 20% on @ 20% on @ 20% on


20,852.02 20,959.85 21,332.98
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
12,511.21 12,575.91 12,799.79
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 137,623.35 138,334.98 140,797.67
Rate per cum = (a+b+c+d+e+f)/15 9,174.89 9,222.33 9,386.51
Say 9,175.00 9,222.00 9,387.00
12.08 F PCC Grade M30
Case I PCC Grade M30 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,819.00 144,570.00 144,570.00 144,570.00 of Concrete -
20.08

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity
hour 0.109xL1+0.656 1,501.00 5,892.93 P&M-023
(ii) 12 KL capacity
hour 0.146xL1+0.875 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity hour 0.292xL1+1.75 1,005.00 10,562.55 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6237.000 6273.000 6392.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 7,483.42 7,526.63 7,670.20

e) Overhead charges @ 20% on @ 20% on @ 20% on


38,913.76 39,138.50 39,885.04
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
f) Contractor's profit @ 10% on @ 10% on @ 10% on
23,348.26 23,483.10 23,931.03
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 256,830.83 258,314.08 263,241.29
Rate per cum = (a+b+c+d+e+f)/30 8,561.03 8,610.47 8,774.71
Say 8,561.00 8,610.00 8,775.00
Case II PCC Grade M30 using batching plant transit mixer
& manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 4,819.00 72,285.00 72,285.00 72,285.00 of Concrete -
20.08

Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity
hour 0.055xL1+0.328 1,501.00 2,968.98 P&M-023
(ii) 12 KL capacity
hour 0.073xL1+0.438 1,327.00 3,487.36 P&M-024
(iii) 6 KL capacity
hour 0.146xL1+0.875 1,005.00 5,281.28 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6522.000 6557.000 6676.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 3,912.96 3,933.69 4,005.45

e) Overhead charges @ 20% on @ 20% on @ 20% on


20,347.37 20,455.20 20,828.33
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
12,208.42 12,273.12 12,497.00
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 134,292.66 135,004.29 137,466.99
Rate per cum = (a+b+c+d+e+f)/15 8,952.84 9,000.29 9,164.47
Say 8,953.00 9,000.00 9,164.00
12.08 G RCC Grade M30
Case I RCC Grade M30 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 5,032.00 150,960.00 150,960.00 150,960.00 of Concrete -
20.09

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity
hour 0.109xL1+0.656 1,501.00 5,892.93 P&M-023
(ii) 12 KL capacity
hour 0.146xL1+0.875 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity hour 0.292xL1+1.75 1,005.00 10,562.55 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6468.000 6504.000 6623.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 7,760.46 7,803.68 7,947.25

e) Overhead charges @ 20% on @ 20% on @ 20% on


40,354.41 40,579.15 41,325.69
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
24,212.65 24,347.49 24,795.42
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 266,339.12 267,822.37 272,749.58
Rate per cum = (a+b+c+d+e+f)/30 8,877.97 8,927.41 9,091.65
Say 8,878.00 8,927.00 9,092.00
Case II RCC Grade M30 using batching plant transit mixer
& manual placing
Unit = cum
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 5,032.00 75,480.00 75,480.00 75,480.00 of Concrete -
20.09

Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.420 0.420 0.420 617.00 259.14 259.14 259.14 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity
hour 0.055xL1+0.328 1,501.00 2,968.98 P&M-023
(ii) 12 KL capacity
hour 0.073xL1+0.438 1,327.00 3,487.36 P&M-024
(iii) 6 KL capacity
hour 0.146xL1+0.875 1,005.00 5,281.28 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6771.000 6805.000 6925.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 4,062.20 4,082.94 4,154.70

e) Overhead charges @ 20% on @ 20% on @ 20% on


21,123.46 21,231.29 21,604.42
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
12,674.08 12,738.77 12,962.65
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 139,414.86 140,126.49 142,589.18
Rate per cum = (a+b+c+d+e+f)/15 9,294.32 9,341.77 9,505.95
Say 9,294.00 9,342.00 9,506.00
12.08 H RCC Grade M35
Case I RCC Grade M35 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 5,186.00 155,580.00 155,580.00 155,580.00 of Concrete -
20.11

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity
hour 0.109xL1+0.656 1,501.00 5,892.93 P&M-023
(ii) 12 KL capacity
hour 0.146xL1+0.875 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity hour 0.292xL1+1.75 1,005.00 10,562.55 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6622.000 6658.000 6777.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 7,945.26 7,988.48 8,132.05

e) Overhead charges @ 20% on @ 20% on @ 20% on


41,315.37 41,540.11 42,286.65
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
24,789.22 24,924.06 25,371.99
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 272,681.45 274,164.71 279,091.91
Rate per cum = (a+b+c+d+e+f)/30 9,089.38 9,138.82 9,303.06
Say 9,089.00 9,139.00 9,303.00
Case II RCC Grade M35 using batching plant transit mixer
& manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 5,186.00 77,790.00 77,790.00 77,790.00 of Concrete -
20.11

Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
For pouring and placing
Mate day 0.420 0.420 0.420 617.00 259.14 259.14 259.14 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity
hour 0.055xL1+0.328 1,501.00 2,968.98 P&M-023
(ii) 12 KL capacity
hour 0.073xL1+0.438 1,327.00 3,487.36 P&M-024
(iii) 6 KL capacity
hour 0.146xL1+0.875 1,005.00 5,281.28 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6925.000 6959.000 7079.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 4,154.60 4,175.34 4,247.10

e) Overhead charges @ 20% on @ 20% on @ 20% on


21,603.94 21,711.77 22,084.90
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
12,962.37 13,027.06 13,250.94
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 142,586.02 143,297.65 145,760.35
Rate per cum = (a+b+c+d+e+f)/15 9,505.73 9,553.18 9,717.36
Say 9,506.00 9,553.00 9,717.00
12.08 I RCC Grade M40
Case I RCC Grade M40 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 5,519.00 165,570.00 165,570.00 165,570.00 of Concrete -
20.12

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity
hour 0.109xL1+0.656 1,501.00 5,892.93 P&M-023
(ii) 12 KL capacity
hour 0.146xL1+0.875 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity hour 0.292xL1+1.75 1,005.00 10,562.55 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6955.000 6991.000 7110.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 8,344.86 8,388.08 8,531.65

e) Overhead charges @ 20% on @ 20% on @ 20% on


43,393.29 43,618.03 44,364.57
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
26,035.97 26,170.82 26,618.74
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 286,395.72 287,878.98 292,806.18
Rate per cum = (a+b+c+d+e+f)/30 9,546.52 9,595.97 9,760.21
Say 9,547.00 9,596.00 9,760.00
Case II RCC Grade M40 using batching plant transit mixer
& manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 5,519.00 82,785.00 82,785.00 82,785.00 of Concrete -
20.12

Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.420 0.420 0.420 617.00 259.14 259.14 259.14 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity
hour 0.055xL1+0.328 1,501.00 2,968.98 P&M-023
(ii) 12 KL capacity
hour 0.073xL1+0.438 1,327.00 3,487.36 P&M-024
(iii) 6 KL capacity
hour 0.146xL1+0.875 1,005.00 5,281.28 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 7258.000 7292.000 7412.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 4,354.40 4,375.14 4,446.90

e) Overhead charges @ 20% on @ 20% on @ 20% on


22,642.90 22,750.73 23,123.86
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
13,585.74 13,650.44 13,874.32
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 149,443.16 150,154.79 152,617.48
Rate per cum = (a+b+c+d+e+f)/15 9,962.88 10,010.32 10,174.50
Say 9,963.00 10,010.00 10,174.00
12.08 J RCC Grade M45
Case I RCC Grade M45 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 5,663.00 169,890.00 169,890.00 169,890.00 of Concrete -
20.13

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity
hour 0.109xL1+0.656 1,501.00 5,892.93 P&M-023
(ii) 12 KL capacity
hour 0.146xL1+0.875 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity hour 0.292xL1+1.75 1,005.00 10,562.55 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 7099.000 7135.000 7254.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 8,517.66 8,560.88 8,704.45

e) Overhead charges @ 20% on @ 20% on @ 20% on


44,291.85 44,516.59 45,263.13
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
26,575.11 26,709.95 27,157.88
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 292,326.22 293,809.47 298,736.68
Rate per cum = (a+b+c+d+e+f)/30 9,744.21 9,793.65 9,957.89
Say 9,744.00 9,794.00 9,958.00
Case II RCC Grade M45 using batching plant transit mixer
& manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 5,663.00 84,945.00 84,945.00 84,945.00 of Concrete -
20.13

Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.420 0.420 0.420 617.00 259.14 259.14 259.14 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity
hour 0.055xL1+0.328 1,501.00 2,968.98 P&M-023
(ii) 12 KL capacity
hour 0.073xL1+0.438 1,327.00 3,487.36 P&M-024
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
(iii) 6 KL capacity
hour 0.146xL1+0.875 1,005.00 5,281.28 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 7402.000 7436.000 7556.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 4,440.80 4,461.54 4,533.30

e) Overhead charges @ 20% on @ 20% on @ 20% on


23,092.18 23,200.01 23,573.14
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
13,855.31 13,920.00 14,143.88
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 152,408.41 153,120.04 155,582.73
Rate per cum = (a+b+c+d+e+f)/15 10,160.56 10,208.00 10,372.18
Say 10,161.00 10,208.00 10,372.00
WELL FOUNDATION
12.09 1200 Providing and Constructing Temporary Island 24 m
diameter for Construction of Well Foundation for 8
m dia. Well.
A Assuming depth of water 1.0 m and height of island
to be 1.25 m.
Unit = 1 No
Taking output = 1 No.
a) Material
Earth (compacted) cum 565.487 565.487 565.487 45.00 25,446.90 25,446.90 25,446.90 M-093
Sand bags each 1125.000 1125.000 1125.000 8.48 9,540.00 9,540.00 9,540.00 M-160
b) Labour
Mate day 0.880 0.880 0.880 617.00 567.64 567.64 567.64 L-12
Mazdoor for filling sand bags, stitching and placing
day 22.000 22.000 22.000 511.52 11,764.96 11,764.96 11,764.96 L-13
c) Machinery
Crane with grab 1 cum capacity hour 30.000 30.000 30.000 6,330.45 189,913.50 189,913.50 189,913.50 P&M-099

Consumables @ 2.5 per cent of (c) above 4,747.84 4,747.84 4,747.84


d) Overhead charges @ 20% on (a+b+c) @ 20% on @ 20% on @ 20% on
48,396.17 48,396.17 48,396.17
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on (a+b+c+d) @ 10% on @ 10% on @ 10% on
29,037.70 29,037.70 29,037.70
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per No. (a+b+c+d+e) 319,414.71 319,414.71 319,414.71
Say 319,415.00 319,415.00 319,415.00
Note It is assumed that earth will be available within the
working space of crane with grab bucket.

12.09 B Assuming depth of water 4.0 m and height of island


4.5 m.
Unit = 1No
Taking output = 1 No
a) Material
Earth (compacted) cum 1356.000 1356.000 1356.000 45.00 61,020.00 61,020.00 61,020.00 M-093
Sand bags each 9000.000 9000.000 9000.000 8.48 76,320.00 76,320.00 76,320.00 M-160
Wooden ballies 8" Dia and 9 m long each 143.000 143.000 143.000 529.40 75,704.13 75,704.13 75,704.13 M-196
Wooden ballies 2" Dia for bracing metre 285.000 285.000 285.000 21.89 6,239.36 6,239.36 6,239.36 M-195
b) Labour
Mate day 8.400 8.400 8.400 617.00 5,182.80 5,182.80 5,182.80 L-12
Mazdoor for piling 8" dia ballies for piling 8" dia
ballies day 27.000 27.000 27.000 511.52 13,811.04 13,811.04 13,811.04 L-13
Mazdoor for bracing with 2" dia ballies day 18.000 18.000 18.000 511.52 9,207.36 9,207.36 9,207.36 L-13
Mazdoor for filling sand bags, stitching and placing
day 165.000 165.000 165.000 511.52 84,400.80 84,400.80 84,400.80 L-13
c) Machinery
Crane with grab 1 cum capacity hour 75.000 75.000 75.000 6,330.45 474,783.75 474,783.75 474,783.75 P&M-099
Consumables and other arrangements for piling
ballies @ 2.5 per cent of (a+b+c). 20,166.73 20,166.73 20,166.73
d) Overhead charges @ 20% on @ 20% on @ 20% on
165,367.19 165,367.19 165,367.19
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
99,220.32 99,220.32 99,220.32
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per No. (a+b+c+d+e) ### 1,091,423.48 1,091,423.48
Say ### 1,091,423.00 1,091,423.00
Note For other well diameters rate can be worked out on
the basis of cross-sectional area of well. The
diameter of the island shall be in the conformity
with clause 1203.4 of MoRTH specifications.

12.09 C Providing and constructing one span service road


to reach island location from one pier location to
another pier location
Assuming span length 30 m, width of service road
10 m and depth of water 1 m
Unit = 1 meter
Taking output = 30 metre 450.000
a) Material
Earth cum 450.000 450.000 450.000 45.00 20,250.00 20,250.00 20,250.00 M-093
Sand bags each 300.000 300.000 300.000 8.48 2,544.00 2,544.00 2,544.00 M-160
b) Labour
Mate day 0.240 0.240 0.240 617.00 148.08 148.08 148.08 L-12
Mazdoor for filling sand bags, stitching and placing
day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
c) Machinery
Front end Loader 1 cum capacity hour 27.000 27.000 27.000 1,112.00 30,024.00 30,024.00 30,024.00 P&M-013
Tipper 5.5 cum capacity hour 28.000 28.000 28.000 1,731.45 48,480.60 48,480.60 48,480.60 P&M-017
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
d) Overhead charges @ 20% on @ 20% on @ 20% on
20,903.16 20,903.16 20,903.16
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
12,541.90 12,541.90 12,541.90
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 30 m (a+b+c+d+e) 137,960.86 137,960.86 137,960.86
Rate per m (a+b+c+d+e)/30 4,598.70 4,598.70 4,598.70
Say 4,599.00 4,599.00 4,599.00
12.10 1200 & Providing and Laying Cutting Edge of Mild Steel
1900 weighing 40 kg per metre for Well Foundation
complete as per Drawing and Technical
Specification.
Unit = 1 MT
Taking output = 1.0 MT
a) Material
Structural steel in plates, angles, etc including 5
per cent wastage tonne 1.050 1.050 1.050 63,806.54 66,996.87 66,996.87 66,996.87 M-181
Nuts & bolts Kg 20.000 20.000 20.000 64.83 1,296.54 1,296.54 1,296.54 M-129
b) Machinery
Hydra Crane of capacity 10T for lifting shifting hour 8.000 8.000 8.000 1,240.05 9,920.40 9,920.40 9,920.40 P&M-104
Tipper for Transportation to site
(i) 18 cum capacity t.km 1.05 x L1 7.51 236.52 P&M-117
(ii) 14 cum capacity t.km 1.05 x L1 8.52 268.46 P&M-120
(iii) 10 cum capacity t.km 1.05 x L1 10.53 331.67 P&M-123
c) Labour
(for cutting, bending, making holes, joining, welding
and erecting in position)
Mate day 1.080 1.080 1.080 617.00 666.36 666.36 666.36 L-12
Fitter day 4.500 4.500 4.500 738.00 3,321.00 3,321.00 3,321.00 L-08
Blacksmith day 4.500 4.500 4.500 738.00 3,321.00 3,321.00 3,321.00 L-02
Welder day 4.500 4.500 4.500 738.00 3,321.00 3,321.00 3,321.00 L-02
Mazdoor day 13.500 13.500 13.500 511.52 6,905.52 6,905.52 6,905.52 L-13
Electrodes, cutting gas and other consumables @
10 per cent of cost of (a) above 6,829.34 6,829.34 6,829.34

d) Overhead charges @ 20% on @ 20% on @ 20% on


20,562.91 20,569.30 20,581.94
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
12,337.75 12,341.58 12,349.16
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per MT (a+b+c+d) 135,715.21 135,757.37 135,840.81
Say 135,715.00 135,757.00 135,841.00
12.11 1200, Plain/Reinforced Cement Concrete, in Well
1500 & Foundation complete as per Drawing and
1700 Technical Specification.
A Well curb
(i) RCC M20 Grade
12.11 A Case I RCC Grade M20 using batching plant & Concrete
(i) pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,533.00 135,990.00 135,990.00 135,990.00 of Concrete -
20.05

b) Labour
For pouring and placing
Mate day 0.133 0.133 0.133 617.00 82.06 82.06 82.06 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 20 per cent on cost of concrete
i.e. cost of material, labour and machinery 34,520.77 34,520.77 34,520.77

e) Overhead charges @ 20% on @ 20% on @ 20% on


41,424.92 41,424.92 41,424.92
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
24,854.95 24,854.95 24,854.95
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 273,404.46 273,404.46 273,404.46
Rate per cum = (a+b+c+d+e+f)/30 9,113.48 9,113.48 9,113.48
Say 9,113.00 9,113.00 9,113.00
12.11 A Case II RCC Grade M20 using batching plant & manual
(i) placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 4,533.00 67,995.00 67,995.00 67,995.00 of Concrete -
20.05

b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 20 per cent on cost of concrete
i.e. cost of material, labour and machinery 18,029.22 18,029.22 18,029.22

e) Overhead charges @ 20% on @ 20% on @ 20% on


21,635.06 21,635.06 21,635.06
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
12,981.04 12,981.04 12,981.04
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 142,791.41 142,791.41 142,791.41
Rate per cum = (a+b+c+d+e+f)/15 9,519.43 9,519.43 9,519.43
Say 9,519.00 9,519.00 9,519.00
(ii) RCC M25 Grade
12.11 A Case I RCC Grade M25 using batching plant & Concrete
(ii) pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,945.00 148,350.00 148,350.00 148,350.00 of Concrete -
20.07

b) Labour
For pouring and placing
Mate day 0.133 0.133 0.133 617.00 82.06 82.06 82.06 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 20 per cent on cost of concrete
i.e. cost of material, labour and machinery 36,992.77 36,992.77 36,992.77

e) Overhead charges @ 20% on @ 20% on @ 20% on


44,391.32 44,391.32 44,391.32
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
26,634.79 26,634.79 26,634.79
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 292,982.70 292,982.70 292,982.70
Rate per cum = (a+b+c+d+e+f)/30 9,766.09 9,766.09 9,766.09
Say 9,766.00 9,766.00 9,766.00
12.11 A Case II RCC Grade M25 using batching plant & manual
(ii) placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 4,945.00 74,175.00 74,175.00 74,175.00 of Concrete -
20.07

b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 20 per cent on cost of concrete
i.e. cost of material, labour and machinery 19,265.22 19,265.22 19,265.22

e) Overhead charges @ 20% on @ 20% on @ 20% on


23,118.26 23,118.26 23,118.26
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
13,870.96 13,870.96 13,870.96
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 152,580.53 152,580.53 152,580.53
Rate per cum = (a+b+c+d+e+f)/15 10,172.04 10,172.04 10,172.04
Say 10,172.00 10,172.00 10,172.00

12.11 A (iii) RCC M30 Grade


12.11 A Case I RCC Grade M30 using batching plant & Concrete
(iii) pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 5,032.00 150,960.00 150,960.00 150,960.00 of Concrete -
20.09

b) Labour
For pouring and placing
Mate day 0.133 0.133 0.133 617.00 82.06 82.06 82.06 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 20 per cent on cost of concrete
i.e. cost of material, labour and machinery 37,514.77 37,514.77 37,514.77

e) Overhead charges @ 20% on @ 20% on @ 20% on


45,017.72 45,017.72 45,017.72
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
27,010.63 27,010.63 27,010.63
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 297,116.94 297,116.94 297,116.94
Rate per cum = (a+b+c+d+e+f)/30 9,903.90 9,903.90 9,903.90
Say 9,904.00 9,904.00 9,904.00
12.11 A Case II RCC Grade M30 using batching plant & manual
(iii) placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 5,032.00 75,480.00 75,480.00 75,480.00 of Concrete -
20.09

b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 20 per cent on cost of concrete
i.e. cost of material, labour and machinery 19,526.22 19,526.22 19,526.22

e) Overhead charges @ 20% on @ 20% on @ 20% on


23,431.46 23,431.46 23,431.46
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
14,058.88 14,058.88 14,058.88
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 154,647.65 154,647.65 154,647.65
Rate per cum = (a+b+c+d+e+f)/15 10,309.84 10,309.84 10,309.84
Say 10,310.00 10,310.00 10,310.00
Note. If curb concrete is carried out within steel liner, cost
of formwork shall be excluded.
12.11 A (iv) RCC M35 Grade
12.11 A Case I RCC Grade M35 using batching plant & Concrete
(iv) pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 5,186.00 155,580.00 155,580.00 155,580.00 of Concrete -
20.11

b) Labour
For pouring and placing
Mate day 0.133 0.133 0.133 617.00 82.06 82.06 82.06 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 20 per cent on cost of concrete
i.e. cost of material, labour and machinery 38,438.77 38,438.77 38,438.77

e) Overhead charges @ 20% on @ 20% on @ 20% on


46,126.52 46,126.52 46,126.52
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
27,675.91 27,675.91 27,675.91
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 304,435.02 304,435.02 304,435.02
Rate per cum = (a+b+c+d+e+f)/30 10,147.83 10,147.83 10,147.83
Say 10,148.00 10,148.00 10,148.00
12.11 A Case II RCC Grade M35 using batching plant & manual
(iv) placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 5,186.00 77,790.00 77,790.00 77,790.00 of Concrete -
20.11

b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 20 per cent on cost of concrete
i.e. cost of material, labour and machinery 19,988.22 19,988.22 19,988.22

e) Overhead charges @ 20% on @ 20% on @ 20% on


23,985.86 23,985.86 23,985.86
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
14,391.52 14,391.52 14,391.52
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 158,306.69 158,306.69 158,306.69
Rate per cum = (a+b+c+d+e+f)/15 10,553.78 10,553.78 10,553.78
Say 10,554.00 10,554.00 10,554.00
Note. If curb concrete is carried out within steel liner, cost
of formwork shall be excluded.

12.11 A (v) RCC M40 Grade


12.11 A Case I RCC Grade M40 using batching plant & Concrete
(v) pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 5,519.00 165,570.00 165,570.00 165,570.00 of Concrete -
20.12

b) Labour
For pouring and placing
Mate day 0.133 0.133 0.133 617.00 82.06 82.06 82.06 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 20 per cent on cost of concrete
i.e. cost of material, labour and machinery 40,436.77 40,436.77 40,436.77

e) Overhead charges @ 20% on @ 20% on @ 20% on


48,524.12 48,524.12 48,524.12
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
29,114.47 29,114.47 29,114.47
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 320,259.18 320,259.18 320,259.18
Rate per cum = (a+b+c+d+e+f)/30 10,675.31 10,675.31 10,675.31
Say 10,675.00 10,675.00 10,675.00
12.11 A Case II RCC Grade M40 using batching plant & manual
(v) placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 5,519.00 82,785.00 82,785.00 82,785.00 of Concrete -
20.12

b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 20 per cent on cost of concrete
i.e. cost of material, labour and machinery 20,987.22 20,987.22 20,987.22

e) Overhead charges @ 20% on @ 20% on @ 20% on


25,184.66 25,184.66 25,184.66
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
15,110.80 15,110.80 15,110.80
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 166,218.77 166,218.77 166,218.77
Rate per cum = (a+b+c+d+e+f)/15 11,081.25 11,081.25 11,081.25
Say 11,081.00 11,081.00 11,081.00
Note. If curb concrete is carried out within steel liner, cost
of formwork shall be excluded.
12.11 B Well steining
(i) PCC M15 Grade
12.11 B Case I PCC Grade M15 using batching plant & Concrete
(i) pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,176.00 125,280.00 125,280.00 125,280.00 of Concrete -
20.03

b) Labour
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
For pouring and placing
Mate day 0.093 0.093 0.093 617.00 57.38 57.38 57.38 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 16,135.76 16,135.76 16,135.76

e) Overhead charges @ 20% on @ 20% on @ 20% on


35,498.68 35,498.68 35,498.68
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
21,299.21 21,299.21 21,299.21
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 234,291.28 234,291.28 234,291.28
Rate per cum = (a+b+c+d+e+f)/30 7,809.71 7,809.71 7,809.71
Say 7,810.00 7,810.00 7,810.00
12.11 B Case II PCC Grade M15 using batching plant & manual
(i) placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 4,176.00 62,640.00 62,640.00 62,640.00 of Concrete -
20.03

b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 8,479.11 8,479.11 8,479.11

e) Overhead charges @ 20% on @ 20% on @ 20% on


18,654.04 18,654.04 18,654.04
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
11,192.42 11,192.42 11,192.42
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 123,116.67 123,116.67 123,116.67
Rate per cum = (a+b+c+d+e+f)/15 8,207.78 8,207.78 8,207.78
Say 8,208.00 8,208.00 8,208.00
12.11 B (ii) PCC M20 Grade
12.11 B Case I PCC Grade M20 using batching plant & Concrete
(ii) pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,518.00 135,540.00 135,540.00 135,540.00 of Concrete -
20.04

b) Labour
For pouring and placing
Mate day 0.093 0.093 0.093 617.00 57.38 57.38 57.38 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 17,161.76 17,161.76 17,161.76

e) Overhead charges @ 20% on @ 20% on @ 20% on


37,755.88 37,755.88 37,755.88
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
22,653.53 22,653.53 22,653.53
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 249,188.80 249,188.80 249,188.80
Rate per cum = (a+b+c+d+e+f)/30 8,306.29 8,306.29 8,306.29
Say 8,306.00 8,306.00 8,306.00
12.11 B Case II PCC Grade M20 using batching plant & manual
(ii) placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 4,518.00 67,770.00 67,770.00 67,770.00 of Concrete -
20.04

b) Labour
For pouring and placing
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 8,992.11 8,992.11 8,992.11

e) Overhead charges @ 20% on @ 20% on @ 20% on


19,782.64 19,782.64 19,782.64
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
11,869.58 11,869.58 11,869.58
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 130,565.43 130,565.43 130,565.43
Rate per cum = (a+b+c+d+e+f)/15 8,704.36 8,704.36 8,704.36
Say 8,704.00 8,704.00 8,704.00
12.11 B (iii) RCC M20 Grade
12.11 B Case I RCC Grade M20 using batching plant & Concrete
(iii) pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,533.00 135,990.00 135,990.00 135,990.00 of Concrete -
20.05

b) Labour
For pouring and placing
Mate day 0.133 0.133 0.133 617.00 82.06 82.06 82.06 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 17,260.38 17,260.38 17,260.38

e) Overhead charges @ 20% on @ 20% on @ 20% on


37,972.84 37,972.84 37,972.84
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
22,783.71 22,783.71 22,783.71
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 250,620.76 250,620.76 250,620.76
Rate per cum = (a+b+c+d+e+f)/30 8,354.03 8,354.03 8,354.03
Say 8,354.00 8,354.00 8,354.00
12.11 B Case II RCC Grade M20 using batching plant & manual
(iii) placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 4,533.00 67,995.00 67,995.00 67,995.00 of Concrete -
20.05

b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 9,014.61 9,014.61 9,014.61

e) Overhead charges @ 20% on @ 20% on @ 20% on


19,832.14 19,832.14 19,832.14
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
11,899.28 11,899.28 11,899.28
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 130,892.13 130,892.13 130,892.13
Rate per cum = (a+b+c+d+e+f)/15 8,726.14 8,726.14 8,726.14
Say 8,726.00 8,726.00 8,726.00
12.11 B (iv) PCC M25 Grade
12.11 B Case I PCC Grade M25 using batching plant & Concrete
(iv) pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,793.00 143,790.00 143,790.00 143,790.00 of Concrete -
20.06

b) Labour
For pouring and placing
Mate day 0.093 0.093 0.093 617.00 57.38 57.38 57.38 L-12
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 17,986.76 17,986.76 17,986.76

e) Overhead charges @ 20% on @ 20% on @ 20% on


39,570.88 39,570.88 39,570.88
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
23,742.53 23,742.53 23,742.53
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 261,167.80 261,167.80 261,167.80
Rate per cum = (a+b+c+d+e+f)/30 8,705.59 8,705.59 8,705.59
Say 8,706.00 8,706.00 8,706.00
12.11 B Case II PCC Grade M25 using batching plant & manual
(iv) placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 4,793.00 71,895.00 71,895.00 71,895.00 of Concrete -
20.06

b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 9,404.61 9,404.61 9,404.61

e) Overhead charges @ 20% on @ 20% on @ 20% on


20,690.14 20,690.14 20,690.14
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
12,414.08 12,414.08 12,414.08
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 136,554.93 136,554.93 136,554.93
Rate per cum = (a+b+c+d+e+f)/15 9,103.66 9,103.66 9,103.66
Say 9,104.00 9,104.00 9,104.00
12.11 B (v) RCC M25 Grade
12.11 B Case I RCC Grade M25 using batching plant & Concrete
(v) pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,945.00 148,350.00 148,350.00 148,350.00 of Concrete -
20.07

b) Labour
For pouring and placing
Mate day 0.133 0.133 0.133 617.00 82.06 82.06 82.06 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 18,496.38 18,496.38 18,496.38

e) Overhead charges @ 20% on @ 20% on @ 20% on


40,692.04 40,692.04 40,692.04
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
24,415.23 24,415.23 24,415.23
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 268,567.48 268,567.48 268,567.48
Rate per cum = (a+b+c+d+e+f)/30 8,952.25 8,952.25 8,952.25
Say 8,952.00 8,952.00 8,952.00
12.11 B Case II RCC Grade M25 using batching plant & manual
(v) placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 4,945.00 74,175.00 74,175.00 74,175.00 of Concrete -
20.07

b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 9,632.61 9,632.61 9,632.61

e) Overhead charges @ 20% on @ 20% on @ 20% on


21,191.74 21,191.74 21,191.74
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
12,715.04 12,715.04 12,715.04
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 139,865.49 139,865.49 139,865.49
Rate per cum = (a+b+c+d+e+f)/15 9,324.37 9,324.37 9,324.37
Say 9,324.00 9,324.00 9,324.00
12.11 B (vi) PCC M30 Grade
12.11 B Case I PCC Grade M30 using batching plant & Concrete
(vi) pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,819.00 144,570.00 144,570.00 144,570.00 of Concrete -
20.08

b) Labour
For pouring and placing
Mate day 0.093 0.093 0.093 617.00 57.38 57.38 57.38 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 18,064.76 18,064.76 18,064.76

e) Overhead charges @ 20% on @ 20% on @ 20% on


39,742.48 39,742.48 39,742.48
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
23,845.49 23,845.49 23,845.49
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 262,300.36 262,300.36 262,300.36
Rate per cum = (a+b+c+d+e+f)/30 8,743.35 8,743.35 8,743.35
Say 8,743.00 8,743.00 8,743.00
12.11 B Case II PCC Grade M30 using batching plant & manual
(vi) placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 4,819.00 72,285.00 72,285.00 72,285.00 of Concrete -
20.08

b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 9,443.61 9,443.61 9,443.61

e) Overhead charges @ 20% on @ 20% on @ 20% on


20,775.94 20,775.94 20,775.94
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
12,465.56 12,465.56 12,465.56
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 137,121.21 137,121.21 137,121.21
Rate per cum = (a+b+c+d+e+f)/15 9,141.41 9,141.41 9,141.41
Say 9,141.00 9,141.00 9,141.00
12.11 B (vii) RCC M30 Grade
12.11 B Case I RCC Grade M30 using batching plant & Concrete
(vii) pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 5,032.00 150,960.00 150,960.00 150,960.00 of Concrete -
20.09

b) Labour
For pouring and placing
Mate day 0.133 0.133 0.133 617.00 82.06 82.06 82.06 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 18,757.38 18,757.38 18,757.38

e) Overhead charges @ 20% on @ 20% on @ 20% on


41,266.24 41,266.24 41,266.24
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
24,759.75 24,759.75 24,759.75
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 272,357.20 272,357.20 272,357.20
Rate per cum = (a+b+c+d+e+f)/30 9,078.57 9,078.57 9,078.57
Say 9,079.00 9,079.00 9,079.00
12.11 B Case II RCC Grade M30 using batching plant & manual
(vii) placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 5,032.00 75,480.00 75,480.00 75,480.00 of Concrete -
20.09

b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 9,763.11 9,763.11 9,763.11

e) Overhead charges @ 20% on @ 20% on @ 20% on


21,478.84 21,478.84 21,478.84
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
12,887.30 12,887.30 12,887.30
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 141,760.35 141,760.35 141,760.35
Rate per cum = (a+b+c+d+e+f)/15 9,450.69 9,450.69 9,450.69
Say 9,451.00 9,451.00 9,451.00
12.11 B (viii) RCC M35 Grade
12.11 B Case I RCC Grade M35 using batching plant & Concrete
(viii) pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 5,186.00 155,580.00 155,580.00 155,580.00 of Concrete -
20.11

b) Labour
For pouring and placing
Mate day 0.133 0.133 0.133 617.00 82.06 82.06 82.06 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 19,219.38 19,219.38 19,219.38

e) Overhead charges @ 20% on @ 20% on @ 20% on


42,282.64 42,282.64 42,282.64
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
25,369.59 25,369.59 25,369.59
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 279,065.44 279,065.44 279,065.44
Rate per cum = (a+b+c+d+e+f)/30 9,302.18 9,302.18 9,302.18
Say 9,302.00 9,302.00 9,302.00
12.11 B Case II RCC Grade M35 using batching plant & manual
(viii) placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 5,186.00 77,790.00 77,790.00 77,790.00 of Concrete -
20.11

b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 9,994.11 9,994.11 9,994.11

e) Overhead charges @ 20% on @ 20% on @ 20% on


21,987.04 21,987.04 21,987.04
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
13,192.22 13,192.22 13,192.22
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 145,114.47 145,114.47 145,114.47
Rate per cum = (a+b+c+d+e+f)/15 9,674.30 9,674.30 9,674.30
Say 9,674.00 9,674.00 9,674.00
12.11 B (ix) RCC M40 Grade
12.11 B Case I RCC Grade M40 using batching plant & Concrete
(ix) pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 5,519.00 165,570.00 165,570.00 165,570.00 of Concrete -
20.12

b) Labour
For pouring and placing
Mate day 0.133 0.133 0.133 617.00 82.06 82.06 82.06 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 20,218.38 20,218.38 20,218.38

e) Overhead charges @ 20% on @ 20% on @ 20% on


44,480.44 44,480.44 44,480.44
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
26,688.27 26,688.27 26,688.27
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 293,570.92 293,570.92 293,570.92
Rate per cum = (a+b+c+d+e+f)/30 9,785.70 9,785.70 9,785.70
Say 9,786.00 9,786.00 9,786.00
12.11 B Case II RCC Grade M40 using batching plant & manual
(ix) placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 5,519.00 82,785.00 82,785.00 82,785.00 of Concrete -
20.12

b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 10,493.61 10,493.61 10,493.61

e) Overhead charges @ 20% on @ 20% on @ 20% on


23,085.94 23,085.94 23,085.94
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
13,851.56 13,851.56 13,851.56
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 152,367.21 152,367.21 152,367.21
Rate per cum = (a+b+c+d+e+f)/15 10,157.81 10,157.81 10,157.81
Say 10,158.00 10,158.00 10,158.00
12.11 C C Bottom Plug
(i) PCC Grade M20
Case I PCC Grade M20 using batching plant & Concrete
pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,518.00 135,540.00 135,540.00 135,540.00 of Concrete -
20.04

b) Labour
For pouring and placing
Mate day 0.093 0.093 0.093 617.00 57.38 57.38 57.38 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Hydra Crane for holding tremie pipe hour 0.650 0.650 0.650 1,083.60 704.34 704.34 704.34 P&M-102
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 5745.000 5745.000 5745.000
Add 5 per cent of cost of material and labour
towards cost of forming sump, protective bunds,
chiselling and making arrangements for under 8,616.10 8,616.10 8,616.10
water concreting with tremie pipe..

d) Overhead charges @ 20% on @ 20% on @ 20% on


36,187.61 36,187.61 36,187.61
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
21,712.57 21,712.57 21,712.57
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 30 cum = a+b+c+d+e 238,838.25 238,838.25 238,838.25
Rate per cum = (a+b+c+d+e)/30 7,961.27 7,961.27 7,961.27
Say 7,961.00 7,961.00 7,961.00
Case II PCC Grade M20 using batching plant & manual
placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 4,518.00 67,770.00 67,770.00 67,770.00 of Concrete -
20.04

b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Hydra Crane for holding tremie pipe hour 0.833 0.833 0.833 1,083.60 903.00 903.00 903.00 P&M-102
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6055.000 6055.000 6055.000
Add 5 per cent of cost of material and labour
towards cost of forming sump, protective bunds,
chiselling and making arrangements for under 4,541.20 4,541.20 4,541.20
water concreting with tremie pipe..

d) Overhead charges @ 20% on @ 20% on @ 20% on


19,073.06 19,073.06 19,073.06
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
11,443.84 11,443.84 11,443.84
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 15 cum = a+b+c+d+e 125,882.19 125,882.19 125,882.19
Rate per cum = (a+b+c+d+e)/15 8,392.15 8,392.15 8,392.15
Say 8,392.00 8,392.00 8,392.00
12.11 C (ii) PCC Grade M25
Case I PCC Grade M25 using batching plant & Concrete
pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,793.00 143,790.00 143,790.00 143,790.00 of Concrete -
20.06

b) Labour
For pouring and placing
Mate day 0.093 0.093 0.093 617.00 57.38 57.38 57.38 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Hydra Crane for holding tremie pipe hour 0.650 0.650 0.650 1,083.60 704.34 704.34 704.34 P&M-102
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6020.000 6020.000 6020.000
Add 5 per cent of cost of material and labour
towards cost of forming sump, protective bunds,
chiselling and making arrangements for under 9,028.60 9,028.60 9,028.60
water concreting with tremie pipe..

d) Overhead charges @ 20% on @ 20% on @ 20% on


37,920.11 37,920.11 37,920.11
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
22,752.07 22,752.07 22,752.07
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 30 cum = a+b+c+d+e 250,272.75 250,272.75 250,272.75
Rate per cum = (a+b+c+d+e)/30 8,342.42 8,342.42 8,342.42
Say 8,342.00 8,342.00 8,342.00
Case II PCC Grade M25 using batching plant & manual
placing
Unit = cum
Taking output = 15 cum
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 4,793.00 71,895.00 71,895.00 71,895.00 of Concrete -
20.06

b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Hydra Crane for holding tremie pipe hour 0.833 0.833 0.833 1,083.60 903.00 903.00 903.00 P&M-102
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6330.000 6330.000 6330.000
Add 5 per cent of cost of material and labour
towards cost of forming sump, protective bunds,
chiselling and making arrangements for under 4,747.45 4,747.45 4,747.45
water concreting with tremie pipe..

d) Overhead charges @ 20% on @ 20% on @ 20% on


19,939.31 19,939.31 19,939.31
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
11,963.59 11,963.59 11,963.59
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 15 cum = a+b+c+d+e 131,599.44 131,599.44 131,599.44
Rate per cum = (a+b+c+d+e)/15 8,773.30 8,773.30 8,773.30
Say 8,773.00 8,773.00 8,773.00
12.11 C (iii) PCC Grade M30
Case I PCC Grade M30 using batching plant & Concrete
pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,819.00 144,570.00 144,570.00 144,570.00 of Concrete -
20.08

b) Labour
For pouring and placing
Mate day 0.093 0.093 0.093 617.00 57.38 57.38 57.38 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Hydra Crane for holding tremie pipe hour 0.650 0.650 0.650 1,083.60 704.34 704.34 704.34 P&M-102
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6046.000 6046.000 6046.000
Add 5 per cent of cost of material and labour
towards cost of forming sump, protective bunds,
chiselling and making arrangements for under 9,067.60 9,067.60 9,067.60
water concreting with tremie pipe..

d) Overhead charges @ 20% on @ 20% on @ 20% on


38,083.91 38,083.91 38,083.91
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
22,850.35 22,850.35 22,850.35
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 30 cum = a+b+c+d+e 251,353.83 251,353.83 251,353.83
Rate per cum = (a+b+c+d+e)/30 8,378.46 8,378.46 8,378.46
Say 8,378.00 8,378.00 8,378.00
Case II PCC Grade M30 using batching plant & manual
placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 4,819.00 72,285.00 72,285.00 72,285.00 of Concrete -
20.08

b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Hydra Crane for holding tremie pipe hour 0.833 0.833 0.833 1,083.60 903.00 903.00 903.00 P&M-102
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6356.000 6356.000 6356.000
Add 5 per cent of cost of material and labour
towards cost of forming sump, protective bunds,
chiselling and making arrangements for under 4,766.95 4,766.95 4,766.95
water concreting with tremie pipe..
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
d) Overhead charges @ 20% on @ 20% on @ 20% on
20,021.21 20,021.21 20,021.21
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
12,012.73 12,012.73 12,012.73
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 15 cum = a+b+c+d+e 132,139.98 132,139.98 132,139.98
Rate per cum = (a+b+c+d+e)/15 8,809.33 8,809.33 8,809.33
Say 8,809.00 8,809.00 8,809.00
12.11 C (iv) PCC Grade M35
Case I PCC Grade M35 using batching plant & Concrete
pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 5,102.00 153,060.00 153,060.00 153,060.00 of Concrete -
20.1

b) Labour
For pouring and placing
Mate day 0.093 0.093 0.093 617.00 57.38 57.38 57.38 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Hydra Crane for holding tremie pipe hour 0.650 0.650 0.650 1,083.60 704.34 704.34 704.34 P&M-102
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6329.000 6329.000 6329.000
Add 5 per cent of cost of material and labour
towards cost of forming sump, protective bunds,
chiselling and making arrangements for under 9,492.10 9,492.10 9,492.10
water concreting with tremie pipe..

d) Overhead charges @ 20% on @ 20% on @ 20% on


39,866.81 39,866.81 39,866.81
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
23,920.09 23,920.09 23,920.09
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 30 cum = a+b+c+d+e 263,120.97 263,120.97 263,120.97
Rate per cum = (a+b+c+d+e)/30 8,770.70 8,770.70 8,770.70
Say 8,771.00 8,771.00 8,771.00
Case II PCC Grade M35 using batching plant & manual
placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 5,102.00 76,530.00 76,530.00 76,530.00 of Concrete -
20.1

b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Hydra Crane for holding tremie pipe hour 0.833 0.833 0.833 1,083.60 903.00 903.00 903.00 P&M-102
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6639.000 6639.000 6639.000
Add 5 per cent of cost of material and labour
towards cost of forming sump, protective bunds,
chiselling and making arrangements for under 4,979.20 4,979.20 4,979.20
water concreting with tremie pipe..

d) Overhead charges @ 20% on @ 20% on @ 20% on


20,912.66 20,912.66 20,912.66
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
12,547.60 12,547.60 12,547.60
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 15 cum = a+b+c+d+e 138,023.55 138,023.55 138,023.55
Rate per cum = (a+b+c+d+e)/15 9,201.57 9,201.57 9,201.57
Say 9,202.00 9,202.00 9,202.00
12.11 D Intermediate plug
(i) Grade M20 PCC
Same as in bottom plug concrete, excluding cost of
forming sump, protective bunds, chiseling etc.

12.11 D Case I PCC Grade M20 using batching plant & Concrete
(i) pump
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 5,745.00 5,745.00 5,745.00
12.11 C (i)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,149.00 1,149.00 1,149.00
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
689.40 689.40 689.40
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 7,583.40 7,583.40 7,583.40
Say 7,583.00 7,583.00 7,583.00
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
12.11 D Case II PCC Grade M20 using batching plant & manual
(i) placing
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 6,055.00 6,055.00 6,055.00
12.11 C (i)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,211.00 1,211.00 1,211.00
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
726.60 726.60 726.60
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 7,992.60 7,992.60 7,992.60
Say 7,993.00 7,993.00 7,993.00
12.11 D (ii) Grade M25 PCC
Same as in bottom plug concrete, excluding cost of
forming sump, protective bunds, chiseling etc.

12.11 D Case I PCC Grade M25 using batching plant & Concrete
(ii) pump
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 6,020.00 6,020.00 6,020.00
12.11 C (ii)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,204.00 1,204.00 1,204.00
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
722.40 722.40 722.40
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 7,946.40 7,946.40 7,946.40
Say 7,946.00 7,946.00 7,946.00
12.11 D Case II PCC Grade M25 using batching plant & manual
(ii) placing
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 6,330.00 6,330.00 6,330.00
12.11 C (ii)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,266.00 1,266.00 1,266.00
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
759.60 759.60 759.60
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 8,355.60 8,355.60 8,355.60
Say 8,356.00 8,356.00 8,356.00
'12.11 D (iii) Grade M30 PCC

Same as in bottom plug concrete, excluding cost of


forming sump, protective bunds, chiseling etc.

12.11 D Case I PCC Grade M30 using batching plant & Concrete
(iii) pump
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 6,046.00 6,046.00 6,046.00
12.11 C (iii)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,209.20 1,209.20 1,209.20
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
725.52 725.52 725.52
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 7,980.72 7,980.72 7,980.72
Say 7,981.00 7,981.00 7,981.00
12.11 D Case II PCC Grade M30 using batching plant & manual
(iii) placing
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 6,356.00 6,356.00 6,356.00
12.11 C (iii)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,271.20 1,271.20 1,271.20
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
762.72 762.72 762.72
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 8,389.92 8,389.92 8,389.92
Say 8,390.00 8,390.00 8,390.00
12.11 E Top plug
(i) Grade M15 PCC
Same as Item 12.8(a) excluding formwork
12.11 E Case I PCC Grade M15 using batching plant & Concrete
(i) pump
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 5,594.00 5,630.00 5,749.00
12.08 (A)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,118.80 1,126.00 1,149.80
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
671.28 675.60 689.88
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 7,384.08 7,431.60 7,588.68
Say 7,384.00 7,432.00 7,589.00
12.11 E Case II PCC Grade M15 using batching plant & manual
(i) placing
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 5,879.00 5,914.00 6,033.00
12.08 (A)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,175.80 1,182.80 1,206.60
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
705.48 709.68 723.96
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 7,760.28 7,806.48 7,963.56
Say 7,760.00 7,806.00 7,964.00
12.11 E (ii) Grade M20 PCC
Same as Item 12.8(b) excluding formwork
12.11 E Case I PCC Grade M20 using batching plant & Concrete
(ii) pump
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 5,936.00 5,972.00 6,091.00
12.08 (B)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,187.20 1,194.40 1,218.20
(a+b+c) (a+b+c) (a+b+c)
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
e) Contractor's profit @ 10% on @ 10% on @ 10% on
712.32 716.64 730.92
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 7,835.52 7,883.04 8,040.12
Say 7,836.00 7,883.00 8,040.00
12.11 E Case II PCC Grade M20 using batching plant & manual
(ii) placing
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 6,221.00 6,256.00 6,375.00
12.08 (B)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,244.20 1,251.20 1,275.00
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
746.52 750.72 765.00
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 8,211.72 8,257.92 8,415.00
Say 8,212.00 8,258.00 8,415.00
12.11 E (iii) Grade M25 PCC
Same as Item 12.8 (d) excluding formwork

12.11 E Case I PCC Grade M25 using batching plant & Concrete
(iii) pump
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 6,211.00 6,247.00 6,366.00
12.08 (D)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,242.20 1,249.40 1,273.20
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
745.32 749.64 763.92
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 8,198.52 8,246.04 8,403.12
Say 8,199.00 8,246.00 8,403.00
12.11 E Case II PCC Grade M25 using batching plant & manual
(iii) placing
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 6,496.00 6,531.00 6,650.00
12.08 (D)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,299.20 1,306.20 1,330.00
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
779.52 783.72 798.00
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 8,574.72 8,620.92 8,778.00
Say 8,575.00 8,621.00 8,778.00
12.11 E (iv) Grade M30 PCC
Same as Item 12.8(f) excluding formwork
12.11 E Case I PCC Grade M30 using batching plant & Concrete
(iv) pump
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 6,237.00 6,273.00 6,273.00
12.08 (F)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,247.40 1,254.60 1,254.60
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
748.44 752.76 752.76
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 8,232.84 8,280.36 8,280.36
Say 8,233.00 8,280.00 8,280.00
12.11 E Case II PCC Grade M30 using batching plant & manual
(iv) placing
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 6,522.00 6,557.00 6,676.00
12.08 (F)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,304.40 1,311.40 1,335.20
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
782.64 786.84 801.12
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 8,609.04 8,655.24 8,812.32
Say 8,609.00 8,655.00 8,812.00
12.11 F Well cap
(i) RCC Grade M20
Case I RCC Grade M20 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,533.00 135,990.00 135,990.00 135,990.00 of Concrete -
20.05

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.152 0.152 617.00 94.40 93.78 93.78 L-12
Mason day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-11
Mazdoor day 2.325 2.300 2.300 511.52 1,189.28 1,176.50 1,176.50 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity hour 3.926 1,501.00 5,892.93 P&M-023


(ii) 12 KL capacity hour 5.255 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity hour 10.510 1,005.00 10,562.55 P&M-025
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 7,165.20 7,207.89 7,351.45
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
e) Overhead charges @ 20% on @ 20% on @ 20% on
37,259.06 37,481.01 38,227.55
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
22,355.44 22,488.60 22,936.53
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 245,909.79 247,374.64 252,301.85
Rate per cum = (a+b+c+d+e+f)/30 8,196.99 8,245.82 8,410.06
Say 8,197.00 8,246.00 8,410.00
Case II RCC Grade M20 using batching plant transit mixer
& manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 4,533.00 67,995.00 67,995.00 67,995.00 of Concrete -
20.05

Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity hour 1.978 1,501.00 2,968.98 P&M-023


(ii) 12 KL capacity hour 2.628 1,327.00 3,487.36 P&M-024
(iii) 6 KL capacity hour 5.255 1,005.00 5,281.28 P&M-025
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 3,744.90 3,765.63 3,837.39

e) Overhead charges @ 20% on @ 20% on @ 20% on


19,473.46 19,581.28 19,954.42
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
11,684.08 11,748.77 11,972.65
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 128,524.85 129,236.47 131,699.17
Rate per cum = (a+b+c+d+e+f)/15 8,568.32 8,615.76 8,779.94
Say 8,568.00 8,616.00 8,780.00
12.11 F (ii) RCC Grade M25
12.11 F Case I RCC Grade M25 using batching plant transit mixer
(ii) & Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,945.00 148,350.00 148,350.00 148,350.00 of Concrete -
20.07

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity hour 3.926 1,501.00 5,892.93 P&M-023


(ii) 12 KL capacity hour 5.255 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity hour 10.510 1,005.00 10,562.55 P&M-025
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 7,659.60 7,702.82 7,846.39

e) Overhead charges @ 20% on @ 20% on @ 20% on


39,829.94 40,054.67 40,801.22
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
23,897.96 24,032.80 24,480.73
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 262,877.60 264,360.85 269,288.06
Rate per cum = (a+b+c+d+e+f)/30 8,762.59 8,812.03 8,976.27
Say 8,763.00 8,812.00 8,976.00
12.11 F Case II RCC Grade M25 using batching plant transit mixer
(iii) & manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 4,945.00 74,175.00 74,175.00 74,175.00 of Concrete -
20.07

Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity hour 1.978 1,501.00 2,968.98 P&M-023


(ii) 12 KL capacity hour 2.628 1,327.00 3,487.36 P&M-024
(iii) 6 KL capacity hour 5.255 1,005.00 5,281.28 P&M-025
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 3,992.10 4,012.83 4,084.59

e) Overhead charges @ 20% on @ 20% on @ 20% on


20,758.90 20,866.72 21,239.86
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
12,455.34 12,520.03 12,743.92
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 137,008.75 137,720.38 140,183.07
Rate per cum = (a+b+c+d+e+f)/15 9,133.92 9,181.36 9,345.54
Say 9,134.00 9,181.00 9,346.00
12.11 F (iii) RCC Grade M30
12.11 F Case I RCC Grade M30 using batching plant transit mixer
(iii) & Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 5,032.00 150,960.00 150,960.00 150,960.00 of Concrete -
20.09

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity hour 3.926 1,501.00 5,892.93 P&M-023


(ii) 12 KL capacity hour 5.255 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity hour 10.510 1,005.00 10,562.55 P&M-025
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 7,764.00 7,807.22 7,950.79

e) Overhead charges @ 20% on @ 20% on @ 20% on


40,372.82 40,597.55 41,344.10
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
24,223.69 24,358.53 24,806.46
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 266,460.61 267,943.86 272,871.07
Rate per cum = (a+b+c+d+e+f)/30 8,882.02 8,931.46 9,095.70
Say 8,882.00 8,931.00 9,096.00
12.11 F Case II RCC Grade M30 using batching plant transit mixer
(iii) & manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 5,032.00 75,480.00 75,480.00 75,480.00 of Concrete -
20.09

Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity hour 1.978 1,501.00 2,968.98 P&M-023


(ii) 12 KL capacity hour 2.628 1,327.00 3,487.36 P&M-024
(iii) 6 KL capacity hour 5.255 1,005.00 5,281.28 P&M-025
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 4,044.30 4,065.03 4,136.79

e) Overhead charges @ 20% on @ 20% on @ 20% on


21,030.34 21,138.16 21,511.30
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
12,618.20 12,682.90 12,906.78
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 138,800.25 139,511.88 141,974.57
Rate per cum = (a+b+c+d+e+f)/15 9,253.35 9,300.79 9,464.97
Say 9,253.00 9,301.00 9,465.00
12.11 F (iv) RCC Grade M35
12.11 F Case I RCC Grade M35 using batching plant transit mixer
(iv) & Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 5,186.00 155,580.00 155,580.00 155,580.00 of Concrete -
20.11

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity
hour 0.109xL1+0.656 1,501.00 5,892.93 P&M-023
(ii) 12 KL capacity
hour 0.146xL1+0.875 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity hour 0.292xL1+1.75 1,005.00 10,562.55 P&M-025
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 7,945.26 7,988.48 8,132.05

e) Overhead charges @ 20% on @ 20% on @ 20% on


41,315.37 41,540.11 42,286.65
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
24,789.22 24,924.06 25,371.99
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 272,681.45 274,164.71 279,091.91
Rate per cum = (a+b+c+d+e+f)/30 9,089.38 9,138.82 9,303.06
Say 9,089.00 9,139.00 9,303.00
12.11 F Case II RCC Grade M35 using batching plant transit mixer
(iv) & manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 5,186.00 77,790.00 77,790.00 77,790.00 of Concrete -
20.11

Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity hour 1.978 1,501.00 2,968.98 P&M-023


(ii) 12 KL capacity hour 2.628 1,327.00 3,487.36 P&M-024
(iii) 6 KL capacity hour 5.255 1,005.00 5,281.28 P&M-025
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 4,136.70 4,157.43 4,229.19

e) Overhead charges @ 20% on @ 20% on @ 20% on


21,510.82 21,618.64 21,991.78
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
12,906.49 12,971.19 13,195.07
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 141,971.42 142,683.05 145,145.74
Rate per cum = (a+b+c+d+e+f)/15 9,464.76 9,512.20 9,676.38
Say 9,465.00 9,512.00 9,676.00
12.11 F (v) RCC Grade M40
12.11 F Case I RCC Grade M40 using batching plant transit mixer
(v) & Concrete pump
Unit = cum
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 5,519.00 165,570.00 165,570.00 165,570.00 of Concrete -
20.12

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity hour 3.926 1,501.00 5,892.93 P&M-023


(ii) 12 KL capacity hour 5.255 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity hour 10.510 1,005.00 10,562.55 P&M-025
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 8,348.40 8,391.62 8,535.19

e) Overhead charges @ 20% on @ 20% on @ 20% on


43,411.70 43,636.43 44,382.98
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
26,047.02 26,181.86 26,629.79
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 286,517.22 288,000.47 292,927.68
Rate per cum = (a+b+c+d+e+f)/30 9,550.57 9,600.02 9,764.26
Say 9,551.00 9,600.00 9,764.00
12.11 F Case II RCC Grade M40 using batching plant transit mixer
(v) & manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 5,519.00 82,785.00 82,785.00 82,785.00 of Concrete -
20.12

Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity hour 1.978 1,501.00 2,968.98 P&M-023


(ii) 12 KL capacity hour 2.628 1,327.00 3,487.36 P&M-024
(iii) 6 KL capacity hour 5.255 1,005.00 5,281.28 P&M-025
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 4,336.50 4,357.23 4,428.99

e) Overhead charges @ 20% on @ 20% on @ 20% on


22,549.78 22,657.60 23,030.74
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
13,529.87 13,594.56 13,818.44
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 148,828.56 149,540.19 152,002.88
Rate per cum = (a+b+c+d+e+f)/15 9,921.90 9,969.35 10,133.53
Say 9,922.00 9,969.00 10,134.00

12.11 F (vi) RCC Grade M45


Case I RCC Grade M45 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 5,663.00 169,890.00 169,890.00 169,890.00 of Concrete -
20.13

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity hour 3.926 1,501.00 5,892.93 P&M-023


(ii) 12 KL capacity hour 5.255 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity hour 10.510 1,005.00 10,562.55 P&M-025
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 8,521.20 8,564.42 8,707.99

e) Overhead charges @ 20% on @ 20% on @ 20% on


44,310.26 44,534.99 45,281.54
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
26,586.16 26,721.00 27,168.92
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 292,447.71 293,930.97 298,858.17
Rate per cum = (a+b+c+d+e+f)/30 9,748.26 9,797.70 9,961.94
Say 9,748.00 9,798.00 9,962.00
12.11 F Case II RCC Grade M45 using batching plant transit mixer
(vi) & manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 5,663.00 84,945.00 84,945.00 84,945.00 of Concrete -
20.13

Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity hour 1.978 1,501.00 2,968.98 P&M-023


(ii) 12 KL capacity hour 2.628 1,327.00 3,487.36 P&M-024
(iii) 6 KL capacity hour 5.255 1,005.00 5,281.28 P&M-025
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 4,422.90 4,443.63 4,515.39

e) Overhead charges @ 20% on @ 20% on @ 20% on


22,999.06 23,106.88 23,480.02
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
13,799.44 13,864.13 14,088.01
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 151,793.81 152,505.43 154,968.13
Rate per cum = (a+b+c+d+e+f)/15 10,119.59 10,167.03 10,331.21
Say 10,120.00 10,167.00 10,331.00
12.12 Section Sinking of 6 m external diameter well (other than
1200 pneumatic method of sinking) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is
reckoned from bed level.

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 6 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.50 m per hour.
a) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Sinker ( skilled ) day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Sinking helper ( semi-skilled ) day 2.000 2.000 2.000 617.00 1,234.00 1,234.00 1,234.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 2.000 2.000 2.000 1,094.10 2,188.20 2,188.20 2,188.20 P&M-111

Consumables in sinking @10 per cent of (b) 218.82 218.82 218.82


c) Overhead charges @ 20% on @ 20% on @ 20% on
856.16 856.16 856.16
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
513.69 513.69 513.69
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 5,650.64 5,650.64 5,650.64
Say 5,651.00 5,651.00 5,651.00
12.12 A (ii) Beyond 3m upto 10m depth
Rate of sinking = 0.33 m per hour.
a) Labour
Mate day 0.150 0.150 0.150 617.00 92.55 92.55 92.55 L-12
Sinker day 1.250 1.250 1.250 565.73 707.16 707.16 707.16 L-15
Sinking helper ( semi-skilled ) day 2.500 2.500 2.500 617.00 1,542.50 1,542.50 1,542.50 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories hour 3.000 3.000 3.000 1,094.10 3,282.30 3,282.30 3,282.30 P&M-111
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Consumables in sinking @10 per cent of (b) 328.23 328.23 328.23
c) Overhead charges @ 20% on @ 20% on @ 20% on
1,190.55 1,190.55 1,190.55
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
714.33 714.33 714.33
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 7,857.62 7,857.62 7,857.62
Say 7,858.00 7,858.00 7,858.00
12.12 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous For For
For dewatering @
meter dewatering @ dewatering @
5% of cost, if
5% of cost, if 5% of cost, if
required
required required

11th m 5% 8251.000 8251.000 8251.000 413.00 413.00 413.00


12th m 5% 8664.000 8664.000 8664.000 433.00 433.00 433.00
13th m 5% 9097.000 9097.000 9097.000 455.00 455.00 455.00
14th m 5% 9552.000 9552.000 9552.000 478.00 478.00 478.00
15th m 5% 10030.000 10030.000 10030.000 502.00 502.00 502.00
16th m 5% 10532.000 10532.000 10532.000 527.00 527.00 527.00
17th m 5% 11059.000 11059.000 11059.000 553.00 553.00 553.00
18th m 5% 11612.000 11612.000 11612.000 581.00 581.00 581.00
19th m 5% 12193.000 12193.000 12193.000 610.00 610.00 610.00
20th m 5% 12803.000 12803.000 12803.000 640.00 640.00 640.00
Total Cost from 10m upto 20m 103793.000 103793.000 103793.000 5,192.00 5,192.00 5,192.00
Avg Rate per metre Say 10379.000 10379.000 10379.000 519.00 519.00 519.00
12.12 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 20 per cent of cost for Kentledge including
supports, loading arrangement and Labour. 20% for 20% for
20% for Kentledge
Kentledge Kentledge

21st m 7.5% 13763.000 13763.000 13763.000 2,753.00 2,753.00 2,753.00


22nd m 7.5% 14795.000 14795.000 14795.000 2,959.00 2,959.00 2,959.00
23rd m 7.5% 15905.000 15905.000 15905.000 3,181.00 3,181.00 3,181.00
24th m 7.5% 17098.000 17098.000 17098.000 3,420.00 3,420.00 3,420.00
25th m 7.5% 18380.000 18380.000 18380.000 3,676.00 3,676.00 3,676.00
26th m 7.5% 19759.000 19759.000 19759.000 3,952.00 3,952.00 3,952.00
27th m 7.5% 21241.000 21241.000 21241.000 4,248.00 4,248.00 4,248.00
28th m 7.5% 22834.000 22834.000 22834.000 4,567.00 4,567.00 4,567.00
29th m 7.5% 24547.000 24547.000 24547.000 4,909.00 4,909.00 4,909.00
30th m 7.5% 26388.000 26388.000 26388.000 5,278.00 5,278.00 5,278.00
Total Cost from 20m upto 30m 194710.000 194710.000 194710.000 38,943.00 38,943.00 38,943.00
Avg Rate per metre Say 19471.000 19471.000 19471.000 3,894.00 3,894.00 3,894.00
12.12 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 20 per cent of cost for Kentledge including
supports, loading arrangement and Labour. 20% for 20% for
20% for Kentledge
Kentledge Kentledge

31st m 10% 29027.000 29027.000 29027.000 5,805.00 5,805.00 5,805.00


32nd 10% 31930.000 31930.000 31930.000 6,386.00 6,386.00 6,386.00
33rd m 10% 35123.000 35123.000 35123.000 7,025.00 7,025.00 7,025.00
34th m 10% 38635.000 38635.000 38635.000 7,727.00 7,727.00 7,727.00
35th m 10% 42499.000 42499.000 42499.000 8,500.00 8,500.00 8,500.00
36th m 10% 46749.000 46749.000 46749.000 9,350.00 9,350.00 9,350.00
37th m 10% 51424.000 51424.000 51424.000 10,285.00 10,285.00 10,285.00
38th m 10% 56566.000 56566.000 56566.000 11,313.00 11,313.00 11,313.00
39th m 10% 62223.000 62223.000 62223.000 12,445.00 12,445.00 12,445.00
40th m 10% 68445.000 68445.000 68445.000 13,689.00 13,689.00 13,689.00
Total Cost from 30m upto 40m 462621.000 462621.000 462621.000 92,525.00 92,525.00 92,525.00
Avg Rate per metre Say 46262.000 46262.000 46262.000 9,253.00 9,253.00 9,253.00
12.12 B Clayey Soil ( 6m dia. Well )
Unit = Running Meter.
Taking output = 1 meter
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.33 m per hour.
a) Labour
Mate day 0.150 0.150 0.150 617.00 92.55 92.55 92.55 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 2.250 2.250 2.250 617.00 1,388.25 1,388.25 1,388.25 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories hour 3.000 3.000 3.000 1,094.10 3,282.30 3,282.30 3,282.30 P&M-111
Consumables in sinking @ 10 per cent of (b) 328.23 328.23 328.23
c) Overhead charges @ 20% on @ 20% on @ 20% on
1,187.99 1,187.99 1,187.99
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
712.79 712.79 712.79
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 7,840.70 7,840.70 7,840.70
Say 7,841.00 7,841.00 7,841.00
12.12 B (ii) Beyond 3m upto 10m depth
Rate of sinking = 0.17 m per hour.
a) Labour
Mate day 0.300 0.300 0.300 617.00 185.10 185.10 185.10 L-12
Sinker day 3.000 3.000 3.000 565.73 1,697.19 1,697.19 1,697.19 L-15
Sinking helper ( semi-skilled ) day 4.500 4.500 4.500 617.00 2,776.50 2,776.50 2,776.50 L-14
b) Machinery
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 6.000 6.000 6.000 1,094.10 6,564.60 6,564.60 6,564.60 P&M-111

Air compressor with pneumatic chisel attachment


for cutting hard clay. P&M-029
hour 2.000 2.000 2.000 625.80 1,251.60 1,251.60 1,251.60
+P&M-078

Consumables in sinking @ 10 per cent of (b) 781.62 781.62 781.62


c) Overhead charges @ 20% on @ 20% on @ 20% on
2,651.32 2,651.32 2,651.32
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,590.79 1,590.79 1,590.79
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 17,498.73 17,498.73 17,498.73
Say 17,499.00 17,499.00 17,499.00
12.12 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous
meter
b Add for dewatering @ 5 per cent of cost, if
required. For For
For dewatering @
dewatering @ dewatering @
5% of cost, if
5% of cost, if 5% of cost, if
required
required required

11th m 5% 18374.000 18374.000 18374.000 919.00 919.00 919.00


12th m 5% 19293.000 19293.000 19293.000 965.00 965.00 965.00
13th m 5% 20258.000 20258.000 20258.000 1,013.00 1,013.00 1,013.00
14th m 5% 21271.000 21271.000 21271.000 1,064.00 1,064.00 1,064.00
15th m 5% 22335.000 22335.000 22335.000 1,117.00 1,117.00 1,117.00
16th m 5% 23452.000 23452.000 23452.000 1,173.00 1,173.00 1,173.00
17th m 5% 24625.000 24625.000 24625.000 1,231.00 1,231.00 1,231.00
18th m 5% 25856.000 25856.000 25856.000 1,293.00 1,293.00 1,293.00
19th m 5% 27149.000 27149.000 27149.000 1,357.00 1,357.00 1,357.00
20th m 5% 28506.000 28506.000 28506.000 1,425.00 1,425.00 1,425.00
Total Cost from 10m upto 20m 231119.000 231119.000 231119.000 11,557.00 11,557.00 11,557.00
Avg Rate per metre Say 23112.000 23112.000 23112.000 1,156.00 1,156.00 1,156.00
12.12 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 5 per cent of cost for dewatering of the cost, if
required
c Add 25 per cent of cost for Kentledge including Including Including 5%
supports, loading arrangement and Labour ). Including 25% Including 25% for
25% for for dewatering, if
for Kentledge Kentledge
Kentledge required
21st m 7.5% 30644.000 30644.000 30644.000 7,661.00 7,661.00 7,661.00 1,532.00
22nd m 7.5% 32942.000 32942.000 32942.000 8,236.00 8,236.00 8,236.00 1,647.00
23rd m 7.5% 35413.000 35413.000 35413.000 8,853.00 8,853.00 8,853.00 1,771.00
24th m 7.5% 38069.000 38069.000 38069.000 9,517.00 9,517.00 9,517.00 1,903.00
25th m 7.5% 40924.000 40924.000 40924.000 10,231.00 10,231.00 10,231.00 2,046.00
26th m 7.5% 43993.000 43993.000 43993.000 10,998.00 10,998.00 10,998.00 2,200.00
27th m 7.5% 47292.000 47292.000 47292.000 11,823.00 11,823.00 11,823.00 2,365.00
28th m 7.5% 50839.000 50839.000 50839.000 12,710.00 12,710.00 12,710.00 2,542.00
29th m 7.5% 54652.000 54652.000 54652.000 13,663.00 13,663.00 13,663.00 2,733.00
30th m 7.5% 58751.000 58751.000 58751.000 14,688.00 14,688.00 14,688.00 2,938.00
Total Cost from 20m upto 30m 433519.000 433519.000 433519.000 108,380.00 108,380.00 108,380.00 21,677.00
Avg Rate per metre Say 43352.000 43352.000 43352.000 10,838.00 10,838.00 10,838.00 2,168.00
12.12 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 5 per cent of cost for dewatering, if required

c Add 20 per cent of cost for Kentledge including 5% for


supports, loading arrangement and Labour). 20% for 20% for
20% for Kentledge dewatering, if
Kentledge Kentledge
required
31st m 10% 64626.000 64626.000 64626.000 12,925.00 12,925.00 12,925.00 3,231.00
32nd 10% 71089.000 71089.000 71089.000 14,218.00 14,218.00 14,218.00 3,554.00
33rd m 10% 78198.000 78198.000 78198.000 15,640.00 15,640.00 15,640.00 3,910.00
34th m 10% 86018.000 86018.000 86018.000 17,204.00 17,204.00 17,204.00 4,301.00
35th m 10% 94620.000 94620.000 94620.000 18,924.00 18,924.00 18,924.00 4,731.00
36th m 10% 104082.000 104082.000 104082.000 20,816.00 20,816.00 20,816.00 5,204.00
37th m 10% 114490.000 114490.000 114490.000 22,898.00 22,898.00 22,898.00 5,725.00
38th m 10% 125939.000 125939.000 125939.000 25,188.00 25,188.00 25,188.00 6,297.00
39th m 10% 138533.000 138533.000 138533.000 27,707.00 27,707.00 27,707.00 6,927.00
40th m 10% 152386.000 152386.000 152386.000 30,477.00 30,477.00 30,477.00 7,619.00
Total Cost from 30m upto 40m 1029981.000 1029981.000 1029981.000 205,997.00 205,997.00 205,997.00 51,499.00
Avg Rate per metre Say 102998.000 102998.000 102998.000 20,600.00 20,600.00 20,600.00 5,150.00
12.12 C Extra over item no. 12.12 (A) & (B) irrespective of
depth for sinking in Soft Rock (6m dia well )

Unit = Running Meter.


Taking output = 1 m
a) Labour
Mate day 0.490 0.490 0.490 617.00 302.33 302.33 302.33 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 2.250 2.250 2.250 617.00 1,388.25 1,388.25 1,388.25 L-14
Diver day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-07
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Air Compressor 250 cfm hour 28.274 28.274 28.274 614.25 17,367.30 17,367.30 17,367.30 P&M-029
Pneumatic breaker hour 56.549 56.549 56.549 11.55 653.14 653.14 653.14 P&M-078
Consumables in sinking @ 5 per cent of (b) 901.02 901.02 901.02
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Add for dewatering @ of 15 per cent of (a+b), if
required 3,888.27 3,888.27 3,888.27
Additional Hire & running charges for shifting of
crane (rock breaking time) with grab bucket of 0.75
cum capacity and accessories. hour 3.000 3.000 3.000 1,094.10 3,282.30 3,282.30 3,282.30 P&M-111

c) Overhead charges @ 20% on @ 20% on @ 20% on


6,618.47 6,618.47 6,618.47
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
3,971.08 3,971.08 3,971.08
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 43,681.93 43,681.93 43,681.93
Say 43,682.00 43,682.00 43,682.00
12.12 D Extra over item no. 12.12 (A) & (B) irrespective of
depth for sinking in Hard Rock (6m dia well )

Unit = Running Meter


Taking output = 1 m
a) Material
Small dia.Explosive at 0.20 kg / cum kg 5.655 5.655 5.655 81.90 463.13 463.13 463.13 M-215
Electric detonators no 25.000 25.000 25.000 21.00 525.00 525.00 525.00 M-217
Detonating fuse coil m 78.000 78.000 78.000 19.00 1,482.00 1,482.00 1,482.00 M-218
b) Labour
Mate day 0.500 0.500 0.500 617.00 308.50 308.50 308.50 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 2.250 2.250 2.250 617.00 1,388.25 1,388.25 1,388.25 L-14
Diver day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-07
Driller day 2.000 2.000 2.000 558.00 1,116.00 1,116.00 1,116.00 L-06
Blaster day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-03
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
c) Machinery
Air Compressor 250 cfm hour 26.590 26.590 26.590 614.25 16,333.05 16,333.05 16,333.05 P&M-029
Pneumatic breaker hour 22.619 22.619 22.619 11.55 261.25 261.25 261.25 P&M-078
Pneumatic breaker for drilling holes (@ 4.5 m per
hour) hour 14.561 14.561 14.561 11.55 168.18 168.18 168.18 P&M-078
Consumables in protected blasting @ 10 per cent
1,676.25 1,676.25 1,676.25
of (c)
Add for dewatering @ of 15 per cent of (a+b+c), if
required 4,220.43 4,220.43 4,220.43
Additional Hire & running charges for shifting of
crane (rock breaking time) with grab bucket of 0.75
cum capacity and accessories. hour 3.000 3.000 3.000 1,094.10 3,282.30 3,282.30 3,282.30 P&M-111

d) Overhead charges @ 20% on @ 20% on @ 20% on


7,127.79 7,127.79 7,127.79
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
4,276.67 4,276.67 4,276.67
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per metre = (a+b+c+d+e) 44,573.27 44,573.27 44,573.27
Say 44,573.00 44,573.00 44,573.00
12.12 E Extra over item no. 12.12 (A) & (B) irrespective of
depth for sinking in rock bouldery strata (6m dia
well )
Unit = Running Meter.
Taking output = 1 m
a) Labour
Mate day 0.410 0.410 0.410 617.00 252.97 252.97 252.97 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 2.250 2.250 2.250 617.00 1,388.25 1,388.25 1,388.25 L-14
Diver day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-07
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
b) Machinery
Air Compressor 250 cfm hour 18.850 18.850 18.850 614.25 11,578.34 11,578.34 11,578.34 P&M-029
Pneumatic breaker hour 37.699 37.699 37.699 11.55 435.42 435.42 435.42 P&M-078
Consumables in sinking @ 5 per cent of (b) 600.69 600.69 600.69
Add for dewatering @ of 15 per cent of (a+b), if
required 2,781.36 2,781.36 2,781.36
Additional Hire & running charges for shifting of
crane (rock breaking time) with grab bucket of 0.75
cum capacity and accessories. hour 3.000 3.000 3.000 1,094.10 3,282.30 3,282.30 3,282.30 P&M-111

c) Overhead charges @ 20% on @ 20% on @ 20% on


4,921.21 4,921.21 4,921.21
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
2,952.73 2,952.73 2,952.73
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 32,479.98 32,479.98 32,479.98
Say 32,480.00 32,480.00 32,480.00
12.13 Section Sinking of 7 m external diameter well ( other than
1200 pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is
reckoned from bed level.

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 7 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.30 m per hour.
a) Labour
Mate day 0.150 0.150 0.150 617.00 92.55 92.55 92.55 L-12
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Sinker ( skilled ) day 1.250 1.250 1.250 565.73 707.16 707.16 707.16 L-15
Sinking helper ( semi-skilled ) day 2.500 2.500 2.500 617.00 1,542.50 1,542.50 1,542.50 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 3.250 3.250 3.250 1,094.10 3,555.83 3,555.83 3,555.83 P&M-111

Consumables in sinking @10 per cent of (b) 355.58 355.58 355.58


c) Overhead charges @ 20% on @ 20% on @ 20% on
1,250.72 1,250.72 1,250.72
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
750.43 750.43 750.43
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 8,254.78 8,254.78 8,254.78
16,509.56 16,509.56 16,509.56
Say 16,510.00 16,510.00 16,510.00
12.13 A (ii) Beyond 3m upto 10m depth
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.180 0.180 0.180 617.00 111.06 111.06 111.06 L-12
Sinker day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 3.000 3.000 3.000 617.00 1,851.00 1,851.00 1,851.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 4.500 4.500 4.500 1,094.10 4,923.45 4,923.45 4,923.45 P&M-111

Consumables in sinking @10 per cent of (b) 492.35 492.35 492.35


c) Overhead charges @ 20% on @ 20% on @ 20% on
1,645.29 1,645.29 1,645.29
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
987.17 987.17 987.17
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 10,858.91 10,858.91 10,858.91
Say 10,859.00 10,859.00 10,859.00
12.13 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous for
for dewatering for dewatering @
meter dewatering @
@ 5% of cost, 5% of cost, if
5% of cost, if
if required required
required

11th m 5% 11402.000 11402.000 11402.000 570.00 570.00 570.00


12th m 5% 11972.000 11972.000 11972.000 599.00 599.00 599.00
13th m 5% 12571.000 12571.000 12571.000 629.00 629.00 629.00
14th m 5% 13200.000 13200.000 13200.000 660.00 660.00 660.00
15th m 5% 13860.000 13860.000 13860.000 693.00 693.00 693.00
16th m 5% 14553.000 14553.000 14553.000 728.00 728.00 728.00
17th m 5% 15281.000 15281.000 15281.000 764.00 764.00 764.00
18th m 5% 16045.000 16045.000 16045.000 802.00 802.00 802.00
19th m 5% 16847.000 16847.000 16847.000 842.00 842.00 842.00
20th m 5% 17689.000 17689.000 17689.000 884.00 884.00 884.00
Total Cost from 10m upto 20m 143420.000 143420.000 143420.000 7,171.00 7,171.00 7,171.00
Avg Rate per metre Say 14342.000 14342.000 14342.000 717.00 717.00 717.00
12.13 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 20 per cent of cost for Kentledge including
supports, loading arrangement and Labour). 20% for 20% for
20% for Kentledge
Kentledge Kentledge

21st m 7.5% 19016.000 19016.000 19016.000 3,803.00 3,803.00 3,803.00


22nd m 7.5% 20442.000 20442.000 20442.000 4,088.00 4,088.00 4,088.00
23rd m 7.5% 21975.000 21975.000 21975.000 4,395.00 4,395.00 4,395.00
24th m 7.5% 23623.000 23623.000 23623.000 4,725.00 4,725.00 4,725.00
25th m 7.5% 25395.000 25395.000 25395.000 5,079.00 5,079.00 5,079.00
26th m 7.5% 27300.000 27300.000 27300.000 5,460.00 5,460.00 5,460.00
27th m 7.5% 29348.000 29348.000 29348.000 5,870.00 5,870.00 5,870.00
28th m 7.5% 31549.000 31549.000 31549.000 6,310.00 6,310.00 6,310.00
29th m 7.5% 33915.000 33915.000 33915.000 6,783.00 6,783.00 6,783.00
30th m 7.5% 36459.000 36459.000 36459.000 7,292.00 7,292.00 7,292.00
Total Cost from 20m upto 30m 269022.000 269022.000 269022.000 53,805.00 53,805.00 53,805.00
Avg Rate per metre Say 26902.000 26902.000 26902.000 5,381.00 5,381.00 5,381.00
12.13 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 20 per cent of cost for Kentledge including
supports, loading arrangement, and Labour etc. 20% for 20% for
20% for Kentledge
Kentledge Kentledge

31st m 10% 40105.000 40105.000 40105.000 8,021.00 8,021.00 8,021.00


32nd 10% 44116.000 44116.000 44116.000 8,823.00 8,823.00 8,823.00
33rd m 10% 48528.000 48528.000 48528.000 9,706.00 9,706.00 9,706.00
34th m 10% 53381.000 53381.000 53381.000 10,676.00 10,676.00 10,676.00
35th m 10% 58719.000 58719.000 58719.000 11,744.00 11,744.00 11,744.00
36th m 10% 64591.000 64591.000 64591.000 12,918.00 12,918.00 12,918.00
37th m 10% 71050.000 71050.000 71050.000 14,210.00 14,210.00 14,210.00
38th m 10% 78155.000 78155.000 78155.000 15,631.00 15,631.00 15,631.00
39th m 10% 85971.000 85971.000 85971.000 17,194.00 17,194.00 17,194.00
40th m 10% 94568.000 94568.000 94568.000 18,914.00 18,914.00 18,914.00
Total Cost from 30m upto 40m 639184.000 639184.000 639184.000 127,837.00 127,837.00 127,837.00
Avg Rate per metre Say 63918.000 63918.000 63918.000 12,784.00 12,784.00 12,784.00
12.13 B Clayey Soil ( 7m dia. Well )
Unit = Running Meter.
Taking output = 1 cum
(I) Depth below bed level upto 3.0 M
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Rate of sinking = 0.22 m per hour.
a) Labour
Mate day 0.180 0.180 0.180 617.00 111.06 111.06 111.06 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 3.000 3.000 3.000 617.00 1,851.00 1,851.00 1,851.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 4.500 4.500 4.500 1,094.10 4,923.45 4,923.45 4,923.45 P&M-111

Consumables in sinking @ 10 per cent of (b) 492.35 492.35 492.35


c) Overhead charges @ 20% on @ 20% on @ 20% on
1,645.29 1,645.29 1,645.29
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
987.17 987.17 987.17
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 10,858.91 10,858.91 10,858.91
Say 10,859.00 10,859.00 10,859.00
12.13 B (ii) Beyond 3m upto 10m depth
Rate of sinking = 0.17 m per hour.
a) Labour
Mate day 0.260 0.260 0.260 617.00 160.42 160.42 160.42 L-12
Sinker day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Sinking helper ( semi-skilled ) day 4.000 4.000 4.000 617.00 2,468.00 2,468.00 2,468.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 6.000 6.000 6.000 1,094.10 6,564.60 6,564.60 6,564.60 P&M-111

Air compressor with pneumatic chisel attachment


for cutting hard clay. P&M-029
hour 3.250 3.250 3.250 625.80 2,033.85 2,033.85 2,033.85
+P&M-078

Consumables in sinking @ 10 per cent of (b) 859.85 859.85 859.85


c) Overhead charges @ 20% on @ 20% on @ 20% on
2,643.64 2,643.64 2,643.64
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,586.18 1,586.18 1,586.18
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 17,447.99 17,447.99 17,447.99
Say 17,448.00 17,448.00 17,448.00
12.13 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous
meter
b Add for dewatering @ 5 per cent of cost, if
required. for
for dewatering for dewatering @
dewatering @
@ 5% of cost, 5% of cost, if
5% of cost, if
if required required
required

11th m 5% 18320.000 18320.000 18320.000 916.00 916.00 916.00


12th m 5% 19236.000 19236.000 19236.000 962.00 962.00 962.00
13th m 5% 20198.000 20198.000 20198.000 1,010.00 1,010.00 1,010.00
14th m 5% 21208.000 21208.000 21208.000 1,060.00 1,060.00 1,060.00
15th m 5% 22268.000 22268.000 22268.000 1,113.00 1,113.00 1,113.00
16th m 5% 23381.000 23381.000 23381.000 1,169.00 1,169.00 1,169.00
17th m 5% 24550.000 24550.000 24550.000 1,228.00 1,228.00 1,228.00
18th m 5% 25778.000 25778.000 25778.000 1,289.00 1,289.00 1,289.00
19th m 5% 27067.000 27067.000 27067.000 1,353.00 1,353.00 1,353.00
20th m 5% 28420.000 28420.000 28420.000 1,421.00 1,421.00 1,421.00
Total Cost from 10m upto 20m 230426.000 230426.000 230426.000 11,521.00 11,521.00 11,521.00
Avg Rate per metre Say 23043.000 23043.000 23043.000 1,152.00 1,152.00 1,152.00
12.13 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 5 per cent of cost for dewatering on the cost,
if required
c Add 25 per cent of cost for Kentledge including 5% for
supports, loading arrangement and Labour ). 25% for 25% for
25% for Kentledge dewatering, if
Kentledge Kentledge
required
31st m 7.5% 30552.000 30552.000 30552.000 7,638.00 7,638.00 7,638.00 1,528.00
32nd 7.5% 32843.000 32843.000 32843.000 8,211.00 8,211.00 8,211.00 1,642.00
33rd m 7.5% 35306.000 35306.000 35306.000 8,827.00 8,827.00 8,827.00 1,765.00
34th m 7.5% 37954.000 37954.000 37954.000 9,489.00 9,489.00 9,489.00 1,898.00
35th m 7.5% 40801.000 40801.000 40801.000 10,200.00 10,200.00 10,200.00 2,040.00
36th m 7.5% 43861.000 43861.000 43861.000 10,965.00 10,965.00 10,965.00 2,193.00
37th m 7.5% 47151.000 47151.000 47151.000 11,788.00 11,788.00 11,788.00 2,358.00
38th m 7.5% 50687.000 50687.000 50687.000 12,672.00 12,672.00 12,672.00 2,534.00
39th m 7.5% 54489.000 54489.000 54489.000 13,622.00 13,622.00 13,622.00 2,724.00
40th m 7.5% 58576.000 58576.000 58576.000 14,644.00 14,644.00 14,644.00 2,929.00
Total Cost from 30m upto 40m 432220.000 432220.000 432220.000 108,056.00 108,056.00 108,056.00 21,611.00
Avg Rate per metre Say 43222.000 43222.000 43222.000 10,806.00 10,806.00 10,806.00 2,161.00
12.13 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 5 per cent of cost for dewatering, if required

c Add 20 per cent of cost for Kentledge including 5% for


supports, loading arrangement and Labour). 20% for 20% for
20% for Kentledge dewatering, if
Kentledge Kentledge
required
31st m 10% 64434.000 64434.000 64434.000 12,887.00 12,887.00 12,887.00 3,222.00
32nd 10% 70877.000 70877.000 70877.000 14,175.00 14,175.00 14,175.00 3,544.00
33rd m 10% 77965.000 77965.000 77965.000 15,593.00 15,593.00 15,593.00 3,898.00
34th m 10% 85762.000 85762.000 85762.000 17,152.00 17,152.00 17,152.00 4,288.00
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
35th m 10% 94338.000 94338.000 94338.000 18,868.00 18,868.00 18,868.00 4,717.00
36th m 10% 103772.000 103772.000 103772.000 20,754.00 20,754.00 20,754.00 5,189.00
37th m 10% 114149.000 114149.000 114149.000 22,830.00 22,830.00 22,830.00 5,707.00
38th m 10% 125564.000 125564.000 125564.000 25,113.00 25,113.00 25,113.00 6,278.00
39th m 10% 138120.000 138120.000 138120.000 27,624.00 27,624.00 27,624.00 6,906.00
40th m 10% 151932.000 151932.000 151932.000 30,386.00 30,386.00 30,386.00 7,597.00
Total Cost from 30m upto 40m 1026913.000 1026913.000 1026913.000 205,382.00 205,382.00 205,382.00 51,346.00
Avg Rate per metre Say 102691.000 102691.000 102691.000 20,538.00 20,538.00 20,538.00 5,135.00
12.13 C Extra over item no. 12.13 (A) & (B) irrespective of
depth for sinking in Soft Rock (7m dia well )

Unit = Running Meter.


