Professional Documents
Culture Documents
LOADING + Lead
Km 10 to Km UNLOADIN Distance(Km) TOTAL CARRIAGE
Sl. No. Name of Materials Unit Source upto 5 km Km 5 to Km 10 20 km and above G
20 COST
1 2 3 4 5 6 7 8 12 12 12
Lime , Stone dust, Building
Rates applicable on
1 Rubbish, Earth, Manure or Sludge Cum 137.24 10.34 8.59 7.10 0.00 50 487.8
compacted volume
and Excavated Rocks
Kochammaniyazhikom
i) Stone dust Cum General metal Industries 137.24 10.34 8.59 7.10 - 50.00 487.8
Kulappadam (20 km from end
Point)
Kochammaniyazhikom
General metal Industries
ii) Screening Material Cum 171.56 12.92 10.74 8.87 - 50.00 609.7
Kulappadam (20 km from end
Point)
Kochammaniyazhikom
General metal Industries
iii) Earth Cum 171.56 12.92 10.74 8.87 - 10.00 254.8
Kulappadam (20 km from end
Point)
Kochammaniyazhikom
General metal Industries
i) Coarse Sand & Fine Sand Cum 137.24 10.34 8.59 7.10 - 50.00 487.8
Kulappadam (20 km from end
Point)
Kochammaniyazhikom
General metal Industries
ii) Stone Agreegate Cum 137.24 10.34 8.59 7.10 - 50.00 487.8
Kulappadam (20 km from end
Point)
Kochammaniyazhikom
ii) Stone Agreegate (Used in DBM, BC Cum General metal Industries 137.24 10.34 8.59 7.10 - 50.00 487.8
& RCC Works) Kulappadam (20 km from end
Point)
Kochammaniyazhikom
iii) Stone Chips Cum General metal Industries 137.24 10.34 8.59 7.10 - 50.00 487.8
Kulappadam (20 km from end
Point)
Kochammaniyazhikom
iv) Soling Stone Cum General metal Industries 161.47 12.16 10.11 8.33 - 50.00 573.2
Kulappadam (20 km from end
Point)
Kochammaniyazhikom
v) Boulder Cum General metal Industries 161.47 12.16 10.11 8.33 0.00 50.00 573.2
Kulappadam (20 km from end
Point)
10 Brick 1000 nos Vijayanagr 365.98 27.57 22.91 18.92 5.00 449.1
TMT BAR FOR August 2021 (SAIL RATEs)
Including GST (18%) Excluding GST
12 Meter
Sr. No. Bar Dia Per Piece Rate per Piece
weight (As SAIL June Per Kg. Rate Per Ton Rate Per Ton Rate
2021)
M-324
(b) Red sqm 515.69
M-324 (C) Yellow sqm 531.88
(ii) M-40 Grade and 80mm thickness (a) White sqm 581.43
(b) Red sqm 596.64
(C) Yellow sqm 615.88
M-325 Kerb-Stone Block- M30 Grade (Size 375mm x 300mm 150 ) each 79.00
M-326 inclusive
Autoclavedof Aerated
OH & CPConcrete (AAC) Block cum 2457.20
M-327 Bitumen grade VG 40 (30/40) packed Mathura MT 44020.00
MR01 Construction of restaurant, workshop, first aid room, shop etc. Sqm 1
MR02 in truck parking
Providing area booth
Telephone complete as peras
complete drg.
perand direction ofand
specifications the Engineer. Nos. 1
MR03 direction of
Providing & Engineer.
fixing tube well, complete as per drawing and Nr. 1
MR04 additional
Providing aspecifictions.
Drinking Water Kiosk complete as per drawing & Nr. 1
MR05 specification.
Providing and fixing of litter bins in Truck lay Bye locations Nr. 1
MR06 complete as per
Construction drawing
of toilet orprovided
block as directed byfittings
with the engineer.
and fixtures complete in truck Nr. 1
MR07 parking area complete
Construction as per
of Open lined U -drg. and
Drain in truck laybye area Meter 1
direction of
complete the Engineer.
MR08 Providing as shown
shelters in bus
for drawing and technical
passengers specification
as per drawing and clause 309. Nr. 1
MR09 MORT&H Specifications section 300, 1500, 1600 and 1700.
Providing & fixing guard railing with tubular steel sections at foot path / medians / Meter 1
MR10 islands etc at
Toll Booth including
Tollplazafoundation concrete and painting with approved paint etc. all Nr. 1
complete as per drawing & MORT&H Specifications Clauses 808, 300, 1500, 1700
MR11 Barrier
& 1900.gates at Tollplaza For 3.2 m wide toll lane Nr. 1
MR12 Barrier gates at Tollplaza For 4.5 m wide toll lane Nr. 1
MR13 Canopy Sqm 1
MR14 Canopy Lights Halide lamps 150 watt Nr. 1
MR15 Canopy Lights Halogen lamps 1000 watt Nr. 1
MR16 Loading Unloading Platform Sqm 1
MR17 Traffic Aid Post at Toll Plaza Nr. 1
MR18 Medical Aid Post at Toll Plaza Nr. 1
MR19 Vehicle Rescue Post at Toll Plaza Nr. 1
MR20 Ambulances at Toll Plaza Nr. 1
MR21 Cranesat Toll Plaza Nr. 1
MR22 Electronic Toll Connection (ETC lanes) at Toll Plaza Nr. 1
MR23 Intercom facility at Toll Plaza Nr. 1
MR24 Weigh Bridge Nr. 1
MR25 Car Parking area Sqm 1
MR26 Generator room Sqm 1
MR27 Base Maintainance Camp Sqm 1
MR28 Toll plaza equipment Lane 1
MR29 Electrification And Air conditioning for toll Booth and toll Plaza LS 1
MR30 Bull nose crash barrier Nr. 1
MR31 Standby Generator at Toll Plaza Nr. 1
MR32 CCTV camera installed at each booth Nr. 1
MR33 T1for Toll Road Start Nr. 1
MR34 T2 for Toll Gate 1 Km Nr. 1
MR35 T3 for Toll Gate 500 m and toll rates Nr. 1
MR36 T4 for exempt vehicles at Toll Plaza Nr. 1
MR37 T5 for pictorial description of toll rates Nr. 1
MR38 T6 for over size vehicle lane direction sign at Toll Plaza Nr. 1
MR39 T7 near the Toll booths displaying Toll Rates, exempt vehicles Nr. 1
MR40 andfor
T8 complaint telephone
Toll Road End number & address Nr. 1
MR41 Picnic Area at Rest Area Sqm 1
MR42 Petrol Pump & Pepairing Shop at Rest Area Sqm 1
MR43 Buffer Zone at Rest Area Sqm 1
MR44 Traffic blinker Signal (L.E.D.) Nr 1
MR4S PVC Roof Sheet at FOB Sqm 1
MR46 Cost of Water Quality Monitoring Nos. 1
MR47 Cost of Soil Quality Monitoring Nos. 1
MR48 Cost of Ambient Air Quality Nos. 1
MR49 Cost of Ambient Noise Monitoring 24 hour continuous Nos. 1
MR50 Consent to Establish (CTE) Nos. 1
MR51 Consent to Operate (CTO) Nos. 1
MR52 Compliance submission for Consent to Establish (CTE) Nos. 1
MR53 Compliance submission for Consent to Operate (CTO) Nos. 1
MR54 Cost of Environmental Workshop Nos. 1
PM1001 Dozer - 240 HP Hour 6,586.65
PM1002 Dozer - 175 HP Hour 5,087.25
PM1003 Dozer - 90 HP Hour 3,502.80
PM2001 Motor Grader 4.3 metre blade Hour 5,991.00
PM2002 Motor Grader 3.7 metre blade Hour 5,497.00
PM2003 Motor Grader 3.35 metre blade Hour 4796
PM3003 Hydraulic Excavator of 1.2 cum bucket Hour 3,420.00
PM3004 Hydraulic Excavator of 1.1 cum bucket Hour 3,074.00
PM3005 Hydraulic Excavator of 0.9 cum bucket Hour 2,782.00
PM4001 Jack Hammer (attachment of Hydraulic Excavator) Hour 216.30
PM5001 Front End loader 3.1 cum bucket capacity Hour 4,279.80
PM5002 Front End loader 2.1 cum bucket capacity Hour 2,640.75
PM5003 Backhoe-loader 1 cum bucket capacity Hour 1112
PM6001 Tipper-18 Cum Hour 2,883.30
PM6002 Tipper-14 Cum Hour 2,556.75
PM6003 Tipper-10 Cum Hour 2,274.30
PM6004 Tipper-5.5 Cum Hour 1,731.45
PM7001 Vibratory Soil Compactor (10 tonne) Hour 903.5
PM8001 Smooth Wheeled Roller 8 tonne Hour 417
PM9001 Tandem Roller Hour 1668
PM9002 Mini Tandem Roller hour 1,437.45
Vibratory
PM10001 Pneumatic Road Roller Hour 2,562.00
road Roller
PM11001 Water Tanker (16 KL) Hour 1,501.00
PM11002 Water Tanker (12 KL) Hour 1,327.00
PM11003 Water Tanker (6 KL) Hour 1005
PM12001 Tractor-Trolly Hour 1876.5
PM13001 Rotavator Hour 16.80
PM14001 Ripper Hour 22.05
PM15001 Air Compressor -250 cfm Hour 614.25
PM15002 Air Compressor -500 cfm Hour 2,752.05
PM16001 Integrated Stone Crusher Stone (3 Stage) 250 TPH Hour 15,481.20
PM17001 Wet Mix Plant - 250 TPH Capacity Hour 921.90
PM17002 Wet Mix Plant - 200 TPH Capacity Hour 612.15
PM17003 Wet Mix Plant - 100 TPH Capacity Hour 585.90
PM18001 Hotmix Plant - 200 TPH Capacity Hour 14,634.90
PM18002 Hotmix Plant - 160 TPH Capacity Hour 10,338.30
PM18003 Hotmix Plant - 120 TPH capacity Hour 8,372.70
PM19001 Batching and Mixing Plant - 240 cum Capacity Hour 6,313.65
PM19002 Batching and Mixing Plant - 120 cum Capacity Hour 4,104.45
PM20001 Mobile Concrete Batching / Mixing Plant Hour 983.85
PM21001 Concrete Mixer - 0.4/0.28 cum Hour 511.35
PM21002 Concrete Mixer - 1 cum Hour 551.25
PM22001 Generator 725 KVA Hour 11,596.20
PM22002 Generator 500 KVA Hour 8,022.00
PM22003 Generator 400 KVA Hour 6,470.10
PM22004 Generator 250 KVA Hour 3475
PM22005 Generator 125 KVA Hour 2,390.85
PM22006 Generator 100 KVA Hour 2,041.20
PM22007 Generator 62.5 KVA Hour 1,312.50
PM22008 Generator 33 KVA Hour 753.90
PM22009 Generator 15 KVA Hour 425.25
PM23001 Mechanical Broom Hydraulic Hour 500.4
PM24001 Bitumen Pressure Distributor Hour 1,729.35
PM25001 Emulsion Pressure Distributor Hour 1112
PM26001 Bitumen Boiler Oil Fired Hour 743.40
PM27001 Mastic Cooker Hour 1042.5
PM28001 Paver Finisher Mechanical Hour 1112
PM29001 Paver Finisher Hydrostatic with sensor control -240 HP Hour 9,233.70
PM29002 Paver Finisher Hydrostatic with sensor control -170 HP Hour 2,362.50
PM30001 Paver Finisher Concrete with 300 HP Motor Hour 28,108.50
PM30002 Paver Finisher Concrete with 241 HP Motor Hour 18,201.75
PM30003 Paver Finisher Concrete with 118 HP Motor Hour 4,517.10
PM31001 Texture Curing Machine (TCM) - upto 18 m Hour 4,830.00
PM31002 Texture Curing Machine (TCM) - upto 9 m Hour 3,807.30
PM32001 Hydraulic Chip Spreader Hour 2,220.75
PM33001 Pot-Hole Repair Machine Hour 1,796.55
PM34001 Transit Mixer - 6 Cum Hour 2,413.95
PM35001 Concrete Pump Hour 1,341.90
PM36001 Boom Placer Hour 4,401.60
PM37001 Kerb Casting Machine Hour 1,957.20
PM38001 Piling Rig with Bentonite Pump Hour 19,747.35
PM39001 Pneumatic Sinking Plant Hour 6,920.55
PM40001 Road marking machine Hour 1,951.95
PM41001 Mobile Slurry Seal Equipment Hour 3,998.40
PM42001 Joint Cutting Machine Hour 511.35
PM43001 Bar Bending & Cutting Machine Hour 528.15
PM44001 Needle Vibrator Hour 590.10
PM45001 Jack Hammer for air compressor Hour 11.55
PM46001 Plate Compactor Hour 597.45
PM47001 Milling Machine with 1 meter Drum Width Hour 4,784.85
PM47002 Milling Machine with 1.2 meter Drum Width Hour 5,592.30
PM47003 Milling Machine With 1.3 meter Drum Width Hour 8,006.25
PM47004 Milling Machine With 2 meter Drum Width Hour 11,982.60
PM48001 Cold in Situ recycling of bitumen's pavement with foam Hour 30,811.20
PM49001 bitumen technologyof WMM/GSB/Sub grade
In situ stabilisation Hour 26,741.40
PM50001 Cement spreader Hour 8,300.25
PM51001 Mobile cold recycling mixing plant Hour 22,397.55
PM52001 Hot in place recycling Hour 108,654.00
PM53001 Pre heater unit for hot in place recycling Hour 1,271.55
PM54001 Single boom Hydraulic Drill Jumbo Hour 5,420.10
PM55001 Two boom Hydraulic Drill Jumbo Hour 8,220.45
PM56001 Three boom Hydraulic Drill Jumbo Hour 12,007.80
PM57001 Hydraulic Rock bolt drill Hour 7,787.85
PM58001 Rotating Telehandlers Hour 1,207.50
PM59001 Shotcrete Machine Hour 1,830.15
PM60001 Grouting machine Hour 798.00
PM61001 Dewatering Pump 10 HP Hour 328.65
PM61002 Concrete cutting machine Hour 1251
PM62001 Crawler mounted Crane 35 tonne capacity Hour 6,330.45
PM62002 Crawler mounted Crane 80 tonne capacity Hour 6,580.35
PM62003 Crawler mounted Crane 100 tonne capacity Hour 9,978.15
PM63001 Mobile Hydraulic Crane 3 tonne capacity Hour 1,083.60
PM63002 Mobile Hydraulic Crane 5 tonne capacity Hour 1,128.75
PM63003 Mobile Hydraulic Crane 10 tonne capacity Hour 1,240.05
PM63004 Mobile Hydraulic Crane 15 tonne capacity Hour 1,278.90
PM63005 Mobile Hydraulic Crane 20 tonne capacity Hour 1,584.45
PM63006 Mobile Hydraulic Crane 35 toone capacity Hour 2,394.00
PM64001 Concrete Bucket Hour 153.30
PM65001 Prestressing Jack with Pump & Access Hour 559.65
PM66001 Boat to carry atleast 20 persons hour 975.45
PM67001 Crane with grab 0.75 cum capacity hour 1,094.10
PM68001 Epoxy Injection gun hour 380.10
PM69001 Induction, deinduction and erection of plant and equipment including all hour 10,073.70
PM70001 components and40
Jack for Lifting accessories forcapacity.
tonne lifting pneumatic hour 378.00
method of well sinking.
PM71001 Vibrating Pile driving hammer complete with power unit and hour 18,571.35
accessories.
Per
PM72001 Tipper 18 Cum ( Surface Road) 5.88 As per Carriage Rate
Tonne Km.