Taking output = 1 m
a) Labour
Mate day 0.570 0.570 0.570 617.00 351.69 351.69 351.69 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 2.250 2.250 2.250 617.00 1,388.25 1,388.25 1,388.25 L-14
Diver day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-07
Mazdoor day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-13
b) Machinery
Air Compressor 250 cfm hour 38.485 38.485 38.485 614.25 23,639.41 23,639.41 23,639.41 P&M-029
Pneumatic breaker hour 76.969 76.969 76.969 11.55 888.99 888.99 888.99 P&M-078
Consumables in sinking @ 5 per cent of (b) 1,226.42 1,226.42 1,226.42
Add for dewatering @ of 15 per cent of (a+b), if
required 5,074.13 5,074.13 5,074.13
Additional Hire & running charges for shifting of
crane (rock breaking time) with grab bucket of 0.75
cum capacity and accessories. hour 3.000 3.000 3.000 1,094.10 3,282.30 3,282.30 3,282.30 P&M-111

c) Overhead charges @ 20% on @ 20% on @ 20% on


8,436.80 8,436.80 8,436.80
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
5,062.08 5,062.08 5,062.08
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 55,682.87 55,682.87 55,682.87
Say 55,683.00 55,683.00 55,683.00
12.13 D Extra over item no. 12.13 (A) & (B) irrespective of
depth for sinking in Hard Rock (7m dia well )

Unit = Running Meter


Taking output = 1 m
a) Material
Small dia.Explosive at 0.20 kg / cum kg 7.697 7.697 7.697 81.90 630.38 630.38 630.38 M-215
Electric detonators no 36.000 36.000 36.000 21.00 756.00 756.00 756.00 M-217
Detonating fuse coil m 112.000 112.000 112.000 19.00 2,128.00 2,128.00 2,128.00 M-218
b) Labour
Mate day 0.580 0.580 0.580 617.00 357.86 357.86 357.86 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 2.250 2.250 2.250 617.00 1,388.25 1,388.25 1,388.25 L-14
Diver day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-07
Driller day 2.000 2.000 2.000 558.00 1,116.00 1,116.00 1,116.00 L-06
Blaster day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-03
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Air Compressor 250 cfm hour 33.304 33.304 33.304 614.25 20,456.86 20,456.86 20,456.86 P&M-029
Pneumatic breaker hour 30.788 30.788 30.788 11.55 355.60 355.60 355.60 P&M-078
Pneumatic breaker for drilling holes (@ 4.5 m per
hour) hour 19.820 19.820 19.820 11.55 228.92 228.92 228.92 P&M-078
Consumables in protected blasting @ 10 per cent
2,104.14 2,104.14 2,104.14
of (c)
Add for dewatering @ of 15 per cent of (a+b+c), if
required 5,243.95 5,243.95 5,243.95
Additional Hire & running charges for shifting of
crane (rock breaking time) with grab bucket of 0.75
cum capacity and accessories. hour 3.000 3.000 3.000 1,094.10 3,282.30 3,282.30 3,282.30 P&M-111

d) Overhead charges @ 20% on @ 20% on @ 20% on


8,697.18 8,697.18 8,697.18
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
5,218.31 5,218.31 5,218.31
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per metre = (a+b+c+d+e) 57,401.37 57,401.37 57,401.37
Say 57,401.00 57,401.00 57,401.00
12.13 E Extra over item no. 12.13 (A) & (B) irrespective of
depth for sinking in rock bouldery strata (7m dia
well )
Unit = Running Meter.
Taking output = 1 m
a) Labour
Mate day 0.490 0.490 0.490 617.00 302.33 302.33 302.33 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 2.250 2.250 2.250 617.00 1,388.25 1,388.25 1,388.25 L-14
Diver day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-07
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Air Compressor 250 cfm hour 64.141 64.141 64.141 614.25 39,398.61 39,398.61 39,398.61 P&M-029
Pneumatic breaker hour 128.282 128.282 128.282 11.55 1,481.66 1,481.66 1,481.66 P&M-078
Consumables in sinking @ 5 per cent of (b) 2,044.01 2,044.01 2,044.01
Add for dewatering @ of 15 per cent of (a+b), if
required 7,488.69 7,488.69 7,488.69
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Additional Hire & running charges for shifting of
crane (rock breaking time) with grab bucket of 0.75
cum capacity and accessories. hour 3.000 3.000 3.000 1,094.10 3,282.30 3,282.30 3,282.30 P&M-111

c) Overhead charges @ 20% on @ 20% on @ 20% on


12,139.12 12,139.12 12,139.12
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
7,283.47 7,283.47 7,283.47
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 80,118.20 80,118.20 80,118.20
Say 80,118.00 80,118.00 80,118.00
12.14 Section Sinking of 8 m external diameter well ( other than
1200 pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is
reckoned from bed level.

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 8 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a) Labour
Mate day 0.180 0.180 0.180 617.00 111.06 111.06 111.06 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 3.000 3.000 3.000 617.00 1,851.00 1,851.00 1,851.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 4.000 4.000 4.000 1,094.10 4,376.40 4,376.40 4,376.40 P&M-111

Consumables in sinking @10 per cent of (b) 437.64 437.64 437.64


c) Overhead charges @ 20% on @ 20% on @ 20% on
1,524.94 1,524.94 1,524.94
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
914.96 914.96 914.96
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 10,064.60 10,064.60 10,064.60
Say 10,065.00 10,065.00 10,065.00
12.14 A (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.20 m/hour
a) Labour
Mate day 0.210 0.210 0.210 617.00 129.57 129.57 129.57 L-12
Sinker day 1.750 1.750 1.750 565.73 990.03 990.03 990.03 L-15
Sinking helper ( semi-skilled ) day 3.500 3.500 3.500 617.00 2,159.50 2,159.50 2,159.50 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 5.000 5.000 5.000 1,094.10 5,470.50 5,470.50 5,470.50 P&M-111

Consumables in sinking @10 per cent of (b) 547.05 547.05 547.05


c) Overhead charges @ 20% on @ 20% on @ 20% on
1,859.33 1,859.33 1,859.33
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,115.60 1,115.60 1,115.60
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 12,271.57 12,271.57 12,271.57
Say 12,272.00 12,272.00 12,272.00
12.14 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous
meter
11th m 5% 12885.000 12885.000 12885.000
12th m 5% 13529.000 13529.000 13529.000
13th m 5% 14205.000 14205.000 14205.000
14th m 5% 14915.000 14915.000 14915.000
15th m 5% 15661.000 15661.000 15661.000
16th m 5% 16444.000 16444.000 16444.000
17th m 5% 17266.000 17266.000 17266.000
18th m 5% 18129.000 18129.000 18129.000
19th m 5% 19035.000 19035.000 19035.000
20th m 5% 19987.000 19987.000 19987.000
Total Cost from 10m upto 20m 162056.000 162056.000 162056.000
Avg Rate per metre Say 16206.000 16206.000 16206.000
12.14 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 20 per cent of cost for Kentledge including Including
supports, loading arrangement and Labour. 20% for Including 20% for
20% for
Kentledge Kentledge
Kentledge
21st m 7.5% 21486.000 21486.000 21486.000 4,297.00 4,297.00 4,297.00
22nd m 7.5% 23097.000 23097.000 23097.000 4,619.00 4,619.00 4,619.00
23rd m 7.5% 24829.000 24829.000 24829.000 4,966.00 4,966.00 4,966.00
24th m 7.5% 26691.000 26691.000 26691.000 5,338.00 5,338.00 5,338.00
25th m 7.5% 28693.000 28693.000 28693.000 5,739.00 5,739.00 5,739.00
26th m 7.5% 30845.000 30845.000 30845.000 6,169.00 6,169.00 6,169.00
27th m 7.5% 33158.000 33158.000 33158.000 6,632.00 6,632.00 6,632.00
28th m 7.5% 35645.000 35645.000 35645.000 7,129.00 7,129.00 7,129.00
29th m 7.5% 38318.000 38318.000 38318.000 7,664.00 7,664.00 7,664.00
30th m 7.5% 41192.000 41192.000 41192.000 8,238.00 8,238.00 8,238.00
Total Cost from 20m upto 30m 303954.000 303954.000 303954.000 60,791.00 60,791.00 60,791.00
Avg Rate per metre Say 30395.000 30395.000 30395.000 6,079.00 6,079.00 6,079.00
12.14 A (v) Beyond 30m upto 40 m
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
a Add 10 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 20 per cent of cost for Kentledge including Including
supports, loading arrangement, and Labour etc. 20% for Including 20% for
20% for
Kentledge Kentledge
Kentledge
31st m 10% 45311.000 45311.000 45311.000 9,062.00 9,062.00 9,062.00
32nd 10% 49842.000 49842.000 49842.000 9,968.00 9,968.00 9,968.00
33rd m 10% 54826.000 54826.000 54826.000 10,965.00 10,965.00 10,965.00
34th m 10% 60309.000 60309.000 60309.000 12,062.00 12,062.00 12,062.00
35th m 10% 66340.000 66340.000 66340.000 13,268.00 13,268.00 13,268.00
36th m 10% 72974.000 72974.000 72974.000 14,595.00 14,595.00 14,595.00
37th m 10% 80271.000 80271.000 80271.000 16,054.00 16,054.00 16,054.00
38th m 10% 88298.000 88298.000 88298.000 17,660.00 17,660.00 17,660.00
39th m 10% 97128.000 97128.000 97128.000 19,426.00 19,426.00 19,426.00
40th m 10% 106841.000 106841.000 106841.000 21,368.00 21,368.00 21,368.00
Total Cost from 30m upto 40m 722140.000 722140.000 722140.000 144428.000 144428.000 144428.000
Avg Rate per metre Say 72214.000 72214.000 72214.000 14,443.00 14,443.00 14,443.00
12.14 B Clayey Soil ( 8m dia. Well )
Unit = Running Meter.
Taking output = 1 meter
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.220 0.220 0.220 617.00 135.74 135.74 135.74 L-12
Sinker ( skilled ) day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Sinking helper ( semi-skilled ) hour 3.500 3.500 3.500 617.00 2,159.50 2,159.50 2,159.50 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 5.500 5.500 5.500 1,094.10 6,017.55 6,017.55 6,017.55 P&M-111

Consumables in sinking @ 10 per cent of (b) 601.76 601.76 601.76


c) Overhead charges @ 20% on @ 20% on @ 20% on
2,009.20 2,009.20 2,009.20
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,205.52 1,205.52 1,205.52
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 13,260.73 13,260.73 13,260.73
Say 13,261.00 13,261.00 13,261.00
12.14 B (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.17 m/hour
a) Labour
Mate day 0.280 0.280 0.280 617.00 172.76 172.76 172.76 L-12
Sinker day 2.500 2.500 2.500 565.73 1,414.33 1,414.33 1,414.33 L-15
Sinking helper ( semi-skilled ) day 4.500 4.500 4.500 617.00 2,776.50 2,776.50 2,776.50 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 6.000 6.000 6.000 1,094.10 6,564.60 6,564.60 6,564.60 P&M-111

Air compressor with pneumatic chisel attachment


for cutting hard clay. P&M-029
hour 3.500 3.500 3.500 625.80 2,190.30 2,190.30 2,190.30
+P&M-078

Consumables in sinking @ 10 per cent of (b) 875.49 875.49 875.49


c) Overhead charges @ 20% on @ 20% on @ 20% on
2,798.80 2,798.80 2,798.80
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,679.28 1,679.28 1,679.28
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 18,472.05 18,472.05 18,472.05
Say 18,472.00 18,472.00 18,472.00
12.14 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous
meter
b Add for dewatering @ 5 per cent of cost, if
required. for
for dewatering for dewatering @
dewatering @
@ 5% of cost, 5% of cost, if
5% of cost, if
if required required
required

11th m 5% 19396.000 19396.000 19396.000 970.00 970.00 970.00


12th m 5% 20366.000 20366.000 20366.000 1,018.00 1,018.00 1,018.00
13th m 5% 21384.000 21384.000 21384.000 1,069.00 1,069.00 1,069.00
14th m 5% 22453.000 22453.000 22453.000 1,123.00 1,123.00 1,123.00
15th m 5% 23576.000 23576.000 23576.000 1,179.00 1,179.00 1,179.00
16th m 5% 24755.000 24755.000 24755.000 1,238.00 1,238.00 1,238.00
17th m 5% 25993.000 25993.000 25993.000 1,300.00 1,300.00 1,300.00
18th m 5% 27293.000 27293.000 27293.000 1,365.00 1,365.00 1,365.00
19th m 5% 28658.000 28658.000 28658.000 1,433.00 1,433.00 1,433.00
20th m 5% 30091.000 30091.000 30091.000 1,505.00 1,505.00 1,505.00
Total Cost from 10m upto 20m 243965.000 243965.000 243965.000 12,200.00 12,200.00 12,200.00
Avg Rate per metre Say 24397.000 24397.000 24397.000 1,220.00 1,220.00 1,220.00
12.14 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 5 per cent of cost for dewatering on the cost,
if required
c Add 25 per cent of cost for Kentledge including 5% for
supports, loading arrangement and Labour ). 25% for 25% for
25% for Kentledge dewatering, if
Kentledge Kentledge
required
31st m 7.5% 32348.000 32348.000 32348.000 8,087.00 8,087.00 8,087.00 1,617.00
32nd 7.5% 34774.000 34774.000 34774.000 8,694.00 8,694.00 8,694.00 1,739.00
33rd m 7.5% 37382.000 37382.000 37382.000 9,346.00 9,346.00 9,346.00 1,869.00
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
34th m 7.5% 40186.000 40186.000 40186.000 10,047.00 10,047.00 10,047.00 2,009.00
35th m 7.5% 43200.000 43200.000 43200.000 10,800.00 10,800.00 10,800.00 2,160.00
36th m 7.5% 46440.000 46440.000 46440.000 11,610.00 11,610.00 11,610.00 2,322.00
37th m 7.5% 49923.000 49923.000 49923.000 12,481.00 12,481.00 12,481.00 2,496.00
38th m 7.5% 53667.000 53667.000 53667.000 13,417.00 13,417.00 13,417.00 2,683.00
39th m 7.5% 57692.000 57692.000 57692.000 14,423.00 14,423.00 14,423.00 2,885.00
40th m 7.5% 62019.000 62019.000 62019.000 15,505.00 15,505.00 15,505.00 3,101.00
Total Cost from 30m upto 40m 457631.000 457631.000 457631.000 114,410.00 114,410.00 114,410.00 22,881.00
Avg Rate per metre Say 45763.000 45763.000 45763.000 11,441.00 11,441.00 11,441.00 2,288.00
12.14 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 5 per cent of cost for dewatering, if required

c Add 20 per cent of cost for Kentledge including 5% for


supports, loading arrangement and Labour). 20% for 20% for
20% for Kentledge dewatering, if
Kentledge Kentledge
required
31st m 10% 68221.000 68221.000 68221.000 13,644.00 13,644.00 13,644.00 3,411.00
32nd 10% 75043.000 75043.000 75043.000 15,009.00 15,009.00 15,009.00 3,752.00
33rd m 10% 82547.000 82547.000 82547.000 16,509.00 16,509.00 16,509.00 4,127.00
34th m 10% 90802.000 90802.000 90802.000 18,160.00 18,160.00 18,160.00 4,540.00
35th m 10% 99882.000 99882.000 99882.000 19,976.00 19,976.00 19,976.00 4,994.00
36th m 10% 109870.000 109870.000 109870.000 21,974.00 21,974.00 21,974.00 5,494.00
37th m 10% 120857.000 120857.000 120857.000 24,171.00 24,171.00 24,171.00 6,043.00
38th m 10% 132943.000 132943.000 132943.000 26,589.00 26,589.00 26,589.00 6,647.00
39th m 10% 146237.000 146237.000 146237.000 29,247.00 29,247.00 29,247.00 7,312.00
40th m 10% 160861.000 160861.000 160861.000 32,172.00 32,172.00 32,172.00 8,043.00
Total Cost from 30m upto 40m 1087263.000 1087263.000 1087263.000 217,451.00 217,451.00 217,451.00 54,363.00
Avg Rate per metre Say 108726.000 108726.000 108726.000 21,745.00 21,745.00 21,745.00 5,436.00
12.14 C Extra over item no. 12.14 (A) & (B) irrespective of
depth for sinking in Soft Rock (8 m dia well )

Unit = Running Meter.


Taking output = 1 m
a) Labour
Mate day 0.650 0.650 0.650 617.00 401.05 401.05 401.05 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 2.250 2.250 2.250 617.00 1,388.25 1,388.25 1,388.25 L-14
Diver day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-07
Mazdoor day 12.000 12.000 12.000 511.52 6,138.24 6,138.24 6,138.24 L-13
b) Machinery
Air Compressor 250 cfm hour 50.266 50.266 50.266 614.25 30,875.58 30,875.58 30,875.58 P&M-029
Pneumatic breaker hour 100.531 100.531 100.531 11.55 1,161.13 1,161.13 1,161.13 P&M-078
Consumables in sinking @ 5 per cent of (b) 1,601.84 1,601.84 1,601.84
Add for dewatering @ of 15 per cent of (a+b), if
required 6,417.55 6,417.55 6,417.55
Additional Hire & running charges for shifting of
crane (rock breaking time) with grab bucket of 0.75
cum capacity and accessories. hour 3.000 3.000 3.000 1,094.10 3,282.30 3,282.30 3,282.30 P&M-111

c) Overhead charges @ 20% on @ 20% on @ 20% on


10,496.71 10,496.71 10,496.71
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
6,298.02 6,298.02 6,298.02
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 69,278.27 69,278.27 69,278.27
Say 69,278.00 69,278.00 69,278.00
12.14 D Extra over item no. 12.14 (A) & (B) irrespective of
depth for sinking in Hard Rock (8 m dia well )

Unit = Running Meter


Taking output = 1 m
a) Material
Small dia.Explosive at 0.20 kg / cum kg 10.053 10.053 10.053 19.00 191.01 191.01 191.01 M-218
Electric detonators no 50.000 50.000 50.000 81.90 4,095.00 4,095.00 4,095.00 M-215
Detonating fuse coil m 155.000 155.000 155.000 21.00 3,255.00 3,255.00 3,255.00 M-217
b) Labour
Mate day 0.660 0.660 0.660 617.00 407.22 407.22 407.22 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 2.250 2.250 2.250 617.00 1,388.25 1,388.25 1,388.25 L-14
Diver day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-07
Driller day 2.000 2.000 2.000 558.00 1,116.00 1,116.00 1,116.00 L-06
Blaster day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-03
Mazdoor day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-13
c) Machinery
Air Compressor 250 cfm hour 41.050 41.050 41.050 614.25 25,214.77 25,214.77 25,214.77 P&M-029
Pneumatic breaker hour 40.212 40.212 40.212 11.55 464.45 464.45 464.45 P&M-078
Pneumatic breaker for drilling holes (@ 4.5 m per
hour) hour 25.887 25.887 25.887 11.55 298.99 298.99 298.99 P&M-078
Consumables in protected blasting @ 10 per cent
2,597.82 2,597.82 2,597.82
of (c)
Add for dewatering @ of 15 per cent of (a+b+c), if
required 6,823.38 6,823.38 6,823.38
Additional Hire & running charges for shifting of
crane (rock breaking time) with grab bucket of 0.75
cum capacity and accessories. hour 3.000 3.000 3.000 1,094.10 3,282.30 3,282.30 3,282.30 P&M-111

d) Overhead charges @ 20% on @ 20% on @ 20% on


11,118.98 11,118.98 11,118.98
(a+b+c) (a+b+c) (a+b+c)
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
e) Contractor's profit @ 10% on @ 10% on @ 10% on
6,671.39 6,671.39 6,671.39
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per metre = (a+b+c+d+e) 73,385.24 73,385.24 73,385.24
Say 73,385.00 73,385.00 73,385.00
12.14 E Extra over item no. 12.14 (A) & (B) irrespective of
depth for sinking in rock bouldery strata (8 m dia
well )
Unit = Running Meter.
Taking output = 1 m
a) Labour
Mate day 0.570 0.570 0.570 617.00 351.69 351.69 351.69 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 2.250 2.250 2.250 617.00 1,388.25 1,388.25 1,388.25 L-14
Diver day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-07
Mazdoor day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-13
b) Machinery
Air Compressor 250 cfm hour 83.776 83.776 83.776 614.25 51,459.41 51,459.41 51,459.41 P&M-029
Pneumatic breaker hour 167.552 167.552 167.552 11.55 1,935.23 1,935.23 1,935.23 P&M-078
Consumables in sinking @ 5 per cent of (b) 2,669.73 2,669.73 2,669.73
Add for dewatering @ of 15 per cent of (a+b), if
required 9,620.57 9,620.57 9,620.57
Additional Hire & running charges for shifting of
crane (rock breaking time) with grab bucket of 0.75
cum capacity and accessories. hour 3.000 3.000 3.000 1,094.10 3,282.30 3,282.30 3,282.30 P&M-111

c) Overhead charges @ 20% on @ 20% on @ 20% on


15,407.99 15,407.99 15,407.99
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
9,244.80 9,244.80 9,244.80
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 101,692.75 101,692.75 101,692.75
Say 101,693.00 101,693.00 101,693.00
12.15 Section Sinking of 9 m external diameter well ( other than
1200 pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is
reckoned from bed level.

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 9 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a) Labour
Mate day 0.190 0.190 0.190 617.00 117.23 117.23 117.23 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 3.250 3.250 3.250 617.00 2,005.25 2,005.25 2,005.25 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 4.000 4.000 4.000 1,094.10 4,376.40 4,376.40 4,376.40 P&M-111

Consumables in sinking @10 per cent of (b) 437.64 437.64 437.64


c) Overhead charges @ 20% on @ 20% on @ 20% on
1,557.02 1,557.02 1,557.02
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
934.21 934.21 934.21
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 10,276.35 10,276.35 10,276.35
Say 10,276.00 10,276.00 10,276.00
12.15 A (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.230 0.230 0.230 617.00 141.91 141.91 141.91 L-12
Sinker day 1.750 1.750 1.750 565.73 990.03 990.03 990.03 L-15
Sinking helper ( semi-skilled ) day 4.000 4.000 4.000 617.00 2,468.00 2,468.00 2,468.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 5.500 5.500 5.500 1,094.10 6,017.55 6,017.55 6,017.55 P&M-111

Consumables in sinking @10 per cent of (b) 601.76 601.76 601.76


c) Overhead charges @ 20% on @ 20% on @ 20% on
2,043.85 2,043.85 2,043.85
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,226.31 1,226.31 1,226.31
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 13,489.40 13,489.40 13,489.40
Say 13,489.00 13,489.00 13,489.00
12.15 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous
meter
11th m 5% 14164.000 14164.000 14164.000
12th m 5% 14872.000 14872.000 14872.000
13th m 5% 15616.000 15616.000 15616.000
14th m 5% 16397.000 16397.000 16397.000
15th m 5% 17217.000 17217.000 17217.000
16th m 5% 18078.000 18078.000 18078.000
17th m 5% 18982.000 18982.000 18982.000
18th m 5% 19931.000 19931.000 19931.000
19th m 5% 20928.000 20928.000 20928.000
20th m 5% 21974.000 21974.000 21974.000
Total Cost from 10m upto 20m 178159.000 178159.000 178159.000
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Avg Rate per metre Say 17816.000 17816.000 17816.000
12.15 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 20 per cent of cost for Kentledge including Including
supports, loading arrangement and Labour. 20% for Including 20% for
20% for
Kentledge Kentledge
Kentledge
21st m 7.5% 23622.050 23622.050 23622.050 4,724.00 4,724.00 4,724.00
22nd m 7.5% 25394.000 25394.000 25394.000 5,079.00 5,079.00 5,079.00
23rd m 7.5% 27299.000 27299.000 27299.000 5,460.00 5,460.00 5,460.00
24th m 7.5% 29346.000 29346.000 29346.000 5,869.00 5,869.00 5,869.00
25th m 7.5% 31547.000 31547.000 31547.000 6,309.00 6,309.00 6,309.00
26th m 7.5% 33913.000 33913.000 33913.000 6,783.00 6,783.00 6,783.00
27th m 7.5% 36456.000 36456.000 36456.000 7,291.00 7,291.00 7,291.00
28th m 7.5% 39190.000 39190.000 39190.000 7,838.00 7,838.00 7,838.00
29th m 7.5% 42129.000 42129.000 42129.000 8,426.00 8,426.00 8,426.00
30th m 7.5% 45289.000 45289.000 45289.000 9,058.00 9,058.00 9,058.00
Total Cost from 20m upto 30m 334185.050 334185.050 334185.050 66,837.00 66,837.00 66,837.00
Avg Rate per metre Say 33419.000 33419.000 33419.000 6,684.00 6,684.00 6,684.00
12.15 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 20 per cent of cost for Kentledge including
supports, loading arrangement, and Labour etc. 20% for 20% for
20% for Kentledge
Kentledge Kentledge

31st m 10% 49817.900 49817.900 49817.900 9,964.00 9,964.00 9,964.00


32nd 10% 54800.000 54800.000 54800.000 10,960.00 10,960.00 10,960.00
33rd m 10% 60280.000 60280.000 60280.000 12,056.00 12,056.00 12,056.00
34th m 10% 66308.000 66308.000 66308.000 13,262.00 13,262.00 13,262.00
35th m 10% 72939.000 72939.000 72939.000 14,588.00 14,588.00 14,588.00
36th m 10% 80233.000 80233.000 80233.000 16,047.00 16,047.00 16,047.00
37th m 10% 88256.000 88256.000 88256.000 17,651.00 17,651.00 17,651.00
38th m 10% 97082.000 97082.000 97082.000 19,416.00 19,416.00 19,416.00
39th m 10% 106790.000 106790.000 106790.000 21,358.00 21,358.00 21,358.00
40th m 10% 117469.000 117469.000 117469.000 23,494.00 23,494.00 23,494.00
Total Cost from 30m upto 40m 793974.900 793974.900 793974.900 158,796.00 158,796.00 158,796.00
Avg Rate per metre Say 79397.000 79397.000 79397.000 15,880.00 15,880.00 15,880.00
12.15 B Clayey Soil ( 9m dia. Well )
Unit = Running Meter.
Taking output = 1 cum
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.17 m / hour
a) Labour
Mate day 0.240 0.240 0.240 617.00 148.08 148.08 148.08 L-12
Sinker ( skilled ) day 2.250 2.250 2.250 565.73 1,272.89 1,272.89 1,272.89 L-15
Sinking helper ( semi-skilled ) day 3.750 3.750 3.750 617.00 2,313.75 2,313.75 2,313.75 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 5.750 5.750 5.750 1,094.10 6,291.08 6,291.08 6,291.08 P&M-111

Consumables in sinking @ 10 per cent of (b) 629.11 629.11 629.11


c) Overhead charges @ 20% on @ 20% on @ 20% on
2,130.98 2,130.98 2,130.98
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,278.59 1,278.59 1,278.59
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 14,064.47 14,064.47 14,064.47
Say 14,064.00 14,064.00 14,064.00
12.15 B (ii) Beyond 3m upto 10m depth
Rate of sinking 0.15 m / hour
a) Labour
Mate day 0.300 0.300 0.300 617.00 185.10 185.10 185.10 L-12
Sinker day 2.500 2.500 2.500 565.73 1,414.33 1,414.33 1,414.33 L-15
Sinking helper ( semi-skilled ) day 5.000 5.000 5.000 617.00 3,085.00 3,085.00 3,085.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 6.500 6.500 6.500 1,094.10 7,111.65 7,111.65 7,111.65 P&M-111

Air compressor with pneumatic chisel attachment


for cutting hard clay. P&M-029
hour 3.750 3.750 3.750 625.80 2,346.75 2,346.75 2,346.75
+P&M-078

Consumables in sinking @ 10 per cent of (b) 945.84 945.84 945.84


c) Overhead charges @ 20% on @ 20% on @ 20% on
3,017.73 3,017.73 3,017.73
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,810.64 1,810.64 1,810.64
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 19,917.04 19,917.04 19,917.04
Say 19,917.00 19,917.00 19,917.00
12.15 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous
meter
b Add for dewatering @ 5 per cent of cost, if
required. for
for dewatering for dewatering @
dewatering @
@ 5% of cost, 5% of cost, if
5% of cost, if
if required required
required

11th m 5% 20913.000 20913.000 20913.000 1,046.00 1,046.00 1,046.00


12th m 5% 21959.000 21959.000 21959.000 1,098.00 1,098.00 1,098.00
13th m 5% 23057.000 23057.000 23057.000 1,153.00 1,153.00 1,153.00
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
14th m 5% 24210.000 24210.000 24210.000 1,211.00 1,211.00 1,211.00
15th m 5% 25421.000 25421.000 25421.000 1,271.00 1,271.00 1,271.00
16th m 5% 26692.000 26692.000 26692.000 1,335.00 1,335.00 1,335.00
17th m 5% 28027.000 28027.000 28027.000 1,401.00 1,401.00 1,401.00
18th m 5% 29428.000 29428.000 29428.000 1,471.00 1,471.00 1,471.00
19th m 5% 30899.000 30899.000 30899.000 1,545.00 1,545.00 1,545.00
20th m 5% 32444.000 32444.000 32444.000 1,622.00 1,622.00 1,622.00
Total Cost from 10m upto 20m 263050.000 263050.000 263050.000 13,153.00 13,153.00 13,153.00
Avg Rate per metre Say 26305.000 26305.000 26305.000 1,315.00 1,315.00 1,315.00
12.15 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 5 per cent of cost for dewatering on the cost,
if required
c Add 25 per cent of cost for Kentledge including Including Including 5%
supports, loading arrangement and Labour ). Including 25% Including 25% for
25% for for dewatering, if
for Kentledge Kentledge
Kentledge required
31st m 7.5% 34877.000 34877.000 34877.000 8,719.00 8,719.00 8,719.00 1,744.00
32nd 7.5% 37493.000 37493.000 37493.000 9,373.00 9,373.00 9,373.00 1,875.00
33rd m 7.5% 40305.000 40305.000 40305.000 10,076.00 10,076.00 10,076.00 2,015.00
34th m 7.5% 43328.000 43328.000 43328.000 10,832.00 10,832.00 10,832.00 2,166.00
35th m 7.5% 46578.000 46578.000 46578.000 11,645.00 11,645.00 11,645.00 2,329.00
36th m 7.5% 50071.000 50071.000 50071.000 12,518.00 12,518.00 12,518.00 2,504.00
37th m 7.5% 53826.000 53826.000 53826.000 13,457.00 13,457.00 13,457.00 2,691.00
38th m 7.5% 57863.000 57863.000 57863.000 14,466.00 14,466.00 14,466.00 2,893.00
39th m 7.5% 62203.000 62203.000 62203.000 15,551.00 15,551.00 15,551.00 3,110.00
40th m 7.5% 66868.000 66868.000 66868.000 16,717.00 16,717.00 16,717.00 3,343.00
Total Cost from 30m upto 40m 493412.000 493412.000 493412.000 123,354.00 123,354.00 123,354.00 24,670.00
Avg Rate per metre Say 49341.000 49341.000 49341.000 12,335.00 12,335.00 12,335.00 2,467.00
12.15 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 5 per cent of cost for dewatering, if required

c Add 20 per cent of cost for Kentledge including Including Including 5%


supports, loading arrangement and Labour). Including 20% Including 20% for
20% for for dewatering, if
for Kentledge Kentledge
Kentledge required
31st m 10% 73555.000 73555.000 73555.000 14,711.00 14,711.00 14,711.00 3,678.00
32nd 10% 80911.000 80911.000 80911.000 16,182.00 16,182.00 16,182.00 4,046.00
33rd m 10% 89002.000 89002.000 89002.000 17,800.00 17,800.00 17,800.00 4,450.00
34th m 10% 97902.000 97902.000 97902.000 19,580.00 19,580.00 19,580.00 4,895.00
35th m 10% 107692.000 107692.000 107692.000 21,538.00 21,538.00 21,538.00 5,385.00
36th m 10% 118461.000 118461.000 118461.000 23,692.00 23,692.00 23,692.00 5,923.00
37th m 10% 130307.000 130307.000 130307.000 26,061.00 26,061.00 26,061.00 6,515.00
38th m 10% 143338.000 143338.000 143338.000 28,668.00 28,668.00 28,668.00 7,167.00
39th m 10% 157672.000 157672.000 157672.000 31,534.00 31,534.00 31,534.00 7,884.00
40th m 10% 173439.000 173439.000 173439.000 34,688.00 34,688.00 34,688.00 8,672.00
Total Cost from 30m upto 40m 1172279.000 1172279.000 1172279.000 234,454.00 234,454.00 234,454.00 58,615.00
Avg Rate per metre Say 117228.000 117228.000 117228.000 23,445.00 23,445.00 23,445.00 5,862.00
12.15 C Extra over item no. 12.15 (A) & (B) irrespective of
depth for sinking in Soft Rock (9 m dia well )

Unit = Running Meter.


Taking output = 1 m
a) Labour
Mate day 0.730 0.730 0.730 617.00 450.41 450.41 450.41 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 2.250 2.250 2.250 617.00 1,388.25 1,388.25 1,388.25 L-14
Diver day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-07
Mazdoor day 14.000 14.000 14.000 511.52 7,161.28 7,161.28 7,161.28 L-13
b) Machinery
Air Compressor 250 cfm hour 63.618 63.618 63.618 614.25 39,077.05 39,077.05 39,077.05 P&M-029
Pneumatic breaker hour 127.235 127.235 127.235 11.55 1,469.56 1,469.56 1,469.56 P&M-078
Consumables in sinking @ 5 per cent of (b) 2,027.33 2,027.33 2,027.33
Add for dewatering @ of 15 per cent of (a+b), if
required 7,918.72 7,918.72 7,918.72
Additional Hire & running charges for shifting of
crane (rock breaking time) with grab bucket of 0.75
cum capacity and accessories. hour 3.000 3.000 3.000 1,094.10 3,282.30 3,282.30 3,282.30 P&M-111

c) Overhead charges @ 20% on @ 20% on @ 20% on


12,798.50 12,798.50 12,798.50
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
7,679.10 7,679.10 7,679.10
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 84,470.10 84,470.10 84,470.10
Say 84,470.00 84,470.00 84,470.00
12.15 D Extra over item no. 12.15 (A) & (B) irrespective of
depth for sinking in Hard Rock (9 m dia well )

Unit = Running Meter


Taking output = 1 m
a) Material
Small dia.Explosive at 0.20 kg / cum kg 12.723 12.723 12.723 81.90 1,042.05 1,042.05 1,042.05 M-215
Electric detonators no 65.000 65.000 65.000 21.00 1,365.00 1,365.00 1,365.00 M-217
Detonating fuse coil m 202.000 202.000 202.000 19.00 3,838.00 3,838.00 3,838.00 M-218
b) Labour
Mate day 0.740 0.740 0.740 617.00 456.58 456.58 456.58 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Sinking helper ( semi-skilled ) day 2.250 2.250 2.250 617.00 1,388.25 1,388.25 1,388.25 L-14
Diver day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-07
Driller day 2.000 2.000 2.000 558.00 1,116.00 1,116.00 1,116.00 L-06
Blaster day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-03
Mazdoor day 12.000 12.000 12.000 511.52 6,138.24 6,138.24 6,138.24 L-13
c) Machinery
Air Compressor 250 cfm hour 49.829 49.828 49.828 614.25 30,607.16 30,607.10 30,607.10 P&M-029
Pneumatic breaker hour 50.894 50.894 50.894 11.55 587.83 587.82 587.82 P&M-078
Pneumatic breaker for drilling holes (@ 4.5 m per
hour) hour 32.763 32.763 32.763 11.55 378.41 378.41 378.41 P&M-078
Consumables in protected blasting @ 10 per cent
of (c) 3,157.34 3,157.33 3,157.33
Add for dewatering @ of 15 per cent of (a+b+c), if
required 7,713.05 7,713.04 7,713.04
Additional Hire & running charges for shifting of
crane (rock breaking time) with grab bucket of 0.75
cum capacity and accessories. hour 3.000 3.000 3.000 1,094.10 3,282.30 3,282.30 3,282.30 P&M-111

d) Overhead charges @ 20% on @ 20% on @ 20% on


12,483.14 12,483.12 12,483.12
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
7,489.88 7,489.87 7,489.87
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per metre = (a+b+c+d+e) 76,143.65 76,143.54 76,143.54
Say 76,144.00 76,144.00 76,144.00
12.15 E Extra over item no. 12.15 (A) & (B) irrespective of
depth for sinking in rock bouldery strata (9 m dia
well )
Unit = Running Meter.
Taking output = 1 m
a) Labour
Mate day 0.650 0.650 0.650 617.00 401.05 401.05 401.05 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 2.250 2.250 2.250 617.00 1,388.25 1,388.25 1,388.25 L-14
Diver day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-07
Mazdoor day 12.000 12.000 12.000 511.52 6,138.24 6,138.24 6,138.24 L-13
b) Machinery
Air Compressor 250 cfm hour 106.029 106.029 106.029 614.25 65,128.31 65,128.31 65,128.31 P&M-029
Pneumatic breaker hour 212.058 212.058 212.058 11.55 2,449.27 2,449.27 2,449.27 P&M-078
Consumables in sinking @ 5 per cent of (b) 3,378.88 3,378.88 3,378.88
Add for dewatering @ of 15 per cent of (a+b), if
required 12,015.24 12,015.24 12,015.24
Additional Hire & running charges for shifting of
crane (rock breaking time) with grab bucket of 0.75
cum capacity and accessories. hour 3.000 3.000 3.000 1,094.10 3,282.30 3,282.30 3,282.30 P&M-111

c) Overhead charges @ 20% on @ 20% on @ 20% on


19,079.83 19,079.83 19,079.83
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
11,447.90 11,447.90 11,447.90
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 125,926.86 125,926.86 125,926.86
Say 125,927.00 125,927.00 125,927.00
12.16 1200 Sinking of 10 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is
reckoned from bed level.

Unit = Running Meter


Taking output = 1 m
Diameter of well - 10 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.20 m / hour
a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 3.500 3.500 3.500 617.00 2,159.50 2,159.50 2,159.50 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 5.000 5.000 5.000 1,094.10 5,470.50 5,470.50 5,470.50 P&M-111

Consumables in sinking @10 per cent of (b) 547.05 547.05 547.05


c) Overhead charges @ 20% on @ 20% on @ 20% on
1,829.81 1,829.81 1,829.81
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,097.89 1,097.89 1,097.89
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 12,076.74 12,076.74 12,076.74
Say 12,077.00 12,077.00 12,077.00
12.16 A (ii) Beyond 3m upto 10m depth
Rate of sinking 0.17 m / hour
a) Labour
Mate day 0.250 0.250 0.250 617.00 154.25 154.25 154.25 L-12
Sinker day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Sinking helper ( semi-skilled ) day 4.250 4.250 4.250 617.00 2,622.25 2,622.25 2,622.25 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 5.750 5.750 5.750 1,094.10 6,291.08 6,291.08 6,291.08 P&M-111

Consumables in sinking @10 per cent of (b) 629.11 629.11 629.11


Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
c) Overhead charges @ 20% on @ 20% on @ 20% on
2,165.63 2,165.63 2,165.63
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,299.38 1,299.38 1,299.38
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 14,293.15 14,293.15 14,293.15
Say 14,293.00 14,293.00 14,293.00
12.16 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous
meter
11th m 5% 15008.000 15008.000 15008.000
12th m 5% 15758.000 15758.000 15758.000
13th m 5% 16546.000 16546.000 16546.000
14th m 5% 17373.000 17373.000 17373.000
15th m 5% 18242.000 18242.000 18242.000
16th m 5% 19154.000 19154.000 19154.000
17th m 5% 20112.000 20112.000 20112.000
18th m 5% 21118.000 21118.000 21118.000
19th m 5% 22174.000 22174.000 22174.000
20th m 5% 23283.000 23283.000 23283.000
Total Cost from 10m upto 20m 188768.000 188768.000 188768.000
Avg Rate per metre Say 18877.000 18877.000 18877.000
12.16 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 20 per cent of cost for Kentledge including Including
supports, loading arrangement and Labour. Including 20% Including 20% for
20% for
for Kentledge Kentledge
Kentledge
21st m 7.5% 25029.000 25029.000 25029.000 5,006.00 5,006.00 5,006.00
22nd m 7.5% 26906.000 26906.000 26906.000 5,381.00 5,381.00 5,381.00
23rd m 7.5% 28924.000 28924.000 28924.000 5,785.00 5,785.00 5,785.00
24th m 7.5% 31093.000 31093.000 31093.000 6,219.00 6,219.00 6,219.00
25th m 7.5% 33425.000 33425.000 33425.000 6,685.00 6,685.00 6,685.00
26th m 7.5% 35932.000 35932.000 35932.000 7,186.00 7,186.00 7,186.00
27th m 7.5% 38627.000 38627.000 38627.000 7,725.00 7,725.00 7,725.00
28th m 7.5% 41524.000 41524.000 41524.000 8,305.00 8,305.00 8,305.00
29th m 7.5% 44638.000 44638.000 44638.000 8,928.00 8,928.00 8,928.00
30th m 7.5% 47986.000 47986.000 47986.000 9,597.00 9,597.00 9,597.00
Total Cost from 20m upto 30m 354084.000 354084.000 354084.000 70,817.00 70,817.00 70,817.00
Avg Rate per metre Say 35408.000 35408.000 35408.000 7,082.00 7,082.00 7,082.00
12.16 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 20 per cent of cost for Kentledge including Including
supports, loading arrangement, and Labour etc. Including 20% Including 20% for
20% for
for Kentledge Kentledge
Kentledge
31st m 10% 52785.000 52785.000 52785.000 10,557.00 10,557.00 10,557.00
32nd 10% 58064.000 58064.000 58064.000 11,613.00 11,613.00 11,613.00
33rd m 10% 63870.000 63870.000 63870.000 12,774.00 12,774.00 12,774.00
34th m 10% 70257.000 70257.000 70257.000 14,051.00 14,051.00 14,051.00
35th m 10% 77283.000 77283.000 77283.000 15,457.00 15,457.00 15,457.00
36th m 10% 85011.000 85011.000 85011.000 17,002.00 17,002.00 17,002.00
37th m 10% 93512.000 93512.000 93512.000 18,702.00 18,702.00 18,702.00
38th m 10% 102863.000 102863.000 102863.000 20,573.00 20,573.00 20,573.00
39th m 10% 113149.000 113149.000 113149.000 22,630.00 22,630.00 22,630.00
40th m 10% 124464.000 124464.000 124464.000 24,893.00 24,893.00 24,893.00
Total Cost from 30m upto 40m 841258.000 841258.000 841258.000 168,252.00 168,252.00 168,252.00
Avg Rate per metre Say 84126.000 84126.000 84126.000 16,825.00 16,825.00 16,825.00
12.16 B Clayey Soil (10m dia. Well )
Unit = Running Meter
Taking output = 1 cum
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.18m/hour.
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Sinker ( skilled ) day 2.500 2.500 2.500 565.73 1,414.33 1,414.33 1,414.33 L-15
Sinking helper ( semi-skilled ) day 5.500 5.500 5.500 617.00 3,393.50 3,393.50 3,393.50 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 6.000 6.000 6.000 1,094.10 6,564.60 6,564.60 6,564.60 P&M-111

Consumables in sinking @ 10 per cent of (b) 656.46 656.46 656.46


c) Overhead charges @ 20% on @ 20% on @ 20% on
2,445.27 2,445.27 2,445.27
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,467.16 1,467.16 1,467.16
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 16,138.75 16,138.75 16,138.75
Say 16,139.00 16,139.00 16,139.00
12.16 B (ii) Beyond 3m upto 10m depth
Rate of sinking 0.15m/hour.
a) Labour
Mate day 0.340 0.340 0.340 617.00 209.78 209.78 209.78 L-12
Sinker day 3.000 3.000 3.000 565.73 1,697.19 1,697.19 1,697.19 L-15
Sinking helper ( semi-skilled ) day 5.500 5.500 5.500 617.00 3,393.50 3,393.50 3,393.50 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 6.000 6.000 6.000 1,094.10 6,564.60 6,564.60 6,564.60 P&M-111
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Air compressor with pneumatic chisel attachment
for cutting hard clay P&M-029
hour 4.000 4.000 4.000 625.80 2,503.20 2,503.20 2,503.20
+P&M-078

Consumables in sinking @ 10 per cent of (b) 906.78 906.78 906.78


c) Overhead charges @ 20% on @ 20% on @ 20% on
3,055.01 3,055.01 3,055.01
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,833.01 1,833.01 1,833.01
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 20,163.07 20,163.07 20,163.07
Say 20,163.00 20,163.00 20,163.00
12.16 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous
meter
b Add for dewatering @ 5 per cent of cost, if
required. Including for
for dewatering Including for
dewatering @
@ 5% of cost, dewatering @ 5%
5% of cost, if
if required of cost, if required
required

11th m 5% 21171.000 21171.000 21171.000 1,059.00 1,059.00 1,059.00


12th m 5% 22230.000 22230.000 22230.000 1,112.00 1,112.00 1,112.00
13th m 5% 23342.000 23342.000 23342.000 1,167.00 1,167.00 1,167.00
14th m 5% 24509.000 24509.000 24509.000 1,225.00 1,225.00 1,225.00
15th m 5% 25734.000 25734.000 25734.000 1,287.00 1,287.00 1,287.00
16th m 5% 27021.000 27021.000 27021.000 1,351.00 1,351.00 1,351.00
17th m 5% 28372.000 28372.000 28372.000 1,419.00 1,419.00 1,419.00
18th m 5% 29791.000 29791.000 29791.000 1,490.00 1,490.00 1,490.00
19th m 5% 31281.000 31281.000 31281.000 1,564.00 1,564.00 1,564.00
20th m 5% 32845.000 32845.000 32845.000 1,642.00 1,642.00 1,642.00
Total Cost from 10m upto 20m 266296.000 266296.000 266296.000 13,316.00 13,316.00 13,316.00
Avg Rate per metre Say 26630.000 26630.000 26630.000 1,332.00 1,332.00 1,332.00
12.16 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 5 per cent of cost for dewatering on the cost,
if required
c Add 25 per cent of cost for Kentledge including 5% for
supports, loading arrangement and Labour ). 25% for 25% for
25% for Kentledge dewatering, if
Kentledge Kentledge
required
31st m 7.5% 35308.000 35308.000 35308.000 8,827.00 8,827.00 8,827.00 1,765.00
32nd 7.5% 37956.000 37956.000 37956.000 9,489.00 9,489.00 9,489.00 1,898.00
33rd m 7.5% 40803.000 40803.000 40803.000 10,201.00 10,201.00 10,201.00 2,040.00
34th m 7.5% 43863.000 43863.000 43863.000 10,966.00 10,966.00 10,966.00 2,193.00
35th m 7.5% 47153.000 47153.000 47153.000 11,788.00 11,788.00 11,788.00 2,358.00
36th m 7.5% 50689.000 50689.000 50689.000 12,672.00 12,672.00 12,672.00 2,534.00
37th m 7.5% 54491.000 54491.000 54491.000 13,623.00 13,623.00 13,623.00 2,725.00
38th m 7.5% 58578.000 58578.000 58578.000 14,645.00 14,645.00 14,645.00 2,929.00
39th m 7.5% 62971.000 62971.000 62971.000 15,743.00 15,743.00 15,743.00 3,149.00
40th m 7.5% 67694.000 67694.000 67694.000 16,924.00 16,924.00 16,924.00 3,385.00
Total Cost from 30m upto 40m 499506.000 499506.000 499506.000 124,878.00 124,878.00 124,878.00 24,976.00
Avg Rate per metre Say 49951.000 49951.000 49951.000 12,488.00 12,488.00 12,488.00 2,498.00
12.16 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 5 per cent of cost for dewatering, if required

c Add 20 per cent of cost for Kentledge including 5% for


supports, loading arrangement and Labour). 20% for 20% for
20% for Kentledge dewatering, if
Kentledge Kentledge
required
31st m 10% 74463.000 74463.000 74463.000 14,893.00 14,893.00 14,893.00 3,723.00
32nd 10% 81909.000 81909.000 81909.000 16,382.00 16,382.00 16,382.00 4,095.00
33rd m 10% 90100.000 90100.000 90100.000 18,020.00 18,020.00 18,020.00 4,505.00
34th m 10% 99110.000 99110.000 99110.000 19,822.00 19,822.00 19,822.00 4,956.00
35th m 10% 109021.000 109021.000 109021.000 21,804.00 21,804.00 21,804.00 5,451.00
36th m 10% 119923.000 119923.000 119923.000 23,985.00 23,985.00 23,985.00 5,996.00
37th m 10% 131915.000 131915.000 131915.000 26,383.00 26,383.00 26,383.00 6,596.00
38th m 10% 145107.000 145107.000 145107.000 29,021.00 29,021.00 29,021.00 7,255.00
39th m 10% 159618.000 159618.000 159618.000 31,924.00 31,924.00 31,924.00 7,981.00
40th m 10% 175580.000 175580.000 175580.000 35,116.00 35,116.00 35,116.00 8,779.00
Total Cost from 30m upto 40m 1186746.000 1186746.000 1186746.000 237,350.00 237,350.00 237,350.00 59,337.00
Avg Rate per metre Say 118675.000 118675.000 118675.000 23,735.00 23,735.00 23,735.00 5,934.00
12.16 C Extra over item no. 12.16 (A) & (B) irrespective of
depth for sinking in Soft Rock (10 m dia well )

Unit = Running Meter.


Taking output = 1 m
a) Labour
Mate day 0.810 0.810 0.810 617.00 499.77 499.77 499.77 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 2.250 2.250 2.250 617.00 1,388.25 1,388.25 1,388.25 L-14
Diver day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-07
Mazdoor day 16.000 16.000 16.000 511.52 8,184.32 8,184.32 8,184.32 L-13
b) Machinery
Air Compressor 250 cfm hour 78.540 78.540 78.540 614.25 48,243.20 48,243.20 48,243.20 P&M-029
Pneumatic breaker hour 157.080 157.080 157.080 11.55 1,814.27 1,814.27 1,814.27 P&M-078
Consumables in sinking @ 5 per cent of (b) 2,502.87 2,502.87 2,502.87
Add for dewatering @ of 15 per cent of (a+b), if
required 9,577.54 9,577.54 9,577.54
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Additional Hire & running charges for shifting of
crane (rock breaking time) with grab bucket of 0.75
cum capacity and accessories. hour 3.000 3.000 3.000 1,094.10 3,282.30 3,282.30 3,282.30 P&M-111

c) Overhead charges @ 20% on @ 20% on @ 20% on


15,342.02 15,342.02 15,342.02
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
9,205.21 9,205.21 9,205.21
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 101,257.36 101,257.36 101,257.36
Say 101,257.00 101,257.00 101,257.00
12.16 D Extra over item no. 12.16 (A) & (B) irrespective of
depth for sinking in Hard Rock (10 m dia well )

Unit = Running Meter


Taking output = 1 m
a) Material
Small dia.Explosive at 0.20 kg / cum kg 15.708 15.708 15.708 81.90 1,286.48 1,286.48 1,286.48 M-215
Electric detonators no 82.000 82.000 82.000 21.00 1,722.00 1,722.00 1,722.00 M-217
Detonating fuse coil m 255.000 255.000 255.000 19.00 4,845.00 4,845.00 4,845.00 M-218
b) Labour
Mate day 0.820 0.820 0.820 617.00 505.94 505.94 505.94 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 2.250 2.250 2.250 617.00 1,388.25 1,388.25 1,388.25 L-14
Diver day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-07
Driller day 2.000 2.000 2.000 558.00 1,116.00 1,116.00 1,116.00 L-06
Blaster day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-03
Mazdoor day 14.000 14.000 14.000 511.52 7,161.28 7,161.28 7,161.28 L-13
c) Machinery
Air Compressor 250 cfm hour 59.640 59.640 59.640 614.25 36,633.82 36,633.82 36,633.82 P&M-029
Pneumatic breaker hour 62.832 62.832 62.832 11.55 725.71 725.71 725.71 P&M-078
Pneumatic breaker for drilling holes (@ 4.5 m per
hour) hour 40.448 40.448 40.448 11.55 467.17 467.17 467.17 P&M-078
Consumables in protected blasting @ 10 per cent
of (c) 3,782.67 3,782.67 3,782.67
Add for dewatering @ of 15 per cent of (a+b+c), if
9,146.97 9,146.97 9,146.97
required
Additional Hire & running charges for shifting of
crane (rock breaking time) with grab bucket of 0.75
cum capacity and accessories. hour 3.000 3.000 3.000 1,094.10 3,282.30 3,282.30 3,282.30 P&M-111

d) Overhead charges @ 20% on @ 20% on @ 20% on


14,681.82 14,681.82 14,681.82
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
8,809.09 8,809.09 8,809.09
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per metre = (a+b+c+d+e) 96,899.98 96,899.98 96,899.98
Say 96,900.00 96,900.00 96,900.00
12.16 E Extra over item no. 12.16 (A) & (B) irrespective of
depth for sinking in rock bouldery strata (10 m dia
well )
Unit = Running Meter.
Taking output = 1 m
a) Labour
Mate day 0.730 0.730 0.730 617.00 450.41 450.41 450.41 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 2.250 2.250 2.250 617.00 1,388.25 1,388.25 1,388.25 L-14
Diver day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-07
Mazdoor day 14.000 14.000 14.000 511.52 7,161.28 7,161.28 7,161.28 L-13
b) Machinery
Air Compressor 250 cfm hour 130.900 130.900 130.900 614.25 80,405.02 80,405.02 80,405.02 P&M-029
Pneumatic breaker hour 261.799 261.799 261.799 11.55 3,023.78 3,023.78 3,023.78 P&M-078
Consumables in sinking @ 5 per cent of (b) 4,171.44 4,171.44 4,171.44
Add for dewatering @ of 15 per cent of (a+b), if
required 14,672.67 14,672.67 14,672.67
Additional Hire & running charges for shifting of
crane (rock breaking time) with grab bucket of 0.75
cum capacity and accessories. hour 3.000 3.000 3.000 1,094.10 3,282.30 3,282.30 3,282.30 P&M-111

c) Overhead charges @ 20% on @ 20% on @ 20% on


23,154.55 23,154.55 23,154.55
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
13,892.73 13,892.73 13,892.73
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 152,820.01 152,820.01 152,820.01
Say 152,820.00 152,820.00 152,820.00
12.17 1200 Sinking of 11 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is
reckoned from bed level.

Unit = Running Meter


Taking output = 0.50 m
Diameter of well - 11 m.
A Sandy Soil
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.15 m/hour
a) Labour
Mate day 0.192 0.192 0.192 617.00 118.46 118.46 118.46 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper (semi-skilled) day 3.300 3.300 3.300 617.00 2,036.10 2,036.10 2,036.10 L-14
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 6.000 6.000 6.000 1,094.10 6,564.60 6,564.60 6,564.60 P&M-111

Consumables in sinking @10 per cent of (b) 656.46 656.46 656.46


c) Overhead charges @ 20% on @ 20% on @ 20% on
2,044.84 2,044.84 2,044.84
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,226.91 1,226.91 1,226.91
(a+b+c) (a+b+c) (a+b+c)
Cost for 0.5m = a+b+c+d 13,495.97 13,495.97 13,495.97
Rate per metre = (a+b+c+d)/0.50 26,991.94 26,991.94 26,991.94
Say 26,992.00 26,992.00 26,992.00
12.17 A (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.13 m/hour
a) Labour
Mate day 0.260 0.260 0.260 617.00 160.42 160.42 160.42 L-12
Sinker day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Sinking helper (semi-skilled) day 4.500 4.500 4.500 617.00 2,776.50 2,776.50 2,776.50 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 4.000 4.000 4.000 1,094.10 4,376.40 4,376.40 4,376.40 P&M-111

Consumables in sinking @10 per cent of (b) 437.64 437.64 437.64


c) Overhead charges @ 20% on @ 20% on @ 20% on
1,776.48 1,776.48 1,776.48
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,065.89 1,065.89 1,065.89
(a+b+c) (a+b+c) (a+b+c)
Cost for 0.5m = a+b+c+d 11,724.79 11,724.79 11,724.79
Rate per metre = (a+b+c+d)/0.50 23,449.59 23,449.59 23,449.59
Say 23,450.00 23,450.00 23,450.00
12.17 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous
meter
11th m 5% 24622.000 24622.000 24622.000
12th m 5% 25853.000 25853.000 25853.000
13th m 5% 27146.000 27146.000 27146.000
14th m 5% 28503.000 28503.000 28503.000
15th m 5% 29928.000 29928.000 29928.000
16th m 5% 31424.000 31424.000 31424.000
17th m 5% 32995.000 32995.000 32995.000
18th m 5% 34645.000 34645.000 34645.000
19th m 5% 36377.000 36377.000 36377.000
20th m 5% 38196.000 38196.000 38196.000
Total Cost from 10m upto 20m 309689.000 309689.000 309689.000
Avg Rate per metre Say 30969.000 30969.000 30969.000
12.17 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 20 per cent of cost for Kentledge including
supports, loading arrangement and Labour. 20% for 20% for
20% for Kentledge
Kentledge Kentledge

21st m 7.5% 41061.000 41061.000 41061.000 8,212.00 8,212.00 8,212.00


22nd m 7.5% 44141.000 44141.000 44141.000 8,828.00 8,828.00 8,828.00
23rd m 7.5% 47452.000 47452.000 47452.000 9,490.00 9,490.00 9,490.00
24th m 7.5% 51011.000 51011.000 51011.000 10,202.00 10,202.00 10,202.00
25th m 7.5% 54837.000 54837.000 54837.000 10,967.00 10,967.00 10,967.00
26th m 7.5% 58950.000 58950.000 58950.000 11,790.00 11,790.00 11,790.00
27th m 7.5% 63371.000 63371.000 63371.000 12,674.00 12,674.00 12,674.00
28th m 7.5% 68124.000 68124.000 68124.000 13,625.00 13,625.00 13,625.00
29th m 7.5% 73233.000 73233.000 73233.000 14,647.00 14,647.00 14,647.00
30th m 7.5% 78725.000 78725.000 78725.000 15,745.00 15,745.00 15,745.00
Total Cost from 20m upto 30m 580905.000 580905.000 580905.000 116,180.00 116,180.00 116,180.00
Avg Rate per metre Say 58091.000 58091.000 58091.000 11,618.00 11,618.00 11,618.00
12.17 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 20 per cent of cost for Kentledge including
supports, loading arrangement, and Labour etc. 20% for
Kentledge

31st m 10% 86598.000 86598.000 86598.000 17,320.00 17,320.00 17,320.00


32nd 10% 95258.000 95258.000 95258.000 19,052.00 19,052.00 19,052.00
33rd m 10% 104784.000 104784.000 104784.000 20,957.00 20,957.00 20,957.00
34th m 10% 115262.000 115262.000 115262.000 23,052.00 23,052.00 23,052.00
35th m 10% 126788.000 126788.000 126788.000 25,358.00 25,358.00 25,358.00
36th m 10% 139467.000 139467.000 139467.000 27,893.00 27,893.00 27,893.00
37th m 10% 153414.000 153414.000 153414.000 30,683.00 30,683.00 30,683.00
38th m 10% 168755.000 168755.000 168755.000 33,751.00 33,751.00 33,751.00
39th m 10% 185631.000 185631.000 185631.000 37,126.00 37,126.00 37,126.00
40th m 10% 204194.000 204194.000 204194.000 40,839.00 40,839.00 40,839.00
Total Cost from 30m upto 40m 1380151.000 1380151.000 1380151.000 276,031.00 276,031.00 276,031.00
Avg Rate per metre Say 138015.000 138015.000 138015.000 27,603.00 27,603.00 27,603.00
12.17 B Clayey Soil (11 m dia. Well )
Unit = Running Meter
Taking output = 0.50 meter
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.10 m/hour
a) Labour
Mate day 0.260 0.260 0.260 617.00 160.42 160.42 160.42 L-12
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Sinker ( skilled ) day 2.500 2.500 2.500 565.73 1,414.33 1,414.33 1,414.33 L-15
Sinking helper (semi-skilled) day 4.000 4.000 4.000 617.00 2,468.00 2,468.00 2,468.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 5.000 5.000 5.000 1,094.10 5,470.50 5,470.50 5,470.50 P&M-111

Consumables in sinking @ 10 per cent of (b) 547.05 547.05 547.05


c) Overhead charges @ 20% on @ 20% on @ 20% on
2,012.06 2,012.06 2,012.06
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,207.24 1,207.24 1,207.24
(a+b+c) (a+b+c) (a+b+c)
Cost for 0.5m = a+b+c+d 13,279.59 13,279.59 13,279.59
Rate per metre = (a+b+c+d)/0.50 26,559.18 26,559.18 26,559.18
Say 26,559.00 26,559.00 26,559.00
12.17 B (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.08 m/hour
a) Labour
Mate day 0.370 0.370 0.370 617.00 228.29 228.29 228.29 L-12
Sinker day 3.500 3.500 3.500 565.73 1,980.06 1,980.06 1,980.06 L-15
Sinking helper (semi-skilled) day 5.750 5.750 5.750 617.00 3,547.75 3,547.75 3,547.75 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 6.000 6.000 6.000 1,094.10 6,564.60 6,564.60 6,564.60 P&M-111

Air compressor with pneumatic chisel attachment


for cutting hard clay P&M-029
hour 4.250 4.250 4.250 625.80 2,659.65 2,659.65 2,659.65
+P&M-078

Consumables in sinking @ 10 per cent of (b) 922.43 922.43 922.43


c) Overhead charges @ 20% on @ 20% on @ 20% on
3,180.55 3,180.55 3,180.55
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,908.33 1,908.33 1,908.33
(a+b+c) (a+b+c) (a+b+c)
Cost for 0.5m = a+b+c+d 20,991.66 20,991.66 20,991.66
Rate per metre = (a+b+c+d)/0.50 41,983.31 41,983.31 41,983.31
Say 41,983.00 41,983.00 41,983.00
12.17 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous
meter
b
for
for dewatering for dewatering @
Add for dewatering @ 5 per cent of cost, if dewatering @
@ 5% of cost, 5% of cost, if
required. 5% of cost, if
if required required
required

11th m 5% 44082.000 44082.000 44082.000 2,204.00 2,204.00 2,204.00


12th m 5% 46286.000 46286.000 46286.000 2,314.00 2,314.00 2,314.00
13th m 5% 48600.000 48600.000 48600.000 2,430.00 2,430.00 2,430.00
14th m 5% 51030.000 51030.000 51030.000 2,552.00 2,552.00 2,552.00
15th m 5% 53582.000 53582.000 53582.000 2,679.00 2,679.00 2,679.00
16th m 5% 56261.000 56261.000 56261.000 2,813.00 2,813.00 2,813.00
17th m 5% 59074.000 59074.000 59074.000 2,954.00 2,954.00 2,954.00
18th m 5% 62028.000 62028.000 62028.000 3,101.00 3,101.00 3,101.00
19th m 5% 65129.000 65129.000 65129.000 3,256.00 3,256.00 3,256.00
20th m 5% 68385.000 68385.000 68385.000 3,419.00 3,419.00 3,419.00
Total Cost from 10m upto 20m 554457.000 554457.000 554457.000 27,722.00 27,722.00 27,722.00
Avg Rate per metre Say 55446.000 55446.000 55446.000 2,772.00 2,772.00 2,772.00
12.17 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 5 per cent of cost for dewatering on the cost,
if required
c Add 25 per cent of cost for Kentledge including 5% for
supports, loading arrangement and Labour ). 25% for 25% for
25% for Kentledge dewatering, if
Kentledge Kentledge
required
31st m 7.5% 73514.000 73514.000 73514.000 18,379.00 18,379.00 18,379.00 3,676.00
32nd 7.5% 79028.000 79028.000 79028.000 19,757.00 19,757.00 19,757.00 3,951.00
33rd m 7.5% 84955.000 84955.000 84955.000 21,239.00 21,239.00 21,239.00 4,248.00
34th m 7.5% 91327.000 91327.000 91327.000 22,832.00 22,832.00 22,832.00 4,566.00
35th m 7.5% 98177.000 98177.000 98177.000 24,544.00 24,544.00 24,544.00 4,909.00
36th m 7.5% 105540.000 105540.000 105540.000 26,385.00 26,385.00 26,385.00 5,277.00
37th m 7.5% 113456.000 113456.000 113456.000 28,364.00 28,364.00 28,364.00 5,673.00
38th m 7.5% 121965.000 121965.000 121965.000 30,491.00 30,491.00 30,491.00 6,098.00
39th m 7.5% 131112.000 131112.000 131112.000 32,778.00 32,778.00 32,778.00 6,556.00
40th m 7.5% 140945.000 140945.000 140945.000 35,236.00 35,236.00 35,236.00 7,047.00
Total Cost from 30m upto 40m 1040019.000 1040019.000 1040019.000 260,005.00 260,005.00 260,005.00 52,001.00
Avg Rate per metre Say 104002.000 104002.000 104002.000 26,001.00 26,001.00 26,001.00 5,200.00
12.17 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 5 per cent of cost for dewatering, if required

c Add 20 per cent of cost for Kentledge including 5% for


supports, loading arrangement and Labour). 20% for 20% for
20% for Kentledge dewatering, if
Kentledge Kentledge
required
31st m 10% 155040.000 155040.000 155040.000 31,008.00 31,008.00 31,008.00 7,752.00
32nd 10% 170544.000 170544.000 170544.000 34,109.00 34,109.00 34,109.00 8,527.00
33rd m 10% 187598.000 187598.000 187598.000 37,520.00 37,520.00 37,520.00 9,380.00
34th m 10% 206358.000 206358.000 206358.000 41,272.00 41,272.00 41,272.00 10,318.00
35th m 10% 226994.000 226994.000 226994.000 45,399.00 45,399.00 45,399.00 11,350.00
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
36th m 10% 249693.000 249693.000 249693.000 49,939.00 49,939.00 49,939.00 12,485.00
37th m 10% 274662.000 274662.000 274662.000 54,932.00 54,932.00 54,932.00 13,733.00
38th m 10% 302128.000 302128.000 302128.000 60,426.00 60,426.00 60,426.00 15,106.00
39th m 10% 332341.000 332341.000 332341.000 66,468.00 66,468.00 66,468.00 16,617.00
40th m 10% 365575.000 365575.000 365575.000 73,115.00 73,115.00 73,115.00 18,279.00
Total Cost from 30m upto 40m 2470933.000 2470933.000 2470933.000 494,188.00 494,188.00 494,188.00 123,547.00
Avg Rate per metre Say 247093.000 247093.000 247093.000 49,419.00 49,419.00 49,419.00 12,355.00
12.17 C Extra over item no. 12.17 (A) & (B) irrespective of
depth for sinking in Soft Rock (11 m dia well )

Unit = Running Meter.


Taking output = 1 m
a) Labour
Mate day 0.890 0.890 0.890 617.00 549.13 549.13 549.13 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 2.250 2.250 2.250 617.00 1,388.25 1,388.25 1,388.25 L-14
Diver day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-07
Mazdoor day 18.000 18.000 18.000 511.52 9,207.36 9,207.36 9,207.36 L-13
b) Machinery
Air Compressor 250 cfm hour 95.033 95.033 95.033 614.25 58,374.02 58,374.02 58,374.02 P&M-029
Pneumatic breaker hour 190.066 190.066 190.066 11.55 2,195.26 2,195.26 2,195.26 P&M-078
Consumables in sinking @ 5 per cent of (b) 3,028.46 3,028.46 3,028.46
Add for dewatering @ of 15 per cent of (a+b), if
required 11,394.01 11,394.01 11,394.01
Additional Hire & running charges for shifting of
crane (rock breaking time) with grab bucket of 0.75
cum capacity and accessories. hour 3.000 3.000 3.000 1,094.10 3,282.30 3,282.30 3,282.30 P&M-111

c) Overhead charges @ 20% on @ 20% on @ 20% on


18,127.28 18,127.28 18,127.28
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
10,876.37 10,876.37 10,876.37
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 119,640.04 119,640.04 119,640.04
Say 119,640.00 119,640.00 119,640.00
12.17 D Extra over item no. 12.17 (A) & (B) irrespective of
depth for sinking in Hard Rock (11 m dia well )

Unit = Running Meter


Taking output = 1 m
a) Material
Small dia.Explosive at 0.20 kg / cum kg 19.007 19.007 19.007 81.90 1,556.64 1,556.64 1,556.64 M-215
Electric detonators no 101.000 101.000 101.000 21.00 2,121.00 2,121.00 2,121.00 M-217
Detonating fuse coil m 314.000 314.000 314.000 19.00 5,966.00 5,966.00 5,966.00 M-218
b) Labour
Mate day 0.900 0.900 0.900 617.00 555.30 555.30 555.30 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 2.250 2.250 2.250 617.00 1,388.25 1,388.25 1,388.25 L-14
Diver day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-07
Driller day 2.000 2.000 2.000 558.00 1,116.00 1,116.00 1,116.00 L-06
Blaster day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-03
Mazdoor day 16.000 16.000 16.000 511.52 8,184.32 8,184.32 8,184.32 L-13
c) Machinery
Air Compressor 250 cfm hour 70.484 70.484 70.484 614.25 43,294.96 43,294.96 43,294.96 P&M-029
Pneumatic breaker hour 76.027 76.027 76.027 11.55 878.11 878.11 878.11 P&M-078
Pneumatic breaker for drilling holes (@ 4.5 m per
hour) hour 48.942 48.942 48.942 11.55 565.28 565.28 565.28 P&M-078
Consumables in protected blasting @ 10 per cent
of (c) 4,473.84 4,473.84 4,473.84
Add for dewatering @ of 15 per cent of (a+b+c), if
required 10,716.78 10,716.78 10,716.78
Additional Hire & running charges for shifting of
crane (rock breaking time) with grab bucket of 0.75
cum capacity and accessories. hour 3.000 3.000 3.000 1,094.10 3,282.30 3,282.30 3,282.30 P&M-111

d) Overhead charges @ 20% on @ 20% on @ 20% on


17,088.85 17,088.85 17,088.85
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
10,253.31 10,253.31 10,253.31
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d+e) 112,786.41 112,786.41 112,786.41
Say 112,786.00 112,786.00 112,786.00
12.17 E Extra over item no. 12.17 (A) & (B) irrespective of
depth for sinking inrock bouldery strata (11 m dia
well )
Unit = Running Meter.
Taking output = 1 m
a) Labour
Mate day 0.810 0.810 0.810 617.00 499.77 499.77 499.77 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 2.250 2.250 2.250 617.00 1,388.25 1,388.25 1,388.25 L-14
Diver day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-07
Mazdoor day 16.000 16.000 16.000 511.52 8,184.32 8,184.32 8,184.32 L-13
b) Machinery
Air Compressor 250 cfm hour 158.389 158.389 158.389 614.25 97,290.14 97,290.14 97,290.14 P&M-029
Pneumatic breaker hour 316.777 316.777 316.777 11.55 3,658.77 3,658.77 3,658.77 P&M-078
Consumables in sinking @ 5 per cent of (b) 5,047.45 5,047.45 5,047.45
Add for dewatering @ of 15 per cent of (a+b), if
required 17,592.94 17,592.94 17,592.94
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Additional Hire & running charges for shifting of
crane (rock breaking time) with grab bucket of 0.75
cum capacity and accessories. hour 3.000 3.000 3.000 1,094.10 3,282.30 3,282.30 3,282.30 P&M-111

c) Overhead charges @ 20% on @ 20% on @ 20% on


27,632.31 27,632.31 27,632.31
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
16,579.38 16,579.38 16,579.38
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 182,373.23 182,373.23 182,373.23
Say 182,373.00 182,373.00 182,373.00
12.18 1200 Sinking of 12 m external diameter well ( other than
pneumatic method of sinking ) through all types of
strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing
and technical specifications. Depth of sinking is
reckoned from bed level.