PM72002 Tipper-18 Cum (Unsurfaced Gravelled Road) excluding OH & t.km 7.15 Do
PM72003 CP
Tipper-18 Cum (Katcha Track) excluding OH & CP t.km 14.30 Do
PM73001 Tipper -14 Cum (Surface Road) excluding OH & CP t.km 6.68 Do
PM73002 Tipper -14 Cum (Unsurfaced Gravelled Road) excluding OH & t.km 8.12 Do
PM73003 CP
Tipper -14 Cum (Katcha Track) excluding OH & CP t.km 16.23 Do
PM74001 Tipper -10 Cum (Surface Road) excluding OH & CP t.km 8.25 Do
PM74002 Tipper -10 Cum (Unsurfaced Gravelled Road) excluding OH & t.km 10.03 Do
PM74003 CP
Tipper -10 Cum (Katcha Track) excluding OH & CP t.km 20.06 Do
PM75001 Tipper- 5.5 Cum (Surface Road) excluding OH & CP t.km 11.31 Do
PM75002 Tipper- 5.5 Cum (Unsurfaced Gravelled Road) excluding OH t.km 13.74 Do
PM75003 & CP 5.5 Cum (Katcha Track) excluding OH & CP
Tipper- t.km 27.48 Do
PM76001 Transit Mixer - 6 Cum excluding OH & CP t.km 12.77 Do
PM77001 Loading and unloading of stone boulder / stone aggregates / sand / kanker / cum 0.00 Do
PM77002 moorum (Using
Loading and by 18 cum
unloading capacity
of stone Tipper
boulder & aggregates / sand / kanker /
/ stone cum 0.00 Do
3.1 Cum capacity
moorum (Using Loader)
by 14 cum excluding
capacity OH & CP
Tipper & aggregates /
PM77003 Loading and unloading of stone boulder / stone cum 0.00 Do
2.1
sandCum capacity
/ kanker Loader) (Using
/ moorum excluding OHcum
by 10 & CPcapacity Tipper & 1.0 Cum capacity
PM77004 Loading and unloading of stone boulder / stone aggregates / sand / kanker / cum 0.00 Do
Loader)
moorum excluding
(Using byOH & CPcapacity Tipper &
5 cum
PM77005 Loading and Unloading of Cement or Steel by Manual Means tonne 0.00 Do
1.0
and Cum capacity Loader) excluding OH & CP
Stacking
PM78001 Centrifugal water pump Hour 329.00
PM79001 Shredding Machine Hour 416.00
PM80001 Mobile Bridge Inspection Unit (MBIU) hour 6,887.00
PM81001 Network Survey Vehicle (NSV) With SUV hour 6,415.00
PM82001 Falling weight deflectometer (FWD) Equipment With SUV hour 3,128.00
PM83001 Retroreflectometer testing equipment with Vehicle With SUV hour 1,709.00
PM84001 Sport utility vehicle (SUV) hour 1,221.00
PM85001 Automatic Vehicle Counter Classifier (ATCC) System hour 74.00
PM90001 WMM Paver finisher hour 1810.00
PM90002 6.5 KVA Generator set hour 304.00
PM90003 Sensor Paver Finisher(158 BHP) hour 3958.00
Approved
S.No. Description of Labour Unit
Rate
1 2 3 4
L-01 Blacksmith (IInd class) day 679
L-02 Blacksmith (Ist class)/ Welder/Plumber/Electrician day 738
L-03 Blaster (Stone cutter) day 511.52
L-04 Carpenter I Class day 738
L-05 Chiseller (Head Mazdoor) day 617
L-06 Driller (Jumper) day 558
L-07 Diver day 738
L-08 Fitter day 738
L-09 Mali day 511.52
L-10 Mason (IInd class) day 679
L-11 Mason (Ist class) day 738
L-12 Mate / Supervisor day 617
L-13 Mazdoor day 511.52
L-14 Mazdoor/Dresser (Semi Skilled) day 617
L-15 Mazdoor/Dresser/Sinker (Skilled) day 565.73
L-16 Medical Officer day 1077.25
L-17 Operator(grouting) day 738
L-18 Painter I class day 679
L-19 Para medical personnel day 622.72
L-20 Heavy Plant Operator day 626.89
L-21 Light Plant Operator. day 514.3
L-22 Heavy Vehicle Driver. day 1459.5
L-23 Light Vehicle Driver. day 676.93
L-24 Helper day 558
L-25 Black smith day 679
Basic Rate As per
2016 SOR
748.79
748.79
987.08
1303.77
1303.77
863.77
553.77
822.08
903.77
111.77
400
1325.57
1383.77
1383.77
1313.77
1343.77
1253.77
1253.77
1303.77
968.77
1136.27
1253.77
1253.77
1298.77
1318.77
1353.77
1353.77
1353.77
1353.77
1303.77
1378.77
1328.77
1349.22
1323.77
1321.93
1314.43
1262.79
1247.79
1403.77
1338.77
1353.77
1338.77
1303.77
1403.77
1318.77
1403.77
1370.44
1353.77
1403.77
1403.77
1303.77
1403.77
1353.77
1362.79
42.54
170
130
7980.04
7560.00
169.19
48
630
5145.00
0.59
12915.00
6310.00
136.66
34165.00
136.66
146.43
156.19
151.31
34788.00
10933.11
3.1
48
46064.00
40930.00
42380.00
40930.00
42036.00
41270.00
5.48
50
5700
45
55.00
735.00
5
280
52
230
30
275
159
27202.73
550
502
150
378.00
118.00
100.00
20
19.00
126.00
236.00
89.00
210.00
45
45
15.96
1.00
25
25
234.00
252.00
25.00
1008
120
27
56.00
83
30
45
50.00
8400.00
8400.00
19
61.74
224.02
124
76.89
336.00
178.00
160
160.18
30
1124
205
450
1403.77
948
376.00
41
288.00
103
440
5565
6510
4494
2310
1200
65.04
6.00
8.48
300.00
130.00
84.00
159.71
12
210.00
54.00
300.00
4210
889.00
10000
15000
123.62
221.22
321
42.65
42.65
159.51
330.00
43
1.50
23.85
46.14
2700
16.00
70
48
48
20.85
504.19
32.00
200
220
300
330
350
390
420
500
550
650
708
841
950
1000
1088
78
6,273.00
4,845.00
3,336.00
5,907.00
5,419.00
2100
3,293.00
2,965.00
2,689.00
206.00
4,076.00
2,515.00
800
2,746.00
2,435.00
2,166.00
1,649.00
650
200
1150
1,369.00
2,440.00
1,440.00
1,270.00
200
1250
16
21
585
2621
14744
878
583
558
13938
9846
7974
6013
3909
937
487
525
11044
7640
6162
2500
2277
1944
1250
718
405
200
1647
800
708
750
1500
8794
6971
26770
17335
4302
4600
3626
2115
1711
2299
1278
4192
1864
18807
6591
1859
3808
487
503
562
11
569
4557
5326
7625
11412
29344
25468
7905
21331
103480
1211
5162
7829
11436
7417
1150
1743
760
313
900
6029
6267
9503
1032
1075
1181
1218
1509
2280
146
533
929
1042
362
9594
360
17687
448
487
368
487
407
368
487
487
368
448
487
407
368
368
407
775
1050
448
448
451
370
1050
487
900
448
(A) Usage Rates of Plant and Machinery
Power
Sl. No. Description of Machine Activity Unit Rate
(in HP)
P&M-001 Dozer - 240 HP Spreading Cutting Clearing 6587 Hour 6,586.65
P&M-002 Dozer - 175 HP Spreading Cutting Clearing 5087 Hour 5,087.25
P&M-003 Dozer - 90 HP Spreading Cutting Clearing 3503 Hour 3,502.80
P&M-004 Motor Grader 4.3 metre blade Clearing Scarifying Spreading GSB WMM 5991 Hour 5,991.00
P&M-005 Motor Grader 3.7 metre blade Clearing Scarifying Spreading GSB WMM 5497 Hour 5,497.00
P&M-006 Motor Grader 3.35 metre blade Clearing Scarifying Spreading GSB WMM 4796 Hour 4,796.00
P&M-007 Hydraulic Excavator of 1.2 cum bucket Soil Ordinary Soil Marshy Soil Unsuitable 3420 Hour 3,420.00
P&M-008 Hydraulic Excavator of 1.1 cum bucket Soil Ordinary Soil Marshy Soil Unsuitable 3074 Hour 3,074.00
P&M-009 Hydraulic Excavator of 0.9 cum bucket Soil Ordinary Soil Marshy Soil Unsuitable 2782 Hour 2,782.00
P&M-010 Jack Hammer (attachment of Hydraulic Excavator) For Drilling Purpose 216 Hour 206.00
P&M-011 Front End loader 3.1 cum bucket capacity Soil loading, Aggregate loading, etc. 4280 Hour 4,279.80
P&M-012 Front End loader 2.1 cum bucket capacity Soil loading, Aggregate loading, etc. 2641 Hour 2,640.75
P&M-013 Backhoe-loader 1 cum bucket capacity Soil loading, Aggregate loading, etc. 1112 Hour 1,112.00
P&M-014 Tipper-18 Cum Transpotation of Soil, GSB,WMM, Hotmix etc. 2883 Hour 2,883.30
P&M-015 Tipper-14 Cum Transpotation of Soil, GSB,WMM, Hotmix etc. 2557 Hour 2,556.75
P&M-016 Tipper-10 Cum Transpotation of Soil, GSB,WMM, Hotmix etc. 2274 Hour 2,274.30
P&M-017 Tipper-5.5 Cum Transpotation of Soil, GSB,WMM, Hotmix etc. 1731 Hour 1,731.45
P&M-018 Vibratory Soil Compactor (10 tonne) Earth/Soil, GSB, WMM 904 Hour 903.50
P&M-019 Smooth Wheeled Roller 8 tonne Soil Compaction BM Compaction 417 Hour 417.00
P&M-020 Tandem Roller Rolling of Asphalt Surface 1668 Hour 1,668.00
P&M-021 Mini Tandem Roller Earth/Soil 1437 Hour 1,437.45
P&M-022 Pneumatic Road Roller Rolling of Asphalt Surface 2562 Hour 2,562.00
P&M-023 Water Tanker (16 KL) Water Transport. 1501 Hour 1,501.00
P&M-024 Water Tanker (12 KL) Water Transport. 1327 Hour 1,327.00
P&M-025 Water Tanker (6 KL) Water Transport. 1005 Hour 1,005.00
P&M-026 Tractor-trolley Pulling, Tranportation,etc. 1877 Hour 1,876.50
P&M-027 Rotavator Scarifying 17 Hour 16.80
P&M-028 Ripper Scarifying 22 Hour 22.05
P&M-029 Air Compressor -250 cfm General Purpose 614 Hour 614.25
P&M-030 Air Compressor -500 cfm General Purpose 2752 Hour 2,752.05
P&M-031 Integrated Stone Crusher Stone (3 Stage) 250 TPH Crushing of Spalls 15481 Hour 15,481.20
P&M-032 Wet Mix Plant - 250 TPH Capacity Wet Mix 922 Hour 921.90
P&M-033 Wet Mix Plant - 200 TPH Capacity Wet Mix 612 Hour 612.15
P&M-034 Wet Mix Plant - 100 TPH Capacity Wet Mix 586 Hour 585.90
P&M-035 Hotmix Plant - 200 TPH Capacity DBM / BM / BC / Premix etc. 14635 Hour 14,634.90
P&M-036 Hotmix Plant - 160 TPH Capacity DBM / BM / BC / Premix etc. 10338 Hour 10,338.30
P&M-037 Hotmix Plant - 120 TPH capacity DBM / BM / BC / Premix etc. 8373 Hour 8,372.70
P&M-038 Batching and Mixing Plant - 240 cum Capacity Concrete Mixing 6314 Hour 6,313.65
P&M-039 Batching and Mixing Plant - 120 cum Capacity Concrete Mixing 4104 Hour 4,104.45
P&M-040 Mobile Concrete Batching / Mixing Plant Concrete Mixing 984 Hour 983.85
P&M-041 Concrete Mixer - 0.4/0.28 cum Concrete Mixing 511 Hour 511.35
P&M-042 Concrete Mixer - 1 cum Concrete Mixing 551 Hour 551.25
P&M-043 Generator 725 KVA Generation of Electric Energy 11596 Hour 11,596.20
P&M-044 Generator 500 KVA Generation of Electric Energy 8022 Hour 8,022.00
P&M-045 Generator 400 KVA Generation of Electric Energy 6470 Hour 6,470.10
P&M-046 Generator 250 KVA Generation of Electric Energy 3475 Hour 3,475.00
P&M-047 Generator 125 KVA Generation of Electric Energy 2391 Hour 2,390.85
P&M-048 Generator 100 KVA Generation of Electric Energy 2041 Hour 2,041.20
P&M-049 Generator 62.5 KVA Generation of Electric Energy 1313 Hour 1,312.50
P&M-050 Generator 33 KVA Generation of Electric Energy 754 Hour 753.90
P&M-051 Generator 15 KVA Generation of Electric Energy 425 Hour 425.25
P&M-052 Mechanical Broom Hydraulic Surface Cleaning 500 Hour 500.40
P&M-053 Bitumen Pressure Distributor Applying bitumen tack coat 1729 Hour 1,729.35
P&M-054 Emulsion Pressure Distributor Applying bitumen tack coat 1112 Hour 1,112.00
P&M-055 Bitumen Boiler Oil Fired Bitumen Spraying 743 Hour 743.40
P&M-056 Mastic Cooker Mastic Wearing Coat 1043 Hour 1,042.50
P&M-057 Paver Finisher Mechanical Paving of WMM 1112 Hour 1,112.00
P&M-058 Paver Finisher Hydrostatic with sensor control -240 HP Paving of DBM/BM/BC/ Premix etc. 9234 Hour 9,233.70
P&M-059 Paver Finisher Hydrostatic with sensor control -170 HP Paving of DBM/BM/BC/ Premix etc. 2363 Hour 2,362.50
P&M-060 Paver Finisher Concrete with 300 HP Motor Paving of Concrete Surface 28109 Hour 28,108.50
P&M-061 Paver Finisher Concrete with 241 HP Motor Paving of Concrete Surface 18202 Hour 18,201.75
P&M-062 Paver Finisher Concrete with 118 HP Motor Paving of Concrete Surface 4517 Hour 4,517.10
P&M-063 Texture Curing Machine (TCM) - upto 18 m Texturing of Concrete Surface 4830 Hour 4,830.00
P&M-064 Texture Curing Machine (TCM) - upto 9 m Texturing of Concrete Surface 3807 Hour 3,807.30
P&M-065 Hydraulic Chip Spreader Surface Dressing 2221 Hour 2,220.75
P&M-066 Pot-Hole Repair Machine Repair of pot-holes 1797 Hour 1,796.55
P&M-067 Transit Mixer - 6 Cum Mix to Site Transportation of Concrete 2414 Hour 2,413.95
P&M-068 Concrete Pump Pumping of Concrete 1342 Hour 1,341.90
P&M-069 Boom Placer Pumping of Concrete 4402 Hour 4,401.60
P&M-070 Kerb Casting Machine Kerb Making 1957 Hour 1,957.20
P&M-071 Piling Rig with Bentonite Pump Piling in foundation 19747 Hour 19,747.35
P&M-072 Pneumatic Sinking Plant Sinking Purpose 6921 Hour 6,920.55
P&M-073 Road marking machine Road Marking 1952 Hour 1,951.95
P&M-074 Mobile Slurry Seal Equipment Mixing and laying slurry seat 3998 Hour 3,998.40
P&M-075 Joint Cutting Machine Cutting Purpose 511 Hour 511.35
P&M-076 Bar Bending & Cutting Machine Bar Cutting & Bending 528 Hour 528.15
P&M-077 Needle Vibrator Concrete pouring 590 Hour 590.10
P&M-078 Jack Hammer for air compressor General Purpose 12 Hour 11.55
P&M-079 Plate Compactor Compaction 597 Hour 597.45
P&M-080 Milling Machine with 1 meter Drum Width Milling of bitumen surface 4785 Hour 4,784.85
P&M-081 Milling Machine with 1.2 meter Drum Width Milling of bitumen surface 5592 Hour 5,592.30
P&M-082 Milling Machine With 1.3 meter Drum Width Milling of bitumen surface 8006 Hour 8,006.25
P&M-083 Milling Machine With 2 meter Drum Width Milling of bitumen surface 11983 Hour 11,982.60
P&M-084 Cold in Situ recycling of bitumen's pavement with foam bitumen technology Recycling of bitumen surface 30811 Hour 30,811.20
P&M-085 In situ stabilisation of WMM/GSB/Sub grade Stabilisation of WMM/GSB/Sub grade 26741 Hour 26,741.40
P&M-086 Cement spreader Spreading 8300 Hour 8,300.25
P&M-087 Mobile cold recycling mixing plant Recycling of bitumen surface 22398 Hour 22,397.55
P&M-088 Hot in place recycling Recycling of bitumen surface 108654 Hour 108,654.00
P&M-089 Pre heater unit for hot in place recycling Recycling of bitumen surface 1272 Hour 1,271.55
P&M-090 Single boom Hydraulic Drill Jumbo Drilling Purpose 5420 Hour 5,420.10
P&M-091 Two boom Hydraulic Drill Jumbo Drilling Purpose 8220 Hour 8,220.45
P&M-092 Three boom Hydraulic Drill Jumbo Drilling Purpose 12008 Hour 12,007.80
P&M-093 Hydraulic Rock bolt drill Drilling Purpose 7788 Hour 7,787.85
P&M-094 Rotating Telehandlers General Purpose 1208 Hour 1,207.50
P&M-095 Shotcrete Machine Concreting Purpose 1830 Hour 1,830.15
P&M-096 Grouting machine Grouting Purpose 798 Hour 798.00
P&M-097 Dewatering Pump 10 HP Dewatering 329 Hour 328.65
P&M-098 Concrete cutting machine Concrete cutting Purpose 1251 Hour 1,251.00
P&M-099 Crawler mounted Crane 35 tonne capacity Lifting Purpose 6330 Hour 6,330.45
P&M-100 Crawler mounted Crane 80 tonne capacity Lifting Purpose 6580 Hour 6,580.35
P&M-101 Crawler mounted Crane 100 tonne capacity Lifting Purpose 9978 Hour 9,978.15
P&M-102 Mobile Hydraulic Crane 3 tonne capacity Lifting Purpose 1084 Hour 1,083.60
P&M-103 Mobile Hydraulic Crane 5 tonne capacity Lifting Purpose 1129 Hour 1,128.75
P&M-104 Mobile Hydraulic Crane 10 tonne capacity Lifting Purpose 1240 Hour 1,240.05
P&M-105 Mobile Hydraulic Crane 15 tonne capacity Lifting Purpose 1279 Hour 1,278.90
P&M-106 Mobile Hydraulic Crane 20 tonne capacity Lifting Purpose 1584 Hour 1,584.45
P&M-107 Mobile Hydraulic Crane 35 toone capacity Lifting Purpose 2394 Hour 2,394.00
P&M-108 Concrete Bucket For Purring Concrete 153 Hour 153.30
P&M-109 Prestressing Jack with Pump & Access (400 tonne) Stressing of Steel Wires/Stands 560 Hour 559.65
P&M-110 Boat to carry atleast 20 persons General Purpose 975 hour 975.45
P&M-111 Crane with grab 0.75 cum capacity Lifting Purpose 1094 hour 1,094.10
P&M-112 Epoxy Injection gun - 380 hour 380.10
Induction, deinduction and erection of plant and equipment including all
P&M-113 Well sinking 10074 hour 10,073.70
components and accessories for pneumatic method of well sinking.
P&M-114 Jack for Lifting 40 tonne lifting capacity. Lifting Purpose 378 hour 378.00
P&M-115 Vibrating Pile driving hammer complete with power unit and accessories. Pile driving 18571 hour 18,571.35
Per Tonne
P&M-116 Tipper-18 Cum (Surface Road) excluding OH & CP Transportation of Soil, GSB,WMM, Hotmix etc. 6 6.18
Km.
Per Tonne
P&M-117 Tipper-18 Cum (Unsurfaced Gravelled Road) excluding OH & CP Transportation of Soil, GSB,WMM, Hotmix etc. 7 7.51
Km.
Per Tonne
P&M-118 Tipper-18 Cum (Katcha Track) excluding OH & CP Transportation of Soil, GSB,WMM, Hotmix etc. 14 15.02
Km.
Per Tonne
P&M-119 Tipper -14 Cum (Surface Road) excluding OH & CP Transportation of Soil, GSB,WMM, Hotmix etc. 7 7.01
Km.
Per Tonne
P&M-120 Tipper -14 Cum (Unsurfaced Gravelled Road) excluding OH & CP Transportation of Soil, GSB,WMM, Hotmix etc. 8 8.52
Km.
Per Tonne
P&M-121 Tipper -14 Cum (Katcha Track) excluding OH & CP Transportation of Soil, GSB,WMM, Hotmix etc. 16 17.05
Km.
Per Tonne
P&M-122 Tipper -10 Cum (Surface Road) excluding OH & CP Transportation of Soil, GSB,WMM, Hotmix etc. 8 8.66
Km.
Per Tonne
P&M-123 Tipper -10 Cum (Unsurfaced Gravelled Road) excluding OH & CP Transportation of Soil, GSB,WMM, Hotmix etc. 10 10.53
Km.
Per Tonne
P&M-124 Tipper -10 Cum (Katcha Track) excluding OH & CP Transportation of Soil, GSB,WMM, Hotmix etc. 20 21.06
Km.
Per Tonne
P&M-125 Tipper- 5.5 Cum (Surface Road) excluding OH & CP Transportation of Soil, GSB,WMM, Hotmix etc. 11 11.87
Km.
Per Tonne
P&M-126 Tipper- 5.5 Cum (Unsurfaced Gravelled Road) excluding OH & CP Transportation of Soil, GSB,WMM, Hotmix etc. 14 14.43
Km.
Per Tonne
P&M-127 Tipper- 5.5 Cum (Katcha Track) excluding OH & CP Transportation of Soil, GSB,WMM, Hotmix etc. 27 28.86
Km.
Per Tonne
P&M-128 Transit Mixer - 6 Cum excluding OH & CP Mix to Site Transportation of Concrete 13 13.41
Km.
Loading and unloading of stone boulder / stone aggregates / sand / kanker /
P&M-129 moorum (Using by 18 cum capacity Tipper & 3.1 Cum capacity Loader) - 0 Cum 92.72
excluding OH & CP.
Loading and unloading of stone boulder / stone aggregates / sand / kanker /
P&M-130 moorum (Using by 14 cum capacity Tipper & 2.1 Cum capacity Loader) - 0 Cum 92.81
excluding OH & CP
P&M-131 Loading and unloading of stone boulder / stone aggregates / sand / kanker / - 0 Cum 118.14
P&M-132 moorum (Using
Loading and by 10 cum
unloading capacity
of stone Tipper
boulder & 1.0
/ stone Cum capacity
aggregates / sandLoader)
/ kanker / - 0 Cum 117.36
P&M-133 moorum (Using
Loading and by 5 cumof capacity
Unloading Cement Tipper
or Steel&by
1.0Manual
Cum capacity Loader)
Means and Stacking - 0 tonne 562.10
P&M-134 Centrifugal water pump Water Pumping 329 Hour 329.00
P&M-135 Shredding Machine Shredding of waste Plastic 416 Hour 416.00
P&M-136 Mobile Bridge Inspection Unit (MBIU) For Inspection of Bridge 6887 hour 6,887.00
P&M-137 Network Survey Vehicle (NSV) With SUV For Pavement Inspection/Survey Purpose 6415 hour 6,415.00
P&M-138 Falling weight deflectometer (FWD) Equipment With SUV For Testing Purpose 3128 hour 3,128.00
P&M-139 Retroreflectometer testing equipment with Vehicle With SUV For Testing Retro reflection 1709 hour 1,709.00
P&M-140 Sport utility vehicle (SUV) General Purpose 1221 hour 1,221.00
P&M-141 Automatic Vehicle Counter Classifier (ATCC) System Traffic Counting 74 hour 74.00
P&M-142 Boring Machine hour 5,000.00
(B) Labour
Sl. No. Description of Labour Unit Rate
L-01 Blacksmith (IInd class) day 679.00
L-02 Blacksmith (Ist class)/ Welder/ Plumber/ Electrician day 738.00
L-03 Blaster (Stone cutter) day 511.52
L-04 Carpenter I Class day 738.00
L-05 Chiseller (Head Mazdoor) day 617.00
L-06 Driller (Jumper) day 558.00
L-07 Diver day 738.00
L-08 Fitter day 738.00
L-09 Mali day 511.52
L-10 Mason (IInd class) day 679.00
L-11 Mason (Ist class) day 738.00
L-12 Mate / Supervisor day 617.00
L-13 Mazdoor day 511.52
L-14 Mazdoor/Dresser (Semi Skilled) day 617.00
L-15 Mazdoor/Dresser/Sinker (Skilled) day 565.73
L-16 Medical Officer day 1,077.25
L-17 Operator(grouting) day 738.00
L-18 Painter I class day 679.00
L-19 Para medical personnel day 622.72
L-20 Black smith day 679.00
(C) Materials
Sl. No. Description Unit Rate
M-001 Stone Boulder of size 150 mm and below at Cruser Plant cum 1472.59
M-002 Supply of quarried stone 150 - 200 mm size for Hand Broken at site cum 1472.59
M-003 Boulder with minimum size of 300 mm for Pitching at Site cum 1994.63
M-009 Granular Material or hard murrum for GSB works at Site Cum 1887.12
M-010 Fly ash conforming to IS: 3812 ( Part II & I) atHMP Plant / Batching Plant / Crushing Plant MT 204.70
M-011 Filter media/Filter Material as per Table 300-3 (MoRT&H Specification) at Site Cum 1215.07
M-013 Close graded Granular sub-base Material 37.5 mm to 9.5 mm cum 1837.12
M-014 Close graded Granular sub-base Material 26.5 mm to 9.5 mm cum 1887.12
M-015 Close graded Granular sub-base Material 9.5 mm to 4.75 mm cum 1887.12
M-016 Close graded Granular sub-base Material 9.5 mm to 2.36 mm cum 1887.12
M-017 Close graded Granular sub-base Material 4.75mm to 2.36 mm cum 1937.12
M-018 Close graded Granular sub-base Material 4.75mm to 75 micron mm cum 1887.12
M-019 Close graded Granular sub-base Material 2.36 mm cum 1887.12
M-020 Stone crusher dust finer than 3mm with not more than 10% passing 0.075 sieve. cum 1887.12
M-021 Coarse graded Granular sub-base Material 2.36 mm & below cum 1887.12
M-022 Coarse graded Granular sub-base Material 4.75mm to 75 micron mm cum 1887.12
M-023 Granular sub-base Material 4.75 mm to 2.36 mm cum 1887.12
M-024 Granular sub-base Material 9.5 mm to 4.75 mm cum 1887.12
M-025 Coarse graded Granular sub-base Material 26.5 mm to 4.75 mm cum 1887.12
M-026 Granular sub-base Material 26.5 mm to 9.5 mm cum 1887.12
M-027 Coarse graded Granular sub-base Material 37.5 mm to 9.5 mm cum 1887.12
M-028 Granular sub-base Material 53 mm to 26 .5mm cum 1887.12
M-029 Aggregates below 5.6 mm cum 1887.12
M-030 Aggregates 22.4 mm to 2.36 mm cum 1887.12
M-031 Aggregates 22.4 mm to 5.6 mm cum 1887.12
M-032 Aggregates 45 mm to 2.8 mm cum 1887.12
M-033 Aggregates 45 mm to 22.4 mm cum 1887.12
M-034 Aggregates 53 mm to 2.8 mm cum 1887.12
M-035 Aggregates 53 mm to 22.4 mm cum 1887.12
M-036 Aggregates 63 mm to 2.8 mm cum 1887.12
M-037 Aggregates 63 mm to 45 mm cum 1887.12
M-038 Aggregates 90 mm to 45 mm cum 1887.12
M-039 Aggregates 10 mm to 5 mm cum 1887.12
M-040 Aggregates 11.2 mm to 0.09 mm cum 1887.12
M-041 Aggregates 13.2 mm to 0.09 mm cum 1887.12
M-042 Aggregates 13.2 mm to 5.6 mm cum 1887.12
M-043 Aggregates 13.2 mm to 10 mm cum 1887.12
M-044 Aggregates 20 mm to 10 mm cum 1887.12
M-045 Aggregates 25 mm to 10 mm cum 1887.12
M-046 Aggregates 19 mm to 6 mm cum 1887.12
M-047 Aggregates 37.5 mm to 19 mm cum 1887.12
M-048 Aggregates 37.5 mm to 25 mm cum 1887.12
M-049 Aggregates 6 mm nominal size cum 1887.12
M-050 Aggregates 10 mm nominal size cum 1887.12
M-051 Aggregates 13.2/12.5 mm nominal size cum 1887.12
M-052 Aggregates 20 mm nominal size cum 1887.12
M-053 Aggregates 25 mm nominal size cum 1887.12
M-054 Aggregates 40 mm nominal size cum 1887.12
M-055 Crushing of stone aggregates (GSB Crusher Run) cum 537.12
M-056 AC pipe 100 mm dia metre 59.13
M-057 Acrylic polymer bonding coat litre 236.30
M-058 Alluminium Paint litre 180.70
M-059 Aluminium alloy plate 2mm Thick sqm 8379.04
M-060 Aluminium alloy/galvanised steel tonne 46496.54
Aluminium sheeting fixed with encapsulated lens type reflective sheeting including 2% towards lettering, cost of angle iron, cost of drilling holes,
M-061 sqm 7560.00
nuts, bolts etc.and signs as applicable
M-062 Aluminium studs 100 x 100 mm fitted with lense reflectors nos 169.19
M-063 Barbed wire kg 66.72
M-064 Bearing (Cost of parts) nos 630.00
M-065 Bearing (Cast steel rocker bearing assembly of 250 tonne ) nos 55660.00
Bearing (Elastomeric bearing assembly consisting of 7 internal layers of elastomer bonded to 6 nos. internal reinforcing steel laminates by the cubic cm 0.59
M-066 process of vulcanisation,)
Taking elastomeric bearing of size 500 X 400 X 96mm, Overall nos 12915.00
volume=19200 cubic cm @Rs 0.59/cucm= Rs 11328
M-067 Bearing (Forged steel roller bearing of 250 tonne nos 85008.00
Bearing (Pot type bearing assembly consisting of a metal piston supported by a disc, PTFE pads providing sliding surfaces against stainless steel MT 136.66
mating together with cast steel assemblies/fabricated structural steel assemblies duly painted with all components
Do nos 34165.00
(a) Fixed POT-PTFE Bearing MT 136.66
M-068 (b) Free POT-PTFE Bearing MT 146.43
(c) Guide Slide (L) POT-PTFE Bearing MT 156.19
(d) Guide Slide (T) POT-PTFE Bearing MT 151.31
M-069 Bearing (PTFE sliding plate bearing assembly of 80 tonnes ) nos 34788.00
M-070 Bearing (Supply of sliding plate bearing of 80 tonne) nos 34420.00
M-071 Bentonite kg 4.31
M-072 Binding wire kg 66.72
M-073 Bitumen ( Cationic Emulsion ) tonne 51690.37
M-074 Bitumen (60-70 grade)VG-40 tonne 46556.37
M-075 Bitumen (80-100 grade )VG-40 tonne 48006.37
M-324
(b) Red sqm 515.69
M-324 (C) Yellow sqm 531.88
(ii) M-40 Grade and 80mm thickness (a) White sqm 581.43
(b) Red sqm 596.64
(C) Yellow sqm 615.88
M-325 Kerb-Stone Block- M30 Grade (Size 375mm x 300mm 150 ) each 79.00
M-326 inclusive
Autoclavedof OH & CPConcrete (AAC) Block
Aerated cum 2457.20
M-327 Bitumen grade VG 40 (30/40) packed Ex Fatuha. MT 44020.00
Core tube (drilling bit) No. 2000.00
Core tube (drilling pipe) No. 2000.00
Core tube (Inner rod) No. 2000.00
CHAPTER-2
SITE CLEARANCE
Cutting of trees, excluding removal of stumps and roots of trees
(Cutting of trees, trunks and branches excluding removal of stumps
2.01 (A)
and roots of trees and stacking of serviceable material with all lifts and
up to a lead of 1000 mtrs )
(i) Girth from 300 mm to 600 mm each 523.00 548.00
(ii) Girth from 600 mm to 900 mm each 750.00 796.00
(iii) Girth from 900 mm to 1800 mm each 1,458.00 1,517.00
(iv) Girth above 1800 mm each 2,859.00 3,008.00
Cutting of Trees, including Cutting of Trunks, Branches and Removal
(Removal of stumps, roots, stacking of serviceable material with all
2.01 (B)
lifts and up to a lead of 1000 metres and earth filling in the
depression/pit.)