Unit = Running Meter


Taking output = 0.25 m
Diameter of well - 12 m.
A Sandy Soil
(i) I) Depth below bed level upto 3.0 M
Rate of sinking @ 0.05 m/hour
a) Labour
Mate day 0.230 0.230 0.230 617.00 141.91 141.91 141.91 L-12
Sinker ( skilled ) day 1.750 1.750 1.750 565.73 990.03 990.03 990.03 L-15
Sinking helper (semi-skilled) day 4.000 4.000 4.000 617.00 2,468.00 2,468.00 2,468.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 6.000 6.000 6.000 1,094.10 6,564.60 6,564.60 6,564.60 P&M-111

Consumables in sinking @10 per cent of (b) 656.46 656.46 656.46


c) Overhead charges @ 20% on @ 20% on @ 20% on
2,164.20 2,164.20 2,164.20
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,298.52 1,298.52 1,298.52
(a+b+c) (a+b+c) (a+b+c)
Cost for 0.25m = a+b+c+d 14,283.72 14,283.72 14,283.72
Rate per metre = (a+b+c+d)/0.25 57,134.87 57,134.87 57,134.87
Say 57,135.00 57,135.00 57,135.00
12.18 A (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.038 m/hour
a) Labour
Mate day 0.290 0.290 0.290 617.00 178.93 178.93 178.93 L-12
Sinker day 2.500 2.500 2.500 565.73 1,414.33 1,414.33 1,414.33 L-15
Sinking helper (semi-skilled) day 4.750 4.750 4.750 617.00 2,930.75 2,930.75 2,930.75 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 6.500 6.500 6.500 1,094.10 7,111.65 7,111.65 7,111.65 P&M-111

Consumables in sinking @10 per cent of (b) 711.17 711.17 711.17


c) Overhead charges @ 20% on @ 20% on @ 20% on
2,469.36 2,469.36 2,469.36
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,481.62 1,481.62 1,481.62
(a+b+c) (a+b+c) (a+b+c)
Cost for 0.25m = a+b+c+d 16,297.80 16,297.80 16,297.80
Rate per metre = (a+b+c+d)/0.25 65,191.21 65,191.21 65,191.21
Say 65,191.00 65,191.00 65,191.00
12.18 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous
meter
11th m 5% 68451.000 68451.000 68451.000
12th m 5% 71874.000 71874.000 71874.000
13th m 5% 75467.700 75468.000 75468.000
14th m 5% 79241.085 79241.000 79241.000
15th m 5% 83203.139 83203.000 83203.000
16th m 5% 87363.296 87363.000 87363.000
17th m 5% 91731.461 91731.000 91731.000
18th m 5% 96318.034 96318.000 96318.000
19th m 5% 101133.936 101134.000 101134.000
20th m 5% 106190.633 106191.000 106191.000
Total Cost from 10m upto 20m 860974.284 860974.000 860974.000
Avg Rate per metre Say 86097.000 86097.000 86097.000
12.18 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 20 per cent of cost for Kentledge including
supports, loading arrangement and Labour. 20% for 20% for
20% for Kentledge
Kentledge Kentledge

21st m 7.5% 114155.000 114155.000 114155.000 22,831.00 22,831.00 22,831.00


22nd m 7.5% 122717.000 122717.000 122717.000 24,543.00 24,543.00 24,543.00
23rd m 7.5% 131921.000 131921.000 131921.000 26,384.00 26,384.00 26,384.00
24th m 7.5% 141815.000 141815.000 141815.000 28,363.00 28,363.00 28,363.00
25th m 7.5% 152451.000 152451.000 152451.000 30,490.00 30,490.00 30,490.00
26th m 7.5% 163885.000 163885.000 163885.000 32,777.00 32,777.00 32,777.00
27th m 7.5% 176176.000 176176.000 176176.000 35,235.00 35,235.00 35,235.00
28th m 7.5% 189389.000 189389.000 189389.000 37,878.00 37,878.00 37,878.00
29th m 7.5% 203593.000 203593.000 203593.000 40,719.00 40,719.00 40,719.00
30th m 7.5% 218862.000 218862.000 218862.000 43,772.00 43,772.00 43,772.00
Total Cost from 20m upto 30m 1614964.000 1614964.000 1614964.000 322,992.00 322,992.00 322,992.00
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Avg Rate per metre Say 161496.000 161496.000 161496.000 32,299.00 32,299.00 32,299.00
12.18 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 20 per cent of cost for Kentledge including
supports, loading arrangement, and Labour etc. 20% for 20% for
20% for Kentledge
Kentledge Kentledge

31st m 10% 240748.000 240748.000 240748.000 48,150.00 48,150.00 48,150.00


32nd 10% 264823.000 264823.000 264823.000 52,965.00 52,965.00 52,965.00
33rd m 10% 291305.000 291305.000 291305.000 58,261.00 58,261.00 58,261.00
34th m 10% 320436.000 320436.000 320436.000 64,087.00 64,087.00 64,087.00
35th m 10% 352480.000 352480.000 352480.000 70,496.00 70,496.00 70,496.00
36th m 10% 387728.000 387728.000 387728.000 77,546.00 77,546.00 77,546.00
37th m 10% 426501.000 426501.000 426501.000 85,300.00 85,300.00 85,300.00
38th m 10% 469151.000 469151.000 469151.000 93,830.00 93,830.00 93,830.00
39th m 10% 516066.000 516066.000 516066.000 103,213.00 103,213.00 103,213.00
40th m 10% 567673.000 567673.000 567673.000 113,535.00 113,535.00 113,535.00
Total Cost from 30m upto 40m 3836911.000 3836911.000 3836911.000 767,383.00 767,383.00 767,383.00
Avg Rate per metre Say 383691.000 383691.000 383691.000 76,738.00 76,738.00 76,738.00
12.18 B Clayey Soil (12 m dia. Well )
Unit = Running Meter.
Taking output = 0.25 meter.
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.04 m/hour
a) Labour
Mate day 0.300 0.300 0.300 617.00 185.10 185.10 185.10 L-12
Sinker ( skilled ) day 3.000 3.000 3.000 565.73 1,697.19 1,697.19 1,697.19 L-15
Sinking helper (semi-skilled) day 4.500 4.500 4.500 617.00 2,776.50 2,776.50 2,776.50 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 6.250 6.250 6.250 1,094.10 6,838.13 6,838.13 6,838.13 P&M-111

Consumables in sinking @ 10 per cent of (b) 683.81 683.81 683.81


c) Overhead charges @ 20% on @ 20% on @ 20% on
2,436.15 2,436.15 2,436.15
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,461.69 1,461.69 1,461.69
(a+b+c) (a+b+c) (a+b+c)
Cost for 0.25m = a+b+c+d 16,078.56 16,078.56 16,078.56
Rate per metre = (a+b+c+d)/0.25 64,314.24 64,314.24 64,314.24
Say 64,314.00 64,314.00 64,314.00
12.18 B (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.03 m/hour
a) Labour
Mate day 0.390 0.390 0.390 617.00 240.63 240.63 240.63 L-12
Sinker day 3.750 3.750 3.750 565.73 2,121.49 2,121.49 2,121.49 L-15
Sinking helper (semi-skilled) day 6.000 6.000 6.000 617.00 3,702.00 3,702.00 3,702.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 8.330 8.330 8.330 1,094.10 9,113.85 9,113.85 9,113.85 P&M-111

Air compressor with pneumatic chisel attachment


for cutting hard clay. P&M-029
hour 4.500 4.500 4.500 625.80 2,816.10 2,816.10 2,816.10
+P&M-078

Consumables in sinking @ 10 per cent of (b) 1,193.00 1,193.00 1,193.00


c) Overhead charges @ 20% on @ 20% on @ 20% on
3,837.41 3,837.41 3,837.41
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
2,302.45 2,302.45 2,302.45
(a+b+c) (a+b+c) (a+b+c)
Cost for 0.25m = a+b+c+d 25,326.93 25,326.93 25,326.93
Rate per metre = (a+b+c+d)/0.25 101,307.71 101,307.71 101,307.71
Say 101,308.00 101,308.00 101,308.00
12.18 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous
meter
b Add for dewatering @ 5 per cent of cost, if
required. for
for dewatering for dewatering @
dewatering @
@ 5% of cost, 5% of cost, if
5% of cost, if
if required required
required

11th m 5% 106373.000 106373.000 106373.000 5,319.00 5,319.00 5,319.00


12th m 5% 111692.000 111692.000 111692.000 5,585.00 5,585.00 5,585.00
13th m 5% 117277.000 117277.000 117277.000 5,864.00 5,864.00 5,864.00
14th m 5% 123141.000 123141.000 123141.000 6,157.00 6,157.00 6,157.00
15th m 5% 129298.000 129298.000 129298.000 6,465.00 6,465.00 6,465.00
16th m 5% 135763.000 135763.000 135763.000 6,788.00 6,788.00 6,788.00
17th m 5% 142551.000 142551.000 142551.000 7,128.00 7,128.00 7,128.00
18th m 5% 149679.000 149679.000 149679.000 7,484.00 7,484.00 7,484.00
19th m 5% 157163.000 157163.000 157163.000 7,858.00 7,858.00 7,858.00
20th m 5% 165021.000 165021.000 165021.000 8,251.00 8,251.00 8,251.00
Total Cost from 10m upto 20m 1337958.000 1337958.000 1337958.000 66,899.00 66,899.00 66,899.00
Avg Rate per metre Say 133796.000 133796.000 133796.000 6,690.00 6,690.00 6,690.00
12.18 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 5 per cent of cost for dewatering on the cost,
if required
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
c Add 25 per cent of cost for Kentledge including 5% for
supports, loading arrangement and Labour ). 25% for 25% for
25% for Kentledge dewatering, if
Kentledge Kentledge
required
31st m 7.5% 177398.000 177398.000 177398.000 44,350.00 44,350.00 44,350.00 8,870.00
32nd 7.5% 190703.000 190703.000 190703.000 47,676.00 47,676.00 47,676.00 9,535.00
33rd m 7.5% 205006.000 205006.000 205006.000 51,252.00 51,252.00 51,252.00 10,250.00
34th m 7.5% 220381.000 220381.000 220381.000 55,095.00 55,095.00 55,095.00 11,019.00
35th m 7.5% 236910.000 236910.000 236910.000 59,228.00 59,228.00 59,228.00 11,846.00
36th m 7.5% 254678.000 254678.000 254678.000 63,670.00 63,670.00 63,670.00 12,734.00
37th m 7.5% 273779.000 273779.000 273779.000 68,445.00 68,445.00 68,445.00 13,689.00
38th m 7.5% 294312.000 294312.000 294312.000 73,578.00 73,578.00 73,578.00 14,716.00
39th m 7.5% 316385.000 316385.000 316385.000 79,096.00 79,096.00 79,096.00 15,819.00
40th m 7.5% 340114.000 340114.000 340114.000 85,029.00 85,029.00 85,029.00 17,006.00
Total Cost from 30m upto 40m 2509666.000 2509666.000 2509666.000 627,419.00 627,419.00 627,419.00 125,484.00
Avg Rate per metre Say 250967.000 250967.000 250967.000 62,742.00 62,742.00 62,742.00 12,548.00
12.18 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 5 per cent of cost for dewatering, if required

c Add 20 per cent of cost for Kentledge including 5% for


supports, loading arrangement and Labour). 20% for 20% for
20% for Kentledge dewatering, if
Kentledge Kentledge
required
31st m 10% 374125.000 374125.000 374125.000 74,825.00 74,825.00 74,825.00 18,706.00
32nd 10% 411538.000 411538.000 411538.000 82,308.00 82,308.00 82,308.00 20,577.00
33rd m 10% 452692.000 452692.000 452692.000 90,538.00 90,538.00 90,538.00 22,635.00
34th m 10% 497961.000 497961.000 497961.000 99,592.00 99,592.00 99,592.00 24,898.00
35th m 10% 547757.000 547757.000 547757.000 109,551.00 109,551.00 109,551.00 27,388.00
36th m 10% 602533.000 602533.000 602533.000 120,507.00 120,507.00 120,507.00 30,127.00
37th m 10% 662786.000 662786.000 662786.000 132,557.00 132,557.00 132,557.00 33,139.00
38th m 10% 729065.000 729065.000 729065.000 145,813.00 145,813.00 145,813.00 36,453.00
39th m 10% 801972.000 801972.000 801972.000 160,394.00 160,394.00 160,394.00 40,099.00
40th m 10% 882169.000 882169.000 882169.000 176,434.00 176,434.00 176,434.00 44,108.00
Total Cost from 30m upto 40m 5962598.000 5962598.000 5962598.000 1,192,519.00 ### 1,192,519.00 298,130.00
Avg Rate per metre Say 596260.000 596260.000 596260.000 119,252.00 119,252.00 119,252.00 29,813.00
12.18 C Extra over item no. 12.18 (A) & (B) irrespective of
depth for sinking in Soft Rock (12 m dia well )

Unit = Running Meter.


Taking output = 1 m
a) Labour
Mate day 0.970 0.970 0.970 617.00 598.49 598.49 598.49 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 2.250 2.250 2.250 617.00 1,388.25 1,388.25 1,388.25 L-14
Diver day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-07
Mazdoor day 20.000 20.000 20.000 511.52 10,230.40 10,230.40 10,230.40 L-13
b) Machinery
Air Compressor 250 cfm hour 113.098 113.098 113.098 614.25 69,470.14 69,470.14 69,470.14 P&M-029
Pneumatic breaker hour 226.195 226.195 226.195 11.55 2,612.55 2,612.55 2,612.55 P&M-078
Consumables in sinking @ 5 per cent of (b) 3,604.13 3,604.13 3,604.13
Add for dewatering @ of 15 per cent of (a+b), if
13,368.23 13,368.23 13,368.23
required
Additional Hire & running charges for shifting of
crane (rock breaking time) with grab bucket of 0.75
cum capacity and accessories. hour 3.000 3.000 3.000 1,094.10 3,282.30 3,282.30 3,282.30 P&M-111

c) Overhead charges @ 20% on @ 20% on @ 20% on


21,154.42 21,154.42 21,154.42
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
12,692.65 12,692.65 12,692.65
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 139,619.17 139,619.17 139,619.17
Say 139,619.00 139,619.00 139,619.00
12.18 D Extra over item no. 12.18 (A) & (B) irrespective of
depth for sinking in Hard Rock (12 m dia well )

Unit = Running Meter


Taking output = 1 m
a) Material
Small dia.Explosive at 0.20 kg / cum kg 22.619 22.619 22.619 81.90 1,852.53 1,852.53 1,852.53 M-215
Electric detonators no 122.000 122.000 122.000 21.00 2,562.00 2,562.00 2,562.00 M-217
Detonating fuse coil m 379.000 379.000 379.000 19.00 7,201.00 7,201.00 7,201.00 M-218
b) Labour
Mate day 0.980 0.980 0.980 617.00 604.66 604.66 604.66 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 2.250 2.250 2.250 617.00 1,388.25 1,388.25 1,388.25 L-14
Diver day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-07
Driller day 2.000 2.000 2.000 558.00 1,116.00 1,116.00 1,116.00 L-06
Blaster day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-03
Mazdoor day 18.000 18.000 18.000 511.52 9,207.36 9,207.36 9,207.36 L-13
c) Machinery
Air Compressor 250 cfm hour 82.361 82.361 82.361 614.25 50,590.51 50,590.51 50,590.51 P&M-029
Pneumatic breaker hour 90.478 90.478 90.478 11.55 1,045.02 1,045.02 1,045.02 P&M-078
Pneumatic breaker for drilling holes (@ 4.5 m per
hour) hour 58.245 58.245 58.245 11.55 672.73 672.73 672.73 P&M-078
Consumables in protected blasting @ 10 per cent
of (c) 5,230.83 5,230.83 5,230.83
Add for dewatering @ of 15 per cent of (a+b+c), if
required 12,422.45 12,422.45 12,422.45
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Additional Hire & running charges for shifting of
crane (rock breaking time) with grab bucket of 0.75
cum capacity and accessories. hour 3.000 3.000 3.000 1,094.10 3,282.30 3,282.30 3,282.30 P&M-111

d) Overhead charges @ 20% on @ 20% on @ 20% on


19,704.22 19,704.22 19,704.22
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
11,822.53 11,822.53 11,822.53
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per metre = (a+b+c+d+e) 130,047.88 130,047.88 130,047.88
Say 130,048.00 130,048.00 130,048.00
12.18 E Extra over item no. 12.18 (A) & (B) irrespective of
depth for sinking in rock bouldery strata (12 m dia
well )
Unit = Running Meter.
Taking output = 1 m
a) Labour
Mate day 0.890 0.890 0.890 617.00 549.13 549.13 549.13 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 2.250 2.250 2.250 617.00 1,388.25 1,388.25 1,388.25 L-14
Diver day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-07
Mazdoor day 18.000 18.000 18.000 511.52 9,207.36 9,207.36 9,207.36 L-13
b) Machinery
Air Compressor 250 cfm hour 188.496 188.496 188.496 614.25 115,783.36 115,783.36 115,783.36 P&M-029
Pneumatic breaker hour 376.991 376.991 376.991 11.55 4,354.25 4,354.25 4,354.25 P&M-078
Consumables in sinking @ 5 per cent of (b) 6,006.88 6,006.88 6,006.88
Add for dewatering @ of 15 per cent of (a+b), if
required 20,776.02 20,776.02 20,776.02
Additional Hire & running charges for shifting of
crane (rock breaking time) with grab bucket of 0.75
cum capacity and accessories. hour 3.000 3.000 3.000 1,094.10 3,282.30 3,282.30 3,282.30 P&M-111

c) Overhead charges @ 20% on @ 20% on @ 20% on


32,513.03 32,513.03 32,513.03
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
19,507.82 19,507.82 19,507.82
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 214,585.99 214,585.99 214,585.99
Say 214,586.00 214,586.00 214,586.00
12.19 1200 Sinking of Twin D Type well (other than pneumatic
method of sinking) through all types of strata
namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and
technical specifications. Depth of sinking is
reckoned from bed level.

Unit = Running Meter


Taking output = 1 m
Dimensions of well.
Overall length = 12 m
Overall width = 6 m
A Sandy Soil
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/hour
a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Sinker ( skilled ) day 1.250 1.250 1.250 565.73 707.16 707.16 707.16 L-15
Sinking helper (semi-skilled) day 3.750 3.750 3.750 617.00 2,313.75 2,313.75 2,313.75 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 5.500 5.500 5.500 1,094.10 6,017.55 6,017.55 6,017.55 P&M-111

Consumables in sinking @10 per cent of (b) 601.76 601.76 601.76


c) Overhead charges @ 20% on @ 20% on @ 20% on
1,952.72 1,952.72 1,952.72
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,171.63 1,171.63 1,171.63
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 12,887.98 12,887.98 12,887.98
Say 12,888.00 12,888.00 12,888.00
12.19 A (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.17 m/hour
a) Labour
Mate day 0.220 0.220 0.220 617.00 135.74 135.74 135.74 L-12
Sinker day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper (semi-skilled) day 4.000 4.000 4.000 617.00 2,468.00 2,468.00 2,468.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 5.880 5.880 5.880 1,094.10 6,433.31 6,433.31 6,433.31 P&M-111

Consumables in sinking @10 per cent of (b) 643.33 643.33 643.33


c) Overhead charges @ 20% on @ 20% on @ 20% on
2,105.79 2,105.79 2,105.79
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,263.48 1,263.48 1,263.48
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 13,898.25 13,898.25 13,898.25
Say 13,898.00 13,898.00 13,898.00
12.19 A (iii) Beyond 10m upto 20m
a Add 5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous
meter
11th m 5% 14593.000 14593.000 14593.000
12th m 5% 15323.000 15323.000 15323.000
13th m 5% 16089.000 16089.000 16089.000
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
14th m 5% 16893.000 16893.000 16893.000
15th m 5% 17738.000 17738.000 17738.000
16th m 5% 18625.000 18625.000 18625.000
17th m 5% 19556.000 19556.000 19556.000
18th m 5% 20534.000 20534.000 20534.000
19th m 5% 21561.000 21561.000 21561.000
20th m 5% 22639.000 22639.000 22639.000
Total Cost from 10m upto 20m 183551.000 183551.000 183551.000
Avg Rate per metre Say 18355.000 18355.000 18355.000
12.19 A (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 20 per cent of cost for Kentledge including
supports, loading arrangement and Labour. 20% for 20% for
20% for Kentledge
Kentledge Kentledge

21st m 7.5% 24337.000 24337.000 24337.000 4,867.00 4,867.00 4,867.00


22nd m 7.5% 26162.000 26162.000 26162.000 5,232.00 5,232.00 5,232.00
23rd m 7.5% 28124.000 28124.000 28124.000 5,625.00 5,625.00 5,625.00
24th m 7.5% 30233.000 30233.000 30233.000 6,047.00 6,047.00 6,047.00
25th m 7.5% 32500.000 32500.000 32500.000 6,500.00 6,500.00 6,500.00
26th m 7.5% 34938.000 34938.000 34938.000 6,988.00 6,988.00 6,988.00
27th m 7.5% 37558.000 37558.000 37558.000 7,512.00 7,512.00 7,512.00
28th m 7.5% 40375.000 40375.000 40375.000 8,075.00 8,075.00 8,075.00
29th m 7.5% 43403.000 43403.000 43403.000 8,681.00 8,681.00 8,681.00
30th m 7.5% 46658.000 46658.000 46658.000 9,332.00 9,332.00 9,332.00
Total Cost from 20m upto 30m 344288.000 344288.000 344288.000 68,859.00 68,859.00 68,859.00
Avg Rate per metre Say 34429.000 34429.000 34429.000 6,886.00 6,886.00 6,886.00
12.19 A (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 20 per cent of cost for Kentledge including
supports, loading arrangement, and Labour etc. 20% for 20% for
20% for Kentledge
Kentledge Kentledge

31st m 10% 51324.000 51324.000 51324.000 10,265.00 10,265.00 10,265.00


32nd 10% 56456.000 56456.000 56456.000 11,291.00 11,291.00 11,291.00
33rd m 10% 62102.000 62102.000 62102.000 12,420.00 12,420.00 12,420.00
34th m 10% 68312.000 68312.000 68312.000 13,662.00 13,662.00 13,662.00
35th m 10% 75143.000 75143.000 75143.000 15,029.00 15,029.00 15,029.00
36th m 10% 82657.000 82657.000 82657.000 16,531.00 16,531.00 16,531.00
37th m 10% 90923.000 90923.000 90923.000 18,185.00 18,185.00 18,185.00
38th m 10% 100015.000 100015.000 100015.000 20,003.00 20,003.00 20,003.00
39th m 10% 110017.000 110017.000 110017.000 22,003.00 22,003.00 22,003.00
40th m 10% 121019.000 121019.000 121019.000 24,204.00 24,204.00 24,204.00
Total Cost from 30m upto 40m 817968.000 817968.000 817968.000 163,593.00 163,593.00 163,593.00
Avg Rate per metre Say 81797.000 81797.000 81797.000 16,359.00 16,359.00 16,359.00
12.19 B Clayey Soil (Twin D Type Well )
Unit = Running Meter
Taking output = 1 meter
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.16 m/hour
a) Labour
Mate day 0.260 0.260 0.260 617.00 160.42 160.42 160.42 L-12
Sinker ( skilled ) day 2.500 2.500 2.500 565.73 1,414.33 1,414.33 1,414.33 L-15
Sinking helper (semi-skilled) day 4.000 4.000 4.000 617.00 2,468.00 2,468.00 2,468.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 6.250 6.250 6.250 1,094.10 6,838.13 6,838.13 6,838.13 P&M-111

Consumables in sinking @ 10 per cent of (b) 683.81 683.81 683.81


c) Overhead charges @ 20% on @ 20% on @ 20% on
2,312.94 2,312.94 2,312.94
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,387.76 1,387.76 1,387.76
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 15,265.38 15,265.38 15,265.38
Say 15,265.00 15,265.00 15,265.00
12.19 B (ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.15 m/hour
a) Labour
Mate day 0.450 0.450 0.450 617.00 277.65 277.65 277.65 L-12
Sinker day 3.250 3.250 3.250 565.73 1,838.62 1,838.62 1,838.62 L-15
Sinking helper (semi-skilled) day 6.000 6.000 6.000 617.00 3,702.00 3,702.00 3,702.00 L-14
b) Machinery
Hire & running charges of crane with grab bucket
of 0.75 cum capacity and accessories. hour 6.670 6.670 6.670 1,094.10 7,297.65 7,297.65 7,297.65 P&M-111

Air compressor with pneumatic chisel attachment


for cutting hard clay. P&M-029
hour 4.500 4.500 4.500 625.80 2,816.10 2,816.10 2,816.10
+P&M-078

Consumables in sinking @ 10 per cent of (b) 1,011.37 1,011.37 1,011.37


c) Overhead charges @ 20% on @ 20% on @ 20% on
3,388.68 3,388.68 3,388.68
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
2,033.21 2,033.21 2,033.21
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 22,365.28 22,365.28 22,365.28
Say 22,365.00 22,365.00 22,365.00
12.19 B (iii) Beyond 10 m upto 20 m
a Add 5 per cent for every additional meter depth of
sinking over the rate of sinking for the previous
meter
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
b Add for dewatering @ 5 per cent of cost, if
required. for
for dewatering for dewatering @
dewatering @
@ 5% of cost, 5% of cost, if
5% of cost, if
if required required
required

11th m 5% 23484.000 23484.000 23484.000 1,174.00 1,174.00 1,174.00


12th m 5% 24658.000 24658.000 24658.000 1,233.00 1,233.00 1,233.00
13th m 5% 25891.000 25891.000 25891.000 1,295.00 1,295.00 1,295.00
14th m 5% 27186.000 27186.000 27186.000 1,359.00 1,359.00 1,359.00
15th m 5% 28545.000 28545.000 28545.000 1,427.00 1,427.00 1,427.00
16th m 5% 29972.000 29972.000 29972.000 1,499.00 1,499.00 1,499.00
17th m 5% 31471.000 31471.000 31471.000 1,574.00 1,574.00 1,574.00
18th m 5% 33045.000 33045.000 33045.000 1,652.00 1,652.00 1,652.00
19th m 5% 34697.000 34697.000 34697.000 1,735.00 1,735.00 1,735.00
20th m 5% 36432.000 36432.000 36432.000 1,822.00 1,822.00 1,822.00
Total Cost from 10m upto 20m 295381.000 295381.000 295381.000 14,770.00 14,770.00 14,770.00
Avg Rate per metre Say 29538.000 29538.000 29538.000 1,477.00 1,477.00 1,477.00
12.19 B (iv) Beyond 20m upto 30 m
a Add 7.5 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 5 per cent of cost for dewatering on the cost,
if required
c Add 25 per cent of cost for Kentledge including 5% for
supports, loading arrangement and Labour ). 25% for 25% for
25% for Kentledge dewatering, if
Kentledge Kentledge
required
31st m 7.5% 39164.000 39164.000 39164.000 9,791.00 9,791.00 9,791.00 1,958.00
32nd 7.5% 42101.000 42101.000 42101.000 10,525.00 10,525.00 10,525.00 2,105.00
33rd m 7.5% 45259.000 45259.000 45259.000 11,315.00 11,315.00 11,315.00 2,263.00
34th m 7.5% 48653.000 48653.000 48653.000 12,163.00 12,163.00 12,163.00 2,433.00
35th m 7.5% 52302.000 52302.000 52302.000 13,076.00 13,076.00 13,076.00 2,615.00
36th m 7.5% 56225.000 56225.000 56225.000 14,056.00 14,056.00 14,056.00 2,811.00
37th m 7.5% 60442.000 60442.000 60442.000 15,111.00 15,111.00 15,111.00 3,022.00
38th m 7.5% 64975.000 64975.000 64975.000 16,244.00 16,244.00 16,244.00 3,249.00
39th m 7.5% 69848.000 69848.000 69848.000 17,462.00 17,462.00 17,462.00 3,492.00
40th m 7.5% 75087.000 75087.000 75087.000 18,772.00 18,772.00 18,772.00 3,754.00
Total Cost from 30m upto 40m 554056.000 554056.000 554056.000 138,515.00 138,515.00 138,515.00 27,702.00
Avg Rate per metre Say 55406.000 55406.000 55406.000 13,852.00 13,852.00 13,852.00 2,770.00
12.19 B (v) Beyond 30m upto 40 m
a Add 10 per cent for every additional meter depth
of sinking over the rate of sinking for the previous
meter
b Add 5 per cent of cost for dewatering, if required

c Add 20 per cent of cost for Kentledge including Including Including 5%


supports, loading arrangement and Labour). 20% for Including 20% for
20% for for dewatering, if
Kentledge Kentledge
Kentledge required
31st m 10% 82596.000 82596.000 82596.000 16,519.00 16,519.00 16,519.00 4,130.00
32nd 10% 90856.000 90856.000 90856.000 18,171.00 18,171.00 18,171.00 4,543.00
33rd m 10% 99942.000 99942.000 99942.000 19,988.00 19,988.00 19,988.00 4,997.00
34th m 10% 109936.000 109936.000 109936.000 21,987.00 21,987.00 21,987.00 5,497.00
35th m 10% 120930.000 120930.000 120930.000 24,186.00 24,186.00 24,186.00 6,047.00
36th m 10% 133023.000 133023.000 133023.000 26,605.00 26,605.00 26,605.00 6,651.00
37th m 10% 146325.000 146325.000 146325.000 29,265.00 29,265.00 29,265.00 7,316.00
38th m 10% 160958.000 160958.000 160958.000 32,192.00 32,192.00 32,192.00 8,048.00
39th m 10% 177054.000 177054.000 177054.000 35,411.00 35,411.00 35,411.00 8,853.00
40th m 10% 194759.000 194759.000 194759.000 38,952.00 38,952.00 38,952.00 9,738.00
Total Cost from 30m upto 40m 1316379.000 1316379.000 1316379.000 263,276.00 263,276.00 263,276.00 65,820.00
Avg Rate per metre Say 131638.000 131638.000 131638.000 26,328.00 26,328.00 26,328.00 6,582.00
12.19 C Extra over item no. 12.19 (A) & (B) irrespective of
depth for sinking in Soft Rock

Unit = Running Meter.


Taking output = 1 m
a) Labour
Mate day 0.730 0.730 0.730 617.00 450.41 450.41 450.41 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 2.250 2.250 2.250 617.00 1,388.25 1,388.25 1,388.25 L-14
Diver day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-07
Mazdoor day 14.000 14.000 14.000 511.52 7,161.28 7,161.28 7,161.28 L-13
b) Machinery
Air Compressor 250 cfm hour 64.275 64.275 64.275 614.25 39,480.61 39,480.61 39,480.61 P&M-029
Pneumatic breaker hour 128.549 128.549 128.549 11.55 1,484.74 1,484.74 1,484.74 P&M-078
Consumables in sinking @ 5 per cent of (b) 2,048.27 2,048.27 2,048.27
Add for dewatering @ of 15 per cent of (a+b), if
required 7,984.67 7,984.67 7,984.67
Additional Hire & running charges for shifting of
crane (rock breaking time) with grab bucket of 0.75
cum capacity and accessories. hour 3.000 3.000 3.000 1,094.10 3,282.30 3,282.30 3,282.30 P&M-111

c) Overhead charges @ 20% on @ 20% on @ 20% on


12,899.63 12,899.63 12,899.63
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
7,739.78 7,739.78 7,739.78
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 85,137.53 85,137.53 85,137.53
Say 85,138.00 85,138.00 85,138.00
12.19 D Extra over item no. 12.19 (A) & (B) irrespective of
depth for sinking in Hard Rock

Unit = Running Meter


Taking output = 1 m
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
a) Material
Small dia.Explosive at 0.20 kg / cum kg 12.855 12.855 12.855 81.90 1,052.81 1,052.81 1,052.81 M-215
Electric detonators no 72.000 72.000 72.000 21.00 1,512.00 1,512.00 1,512.00 M-217
Detonating fuse coil m 224.000 224.000 224.000 19.00 4,256.00 4,256.00 4,256.00 M-218
b) Labour
Mate day 0.740 0.740 0.740 617.00 456.58 456.58 456.58 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 2.250 2.250 2.250 617.00 1,388.25 1,388.25 1,388.25 L-14
Diver day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-07
Driller day 2.000 2.000 2.000 558.00 1,116.00 1,116.00 1,116.00 L-06
Blaster day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-03
Mazdoor day 12.000 12.000 12.000 511.52 6,138.24 6,138.24 6,138.24 L-13
c) Machinery
Air Compressor 250 cfm hour 50.260 50.260 50.260 614.25 30,872.35 30,872.35 30,872.35 P&M-029
Pneumatic breaker hour 51.419 51.419 51.419 11.55 593.89 593.89 593.89 P&M-078
Pneumatic breaker for drilling holes (@ 4.5 m per
hour) hour 33.101 33.101 33.101 11.55 382.32 382.32 382.32 P&M-078
Consumables in protected blasting @ 10 per cent
of (c) 3,184.86 3,184.86 3,184.86
Add for dewatering @ of 15 per cent of (a+b+c), if
required 7,844.82 7,844.82 7,844.82
Additional Hire & running charges for shifting of
crane (rock breaking time) with grab bucket of 0.75
cum capacity and accessories. hour 3.000 3.000 3.000 1,094.10 3,282.30 3,282.30 3,282.30 P&M-111

d) Overhead charges @ 20% on @ 20% on @ 20% on


12,685.18 12,685.18 12,685.18
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
7,611.11 7,611.11 7,611.11
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per metre = (a+b+c+d+e) 83,722.18 83,722.18 83,722.18
Say 83,722.00 83,722.00 83,722.00
12.19 E Extra over item no. 12.19 (A) & (B) irrespective of
depth for sinking in rock bouldery strata

Unit = Running Meter.


Taking output = 1 m
a) Labour
Mate day 0.650 0.650 0.650 617.00 401.05 401.05 401.05 L-12
Sinker ( skilled ) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Sinking helper ( semi-skilled ) day 2.250 2.250 2.250 617.00 1,388.25 1,388.25 1,388.25 L-14
Diver day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-07
Mazdoor day 12.000 12.000 12.000 511.52 6,138.24 6,138.24 6,138.24 L-13
b) Machinery
Air Compressor 250 cfm hour 42.850 42.850 42.850 614.25 26,320.34 26,320.34 26,320.34 P&M-029
Pneumatic breaker hour 85.699 85.699 85.699 11.55 989.82 989.82 989.82 P&M-078
Consumables in sinking @ 5 per cent of (b) 1,365.51 1,365.51 1,365.51
Add for dewatering @ of 15 per cent of (a+b), if
required 5,673.12 5,673.12 5,673.12
Additional Hire & running charges for shifting of
crane (rock breaking time) with grab bucket of 0.75
cum capacity and accessories. hour 3.000 3.000 3.000 1,094.10 3,282.30 3,282.30 3,282.30 P&M-111

c) Overhead charges @ 20% on @ 20% on @ 20% on


9,355.25 9,355.25 9,355.25
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
5,613.15 5,613.15 5,613.15
(a+b+c) (a+b+c) (a+b+c)
Rate per metre = (a+b+c+d) 61,744.62 61,744.62 61,744.62
Say 61,745.00 61,745.00 61,745.00
12.20 1200 Pneumatic sinking of wells with equipment of
approved design, drawing and specifications
worked by competent and trained personnel and
comprising of compression and decompression
chambers, reducers, two air locks separately for
men and plant & materials, arrangement for supply
of fresh air to working chambers, check valves,
exhaust valves, shafts made from steel plates of
riveted construction not less than 6 mm thick to
withstand an air pressure of 0.50 MPa, controlled
blasting of hard rock where required, staircases
and 1 m wide landing plateforms with railing,
arrangement for compression and decompression,
electric lighting of 50 V maximum, proper rooms for
rest and medical examinations and compliance
with safety precautions as per IS:4138, all as per
clause1208.8 of MoRTH Specifications.

Unit - 1 cum
Taking output = 5 cum
a) Material
M35 grade RCC corbel provided for supporting of Cum 8.000 6,622.00 52,976.00
Item No. -
equipment (Dimensions as per ground conditions). Cum 8.000 6,658.00 53,264.00
12.08 H
Rate may be adopted vide Item 12.8 (H) Cum 8.000 6,777.00 54,216.00
HYSD bar reinforcement in corbel tonne 0.480 0.480 0.480 46,496.54 22,318.34 22,318.34 22,318.34 M-083
Blasting material
Explosives Kg 1.500 1.500 1.500 81.90 122.85 122.85 122.85 M-215
Electric detonators each 6.000 6.000 6.000 21.00 126.00 126.00 126.00 M-217
b) Labour
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Mate day 1.880 1.880 1.880 617.00 1,159.96 1,159.96 1,159.96 L-12
Driller day 1.000 1.000 1.000 558.00 558.00 558.00 558.00 L-06
Blaster day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-03
Mazdoor (for cutting, blasting, cleaning, removal of
Material etc.) day 30.000 30.000 30.000 511.52 15,345.60 15,345.60 15,345.60 L-13
Mazdoor (Skilled) (for fixation and removal of
adopter for air lock, carrying out mechanical and
electrical operations and repairs and other skilled day 10.000 10.000 10.000 565.73 5,657.30 5,657.30 5,657.30 L-15
jobs.)
Diver day 4.000 4.000 4.000 738.00 2,952.00 2,952.00 2,952.00 L-07
Medical Officer day 0.500 0.500 0.500 1,077.25 538.63 538.63 538.63 L-16
Para medical personnel day 1.000 1.000 1.000 622.72 622.72 622.72 622.72 L-19
c) Machinery
(i) Induction, deinduction and erection of plant and
equipment including all components and
accessories for pneumatic method of well sinking. hour 6.000 6.000 6.000 10,073.70 60,442.20 60,442.20 60,442.20 P&M-113

Induction and deinduction L.S 200,000.00 200,000.00 200,000.00


Erection at site and commissioning L.S 250,000.00 250,000.00 250,000.00
Usage of plant and equipment for pneumatic
method of well sinking hour 6.000 6.000 6.000 6,920.55 41,523.30 41,523.30 41,523.30 P&M-072
Air compressor 250 cfm, 2 nos. hour 12.000 12.000 12.000 614.25 7,371.00 7,371.00 7,371.00 P&M-029
Hire and running charges of crane of 15 tonne
capacity hour 6.000 6.000 6.000 1,278.90 7,673.40 7,673.40 7,673.40 P&M-105
Motorised barge of 20 tonne capacity hour 6.000 6.000 6.000 975.45 5,852.70 5,852.70 5,852.70 P&M-110
Boat to carry atleast 20 persons hour 6.000 6.000 6.000 975.45 5,852.70 5,852.70 5,852.70 P&M-110
Electric generating set 33 KVA hour 6.000 6.000 6.000 753.90 4,523.40 4,523.40 4,523.40 P&M-050
Tipper 10 tonne capacity hour 6.000 6.000 6.000 1,731.45 10,388.70 10,388.70 10,388.70 P&M-017
d) Overhead charges @ 20% on @ 20% on @ 20% on
139,252.11 139,309.71 139,500.11
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
83,551.27 83,585.83 83,700.07
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 5 cum = a+b+c+d+e (see notes below)
919,063.93 919,444.09 920,700.73
Rate per cum = (a+b+c+d+e)/5 183,812.79 183,888.82 184,140.15
Say 183,813.00 183,889.00 184,140.00

Note 1.The cost of induction, deinduction and erection of


equipment shall be divided by the total quantity of
pneumatic sinking for all the wells of a particular
bridge to arrive at the per cum rate on account of
this item.

2.Cost of pneumatic sinking per cum of individual


wells will be added to the cost indicated at (1)
above to arrive at the final rate of pneumatic
sinking per cum.
3.The cost of induction and deinduction will depend
upon the distance involved for shifting of
equipment which may be assessed in individual
cases as per actual ground conditions at the time
of making of cost estimates.

4.In case pneumatic sinking is involved on a dry


bed, the provision of barge and boat may be
omitted.
5.The necessity and dimensions of the corbel will
be as per actual ground conditions.

6.Small equipments like welding sets, pumps,


vibrators, pneumatic tools, portable lamps, fire
extinguishers, hose pipes etc., have not been
included as the same are covered as items of
minor T&P under overhead charges.

7.Depth of sinking shall be restricted to 30 m.


12.21 1207 Sand Filling in Wells complete as per Drawing and
Technical Specifications.
Unit = 1 cum
Taking output = 1 cum
a) Material
Sand (assuming 20 per cent voids ) cum 1.200 1.200 1.200 1,544.03 1,852.84 1,852.84 1,852.84 M-006
b) Labour
Mate day 0.012 0.012 0.012 617.00 7.40 7.40 7.40 L-12
Mazdoor day 0.300 0.300 0.300 511.52 153.46 153.46 153.46 L-13
c) Overhead charges @ 20% on @ 20% on @ 20% on
402.74 402.74 402.74
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
241.64 241.64 241.64
(a+b+c) (a+b+c) (a+b+c)
Rate per cum (a+b+c+d) 2,658.08 2,658.08 2,658.08
Say 2,658.00 2,658.00 2,658.00
12.22 1200 & Providing Steel Liner 10 mm thick for Curbs and 6
1900 mm thick for Steining of Wells including Fabricating
and Setting out as per Detailed Drawing.

Unit = 1 MT
Taking output = 1 MT
a) Material
i) Structural steel including 5 per cent wastage
tonne 1.050 1.050 1.050 63,806.54 66,996.87 66,996.87 66,996.87 M-181
b) Labour
Mate day 0.800 0.800 0.800 617.00 493.60 493.60 493.60 L-12
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Fitter day 4.000 4.000 4.000 738.00 2,952.00 2,952.00 2,952.00 L-08
Blacksmith day 4.000 4.000 4.000 679.00 2,716.00 2,716.00 2,716.00 L-01
Welder day 4.000 4.000 4.000 738.00 2,952.00 2,952.00 2,952.00 L-02
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
Electrodes, cutting gas and other consumables @
5 per cent on cost a (a) above. 3,349.84 3,349.84 3,349.84

c) Machinery
Hydra Crane of capacity 10T for lifting shifting hour 8.000 8.000 8.000 1,240.05 9,920.40 9,920.40 9,920.40 P&M-104

d) Overhead charges @ 20% on @ 20% on @ 20% on


18,694.58 18,694.58 18,694.58
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
11,216.75 11,216.75 11,216.75
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate for per MT (a+b+c+d) 123,384.20 123,384.20 123,384.20
Say 123,384.00 123,384.00 123,384.00
12.23 1100 & Bored cast-in-situ M35 grade R.C.C. Pile excluding
1700 Reinforcement complete as per Drawing and
Technical Specifications and removal of excavated
earth with all lifts and lead upto 1000 m.

Pile diameter-750 mm
Unit = meter
Taking output = 25 m
a) Materials
RCC Grade M35 (including additional concreteing
of 1m for pile head ) cum 11.486 9,089.00 104,400.33
Item No. -
Rate for concrete may be adopted same as for pile cum 11.486 9,139.00 104,974.65
12.11 F (iv)
vide item no. 12.11 F (iv) cum 11.486 9,303.00 106,858.43
Concrete
Bentonite to be cast with a tremie pipe 200mm dia. kg 574.500 574.500 574.500 4.31 2,476.10 2,476.10 2,476.10 M-071
b) Machinery (for boring and construction)
Hire and running charges of hydraulic piling rig with
power unit and complete accessories including
shifting from one bore location to another. hour 6.000 6.000 6.000 19,747.35 118,484.10 118,484.10 118,484.10 P&M-071

Hire and running charges of light crane for lowering


reinforcement cage, trime pipe, holding trime pipe
for concreting, removal of temporary casing etc hour 3.138 3.138 3.138 1,083.60 3,400.34 3,400.34 3,400.34 P&M-102

Hire and running charges of Bentonite pump


Rate included
hour 6.000 6.000 6.000 P&M-071
in piling rig

Transit truck agitator


For transportation (6 cum Capacity) tonne-km 29.07 x L1 29.07 x L1 29.07 x L1 13.41 11,695.59 11,695.59 11,695.59 P&M-128
For unloading hour 0.638 0.638 0.638 2,413.95 1,540.43 1,540.43 1,540.43 P&M-067
Front end loader for removing muck
(i) 3.1 Cum Capacity hour 0.342 4,279.80 1,463.09 P&M-011
(ii) 2.1 Cum Capacity hour 0.504 2,640.75 1,330.39 P&M-012
(iii) 1 Cum Capacity hour 1.064 1,112.00 1,182.68 P&M-013
Tipper
For Loading time
(i) 18 cum capacity hour 0.342 2,883.30 986.09 P&M-014
(ii) 14 cum capacity hour 0.504 2,556.75 1,288.60 P&M-015
(iii) 10 cum capacity hour 1.064 2,274.30 2,419.86 P&M-016
For disposal of muck from pile bore hole up to a
lead of 1 km
(i) 18 cum capacity t.km 18.384 6.18 113.59 P&M-116
(ii) 14 cum capacity t.km 18.384 7.01 128.92 P&M-119
(iii) 10 cum capacity t.km 18.384 8.66 159.28 P&M-122
c) Labour
Mate/Supervisor day 0.140 0.140 0.140 617.00 86.38 86.38 86.38 L-12
Mazdoor day 3.500 3.500 3.500 511.52 1,790.32 1,790.32 1,790.32 L-13
d) Overhead charges @ 20% on @ 20% on @ 20% on
28,407.20 28,444.23 28,647.01
(b+c) (b+c) (b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
17,044.32 17,066.54 17,188.21
(b+c+d) (b+c+d) (b+c+d)
Cost for 25 m = a+b+c+d+d+e 291,887.86 292,706.58 295,928.71
Rate per metre (a+b+c+d+e)/25 11,675.51 11,708.26 11,837.15
Say 11,676.00 11,708.00 11,837.00
12.24 Bored cast-in-situ M35 grade R.C.C. Pile excluding
1100,16 Reinforcement complete as per Drawing and
00 & Technical Specifications and removal of excavated
1700 earth with all lifts and lead upto 1000 m.

Pile diameter-1000 mm
Unit = meter
Taking output = 25 m
a)
RCC Materials
Grade M35 (including additional concreteing
of 1m for pile head ) cum 20.420 9,089.00 185,600.58
Item No. -
Rate for concrete may be adopted same as for pile cum 20.420 9,139.00 186,621.60
12.11 F (iv)
vide item no. 12.11 F (iv) cum 20.420 9,303.00 189,970.54
Concrete
Bentonite to be cast with a tremie pipe 200mm dia. kg 1021.018 1021.018 1021.018 4.31 4,400.59 4,400.59 4,400.59 M-071
b) Machinery( for boring and construction )

Hire and running charges of hydraulic piling rig with


power unit and complete accessories including
shifting from one bore location to another. hour 6.000 6.000 6.000 19,747.35 118,484.10 118,484.10 118,484.10 P&M-071
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Hire and running charges of light crane for lowering
reinforcement cage, trime pipe, holding trime pipe
for concreting, removal of temporary casing etc hour 3.634 3.634 3.634 1,083.60 3,937.80 3,937.80 3,937.80 P&M-102

Hire and running charges of Bentonite pump


Rate included
hour 6.000 6.000 6.000 P&M-071
in piling rig

Transit truck agitator


For transportation (6 cum Capacity) tonne-km 51.05 x L1 51.05 x L1 51.05 x L1 13.41 20,538.69 20,538.69 20,538.69 P&M-128
For unloading hour 1.134 1.134 1.134 2,413.95 2,737.42 2,737.42 2,737.42 P&M-067
Front end loader for removing muck
(i) 3.1 Cum Capacity hour 0.608 4,279.80 2,602.12 P&M-011
(ii) 2.1 Cum Capacity hour 0.896 2,640.75 2,366.11 P&M-012
(iii) 1 Cum Capacity hour 1.891 1,112.00 2,102.79 P&M-013
Tipper
For Loading time
(i) 18 cum capacity hour 0.608 2,883.30 1,753.05 P&M-014
(ii) 14 cum capacity hour 0.896 2,556.75 2,290.85 P&M-015
(iii) 10 cum capacity hour 1.891 2,274.30 4,300.70 P&M-016
For disposal of muck from pile bore hole up to a
lead of 1 km
(i) 18 cum capacity t.km 32.673 6.18 201.87 P&M-116
(ii) 14 cum capacity t.km 32.673 7.01 229.13 P&M-119
(iii) 10 cum capacity t.km 32.673 8.66 283.08 P&M-122
c) Labour
Mate/Supervisor day 0.140 0.140 0.140 617.00 86.38 86.38 86.38 L-12
Mazdoor day 3.500 3.500 3.500 511.52 1,790.32 1,790.32 1,790.32 L-13
d) Overhead charges @ 20% on @ 20% on @ 20% on
31,306.47 31,372.28 31,732.37
(b+c) (b+c) (b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
18,783.88 18,823.37 19,039.42
(b+c+d) (b+c+d) (b+c+d)
Cost for 25 m = a+b+c+d+d+e 392,223.26 393,678.63 399,404.20
Rate per metre (a+b+c+d+e)/25 15,688.93 15,747.15 15,976.17
Say 15,689.00 15,747.00 15,976.00
12.25 1100 & Bored cast-in-situ M35 grade R.C.C. Pile excluding
1700 Reinforcement complete as per Drawing and
Technical Specifications and removal of excavated
earth with all lifts and lead upto 1000 m.

A Pile diameter-1200 mm
Unit = meter
Taking output = 25 m
a)
RCC Materials
Grade M35 (including additional concreteing
of 1m for pile head ) cum 29.405 9,089.00 267,264.84
Item No. -
Rate for concrete may be adopted same as for pile cum 29.405 9,139.00 268,735.10
12.11 F (iv)
vide item no. 12.11 F (iv) cum 29.405 9,303.00 273,557.57
Concrete
Bentonite to be cast with a tremie pipe 200mm dia. kg 1470.265 1470.265 1470.265 4.31 6,336.84 6,336.84 6,336.84 M-071
b) Machinery( for boring and construction )

Hire and running charges of hydraulic piling rig with


power unit and complete accessories including
shifting from one bore location to another. hour 7.000 7.000 7.000 19,747.35 138,231.45 138,231.45 138,231.45 P&M-071

Hire and running charges of light crane for lowering


reinforcement cage, trime pipe, holding trime pipe
for concreting, removal of temporary casing etc hour 4.134 4.134 4.134 1,083.60 4,479.60 4,479.60 4,479.60 P&M-102

Hire and running charges of Bentonite pump


Rate included
hour 7.000 7.000 7.000 P&M-071
in piling rig

Transit truck agitator


For transportation (6 cum Capacity) tonne-km 73.53 x L1 73.53 x L1 73.53 x L1 13.41 29,582.96 29,582.96 29,582.96 P&M-128
For unloading hour 1.634 1.634 1.634 2,413.95 3,944.39 3,944.39 3,944.39 P&M-067
Front end loader for removing muck
(i) 3.1 Cum Capacity hour 0.875 4,279.80 3,745.50 P&M-011
(ii) 2.1 Cum Capacity hour 1.290 2,640.75 3,405.79 P&M-012
(iii) 1 Cum Capacity hour 2.723 1,112.00 3,027.66 P&M-013
Tipper
For Loading time
(i) 18 cum capacity hour 0.875 2,883.30 2,522.89 P&M-014
(ii) 14 cum capacity hour 1.290 2,556.75 3,298.21 P&M-015
(iii) 10 cum capacity hour 2.723 2,274.30 6,192.92 P&M-016
For disposal of muck from pile bore hole up to a
lead of 1 km
(i) 18 cum capacity t.km 47.048 6.18 290.69 P&M-116
(ii) 14 cum capacity t.km 47.048 7.01 329.94 P&M-119
(iii) 10 cum capacity t.km 47.048 8.66 407.63 P&M-122
c) Labour
Mate/Supervisor day 0.140 0.140 0.140 617.00 86.38 86.38 86.38 L-12
Mazdoor day 3.500 3.500 3.500 511.52 1,790.32 1,790.32 1,790.32 L-13
d) Overhead charges @ 20% on @ 20% on @ 20% on
38,202.21 38,297.18 38,816.03
(b+c) (b+c) (b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
22,921.32 22,978.31 23,289.62
(b+c+d) (b+c+d) (b+c+d)
Cost for 25 m = a+b+c+d+d+e 519,399.39 521,496.48 529,743.37
Rate per metre (a+b+c+d+e)/25 20,775.98 20,859.86 21,189.73
Say 20,776.00 20,860.00 21,190.00
12.26 1100 & Pile diameter-1500 mm
1700
Unit = meter
Taking output = 25 m
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
a) Materials
RCC Grade M35 (including additional concreteing
of 1m for pile head ) cum 45.946 9,089.00 417,601.31
Item No. -
Rate for concrete may be adopted same as for pile cum 45.946 9,139.00 419,898.60
12.11 F (iv)
vide item no. 12.11 F (iv) cum 45.946 9,303.00 427,433.71
Concrete
Bentonite to be cast with a tremie pipe 200mm dia. kg 2297.290 2297.290 2297.290 4.31 9,901.32 9,901.32 9,901.32 M-071
b) Machinery( for boring and construction )

Hire and running charges of hydraulic piling rig with


power unit and complete accessories including
shifting from one bore location to another. hour 8.000 8.000 8.000 19,747.35 157,978.80 157,978.80 157,978.80 P&M-071

Hire and running charges of light crane for lowering


reinforcement cage, trime pipe, holding trime pipe
for concreting, removal of temporary casing etc hour 5.053 5.053 5.053 1,083.60 5,475.43 5,475.43 5,475.43 P&M-102

Hire and running charges of Bentonite pump


Rate included
hour 8.000 8.000 8.000 P&M-071
in piling rig

Transit truck agitator


For transportation (6 cum Capacity) tonne-km 114.86 x L1 114.86 x L1 114.86 x L1 13.41 46,211.05 46,211.05 46,211.05 P&M-128
For unloading hour 2.553 2.553 2.553 2,413.95 6,162.81 6,162.81 6,162.81 P&M-067
Front end loader for removing muck
(i) 3.1 Cum Capacity hour 1.367 4,279.80 5,850.49 P&M-011
(ii) 2.1 Cum Capacity hour 2.015 2,640.75 5,321.11 P&M-012
(iii) 1 Cum Capacity hour 4.254 1,112.00 4,730.45 P&M-013
Tipper
For Loading time
(i) 18 cum capacity hour 1.367 2,883.30 3,941.47 P&M-014
(ii) 14 cum capacity hour 2.015 2,556.75 5,151.85 P&M-015
(iii) 10 cum capacity hour 4.254 2,274.30 9,674.87 P&M-016
For disposal of muck from pile bore hole up to a
lead of 1 km
(i) 18 cum capacity t.km 73.513 6.18 454.20 P&M-116
(ii) 14 cum capacity t.km 73.513 7.01 515.53 P&M-119
(iii) 10 cum capacity t.km 73.513 8.66 636.92 P&M-122
c) Labour
Mate/Supervisor day 0.140 0.140 0.140 617.00 86.38 86.38 86.38 L-12
Mazdoor day 3.500 3.500 3.500 511.52 1,790.32 1,790.32 1,790.32 L-13
d) Overhead charges @ 20% on @ 20% on @ 20% on
47,570.45 47,718.92 48,529.67
(b+c) (b+c) (b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
28,542.27 28,631.35 29,117.80
(b+c+d) (b+c+d) (b+c+d)
Cost for 25 m = a+b+c+d+d+e 731,566.31 734,843.48 747,729.53
Rate per metre (a+b+c+d+e)/25 29,262.65 29,393.74 29,909.18
Say 29,263.00 29,394.00 29,909.00
12.27 1100 & Driven cast-in-place vertical M35 grade R.C.C. Pile
1700 excluding Reinforcement complete as per Drawing
and & Technical Specification

Pile diameter - 750 mm


Unit = Running meter
Taking output = 40 metre
a) Materials
RCC Grade M35 cum 17.660 9,089.00 160,511.74
Item No. -
(Rate for concrete may be adopted same as for cum 17.660 9,139.00 161,394.74
12.11 F (iv)
pile vide item no. 12.11 F (iv)) cum 17.660 9,303.00 164,290.98
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.000 160.000 160.000 69.50 11,120.00 11,120.00 11,120.00 M-080
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m
Kg 70.000 70.000 70.000 62.55 4,378.50 4,378.50 4,378.50 M-123
iii) Steel helmet and cushion block on top of casing
head during driving Kg 50.000 50.000 50.000 135.00 6,750.00 6,750.00 6,750.00 M-174
c) Machinery
Hire and running charges of piling rig Including
double acting pile driving hammer complete with hour 6.000 6.000 6.000 19,747.35 118,484.10 118,484.10 118,484.10 P&M-071
power unit and accessories..
Hiring and running charges for light crane 5 tonnes
lifting capacity for lowering reinforcement and hour 0.500 0.500 0.500 1,128.75 564.38 564.38 564.38 P&M-103
handling steel casing.
d) Labour
Mate/Supervisor day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
e) Overhead charges @ 20% on @ 20% on @ 20% on
28,581.12 28,581.12 28,581.12
(b+c+d) (b+c+d) (b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
17,148.67 17,148.67 17,148.67
(b+c+d+e) (b+c+d+e) (b+c+d+e)
Cost for 40 m = a+b+c+d+e 349,147.10 350,030.10 352,926.34
Rate per metre (a+b+c+d+e)/40 8,728.68 8,750.75 8,823.16
Say 8,729.00 8,751.00 8,823.00
Note 1.The quantity of concrete required to be removed
above the designed top level of concrete, if any,
will be provided for in the rate analysis.

2.In case steel lining is included in the design for


driven cast-in-situ pile and is planned to be
retained, the same may be included in the rate
analysis. In case the temporary steel casing used
during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete
may be provided to cover its usage.
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
12.28 1100 & Driven cast-in-place vertical M35 grade R.C.C. Pile
1700 excluding Reinforcement complete as per Drawing
and & Technical Specification

Pile diameter - 1000 mm


Unit = Running meter
Taking output = 30 metre
a) Materials
RCC Grade M35 cum 23.550 9,089.00 214,045.95
Item No. -
(Rate for concrete may be adopted same as for cum 23.550 9,139.00 215,223.45
12.11 F (iv)
pile vide item no. 12.11 F (iv)) cum 23.550 9,303.00 219,085.65
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.000 160.000 160.000 69.50 11,120.00 11,120.00 11,120.00 M-080
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m
Kg 70.000 70.000 70.000 62.55 4,378.50 4,378.50 4,378.50 M-123
iii) Steel helmet and cushion block on top of casing
head during driving Kg 50.000 50.000 50.000 135.00 6,750.00 6,750.00 6,750.00 M-174
c) Machinery
Hire and running charges of piling rig Including
double acting pile driving hammer complete with hour 6.000 6.000 6.000 19,747.35 118,484.10 118,484.10 118,484.10 P&M-071
power unit and accessories.
Hiring and running charges for light crane 5 tonnes
lifting capacity for lowering reinforcement and hour 0.500 0.500 0.500 1,128.75 564.38 564.38 564.38 P&M-103
handling steel casing.
Hire and running charges for light crane for
lowering reinforcement cage. hour 0.500 0.500 0.500 1,128.75 564.38 564.38 564.38 P&M-103
d) Labour
Mate/Supervisor day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Mazdoor day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
e) Overhead charges @ 20% on @ 20% on @ 20% on
28,801.23 28,801.23 28,801.23
(b+c+d) (b+c+d) (b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
17,280.74 17,280.74 17,280.74
(b+c+d+e) (b+c+d+e) (b+c+d+e)
Cost for 30 m = a+b+c+d+e 404,134.07 405,311.57 409,173.77
Rate per metre (a+b+c+d+e)/30 13,471.14 13,510.39 13,639.13
Say 13,471.00 13,510.00 13,639.00
Note 1.The quantity of concrete required to be removed
above the designed top level of concrete, if any,
will be provided for in the rate analysis.

2.In case steel lining is included in the design for


driven cast-in-situ pile and is planned to be
retained, the same may be included in the rate
analysis. In case the temporary steel casing used
during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete
may be provided to cover its usage.

12.29 1100 & Driven cast-in-place vertical M35 grade R.C.C. Pile
1700 excluding Reinforcement complete as per Drawing
and & Technical Specification

Pile diameter - 1200 mm


Unit = Running meter
Taking output = 20 metre
a) Materials
RCC Grade M35 cum 22.610 9,089.00 205,502.29
Item No. -
(Rate for concrete may be adopted same as for cum 22.610 9,139.00 206,632.79
12.11 F (iv)
pile vide item no. 12.11 F (iv)) cum 22.610 9,303.00 210,340.83
b) Materials Pile shoes
i) C.I. shoes for the pile Kg 160.000 160.000 160.000 69.50 11,120.00 11,120.00 11,120.00 M-080
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m
Kg 70.000 70.000 70.000 62.55 4,378.50 4,378.50 4,378.50 M-123
iii) Steel helmet on top of casing head during
driving Kg 50.000 50.000 50.000 135.00 6,750.00 6,750.00 6,750.00 M-174
c) Machinery
Hire and running charges of piling rig Including
double acting pile driving hammer complete with hour 6.000 6.000 6.000 19,747.35 118,484.10 118,484.10 118,484.10 P&M-071
power unit and accessories.
Hiring and running charges for light crane 5 tonnes
lifting capacity for lowering reinforcement and hour 0.500 0.500 0.500 1,083.60 541.80 541.80 541.80 P&M-102
handling steel casing.
d) Labour
Mate/Supervisor day 0.180 0.180 0.180 617.00 111.06 111.06 111.06 L-12
Mazdoor day 4.500 4.500 4.500 511.52 2,301.84 2,301.84 2,301.84 L-13
e) Overhead charges @ 20% on @ 20% on @ 20% on
28,737.46 28,737.46 28,737.46
(b+c+d) (b+c+d) (b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
17,242.48 17,242.48 17,242.48
(b+c+d+e) (b+c+d+e) (b+c+d+e)
Cost for 20 m = a+b+c+d+e 395,169.53 396,300.03 400,008.07
Rate per metre (a+b+c+d+e)/20 19,758.48 19,815.00 20,000.40
Say 19,758.00 19,815.00 20,000.00
Note 1.The quantity of concrete required to be removed
above the designed top level of concrete, if any,
will be provided for in the rate analysis.
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
2.In case steel lining is included in the design for
driven cast-in-situ pile and is planned to be
retained, the same may be included in the rate
analysis. In case the temporary steel casing used
during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete
may be provided to cover its usage.

12.30 1100 & Driven precast vertical M35 grade R.C.C. Piles
1700 excluding Reinforcement complete as per Drawing
and & Technical Specification
Pile Diameter = 500 mm
Unit = Running Meter
Taking output = 60 m
a) Materials
RCC Grade M35 cum 11.780 9,089.00 107,068.42
Item No. -
(Rate for concrete may be adopted same as for cum 11.780 9,139.00 107,657.42
12.11 F (iv)
pile vide item no. 12.11 F (iv)) cum 11.780 9,303.00 109,589.34
b ) Material Pile shoes
a) C.I Shoes Kg 240.000 240.000 240.000 69.50 16,680.00 16,680.00 16,680.00 M-080
b) M.S. shoes Kg 105.000 105.000 105.000 50.00 5,250.00 5,250.00 5,250.00 M-124
c) Steel helmet and cushion block on top of pile
head during driving. Kg 30.000 30.000 30.000 135.00 4,050.00 4,050.00 4,050.00 M-174
c) Machinery
Crane20 t capacity hour 6.000 6.000 6.000 1,584.45 9,506.70 9,506.70 9,506.70 P&M-106
Vibrating Pile driving hammer complete with power
unit and accessories. hour 6.000 6.000 6.000 18,571.35 111,428.10 111,428.10 111,428.10 P&M-115
d) Labour
Mate/Supervisor day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Add 1 per cent of (a+b+c) for carriage of piles
from casting yard to work site and stacking, and
other imponderables during installation. 2,555.92 2,561.81 2,581.13

e) Overhead charges @ 20% on @ 20% on @ 20% on


30,215.86 30,217.04 30,220.91
(b+c+d) (b+c+d) (b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
18,129.52 18,130.22 18,132.54
(b+c+d+e) (b+c+d+e) (b+c+d+e)
Cost for 60 m = a+b+c+d+e+f 306,493.12 307,089.89 309,047.32
Rate per metre (a+b+c+d+e+f)/60 5,108.22 5,118.16 5,150.79
Say 5,108.00 5,118.00 5,151.00
Note The quantity of concrete required to be removed
above the designed top level of concrete, if any,
will be provided for in the rate analysis.

12.31 1100 & Driven precast vertical M35 grade R.C.C. Piles
1700 excluding Reinforcement complete as per Drawing
and & Technical Specification
Pile Diameter = 750 mm
Unit = Running Meter
Taking output = 50 m
a) Materials
RCC Grade M35 cum 22.080 9,089.00 200,685.12
Item No. -
(Rate for concrete may be adopted same as for cum 22.080 9,139.00 201,789.12
12.11 F (iv)
pile vide item no. 12.11 F (iv)) cum 22.080 9,303.00 205,410.24
b ) Material Pile shoes
a) C.I. shoes Kg 160.000 160.000 160.000 69.50 11,120.00 11,120.00 11,120.00 M-080
b) M.S. shoes Kg 70.000 70.000 70.000 50.00 3,500.00 3,500.00 3,500.00 M-124
c) Steel helmet and cushion block on top of pile
head during driving. Kg 40.000 40.000 40.000 135.00 5,400.00 5,400.00 5,400.00 M-174
c) Machinery
Crane 35 T capacity hour 6.000 6.000 6.000 2,394.00 14,364.00 14,364.00 14,364.00 P&M-107
Vibrating Pile driving hammer complete with power
unit and accessories. hour 6.000 6.000 6.000 18,571.35 111,428.10 111,428.10 111,428.10 P&M-115
d) Labour
Mate/Supervisor day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Mazdoor day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
Add 1 per cent of (a+b+c) for carriage of piles
from casting yard to work site and stacking, and
other imponderables during installation. 3,486.42 3,497.46 3,533.67

e) Overhead charges @ 20% on @ 20% on @ 20% on


30,288.66 30,290.87 30,298.11
(b+c+d) (b+c+d) (b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
18,173.20 18,174.52 18,178.87
(b+c+d+e) (b+c+d+e) (b+c+d+e)
Cost for 50 m = a+b+c+d+e+f 400,590.30 401,708.88 405,377.79
Rate per metre (a+b+c+d+e+f)/50 8,011.81 8,034.18 8,107.56
Say 8,012.00 8,034.00 8,108.00
Note The quantity of concrete required to be removed
above the designed top level of concrete, if any,
will be provided for in the rate analysis.

12.32 1100 & Driven precast vertical M35 grade R.C.C. Piles
1700 excluding Reinforcement complete as per Drawing
and & Technical Specification
Pile Diameter = 1000 mm
Unit = Running Meter
Taking output = 40 m
a) Materials
RCC Grade M35 cum 31.400 9,089.00 285,394.60
Item No. -
(Rate for concrete may be adopted same as for cum 31.400 9,139.00 286,964.60
12.11 F (iv)
pile vide item no. 12.11 F (iv))
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H RCC Grade M35 Description Unit For Large For Medium For Small Large Medium Small
(Rs.) InputNo.
Item ref.-
Specification (Rate for concrete may be adopted same as for Project Project Project Project Project Project
12.11 F (iv)
pile vide item no. 12.11 F (iv)) cum 31.400 9,303.00 292,114.20
b ) Material Pile shoes
a) C.I. shoes for the pile Kg 160.000 160.000 160.000 69.50 11,120.00 11,120.00 11,120.00 M-080
b) M.S. shoes @ 35 Kg per pile of 15 m Kg 70.000 70.000 70.000 50.00 3,500.00 3,500.00 3,500.00 M-124
c) Steel helmet and cushion block on top of pile
head during driving. Kg 50.000 50.000 50.000 135.00 6,750.00 6,750.00 6,750.00 M-174
c) Machinery
Crane 50 t capacity. hour 6.000 6.000 6.000 6,580.35 39,482.10 39,482.10 39,482.10 P&M-100
Vibrating Pile driving hammer complete with power
unit and accessories. hour 6.000 6.000 6.000 18,571.35 111,428.10 111,428.10 111,428.10 P&M-115
d) Labour
Mate/Supervisor day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 5.000 5.000 5.000 511.52 2,557.60 2,557.60 2,557.60 L-13
Add 1 per cent of (a+b+c) for carriage of piles
from casting yard to work site and stacking, and
other imponderables during installation. 4,603.56 4,619.26 4,670.75

e) Overhead charges @ 20% on @ 20% on @ 20% on


35,912.95 35,916.09 35,926.39
(b+c+d) (b+c+d) (b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
21,547.77 21,549.65 21,555.83
(b+c+d+e) (b+c+d+e) (b+c+d+e)
Cost for 40 m = a+b+c+d+e+f 522,420.08 524,010.80 529,228.38
Rate per metre (a+b+c+d+e+f)/40 13,060.50 13,100.27 13,230.71
Say 13,061.00 13,100.00 13,231.00
Note The quantity of concrete required to be removed
above the designed top level of concrete, if any,
will be provided for in the rate analysis.

12.33 1100&1 Driven precast vertical M35 grade R.C.C. Piles


700 excluding Reinforcement complete as per Drawing
and & Technical Specification
Size of pile - 300 mm x 300 mm
Unit = Running Meter
Taking output = 60 m
a) Materials
RCC Grade M35 cum 5.400 9,089.00 49,080.60
Item No. -
(Rate for concrete may be adopted same as for cum 5.400 9,139.00 49,350.60
12.11 F (iv)
pile vide item no. 12.11 F (iv)) cum 5.400 9,303.00 50,236.20
b ) Material Pile shoes
a) C I shoes kg 240.000 240.000 240.000 69.50 16,680.00 16,680.00 16,680.00 M-080
b) M. S shoes kg 105.000 105.000 105.000 50.00 5,250.00 5,250.00 5,250.00 M-124
c) Steel helmet and cushion block on top of pile
head during driving. Kg 30.000 30.000 30.000 135.00 4,050.00 4,050.00 4,050.00 M-174
c) Machinery
Crane 10 tonne capacity hour 6.000 6.000 6.000 1,240.05 7,440.30 7,440.30 7,440.30 P&M-104
Vibrating Pile driving hammer complete with power
hour 6.000 6.000 6.000 18,571.35 111,428.10 111,428.10 111,428.10 P&M-115
unit and accessories.
d ) Labour
Mate/Supervisor day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Add 1 per cent of (a+b+c) for carriage of piles
from casting yard to work site and stacking, and
other imponderables during installation. 1,955.38 1,958.08 1,966.93

e) Overhead charges @ 20% on @ 20% on @ 20% on


29,682.48 29,683.02 29,684.79
(b+c+d) (b+c+d) (b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
17,809.49 17,809.81 17,810.87
(b+c+d+e) (b+c+d+e) (b+c+d+e)
Cost for 60 m = a+b+c+d+e+f 244,984.94 245,258.50 246,155.79
Rate per metre (a+b+c+d+e+f)/60 4,083.08 4,087.64 4,102.60
Say 4,083.00 4,088.00 4,103.00
Note The quantity of concrete required to be removed
above the designed top level of concrete, if any,
will be provided for in the rate analysis.

12.34 1100 Driven precast vertical M35 grade R.C.C. Piles


&1700 excluding Reinforcement complete as per Drawing
and & Technical Specification
Size of pile - 500 mm x 500 mm
Unit = Running Meter
Taking output = 50 m
a) Materials
RCC Grade M35 cum 12.500 9,089.00 113,612.50
Item No. -
(Rate for concrete may be adopted same as for cum 12.500 9,139.00 114,237.50
12.11 F (iv)
pile vide item no. 12.11 F (iv)) cum 12.500 9,303.00 116,287.50
b ) Material Pile shoes
a) C I shoes kg 160.000 160.000 160.000 69.50 11,120.00 11,120.00 11,120.00 M-080
b) M. S shoes kg 70.000 70.000 70.000 50.00 3,500.00 3,500.00 3,500.00 M-124
c) Steel helmet and cushion block on top of pile
Kg 30.000 30.000 30.000 135.00 4,050.00 4,050.00 4,050.00 M-174
head during driving.
c) Machinery
Crane 20 tonne capacity hour 6.000 6.000 6.000 1,584.45 9,506.70 9,506.70 9,506.70 P&M-106
Vibrating Pile driving hammer complete with power
unit and accessories. hour 6.000 6.000 6.000 18,571.35 111,428.10 111,428.10 111,428.10 P&M-115
d ) Labour
Mate/Supervisor day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Mazdoor day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
Add 1 per cent of (a+b+c) for carriage of piles
from casting yard to work site and stacking, and
other imponderables during installation. 2,553.62 2,559.87 2,580.37
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
e) Overhead charges @ 20% on @ 20% on @ 20% on
28,860.64 28,861.89 28,865.99
(b+c+d) (b+c+d) (b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
17,316.39 17,317.14 17,319.60
(b+c+d+e) (b+c+d+e) (b+c+d+e)
Cost for 50 m = a+b+c+d+e+f 304,092.75 304,726.00 306,803.06
Rate per metre (a+b+c+d+e+f)/50 6,081.86 6,094.52 6,136.06
Say 6,082.00 6,095.00 6,136.00
Note The quantity of concrete required to be removed
above the designed top level of concrete, if any,
will be provided for in the rate analysis.

12.35 1100 Driven precast vertical M35 grade R.C.C. Piles


&1700 excluding Reinforcement complete as per Drawing
and & Technical Specification
Size of pile - 750 mm x 750 mm
Unit = Running Meter
Taking output = 40 m
a) Materials
RCC Grade M35 cum 22.500 9,089.00 204,502.50
Item No. -
(Rate for concrete may be adopted same as for cum 22.500 9,139.00 205,627.50
12.11 F (iv)
pile vide item no. 12.11 F (iv)) cum 22.500 9,303.00 209,317.50
b ) Material
Pile shoes
a) C I shoes kg 160.000 160.000 160.000 69.50 11,120.00 11,120.00 11,120.00 M-080
b) M. S shoes kg 70.000 70.000 70.000 50.00 3,500.00 3,500.00 3,500.00 M-124
c) Steel helmet and cushion block on top of pile
head during driving. Kg 30.000 30.000 30.000 135.00 4,050.00 4,050.00 4,050.00 M-174
c) Machinery
Crane 20 tonne capacity hour 6.000 6.000 6.000 1,584.45 9,506.70 9,506.70 9,506.70 P&M-106
Vibrating Pile driving hammer complete with power
unit and accessories. hour 6.000 6.000 6.000 18,571.35 111,428.10 111,428.10 111,428.10 P&M-115
d ) Labour
Mate/Supervisor day 0.180 0.180 0.180 617.00 111.06 111.06 111.06 L-12
Mazdoor day 4.500 4.500 4.500 511.52 2,301.84 2,301.84 2,301.84 L-13
Add 1 per cent of (a+b+c) for carriage of piles
from casting yard to work site and stacking, and
other imponderables during installation. 3,465.20 3,476.45 3,513.35

e) Overhead charges @ 20% on @ 20% on @ 20% on


29,096.58 29,098.83 29,106.21
(b+c+d) (b+c+d) (b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
17,457.95 17,459.30 17,463.73
(b+c+d+e) (b+c+d+e) (b+c+d+e)
Cost for 40 m = a+b+c+d+e+f 396,539.93 397,679.78 401,418.49
Rate per metre (a+b+c+d+e+f)/40 9,913.50 9,941.99 10,035.46
Say 9,913.00 9,942.00 10,035.00
Note The quantity of concrete required to be removed
above the designed top level of concrete, if any,
will be provided for in the rate analysis.

12.36 1100, Driven Vertical Steel Piles complete as per


1900 Drawing and & Technical Specification
Section of the pile - H Section steel column 400 x
250 mm (ISHB Series)
Unit = Running Meter
Taking output = 70 m
a) Materials
Structural steel including 5 per cent wastage @
tonnes 6.040 6.040 6.040 63,806.54 385,391.53 385,391.53 385,391.53 M-181
82.20 kg/m
b) Machinery
Crane 10 T capacity hour 6.000 6.000 6.000 1,240.05 7,440.30 7,440.30 7,440.30 P&M-104
Vibrating Pile driving hammer complete with power
unit and other accessories. hour 6.000 6.000 6.000 19,747.35 118,484.10 118,484.10 118,484.10 P&M-071
c) Labour
Mate/Supervisor day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Add 0.5 per cent of (a+b+c) for providing steel
helmet on top of pile head during driving, stacking
of piles at site, providing anti-corrosion treatment 2,564.62 2,564.62 2,564.62
and other imponderables during installation.

d) Overhead charges @ 20% on @ 20% on @ 20% on


103,097.83 103,097.83 103,097.83
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
61,858.70 61,858.70 61,858.70
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 70 m = a+b+c+d+e 680,445.68 680,445.68 680,445.68
Rate per metre (a+b+c+d+e)/70 9,720.65 9,720.65 9,720.65
Say 9,721.00 9,721.00 9,721.00
12.37 1100 Driven Vertical Steel Piles complete as per
&1900 Drawing and & Technical Specification
Section of the pile - H Section steel column 450 x
250 mm (ISHB Series)
Unit = Running Meter
Taking output = 60 m
a) Materials
Structural steel including 5 per cent wastage
@92.50 kg/m tonnes 5.830 5.830 5.830 63,806.54 371,992.15 371,992.15 371,992.15 M-181
b) Machinery
Crane 10 T capacity hour 6.000 6.000 6.000 1,240.05 7,440.30 7,440.30 7,440.30 P&M-104
Vibrating Pile driving hammer complete with power
unit and accessories. hour 6.000 6.000 6.000 18,571.35 111,428.10 111,428.10 111,428.10 P&M-115
c) Labour
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Mate/Supervisor day 0.140 0.140 0.140 617.00 86.38 86.38 86.38 L-12
Mazdoor day 3.500 3.500 3.500 511.52 1,790.32 1,790.32 1,790.32 L-13
Add 0.5 per cent of (a+b+c) for providing steel
helmet and cushion block on top of pile head
during driving, stacking of piles at site, providing 2,463.69 2,463.69 2,463.69
anti-corrosive treatment and other imponderables
during installation.

d) Overhead charges @ 20% on @ 20% on @ 20% on


99,040.19 99,040.19 99,040.19
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
59,424.11 59,424.11 59,424.11
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 60 m = a+b+c+d+e 653,665.24 653,665.24 653,665.24
Rate per metre (a+b+c+d+e)/60 10,894.42 10,894.42 10,894.42
Say 10,894.00 10,894.00 10,894.00
12.38 1100 Pile Load Test on single Vertical Pile in accordance
with IS:2911(Part-IV)
Unit = 1 MT
Taking output = 1 MT
a) Initial and routine load test tonne 1.000 1.000 1.000 300.00 300.00 300.00 300.00 300.00
b) Lateral load test tonne 1.000 1.000 1.000 500.00 500.00 500.00 500.00 500.00
say 500.00 500.00 500.00
Note Although, this item is incidental to work and is not
required to be included in BOQ of contract, the
same is required to be added in the estimate to
assess cost of work.
12.39 Dismantling of Reinforced Concrete Pile head
complete as per Drawing and Technical
Specification
Unit = cum
Taking output = 1.25 cum
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor with Pneumatic breaker day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
Blacksmith day 0.250 0.250 0.250 679.00 169.75 169.75 169.75 L-01
Mazdoor for loading and unloading day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
b) Machinery
Air Compressor 250 cfm hour 0.625 0.625 0.625 614.25 383.91 383.91 383.91 P&M-029
Pneumatic breaker hour 1.250 1.250 1.250 206.00 257.50 257.50 257.50 P&M-010
Tipper
For transportation to dumping yard considering
lead @ 1 km
(i) 18 cum capacity t.km 1.875 6.18 11.58 P&M-116
(ii) 14 cum capacity t.km 1.875 7.01 13.15 P&M-119
(iii) 10 cum capacity t.km 1.875 8.66 16.25 P&M-122
Loading & unloading time
(i) 18 cum capacity hour 0.208 2,883.30 599.73 P&M-014
(ii) 14 cum capacity hour 0.250 2,556.75 639.19 P&M-015
(iii) 10 cum capacity hour 0.292 2,274.30 664.10 P&M-016
d) Overhead charges @ 20% on @ 20% on @ 20% on
366.16 374.36 379.96
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
219.69 224.62 227.98
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 1.25 cum = a+b+c+d 2,416.64 2,470.79 2,507.76
Rate per cum = (a+b+c+d)/ 1.25 1,933.31 1,976.63 2,006.21
Say 1,933.00 1,977.00 2,006.00
12.40 1100, Cement Concrete for Reinforced Concrete in Pile
1500 Cap complete as per Drawing and Technical
&1700 Specification
A RCC Grade M20
Case I RCC Grade M20 using batching plant & Concrete
pump
Unit = cum
Taking output = 60 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 60.000 60.000 60.000 4,533.00 271,980.00 271,980.00 271,980.00 of Concrete -
20.05

b) Labour
For pouring and placing
Mate day 0.146 0.146 0.146 617.00 90.08 90.08 90.08 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 2.650 2.650 2.650 511.52 1,355.53 1,355.53 1,355.53 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 150 x L1 150 x L1 150 x L1 13.41 60,348.75 60,348.75 60,348.75 P&M-128
For unloading hour 1.300 1.300 1.300 2,413.95 3,138.14 3,138.14 3,138.14 P&M-067
Hydraulic Boom placer pump hour 1.300 1.300 1.300 4,401.60 5,722.08 5,722.08 5,722.08 P&M-069
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 13,734.90 13,734.90 13,734.90

e) Overhead charges @ 20% on @ 20% on @ 20% on


71,421.50 71,421.50 71,421.50
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
42,852.90 42,852.90 42,852.90
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 60 cum = a+b+c+d+e+f 471,381.87 471,381.87 471,381.87
Rate per cum = (a+b+c+d+e+f)/60 7,856.36 7,856.36 7,856.36
Say 7,856.00 7,856.00 7,856.00
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Case II RCC Grade M20 using batching plant & manual
placing
Unit = cum
Taking output = 60 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 60.000 60.000 60.000 4,533.00 271,980.00 271,980.00 271,980.00 of Concrete -
20.05

b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 150 x L1 150 x L1 150 x L1 13.41 60,348.75 60,348.75 60,348.75 P&M-128
For unloading hour 3.333 3.333 3.333 2,413.95 8,046.50 8,046.50 8,046.50 P&M-067
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 13,817.10 13,817.10 13,817.10

e) Overhead charges @ 20% on @ 20% on @ 20% on


71,848.93 71,848.93 71,848.93
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
43,109.36 43,109.36 43,109.36
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 60 cum = a+b+c+d+e+f 474,202.91 474,202.91 474,202.91
Rate per cum = (a+b+c+d+e+f)/60 7,903.38 7,903.38 7,903.38
Say 7,903.00 7,903.00 7,903.00
Note The value of a, b and c may be taken as applicable
i.e. either using concrete mixer or batching plant.

12.40 B RCC Grade M25


Case I RCC Grade M25 using batching plant & Concrete
pump
Unit = cum
Taking output = 60 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 60.000 60.000 60.000 4,945.00 296,700.00 296,700.00 296,700.00 of Concrete -
20.07

b) Labour
For pouring and placing
Mate day 0.146 0.146 0.146 617.00 90.08 90.08 90.08 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 2.650 2.650 2.650 511.52 1,355.53 1,355.53 1,355.53 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 150 x L1 150 x L1 150 x L1 13.41 60,348.75 60,348.75 60,348.75 P&M-128
For unloading hour 1.300 1.300 1.300 2,413.95 3,138.14 3,138.14 3,138.14 P&M-067
Hydraulic Boom placer pump hour 1.300 1.300 1.300 4,401.60 5,722.08 5,722.08 5,722.08 P&M-069
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 14,723.70 14,723.70 14,723.70

e) Overhead charges @ 20% on @ 20% on @ 20% on


76,563.26 76,563.26 76,563.26
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
45,937.95 45,937.95 45,937.95
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 60 cum = a+b+c+d+e+f 505,317.49 505,317.49 505,317.49
Rate per cum = (a+b+c+d+e+f)/60 8,421.96 8,421.96 8,421.96
Say 8,422.00 8,422.00 8,422.00
Case II RCC Grade M25 using batching plant & manual
placing
Unit = cum
Taking output = 60 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 60.000 60.000 60.000 4,945.00 296,700.00 296,700.00 296,700.00 of Concrete -
20.07

b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 150 x L1 150 x L1 150 x L1 13.41 60,348.75 60,348.75 60,348.75 P&M-128
For unloading hour 3.333 3.333 3.333 2,413.95 8,046.50 8,046.50 8,046.50 P&M-067
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 14,805.90 14,805.90 14,805.90

e) Overhead charges @ 20% on @ 20% on @ 20% on


76,990.69 76,990.69 76,990.69
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
46,194.41 46,194.41 46,194.41
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 60 cum = a+b+c+d+e+f 508,138.53 508,138.53 508,138.53
Rate per cum = (a+b+c+d+e+f)/60 8,468.98 8,468.98 8,468.98
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Say 8,469.00 8,469.00 8,469.00
Note The value of a, b and c may be taken as applicable
i.e. either using concrete mixer or batching plant.

12.40 C RCC Grade M30


Case I RCC Grade M30 using batching plant & Concrete
pump
Unit = cum
Taking output = 60 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 60.000 60.000 60.000 5,032.00 301,920.00 301,920.00 301,920.00 of Concrete -
20.09

b) Labour
For pouring and placing
Mate day 0.146 0.146 0.146 617.00 90.08 90.08 90.08 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 2.650 2.650 2.650 511.52 1,355.53 1,355.53 1,355.53 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 150 x L1 150 x L1 150 x L1 13.41 60,348.75 60,348.75 60,348.75 P&M-128
For unloading hour 1.300 1.300 1.300 2,413.95 3,138.14 3,138.14 3,138.14 P&M-067
Hydraulic Boom placer pump hour 1.300 1.300 1.300 4,401.60 5,722.08 5,722.08 5,722.08 P&M-069
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 14,932.50 14,932.50 14,932.50

e) Overhead charges @ 20% on @ 20% on @ 20% on


77,649.02 77,649.02 77,649.02
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
46,589.41 46,589.41 46,589.41
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 60 cum = a+b+c+d+e+f 512,483.50 512,483.50 512,483.50
Rate per cum = (a+b+c+d+e+f)/60 8,541.39 8,541.39 8,541.39
Say 8,541.00 8,541.00 8,541.00
Case II RCC Grade M30 using batching plant & manual
placing
Unit = cum
Taking output = 60 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 60.000 60.000 60.000 5,032.00 301,920.00 301,920.00 301,920.00 of Concrete -
20.09

b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 150 x L1 150 x L1 150 x L1 13.41 60,348.75 60,348.75 60,348.75 P&M-128
For unloading hour 3.333 3.333 3.333 2,413.95 8,046.50 8,046.50 8,046.50 P&M-067
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 15,014.70 15,014.70 15,014.70

e) Overhead charges @ 20% on @ 20% on @ 20% on


78,076.45 78,076.45 78,076.45
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
46,845.87 46,845.87 46,845.87
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 60 cum = a+b+c+d+e+f 515,304.55 515,304.55 515,304.55
Rate per cum = (a+b+c+d+e+f)/60 8,588.41 8,588.41 8,588.41
Say 8,588.00 8,588.00 8,588.00
Note The value of a, b and c may be taken as applicable
i.e. either using concrete mixer or batching plant.