(i) Girth from 300 mm to 600 mm each 586.00 605.00
(ii) Girth from 600 mm to 900 mm each 784.00 807.00
(iii) Girth from 900 mm to 1800 mm each 942.00 968.00
(iv) Girth above 1800 mm each 1,170.00 1,210.00
2.02 Clearing Grass and Removal of Rubbish hectare 31,850.00 32,440.00
Clearing and Grubbing Road Land .(Clearing and grubbing road land
including uprooting rank vegetation, grass, bushes, shrubs, saplings
and trees girth up to 300 mm, removal of stumps of trees cut earlier
2.03 and disposal of unserviceable materials and stacking of serviceable
material to be used or auctioned up to a lead of 1000 metres including
removal and disposal of top organic soil not exceeding 150 mm in
thickness.)
(i) By Manual Means:-
A In area of light jungle hectare 368,018.00 374,833.00
B In area of thorny jungle hectare 399,868.00 407,273.00
(ii) By Mechanical Meansby by Dozer
A In area of light jungle hectare 169,012.00 173,678.00
B In area of thorny jungle hectare 180,656.00 185,515.00
(iii) By Mechanical Means using by motor Grader
A In area of light jungle hectare 150,498.00 158,032.00
B In area of thorny jungle hectare 157,672.00 166,120.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Removing all type of hume pipes and stacking within a lead of 1000
(ix)
metres including earthwork and dismantling of masonry works.
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
A Up to 600 mm dia metre 1,186.00 1,335.00
B Above 600 mm to 900 mm dia metre 1,447.00 1,573.00
C Above 900 mm metre 1,707.00 1,811.00
CHAPTER-3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Excavation in Soil by Manual Means. (Excavation for roadway in soil
3.01 using manual means including loading in truck for carrying of cut earth cum 397.00 405.00
to embankment site with all lifts and lead upto1000 metres.)
Rate per Cum after adding royalty Rs 33.00/ cum cum 121.00 134.00
3.20 Compacting Original Ground
Compacting original ground supporting subgrade (Loosening of the
ground upto a level of500 mm below the subgrade level, watered,
Case-I cum 123.00 139.00
graded and compacted in layers to meet requirement of table 300-2
for subgrade construction.)
Case-II :Compacting original ground supporting embankment cum 135.00 152.00
Stripping and Storing Top Soil (Stripping, storing of top soil by road
side at 15 m internal and re-application on embankment slopes, cut
3.21 cum 120.00 130.00
slopes and other areas in localities where the available embankment
material is not conducive to plant growth)
Turfing with Sods (Furnishing and laying of the live sods of perennial
turf forming grass on embankment slope, verges or other locations
3.23 sqm 314.00 368.00
shown on the drawing or as directed by the engineer including
preparation of ground, fetching of rods and watering)
CHAPTER-4
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
B By Mechanical Means
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
B By Mechanical Means
Lime Treated Soil for Sub- Base (Providing, laying and spreading soil
on a prepared sub grade, pulverising, mixing the spread soil in place
with rotavator with 3 % slaked lime with minimum content of 70% of
4.05 cum 679.00 718.00
CaO, grading with motor grader and compacting with the road roller at
OMC to achieve at least 98%of the max dry density to form a layer of
sub base.)
Cement Treated Soil Sub Base/ Base (Providing, laying and
spreading soil on a prepared sub grade, pulverising, adding the
designed quantity of cement to the spread soil, mixing in place with
4.06 cum 856.00 898.00
rotavator, grading with the motor grader and compacting with the road
roller at OMC to achieve the desired unconfined compressive strength
and to form a layer of sub-base/base.)
CHAPTER-5
BASES AND SURFACE COURSES (BITUMINOUS)
5.01 Prime coat
A Prime Coat over WMM/WBM
Providing and applying primer coat with bitumen emulsion on
prepared surface of granular Base including clearing of road surface
(i) sqm 42.00 42.00
and spraying primer at the rate of 0.60 kg/sqm using mechanical
means
Providing and applying primer coat with cutback MC 30 bitumen
emulsion on prepared surface of granular Base including clearing of
(ii) sqm 35.00 36.00
road surface and spraying primer at the rate of 0.60 to 0.90 kg/sqm
using mechanical means.
Providing and applying primer coat with SS1 grade bitumen emulsion
on prepared surface of granular Base including clearing of road
(i) sqm 53.00 54.00
surface and spraying primer at the rate of 0.90 to 1.20 kg/sqm using
mechanical means.
Providing and applying primer coat with cutback MC 70 bitumen
emulsion on prepared surface of granular Base including clearing of
(ii) sqm 52.00 53.00
road surface and spraying primer at the rate of 0.90 to 1.20 kg/sqm
using mechanical means.
5.02 Tack coat on Bituminous surfaces
Tack Coat on Bituminous surfaces (Providing and applying tack coat
with bitumen emulsion using emulsion pressure distributor at the rate
(i) sqm 12.00 12.00
of 0.20 to 0.30 kg per sqm on the prepared bituminous surface
cleaned with mechanical broom.)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
B (ii) Using by Dense Graded bituminous Macadam Grading- II cum 9,482.00 9,989.00
C (i) Using by bituminous concrete Grading- I cum 10,366.00 10,863.00
C (ii) Using by bituminous concrete Grading- II cum 10,459.00 10,895.00
5.14 Fog Spray
Providing and applying low viscosity bitumen emulsion for sealing
(i) cracks less than 3 mm wide or incipient fretting or disintegration in an sqm 44.00 44.00
existing bituminous surfacing.
1.In case it is decided by the engineer to blind the fog spray, the
(ii) sqm 20.00 21.00
following may be added
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Bituminous Cold Mix ( Including Gravel Emulsion) (Providing, laying
and rolling of bituminous cold mix on prepared base consisting of a
mixture of unheated mineral aggregate and emulsified or cutback
5.15
bitumen, including mixing in a plant of suitable type and capacity,
transporting, laying, compacting and finishing to specified grades and
levels.)
Using bitumen emulsion and 9.5 mm or 13.2 mm nominal size
(i) cum 14,587.00 14,952.00
aggregate
Using bitumen emulsion and 19 mm or 26.5 mm nominal size
(ii) cum 14,587.00 14,952.00
aggregate
Using cutback bitumen and 9.5 mm or 13.2 mm nominal size
(iii) cum 10,816.00 11,111.00
aggregate
Using cutback bitumen and 19 mm or 26.5 mm nominal size
(iv) cum 10,816.00 11,111.00
aggregate
Sand Asphalt Base Course (Providing, laying and rolling sand-asphalt
base course composed of sand, mineral filler and bituminous binder
on a prepared sub-grade or sub-base to the lines, levels, grades and
5.16 cum 11,051.00 11,348.00
cross sections as per the drawings including mixing in a plant of
suitable type and capacity, transporting, laying, compacting and
finishing.)
5.17 Crack Prevention Courses
CHAPTER-6
CEMENT CONCRETE PAVEMENTS
Dry Lean Cement Concrete Sub- base (Construction of dry lean
cement concrete Sub- base over a prepared sub-grade with coarse
and fine aggregate conforming to IS: 383, the size of coarse
aggregate not exceeding 25 mm, aggregate cement ratio not to
exceed 15:1, aggregate gradation after blending to be as per table
6.01 600-1, cement content not to be less than 150 kg/ cum, optimum cum 5,073.00 5,273.00
moisture content to be determined during trial length construction,
concrete strength not to be less than 10 Mpa at 7 days, mixed in a
batching plant, transported to site, laid with a paver with electronic
sensor, compacting with 8-10 tonnes vibratory roller, finishing and
curing.)
CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
(i) Synthetic Geogrid Ultimate tensile strength- 100 kN/m sqm 411.00 418.00
(ii) Synthetic Geogrid Ultimate tensile strength- 150 kN/m sqm 451.00 459.00
(iii) Synthetic Geogrid Ultimate tensile strength- 200 kN/m sqm 610.00 622.00
(iv) Synthetic Geogrid Ultimate tensile strength- 250 kN/m sqm 670.00 683.00
(v) Synthetic Geogrid Ultimate tensile strength- 300 kN/m sqm 710.00 724.00
(vi) Synthetic Geogrid Ultimate tensile strength- 350 kN/m sqm 790.00 805.00
(vii) Synthetic Geogrid Ultimate tensile strength- 400 kN/m sqm 850.00 866.00
(viii) Synthetic Geogrid Ultimate tensile strength- 500 kN/m sqm 1,010.00 1,029.00
(ix) Synthetic Geogrid Ultimate tensile strength- 600 kN/m sqm 1,110.00 1,131.00
(x) Synthetic Geogrid Ultimate tensile strength- 800 kN/m sqm 1,426.00 1,452.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
(xi) Synthetic Geogrid Ultimate tensile strength- 900 kN/m sqm 1,691.00 1,723.00
(xii) Synthetic Geogrid Ultimate tensile strength- 1000 kN/m sqm 1,909.00 1,945.00
(xiii) Synthetic Geogrid Ultimate tensile strength- 1100 kN/m sqm 2,009.00 2,046.00
(xiv) Synthetic Geogrid Ultimate tensile strength- 1200 kN/m sqm 2,185.00 2,225.00
Supplying & laying of drainage composite for use behind walls with
7.16
Geosynthetic drainage composite
Direction and Place Identification signs with size more than 0.9 sqm
size board. (Providing and erecting direction and place identification
retro- reflectorised sign asper IRC :67 made of encapsulated lens
type reflective sheeting vide clause 801.3, fixed over aluminium
8.06 sheeting, 2 mm thick with area exceeding 0.9 sqm supported on a sqm 13,806.00 14,069.00
mild steel angle iron post 75 mm x 75 mm x 6 mm, 2 Nos. firmly fixed
to the ground by means of properly designed foundation with M 15
grade cement concrete45 cm x 45 cm x 60 cm, 60 cm below ground
level as per approved drawing)
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
G.I Barbed wire Fencing 1.2 metre high (Providing and fixing 1.2
metres high GI barbed wire fencing with 1.8 m angle iron posts 40
mm x 40 mm x 6 mm placed every 3 metres center to center founded
in M15 grade cement concrete, 0.6 metre below ground level, every
8.17 metre 349.00 355.00
15th post, last but one end post and corner post shall be strutted on
both sides and end post on one side only and provided with 9
horizontal lines and 2 diagonals interwoven with horizontal wires,
fixed with GI staples, turn buckles etc complete as per clause 808 )
G.I Barbed wire Fencing 1.8 metre high (Providing and fixing 1.8
metres high GI barbed wire fencing with 2.4 m angle iron posts 50
mm x 50 mm x 6 mm placed every 3 metres center to center founded
in M15 grade cement concrete, 0.6 metre below ground level, every
8.18 metre 577.00 588.00
15th post, last but one end post and corner post shall be strutted on
both sides and end post on one side only and provided with 12
horizontal lines and 2 diagonals interwoven with horizontal wires,
fixed with GI staples, turn buckles etc complete as per clause 808 )
(i) Single Row for one utility service metre 3,754.00 3,824.00
(ii) Double Row for two utility services metre 7,362.00 7,637.00
(iii) Triple Row for three utility services metre 11,269.00 11,478.00
Highway Patrolling and Traffic Aid Post (It is proposed to locate one
8.30
Traffic Aid Post every 50-60 km of the highway. )
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
CHAPTER-9
CULVERTS & BOX CELL
I Ordinary soil
A Manual Means
(i) upto 3 m depth cum 223.00 227.00
(ii) 3 m to 6 m depth cum 287.00 292.00
(iii) Above 6 m depth cum 382.00 389.00
B Mechanical Means
(i) Depth upto 3 m cum 111.00 117.00
(ii) Depth 3 m to 6 m cum 123.00 129.00
(iii) Depth above 6m cum 137.00 144.00
II Ordinary rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m cum 319.00 324.00
B Mechanical Means cum 681.00 732.00
III Hard rock ( requiring blasting )
A Manual Means cum 703.00 716.00
B Mechanical Means cum 344.00 352.00
IV Hard rock ( blasting prohibited )
A Mechanical Means cum 913.00 1,033.00
V Marshy soil
(i) upto 3 m depth
A Manual means cum 1,232.00 1,255.00
B Mechanical Means cum 417.00 433.00
Sand Filling in Foundation Trenches as per Drawing & Technical
9.02 cum 2,922.00 2,989.00
Specification
CHAPTER-10
MAINTENANCE OF ROADS
Filling Pot- holes and Patch Repairs with open - graded Premix
surfacing, 20mm. (Removal of all failed material, trimming of
completed excavation to provide firm vertical faces, cleaning of
10.04 surface, painting of tack coat on the sides and base of excavation as sqm 182.00 186.00
per clause 503, back filling the pot holes with hot bituminous material
as per clause 510, compacting, trimming and finishing the surface to
form a smooth continuous surface, all as per clause 3004.2)
(ii) Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm sqm 87.00 88.00
Stress Absorbing Membrane (SAM) crack width above 9 mm and
(iii) sqm 113.00 116.00
cracked area above 50 %
(iv) Bitumen Impregnated Geotextile sqm 146.00 148.00
C Slurry Seal (ref item 5.12)
(i) 5 mm thickness sqm 87.00 89.00
(ii) 3 mm thickness sqm 54.00 55.00
(iii) 1.5 mm thickness sqm 54.00 55.00
D Surface Dressing for maintance works. (ref item 5.06)
(i) 19 mm nominal chipping size sqm 116.00 118.00
(ii) 13 mm nominal size chipping sqm 90.00 92.00
11.06 Maintenance of Lawns with Fine Grassing for the First Year sqm 314.00 320.00
11.13 Supplying Sludge (Supplying sludge duly stacked at site/ store) cum 356.00 363.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Half Brick Circular Tree Guard, in 2nd class Brick, internal diametre
1.25 metres, and height 1.2 metres, above ground and 0.20 metre
below ground (Half brick circular tree guard, in 2nd class brick,
internal diametre 1.25 metres, and height 1.2 metres, above ground
11.14 each 1,478.00 1,506.00
and 0.20 metre below ground, bottom two courses laid dry, and top
three courses in cement mortar 1:6 ( 1 cement 6 sand) and the
intermediate courses being in dry honey comb masonry, as per
design complete)
Edging with 2nd class Bricks, laid dry lengthwise (Edging with 2nd
class bricks, laid dry lengthwise, including excavation, refilling,
11.15 metre 29.00 29.00
consolidation, with a hand packing and spreading nearly surplus
earth within a lead of 50 metres)
Making Tree Guard 53 cm dia and 1.3 m high as per design from
empty bitumen drum (Making tree guard 53 cm dia and 1.3 m high as
per design from empty bitumen drum, slit suitably to permit sun and
11.16 each 686.00 699.00
air, (supplied by the department at stock issue rate) including
providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with rivets,
complete in all respect)
Making Tree Guard 53 cm dia and 2 metres high as per design from
empty bitumen drums (Making tree guard 53 cm dia and 2 metres
high as per design from empty bitumen drums, slit suitably to permit
11.17 sun and air, ( supplied by the department at stock issue rate) each 1,262.00 1,285.00
including providing and fixing four legs 40 cm long of 30 x 3 mm MS
riveted to tree guard and providing and fixing 2 nos MS sheet rings 50
x 0.5 mm with rivets complete in all respects)
Wrought Iron and Mild Steel Welded Work (Wrought iron and mild
steel welded work) (using angles, square bars, tees and channel
grills, grating frames, gates and tree guards of any size and design
11.18 quintal 11,635.00 11,851.00
etc. including cost of screens and welding rods or bolts and nuts
complete fixed in position but without the cost of excavation and
concrete for fixing which will be paid separately)
Tree Guard with MS Iron (Providing and fixing MS iron tree guard 60
cm dia and 2 metre high above ground level formed of 4 Nos (25 x 6
mm) and 8 Nos (25 x 3 mm) vertical MS riveted to 3 Nos (25 x 6 mm) each tree
11.19 2,932.00 2,987.00
iron rings in two halves, bolted together with 8 mm dia and 30 mm guard
long bolts including painting two coats with paint of approved brand
over a coat of priming, complete in all respects.)
Tree Guard with MS Angle Iron and Steel Wire (Providing and fixing
tree guard 0.60 metre square, 2.00 metre high fabricated with MS each tree
11.20 3,847.00 3,919.00
angle iron 30 x 30 x 3 mm, MS iron 25 x 3 mm and steel wire3 mm guard
dia welded and fabricated as per design in two halves bolted together)
CHAPTER-12
FOUNDATIONS
I Ordinary soil
A Manual Means
(i) upto 3 m depth cum 248.00 248.00
(ii) 3 m to 6 m depth cum 319.00 319.00
(iii) Above 6 m depth cum 425.00 425.00
B Mechanical Means
(i) Depth upto 3 m cum 123.00 128.00
(ii) Depth 3 m to 6 m cum 136.00 141.00
(iii) Depth above 6m cum 152.00 158.00
II Ordinary rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m cum 354.00 354.00
B Mechanical Means cum 757.00 798.00
III Hard rock ( requiring blasting )
A Manual Means cum 380.00 389.00
IV Hard rock ( blasting prohibited )
A Mechanical Means cum 1,015.00 1,043.00
V Marshy soil
(i) upto 3 m depth
A Manual means cum 1,369.00 1,369.00
B Mechanical Means cum 463.00 472.00
VI Back Filling in Marshy Foundation Pits cum 1,180.00 1,180.00
Filling Annular Space Around Footing in Rock (Lean cement concrete
12.02 cum 6,152.00 6,170.00
1:3:6 nominal mix. Rate may be taken as per items 12.4.)
Sand Filling in Foundation Trenches as per Drawing & Technical
12.03 cum 3,259.00 3,275.00
Specification
A Assuming depth of water 1.0 m and height of island to be 1.25m. each 319,415.00 319,415.00
B Assuming depth of water 4.0 m and height of island 4.5 m. each 1,091,423.00 1,091,423.00
Providing and constructing one span service road to reach island
C metre 4,599.00 4,599.00
location from one pier location to another pier location
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 5,651.00 5,651.00
(ii) Beyond 3m upto 10m depth metre 7,858.00 7,858.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
(iii) Beyond 10m upto 20m
a Add for every additional meter depth of sinking metre 10,379.00 10,379.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 19,471.00 19,471.00
Add 20% of cost for Kentledge including supports, loading
b metre 3,894.00 3,894.00
arrangement and Labour .
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 46,262.00 46,262.00
Add 20% of cost for Kentledge including supports, loading
b metre 9,253.00 9,253.00
arrangement and Labour .
B Clayey soil ( 6m dia. Well )
(i) Depth below bed level upto 3.0 M metre 7,841.00 7,841.00
(ii) Beyond 3m upto 10m depth metre 17,499.00 17,499.00
(iii) Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of
a metre 23,112.00 23,112.00
sinking for the previous meter
b Add for dewatering @ 5% of cost, if required. metre 1,156.00 1,156.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 43,352.00 43,352.00
b Add 5% of cost for dewatering of the cost, if required metre 2,168.00 2,168.00
Add 25% of cost for Kentledge including supports, loading
c metre 10,838.00 10,838.00
arrangement and Labour ).
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 102,998.00 102,998.00
b Add 5% of cost for dewatering, if required metre 5,150.00 5,150.00
Add 20% of cost for Kentledge including supports, loading
c metre 20,600.00 20,600.00
arrangement and Labour).
C Soft rock (6m dia well )
Extra over item no. 12.12 (A) & (B) irrespective of depth for sinking in
(i) metre 43,682.00 43,682.00
Soft Rock
D Hard rock (6m dia well )
Extra over item no. 12.12 (A) & (B) irrespective of depth for sinking in
(i) metre 44,573.00 44,573.00
Soft Rock
E Bouldery strata(6m dia well )
Extra over item no. 12.12 (A) & (B) irrespective of depth for sinking in
(i) metre 32,480.00 32,480.00
rock bouldery strata
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 16,510.00 16,510.00
(ii) Beyond 3m upto 10m depth metre 10,859.00 10,859.00
(iii) Beyond 10m upto 20m metre 14,342.00 14,342.00
a Add for every additional meter depth of sinking metre 717.00 717.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 26,902.00 26,902.00
Add 20% of cost for Kentledge including supports, loading
b metre 5,381.00 5,381.00
arrangement and Labour) .
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 63,918.00 63,918.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Add 20% of cost for Kentledge including supports, loading
b metre 12,784.00 12,784.00
arrangement, and Labour etc.
B Clayey soil ( 7m dia. Well )
(I) Depth below bed level upto 3.0 M metre 10,859.00 10,859.00
(ii) Beyond 3m upto 10m depth metre 17,448.00 17,448.00
(iii) Beyond 10 m upto 20 m
a Add for every additional meter depth of sinking metre 23,043.00 23,043.00
b Add for dewatering @ 5% of cost, if required. metre 1,152.00 1,152.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 43,222.00 43,222.00
b Add 5% of cost for dewatering on the cost, if required metre 2,161.00 2,161.00
Add 25% of cost for Kentledge including supports, loading
c metre 10,806.00 10,806.00
arrangement and Labour ).
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 102,691.00 102,691.00
b Add 5% of cost for dewatering, if required metre 5,135.00 5,135.00
Add 20% of cost for Kentledge including supports, loading
c metre 20,538.00 20,538.00
arrangement and Labour).
C Soft rock (7 m dia well )
Extra over item no. 12.13 (A) & (B) irrespective of depth for sinking in
(i) metre 55,683.00 55,683.00
Soft Rock
D Hard rock (7 m dia well )
Extra over item no. 12.13(A) & (B) irrespective of depth for sinking in
(i) metre 57,401.00 57,401.00
Soft Rock
E Bouldery strata(7 m dia well )
Extra over item no. 12.13 (A) & (B) irrespective of depth for sinking in
(i) metre 80,118.00 80,118.00
rock bouldery strata
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 10,065.00 10,065.00
(ii) Beyond 3m upto 10m depth metre 12,272.00 12,272.00
(iii) Beyond 10m upto 20m
a Add for every additional meter depth of sinking metre 16,206.00 16,206.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 30,395.00 30,395.00
Add 20% of cost for Kentledge including supports, loading
b metre 6,079.00 6,079.00
arrangement and Labour .
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 72,214.00 72,214.00
Add 20% of cost for Kentledge including supports, loading
b metre 14,443.00 14,443.00
arrangement, and Labour etc.
B Clayey soil ( 8m dia. Well )
(i) Depth upto 3.0 M metre 13,261.00 13,261.00
(ii) Beyond 3m upto 10m depth metre 18,472.00 18,472.00
(iii) Beyond 10 m upto 20 m
a Add for every additional meter depth of sinking metre 24,397.00 24,397.00
b Add for dewatering @ 5% of cost, if required. metre 1,220.00 1,220.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 45,763.00 45,763.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
b Add 5% of cost for dewatering on the cost, if required metre 2,288.00 2,288.00
Add 25% of cost for Kentledge including supports, loading
c metre 11,441.00 11,441.00
arrangement and Labour ).
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 108,726.00 108,726.00
b Add 5% of cost for dewatering, if required metre 5,436.00 5,436.00
Add 20% of cost for Kentledge including supports, loading
c metre 21,745.00 21,745.00
arrangement and Labour).
C Soft rock (8 m dia well )
Extra over item no. 12.14 (A) & (B) irrespective of depth for sinking in
(i) metre 69,278.00 69,278.00
Soft Rock
D Hard rock (8 m dia well )
Extra over item no. 12.14 (A) & (B) irrespective of depth for sinking in
(i) metre 73,385.00 73,385.00
Soft Rock
E Bouldery strata(8 m dia well )
Extra over item no. 12.14 (A) & (B) irrespective of depth for sinking in
(i) metre 101,693.00 101,693.00
rock bouldery strata
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 10,276.00 10,276.00
(ii) Beyond 3m upto 10m depth metre 13,489.00 13,489.00
(iii) Beyond 10m upto 20m
a Add for every additional meter depth of sinking metre 17,816.00 17,816.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 33,419.00 33,419.00
Add 20% of cost for Kentledge including supports, loading
b metre 6,684.00 6,684.00
arrangement and Labour .
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 79,397.00 79,397.00
Add 20% of cost for Kentledge including supports, loading
b metre 15,880.00 15,880.00
arrangement, and Labour etc.
B Clayey soil ( 9m dia. Well )
(i) Depth below bed level upto 3.0 M metre 14,064.00 14,064.00
(ii) Beyond 3m upto 10m depth metre 19,917.00 19,917.00
(iii) Beyond 10 m upto 20 m
a Add for every additional meter depth of sinking metre 26,305.00 26,305.00
b Add for dewatering @ 5% of cost, if required. metre 1,315.00 1,315.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 49,341.00 49,341.00
b Add 5% of cost for dewatering on the cost, if required metre 2,467.00 2,467.00
Add 25% of cost for Kentledge including supports, loading
c metre 12,335.00 12,335.00
arrangement and Labour ).
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 117,228.00 117,228.00
b Add 5% of cost for dewatering, if required metre 5,862.00 5,862.00
Add 20% of cost for Kentledge including supports, loading
c metre 23,445.00 23,445.00
arrangement and Labour).
C Soft rock (9 m dia well )
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Extra over item no. 12.15 (A) & (B) irrespective of depth for sinking in
(i) metre 84,470.00 84,470.00
Soft Rock
D Hard rock (9 m dia well )
Extra over item no. 12.15(A) & (B) irrespective of depth for sinking in
(i) metre 76,144.00 76,144.00
Soft Rock
E Bouldery strata (9 m dia well )
Extra over item no. 12.15 (A) & (B) irrespective of depth for sinking in
(i) metre 125,927.00 125,927.00
rock bouldery strata
A Sandy soil
(i) Depth below bed level upto 3.0 M metre 12,077.00 12,077.00
(ii) Beyond 3m upto 10m depth metre 14,293.00 14,293.00
(iii) Beyond 10m upto 20m
a Add for every additional meter depth of sinking metre 18,877.00 18,877.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 35,408.00 35,408.00
Add 20% of cost for Kentledge including supports, loading
b metre 7,082.00 7,082.00
arrangement and Labour .
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 84,126.00 84,126.00
Add 20% of cost for Kentledge including supports, loading
b metre 16,825.00 16,825.00
arrangement, and Labour etc.
B Clayey soil (10m dia. Well )
(i) Depth below bed level upto 3.0 M metre 16,139.00 16,139.00
(ii) Beyond 3m upto 10m depth metre 20,163.00 20,163.00
(iii) Beyond 10 m upto 20 m
a Add for every additional meter depth of sinking metre 26,630.00 26,630.00
b Add for dewatering @ 5% of cost, if required. metre 1,332.00 1,332.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 49,951.00 49,951.00
'b Add 5% of cost for dewatering on the cost, if required metre 2,498.00 2,498.00
Add 25% of cost for Kentledge including supports, loading
c metre 12,488.00 12,488.00
arrangement and Labour ).
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 118,675.00 118,675.00
b Add 5% of cost for dewatering, if required metre 5,934.00 5,934.00
Add 20% of cost for Kentledge including supports, loading
c 23,735.00 23,735.00
arrangement and Labour).
C Soft rock (10 m dia well )
Extra over item no. 12.16 (A) & (B) irrespective of depth for sinking in
(i) metre 101,257.00 101,257.00
Soft Rock
D Hard rock (10 m dia well )
Extra over item no. 12.16 (A) & (B) irrespective of depth for sinking in
(i) metre 96,900.00 96,900.00
Soft Rock
E Bouldery strata (10 m dia well )
Extra over item no. 12.16 (A) & (B) irrespective of depth for sinking in
(i) metre 152,820.00 152,820.00
rock bouldery strata
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
A Sandy soil
(i) Depth from bed level upto 3.0 M metre 26,992.00 26,992.00
(ii) Beyond 3m upto 10m depth metre 23,450.00 23,450.00
(iii) Beyond 10m upto 20m
a Add for every additional meter depth of sinking metre 30,969.00 30,969.00
(iv) Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of
a metre 58,091.00 58,091.00
sinking for the previous meter
Add 20% of cost for Kentledge including supports, loading
b metre 11,618.00 11,618.00
arrangement and Labour .
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 138,015.00 138,015.00
Add 20% of cost for Kentledge including supports, loading
b metre 27,603.00 27,603.00
arrangement, and Labour etc.
B Clayey soil (11 m dia. Well )
(i) Depth from bed level upto 3.0 M metre 26,559.00 26,559.00
(ii) Beyond 3m upto 10m depth metre 41,983.00 41,983.00
(iii) Beyond 10 m upto 20 m
a Add for every additional meter depth of sinking metre 55,446.00 55,446.00
b Add for dewatering @ 5% of cost, if required. metre 2,772.00 2,772.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 104,002.00 104,002.00
b Add 5% of cost for dewatering on the cost, if required metre 5,200.00 5,200.00
Add 25% of cost for Kentledge including supports, loading
c metre 26,001.00 26,001.00
arrangement and Labour ).
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 247,093.00 247,093.00
b Add 5% of cost for dewatering, if required metre 12,355.00 12,355.00
Add 20% of cost for Kentledge including supports, loading
c metre 49,419.00 49,419.00
arrangement and Labour).
C Soft rock (11 m dia well )
Extra over item no. 12.17(A) & (B) irrespective of depth for sinking in
(i) metre 119,640.00 119,640.00
Soft Rock
D Hard rock (11 m dia well )
Extra over item no. 12.17 (A) & (B) irrespective of depth for sinking in
(i) metre 112,786.00 112,786.00
Soft Rock
E Bouldery strata (11 m dia well )
Extra over item no. 12.17 (A) & (B) irrespective of depth for sinking in
(i) metre 182,373.00 182,373.00
rock bouldery strata
A Sandy soil
(i) I) Depth below bed level upto 3.0 M metre 57,135.00 57,135.00
(ii) Beyond 3m upto 10m depth metre 65,191.00 65,191.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
(iii) Beyond 10m upto 20m
a Add for every additional meter depth of sinking metre 86,097.00 86,097.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 161,496.00 161,496.00
Add 20% of cost for Kentledge including supports, loading
b metre 32,299.00 32,299.00
arrangement and Labour .
(v) Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of
a metre 383,691.00 383,691.00
sinking for the previous meter
Add 20% of cost for Kentledge including supports, loading
b metre 76,738.00 76,738.00
arrangement, and Labour etc.
B Clayey soil (12 m dia. Well )
(i) Depth below bed level upto 3.0 M metre 64,314.00 64,314.00
(ii) Beyond 3m upto 10m depth metre 101,308.00 101,308.00
(iii) Beyond 10 m upto 20 m
a Add for every additional meter depth of sinking metre 133,796.00 133,796.00
b Add for dewatering @ 5% of cost, if required. metre 6,690.00 6,690.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 250,967.00 250,967.00
b Add 5% of cost for dewatering on the cost, if required metre 12,548.00 12,548.00
Add 25% of cost for Kentledge including supports, loading
c metre 62,742.00 62,742.00
arrangement and Labour ).
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 596,260.00 596,260.00
b Add 5% of cost for dewatering, if required metre 29,813.00 29,813.00
Add 20% of cost for Kentledge including supports, loading
c metre 119,252.00 119,252.00
arrangement and Labour).
C Soft rock (12 m dia well )
Extra over item no. 12.18 (A) & (B) irrespective of depth for sinking in
(i) metre 139,619.00 139,619.00
Soft Rock
D Hard rock (12 m dia well )
Extra over item no. 12.18 (A) & (B) irrespective of depth for sinking in
(i) metre 130,048.00 130,048.00
Soft Rock
E Bouldery strata (12 m dia well )
Extra over item no. 12.18 (A) & (B) irrespective of depth for sinking in
(i) metre 214,586.00 214,586.00
rock bouldery strata
A Sandy soil
(i) Depth from bed level upto 3.0 M metre 12,888.00 12,888.00
(ii) Beyond 3m upto 10m depth metre 13,898.00 13,898.00
(iii) Beyond 10m upto 20m
a Add for every additional meter depth of sinking metre 18,355.00 18,355.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 34,429.00 34,429.00
Add 20% of cost for Kentledge including supports, loading
b metre 6,886.00 6,886.00
arrangement and Labour .
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 81,797.00 81,797.00
Add 20% of cost for Kentledge including supports, loading
b metre 16,359.00 16,359.00
arrangement, and Labour etc.
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
B Clayey soil (Twin D Type Well )
(i) Depth below bed level upto 3.0 M metre 15,265.00 15,265.00
(ii) Beyond 3m upto 10m depth metre 22,365.00 22,365.00
(iii) Beyond 10 m upto 20 m
a Add for every additional meter depth of sinking metre 29,538.00 29,538.00
b Add for dewatering @ 5% of cost, if required. metre 1,477.00 1,477.00
(iv) Beyond 20m upto 30 m
a Add for every additional meter depth of sinking metre 55,406.00 55,406.00
b Add 5% of cost for dewatering on the cost, if required metre 2,770.00 2,770.00
Add 25% of cost for Kentledge including supports, loading
c metre 13,852.00 13,852.00
arrangement and Labour ).
(v) Beyond 30m upto 40 m
a Add for every additional meter depth of sinking metre 131,638.00 131,638.00
b Add 5% of cost for dewatering, if required metre 6,582.00 6,582.00
Add 20% of cost for Kentledge including supports, loading
c metre 26,328.00 26,328.00
arrangement and Labour).
C Soft rock (Twin D Type well )
Extra over item no. 12.19 (A) & (B) irrespective of depth for sinking in
(i) metre 85,138.00 85,138.00
Soft Rock
D Hard rock (Twin D Type well )
Extra over item no. 12.19(A) & (B) irrespective of depth for sinking in
(i) metre 83,722.00 83,722.00
Soft Rock
E Bouldery strata (Twin D Type well )
Extra over item no. 12.19 (A) & (B) irrespective of depth for sinking in
(i) metre 61,745.00 61,745.00
rock bouldery strata
Back filling behind abutment, wing wall and return wall complete as
13.09
per drawing and Technical specification
A Granular material cum 3,688.00 3,688.00
B Sandy material cum 3,146.00 3,146.00
Supplying, fitting and fixing in position true to line and level cast steel
rocker bearing conforming to IRC: 83(Pt.-1) section IX and clause tonne
13.13 301.00 301.00
2003 of MoRTH specifications complete including all accessories as capacity
per drawing and Technical Specifications.
Supplying, fitting and fixing in position true to line and level forged
steel roller bearing conforming to IRC: 83(Pt.-1) section IX and clause tonne
13.14 458.00 458.00
2003 of MoRTH specifications complete including all accessories as capacity
per drawing and Technical Specifications.
Supplying, fitting and fixing in position true to line and level sliding
plate bearing with PTFE surface sliding on stainless steel complete
tonne
13.15 including all accessories as per drawing and Technical Specifications 593.00 593.00
capacity
and BS: 5400, section 9.1 & 9.2 (for PTFE) and clause 2004 of
MoRTH Specifications.
Supplying, fitting and fixing in position true to line and level sliding
plate bearing with stainless steel plate sliding on stainless steel plate tonne
13.17 584.00 584.00
with mild steel matrix complete including all accessories as per capacity
drawing and Technical Specifications.
Supplying, fitting and fixing in position true to line and level POT-
PTFE bearing consisting of a metal piston supported by a disc or
unreinforced elastomer confined within a metal cylinder, sealing
rings, dust seals, PTFE surface sliding against stainless steel mating
tonne
13.18 surface, completre assembly to be of cast steel/fabricated structural 188.00 188.00
capacity
steel, metal and elastomer elements to be as per IRC: 83 part-I & II
respectively and other parts conforming to BS: 5400, section 9.1 &
9.2 and clause 2006 of MoRTH Specifications complete asper
drawing and approved technical specifications.
13.19 Protection to substructure by using coal tar epoxy sqm 342.00 342.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Providing structural steel for sub-structure complete as per drawing
13.20 tonne 166,698.00 166,698.00
and technical specifications
CHAPTER-14
SUPER-STRUCTURE
Furnishing and Placing Reinforced/Prestressed cement concrete in
14.01
super-structure as per drawing and Technical Specification
A RCC Grade M20
Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 9,370.00 9,426.00
(q) Height 5m to 10m cum 9,761.00 9,818.00
(r) Height above 10m cum 10,151.00 10,211.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 9,761.00 9,818.00
(q) Height 5m to 10m cum 10,151.00 10,211.00
(r) Height above 10m cum 10,542.00 10,604.00
B RCC Grade M25
Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 10,023.00 10,078.00
(q) Height 5m to 10m cum 10,441.00 10,498.00
(r) Height above 10m cum 10,858.00 10,918.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 10,441.00 10,498.00
(q) Height 5m to 10m cum 10,858.00 10,918.00
(r) Height above 10m cum 11,276.00 11,338.00
C RCC Grade M 30
Using Batching Plant, Transit Mixer and Concrete Pump.
(i) For solid slab super-structure, 20-30% of (a+b+c)
(p) Height upto 5m cum 10,161.00 10,216.00
(q) Height 5m to 10m cum 10,584.00 10,642.00
(r) Height above 10m cum 11,007.00 11,067.00
(ii) For T-beam & slab, 25-35% of (a+b+c)
(p) Height upto 5m cum 10,584.00 10,642.00
(q) Height 5m to 10m cum 11,007.00 11,067.00
(r) Height above 10m cum 11,431.00 11,493.00
D RCC/PSC Grade M35
Using Batching Plant, Transit Mixer and Concrete Pump
(i) For solid slab super-structure, 18-28% of (a+b+c)
(p) Height upto 5m cum 10,231.00 10,286.00
(q) Height 5m to 10m cum 10,665.00 10,722.00
(r) Height above 10m cum 11,098.00 11,157.00
(ii) For T-beam & slab, 23-33% of (a+b+c)
(p) Height upto 5m cum 10,665.00 10,722.00
(q) Height 5m to 10m cum 11,098.00 11,157.00
(r) Height above 10m cum 11,532.00 11,593.00
(iii) For box girder and balanced cantilever, 38-58% of cost of concrete.
(p) Height upto 5m cum 11,965.00 12,029.00
(q) Height 5m to 10m cum 12,832.00 12,901.00
(r) Height above 10m cum 13,700.00 13,772.00
E RCC/PSC Grade M-40
Using Batching Plant, Transit Mixer and Concrete Pump
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
(i) For solid slab super-structure, 18-28% of (a+b+c)
(p) Height upto 5m cum 10,750.00 10,804.00
(q) Height 5m to 10m cum 11,205.00 11,262.00
(r) Height above 10m cum 11,661.00 11,720.00
(ii) For T-beam & slab, 23-33% of (a+b+c)
(p) Height upto 5m cum 11,205.00 11,262.00
(q) Height 5m to 10m cum 11,661.00 11,720.00
(r) Height above 10m cum 12,116.00 12,178.00
(iii) For box girder and balanced cantilever, 38-58% of cost of concrete.
(p) Height upto 5m cum 12,572.00 12,636.00
(q) Height 5m to 10m cum 13,483.00 13,551.00
(r) Height above 10m cum 14,394.00 14,467.00
F RCC/PSC Grade M-45
For solid slab/voided slab super-structure, 16-26% of cost of
(i)
concrete (a+b+c)
(p) Height upto 5m cum 10,788.00 10,842.00
(q) Height 5m to 10m cum 11,253.00 11,309.00
(r) Height above 10m cum 11,718.00 11,776.00
For I-beam & slab including launching of precast girders by launching
(ii)
truss upto 40 m span, 21-31% of cost of concrete.
(p) Height upto 5m cum 11,253.00 11,309.00
(q) Height 5m to 10m cum 11,718.00 11,776.00
(r) Height above 10m cum 12,183.00 12,244.00
For cast-in-situ box girder, segmental construction and balanced
(iii)
cantilever, 36-56% of cost of concrete.