12.40 D RCC Grade M35


Case I RCC Grade M35 using batching plant & Concrete
pump
Unit = cum
Taking output = 60 cum
a) Material

Sub-Analysis
Per Cum Basic Cost (Rate as in sub-analysis) cum 60.000 60.000 60.000 5,186.00 311,160.00 311,160.00 311,160.00 of Concrete -
20.11

b) Labour
For pouring and placing
Mate day 0.146 0.146 0.146 617.00 90.08 90.08 90.08 L-12
Mason day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-10
Mazdoor day 2.650 2.650 2.650 511.52 1,355.53 1,355.53 1,355.53 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 150 x L1 150 x L1 150 x L1 13.41 60,348.75 60,348.75 60,348.75 P&M-128
For unloading hour 1.300 1.300 1.300 2,413.95 3,138.14 3,138.14 3,138.14 P&M-067
Hydraulic Boom placer pump hour 1.300 1.300 1.300 4,401.60 5,722.08 5,722.08 5,722.08 P&M-069
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 15,299.74 15,299.74 15,299.74
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
e) Overhead charges @ 20% on @ 20% on @ 20% on
79,558.66 79,558.66 79,558.66
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
47,735.20 47,735.20 47,735.20
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 60 cum = a+b+c+d+e+f 525,087.18 525,087.18 525,087.18
Rate per cum = (a+b+c+d+e+f)/60 8,751.45 8,751.45 8,751.45
Say 8,751.00 8,751.00 8,751.00
Case II RCC Grade M35 using batching plant & manual
placing
Unit = cum
Taking output = 60 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 60.000 60.000 60.000 5,186.00 311,160.00 311,160.00 311,160.00 of Concrete -
20.11

b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 150 x L1 150 x L1 150 x L1 13.41 60,348.75 60,348.75 60,348.75 P&M-128
For unloading hour 3.333 3.333 3.333 2,413.95 8,046.50 8,046.50 8,046.50 P&M-067
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 15,381.94 15,381.94 15,381.94

e) Overhead charges @ 20% on @ 20% on @ 20% on


79,986.09 79,986.09 79,986.09
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
47,991.66 47,991.66 47,991.66
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 60 cum = a+b+c+d+e+f 527,908.22 527,908.22 527,908.22
Rate per cum = (a+b+c+d+e+f)/60 8,798.47 8,798.47 8,798.47
Say 8,798.00 8,798.00 8,798.00
Note The value of a, b and c may be taken as applicable
i.e. either using concrete mixer or batching plant.

12.40 E RCC Grade M40


Case I RCC Grade M40 using batching plant & Concrete
pump
Unit = cum
Taking output = 60 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 60.000 60.000 60.000 5,519.00 331,140.00 331,140.00 331,140.00 of Concrete -
20.12

b) Labour
For pouring and placing
Mate day 0.146 0.146 0.146 617.00 90.08 90.08 90.08 L-12
Mason day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-10
Mazdoor day 2.650 2.650 2.650 511.52 1,355.53 1,355.53 1,355.53 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 150 x L1 150 x L1 150 x L1 13.41 60,348.75 60,348.75 60,348.75 P&M-128
For unloading hour 1.300 1.300 1.300 2,413.95 3,138.14 3,138.14 3,138.14 P&M-067
Hydraulic Boom placer pump hour 1.300 1.300 1.300 4,401.60 5,722.08 5,722.08 5,722.08 P&M-069
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 16,098.94 16,098.94 16,098.94

e) Overhead charges @ 20% on @ 20% on @ 20% on


83,714.50 83,714.50 83,714.50
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
50,228.70 50,228.70 50,228.70
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 60 cum = a+b+c+d+e+f 552,515.72 552,515.72 552,515.72
Rate per cum = (a+b+c+d+e+f)/60 9,208.60 9,208.60 9,208.60
Say 9,209.00 9,209.00 9,209.00
Case II RCC Grade M40 using batching plant & manual
placing
Unit = cum
Taking output = 60 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 60.000 60.000 60.000 5,519.00 331,140.00 331,140.00 331,140.00 of Concrete -
20.12

b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 150 x L1 150 x L1 150 x L1 13.41 60,348.75 60,348.75 60,348.75 P&M-128
For unloading hour 3.333 3.333 3.333 2,413.95 8,045.70 8,045.70 8,045.70 P&M-067
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 16,181.11 16,181.11 16,181.11

e) Overhead charges @ 20% on @ 20% on @ 20% on


84,141.77 84,141.77 84,141.77
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
50,485.06 50,485.06 50,485.06
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 60 cum = a+b+c+d+e+f 555,335.66 555,335.66 555,335.66
Rate per cum = (a+b+c+d+e+f)/60 9,255.59 9,255.59 9,255.59
Say 9,256.00 9,256.00 9,256.00
Note The value of a, b and c may be taken as applicable
i.e. either using concrete mixer or batching plant.

12.40 F RCC Grade M45


Case I RCC Grade M45 using batching plant & Concrete
pump
Unit = cum
Taking output = 60 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 60.000 60.000 60.000 5,663.00 339,780.00 339,780.00 339,780.00 of Concrete -
20.13

b) Labour
For pouring and placing
Mate day 0.146 0.146 0.146 617.00 90.08 90.08 90.08 L-12
Mason day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-10
Mazdoor day 2.650 2.650 2.650 511.52 1,355.53 1,355.53 1,355.53 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 150 x L1 150 x L1 150 x L1 13.41 60,348.75 60,348.75 60,348.75 P&M-128
For unloading hour 1.300 1.300 1.300 2,413.95 3,138.14 3,138.14 3,138.14 P&M-067
Hydraulic Boom placer pump hour 1.300 1.300 1.300 4,401.60 5,722.08 5,722.08 5,722.08 P&M-069
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 16,444.54 16,444.54 16,444.54

e) Overhead charges @ 20% on @ 20% on @ 20% on


85,511.62 85,511.62 85,511.62
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
51,306.97 51,306.97 51,306.97
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 60 cum = a+b+c+d+e+f 564,376.72 564,376.72 564,376.72
Rate per cum = (a+b+c+d+e+f)/60 9,406.28 9,406.28 9,406.28
Say 9,406.00 9,406.00 9,406.00
Case II RCC Grade M45 using batching plant & manual
placing
Unit = cum
Taking output = 60 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 60.000 60.000 60.000 5,663.00 339,780.00 339,780.00 339,780.00 of Concrete -
20.13

b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 150 x L1 150 x L1 150 x L1 13.41 60,348.75 60,348.75 60,348.75 P&M-128
For unloading hour 3.333 3.333 3.333 2,413.95 8,046.50 8,046.50 8,046.50 P&M-067
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 16,526.74 16,526.74 16,526.74

e) Overhead charges @ 20% on @ 20% on @ 20% on


85,939.05 85,939.05 85,939.05
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
51,563.43 51,563.43 51,563.43
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 60 cum = a+b+c+d+e+f 567,197.76 567,197.76 567,197.76
Rate per cum = (a+b+c+d+e+f)/60 9,453.30 9,453.30 9,453.30
Say 9,453.00 9,453.00 9,453.00
Note The value of a, b and c may be taken as applicable
i.e. either using concrete mixer or batching plant.

12.41 1100&1 Levelling Course for Pile cap


700
Providing and laying of PCC M15 levelling course
100mm thick below the pile cap.
Case I PCC Grade M15 using batching plant & Concrete
pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,176.00 125,280.00 125,280.00 125,280.00 of Concrete -
20.03
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity hour 3.926 1,501.00 5,892.93 P&M-023


(ii) 12 KL capacity hour 5.255 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity hour 10.510 1,005.00 10,562.55 P&M-025

e) Overhead charges @ 20% on @ 20% on @ 20% on


33,559.08 33,775.17 34,493.00
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
20,135.45 20,265.10 20,695.80
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 221,489.92 222,916.13 227,653.82
Rate per cum = (a+b+c+d+e+f)/30 7,383.00 7,430.54 7,588.46
Say 7,383.00 7,431.00 7,588.00
Case II PCC Grade M15 using batching plant & manual
placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 4,176.00 62,640.00 62,640.00 62,640.00 of Concrete -
20.03

Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )

(i) 16 KL capacity hour 1.978 1,501.00 2,968.98 P&M-023


(ii) 12 KL capacity hour 2.628 1,327.00 3,487.36 P&M-024
(iii) 6 KL capacity hour 5.255 1,005.00 5,281.28 P&M-025

e) Overhead charges @ 20% on @ 20% on @ 20% on


17,635.78 17,739.46 18,098.24
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
10,581.47 10,643.67 10,858.94
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 116,396.16 117,080.42 119,448.39
Rate per cum = (a+b+c+d+e+f)/15 7,759.74 7,805.36 7,963.23
Say 7,760.00 7,805.00 7,963.00
12.42 1600 Supplying, Fitting and Placing un-coated HYSD bar
Reinforcement in Foundation complete as per
Drawing and Technical Specifications.

Unit = MT
Taking output = 8 MT
a) Material
MS bars including 5 per cent overlaps and
wastage tonne 8.400 8.400 8.400 46,496.54 390,570.97 390,570.97 390,570.97 M-083
Binding wire Kg 48.000 48.000 48.000 66.72 3,202.56 3,202.56 3,202.56 M-072
b) Labour for straightening, cutting, bending,
shifting to site, tying and placing in position

Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Blacksmith day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-01
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
c) Machinery
Cutting Machine hour 5.333 5.333 5.333 528.15 2,816.80 2,816.80 2,816.80 P&M-076
Bending Machine hour 5.333 5.333 5.333 528.15 2,816.80 2,816.80 2,816.80 P&M-076
Electric generator 15 KVA hour 5.333 5.333 5.333 425.25 2,268.00 2,268.00 2,268.00 P&M-051
Tipper
Tipper for Transportation
(i) 18 cum capacity t.km 8 x L1 6.18 1,482.84 P&M-116
(ii) 14 cum capacity t.km 8 x L1 7.01 1,683.07 P&M-119
(iii) 10 cum capacity t.km 8 x L1 8.66 2,079.36 P&M-122
Loading & Unloading Time hour
(i) 18 cum capacity hour 1.000 2,883.30 2,883.30 P&M-014
(ii) 14 cum capacity hour 1.280 2,556.75 3,272.64 P&M-015
(iii) 10 cum capacity hour 1.778 2,274.30 4,043.20 P&M-016
Light weight Crane
At cutting bending yard hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102
At site hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Per MT Basic Cost of Labour, Material &
51586.000 51660.000 51806.000
Machinery (a+b+c)

d) Overhead charges @ 20% on @ 20% on @ 20% on


82,537.59 82,655.51 82,888.87
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
49,522.55 49,593.30 49,733.32
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 8 MT (a+b+c+d) 544,748.10 545,526.33 547,066.57
Rate for per MT (a+b+c+d)/8 68,093.51 68,190.79 68,383.32
Say 68,094.00 68,191.00 68,383.00
12.43 1600 Supplying, Fitting and Placing un-coated Mild steel
reinforcement in Foundation complete as per
Drawing and Technical Specifications.

Unit = MT
Taking output = 8 MT
a) Material
MS bars including 5 per cent overlaps and
wastage tonne 8.400 8.400 8.400 63,806.54 535,974.97 535,974.97 535,974.97 M-125
Binding wire Kg 48.000 48.000 48.000 66.72 3,202.56 3,202.56 3,202.56 M-072
b) Labour for straightening, cutting, bending,
shifting to site, tying and placing in position

Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Blacksmith day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-01
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
c) Machinery
Cutting Machine hour 5.333 5.333 5.333 528.15 2,816.80 2,816.80 2,816.80 P&M-076
Bending Machine hour 5.333 5.333 5.333 528.15 2,816.80 2,816.80 2,816.80 P&M-076
Electric generator 15 KVA hour 5.333 5.333 5.333 425.25 2,268.00 2,268.00 2,268.00 P&M-051
Tipper
Tipper for Transportation
(i) 18 cum capacity t.km 8 x L1 6.18 1,482.84 P&M-116
(ii) 14 cum capacity t.km 8 x L1 7.01 1,683.07 P&M-119
(iii) 10 cum capacity t.km 8 x L1 8.66 2,079.36 P&M-122
Loading & Unloading Time hour
(i) 18 cum capacity hour 1.000 2,883.30 2,883.30 P&M-014
(ii) 14 cum capacity hour 1.280 2,556.75 3,272.64 P&M-015
(iii) 10 cum capacity hour 1.778 2,274.30 4,043.20 P&M-016
Light weight Crane
At cutting bending yard hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102
At site hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102
Per MT Basic Cost of Labour, Material &
69762.000 69836.000 69982.000
Machinery (a+b+c)

d) Overhead charges @ 20% on @ 20% on @ 20% on


111,618.39 111,736.31 111,969.67
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
66,971.03 67,041.78 67,181.80
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 8 MT (a+b+c+d) 736,681.38 737,459.61 738,999.85
Rate for per MT (a+b+c+d)/8 92,085.17 92,182.45 92,374.98
Say 92,085.00 92,182.00 92,375.00
CHAPTER-13
SUB-STRUCTURE
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
13.01 1300 &
2200 Brick masonry work in 1:3 in sub-structure
complete excluding pointing and plastering, as per
drawing and Technical Specifications

Unit = cum
Taking output = 1 cum
a) Material
Bricks Ist class each 500.000 500.000 500.000 3.50 1,750.00 1,750.00 1,750.00 M-079
Sub-Analysis of
Cement mortar 1:3 (Rate as sub-analysis) cum 0.240 0.240 0.240 5,125.00 1,230.00 1,230.00 1,230.00 Concrete -
20.01 (A)
Water for curing KL 0.483 0.483 0.483 16.00 7.73 7.73 7.73 M-191
b) Labour
Mate day 0.064 0.064 0.064 617.00 39.49 39.49 39.49 L-12
Mason day 0.800 0.800 0.800 679.00 543.20 543.20 543.20 L-10
Mazdoor day 0.800 0.800 0.800 511.52 409.22 409.22 409.22 L-13
Add for scaffolding @ 5 per cent of cost of material
198.98 198.98 198.98
and labour
c) Machinery

Water tanker (speed @ 20km/hr and return speed


@ 30 km/hr and spreading @ 30 mins per trip )

P&M-023
(i) 16 KL capacity hour 0.003XL1+0.02 1,501.00 165.11

0.004XL1+0.02 P&M-024
(ii) 12 KL capacity hour 1,327.00 195.07
7
0.009XL1+0.05 P&M-025
(iii) 6 KL capacity hour 1,005.00 325.62
4
@ 20% on @ 20% on @ 20% on
d) Overhead charges 868.74 874.74 900.85
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 521.25 524.84 540.51
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum (a+b+c+d+e) 5,733.72 5,773.26 5,945.59
Say 5,734.00 5,773.00 5,946.00
13.02 1300 &
2200 Pointing with cement mortar (1:3 ) on brick work in
substructure as per Technical Specifications

Unit = sqm
Taking output = 10 sqm
a) Material
Sub-Analysis of
Cement mortar 1:3 (Rate as sub-analysis) cum 0.030 0.030 0.030 5,125.00 153.75 153.75 153.75 Concrete -
20.01 (A)
b) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mason day 0.500 0.500 0.500 679.00 339.50 339.50 339.50 L-10
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
@ 20% on @ 20% on @ 20% on
c) Overhead charges 154.74 154.74 154.74
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 92.84 92.84 92.84
(a+b+c) (a+b+c) (a+b+c)
Rate per 10 sqm (a+b+c+d) 1,021.27 1,021.27 1,021.27
Rate per sqm =(a+b+c+d+e)/10 102.13 102.13 102.13
Say 102.00 102.00 102.00
Note Scaffolding is already included in item 13.1
13.03 1300 &
2200 Plastering with cement mortar (1:3 ) on brick work
in sub-structure as per Technical Specifications

Unit = 10 sqm
Taking output = 10 sqm
a) Material
Sub-Analysis of
Cement mortar 1:3 (Rate as sub-analysis) cum 0.144 0.144 0.144 5,125.00 738.00 738.00 738.00 Concrete -
20.01 (A)
Water for curing KL 0.139 0.139 0.139 16.00 2.23 2.23 2.23 M-191
b) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mason day 0.500 0.500 0.500 679.00 339.50 339.50 339.50 L-11
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
c) Machinery

Water tanker (speed @ 20km/hr and return speed


@ 30 km/hr and spreading @ 30 mins per trip )

0.001XL1+0.00 P&M-023
(i) 16 KL capacity hour 1,501.00 54.04
6
0.001XL1+0.00 P&M-024
(ii) 12 KL capacity hour 1,327.00 50.43
8
0.003XL1+0.01 P&M-025
(iii) 6 KL capacity hour 1,005.00 105.53
5

@ 20% on @ 20% on @ 20% on


d) Overhead charges 282.84 282.12 293.14
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 169.70 169.27 175.88
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per 10 sqm (a+b+c+d+e) 1,866.75 1,861.98 1,934.71
Rate per sqm =(a+b+c+d+e)/10 186.67 186.20 193.47
Say 187.00 186.00 193.00
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Note
1.Scaffolding is already included in item no. 13.1

2.The number of masons and Mazdoors already


catered in the cement mortar have been taken into
account while providing these categories in brick
masonry, pointing and plastering.

13.04 1400 & Stone masonry work in cement mortar 1:3 for
2200 substructure complete as per drawing and
Technical Specifications
A Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.000 1.000 1.000 1,472.59 1,472.59 1,472.59 1,472.59 M-001
Through and bond stone No 7.000 7.000 7.000 59.77 418.39 418.39 418.39 M-184
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Sub-Analysis of
Cement mortar 1:3 (Rate as sub-analysis) cum 0.330 0.330 0.330 5,125.00 1,691.25 1,691.25 1,691.25 Concrete -
20.01 (A)
Water for curing KL 0.966 0.966 0.966 16.00 15.46 15.46 15.46 M-191
b) Labour
Mate day 0.096 0.096 0.096 617.00 59.23 59.23 59.23 L-12
Mason day 1.200 1.200 1.200 679.00 814.80 814.80 814.80 L-10
Mazdoor day 1.200 1.200 1.200 511.52 613.82 613.82 613.82 L-13
Add for scaffolding @ 5 per cent of cost of a)
254.28 254.28 254.28
Material and b) Labour
c) Machinery

Water tanker (speed @ 20km/hr and return speed


@ 30 km/hr and spreading @ 30 mins per trip )

P&M-023
(i) 16 KL capacity hour 0.007XL1+0.04 1,501.00 375.25

0.009XL1+0.05 P&M-024
(ii) 12 KL capacity hour 1,327.00 429.95
4
0.018XL1+0.10 P&M-025
(iii) 6 KL capacity hour 1,005.00 650.24
7
@ 20% on @ 20% on @ 20% on
d) Overhead charges 1,143.01 1,153.95 1,198.01
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 685.81 692.37 718.81
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum (a+b+c+d) 7,543.89 7,616.09 7,906.87
Say 7,544.00 7,616.00 7,907.00
13.04 B Coursed rubble masonry (first sort )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.100 1.100 1.100 1,472.59 1,619.85 1,619.85 1,619.85 M-001
Through and bond stone each 7.000 7.000 7.000 59.77 418.39 418.39 418.39 M-184
(7 no.x 0.24 m x 0.24 m x 0.39 m = 0.16 cum)
Sub-Analysis of
Cement mortar 1:3 (Rate as sub-analysis) cum 0.300 0.300 0.300 5,125.00 1,537.50 1,537.50 1,537.50 Concrete -
20.01 (A)
Water for curing KL 0.966 0.966 0.966 16.00 15.46 15.46 15.46 M-191
b) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.500 1.500 1.500 511.52 767.28 767.28 767.28 L-13
Add for scaffolding @ 5 per cent of cost of material
272.55 272.55 272.55
and labour
c) Machinery

Water tanker (speed @ 20km/hr and return speed


@ 30 km/hr and spreading @ 30 mins per trip )

P&M-023
(i) 16 KL capacity hour 0.007XL1+0.04 1,501.00 375.25

0.009XL1+0.05 P&M-024
(ii) 12 KL capacity hour 1,327.00 429.95
4
0.018XL1+0.10 P&M-025
(iii) 6 KL capacity hour 1,005.00 650.24
7
@ 20% on @ 20% on @ 20% on
d) Overhead charges 1,219.76 1,230.70 1,274.76
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 731.86 738.42 764.86
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum (a+b+c+d) 8,050.44 8,122.64 8,413.42
Say 8,050.00 8,123.00 8,413.00
13.04 C Ashlar masonry ( first sort )
Plain ashlar
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.110 1.110 1.110 1,472.59 1,634.58 1,634.58 1,634.58 M-001
Through and bond stone each 7.000 7.000 7.000 59.77 418.39 418.39 418.39 M-184
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Sub-Analysis of
Cement mortar 1:3 (Rate as sub-analysis) cum 0.330 0.330 0.330 5,125.00 1,691.25 1,691.25 1,691.25 Concrete -
20.01 (A)
Water for curing KL 0.966 0.966 0.966 16.00 15.46 15.46 15.46 M-191
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
b) Labour for masonry work
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mason day 2.500 2.500 2.500 679.00 1,697.50 1,697.50 1,697.50 L-10
Mazdoor day 2.500 2.500 2.500 511.52 1,278.80 1,278.80 1,278.80 L-13
Add for scaffolding @ 5 per cent of cost of a)
342.97 342.97 342.97
Material and b) Labour
c) Machinery

Water tanker (speed @ 20km/hr and return speed


@ 30 km/hr and spreading @ 30 mins per trip )

P&M-023
(i) 16 KL capacity hour 0.007XL1+0.04 1,501.00 375.25

0.009XL1+0.05 P&M-024
(ii) 12 KL capacity hour 1,327.00 429.95
4
0.018XL1+0.10 P&M-025
(iii) 6 KL capacity hour 1,005.00 650.24
7
@ 20% on @ 20% on @ 20% on
d) Overhead charges 1,515.52 1,526.46 1,570.52
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 909.31 915.87 942.31
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum (a+b+c+d) 10,002.42 10,074.62 10,365.40
Say 10,002.00 10,075.00 10,365.00
Note The labour already considered in the cement
mortar have been taken into account while
providing these categories in the stone masonry
works.
13.05 1500, Plain/Reinforced cement concrete in sub-structure
1700 & complete as per drawing and Technical
2200 Specifications
A PCC Grade M15
(p) Height upto 5m
PCC Grade M15 using batching plant & Concrete
pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 4,176.00 125,280.00 125,280.00 125,280.00 Concrete -
20.03
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )

0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55

d) Formwork @ 10 per cent on cost of concrete


16,779.54 16,887.59 17,246.50
i.e. cost of material, labour and machinery

@ 20% on @ 20% on @ 20% on


e) Overhead charges 36,914.99 37,152.69 37,942.30
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 22,148.99 22,291.61 22,765.38
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 243,638.91 245,207.74 250,419.21
Rate per cum = (a+b+c+d+e+f)/30 8,121.30 8,173.59 8,347.31
Say 8,121.00 8,174.00 8,347.00
13.05 B PCC Grade M20
(p) Height upto 5m
PCC Grade M20 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 4,518.00 135,540.00 135,540.00 135,540.00 Concrete -
20.04
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )

0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55

d) Formwork @ 10 per cent on cost of concrete


17,805.54 17,913.59 18,272.50
i.e. cost of material, labour and machinery

@ 20% on @ 20% on @ 20% on


e) Overhead charges 39,172.19 39,409.89 40,199.50
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 23,503.31 23,645.93 24,119.70
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 258,536.43 260,105.26 265,316.73
Rate per cum = (a+b+c+d+e+f)/30 8,617.88 8,670.18 8,843.89
Say 8,618.00 8,670.00 8,844.00
13.05 C Height upto 5m
PCC Grade M25 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 4,793.00 143,790.00 143,790.00 143,790.00 Concrete -
20.06
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )

0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55

d) Formwork @ 10 per cent on cost of concrete


18,630.54 18,738.59 19,097.50
i.e. cost of material, labour and machinery

@ 20% on @ 20% on @ 20% on


e) Overhead charges 40,987.19 41,224.89 42,014.50
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 24,592.31 24,734.93 25,208.70
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 270,515.43 272,084.26 277,295.73
Rate per cum = (a+b+c+d+e+f)/30 9,017.18 9,069.48 9,243.19
Say 9,017.00 9,069.00 9,243.00
13.05 C (q) Height 5m to 10m
PCC Grade M25 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 4,793.00 143,790.00 143,790.00 143,790.00 Concrete -
20.06
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55

d) Formwork @ 12 per cent on cost of concrete


22,356.65 22,486.30 22,917.00
i.e. cost of material, labour and machinery

Add 2 per cent of cost of material, Labour and


3,726.11 3,747.72 3,819.50
machinery excluding formwork to cater for extra lift"

@ 20% on @ 20% on @ 20% on


e) Overhead charges 42,477.63 42,723.97 43,542.30
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 25,486.58 25,634.38 26,125.38
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 280,352.36 281,978.23 287,379.21
Rate per cum = (a+b+c+d+e+f)/30 9,345.08 9,399.27 9,579.31
Say 9,345.00 9,399.00 9,579.00
13.05 C (r) Height above 10m
Case II PCC Grade M25 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 4,793.00 143,790.00 143,790.00 143,790.00 Concrete -
20.06
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )

0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55

d) Formwork @ 15 per cent on cost of concrete


27,945.81 28,107.88
i.e. cost of material, labour and machinery

Add 4 per cent per cent of cost of material,


Labour and machinery excluding formwork to cater 7,452.22 7,495.43 7,639.00
for extra lift"
@ 20% on @ 20% on @ 20% on
e) Overhead charges 44,340.68 44,597.83 39,722.80
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 26,604.41 26,758.70 23,833.68
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 292,648.51 294,345.70 262,170.50
Rate per cum = (a+b+c+d+e+f)/30 9,754.95 9,811.52 8,739.02
Say 9,755.00 9,812.00 8,739.00
13.05 D PCC Grade M30
(p) Height upto 5m
Case II PCC Grade M30 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 4,819.00 144,570.00 144,570.00 144,570.00 Concrete -
20.08
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )

0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55

d) Formwork @ 10 per cent on cost of concrete


18,708.54 18,816.59 19,175.50
i.e. cost of material, labour and machinery

@ 20% on @ 20% on @ 20% on


e) Overhead charges 41,158.79 41,396.49 42,186.10
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 24,695.27 24,837.89 25,311.66
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 271,647.99 273,216.82 278,428.29
Rate per cum = (a+b+c+d+e+f)/30 9,054.93 9,107.23 9,280.94
Say 9,055.00 9,107.00 9,281.00
13.5 D (q) Height 5m to 10m
Case II PCC Grade M30 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 4,819.00 144,570.00 144,570.00 144,570.00 Concrete -
20.08
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )

0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55

d) Formwork @ 12 per cent on cost of concrete


22,450.25 22,579.90 23,010.60
i.e. cost of material, labour and machinery

Add 2 per cent of cost of material, Labour and


3,741.71 3,763.32 3,835.10
machinery excluding formwork to cater for extra lift

@ 20% on @ 20% on @ 20% on


e) Overhead charges 42,655.47 42,901.81 43,720.14
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 25,593.28 25,741.09 26,232.09
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 281,526.10 283,151.97 288,552.95
Rate per cum = (a+b+c+d+e+f)/30 9,384.20 9,438.40 9,618.43
Say 9,384.00 9,438.00 9,618.00
13.05 D (r) Height above 10m
Case II PCC Grade M30 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 4,819.00 144,570.00 144,570.00 144,570.00 Concrete -
20.08
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )

0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project

d) Formwork @ 15 per cent on cost of concrete


28,062.81 28,224.88 28,763.25
i.e. cost of material, labour and machinery

Add 4 per cent of cost of material, Labour and


7,483.42 7,526.63 7,670.20
machinery excluding formwork to cater for extra lift

@ 20% on @ 20% on @ 20% on


e) Overhead charges 44,526.32 44,783.47 45,637.69
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 26,715.79 26,870.08 27,382.62
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 293,873.74 295,570.92 301,208.78
Rate per cum = (a+b+c+d+e+f)/30 9,795.79 9,852.36 10,040.29
Say 9,796.00 9,852.00 10,040.00
13.05 E RCC Grade M20
(p) Height upto 5m

Same as Item 12.8 (C) upto 5 m height, except for


formwork which shall be 10 per cent instead of 4
per cent of cost of material, labour and machinery.

Case II RCC Grade M20 using batching plant transit mixer


& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 4,533.00 135,990.00 135,990.00 135,990.00 Concrete -
20.05
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )

0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55

d) Formwork @ 10 per cent on cost of concrete


17,904.16 18,012.21 18,371.12
i.e. cost of material, labour and machinery

@ 20% on @ 20% on @ 20% on


e) Overhead charges 39,389.15 39,626.85 40,416.47
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 23,633.49 23,776.11 24,249.88
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 259,968.39 261,537.22 266,748.69
Rate per cum = (a+b+c+d+e+f)/30 8,665.61 8,717.91 8,891.62
Say 8,666.00 8,718.00 8,892.00
13.05 E (q) Height 5m to 10m
For height, upto 10m, add 2 per cent of cost as
above excluding formwork. For cost of formwork
add 12 per cent of cost of material, labour and
machinery instead of 4 per cent .
Case II RCC Grade M20 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 4,533.00 135,990.00 135,990.00 135,990.00 Concrete -
20.05
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )

0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55

d) Formwork @ 12 per cent on cost of concrete


12.000 21,484.99 21,614.65 22,045.35
i.e. cost of material, labour and machinery

Add 2 per cent of cost of material, Labour and


2.000 3,580.83 3,602.44 3,674.22
machinery excluding formwork to cater for extra lift

@ 20% on @ 20% on @ 20% on


e) Overhead charges 40,821.48 41,067.83 41,886.16
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 24,492.89 24,640.70 25,131.69
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 269,421.79 271,047.66 276,448.64
Rate per cum = (a+b+c+d+e+f)/30 8,980.73 9,034.92 9,214.95
Say 8,981.00 9,035.00 9,215.00
13.5 E (r) Height above 10m

Same as Item 12.8 (C) with the following changes:


(i) Add 4 per cent of cost of material, labour and
machinery excluding form work to cater for extra
lift. (ii) The provision of form work shall be 15 per
cent instead of 4 per cent of cost of material,
labour and machinery.

Case II RCC Grade M20 using batching plant transit mixer


& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 4,533.00 135,990.00 135,990.00 135,990.00 Concrete -
20.05
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.694 0.694 2,413.95 1,569.07 1,676.35 1,676.35 P&M-067
Hydraulic Boom placer pump hour 0.650 0.694 0.694 4,401.60 2,861.04 3,056.67 3,056.67 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )

0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55

d) Formwork @ 15 per cent on cost of concrete


15.000 26,856.24 27,063.74 27,602.12
i.e. cost of material, labour and machinery

Add 4 per cent of cost of material, Labour and


4.000 7,161.66 7,217.00 7,360.57
machinery excluding formwork to cater for extra lift

@ 20% on @ 20% on @ 20% on


e) Overhead charges 42,611.90 42,941.14 43,795.36
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 25,567.14 25,764.69 26,277.22
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 281,238.54 283,411.54 289,049.40
Rate per cum = (a+b+c+d+e+f)/30 9,374.62 9,447.05 9,634.98
Say 9,375.00 9,447.00 9,635.00
13.05 F RCC Grade M25
(p) Height upto 5m
Case II RCC Grade M25 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 4,945.00 148,350.00 148,350.00 148,350.00 Concrete -
20.07
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )

0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 10 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 10.000 19,140.16 19,248.21 19,607.12
Formwork

@ 20% on @ 20% on @ 20% on


e) Overhead charges 42,108.35 42,346.05 43,135.67
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 25,265.01 25,407.63 25,881.40
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 277,915.11 279,483.94 284,695.41
Rate per cum = (a+b+c+d+e+f)/30 9,263.84 9,316.13 9,489.85
Say 9,264.00 9,316.00 9,490.00
13.05 F (q) Height 5m to 10m
Case II RCC Grade M25 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 4,945.00 148,350.00 148,350.00 148,350.00 Concrete -
20.07
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )

0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 11.8 per cent on cost of concrete i.e. cost
of material, labour and machinery (a+b+c) for 11.800 22,585.39 22,712.88 23,136.40
Formwork

Add 1.8 per cent of cost of material, Labour and


1.800 3,445.23 3,464.68 3,529.28
machinery excluding formwork to cater for extra lift

@ 20% on @ 20% on @ 20% on


e) Overhead charges 43,486.44 43,731.92 44,547.38
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 26,091.87 26,239.15 26,728.43
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 287,010.52 288,630.69 294,012.71
Rate per cum = (a+b+c+d+e+f)/30 9,567.02 9,621.02 9,800.42
Say 9,567.00 9,621.00 9,800.00
13.05 F (r) Height above 10m
Case II RCC Grade M25 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 4,945.00 148,350.00 148,350.00 148,350.00 Concrete -
20.07
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 15 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 15.000 28,710.24 28,872.31 29,410.68
Formwork

Add 4 per cent of cost of material, Labour and


4.000 7,656.06 7,699.28 7,842.85
machinery excluding formwork to cater for extra lift

@ 20% on @ 20% on @ 20% on


e) Overhead charges 45,553.58 45,810.73 46,664.95
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 27,332.15 27,486.44 27,998.97
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 300,653.62 302,350.81 307,988.67
Rate per cum = (a+b+c+d+e+f)/30 10,021.79 10,078.36 10,266.29
Say 10,022.00 10,078.00 10,266.00

13.05 G RCC Grade M30


(p) Height upto 5m
RCC Grade M30 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 5,032.00 150,960.00 150,960.00 150,960.00 Concrete -
20.09
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )

0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 10 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 10.000 19,401.16 19,509.21 19,868.12
Formwork

@ 20% on @ 20% on @ 20% on


e) Overhead charges 42,682.55 42,920.25 43,709.87
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 25,609.53 25,752.15 26,225.92
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 281,704.83 283,273.66 288,485.13
Rate per cum = (a+b+c+d+e+f)/30 9,390.16 9,442.46 9,616.17
Say 9,390.00 9,442.00 9,616.00
13.05 G (q) Height 5m to 10m
RCC Grade M30 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 5,032.00 150,960.00 150,960.00 150,960.00 Concrete -
20.09
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 11.5 per cent on cost of concrete i.e. cost
of material, labour and machinery (a+b+c) for 11.500 11.500 11.500 22,311.33 22,435.59 22,848.34
Formwork

Add 1.6 per cent of cost of material, Labour and


1.600 1.600 1.600 3,104.19 3,121.47 3,178.90
machinery excluding formwork to cater for extra lift

@ 20% on @ 20% on @ 20% on


e) Overhead charges 43,885.42 44,129.82 44,941.69
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 26,331.25 26,477.89 26,965.01
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 289,643.79 291,256.83 296,615.16
Rate per cum = (a+b+c+d+e+f)/30 9,654.79 9,708.56 9,887.17
Say 9,655.00 9,709.00 9,887.00
13.05 G (r) Height above 10m
Case II RCC Grade M30 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 5,032.00 150,960.00 150,960.00 150,960.00 Concrete -
20.09
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )

0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 14 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 14.000 27,161.62 27,312.89 27,815.37
Formwork

Add 3.5 per cent of cost of material, Labour and


3.500 6,790.41 6,828.22 6,953.84
machinery excluding formwork to cater for extra lift

@ 20% on @ 20% on @ 20% on


e) Overhead charges 45,592.72 45,846.63 46,690.09
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 27,355.63 27,507.98 28,014.05
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 300,911.98 302,587.77 308,154.57
Rate per cum = (a+b+c+d+e+f)/30 10,030.40 10,086.26 10,271.82
Say 10,030.00 10,086.00 10,272.00
13.05 H RCC Grade M35
(p) Height upto 5m
RCC Grade M35 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 5,186.00 155,580.00 155,580.00 155,580.00 Concrete -
20.11
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 10 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 10.000 10.000 10.000 19,863.16 19,971.21 20,330.12
Formwork

@ 20% on @ 20% on @ 20% on


e) Overhead charges 43,698.95 43,936.65 44,726.27
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 26,219.37 26,361.99 26,835.76
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 288,413.07 289,981.90 295,193.37
Rate per cum = (a+b+c+d+e+f)/30 9,613.77 9,666.06 9,839.78
Say 9,614.00 9,666.00 9,840.00
13.05 H (q) Height 5m to 10m
RCC Grade M35 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 5,186.00 155,580.00 155,580.00 155,580.00 Concrete -
20.11
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )

0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 11 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 11.000 11.000 11.000 21,849.48 21,968.33 22,363.13
Formwork

Add 1.4 per cent of cost of material, Labour and


1.400 1.400 1.400 2,780.84 2,795.97 2,846.22
machinery excluding formwork to cater for extra lift

@ 20% on @ 20% on @ 20% on


e) Overhead charges 44,652.38 44,895.27 45,702.11
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 26,791.43 26,937.16 27,421.27
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 294,705.72 296,308.78 301,633.95
Rate per cum = (a+b+c+d+e+f)/30 9,823.52 9,876.96 10,054.47
Say 9,824.00 9,877.00 10,054.00
Note The basic components of this analysis are the
same as those of items 13.8 (A to H). The only
changes are as under:

a) Ramps/Stairs: Extra expenditure on structures


which are more than 5 m high @ 2 per cent of cost
for height upto 10 m and 4 per cent for heights
above 10 m will be involved for approaching the
work spot by providing higher ramp/stair case for
use by the working parties.

b) The above mentioned percentages have been


suitably modified for different categories as cost for
various categories varies, whereas effort for
access for same height will be similar. As the cost
of richer concrete is comparatively more, the
percentage to be added has been reduced to
maintain the same cost for extra efforts.

13.05 H (r) Height above 10m


RCC Grade M35 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 5,186.00 155,580.00 155,580.00 155,580.00 Concrete -
20.11
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )

0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 13 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 13.000 25,822.11 25,962.57 26,429.16
Formwork

Add 3 per cent of cost of material, Labour and


3.000 5,958.95 5,991.36 6,099.04
machinery excluding formwork to cater for extra lift

@ 20% on @ 20% on @ 20% on


e) Overhead charges 46,082.53 46,333.20 47,165.88
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 27,649.52 27,799.92 28,299.53
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 304,144.70 305,799.09 311,294.82
Rate per cum = (a+b+c+d+e+f)/30 10,138.16 10,193.30 10,376.49
Say 10,138.00 10,193.00 10,376.00
13.05 I RCC Grade M40
(p) Height upto 5m
RCC Grade M40 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 5,519.00 165,570.00 165,570.00 165,570.00 Concrete -
20.12
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )

0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 10 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 10.000 10.000 10.000 20,862.16 20,970.21 21,329.12
Formwork

@ 20% on @ 20% on @ 20% on


e) Overhead charges 45,896.75 46,134.45 46,924.07
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 27,538.05 27,680.67 28,154.44
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 302,918.55 304,487.38 309,698.85
Rate per cum = (a+b+c+d+e+f)/30 10,097.29 10,149.58 10,323.29
Say 10,097.00 10,150.00 10,323.00
13.05 I (q) Height 5m to 10m
For height, upto 10m, add 1.4 per cent of cost as
above excluding formwork. For cost of formwork
add 11 per cent of cost of material, labour and
machinery .
RCC Grade M40 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 5,519.00 165,570.00 165,570.00 165,570.00 Concrete -
20.12
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )

0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 11 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 11.000 11.000 11.000 22,948.38 23,067.23 23,462.03
Formwork

Add 1.4 per cent of cost of material, Labour and


1.400 1.400 1.400 2,920.70 2,935.83 2,986.08
machinery excluding formwork to cater for extra lift

@ 20% on @ 20% on @ 20% on


e) Overhead charges 46,898.13 47,141.02 47,947.87
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 28,138.88 28,284.61 28,768.72
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 309,527.69 311,130.74 316,455.91
Rate per cum = (a+b+c+d+e+f)/30 10,317.59 10,371.02 10,548.53
Say 10,318.00 10,371.00 10,549.00
13.05 H (r) Height above 10m
For height, above 10m, add 3 per cent of cost as
above excluding formwork. For cost of formwork
add 13 per cent of cost of material, labour and
machinery
RCC Grade M40 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 5,519.00 165,570.00 165,570.00 165,570.00 Concrete -
20.12
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )

0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 13 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 13.000 13.000 13.000 27,120.81 27,261.27 27,727.86
Formwork

Add 3 per cent of cost of material, Labour and


3.000 3.000 3.000 6,258.65 6,291.06 6,398.74
machinery excluding formwork to cater for extra lift

@ 20% on @ 20% on @ 20% on


e) Overhead charges 48,400.21 48,650.88 49,483.56
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 29,040.13 29,190.53 29,690.14
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 319,441.38 321,095.78 326,591.51
Rate per cum = (a+b+c+d+e+f)/30 10,648.05 10,703.19 10,886.38
Say 10,648.00 10,703.00 10,886.00
13.05 J RCC Grade M45
(p) Height upto 5m
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
RCC Grade M45 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 5,663.00 169,890.00 169,890.00 169,890.00 Concrete -
20.13
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )

0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 10 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 10.000 10.000 10.000 21,294.16 21,402.21 21,761.12
Formwork

@ 20% on @ 20% on @ 20% on


e) Overhead charges 46,847.15 47,084.85 47,874.47
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 28,108.29 28,250.91 28,724.68
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 309,191.19 310,760.02 315,971.49
Rate per cum = (a+b+c+d+e+f)/30 10,306.37 10,358.67 10,532.38
Say 10,306.00 10,359.00 10,532.00
13.05 J (q) Height 5m to 10m
For height, upto 10m, add 1.4 per cent of cost as
above excluding formwork. For cost of formwork
add 11 per cent of cost of material, labour and
machinery .
RCC Grade M45 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 5,663.00 169,890.00 169,890.00 169,890.00 Concrete -
20.13
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )

0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 11 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 11.000 11.000 11.000 23,423.58 23,542.43 23,937.23
Formwork

Add 1.4 per cent of cost of material, Labour and


1.400 1.400 1.400 2,981.18 2,996.31 3,046.56
machinery excluding formwork to cater for extra lift

@ 20% on @ 20% on @ 20% on


e) Overhead charges 47,869.27 48,112.16 48,919.00
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 28,721.56 28,867.29 29,351.40
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 315,937.18 317,540.24 322,865.41
Rate per cum = (a+b+c+d+e+f)/30 10,531.24 10,584.67 10,762.18
Say 10,531.00 10,585.00 10,762.00
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
13.05 J (r) Height above 10m
For height, above 10m, add 3 per cent of cost as
above excluding formwork. For cost of formwork
add 13 per cent of cost of material, labour and
machinery
RCC Grade M45 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 5,663.00 169,890.00 169,890.00 169,890.00 Concrete -
20.13
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )

0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 13 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 13.000 13.000 13.000 27,682.41 27,822.87 28,289.46
Formwork

Add 3 per cent of cost of material, Labour and


3.000 3.000 3.000 6,388.25 6,420.66 6,528.34
machinery excluding formwork to cater for extra lift

@ 20% on @ 20% on @ 20% on


e) Overhead charges 49,402.45 49,653.12 50,485.80
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 29,641.47 29,791.87 30,291.48
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 326,056.17 327,710.57 333,206.30
Rate per cum = (a+b+c+d+e+f)/30 10,868.54 10,923.69 11,106.88
Say 10,869.00 10,924.00 11,107.00
13.05 K RCC Grade M50
RCC Grade M50 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 6,242.00 187,260.00 187,260.00 187,260.00 Concrete -
20.14
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )

0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 10 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 10.000 10.000 10.000 23,031.16 23,139.21 23,498.12
Formwork
@ 20% on @ 20% on @ 20% on
e) Overhead charges 50,668.55 50,906.25 51,695.87
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 30,401.13 30,543.75 31,017.52
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 334,412.43 335,981.26 341,192.73
Rate per cum = (a+b+c+d+e+f)/30 11,147.08 11,199.38 11,373.09
Say 11,147.00 11,199.00 11,373.00
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
13.05 K (q) Height 5m to 10m
For height, upto 10m, add 1.4 per cent of cost as
above excluding formwork. For cost of formwork
add 11 per cent of cost of material, labour and
machinery .
RCC Grade M50 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 6,242.00 187,260.00 187,260.00 187,260.00 Concrete -
20.14
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )

0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 11 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 11.000 11.000 11.000 25,334.28 25,453.13 25,847.93
Formwork

Add 1.4 per cent of cost of material, Labour and


1.400 1.400 1.400 3,224.36 3,239.49 3,289.74
machinery excluding formwork to cater for extra lift

@ 20% on @ 20% on @ 20% on


e) Overhead charges 51,774.05 52,016.93 52,823.78
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 31,064.43 31,210.16 31,694.27
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 341,708.71 343,311.76 348,636.93
Rate per cum = (a+b+c+d+e+f)/30 11,390.29 11,443.73 11,621.23
Say 11,390.00 11,444.00 11,621.00
13.05 K (r) Height above 10m
For height, above 10m, add 3 per cent of cost as
above excluding formwork. For cost of formwork
add 13 per cent of cost of material, labour and
machinery
RCC Grade M50 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 6,242.00 187,260.00 187,260.00 187,260.00 Concrete -
20.14
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )

0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 13 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 13.000 13.000 13.000 29,940.51 30,080.97 30,547.56
Formwork

Add 3 per cent of cost of material, Labour and


3.000 3.000 3.000 6,909.35 6,941.76 7,049.44
machinery excluding formwork to cater for extra lift
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
@ 20% on @ 20% on @ 20% on
e) Overhead charges 53,432.29 53,682.96 54,515.64
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 32,059.37 32,209.77 32,709.39
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 352,653.11 354,307.51 359,803.24
Rate per cum = (a+b+c+d+e+f)/30 11,755.10 11,810.25 11,993.44
Say 11,755.00 11,810.00 11,993.00
Note The basic components of this analysis are the
same as those of items 13.8 (A to H). The only
changes are as under:

a) Ramps/Stairs: Extra expenditure on structures


which are more than 5 m high @ 2 per cent of cost
for height upto 10 m and 4 per cent for heights
above 10 m will be involved for approaching the
work spot by providing higher ramp/stair case for
use by the working parties.

b) The above mentioned percentages have been


suitably modified for different categories as cost for
various categories varies, whereas effort for
access for same height will be similar. As the cost
of richer concrete is comparatively more, the
percentage to be added has been reduced to
maintain the same cost for extra efforts.

13.06 Section Supplying, fitting and placing HYSD bar


1600 & reinforcement in sub-structure complete as per
2200 drawing and Technical Specifications
Unit = MT
Taking output = 8 MT
a) Material
MS bars including 5 per cent overlaps and M-083
tonne 8.400 8.400 8.400 46,496.54 390,570.97 390,570.97 390,570.97
wastage
Binding wire Kg 48.000 48.000 48.000 66.72 3,202.56 3,202.56 3,202.56 M-072

b) Labour for straightening, cutting, bending,


shifting to site, tying and placing in position

Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Blacksmith day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-20
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
c) Machinery
Cutting Machine hour 6.667 6.667 6.667 528.15 3,521.00 3,521.00 3,521.00 P&M-076
Bending Machine hour 6.667 6.667 6.667 528.15 3,521.00 3,521.00 3,521.00 P&M-076
Electric generator 15 KVA hour 6.667 6.667 6.667 425.25 2,835.00 2,835.00 2,835.00 P&M-051
Tipper
Tipper for Transportation
(i) 18 cum capacity t.km 8 x L1 6.18 1,482.84 P&M-116
(ii) 14 cum capacity t.km 8 x L1 7.01 1,683.07 P&M-119
(iii) 10 cum capacity t.km 8 x L1 8.66 2,079.36 P&M-122
Loading & Unloading Time hour
(i) 18 cum capacity hour 1.000 2,883.30 2,883.30 P&M-014
(ii) 14 cum capacity hour 1.280 2,556.75 3,272.64 P&M-015
(iii) 10 cum capacity hour 1.778 2,274.30 4,043.71 P&M-016
Light weight Crane
At cutting bending yard hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102
At site hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102

@ 20% on @ 20% on @ 20% on


d) Overhead charges 82,932.67 83,050.59 83,284.06
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 49,759.60 49,830.35 49,970.43
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 8 MT (a+b+c+d+e) 547,355.63 548,133.86 549,674.77
Rate for per MT (a+b+c+d+e)/8 68,419.45 68,516.73 68,709.35
Say 68,419.00 68,517.00 68,709.00
13.07 Section Supplying, fitting and placing Mild steel
1600 & reinforcement complete in sub-structure as per
2200 drawing and Technical Specification
Unit = MT
Taking output = 8 MT
a) Material
MS bars including 5 per cent overlaps and M-125
tonne 8.400 8.400 8.400 63,806.54 535,974.97 535,974.97 535,974.97
wastage
Binding wire Kg 48.000 48.000 48.000 66.72 3,202.56 3,202.56 3,202.56 M-072

b) Labour for straightening, cutting, bending,


shifting to site, tying and placing in position

Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Blacksmith day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-20
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
c) Machinery
Cutting Machine hour 6.667 6.667 6.667 528.15 3,521.00 3,521.00 3,521.00 P&M-076
Bending Machine hour 6.667 6.667 6.667 528.15 3,521.00 3,521.00 3,521.00 P&M-076
Electric generator 15 KVA hour 6.667 6.667 6.667 425.25 2,835.00 2,835.00 2,835.00 P&M-051
Tipper
Tipper for Transportation
(i) 18 cum capacity t.km 8 x L1 6.18 1,482.84 P&M-116
(ii) 14 cum capacity t.km 8 x L1 7.01 1,683.07 P&M-119
(iii) 10 cum capacity t.km 8 x L1 8.66 2,079.36 P&M-122
Loading & Unloading Time hour
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
(i) 18 cum capacity hour 1.000 2,883.30 2,883.30 P&M-014
(ii) 14 cum capacity hour 1.280 2,556.75 3,272.64 P&M-015
(iii) 10 cum capacity hour 1.778 2,274.30 4,043.71 P&M-016
Light weight Crane
At cutting bending yard hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102
At site hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102

@ 20% on @ 20% on @ 20% on


d) Overhead charges 112,013.47 112,131.39 112,364.86
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 67,208.08 67,278.83 67,418.91
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 8 MT (a+b+c+d+e) 739,288.91 740,067.14 741,608.05
Rate for per MT (a+b+c+d+e)/8 92,411.11 92,508.39 92,701.01
Say 92,411.00 92,508.00 92,701.00
13.08 2706 &
2200 Providing weep holes in Brick masonry/Plain/
Reinforced concrete abutment, wing wall/ return
wall with 100 mm dia AC pipe, extending through
the full width of the structure with slope of 1V :20H
towards drawing foce. Complete as per drawing
and Technical Specifications

Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including wastage @ 5 per M-056
metre 31.500 31.500 31.500 59.13 1,862.60 1,862.60 1,862.60
cent )
Average length of weep hole is taken as one metre
for the purpose of estimating.
MS clamp each. 30.000 30.000 30.000 41.70 1,251.00 1,251.00 1,251.00 M-122
collar for AC pipe (average) taking 10% of above M-056/10
each. 10.000 10.000 10.000 5.91 59.13 59.13 59.13
pipe rate
Sub-Analysis of
Cement mortar 1:3 (Rate as sub-analysis) cum 0.050 0.050 0.050 5,125.00 256.25 256.25 256.25 Concrete -
20.01 (A)
b) Labour
Mate day 0.030 0.030 0.030 617.00 18.51 18.51 18.51 L-12
Mason day 0.500 0.500 0.500 679.00 339.50 339.50 339.50 L-10
Mazdoor day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
@ 20% on @ 20% on @ 20% on
c) Overhead charges 782.97 782.97 782.97
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 469.78 469.78 469.78
(a+b+c) (a+b+c) (a+b+c)
Cost for 30 m = a+b+c+d 5,167.62 5,167.62 5,167.62
Rate per m (a+b+c+d)/30 172.25 172.25 172.25
Say 172.00 172.00 172.00
Note 1. In case of stone masonry, the size of the weep
hole shall be 150 mm x 80 mm or circular with 150
mm diameter.

2. For structure in stone masonry, the weep holes


shall be deemed to be included in the item of stone
masonry work and shall not be paid separately.

13.09 710.1.4.of Back filling behind abutment, wing wall and return
IRC:78 & wall complete as per drawing and Technical
2200 Specification
Unit = cum
Taking output = 10 cum
A Granular material
a) Labour
Mate day 0.280 0.280 0.280 617.00 172.76 172.76 172.76 L-12
Mazdoor day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
b) Material
Granular material cum 12.000 12.000 12.000 1,887.12 22,645.48 22,645.48 22,645.48 M-009
c) Machinery
Plate compactor/power rammer hour 2.500 2.500 2.500 597.45 1,493.63 1,493.63 1,493.63 P&M-079
Water Tanker hour 0.050 0.050 0.050 1,005.00 50.25 50.25 50.25 P&M-025
@ 20% on @ 20% on @ 20% on
d) Overhead charges 5,588.55 5,588.55 5,588.55
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 3,353.13 3,353.13 3,353.13
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 10 cum of granular backfill = a+b+c+d+e 36,884.43 36,884.43 36,884.43


Rate per cum = (a+b+c+d+e)/10 3,688.44 3,688.44 3,688.44
Say 3,688.00 3,688.00 3,688.00
13.09 B Sandy material
a) Labour
Mate day 0.280 0.280 0.280 617.00 172.76 172.76 172.76 L-12
Mazdoor for filling, watering, ramming etc. day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
b) Material
Sand cum 12.000 12.000 12.000 1,544.03 18,528.37 18,528.37 18,528.37 M-006
c) Machinery
Plate compactor/power rammer hour 2.500 2.500 2.500 597.45 1,493.63 1,493.63 1,493.63 P&M-079
Water Tanker hour 0.060 0.060 0.060 1,005.00 60.30 60.30 60.30 P&M-025
@ 20% on @ 20% on @ 20% on
d) Overhead charges 4,767.14 4,767.14 4,767.14
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 2,860.28 2,860.28 2,860.28
(a+b+c+d) (a+b+c+d) (a+b+c+d)

Cost for 10 cum of sandy backfill = a+b+c+d+e 31,463.12 31,463.12 31,463.12


Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Rate per cum = (a+b+c+d+e)/10 3,146.31 3,146.31 3,146.31
Say 3,146.00 3,146.00 3,146.00
13.10 710.1.4.of
IRC:78
and Providing and laying of Filter media with granular
2504.2 materials/stone crushed aggregates satisfying the
requirements laid down in clause 2504.2.2. of
MoRTH specifications to a thickness of not less
than 600 mm with smaller size towards the soil and
bigger size towards the wall and provided over the
entire surface behind abutment, wing wall and
return wall to the full height compacted to a firm
condition complete as per drawing and Technical
Specification.

Unit = cum
Taking output = 10 cum.
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mazdoor for filling, watering, ramming etc. day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
Mazdoor (Skilled) day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
b) Material
Filter media of stone aggregate conforming to M-011
cum 12.000 12.000 12.000 1,215.07 14,580.87 14,580.87 14,580.87
clause 2504.2.2. of MoRTH specifications.
c) Machinery
Water Tanker of 6 KL capacity hour 0.060 0.060 0.060 1,005.00 60.30 60.30 60.30 P&M-025
@ 20% on @ 20% on @ 20% on
d) Overhead charges 3,797.00 3,797.00 3,797.00
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 2,278.20 2,278.20 2,278.20
(a+b+c+d) (a+b+c+d) (a+b+c+d)
cost for 10 cum of Fiter Media = a+b+c+d+e 25,060.18 25,060.18 25,060.18
Rate per cum = (a+b+c+d+e)/10 2,506.02 2,506.02 2,506.02
Say 2,506.00 2,506.00 2,506.00
13.11 704

Supplying & laying of drainage composite for use


behind walls, between two different fills, alongside
drains of road, below concrete lining of canals etc.
Geocomposite for planar drainage, realized by
thermobonding a draining core in extruded
monofilaments with two filtering nonwoven
geotextiles that may also be working as separation
or protecting layers. The draining three
dimensional core will have a “W” configuration as
longitudinal parallel channels. Minimum thickness
to be 7.2mm, with two filtering UV stabilized
polypropylene nonwoven geotextile of minimum
thickness of 0.75 mm having pores of 150 micron
and tensile strength of 8.0 kN/m that will be
working as separation or protecting layer,
geocomposite having in plane flow capacity of 2.1
L / (m.s) at hydraulic gradient of 1.0 & 20 kpa
pressure and tensile strength of 18 kN/m , with
mass per unit area of 740 gsm, supplied in the
form of roll for easy transportation to site of work as
per detailed specification all complete as per
directions of Engineer in charge.

Unit = Sqm
Taking output 300 Sqm

a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Mazdoor (Skilled ) day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Material
Geosynthetic Drainage Composite sqm 300.000 300.000 300.000 175.00 52,500.00 52,500.00 52,500.00 M-290

Add 10 per cent of the cost of synthetic Composits


for wastage and accessories for joining sheets with
the facia pannels, overlaps and other protective
5,250.00 5,250.00 5,250.00
elements for synthetic Composits and other
miscelleneus activities required to complete the
item in all respect including transpotarion & takes.

@ 20% on @ 20% on @ 20% on


c) Overhead charges 12,107.88 12,107.88 12,107.88
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 7,264.73 7,264.73 7,264.73
(a+b+c) (a+b+c) (a+b+c)
Cost for 300 sqm = a+b+c+d 79,912.03 79,912.03 79,912.03
Rate per sqm = (a+b+c+d)/300 266.37 266.37 266.37
Say 266.00 266.00 266.00
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
13.12 704

Supplying & laying of drainage composite for use


behind walls, between two different fills, alongside
drains of road, below concrete lining of canals etc.
having thermobonding a draining core - HDPE
geonet comprises of two sets of parallel overlayed
ribs integrally connected to have a rhomboidal
shape with a polyethylene film and a nonwoven
geotextile having mass per unit area 130 g/m2 and
tensile strength of 8.0 kN/m that will be working as
separation or protecting layer, geocomposite
having in plane flow capacity of 0.7 L / (m.s) at
hydraulic gradient of 1.0 & 20 kPa pressure and
tensile strength of 13.5 kN/ m , with mass per unit
area of 830 gsm, at easily accessible location
including top and bottom, with all leads and lifts,
manpower and machinery, materials, labour etc.
complete and as directed by Engineer - In -
Charge.

Unit = Sqm
Taking output 300 Sqm
a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Mazdoor (Skilled ) day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Material
Geosynthetic Drainage Composite sqm 300.000 300.000 300.000 150.00 45,000.00 45,000.00 45,000.00 M-291

Add 10 per cent of the cost of synthetic Composits


for wastage and accessories for joining sheets with
the facia pannels, overlaps and other protective
4,500.00 4,500.00 4,500.00
elements for synthetic Composits and other
miscelleneus activities required to complete the
item in all respect including transpotarion & takes.

@ 20% on @ 20% on @ 20% on


c) Overhead charges 10,457.88 10,457.88 10,457.88
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 6,274.73 6,274.73 6,274.73
(a+b+c) (a+b+c) (a+b+c)
Cost for sqm = a+b+c+d 69,022.03 69,022.03 69,022.03
Rate per sqm = (a+b+c+d)/ 230.07 230.07 230.07
Say 230.00 230.00 230.00

13.13 2000,
1000 & Supplying, fitting and fixing in position true to line
2200 and level cast steel rocker bearing conforming to
IRC: 83(Pt.-1) section IX and clause 2003 of
MoRTH specifications complete including all
accessories as per drawing and Technical
Specifications.

Unit: one tonne capacity


Considering a 250 tonne capacity bearing for this
analysis
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Mazdoor (Skilled) day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Material
M-065
Cast steel rocker bearing assembly of 250 tonne
design load capacity duly painted complete with all each. 1.000 1.000 1.000 55,660.00 55,660.00 55,660.00 55,660.00
its components as per drawing and specifications

Add 1 per cent of cost of bearing assembly for


foundation anchorage bolts, lifting arrangements, 556.60 556.60 556.60
grease and other consumables.

@ 20% on @ 20% on @ 20% on


c) Overhead charges 11,409.60 11,409.60 11,409.60
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 6,845.76 6,845.76 6,845.76
(a+b+c) (a+b+c) (a+b+c)

cost for 250 tonnes capacity bearing = a+b+c+d 75,303.37 75,303.37 75,303.37
Rate per tonne capacity = (a+b+c+d)/250 301.21 301.21 301.21
Say 301.00 301.00 301.00
13.14 2000 ,
1000 & Supplying, fitting and fixing in position true to line
2200 and level forged steel roller bearing conforming to
IRC: 83(Pt.-1) section IX and clause 2003 of
MoRTH specifications complete including all
accessories as per drawing and Technical
Specifications.

Unit: one tonne capacity


Considering a 250 tonne capacity bearing for this
analysis
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Mazdoor (Skilled) day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
b) Material
M-067
Forged steel roller bearing of 250 tonne design
load capacity duly painted complete with all its each. 1.000 1.000 1.000 85,008.00 85,008.00 85,008.00 85,008.00
components as per drawing and specifications

Add 1 per cent of cost of bearing assembly for


foundation anchorage bolts, lifting arrangements, 850.08 850.08 850.08
grease and other consumables.

@ 20% on @ 20% on @ 20% on


c) Overhead charges 17,337.90 17,337.90 17,337.90
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 10,402.74 10,402.74 10,402.74
(a+b+c) (a+b+c) (a+b+c)

cost for 250 tonnes capacity bearing = a+b+c+d 114,430.12 114,430.12 114,430.12
Rate per tonne capacity = (a+b+c+d)/250 457.72 457.72 457.72
Say 458.00 458.00 458.00
13.15 2000 &
Supplying, fitting and fixing in position true to line
2200
and level sliding plate bearing with PTFE surface
sliding on stainless steel complete including all
accessories as per drawing and Technical
Specifications and BS: 5400, section 9.1 & 9.2 (for
PTFE) and clause 2004 of MoRTH
Specifications.
Unit: one tonne capacity
Considering a 80 tonne capacity bearing for this
analysis
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
Mazdoor (Skilled) day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
b) Material
PTFE sliding plate bearing assembly of 80 tonnes M-069
design load capacity duly painted complete with all
each. 1.000 1.000 1.000 34,788.00 34,788.00 34,788.00 34,788.00
its components as per drawing and Technical
Specifications
Add 1 per cent for foundation anchorage bolts and
347.88 347.88 347.88
consumables.
@ 20% on @ 20% on @ 20% on
c) Overhead charges 7,193.46 7,193.46 7,193.46
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 4,316.07 4,316.07 4,316.07
(a+b+c) (a+b+c) (a+b+c)

cost for 80 tonnes capacity bearing = a+b+c+d 47,476.82 47,476.82 47,476.82


Rate per tonne capacity = (a+b+c+d)/80 593.46 593.46 593.46
Say 593.00 593.00 593.00
13.16 2000 &
2200 Supplying, fitting and fixing in position true to line
and level elastomeric bearing conforming to IRC:
83 (Part-II) section IX and clause 2005 of MoRTH
specifications complete including all accessories as
per drawing and Technical Specifications.

Unit: one cubic centimetre


Considering an elastomeric bearing of size 500 x
400 x 96 mm for this analysis.
Overall volume - 19200 cu.cm
Volume of 6 nos. 488 x 388 x 4 mm size reinforcing
steel plates = 4545 cu.cm.

Hence volume of elastometer = 14655 cu.cm.


a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
Mazdoor (Skilled) day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
b) Material
M-066
Elastomeric bearing assembly consisting of 7
layers of elastomer bonded to 6 nos. internal
reinforcing steel laminates by the process of each. 1.000 1.000 1.000 12,915.00 12,915.00 12,915.00 12,915.00
vulcanisation, complete with all components as per
drawing and Technical Specifications.

Add 1 per cent of cost of bearing assembly for


129.15 129.15 129.15
foundation anchorage bolts and consumables.

@ 20% on @ 20% on @ 20% on


c) Overhead charges 2,775.11 2,775.11 2,775.11
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 1,665.07 1,665.07 1,665.07
(a+b+c) (a+b+c) (a+b+c)

cost for 19200cc of elastomeric bearing = a+b+c+d 18,315.73 18,315.73 18,315.73

Rate per cc of elastomeric bearing =


0.95 0.95 0.95
(a+b+c+d)/19200
Say 1.00 1.00 1.00
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
13.17 2000 &
2200 Supplying, fitting and fixing in position true to line
and level sliding plate bearing with stainless steel
plate sliding on stainless steel plate with mild steel
matrix complete including all accessories as per
drawing and Technical Specifications.

Unit: one tonne capacity


Considering the sliding bearing of 80 tonnes
design capacity for this analysis.
a) Labour
Mate day 0.044 0.044 0.044 617.00 27.15 27.15 27.15 L-12
Mazdoor day 0.750 0.750 0.750 511.52 383.64 383.64 383.64 L-13
Mazdoor (Skilled) day 0.350 0.350 0.350 565.73 198.01 198.01 198.01 L-15
b) Material
Supply of sliding plate bearing of 80 tonne design M-070
capacity complete as per drawings and Technical each. 1.000 1.000 1.000 34,420.00 34,420.00 34,420.00 34,420.00
Specifications.

Add 1 per cent of cost of bearing assembly for


344.20 344.20 344.20
foundation anchorage bolts and consumables.

@ 20% on @ 20% on @ 20% on


c) Overhead charges 7,074.60 7,074.60 7,074.60
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 4,244.76 4,244.76 4,244.76
(a+b+c) (a+b+c) (a+b+c)

cost for 80 tonnes of capacity bearing = a+b+c+d 46,692.35 46,692.35 46,692.35


583.65 583.65 583.65
Say 584.00 584.00 584.00
13.18 2000 &
2200
Supplying, fitting and fixing in position true to line
and level POT-PTFE bearing consisting of a metal
piston supported by a disc or unreinforced
elastomer confined within a metal cylinder, sealing
rings, dust seals, PTFE surface sliding against
stainless steel mating surface, complete assembly
to be of cast steel/fabricated structural steel, metal
and elastomer elements to be as per IRC: 83 part-I
& II respectively and other parts conforming to BS:
5400, section 9.1 & 9.2 and clause 2006 of MoRTH
Specifications complete as per drawing and
approved Technical Specifications.

Unit: one tonne capacity


Considering a Pot bearing assembly of 250 tonne
capacity for this analysis.
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 1.500 1.500 1.500 511.52 767.28 767.28 767.28 L-13
Mazdoor (Skilled) day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
b) Material
M-068
Pot type bearing assembly consisting of a metal
piston supported by a disc, PTFE pads providing
sliding surfaces against stainless steel mating
together with cast steel assemblies/fabricated each. 1.000 1.000 1.000 34,165.00 34,165.00 34,165.00 34,165.00
structural steel assemblies duly painted with all
components as per clause 2006 and complete as
per drawings and Technical Specifications.

Add 1 per cent of cost of bearing assembly for


341.65 341.65 341.65
foundation anchorage bolts and consumables.

@ 20% on @ 20% on @ 20% on


c) Overhead charges 7,121.23 7,121.23 7,121.23
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 4,272.74 4,272.74 4,272.74
(a+b+c) (a+b+c) (a+b+c)

cost for 250 tonnes capacity bearing = a+b+c+d 47,000.12 47,000.12 47,000.12
Rate per tonne capacity = (a+b+c+d)/250 188.00 188.00 188.00
Say 188.00 188.00 188.00
13.19 Protection to substructure by using coal tar epoxy

Providing and applying two coats of Two


component, high build, 100 % solid content, low
VOC,, polycyclin aromatic hydrocarbon based, Pot
life – 2 hrs @ 72 deg. F , Tack free – 4-6 hrs , DFT
per coat 80 -120 microns (dry) coal tar epoxy
coating with Coal tar
Unit = Sqm
Taking output = 100.00 Sqm
a) Labour
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Painter day 6.000 6.000 6.000 679.00 4,074.00 4,074.00 4,074.00 L-18
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Material

Coal Tar Epoxy coating @0.5 Kg per Square Meter


Kg 52.500 52.500 52.500 378.00 19,845.00 19,845.00 19,845.00 M-098
coverage including 5% wastage
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Add 1 Percent of cost of abs towards
256.76 256.76 256.76
miscellaneous (water, painting brush etc.).
@ 20% on @ 20% on @ 20% on
c) Overhead charges 5,186.49 5,186.49 5,186.49
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 3,111.89 3,111.89 3,111.89
(a+b+c) (a+b+c) (a+b+c)
cost for 100 sqm. = a+b+c+d 34,230.82 34,230.82 34,230.82
Rate per sqm = (a+b+c+d)/100 342.31 342.31 342.31
Say 342.00 342.00 342.00
Providing structural steel for sub-structure
13.20 complete as per drawing and technical
specifications
Unit = MT
Taking output = 10.00 MT
a) Material
Structural steel in plates, angles, etc including 5 M-181
tonne 10.500 10.500 10.500 63,806.54 669,968.72 669,968.72 669,968.72
per cent wastage
Nuts & bolts Kg 105.000 105.000 105.000 64.83 6,806.84 6,806.84 6,806.84 M-129
b) Labour
(for cutting, bending, making holes, joining, welding
and erecting in position)
Mate day 12.312 12.312 12.312 617.00 7,596.50 7,596.50 7,596.50 L-12
Fitter day 45.000 45.000 45.000 738.00 33,210.00 33,210.00 33,210.00 L-08
Blacksmith day 45.000 45.000 45.000 738.00 33,210.00 33,210.00 33,210.00 L-08
Welder day 45.000 45.000 45.000 738.00 33,210.00 33,210.00 33,210.00 L-02
Painter I Class day 18.900 18.900 18.900 679.00 12,833.10 12,833.10 12,833.10 L-18
Mazdoor day 153.900 153.900 153.900 511.52 78,722.93 78,722.93 78,722.93 L-13

Electrodes, cutting gas and other consumables @


67,677.56 67,677.56 67,677.56
10 per cent of cost of (a) above
c) Machinery
Mobile hydraulic cran 10 tonne capacity (for
Hrs 40.000 40.000 40.000 1,240.05 49,602.00 49,602.00 49,602.00 P&M-104
fabrication)
Crane 35 tonne capacity (For loading & unloading
Hrs 2.000 2.000 2.000 2,394.00 4,788.00 4,788.00 4,788.00 P&M-107
@ 1hr for each operation)
Crane 35 tonne capacity (Forlifting and placing in
Hrs 2.000 2.000 2.000 2,394.00 4,788.00 4,788.00 4,788.00 P&M-107
position @ 2 hr)

Trailer 30 tonne capacity for transporting to site Hrs 2+L/15 2+L/15 2+L/15 2,883.30 11,533.20 11,533.20 11,533.20 P&M-014

Applying two coats primer before painting of truss


lits 525.000 525.000 525.000 288.00 151,200.00 151,200.00 151,200.00 M-145
and girder (42sqm/tonne)
Painting of Truss and Girder lits 525.000 525.000 525.000 180.70 94,867.50 94,867.50 94,867.50 M-058
Sundries @3% of above 2,846.03 2,846.03 2,846.03
Basic Cost of Labour, Material & Machinery
126287.000 126287.000 126287.000
(a+b+c) for 1 MT

@ 20% on @ 20% on @ 20% on


d) Overhead charges 252,572.07 252,572.07 252,572.07
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 151,543.24 151,543.24 151,543.24
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 1 MT (a+b+c+d+e) 1,666,975.68 1,666,975.68 1,666,975.68
Rate for per MT (a+b+c+d+e) 166,697.57 166,697.57 166,697.57
Say 166,698.00 166,698.00 166,698.00
CHAPTER-14
SUPER-STRUCTURE
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
14.01 1500
&1600 Furnishing and Placing Reinforced/ Prestressed
1700 cement concrete in super-structure as per drawing
and Technical Specification

A RCC Grade M20


14.01A Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum
a) Material

Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 120.000 120.000 4,533.00 543,960.00 543,960.00 543,960.00
Concrete - 20.05

Water for curing Kl 63.000 63.000 63.000 16.00 1,008.00 1,008.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.192 0.192 0.192 617.00 118.46 118.46 118.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 3.300 3.300 3.300 511.52 1,688.02 1,688.02 1,688.02 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L1 lead in tonne-
300 x L 300 x L 300 x L 13.41 120,697.50 120,697.50 120,697.50 P&M-128
Kilometer km
For unloading hour 2.600 2.600 2.600 2,413.95 6,276.27 6,276.27 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 2.600 2.600 4,401.60 11,444.16 11,444.16 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
0.438XL1+2.62
(i) 16 KL capacity hour 1,501.00 23,663.27 P&M-023
5
0.583XL1+3.50
(ii) 12 KL capacity hour 1,327.00 27,853.73 P&M-024
0
1.167XL1+7.00
(iii) 6 KL capacity hour 1,005.00 42,220.05 P&M-025
0
Basic Cost of Labour, Material & Machinery (a+b+c)
709,875.00 714,065.00 728,431.00
for 120 cum
For formwork and staging add the following:
14.01 A (i) For solid slab super-structure, 20-30 per cent of
(a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
709,875.00 714,065.00 728,431.00
for 120 cum

d) Formwork and staging 20 per cent of (a+b+c) 20.000 141,975.00 142,813.00 145,686.20

@ 20% on @ 20% on @ 20% on


e) Overhead charges 170,370.00 171,375.60 174,823.44
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 102,222.00 102,825.36 104,894.06
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,124,442.00 1,131,078.96 1,153,834.70
Rate per cum = (a+b+c+d+e+f)/120 9,370.35 9,425.66 9,615.29
Say 9,370.00 9,426.00 9,615.00
14.01 A (q) Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
709,875.00 714,065.00 728,431.00
for 120 cum

d) Formwork and staging 25 per cent of (a+b+c) 25.000 177,468.75 178,516.25 182,107.75

@ 20% on @ 20% on @ 20% on


e) Overhead charges 177,468.75 178,516.25 182,107.75
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 106,481.25 107,109.75 109,264.65
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,171,293.75 1,178,207.25 1,201,911.15
Rate per cum = (a+b+c+d+e+f)/120 9,760.78 9,818.39 10,015.93
Say 9,761.00 9,818.00 10,016.00
'14.01 A (r) Height above 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
709,875.00 714,065.00 728,431.00
for 120 cum

d) Formwork and staging 30 per cent of (a+b+c) 30.000 212,962.50 214,219.50 218,529.30

@ 20% on @ 20% on @ 20% on


e) Overhead charges 184,567.50 185,656.90 189,392.06
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 110,740.50 111,394.14 113,635.24
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,218,145.50 1,225,335.54 1,249,987.60
Rate per cum = (a+b+c+d+e+f)/120 10,151.21 10,211.13 10,416.56
Say 10,151.00 10,211.00 10,417.00
14.01 A (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
709,875.00 714,065.00 728,431.00
for 120 cum

d) Formwork and staging 25 per cent of (a+b+c) 25.000 177,468.75 178,516.25 182,107.75

@ 20% on @ 20% on @ 20% on


e) Overhead charges 177,468.75 178,516.25 182,107.75
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 106,481.25 107,109.75 109,264.65
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,171,293.75 1,178,207.25 1,201,911.15
Rate per cum = (a+b+c+d+e+f)/120 9,760.78 9,818.39 10,015.93
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Say 9,761.00 9,818.00 10,016.00
14.01 A (q) Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
709,875.00 714,065.00 728,431.00
for 120 cum

d) Formwork and staging 30 per cent of (a+b+c) 30.000 212,962.50 214,219.50 218,529.30

@ 20% on @ 20% on @ 20% on


e) Overhead charges 184,567.50 185,656.90 189,392.06
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 110,740.50 111,394.14 113,635.24
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,218,145.50 1,225,335.54 1,249,987.60
Rate per cum = (a+b+c+d+e+f)/120 10,151.21 10,211.13 10,416.56
Say 10,151.00 10,211.00 10,417.00
14.01A (r)
(ii) Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


709,875.00 714,065.00 728,431.00
for 120 cum

d) Formwork and staging 35 per cent of (a+b+c) 35.000 248,456.25 249,922.75 254,950.85

@ 20% on @ 20% on @ 20% on


e) Overhead charges 191,666.25 192,797.55 196,676.37
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 114,999.75 115,678.53 118,005.82
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,264,997.25 1,272,463.83 1,298,064.04
Rate per cum = (a+b+c+d+e+f)/120 10,541.64 10,603.87 10,817.20
Say 10,542.00 10,604.00 10,817.00
14.01 B RCC Grade M25
14.01B Case Using Batching Plant, Transit Mixer and Concrete
II Pump
Unit = cum
Taking output = 120 cum
a) Material

Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 120.000 120.000 4,945.00 593,400.00 593,400.00 593,400.00
Concrete - 20.07

Water for curing Kl 63.000 63.000 63.000 16.00 1,008.00 1,008.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.192 0.192 0.192 617.00 118.46 118.46 118.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 3.300 3.300 3.300 511.52 1,688.02 1,688.02 1,688.02 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-
300 x L 300 x L 301 x L 13.41 120,697.50 120,697.50 120,697.50 P&M-128
Kilometer km
For unloading hour 2.600 2.600 2.600 2,413.95 6,276.27 6,276.27 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 2.600 2.600 4,401.60 11,444.16 11,444.16 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
0.438XL1+2.62
(i) 16 KL capacity hour 1,501.00 23,663.27 P&M-023
5
0.583XL1+3.50
(ii) 12 KL capacity hour 1,327.00 27,853.73 P&M-024
0
1.167XL1+7.00
(iii) 6 KL capacity hour 1,005.00 42,220.05 P&M-025
0
Basic Cost of Labour, Material & Machinery (a+b+c)
759,315.00 763,505.00 777,871.00
for 120 Cum
For formwork and staging add the following:
14.01B (i) For solid slab super-structure, 20-30 per cent of
(a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
759,315.00 763,505.00 777,871.00
for 120 cum

d) Formwork and staging 20 per cent of (a+b+c) 20.000 151,863.00 152,701.00 155,574.20

@ 20% on @ 20% on @ 20% on


e) Overhead charges 182,235.60 183,241.20 186,689.04
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 109,341.36 109,944.72 112,013.42
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,202,754.96 1,209,391.92 1,232,147.66
Rate per cum = (a+b+c+d+e+f)/120 10,022.96 10,078.27 10,267.90
Say 10,023.00 10,078.00 10,268.00
14.01B (q)
(i) Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


759,315.00 763,505.00 777,871.00
for 120 cum

d) Formwork and staging 25 per cent of (a+b+c) 25.000 189,828.75 190,876.25 194,467.75

@ 20% on @ 20% on @ 20% on


e) Overhead charges 189,828.75 190,876.25 194,467.75
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 113,897.25 114,525.75 116,680.65
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,252,869.75 1,259,783.25 1,283,487.15
Rate per cum = (a+b+c+d+e+f)/120 10,440.58 10,498.19 10,695.73
Say 10,441.00 10,498.00 10,696.00
14.01B (r)
Height above 10m
(i)
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Basic Cost of Labour, Material & Machinery (a+b+c)
759,315.00 763,505.00 777,871.00
for 120 cum

d) Formwork and staging 30 per cent of (a+b+c) 30.000 227,794.50 229,051.50 233,361.30

@ 20% on @ 20% on @ 20% on


e) Overhead charges 197,421.90 198,511.30 202,246.46
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 118,453.14 119,106.78 121,347.88
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,302,984.54 1,310,174.58 1,334,826.64
Rate per cum = (a+b+c+d+e+f)/120 10,858.20 10,918.12 11,123.56
Say 10,858.00 10,918.00 11,124.00
14.01B (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
759,315.00 763,505.00 777,871.00
for 120 cum

d) Formwork and staging 25 per cent of (a+b+c) 25.000 189,828.75 190,876.25 194,467.75

@ 20% on @ 20% on @ 20% on


e) Overhead charges 189,828.75 190,876.25 194,467.75
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 113,897.25 114,525.75 116,680.65
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,252,869.75 1,259,783.25 1,283,487.15
Rate per cum = (a+b+c+d+e+f)/120 10,440.58 10,498.19 10,695.73
Say 10,441.00 10,498.00 10,696.00
14.01B (q)
(ii) Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


759,315.00 763,505.00 777,871.00
for 120 cum

d) Formwork and staging 30 per cent of (a+b+c) 30.000 227,794.50 229,051.50 233,361.30

@ 20% on @ 20% on @ 20% on


e) Overhead charges 197,421.90 198,511.30 202,246.46
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 118,453.14 119,106.78 121,347.88
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,302,984.54 1,310,174.58 1,334,826.64
Rate per cum = (a+b+c+d+e+f)/120 10,858.20 10,918.12 11,123.56
Say 10,858.00 10,918.00 11,124.00
14.01B (r)
(ii) Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


759,315.00 763,505.00 777,871.00
for 120 cum

d) Formwork and staging 35 per cent of (a+b+c) 35.000 265,760.25 267,226.75 272,254.85