(p) Height upto 5m cum 12,648.00 12,711.00
(q) Height 5m to 10m cum 13,578.00 13,646.00
(r) Height above 10m cum 14,508.00 14,580.00
G PSC Grade M-50
For cast-in-situ box girder, segmental construction and balanced
(i)
cantilever, 35-55% of cost of concrete
(p) Height upto 5m cum 13,587.00 13,649.00
(q) Height 5m to 10m cum 14,594.00 14,660.00
(r) Height above 10m cum 15,600.00 15,671.00
H PSC Grade M- 55
For cast-in-situ box girder, segmental construction and balanced
(i)
cantilever, 35-55% of cost of concrete
(p) Height upto 5m cum 13,728.00 13,790.00
(q) Height 5m to 10m cum 14,745.00 14,812.00
(r) Height above 10m cum 15,762.00 15,833.00
I PSC Grade M- 60
For cast-in-situ box girder, segmental construction and balanced
(i)
cantilever, 35-55% of cost of concrete
(p) Height upto 5m cum 14,066.00 14,129.00
(q) Height 5m to 10m cum 15,108.00 15,175.00
(r) Height above 10m cum 16,150.00 16,222.00
J PSC Grade M- 65
For cast-in-situ box girder, segmental construction and balanced
(i)
cantilever, 35-55% of cost of concrete
(p) Height upto 5m cum 14,140.00 14,202.00
(q) Height 5m to 10m cum 15,187.00 15,254.00
(r) Height above 10m cum 16,234.00 16,306.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
Providing, fitting and fixing mild steel railing complete as per drawing
14.08 metre 4,246.00 4,246.00
and Technical Specification
14.09 Drainage Spouts complete as per drawing and Technical specification each 4,779.00 4,779.00
PCC M15 Grade leveling course below approach slab complete as
14.10 cum
per drawing and Technical specification
(i) PCC Grade M15 with Batching Plant and Concrete Pump cum 7,384.00 7,432.00
(ii) PCC Grade M15 with Batching Plant and Manual placing cum 7,760.00 7,806.00
Reinforced cement concrete approach slab including reinforcement
14.11 cum 12,146.00 11,625.00
and formwork complete as per drawing and Technical specification
Crash Barriers (The rate analysis for rigid crash barrier in reinforced
cement concrete, semi-rigid crash barrier with metal beam and
14.15
flexible crash barrier with wire ropes have been made and included in
chapter-8 on Traffic and Transportation.)
Painting on concrete surface (Providing and applying 2 coats of water
based cement paint to unplastered concrete surface after cleaning the
14.16 Sqm 107.00 107.00
surface of dirt, dust, oil, grease, efflorescence and applying paint @
of 1 litre for 2 Sq.m. )
14.17 Filler joint
Providing & fixing 2 mm thick corrugated copper plate in expansion
(i) metre 2,417.00 2,417.00
joint complete as per drawing & Technical Specification.
Modular Strip / Box Seal Joint (Providing and laying of a modular strip
Box steel expansion joint including anchorage catering to a horizontal
movement beyond 70 mm and upto 140mm, complete as per
14.22 metre 11,173.00 11,173.00
approved drawings and standard specifications to be installed by the
manufacturer/supplier or their authorised representative ensuring
compliance to the manufacturer's instructions for installation.)
Modular Strip / Box Seal Joint (Providing and laying of a modular strip
box seal expansion joint catering to a horizontal movement beyond
140mm and upto 210mm, complete as per approved drawings and
14.23 metre 11,194.00 11,194.00
standard specifications to be installed by the manufacturer/supplier or
their authorised representative ensuring compliance to the
manufacturer's instructions for installation.)
Painting two coats after filling the surface with synthetic enamel paint
14.24 Nos. 208.00 208.00
bridge No. and span arrangements as per as directed by Engineer.
I Ordinary soil
A Manual Means
(i) Depth upto 3 m cum 248.00 248.00
(ii) Depth 3 m to 6 m cum 319.00 319.00
(iii) Depth above 6 m cum 425.00 425.00
B Mechanical Means
(i) Depth upto 3 m cum 123.00 128.00
(ii) Depth 3 m to 6 m cum 136.00 141.00
(iii) Depth above 6m cum 152.00 40,036.27
II Ordinary rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m cum 354.00 354.00
B Mechanical Means cum 757.00 798.00
III Hard rock ( requiring blasting )
A Manual Means cum 380.00 389.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
IV Hard rock ( blasting prohibited )
A Mechanical Means cum 1,015.00 1,043.00
V Marshy soil
(i) upto 3 m depth
A Manual means cum 1,369.00 1,369.00
B Mechanical Means cum 463.00 472.00
VI Back Filling in Marshy Foundation Pits cum 1,180.00 1,180.00
Filling Annular Space Around Footing in Rock (PCC-15 nominal mix.
15.02 cum 8,121.00 8,168.00
Rate may be taken as per items 15.11)
Sand Filling in Foundation Trenches as per Drawing & Technical
15.03 cum 3,259.00 3,275.00
Specification
Brick masonry work in cement mortar 1:3 in foundation complete
15.04 excluding pointing and plastering, as per drawing and technical cum 6,061.00 6,098.00
specifications
15.05 A Cement mortar1:3 (1cement :3 sand) cum 6,765.00 6,765.00
B Cement mortar1:2 (1cement :2 sand) cum 7,517.00 7,517.00
C Cement mortar1:4 (1cement :4 sand) cum 6,244.00 6,244.00
D Cement mortar1:6 (1cement :6 sand) cum 6,056.00 6,056.00
Stone masonry work in cement mortar 1:3 in foundation complete as
15.06
drawing and Technical Specification
(a) Square Rubble Coursed rubble masonry( first sort ) cum 6,604.00 6,604.00
(b) Random Rubble Masonry cum 5,926.00 5,926.00
Brick masonry work in cement mortar 1:3 in sub-structure complete
15.07 excluding pointing and plastering, as per drawing and technical cum 5,734.00 5,773.00
specifications
Pointing with cement mortar (1:3) on brick work in sub-structure as
15.08 Sqm 102.00 102.00
per Technical specification.
Plastering with cement mortar (1:3 ) on brick work in sub-structure as
15.09 Sqm 196.00 195.00
per Technical Specification
Stone masonry work in cement mortar 1:3 in sub-structure complete
15.10
as per drawing and Technical Specification
A Random Rubble Masonray cum 6,351.00 6,423.00
B Coursed Rubble Masonary cum 7,442.00 7,514.00
C Ashlar Masonary cum 9,160.00 9,232.00
Plain/Reinforced cement concrete, in open foundation complete as
15.11
per drawing and technical specification
A PCC Grade M15
Case I PCC Grade M15 using batching plant and concrete pump cum 8,121.00 8,168.00
Case II PCC Grade M15 using batching plant and manual placing cum 8,536.00 8,586.00
B PCC Grade M20
Case I PCC Grade M20 using batching plant and concrete pump cum 8,618.00 8,670.00
Case II PCC Grade M20 using batching plant and manual placing cum 9,032.00 9,082.00
C RCC Grade M20
Case I RCC Grade M20 using batching plant and concrete pump cum 8,666.00 8,718.00
Case II RCC Grade M20 using batching plant and manual placing cum 9,106.00 9,156.00
D PCC Grade M25
Case I PCC Grade M25 using batching plant and concrete pump cum 9,017.00 9,069.00
Case II PCC Grade M25 using batching plant and manual placing cum 9,432.00 9,482.00
E RCC Grade M25
Case I RCC Grade M25 using batching plant and concrete pump cum 9,264.00 9,316.00
Case II RCC Grade M25 using batching plant and manual placing cum 9,704.00 9,754.00
F PCC Grade M30
Case I PCC Grade M30 using batching plant and concrete pump cum 9,055.00 9,107.00
Case II PCC Grade M30 using batching plant and manual placing cum 9,469.00 9,520.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
G RCC Grade M30
Case I RCC Grade M30 using batching plant and concrete pump cum 9,390.00 9,442.00
Case II RCC Grade M30 using batching plant and manual placing cum 9,831.00 9,881.00
H RCC Grade M35
Case I RCC Grade M35 using batching plant and concrete pump cum 9,614.00 9,666.00
Case II RCC Grade M35 using batching plant and manual placing cum 10,054.00 10,104.00
I RCC Grade M40
Case I RCC Grade M40 using batching plant and concrete pump cum 10,097.00 10,150.00
Case II RCC Grade M40 using batching plant and manual placing cum 10,794.00 10,893.00
Plain/Reinforced cement concrete for wall & slab etc. complete as per
15.12
drawing and technical specification
A RCC Grade M20
With Batching Plant, Transit Mixer and Concrete Pump cum 9,847.00 9,907.00
B RCC Grade M25
With Batching Plant, Transit Mixer and Concrete Pump cum 10,527.00 10,587.00
C RCC Grade M30
With Batching Plant, Transit Mixer and Concrete Pump cum 10,671.00 10,701.00
D RCC Grade M35
With Batching Plant, Transit Mixer and Concrete Pump cum 10,925.00 10,984.00
E RCC Grade M40
With Batching Plant, Transit Mixer and Concrete Pump cum 11,474.00 11,534.00
Supplying, fitting and placing un-coated HYSD bar reinforcement in
15.13 MT 68,094.00 68,191.00
foundation complete as per drawing and technical specifications
15.17 Drainage Spouts complete as per drawing and Technical specification Number 875.00 875.00
Cement concrete blocks (size 0.5 x 0.5 x 0.5 m) (Providing and laying
of apron with cement concrete blocks of size 0.5x0.5x0.5 m cast in-
16.03 cum 8,231.00 8,280.00
situ and made with nominal mix of M-15 grade cement concrete with a
minimum cement content of 250 kg/cum as per IRC: 21-2000.)
Providing and laying Pitching on slopes laid over prepared filter media
16.04 including boulder apron laid dry in front of toe of embankment
complete as per drawing and Technical specifications
A Stone/Boulder cum 3,932.00 3,932.00
Cement Concrete blocks of size 0.3x0.3 x0.3 m cast in cement
B cum 8,231.00 8,280.00
concrete of Grade M15
Providing and laying Filter material underneath pitching in slopes
16.05 cum 2,827.00 2,827.00
complete as per drawing and Technical specification
Toe protection (A toe wall for toe protection can either be in dry rubble
masonry in case of dry rubble pitching or pitching with stones in wire
crates or it can be in PCC M15 nominal mix if cement concrete block
16.07 have been used for pitching . Rates for toe wall can be adopted from
respective clauses depending upon approved design. The rate for
excavation for foundation, dry rubble masonry and PCC M15 have
been analysed and given in respective chapters.)
Laying of a fine aggregate concrete grade M30 filled fabric form for
16.15 erosion protection of embankments (Embankment Erosion Protection cum 1,105.00 1,110.00
using Fine Aggregate Concrete Filled Fabric Form Mattress system)
CHAPTER-17
REPAIR AND REHABILITATION
17.15 Replacement of bearings complete as per Technical specification each 84,446.00 84,446.00
17.16 Rectification of bearings as per Technical specifications each 5,753.00 5,753.00
17.17 Replacement of Expansion Joints complete as per drawings metre 4,595.00 4,613.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
Item No. Descriptions Unit for Large for Medium
Project Project
17.18 Replacement of damaged concrete railing. metre 652.00 652.00
17.19 Replacement of crash barrier. metre 1,035.00 1,035.00
17.20 Replacement of damaged mild steel railing metre 575.00 575.00
Repair of RCC Railing (Carrying out repair of RCC M30 railing to bring
17.22 metre 222.00 223.00
it to the original shape.)
Repair of steel Railing (Repair of steel railing to bring it to the original
17.23 metre 416.00 416.00
shape)
Mobile Bridge Inspection Unit (MBIU) Inspection of bridge by using of
17.24 km 55,382.00 55,382.00
Mobile Bridge Inspection Unit (MBIU)
CHAPTER-18
TUNNEL WORK
Excavation for Portal in Ordinary Rock with hydraulic excavator
including cutting and loading in tippers, trimming bottom and side
18.01 slopes, in accordance with requirements of lines, grades and cross Cum 854.00
sections, and disposal of excavated materials including all lifts and
lead upto 1000 m
Excavation for tunnel by using drilling & blasting methods in all types
of rock including cost of all materials,machinery, labour, scaling
18.04 excavated surface, marking, ventilation, lighting, drainage, removing Cum 1,744.00
and hauling the excavated muck outside tunnel upto specified dump
area and all other ancillary operations etc.
145.00
133.00
114.00
114.00
472.00
693.00
15.00
11.00
9.00
8.00
18.00
13.00
10.00
9.00
36.00
26.00
21.00
19.00
73.00
17.00
2,987.00
2,760.00
3,005.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
2,572.00
633.00
1,751.00
587.00
951.00
1,685.00
3,369.00
667.00
905.00
1,082.00
1,347.00
33,030.00
381,648.00
414,678.00
222,818.00
237,801.00
194,263.00
202,275.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
1,081.00
1,214.00
2,498.00
1,058.00
1,442.00
740.00
872.00
687.00
660.00
792.00
872.00
739.00
713.00
687.00
739.00
285.00
1,380.00
2,866.00
2,083.00
20.00
2.00
1.00
925.00
198.00
34.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
1,468.00
1,687.00
2,124.00
1,377.00
1,047.00
623.00
91.00
1,078.00
113.00
42.00
54.00
842.00
561.00
112.00
99.00
275.00
420.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
398.00
412.00
550.00
238.00
357.00
822.00
130.00
742.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
850.00
2,090.00
863.00
281.00
133.00
236.00
528.00
125.00
661.00
775.00
445.00
1,520.00
1,415.00
589.00
72.00
8.00
10.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
10.00
10.00
305.00
100.00
133.00
312.00
124.00
157.00
157.00
170.00
150.00
281.00
544.00
1,616.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
104.00
322.00
133.00
440.00
708.00
301.00
5,437.00
8.00
202.00
176.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
4,138.00
4,138.00
4,138.00
4,138.00
4,138.00
4,138.00
3,430.00
3,430.00
3,430.37
3,430.00
3,430.00
3,430.00
4,102.00
4,102.00
4,102.00
4,102.00
4,102.00
3,820.00
717.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
1,076.00
1,000.00
768.00
1,127.00
1,052.00
654.00
1,013.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
937.00
1,057.00
981.00
832.00
1,015.00
3,691.00
3,709.00
4,612.00
4,612.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
4,307.00
4,307.00
8.00
17.00
3,223.00
3,998.00
3,901.00
4,087.00
3,998.00
4,087.00
3,927.00
3,830.00
3,927.00
4,016.00
1,156.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
42.00
3,609.00
3,595.00
4,476.00
485.00
382.00
1,240.00
3,410.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
3,410.00
3,443.00
3,443.00
1,093.00
44.00
37.00
55.00
54.00
13.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
16.00
19.00
8,611.00
9,105.00
10,463.00
11,107.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
12,360.00
12,680.00
122.00
95.00
180.00
223.00
206.00
91.00
61.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
1,685.00
57.00
92.00
112.00
9,465.00
9,079.00
10,259.00
10,258.00
11,434.00
11,265.00
45.00
21.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
15,255.00
15,255.00
11,343.00
11,343.00
11,565.00
78.00
90.00
118.00
151.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
10,717.00
13,751.00
15,438.00
11,926.00
12,188.00
5,637.00
9,326.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
5,638.00
8,689.00
8,785.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
8,193.00
1,045.00
171.00
7,450.00
9.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
9.00
9.00
9.00
9.00
259.00
2,351.00
13.00
13.00
13.00
13.00
426.00
467.00
633.00
695.00
737.00
820.00
882.00
1,048.00
1,151.00
1,479.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
1,754.00
1,980.00
2,084.00
2,266.00
249.00
215.00
16,728.00
4,397.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
3,055.00
4,252.00
5,688.00
4,635.00
3,578.00
5,026.00
6,757.00
5,467.00
4,013.00
5,189.00
6,533.00
5,466.00
4,719.00
6,130.00
7,722.00
6,448.00
4,761.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
6,166.00
7,030.00
6,166.00
5,601.00
7,299.00
8,362.00
7,795.00
2,964.00
2,012.00
2,339.00
249.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
215.00
119.00
78.00
44.00
249.00
322.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
259.00
434.00
1.60
1.00
9,152.00
6,586.00
5,577.00
4,753.00
13,925.00
9,271.00
7,442.00
5,946.00
9,636.00
7,802.00
6,108.00
5,826.00
6,673.00
14,508.00
9,599.00
7,670.00
13,506.00
14,338.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
77,459.00
10,526.00
97.00
97.00
105.00
182.00
151.00
128.00
139.00
578.00
7,206.00
4,026.00
1,166.00
540.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
1,219.00
362.00
599.00
869.00
1,258.00
2,248.00
5,567.00
3,126.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
3,159.00
3,356.00
3,392.00
4,054.00
5,091.00
2,882.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
3,683.00
1,331.00
25,973.00
25,864.00
18,399.00
3,893.00
7,917.00
11,686.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
6,868.00
1,467.00
1,828.00
2,143.00
6,995.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
242.00
797.00
199.00
7,893.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
4,262.00
6,502.00
1,842.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
13,207.00
837.00
3,245.00
596.00
627.00
826.00
1.00
1.00
1.00
1.00
1.00
1.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
29.00
1.00
1.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
3,025.00
3,248.00
231.00
297.00
396.00
146.00
162.00
181.00
330.00
766.00
730.00
395.00
1,195.00
1,278.00
511.00
3,087.00
5,819.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
8,538.00
9,498.00
11,430.00
17,726.00
19,694.00
23,219.00
7,805.00
8,176.00
8,254.00
8,639.00
8,299.00
8,708.00
8,631.00
9,012.00
8,857.00
9,266.00
63,391.00
189.00
122.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
46.00
191.00
510.00
510.00
5.00
5.00
45.00
78.00
90.00
118.00
151.00
92.00
57.00
57.00
122.00
95.00
1,082.00
50.00
66.00
111.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
175.00
8.00
11.00
3,077.00
4,188.00
466.00
467.00
4,286.00
147,706.00
44.00
61.00
110.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
60.00
270.00
68.00
326.00
327.00
296.00
117,587.00
367,994.00
1,812.00
27.00
370.00
4,928.00
370.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
1,533.00
30.00
711.00
1,309.00
12,066.00
3,041.00
3,991.00
248,860.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
136,980.00
248.00
319.00
425.00
157.00
173.00
194.00
354.00
821.00
429.00
1,087.00
1,369.00
547.00
1,180.00
6,235.00
3,328.00
6,235.00
6,249.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
6,765.00
7,517.00
6,244.00
6,056.00
6,604.00
5,926.00
7,892.00
8,282.00
8,361.00
8,751.00
8,764.00
9,178.00
8,739.00
9,129.00
8,972.00
9,387.00
8,775.00
9,164.00
9,092.00
9,506.00
9,303.00
9,717.00
9,760.00
10,174.00
9,958.00
10,372.00
319,415.00
1,091,423.00
4,599.00
135,841.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
9,113.00
9,519.00
9,766.00
10,172.00
9,904.00
10,310.00
10,148.00
10,554.00
10,675.00
11,081.00
7,810.00
8,208.00
8,306.00
8,704.00
8,354.00
8,726.00
8,706.00
9,104.00
8,952.00
9,324.00
8,743.00
9,141.00
9,079.00
9,451.00
9,302.00
9,674.00
9,786.00
10,158.00
7,961.00
8,392.00
8,342.00
8,773.00
8,378.00
8,809.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
8,771.00
9,202.00
7,583.00
7,993.00
7,946.00
8,356.00
7,981.00
8,390.00
7,589.00
7,964.00
8,040.00
8,415.00
8,403.00
8,778.00
8,280.00
8,812.00
8,410.00
8,780.00
8,976.00
9,346.00
9,096.00
9,465.00
9,303.00
9,676.00
9,764.00
10,134.00
9,962.00
10,331.00
5,651.00
7,858.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
10,379.00
19,471.00
3,894.00
46,262.00
9,253.00
7,841.00
17,499.00
23,112.00
1,156.00
43,352.00
2,168.00
10,838.00
102,998.00
5,150.00
20,600.00
43,682.00
44,573.00
32,480.00
16,510.00
10,859.00
14,342.00
717.00
26,902.00
5,381.00
63,918.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
12,784.00
10,859.00
17,448.00
23,043.00
1,152.00
43,222.00
2,161.00
10,806.00
102,691.00
5,135.00
20,538.00
55,683.00
57,401.00
80,118.00
10,065.00
12,272.00
16,206.00
30,395.00
6,079.00
72,214.00
14,443.00
13,261.00
18,472.00
24,397.00
1,220.00
45,763.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
2,288.00
11,441.00
108,726.00
5,436.00
21,745.00
69,278.00
73,385.00
101,693.00
10,276.00
13,489.00
17,816.00
33,419.00
6,684.00
79,397.00
15,880.00
14,064.00
19,917.00
26,305.00
1,315.00
49,341.00
2,467.00
12,335.00
117,228.00
5,862.00
23,445.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
84,470.00
76,144.00
125,927.00
12,077.00
14,293.00
18,877.00
35,408.00
7,082.00
84,126.00
16,825.00
16,139.00
20,163.00
26,630.00
1,332.00
49,951.00
2,498.00
12,488.00
118,675.00
5,934.00
23,735.00
101,257.00
96,900.00
152,820.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
26,992.00
23,450.00
30,969.00
58,091.00
11,618.00
138,015.00
27,603.00
26,559.00
41,983.00
55,446.00
2,772.00
104,002.00
5,200.00
26,001.00
247,093.00
12,355.00
49,419.00
119,640.00
112,786.00
182,373.00
57,135.00
65,191.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
86,097.00
161,496.00
32,299.00
383,691.00
76,738.00
64,314.00
101,308.00
133,796.00
6,690.00
250,967.00
12,548.00
62,742.00
596,260.00
29,813.00
119,252.00
139,619.00
130,048.00
214,586.00
12,888.00
13,898.00
18,355.00
34,429.00
6,886.00
81,797.00
16,359.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
15,265.00
22,365.00
29,538.00
1,477.00
55,406.00
2,770.00
13,852.00
131,638.00
6,582.00
26,328.00
85,138.00
83,722.00
61,745.00
184,140.00
2,658.00
123,384.00
11,837.00
15,976.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
21,190.00
29,909.00
8,823.00
13,639.00
20,000.00
5,151.00
8,108.00
13,231.00
4,103.00
6,136.00
10,035.00
9,721.00
10,894.00
300.00
500.00
2,006.00
7,856.00
7,903.00
8,422.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
8,469.00
8,541.00
8,588.00
8,751.00
8,798.00
9,209.00
9,256.00
9,406.00
9,453.00
7,588.00
7,963.00
68,383.00
92,375.00
5,946.00
102.00
193.00
7,907.00
8,413.00
10,365.00
8,347.00
8,844.00
9,243.00
9,579.00
8,739.00
9,281.00
9,618.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
10,040.00
8,892.00
9,215.00
9,635.00
9,490.00
9,800.00
10,266.00
9,616.00
9,887.00
10,272.00
9,840.00
10,054.00
10,376.00
10,323.00
10,549.00
10,886.00
10,532.00
10,762.00
11,107.00
11,373.00
11,621.00
11,993.00
68,709.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
92,701.00
172.00
3,688.00
3,146.00
2,506.00
266.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
230.00
301.00
458.00
593.00
1.00
584.00
188.00
342.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
166,698.00
9,615.00
10,016.00
10,417.00
10,016.00
10,417.00
10,817.00
10,268.00
10,696.00
11,124.00
10,696.00
11,124.00
11,551.00
10,406.00
10,839.00
11,273.00
10,839.00
11,273.00
11,706.00
10,472.00
10,916.00
11,360.00
10,916.00
11,360.00
11,803.00
12,247.00
13,135.00
14,022.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
10,991.00
11,457.00
11,922.00
11,457.00
11,922.00
12,388.00
12,854.00
13,785.00
14,717.00
11,025.00
11,500.00
11,975.00
11,500.00
11,975.00
12,451.00
12,926.00
13,876.00
14,827.00
13,863.00
14,890.00
15,916.00
14,003.00
15,041.00
16,078.00
14,342.00
15,404.00
16,467.00
14,415.00
15,483.00
16,551.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
69,035.00
150,058.00
13,950.00
574.00
2,121.00
2,072.00
4,246.00
4,779.00
7,589.00
7,964.00
11,794.00
To be noted
60,659.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
1,591.00
107.00
2,417.00
255.00
266.00
44.00
1,569.00
37,794.00
4,567.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
11,281.00
11,173.00
11,194.00
208.00
277.00
174,295.00
248.00
319.00
425.00
157.00
173.00
40,782.81
354.00
821.00
429.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
1,087.00
1,369.00
547.00
1,180.00
8,347.00
3,328.00
6,249.00
6,765.00
7,517.00
6,244.00
6,056.00
6,604.00
5,926.00
5,946.00
102.00
203.00
6,714.00
7,805.00
9,523.00
8,347.00
8,760.00
8,844.00
9,256.00
8,892.00
9,330.00
9,243.00
9,655.00
9,490.00
9,928.00
9,281.00
9,693.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
9,616.00
10,054.00
9,840.00
10,278.00
10,323.00
11,224.00
10,104.00
10,784.00
10,898.00
11,182.00
11,731.00
68,383.00
172.00
7,589.00
7,964.00
12,336.00
875.00
13,949.00
574.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
107.00
2,417.00
255.00
266.00
44.00
3,688.00
3,146.00
2,506.00
208.00
3,932.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
3,761.00
8,448.00
3,932.00
8,448.00
2,827.00
30.00
8,672.00
10,601.00
4,618.00
6,604.00
7,892.00
4,057.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
3,602.00
3,773.00
3,534.00
1,125.00
300.00
232.00
1,525.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
224.00
285.00
281.00
2,196.00
1,418.00
557.00
638.00
202.00
526.00
426,592.00
413,981.00
378,259.00
84,446.00
5,753.00
4,675.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
652.00
1,035.00
575.00
415.00
225.00
416.00
55,382.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
6,159.00
149.00
274.00
439.00
499.00
114.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
421.00
114.00
197.00
3,326.00
7,392.00
3,080.00
2,464.00
123,200.00
123,200.00
14,784.00
14,784.00
30,800.00
30,800.00
409.00
2,285,545.00
3,028,194.00
3,770,844.00
1,374,173.00
1,611,333.00
1,848,493.00
Summary of Rate Analysis
Rate As Per Proposed Data Book
for Small
Project
CHAPTER-1
CARRIAGE OF MATERIALS
Reference to Quantity For Quantity For Quantity For Amount Amount Amount
Rate Remarks/
Sr No MORT&H Description Unit Large Medium Small (Rs.) Large (Rs.) Medium (Rs.) Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Time taken for empty return trip. hour 0.286 0.286 0.286 1,731.45 494.70 494.70 494.70 P&M-017
Total cost Excluding OH & CP 1187.28 1187.28 1187.28
b) Overhead Charges @ 8% on @ 10% on @ 12% on
(a) (a) (a) 94.98 118.73 142.47
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 128.23 130.60 132.98
cost for 100 t km = a+b+c 1,410.49 1,436.61 1,462.73
Rate per t.km = (a+b+c)/100 14.10 14.37 14.63
Say 14.00 14.00 15.00
B Case-I : Surfaced Road
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit : t.km
Taking output 18 tonnes load and lead 10 km = 180 t.km t.km t.km
Time taken for onward hanlage with load hour 0.500 0.500 0.500 1,731.45 865.73 865.73 865.73 P&M-017
Time taken for empty return trip hour 0.333 0.333 0.333 1,731.45 577.15 577.15 577.15 P&M-017
Total cost Excluding OH & CP 1442.88 1442.88 1442.88
b) Overhead Charges @ 8% on @ 10% on @ 12% on
(a) (a) (a) 115.43 144.29 173.15
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 155.83 158.72 161.60
Cost for 100 t .km = a+b+c 1,714.14 1,745.88 1,777.62
Rate per t.Km = (a+b+c)/100 17.14 17.46 17.78
Say 17.00 17.00 18.00
1.04 (ii) B Case-II : Unsurfaced Gravelled Road
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit : t.km
Taking output 18 tonnes load and lead 10 km = 180 t.km t.km t.km
a) Machinery
I) Tipper 10 tonnes capacity P&M-017
Time taken for onward haulage hour 1.000 1.000 1.000 1,731.45 1,731.45 1,731.45 1,731.45 P&M-017
Time taken for empty return trip hour 0.667 0.667 0.667 1,731.45 1,154.30 1,154.30 1,154.30 P&M-017
Total cost Excluding OH & CP 2885.75 2885.75 2885.75
b) Overhead Charges @ 8% on @ 10% on @ 12% on
(a) (a) (a) 230.86 288.58 346.29
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 311.66 317.43 323.20
Cost for 100 t .km = a+b+c 3,428.27 3,491.76 3,555.24
Rate per t.Km = (a+b+c)/100 34.28 34.92 35.55
Say 34.00 35.00 36.00
1.04 (iii) B Case-III : Katcha Track and Track in river bed /
nallah bed and choe bed.
Haulage of materials by tipper excluding cost of
loading, unloading and stacking.
Unit : t.km
Taking output 18 tonnes load and lead 10 km = 180 t.km t.km t.km
Taking output 10 tonnes load and lead 10 km = 100 t.km t.km t.km
Unit : t.km
Taking output 15 tonnes load and lead 10 km = 150 t.km t.km t.km
Unit : cum
Taking Output = 1125 tonne tonne tonne (750 cum)
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mazdoor Skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
b) Material
Stone Boulder of size 150 mm and below cum 750.000 750.000 750.000 1,472.59 1,104,442.95 1,104,442.95 1,104,442.95 M-001
c) Machinery
Integrated stone crusher of 250 TPH including belt Hour
conveyor and vibrating screens 6.000 6.000 6.000 15,481.20 92,887.20 92,887.20 92,887.20 P&M-031
Generator 725 KVA Hour 6.000 6.000 6.000 11,596.20 69,577.20 69,577.20 69,577.20 P&M-043
Front end loader 3.1 cum bucket capacity at quarry Hour
and crusher 5.515 5.515 5.515 4,279.80 23,603.10 23,603.10 23,603.10 P&M-011
Reference to Quantity For Quantity For Quantity For Amount Amount Amount
Rate Remarks/
Sr No MORT&H Description Unit Large Medium Small (Rs.) Large (Rs.) Medium (Rs.) Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Unit : cum
Taking Output = 1125 tonne tonne tonne (750 cum)
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mazdoor Skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
b) Material
Stone Boulder of size 150 mm and below cum 750.000 750.000 750.000 1,472.59 1,104,442.95 1,104,442.95 1,104,442.95 M-001
c) Machinery
Integrated stone crusher of 250 TPH including belt
conveyor and vibrating screens (for producing
crusher run production capacity will increas by 30%) Hour 4.615 4.615 4.615 15,481.20 71,445.74 71,445.74 71,445.74 P&M-031
Generator 725 KVA Hour 4.615 4.615 4.615 11,596.20 53,516.46 53,516.46 53,516.46 P&M-043
Front end loader 3.1 cum bucket capacity at quarry
and crusher Hour 5.515 5.515 5.515 4,279.80 23,603.10 23,603.10 23,603.10 P&M-011
Tipper 14 cum capacity for loading at quarry site
Hour 5.515 5.515 5.515 2,556.75 14,100.48 14,100.48 14,100.48 P&M-015
Tipper 14 cum capacity for transportation within 1
km t.km 1125.000 1125.000 1125.000 7.01 7,889.40 7,889.40 7,889.40 P&M-119
By Manual Means
Unit = Hectare
Taking output = 1 Hectare
a) Labour
Mate day 2.000 2.000 2.000 617.00 1,234.00 1,234.00 1,234.00 L-12
Mazdoor day 50.000 50.000 50.000 511.52 25,576.00 25,576.00 25,576.00 L-13
b) Overhead charges @ 8% on (a) @ 10% on @ 12% on
(a) (a) 2,144.80 2,681.00 3,217.20
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 2,895.48 2,949.10 3,002.72
Rate per Hectare = a+b+c 31,850.28 32,440.10 33,029.92
Say 31,850.00 32,440.00 33,030.00
2.03 201 Clearing and Grubbing Road Land .
Clearing and grubbing road land including uprooting
rank vegetation, grass, bushes, shrubs, saplings and
trees girth up to 300 mm, removal of stumps of trees
cut earlier and disposal of unserviceable materials and
stacking of serviceable material to be used or
auctioned, up to a lead of 1000 metres including
removal and disposal of top organic soil not exceeding
150 mm in thickness.
Unit = Hectare
Taking output = 1 Hectare
(i) By Manual Means:-
A In area of light jungle
a) Labour
Mate day 6.000 6.000 6.000 617.00 3,702.00 3,702.00 3,702.00 L-12
Mazdoor day 150.000 150.000 150.000 511.52 76,728.00 76,728.00 76,728.00 L-13
b) Machinery
Tractor-trolley hour 122.222 122.222 122.222 1,876.50 229,349.58 229,349.58 229,349.58 P&M-026
b) Overhead charges @ 8% on (a) @ 10% on @ 12% on
(a) (a) 24,782.37 30,977.96 37,173.55
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 33,456.19 34,075.75 34,695.31
Rate per Hectare = a+b+c+d 368,018.14 374,833.30 381,648.45
Quantity Amount (Rs.)
Ref.to
Rate Remarks
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project /Input ref.
Specification Project Project Project Project
Unit = cum
Taking output = 1.25 cum
(i) Lime /Cement Concrete
I By Manual Means
A Lime Concrete, cement concrete grade M-10 and
below
Quantity Amount (Rs.)
Ref.to
Rate Remarks
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project /Input ref.
Specification Project Project Project Project
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor for dismantling and loading day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Tractor-trolley (considering 15 min loading time) hour 0.299 0.299 0.299 1,876.50 561.07 561.07 561.07 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 87.78 109.73 131.67
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 118.51 120.70 122.89
Cost for 1.25 cum = a+b+c+d 1,303.56 1,327.70 1,351.84
Rate per cum = (a+b+c+d)/ 1.25 1,042.85 1,062.16 1,081.47
Say 1,043.00 1,062.00 1,081.00
2.04 B Cement Concrete Grade M-15 & M-20
a) Labour
Mate day 0.050 0.050 0.050 617.00 30.85 30.85 30.85 L-12
Mazdoor for dismantling and loading day 1.250 1.250 1.250 511.52 639.40 639.40 639.40 L-13
b) Machinery
Tractor-trolley (considering 15 min loading time) hour 0.299 0.299 0.299 1,876.50 561.07 561.07 561.07 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 98.51 123.13 147.76
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 132.98 135.45 137.91
Cost for 1.25 cum = a+b+c+d 1,462.81 1,489.90 1,516.99
Rate per cum = (a+b+c+d)/ 1.25 1,170.25 1,191.92 1,213.59
Say 1,170.00 1,192.00 1,214.00
2.04 C Prestressed / Reinforced cement concrete grade M-20
& above
a) Labour
Mate day 0.150 0.150 0.150 617.00 92.55 92.55 92.55 L-12
Blacksmith day 0.250 0.250 0.250 679.00 169.75 169.75 169.75 L-02
Mazdoor for dismantling, loading and unloading day 3.500 3.500 3.500 511.52 1,790.32 1,790.32 1,790.32 L-13
b) Machinery
Tractor-trolley (considering 15 min loading time) hour 0.257 0.257 0.257 1,876.50 482.26 482.26 482.26 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 202.79 253.49 304.19
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 273.77 278.84 283.91
Cost for 1.25 cum = a+b+c+d 3,011.44 3,067.21 3,122.97
Rate per cum = (a+b+c+d)/ 1.25 2,409.15 2,453.76 2,498.38
Say 2,409.00 2,454.00 2,498.00
2.04 II By Mechanical Means
A Cement Concrete Grade M-15 & M-20
Unit = cum
Taking output = 1.25 cum
a) Labour
Mate day 0.020 0.020 0.020 617.00 12.34 12.34 12.34 L-12
Mazdoor for loading and unloading & Pneumatic day 0.500 0.500 0.500 L-13
breaker 511.52 255.76 255.76 255.76
b) Machinery
Air Compressor 250 cfm hour 0.6250 0.625 0.625 614.25 383.91 383.91 383.91 P&M-029
Pneumatic breaker @ 1 cum per hour hour 1.250 1.250 1.250 206.00 257.50 257.50 257.50 P&M-010
Tipper
For transportation to dumping yard considering lead @
1 km
(i) 18 cum capacity t.km 1.875 6.18 11.58 P&M-117
(ii) 14 cum capacity t.km 1.875 7.01 13.15 P&M-120
(iii) 10 cum capacity t.km 1.875 8.66 16.25 P&M-123
Loading & unloading charges for disposed of material
(i) Using by 18 cum capacity Tipper & 3.1 Cum cum 1.250 P&M-129
capacity Loader 92.72 115.90
(ii) Using by 14 cum capacity Tipper & 2.1 Cum cum 1.250 P&M-130
capacity Loader 92.81 116.02
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 1.250 P&M-131
Loader 118.14 147.68
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 82.96 103.87 128.81
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 112.00 114.25 120.22
Cost for 1.25 cum = a+b+c+d 1,231.95 1,256.79 1,322.46
Rate per cum = (a+b+c+d)/ 1.25 985.56 1,005.43 1,057.97
Quantity Amount (Rs.)
Ref.to
Rate Remarks
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project /Input ref.
Specification Project Project Project Project
b) Machinery
Air Compressor 250 cfm hour 0.625 0.625 0.625 614.25 383.91 383.91 383.91 P&M-029
Pneumatic breaker @ 1 cum per hour hour 1.250 1.250 1.250 206.00 257.50 257.50 257.50 P&M-010
Tipper
For transportation to dumping yard considering lead @
1 km
(i) 18 cum capacity t.km 1.875 6.18 11.58 P&M-117
(ii) 14 cum capacity t.km 1.875 7.01 13.15 P&M-120
(iii) 10 cum capacity t.km 1.875 8.66 16.25 P&M-123
Loading & unloading charges for disposed of material
(i) Using by 18 cum capacity Tipper & 3.1 Cum cum 1.250 P&M-129
capacity Loader 92.72 115.90
(ii) Using by 14 cum capacity Tipper & 2.1 Cum cum 1.250 P&M-130
capacity Loader 92.81 116.02
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 1.250 P&M-131
Loader 118.14 147.68
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 114.11 142.80 175.53
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 154.04 157.08 163.83
Cost for 1.25 cum = a+b+c+d 1,694.49 1,727.90 1,802.13
Rate per cum = (a+b+c+d)/ 1.25 1,355.59 1,382.32 1,441.71
Say 1,356.00 1,382.00 1,442.00
2.04 (ii) Dismantling Brick / Tile work
By Manual Means
A In lime mortar
a) Labour
Mate day 0.020 0.020 0.020 617.00 12.34 12.34 12.34 L-12
Mazdoor for dismantling, loading and unloading day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 1,876.50 482.26 482.26 482.26 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 60.03 75.04 90.04
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 81.04 82.54 84.04
Cost for 1.25 cum = a+b+c+d 891.43 907.94 924.44
Rate per cum = (a+b+c+d)/ 1.25 713.14 726.35 739.56
Say 713.00 726.00 740.00
2.04 B In cement mortar
a) Labour
Mate day 0.030 0.030 0.030 617.00 18.51 18.51 18.51 L-12
Mazdoor for dismantling, loading and unloading day 0.750 0.750 0.750 511.52 383.64 383.64 383.64 L-13
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 1,876.50 482.26 482.26 482.26 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 70.75 88.44 106.13
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 95.52 97.29 99.05
Cost for 1.25 cum = a+b+c+d 1,050.68 1,070.14 1,089.59
Rate per cum = (a+b+c+d)/ 1.25 840.54 856.11 871.67
Say 841.00 856.00 872.00
2.04 C In mud mortar
a) Labour
Mate day 0.016 0.016 0.016 617.00 9.87 9.87 9.87 L-12
Mazdoor for dismantling and loading day 0.400 0.400 0.400 511.52 204.61 204.61 204.61 L-13
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 1,876.50 482.16 482.16 482.16 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 55.73 69.66 83.60
Quantity Amount (Rs.)
Ref.to
Rate Remarks
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project /Input ref.
Specification Project Project Project Project
a) Labour
Mate day 0.020 0.020 0.020 617.00 12.34 12.34 12.34 L-12
Mazdoor for dismantling, loading and unloading day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 1,876.50 482.16 482.26 482.16 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 60.02 75.04 90.03
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 81.03 82.54 84.03
Cost for 1.25 cum = a+b+c+d 891.30 907.94 924.32
Rate per cum = (a+b+c+d)/ 1.25 713.04 726.35 739.45
Say 713.00 726.00 739.00
II By Mechanical Means
2.04 A Dismantling Brick / Tile work/ rubble masonary/
pitching/ etc by mechanical means
Unit = cum
Taking output = 20 cum
a) Labour
Mate day 0.008 0.008 0.008 617.00 4.94 4.94 4.94 L-12
Mazdoor day 0.200 0.200 0.200 511.52 102.30 102.30 102.30 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 0.523 3,420.00 1,788.66 P&M-007
(ii) 1.1 cum bucket capacity hour 0.603 3,074.00 1,853.62 P&M-008
(iii) 0.9 cum bucket capacity hour 0.843 2,782.00 2,345.23 P&M-009
Tipper
For transportation to dumping yard considering lead @
1km
(i) 18 cum capacity t.km 30.000 6.18 185.36 P&M-117
(ii) 14 cum capacity t.km 30.000 7.01 210.38 P&M-120
(iii) 10 cum capacity t.km 30.000 8.66 259.92 P&M-123
Loading & unloading time
(i) 18 cum capacity hour 0.523 2,883.30 1,507.97 P&M-014
(ii) 14 cum capacity hour 0.603 2,556.75 1,541.72 P&M-015
(iii) 10 cum capacity hour 0.843 2,274.30 1,917.23 P&M-016
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 287.14 371.30 555.55
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 387.64 408.43 518.52
Cost for 20 cum = a+b+c+d 4,263.99 4,492.69 5,703.69
Rate per cum = (a+b+c+d)/ 20 213.20 224.63 285.18
Say 213.00 225.00 285.00
2.04 (iv) Wood Work wrought framed and fixed in frames of
trusses upto a height of 5 m above plinth level
Unit = Cum
Taking output = 1.25 Cum
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Carpenter day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-04
Mazdoor for dismantling, loading and unloading. day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Tractor-trolley hour 0.257 0.257 0.257 1,876.50 482.16 482.16 482.16 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 111.98 139.97 167.96
Quantity Amount (Rs.)
Ref.to
Rate Remarks
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project /Input ref.
Specification Project Project Project Project
Unit = tonne
Taking output = 1 tonne
A Including dismembering
a) Labour
Mate day 0.140 0.140 0.140 617.00 86.38 86.38 86.38 L-12
Blacksmith day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-02
Mazdoor for dismantling, loading and unloading day 2.500 2.500 2.500 511.52 1,278.80 1,278.80 1,278.80 L-13
Add 2.5 per cent of cost of labour for gas cutting,
ropes, pulleys etc. 51.10 51.10 51.10
b) Machinery
Tractor-trolley hour 0.123 0.123 0.123 1,876.50 230.81 230.81 230.81 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 186.09 232.61 279.13
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 251.22 255.87 260.52
Rate per tonne = a+b+c+d 2,763.40 2,814.57 2,865.75
Say 2,763.00 2,815.00 2,866.00
2.04 B Excluding dismembering.
a) Labour
Mate day 0.100 0.100 0.100 617.00 61.70 61.70 61.70 L-12
Mazdoor for dismantling, loading and unloading day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
Blacksmith day 0.500 0.500 0.500 679.00 339.50 339.50 339.50 L-02
Add 2.5 per cent of cost of labour for gas cutting,
35.61 35.61 35.61
ropes, pulleys etc.
b) Machinery
Tractor-trolley hour 0.123 0.123 0.123 1,876.50 230.81 230.81 230.81 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 135.25 169.07 202.88
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 182.59 185.97 189.35
Rate per tonne = a+b+c+d 2,008.50 2,045.69 2,082.89
Say 2,008.00 2,046.00 2,083.00
2.04 C Extra over item No( v ) A and( v ) B for cutting rivets.
Unit = each
Taking output = 10 rivets
a) Labour
Mate day 0.010 0.010 0.010 617.00 6.17 6.17 6.17 L-12
Blacksmith day 0.130 0.130 0.130 679.00 88.27 88.27 88.27 L-02
Mazdoor day 0.130 0.130 0.130 511.52 66.50 66.50 66.50 L-13
b) Overhead charges @ 8% on (a) @ 10% on @ 12% on
(a) (a) 12.88 16.09 19.31
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 17.38 17.70 18.03
Cost for 10 rivets = a+b+c 191.19 194.73 198.28
Rate for each rivet = ( a+b+c)/10 19.12 19.47 19.83
Say 19.00 19.00 20.00
2.04 (vi) Scraping of Bricks Dismantled from Brick Work
including Stacking.