@ 20% on @ 20% on @ 20% on


e) Overhead charges 205,015.05 206,146.35 210,025.17
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 123,009.03 123,687.81 126,015.10
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,353,099.33 1,360,565.91 1,386,166.12
Rate per cum = (a+b+c+d+e+f)/120 11,275.83 11,338.05 11,551.38
Say 11,276.00 11,338.00 11,551.00
14.01 C RCC Grade M 30
14.01C Using Batching Plant, Transit Mixer and Concrete
Pump.
Unit = cum
Taking output = 120 cum
a) Material

Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 120.000 120.000 5,032.00 603,840.00 603,840.00 603,840.00
Concrete - 20.09

Water for curing Kl 63.000 63.000 63.000 16.00 1,008.00 1,008.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.192 0.192 0.192 617.00 118.46 118.46 118.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 3.300 3.300 3.300 511.52 1,688.02 1,688.02 1,688.02 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-
300 x L 300 x L 301 x L 13.41 120,697.50 120,697.50 120,697.50 P&M-128
Kilometer km
For unloading hour 2.600 2.600 2.600 2,413.95 6,276.27 6,276.27 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 2.600 2.600 4,401.60 11,444.16 11,444.16 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
0.438XL1+2.62
(i) 16 KL capacity hour 1,501.00 23,663.27 P&M-023
5
0.583XL1+3.50
(ii) 12 KL capacity hour 1,327.00 27,853.73 P&M-024
0
1.167XL1+7.00
(iii) 6 KL capacity hour 1,005.00 42,220.05 P&M-025
0
Basic Cost of Labour, Material & Machinery (a+b+c)
769,754.18 773,944.64 788,310.96
for 120 Cum
For formwork and staging add the following:
14.01C (i) For solid slab super-structure, 20-30 per cent of
(a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
769,754.18 773,944.64 788,310.96
for 120 cum
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project

d) Formwork and staging 20 per cent of (a+b+c) 20.000 153,950.84 154,788.93 157,662.19

@ 20% on @ 20% on @ 20% on


e) Overhead charges 184,741.00 185,746.71 189,194.63
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 110,844.60 111,448.03 113,516.78
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,219,290.61 1,225,928.31 1,248,684.56
Rate per cum = (a+b+c+d+e+f)/120 10,160.76 10,216.07 10,405.70
Say 10,161.00 10,216.00 10,406.00
14.01C (q)
(i) Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


769,754.18 773,944.64 788,310.96
for 120 cum

d) Formwork and staging 25 per cent of (a+b+c) 25.000 192,438.54 193,486.16 197,077.74

@ 20% on @ 20% on @ 20% on


e) Overhead charges 192,438.54 193,486.16 197,077.74
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 115,463.13 116,091.70 118,246.64
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,270,094.39 1,277,008.66 1,300,713.08
Rate per cum = (a+b+c+d+e+f)/120 10,584.12 10,641.74 10,839.28
Say 10,584.00 10,642.00 10,839.00
14.01C (r)
(i) Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


769,754.18 773,944.64 788,310.96
for 120 cum

d) Formwork and staging 30 per cent of (a+b+c) 30.000 230,926.25 232,183.39 236,493.29

@ 20% on @ 20% on @ 20% on


e) Overhead charges 200,136.09 201,225.61 204,960.85
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 120,081.65 120,735.36 122,976.51
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
1,320,898.16 1,328,089.00 1,352,741.61
Rate per cum = (a+b+c+d+e+f)/120 11,007.48 11,067.41 11,272.85
Say 11,007.00 11,067.00 11,273.00
14.01C (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
769,754.18 773,944.64 788,310.96
for 120 cum

d) Formwork and staging 25 per cent of (a+b+c) 25.000 192,438.54 193,486.16 197,077.74

@ 20% on @ 20% on @ 20% on


e) Overhead charges 192,438.54 193,486.16 197,077.74
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 115,463.13 116,091.70 118,246.64
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,270,094.39 1,277,008.66 1,300,713.08
Rate per cum = (a+b+c+d+e+f)/120 10,584.12 10,641.74 10,839.28
Say 10,584.00 10,642.00 10,839.00
14.01C (q)
(ii) Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


769,754.18 773,944.64 788,310.96
for 120 cum

d) Formwork and staging 30 per cent of (a+b+c) 30.000 230,926.25 232,183.39 236,493.29

@ 20% on @ 20% on @ 20% on


e) Overhead charges 200,136.09 201,225.61 204,960.85
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 120,081.65 120,735.36 122,976.51
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,320,898.16 1,328,089.00 1,352,741.61
Rate per cum = (a+b+c+d+e+f)/120 11,007.48 11,067.41 11,272.85
Say 11,007.00 11,067.00 11,273.00
14.01C (r)
(ii) Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


769,754.18 773,944.64 788,310.96
for 120 cum

d) Formwork and staging 35 per cent of (a+b+c) 35.000 269,413.96 270,880.62 275,908.84

@ 20% on @ 20% on @ 20% on


e) Overhead charges 207,833.63 208,965.05 212,843.96
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 124,700.18 125,379.03 127,706.38
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,371,701.94 1,379,169.35 1,404,770.13
Rate per cum = (a+b+c+d+e+f)/120 11,430.85 11,493.08 11,706.42
Say 11,431.00 11,493.00 11,706.00
14.01 D RCC/PSC Grade M35
Case Using Batching Plant, Transit Mixer and Concrete
II Pump
Unit = cum
Taking output = 120 cum 120 cum
a) Material

Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 120.000 120.000 5,186.00 622,320.00 622,320.00 622,320.00
Concrete - 20.11

Water for curing Kl 63.000 63.000 63.000 16.00 1,008.00 1,008.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.192 0.192 0.192 617.00 118.46 118.46 118.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Mazdoor day 3.300 3.300 3.300 511.52 1,688.02 1,688.02 1,688.02 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-
300 x L 300 x L 300 x L 13.41 120,697.50 120,697.50 120,697.50 P&M-128
Kilometer km
For unloading hour 2.600 2.600 2.600 2,413.95 6,276.27 6,276.27 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 2.600 2.600 4,401.60 11,444.16 11,444.16 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
0.438XL1+2.62
(i) 16 KL capacity hour 1,501.00 23,663.27 P&M-023
5
0.583XL1+3.50
(ii) 12 KL capacity hour 1,327.00 27,853.73 P&M-024
0
1.167XL1+7.00
(iii) 6 KL capacity hour 1,005.00 42,220.05 P&M-025
0
Basic Cost of Labour, Material & Machinery (a+b+c)
788,235.00 792,425.00 806,791.00
for 120 Cum
For formwork and staging add the following:
14.01D (i) For solid slab super-structure, 18-28 per cent of
(a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
788,235.00 792,425.00 806,791.00
for 120 cum

d) Formwork and staging 18 per cent of (a+b+c) 18.000 141,882.30 142,636.50 145,222.38

@ 20% on @ 20% on @ 20% on


e) Overhead charges 186,023.46 187,012.30 190,402.68
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 111,614.08 112,207.38 114,241.61
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,227,754.84 1,234,281.18 1,256,657.66
Rate per cum = (a+b+c+d+e+f)/120 10,231.29 10,285.68 10,472.15
Say 10,231.00 10,286.00 10,472.00
14.01D (q)
(i) Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


788,235.00 792,425.00 806,791.00
for 120 cum

d) Formwork and staging 23 per cent of (a+b+c) 23.000 181,294.05 182,257.75 185,561.93

@ 20% on @ 20% on @ 20% on


e) Overhead charges 193,905.81 194,936.55 198,470.59
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 116,343.49 116,961.93 119,082.35
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,279,778.35 1,286,581.23 1,309,905.87
Rate per cum = (a+b+c+d+e+f)/120 10,664.82 10,721.51 10,915.88
Say 10,665.00 10,722.00 10,916.00
14.01D (r)
(i) Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


788,235.00 792,425.00 806,791.00
for 120 cum

d) Formwork and staging 28 per cent of (a+b+c) 28.000 220,705.80 221,879.00 225,901.48

@ 20% on @ 20% on @ 20% on


e) Overhead charges 201,788.16 202,860.80 206,538.50
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 121,072.90 121,716.48 123,923.10
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,331,801.86 1,338,881.28 1,363,154.07
Rate per cum = (a+b+c+d+e+f)/120 11,098.35 11,157.34 11,359.62
Say 11,098.00 11,157.00 11,360.00
14.01D (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
788,235.00 792,425.00 806,791.00
for 120 cum

d) Formwork and staging 23 per cent of (a+b+c) 23.000 181,294.05 182,257.75 185,561.93

@ 20% on @ 20% on @ 20% on


e) Overhead charges 193,905.81 194,936.55 198,470.59
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 116,343.49 116,961.93 119,082.35
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,279,778.35 1,286,581.23 1,309,905.87
Rate per cum = (a+b+c+d+e+f)/120 10,664.82 10,721.51 10,915.88
Say 10,665.00 10,722.00 10,916.00
14.01D (q)
(ii) Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


788,235.00 792,425.00 806,791.00
for 120 cum

d) Formwork and staging 28 per cent of (a+b+c) 28.000 220,705.80 221,879.00 225,901.48

@ 20% on @ 20% on @ 20% on


e) Overhead charges 201,788.16 202,860.80 206,538.50
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 121,072.90 121,716.48 123,923.10
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,331,801.86 1,338,881.28 1,363,154.07
Rate per cum = (a+b+c+d+e+f)/120 11,098.35 11,157.34 11,359.62
Say 11,098.00 11,157.00 11,360.00
14.01D (r)
(ii) Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


788,235.00 792,425.00 806,791.00
for 120 cum
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project

d) Formwork and staging 33 per cent of (a+b+c) 33.000 260,117.55 261,500.25 266,241.03

@ 20% on @ 20% on @ 20% on


e) Overhead charges 209,670.51 210,785.05 214,606.41
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 125,802.31 126,471.03 128,763.84
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,383,825.37 1,391,181.33 1,416,402.28
Rate per cum = (a+b+c+d+e+f)/120 11,531.88 11,593.18 11,803.35
Say 11,532.00 11,593.00 11,803.00
14.01D (iii) For box girder and balanced cantilever, 38-58 per
cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
788,235.00 792,425.00 806,791.00
for 120 cum

d) Formwork and staging 38 per cent of (a+b+c) 38.000 299,529.30 301,121.50 306,580.58

@ 20% on @ 20% on @ 20% on


e) Overhead charges 217,552.86 218,709.30 222,674.32
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 130,531.72 131,225.58 133,604.59
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,435,848.88 1,443,481.38 1,469,650.49
Rate per cum = (a+b+c+d+e+f)/120 11,965.41 12,029.01 12,247.09
Say 11,965.00 12,029.00 12,247.00
14.01D (q)
(iii) Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


788,235.00 792,425.00 806,791.00
for 120 cum

d) Formwork and staging 48 per cent of (a+b+c) 48.000 378,352.80 380,364.00 387,259.68

@ 20% on @ 20% on @ 20% on


e) Overhead charges 233,317.56 234,557.80 238,810.14
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 139,990.54 140,734.68 143,286.08
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,539,895.90 1,548,081.48 1,576,146.90
Rate per cum = (a+b+c+d+e+f)/120 12,832.47 12,900.68 13,134.56
Say 12,832.00 12,901.00 13,135.00
14.01D (r)
(iii) Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


788,235.00 792,425.00 806,791.00
for 120 cum

d) Formwork and staging 58 per cent of (a+b+c) 58.000 457,176.30 459,606.50 467,938.78

@ 20% on @ 20% on @ 20% on


e) Overhead charges 249,082.26 250,406.30 254,945.96
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 149,449.36 150,243.78 152,967.57
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,643,942.92 1,652,681.58 1,682,643.31
Rate per cum = (a+b+c+d+e+f)/120 13,699.52 13,772.35 14,022.03
Say 13,700.00 13,772.00 14,022.00
14.01 E RCC/PSC Grade M-40
14.01E Using Batching Plant, Transit Mixer and Concrete
Pump
Unit = cum
Taking output = 120 cum 120 cum
a) Material

Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 120.000 120.000 5,519.00 662,280.00 662,280.00 662,280.00
Concrete - 20.12

Water for curing Kl 63.000 63.000 63.000 16.00 1,008.00 1,008.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.192 0.192 0.192 617.00 118.46 118.46 118.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 3.300 3.300 3.300 511.52 1,688.02 1,688.02 1,688.02 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-
300 x L 300 x L 300 x L 13.41 120,697.50 120,697.50 120,697.50 P&M-128
Kilometer km
For unloading hour 2.600 2.600 2.600 2,413.95 6,276.27 6,276.27 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 2.600 2.600 4,401.60 11,444.16 11,444.16 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
0.438XL1+2.62
(i) 16 KL capacity hour 1,501.00 23,663.27 P&M-023
5
0.583XL1+3.50
(ii) 12 KL capacity hour 1,327.00 27,853.73 P&M-024
0
1.167XL1+7.00
(iii) 6 KL capacity hour 1,005.00 42,220.05 P&M-025
0
Basic Cost of Labour, Material & Machinery (a+b+c)
828,195.00 832,385.00 846,751.00
for 120 Cum
For formwork and staging add the following:
14.01E (i) For solid/voided slab super-structure, 18-28 per cent
of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
828,195.00 832,385.00 846,751.00
for 120 cum

d) Formwork and staging 18 per cent of (a+b+c) 18.000 149,075.10 149,829.30 152,415.18
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
@ 20% on @ 20% on @ 20% on
e) Overhead charges 195,454.02 196,442.86 199,833.24
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 117,272.41 117,865.72 119,899.94
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 1,289,996.53 1,296,522.88 1,318,899.36
Rate per cum = (a+b+c+d+e+f)/120 10,749.97 10,804.36 10,990.83
Say 10,750.00 10,804.00 10,991.00
14.01E (q)
(i) Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


828,195.00 832,385.00 846,751.00
for 120 cum

d) Formwork and staging 23 per cent of (a+b+c) 23.000 190,484.85 191,448.55 194,752.73

@ 20% on @ 20% on @ 20% on


e) Overhead charges 203,735.97 204,766.71 208,300.75
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 122,241.58 122,860.03 124,980.45
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,344,657.40 1,351,460.29 1,374,784.92
Rate per cum = (a+b+c+d+e+f)/120 11,205.48 11,262.17 11,456.54
Say 11,205.00 11,262.00 11,457.00
14.01E (r)
(i) Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


828,195.00 832,385.00 846,751.00
for 120 cum

d) Formwork and staging 28 per cent of (a+b+c) 28.000 231,894.60 233,067.80 237,090.28

@ 20% on @ 20% on @ 20% on


e) Overhead charges 212,017.92 213,090.56 216,768.26
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 127,210.75 127,854.34 130,060.95
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,399,318.27 1,406,397.70 1,430,670.49
Rate per cum = (a+b+c+d+e+f)/120 11,660.99 11,719.98 11,922.25
Say 11,661.00 11,720.00 11,922.00
14.01E (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
828,195.00 832,385.00 846,751.00
for 120 cum

d) Formwork and staging 23 per cent of (a+b+c) 23.000 190,484.85 191,448.55 194,752.73

@ 20% on @ 20% on @ 20% on


e) Overhead charges 203,735.97 204,766.71 208,300.75
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 122,241.58 122,860.03 124,980.45
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,344,657.40 1,351,460.29 1,374,784.92
Rate per cum = (a+b+c+d+e+f)/120 11,205.48 11,262.17 11,456.54
Say 11,205.00 11,262.00 11,457.00
14.01E (q)
(ii) Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


828,195.00 832,385.00 846,751.00
for 120 cum

d) Formwork and staging 28 per cent of (a+b+c) 28.000 231,894.60 233,067.80 237,090.28

@ 20% on @ 20% on @ 20% on


e) Overhead charges 212,017.92 213,090.56 216,768.26
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 127,210.75 127,854.34 130,060.95
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,399,318.27 1,406,397.70 1,430,670.49
Rate per cum = (a+b+c+d+e+f)/120 11,660.99 11,719.98 11,922.25
Say 11,661.00 11,720.00 11,922.00
14.01E (r)
(ii) Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


828,195.00 832,385.00 846,751.00
for 120 cum

d) Formwork and staging 33 per cent of (a+b+c) 33.000 273,304.35 274,687.05 279,427.83

@ 20% on @ 20% on @ 20% on


e) Overhead charges 220,299.87 221,414.41 225,235.77
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 132,179.92 132,848.65 135,141.46
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,453,979.14 1,461,335.11 1,486,556.06
Rate per cum = (a+b+c+d+e+f)/120 12,116.49 12,177.79 12,387.97
Say 12,116.00 12,178.00 12,388.00
14.01E (iii) For cast-in-situ box girder, segment construction and
balanced cantilever, 38-58 per cent of cost of
concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
828,195.00 832,385.00 846,751.00
for 120 cum

d) Formwork and staging 38 per cent of (a+b+c) 38.000 314,714.10 316,306.30 321,765.38

@ 20% on @ 20% on @ 20% on


e) Overhead charges 228,581.82 229,738.26 233,703.28
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 137,149.09 137,842.96 140,221.97
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,508,640.01 1,516,272.52 1,542,441.62
Rate per cum = (a+b+c+d+e+f)/120 12,572.00 12,635.60 12,853.68
Say 12,572.00 12,636.00 12,854.00
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
14.01E (q)
(iii) Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


828,195.00 832,385.00 846,751.00
for 120 cum

d) Formwork and staging 48 per cent of (a+b+c) 48.000 397,533.60 399,544.80 406,440.48

@ 20% on @ 20% on @ 20% on


e) Overhead charges 245,145.72 246,385.96 250,638.30
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 147,087.43 147,831.58 150,382.98
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,617,961.75 1,626,147.34 1,654,212.75
Rate per cum = (a+b+c+d+e+f)/120 13,483.01 13,551.23 13,785.11
Say 13,483.00 13,551.00 13,785.00
14.01E (r)
(iii) Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


828,195.00 832,385.00 846,751.00
for 120 cum

d) Formwork and staging 58 per cent of (a+b+c) 58.000 480,353.10 482,783.30 491,115.58

@ 20% on @ 20% on @ 20% on


e) Overhead charges 261,709.62 263,033.66 267,573.32
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 157,025.77 157,820.20 160,543.99
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,727,283.49 1,736,022.16 1,765,983.89
Rate per cum = (a+b+c+d+e+f)/120 14,394.03 14,466.85 14,716.53
Say 14,394.00 14,467.00 14,717.00
14.01F F RCC/PSC Grade M-45
Unit = 1 cum
Taking output = 120 cum 120 cum
a) Material

Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 120.000 120.000 5,663.00 679,560.00 679,560.00 679,560.00
Concrete - 20.13

Water for curing Kl 63.000 63.000 63.000 16.00 1,008.00 1,008.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.192 0.192 0.192 617.00 118.46 118.46 118.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 3.300 3.300 3.300 511.52 1,688.02 1,688.02 1,688.02 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-
300 x L 300 x L 300 x L 13.41 120,697.50 120,697.50 120,697.50 P&M-128
Kilometer km
For unloading hour 2.600 2.600 2.600 2,413.95 6,276.27 6,276.27 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 2.600 2.600 4,401.60 11,444.16 11,444.16 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
0.438XL1+2.62
(i) 16 KL capacity hour 1,501.00 23,663.27 P&M-023
5
0.583XL1+3.50
(ii) 12 KL capacity hour 1,327.00 27,853.73 P&M-024
0
1.167XL1+7.00
(iii) 6 KL capacity hour 1,005.00 42,220.05 P&M-025
0
Basic Cost of Labour, Material & Machinery (a+b+c)
845,475.00 849,665.00 864,031.00
for 120 Cum
For formwork and staging add the following:
14.01F (i) For solid slab/voided slab super-structure, 16-26 per
cent of cost of concrete (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
845,475.00 849,665.00 864,031.00
for 120 cum

d) Formwork and staging 16 per cent of (a+b+c) 16.000 135,276.00 135,946.40 138,244.96

@ 20% on @ 20% on @ 20% on


e) Overhead charges 196,150.20 197,122.28 200,455.19
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 117,690.12 118,273.37 120,273.12
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,294,591.32 1,301,007.05 1,323,004.27
Rate per cum = (a+b+c+d+e+f)/120 10,788.26 10,841.73 11,025.04
Say 10,788.00 10,842.00 11,025.00
14.01F (q)
(i) Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


845,475.00 849,665.00 864,031.00
for 120 cum

d) Formwork and staging 21 per cent of (a+b+c) 21.000 177,549.75 178,429.65 181,446.51

@ 20% on @ 20% on @ 20% on


e) Overhead charges 204,604.95 205,618.93 209,095.50
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 122,762.97 123,371.36 125,457.30
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,350,392.67 1,357,084.94 1,380,030.31
Rate per cum = (a+b+c+d+e+f)/120 11,253.27 11,309.04 11,500.25
Say 11,253.00 11,309.00 11,500.00
14.01F (r)
(i) Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


845,475.00 849,665.00 864,031.00
for 120 cum
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project

d) Formwork and staging 26 per cent of (a+b+c) 26.000 219,823.50 220,912.90 224,648.06

@ 20% on @ 20% on @ 20% on


e) Overhead charges 213,059.70 214,115.58 217,735.81
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 127,835.82 128,469.35 130,641.49
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,406,194.02 1,413,162.83 1,437,056.36
Rate per cum = (a+b+c+d+e+f)/120 11,718.28 11,776.36 11,975.47
Say 11,718.00 11,776.00 11,975.00
14.01F (ii)For T-beam & slab including launching of precast
girders by launching truss upto 40 m span, 21-31 per
cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
845,475.00 849,665.00 864,031.00
for 120 cum

d) Formwork and staging 21 per cent of (a+b+c) 21.000 177,549.75 178,429.65 181,446.51

@ 20% on @ 20% on @ 20% on


e) Overhead charges 204,604.95 205,618.93 209,095.50
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 122,762.97 123,371.36 125,457.30
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,350,392.67 1,357,084.94 1,380,030.31
Rate per cum = (a+b+c+d+e+f)/120 11,253.27 11,309.04 11,500.25
Say 11,253.00 11,309.00 11,500.00
14.01F (q)
(ii) Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


845,475.00 849,665.00 864,031.00
for 120 cum

d) Formwork and staging 26 per cent of (a+b+c) 26.000 219,823.50 220,912.90 224,648.06

@ 20% on @ 20% on @ 20% on


e) Overhead charges 213,059.70 214,115.58 217,735.81
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 127,835.82 128,469.35 130,641.49
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,406,194.02 1,413,162.83 1,437,056.36
Rate per cum = (a+b+c+d+e+f)/120 11,718.28 11,776.36 11,975.47
Say 11,718.00 11,776.00 11,975.00
14.01F (r)
(ii) Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


845,475.00 849,665.00 864,031.00
for 120 cum

d) Formwork and staging 31 per cent of (a+b+c) 31.000 262,097.25 263,396.15 267,849.61

@ 20% on @ 20% on @ 20% on


e) Overhead charges 221,514.45 222,612.23 226,376.12
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 132,908.67 133,567.34 135,825.67
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,461,995.37 1,469,240.72 1,494,082.41
Rate per cum = (a+b+c+d+e+f)/120 12,183.29 12,243.67 12,450.69
Say 12,183.00 12,244.00 12,451.00
14.01F (iii) For cast-in-situ box girder, segmental construction
and balanced cantilever, 36-56 per cent of cost of
concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
845,475.00 849,665.00 864,031.00
for 120 cum

d) Formwork and staging 36 per cent of (a+b+c) 36.000 304,371.00 305,879.40 311,051.16

@ 20% on @ 20% on @ 20% on


e) Overhead charges 229,969.20 231,108.88 235,016.43
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 137,981.52 138,665.33 141,009.86
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,517,796.72 1,525,318.61 1,551,108.45
Rate per cum = (a+b+c+d+e+f)/120 12,648.31 12,710.99 12,925.90
Say 12,648.00 12,711.00 12,926.00
14.01F (q)
(iii) Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


845,475.00 849,665.00 864,031.00
for 120 cum

d) Formwork and staging 46 per cent of (a+b+c) 46.000 388,918.50 390,845.90 397,454.26

@ 20% on @ 20% on @ 20% on


e) Overhead charges 246,878.70 248,102.18 252,297.05
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 148,127.22 148,861.31 151,378.23
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,629,399.42 1,637,474.39 1,665,160.54
Rate per cum = (a+b+c+d+e+f)/120 13,578.33 13,645.62 13,876.34
Say 13,578.00 13,646.00 13,876.00
14.1F (r)
(iii) Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


845,475.00 849,665.00 864,031.00
for 120 cum

d) Formwork and staging 56 per cent of (a+b+c) 56.000 473,466.00 475,812.40 483,857.36

@ 20% on @ 20% on @ 20% on


e) Overhead charges 263,788.20 265,095.48 269,577.67
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 158,272.92 159,057.29 161,746.60
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Cost for 120 cum = a+b+c+d+e+f 1,741,002.12 1,749,630.17 1,779,212.64
Rate per cum = (a+b+c+d+e+f)/120 14,508.35 14,580.25 14,826.77
Say 14,508.00 14,580.00 14,827.00
14.01 G PSC Grade M-50
Unit = 1 cum
Taking output = 120 cum 120 cum
a) Material

Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 120.000 120.000 6,242.00 749,040.00 749,040.00 749,040.00
Concrete - 20.14

Water for curing Kl 63.000 63.000 63.000 16.00 1,008.00 1,008.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.192 0.192 0.192 617.00 118.46 118.46 118.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 3.300 3.300 3.300 511.52 1,688.02 1,688.02 1,688.02 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-
300 x L 300 x L 300 x L 13.41 120,697.50 120,697.50 120,697.50 P&M-128
Kilometer km
For unloading hour 2.600 2.600 2.600 2,413.95 6,276.27 6,276.27 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 2.600 2.600 4,401.60 11,444.16 11,444.16 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
0.438XL1+2.62
(i) 16 KL capacity hour 1,501.00 23,663.27 P&M-023
5
0.583XL1+3.50
(ii) 12 KL capacity hour 1,327.00 27,853.73 P&M-024
0
1.167XL1+7.00
(iii) 6 KL capacity hour 1,005.00 42,220.05 P&M-025
0
Basic Cost of Labour, Material & Machinery (a+b+c)
914,955.00 919,145.00 933,511.00
for 120 Cum
For formwork and staging add the following:
14.01G (i) For cast-in-situ box girder, segmental construction
and balanced cantilever, 35-55 per cent of cost of
concrete
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
914,955.00 919,145.00 933,511.00
for 120 cum

d) Formwork and staging 35 per cent of (a+b+c) 35.000 320,234.25 321,700.75 326,728.85

@ 20% on @ 20% on @ 20% on


e) Overhead charges 247,037.85 248,169.15 252,047.97
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 148,222.71 148,901.49 151,228.78
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,630,449.81 1,637,916.39 1,663,516.60
Rate per cum = (a+b+c+d+e+f)/120 13,587.08 13,649.30 13,862.64
Say 13,587.00 13,649.00 13,863.00
14.01G (q)
(i) Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


914,955.00 919,145.00 933,511.00
for 120 cum

d) Formwork and staging 45 per cent of (a+b+c) 45.000 411,729.75 413,615.25 420,079.95

@ 20% on @ 20% on @ 20% on


e) Overhead charges 265,336.95 266,552.05 270,718.19
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 159,202.17 159,931.23 162,430.91
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,751,223.87 1,759,243.53 1,786,740.05
Rate per cum = (a+b+c+d+e+f)/120 14,593.53 14,660.36 14,889.50
Say 14,594.00 14,660.00 14,890.00
14.01G (r)
(i) Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


914,955.00 919,145.00 933,511.00
for 120 cum

d) Formwork and staging 55 per cent of (a+b+c) 55.000 503,225.25 505,529.75 513,431.05

@ 20% on @ 20% on @ 20% on


e) Overhead charges 283,636.05 284,934.95 289,388.41
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 170,181.63 170,960.97 173,633.05
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,871,997.93 1,880,570.67 1,909,963.51
Rate per cum = (a+b+c+d+e+f)/120 15,599.98 15,671.42 15,916.36
Say 15,600.00 15,671.00 15,916.00
14.01 H PSC Grade M- 55
Unit = 1 cum
Taking output = 120 cum 120 cum
a) Material

Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 120.000 120.000 6,321.00 758,520.00 758,520.00 758,520.00
Concrete - 20.15

Water for curing Kl 63.000 63.000 63.000 16.00 1,008.00 1,008.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.192 0.192 0.192 617.00 118.46 118.46 118.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 3.300 3.300 3.300 511.52 1,688.02 1,688.02 1,688.02 L-13
c) Machinery
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-
300 x L 300 x L 300 x L 13.41 120,697.50 120,697.50 120,697.50 P&M-128
Kilometer km
For unloading hour 2.600 2.600 2.600 2,413.95 6,276.27 6,276.27 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 2.600 2.600 4,401.60 11,444.16 11,444.16 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
0.438XL1+2.62
(i) 16 KL capacity hour 1,501.00 23,663.27 P&M-023
5
0.583XL1+3.50
(ii) 12 KL capacity hour 1,327.00 27,853.73 P&M-024
0
1.167XL1+7.00
(iii) 6 KL capacity hour 1,005.00 42,220.05 P&M-025
0
Basic Cost of Labour, Material & Machinery (a+b+c)
924,435.00 928,625.00 942,991.00
for 120 Cum
For formwork and staging add the following:
14.01H (i) For cast-in-situ box girder, segmental construction
and balanced cantilever, 35-55 per cent of cost of
concrete
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
924,435.00 928,625.00 942,991.00
for 120 cum

d) Formwork and staging 35 per cent of (a+b+c) 35.000 323,552.25 325,018.75 330,046.85

@ 20% on @ 20% on @ 20% on


e) Overhead charges 249,597.45 250,728.75 254,607.57
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 149,758.47 150,437.25 152,764.54
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,647,343.17 1,654,809.75 1,680,409.96
Rate per cum = (a+b+c+d+e+f)/120 13,727.86 13,790.08 14,003.42
Say 13,728.00 13,790.00 14,003.00
14.01H (q)
Height 5m to 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c)
924,435.00 928,625.00 942,991.00
for 120 cum

d) Formwork and staging 45 per cent of (a+b+c) 45.000 415,995.75 417,881.25 424,345.95

@ 20% on @ 20% on @ 20% on


e) Overhead charges 268,086.15 269,301.25 273,467.39
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 160,851.69 161,580.75 164,080.43
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,769,368.59 1,777,388.25 1,804,884.77
Rate per cum = (a+b+c+d+e+f)/120 14,744.74 14,811.57 15,040.71
Say 14,745.00 14,812.00 15,041.00
14.01H (r)
(i) Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


924,435.00 928,625.00 942,991.00
for 120 cum

d) Formwork and staging 55 per cent of (a+b+c) 55.000 508,439.25 510,743.75 518,645.05

@ 20% on @ 20% on @ 20% on


e) Overhead charges 286,574.85 287,873.75 292,327.21
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 171,944.91 172,724.25 175,396.33
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,891,394.01 1,899,966.75 1,929,359.59
Rate per cum = (a+b+c+d+e+f)/120 15,761.62 15,833.06 16,078.00
Say 15,762.00 15,833.00 16,078.00
Note 1.Where ever concrete is carried out using batching
plant, transit mixer, concrete pump, admixers
conforming IS: 9103 @ 0.4 per cent of weight of
cement may be added for achieving desired slump of
concrete.

2. Cement provided for various components of the


super structure is for estimating purpose only. Actual
quantity of cement will be as per approved mix
design. Similarly, the provision for coarse and fine
aggregates is for estimating purpose and the exact
quantity shall be as per the mix design.

3. The items like needle and surface vibrators are


part of minor T & P which is already covered under
the overhead charges. As such these items have not
been added separately in the rate analysis.

14.01 I PSC Grade M- 60


Unit = 1 cum
Taking output = 120 cum 120 cum
a) Material

Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 120.000 120.000 6,511.00 781,320.00 781,320.00 781,320.00
Concrete - 20.16

Water for curing Kl 63.000 63.000 63.000 16.00 1,008.00 1,008.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.192 0.192 0.192 617.00 118.46 118.46 118.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 3.300 3.300 3.300 511.52 1,688.02 1,688.02 1,688.02 L-13
c) Machinery
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-
300 x L 300 x L 300 x L 13.41 120,697.50 120,697.50 120,697.50 P&M-128
Kilometer km
For unloading hour 2.600 2.600 2.600 2,413.95 6,276.27 6,276.27 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 2.600 2.600 4,401.60 11,444.16 11,444.16 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
0.438XL1+2.62
(i) 16 KL capacity hour 1,501.00 23,663.27 P&M-023
5
0.583XL1+3.50
(ii) 12 KL capacity hour 1,327.00 27,853.73 P&M-024
0
1.167XL1+7.00
(iii) 6 KL capacity hour 1,005.00 42,220.05 P&M-025
0
Basic Cost of Labour, Material & Machinery (a+b+c)
947,235.00 951,425.00 965,791.00
for 120 Cum
For formwork and staging add the following:
14.01H (i) For cast-in-situ box girder, segmental construction
and balanced cantilever, 35-55 per cent of cost of
concrete
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
947,235.00 951,425.00 965,791.00
for 120 cum

d) Formwork and staging 35 per cent of (a+b+c) 35.000 331,532.25 332,998.75 338,026.85

@ 20% on @ 20% on @ 20% on


e) Overhead charges 255,753.45 256,884.75 260,763.57
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 153,452.07 154,130.85 156,458.14
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,687,972.77 1,695,439.35 1,721,039.56
Rate per cum = (a+b+c+d+e+f)/120 14,066.44 14,128.66 14,342.00
Say 14,066.00 14,129.00 14,342.00
14.01H (q)
Height 5m to 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c)
947,235.00 951,425.00 965,791.00
for 120 cum

d) Formwork and staging 45 per cent of (a+b+c) 45.000 426,255.75 428,141.25 434,605.95

@ 20% on @ 20% on @ 20% on


e) Overhead charges 274,698.15 275,913.25 280,079.39
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 164,818.89 165,547.95 168,047.63
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,813,007.79 1,821,027.45 1,848,523.97
Rate per cum = (a+b+c+d+e+f)/120 15,108.40 15,175.23 15,404.37
Say 15,108.00 15,175.00 15,404.00
14.01H (r)
(i) Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


947,235.00 951,425.00 965,791.00
for 120 cum

d) Formwork and staging 55 per cent of (a+b+c) 55.000 520,979.25 523,283.75 531,185.05

@ 20% on @ 20% on @ 20% on


e) Overhead charges 293,642.85 294,941.75 299,395.21
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 176,185.71 176,965.05 179,637.13
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,938,042.81 1,946,615.55 1,976,008.39
Rate per cum = (a+b+c+d+e+f)/120 16,150.36 16,221.80 16,466.74
Say 16,150.00 16,222.00 16,467.00
14.01 J PSC Grade M- 65
Unit = 1 cum
Taking output = 120 cum 120 cum
a) Material

Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 120.000 120.000 6,552.00 786,240.00 786,240.00 786,240.00
Concrete - 20.17

Water for curing Kl 63.000 63.000 63.000 16.00 1,008.00 1,008.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.192 0.192 0.192 617.00 118.46 118.46 118.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 3.300 3.300 3.300 511.52 1,688.02 1,688.02 1,688.02 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-
300 x L 300 x L 300 x L 13.41 120,697.50 120,697.50 120,697.50 P&M-128
Kilometer km
For unloading hour 2.600 2.600 2.600 2,413.95 6,276.27 6,276.27 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 2.600 2.600 4,401.60 11,444.16 11,444.16 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
0.438XL1+2.62
(i) 16 KL capacity hour 1,501.00 23,663.27 P&M-023
5
0.583XL1+3.50
(ii) 12 KL capacity hour 1,327.00 27,853.73 P&M-024
0
1.167XL1+7.00
(iii) 6 KL capacity hour 1,005.00 42,220.05 P&M-025
0
Basic Cost of Labour, Material & Machinery (a+b+c)
952,155.00 956,345.00 970,711.00
for 120 Cum
For formwork and staging add the following:
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
14.01 (i) For cast-in-situ box girder, segmental construction
and balanced cantilever, 35-55 per cent of cost of
concrete
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
952,155.00 956,345.00 970,711.00
for 120 cum

d) Formwork and staging 35 per cent of (a+b+c) 35.000 333,254.25 334,720.75 339,748.85

@ 20% on @ 20% on @ 20% on


e) Overhead charges 257,081.85 258,213.15 262,091.97
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 154,249.11 154,927.89 157,255.18
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,696,740.21 1,704,206.79 1,729,807.00
Rate per cum = (a+b+c+d+e+f)/120 14,139.50 14,201.72 14,415.06
Say 14,140.00 14,202.00 14,415.00
14.01H (q)
(i) Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


952,155.00 956,345.00 970,711.00
for 120 cum

d) Formwork and staging 45 per cent of (a+b+c) 45.000 428,469.75 430,355.25 436,819.95

@ 20% on @ 20% on @ 20% on


e) Overhead charges 276,124.95 277,340.05 281,506.19
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 165,674.97 166,404.03 168,903.71
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,822,424.67 1,830,444.33 1,857,940.85
Rate per cum = (a+b+c+d+e+f)/120 15,186.87 15,253.70 15,482.84
Say 15,187.00 15,254.00 15,483.00
14.01H (r)
(i) Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


952,155.00 956,345.00 970,711.00
for 120 cum

d) Formwork and staging 55 per cent of (a+b+c) 55.000 523,685.25 525,989.75 533,891.05

@ 20% on @ 20% on @ 20% on


e) Overhead charges 295,168.05 296,466.95 300,920.41
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 177,100.83 177,880.17 180,552.25
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f 1,948,109.13 1,956,681.87 1,986,074.71
Rate per cum = (a+b+c+d+e+f)/120 16,234.24 16,305.68 16,550.62
Say 16,234.00 16,306.00 16,551.00
Note 1.Where ever concrete is carried out using batching
plant, transit mixer, concrete pump, admixers
conforming IS: 9103 @ 0.4 per cent of weight of
cement may be added for achieving desired slump of
concrete.

2. Cement provided for various components of the


super structure is for estimating purpose only. Actual
quantity of cement will be as per approved mix
design. Similarly, the provision for coarse and fine
aggregates is for estimating purpose and the exact
quantity shall be as per the mix design.

3. The items like needle and surface vibrators are


part of minor T & P which is already covered under
the overhead charges. As such these items have not
been added separately in the rate analysis.

14.02 1600 Supplying, fitting and placing HYSD bar


reinforcement in super-structure complete as per
drawing and technical specifications
Unit = MT
Taking output = 8 MT
a) Material
MS bars including 5 per cent overlaps and wastage tonne 8.400 8.400 8.400 46,496.54 390,570.97 390,570.97 390,570.97 M-083
Binding wire Kg 48.000 48.000 48.000 66.72 3,202.56 3,202.56 3,202.56 M-072

b) Labour for straightening, cutting, bending,


shifting to site, tying and placing in position

Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Blacksmith day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-01
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
c) Machinery
Cutting Machine hour 8.000 8.000 8.000 528.15 4,225.20 4,225.20 4,225.20 P&M-076
Bending Machine hour 8.000 8.000 8.000 528.15 4,225.20 4,225.20 4,225.20 P&M-076
Electric generator 15 KVA hour 8.000 8.000 8.000 425.25 3,402.00 3,402.00 3,402.00 P&M-051
Tipper
Tipper for Transportation
(i) 18 cum capacity t.km 8xL 6.18 1,482.84 P&M-116
(ii) 14 cum capacity t.km 8xL 7.01 1,683.07 P&M-119
(iii) 10 cum capacity t.km 8xL 8.66 2,079.36 P&M-122
Loading & Unloading Time hour
(i) 18 cum capacity hour 1.000 2,883.30 2,883.30 P&M-014
(ii) 14 cum capacity hour 1.280 2,556.75 3,272.64 P&M-015
(iii) 10 cum capacity hour 1.778 2,274.30 4,043.20 P&M-016
Light weight Crane
At cutting bending yard hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
At site hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102
Basic Cost of Labour, Material & Machinery (a+b) for
52080.000 52154.000 52300.000
1 MT

@ 20% on @ 20% on @ 20% on


d) Overhead charges 83,327.75 83,445.67 83,679.03
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 49,996.65 50,067.40 50,207.42
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 8 MT (a+b+c+d+e) 549,963.16 550,741.39 552,281.63
Rate for per MT (a+b+c+d+e)/8 68,745.39 68,842.67 69,035.20
Say 68,745.00 68,843.00 69,035.00
14.03 1800 High tensile steel wires/strands including all
accessories for stressing, stressing operations and
grouting complete as per drawing and Technical
Specifications
Unit = 1 MT
Taking output = 0.377 MT
Details of cost for 12T13 strand 40 m long cable
(weight = 0.377 MT)
a) Material
H.T. Strand @ 9.42 kg/m including 2 per cent for
tonne 0.385 0.385 0.385 63,806.54 24,565.52 24,565.52 24,565.52 M-118
wastage and extra length for jacking
Sheathing duct ID 66 mm along with 5 per cent extra
metre 42.000 42.000 42.000 210.00 8,820.00 8,820.00 8,820.00 M-166
length 40 x 1.05 = 42 m.
Tube anchorage set complete with bearing plate,
each 2.000 2.000 2.000 48.45 96.89 96.89 96.89 M-189
permanent wedges etc

Cement for grouting including 3 per cent wastage @


tonne 0.125 0.125 0.125 4,940.00 617.50 617.50 617.50 M-081
3.00 kg/m = 3 x 1.03 x 40 = 123.60 kg (say, = 125 kg)

Add 0.50 per cent cost of material for Spacers,


170.50 170.50 170.50
Insulation tape and miscellaneous items

b) Labour
i) For making and fixing cables, anchorages
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Blacksmith day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-01
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
ii) For prestressing
Mate/Supervisor day 0.050 0.050 0.050 617.00 30.85 30.85 30.85 L-12
Prestressing operator / Fitter day 0.250 0.250 0.250 738.00 184.50 184.50 184.50 L-08
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
iii) For grouting
Mate/Supervisor day 0.050 0.050 0.050 617.00 30.85 30.85 30.85 L-12
Mason day 0.250 0.250 0.250 679.00 169.75 169.75 169.75 L-10
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
c) Machinery
Stressing jack with pump hour 2.500 2.500 2.500 559.65 1,399.13 1,399.13 1,399.13 P&M-109
Grouting pump with agitator hour 1.000 1.000 1.000 798.00 798.00 798.00 798.00 P&M-096
Generator 33 KVA. hour 3.500 3.500 3.500 753.90 2,638.65 2,638.65 2,638.65 P&M-050
@ 20% on @ 20% on @ 20% on
d) Overhead charges 8,571.49 8,571.49 8,571.49
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 5,142.89 5,142.89 5,142.89
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 0.377 MT (a+b+c+d+e) 56,571.84 56,571.84 56,571.84
Rate per MT = (a+b+c+d+e)/0.377 150,057.94 150,057.94 150,057.94
Say 150,058.00 150,058.00 150,058.00
Note Cost of HT steel has been taken for delivery at site.
Hence carriage has not been considered.
14.04 2702
Providing and laying Cement concrete wearing coat
M-30 grade including reinforcement complete as per
drawing and Technical Specifications

Unit = 1 cum
Taking output = 1 cum
a) Material
cum 1.000 6,414.62 6,414.62
Cement concrete M30 Grade Refer relevant item of Item No. - 14.01
cum 1.000 6,449.54 6,449.54
concrete in Item 14.1 excluding formwork C
cum 1.000 6,569.26 6,569.26
tonne 0.075 52,080.00 3,906.00
HYSD bar reinforcement Rate as per item No
tonne 0.075 52,154.00 3,911.55 Item No. - 14.02
14.2(Excluding OH & CP)
tonne 0.075 52,300.00 3,922.50
b) Labour
Mazdoor for cleaning deck slab concrete surface. day 0.150 0.150 0.150 511.52 76.73 76.73 76.73 L-13

@ 20% on @ 20% on @ 20% on


c) Overhead charges 2,079.47 2,087.56 2,113.70
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 1,247.68 1,252.54 1,268.22
(a+b+c) (a+b+c) (a+b+c)
Rate per cum (a+b+c+d) 13,724.50 13,777.92 13,950.40
Say 13,724.00 13,778.00 13,950.00
14.05 516 &
2702 Mastic Asphalt
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project

Providing and laying 12 mm thick mastic asphalt


wearing course on top of deck slab excluding prime
coat with paving grade bitumen meeting the
requirements given in table 500-39, prepared by
using mastic cooker and laid to required level and
slope after cleaning the surface, including providing
antiskid surface with bitumen precoated fine grained
hard stone chipping of 9.5 mm nominal size at the
rate of 0.005cum per 10 sqm and at an approximate
spacing of 10 cm center to center in both directions,
pressed into surface when the temperature of
surfaces not less than 100 deg. C, protruding 1 mm
to 4 mm over mastic surface, all complete as per
clause 516.

Unit = sqm
Taking output = 72.46 sqm (2 tonnes)(0.869 cum)
assuming a density of 2.3 tonnes/cum.
a) Labour
Mate day 0.490 0.490 0.490 617.00 302.33 302.33 302.33 L-12
Mazdoor day 11.000 11.000 11.000 511.52 5,626.72 5,626.72 5,626.72 L-13
Mazdoor (Skilled) day 1.250 1.250 1.250 565.73 707.16 707.16 707.16 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.060 0.060 0.060 500.40 30.02 30.02 30.02 P&M-052
Air compressor 250 cfm hour 0.060 0.060 0.060 614.25 36.86 36.86 36.86 P&M-029
Mastic cooker 1 tonne capacity hour 6.000 6.000 6.000 1,042.50 6,255.00 6,255.00 6,255.00 P&M-056
Bitumen boiler 1500 litres capacity hour 6.000 6.000 6.000 743.40 4,460.40 4,460.40 4,460.40 P&M-055
Tractor for towing and positioning of mastic cooker
hour 1.000 1.000 1.000 1,876.50 1,876.50 1,876.50 1,876.50 P&M-026
and bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60 per
cent
Coarse aggregate(3.35mm to 9.5 mm size) = 40 per
cent .
Proportion of material required for mastic asphalt with
coarse aggregates (based on mix design done by
CRRI for a specific case)
i) Bitumen 80/100 or 60/70 or 30/40 @ 10.2 per cent
tonne 0.204 0.204 0.204 44,020.00 8,980.08 8,980.08 8,980.08 M-327
by weight of mix. 2 x 10.2/100 = 0.204
ii) Crusher stone dust @ 31.9 per cent by weight of
mix = 2 x 31.9/100 = 0.638 tonnes = 0.638/1.625 = cum 0.390 0.390 0.390 1,887.12 735.98 735.98 735.98 M-020
0.39

iii) Lime stone dust filler with calcium carbonate


content not less than 80 per cent by weight @ 17.92 tonne 0.360 0.360 0.360 3,753.00 1,351.08 1,351.08 1,351.08 M-190
per cent by weight of mix = 2 x 17.92/100 = 0.36

iv) Coarse aggregates 9.5 mm to 3.35 mm size @ 40


per cent by weight of mix = 2 x 40/100 = 0.8 MT = cum 0.550 0.550 0.550 1,887.12 1,037.92 1,037.92 1,037.92 M-050
0.8/1.456 = 0.55

v) Pre-coated stone chips of 9.5 mm nominal size for


cum 0.036 0.036 0.036 1,951.24 70.24 70.24 70.24 M-141
skid resistance = 72.46x0.005/10 = 0.036

vi) Bitumen for coating of chips @ 2 per cent by


weight = 0.036 x 1.456 x 2/100 = 0.001048MT = kg 1.050 1.050 1.050 44.02 46.22 46.22 46.22 M-327
1.05kg
@ 20% on @ 20% on @ 20% on
d) Overhead charges 6,303.30 6,303.30 6,303.30
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 3,781.98 3,781.98 3,781.98
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 72.46 sqm = a+b+c+d+e 41,601.80 41,601.80 41,601.80
Rate per sqm = (a+b+c+d+e)/72.46 574.13 574.13 574.13
Say 574.00 574.00 574.00
Note 1.The rates for 6 mm or any other thickness may be worked out on pro-rata basis.
2. Where tack coat is required to be provided before laying mastic asphalt, the same is required to be measured and paid separately.
3.The quantities of binder, filler and aggregates are for estimating purpose. Exact quantities shall be as per mix design.
4.This rate analysis is based on design made by CRRI for a specific case and is meant for estimating purposes only. Actual design is required to be done for each case.
5.The quantity of bitumen works out 17 per cent of the mastic asphalt blocks without aggregates and falls within the standards laid down by MoRTH Specifications.
14.06 2703,
1500,
1600 & Construction of precast RCC railing of M30 Grade,
1700 aggregate size not exceeding 12 mm, true to line and
grade, tolerance of vertical RCC post not to exceed 1
in 500, centre to centre spacing between vertical post
not to exceed 2000 mm, leaving adequate space
between vertical post for expansion, complete as per
approved drawings and technical specifications.

Unit = 1 RM
Taking output = 2 x 24 m span = 48 m
a) Material
Cement concreteM30 Grade Refer relevant item of cum 4.092 6,414.62 26,248.62
Item No. - 14.01
concrete in Item 14.1(C) by using batching plant, cum 4.092 6,449.54 26,391.51
C
excluding formwork i.e. per cum basic cost (a+b+c) cum 4.092 6,569.26 26,881.40
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project

No. of vertical posts = (12 + 2)2 = 28 Nos., External


area of vertical post 0.25x0.275 = 0.069sqm,
Concrete in Vertical posts = 0.069 x 28 = 1.932 cum,
Hand rail in 3 tiers = 3 x 24 = 72 m, External area =
0.170 x 0.175 = 0.03 sqm, Concrete in hand rails =
0.03 x 72 = 2.16 cum, Total Concrete = 1.932 + 2.16
= 4.092 cum. (Refer MoRTH SD / 202).

Add 5 per cent of above cost for form work for


1,312.43 1,319.58 1,344.07
casting in casting yard.
tonne 0.865 52,080.00 45,049.20
HYSD bar reinforcement Rate as per item No
tonne 0.865 52,154.00 45,113.21 Item No. - 14.02
14.2(Excluding OH & CP)
tonne 0.865 52,300.00 45,239.50
Refer MoRTH SD / 202.
Add 5 per cent of (a) for handling and fixing of
3,630.51 3,641.21 3,673.25
precast panels in position

b) Overhead charges @ 20% on (a) @ 20% on (a) @ 20% on (a) 15,248.15 15,293.10 15,427.64

@ 10% on @ 10% on @ 10% on


c) Contractor's profit 9,148.89 9,175.86 9,256.59
(a+b) (a+b) (a+b)
Rate for 48 m (a+b+c) 100,637.80 100,934.48 101,822.45
Rate per metre (a+b+c)/48 2,096.62 2,102.80 2,121.30
Say 2,097.00 2,103.00 2,121.00
Note
1.Quantities of material have been adopted from
standard plans of MoRTH vide drawing no. SD/202.

2.48 m length is the total linear length adding both


sides of 24 m span.
14.07 2703,
1500,
1600 & Construction of RCC railing of M30 Grade in-situ with
1700 20 mm nominal size aggregate, true to line and
grade, tolerance of vertical RCC post not to exceed 1
in 500, centre to centre spacing between vertical post
not to exceed 2000 mm, leaving adequate space
between vertical post for expansion, complete as per
approved drawings and technical specifications.

Unit = 1 RM
Taking output = 2 x 24 m span = 48 m.
a) Material
Cement concreteM30 Grade Refer relevant item of cum 4.092 6,414.62 26,248.62
Item No. - 14.01
concrete in Item 14.1(C) by using batching plant, cum 4.092 6,449.54 26,391.51
C
excluding formwork i.e. per cum basic cost (a+b+c) cum 4.092 6,569.26 26,881.40

No. of vertical posts = (12 + 2)2 = 28 Nos., External


area of vertical post 0.25x0.275 = 0.069sqm,
Concrete in vehicle posts = 0.069 x 28 = 1.932 cum,
Hand rail in 3 tiers = 3 x 24 = 72 m, External area =
0.170 x 0.175 = 0.03 sqm, Concrete in hand rails =
0.03 x 72 = 2.16 cum, Total Concrete = 1.932 + 2.16
= 4.092 cum. (Refer MoRTH SD / 202).

Add 12 per cent of above cost for form work. 3,149.83 3,166.98 3,225.77
tonne 0.865 52,080.00 45,049.20
HYSD bar reinforcement Rate as per item No
tonne 0.865 52,154.00 45,113.21 Item No. - 14.02
14.2(Excluding OH & CP)
tonne 0.865 52,300.00 45,239.50
refer MoRTH SD / 202.
b) Overhead charges @ 20% on (a) @ 20% on (a) @ 20% on (a) 14,889.53 14,934.34 15,069.33

@ 10% on @ 10% on @ 10% on


c) Contractor's profit 8,933.72 8,960.60 9,041.60
(a+b) (a+b) (a+b)
Rate for 48 m (a+b+c) 98,270.90 98,566.65 99,457.61
Rate per metre (a+b+c)/48 2,047.31 2,053.47 2,072.03
Say 2,047.00 2,053.00 2,072.00
Note
1. Quantities of material have been adopted from
standard plans of MoRTH vide drawing no. SD/202.

2. 48 m length is the total linear length adding both


sides of 24 m span.
14.08 2703.2 &
1900 Providing, fitting and fixing mild steel railing complete
as per drawing and Technical Specification

Unit = 1 RM
Taking output = 2 x 50 m span = 100 m
a) Material:
1) ISMC 100 = 2.806 x 1.05 = 2.946 MT tonne 2.946 2.946 2.946 63,806.54 187,974.08 187,974.08 187,974.08 M-181
2) MS Flat = 0.964 x 1.05 = 1.012 MT tonne 1.012 1.012 1.012 63,806.54 64,572.22 64,572.22 64,572.22 M-181
3) MS bars = 0.17 x 1.05 = 0.180 MT tonne 0.180 0.180 0.180 63,806.54 11,485.18 11,485.18 11,485.18 M-125
4) MS bolts, nuts and washers tonne 0.150 0.150 0.150 64.83 9.72 9.72 9.72 M-129

Add @ 5 per cent of cost of material for painting one


shop coat with red oxide primer and three coats of
13,202.06 13,202.06 13,202.06
synthetic enamel paint and consumables to
safeguard against weathering and corrosion.

Add for cost of concrete for fixing vertical posts in the


2,640.41 2,640.41 2,640.41
performed recess @ 1 per cent of cost of material.
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Add for electricity charges, welding and drilling
equipment, electrodes and other consumables @ 1 2,640.41 2,640.41 2,640.41
per cent of cost of material.
b) Labour
Mate day 2.800 2.800 2.800 617.00 1,727.60 1,727.60 1,727.60 L-12
Mazdoor (Skilled) day 30.000 30.000 30.000 565.73 16,971.90 16,971.90 16,971.90 L-15
Mazdoor day 40.000 40.000 40.000 511.52 20,460.80 20,460.80 20,460.80 L-13
@ 20% on @ 20% on @ 20% on
c) Overhead charges 64,336.88 64,336.88 64,336.88
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 38,602.13 38,602.13 38,602.13
(a+b+c) (a+b+c) (a+b+c)
Cost for 100 m steel railing = a+b+c+d 424,623.39 424,623.39 424,623.39
Rate per metre (a+b+c+d)/100 4,246.23 4,246.23 4,246.23
Say 4,246.00 4,246.00 4,246.00
14.09 2705 Drainage Spouts complete as per drawing and
Technical specification
Unit = 1 No.
Taking output = 1 No.
a) Material
Corrosion resistant Structural steel including 5 per
Kg 4.000 4.000 4.000 44.00 176.00 176.00 176.00 M-088/1000
cent wastage
GI pipe 100mm dia metre 6.000 6.000 6.000 496.00 2,976.00 2,976.00 2,976.00 M-239
GI bolt 10 mm Dia each 6.000 6.000 6.000 16.76 100.55 100.55 100.55 M-109
Galvanised MS flat clamp each 2.000 2.000 2.000 27.80 55.60 55.60 55.60 M-101
b) Labour
For fabrication
Mate day 0.002 0.002 0.002 617.00 1.23 1.23 1.23 L-12
Skilled (Blacksmith, welder etc.) day 0.020 0.020 0.020 738.00 14.76 14.76 14.76 L-02
Mazdoor day 0.020 0.020 0.020 511.52 10.23 10.23 10.23 L-13
For fixing in position
Mate day 0.008 0.008 0.008 617.00 4.94 4.94 4.94 L-12
Mason day 0.010 0.010 0.010 679.00 6.79 6.79 6.79 L-10
Mazdoor day 0.200 0.200 0.200 511.52 102.30 102.30 102.30 L-13

Add @ 5 per cent of cost of material and labour for


electrodes, cutting gas, sealant, anti-corrosive 172.42 172.42 172.42
bituminous paint, mild steel grating etc.

@ 20% on @ 20% on @ 20% on


c) Overhead charges 724.16 724.16 724.16
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 434.50 434.50 434.50
(a+b+c) (a+b+c) (a+b+c)
Rate per metre (a+b+c+d) 4,779.49 4,779.49 4,779.49
Say 4,779.00 4,779.00 4,779.00
Note
1. In case of viaducts in urban areas, the drainage
spouts should be connected with suitably located
pipelines to discharge the surface run-off to drains
provided at ground level.

2. In case of bridges, sufficient length of G.I Pipe


shall be provided to ensure that there is no splashing
of water from the drainage spout on the structure.

14.10 2700 PCC M15 Grade leveling course below approach


slab complete as per drawing and Technical
specification
Unit = 1 cum
Taking output = 1 cum
a) Material
Case I PCC Grade M15 using batching plant & Concrete
pump
Concrete, Rate as per item No. 12.8 (A) excluding Item No. - 12.08
cum 1.000 5,594.00 5,594.00
formworks A
Concrete, Rate as per item No. 12.8 (A) excluding Item No. - 12.08
1.000 5,630.00 5,630.00
formworks A
Concrete, Rate as per item No. 12.8 (A) excluding Item No. - 12.08
1.000 5,749.00 5,749.00
formworks A

b) Overhead charges @ 20% on (a) @ 20% on (a) @ 20% on (a) 1,118.80 1,126.00 1,149.80

@ 10% on @ 10% on @ 10% on


c) Contractor's profit 671.28 675.60 689.88
(a+b) (a+b) (a+b)
Rate per cum 7,384.08 7,431.60 7,588.68
Rate per cum Say 7,384.00 7,432.00 7,589.00
Case PCC Grade M15 using batching plant & manual
II placing
Concrete, Rate as per item No. 12.8 (A) excluding Item No. - 12.08
cum 1.000 5,879.00 5,879.00
formworks A
Concrete, Rate as per item No. 12.8 (A) excluding Item No. - 12.08
1.000 5,914.00 5,914.00
formworks A
Concrete, Rate as per item No. 12.8 (A) excluding Item No. - 12.08
1.000 6,033.00 6,033.00
formworks A

c) Overhead charges @ 20% on (a) @ 20% on (a) @ 20% on (a) 1,175.80 1,182.80 1,206.60

@ 10% on @ 10% on @ 10% on


d) Contractor's profit 705.48 709.68 723.96
(a+b) (a+b) (a+b)
Rate per cum 7,760.28 7,806.48 7,963.56
Rate per cum Say 7,760.00 7,806.00 7,964.00
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
14.11 1500,16
00,1700 Reinforced cement concrete approach slab including
& 2704 reinforcement and formwork complete as per drawing
and Technical specification

Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concreteM30 Grade Refer relevant item of cum 1.000 6,468.00 6,468.00
concrete in item 12.8(G)by using batching plant, Item No. - 12.08
cum 1.000 6,504.00 6,504.00
excluding formwork i.e. per cum basic cost. (a+b+c) G
(Excluding OH & CP). cum 1.000 6,623.00 6,623.00
( Refer relevant item of concrete in item No. 13.8 (G)
except that form work may be added at the rate of 2
129.36 130.08 132.46
per cent of cost against 3.5 per cent provided in the
foundation concrete.
tonne 0.050 52,080.00 2,604.00
HYSD bar reinforcement Rate as per item No
tonne 0.050 52,154.00 2,607.70 Item No. - 14.02
14.02(Excluding OH & CP)
tonne 0.050 52,300.00 2,615.00
b) Overhead charges @ 20% on (a) @ 20% on (a) @ 20% on (a) 1,840.27 1,326.82 1,351.09

@ 10% on @ 10% on @ 10% on


c) Contractor's profit 1,104.16 1,056.86 1,072.16
(a+b) (a+b) (a+b)
Rate per cum (a+b+c) 12,145.80 11,625.46 11,793.71
Say 12,146.00 11,625.00 11,794.00
Note The grade of reinforced cement concrete may be
adopted as M30 for severe conditions and M25 for
moderate conditions.
14.12 1600 Providing anti-corrosive treatment to HYSD
reinforcement with Fusion Bonded Epoxy Coating
(FBEC)
Unit = 1 MT
Taking output = 1 MT
To be taken as per the prevailing market rates.
Note
Contractors generally do not have expertise for this
item . The job is therefore, got done from specialised
firms who have the expertise in the field of
construction chemicals. The prevailing rate in the
market is required to be ascertained from the market
and added in the cost estimate. Detailed guidelines in
this regard have been issued by MoRTH vide their
circular no. RW/NH-34041/44/91-S&R dated
21.3.2000.

14.13 1800 &


2300 Precast - pretensioned Girders

Providing, precasting, transportation and placing in


position precast pretensioned concrete girders as per
drawing and technical specifications

Unit = 1 cum
Taking output = 1 cum
Grade of concrete - M40
a) Material

Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 1.000 1.000 1.000 5,519.00 5,519.00 5,519.00 5,519.00
Concrete - 20.12

Water for curing Kl 0.525 0.525 0.525 16.00 8.40 8.40 8.40 M-191
HYSD steel . tonne 0.100 0.100 0.100 46,496.54 4,649.65 4,649.65 4,649.65 M-083
HT strand with 5 per cent as wastage and extra
tonne 0.060 0.060 0.060 63,806.54 3,828.39 3,828.39 3,828.39 M-118
length for anchoring
LDO for steam curing Litre 37.000 37.000 37.000 83.00 3,071.00 3,071.00 3,071.00 M-121
Add consumables such as binding wire, foam,
packing tape, shuttering oil, HDPE pipe for
170.76 170.76 170.76
unbonding of strand, bolt & nuts etc @ 1 per cent of
material cost
b) Labour

(i) Cutting, bending, making reinforcement cage,


placing in position, binding etc. complete

Taking quantity of steel 100 Kg/cum of concrete


including laps and wastage
Mate day 0.070 0.070 0.070 617.00 43.19 43.19 43.19 L-12
Mazdoor (Skilled) day 0.350 0.350 0.350 565.73 198.01 198.01 198.01 L-15
Mazdoor day 1.400 1.400 1.400 511.52 716.13 716.13 716.13 L-13
(ii) Cable cutting and threading in position including
binding by insulation tape with HDPE pipes etc.,
prestessing and cutting of extra length of HT strand
after de-stressing.
Taking quantity of HT strand 60 Kg/cum
Mate day 0.026 0.026 0.026 617.00 16.04 16.04 16.04 L-12
Mazdoor (Skilled) day 0.140 0.140 0.140 565.73 79.20 79.20 79.20 L-15
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
(iii) Erection and dismantling of shuttering
Taking shuttering area 10 sqm/cum of concrete
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor (Skilled) day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
(iv) Concreting by Batching plant and stationary
concrete pump
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Mate day 0.026 0.026 0.026 617.00 16.04 16.04 16.04 L-12
Mazdoor (Skilled) day 0.050 0.050 0.050 565.73 28.29 28.29 28.29 L-15
Mazdoor day 0.600 0.600 0.600 511.52 306.91 306.91 306.91 L-13
(v) Steam curing and manual curing
Mate day 0.014 0.014 0.014 617.00 8.64 8.64 8.64 L-12
Mazdoor day 0.350 0.350 0.350 511.52 179.03 179.03 179.03 L-13
(vi) Handling of precast girder, stacking in stockyard
and again loading in trailor
Mate day 0.010 0.010 0.010 617.00 6.17 6.17 6.17 L-12
Mazdoor day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
(vii) Placement of girders in position over pier caps
including placement of sand jacks, channel, levelling
etc.
Mate day 0.012 0.012 0.012 617.00 7.40 7.40 7.40 L-12
Mazdoor (Skilled) day 0.060 0.060 0.060 565.73 33.94 33.94 33.94 L-15
Mazdoor day 0.240 0.240 0.240 511.52 122.76 122.76 122.76 L-13
c) Machinery
i) At casting yard
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-
2.5 x L 2.5 x L 2.5 x L 13.41 1,005.81 1,005.81 1,005.81 P&M-128
Kilometer km
For unloading hour 0.022 0.022 0.022 2,413.95 53.11 53.11 53.11 P&M-067
Hydraulic Boom placer pump hour 0.022 0.022 0.022 4,401.60 96.84 96.84 96.84 P&M-069
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
0.004XL1+0.02
(i) 16 KL capacity hour 1,501.00 213.14 P&M-023
2
0.005XL1+0.02
(ii) 12 KL capacity hour 1,327.00 237.53 P&M-024
9

(iii) 6 KL capacity hour 0.01XL1+0.058 1,005.00 359.79 P&M-025


Crane 35 tonne capacity hour 0.100 0.100 0.100 6,330.45 633.05 633.05 633.05 P&M-099
Trailor 30 tonne capacity hour 0.100 0.100 0.100 2,883.30 288.33 288.33 288.33 P&M-014
ii) For transportation and placement at site
Crane 35 tonne capacity hour 0.150 1.150 2.150 6,330.45 949.57 7,280.02 13,610.47 P&M-099
Trailer 30 tonne capacity for transporting to site. (L - tonne.k
2.5xL 2.5xL 2.5xL 6.18 463.39 463.39 463.39 P&M-116
Lead in Kilometer) m
Trailor 30 tonne capacity during placement. hour 0.150 1.150 2.150 2,883.30 432.50 3,315.80 6,199.10 P&M-014
Cost of formwork, steam curing arrangement,
pretensioning arrangement etc @ 5 per cent of cost 1,259.56 1,721.46 2,188.26
material, labour and machinery
@ 20% on @ 20% on @ 20% on
d) Overhead charges 5,290.14 7,230.15 9,190.71
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 3,174.08 4,338.09 5,514.43
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 34,914.93 47,718.99 60,658.69
Say 34,915.00 47,719.00 60,659.00
14.14 1700 & Providing and fixing Helical pipes in voided concrete
1800 slabs
Unit = 1 RM
Taking output = 1 RM
a) Material
Helical pipes 600mm diameter metre 1.000 1.000 1.000 1,008.00 1,008.00 1,008.00 1,008.00 M-116
Tie rods 20mm diameter each 1.000 1.000 1.000 1.50 1.50 1.50 1.50 M-185
Consumables for sealing joints etc.@ 5 per cent of
50.48 50.48 50.48
cost of material
b) Labour
Mate day 0.010 0.010 0.010 617.00 6.17 6.17 6.17 L-12
Fitter day 0.050 0.050 0.050 738.00 36.90 36.90 36.90 L-08
Mazdoor day 0.200 0.200 0.200 511.52 102.30 102.30 102.30 L-13
@ 20% on @ 20% on @ 20% on
c) Overhead charges 241.07 241.07 241.07
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 144.64 144.64 144.64
(a+b+c) (a+b+c) (a+b+c)
Rate per Meter (a+b+c+d) 1,591.06 1,591.06 1,591.06
Say 1,591.00 1,591.00 1,591.00
14.15 800 Crash Barriers

Provision of an Reinforced cement concrete crash


barrier at the bridge decks& approaches to bridge
structures constructed with Rein forced Cement
Concrete With HYSD reinforcement confirming
MoRT&H Specification and as per details given IRC-
5 including dowel bars ,expansion joints filled with
pre- moulded asphalt filler board etc .. and approved
drawing and at locations directed by the Engineer ,all
as specified.

Unit = Linear meter


Taking output = 10 m
A Crash Barriers for Bridge (Height 950 mm) as per
detais given IRC-5 (fig.-1) (Area -0.254 sqm. For 1
meter length )

a) M 40 grade concrete &HYSD steel reinforcment

M 40 grade concrete cum 2.540 10,750.00 27,305.00


Item No. -
(Area -0.254 Sqm. /Meter ) (Rate taken from item No. cum 2.540 10,804.00 27,442.16
14.01E (i)(P)
14.01 E (p) including OH&CP) cum 2.540 10,991.00 27,917.14
tonne 0.229 68,745.00 15,742.61 Item No. - 14.02
HYSD bar reinforcement Rate as per item No 14.2
including OH &
(including OH&CP) )
CP
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project Item No. - 14.02
HYSD bar reinforcement Rate as per item No 14.2
tonne 0.229 68,843.00 15,765.05 including OH &
(including OH&CP) )
tonne 0.229 69,035.00 15,809.02 CP
b) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
c) Material
Pre-moulded ashphalt filler board metre 0.265 0.265 0.265 376.00 99.64 99.64 99.64 M-143
@ 20% on @ 20% on @ 20% on
d) Overhead charges 127.17 127.17 127.17
(b+c) (b+c) (b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 76.30 76.30 76.30
(b+c+d) (b+c+d) (b+c+d)
Rate per cum (a+b+c+d+e) 43,886.91 44,046.52 44,565.46
Rate per cum (a+b+c+d+e)/10 4,388.69 4,404.65 4,456.55
Say 4,389.00 4,405.00 4,457.00
B Crash Barriers for Bridge (Height 1100 mm) as per
detais given IRC-5 (fig.-2) (Area -0.298 sqm. For 1
meter length )

a) M 40 grade concrete &HYSD steel reinforcment

M 40 grade concrete cum 2.980 10,750.00 32,035.00


Item No. -
(Area -0.254 Sqm. /Meter ) (Rate taken from item No. cum 2.980 10,804.00 32,195.92
14.01E (i)(P)
14.01 E (p) including OH&CP) cum 2.980 10,991.00 32,753.18
tonne 0.268 68,745.00 18,423.66 Item No. - 14.02
HYSD bar reinforcement Rate as per item No
tonne 0.268 68,843.00 18,449.92 including OH &
14.2(Excluding OH & CP)
tonne 0.268 69,035.00 18,501.38 CP
b) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
c) Material
Pre-moulded ashphalt filler board metre 0.310 0.310 0.310 376.00 116.56 116.56 116.56 M-143
@ 20% on @ 20% on @ 20% on
d) Overhead charges 130.55 130.55 130.55
(b+c) (b+c) (b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 78.33 78.33 78.33
(b+c+d) (b+c+d) (b+c+d)
Rate per cum (a+b+c+d+e) 51,320.30 51,507.49 52,116.20
Rate per cum (a+b+c+d+e)/10 5,132.03 5,150.75 5,211.62
Say 5,132.00 5,151.00 5,212.00
C Crash Barriers for Bridge (Height 1550 mm) as per
detais given IRC-5 (fig.-3) (Surface Area 0.514 sqm.
For 1 meter length )

a) M 40 grade concrete &HYSD steel reinforcment

M 40 grade concrete cum 5.140 10,750.00 55,255.00


Item No. -
(Area -0.254 Sqm. /Meter ) (Rate taken from item No. cum 5.140 10,804.00 55,532.56
14.01E (i)(P)
14.01 E (p) including OH&CP) cum 5.140 10,991.00 56,493.74
tonne 0.463 68,745.00 31,828.94 Item No. - 14.02
HYSD bar reinforcement Rate as per item No
tonne 0.463 68,843.00 31,874.31 including OH &
14.2(Excluding OH & CP)
tonne 0.463 69,035.00 31,963.21 CP
b) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Mazdoor day 1.500 1.500 1.500 511.52 767.28 767.28 767.28 L-13
c) Material
Pre-moulded ashphalt filler board metre 0.540 0.540 0.540 376.00 203.04 203.04 203.04 M-143
@ 20% on @ 20% on @ 20% on
d) Overhead charges 201.47 201.47 201.47
(b+c) (b+c) (b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 120.88 120.88 120.88
(b+c+d) (b+c+d) (b+c+d)
Rate per cum (a+b+c+d+e) 88,413.62 88,736.56 89,786.63
Rate per cum (a+b+c+d+e)/10 8,841.36 8,873.66 8,978.66
Say 8,841.00 8,874.00 8,979.00
14.16 800 Painting on concrete surface
Providing and applying 2 coats of water based
cement paint to unplastered concrete surface after
cleaning the surface of dirt, dust, oil, grease,
efflorescence and applying paint @ of 1 litre for 2
sqm.
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.020 0.020 0.020 617.00 12.34 12.34 12.34 L-12
Painter day 0.250 0.250 0.250 679.00 169.75 169.75 169.75 L-18
Mazdoor (Skilled) day 0.250 0.250 0.250 565.73 141.43 141.43 141.43 L-15
b) Material
Water based paint of approved quality for cement
Litres 5.000 5.000 5.000 97.30 486.50 486.50 486.50 M-192
concrete surface
@ 20% on @ 20% on @ 20% on
c) Overhead charges 162.00 162.00 162.00
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 97.20 97.20 97.20
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm (a+b+c+d) 1,069.23 1,069.23 1,069.23
Rate per sqm (a+b+c+d)/10 106.92 106.92 106.92
Say 107.00 107.00 107.00
14.17 2605 Filler joint
(i) Providing & fixing 2 mm thick corrugated copper plate
in expansion joint complete as per drawing &
Technical Specification.
Unit = Running meter
Taking output = 12 m
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
a) Labour
Cutting, bending, carrying & fixing etc.
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
Mazdoor (Skilled) day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
b) Material
Copper plate - 12m long x 250 mm wide kg 55.000 55.000 55.000 389.20 21,406.00 21,406.00 21,406.00 M-087
Area = 12 x 0.25 = 3 sqm
Weight = 3 x 0.002 x 8900 = 53.4 kg
Wastage @ 2.5 per cent = 1.33 kg/54.73 kg say = 55
kg.
@ 20% on @ 20% on @ 20% on
c) Overhead charges 4,393.86 4,393.86 4,393.86
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 2,636.32 2,636.32 2,636.32
(a+b+c) (a+b+c) (a+b+c)
Cost for 12 m = (a+b+c+d) 28,999.48 28,999.48 28,999.48
Rate per m = (a+b+c+d)/12 2,416.62 2,416.62 2,416.62
Say 2,417.00 2,417.00 2,417.00
14.17 (ii) Providing & fixing 20 mm thick compressible fibre
board in expansion joint complete as per drawing &
Technical Specification.
Unit = Running meter
Taking output = 12 m
a) Labour
For carrying, placing & fixing.
Mate day 0.008 0.008 0.008 617.00 4.94 4.94 4.94 L-12
Mazdoor day 0.100 0.100 0.100 511.52 51.15 51.15 51.15 L-13
Mazdoor (Skilled) day 0.100 0.100 0.100 565.73 56.57 56.57 56.57 L-15
b) Material
20 mm thick compressible fibre board 12 m long x 25
sqm 3.000 3.000 3.000 735.00 2,205.00 2,205.00 2,205.00 M-085
cm deep.
Area = 12 x 0.25 = 3 sqm
@ 20% on @ 20% on @ 20% on
c) Overhead charges 463.53 463.53 463.53
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 278.12 278.12 278.12
(a+b+c) (a+b+c) (a+b+c)
Cost for 12 m = (a+b+c+d) 3,059.31 3,059.31 3,059.31
Rate per m = (a+b+c+d)/12 254.94 254.94 254.94
Say 255.00 255.00 255.00
14.17 (iii)
Providing and fixing in position 20 mm thick
premoulded joint filler in expansion joint for fixed
ends of simply supported spans not exceeding 10 m
to cater for a horizontal movement upto 20 mm,
covered with sealant complete as per drawing and
technical specifications.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.012 0.012 0.012 617.00 7.40 7.40 7.40 L-12
Mazdoor day 0.200 0.200 0.200 511.52 102.30 102.30 102.30 L-13
Mazdoor (Skilled) day 0.100 0.100 0.100 565.73 56.57 56.57 56.57 L-15
b) Material
Premoulded joint filler 12 m long,20 mm thick and
sqm 3.600 3.600 3.600 625.50 2,251.80 2,251.80 2,251.80 M-140
300 mm deep.
@ 20% on @ 20% on @ 20% on
c) Overhead charges 483.62 483.62 483.62
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 290.17 290.17 290.17
(a+b+c) (a+b+c) (a+b+c)
Cost for 12 m = (a+b+c+d) 3,191.87 3,191.87 3,191.87
Rate per m = (a+b+c+d)/12 265.99 265.99 265.99
Say 266.00 266.00 266.00
14.17 (iv)
Providing and filling joint sealing compound as per
drawings and technical specifications with coarse
sand and 6 per cent bitumen by weight

Unit = Running meter


Taking output = 12 m
12m long x 100 mm wide x 10mm deep recess
a) Labour
Mate day 0.024 0.024 0.024 617.00 14.81 14.81 14.81 L-12
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
Mazdoor (Skilled) day 0.100 0.100 0.100 565.73 56.57 56.57 56.57 L-15
b) Material
Sand cum 0.012 0.012 0.012 1,994.03 23.93 23.93 23.93 M-005
Volume 12 x 0.1 x 0.01 = 0.012 cum
Weight 0.012 x 1400 = 16.8kg
Bitumen cum 0.001 0.001 0.001 46,556.37 46.56 46.56 46.56 M-074
16.8 x 0.06 = 1 kg
@ 20% on @ 20% on @ 20% on
c) Overhead charges 79.53 79.53 79.53
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 47.72 47.72 47.72
(a+b+c) (a+b+c) (a+b+c)
Cost for 12 m = (a+b+c+d) 524.87 524.87 524.87
Rate per m = (a+b+c+d)/12 43.74 43.74 43.74
Say 44.00 44.00 44.00
Note For arriving at the final rate of filler joints per m
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project

length and per cm depth of joint filling compound,

the rates at Sl. No. i), ii), iii) & iv) shall be added
14.18 2600 Asphaltic Plug joint

Providing and laying of asphaltic plug joint to provide


for horizontal movement of 25 mm and vertical
movement of 2 mm, depth of joint varying from 75
mm to 100 mm, width varying from 500 mm to 750
mm (in traffic direction), covered with a closure plate
of 200mm x 6mm of weldable structural steel
conforming to IS: 2062, asphaltic plug to consist of
polymer modified bitumen binder, carefully selected
single size aggregate of 12.5 mm nominal size and a
heat resistant foam caulking/backer rod, all as per
approved drawings and specifications.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.052 0.052 0.052 617.00 32.08 32.08 32.08 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
Mazdoor (Skilled) day 0.300 0.300 0.300 565.73 169.72 169.72 169.72 L-15
b) Material
Crushed stone aggregate 12.5 mm nominal size cum 0.750 0.750 0.750 1,887.12 1,415.34 1,415.34 1,415.34 M-051
Polymer modified bitumen kg 77.500 77.500 77.500 46.90 3,634.47 3,634.47 3,634.47 M-078 / 1000
Galvanised structural steel plate 200 mm wide,6 mm
thick, 12 m long (2.4 sqm) @ 47.10 kg/sqm including kg 113.000 113.000 113.000 63.00 7,119.00 7,119.00 7,119.00 M-103
5 per cent wastage
Add 1 per cent for welding and foam caulking/backer
128.82 128.82 128.82
rod and other incidentals.
c) Machinery
Mastic cooker 1 tonne capacity hour 1.000 1.000 1.000 1,042.50 1,042.50 1,042.50 1,042.50 P&M-056
Smooth 3-wheeled steel roller 8-10 capacity hour 0.500 0.500 0.500 417.00 208.50 208.50 208.50 P&M-019
@ 20% on @ 20% on @ 20% on
c) Overhead charges 2,852.39 2,852.39 2,852.39
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 1,711.43 1,711.43 1,711.43
(a+b+c) (a+b+c) (a+b+c)
Cost for 12 m asphalt plug joint = (a+b+c+d+e) 18,825.78 18,825.78 18,825.78
Rate per m = (a+b+c+d+e)/12 1,568.82 1,568.82 1,568.82
Say 1,569.00 1,569.00 1,569.00
Note The nominal size of aggregates shall be 12.5 mm for
depth of joint upto 75 mm and 20 mm for joints of
depth more than 75 mm.
14.19 2605 Elastomeric Slab Steel Expansion Joint

Providing and laying of an elastomeric slab steel


expansion joint, catering to right or skew (less than
20 deg., moderately curved with maximum horizontal
movement upto 50 mm, complete as per approved
drawings and standard specifications to be installed
by the manufacturer/supplier or their authorised
representative ensuring compliance to the
manufacturer's instructions for installation and clause
2605 of MoRTH specifications for road & bridge
works.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
Mazdoor (Skilled) day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
b) Material

Supply of elastomeric slab seal expansion joint


assembly manufactured by using chloroprene,
elastomer for elastomeric slab unit conforming to
metre 12.000 12.000 12.000 27,202.73 326,432.76 326,432.76 326,432.76 M-094
clause 915.1 of IRC: 83 (part II), complete as per
approved drawings and standard specification
conforming to clause 2605 of MoRT&H Specification

Add 5 per cent of cost of material for anchorage


16,321.64 16,321.64 16,321.64
reinforcement, welding and other incidentals.

@ 20% on @ 20% on @ 20% on


c) Overhead charges 68,717.16 68,717.16 68,717.16
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 41,230.30 41,230.30 41,230.30
(a+b+c) (a+b+c) (a+b+c)
Cost for 12 m = (a+b+c+d) 453,533.26 453,533.26 453,533.26
Rate per m = (a+b+c+d)/12 37,794.44 37,794.44 37,794.44
Say 37,794.00 37,794.00 37,794.00
14.20 2600 Compression Seal Joint
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project

Providing and laying of compression seal joint


consisting of steel armoured nosing at two edges of
the joint gap suitably anchored to the deck concrete
and a preformed chloroprene elastomer or closed cell
foam joint sealer compressed and fixed into the joint
gap with special adhesive binder to cater for a
horizontal movement upto 40 mm and vertical
movement of 3 mm.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.036 0.036 0.036 617.00 22.21 22.21 22.21 L-12
Mazdoor day 0.600 0.600 0.600 511.52 306.91 306.91 306.91 L-13
Mazdoor (Skilled) day 0.300 0.300 0.300 565.73 169.72 169.72 169.72 L-15
b) Material
1. Galvanised angle sections 100mm x 100mm of
12mm thickness weldable structural steel as per IS:
kg 446.000 446.000 446.000 63.00 28,098.00 28,098.00 28,098.00 M-103
2062, 2 nos. of 12 m length each @ 17.7 kg/m and 5
per cent wastage.