Unit = numbers 1000.00
Taking output = 1000 numbers
A In lime/Cement mortar
a) Labour
Mate day 0.140 0.140 0.140 617.00 86.38 86.38 86.38 L-12
Mazdoor day 3.500 3.500 3.500 511.52 1,790.32 1,790.32 1,790.32 L-13
b) Overhead charges @ 8% on (a) @ 10% on @ 12% on
(a) (a) 150.14 187.67 225.20
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 202.68 206.44 210.19
Rate per 1000 Nos = a+b+c 2.23 2.27 2.31
Say 2.00 2.00 2.00
2.04 B In mud mortar
a) Labour
Mate day 0.050 0.050 0.050 617.00 30.85 30.85 30.85 L-12
Quantity Amount (Rs.)
Ref.to
Rate Remarks
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project /Input ref.
Specification Project Project Project Project
Mazdoor day 1.250 1.250 1.250 511.52 639.40 639.40 639.40 L-13
b) Overhead charges @ 8% on (a) @ 10% on @ 12% on
(a) (a) 53.62 67.03 80.43
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 72.39 73.73 75.07
Rate per1000 Nos = a+b+c 0.80 0.81 0.83
Say 1.00 1.00 1.00
2.04 (vii) Scraping of Stone from Dismantled Stone Masonry
Unit = cum
Taking output = 1 cum
A In cement and lime mortar
a) Labour
Mate day 0.056 0.056 0.056 617.00 34.55 34.55 34.55 L-12
Mazdoor day 1.400 1.400 1.400 511.52 716.13 716.13 716.13 L-13
b) Overhead charges @ 8% on (a) @ 10% on @ 12% on
(a) (a) 60.05 75.07 90.08
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 81.07 82.57 84.08
Rate per cum = a+b+c 891.81 908.32 924.84
Say 892.00 908.00 925.00
2.04 B In Mud mortar
a) Labour
Mate day 0.012 0.012 0.012 617.00 7.40 7.40 7.40 L-12
Mazdoor day 0.300 0.300 0.300 511.52 153.46 153.46 153.46 L-13
b) Overhead charges @ 8% on (a) @ 10% on @ 12% on
(a) (a) 12.87 16.09 19.30
c) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b) (a+b) (a+b) 17.37 17.69 18.02
Rate per cum = a+b+c 191.10 194.64 198.18
Say 191.00 195.00 198.00
2.04 (viii) Scarping Plaster in Lime or Cement Mortar from Brick/
Stone Masonry
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Mazdoor for scarping and loading day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
b) Machinery
Tractor-trolley hour 0.308 0.308 0.308 1,876.50 578.59 578.59 578.59 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 217.87 272.34 326.81
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 294.13 299.57 305.02
Cost for 100 sqm = a+b+c+d 3,235.38 3,295.30 3,355.21
Rate per sqm = (a+b+c+d)/100 32.35 32.95 33.55
Say 32.00 33.00 34.00
2.04 (ix) Removing all type of Hume Pipes and Stacking within a
lead of 1000 metres including Earthwork and
Dismantling of Masonry Works.
A Up to 600 mm dia
Unit = metre
Taking output = 15 metre
a) Labour
Mate day 0.084 0.094 0.105 617.00 51.83 58.00 64.79 L-12
Mazdoor day 2.088 2.346 2.617 511.52 1,068.05 1,200.03 1,338.65 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 2.176 3,420.00 7,441.92 P&M-007
(ii) 1.1 cum bucket capacity hour 2.693 3,074.00 8,278.28 P&M-008
(iii) 0.9 cum bucket capacity hour 3.235 2,782.00 8,999.77 P&M-009
Tipper
For loading & Unloding Time & For transportation of
excess material to dumping yard considering lead @
1km
(i) 18 cum capacity hour 2.226 2,883.30 6,418.23 P&M-014
(ii) 14 cum capacity hour 2.743 2,556.75 7,013.17 P&M-015
(iii) 10 cum capacity hour 3.285 2,274.30 7,471.08 P&M-016
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 1,198.40 1,654.95 2,144.91
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 1,617.84 1,820.44 2,001.92
Quantity Amount (Rs.)
Ref.to
Rate Remarks
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project /Input ref.
Specification Project Project Project Project
Tractor-trolley hour 0.167 0.167 0.167 1,876.50 313.38 313.38 313.38 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 89.41 111.77 134.12
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 120.71 122.94 125.18
Rate per cum = a+b+c+d 1,327.80 1,352.39 1,376.98
Say 1,328.00 1,352.00 1,377.00
2.05 B Granular courses
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor for dismantling, loading and unloading. day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Tractor-trolley hour 0.167 0.167 0.167 1,876.50 313.38 313.38 313.38 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 67.97 84.96 101.95
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 91.75 93.45 95.15
Rate per cum = a+b+c+d 1,009.30 1,027.99 1,046.68
Say 1,009.00 1,028.00 1,047.00
2.05 Dismantling of flexible pavements and disposal of
dismantled materials up to a lead of 1000 metres,
stacking serviceable and unserviceable materials
separately
(ii) By Mechanical Means
A Bituminous courses
Unit = cum
Taking output = 20 cum
a) Labour
Mate day 0.024 0.027 0.033 617.00 14.81 16.66 20.36 L-12
Mazdoor for dismantling, loading and unloading day 0.588 0.667 0.833 511.52 300.77 341.18 426.10 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity considering output 85 hour 2.353 P&M-007
sqm/8.5 cum per hour 3,420.00 8,047.26
(ii) 1.1 cum bucket capacity considering output 75 hour 2.667 P&M-008
sqm/7.5 cum per hour 3,074.00 8,198.36
(iii) 0.9 cum bucket capacity considering output 60 hour 3.333 P&M-009
sqm/6 cum per hour 2,782.00 9,272.41
Tipper for transportation
(i) 18 cum capacity t.km 46.000 6.18 284.21 P&M-117
(ii) 14 cum capacity t.km 46.000 7.01 322.59 P&M-120
(iii) 10 cum capacity t.km 46.000 8.66 398.54 P&M-123
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 691.76 887.88 1,214.09
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 933.88 976.67 1,133.15
Rate for 20 metre = a+b+c+d 10,272.70 10,743.34 12,464.65
Rate per metre = (a+b+c+d)/20 513.63 537.17 623.23
Say 514.00 537.00 623.00
B Granular courses
Unit = cum
Taking output = 250 cum
a) Labour
Mate day 0.029 0.033 0.046 617.00 17.72 20.41 28.54 L-12
Mazdoor for dismantling, loading and unloading day 0.718 0.827 1.156 511.52 367.35 423.06 591.46 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 2.873 3,420.00 9,824.39 P&M-007
(ii) 1.1 cum bucket capacity hour 3.308 3,074.00 10,169.64 P&M-008
(iii) 0.9 cum bucket capacity hour 4.625 2,782.00 12,867.06 P&M-009
Tipper for transportation
(i) 18 cum capacity t.km 575.000 6.18 3,552.64 P&M-117
(ii) 14 cum capacity t.km 575.000 7.01 4,032.36 P&M-120
(iii) 10 cum capacity t.km 575.000 8.66 4,981.80 P&M-123
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 1,100.97 1,464.55 2,216.26
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 1,486.31 1,611.00 2,068.51
Rate for 250 metre = a+b+c+d 16,349.38 17,721.03 22,753.64
Rate per metre = (a+b+c+d)/250 65.40 70.88 91.01
Say 65.00 71.00 91.00
2.06 202 Dismantling of Cement Concrete Pavement
Quantity Amount (Rs.)
Ref.to
Rate Remarks
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project /Input ref.
Specification Project Project Project Project
Unit = cum
Taking output = 60 cum
a) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 6.841 3,420.00 23,396.22 P&M-007
(ii) 1.1 cum bucket capacity hour 8.048 3,074.00 24,739.55 P&M-008
(iii) 0.9 cum bucket capacity hour 9.121 2,782.00 25,374.62 P&M-009
Jack Hammer hour 6.841 9.145 12.161 206.00 1,409.25 1,883.96 2,505.23 P&M-010
Air Compressor 250 cfm with 2 leads of pneumatic hour 2.880 2.880 2.880 P&M-029
breaker @ 1 cum per hour 614.25 1,769.04 1,769.04 1,769.04
Pneumatic breaker hour 5.760 5.760 5.760 206.00 1,186.56 1,186.56 1,186.56 P&M-010
Concrete Joint Cutting Machine hour 8.000 8.000 8.000 1,251.00 10,008.00 10,008.00 10,008.00 P&M-098
Tipper
For transportation to dumping yard considering lead @
1km
(i) 18 cum capacity t.km 180.000 6.18 1,112.13 P&M-117
(ii) 14 cum capacity t.km 180.000 7.01 1,262.30 P&M-120
(iii) 10 cum capacity t.km 180.000 8.66 1,559.52 P&M-123
For Loading & unloading charges for disposed of
grabbed material
(i) Using by 18 cum capacity Tipper & 3.1 Cum cum 72.000 P&M-129
capacity Loader 92.72 6,676.01
(ii) Using by 14 cum capacity Tipper & 2.1 Cum cum 72.000 P&M-130
capacity Loader 92.81 6,682.50
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 72.000 P&M-131
Loader 118.14 8,506.08
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 3,773.26 4,914.05 6,302.12
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 5,093.91 5,405.46 5,881.98
Cost for 60 cum = a+b+c+d 56,032.98 59,460.03 64,701.75
Rate per cum = (a+b+c+d)/ 60 933.88 991.00 1,078.36
Say 934.00 991.00 1,078.00
2.07 202 Dismantling of Guard Rails
Dismantling guard rails by manual means and disposal
of dismantled material with all lifts and up to a lead of
1000 metres, stacking serviceable materials and
unserviceable materials separately.
Unit = Each
Taking output = one KM stone
A 5th KM stone
Quantity of cement concrete = 0.392 cum
a) Labour
Mate day 0.030 0.030 0.030 617.00 18.51 18.51 18.51 L-12
Mazdoor day 0.750 0.750 0.750 511.52 383.64 383.64 383.64 L-13
b) Machinery
Tractor-trolley hour 0.150 0.150 0.150 1,876.50 281.48 281.48 281.48 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 54.69 68.36 82.04
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 73.83 75.20 76.57
Rate for one 5th KM stone = a+b+c+d 812.15 827.19 842.23
Say 812.00 827.00 842.00
B Ordinary KM Stone
Quantity of cement concrete = 0.269 cum
a) Labour
Mate day 0.020 0.020 0.020 617.00 12.34 12.34 12.34 L-12
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
b) Machinery
Tractor-trolley hour 0.100 0.100 0.100 1,876.50 187.65 187.65 187.65 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 36.46 45.58 54.69
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 49.22 50.13 51.04
Rate for one ordinary KM stone = a+b+c+d 541.43 551.46 561.48
Say 541.00 551.00 561.00
C Hectometre Stone
Quantity of cement concrete = 0.048 cum
a) Labour
Mate day 0.004 0.004 0.004 617.00 2.47 2.47 2.47 L-12
Mazdoor day 0.100 0.100 0.100 511.52 51.15 51.15 51.15 L-13
b) Machinery
Tractor-trolley hour 0.020 0.020 0.020 1,876.50 37.53 37.53 37.53 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on
(a+b) (a+b) (a+b) 7.29 9.12 10.94
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 9.84 10.03 10.21
Rate for one Hectometre stone = a+b+c+d 108.29 110.29 112.30
Say 108.00 110.00 112.00
2.11 202 Dismantling of Fencing
Quantity Amount (Rs.)
Ref.to
Rate Remarks
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project /Input ref.
Specification Project Project Project Project
Unit = each
Taking output = 30 Nos
a) Labour
Mate day 0.480 0.480 0.480 617.00 296.16 296.16 296.16 L-12
Mazdoor day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-13
Electrician/Lineman day 2.000 2.000 2.000 738.00 1,476.00 1,476.00 1,476.00 L-02
b) Machinery
Tractor-trolley hour 1.500 1.500 1.500 1,876.50 2,814.75 2,814.75 2,814.75 P&M-026
c) Overhead charges for large @ 10% on @ 12% on
Project @ 8% (a+b) (a+b) 776.17 970.21 1,164.25
on (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
(a+b+c) (a+b+c) (a+b+c) 1,047.83 1,067.23 1,086.64
Cost for 30 poles = a+b+c+d 11,526.11 11,739.55 11,953.00
Rate per pole = (a+b+c+d)/30 384.20 391.32 398.43
Say 384.00 391.00 398.00
All the serviceable material resulting from removal of
Note: Telephone / Electric Poles and Lines would be handed
over to the employer.
CHAPTER-3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Unit = cum
Taking output = 120 cum
a) Labour
Mate day 1.800 1.800 1.800 617.00 1,110.60 1,110.60 1,110.60 L-12
Mazdoor day 45.000 45.000 45.000 511.52 23,018.40 23,018.40 23,018.40 L-13
b) Machinery
Truck 5.5 cum capacity hour 9.236 9.236 9.236 1,731.45 15,992.30 15,992.30 15,992.30 P&M-017
@ 8% on @ 10% on @ 12% on 3,209.70 4,012.13 4,814.56
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 4,333.10 4,413.34 4,493.59
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost of 120 cum = a+b+c+d 47,664.11 48,546.78 49,429.44
Rate per cum = (a+b+c+d)/120 397.20 404.56 411.91
Say 397.00 405.00 412.00
Note In case there is a situation where the cross-section is of
cut and fill and cut earth is required to be used in
embankment in the immediate vicinity, the item of carriage
in the truck shall be omitted.
3.03 301
Excavation in Soil with Dozer with lead upto 1000 metres
Unit = cum
Taking output = 500 cum 800 Tonne
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Dozer
Dozer (240HP) hour 3.731 6,586.65 24,577.05 P&M-001
Dozer (175 HP) hour 5.342 5,087.25 27,175.48 P&M-002
Dozer (90 HP) hour 8.621 3,502.80 30,196.55 P&M-003
Tipper
(i) 18 cum capacity t.km 800.000 6.18 4,942.80 P&M-117
(ii) 14 cum capacity t.km 800.000 7.01 5,610.24 P&M-120
(iii) 10 cum capacity t.km 800.000 8.66 6,931.20 P&M-123
Loading & unloading charges
(i) Using by 18 cum capacity Tipper & 3.1 Cum capacity cum 500.000 92.72 46,361.18 P&M-129
Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum capacity cum 500.000 92.81 46,406.25 P&M-130
Loader
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 500.000 118.14 59,070.00 P&M-131
Loader
Unit = cum
Taking output = 300 cum 720 Tonne
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Dozer
Dozer (240HP) hour 4.688 6,586.65 30,878.22 P&M-001
Dozer (175 HP) hour 6.667 5,087.25 33,916.70 P&M-002
Dozer (90 HP) hour 10.714 3,502.80 37,529.00 P&M-003
Tipper
For transportation considering lead @ 1km
(i) 18 cum capacity t.km 720.000 6.18 4,448.52 P&M-117
(ii) 14 cum capacity t.km 720.000 7.01 5,049.22 P&M-120
(iii) 10 cum capacity t.km 720.000 8.66 6,238.08 P&M-123
For Loading & unloading charges
(i) Using by 18 cum capacity Tipper & 3.1 Cum capacity cum 360.000 92.72 33,380.05 P&M-129
Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum capacity cum 360.000 92.81 33,412.50 P&M-130
Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 360.000 118.14 42,530.40 P&M-131
Loader
@ 8% on @ 10% on @ 12% on 5,539.44 7,291.46 10,420.04
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 7,478.24 8,020.61 9,725.37
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 300 cum = a+b+c+d 82,260.66 88,226.68 106,979.09
Rate per cum = (a+b+c+d)/300 274.20 294.09 356.60
Say 274.00 294.00 357.00
3.05 301 Excavation in Hard Rock (requiring blasting) with
disposal upto 1000 metres
Unit = cum
Taking output = 180 cum 360 Tonne
a) Labour
Mate day 0.210 0.210 0.210 617.00 129.57 129.57 129.57 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Driller day 2.000 2.000 2.000 558.00 1,116.00 1,116.00 1,116.00 L-06
Blaster day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-03
b) Machinery
Air Compressor 250 cfm hour 27.500 27.500 27.500 614.25 16,891.88 16,891.88 16,891.88 P&M-029
hour 55.000 55.000 55.000 11.55 635.25 635.25 635.25 P&M-078
Pneumatic breaker for drilling holes (@ 4.5 m per hour)
Dozer
Dozer (240HP) hour 3.375 6,586.65 22,229.94 P&M-001
Dozer (175 HP) hour 4.800 5,087.25 24,418.80 P&M-002
Dozer (90 HP) hour 7.714 3,502.80 27,021.60 P&M-003
Tipper
For transportation considering lead @ 1km
(i) 18 cum capacity t.km 360.000 7.51 2,703.09 P&M-117
(ii) 14 cum capacity t.km 360.000 8.52 3,068.10 P&M-120
(iii) 10 cum capacity t.km 360.000 10.53 3,790.50 P&M-123
For loading & unloading charges
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
(i) Using by 18 cum capacity Tipper & 3.1 Cum capacity cum 216.000 92.72 20,028.03 P&M-129
Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum capacity cum 216.000 92.81 20,047.50 P&M-130
Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 216.000 118.14 25,518.24 P&M-131
Loader
c) Materials
Small dia.Explosive at 0.40 kg / cum for 180 cum ( 180 x kg 73.800 73.800 73.800 81.90 6,044.22 6,044.22 6,044.22 M-215
0.40 )
Explosive at 0.20 kg / cum for secondary blast @ 5%of the
total volume ( 180 x 0.2x5% )
Electric detonators at 1 per hole for main blast holes no 103.000 103.000 103.000 21.00 2,163.00 2,163.00 2,163.00 M-217
(21x3+20*2)=103 nos
Ordinary detonators @ 1 per hole for 10 secondary no 10.000 10.000 10.000 21.00 210.00 210.00 210.00 M-216
holes( required for 5% of the total quantity @ 0.6 m per
hole for I cum )
Detonating fuse coil m 320.000 320.000 320.000 19.00 6,080.00 6,080.00 6,080.00 M-218
Credit for excavated rock found suitable for use @ 50 per cum 90.000 90.000 90.000 319.70 28,773.00 28,773.00 28,773.00 M-090
cent quantity blasted
@ 8% on @ 10% on @ 12% on 8,693.31 11,123.98 14,404.28
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 11,735.97 12,236.37 13,444.00
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 180 cum = a+b+c+d+e 129,095.71 134,600.10 147,883.98
Rate per cum = (a+b+c+d+e)/180 717.20 747.78 821.58
Say 717.00 748.00 822.00
Note 1. The quality and availability of rock shall be checked
before affording credit.
Unit = cum
Taking output = 350 cum
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.926 3,420.00 13,426.67 P&M-007
(ii) 1.1 cum bucket capacity hour 5.024 3,074.00 15,442.79 P&M-008
(iii) 0.9 cum bucket capacity hour 6.321 2,782.00 17,584.99 P&M-009
Tipper
For transportation considering lead @ 1 km
(i) 18 cum capacity t.km 525.000 6.18 3,243.71 P&M-117
(ii) 14 cum capacity t.km 525.000 7.01 3,681.72 P&M-120
(iii) 10 cum capacity t.km 525.000 8.66 4,548.60 P&M-123
For loading & unloading time
(i) 18 cum capacity hour 3.926 2,883.30 11,319.62 P&M-014
(ii) 14 cum capacity hour 5.024 2,556.75 12,844.29 P&M-015
(iii) 10 cum capacity hour 6.321 2,274.30 14,375.82 P&M-016
@ 8% on @ 10% on @ 12% on 2,282.10 3,250.50 4,445.47
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 3,080.83 3,575.55 4,149.11
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 350 cum = a+b+c+d 33,889.13 39,331.05 45,640.19
Rate per cum = (a+b+c+d)/350 96.83 112.37 130.40
Say 97.00 112.00 130.00
3.07 301
Excavation in Ordinary Rock using Hydraulic Excavator
and Tippers with Disposal upto 1000 metres.