Add 5 per cent of cost of above for structural steel


1,429.84 1,429.84 1,429.84
for anchorage, welding and other incidentals.

Preformed continuous chloroprene elastomer or


closed cell foam sealing element with high tear
metre 12.000 12.000 12.000 948.00 11,376.00 11,376.00 11,376.00 M-142
strength, vulcanised in a single operation for the full
length of a joint to ensure water tightness.

Add 1 per cent of cost of sealing element for


113.76 113.76 113.76
lubricant-cum-adhesive and other consumables.

@ 20% on @ 20% on @ 20% on


c) Overhead charges 8,303.29 8,303.29 8,303.29
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 4,981.97 4,981.97 4,981.97
(a+b+c) (a+b+c) (a+b+c)
Cost for 12 m = (a+b+c+d) 54,801.71 54,801.71 54,801.71
Rate per m = (a+b+c+d)/12 4,566.81 4,566.81 4,566.81
Say 4,567.00 4,567.00 4,567.00
Note 1. The installation shall be done by the manufacturer
or his authorised representative to the satisfaction of
the Engineer.
2. The concreting for joining the expansion joint
assembly with the deck has not been included in this
analysis as the same is catered in the quantities of
RCC deck.
3. The anchoring bars of the expansion joint
assembly shall be welded to the main reinforcement
of the deck.
14.21 2607 Strip Seal Expansion Joint

Providing and laying of a strip seal expansion joint


catering to maximum horizontal movement upto 70
mm, complete as per approved drawings and
standard specifications to be installed by the
manufacturer/supplier or their authorised
representative ensuring compliance to the
manufacturer's instructions for installation.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.050 0.050 0.050 617.00 30.85 30.85 30.85 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
Mazdoor (Skilled) day 0.250 0.250 0.250 565.73 141.43 141.43 141.43 L-15
b) Material

Supply of complete assembly of strip seal expansion


joint comprising of edge beams, anchorage, strip seal
metre 12.000 12.000 12.000 8,085.00 97,020.00 97,020.00 97,020.00 M-180
element and complete accessories as per approved
specifications and drawings.

Add 5 per cent of cost of material for anchorage


4,851.00 4,851.00 4,851.00
reinforcement, welding and other incidentals.

@ 20% on @ 20% on @ 20% on


c) Overhead charges 20,510.96 20,510.96 20,510.96
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 12,306.58 12,306.58 12,306.58
(a+b+c) (a+b+c) (a+b+c)
Cost for 12 m = (a+b+c+d) 135,372.34 135,372.34 135,372.34
Rate per m = (a+b+c+d)/12 11,281.03 11,281.03 11,281.03
Say 11,281.00 11,281.00 11,281.00
Note 1. The installation shall be done by the manufacturer
or his authorised representative to the satisfaction of
the Engineer.
2. The concreting for joining the expansion joint
assembly with the deck has not been included in this
analysis as the same is catered in the quantities of
RCC deck.
14.22 2600 Modular Strip / Box Seal Joint
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project

Providing and laying of a modular strip Box seal


expansion joint including anchorage catering to a
horizontal movement beyond 70 mm and upto
140mm, complete as per approved drawings and
standard specifications to be installed by the
manufacturer/supplier or their authorised
representative ensuring compliance to the
manufacturer's instructions for installation.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.056 0.056 0.056 617.00 34.55 34.55 34.55 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
Mazdoor (Skilled) day 0.400 0.400 0.400 565.73 226.29 226.29 226.29 L-15
b) Material

Supply of a modular strip/box seal joint assembly


comprising of edge beams, central beam,2 modules
chloroprene seal, anchorage elements, support and
metre 12.000 12.000 12.000 8,400.00 100,800.00 100,800.00 100,800.00 M-126
control system, all steel sections protected against
corrosion and installed by the manufacturer or his
authorised representative.

@ 20% on @ 20% on @ 20% on


c) Overhead charges 20,314.47 20,314.47 20,314.47
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 12,188.68 12,188.68 12,188.68
(a+b+c) (a+b+c) (a+b+c)

Cost for 12 m Modular strip/box seal joint = (a+b+c+d) 134,075.52 134,075.52 134,075.52
Rate per m = (a+b+c+d)/12 11,172.96 11,172.96 11,172.96
Say 11,173.00 11,173.00 11,173.00
Note 1. The installation shall be done by the manufacturer
or his authorised representative to the satisfaction of
the Engineer.
2. The concreting for joining the expansion joint
assembly with the deck has not been included in this
analysis as the same is catered in the quantities of
RCC deck.
3. The anchoring bars of the expansion joint
assembly shall be welded to the main reinforcement
of the deck.
14.23 2600 Modular Strip / Box Seal Joint

Providing and laying of a modular strip box seal


expansion joint catering to a horizontal movement
beyond 140mm and upto 210mm, complete as per
approved drawings and standard specifications to be
installed by the manufacturer/supplier or their
authorised representative ensuring compliance to the
manufacturer's instructions for installation.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.070 0.070 0.070 617.00 43.19 43.19 43.19 L-12
Mazdoor day 1.250 1.250 1.250 511.52 639.40 639.40 639.40 L-13
Mazdoor (Skilled) day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
b) Material

Supply of a modular box/box seal joint assembly


containing 3 modules/cells and comprising of edge
beams, two central beams, chloroprene seal,
anchorage elements, support and control system, all metre 12.000 12.000 12.000 8,400.00 100,800.00 100,800.00 100,800.00 M-127
steel sections protected against corrosion and
installed by the manufacturer or his authorised
representative.

@ 20% on @ 20% on @ 20% on


c) Overhead charges 20,353.09 20,353.09 20,353.09
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 12,211.85 12,211.85 12,211.85
(a+b+c) (a+b+c) (a+b+c)

Cost for 12 m Modular strip/box seal joint = (a+b+c+d) 134,330.40 134,330.40 134,330.40
Rate per m = (a+b+c+d)/12 11,194.20 11,194.20 11,194.20
Say 11,194.00 11,194.00 11,194.00
Note 1. The installation shall be done by the manufacturer
or his authorised representative to the satisfaction of
the Engineer.
2. The concreting for joining the expansion joint
assembly with the deck has not been included in this
analysis as the same is catered in the quantities of
RCC deck.
3. The anchoring bars of the expansion joint
assembly shall be welded to the main reinforcement
of the deck.
Painting with synthetic enamel paint bridge No. and
14.24
span arrangements
Painting two coats after filling the surface with
synthetic enamel paint bridge No. and span
arrangements as per as directed by Engineer.
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Unit = Nos.
Taking output = 1 Nos.
a) Labour
Mate day 0.006 0.006 0.006 617.00 3.70 3.70 3.70 L-12
Painter day 0.100 0.100 0.100 679.00 67.90 67.90 67.90 L-18
Mazdoor day 0.050 0.050 0.050 511.52 25.58 25.58 25.58 L-13
b) Material
Paint conforming to requirement of clause 803.3. Litre 0.300 0.300 0.300 172.36 51.71 51.71 51.71 M-131

Add for scaffolding @ 1 per cent of labour cost


0.97 0.97 0.97
where required
Add @ 5 per cent cost of labour and materials to
prepare the surface by filling minuts roughness on
7.44 7.44 7.44
the surface and priming the surface before laying 2
coats of painting.

Per Sqm Basic Cost of Labour & Material (a+b) 157.302 157.302 157.302

@ 20% on @ 20% on @ 20% on


c) Overhead charges 31.46 31.46 31.46
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 18.88 18.88 18.88
(a+b+c) (a+b+c) (a+b+c)
Cost for 1 No. = a+b+c+d 207.64 207.64 207.64
Rate per Nos. = (a+b+c+d)/40 207.64 207.64 207.64
Say 208.00 208.00 208.00

Bipolar corrosion inhibiting admixture in concrete for


protection of reinforced steel from corrosion(Admix
polydentate, bipolar, migratory, intergal non nitrate
14.25 base concrete penetrating corrosion inhibiting
admixture at dosage of 3Kg per cu.m. of concrete as
per manufactures specification. Inhibitor should
conforms to following-)

i. ASTM G-109-2005- Long term corrosion test


resulting in a corrosion rate of zero coulombs.

ii. JIS Z 1535- Accelerated corrosion test showing


significant reduction in corrosion using the admixture.

iii. ASTM G1- Immersion test for 720 hrs indicating


rebar weight loss less than 5 mpy
iv. ASTM G3- Polarization test by Tafel test indicating
Rebar weight loss of less than 5 mpy
Unit = cum
Taking output = 100.00 cum
a) Material

Corrosion Inhibiting Admixture @ 3 kg per cubic Meter kg 300.000 300.000 300.000 70.00 21,000.00 21,000.00 21,000.00

b) Overhead charges @ 20% on (a) @ 20% on (a) @ 20% on (a) 4,200.00 4,200.00 4,200.00

@ 10% on @ 10% on @ 10% on


c) Contractor's profit 2,520.00 2,520.00 2,520.00
(a+b) (a+b) (a+b)
Cost for 100 cum. = a+b+c 27,720.00 27,720.00 27,720.00
Rate per cum = (a+b+c)/100 277.20 277.20 277.20
Say 277.00 277.00 277.00

Providing structural steel for super-structure


14.26
complete as per drawing and technical specifications

Unit = MT
Taking output = 17.135 MT
a) Material
Structural steel in plates, angles, etc including 5 per
tonne 17.992 17.992 17.992 63,806.54 1,148,007.35 1,148,007.35 1,148,007.35 M-181
cent wastage
Nuts & bolts Kg 180.000 180.000 180.000 64.83 11,668.86 11,668.86 11,668.86 M-129
b) Labour
(for cutting, bending, making holes, joining, welding
and erecting in position)
Mate day 21.097 21.097 21.097 617.00 13,016.85 13,016.85 13,016.85 L-12
Fitter day 77.108 77.108 77.108 738.00 56,905.70 56,905.70 56,905.70 L-08
Blacksmith day 77.108 77.108 77.108 679.00 52,356.33 52,356.33 52,356.33 L-20
Welder day 77.108 77.108 77.108 738.00 56,905.70 56,905.70 56,905.70 L-02
Painter I Class day 32.385 32.385 32.385 679.00 21,989.42 21,989.42 21,989.42 L-18
Mazdoor day 263.708 263.708 263.708 511.52 134,891.92 134,891.92 134,891.92 L-13
Electrodes, cutting gas and other consumables @ 10
115,967.62 115,967.62 115,967.62
per cent of cost of (a) above
c) Machinery
Mobile hydraulic cran 10 tonne capacity (for
Hrs 68.540 68.540 68.540 1,240.05 84,993.03 84,993.03 84,993.03 P&M-104
fabrication)
Crane 35 tonne capacity (For loading & unloading @
Hrs 4.000 4.000 4.000 2,394.00 9,576.00 9,576.00 9,576.00 P&M-107
1hr for each operation)
Crane 35 tonne capacity (Forlifting and placing in
Hrs 4.000 4.000 4.000 2,394.00 9,576.00 9,576.00 9,576.00 P&M-107
position @ 2 hr)
Trailer 30 tonne capacity for transporting to site Hrs 4+L/15 4+L/15 4+L/15 2,883.30 17,299.80 17,299.80 17,299.80 P&M-014
Applying two coats primer before painting of truss
lits 899.588 899.588 899.588 288.00 259,081.34 259,081.34 259,081.34 M-145
and girder (42sqm/tonne)
Painting of Truss and Girder lits 899.588 899.588 899.588 180.70 162,555.55 162,555.55 162,555.55 M-058
Sundries @5% of above 107,739.57 107,739.57 107,739.57
Basic Cost of Labour, Material & Machinery (a+b+c)
132042.000 132042.000 132042.000
for 1 MT
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project

@ 20% on @ 20% on @ 20% on


d) Overhead charges 452,506.21 452,506.21 452,506.21
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 271,503.73 271,503.73 271,503.73
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 17.135 MT (a+b+c+d+e) 2,986,540.98 2,986,540.98 2,986,540.98
Rate for per MT (a+b+c+d+e)/17.135 174,294.78 174,294.78 174,294.78
Say 174,295.00 174,295.00 174,295.00
CHAPTER-15
BOX CELL STRUCTURE
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

15.01 304 Excavation for Structures


Earth work in excavation of foundation of structures
as per drawing and technical specification, including
setting out, construction of shoring and bracing,
removal of stumps and other deleterious matter,
dressing of sides and bottom and backfilling with
approved material.

I Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means
(i) Depth upto 3 m
a) Labour
Mate day 0.140 0.140 0.140 617.00 86.38 86.38 86.38 L-12
Mazdoor day 3.500 3.500 3.500 511.52 1,790.32 1,790.32 1,790.32 L-13
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 187.670 187.670 187.670
b) Overhead charges @ 20% on @ 20% on
@ 20% on (a) 375.34 375.34 375.34
(a) (a)
c) Contractor's profit @ 10% on @ 10% on @ 10% on
225.20 225.20 225.20
(a+b) (a+b) (a+b)
Cost for 10 cum = a+b+c 2,477.24 2,477.24 2,477.24
Rate per cum = (a+b+c)/10 247.72 247.72 247.72
Say 248.00 248.00 248.00
Note 1. Cost of dewatering may be added where required upto, 10 per cent of labour cost Assessment for dewatering shall be made as per site conditions.
2.The excavated earth can be used partially for backfilling of foundation pit and partly for road work except for marshy soil. Hence cost of disposal has not been added except for
marshy soil. This remark is common to all cases of item 12.1 excluding marshy soil.
3.The cost of shoring and shuttering, where needed, may be added @ 1 per cent on cost of excavation for open foundation.
15.01 A (ii) Depth 3 m to 6 m
(I)
a) Labour
Mate/Supervisor day 0.180 0.180 0.180 617.00 111.06 111.06 111.06 L-12
Mazdoor day 4.500 4.500 4.500 511.52 2,301.84 2,301.84 2,301.84 L-13
b) Overhead charges @ 20% on @ 20% on
@ 20% on (a) 482.58 482.58 482.58
(a) (a)
c) Contractor's profit @ 10% on @ 10% on @ 10% on
289.55 289.55 289.55
(a+b) (a+b) (a+b)
Cost for 10 cum = a+b+c 3,185.03 3,185.03 3,185.03
Rate per cum = (a+b+c)/10 318.50 318.50 318.50
Say 319.00 319.00 319.00
Note Cost of dewatering may be added where required upto 15 per cent of labour cost. Assessment for dewatering shall be done as per actual ground conditions.
15.01 A (iii) Depth above 6 m
(I)
a) Labour
Mate/Supervisor day 0.240 0.240 0.240 617.00 148.08 148.08 148.08 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
b) Overhead charges @ 20% on @ 20% on
@ 20% on (a) 643.44 643.44 643.44
(a) (a)
c) Contractor's profit @ 10% on @ 10% on @ 10% on
386.06 386.06 386.06
(a+b) (a+b) (a+b)
Cost for 10 cum = a+b+c 4,246.70 4,246.70 4,246.70
Rate per cum = (a+b+c)/10 424.67 424.67 424.67
Say 425.00 425.00 425.00
Note 1. Cost of dewatering may be added where required
upto 20 per cent of labour cost. Assessment for
dewatering shall be made as per site conditions..

15.01 B Mechanical Means


(I)
Depth upto 3 m
Unit = cum
Taking output = 330 cum
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Hydraulic Excavator
For excavation
(i) 1.2 cum bucket capacity hour 4.627 3,420.00 15,824.29 P&M-007
(ii) 1.1 cum bucket capacity hour 5.329 3,074.00 16,380.39 P&M-008
(iii) 0.9 cum bucket capacity hour 7.450 2,782.00 20,725.16 P&M-009
For backfilling (considering 60% of the excavated
material)
(i) 1.2 cum bucket capacity hour 2.776 3,420.00 9,494.57 P&M-007
(ii) 1.1 cum bucket capacity hour 3.197 3,074.00 9,828.23 P&M-008
(iii) 0.9 cum bucket capacity hour 4.470 2,782.00 12,435.10 P&M-009
Tipper for transportation of excess material to
dumping yard considering lead @ 1 km
(i) 18 cum capacity t-km 198.000 6.18 1,223.34 P&M-116
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

(ii) 14 cum capacity t-km 198.000 7.01 1,388.53 P&M-119


(iii) 10 cum capacity t-km 198.000 8.66 1,715.47 P&M-122
c) Overhead charges @ 20% on @ 20% on @ 20% on
6,166.36 6,377.35 7,833.07
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
3,699.82 3,826.41 4,699.84
(a+b+c) (a+b+c) (a+b+c)
Cost for 330 cum = a+b+c+d 40,697.98 42,090.51 51,698.24
Rate per cum = (a+b+c+d)/330 123.33 127.55 156.66
Say 123.00 128.00 157.00
Note Cost of dewatering upto 5 per cent of (a+b) may be
added, where required. Assessment for dewatering
shall be made as per site conditions..

15.01 B (ii) Depth 3 m to 6 m


(I)
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Hydraulic Excavator
For excavation
(i) 1.2 cum bucket capacity hour 4.674 3,420.00 15,984.13 P&M-007
(ii) 1.1 cum bucket capacity hour 5.383 3,074.00 16,545.84 P&M-008
(iii) 0.9 cum bucket capacity hour 7.525 2,782.00 20,934.51 P&M-009
For backfilling (considering 60% of the excavated
material)
(i) 1.2 cum bucket capacity hour 2.804 3,420.00 9,590.48 P&M-007
(ii) 1.1 cum bucket capacity hour 3.230 3,074.00 9,927.51 P&M-008
(iii) 0.9 cum bucket capacity hour 4.515 2,782.00 12,560.71 P&M-009
Tipper for transportation of excess material to
dumping yard considering lead @ 1 km
(i) 18 cum capacity t-km 180.000 6.18 1,112.13 P&M-116
(ii) 14 cum capacity t-km 180.000 7.01 1,262.30 P&M-119
(iii) 10 cum capacity t-km 180.000 8.66 1,559.52 P&M-122

c) Overhead charges @ 20% on @ 20% on @ 20% on


6,195.27 6,405.05 7,868.87
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
3,717.16 3,843.03 4,721.32
(a+b+c) (a+b+c) (a+b+c)
Cost for 300 cum = a+b+c+d 40,888.76 42,273.34 51,934.52
Rate per cum = (a+b+c+d)/300 136.30 140.91 173.12
Say 136.00 141.00 173.00
Note Cost of dewatering upto 7.5 per cent of (a+b)
may be added, where required. Assessment for
dewatering shall be made as per site conditions..

15.01 B (iii) Mechanical Means (Depth above 6 m)


(I)
Unit = cum
Taking output = 270 cum
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Hydraulic Excavator
For excavation
(i) 1.2 cum bucket capacity hour 4.732 3,420.00 16,183.93 P&M-007
(ii) 1.1 cum bucket capacity hour 5.450 3,074.00 16,752.67 P&M-008
(iii) 0.9 cum bucket capacity hour 7.619 2,782.00 21,196.19 P&M-009
For backfilling (considering 60% of the excavated
material)
(i) 1.2 cum bucket capacity hour 2.839 3,420.00 9,710.36 P&M-007
(ii) 1.1 cum bucket capacity hour 3.270 3,074.00 10,051.60 P&M-008
(iii) 0.9 cum bucket capacity hour 4.571 2,782.00 12,717.71 P&M-009
Tipper for transportation of excess material to
dumping yard considering lead @ 1 km
(i) 18 cum capacity t-km 162.000 6.18 1,000.92 P&M-116
(ii) 14 cum capacity t-km 162.000 7.01 1,136.07 P&M-119
(iii) 10 cum capacity t-km 162.000 8.66 1,403.57 P&M-122
c) Overhead charges @ 20% on @ 20% on @ 20% on
6,236.96 6,445.99 7,921.41
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
3,742.18 3,867.59 4,752.85
(a+b+c) (a+b+c) (a+b+c)
Cost for 270 cum = a+b+c+d 41,163.94 42,543.52 52,281.34
Rate per cum = (a+b+c+d)/270 152.46 157.57 193.63
Say 152.00 158.00 194.00
Note 1. Cost of dewatering upto 10 per cent of (a+b)
may be added, where required. Assessment for
dewatering shall be made as per site conditions..
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

2.Labour provided for excavation by mechanical


means includes that required for trimming of bottom
and side slopes.
15.01 II Ordinary Rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 5.000 5.000 5.000 511.52 2,557.60 2,557.60 2,557.60 L-13
b) Overhead charges @ 20% on (a) @ 20% on @ 20% on
@ 20% on (a) 536.20 536.20 536.20
(a) (a)
c) Contractor's profit @ 10% on (a+b) @ 10% on @ 10% on @ 10% on
321.72 321.72 321.72
(a+b) (a+b) (a+b)
Cost for 10 cum = a+b+c 3,538.92 3,538.92 3,538.92
Rate per cum = (a+b+c)/10 353.89 353.89 353.89
Say 354.00 354.00 354.00
Note Cost of dewatering upto 10 per cent of labour cost
may be added, where required. Assessment for
dewatering shall be made as per site conditions..

15.01 B Mechanical Means


(II)
Unit = cum
Taking output = 50 cum
a) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Machinery
Hydraulic Excavator
Excavator for excavation
(i) 1.2 cum bucket capacity hour 5.818 3,420.00 19,898.18 P&M-007
(ii) 1.1 cum bucket capacity hour 6.845 3,074.00 21,041.28 P&M-008
(iii) 0.9 cum bucket capacity hour 7.273 2,782.00 20,232.73 P&M-009
For loading
(i) 1.2 cum bucket capacity hour 0.872 3,420.00 2,983.70 P&M-007
(ii) 1.1 cum bucket capacity hour 1.005 3,074.00 3,088.56 P&M-008
(iii) 0.9 cum bucket capacity hour 1.405 2,782.00 3,907.78 P&M-009
Jack Hammer hour 5.818 6.845 7.273 206.00 1,198.55 1,410.05 1,498.18 P&M-010
Tipper
For transportation considering lead @ 1km
(i) 18 cum capacity t-km 75.000 6.18 463.39 P&M-116
(ii) 14 cum capacity t-km 75.000 7.01 525.96 P&M-119
(iii) 10 cum capacity t-km 75.000 8.66 649.80 P&M-122
For loading & unloading time
(i) 18 cum capacity hour 0.872 2,883.30 2,515.47 P&M-014
(ii) 14 cum capacity hour 1.005 2,556.75 2,568.86 P&M-015
(iii) 10 cum capacity hour 1.405 2,274.30 3,194.63 P&M-016
c) Overhead charges @ 20% on @ 20% on @ 20% on
5,733.58 6,048.66 6,218.34
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
3,440.15 3,629.20 3,731.01
(a+b+c) (a+b+c) (a+b+c)
Cost for 50 cum = a+b+c+d 37,841.61 39,921.17 41,041.06
Rate per cum = (a+b+c+d)/50 756.83 798.42 820.82
Say 757.00 798.00 821.00
Note 1.Cost of dewatering upto 10 per cent of (a+b), may
be added, where required Assessment for
dewatering shall be made as per site conditions.

2.In case of rock, foundation beyond3 m is not dug


and hence not included.
15.01 III Hard Rock ( requiring blasting )
Carrying out excavation in hard rock to achieve a
specified slope of the rock face by controlled use of
explosives and blasting accessories in properly
aligned and spaced drill holes, collection of the
excavated rock by a dozer, loading in tipper by a
front end loader and disposing of the material with all
lifts and lead upto 1000 m, all as specified in clause
No. 303

A Manual Means
Unit = cum
Taking output = 120 cum
a) Labour
Mate day 0.210 0.210 0.210 617.00 129.57 129.57 129.57 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Driller day 2.000 2.000 2.000 558.00 1,116.00 1,116.00 1,116.00 L-06
Blaster day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-03
b) Machinery
Air compressor hour 6.000 6.000 6.000 614.25 3,685.50 3,685.50 3,685.50 P&M-029
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

Jack Hammer for drilling holes (@ 4.5 m per hour)


hour 24.000 24.000 24.000 11.55 277.20 277.20 277.20 P&M-078
Jack Hammer (consider 5% of the volume for
dressing) hour 1.024 1.205 1.280 206.00 210.94 248.17 263.68 P&M-010
Hydraulic Excavator
Excavator for excavation
(i) 1.2 cum bucket capacity hour 1.024 3,420.00 3,502.08 P&M-007
(ii) 1.1 cum bucket capacity hour 1.205 3,074.00 3,703.27 P&M-008
(iii) 0.9 cum bucket capacity hour 1.280 2,782.00 3,560.96 P&M-009
For loading
(i) 1.2 cum bucket capacity hour 2.094 3,420.00 7,160.89 P&M-007
(ii) 1.1 cum bucket capacity hour 2.411 3,074.00 7,412.54 P&M-008
(iii) 0.9 cum bucket capacity hour 3.371 2,782.00 9,378.66 P&M-009
Tipper
For transportation considering lead @ 1 km
(i) 18 cum capacity t-km 180.000 6.18 1,112.13 P&M-116
(ii) 14 cum capacity t-km 180.000 7.01 1,262.30 P&M-119
(iii) 10 cum capacity t-km 180.000 8.66 1,559.52 P&M-122
For loading & unloading time
(i) 18 cum capacity hour 2.094 2,883.30 6,037.13 P&M-014
(ii) 14 cum capacity hour 2.411 2,556.75 6,165.26 P&M-015
(iii) 10 cum capacity hour 3.371 2,274.30 7,667.11 P&M-016
c) Materials
Small dia.Explosive at 0.40 kg / cum for 120 cum M-215
( 120 x 0.40 )
Explosive at 0.20 kg / cum for secondary blast @ kg 49.200 49.200 49.200 81.90 4,029.48 4,029.48 4,029.48
5%of the total volume ( 120 x 0.2x5% )
Electric detonators at 1 per hole for main blast holes M-217
(21x3+20*2)=103 nos no 69.000 69.000 69.000 21.00 1,449.00 1,449.00 1,449.00
Ordinary detonators @ 1 per hole for 10 secondary M-216
holes( required for 5% of the total quantity @ 0.6 m no 7.000 7.000 7.000 21.00 147.00 147.00 147.00
per hole for I cum )
Detonating fuse coil m 213.000 213.000 213.000 19.00 4,047.00 4,047.00 4,047.00 M-218
d) Overhead charges @ 20% on @ 20% on @ 20% on
6,913.27 7,066.95 7,794.62
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
4,147.96 4,240.17 4,676.77
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 120 cum = a+b+c+d+e 45,627.60 46,641.84 51,444.51
Rate per cum = (a+b+c+d+e)/120 380.23 388.68 428.70
Say 380.00 389.00 429.00
Note Cost of dewatering @ 10 per cent of (a+b) may
be added, where required Assessment for
dewatering shall be made as per site conditions.

15.01 IV Hard Rock ( blasting prohibited )


Unit = cum
Taking output = 35 cum
A Mechanical Means
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Jack Hammer hour 5.973 6.788 7.467 206.00 1,230.51 1,398.30 1,538.13 P&M-010
Hydraulic Excavator
Excavator for excavation
(i) 1.2 cum bucket capacity hour 5.973 3,420.00 20,428.80 P&M-007
(ii) 1.1 cum bucket capacity hour 6.788 3,074.00 20,865.94 P&M-008
(iii) 0.9 cum bucket capacity hour 7.467 2,782.00 20,772.27 P&M-009
For loading
(i) 1.2 cum bucket capacity hour 0.611 3,420.00 2,088.59 P&M-007
(ii) 1.1 cum bucket capacity hour 0.703 3,074.00 2,161.99 P&M-008
(iii) 0.9 cum bucket capacity hour 0.983 2,782.00 2,735.44 P&M-009
Tipper
For transportation to dumping yard considering lead
@ 1km
(i) 18 cum capacity t-km 52.500 6.18 324.37 P&M-116
(ii) 14 cum capacity t-km 52.500 7.01 368.17 P&M-119
(iii) 10 cum capacity t-km 52.500 8.66 454.86 P&M-122
For loading & unloading time
(i) 18 cum capacity hour 0.611 2,883.30 1,760.83 P&M-014
(ii) 14 cum capacity hour 0.703 2,556.75 1,798.20 P&M-015
(iii) 10 cum capacity hour 0.983 2,274.30 2,236.24 P&M-016

d) Overhead charges @ 20% on @ 20% on @ 20% on


5,381.10 5,533.00 5,761.87
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
3,228.66 3,319.80 3,457.12
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 35 cum = a+b+c+d 35,515.26 36,517.81 38,028.33
Rate per cum = (a+b+c+d)/35 1,014.72 1,043.37 1,086.52
Say 1,015.00 1,043.00 1,087.00
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

Note 1. Cost of dewatering upto10 per cent of (a+b), may


be added, where required Assessment for
dewatering shall be made as per site conditions.

2.In case of rock, foundation beyond3 m is not dug


and hence not included.
15.01 V Marshy Soil
Unit = cum
Taking output = 10 cum
Depth upto 3 m
A Manual means
a) Labour
Mate/Supervisor day 0.400 0.400 0.400 617.00 246.80 246.80 246.80 L-12
Mazdoor day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-13
b) Machinery
Tractor-trolley for removal. hour 2.670 2.670 2.670 1,876.50 5,010.26 5,010.26 5,010.26 P&M-026
c) Overhead charges @ 20% on @ 20% on @ 20% on
2,074.45 2,074.45 2,074.45
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,244.67 1,244.67 1,244.67
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 cum = a+b+c+d 13,691.38 13,691.38 13,691.38
Rate per cum = ( a+b+c+d)/ 10 1,369.14 1,369.14 1,369.14
Say 1,369.00 1,369.00 1,369.00
Note 1. Cost of dewatering @ 30 per cent of (a), may be
added, where required Assessment for dewatering
shall be made as per site conditions.

2. Shoring & strutting 15 per cent of (a), where


required may be added
3. It is assumed that Marshy Soil will be available
upto 3 m depth only. For deeper excavation below 3
m depth, refer analysis in item12.1 (i) to (iv) for
ordinary soil
15.01 B Mechanical Means
(V)
Unit = cum
Taking output = 260 cum
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 8.506 3,420.00 29,091.11 P&M-007
(ii) 1.1 cum bucket capacity hour 9.796 3,074.00 30,113.44 P&M-008
(iii) 0.9 cum bucket capacity hour 13.695 2,782.00 38,100.81 P&M-009
Tipper
For transportation to dumping yard considering lead
@ 1km
(i) 18 cum capacity t-km 390.000 6.18 2,409.62 P&M-116
(ii) 14 cum capacity t-km 390.000 7.01 2,734.99 P&M-119
(iii) 10 cum capacity t-km 390.000 8.66 3,378.96 P&M-122
For loading & unloading time
(i) 18 cum capacity hour 8.506 2,883.30 24,525.85 P&M-014
(ii) 14 cum capacity hour 9.796 2,556.75 25,046.37 P&M-015
(iii) 10 cum capacity hour 13.695 2,274.30 31,147.61 P&M-016
c) Material
Selected earth for refilling cum 156.000 156.000 156.000 222.00 34,632.00 34,632.00 34,632.00 M-164
c) Overhead charges @ 20% on @ 20% on @ 20% on
18,238.95 18,612.60 21,554.18
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
10,943.37 11,167.56 12,932.51
(a+b+c) (a+b+c) (a+b+c)
Cost for 260 cum = a+b+c+d 120,377.10 122,843.15 142,257.59
Rate per cum = (a+b+c+d)/260 462.99 472.47 547.14
Say 463.00 472.00 547.00
Note 1. Cost of dewatering @ 20 per cent of (a+b)
may be added, where required
2. Shoring & strutting @ 10 per cent of (a+b), where
required may be added
3. It is assumed that Marshy Soil will be available
upto 3 m depth only. For deeper excavation below 3
m depth, refer analysis in item 12.1 (i) to (iv) for
ordinary soil
15.01 VI Back Filling in Marshy Foundation Pits
(VI)
Unit : Cum
Taking Output : 6 cum
a) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor for dressing sides, bottom and backfilling
day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Machinery
Tractor-trolley for transportation hour 2.000 2.000 2.000 1,876.50 3,753.00 3,753.00 3,753.00 P&M-026
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

c) Overhead charges @ 20% on @ 20% on @ 20% on


1,072.32 1,072.32 1,072.32
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
643.39 643.39 643.39
(a+b+c) (a+b+c) (a+b+c)
Cost for 6 cum = a+b+c+d 7,077.31 7,077.31 7,077.31
Rate per cum = (a+b+c+d)/6 1,179.55 1,179.55 1,179.55
Say 1,180.00 1,180.00 1,180.00
15.02 304 Filling Annular Space Around Footing in Rock

Unit = cum
Taking out put = 1 cum
PCC-15 nominal mix. Rate may be taken as per item Item No. -
Say 8,121.00 8,168.00 8,347.00
15.11. 15.11
15.03 304 Sand Filling in Foundation Trenches as per Drawing
& Technical Specification
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading @ 30 mins per trip )

(i) 16 KL capacity hour 4.500 1,501.00 6,754.50 P&M-023


(ii) 12 KL capacity hour 6.010 1,327.00 7,975.27 P&M-024
(iii) 6 KL capacity hour 11.990 1,005.00 12,049.95 P&M-025
c) Material
Sand (assuming 20 per cent voids) at site cum 120.000 120.000 120.000 1,994.03 239,283.72 239,283.72 239,283.72 M-004
Water KL 18.000 18.000 18.000 16.00 288.00 288.00 288.00 M-191
d) Overhead charges @ 20% on @ 20% on @ 20% on
49,372.48 49,616.64 50,431.57
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
29,623.49 29,769.98 30,258.94
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per 100 cum = a+b+c+d+e 325,858.39 327,469.81 332,848.39
Rate per cum = (a+b+c+d+e)/100 3,258.58 3,274.70 3,328.48
Say 3,259.00 3,275.00 3,328.00
15.04 1300 Brick Masonry Work in Cement Mortar 1:3 in
Foundation complete excluding Pointing and
Plastering, as per Drawing and Technical
Specifications.
Unit = cum
Taking output = 5 cum
a) Material
Bricks Ist class each 2500.000 2500.000 2500.000 3.50 8,750.00 8,750.00 8,750.00 M-079
Cement mortar 1:3 (Rate as sub-analysis)
Sub-Analysis
cum 1.200 1.200 1.200 5,125.00 6,150.00 6,150.00 6,150.00 of Concrete -
20.01 (A)

Water for curing KL 2.415 2.415 2.415 16.00 38.64 38.64 38.64 M-191
b) Labour
Mate day 0.480 0.480 0.480 617.00 296.16 296.16 296.16 L-12
Mason day 4.000 4.000 4.000 679.00 2,716.00 2,716.00 2,716.00 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading @ 30 mins per trip )

(i) 16 KL capacity 0.017xL1+0.


hour 1,501.00 917.11 P&M-023
101
(ii) 12 KL capacity 0.022xL1+0.1
hour 1,327.00 1,053.64 P&M-024
34
(iii) 6 KL capacity 0.045xL1+0.
hour 1,005.00 1,626.09 P&M-025
268
c) Overhead charges @ 20% on @ 20% on @ 20% on
4,592.01 4,619.32 4,733.81
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
2,755.21 2,771.59 2,840.29
(a+b+c) (a+b+c) (a+b+c)
Cost for 5 cum = a+b+c+d 30,307.29 30,487.51 31,243.15
Rate per cum (a+b+c+d)/5 6,061.46 6,097.50 6,248.63
Say 6,061.00 6,098.00 6,249.00

15.05 Sub- (A) Cement Mortar 1:3 (1 cement : 3 sand)


analysis
Unit = 1 cum
Taking output = 1 cum
Cement mortar 1:3 (Rate as sub-analysis) Sub-Analysis
of Concrete -
Cum 1.000 1.000 1.000 5,125.00 5,125.00 5,125.00 5,125.00 20.01 (A)

c) Overhead charges @ 20% on @ 20% on @ 20% on


1,025.00 1,025.00 1,025.00
(a+b) (a+b) (a+b)
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

d) Contractor's profit @ 10% on @ 10% on @ 10% on


615.00 615.00 615.00
(a+b+c) (a+b+c) (a+b+c)
Cost for 1 cum = a+b+c+d 6,765.00 6,765.00 6,765.00
Say 6,765.00 6,765.00 6,765.00
(B) Cement Mortar 1:2 (1 cement : 2 sand)
Unit = 1 cum
Taking output = 1 cum
Cement mortar 1:2 (Rate as sub-analysis) Sub-Analysis
of Concrete -
Cum 1.000 1.000 1.000 5,695.00 5,695.00 5,695.00 5,695.00 20.01 (B)

c) Overhead charges @ 20% on @ 20% on @ 20% on


1,139.00 1,139.00 1,139.00
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
683.40 683.40 683.40
(a+b+c) (a+b+c) (a+b+c)
Cost for 1 cum = a+b+c+d 7,517.40 7,517.40 7,517.40
Say 7,517.00 7,517.00 7,517.00
(C) Cement Mortar 1:4 (1 cement : 4 sand)
Unit = 1 cum
Taking output = 1 cum
Cement mortar 1:4 (Rate as sub-analysis) Sub-Analysis
of Concrete -
Cum 1.000 1.000 1.000 4,730.00 4,730.00 4,730.00 4,730.00 20.01 (C)

c) Overhead charges @ 20% on @ 20% on @ 20% on


946.00 946.00 946.00
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
567.60 567.60 567.60
(a+b+c) (a+b+c) (a+b+c)
Cost for 1 cum = a+b+c+d 6,243.60 6,243.60 6,243.60
Say 6,244.00 6,244.00 6,244.00
(D) Cement Mortar1:6 (1cement :6 sand)
Unit = 1 cum
Taking output = 1 cum
Cement Mortar1:6 (Rate as sub-analysis) Sub-Analysis
of Concrete -
Cum 1.000 1.000 1.000 4,588.00 4,588.00 4,588.00 4,588.00 20.01 (D)

c) Overhead charges @ 20% on @ 20% on @ 20% on


917.60 917.60 917.60
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
550.56 550.56 550.56
(a+b+c) (a+b+c) (a+b+c)
Cost for 1 cum = a+b+c+d 6,056.16 6,056.16 6,056.16
Say 6,056.00 6,056.00 6,056.00
15.06 1400 Stone Masonry Work in Cement Mortar 1:3 in
Foundation complete as per Drawing and Technical
Specifications.
Unit = cum
Taking output = 5 cum
1405.4 (A) Square Rubble Coursed Rubble Masonry (first sort)

a) Material
Stone cum 5.500 5.500 5.500 933.45 5,133.98 5,133.98 5,133.98 M-170
Through and bond stone each 35.000 35.000 35.000 59.77 2,091.95 2,091.95 2,091.95 M-184
(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as sub-analysis)
Sub-Analysis
cum 1.500 1.500 1.500 5,125.00 7,687.50 7,687.50 7,687.50 of Concrete -
20.01 (A)

b) Labour
Mate day 0.660 0.660 0.660 617.00 407.22 407.22 407.22 L-12
Mason day 7.500 7.500 7.500 679.00 5,092.50 5,092.50 5,092.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Overhead charges @ 20% on @ 20% on @ 20% on
5,003.37 5,003.37 5,003.37
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
3,002.02 3,002.02 3,002.02
(a+b+c) (a+b+c) (a+b+c)
Cost for 5 cum = a+b+c+d 33,022.21 33,022.21 33,022.21
Rate per cum (a+b+c+d)/5 6,604.44 6,604.44 6,604.44
Say 6,604.00 6,604.00 6,604.00
1404.3 (B) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.500 5.500 5.500 611.60 3,363.80 3,363.80 3,363.80 M-147
Through and bond stone each 35.000 35.000 35.000 59.77 2,091.95 2,091.95 2,091.95 M-184
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in sub-analysis)
Sub-Analysis
cum 1.550 1.550 1.550 5,125.00 7,943.75 7,943.75 7,943.75 of Concrete -
20.01 (A)

b) Labour
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

Mate day 0.600 0.600 0.600 617.00 370.20 370.20 370.20 L-12
Mason day 6.000 6.000 6.000 679.00 4,074.00 4,074.00 4,074.00 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Overhead charges @ 20% on @ 20% on @ 20% on
4,489.48 4,489.48 4,489.48
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
2,693.69 2,693.69 2,693.69
(a+b+c) (a+b+c) (a+b+c)
Cost for 5 cum = a+b+c+d 29,630.54 29,630.54 29,630.54
Rate per cum (a+b+c+d)/5 5,926.11 5,926.11 5,926.11
Say 5,926.00 5,926.00 5,926.00
Note The labour already considered in cement mortar has
been taken into account while proposing labour for
masonry works.
15.07 1300 Brick Masonry Work in Cement Mortar 1:3 in Sub-
structure complete excluding Pointing and Plastering,
as per Drawing and Technical Specifications.

Unit = cum
Taking output = 1 cum
a) Material
Bricks Ist class each 500.000 500.000 500.000 3.50 1,750.00 1,750.00 1,750.00 M-079
Cement mortar 1:3 (Rate as sub-analysis)
Sub-Analysis
cum 0.240 0.240 0.240 5,125.00 1,230.00 1,230.00 1,230.00 of Concrete -
20.01 (A)

Water for curing KL 0.483 0.483 0.483 16.00 7.73 7.73 7.73 M-191
b) Labour
Mate day 0.064 0.064 0.064 617.00 39.49 39.49 39.49 L-12
Mason day 0.800 0.800 0.800 679.00 543.20 543.20 543.20 L-10
Mazdoor day 0.800 0.800 0.800 511.52 409.22 409.22 409.22 L-13
Add for scaffolding @ 5 Percent of cost of material
and labour 198.98 198.98 198.98
c) Machinery

Water tanker (speed @ 20km/hr and return speed @


30 km/hr and spreading @ 30 mins per trip )

(i) 16 KL capacity 0.003xL1+0.


hour 1,501.00 165.11 P&M-023
020
(ii) 12 KL capacity 0.004xL1+0.0
hour 1,327.00 195.07 P&M-024
27
(iii) 6 KL capacity 0.009xL1+0.
hour 1,005.00 325.62 P&M-025
054
c) Overhead charges @ 20% on @ 20% on @ 20% on
868.74 874.74 900.85
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
521.25 524.84 540.51
(a+b+c) (a+b+c) (a+b+c)
Cost for 1 cum = a+b+c+d 5,733.72 5,773.26 5,945.59
Rate per cum (a+b+c+d)/5 5,733.72 5,773.26 5,945.59
Say 5,734.00 5,773.00 5,946.00
15.08 1300
Pointing with cement mortar (1:3) on brick work in
sub-structure as per Technical specification.

Unit = sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as sub-analysis)
Sub-Analysis
cum 0.030 0.030 0.030 5,125.00 153.75 153.75 153.75 of Concrete -
20.01 (A)

b) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mason day 0.500 0.500 0.500 679.00 339.50 339.50 339.50 L-10
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
c) Overhead charges @ 20% on @ 20% on @ 20% on
154.74 154.74 154.74
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
92.84 92.84 92.84
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm = a+b+c+d 1,021.27 1,021.27 1,021.27
Rate per sqm (a+b+c+d)/10 102.13 102.13 102.13
Say 102.00 102.00 102.00
15.09 1300
Plastering with cement mortar (1:3 ) on brick work in
sub-structure as per Technical Specification

Unit = sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as sub-analysis)
Sub-Analysis
cum 0.144 0.144 0.144 5,125.00 738.00 738.00 738.00 of Concrete -
20.01 (A)

Water for curing KL 0.139 0.139 0.139 16.00 2.22 2.22 2.22 M-191
b) Labour
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mason day 0.500 0.500 0.500 679.00 339.50 339.50 339.50 L-10
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
Add for scaffolding @ 5 Percent of cost of material
and labour 68.01 68.01 68.01
c) Machinery

Water tanker (speed @ 20km/hr and return speed @


30 km/hr and spreading @ 30 mins per trip )

(i) 16 KL capacity 0.001xL1+0.


hour 1,501.00 54.04 P&M-023
006
(ii) 12 KL capacity 0.001xL1+0.0
hour 1,327.00 50.43 P&M-024
08
(iii) 6 KL capacity 0.003xL1+0.
hour 1,005.00 106.53 P&M-025
016
c) Overhead charges @ 20% on @ 20% on @ 20% on
296.44 295.72 306.94
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
177.86 177.43 184.16
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm = a+b+c+d 1,956.51 1,951.75 2,025.81
Rate per sqm (a+b+c+d)/10 195.65 195.17 202.58
Say 196.00 195.00 203.00
15.10 1300 Stone masonry work in cement mortar 1:3 in sub-
structure complete as per drawing and Technical
Specification
(A) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.000 1.000 1.000 611.60 611.60 611.60 611.60 M-147
Through and bond stone each 7.000 7.000 7.000 59.77 418.39 418.39 418.39 M-184
(7nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in sub-analysis)
Sub-Analysis
cum 0.330 0.330 0.330 5,125.00 1,691.25 1,691.25 1,691.25 of Concrete -
20.01 (A)

Water for curing KL 0.966 0.966 0.966 16.00 15.46 15.46 15.46 M-191
b) Labour
Mate day 0.096 0.096 0.096 617.00 59.23 59.23 59.23 L-12
Mason day 1.200 1.200 1.200 679.00 814.80 814.80 814.80 L-10
Mazdoor day 1.200 1.200 1.200 511.52 613.82 613.82 613.82 L-13
Add for scaffolding @ 5 Percent of cost of material
and labour 211.23 211.23 211.23
c) Machinery

Water tanker (speed @ 20km/hr and return speed @


30 km/hr and spreading @ 30 mins per trip )

(i) 16 KL capacity 0.007xL1+0.


hour 1,501.00 375.25 P&M-023
040
(ii) 12 KL capacity 0.009xL1+0.0
hour 1,327.00 429.95 P&M-024
54
(iii) 6 KL capacity 0.018xL1+0.
hour 1,005.00 650.24 P&M-025
107
c) Overhead charges @ 20% on @ 20% on @ 20% on
962.21 973.15 1,017.20
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
577.32 583.89 610.32
(a+b+c) (a+b+c) (a+b+c)
Cost for 1 cum = a+b+c+d 6,350.56 6,422.76 6,713.54
Rate per cum (a+b+c+d)/1 6,350.56 6,422.76 6,713.54
Say 6,351.00 6,423.00 6,714.00
(B) Coursed rubble masonry (first sort )
( coursed/uncoursed )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.100 1.100 1.100 933.45 1,026.80 1,026.80 1,026.80 M-170
Through and bond stone each 7.000 7.000 7.000 59.77 418.39 418.39 418.39 M-184
(7nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in sub-analysis)
Sub-Analysis
cum 0.330 0.330 0.330 5,125.00 1,691.25 1,691.25 1,691.25 of Concrete -
(A)

Water for curing KL 0.966 0.966 0.966 16.00 15.46 15.46 15.46 M-191
b) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.500 1.500 1.500 511.52 767.28 767.28 767.28 L-13
Add for scaffolding @ 5 Percent of cost of material
and labour 250.59 250.59 250.59
c) Machinery
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

Water tanker (speed @ 20km/hr and return speed @


30 km/hr and spreading @ 30 mins per trip )

(i) 16 KL capacity 0.007xL1+0.


hour 1,501.00 375.25 P&M-023
040
(ii) 12 KL capacity 0.009xL1+0.0
hour 1,327.00 429.95 P&M-024
54
(iii) 6 KL capacity 0.018xL1+0.
hour 1,005.00 650.24 P&M-025
107
c) Overhead charges @ 20% on @ 20% on @ 20% on
1,127.51 1,138.45 1,182.51
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
676.51 683.07 709.50
(a+b+c) (a+b+c) (a+b+c)
Cost for 1 cum = a+b+c+d 7,441.56 7,513.76 7,804.54
Rate per cum (a+b+c+d)/1 7,441.56 7,513.76 7,804.54
Say 7,442.00 7,514.00 7,805.00
(C) Ashlar masonry ( first sort ) Plain ashlar
( coursed/uncoursed )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.100 1.100 1.100 933.45 1,026.80 1,026.80 1,026.80 0.00
Through and bond stone each 7.000 7.000 7.000 59.77 418.39 418.39 418.39 M-184
(7nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in sub-analysis)
Sub-Analysis
cum 0.330 0.330 0.330 5,125.00 1,691.25 1,691.25 1,691.25 of Concrete -
(A)

Water for curing KL 0.966 0.966 0.966 16.00 15.46 15.46 15.46 M-191
b) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mason day 2.500 2.500 2.500 679.00 1,697.50 1,697.50 1,697.50 L-10
Mazdoor day 2.500 2.500 2.500 511.52 1,278.80 1,278.80 1,278.80 L-13
Add for scaffolding @ 5 Percent of cost of material
and labour 312.58 312.58 312.58
c) Machinery

Water tanker (speed @ 20km/hr and return speed @


30 km/hr and spreading @ 30 mins per trip )

(i) 16 KL capacity 0.007xL1+0.


hour 1,501.00 375.25 P&M-023
040
(ii) 12 KL capacity 0.009xL1+0.0
hour 1,327.00 429.95 P&M-024
54
(iii) 6 KL capacity 0.018xL1+0.
hour 1,005.00 650.24 P&M-025
107
c) Overhead charges @ 20% on @ 20% on @ 20% on
1,387.88 1,398.82 1,442.88
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
832.73 839.29 865.73
(a+b+c) (a+b+c) (a+b+c)
Cost for 1 cum = a+b+c+d 9,160.04 9,232.24 9,523.02
Rate per cum (a+b+c+d)/1 9,160.04 9,232.24 9,523.02
Say 9,160.00 9,232.00 9,523.00
15.11 1500, Plain/Reinforced Cement Concrete in Open
1700 & Foundation complete as per Drawing and Technical
2100 Specifications.
A PCC Grade M15
Case I PCC Grade M15 using batching plant & Concrete
pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,176.00 125,280.00 125,280.00 125,280.00 of Concrete -
20.03

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.
hour 1,501.00 5,892.93 P&M-023
656
(ii) 12 KL capacity 0.143xL1+0.8
hour 1,327.00 6,853.96 P&M-024
75
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

(iii) 6 KL capacity 0.292xL1+1.


hour 1,005.00 10,562.55 P&M-025
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 5594.000 5626.000 5749.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 16,779.54 16,875.64 17,246.50

e) Overhead charges @ 20% on @ 20% on @ 20% on


36,914.99 37,126.41 37,942.30
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
22,148.99 22,275.85 22,765.38
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 30 cum = a+b+c+d+e+f 243,638.91 245,034.33 250,419.21


Rate per cum = (a+b+c+d+e+f)/30 8,121.30 8,167.81 8,347.31
Say 8,121.00 8,168.00 8,347.00
Case II PCC Grade M15 using batching plant & manual
placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 4,176.00 62,640.00 62,640.00 62,640.00 of Concrete -
20.03

Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.055xL1+0.
hour 1,501.00 2,968.98 P&M-023
328
(ii) 12 KL capacity 0.073xL1+0.4
hour 1,327.00 3,487.36 P&M-024
38
(iii) 6 KL capacity 0.146xL1+0.
hour 1,005.00 5,281.28 P&M-025
875
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 5879.000 5914.000 6033.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 8,817.89 8,869.73 9,049.12

e) Overhead charges @ 20% on @ 20% on @ 20% on


19,399.36 19,513.40 19,908.07
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
11,639.62 11,708.04 11,944.84
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 15 cum = a+b+c+d+e+f 128,035.78 128,788.46 131,393.23


Rate per cum = (a+b+c+d+e+f)/15 8,535.72 8,585.90 8,759.55
Say 8,536.00 8,586.00 8,760.00
15.11 B PCC Grade M20
Case I PCC Grade M20 using batching plant transit mixer &
Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,518.00 135,540.00 135,540.00 135,540.00 of Concrete -
20.04

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.
hour 1,501.00 5,892.93 P&M-023
656
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

(ii) 12 KL capacity 0.146xL1+0.8


hour 1,327.00 6,973.39 P&M-024
75
(iii) 6 KL capacity 0.292xL1+1.
hour 1,005.00 10,562.55 P&M-025
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 5936.000 5972.000 6091.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 17,805.54 17,913.59 18,272.50

e) Overhead charges @ 20% on @ 20% on @ 20% on


39,172.19 39,409.89 40,199.50
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
23,503.31 23,645.93 24,119.70
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 30 cum = a+b+c+d+e+f 258,536.43 260,105.26 265,316.73


Rate per cum = (a+b+c+d+e+f)/30 8,617.88 8,670.18 8,843.89
Say 8,618.00 8,670.00 8,844.00
Case II PCC Grade M20 using batching plant transit mixer &
manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 4,518.00 67,770.00 67,770.00 67,770.00 of Concrete -
20.04

Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.055xL1+0.
hour 1,501.00 2,968.98 P&M-023
328
(ii) 12 KL capacity 0.073xL1+0.4
hour 1,327.00 3,487.36 P&M-024
38
(iii) 6 KL capacity 0.146xL1+0.
hour 1,005.00 5,281.28 P&M-025
875
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6221.000 6256.000 6375.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 9,330.89 9,382.73 9,562.12

e) Overhead charges @ 20% on @ 20% on @ 20% on


20,527.96 20,642.00 21,036.67
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
12,316.78 12,385.20 12,622.00
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 15 cum = a+b+c+d+e+f 135,484.54 136,237.22 138,841.99


Rate per cum = (a+b+c+d+e+f)/15 9,032.30 9,082.48 9,256.13
Say 9,032.00 9,082.00 9,256.00
15.11 C RCC Grade M20
Case I RCC Grade M20 using batching plant transit mixer &
Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,533.00 135,990.00 135,990.00 135,990.00 of Concrete -
20.05

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

(i) 16 KL capacity 0.109xL1+0.


hour 1,501.00 5,892.93 P&M-023
656
(ii) 12 KL capacity 0.146xL1+0.8
hour 1,327.00 6,973.39 P&M-024
75
(iii) 6 KL capacity 0.292xL1+1.
hour 1,005.00 10,562.55 P&M-025
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 5969.000 6005.000 6124.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 17,904.16 18,012.21 18,371.12

e) Overhead charges @ 20% on @ 20% on @ 20% on


39,389.15 39,626.85 40,416.47
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
23,633.49 23,776.11 24,249.88
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 30 cum = a+b+c+d+e+f 259,968.39 261,537.22 266,748.69


Rate per cum = (a+b+c+d+e+f)/30 8,665.61 8,717.91 8,891.62
Say 8,666.00 8,718.00 8,892.00
Case II RCC Grade M20 using batching plant transit mixer &
manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 4,533.00 67,995.00 67,995.00 67,995.00 of Concrete -
20.05

Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.420 0.420 0.420 617.00 259.14 259.14 259.14 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.055xL1+0.
hour 1,501.00 2,968.98 P&M-023
328
(ii) 12 KL capacity 0.073xL1+0.4
hour 1,327.00 3,487.36 P&M-024
38
(iii) 6 KL capacity 0.146xL1+0.
hour 1,005.00 5,281.28 P&M-025
875
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6272.000 6306.000 6426.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 9,407.01 9,458.85 9,638.24

e) Overhead charges @ 20% on @ 20% on @ 20% on


20,695.42 20,809.47 21,204.13
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
12,417.25 12,485.68 12,722.48
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 15 cum = a+b+c+d+e+f 136,589.80 137,342.49 139,947.26


Rate per cum = (a+b+c+d+e+f)/15 9,105.99 9,156.17 9,329.82
Say 9,106.00 9,156.00 9,330.00
15.11 D PCC Grade M25
Case I PCC Grade M25 using batching plant transit mixer &
Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,793.00 143,790.00 143,790.00 143,790.00 of Concrete -
20.06

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

Water tanker ( speed @ 20km/hr and return speed


@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.
hour 1,501.00 5,892.93 P&M-023
656
(ii) 12 KL capacity 0.146xL1+0.8
hour 1,327.00 6,973.39 P&M-024
75
(iii) 6 KL capacity 0.292xL1+1.
hour 1,005.00 10,562.55 P&M-025
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6211.000 6247.000 6366.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 18,630.54 18,738.59 19,097.50

e) Overhead charges @ 20% on @ 20% on @ 20% on


40,987.19 41,224.89 42,014.50
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
24,592.31 24,734.93 25,208.70
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 30 cum = a+b+c+d+e+f 270,515.43 272,084.26 277,295.73


Rate per cum = (a+b+c+d+e+f)/30 9,017.18 9,069.48 9,243.19
Say 9,017.00 9,069.00 9,243.00
Case II PCC Grade M25 using batching plant transit mixer &
manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 4,793.00 71,895.00 71,895.00 71,895.00 of Concrete -
20.06

Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.055xL1+0.
hour 1,501.00 2,968.98 P&M-023
328
(ii) 12 KL capacity 0.073xL1+0.4
hour 1,327.00 3,487.36 P&M-024
38
(iii) 6 KL capacity 0.146xL1+0.
hour 1,005.00 5,281.28 P&M-025
875
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6496.000 6531.000 6650.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 9,743.39 9,795.23 9,974.62

e) Overhead charges @ 20% on @ 20% on @ 20% on


21,435.46 21,549.50 21,944.17
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
12,861.28 12,929.70 13,166.50
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 15 cum = a+b+c+d+e+f 141,474.04 142,226.72 144,831.49


Rate per cum = (a+b+c+d+e+f)/15 9,431.60 9,481.78 9,655.43
Say 9,432.00 9,482.00 9,655.00
15.11 E RCC Grade M25
Case I RCC Grade M25 using batching plant transit mixer &
Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,945.00 148,350.00 148,350.00 148,350.00 of Concrete -
20.07

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.
hour 1,501.00 5,892.93 P&M-023
656
(ii) 12 KL capacity 0.146xL1+0.8
hour 1,327.00 6,973.39 P&M-024
75
(iii) 6 KL capacity 0.292xL1+1.
hour 1,005.00 10,562.55 P&M-025
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6381.000 6417.000 6536.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 19,140.16 19,248.21 19,607.12

e) Overhead charges @ 20% on @ 20% on @ 20% on


42,108.35 42,346.05 43,135.67
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
25,265.01 25,407.63 25,881.40
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 30 cum = a+b+c+d+e+f 277,915.11 279,483.94 284,695.41


Rate per cum = (a+b+c+d+e+f)/30 9,263.84 9,316.13 9,489.85
Say 9,264.00 9,316.00 9,490.00
Case II RCC Grade M25 using batching plant transit mixer &
manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 4,945.00 74,175.00 74,175.00 74,175.00 of Concrete -
20.07

Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.420 0.420 0.420 617.00 259.14 259.14 259.14 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.055xL1+0.
hour 1,501.00 2,968.98 P&M-023
328
(ii) 12 KL capacity 0.073xL1+0.4
hour 1,327.00 3,487.36 P&M-024
38
(iii) 6 KL capacity 0.146xL1+0.
hour 1,005.00 5,281.28 P&M-025
875
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6684.000 6718.000 6838.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 10,025.01 10,076.85 10,256.24

e) Overhead charges @ 20% on @ 20% on @ 20% on


22,055.02 22,169.07 22,563.73
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
13,233.01 13,301.44 13,538.24
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 15 cum = a+b+c+d+e+f 145,563.16 146,315.85 148,920.62


Rate per cum = (a+b+c+d+e+f)/15 9,704.21 9,754.39 9,928.04
Say 9,704.00 9,754.00 9,928.00
15.11 F PCC Grade M30
Case I PCC Grade M30 using batching plant transit mixer &
Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,819.00 144,570.00 144,570.00 144,570.00 of Concrete -
20.08

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

Transit truck agitator


For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.
hour 1,501.00 5,892.93 P&M-023
656
(ii) 12 KL capacity 0.146xL1+0.8
hour 1,327.00 6,973.39 P&M-024
75
(iii) 6 KL capacity 0.292xL1+1.
hour 1,005.00 10,562.55 P&M-025
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6237.000 6273.000 6392.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 18,708.54 18,816.59 19,175.50

e) Overhead charges @ 20% on @ 20% on @ 20% on


41,158.79 41,396.49 42,186.10
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
24,695.27 24,837.89 25,311.66
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 30 cum = a+b+c+d+e+f 271,647.99 273,216.82 278,428.29


Rate per cum = (a+b+c+d+e+f)/30 9,054.93 9,107.23 9,280.94
Say 9,055.00 9,107.00 9,281.00
Case II PCC Grade M30 using batching plant transit mixer &
manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 4,819.00 72,285.00 72,285.00 72,285.00 of Concrete -
20.08

Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.055xL1+0.
hour 1,501.00 2,968.98 P&M-023
328
(ii) 12 KL capacity 0.073xL1+0.4
hour 1,327.00 3,487.36 P&M-024
38
(iii) 6 KL capacity 0.146xL1+0.
hour 1,005.00 5,281.28 P&M-025
875
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6522.000 6557.000 6676.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 9,782.39 9,834.23 10,013.62

e) Overhead charges @ 20% on @ 20% on @ 20% on


21,521.26 21,635.30 22,029.97
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
12,912.76 12,981.18 13,217.98
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 15 cum = a+b+c+d+e+f 142,040.32 142,793.00 145,397.77


Rate per cum = (a+b+c+d+e+f)/15 9,469.35 9,519.53 9,693.18
Say 9,469.00 9,520.00 9,693.00
15.11 G RCC Grade M30
Case I RCC Grade M30 using batching plant transit mixer &
Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 5,032.00 150,960.00 150,960.00 150,960.00 of Concrete -
20.09

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.
hour 1,501.00 5,892.93 P&M-023
656
(ii) 12 KL capacity 0.146xL1+0.8
hour 1,327.00 6,973.39 P&M-024
75
(iii) 6 KL capacity 0.292xL1+1.
hour 1,005.00 10,562.55 P&M-025
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6468.000 6504.000 6623.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 19,401.16 19,509.21 19,868.12

e) Overhead charges @ 20% on @ 20% on @ 20% on


42,682.55 42,920.25 43,709.87
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
25,609.53 25,752.15 26,225.92
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 30 cum = a+b+c+d+e+f 281,704.83 283,273.66 288,485.13


Rate per cum = (a+b+c+d+e+f)/30 9,390.16 9,442.46 9,616.17
Say 9,390.00 9,442.00 9,616.00
Case II RCC Grade M30 using batching plant transit mixer &
manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 5,032.00 75,480.00 75,480.00 75,480.00 of Concrete -
20.09

Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.420 0.420 0.420 617.00 259.14 259.14 259.14 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.055xL1+0.
hour 1,501.00 2,968.98 P&M-023
328
(ii) 12 KL capacity 0.073xL1+0.4
hour 1,327.00 3,487.36 P&M-024
38
(iii) 6 KL capacity 0.146xL1+0.
hour 1,005.00 5,281.28 P&M-025
875
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 7448.000 7486.000 7617.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 10,155.51 10,207.35 10,386.74

e) Overhead charges @ 20% on @ 20% on @ 20% on


22,342.12 22,456.17 22,850.83
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
13,405.27 13,473.70 13,710.50
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 15 cum = a+b+c+d+e+f 147,458.02 148,210.71 150,815.48


Rate per cum = (a+b+c+d+e+f)/15 9,830.53 9,880.71 10,054.37
Say 9,831.00 9,881.00 10,054.00
15.11 H RCC Grade M35
Case I RCC Grade M35 using batching plant transit mixer &
Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 5,186.00 155,580.00 155,580.00 155,580.00 of Concrete -
20.11

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.
hour 1,501.00 5,892.93 P&M-023
656
(ii) 12 KL capacity 0.146xL1+0.8
hour 1,327.00 6,973.39 P&M-024
75
(iii) 6 KL capacity 0.292xL1+1.
hour 1,005.00 10,562.55 P&M-025
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6622.000 6658.000 6777.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 19,863.16 19,971.21 20,330.12

e) Overhead charges @ 20% on @ 20% on @ 20% on


43,698.95 43,936.65 44,726.27
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
26,219.37 26,361.99 26,835.76
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 30 cum = a+b+c+d+e+f 288,413.07 289,981.90 295,193.37


Rate per cum = (a+b+c+d+e+f)/30 9,613.77 9,666.06 9,839.78
Say 9,614.00 9,666.00 9,840.00
Case II RCC Grade M35 using batching plant transit mixer &
manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 5,186.00 77,790.00 77,790.00 77,790.00 of Concrete -
20.11

Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.420 0.420 0.420 617.00 259.14 259.14 259.14 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.055xL1+0.
hour 1,501.00 2,968.98 P&M-023
328
(ii) 12 KL capacity 0.073xL1+0.4
hour 1,327.00 3,487.36 P&M-024
38
(iii) 6 KL capacity 0.146xL1+0.
hour 1,005.00 5,281.28 P&M-025
875
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6925.000 6959.000 7079.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 10,386.51 10,438.35 10,617.74

e) Overhead charges @ 20% on @ 20% on @ 20% on


22,850.32 22,964.37 23,359.03
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
13,710.19 13,778.62 14,015.42
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 15 cum = a+b+c+d+e+f 150,812.14 151,564.83 154,169.60


Rate per cum = (a+b+c+d+e+f)/15 10,054.14 10,104.32 10,277.97
Say 10,054.00 10,104.00 10,278.00
15.11 I RCC Grade M40
Case I RCC Grade M40 using batching plant transit mixer &
Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 5,519.00 165,570.00 165,570.00 165,570.00 of Concrete -
20.12

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.
hour 1,501.00 5,892.93 P&M-023
656
(ii) 12 KL capacity 0.146xL1+0.8
hour 1,327.00 6,973.39 P&M-024
75
(iii) 6 KL capacity 0.292xL1+1.
hour 1,005.00 10,562.55 P&M-025
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6955.000 6991.000 7110.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 20,862.16 20,970.21 21,329.12

e) Overhead charges @ 20% on @ 20% on @ 20% on


45,896.75 46,134.45 46,924.07
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
27,538.05 27,680.67 28,154.44
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 30 cum = a+b+c+d+e+f 302,918.55 304,487.38 309,698.85


Rate per cum = (a+b+c+d+e+f)/30 10,097.29 10,149.58 10,323.29
Say 10,097.00 10,150.00 10,323.00
Case II RCC Grade M40 using batching plant transit mixer &
manual placing
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 15.000 15.000 15.000 5,519.00 82,785.00 82,785.00 82,785.00 of Concrete -
20.12

Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.420 0.420 0.420 617.00 259.14 259.14 259.14 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.104xL1+0.
hour 1,501.00 5,621.25 P&M-023
625
(ii) 12 KL capacity 0.139xL1+0.8
hour 1,327.00 6,638.98 P&M-024
33
(iii) 6 KL capacity 0.278xL1+1.
hour 1,005.00 10,057.04 P&M-025
667
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 7435.000 7503.000 7730.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 11,151.24 11,253.01 11,594.82

e) Overhead charges @ 20% on @ 20% on @ 20% on


24,532.72 24,756.62 25,508.60
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
14,719.63 14,853.97 15,305.16
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 15 cum = a+b+c+d+e+f 161,915.97 163,393.72 168,356.74


Rate per cum = (a+b+c+d+e+f)/15 10,794.40 10,892.91 11,223.78
Say 10,794.00 10,893.00 11,224.00
15.12 1500, Plain/Reinforced Cement Concrete in Wall & Slab
1700 & etc. complete as per Drawing and Technical
2100 Specifications.
A RCC Grade M20
RCC Grade M20 using batching plant transit mixer &
Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

Per Cum Basic Cost (Rate as in sub-analysis)


Sub-Analysis
cum 30.000 30.000 30.000 4,533.00 135,990.00 135,990.00 135,990.00 of Concrete -
20.05

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.
hour 1,501.00 5,892.93 P&M-023
656
(ii) 12 KL capacity 0.146xL1+0.8
hour 1,327.00 6,973.39 P&M-024
75
(iii) 6 KL capacity 0.292xL1+1.
hour 1,005.00 10,562.55 P&M-025
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 5969.000 6005.000 6124.000
d) Formwork @ 25 per cent on cost of concrete
i.e. cost of material, labour and machinery 44,760.40 45,030.51 45,927.80

e) Overhead charges @ 20% on @ 20% on @ 20% on


44,760.40 45,030.51 45,927.80
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
26,856.24 27,018.31 27,556.68
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 30 cum = a+b+c+d+e+f 295,418.63 297,201.39 303,123.51


Rate per cum = (a+b+c+d+e+f)/30 9,847.29 9,906.71 10,104.12
Say 9,847.00 9,907.00 10,104.00
15.12 B RCC Grade M25
RCC Grade M25 using batching plant transit mixer &
Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,945.00 148,350.00 148,350.00 148,350.00 of Concrete -
20.07

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.
hour 1,501.00 5,892.93 P&M-023
656
(ii) 12 KL capacity 0.146xL1+0.8
hour 1,327.00 6,973.39 P&M-024
75
(iii) 6 KL capacity 0.292xL1+1.
hour 1,005.00 10,562.55 P&M-025
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6381.000 6417.000 6536.000
d) Formwork @ 25 per cent on cost of concrete
i.e. cost of material, labour and machinery 47,850.40 48,120.51 49,017.80

e) Overhead charges @ 20% on @ 20% on @ 20% on


47,850.40 48,120.51 49,017.80
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
28,710.24 28,872.31 29,410.68
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 30 cum = a+b+c+d+e+f 315,812.63 317,595.39 323,517.51


Rate per cum = (a+b+c+d+e+f)/30 10,527.09 10,586.51 10,783.92
Say 10,527.00 10,587.00 10,784.00
15.12 C PCC Grade M30
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

PCC Grade M30 using batching plant transit mixer &


Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 5,032.00 150,960.00 150,960.00 150,960.00 of Concrete -
20.09

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.113 0.113 617.00 94.40 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 1.325 1.325 511.52 1,189.28 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.
hour 1,501.00 5,892.93 P&M-023
656
(ii) 12 KL capacity 0.146xL1+0.8
hour 1,327.00 6,973.39 P&M-024
75
(iii) 6 KL capacity 0.292xL1+1.
hour 1,005.00 10,562.55 P&M-025
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6468.000 6486.000 6605.000
d) Formwork @ 25 per cent on cost of concrete
i.e. cost of material, labour and machinery 48,502.90 48,638.96 49,536.25

e) Overhead charges @ 20% on @ 20% on @ 20% on


48,502.90 48,638.96 49,536.25
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
29,101.74 29,183.38 29,721.75
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 30 cum = a+b+c+d+e+f 320,119.13 321,017.16 326,939.28


Rate per cum = (a+b+c+d+e+f)/30 10,670.64 10,700.57 10,897.98
Say 10,671.00 10,701.00 10,898.00
15.12 D RCC Grade M35
RCC Grade M35 using batching plant transit mixer &
Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 5,186.00 155,580.00 155,580.00 155,580.00 of Concrete -
20.11

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.
hour 1,501.00 5,892.93 P&M-023
656
(ii) 12 KL capacity 0.146xL1+0.8
hour 1,327.00 6,973.39 P&M-024
75
(iii) 6 KL capacity 0.292xL1+1.
hour 1,005.00 10,562.55 P&M-025
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6622.000 6658.000 6777.000
d) Formwork @ 25 per cent on cost of concrete
i.e. cost of material, labour and machinery 49,657.90 49,928.01 50,825.30

e) Overhead charges @ 20% on @ 20% on @ 20% on


49,657.90 49,928.01 50,825.30
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
29,794.74 29,956.81 30,495.18
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

Cost for 30 cum = a+b+c+d+e+f 327,742.13 329,524.89 335,447.01


Rate per cum = (a+b+c+d+e+f)/30 10,924.74 10,984.16 11,181.57
Say 10,925.00 10,984.00 11,182.00
15.12 E RCC Grade M40
RCC Grade M40 using batching plant transit mixer &
Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 5,519.00 165,570.00 165,570.00 165,570.00 of Concrete -
20.12

Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.
hour 1,501.00 5,892.93 P&M-023
656
(ii) 12 KL capacity 0.146xL1+0.8
hour 1,327.00 6,973.39 P&M-024
75
(iii) 6 KL capacity 0.292xL1+1.
hour 1,005.00 10,562.55 P&M-025
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6955.000 6991.000 7110.000
d) Formwork @ 25 per cent on cost of concrete
i.e. cost of material, labour and machinery 52,155.40 52,425.51 53,322.80

e) Overhead charges @ 20% on @ 20% on @ 20% on


52,155.40 52,425.51 53,322.80
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
31,293.24 31,455.31 31,993.68
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)

Cost for 30 cum = a+b+c+d+e+f 344,225.63 346,008.39 351,930.51


Rate per cum = (a+b+c+d+e+f)/30 11,474.19 11,533.61 11,731.02
Say 11,474.00 11,534.00 11,731.00
15.13 1600 Supplying, Fitting and Placing un-coated HYSD bar
Reinforcement in Foundation complete as per
Drawing and Technical Specifications.

Unit = MT
Taking output = 8 MT
a) Material
MS bars including 5 per cent overlaps and wastage
tonne 8.400 8.400 8.400 46,496.54 390,570.97 390,570.97 390,570.97 M-083
Binding wire Kg 48.000 48.000 48.000 66.72 3,202.56 3,202.56 3,202.56 M-072
b) Labour for straightening, cutting, bending,
shifting to site, tying and placing in position

Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Blacksmith day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-01
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
c) Machinery
Cutting Machine hour 5.333 5.333 5.333 528.15 2,816.80 2,816.80 2,816.80 P&M-076
Bending Machine hour 5.333 5.333 5.333 528.15 2,816.80 2,816.80 2,816.80 P&M-076
Electric generator 15 KVA hour 5.333 5.333 5.333 425.25 2,268.00 2,268.00 2,268.00 P&M-051
Tipper
Tipper for Transportation
(i) 18 cum capacity t.km 8 x L1 6.18 1,482.84 P&M-116
(ii) 14 cum capacity t.km 8 x L1 7.01 1,683.07 P&M-119
(iii) 10 cum capacity t.km 8 x L1 8.66 2,079.36 P&M-122
Loading & Unloading Time hour
(i) 18 cum capacity hour 1.000 2,883.30 2,883.30 P&M-014
(ii) 14 cum capacity hour 1.280 2,556.75 3,272.64 P&M-015
(iii) 10 cum capacity hour 1.778 2,274.30 4,043.20 P&M-016
Light weight Crane
At cutting bending yard hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102
At site hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102
Per MT Basic Cost of Labour, Material & Machinery
51586.000 51660.000 51806.000
(a+b+c)
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

d) Overhead charges @ 20% on @ 20% on @ 20% on


82,537.59 82,655.51 82,888.87
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
49,522.55 49,593.30 49,733.32
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 8 MT (a+b+c+d) 544,748.10 545,526.33 547,066.57
Rate for per MT (a+b+c+d)/8 68,093.51 68,190.79 68,383.32
Say 68,094.00 68,191.00 68,383.00
15.14 2706 & Providing weep holes in Brick masonry/Plain/
2200 Reinforced concrete abutment, wing wall/ return wall
with 100 mm dia AC pipe, extending through the full
width of the structure with slope of 1V :20H towards
drawing foce. Complete as per drawing and
Technical Specifications

Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including wastage @ 5 per M-056
cent ) metre 31.500 31.500 31.500 59.13 1,862.60 1,862.60 1,862.60
Average length of weep hole is taken as one metre
for the purpose of estimating.
MS clamp each. 30.000 30.000 30.000 41.70 1,251.00 1,251.00 1,251.00 M-122
collar for AC pipe (average) taking 10% of above M-056/10
pipe rate each. 10.000 10.000 10.000 5.91 59.13 59.13 59.13
Cement mortar 1:3 (Rate as sub-analysis) Sub-Analysis
of Concrete -
cum 0.050 0.050 0.050 5,125.00 256.25 256.25 256.25 20.01 (A)

b) Labour
Mate day 0.030 0.030 0.030 617.00 18.51 18.51 18.51 L-12
Mason day 0.500 0.500 0.500 679.00 339.50 339.50 339.50 L-10
Mazdoor day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
c) Overhead charges @ 20% on @ 20% on @ 20% on
782.97 782.97 782.97
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
469.78 469.78 469.78
(a+b+c) (a+b+c) (a+b+c)
Cost for 30 Nos.= a+b+c+d 5,167.62 5,167.62 5,167.62
Rate per No. (a+b+c+d)/30 172.25 172.25 172.25
Say 172.00 172.00 172.00
15.15 2700 PCC M15 Grade leveling course below approach
slab complete as per drawing and Technical
specification
Unit = 1 cum
Taking output = 1 cum
Material
Case I PCC Grade M15 using batching plant & Concrete
pump
cum 1.000 5,594.00 5,594.00 Item No. -
Concrete, Rate as per item No. 15.11 (A), Case-I
cum 1.000 5,626.00 5,626.00 15.11 A
excluding formworks
cum 1.000 5,749.00 5,749.00 Case-I
c) Overhead charges @ 20% on @ 20% on
@ 20% on (a) 1,118.80 1,125.20 1,149.80
(a) (a)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
671.28 675.12 689.88
(a+b) (a+b) (a+b)
Rate per cum Say 7,384.00 7,426.00 7,589.00
Case II PCC Grade M15 using batching plant & manual
placing
cum 1.000 5,879.00 5,879.00 Item No. -
Concrete, Rate as per item No. 15.11 (A), Case-II
1.000 5,914.00 5,914.00 15.11 A
excluding formworks
1.000 6,033.00 6,033.00 Case-II
c) Overhead charges @ 20% on @ 20% on
@ 20% on (a) 1,175.80 1,182.80 1,206.60
(a) (a)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
705.48 709.68 723.96
(a+b) (a+b) (a+b)
Rate per cum Say 7,760.00 7,806.00 7,964.00
15.16 1500,1600 Reinforced cement concrete approach slab including
,1700 & reinforcement and formwork complete as per drawing
2704 and Technical specification

Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concrete M30 Grade Refer relevant item of cum 1.000 6,468.00 6,468.00 Item No. -
concrete in item 15.11(G)by using batching plant, 15.11 G Case
cum 1.000 6,504.00 6,504.00
excluding formwork i.e. per cum basic cost (a+b+c) 1
(Excluding OH & CP) cum 1.000 6,623.00 6,623.00
Added at the rate of 2 Percent of cost 129.36 130.08 132.46
tonne 0.050 51,586.00 2,579.30
HYSD bar reinforcement Rate as per item No 15.13 Item No. -
tonne 0.050 51,660.00 2,583.00
(Excluding OH & CP) 15.13
tonne 0.050 51,806.00 2,590.30
b) Overhead charges @ 20% on @ 20% on
@ 20% on (a) 1,835.33 1,843.42 1,869.15
(a) (a)
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

c) Contractor's profit @ 10% on @ 10% on @ 10% on


1,101.20 1,106.05 1,121.49
(a+b) (a+b) (a+b)
Rate per cum (a+b+c) 12,113.19 12,166.55 12,336.40
Say 12,113.00 12,167.00 12,336.00
15.17 2705 Drainage Spouts complete as per drawing and
Technical specification
Unit = 1 No.
Taking output = 1 No.
a) Material
Corrosion resistant Structural steel including 5 per M-088/1000
cent wastage Kg 4.000 4.000 4.000 44.00 176.00 176.00 176.00
GI pipe 100mm dia metre 0.320 0.320 0.320 496.00 158.72 158.72 158.72 M-239
GI bolt 10 mm Dia each 6.000 6.000 6.000 16.76 100.55 100.55 100.55 M-109
Galvanised MS flat clamp each 2.000 2.000 2.000 27.80 55.60 55.60 55.60 M-101
b) Labour
For fabrication
Mate day 0.002 0.002 0.002 617.00 1.23 1.23 1.23 L-12
Skilled (Blacksmith, welder etc.) day 0.020 0.020 0.020 738.00 14.76 14.76 14.76 L-02
Mazdoor day 0.020 0.020 0.020 511.52 10.23 10.23 10.23 L-13
For fixing in position
Mate day 0.008 0.008 0.008 617.00 4.94 4.94 4.94 L-12
Mason day 0.010 0.010 0.010 679.00 6.79 6.79 6.79 L-10
Mazdoor day 0.200 0.200 0.200 511.52 102.30 102.30 102.30 L-13
Add @ 5 per cent of cost of material and labour for
electrodes, cutting gas, sealant, anti-corrosive
bituminous paint, mild steel grating etc. 31.56 31.56 31.56

c) Overhead charges @ 20% on @ 20% on @ 20% on


132.54 132.54 132.54
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
79.52 79.52 79.52
(a+b+c) (a+b+c) (a+b+c)
Rate per metre (a+b+c+d) 874.74 874.74 874.74
Say 875.00 875.00 875.00
Note 1. In case of viaducts in urban areas, the drainage
spouts should be connected with suitably located
pipelines to discharge the surface run-off to drains
provided at ground level.

2. In case of bridges, sufficient length of G.I Pipe


shall be provided to ensure that there is no splashing
of water from the drainage spout on the structure.

15.18 2702 Providing and laying Cement concrete wearing coat


M-30 grade including reinforcement complete as per
drawing and Technical Specifications 1143.000

Unit = 1 cum
Taking output = 1 cum
a) Material
cum 1.000 6,468.00 6,468.00
Cement concrete M30 Grade Refer relevant item of Item No. -
cum 1.000 6,486.00 6,486.00
concrete in Item 15.12 (C) excluding formwork 15.12 C
cum 1.000 6,605.00 6,605.00
tonne 0.075 51,586.00 3,868.95
HYSD bar reinforcement Rate as per item No 15.13 Item No. -
tonne 0.075 51,660.00 3,874.50
(Excluding OH & CP) 15.13
tonne 0.075 51,806.00 3,885.45
b) Labour
Mazdoor for cleaning deck slab concrete surface. L-13
day 0.150 0.150 0.150 511.52 76.73 76.73 76.73
c) Overhead charges @ 20% on @ 20% on @ 20% on
2,082.74 2,087.45 2,113.44
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,249.64 1,252.47 1,268.06
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum (a+b+c+d) 13,746.05 13,777.14 13,948.67
Say 13,746.00 13,777.00 13,949.00
15.19 516 & Mastic Asphalt
2702
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

Providing and laying 12 mm thick mastic asphalt


wearing course on top of deck slab excluding prime
coat with paving grade bitumen meeting the
requirements given in table 500-39, prepared by
using mastic cooker and laid to required level and
slope after cleaning the surface, including providing
antiskid surface with bitumen precoated fine grained
hard stone chipping of 9.5 mm nominal size at the
rate of 0.005cum per 10 sqm and at an approximate
spacing of 10 cm center to center in both directions,
pressed into surface when the temperature of
surfaces not less than 100 deg. C, protruding 1 mm
to 4 mm over mastic surface, all complete as per
clause 516.

Unit = sqm
Taking output = 72.46 sqm (2 tonnes)(0.869 cum)
assuming a density of 2.3 tonnes/cum.
a) Labour
Mate day 0.490 0.490 0.490 617.00 302.33 302.33 302.33 L-12
Mazdoor day 11.000 11.000 11.000 511.52 5,626.72 5,626.72 5,626.72 L-13
Mazdoor (Skilled) day 1.250 1.250 1.250 565.73 707.16 707.16 707.16 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.060 0.060 0.060 500.40 30.02 30.02 30.02 P&M-052
Air compressor 250 cfm hour 0.060 0.060 0.060 614.25 36.86 36.86 36.86 P&M-029
Mastic cooker 1 tonne capacity hour 6.000 6.000 6.000 1,042.50 6,255.00 6,255.00 6,255.00 P&M-056
Bitumen boiler 1500 litres capacity hour 6.000 6.000 6.000 743.40 4,460.40 4,460.40 4,460.40 P&M-055
Tractor for towing and positioning of mastic cooker P&M-026
and bitumen boiler hour 1.000 1.000 1.000 1,876.50 1,876.50 1,876.50 1,876.50
c) Material
Base mastic (without coarse aggregates) = 60 per
cent
Coarse aggregate(3.35mm to 9.5 mm size) = 40 per
cent .
Proportion of material required for mastic asphalt
with coarse aggregates (based on mix design done
by CRRI for a specific case)
i) Bitumen 80/100 or 60/70 or 30/40 @ 10.2 per cent M-327
by weight of mix. 2 x 10.2/100 = 0.204 tonne 0.204 0.204 0.204 44,020.00 8,980.08 8,980.08 8,980.08
ii) Crusher stone dust @ 31.9 per cent by weight of M-020
mix = 2 x 31.9/100 = 0.638 tonnes = 0.638/1.625 = cum 0.390 0.390 0.390 1,887.12 735.98 735.98 735.98
0.39
iii) Lime stone dust filler with calcium carbonate M-190
content not less than 80 per cent by weight @ 17.92
per cent by weight of mix = 2 x 17.92/100 = 0.36 tonne 0.360 0.360 0.360 3,753.00 1,351.08 1,351.08 1,351.08

iv) Coarse aggregates 9.5 mm to 3.35 mm size @ 40 M-024


per cent by weight of mix = 2 x 40/100 = 0.8 MT = cum 0.550 0.550 0.550 1,887.12 1,037.92 1,037.92 1,037.92
0.8/1.456 = 0.55
v) Pre-coated stone chips of 9.5 mm nominal size for M-141
skid resistance = 72.46x0.005/10 = 0.036 cum 0.036 0.036 0.036 1,951.24 70.24 70.24 70.24

vi) Bitumen for coating of chips @ 2 per cent by M-327


weight = 0.036 x 1.456 x 2/100 = 0.001048MT = kg 1.050 1.050 1.050 44.02 46.22 46.22 46.22
1.05kg
d) Overhead charges @ 20% on @ 20% on @ 20% on
6,303.30 6,303.30 6,303.30
(a+b) (a+b) (a+b)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
3,781.98 3,781.98 3,781.98
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 72.46 sqm = a+b+c+d+e 41,601.80 41,601.80 41,601.80
Rate per sqm = (a+b+c+d+e)/72.46 574.13 574.13 574.13
Say 574.00 574.00 574.00
Note 1.The rates for 6 mm or any other thickness may be worked out on pro-rata basis.
2. Where tack coat is required to be provided before laying mastic asphalt, the same is required to be measured and paid separately.
3.The quantities of binder, filler and aggregates are for estimating purpose. Exact quantities shall be as per mix design.
4.This rate analysis is based on design made by CRRI for a specific case and is meant for estimating purposes only. Actual design is required to be done for each case.
5.The quantity of bitumen works out 17 per cent of the mastic asphalt blocks without aggregates and falls within the standards laid down by MoRTH Specifications.
15.20 800 Crash Barriers for Bridge

The rate analysis for semi rigid crash barrier with


metal beam and flexible crash barrier with wire ropes
have been made and included in chapter-8 on Traffic
and Transportation. The rate analysis for rigid crash
barrier in reinforced cement concrete,
have been made and included in chapter-14 on
Super-structure

15.21 800 Painting on concrete surface


Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

Providing and applying 2 coats of water based


cement paint to unplastered concrete surface after
cleaning the surface of dirt, dust, oil, grease,
efflorescence and applying paint @ of 1 litre for 2
sqm.

Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.020 0.020 0.020 617.00 12.34 12.34 12.34 L-12
Painter day 0.250 0.250 0.250 679.00 169.75 169.75 169.75 L-18
Mazdoor (Skilled) day 0.250 0.250 0.250 565.73 141.43 141.43 141.43 L-15
b) Material
Water based paint of approved quality for cement M-192
concrete surface Litres 5.000 5.000 5.000 97.30 486.50 486.50 486.50
c) Overhead charges @ 20% on @ 20% on @ 20% on
162.00 162.00 162.00
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
97.20 97.20 97.20
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm (a+b+c+d) 1,069.23 1,069.23 1,069.23
Rate per sqm (a+b+c+d)/10 106.92 106.92 106.92
Say 107.00 107.00 107.00
15.22 2605 Filler joint
(i) Providing & fixing 2 mm thick corrugated copper
plate in expansion joint complete as per drawing &
Technical Specification.
Unit = Running meter
Taking output = 12 m
a) Labour
Cutting, bending, carrying & fixing etc.
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
Mazdoor (Skilled) day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
b) Material
Copper plate - 12m long x 250 mm wide kg 55.000 55.000 55.000 389.20 21,406.00 21,406.00 21,406.00 M-087
Area = 12 x 0.25 = 3 sqm
Weight = 3 x 0.002 x 8900 = 53.4 kg
Wastage @ 2.5 per cent = 1.33 kg/54.73 kg say = 55
kg.
c) Overhead charges @ 20% on @ 20% on @ 20% on
4,393.86 4,393.86 4,393.86
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
2,636.32 2,636.32 2,636.32
(a+b+c) (a+b+c) (a+b+c)
Cost for 12 m = (a+b+c+d) 28,999.48 28,999.48 28,999.48
Rate per m = (a+b+c+d)/12 2,416.62 2,416.62 2,416.62
Say 2,417.00 2,417.00 2,417.00
15.22 (ii) Providing & fixing 20 mm thick compressible fibre
board in expansion joint complete as per drawing &
Technical Specification.
Unit = Running meter
Taking output = 12 m
a) Labour
For carrying, placing & fixing.
Mate day 0.008 0.008 0.008 617.00 4.94 4.94 4.94 L-12
Mazdoor day 0.100 0.100 0.100 511.52 51.15 51.15 51.15 L-13
Mazdoor (Skilled) day 0.100 0.100 0.100 565.73 56.57 56.57 56.57 L-15
b) Material
20 mm thick compressible fibre board 12 m long x 25 M-085
cm deep. sqm 3.000 3.000 3.000 735.00 2,205.00 2,205.00 2,205.00
Area = 12 x 0.25 = 3 sqm
c) Overhead charges @ 20% on @ 20% on @ 20% on
463.53 463.53 463.53
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
278.12 278.12 278.12
(a+b+c) (a+b+c) (a+b+c)
Cost for 12 m = (a+b+c+d) 3,059.31 3,059.31 3,059.31
Rate per m = (a+b+c+d)/12 254.94 254.94 254.94
Say 255.00 255.00 255.00
15.22 (iii) Providing and fixing in position 20 mm thick
premoulded joint filler in expansion joint for fixed
ends of simply supported spans not exceeding 10 m
to cater for a horizontal movement upto 20 mm,
covered with sealant complete as per drawing and
technical specifications.

Unit = Running meter


Taking output = 12 m
a) Labour
Mate day 0.012 0.012 0.012 617.00 7.40 7.40 7.40 L-12
Mazdoor day 0.200 0.200 0.200 511.52 102.30 102.30 102.30 L-13
Mazdoor (Skilled) day 0.100 0.100 0.100 565.73 56.57 56.57 56.57 L-15
b) Material
Premoulded joint filler 12 m long,20 mm thick and M-140
300 mm deep. sqm 3.600 3.600 3.600 625.50 2,251.80 2,251.80 2,251.80
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

c) Overhead charges @ 20% on @ 20% on @ 20% on


483.62 483.62 483.62
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
290.17 290.17 290.17
(a+b+c) (a+b+c) (a+b+c)
Cost for 12 m = (a+b+c+d) 3,191.87 3,191.87 3,191.87
Rate per m = (a+b+c+d)/12 265.99 265.99 265.99
Say 266.00 266.00 266.00
15.22 (iv) Providing and filling joint sealing compound as per
drawings and technical specifications with coarse
sand and 6 per cent bitumen by weight

Unit = Running meter


Taking output = 12 m
12m long x 100 mm wide x 10mm deep recess

a) Labour
Mate day 0.024 0.024 0.024 617.00 14.81 14.81 14.81 L-12
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
Mazdoor (Skilled) day 0.100 0.100 0.100 565.73 56.57 56.57 56.57 L-15
b) Material
Sand cum 0.012 0.012 0.012 1,994.03 23.93 23.93 23.93 M-005
Volume 12 x 0.1 x 0.01 = 0.012 cum
Weight 0.012 x 1400 = 16.8kg
Bitumen cum 0.001 0.001 0.001 46,556.37 46.56 46.56 46.56 M-074
16.8 x 0.06 = 1 kg
c) Overhead charges @ 20% on @ 20% on @ 20% on
79.53 79.53 79.53
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
47.72 47.72 47.72
(a+b+c) (a+b+c) (a+b+c)
Cost for 12 m = (a+b+c+d) 524.87 524.87 524.87
Rate per m = (a+b+c+d)/12 43.74 43.74 43.74
Say 44.00 44.00 44.00
Note For arriving at the final rate of filler joints per m
length and per cm depth of joint filling compound,

the rates at Sl. No. i), ii), iii) & iv) shall be added

15.23 710.1.4.of Back filling behind abutment, wing wall and return
IRC:78 & wall complete as per drawing and Technical
2200 Specification
Unit = cum
Taking output = 10 cum
A Granular material
a) Labour
Mate day 0.280 0.280 0.280 617.00 172.76 172.76 172.76 L-12
Mazdoor day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
b) Material
Granular material cum 12.000 12.000 12.000 1,887.12 22,645.48 22,645.48 22,645.48 M-009
c) Machinery
Plate compactor/power rammer hour 2.500 2.500 2.500 597.45 1,493.63 1,493.63 1,493.63 P&M-079
Water Tanker hour 0.050 0.050 0.050 1,005.00 50.25 50.25 50.25 P&M-025
d) Overhead charges @ 20% on @ 20% on @ 20% on
5,588.55 5,588.55 5,588.55
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
3,353.13 3,353.13 3,353.13
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10 cum of granular backfill = a+b+c+d+e
36,884.43 36,884.43 36,884.43
Rate per cum = (a+b+c+d+e)/10 3,688.44 3,688.44 3,688.44
Say 3,688.00 3,688.00 3,688.00
15.23 B Sandy material
a) Labour
Mate day 0.280 0.280 0.280 617.00 172.76 172.76 172.76 L-12
Mazdoor for filling, watering, ramming etc. day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
b) Material
Sand cum 12.000 12.000 12.000 1,544.03 18,528.37 18,528.37 18,528.37 M-006
c) Machinery
Plate compactor/power rammer hour 2.500 2.500 2.500 597.45 1,493.63 1,493.63 1,493.63 P&M-079
Water Tanker hour 0.060 0.060 0.060 1,005.00 60.30 60.30 60.30 P&M-025
d) Overhead charges @ 20% on @ 20% on @ 20% on
4,767.14 4,767.14 4,767.14
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
2,860.28 2,860.28 2,860.28
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10 cum of sandy backfill = a+b+c+d+e 31,463.12 31,463.12 31,463.12
Rate per cum = (a+b+c+d+e)/10 3,146.31 3,146.31 3,146.31
Say 3,146.00 3,146.00 3,146.00
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project

15.24 710.1.4.of Providing and laying of Filter media with granular


IRC:78 materials/stone crushed aggregates satisfying the
and requirements laid down in clause 2504.2.2. of
2504.2 MoRTH specifications to a thickness of not less than
600 mm with smaller size towards the soil and bigger
size towards the wall and provided over the entire
surface behind abutment, wing wall and return wall to
the full height compacted to a firm condition complete
as per drawing and Technical Specification.

Unit = cum
Taking output = 10 cum.
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mazdoor for filling, watering, ramming etc. day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
Mazdoor (Skilled) day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
b) Material
Filter media of stone aggregate conforming to clause M-011
2504.2.2. of MoRTH specifications. cum 12.000 12.000 12.000 1,215.07 14,580.87 14,580.87 14,580.87
c) Machinery
Water Tanker of 6 KL capacity hour 0.060 0.060 0.060 1,005.00 60.30 60.30 60.30 P&M-025
d) Overhead charges @ 20% on @ 20% on @ 20% on
3,797.00 3,797.00 3,797.00
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
2,278.20 2,278.20 2,278.20
(a+b+c+d) (a+b+c+d) (a+b+c+d)
cost for 10 cum of Fiter Media = a+b+c+d+e 25,060.18 25,060.18 25,060.18
Rate per cum = (a+b+c+d+e)/10 2,506.02 2,506.02 2,506.02
Say 2,506.00 2,506.00 2,506.00
15.25 Painting with synthetic enamel paint bridge No. and
span arrangements
Painting two coats after filling the surface with
synthetic enamel paint bridge No. and span
arrangements as per as directed by Engineer.
Unit = Nos.
Taking output = 1 Nos.
a) Labour
Mate day 0.006 0.006 0.006 617.00 3.70 3.70 3.70 L-12
Painter day 0.100 0.100 0.100 679.00 67.90 67.90 67.90 L-18
Mazdoor day 0.050 0.050 0.050 511.52 25.58 25.58 25.58 L-13
b) Material
M-131
Paint conforming to requirement of clause 803.3. Litre 0.300 0.300 0.300 172.36 51.71 51.71 51.71

Add for scaffolding @ 1 per cent of labour cost


0.97 0.97 0.97
where required
Add @ 5 per cent cost of labour and materials to
prepare the surface by filling minuts roughness on
7.44 7.44 7.44
the surface and priming the surface before laying 2
coats of painting.
Per Sqm Basic Cost of Labour & Material (a+b)
157.302 157.302 157.302

c) Overhead charges @ 20% on @ 20% on @ 20% on


31.46 31.46 31.46
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
18.88 18.88 18.88
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 1 No. = a+b+c+d 207.64 207.64 207.64
Rate per Nos. = (a+b+c+d)/40 207.64 207.64 207.64
Say 208.00 208.00 208.00
CHAPTER - 16
RIVER TRAINING AND PROTECTION WORKS
Quantity Amount (Rs.)
Reference to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) ref.
Specification Project Project Project Project Project Project

16.01 2503
Providing and laying boulders apron on river bed for
protection against scour with stone boulders weighing
not less than 40 kg each complete as per drawing and
Technical specification.

A Boulder Laid Dry Without Wire Crates.


Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.000 1.000 1.000 1,994.63 1,994.63 1,994.63 1,994.63 M-003
Stone Spalls cum 0.200 0.200 0.200 1,679.81 335.96 335.96 335.96 M-008
b) Labour
Mate day 0.044 0.044 0.044 617.00 27.15 27.15 27.15 L-12
Mason day 0.350 0.350 0.350 679.00 237.65 237.65 237.65 L-10
Mazdoor * day 0.750 0.750 0.750 511.52 383.64 383.64 383.64 L-13
@ 20% on @ 20% on @ 20% on
c) Overhead charges 595.81 595.81 595.81
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 357.48 357.48 357.48
(a+b+c) (a+b+c) (a+b+c)
Rate per cum = (a+b+c+d) 3,932.32 3,932.32 3,932.32
Say 3,932.00 3,932.00 3,932.00
* Including excavation for trimming for preparation of
bed.
Note Nominal excavation required for preparation of bed
has been taken into account while making provision
for labour.
16.02 2503 Boulder Apron Laid in Wire Crates
Providing and laying of boulder apron laid in wire
crates made with 4mm dia GI wire conforming to IS:
280 & IS:4826 in 100mm x 100mm mesh (weaved
diagonally) including 10 per cent extra for laps and
joints laid with stone boulders weighing not less than
40 kg each.
Unit = cum
Taking output = 3 mx1.5mx1.25m = 5.63 cum
a) Material
4mm GI wire crates woven in mesh size of 100 mm x M-102
sqm 22.000 22.000 22.000 19.00 418.00 418.00 418.00
100 mm.
Stone cum 5.630 5.630 5.630 1,994.63 11,229.77 11,229.77 11,229.77 M-003
Stone Spalls cum 1.130 1.130 1.130 1,679.81 1,898.19 1,898.19 1,898.19 M-008
b) Labour
Mate day 0.180 0.180 0.180 617.00 111.06 111.06 111.06 L-12
Mazdoor (Skilled) day 1.500 1.500 1.500 565.73 848.60 848.60 848.60 L-15
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
@ 20% on @ 20% on @ 20% on
c) Overhead charges 3,208.03 3,208.03 3,208.03
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 1,924.82 1,924.82 1,924.82
(a+b+c) (a+b+c) (a+b+c)
Cost for 5.63 cum = a+b+c+d 21,173.03 21,173.03 21,173.03
Rate per cum = (a+b+c+d)/5.63 3,760.75 3,760.75 3,760.75
Say 3,761.00 3,761.00 3,761.00
* Including excavation for trimming for preparation of
bed.
Note Readymade woven wire crate rolls have been
considered in the rate analysis. In case readymade
rolls are not available, GI wire 4mm dia. @ 32 kg per
10 sqm may be provided. In that case 2 per cent of
the cost of GI wire may be added for weaving the wire
crates.
16.03 2503
Cement Concrete Blocks (size 0.5 x 0.5 x 0.5 m)

Providing and laying of apron with cement concrete


blocks of size 0.5 x 0.5 x 0.5 m cast in-situ and made
with nominal mix of M-15 grade cement concrete with
a minimum cement content of 250 kg/cum as per IRC:
21.
Unit = cum
Taking out put = 1 cum
cum 1.000 8,070.00 8,070.00
Concrete Grade M15 Rate as per item No. 12.08 (A, Item No. -
cum 1.000 8,118.00 8,118.00
Case-II) including OH & CP 12.08 A
cum 1.000 8,282.00 8,282.00
Quantity Amount (Rs.)
Reference to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) ref.
Specification Project Project Project Project Project Project

Add 2 per cent of cost to account for excavation for


preparation of bed, nominal surface reinforcement and 161.40 162.36 165.64
filling of granular material in recesses between blocks.

Rate per cum 8,231.40 8,280.36 8,447.64


Say 8,231.00 8,280.00 8,448.00
16.04 2504
Providing and laying Pitching on slopes laid over
prepared filter media including boulder apron laid dry
in front of toe of embankment complete as per
drawing and Technical specifications

A Stone/Boulder
Unit = cum
Taking output = 1 cum
a) Material
Stone weighing not less than 40kg cum 1.000 1.000 1.000 1,994.63 1,994.63 1,994.63 1,994.63 M-003
Stone spalls of minimum 25 mm size cum 0.200 0.200 0.200 1,679.81 335.96 335.96 335.96 M-008
b) Labour
Mate day 0.044 0.044 0.044 617.00 27.15 27.15 27.15 L-12
Mason day 0.350 0.350 0.350 679.00 237.65 237.65 237.65 L-10
Mazdoor day 0.750 0.750 0.750 511.52 383.64 383.64 383.64 L-13
@ 20% on @ 20% on @ 20% on
c) Overhead charges 595.81 595.81 595.81
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 357.48 357.48 357.48
(a+b+c) (a+b+c) (a+b+c)
Rate per cum = (a+b+c+d) 3,932.32 3,932.32 3,932.32
Say 3,932.00 3,932.00 3,932.00
16.04 B Cement Concrete Blocks of size 0.3x0.3 x0.3 m cast
in cement concrete of Grade M15
Unit = cum
Taking output = 1 cum
cum 1.000 8,070.00 8,070.00
Concrete Grade M15 Rate as per item No. 12.08 (A, Item No. -
cum 1.000 8,118.00 8,118.00
Case-II) including OH & CP 12.08 A
cum 1.000 8,282.00 8,282.00
Add 2 per cent of cost to account for nominal surface
reinforcement and filling of granular material in 161.40 162.36 165.64
recesses between blocks.
Rate per cum 8,231.40 8,280.36 8,447.64
Say 8,231.00 8,280.00 8,448.00
16.05 2504 Providing and laying Filter material underneath
pitching in slopes complete as per drawing and
Technical specification
Unit = cum
Taking output = 1 cum
a) Material
Graded stone aggregate of required size cum 1.200 1.200 1.200 1,215.07 1,458.09 1,458.09 1,458.09 M-011
b) Labour
Mate day 0.050 0.050 0.050 617.00 30.85 30.85 30.85 L-12
Mazdoor (Skilled) day 0.250 0.250 0.250 565.73 141.43 141.43 141.43 L-15
Mazdoor * day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
@ 20% on @ 20% on @ 20% on
c) Overhead charges 428.38 428.38 428.38
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 257.03 257.03 257.03
(a+b+c) (a+b+c) (a+b+c)
Rate per cum = (a+b+c+d) 2,827.29 2,827.29 2,827.29
Say 2,827.00 2,827.00 2,827.00
Includes Mazdoor required for trimming of slope to
proper profile and preparation of bed.
16.06 700 &
2504 Geotextile Filter

Laying of a geotextile filter between pitching and


embankment slopes on which pitching is laid to
prevent escape of the embankment material through
the voids of the stone pitching/cement concrete blocks
as well as to allow free movement of water without
creating any uplift head on the pitching.

Unit = sqm
Taking output = 10 sqm.
a) Labour
Mate day 0.016 0.016 0.016 617.00 9.87 9.87 9.87 L-12
Mazdoor day 0.300 0.300 0.300 511.52 153.46 153.46 153.46 L-13
Mazdoor (Skilled) day 0.100 0.100 0.100 565.73 56.57 56.57 56.57 L-15
Quantity Amount (Rs.)
Reference to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) ref.
Specification Project Project Project Project Project Project

b) Material
Permeable synthetic geotextile including 5 per cent M301
sqm 11.000 11.000 11.000 1.00 11.00 11.00 11.00
for overlap and wastage
@ 20% on @ 20% on @ 20% on
c) Overhead charges 46.18 46.18 46.18
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 27.71 27.71 27.71
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm = a+b+c+d 304.79 304.79 304.79
Rate per sqm = (a+b+c+d)/10 30.48 30.48 30.48
Say 30.00 30.00 30.00
16.07 2504.4 Toe protection

A toe wall for toe protection can either be in dry rubble


masonry in case of dry rubble pitching or pitching with
stones in wire crates or it can be in PCC M15 nominal
mix if cement concert block have been used for
pitching . Rates for toe wall can be adopted from
respective clauses depending upon approved design.
The rate for excavation for foundation, dry rubble
masonry and PCC M15 have been analysed and
given in respective chapters.

16.08 2505 Providing and laying Flooring complete as per drawing


and Technical specifications laid over cement concert
bedding.
A Rubble stone laid in cement mortar 1:3
Unit = cum
Taking output = 1 cum
Sub-Analysis of
a) Cement mortor 1:3 (Rate taken from items 21.01 Concrete -
cum 0.133 0.133 0.133 5,125.00 683.33 683.33 683.33
A) 20.01 (A)

b) Add for cement concrete bedding (M15 Nominal cum 0.333 7,678.00 2,559.33
mix) vide Item 12.8 (A) excluding OH & CP . Quantity
Item No. -
shall be adopted as per design (Assume Rubble stone cum 0.333 7,728.00 2,576.00
12.08 A
Flooring thickness 300mm and cement concrete
bedding thickness 100mm) cum 0.333 7,892.00 2,630.67
Add 1 per cent of cost to account for excavation for
32.43 32.59 33.14
preparation of bed.
c) Material
Stone cum 1.000 1.000 1.000 1,994.63 1,994.63 1,994.63 1,994.63 M-003
Stone Spalls cum 0.200 0.200 0.200 1,679.81 335.96 335.96 335.96 M-008
d) Labour
Mate day 0.106 0.106 0.106 617.00 65.40 65.40 65.40 L-12
Mason day 0.665 0.665 0.665 679.00 451.54 451.54 451.54 L-10
L-13
Mazdoor (for laying stones, filling of quarry spalls) day 1.995 1.995 1.995 511.52 1,020.48 1,020.48 1,020.48

@ 20% on @ 20% on @ 20% on


e) Overhead charges 910.27 910.27 910.27
(a+b+d) (a+b+d) (a+b+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 546.16 546.16 546.16
(a+b+d+e) (a+b+d+e) (a+b+d+e)
Rate per cum = (a+b+c+d+e+f) 8,599.54 8,616.37 8,671.58
Say 8,600.00 8,616.00 8,672.00
*
Includes cement mortar for laying and filling of joints.
16.08 B Cement Concrete blocks Grade M15 including 100
mm thick bedding
cum 1.000 7,678.00 7,678.00
Concrete Grade M15 block. (Rate as per item No. Item No. -
cum 1.000 7,728.00 7,728.00
12.8 (A) including OH & CP. 12.08 A
cum 1.000 7,892.00 7,892.00
Add for cement concrete bedding (M15 Nominal mix) cum 0.330 7,678.00 2,533.74
vide Item 12.8 (A) including OH & CP. Quantity shall
Item No. -
be adopted as per design ( Assume Cement Concrete cum 0.330 7,728.00 2,550.24
12.08 A
blocks thickness 300mm and cement concrete
bedding thickness 100mm) cum 0.330 7,892.00 2,604.36
Add 1 per cent of cost to account for excavation for
102.12 102.78 104.96
preparation of bed.
Rate per cum 10,313.86 10,381.02 10,601.32
Say 10,314.00 10,381.00 10,601.00
16.09 2506 Dry Rubble Flooring

Construction of dry rubble flooring at cross drainage


works for relatively less important works.

Unit = cum
Quantity Amount (Rs.)
Reference to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) ref.
Specification Project Project Project Project Project Project

Taking output = 1 cum


a) Material
Stone cum 1.000 1.000 1.000 1,994.63 1,994.63 1,994.63 1,994.63 M-003
Stone Spalls cum 0.200 0.200 0.200 1,679.81 335.96 335.96 335.96 M-008
b) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mason day 0.500 0.500 0.500 679.00 339.50 339.50 339.50 L-10
mazdoor day 1.500 1.500 1.500 511.52 767.28 767.28 767.28 L-13
Add 1 per cent of (b) for trimming and preparation of
11.56 11.56 11.56
base.
@ 20% on @ 20% on @ 20% on
c) Overhead charges 699.66 699.66 699.66
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 419.80 419.80 419.80
(a+b+c) (a+b+c) (a+b+c)
Rate per cum = (a+b+c+d) 4,617.75 4,617.75 4,617.75
Say 4,618.00 4,618.00 4,618.00
16.10 2507.2 Curtain wall complete as per drawing and Technical
specification
A Stone masonry in cement mortar (1:3)
cum 1.000 6,604.00 6,604.00
Coursed rubble masonry (1st sort) Rate taken from Item No. -
cum 1.000 6,604.00 6,604.00
item No. 12.07 (A) including OH & CP 12.07 A
cum 1.000 6,604.00 6,604.00
Rate per cum Say 6,604.00 6,604.00 6,604.00
or
16.10 B Cement concrete Grade M15
cum 1.000 7,678.00 7,678.00
Concrete Grade M15 Rate as per item No. 12.8 (A) Item No. -
including OH & CP cum 1.000 7,728.00 7,728.00 12.08 A
cum 1.000 7,892.00 7,892.00
Rate per cum Say 7,678.00 7,728.00 7,892.00
Note Other items like excavation for foundation, filling
behind wall, filter media, weep holes etc. shall be
added separately as per approved design.
16.11 2507.2
Flexible Apron :Construction of flexible apron 1 m
thick comprising of loose stone boulders weighing not
less than 40 kg beyond curtain wall.

Unit = cum
Taking Output = 1 cum
a) Material
Stone cum 1.000 1.000 1.000 1,994.63 1,994.63 1,994.63 1,994.63 M-003
Stone Spalls cum 0.200 0.200 0.200 1,679.81 335.96 335.96 335.96 M-008
b) Labour
Mate day 0.050 0.050 0.050 617.00 30.85 30.85 30.85 L-12
Mason day 0.250 0.250 0.250 679.00 169.75 169.75 169.75 L-10
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
Add 1 per cent of cost of (a+b) for trimming and
30.43 30.43 30.43
preparation of bed.
@ 20% on @ 20% on @ 20% on
c) Overhead charges 614.63 614.63 614.63
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 368.78 368.78 368.78
(a+b+c) (a+b+c) (a+b+c)
Rate per cum = (a+b+c+d) 4,056.55 4,056.55 4,056.55
Say 4,057.00 4,057.00 4,057.00
16.12 2503.3 Gabian Structure for Retaining Earth

Providing and construction of a gabian structure for


retaining earth with segments of wire crates of size 7
m x 3 m x 0.6 m each divided into 1.5 m
compartments by cross netting, made from 4 mm
galvanised steel wire @ 32 kg per 10 sqm having
minimum tensile strength of 300 Mpa conforming to
IS:280 and galvanizing coating conforming to IS:4826,
woven into mesh with double twist, mesh size not
exceeding 100 x 100 mm, filled with boulders with
least dimension of 200 mm, all loose ends to be tied
with 4 mm galvanised steel wire

Unit = cum
Taking output = 7 x 3 x 0.6 = 12.60 cum
a) Labour
Mate day 0.280 0.280 0.280 617.00 172.76 172.76 172.76 L-12
Mazdoor day 5.000 5.000 5.000 511.52 2,557.60 2,557.60 2,557.60 L-13
Mazdoor (Skilled) day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Quantity Amount (Rs.)
Reference to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) ref.
Specification Project Project Project Project Project Project

b) Material
Galvanised steel wire crates of mesh size 100 mm x M-102
100 mm woven with 4mm dia. GI wire in rolls of sqm 61.000 61.000 61.000 19.00 1,159.00 1,159.00 1,159.00
required size.
Stone boulders with least dimension of 200 mm cum 12.600 12.600 12.600 1,994.63 25,132.35 25,132.35 25,132.35 M-003
Stone spalls of minimum size 25 mm cum 2.520 2.520 2.520 1,679.81 4,233.13 4,233.13 4,233.13 M-008
@ 20% on @ 20% on @ 20% on
c) Overhead charges 6,877.26 6,877.26 6,877.26
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 4,126.36 4,126.36 4,126.36
(a+b+c) (a+b+c) (a+b+c)
Cost for 12.60 cum (a+b+c+d) 45,389.91 45,389.91 45,389.91
Rate per cum (a+b+c+d)/12.60 3,602.37 3,602.37 3,602.37
Say 3,602.00 3,602.00 3,602.00
Note Readymade woven wire crate rolls have been
considered in the rate analysis. In case readymade
rolls are not available, GI wire 4mm dia. @ 32 kg per
10 sqm may be provided. In that case 2 per cent of
the cost of GI wire may be added for weaving the wire
crates.
16.13 2503.3 Gabian Structure for Erosion Control, River Training
Works and Protection works

Providing and constructing gabian structures for


erosion control, river training works and protection
works with wire crates of size 2 m x 1 m x 0.3 m each
divided into 1m compartments by cross netting, made
from 4 mm galvanised steel wire @ 32 kg per 10 sqm
having minimum tensile strength of 300 Mpa
conforming to IS:280 and galvanizing coating
conforming to IS:4826, woven into mesh with double
twist, mesh size not exceeding 100 mm x 100 mm,
filled with boulders with least dimension of 200 mm, all
loose ends to be securely tied with 4 mm galvanised
steel wire.

Unit = cum
Taking output = 2 x 1 x 0.3 x 10 Nos. = 6.00 cum
a) Labour
Mate day 0.140 0.140 0.140 617.00 86.38 86.38 86.38 L-12
Mazdoor day 2.500 2.500 2.500 511.52 1,278.80 1,278.80 1,278.80 L-13
Mazdoor (Skilled) day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
b) Material
Galvanised steel wire crates of mesh size 100 mm x M-102
100 mm woven with 4mm dia. GI wire in rolls of sqm 65.000 65.000 65.000 19.00 1,235.00 1,235.00 1,235.00
required size to cover 6.00 cum.
Stone boulders with least dimension of 200 mm cum 6.000 6.000 6.000 1,994.63 11,967.78 11,967.78 11,967.78 M-003
Stone spalls of minimum size 25 mm cum 1.200 1.200 1.200 1,679.81 2,015.78 2,015.78 2,015.78 M-008
@ 20% on @ 20% on @ 20% on
c) Overhead charges 3,429.89 3,429.89 3,429.89
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 2,057.94 2,057.94 2,057.94
(a+b+c) (a+b+c) (a+b+c)
Cost for 6.00 cum (a+b+c+d) 22,637.30 22,637.30 22,637.30
Rate per cum (a+b+c+d)/6.00 3,772.88 3,772.88 3,772.88
Say 3,773.00 3,773.00 3,773.00
Note Readymade woven wire crate rolls have been
considered in the rate analysis. In case readymade
rolls are not available, GI wire 4mm dia. @ 32 kg per
10 sqm may be provided. In that case 2 per cent of
the cost of GI wire may be added for weaving the wire
crates.
Quantity Amount (Rs.)
Reference to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) ref.
Specification Project Project Project Project Project Project

16.14 2503

Providing & making Gabion structure with


Mechanically Woven Double Twisted Hexagonal
Shaped Wire mesh Gabion Boxes as per IS
16014:2012, MORT&H Clause 2500, of required size,
Mesh Type 10x12 (D=100 mm with tolerance of ± 2%)
Zinc coated, Mesh wire diameter 3.0 mm,
mechanically edged/selvedged with partitions at every
1m interval and shall have minimum 10 numbers of
openings per meter of mesh perpendicular to twist,
tying with lacing wire of diameter 2.2 mm, supplied
@3% by weight of Gabion boxes, filled with boulders
with least dimension of 200 mm, as per drawing, all
complete as per direction of Engineer-in-charge.

Unit = cum
Taking output = 2 x 1 x 1 m = 2 cum
a) Material
Crates made of Mesh type 10x12 (D=100 mm) Zn M-102
sqm 11.000 11.000 11.000 19.00 209.00 209.00 209.00
coated. (Mesh wire diameter 3.00 mm).
Surface area required = 11.00 sqm.
Stone boulder with least dimension 200mm cum 2.000 2.000 2.000 1,994.63 3,989.26 3,989.26 3,989.26 M-003
b) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mason (for plain stone work) 2nd class day 0.500 0.500 0.500 679.00 339.50 339.50 339.50 L-10
Mazdoor * day 1.500 1.500 1.500 511.52 767.28 767.28 767.28 L-13
@ 20% on @ 20% on @ 20% on
c) Overhead charges 1,070.88 1,070.88 1,070.88
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 642.53 642.53 642.53
(a+b+c) (a+b+c) (a+b+c)
Cost for 2.00 cum (a+b+c+d) 7,067.81 7,067.81 7,067.81
Rate per cum (a+b+c+d)/2 3,533.90 3,533.90 3,533.90
Say 3,534.00 3,534.00 3,534.00

16.15 Embankment Erosion Protection using Fine


Aggregate Concrete Filled Fabric Form Mattress
system

Laying of a fine aggregate concrete grade M30 filled


fabric form for erosion protection of embankments

Unit = Sqm
Taking output = 60 Sqm
a) Labour
Mate day 0.096 0.096 0.096 617.00 59.23 59.23 59.23 L-12
Mazdoor day 1.800 1.800 1.800 511.52 920.74 920.74 920.74 L-13
Mazdoor (skilled) day 0.600 0.600 0.600 565.73 339.44 339.44 339.44 L-15
b) Machinery
Transit truck agitator
For Transportation Transit truck agitator 6 cum P&M-128
t.km 13.800 x L 13.800 x L 13.800 x L 13.41 5,552.09 5,552.09 5,552.09
capacity
Unloding time hour 0.130 0.130 0.130 2,413.95 313.81 313.81 313.81 P&M-067
Concrete Pump hour 0.130 0.130 0.130 1,341.90 174.45 174.45 174.45 P&M-068
c) Materials
Item No. -
PCC M30 Grade Refer relevant item of concrete in 12.08 F
Item 12.8 (F) by using batching plant, excluding cum 6.000 6.000 6.000 6,237.00 37,422.00 37,638.00 38,352.00
formwork i.e. per cum basic cost (a+b+c)

Fabric Form mattress with 30% shrinkage sqm 78.000 78.000 78.000 62.55 4,878.90 4,878.90 4,878.90 M-108
Non-Woven Geotextile to be placed under concrete
filled fabric form including 15 per cent for overlap and sqm 9.000 9.000 9.000 62.55 562.95 562.95 562.95 M-107
shrinkage
@ 20% on @ 20% on @ 20% on
d) Overhead charges 10,044.72 10,087.92 10,230.72
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 6,026.83 6,052.75 6,138.43
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 60 sqm = a+b+c+d+e 66,295.15 66,580.27 67,522.75
Rate per sqm = (a+b+c+d+e)/60 1,104.92 1,109.67 1,125.38
Say 1,105.00 1,110.00 1,125.00
CHAPTER-17
REPAIR AND REHABILITATION
Quantity Amount (Rs.)
Reference to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project ref.
Specification Project Project Project

17.01 2811
Removal of existing cement concrete wearing coat
including its disposal complete as per Technical
Specification without causing any detrimental effect
to any part of the bridge structure and removal of
dismantled material with all lifts and lead upto 1000
m

Unit = Sq m ( Thickness 75 mm)


Taking output = 10 sqm
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery

Air Compressor 250 cfm with pneumatic P&M-15001


hour 1.000 1.000 1.000 625.80 625.80 625.80 625.80
breaker/jack hammer along with accessories. + P&M45001

Tractor-trolley. hour 0.500 0.500 0.500 1,876.50 938.25 938.25 938.25 P&M-026
@ 30% on @ 30% on @ 30% on
c) Overhead charges 630.08 630.08 630.08
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 273.03 273.03 273.03
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm = (a+d+c+d) 3,003.36 3,003.36 3,003.36
Rate per sqm = (a+b+c+d)/10 300.34 300.34 300.34
Say 300.00 300.00 300.00
17.02 2811
Removal of existing asphaltic wearing coat
comprising of 50 mm thick asphaltic concert laid
over 12 mm thick mastic asphalt including disposal
with all lift and lead upto 1000 m.

Unit = Sq m
Taking output = 10 sqm
a) Labour
Mate day 0.030 0.030 0.030 617.00 18.51 18.51 18.51 L-12
Mazdoor day 0.750 0.750 0.750 511.52 383.64 383.64 383.64 L-13
b) Machinery
P&M-15001
Air Compressor 250 cfm with pneumatic breaker. hour 0.750 0.750 0.750 625.80 469.35 469.35 469.35
+ P&M45001
Tractor-trolley. hour 0.400 0.400 0.400 1,876.50 750.60 750.60 750.60 P&M-026
@ 30% on @ 30% on @ 30% on
c) Overhead charges 486.63 486.63 486.63
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 210.87 210.87 210.87
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm = (a+d+c+d) 2,319.60 2,319.60 2,319.60
Rate per sqm = (a+b+c+d)/10 231.96 231.96 231.96
Say 232.00 232.00 232.00
17.03 2807 Guniting concrete surface with cement mortar
applied with compressor after cleaning surface and
spraying with epoxy complete as per Technical
Specification
Unit = Sq m
Taking output = 1 sqm
Assuming thickness 25 mm
a) Material
Cement kg 16.000 16.000 16.000 4.94 79.04 79.04 79.04 M-081/1000
Graded sand cum 0.040 0.040 0.040 1,994.03 79.76 79.76 79.76 M-005
Wire mesh 50mm x 50mm size of 3mm wire kg 2.000 2.000 2.000 66.72 133.44 133.44 133.44 M-194
Epoxy kg 0.670 0.670 0.670 764.50 512.22 512.22 512.22 M-095
Accelerator compound for guniting @ 4 per cent of
kg 0.640 0.640 0.640 125.00 80.00 80.00 80.00 M-227
weight of cement
Add 2 per cent of cost of material for
miscellaneous consumables like nozzles, wire 17.69 17.69 17.69
brush, cotton waste etc.
b) Labour
Mate day 0.007 0.007 0.007 617.00 4.32 4.32 4.32 L-12
Mason day 0.040 0.040 0.040 679.00 27.16 27.16 27.16 L-10
Mazdoor day 0.140 0.140 0.140 511.52 71.61 71.61 71.61 L-13
c) Machinery
Compressor with guniting equipment along with
hour 0.100 0.100 0.100 614.25 61.43 61.43 61.43 P&M-029
accessories
@ 30% on @ 30% on @ 30% on
d) Overhead charges 320.00 320.00 320.00
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 138.67 138.67 138.67
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per sqm = (a+b+c+d+e) 1,525.33 1,525.33 1,525.33
Say 1,525.00 1,525.00 1,525.00
Quantity Amount (Rs.)
Reference to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project ref.
Specification Project Project Project

17.04 2800
Providing and inserting nipples with approved
fixing compound after drilling holes for grouting as
per Technical Specifications including subsequent
cutting/removal and sealing of the hole as
necessary of nipples after completion of grouting
with Cement/Epoxy

Unit = Number
Taking output = 1 No.
a) Material
Nipples each 1.000 1.000 1.000 26.41 26.41 26.41 26.41 M-128
Cement, fixing compound and consumables @ 15
3.96 3.96 3.96
per cent of cost of nipple
b) Labour
Mate day 0.006 0.006 0.006 617.00 3.70 3.70 3.70 L-12
Mazdoor (Skilled) labour for drilling day 0.080 0.080 0.080 565.73 45.26 45.26 45.26 L-15
Mazdoor (Skilled) labour for fixing nipple and
day 0.080 0.080 0.080 565.73 45.26 45.26 45.26 L-15
sealing inlets
Mazdoor for cutting and removing of nipples day 0.040 0.040 0.040 511.52 20.46 20.46 20.46 L-13
Add 10 per cent of labour cost for drilling holes etc 11.47 11.47 11.47

@ 30% on @ 30% on @ 30% on


c) Overhead charges 46.96 46.96 46.96
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 20.35 20.35 20.35
(a+b+c) (a+b+c) (a+b+c)
Rate per No. = (a+b+c+d) 223.82 223.82 223.82
Say 224.00 224.00 224.00
17.05 2806 Sealing of cracks/porous concrete by injection
process through nipples/Grouting complete as per
Technical Specification.
A Cement Grout
Unit = kg
Taking output = 1 kg
a) Material
Cement including 10 per cent wastage kg 1.100 1.100 1.100 4.94 5.43 5.43 5.43 M-081/1000
Admixtures (anti shrinkage compound) @ 20
1.09 1.09 1.09
per cent of cost of cement
b) Labour
Mate day 0.008 0.008 0.008 617.00 4.94 4.94 4.94 L-12
Mazdoor (Skilled) day 0.100 0.100 0.100 565.73 56.57 56.57 56.57 L-15
Mazdoor day 0.100 0.100 0.100 511.52 51.15 51.15 51.15 L-13
c) Machinery
Grout pump with agitator and accessories hour 0.100 0.100 0.100 798.00 79.80 79.80 79.80 P&M-096
@ 30% on @ 30% on @ 30% on
d) Overhead charges 59.69 59.69 59.69
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 25.87 25.87 25.87
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per kg = (a+b+c+d+e) 284.54 284.54 284.54
Say 285.00 285.00 285.00
B Cement Mortar (1:1) Grouting
Unit = kg
Taking output = 1 kg
a) Material
Cement including 10 per cent wastage kg 0.550 0.550 0.550 4.94 2.72 2.72 2.72 M-081/1000
Sand including 10 per cent wastage kg 0.550 0.550 0.550 1.33 0.73 0.73 0.73 M-005/1500
Admixtures (anti shrinkage compound) @ 20
0.54 0.54 0.54
per cent of cost of cement
b) Labour
Mate day 0.008 0.008 0.008 617.00 4.94 4.94 4.94 L-12
Mazdoor (Skilled) day 0.100 0.100 0.100 565.73 56.57 56.57 56.57 L-15
Mazdoor day 0.100 0.100 0.100 511.52 51.15 51.15 51.15 L-13
c) Machinery
Grout pump with agitator and accessories hour 0.100 0.100 0.100 798.00 79.80 79.80 79.80 P&M-096
@ 30% on @ 30% on @ 30% on
d) Overhead charges 58.94 58.94 58.94
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 25.54 25.54 25.54
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per kg = (a+b+c+d+e) 280.93 280.93 280.93
Say 281.00 281.00 281.00
17.06 2800
Patching of damaged concrete surface with
polymer concrete and curing compounds, initiator
and promoter, available in present formulations, to
be applied as per instructions of manufacturer and
as approved by the Engineer.

Unit = sqm
Taking output = 10 sqm for an average thickness of
25mm.
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Quantity Amount (Rs.)
Reference to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project ref.
Specification Project Project Project

Mazdoor (Skilled) day 0.750 0.750 0.750 565.73 424.30 424.30 424.30 L-15
Mazdoor day 0.750 0.750 0.750 511.52 383.64 383.64 383.64 L-13
b) Material

Pre-packed polymer concrete based on epoxy


system complete with curing compound, intiator kg 315.000 315.000 315.000 41.00 12,915.00 12,915.00 12,915.00 M-144
and promoter including 5 per cent wastage.

c) Machinery
Grout pump with agitator and accessories hour 2.000 2.000 2.000 798.00 1,596.00 1,596.00 1,596.00 P&M-096
@ 30% on @ 30% on @ 30% on
d) Overhead charges 4,606.79 4,606.79 4,606.79
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 1,996.27 1,996.27 1,996.27
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10 sqm = a+b+c+d+e 21,959.02 21,959.02 21,959.02
Rate per sqm = (a+b+c+d+e)/10 2,195.90 2,195.90 2,195.90
Say 2,196.00 2,196.00 2,196.00
Note
This item is a proprietory item available in market
as pre-packed polymer concrete and is required to
be applied as per instructions of the manufacturer.

17.07 2803 Sealing of crack / porous concrete with Epoxy


Grout by injection through nipples complete as per
clause 2803.1.
Unit = kg
Taking output = 1 kg
a) Material
Epoxy including 10 per cent wastage kg 1.100 1.100 1.100 764.50 840.95 840.95 840.95 M-095
b) Labour
Mate day 0.008 0.008 0.008 617.00 4.94 4.94 4.94 L-12
Mazdoor (Skilled) day 0.100 0.100 0.100 565.73 56.57 56.57 56.57 L-15
Mazdoor day 0.100 0.100 0.100 511.52 51.15 51.15 51.15 L-13
c) Machinery
Epoxy Injection gun hour 0.100 0.100 0.100 380.10 38.01 38.01 38.01 P&M-112
@ 30% on @ 30% on @ 30% on
d) Overhead charges 297.49 297.49 297.49
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 128.91 128.91 128.91
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per kg = (a+b+c+d+e) 1,418.02 1,418.02 1,418.02
Say 1,418.00 1,418.00 1,418.00
17.08 2804 Applying epoxy mortar over leached, honey
combed and spalled concrete surface and exposed
steel reinforcement complete as per Technical
Specification
Unit = sqm
Taking output = 10 sqm
Assume average 10mm thickness of epoxy mortar
a) Material
Epoxy resin-hardener mix for prime coat kg 2.500 2.500 2.500 378.00 945.00 945.00 945.00 M-098
Epoxy mortar kg 2.200 2.200 2.200 697.78 1,535.12 1,535.12 1,535.12 M-096
Epoxy resin -hardener mix for seal coat. kg 2.000 2.000 2.000 378.00 756.00 756.00 756.00 M-098
Add 3 per cent cost of material for other
consumables like acetone etc and to cover 97.08 97.08 97.08
wastage.
b) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor (Skilled) day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
@ 30% on @ 30% on @ 30% on
c) Overhead charges 1,168.95 1,168.95 1,168.95
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 506.55 506.55 506.55
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm = a+b+c+d 5,572.00 5,572.00 5,572.00
Rate per sqm = (a+b+c+d)/10 557.20 557.20 557.20
Say 557.00 557.00 557.00
17.09 2807

Removal of defective concrete, cleaning the


surface thoroughly, applying the shotcrete mixture
mechanically with compressed air under pressure,
comprising of cement, sand, coarse aggregates,
water and quick setting compound in the proportion
as per clause 2807.1., sand and coarse
aggregates conforming to IS: 383 and table 1 of IS:
9012 respectively, water cement ratio ranging from
0.35 to 0.50, density of gunite not less than 2000
kg/cum, strength not less than 25 Mpa and
workmanship conforming to clause 2807.6.

unit: sqm
Quantity Amount (Rs.)
Reference to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project ref.
Specification Project Project Project

Taking output = 10 sqm, 40 mm average thickness.


a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
Mazdoor (Skilled) day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
b) Machinery
Air compressor 250 cfm hour 1.000 1.000 1.000 614.25 614.25 614.25 614.25 P&M-029
Shotcreteing equipment hour 1.000 1.000 1.000 1,830.15 1,830.15 1,830.15 1,830.15 P&M-095
water tanker 6 KL capacity hour 0.020 0.020 0.020 1,005.00 20.10 20.10 20.10 P&M-025
c) Material
Cement kg 120.000 120.000 120.000 4.94 592.80 592.80 592.80 M-081/1000
Sand cum 0.150 0.150 0.150 1,994.03 299.10 299.10 299.10 M-005
Coarse aggregate of size 4.75mm cum 0.150 0.150 0.150 1,887.12 283.07 283.07 283.07 M-029
Quick setting compound kg 2.500 2.500 2.500 103.00 257.50 257.50 257.50 M-146
Water KL 0.100 0.100 0.100 16.00 1.60 1.60 1.60 M-191
@ 30% on @ 30% on @ 30% on
d) Overhead charges 1,338.56 1,338.56 1,338.56
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 580.04 580.04 580.04
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10 sqm = a+b+c+d+e 6,380.49 6,380.49 6,380.49
Rate per sqm = (a+b+c+d+e)/10 638.05 638.05 638.05
Say 638.00 638.00 638.00
17.10 2800 Applying pre-packed cement based polymer mortar
of strength 45 Mpa at 28 days for replacement of
spalled concrete
Unit = sqm
Taking output = 10 sqm
Assumed thickness - 10 mm
a) Material
Acrylic polymer bonding coat Litre 1.400 1.400 1.400 236.30 330.82 330.82 330.82 M-057
pre-packed cement based polymer mortar of
kg 12.000 12.000 12.000 41.00 492.00 492.00 492.00 M-144
strength 45 Mpa at 28 days
Add 3 per cent of (a ) above for wastage. 24.68 24.68 24.68
b) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor (Skilled) day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
@ 30% on @ 30% on @ 30% on
c) Overhead charges 423.24 423.24 423.24
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 183.41 183.41 183.41
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm = a+b+c+d 2,017.46 2,017.46 2,017.46
Rate per sqm = (a+b+c+d)/10 201.75 201.75 201.75
Say 202.00 202.00 202.00
17.11 2805
Eproxy bonding of new concrete to old concrete
Unit = sqm
Taking output = 10 sqm
a) Material

Epoxy resin with pot life not less than 60-90


kg 8.000 8.000 8.000 378.00 3,024.00 3,024.00 3,024.00 M-098
minutes and satisfying testing as per clause 2803.9

Add 3 per cent of (a ) above for wastage. 90.72 90.72 90.72


b) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor (Skilled) day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
@ 30% on @ 30% on @ 30% on
c) Overhead charges 1,103.41 1,103.41 1,103.41
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 478.14 478.14 478.14
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm = a+b+c+d 5,259.58 5,259.58 5,259.58
Rate per sqm = (a+b+c+d)/10 525.96 525.96 525.96
Say 526.00 526.00 526.00
17.12 2812
Providing external prestressing with high tensile
steel wires/strands including drilling for passage of
prestessing steel, all accessories for stressing and
stressing operation and grouting complete as per
drawing and Technical Specification

Span assumed: 25 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 1 MT
Assume 12.7mm dia. Strand in 12T13 system.
Weight-9.42 kg/m of cable.
a) Material
Quantity Amount (Rs.)
Reference to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project ref.
Specification Project Project Project

HTS strand including 5 per cent wastage and extra


tonne 1.050 1.050 1.050 63,806.54 66,996.87 66,996.87 66,996.87 M-118
length for jacking
HDPE pipes 75mm dia including 5 per cent
metre 112.000 112.000 112.000 234.00 26,208.00 26,208.00 26,208.00 M-113
wastage
Cement for grouting kg 400.000 400.000 400.000 4.94 1,976.00 1,976.00 1,976.00 M-081/1000
Tube anchorage set complete with bearing plate,
each 8.000 8.000 8.000 48.45 387.58 387.58 387.58 M-189
permanent wedges etc
Epoxy kg 6.000 6.000 6.000 764.50 4,587.00 4,587.00 4,587.00 M-095
MS plates for deviator (where deviator blocks are
tonne 2.100 2.100 2.100 63,806.54 133,993.74 133,993.74 133,993.74 M-181
not provided)
Add 20 per cent cost of material for other
materials like lead sheet, sleeves, deviator fixtures 46,829.84 46,829.84 46,829.84
etc.
b) Labour
i) For making holes in the structure .
Mate day 0.240 0.240 0.240 617.00 148.08 148.08 148.08 L-12
Mazdoor Semi-skilled) day 3.000 3.000 3.000 617.00 1,851.00 1,851.00 1,851.00 L-14
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
ii) For making and fixing anchorages for cables and
placement of cables .
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Blacksmith day 3.000 3.000 3.000 738.00 2,214.00 2,214.00 2,214.00 L-02
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
iii) For prestressing
Mate/Supervisor day 0.134 0.134 0.134 617.00 82.68 82.68 82.68 L-12
Fitter day 0.700 0.700 0.700 738.00 516.60 516.60 516.60 L-08
Mazdoor day 2.650 2.650 2.650 511.52 1,355.53 1,355.53 1,355.53 L-13
iv) For grouting
Mate/Supervisor day 0.134 0.134 0.134 617.00 82.68 82.68 82.68 L-12
Mason day 0.700 0.700 0.700 738.00 516.60 516.60 516.60 L-11
Mazdoor day 2.650 2.650 2.650 511.52 1,355.53 1,355.53 1,355.53 L-13
c) Machinery
Stressing jack with pump hour 4.000 4.000 4.000 559.65 2,238.60 2,238.60 2,238.60 P&M-109
Grouting pump with agitator hour 1.350 1.350 1.350 798.00 1,077.30 1,077.30 1,077.30 M-110
@ 30% on @ 30% on @ 30% on
d) Overhead charges 89,494.75 89,494.75 89,494.75
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 38,781.06 38,781.06 38,781.06
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per MT = (a+b+c+d+e) 426,591.62 426,591.62 426,591.62
Say 426,592.00 426,592.00 426,592.00
17.13 2812
Providing external prestressing with high tensile
steel wires/strands including drilling for passage of
prestessing steel, all accessories for stressing and
stressing operation and grouting complete as per
drawing and Technical Specification

Span assumed: 50 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 3.10 MT
Assume 12.7mm dia. Strand in 19T13 system.
Weight-14.73 kg/m of cable.
a) Material
HTS strand including 5 per cent wastage and extra
tonne 3.100 3.100 3.100 63,806.54 197,800.29 197,800.29 197,800.29 M-118
length for jacking
HDPE pipes 90mm dia including 5 per cent
metre 224.000 224.000 224.000 252.00 56,448.00 56,448.00 56,448.00 M-114
wastage
Cement for grouting tonne 1.010 1.010 1.010 4,940.00 4,989.40 4,989.40 4,989.40 M-081
Tube anchorage set complete with bearing plate,
each 8.000 8.000 8.000 48.45 387.58 387.58 387.58 M-189
permanent wedges etc
Epoxy kg 10.000 10.000 10.000 764.50 7,645.00 7,645.00 7,645.00 M-095
MS plates for deviator (where deviator blocks are
tonne 7.000 7.000 7.000 63,806.54 446,645.81 446,645.81 446,645.81 M-181
not provided)
Add 20 per cent cost of material for other
materials like lead sheet, sleeves, deviator fixtures 142,783.22 142,783.22 142,783.22
etc.
b) Labour
i) For making holes in the structure .
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor Semi-skilled) day 8.000 8.000 8.000 617.00 4,936.00 4,936.00 4,936.00 L-14
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
ii) For making and fixing anchorages for cables and
placement of cables .
Mate day 1.280 1.280 1.280 617.00 789.76 789.76 789.76 L-12
Blacksmith day 7.000 7.000 7.000 738.00 5,166.00 5,166.00 5,166.00 L-02
Mazdoor day 25.000 25.000 25.000 511.52 12,788.00 12,788.00 12,788.00 L-13
iii) For prestressing
Mate/Supervisor day 0.200 0.200 0.200 617.00 123.40 123.40 L-12
Fitter day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-08
Quantity Amount (Rs.)
Reference to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project ref.
Specification Project Project Project

Mazdoor day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
iv) For grouting
Mate/Supervisor day 0.260 0.260 0.260 617.00 160.42 160.42 160.42 L-12
Mason day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-11
Mazdoor day 5.000 5.000 5.000 511.52 2,557.60 2,557.60 2,557.60 L-13
c) Machinery
Stressing jack with pump hour 7.000 7.000 7.000 559.65 3,917.55 3,917.55 3,917.55 P&M-109
Grouting pump with agitator hour 3.000 3.000 3.000 798.00 2,394.00 2,394.00 2,394.00 M-110
@ 30% on @ 30% on @ 30% on
d) Overhead charges 269,269.39 269,269.39 269,232.37
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 116,683.40 116,683.40 116,667.36
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 3.10 MT = a+b+c+d+e 1,283,517.41 1,283,517.41 1,283,340.95
Rate per MT = (a+b+c+d+e)/3.10 414,037.87 414,037.87 413,980.95
Say 414,038.00 414,038.00 413,981.00
17.14 2812
Providing external prestressing with high tensile
steel wires/strands including drilling for passage of
prestessing steel, all accessories for stressing and
stressing operation and grouting complete as per
drawing and Technical Specification

Span assumed: 100 m


No. of cables: 6 no.
No. of anchorages : 12 no.
Unit = MT
Taking output = 9.28 MT
Assume 12.7mm dia. Strand in 19T13 system.
Weight-14.73 kg/m of cable.
a) Material
HTS strand including 5 per cent wastage and extra
tonne 9.280 9.280 9.280 63,806.54 592,124.73 592,124.73 592,124.73 M-118
length for jacking
HDPE pipes 90 mm dia including 5 per cent
metre 672.000 672.000 672.000 252.00 169,344.00 169,344.00 169,344.00 M-114
wastage
Cement for grouting tonne 3.040 3.040 3.040 4,940.00 15,017.60 15,017.60 15,017.60 M-081
Tube anchorage set complete with bearing plate,
each 12.000 12.000 12.000 48.45 581.36 581.36 581.36 M-189
permanent wedges etc
Epoxy kg 14.000 14.000 14.000 764.50 10,703.00 10,703.00 10,703.00 M-095
MS plates for deviator (where deviator blocks are
tonne 20.000 20.000 20.000 63,806.54 1,276,130.89 1,276,130.89 1,276,130.89 M-181
not provided)
Add 20 per cent cost of material for other
materials like lead sheet, sleeves, deviator fixtures 412,780.32 412,780.32 412,780.32
etc.
b) Labour
i) For making holes in the structure .
Mate day 1.720 1.720 1.720 617.00 1,061.24 1,061.24 1,061.24 L-12
Mazdoor Semi-skilled) day 18.000 18.000 18.000 617.00 11,106.00 11,106.00 11,106.00 L-14
Mazdoor day 25.000 25.000 25.000 511.52 12,788.00 12,788.00 12,788.00 L-13
ii) For making and fixing anchorages for cables and
placement of cables .
Mate day 4.000 4.000 4.000 617.00 2,468.00 2,468.00 2,468.00 L-12
Blacksmith day 20.000 20.000 20.000 738.00 14,760.00 14,760.00 14,760.00 L-02
Mazdoor day 80.000 80.000 80.000 511.52 40,921.60 40,921.60 40,921.60 L-13
iii) For prestressing
Mate/Supervisor day 0.300 0.300 0.300 617.00 185.10 185.10 185.10 L-12
Fitter day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-08
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
iv) For grouting
Mate/Supervisor day 1.000 1.000 1.000 617.00 617.00 617.00 617.00 L-12
Mason day 5.000 5.000 5.000 738.00 3,690.00 3,690.00 3,690.00 L-11
Mazdoor day 20.000 20.000 20.000 511.52 10,230.40 10,230.40 10,230.40 L-13
c) Machinery
Stressing jack with pump hour 10.000 10.000 10.000 559.65 5,596.50 5,596.50 5,596.50 P&M-109
Grouting pump with agitator hour 10.000 10.000 10.000 798.00 7,980.00 7,980.00 7,980.00 M-110
@ 30% on @ 30% on @ 30% on
d) Overhead charges 777,678.56 777,678.56 777,678.56
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 336,994.04 336,994.04 336,994.04
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 9.28 MT = a+b+c+d+e 3,706,934.47 3,706,934.47 3,706,934.47
Rate per MT = (a+b+c+d+e)/9.28 378,258.62 378,258.62 378,258.62
Say 378,259.00 378,259.00 378,259.00
17.15 2810 Replacement of Bearings complete as per
Technical Specification
Unit = No
Taking output = 3 No.
Lifting of superstructure span by jacking up from
below i.e. by placing the jacks on pier/abutment
caps for span length of 30m.
a) Labour
Mate day 0.640 0.640 0.640 617.00 394.88 394.88 394.88 L-12
Mazdoor (Skilled) day 4.000 4.000 4.000 565.73 2,262.92 2,262.92 2,262.92 L-15
Quantity Amount (Rs.)
Reference to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project ref.
Specification Project Project Project

Mazdoor day 12.000 12.000 12.000 511.52 6,138.24 6,138.24 6,138.24 L-13
b) Machinery
i) Hire charges for jack of 40 tonne lifting capacity.
Day 3.000 3.000 3.000 378.00 1,134.00 1,134.00 1,134.00 P&M-114
(Lifting of span)
c) Material
Wooden packing cum 0.150 0.150 0.150 1,659.00 248.85 248.85 248.85 M-197
Cost of bearing. (Replacement of bearing) each 3.000 3.000 3.000 55,660.00 166,980.00 166,980.00 166,980.00 M-065
@ 30% on @ 30% on @ 30% on
d) Overhead charges 53,147.67 53,147.67 53,147.67
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 23,030.66 23,030.66 23,030.66
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost of repair of 3 bearings = a+b+c+d 253,337.21 253,337.21 253,337.21
Rate of repair per bearing = (a+b+c+d)/3 84,445.74 84,445.74 84,445.74
Say 84,446.00 84,446.00 84,446.00
Note The work entails replacement of all the bearings on
one side of the span.
17.16 2811 Rectification of Bearings as per Technical
Specifications
Unit = 1 No
Taking output = 3 No.

a) Lifting of superstructure span by jacking up


from below i.e. by placing the jacks on
pier/abutment caps for span length of 30m.

a) Labour
i) Mate day 0.640 0.640 0.640 617.00 394.88 394.88 394.88 L-12
ii) Mazdoor (Skilled) day 4.000 4.000 4.000 565.73 2,262.92 2,262.92 2,262.92 L-15
iii) Mazdoor day 12.000 12.000 12.000 511.52 6,138.24 6,138.24 6,138.24 L-13
b) Machinery
i) Hire charges for jack of 40 tonne lifting capacity.
Day 3.000 3.000 3.000 378.00 1,134.00 1,134.00 1,134.00 P&M-114
(Lifting of span)
c) Material
Cost of parts to be replaced for 3 bearings. each 3.000 3.000 3.000 630.00 1,890.00 1,890.00 1,890.00 M-064
Wooden packing cum 0.150 0.150 0.150 1,659.00 248.85 248.85 248.85 M-197
@ 30% on @ 30% on @ 30% on
d) Overhead charges 3,620.67 3,620.67 3,620.67
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 1,568.96 1,568.96 1,568.96
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost of repair of 3 bearings = a+b+c+d 17,258.51 17,258.51 17,258.51
Rate of repair per bearing = (a+b+c+d)/3 5,752.84 5,752.84 5,752.84
Say 5,753.00 5,753.00 5,753.00
Note The rectification of 3 bearings included in this
analysis are on the same side of the span.
17.17 Replacement of Expansion Joints complete as per
drawings
Unit -1 RM
Taking output = 12 RM
a) Material
Epoxy for bonding new concrete to old concrete @
kg 9.600 9.600 9.600 764.50 7,339.20 7,339.20 7,339.20 M-095
0.8 kg/sqm
cum 3.600 7,697.54 27,711.15
M-30 grade cement concrete excluding OH & CP Item No. -
cum 3.600 7,739.45 27,862.01
(Rate as per items 14.01 C (i) (p) 14.01 C (i)(p)
cum 3.600 7,883.11 28,379.19
b) Labour
Removal of old expansion joint including breaking
of concrete, cutting of lugs and shifting of broken
material etc.
Mate day 0.260 0.260 0.260 617.00 160.42 160.42 160.42 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor (Skilled) day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
@ 30% on @ 30% on @ 30% on
c) Overhead charges 11,568.83 11,614.08 11,769.24
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 5,013.16 5,032.77 5,100.00
(a+b+c) (a+b+c) (a+b+c)
Cost for replacement of 12 RM = a+b+c+d 55,144.74 55,360.47 56,100.04
Rate per RM = (a+b+c+d)/12 4,595.40 4,613.37 4,675.00
Say 4,595.00 4,613.00 4,675.00
Note
The rate for the installation of new expansion joints
may be taken from the chapter on superstructure.
Broken concrete will have to be replaced which has
been included in this analysis.

17.18 Replacement of Damaged Concrete Railing.


Unit = RM
Taking output = 10 RM
a) Labour
Labour for dismantling old railing and disposal of
dismantled material.
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 5.000 5.000 5.000 511.52 2,557.60 2,557.60 2,557.60 L-13
Quantity Amount (Rs.)
Reference to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project ref.
Specification Project Project Project

b) Machinery
Tractor-trolley for disposal of dismantled material hour 1.000 1.000 1.000 1,876.50 1,876.50 1,876.50 1,876.50 P&M-026

@ 30% on @ 30% on @ 30% on


c) Overhead charges 1,367.25 1,367.25 1,367.25
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 592.48 592.48 592.48
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 m = a+b+c+d 6,517.23 6,517.23 6,517.23
Rate per metre = (a+b+c+d)/10 651.72 651.72 651.72
Say 652.00 652.00 652.00
Note
The rate for the provision of new railing may be
adopted from the chapter on superstructure.

17.19 Replacement of Crash Barrier.


Unit = RM
Taking output = 10 M
a) Labour
Labour for dismantling old railing and disposal of
dismantled material.
Mate day 0.400 0.400 0.400 617.00 246.80 246.80 246.80 L-12
Mazdoor day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-13
b) Machinery
Tractor-trolley for disposal of dismantled material hour 1.000 1.000 1.000 1,876.50 1,876.50 1,876.50 1,876.50 P&M-026

@ 30% on @ 30% on @ 30% on


c) Overhead charges 2,171.55 2,171.55 2,171.55
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 941.01 941.01 941.01
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 m = a+b+c+d 10,351.06 10,351.06 10,351.06
Rate per metre = (a+b+c+d)/10 1,035.11 1,035.11 1,035.11
Say 1,035.00 1,035.00 1,035.00
Note The rate for the construction of new crash barrier
may be adopted from chapter 8 on Traffic and
Transportation.
17.20
Replacement of Damaged Mild Steel Railing
Unit = RM
Taking output = 10 M
a) Labour
Labour for dismantling old railing and disposal of
dismantled material.
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Mazdoor day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
b) Machinery
Tractor-trolley for disposal of dismantled material hour 1.000 1.000 1.000 1,876.50 1,876.50 1,876.50 1,876.50 P&M-026

@ 30% on @ 30% on @ 30% on


c) Overhead charges 1,206.39 1,206.39 1,206.39
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 522.77 522.77 522.77
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 m = a+b+c+d 5,750.46 5,750.46 5,750.46
Rate per metre = (a+b+c+d)/10 575.05 575.05 575.05
Say 575.00 575.00 575.00
17.21 Repair of Crash Barrier

Repair of concrete crash barrier with cement


concert of M-30 grade by cutting and trimming the
damaged portion to a regular shape, cleaning the
area to be repaired thoroughly, applying cement
concert after erection of proper form work.

Unit = Running meter.


Taking output = 10 M.
It is assumed that damage is to the extent of 10 per
cent of the volume of concrete .This will require
0.30 cum of concrete.
a) Manpower*
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
*
For dismantling and trimming the surface to a
regular shape and removal of damaged material.

b) Material
cum 0.300 7,697.54 2,309.26
M-30 grade cement concrete excluding OH & CP Item No. -
cum 0.300 7,739.45 2,321.83
(Rate as per items 14.01 C (i) (p) 14.01 C (i)(p)
cum 0.300 7,883.11 2,364.93
This may be priced based on the rate given the
chapter of superstructure.
@ 30% on @ 30% on @ 30% on
c) Overhead charges 853.64 857.41 870.34
(a+b) (a+b) (a+b)
Quantity Amount (Rs.)
Reference to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project ref.
Specification Project Project Project

@ 10% on @ 10% on @ 10% on


d) Contractor's profit 369.91 371.54 377.15
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 m = a+b+c+d 4,069.01 4,086.99 4,148.62
Rate per m = (a+b+c+d)/10 406.90 408.70 414.86
Say 407.00 409.00 415.00
17.22 Repair of RCC Railing
Carrying out repair of RCC M30 railing to bring it to
the original shape.
Unit = Running meter.
Taking output = 10 M.
It is assumed that damage is to the extent of 10 per
cent .
a) Material
cum 0.100 7,697.54 769.75
M-30 grade cement concrete excluding OH & CP Item No. -
cum 0.100 7,739.45 773.94
(Rate as per items 14.01 C (i) (p) 14.01 C (i)(p)
cum 0.100 7,883.11 788.31
tonne 0.013 52,080.00 677.04
HYSD bar reinforcement Rate as per item No Item No. -
tonne 0.013 52,154.00 678.00
14.02(Excluding OH & CP) 14.02
tonne 0.013 52,300.00 679.90
b) Labour*
Mate day 0.008 0.008 0.008 617.00 4.94 4.94 4.94 L-12
mazdoor day 0.200 0.200 0.200 511.52 102.30 102.30 102.30 L-13
*
For dismantling and trimming the surface to a
regular shape and removal of damaged material.

@ 30% on @ 30% on @ 30% on


c) Overhead charges 466.21 467.76 472.64
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 202.02 202.69 204.81
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 m = a+b+c+d 2,222.27 2,229.64 2,252.89
Rate per m = (a+b+c+d)/10 222.23 222.96 225.29
Say 222.00 223.00 225.00
17.23 Repair of Steel Railing
Repair of steel railing to bring it to the original
shape
It is assumed that the damage to the steel railing is
to the extent of 10 per cent .
Unit = Running meter.
Taking output = 10 M.
a) Material
Mild steel ISMC series kg 29.000 29.000 29.000 63.81 1,850.39 1,850.39 1,850.39 M-181/1000
Flat iron kg 10.000 10.000 10.000 63.81 638.07 638.07 638.07 M-181/1000
MS Bolt and nuts kg 1.000 1.000 1.000 64.83 64.83 64.83 64.83 M-129
Add 5 per cent of cost of material for painting. 127.66 127.66 127.66
b) Labour
Mate day 0.016 0.016 0.016 617.00 9.87 9.87 9.87 L-12
Mazdoor (Skilled) day 0.200 0.200 0.200 565.73 113.15 113.15 113.15 L-15
Mazdoor day 0.200 0.200 0.200 511.52 102.30 102.30 102.30 L-13
@ 30% on @ 30% on @ 30% on
c) Overhead charges 871.88 871.88 871.88
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 377.81 377.81 377.81
(a+b+c) (a+b+c) (a+b+c)
Cost of repair for10m = a+b+c+d 4,155.96 4,155.96 4,155.96
Cost of meter = (a+b+c+d)/10 415.60 415.60 415.60
Say 416.00 416.00 416.00
17.24 Mobile Bridge Inspection Unit (MBIU) Inspection of
bridge by using of Mobile Bridge Inspection
Unit(MBIU)
Unit = km
Taking output = 50 km.
a) Labour
Mate day 1.360 1.360 1.360 617.00 839.12 839.12 839.12 L-12
Mazdoor (Skilled) day 34.000 34.000 34.000 565.73 19,234.82 19,234.82 19,234.82 L-15
Mazdoor day 34.000 34.000 34.000 511.52 17,391.68 17,391.68 17,391.68 L-13
b) Machinery
Mobile Bridge Inspection Unit (MBIU) hour 266.667 266.667 266.667 6,887.00 1,836,535.63 1,836,535.63 1,836,535.63 P&M-136
Mobile Bridge Inspection Unit (MBIU) Mobilization
hour 15.000 15.000 15.000 2,883.30 43,249.50 43,249.50 43,249.50 P&M-014
& demobilization
Add 1 Percent of cost of a+b for Miscellaneous
19,172.51 19,172.51 19,172.51
work
@ 30% on @ 30% on @ 30% on
c) Overhead charges 580,926.98 580,926.98 580,926.98
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 251,735.02 251,735.02 251,735.02
(a+b+c) (a+b+c) (a+b+c)
Cost for 50 km. = a+b+c+d 2,769,085.26 2,769,085.26 2,769,085.26
Rate per km. = (a+b+c+d)/50 55,381.71 55,381.71 55,381.71
Say 55,382.00 55,382.00 55,382.00
CHAPTER-18
Tunnel Work
Reference to
Rate Amount Remarks/ Input
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) ref.
Specification
18.01 304 Excavation in Ordinary Rock using Hydraulic Excavator and
Tippers withfor
Excavation Disposal
Portal inupto 1000 metres.
Ordinary Rock with hydraulic excavator
including cutting and loading in tippers, trimming bottom and side
slopes, in accordance with requirements of lines, grades and
cross sections, and disposal of excavated materials including all
lifts and lead upto 1000m

Unit = cum
Taking output = 60 cum
a) Labour
Mate day 0.040 617.00 24.68 L-12
Mazdoor day 1.000 511.52 511.52 L-13
b) Machinery
Excavator 1.1 cum bucket capacity hour 8.214 3,074.00 25,249.54 P&M-008
Jack Hammer hour 8.214 206.00 1,692.06 P&M-010
Loading & unloading charges for disposed of grabbed material cum 72.000 118.14 8,506.08 P&M-131
Tipper
(Using 10 cumcum
by 10 capacity for Tipper
capacity transportation
& 1 Cumtocapacity
dumpingLoader)
yard
t-km 120.000 10.53 1,263.50 P&M-123
considering lead @ 1km
c) Overhead charges @ 25% on (a+b) 9,311.85
d) Contractor's profit @ 10% on (a+b+c) 4,655.92
Cost for 60 cum = a+b+c+d 51,215.15
Rate per cum = (a+b+c+d)/60 853.59
say 854.00
18.02 303 & 304 Excavation in Hard Rock (blasting prohibited)
Excavation for Portal in Hard Rock (blasting prohibited) with
hydraulic
Unit = cumexcavator including cutting and loading in tippers,
trimming bottom and side slopes, in accordance with requirements
Taking output = 50 cum
of lines, grades and cross sections, and and disposal of excavated
a) Labour
materials including all lifts and lead upto 1000m
Mate day 0.040 617.00 24.68 L-12
Mazdoor day 1.000 511.52 511.52 L-13
b) Machinery
Excavator 1.1 cum bucket capacity hour 10.039 3,074.00 30,860.55 P&M-008
Jack Hammer hour 10.039 206.00 2,068.08 P&M-010
Loading & unloading charges for disposed of grabbed material cum 60.000 118.14 7,088.40 P&M-131
(Using
Tipper 10by 10
cumcum capacity
capacity for Tipper & 1 Cumtocapacity
transportation dumpingLoader)
yard t-km 100.000 10.53 1,052.92 P&M-123
considering
Credit lead @ 1km
for excavated rock found suitable for use @ 50 per cent of cum 30.000 319.70 -9,591.00 M-090
excavated
c) Overhead quantity
charges @ 25% on (a+b) 8,003.79
d) Contractor's profit @ 10% on (a+b+c) 4,001.89
Cost for 50 cum = a+b+c+d 44,020.82
Rate per cum = (a+b+c+d)/50 880.42
say 880.00
18.03 304 Excavation in Soil using Hydraulic Excavator and Tippers with
Disposal
Excavationupto
for1000
portalmetres.
in soil with hydraulic excavator including
cutting and loading in tippers, trimming bottom and side slopes, in
accordance with requirements of lines, grades and cross sections,
and and disposal of excavated materials including all lifts and
lead upto 1000m

Unit = cum
Taking output = 350 cum
a) Labour
Mate day 0.040 617.00 24.68 L-12
Mazdoor day 1.000 511.52 511.52 L-13
b) Machinery
Excavator 1.1 cum bucket capacity hour 5.024 3,074.00 15,442.79 P&M-008
Loading & unloading charges for disposed of grabbed material hour 5.024 2,274.30 11,425.35 P&M-016
(Using 10
Tipper by 10
cumcum capacity
capacity for Tipper & 1 Cumtocapacity
transportation dumpingLoader)
yard t-km 525.000 10.53 5,527.81 P&M-123
considering
c) Overhead leadcharges
@ 1km @ 25% on (a+b) 8,233.04
d) Contractor's profit @ 10% on (a+b+c) 4,116.52
Cost for 350 cum = a+b+c+d 45,281.71
Rate per cum = (a+b+c+d)/350 129.38
say 129.00
18.04 Drill steel with Drill jumboo
Excavation for tunnel by using drilling & blasting methods in all
types of rock including cost of all materials,machinery, labour,
scaling excavated surface, marking, ventilation, lighting, drainage,
removing and hauling the excavated muck outside tunnel upto
specified dump area and all other ancillary operations etc.

Unit = cum
Taking output = 480 Cum
a) Labour
Mate day 0.320 617.00 197.44 L-12
Mazdoor day 6.000 511.52 3,069.12 L-13
Mazdoor (Skilled) day 2.000 565.73 1,131.46 L-15
b) Machinery
Three boom Hydraulic Drill Jumbo hour 25.067 12,007.80 300,995.52 P&M-092
Excavator for Scaling hour 2.000 3,074.00 6,148.00 P&M-008
Tipper 10 cum capacity for transportation tonne.km 480 x 2 x L 10.53 28,800.00 P&M-123
Loading & unloading charges(Using by 10 cum capacity Tipper & cum 576.000 118.14 68,048.64 P&M-131
1Dozer
Cum (175
capacity
HP)Loader) hour 9.600 5,087.25 48,837.60 P&M-002
c) Materials
Explosives Kg 576.000 81.90 47,174.40 M-215
Delay Detonators Nos. 228.000 21.00 4,788.00 M-216
Electric Detonators Nos. 35.000 21.00 735.00 M-217
Detonation fuse coil Meter 50.000 19.00 950.00 M-218
3.7 m long extension rod Nos 1.043 10,000.00 10,434.78 M-219
Difter rod Nos 0.505 15,000.00 7,578.95 M-221
R32 shank adapter Nos 1.043 13,000.00 13,565.22 M-222
45 mm Button Bit Nos 3.692 3,000.00 11,076.92 M-223

Add 10 per cent of cost of a+b+c towards Other consumable petty


stores such as balsting batteries, galvanometers and Sharpening 55,353.11
charges of bit etc.
d) Overhead charges @ 25% on (a+b+c) 152,221.04
e) Contractor's profit @ 10% on (a+b+c+d) 76,110.52
Cost for 480 cum = a+b+c+d+e 837,215.71
Rate per cum = (a+b+c+d+e)/480 1,744.20
say 1,744.00

18.05 305
Dewatering tunnel by pumping out water collected by natural
drainage inside tunnel including
Dewatering in tunnel by pumping out water collected by natural
drainage
Unit = cuminside tunnel including providing sump wherever
necessary, cost of all materials, machinery, labour, Taking
drainage and =
output 20000 Hour
all other ancillary operations etc., complete.
a) Labour
Mate day 100.000 617.00 61,700.00 L-12
Mazdoor day 2500.000 511.52 1,278,800.00 L-13
b) Machinery
Water Pump 10 HP hour 20000.000 328.65 6,573,000.00 P&M-097

c) Materials
GI Pipe 100 mm Dia Meter 500.000 496.00 248,000.00 M-239
Flange Kg. 41.667 1.00 41.67 M-241
Nut & Bolt Kg. 133.333 64.83 8,643.60 M-129
Bracket Kg. 1125.000 1.00 1,125.00 M-241
Credit for salvage value of GI Pipe @ 20 per cent Meter 100.000 -496.00 -49,600.00 M-239

d) Overhead charges @ 25% on (a+b+c) 2,030,427.57


e) Contractor's profit @ 10% on (a+b+c+d) 1,015,213.78
Cost for 20000 cum = a+b+c+d+e 11,167,351.62
Rate per cum = (a+b+c+d+e)/20000 558.37
say 558.00

18.06 Providing , Fitting and Placing of Ribs


Providing , Fitting and Placing of Ribs including Fabrication,
Erection,Temporary fixture, Handling of material inside fabrication
workshop, final matching, field welding and complete as per
Drawing and Technical Specifications.

Unit = cum
Taking output = 26 Tonne
a) Labour
Mate day 0.800 617.00 493.60 L-12
Mazdoor day 10.000 511.52 5,115.20 L-13
Mazdoor(Semi Skilled) day 5.000 617.00 3,085.00 L-14
Welder day 5.000 738.00 3,690.00 L-02
b) Machinery
Rotating Telehandlers hour 37.180 1,207.50 44,894.85 P&M-094
c) Materials
ISMB 350 Tonne 20.732 63,806.54 1,322,818.14 M-181
(Including
MS Channel0.25%
ISMCWastage)
75 Tonne 3.830 63,806.54 244,350.35 M-181
(Including
MS 0.25%
Plate 200 Wastage)
x 200 x 12 mm Tonne 1.504 63,806.54 95,949.09 M-181
(Including 0.25%(MWastage)
Nuts and bolts 16X40) Kg 151.200 64.83 9,801.84 M-129
Add 40 per cent of cost of a+b+c towards of Fabrication,
Erection,Temporary fixture, Handling of material, final matching 692,079.23
and field welding etc.

d) Overhead charges @ 25% on (a+b+c) 605,569.33


e) Contractor's profit @ 10% on (a+b+c+d) 302,784.66
Cost for 26 Tonne = a+b+c+d+e 3,330,631.29
Rate per Tonne = (a+b+c+d+e)/26 128,101.20
say 128,101.00
18.07 2807 Shotcreting with Steel fibre reinforced micro silica shotcrete
(SFRS)
Shotcreting to upper bench / lower bench with steel fiber
reinforced shotcrete (SFRS) , shotcrete compressive strength
shall be 25 N/mm2 and complete as per Drawing and Technical
Specifications.

Unit = cum
Taking output = 120 Cum
a) Labour
Mate day 0.320 617.00 197.44 L-12
Mazdoor day 8.000 511.52 4,092.16 L-13
b) Machinery
Batching Plant of capacity 120 cum/hour hour 1.333 4,104.45 5,472.60 P&M-039
Generator 250 KVA hour 1.333 3,475.00 4,633.33 P&M-046
Loader 3.1 cum capacity hour 1.333 4,279.80 5,706.40 P&M-011
Transit truck agitator
For transportation (6 cum Capacity) tonne.km 300 x L 13.41 120,697.50 P&M-128
For loading & unloading hour 11.333 2,413.95 27,358.10 P&M-067
Shotcrete Machine @ 12 cum/hour hour 10.000 1,830.15 18,301.50 P&M-095
Compressor 500 cfm hour 10.000 2,752.05 27,520.50 P&M-030
c) Materials
Cement Tonne 49.440 4,940.00 244,233.60 M-081
Sand Cum 86.850 1,994.03 173,181.59 M-004
10 mm to 4.76 mm Aggregate Cum 52.080 1,887.12 98,281.37 M-039
Steel Fiber Tonne 6.120 46,496.54 284,558.85 M-225
Admixture @ 0.4 % of Cement Kg 197.760 167.49 33,121.93 M-182
Microsilica @ 6 % of Cement Kg 2966.400 32.00 94,924.80 M-226
Accelerator @ 4.5 % of Cement Kg 2224.800 125.00 278,100.00 M-227

Add 20 per cent of cost of a+b+c for Wastage due to rebound. 284,076.34
d) Overhead charges @ 25% on (a+b+c) 426,114.50
e) Contractor's profit @ 10% on (a+b+c+d) 213,057.25
Cost for 120 Cum = a+b+c+d+e 2,343,629.78
Rate per Cum = (a+b+c+d+e)/120 19,530.25
say 19,530.00

18.08 2807 Shotcreting with welded wiremesh


Shotcreting to upper bench / lower bench with welded wiremesh ,
shotcrete compressive strength shall be 25 N/mm2 and complete
as per Drawing and Technical Specifications.

Unit = cum
Taking output = 120 Cum
a) Labour
Mate day 0.320 617.00 197.44 L-12
Mazdoor day 8.000 511.52 4,092.16 L-13
b) Machinery
Batching Plant of capacity 120 cum/hour hour 1.333 4,104.45 5,472.60 P&M-039
Generator 250 KVA hour 1.333 3,475.00 4,633.33 P&M-046
Loader 3.1 cum capacity hour 1.333 4,279.80 5,706.40 P&M-011
Transit truck agitator
For transportation (6 cum Capacity) tonne.km 300 x L 13.41 120,697.50 P&M-128
For loading & unloading hour 11.333 2,413.95 27,358.10 P&M-067
Shotcrete Machine @ 12 cum/hour hour 10.000 1,830.15 18,301.50 P&M-095
Compressor 500 cfm hour 10.000 2,752.05 27,520.50 P&M-030
c) Materials
Cement Tonne 49.440 4,940.00 244,233.60 M-081
Sand Cum 86.850 1,994.03 173,181.59 M-004
10 mm to 4.76 mm Aggregate Cum 52.080 1,887.12 98,281.37 M-039
Wiremesh (Including 10% for lapping) Sqm 1320.000 40.58 53,565.60 M-228
Admixture @ 0.4 % of Cement Kg 197.760 167.49 33,121.93 M-182
Microsilica @ 6 % of Cement Kg 2966.400 32.00 94,924.80 M-226
Accelerator @ 4.5 % of Cement Kg 2224.800 125.00 278,100.00 M-227

Add 20 per cent of cost of a+b+c for Wastage due to rebound. 237,877.69
d) Overhead charges @ 25% on (a+b+c) 356,816.53
e) Contractor's profit @ 10% on (a+b+c+d) 178,408.26
Cost for 120 Cum = a+b+c+d+e 1,962,490.91
Rate per Cum = (a+b+c+d+e)/120 16,354.09
say 16,354.00

18.09 2806 & Providing and fixing 25 mm diameter 3 meter long steel rock bolts
3200 including drilling 45 mm dia holes, plate, nuts, cement grout, cost
of all materials, machinery, labour, ventilation, lighting, drainage
and all other ancillary operations etc. complete as per Drawing
and Technical Specifications.

Unit = cum
Taking output = 155 Nos.
a) Labour
Mate day 0.480 617.00 296.16 L-12
Mazdoor day 8.000 511.52 4,092.16 L-13
Mason (IInd class) day 4.000 679.00 2,716.00 L-10

b) Machinery
Single boom Hydraulic Drill Jumbo hour 25.833 5,420.10 140,019.25 P&M-090
c) Materials
3.7 m long extension rod Nos 1.011 10,000.00 10,108.70 M-219
R32 shank adapter Nos 1.011 13,000.00 13,141.30 M-222
45 mm dia cross bit Nos 3.577 3,000.00 10,730.77 M-223
25 mm Tor Steel (Including 2.5% Wastage) Tonne 1.927 46,496.54 89,587.52 M-083

Add 15 per cent of cost of a+b+c towards of cutting ,making tip, 40,603.78
Threading,
d) Overheadnut , charges
plate,grouting
@ 25%and bit sharpening etc..
on (a+b+c) 77,823.91
e) Contractor's profit @ 10% on (a+b+c+d) 38,911.96
Cost for 155 Nos = a+b+c+d+e 428,031.51
Rate per Number = (a+b+c+d+e)/155 2,761.49
say 2,761.00

18.10 2806 & Providing and fixing 32 mm diameter 7 meter long steel rock bolts
3200 including drilling 51 mm dia holes, plate, nuts, cement grout, cost
of all materials, machinery, labour, ventilation, lighting, drainage
and all other ancillary operations etc. complete as per Drawing
and Technical Specifications.

Unit = cum
Taking output = 70 Nos.
a) Labour
Mate day 0.600 617.00 370.20 L-12
Mazdoor day 10.000 511.52 5,115.20 L-13
Mason (IInd class) day 5.000 679.00 3,395.00 L-10
b) Machinery
Single Boom Hydraulic hour 17.500 5,420.10 94,851.75 P&M-090

c) Materials
3.7 m long extension rod Nos 1.065 10,000.00 10,652.17 M-219
R32 shank adapter Nos 1.065 13,000.00 13,847.83 M-222
32 mm coupling sleeve Nos 1.065 12,000.00 12,782.61 M-220
51 mm dia button bit Nos 3.769 5,000.00 18,846.15 M-224
32 mm Tor Steel (Including 2.5% Wastage) Tonne 3.237 46,496.54 150,514.38 M-083
Add 15 per cent of cost of a+b+c towards of cutting ,making tip, 46,556.29
Threading, nut , plate, grouting and bit sharpening etc..
d) Overhead charges @ 25% on (a+b+c) 89,232.90
e) Contractor's profit @ 10% on (a+b+c+d) 44,616.45
Cost for 70 Nos = a+b+c+d+e 490,780.93
Rate per Number = (a+b+c+d+e)/70 7,011.16
say 7,011.00

18.11 2806 Grouting with Cement

Grouting cement slurry in grout holes under specified pressure for


consolidation / contact grouting including cost of all materials,
machinery, labour, redrilling wherever necessary,
ventilation,lighting, drainage and other ancillary operations etc.
complete as per Drawing and Technical Specifications.

Unit = cum
Taking output = 1.5 Tonne
a) Labour
Mate day 0.080 617.00 49.36 L-12
Mazdoor day 2.000 511.52 1,023.04 L-13

b) Machinery
Grouting machine @ 25 Bags Per Hours hour 1.200 798.00 957.60 P&M-096
Pump 10 HP hour 1.200 -
Single Boom Hydraulic hour 1.250 5,420.10 6,775.13 P&M-090

c) Materials
Cement Including 1% Wastage) Tonne 1.515 4,940.00 7,484.10 M-081
Cost of water (Water/Cement Ratio - 0.4) KL 0.606 16.00 9.70 M-191
3.7 m long extension rod Nos 0.076 10,000.00 760.87 M-219
R32 shank adapter Nos 0.076 13,000.00 989.13 M-222
32 mm coupling sleeve Nos 0.076 12,000.00 913.04 M-220
51 mm dia cross bit Nos 0.269 5,000.00 1,346.15 M-224
Add 5 per cent of cost of a+b+c towards of cutting ,making tip, 1,015.41
Threading, nut , plate, grouting and bit sharpening etc..
d) Overhead charges @ 25% on (a+b+c) 5,330.88
e) Contractor's profit @ 10% on (a+b+c+d) 2,665.44
Cost for 1.5 Tonne = a+b+c+d+e 29,319.85
Rate per Tonne = (a+b+c+d+e)/1.5 19,546.56
say 19,547.00
18.12 1700 Furnishing and Placing Reinforced cement concrete in Tunnel
18.12A 1700 A Work as per M20
RCC Grade drawing and Technical Specification
Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 4,533.00 543,960.00
Concrete - 20.05
Water for curing Kl 63.000 16.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.232 617.00 143.14 L-12
Mason day 1.500 738.00 1,107.00 L-11
Mazdoor day 4.300 511.52 2,199.54 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in Kilometer tonne-km 300 x L 13.41 120,697.50 P&M-128
For unloading hour 2.600 2,413.95 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 4,401.60 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @ 30 km/hr
and
(i) 1230KLmins for unloading )
capacity hour 20.990 1,501.00 31,505.99 P&M-023
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
d) Formwork and staging 40 per cent of (a+b+c) cum 40.000 287,336.64
e) Overhead charges @ 25% on (a+b+c+d) 251,419.56
f) Contractor's profit @ 10% on (a+b+c+d+e) 125,709.78
Cost for 120 cum = a+b+c+d+e+f 1,382,807.58
Rate per cum = (a+b+c+d+e+f)/120 11,523.40
say 11,523.00
18.12B 1700 B RCC Grade M25
Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 4,945.00 593,400.00
Concrete - 20.07
Water for curing Kl 63.000 16.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.232 617.00 143.14 L-12
Mason day 1.500 738.00 1,107.00 L-11
Mazdoor day 4.300 511.52 2,199.54 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in Kilometer tonne-km 300 x L 13.41 120,697.50 P&M-128
For unloading hour 2.600 2,413.95 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 4,401.60 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @ 30 km/hr
and
(i) 1230KLmins for unloading )
capacity hour 20.990 1,501.00 31,505.99 P&M-023
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 Cum
d) Formwork and staging 40 per cent of (a+b+c) 40.000 307,112.64
e) Overhead charges @ 25% on (a+b+c+d) 268,723.56
f) Contractor's profit @ 10% on (a+b+c+d+e) 134,361.78
Cost for 120 cum = a+b+c+d+e+f 1,477,979.58
Rate per cum = (a+b+c+d+e+f)/120 12,316.50
say 12,316.00
18.12C 1700 C RCC Grade M 30
Using Batching Plant, Transit Mixer and Concrete Pump.
Unit = cum
Taking output = 120 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 5,032.00 603,840.00
Concrete - 20.09
Water for curing Kl 63.000 16.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.232 617.00 143.14 L-12
Mason day 1.500 738.00 1,107.00 L-11
Mazdoor day 4.300 511.52 2,199.54 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in Kilometer tonne-km 300 x L 13.41 120,697.50 P&M-128
For unloading hour 2.600 2,413.95 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 4,401.60 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @ 30 km/hr
and
(i) 1230KLmins for unloading )
capacity hour 20.990 1,501.00 31,505.99 P&M-023
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 Cum
d) Formwork and staging 40 per cent of (a+b+c) 40.000 311,288.64
e) Overhead charges @ 25% on (a+b+c+d) 272,377.56
f) Contractor's profit @ 10% on (a+b+c+d+e) 136,188.78
Cost for 120 cum = a+b+c+d+e+f 1,498,076.58
Rate per cum = (a+b+c+d+e+f)/120 12,483.97
say 12,484.00
18.12D 1700 D RCC Grade M35
Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum 120 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 5,186.00 622,320.00
Concrete - 20.11
Water for curing Kl 63.000 16.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.232 617.00 143.14 L-12
Mason day 1.500 738.00 1,107.00 L-11
Mazdoor day 4.300 511.52 2,199.54 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in Kilometer tonne-km 300 x L 13.41 120,697.50 P&M-128
For unloading hour 2.600 2,413.95 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 4,401.60 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @ 30 km/hr
and
(i) 1230KLmins for unloading )
capacity hour 20.990 1,501.00 31,505.99 P&M-023
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 Cum
d) Formwork and staging 40 per cent of (a+b+c) 40.000 318,680.64
e) Overhead charges @ 25% on (a+b+c+d) 278,845.56
f) Contractor's profit @ 10% on (a+b+c+d+e) 139,422.78
Cost for 120 cum = a+b+c+d+e+f 1,533,650.58
Rate per cum = (a+b+c+d+e+f)/120 12,780.42
say 12,780.00
18.12E 1700 E RCC Grade M-40
Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum 120 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 5,519.00 662,280.00
Concrete - 20.12
Water for curing Kl 63.000 16.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.232 617.00 143.14 L-12
Mason day 1.500 738.00 1,107.00 L-11
Mazdoor day 4.300 511.52 2,199.54 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in Kilometer tonne-km 300 x L 13.41 120,697.50 P&M-128
For unloading hour 2.600 2,413.95 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 4,401.60 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @ 30 km/hr
and
(i) 1230KLmins for unloading )
capacity hour 20.990 1,501.00 31,505.99 P&M-023
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 Cum
d) Formwork and staging 40 per cent of (a+b+c) 40.000 334,664.64
e) Overhead charges @ 25% on (a+b+c+d) 292,831.56
f) Contractor's profit @ 10% on (a+b+c+d+e) 146,415.78
Cost for 15 cum = a+b+c+d+e+f 1,610,573.58
Rate per cum = (a+b+c+d+e+f)/120 13,421.45
say 13,421.00
18.12F 1700 F RCC Grade M-45
Unit = 1 cum
Taking output = 120 cum 120 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 5,663.00 679,560.00
Concrete - 20.13
Water for curing Kl 63.000 16.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.232 617.00 143.14 L-12
Mason day 1.500 738.00 1,107.00 L-11
Mazdoor day 4.300 511.52 2,199.54 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in Kilometer tonne-km 300 x L 13.41 120,697.50 P&M-128
For unloading hour 2.600 2,413.95 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 4,401.60 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @ 30 km/hr
and
(i) 1230KLmins for unloading )
capacity hour 20.990 1,501.00 31,505.99 P&M-023
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 Cum
d) Formwork and staging 40 per cent of (a+b+c) 40.000 341,576.64
e) Overhead charges @ 25% on (a+b+c+d) 298,879.56
f) Contractor's profit @ 10% on (a+b+c+d+e) 149,439.78
Cost for 120 cum = a+b+c+d+e+f 1,643,837.58
Rate per cum = (a+b+c+d+e+f)/120 13,698.65
say 13,699.00
18.12G 1700 G RCC Grade M-50
Unit = 1 cum
Taking output = 120 cum 120 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 6,242.00 749,040.00
Concrete - 20.14
Water for curing Kl 63.000 16.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.232 617.00 143.14 L-12
Mason day 1.500 738.00 1,107.00 L-11
Mazdoor day 4.300 511.52 2,199.54 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in Kilometer tonne-km 300 x L 13.41 120,697.50 P&M-128
For unloading hour 2.600 2,413.95 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 4,401.60 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @ 30 km/hr
and
(i) 1230KLmins for unloading )
capacity hour 20.990 1,501.00 31,505.99 P&M-023
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 Cum
d) Formwork and staging 40 per cent of (a+b+c) 40.000 369,368.64
e) Overhead charges @ 25% on (a+b+c+d) 323,197.56
f) Contractor's profit @ 10% on (a+b+c+d+e) 161,598.78
Cost for 120 cum = a+b+c+d+e+f 1,777,586.58
Rate per cum = (a+b+c+d+e+f)/120 14,813.22
say 14,813.00
18.12H 1700 H RCC Grade M- 55
Unit = 1 cum
Taking output = 120 cum 120 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 6,321.00 758,520.00
Concrete - 20.15
Water for curing Kl 63.000 16.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.232 617.00 143.14 L-12
Mason day 1.500 738.00 1,107.00 L-11
Mazdoor day 4.300 511.52 2,199.54 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in Kilometer tonne-km 300 x L 13.41 120,697.50 P&M-128
For unloading hour 2.600 2,413.95 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 4,401.60 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @ 30 km/hr
and
(i) 1630KLmins for unloading )
capacity hour 20.990 1,501.00 31,505.99 P&M-023
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 Cum
d) Formwork and staging 40 per cent of (a+b+c) 40.000 373,160.64
e) Overhead charges @ 25% on (a+b+c+d) 326,515.56
f) Contractor's profit @ 10% on (a+b+c+d+e) 163,257.78
Cost for 120 cum = a+b+c+d+e+f 1,795,835.58
Rate per cum = (a+b+c+d+e+f)/120 14,965.30
say 14,965.00
18.12 I 1700 I RCC Grade M- 60
Unit = 1 cum
Taking output = 120 cum 120 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost cum 120.000 6,511.00 781,320.00
Concrete - 20.16
(Rate
Water as forincuring
sub-analysis of concrete) Kl 63.000 16.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.232 617.00 143.14 L-12
Mason day 1.500 738.00 1,107.00 L-11
Mazdoor day 4.300 511.52 2,199.54 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in Kilometer tonne-km 300 x L 13.41 120,697.50 P&M-128
For unloading hour 2.600 2,413.95 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 4,401.60 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @ 30 km/hr
and
(i) 1230KLmins for unloading )
capacity hour 20.990 1,327.00 27,853.73 P&M-024
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 Cum
d) Formwork and staging 40 per cent of (a+b+c) 40.000 380,819.74
e) Overhead charges @ 25% on (a+b+c+d) 333,217.27
f) Contractor's profit @ 10% on (a+b+c+d+e) 166,608.63
Cost for 120 cum = a+b+c+d+e+f 1,832,694.98
Rate per cum = (a+b+c+d+e+f)/120 15,272.46
18.12J 1700 J RCC Grade M- 65 15,272.00
Unit = 1 cum
Taking output = 120 cum 120 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 6,552.00 786,240.00
Concrete - 20.17
Water for curing Kl 63.000 16.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.232 617.00 143.14 L-12
Mason day 1.500 738.00 1,107.00 L-11
Mazdoor day 4.300 511.52 2,199.54 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in Kilometer tonne-km 300 x L 13.41 120,697.50 P&M-128
For unloading hour 2.600 2,413.95 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 4,401.60 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @ 30 km/hr
and
(i) 1230KLmins for unloading )
capacity hour 20.990 1,327.00 27,853.73 P&M-024
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 Cum
d) Formwork and staging 40 per cent of (a+b+c) 40.000 382,787.74
e) Overhead charges @ 25% on (a+b+c+d) 334,939.27
f) Contractor's profit @ 10% on (a+b+c+d+e) 167,469.63
Cost for 120 cum = a+b+c+d+e+f 1,842,165.98
Rate per cum = (a+b+c+d+e+f)/120 15,351.38
say 15,351.00
18.13 1600 Supplying, fitting and placing HYSD bar reinforcement in Tunnel
Work
Unit =complete
MT as per drawing and technical specifications
Taking output = 8 MT
a) Material
MS bars including 5 per cent overlaps and wastage tonne 8.400 46,496.54 390,570.97 M-083
Binding wire Kg 48.000 66.72 3,202.56 M-072
b) Labour for straightening, cutting, bending, shifting to site,
tying
Mate and placing in position day 0.160 617.00 98.72 L-12
Blacksmith day 1.000 738.00 738.00 L-02
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Cutting Machine hour 8.000 528.15 4,225.20 P&M-076
Bending Machine hour 8.000 528.15 4,225.20 P&M-076
Electric generator 15 KVA hour 8.000 425.25 3,402.00 P&M-051
Tipper
Tipper for Transportation
(i) 14 cum capacity t.km 8xL 8.52 2,045.40 P&M-120
Loading & Unloading Time hour
(i) 14 cum capacity hour 2.000 2,556.75 5,113.50 P&M-015
Light weight Crane
At cutting bending yard hour 2.000 1,083.60 2,167.20 P&M-102
At site hour 2.000 1,083.60 2,167.20 P&M-102
Basic Cost of Labour, Material & Machinery (a+b) for 8 MT

c) Overhead charges @ 25% on (a+b) 104,872.63


d) Contractor's profit @ 10% on (a+b+c) 52,436.31
Cost for 8 MT (a+b+c+d) 576,799.46
Rate for per MT (a+b+c+d)/8 72,099.93
say 72,100.00
CHAPTER-18
Environmental & Safety Management And Bio Engineering
Reference Amount
Quantity
to (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit
For Large For Medium For Small (Rs.) Medium Small Input ref.
Specificatio Large Project
n Project Project Project Project Project

19.01 Suggestive Noise Barrier


(i) Masonry wall
Unit = cum
Taking output = 5 Cum
a) Material
Bricks Ist Class each 2500.00 2500.00 2500.00 3.50 8,750.00 8,750.00 8,750.00 M-079
Sub-Analysis
Cement mortar 1:3 (Rate as sub-analysis) cum 1.200 1.200 1.200 5,125.00 6,150.00 6,150.00 6,150.00 of Concrete -
20.01 (A)
Water for curing KL 2.415 2.415 2.415 16.00 38.64 38.64 38.64 M-191
b) Labour
Mate day 0.480 0.480 0.480 617.00 296.16 296.16 296.16 L-12
Mason day 4.000 4.000 4.000 679.00 2,716.00 2,716.00 2,716.00 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Water tanker (speed @ 10 km/hr. and return speed @ 15
km/hr. and 30 mins for unloading )
(i) 16 KL capacity hour 1.121 1,501.00 1,682.62 P&M-023
(ii) 12 KL capacity hour 1.484 1,327.00 1,969.27 P&M-024
(iii) 6 KL capacity hour 2.938 1,005.00 2,952.69 P&M-025
@ 8% on @ 10% on @ 12% on
d) Overhead charges 1,898.05 2,401.22 2,999.48
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 2,562.36 2,641.35 2,799.51
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 5 Cum = a+b+c+d+e 28,185.99 29,054.80 30,794.64
Rate per Cum = (a+b+c+d+e) /5 5,637.20 5,810.96 6,158.93
Say 5,637.00 5,811.00 6,159.00
(ii) Galvanized steel plain sheet
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Blacksmith day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-02
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Material
Galvanized steel plain sheet (5 mm) including 5% wastage Kg 3.150 3.150 3.150 63.00 198.45 198.45 198.45 M-103
MS Angle Kg 154.500 154.500 154.500 63.81 9,858.11 9,858.11 9,858.11 M-181
Add 10 Percent of cost of a+b towards of drilling , nut &
1,097.41 1,097.41 1,097.41
bolt etc.
@ 8% on @ 10% on @ 12% on
c) Overhead charges 965.72 1,207.15 1,448.58
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 1,303.72 1,327.87 1,352.01
(a+b+c) (a+b+c) (a+b+c)
Cost for 100 sqm = a+b+c+d 14,340.96 14,606.53 14,872.10
Rate per Sqm= (a+b+c+d) /100 143.41 146.07 148.72
Say 143.00 146.00 149.00
(ii) Acrylic noise barrier sheet
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Blacksmith day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-02
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Material
Acrylic noise barrier sheet (3 mm) including 5% wastage sqm 105.000 105.000 105.000 90.00 9,450.00 9,450.00 9,450.00 M294
MS Angle Kg 154.500 154.500 154.500 63.81 9,858.11 9,858.11 9,858.11 M-181
Add 10 Percent of cost of a+b towards of drilling , nut &
2,022.57 2,022.57 2,022.57
bolt etc.
@ 8% on @ 10% on @ 12% on
c) Overhead charges 1,779.86 2,224.82 2,669.79
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 2,402.81 2,447.30 2,491.80
(a+b+c) (a+b+c) (a+b+c)
Cost for 100 sqm = a+b+c+d 26,430.88 26,920.34 27,409.80
Rate per Sqm= (a+b+c+d) /100 264.31 269.20 274.10
Say 264.00 269.00 274.00

Construction of bamboo crib wall complete as per drawing


19.02
and additional Technical specification.

Unit = Rm
Taking output = 1Rm
a) Labour
Mate day 0.016 0.016 0.016 617.00 9.87 9.87 9.87 L-12
Mazdoor skilled day 0.100 0.100 0.100 565.73 56.57 56.57 56.57 L-15
Mazdoor day 0.300 0.300 0.300 511.52 153.46 153.46 153.46 L-13
b) Machinery
Water tanker 6 KL capacity hour 0.008 0.008 0.008 1,005.00 8.38 8.38 8.38 P&M-025
c) Materials
Bamboos ( For Horizontal Beam) Rm 4.000 4.000 4.000 17.75 71.00 71.00 71.00 M-229
Live Stake Stump / Bamboos (Vertical) Rm 1.500 1.500 1.500 1.00 1.50 1.50 1.50 M-230
Live Stake Stump / Bamboos (Horizontal) Rm 1.000 1.000 1.000 1.00 1.00 1.00 1.00 M-230
Binding Material Rm 2.000 2.000 2.000 1.00 2.00 2.00 2.00 M-235
Cost of Water KL 0.050 0.050 0.050 16.00 0.80 0.80 0.80 M-191
Grass Kg 1.500 1.500 1.500 34.75 52.13 52.13 52.13 M-112
@ 8% on @ 10% on @ 12% on
d) Overhead charges 28.54 35.67 42.80
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 38.52 39.24 39.95
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 1 RM = a+b+c+d+e 423.76 431.61 439.46
Rate per cum = (a+b+c+d+e) 423.76 431.61 439.46
Say 424.00 432.00 439.00

Construction of Fascines with a bundle of sticks complete


19.03
as per drawing and additional Technical specification.

Unit = Rm
Taking output = 10 Rm
a) Labour
Mate day 0.100 0.100 0.100 617.00 61.70 61.70 61.70 L-12
Mazdoor skilled day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Tractor-trolley hour 1.000 1.000 1.000 1,876.50 1,876.50 1,876.50 1,876.50 P&M-026
c) Material
Hard wood sticks Nr 8.000 8.000 8.000 100.00 800.00 800.00 800.00 M-231
Binding Material Rm 5.000 5.000 5.000 1.00 5.00 5.00 5.00 M-235
@ 8% on @ 10% on @ 12% on
d) Overhead charges 323.93 404.91 485.89
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 437.30 445.40 453.50
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 1 M = a+b+c+d+e 4,810.34 4,899.42 4,988.50
Rate per Rm = (a+b+c+d+e)/10 481.03 489.94 498.85
Say 481.00 490.00 499.00
Construction and laying of brush Layers across the slope
19.04 complete as per drawing and additional Technical
specification.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor for preparation of ground day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Machinery
Water tanker including watering for 3 months hour 2.000 2.000 2.000 1,005.00 2,010.00 2,010.00 2,010.00 P&M-025
Tractor-trolley hour 0.500 0.500 0.500 1,876.50 938.25 938.25 938.25 P&M-026
c) Material
Live Sods (.6m Length) Nr 1000.000 1000.000 1000.000 1.00 1,000.00 1,000.00 1,000.00 M-232
Farm yard manure @ 0.18 cum per 100 sqm at site of
cum 0.180 0.180 0.180 300.00 54.00 54.00 54.00 M-168
work
Cost of water KL 12.000 12.000 12.000 16.00 192.00 192.00 192.00 M-191
Grass Kg 100.000 100.000 100.000 34.75 3,475.00 3,475.00 3,475.00 M-112
@ 8% on @ 10% on @ 12% on
d) Overhead charges 742.23 927.79 1,113.34
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 1,002.01 1,020.56 1,039.12
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 11,022.09 11,226.20 11,430.31
Rate per sqm = (a+b+c+d+e)/100 110.22 112.26 114.30
Say 110.00 112.00 114.00
Construction of vegetative Palisades in Rills using hard
19.05 wood cutting complete as per drawing and additional
Technical specification.
Unit = Rm
Taking output = 2 Rm
a) Labour
Mate day 0.012 0.012 0.012 617.00 7.40 7.40 7.40 L-12
Mazdoor skilled day 0.100 0.100 0.100 565.73 56.57 56.57 56.57 L-15
Mazdoor day 0.200 0.200 0.200 511.52 102.30 102.30 102.30 L-13
b) Machinery
Tractor-trolley hour 0.250 0.250 0.250 1,876.50 469.13 469.13 469.13 P&M-026
c) Material
Horizontal Live Sods (2M Length) Nr 2.000 2.000 2.000 1.00 2.00 2.00 2.00 M-233
Vertical Live Sods (2 M Length) Nr 40.000 40.000 40.000 1.00 40.00 40.00 40.00 M-233
Cost of water KL 0.100 0.100 0.100 16.00 1.60 1.60 1.60 M-191
Binding Material Rm 5.000 5.000 5.000 1.00 5.00 5.00 5.00 M-235
@ 8% on @ 10% on @ 12% on
d) Overhead charges 54.72 68.40 82.08
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 73.87 75.24 76.61
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 2 M = a+b+c+d+e 812.60 827.65 842.70
Rate per Rm = (a+b+c+d+e)/2 406.30 413.82 421.35
Say 406.00 414.00 421.00
Laying of Palisades in Slopes complete as per drawing
19.06
and additional Technical specification.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor for preparation of ground day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Machinery
Water tanker including watering for 3 months hour 2.000 2.000 2.000 1,005.00 2,010.00 2,010.00 2,010.00 P&M-025
Tractor-trolley hour 0.500 0.500 0.500 1,876.50 938.25 938.25 938.25 P&M-026
c) Material
Live Sods (.6m Length) Nr 1000.000 1000.000 1000.000 1.00 1,000.00 1,000.00 1,000.00 M-232
Farm yard manure @ 0.18 cum per 100 sqm at site of
cum 0.180 0.180 0.180 300.00 54.00 54.00 54.00 M-168
work
Cost of water KL 12.000 12.000 12.000 16.00 192.00 192.00 192.00 M-191
Grass Kg 100.000 100.000 100.000 34.75 3,475.00 3,475.00 3,475.00 M-112
@ 8% on @ 10% on @ 12% on
d) Overhead charges 742.23 927.79 1,113.34
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 1,002.01 1,020.56 1,039.12
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 11,022.09 11,226.20 11,430.31
Rate per sqm = (a+b+c+d+e)/100 110.22 112.26 114.30
Say 110.00 112.00 114.00

Dust suppression Sprinkling of water in the sellement and


19.07
working area as per instruction of Engineer.

Unit = KL
Taking output = 6KL
a) Labour
Mate day 0.008 0.008 0.008 617.00 4.94 4.94 4.94 L-12
Mazdoor day 0.200 0.200 0.200 511.52 102.30 102.30 102.30 L-13
b) Machinery
Water tanker 6 KL capacity hour 0.750 0.750 0.750 1,005.00 753.75 753.75 753.75 P&M-025
c) Materials
Cost of Water KL 6.000 6.000 6.000 16.00 96.00 96.00 96.00 M-191
@ 8% on @ 10% on @ 12% on
d) Overhead charges 76.56 95.70 114.84
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 103.35 105.27 107.18
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 6 KL = a+b+c+d+e 1,136.90 1,157.96 1,179.01
Cost per KL = (a+b+c+d+e) 189.48 192.99 196.50
Say 189.00 193.00 197.00

Water Quality Monitoring


19.08 New (Grab Sample as per the monitoring locations mention in
the EIA/EMP report or one sample/10 km length.)

Unit = Number
Taking output = One Number
a) Cost of Water Quality Monitoring Nos. 1.000 1.000 1.000 2,700.00 2,700.00 2,700.00 2,700.00
@ 10% on @ 12% on
b) Overhead charges @ 8% on (a) 216.00 270.00 324.00
(a) (a)
@ 10% on @ 10% on @ 10% on
c) Contractor's profit 291.60 297.00 302.40
(a+b) (a+b) (a+b)
Rate per Number = a+b+c 3,207.60 3,267.00 3,326.40
Say 3,208.00 3,267.00 3,326.00

Soil Quality Monitoring (Grab Sample as per the


19.09 New monitoring locations mention in the EIA/EMP report or one
sample/10 km length.

Unit = Number
Taking output = One Number
a) Cost of Soil Quality Monitoring Nos. 1.000 1.000 1.000 6,000.00 6,000.00 6,000.00 6,000.00
@ 10% on @ 12% on
b) Overhead charges @ 8% on (a) 480.00 600.00 720.00
(a) (a)
@ 10% on @ 10% on @ 10% on
c) Contractor's profit 648.00 660.00 672.00
(a+b) (a+b) (a+b)
Rate per Number = a+b+c 7,128.00 7,260.00 7,392.00
Say 7,128.00 7,260.00 7,392.00

Ambient Air Quality Monitoring 24 hrs continuous for


19.10 New location as mention in the EIA/EMP report or one
monitoring location within 10 km radius.

Unit = Number
Taking output = One Number
Cost of Ambient Air Quality Nos. 1.000 1.000 1.000 2,500.00 2,500.00 2,500.00 2,500.00
@ 10% on @ 12% on
b) Overhead charges @ 8% on (a) 200.00 250.00 300.00
(a) (a)
@ 10% on @ 10% on @ 10% on
c) Contractor's profit 270.00 275.00 280.00
(a+b) (a+b) (a+b)
Rate per Number = a+b+c 2,970.00 3,025.00 3,080.00
Say 2,970.00 3,025.00 3,080.00

Ambient Noise Monitoring 24 hour continuous (To be


19.11 New carried out as per the location mention in the EIA/EMP
report.
Unit = Number
Taking output = One Number
Cost of Ambient Noise Monitoring 24 hour continuous Nos. 1.000 1.000 1.000 2,000.00 2,000.00 2,000.00 2,000.00

@ 10% on @ 12% on
b) Overhead charges @ 8% on (a) 160.00 200.00 240.00
(a) (a)
@ 10% on @ 10% on @ 10% on
c) Contractor's profit 216.00 220.00 224.00
(a+b) (a+b) (a+b)
Rate per Number = a+b+c 2,376.00 2,420.00 2,464.00
Say 2,376.00 2,420.00 2,464.00

19.12 New Consent Approvals (Once)


Unit = Number
Taking output = One Number
(i) Consent to Establish (CTE) Nos. 1.000 1.000 1.000 100,000.00 100,000.00 100,000.00 100,000.00
@ 10% on @ 12% on
b) Overhead charges @ 8% on (a) 8,000.00 10,000.00 12,000.00
(a) (a)
@ 10% on @ 10% on @ 10% on
c) Contractor's profit 10,800.00 11,000.00 11,200.00
(a+b) (a+b) (a+b)
Rate per Number = a+b+c 118,800.00 121,000.00 123,200.00
Say 118,800.00 121,000.00 123,200.00

Unit = Number
Taking output = One Number
(ii) Consent to Operate (CTO) Nos. 1.000 1.000 1.000 100,000.00 100,000.00 100,000.00 100,000.00
@ 10% on @ 12% on
b) Overhead charges @ 8% on (a) 8,000.00 10,000.00 12,000.00
(a) (a)
@ 10% on @ 10% on @ 10% on
c) Contractor's profit 10,800.00 11,000.00 11,200.00
(a+b) (a+b) (a+b)
Rate per Number = a+b+c 118,800.00 121,000.00 123,200.00
Say 118,800.00 121,000.00 123,200.00

Compliance submission for Consent Approvals (Half


19.13 New
Yearly).
Unit = Number
Taking output = One Number
(i) compliance submission for Consent to Establish (CTE) Nos. 1.000 1.000 1.000 12,000.00 12,000.00 12,000.00 12,000.00

@ 10% on @ 12% on
b) Overhead charges @ 8% on (a) 960.00 1,200.00 1,440.00
(a) (a)
@ 10% on @ 10% on @ 10% on
c) Contractor's profit 1,296.00 1,320.00 1,344.00
(a+b) (a+b) (a+b)
Rate per Number = a+b+c 14,256.00 14,520.00 14,784.00
Say 14,256.00 14,520.00 14,784.00

Unit = Number
Taking output = One Number
(ii) compliance submission for Consent to Operate (CTO) Nos. 1.000 1.000 1.000 12,000.00 12,000.00 12,000.00 12,000.00

@ 10% on @ 12% on
b) Overhead charges @ 8% on (a) 960.00 1,200.00 1,440.00
(a) (a)
@ 10% on @ 10% on @ 10% on
c) Contractor's profit 1,296.00 1,320.00 1,344.00
(a+b) (a+b) (a+b)
Rate per Number = a+b+c 14,256.00 14,520.00 14,784.00
Say 14,256.00 14,520.00 14,784.00

19.14 New Environmental Clearance Compliance (Half Yearly)


Unit = Number
Taking output = One Number
Cost of Workshop Nos. 1.000 1.000 1.000 25,000.00 25,000.00 25,000.00 25,000.00
@ 10% on @ 12% on
b) Overhead charges @ 8% on (a) 2,000.00 2,500.00 3,000.00
(a) (a)
@ 10% on @ 10% on @ 10% on
c) Contractor's profit 2,700.00 2,750.00 2,800.00
(a+b) (a+b) (a+b)
Rate per Number = a+b+c 29,700.00 30,250.00 30,800.00
Say 29,700.00 30,250.00 30,800.00

19.15 New Environmental Workshops (Half Yearly)

Unit = Number
Taking output = One Number
Cost of Workshop Nos. 1.000 1.000 1.000 25,000.00 25,000.00 25,000.00 25,000.00
@ 10% on @ 12% on
b) Overhead charges @ 8% on (a) 2,000.00 2,500.00 3,000.00
(a) (a)
@ 10% on @ 10% on @ 10% on
c) Contractor's profit 2,700.00 2,750.00 2,800.00
(a+b) (a+b) (a+b)
Rate per Number = a+b+c 29,700.00 30,250.00 30,800.00
Say 29,700.00 30,250.00 30,800.00
19.16 Pollution prevention
Silt fencing on eirther side of the streams and rivers
including erection and maintenance for entire construction
phase.
Unit = Rm
Taking output = 100 Rm
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Tractor-trolley for transportation hour 2.000 2.000 2.000 1,876.50 3,753.00 3,753.00 3,753.00 P&M-026
c) Material
Silt Fence Sheet Sqm 100.000 100.000 100.000 250.00 25,000.00 25,000.00 25,000.00 P&M-026
Hard wood sticks Nos. 34.000 34.000 34.000 100.00 3,400.00 3,400.00 3,400.00 P&M-026
@ 8% on @ 10% on @ 12% on
d) Overhead charges @ on (a+b+c) 2,658.03 3,322.54 3,987.05
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit @ on (a+b+c+d) 3,588.34 3,654.79 3,721.24
(a+b+c) (a+b+c) (a+b+c)
Cost for 100 Rm = a+b+c+d+e 39,471.78 40,202.73 40,933.69
Rate per Rm = (a+b+c+d+e)/100 394.72 402.03 409.34
Say 395.00 402.00 409.00
Road Safety Audit during Construction Period &
19.17 IRC-SP-88
Maintenance Period

Road Safety Audit during Construction Period &


Maintenance Period including collection of Road accident
data and analysis of fatal and grievously injured accident
with black spot identification report, submission of GAP
report, Road Safety Audit Reports on all activities which
were planned, actually executed and planned for the next
quarter report, Submission of audit report of work zone
safety, workshop report and Final Safety report complete
as per IRC-SP-88 and directed by engineer.

Unit = Km
19.17 A Upto 50.00 Kilometer
a) Experts/Key Personnel
Sr. Road Safety/Auditor/ Team leader Month 4.000 4.000 4.000 100,000.00 400,000.00 400,000.00 400,000.00 M312
Traffic Planner Month 6.000 6.000 6.000 75,000.00 450,000.00 450,000.00 450,000.00 M313
b) Boarding & Loading
Boarding & Loading and Per Diem for Site Visits. days 90.000 90.000 90.000 3,500.00 315,000.00 315,000.00 315,000.00 M314
No. of
Transportation at site and Head Office 20.000 20.000 20.000 1,200.00 24,000.00 24,000.00 24,000.00 M315
trip
Duty travel to Site days 90.000 90.000 90.000 2,000.00 180,000.00 180,000.00 180,000.00 M316
c) Reports and Documents Cost

Collection of Road accident data and analysis of fatal and No.of


5.000 5.000 5.000 5,000.00 25,000.00 25,000.00 25,000.00 M317
grievously injured accident with black spot identification Copies

No.of
Submission of GAP report 5.000 5.000 5.000 7,000.00 35,000.00 35,000.00 35,000.00 M318
Copies

Road Safety Audit Reports on all activities which were


No.of
planned, actually executed and planned for the next 5.000 5.000 5.000 7,000.00 35,000.00 35,000.00 35,000.00 M319
Copies
quarter.

No.of
Submission of audit report of work zone safety 5.000 5.000 5.000 15,000.00 75,000.00 75,000.00 75,000.00 M320
Copies
No.of
workshop report. 5.000 5.000 5.000 4,500.00 22,500.00 22,500.00 22,500.00 M321
Copies

No.of
Final Safety report 5.000 5.000 5.000 25,000.00 125,000.00 125,000.00 125,000.00 M322
Copies

Add 10 percent of cost of a+b+c as Miscellaneous work 168,650.00 168,650.00 168,650.00

@ 8% on @ 10% on @ 12% on
d) Overhead charges @ on (a+b+c) 148,412.00 185,515.00 222,618.00
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit @ on (a+b+c+d) 200,356.20 204,066.50 207,776.80
(a+b+c) (a+b+c) (a+b+c)
Rate for Upto 50.00 Kilometer = a+b+c+d+e 2,203,918.20 2,244,731.50 2,285,544.80
Say 2,203,918.00 2,244,732.00 2,285,545.00
19.17 B Between 50.00 Km. to 100.00 Km.
a) Experts/Key Personnel
Sr. Road Safety/Auditor/ Team leader Month 6.000 6.000 6.000 100,000.00 600,000.00 600,000.00 600,000.00 M312
Traffic Planner Month 8.000 8.000 8.000 75,000.00 600,000.00 600,000.00 600,000.00 M313
b) Boarding & Loading
Boarding & Loading and Per Diem for Site Visits. days 126.000 126.000 126.000 3,500.00 441,000.00 441,000.00 441,000.00 M314
No. of
Transportation at site and Head Office 20.000 20.000 20.000 1,200.00 24,000.00 24,000.00 24,000.00 M315
trip
Duty travel to Site days 126.000 126.000 126.000 2,000.00 252,000.00 252,000.00 252,000.00 M316
c) Reports and Documents Cost

Collection of Road accident data and analysis of fatal and No.of


5.000 5.000 5.000 5,000.00 25,000.00 25,000.00 25,000.00 M317
grievously injured accident with black spot identification Copies

No.of
Submission of GAP report 5.000 5.000 5.000 7,000.00 35,000.00 35,000.00 35,000.00 M318
Copies

Road Safety Audit Reports on all activities which were


No.of
planned, actually executed and planned for the next 5.000 5.000 5.000 7,000.00 35,000.00 35,000.00 35,000.00 M319
Copies
quarter.

No.of
Submission of audit report of work zone safety 5.000 5.000 5.000 15,000.00 75,000.00 75,000.00 75,000.00 M320
Copies

No.of
workshop report. 5.000 5.000 5.000 4,500.00 22,500.00 22,500.00 22,500.00 M321
Copies

No.of
Final Safety report 5.000 5.000 5.000 25,000.00 125,000.00 125,000.00 125,000.00 M322
Copies

Add 10 percent of cost of a+b+c as Miscellaneous work 223,450.00 223,450.00 223,450.00

@ 8% on @ 10% on @ 12% on
d) Overhead charges @ on (a+b+c) 196,636.00 245,795.00 294,954.00
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit @ on (a+b+c+d) 265,458.60 270,374.50 275,290.40
(a+b+c) (a+b+c) (a+b+c)
Rate for 50.00 to 100.00 Kilometer = a+b+c+d+e 2,920,044.60 2,974,119.50 3,028,194.40
Say 2,920,045.00 2,974,120.00 3,028,194.00
19.17 C More than 100 Km.
a) Experts/Key Personnel
Sr. Road Safety/Auditor/ Team leader Month 8.000 8.000 8.000 100,000.00 800,000.00 800,000.00 800,000.00 M312
Traffic Planner Month 10.000 10.000 10.000 75,000.00 750,000.00 750,000.00 750,000.00 M313
b) Boarding & Loading
Boarding & Loading and Per Diem for Site Visits. days 162.000 162.000 162.000 3,500.00 567,000.00 567,000.00 567,000.00 M314
No. of
Transportation at site and Head Office 20.000 20.000 20.000 1,200.00 24,000.00 24,000.00 24,000.00 M315
trip
Duty travel to Site days 162.000 162.000 162.000 2,000.00 324,000.00 324,000.00 324,000.00 M316
c) Reports and Documents Cost

Collection of Road accident data and analysis of fatal and No.of


5.000 5.000 5.000 5,000.00 25,000.00 25,000.00 25,000.00 M317
grievously injured accident with black spot identification Copies

No.of
Submission of GAP report 5.000 5.000 5.000 7,000.00 35,000.00 35,000.00 35,000.00 M318
Copies

Road Safety Audit Reports on all activities which were


No.of
planned, actually executed and planned for the next 5.000 5.000 5.000 7,000.00 35,000.00 35,000.00 35,000.00 M319
Copies
quarter.

No.of
Submission of audit report of work zone safety 5.000 5.000 5.000 15,000.00 75,000.00 75,000.00 75,000.00 M320
Copies

No.of
workshop report. 5.000 5.000 5.000 4,500.00 22,500.00 22,500.00 22,500.00 M321
Copies

No.of
Final Safety report 5.000 5.000 5.000 25,000.00 125,000.00 125,000.00 125,000.00 M322
Copies
Add 10 percent of cost of a+b+c as Miscellaneous work 278,250.00 278,250.00 278,250.00

@ 8% on @ 10% on @ 12% on
d) Overhead charges @ on (a+b+c) 244,860.00 306,075.00 367,290.00
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit @ on (a+b+c+d) 330,561.00 336,682.50 342,804.00
(a+b+c) (a+b+c) (a+b+c)
Rate for More than 100.00 Kilometer = a+b+c+d+e 3,636,171.00 3,703,507.50 3,770,844.00
Say 3,636,171.00 3,703,508.00 3,770,844.00
19.18 IRC-SP-88 Road Safety Audit during Maintenance Period

Road Safety Audit during Maintenance Period including


collection of Road accident data and analysis of fatal and
grievously injured accident with black spot identification
report, submission of GAP report, Road Safety Audit
Reports on all activities which were planned, actually
executed and planned for the next quarter report,
submission of audit report of work zone safety
(Maintenance work), workshop report and Final Safety
report complete as per IRC-SP-88 and directed by
engineer.

Unit = Km
19.18 A Upto 50.00 Kilometer
a) Experts/Key Personnel
Sr. Road Safety/Auditor/ Team leader Month 2.000 2.000 2.000 100,000.00 200,000.00 200,000.00 200,000.00 M312
Traffic Planner Month 3.000 3.000 3.000 75,000.00 225,000.00 225,000.00 225,000.00 M313
b) Boarding & Loading
Boarding & Loading and Per Diem for Site Visits. days 45.000 45.000 45.000 3,500.00 157,500.00 157,500.00 157,500.00 M314
No. of
Transportation at site and Head Office 20.000 20.000 20.000 1,200.00 24,000.00 24,000.00 24,000.00 M315
trip
Duty travel to Site days 45.000 45.000 45.000 2,000.00 90,000.00 90,000.00 90,000.00 M316
c) Reports and Documents Cost

Collection of Road accident data and analysis of fatal and No.of


5.000 5.000 5.000 5,000.00 25,000.00 25,000.00 25,000.00 M317
grievously injured accident with black spot identification Copies

No.of
Submission of GAP report 5.000 5.000 5.000 7,000.00 35,000.00 35,000.00 35,000.00 M318
Copies

Road Safety Audit Reports on all activities which were


No.of
planned, actually executed and planned for the next 5.000 5.000 5.000 7,000.00 35,000.00 35,000.00 35,000.00 M319
Copies
quarter.

Submission of audit report of work zone safety No.of


5.000 5.000 5.000 15,000.00 75,000.00 75,000.00 75,000.00 M320
(Maintenance Work) Copies

No.of
workshop report. 5.000 5.000 5.000 4,500.00 22,500.00 22,500.00 22,500.00 M321
Copies

No.of
Final Safety report 5.000 5.000 5.000 25,000.00 125,000.00 125,000.00 125,000.00 M322
Copies

Add 10 percent of cost of a+b+c as Miscellaneous work 101,400.00 101,400.00 101,400.00

@ 8% on @ 10% on @ 12% on
d) Overhead charges @ on (a+b+c) 89,232.00 111,540.00 133,848.00
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit @ on (a+b+c+d) 120,463.20 122,694.00 124,924.80
(a+b+c) (a+b+c) (a+b+c)
Rate for Upto 50.00 Kilometer = a+b+c+d+e 1,325,095.20 1,349,634.00 1,374,172.80
Say 1,325,095.00 1,349,634.00 1,374,173.00
19.18 B Between 50.00 Km. to 100.00 Km.
a) Experts/Key Personnel
Sr. Road Safety/Auditor/ Team leader Month 3.000 3.000 3.000 100,000.00 300,000.00 300,000.00 300,000.00 M312
Traffic Planner Month 4.000 4.000 4.000 75,000.00 300,000.00 300,000.00 300,000.00 M313
b) Boarding & Loading
Boarding & Loading and Per Diem for Site Visits. days 45.000 45.000 45.000 3,500.00 157,500.00 157,500.00 157,500.00 M314
No. of
Transportation at site and Head Office 20.000 20.000 20.000 1,200.00 24,000.00 24,000.00 24,000.00 M315
trip
Duty travel to Site days 45.000 45.000 45.000 2,000.00 90,000.00 90,000.00 90,000.00 M316
c) Reports and Documents Cost

Collection of Road accident data and analysis of fatal and No.of


5.000 5.000 5.000 5,000.00 25,000.00 25,000.00 25,000.00 M317
grievously injured accident with black spot identification Copies

No.of
Submission of GAP report 5.000 5.000 5.000 7,000.00 35,000.00 35,000.00 35,000.00 M318
Copies

Road Safety Audit Reports on all activities which were


No.of
planned, actually executed and planned for the next 5.000 5.000 5.000 7,000.00 35,000.00 35,000.00 35,000.00 M319
Copies
quarter.

Submission of audit report of work zone safety No.of


5.000 5.000 5.000 15,000.00 75,000.00 75,000.00 75,000.00 M320
(Maintenance Work) Copies
No.of
workshop report. 5.000 5.000 5.000 4,500.00 22,500.00 22,500.00 22,500.00 M321
Copies

No.of
Final Safety report 5.000 5.000 5.000 25,000.00 125,000.00 125,000.00 125,000.00 M322
Copies

Add 10 percent of cost of a+b+c as Miscellaneous work 118,900.00 118,900.00 118,900.00

@ 8% on @ 10% on @ 12% on
d) Overhead charges @ on (a+b+c) 104,632.00 130,790.00 156,948.00
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit @ on (a+b+c+d) 141,253.20 143,869.00 146,484.80
(a+b+c) (a+b+c) (a+b+c)
Rate for 50.00 to 100.00 Kilometer = a+b+c+d+e 1,553,785.20 1,582,559.00 1,611,332.80
Say 1,553,785.00 1,582,559.00 1,611,333.00
19.18 C More than 100 Km.
a) Experts/Key Personnel
Sr. Road Safety/Auditor/ Team leader Month 4.000 4.000 4.000 100,000.00 400,000.00 400,000.00 400,000.00 M312
Traffic Planner Month 5.000 5.000 5.000 75,000.00 375,000.00 375,000.00 375,000.00 M313
b) Boarding & Loading
Boarding & Loading and Per Diem for Site Visits. days 45.000 45.000 45.000 3,500.00 157,500.00 157,500.00 157,500.00 M314
No. of
Transportation at site and Head Office 20.000 20.000 20.000 1,200.00 24,000.00 24,000.00 24,000.00 M315
trip
Duty travel to Site days 45.000 45.000 45.000 2,000.00 90,000.00 90,000.00 90,000.00 M316
c) Reports and Documents Cost

Collection of Road accident data and analysis of fatal and No.of


5.000 5.000 5.000 5,000.00 25,000.00 25,000.00 25,000.00 M317
grievously injured accident with black spot identification Copies

No.of
Submission of GAP report 5.000 5.000 5.000 7,000.00 35,000.00 35,000.00 35,000.00 M318
Copies

Road Safety Audit Reports on all activities which were


No.of
planned, actually executed and planned for the next 5.000 5.000 5.000 7,000.00 35,000.00 35,000.00 35,000.00 M319
Copies
quarter.

Submission of audit report of work zone safety No.of


5.000 5.000 5.000 15,000.00 75,000.00 75,000.00 75,000.00 M320
(Maintenance Work) Copies

No.of
workshop report. 5.000 5.000 5.000 4,500.00 22,500.00 22,500.00 22,500.00 M321
Copies

No.of
Final Safety report 5.000 5.000 5.000 25,000.00 125,000.00 125,000.00 125,000.00 M322
Copies

Add 10 percent of cost of a+b+c as Miscellaneous work 136,400.00 136,400.00 136,400.00

@ 8% on @ 10% on @ 12% on
d) Overhead charges @ on (a+b+c) 120,032.00 150,040.00 180,048.00
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit @ on (a+b+c+d) 162,043.20 165,044.00 168,044.80
(a+b+c) (a+b+c) (a+b+c)
Rate for More than 100.00 Kilometer = a+b+c+d+e 1,782,475.20 1,815,484.00 1,848,492.80
Say 1,782,475.00 1,815,484.00 1,848,493.00
SUB-ANALYSIS OF CONCRETE / MORTAR RATE
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
20.01 (A) Cement Mortar 1:3 (1 cement : 3 sand)

Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.510 4,940.00 2,519.40 M-081
Coarse sand cum 1.050 1,994.03 2,093.73 M-005
Cost of water KL 0.255 16.00 4.08 M-191
b) Labour
Mate day 0.036 617.00 22.21 L-12
Mazdoor day 0.900 511.52 460.37 L-13
c) Machinery
Water tanker 12 KL capacity ( speed @
20km/hr and return speed @ 30 km/hr and hour 0.019 1,327.00 25.21 P&M-024
30 mins for unloading )
Rate per cum = (a+b+c) 5,125.00
20.01 (B) Cement Mortar1:2 (1cement :2 sand)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.672 4,940.00 3,319.68 M-081
Coarse sand cum 0.930 1,994.03 1,854.45 M-005
Cost of water KL 0.336 16.00 5.38 M-191
b) Labour
Mate day 0.036 617.00 22.21 L-12
Mazdoor day 0.900 511.52 460.37 L-13
c) Machinery
Water tanker 12 KL capacity ( speed @
20km/hr and return speed @ 30 km/hr and hour 0.025 1,327.00 33.18 P&M-024
30 mins for unloading )
Rate per cum = (a+b+c) 5,695.00
20.01 (C) Cement Mortar1:4 (1cement :4 sand)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.403 4,940.00 1,990.82 M-081
Coarse sand cum 1.120 1,994.03 2,233.31 M-005
Cost of water KL 0.202 16.00 3.22 M-191
b) Labour
Mate day 0.036 617.00 22.21 L-12
Mazdoor day 0.900 511.52 460.37 L-13
c) Machinery
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
Water tanker 12 KL capacity ( speed @
20km/hr and return speed @ 30 km/hr and hour 0.015 1,327.00 19.91 P&M-024
30 mins for unloading )
Rate per cum = (a+b+c) 4,730.00
20.01 (D) Cement Mortar1:6 (1cement :6 sand)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.288 4,940.00 1,422.72 M-081
Coarse sand cum 1.337 1,994.03 2,666.02 M-005
Cost of water KL 0.144 16.00 2.30 M-191
b) Labour
Mate day 0.036 617.00 22.21 L-12
Mazdoor day 0.900 511.52 460.37 L-13
c) Machinery
Water tanker 12 KL capacity ( speed @
20km/hr and return speed @ 30 km/hr and hour 0.011 1,327.00 14.60 P&M-024
30 mins for unloading )
Rate per cum = (a+b+c) 4,588.00

20.02 PCC 1:3:6 using batching Plant


Plain cement concrete 1:3:6 nominal mix
with crushed stone aggregate 40 mm
nominal size mechanically mixed
Unit = cum
Taking output = 15 Cum
a) Labour
Mate day 0.320 617.00 197.44 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 7.000 511.52 3,580.64 L-13
b) Material
40 mm Aggregate cum 13.500 1,887.12 25,476.16 M-054
Coarse sand cum 6.750 1,994.03 13,459.71 M-004
cement tonne 3.450 4,940.00 17,043.00 M-081
Cost of water KL 1.380 16.00 22.08 M-191
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 0.167 4,104.45 685.44 P&M-039
Generator 250 KVA hour 0.167 3,475.00 580.33 P&M-046
Loader 3.1 cum capacity hour 0.362 4,279.80 1,549.29 P&M-011
Transit truck agitator
For loading & Unloding time hour 0.167 2,413.95 403.13 P&M-067
Rate per cum = (a+b+c)/15 4,238.00
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
Note Vibrator is a part of minor T & P which is
already included in overhead charges of
the contractor.
20.03 Plain/Reinforced Cement Concrete
complete as per Drawing and Technical
Specifications.
PCC Grade M15 Using Batching Plant

Unit = cum
Taking output = 360 Cum
a) Material
Cement tonne 99.000 4,940.00 489,060.00 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
40 mm Aggregate cum 194.400 1,887.12 366,856.73 M-054
20 mm Aggregate cum 97.200 1,887.12 183,428.37 M-052
10 mm Aggregate cum 32.400 1,887.12 61,142.79 M-050
Cost of water (Water/Cement Ratio - 0.4)
KL 39.600 16.00 633.60 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067

Per Cum Basic Cost of Labour, Material &


Machinery (a+b+c)/360 4,176.00
20.04 PCC Grade M20 Using Batching Plant

Unit = cum
Taking output = 360 Cum
a) Material
Cement tonne 123.840 4,940.00 611,769.60 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
40 mm Aggregate cum 129.600 1,887.12 244,571.15 M-054
20 mm Aggregate cum 129.600 1,887.12 244,571.15 M-052
10 mm Aggregate cum 64.800 1,887.12 122,285.58 M-050
Cost of water (Water/Cement Ratio - 0.4)
KL 49.536 16.00 792.58 M-191
b) Labour
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067

Per Cum Basic Cost of Labour, Material &


Machinery (a+b+c)/360 4,518.00
20.05 RCC Grade M20 Using Batching Plant

Unit : cum
Taking output = 360 Cum
a) Material
Cement tonne 124.980 4,940.00 617,401.20 M-081
Coarse Sand cum 162.000 1,994.03 323,033.02 M-004
20 mm Aggregate cum 194.400 1,887.12 366,856.73 M-052
10 mm Aggregate cum 129.600 1,887.12 244,571.15 M-050
Cost of water KL 49.992 16.00 799.87 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,144.38 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 4,533.00
20.06 PCC Grade M25 Using Batching Plant

Unit : cum
Taking output = 360 Cum
a) Material
Cement tonne 143.850 4,940.00 710,619.00 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
40 mm Aggregate cum 129.600 1,887.12 244,571.15 M-054
20 mm Aggregate cum 129.600 1,887.12 244,571.15 M-052
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
10 mm Aggregate cum 64.800 1,887.12 122,285.58 M-050
Cost of water KL 57.540 16.00 920.64 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,144.38 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 4,793.00
20.07 RCC Grade M25 Using Batching Plant

Unit: cum
Taking output = 360 Cum
a) Material
Cement tonne 145.140 4,940.00 716,991.60 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
20 mm Aggregate cum 194.400 1,887.12 366,856.73 M-052
10 mm Aggregate cum 129.600 1,887.12 244,571.15 M-050
Admixture @ 0.2 % of Cement Kg 290.280 167.49 48,617.69 M-182
Cost of water KL 58.056 16.00 928.90 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 4,945.00
20.08 PCC Grade M30 Using Batching Plant

Unit : cum
Taking output = 360 Cum
a) Material
Cement tonne 145.800 4,940.00 720,252.00 M-081
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
40 mm Aggregate cum 129.600 1,887.12 244,571.15 M-054
20 mm Aggregate cum 129.600 1,887.12 244,571.15 M-052
10 mm Aggregate cum 64.800 1,887.12 122,285.58 M-050
Cost of water KL 58.320 16.00 933.12 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 4,819.00
20.09 RCC Grade M30 Using Batching Plant

Unit = cum
Taking output = 360 Cum
a) Material
Cement tonne 146.400 4,940.00 723,216.00 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
20 mm Aggregate cum 194.400 1,887.12 366,856.73 M-052
10 mm Aggregate cum 129.600 1,887.12 244,571.15 M-050
Admixture @ 0.3 % of Cement Kg 439.200 167.49 73,559.63 M-182
Cost of water KL 58.560 16.00 936.96 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 5,032.00
20.10 PCC Grade M35 Using Batching Plant

Unit : cum
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
Taking output = 360 Cum
a) Material
Cement tonne 150.840 4,940.00 745,149.60 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
20 mm Aggregate cum 194.400 1,887.12 366,856.73 M-052
10 mm Aggregate cum 129.600 1,887.12 244,571.15 M-050
Admixture @ 0.3 % of Cement Kg 452.520 167.49 75,790.54 M-182
Cost of water KL 60.336 16.00 965.38 M-191
b) Labour
Mate day 0.160 617.00 965.38 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 5,102.00
20.11 RCC Grade M35 Using Batching Plant

Unit ; cum
Taking output = 360 Cum
a) Material
Cement tonne 151.920 4,940.00 750,484.80 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
20 mm Aggregate cum 194.400 1,887.12 366,856.73 M-052
10 mm Aggregate cum 129.600 1,887.12 244,571.15 M-050
Admixture @ 0.4 % of Cement Kg 607.680 167.49 101,777.59 M-182
Cost of water KL 60.768 16.00 972.29 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 5,186.00
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.

20.12 RCC Grade M40 Using Batching Plant

Unit ; cum
Taking output = 360 Cum
a) Material
Cement tonne 154.800 4,940.00 764,712.00 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
20 mm Aggregate cum 194.400 1,887.12 366,856.73 M-052
10 mm Aggregate cum 129.600 1,887.12 244,571.15 M-050
Admixture @ 0.8 % of Cement Kg 1238.400 167.49 207,414.04 M-182
Cost of water KL 61.920 16.00 990.72 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 5,519.00
20.13 RCC Grade M45 Using Batching Plant

Unit ; cum
Taking output = 360 Cum
a) Material
Cement tonne 154.800 4,940.00 764,712.00 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
20 mm Aggregate cum 194.400 1,887.12 366,856.73 M-052
10 mm Aggregate cum 129.600 1,887.12 244,571.15 M-050
Admixture @ 1 % of Cement Kg 1548.000 167.49 259,267.55 M-182
Cost of water KL 61.920 16.00 990.72 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 5,663.00
20.14 RCC Grade M50 Using Batching Plant

Unit ; cum
Taking output = 360 Cum
a) Material
Cement tonne 154.800 4,940.00 764,712.00 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
20 mm Aggregate cum 194.400 1,887.12 366,856.73 M-052
10 mm Aggregate cum 129.600 1,887.12 244,571.15 M-050
Admixture @ 0.8 % of Cement Kg 1238.400 167.49 207,414.04 M-182
Silica Fume @ 5% of Cement Kg 7740.000 33.60 260,064.00 M-199
Cost of water KL 61.920 16.00 990.72 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 6,242.00
20.15 RCC Grade M55 Using Batching Plant

Unit ; cum
Taking output = 360 Cum
a) Material
Cement tonne 158.400 4,940.00 782,496.00 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
20 mm Aggregate cum 194.400 1,887.12 366,856.73 M-052
10 mm Aggregate cum 129.600 1,887.12 244,571.15 M-050
Admixture @ 1 % of Cement Kg 1267.200 167.49 212,237.63 M-182
Silica Fume @ 5% of Cement Kg 7920.000 33.60 266,112.00 M-199
Cost of water KL 63.360 16.00 1,013.76 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 6,321.00
20.16 RCC Grade M60 Using Batching Plant

Unit ; cum
Taking output = 360 Cum
a) Material
Cement tonne 160.200 4,940.00 791,388.00 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
20 mm Aggregate cum 194.400 1,887.12 366,856.73 M-052
10 mm Aggregate cum 129.600 1,887.12 244,571.15 M-050
Admixture @ 1 % of Cement Kg 1281.600 167.49 214,649.42 M-182
Silica Fume @ 6% of Cement Kg 9612.000 33.60 322,963.20 M-199
Cost of water KL 64.080 16.00 1,025.28 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 6,511.00
20.17 RCC Grade M65 Using Batching Plant

Unit ; cum
Taking output = 360 Cum
a) Material
Cement tonne 162.000 4,940.00 800,280.00 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
20 mm Aggregate cum 194.400 1,887.12 366,856.73 M-052
10 mm Aggregate cum 129.600 1,887.12 244,571.15 M-050
Admixture @ 1 % of Cement Kg 1296.000 167.49 217,061.21 M-182
Silica Fume @ 6% of Cement Kg 9720.000 33.60 326,592.00 M-199
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
Cost of water KL 64.800 16.00 1,036.80 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 6,552.00
20.18 A DLC Using Batching Plant-240 cum
capacity Plant
Unit = cum
Taking output = 450 Cum
a) Material
Cement @ 150 kg/cum of concrete tonne 67.500 4,940.00 333,450.00 M-081
Coarse Sand as per IS: 383 @ 0.45
cum/cum of concrete cum 202.500 1,994.03 403,791.28 M-004
Crushed stone coarse aggregate of 25 mm
and 12.5 mm nominal sizes graded as per
table 600-1 @ 0.90 cum/cum of concrete cum 405.000 1,887.12 764,284.86 M-045
conforming to clause 602.2.6.

Cost of water (Water/Cement Ratio - 0.4)


KL 27.000 16.00 432.00 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 240 cum/hour
hour 2.500 6,313.65 15,784.13 P&M-038
Generator 250 KVA hour 2.500 3,475.00 8,687.50 P&M-046
Loader 3.1 cum capacity hour 10.848 4,279.80 46,428.19 P&M-011

Per Cum Basic Cost of Labour, Material &


Machinery (a+b+c)/450 3,500.00
20.18 B Dry Lean Cement Concrete Sub- base
Flyash (Using Batching Plant)-240 cum
capacity Plant
Unit = cum
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
Taking output = 450 Cum
a) Material
Cement @ 150 kg/cum of concrete tonne 57.860 4,940.00 285,828.40 M-081
Coarse Sand as per IS: 383 @ 0.45
cum/cum of concrete cum 202.500 1,994.03 403,791.28 M-004
Crushed stone coarse aggregate of 25 mm
and 12.5 mm nominal sizes graded as per
table 600-1 @ 0.90 cum/cum of concrete cum 405.000 M-053 +M-
1,887.12 764,284.86
conforming to clause 602.2.6. 051 / 2

Fly ash conforming to IS: 3812-1966 (Part-


I) tonne 9.640 204.70 1,973.33 M-010
Cost of water (Water/Cement Ratio - 0.4)
KL 23.144 16.00 370.30 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 240 cum/hour
hour 2.500 6,313.65 15,784.13 P&M-038
Generator 250 KVA hour 2.500 3,475.00 8,687.50 P&M-046
Loader 3.1 cum capacity hour 10.848 4,279.80 46,428.19 P&M-011

Per Cum Basic Cost of Labour, Material &


Machinery (a+b+c)/450 3,399.00
Note Quantity provided for aggregate is for
estimating purpose. Exact quantity shall be
as per mix design.
*Calculation of cement and fly ash.
Cement @ 150 kg/cum = 450 x 150 =
67.500 tonnes. 20 per cent of cement to
be replaced by fly ash = 13.50 tonnes.
Balance cement = 54.0 tonnes. Quantity of
fly ash = 13.50 x specific gravity of fly
ash /specific gravity of cement = 13.50 x
2.25/3.15 = 9.64 tonnes.

20.18 C DLC Using Batching Plant-120 cum


capacity Plant
Unit = cum
Taking output = 450 Cum
a) Material
Cement @ 150 kg/cum of concrete tonne 67.500 4,940.00 333,450.00 M-081
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
Coarse Sand as per IS: 383 @ 0.45
cum/cum of concrete cum 202.500 1,994.03 403,791.28 M-004
Crushed stone coarse aggregate of 25 mm
and 12.5 mm nominal sizes graded as per
table 600-1 @ 0.90 cum/cum of concrete cum M-053 +M-
405.000 1,887.12 764,284.86
conforming to clause 602.2.6. 051 / 2

Cost of water (Water/Cement Ratio - 0.4)


KL 27.000 16.00 432.00 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 5.000 4,104.45 20,522.25 P&M-039
Generator 250 KVA hour 5.000 3,475.00 17,375.00 P&M-046
Loader 3.1 cum capacity hour 10.848 4,279.80 46,428.19 P&M-011

Per Cum Basic Cost of Labour, Material &


Machinery (a+b+c)/450 3,530.00
20.18 D Dry Lean Cement Concrete Sub- base
Flyash (Using Batching Plant) -120 cum
capacity Plant
Unit = cum
Taking output = 450 Cum
a) Material
Cement @ 150 kg/cum of concrete tonne 57.860 4,940.00 285,828.40 M-081
Coarse Sand as per IS: 383 @ 0.45
cum/cum of concrete cum 202.500 1,994.03 403,791.28 M-004
Crushed stone coarse aggregate of 25 mm
and 12.5 mm nominal sizes graded as per
table 600-1 @ 0.90 cum/cum of concrete cum 405.000 M-053 +M-
1,887.12 764,284.86
conforming to clause 602.2.6. 051 / 2

Fly ash conforming to IS: 3812-1966 (Part-


I) tonne 9.640 204.70 1,973.33 M-010
Cost of water (Water/Cement Ratio - 0.4)
KL 23.144 16.00 370.30 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
Batching Plant of capacity 120 cum/hour
hour 5.000 4,104.45 20,522.25 P&M-039
Generator 250 KVA hour 5.000 3,475.00 17,375.00 P&M-046
Loader 3.1 cum capacity hour 10.848 4,279.80 46,428.19 P&M-011

Per Cum Basic Cost of Labour, Material &


Machinery (a+b+c)/450 3,428.00
Note Quantity provided for aggregate is for
estimating purpose. Exact quantity shall be 67.500 13.50 54.00
as per mix design.
*Calculation of cement and fly ash.
Cement @ 150 kg/cum = 450 x 150 =
67.500 tonnes. 20 per cent of cement to
be replaced by fly ash = 13.50 tonnes.
Balance cement = 54.0 tonnes. Quantity of
fly ash = 13.50 x specific gravity of fly
ash /specific gravity of cement = 13.50 x
2.25/3.15 = 9.64 tonnes.

20.19 A PQC M 35 grade Using Batching Plant-


240 cum capacity Plant
Unit ; cum
Taking output = 900 Cum
a) Material
Cement @4000 kg/cum of concrete tonne 360.000 4,940.00 1,778,400.00 M-081
Coarse sand as per IS :383 and confirming
to clause 602.2.4 @0.45 cum/cum of cum 405.000 1,994.03 807,582.56 M-004
concrete
Crushed stone coarse aggregate of 25mm
and 12.5mm nominal size @0.90 cum/cum
of concrete confirming to clause 602.2.4 cum 810.000 1,887.12 1,528,569.72 M-045

Admixture @ 0.5 % of Cement Kg 1800.000 167.49 301,473.90 M-182


Cost of water KL 144.000 16.00 2,304.00 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 240 cum/hour
hour 5.000 6,313.65 31,568.25 P&M-038
Generator 250 KVA hour 5.000 3,475.00 17,375.00 P&M-046
Loader 3.1 cum capacity hour 21.696 4,279.80 92,856.38 P&M-011
Transit truck agitator
For loading & Unloding time hour 5.000 2,413.95 12,069.75 P&M-067
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/900 5,082.67
Say 5,083.00

20.19 B PQC M 35 grade Using Batching-240 cum


capacity Plant (Cement - Flyash)

Unit ; cum
Taking output = 900 Cum
a) Material
Cement tonne 306.000 4,940.00 1,511,640.00 M-081
Fly ash conforming to IS: 3812 (Part-I) tonne 93.000 204.70 19,037.30 M-010
Coarse sand as per IS :383 and confirming
to clause 602.2.4 @0.45 cum/cum of cum 364.500 1,994.03 726,824.30 M-004
concrete
Crushed stone coarse aggregate of 25mm
and 12.5mm nominal size @0.90 cum/cum
of concrete confirming to clause 602.2.4 cum 810.000 1,887.12 1,528,569.72 M-045

Admixture @ 0.5 % of Cement Kg 1530.000 167.49 256,252.82 M-182


Cost of water KL 122.400 16.00 1,958.40 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 240 cum/hour
hour 5.000 6,313.65 31,568.25 P&M-038
Generator 250 KVA hour 5.000 3,475.00 17,375.00 P&M-046
Loader 3.1 cum capacity hour 20.973 4,279.80 89,761.16 P&M-011
Transit truck agitator
For loading & Unloding time hour 5.000 2,413.95 12,069.75 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/900 4,664.00
Note 1.The quantities for cement, coarse
aggregate and fine aggregates are for
estimating only .The exact quantities will
be as per mix design.
2.IRC: 68 may be referred for guidelines
on the design of cement-fly ash concrete
for rigid pavement construction.

*Calculation of cement, sand and fly ash.


Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
Cement @ 400 kg/cum = 900 x 400 = 360
tonnes. 15 per cent of cement to be
replaced by fly ash = 54 tonnes. Balance
cement = 306 tonnes. Quantity of fly ash =
54 x specific gravity of fly ash /specific
gravity of cement = 54 x 2.25/3.15 =38.571
tonnes.

Sand @ 0.45 cum / cum of concrete = 900


x 0.45 = 405 x 1.6 = 648 tonnes.10 per
cent to be replaced by flyash. Balance
sand = 648 x 0.9 = 583.2 tonnes =
583.02 / 1.6 = 364.5cum. Quantity of
flyash = (648-583.2) x specific gravity of fly
ash/specific gravity of sand = 64.8 x 2.25 /
2.687 = 54.26 tonnes

Fly ash Total fly ash = 38.571 + 54.26 =


92.831 (Say 93 tonnes)
20.19 C PQC M 35 grade Using Batching Plant-
120 cum capacity
Unit ; cum
Taking output = 900 Cum
a) Material
Cement @4000 kg/cum of concrete tonne 360.000 4,940.00 1,778,400.00 M-081
Coarse sand as per IS :383 and confirming
to clause 602.2.4 @0.45 cum/cum of cum 405.000 1,994.03 807,582.56 M-004
concrete
Crushed stone coarse aggregate of 25mm
and 12.5mm nominal size @0.90 cum/cum
of concrete confirming to clause 602.2.4 cum 810.000 1,887.12 1,528,569.72 M-045

Admixture @ 0.5 % of Cement cum 1800.000 167.49 301,473.90 M-182


Cost of water KL 144.000 16.00 2,304.00 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 10.000 4,104.45 41,044.50 P&M-039
Generator 250 KVA hour 10.000 3,475.00 34,750.00 P&M-046
Loader 3.1 cum capacity hour 21.696 4,279.80 92,854.54 P&M-011
Transit truck agitator
For loading & Unloding time hour 10.000 2,413.95 24,139.50 P&M-067
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/900 5,126.00

20.19 D PQC M 35 grade Using Batching Plant-


120 cum capacity (Cement - Flyash)

Unit ; cum
Taking output = 900 Cum
a) Material
Cement tonne 306.000 4,940.00 1,511,640.00 M-081
Fly ash conforming to IS: 3812 (Part-I) tonne 93.000 204.70 19,037.30 M-010
Coarse sand as per IS :383 and confirming
to clause 602.2.4 @0.45 cum/cum of cum 364.500 1,994.03 726,824.30 M-004
concrete
Crushed stone coarse aggregate of 25mm
and 12.5mm nominal size @0.90 cum/cum
of concrete confirming to clause 602.2.4 cum 810.000 1,887.12 1,528,569.72 M-045

Admixture @ 0.4 % of Cement Kg 1224.000 167.49 205,002.25 M-182


Cost of water KL 122.400 16.00 1,958.40 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 10.000 4,104.45 41,044.50 P&M-039
Generator 250 KVA hour 10.000 3,475.00 34,750.00 P&M-046
Loader 3.1 cum capacity hour 20.973 4,279.80 89,761.16 P&M-011
Transit truck agitator
For loading & Unloding time hour 10.000 2,413.95 24,139.50 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/900 4,650.00
Note 1.The quantities for cement, coarse
aggregate and fine aggregates are for
estimating only .The exact quantities will
be as per mix design.
2.IRC: 68 may be referred for guidelines
on the design of cement-fly ash concrete
for rigid pavement construction.

*Calculation of cement, sand and fly ash.


Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
Cement @ 422 kg/cum = 900 x 422 =
379.8 tonnes. 15 per cent of cement to be
replaced by fly ash = 56.97 tonnes.
Balance cement = 322.830 tonnes.
Quantity of fly ash = 56.97 x specific
gravity of fly ash /specific gravity of cement
= 56.97 x 2.25/3.15 = 40.693 tonnes.

Sand @ 0.45 cum / cum of concrete = 900


x 0.45 = 405 x 1.6 = 648 tonnes.10 per
cent to be replaced by flyash. Balance
sand = 648 x 0.9 = 583.2 tonnes =
583.02 / 1.6 = 364.5cum. Quantity of
flyash = (648-583.2) x specific gravity of fly
ash/specific gravity of sand = 64.8 x 2.25 /
2.687 = 54.26 tonnes

Fly ash Total fly ash = 40.693 + 54.26 =


94.95 tonnes. (Say 95 tonnes)

20.20 PCC Grade M15 Using Batching Plant for


Kerb
Unit = cum
Taking output = 360 Cum
a) Material
Cement tonne 99.000 4,940.00 489,060.00 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
40 mm Aggregate cum 194.400 1,887.12 366,856.73 M-054
20 mm Aggregate cum 97.200 1,887.12 183,428.37 M-052
10 mm Aggregate cum 32.400 1,887.12 61,142.79 M-050
Cost of water (Water/Cement Ratio - 0.4)
KL 39.600 16.00 633.60 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 4,176.00
20.21 PCC Grade M20 Using Batching Plant for
Kerb
Unit = cum
Taking output = 360 Cum
a) Material
Cement tonne 123.840 4,940.00 611,769.60 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
40 mm Aggregate cum 129.600 1,887.12 244,571.15 M-054
20 mm Aggregate cum 129.600 1,887.12 244,571.15 M-052
10 mm Aggregate cum 64.800 1,887.12 122,285.58 M-050
Cost of water (Water/Cement Ratio - 0.4)
KL 49.536 16.00 792.58 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067

Per Cum Basic Cost of Labour, Material &


Machinery (a+b+c)/360 4,518.00
20.21 Cost of Water
Unit = KL
Taking output = 12 KL
a) Labour
Mate day 0.005 617.00 3.09 L-12
Mazdoor day 0.133 511.52 68.03 L-13
c) Machinery
Centrifugal water pump (600 LMP) hour 0.533 329.00 175.36 P&M-134
Water tanker 12 KL hour 0.533 1,327.00 707.29 P&M-024

Rate Per KL (a+b+c)/12 79.00

You might also like