Unit = cum
Taking output = 60 cum 120 Tonne
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator for Jack Hammer
(i) 1.2 cum bucket capacity hour 6.982 3,420.00 23,878.44 P&M-007
(ii) 1.1 cum bucket capacity hour 8.214 3,074.00 25,249.84 P&M-008
(iii) 0.9 cum bucket capacity hour 8.727 2,782.00 24,278.51 P&M-009
Jack Hammer hour 6.982 8.214 8.727 206.00 1,438.25 1,692.06 1,797.82 P&M-010
Tipper
For transportation considering lead @ 1km
(i) 18 cum capacity t.km 120.000 6.18 741.42 P&M-117
(ii) 14 cum capacity t.km 120.000 7.01 841.54 P&M-120
(iii) 10 cum capacity t.km 120.000 8.66 1,039.68 P&M-123
For loading & unloading charges for disposed of grabbed
material
(i) Using by 18 cum capacity Tipper & 3.1 Cum capacity cum 72.000 92.72 6,676.01 P&M-129
Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum capacity cum 72.000 92.81 6,682.50 P&M-130
Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 72.000 118.14 8,506.08 P&M-131
Loader
@ 8% on @ 10% on @ 12% on 2,661.63 3,500.21 4,339.00
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 3,593.19 3,850.23 4,049.73
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 60 cum = a+b+c+d 39,525.14 42,352.58 44,547.02
Rate per cum = (a+b+c+d)/60 658.75 705.88 742.45
Say 659.00 706.00 742.00
3.08 301 Excavation in Hard Rock (blasting prohibited)
A Unit = cum
Taking output = 50 cum 100 Tonne
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator for Jack Hammer
(i) 1.2 cum bucket capacity hour 8.533 3,420.00 29,184.00 P&M-007
(ii) 1.1 cum bucket capacity hour 10.039 3,074.00 30,859.89 P&M-008
(iii) 0.9 cum bucket capacity hour 11.378 2,782.00 31,652.98 P&M-009
Jack Hammer hour 8.533 10.039 11.378 206.00 1,757.87 2,068.08 2,343.82 P&M-010
Tipper
For transportation considering lead @ 1km
(i) 18 cum capacity t.km 100.000 6.18 617.85 P&M-117
(ii) 14 cum capacity t.km 100.000 7.01 701.28 P&M-120
(iii) 10 cum capacity t.km 100.000 8.66 866.40 P&M-123
For loading & unloading charges for disposed of grabbed
material
(i) Using by 18 cum capacity Tipper & 3.1 Cum capacity cum 60.000 92.72 5,563.34 P&M-129
Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum capacity cum 60.000 92.81 5,568.75 P&M-130
Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 60.000 118.14 7,088.40 P&M-131
Loader
Credit for excavated rock found suitable for use @ 50 per cum 25.000 25.000 25.000 319.70 -7,992.50 -7,992.50 -7,992.50 M-090
cent of excavated quantity
@ 8% on @ 10% on @ 12% on 2,373.34 3,174.17 4,139.44
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 3,204.01 3,491.59 3,863.47
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 50 cum = a+b+c+d 35,244.11 38,407.45 42,498.21
Rate per cum = (a+b+c+d)/50 704.88 768.15 849.96
Say 705.00 768.00 850.00
3.08 B Manual Method
Unit = cum
Taking output = 16 cum
a) Labour
Mate day 1.640 1.640 1.640 617.00 1,011.88 1,011.88 1,011.88 L-12
Mazdoor including loading in truck day 16.000 16.000 16.000 511.52 8,184.32 8,184.32 8,184.32 L-13
Chiseller day 24.000 24.000 24.000 617.00 14,808.00 14,808.00 14,808.00 L-05
Blacksmith (IInd class) day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-01
b) Machinery
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Tipper 5.5 cum capacity, 1 trip per hour. hour 2.900 2.900 2.900 1,731.45 5,021.21 5,021.21 5,021.21 P&M-017
Credit for excavated rock found suitable for use @ 50 per cum 8.000 8.000 8.000 319.70 -2,557.60 -2,557.60 -2,557.60 M-090
cent of excavated
@ 8% on @ 10% on @ 12% on 2,171.74 2,714.68 3,257.62
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 2,931.85 2,986.15 3,040.44
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 16 cum = a+b+c+d 32,250.40 32,847.63 33,444.86
Rate per cum = (a+b+c+d)/16 2,015.65 2,052.98 2,090.30
Say 2,016.00 2,053.00 2,090.00
Note
1. Credit is considered for 50 per cent of quantity of work.
Unit = cum
Taking output = 180 cum 360 Tonne
a) Labour
Mate day 0.210 0.210 0.210 617.00 129.57 129.57 129.57 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Driller day 2.000 2.000 2.000 558.00 1,116.00 1,116.00 1,116.00 L-06
Blaster day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-03
b) Machinery
Air Compressor 250 cfm hour 27.500 27.500 27.500 614.25 16,891.88 16,891.88 16,891.88 P&M-029
hour 55.000 55.000 55.000 11.55 635.25 635.25 635.25 P&M-078
Pneumatic breaker for drilling holes (@ 4.5 m per hour)
Dozer
Dozer (240HP) hour 3.375 6,586.65 22,229.94 P&M-001
Dozer (175 HP) hour 4.320 5,087.25 21,976.92 P&M-002
Dozer (90 HP) hour 7.714 3,502.80 27,021.60 P&M-003
Tipper
For transportation considering lead @ 1km
(i) 18 cum capacity t.km 360.000 7.51 2,703.09 P&M-117
(ii) 14 cum capacity t.km 360.000 8.52 3,068.10 P&M-120
(iii) 10 cum capacity t.km 360.000 10.53 3,790.50 P&M-123
For loading & unloading charges
(i) Using by 18 cum capacity Tipper & 3.1 Cum capacity cum 216.000 92.72 20,028.03 P&M-129
Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum capacity cum 216.000 92.81 20,047.50 P&M-130
Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 216.000 118.14 25,518.24 P&M-131
Loader
c) Materials
Small dia.Explosive at 0.40 kg / cum for 180 cum ( 180 x kg 73.800 73.800 73.800 81.90 6,044.22 6,044.22 6,044.22 M-215
0.40 )
Explosive at 0.20 kg / cum for secondary blast @ 5%of the
total volume ( 180 x 0.2x5% )
Electric detonators at 1 per hole for main blast holes no 103.000 103.000 103.000 21.00 2,163.00 2,163.00 2,163.00 M-217
(21x3+20*2)=103 nos
Ordinary detonators @ 1 per hole for 10 secondary no 10.000 10.000 10.000 21.00 210.00 210.00 210.00 M-216
holes( required for 5% of the total quantity @ 0.6 m per
hole for I cum )
Detonating fuse coil m 320.000 320.000 320.000 19.00 6,080.00 6,080.00 6,080.00 M-218
Credit for excavated rock found suitable for use @ 50 per cum 90.000 90.000 90.000 319.70 28,773.00 28,773.00 28,773.00 M-090
cent quantity blasted
Add 5 per cent of cost of a+b+c towards muffling
arrangements to guard against any rock fly off during 5,433.32 5,439.89 6,001.78
blasting
@ 8% on @ 10% on @ 12% on 9,127.98 11,423.78 15,124.50
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 12,322.77 12,566.15 14,116.20
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 180 cum = a+b+c+d+e 135,550.49 138,227.70 155,278.18
Rate per cum = (a+b+c+d+e)/180 753.06 767.93 862.66
Say 753.00 768.00 863.00
Note 1. The quality and availability of rock shall be checked
before affording credit.
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
3.10 301
Excavation in Marshy Soil using Hydraulic Excavator and
Tippers with Disposal upto 1000 metres.
Unit = cum
Taking output = 325 cum 487.5 Tonne
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 8.506 3,420.00 29,091.11 P&M-007
(ii) 1.1 cum bucket capacity hour 9.796 3,074.00 30,113.44 P&M-008
(iii) 0.9 cum bucket capacity hour 13.695 2,782.00 38,100.81 P&M-009
Tipper
For transportation to dumping yard considering lead @
1km
(i) 18 cum capacity t.km 487.500 6.18 3,012.02 P&M-117
(ii) 14 cum capacity t.km 487.500 7.01 3,418.74 P&M-120
(iii) 10 cum capacity t.km 487.500 8.66 4,223.70 P&M-123
For loading & unloading time
(i) 18 cum capacity hour 8.506 2,883.30 24,525.85 P&M-014
(ii) 14 cum capacity hour 9.796 2,556.75 25,046.37 P&M-015
(iii) 10 cum capacity hour 13.695 2,274.30 31,147.61 P&M-016
@ 8% on @ 10% on @ 12% on 4,573.21 5,911.47 8,881.00
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 6,173.84 6,502.62 8,288.93
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 325 cum = a+b+c+d 67,912.23 71,528.84 91,178.25
Rate per cum = (a+b+c+d)/325 208.96 220.09 280.55
Say 209.00 220.00 281.00
3.11 301 Removal of Unserviceable Soil with Disposal upto 1000
metres
Removal of unserviceable soil including excavation,
loading and disposal upto 1000 metres lead but excluding
replacement by suitable soil which shall be paid separately
as per clause 305.
Unit = cum
Taking output = 415 cum 622.5 Tonne
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 4.769 3,420.00 16,309.98 P&M-007
(ii) 1.1 cum bucket capacity hour 5.492 3,074.00 16,882.41 P&M-008
(iii) 0.9 cum bucket capacity hour 7.678 2,782.00 21,360.20 P&M-009
Tipper
For transportation to dumping yard considering lead @
1km
(i) 18 cum capacity t.km 622.500 6.18 3,846.12 P&M-117
(ii) 14 cum capacity t.km 622.500 7.01 4,365.47 P&M-120
(iii) 10 cum capacity t.km 622.500 8.66 5,393.34 P&M-123
For loading & unloading time
(i) 18 cum capacity hour 4.769 2,883.30 13,750.46 P&M-014
(ii) 14 cum capacity hour 5.492 2,556.75 14,041.67 P&M-015
(iii) 10 cum capacity hour 7.678 2,274.30 17,462.08 P&M-016
@ 8% on @ 10% on @ 12% on 2,755.42 3,582.57 5,370.22
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 3,719.82 3,940.83 5,012.20
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 415 cum = a+b+c+d 40,917.99 43,349.15 55,134.23
Rate per cum = (a+b+c+d)/415 98.60 104.46 132.85
Say 99.00 104.00 133.00
3.12 303 Presplitting of Rock Excavation Slopes
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Unit = Sqm
Taking output = 400 sqm 240 Tonne
a) Labour
Mate day 0.210 0.210 0.210 617.00 129.57 129.57 129.57 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Driller day 2.000 2.000 2.000 558.00 1,116.00 1,116.00 1,116.00 L-06
Blaster day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-03
b) Machinery
Air Compressor 250 cfm hour 17.000 17.000 17.000 614.25 10,442.25 10,442.25 10,442.25 P&M-029
hour 34.000 34.000 34.000 11.55 392.70 392.70 392.70 P&M-078
Pneumatic breaker for drilling holes (@ 4.5 m per hour)
Dozer
(i) Dozer (240HP) hour 1.875 6,586.65 12,349.97 P&M-001
(ii) Dozer (175 HP) hour 2.400 5,087.25 12,209.40 P&M-002
(iii) Dozer (90 HP) hour 4.286 3,502.80 15,012.00 P&M-003
Tipper
For transportation considering lead @ 1km
(i) 18 cum capacity t.km 240.000 6.18 1,482.84 P&M-117
(ii) 14 cum capacity t.km 240.000 7.01 1,683.07 P&M-120
(iii) 10 cum capacity t.km 240.000 8.66 2,079.36 P&M-123
For Loading & unloading charges
(i) Using by 18 cum capacity Tipper & 3.1 Cum capacity cum 144.000 92.72 13,352.02 P&M-129
Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum capacity cum 144.000 92.81 13,365.00 P&M-130
Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 144.000 118.14 17,012.16 P&M-131
Loader
c) Materials
Small dia.Explosive at 0.40 kg / cum for 400 cum ( 400 x kg 49.200 49.200 49.200 81.90 4,029.48 4,029.48 4,029.48 M-215
0.40 )
Explosive at 0.20 kg / cum for secondary blast @ 5%of the
total volume ( 400 x 0.2x5% )
Electric detonators at 1 per hole for main blast holes no 69.000 69.000 69.000 21.00 1,449.00 1,449.00 1,449.00 M-217
(21x3+20*2)=103 nos
Ordinary detonators @ 1 per hole for 10 secondary no 7.000 7.000 7.000 21.00 147.00 147.00 147.00 M-216
holes( required for 5% of the total quantity @ 0.6 m per
hole for I cum )
Detonating fuse coil m 213.000 213.000 213.000 19.00 4,047.00 4,047.00 4,047.00 M-218
Credit for excavated rock found suitable for use @ 50 per cum 60.000 60.000 60.000 319.70 19,182.00 19,182.00 19,182.00 M-090
cent quantity blasted
@ 8% on @ 10% on @ 12% on 5,582.58 6,985.49 9,204.12
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 7,536.48 7,684.04 8,590.51
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 400 Sqm = a+b+c+d+e 82,901.33 84,524.44 94,495.58
Rate per cum = (a+b+c+d+e)/400 207.25 211.31 236.24
Say 207.00 211.00 236.00
Note 1. The quality and availability of rock shall be checked
before affording credit.
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
@ 8% on (a) @ 10% on (a) @ 12% on (a) 343.17 428.96 514.75
b) Overhead charges
@ 10% on @ 10% on @ 10% on 463.28 471.86 480.44
c) Contractor's profit (a+b) (a+b) (a+b)
Cost for 10 cum = a+b+c 5,096.04 5,190.42 5,284.79
Rate per cum = (a+b+c)/10 509.60 519.04 528.48
Say 510.00 519.00 528.00
Note Cost of dewatering may be added where required upto 10
per cent of labour cost Assessment for dewatering shall
be made as per site conditions..
Unit = cum
Taking output = 120 cum
a) Labour
Mate day 0.210 0.210 0.210 617.00 129.57 129.57 129.57 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Driller day 2.000 2.000 2.000 558.00 1,116.00 1,116.00 1,116.00 L-06
Blaster day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-03
b) Machinery
hour 17.000 17.000 17.000 637.35 10,834.95 10,834.95 10,834.95 P&M-029 +
P&M-078 x 2
Air Compressor 250 cfm
Tipper
For transportation considering lead @ 1km
(i) 18 cum capacity t.km 96.000 6.18 593.14 P&M-117
(ii) 14 cum capacity t.km 96.000 7.01 673.23 P&M-120
(iii) 10 cum capacity t.km 96.000 8.66 831.74 P&M-123
For loading & unloading time
(i) 18 cum capacity hour 1.005 2,883.30 2,897.82 P&M-014
(ii) 14 cum capacity hour 1.157 2,556.75 2,959.32 P&M-015
(iii) 10 cum capacity hour 1.618 2,274.30 3,680.21 P&M-016
c) Materials
Small dia.Explosive at 0.40 kg / cum for 120 cum ( 120 x kg 49.200 49.200 49.200 81.90 4,029.48 4,029.48 4,029.48 M-215
0.40 )
Explosive at 0.20 kg / cum for secondary blast @ 5%of the
total volume ( 120 x 0.2x5% )
Electric detonators at 1 per hole for main blast holes no 69.000 69.000 69.000 21.00 1,449.00 1,449.00 1,449.00 M-217
(21x3+20*2)=103 nos
Ordinary detonators @ 1 per hole for 10 secondary no 7.000 7.000 7.000 21.00 147.00 147.00 147.00 M-216
holes( required for 5% of the total quantity @ 0.6 m per
hole for I cum )
Detonating fuse coil m 213.000 213.000 213.000 19.00 4,047.00 4,047.00 4,047.00 M-218
@ 8% on @ 10% on @ 12% on 3,152.49 4,028.52 5,206.63
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 4,255.86 4,431.38 4,859.52
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 120 cum = a+b+c+d+e 46,814.41 48,745.14 53,454.77
Rate per cum = (a+b+c+d+e)/120 390.12 406.21 445.46
Say 390.00 406.00 445.00
3.13 (iv) Hard Rock ( blasting prohibited )
Unit = cum
Taking output = 35 cum
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
(i) 1.2 cum bucket capacity hour 9.571 3,420.00 32,731.79 P&M-007
(ii) 1.1 cum bucket capacity hour 11.244 3,074.00 34,564.06 P&M-008
(iii) 0.9 cum bucket capacity hour 13.783 2,782.00 38,344.31 P&M-009
Jack Hammer hour 8.960 10.541 12.800 206.00 1,845.76 2,171.48 2,636.80 P&M-010
Tipper
For transportation to dumping yard considering lead @
1km
(i) 18 cum capacity t.km 28.000 6.18 173.00 P&M-117
(ii) 14 cum capacity t.km 28.000 7.01 196.36 P&M-120
(iii) 10 cum capacity t.km 28.000 8.66 242.59 P&M-123
For loading & unloading
(i) 18 cum capacity hour 0.244 2,883.30 704.33 P&M-014
(ii) 14 cum capacity hour 0.281 2,556.75 718.78 P&M-015
(iii) 10 cum capacity hour 0.393 2,274.30 894.25 P&M-016
@ 8% on @ 10% on @ 12% on 2,922.18 3,872.31 5,182.84
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 3,944.95 4,259.54 4,837.32
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 35 cum = a+b+c+d 43,394.41 46,854.92 53,210.51
Rate per cum = (a+b+c+d)/35 1,239.84 1,338.71 1,520.30
Say 1,240.00 1,339.00 1,520.00
3.13 (v) Marshy soil
Unit = cum
Taking output = 10 cum
A Manual means ( upto 3 m depth)
a) Labour
Mate/Supervisor day 0.400 0.400 0.400 617.00 246.80 246.80 246.80 L-12
Mazdoor day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-13
b) Machinery
Tractor-trolley hour 2.670 2.670 2.670 1,876.50 5,010.26 5,010.26 5,010.26 P&M-026
c) Material
Selected earth for refilling cum 5.000 5.000 5.000 222.00 1,110.00 1,110.00 1,110.00 M-164
@ 8% on @ 10% on @ 12% on 918.58 1,148.23 1,377.87
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 1,240.08 1,263.05 1,286.01
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 10 cum = a+b+c+d+e 13,640.92 13,893.53 14,146.14
Rate per cum = ( a+b+c+d+e)/ 10 1,364.09 1,389.35 1,414.61
Say 1,364.00 1,389.00 1,415.00
Note 1. Cost of dewatering @ 30 per cent of (a), may be
added, where required Assessment for dewatering shall
be made as per site conditions.
2. Shoring & strutting 20 per cent of (a), where required
may be added
(ii) Using by 14 cum capacity Tipper & 2.1 Cum capacity cum 625.000 92.81 58,007.81 P&M-130
Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 625.000 118.14 73,837.50 P&M-131
Loader
@ 8% on @ 10% on @ 12% on 6,765.25 8,751.96 12,365.52
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 9,133.08 9,627.15 11,541.15
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 12500 sqm = a+b+c+d 100,463.90 105,898.68 126,952.63
Rate per sqm = (a+b+c+d)/12500 8.04 8.47 10.16
Say 8.00 8.00 10.00
Note
In case material is to be reused at site, transportation cost
catered above for disposal shall be deleted.
Unit = cum
Taking output = 450 cum
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 5.048 3,420.00 17,264.16 P&M-007
(ii) 1.1 cum bucket capacity hour 5.813 3,074.00 17,869.16 P&M-008
(iii) 0.9 cum bucket capacity hour 8.127 2,782.00 22,609.31 P&M-009
Tipper
For Transportation
(i) 18 cum capacity t.km 450x1.6 x L2 6.18 4,448.52 P&M-117
(ii) 14 cum capacity t.km 450x1.6 x L2 7.01 5,049.22 P&M-120
(iii) 10 cum capacity t.km 450x1.6 x L2 8.66 6,238.08 P&M-123
For Loading & unloading time
(i) 18 cum capacity hour 5.048 2,883.30 14,554.90 P&M-014
(ii) 14 cum capacity hour 5.813 2,556.75 14,862.39 P&M-015
(iii) 10 cum capacity hour 8.127 2,274.30 18,483.24 P&M-016
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 2.177 5,991.00 13,042.41 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.626 5,497.00 14,435.12 P&M-005
(iii) Motor grader 3.35 metre blade hour 2.929 4,796.00 14,047.48 P&M-006
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 8.364 1,501.00 12,554.36 P&M-023
(ii) 12 KL capacity hour 11.142 1,327.00 14,785.43 P&M-024
(iii) 6 KL capacity hour 22.314 1,005.00 22,425.57 P&M-025
Vibratory roller hour 2.184 2.184 2.184 2,562.00 5,595.41 5,595.41 5,595.41 P&M-022
c) Material
Cost of water (considering 5% additional moisture KL 36.000 36.000 36.000 16.00 576.00 576.00 576.00 M-191
required)
Compensation for earth taken from private land cum 450.000 450.000 450.000 45.00 20,250.00 20,250.00 20,250.00 M-093
@ 8% on @ 10% on @ 12% on 7,148.65 9,449.51 13,355.70
d) Overhead charges (a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on 9,650.68 10,394.46 12,465.32
e) Contractor's profit (a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 450 cum = a+b+c+d+e 106,157.49 114,339.11 137,118.51
Rate per cum = (a+b+c+d+e)/450 235.91 254.09 304.71
Say 236.00 254.00 305.00
Note Compensation for earth will vary from place to place and
will have to be assessed realistically as per particular
ground situation. In case earth is available from Govt.
land, compensation for earth will not be required. The
position is required to be clearly stated in the cost
estimate.
3.17 305 Construction of Embankment with Material Deposited from
Roadway Cutting
Unit = cum
Taking output = 450 cum
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 2.177 5,991.00 13,042.41 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.626 5,497.00 14,435.12 P&M-005
(iii) Motor grader 3.35 metre blade hour 2.929 4,796.00 14,047.48 P&M-006
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 5.864 1,501.00 8,801.86 P&M-023
(ii) 12 KL capacity hour 7.812 1,327.00 10,366.52 P&M-024
(iii) 6 KL capacity hour 15.644 1,005.00 15,722.22 P&M-025
Vibratory roller hour 2.184 2.184 2.184 2,562.00 5,596.60 5,596.60 5,596.60 P&M-022
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
c) Material
Cost of water (considering 5% additional moisture KL 36.000 36.000 36.000 16.00 576.00 576.00 576.00 M-191
required)
@ 8% on @ 10% on @ 12% on 2,284.25 3,151.04 4,377.42
d) Overhead charges (a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on 3,083.73 3,466.15 4,085.59
e) Contractor's profit (a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 450 cum = a+b+c+d+e 33,921.05 38,127.64 44,941.52
Rate per cum = (a+b+c+d+e)/450 75.38 84.73 99.87
Say 75.00 85.00 100.00
3.18 305 Construction of Subgrade and Earthen Shoulders
Construction of sub-grade and earthen shoulders with
approved material obtained from borrow pits with all lifts &
leads, transporting to site, spreading, grading to required
slope and compacted to meet requirement of table No.
300-2
Unit = cum
Taking output = 450 cum
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 5.048 3,420.00 17,264.16 P&M-007
(ii) 1.1 cum bucket capacity hour 5.813 3,074.00 17,869.16 P&M-008
(iii) 0.9 cum bucket capacity hour 8.127 2,782.00 22,609.31 P&M-009
Tipper
For Transportation
(i) 18 cum capacity t.km 450x1.75 x L2 6.18 4,865.57 P&M-117
(ii) 14 cum capacity t.km 450x1.75 x L2 7.01 5,522.58 P&M-120
(iii) 10 cum capacity t.km 450x1.75 x L2 8.66 6,822.90 P&M-123
For Loading & unloading time
(i) 18 cum capacity hour 5.048 2,883.30 14,554.90 P&M-014
(ii) 14 cum capacity hour 5.813 2,556.75 14,862.39 P&M-015
(iii) 10 cum capacity hour 8.127 2,274.30 18,483.24 P&M-016
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 2.177 5,991.00 13,042.41 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.626 5,497.00 14,435.12 P&M-005
(iii) Motor grader 3.35 metre blade hour 2.929 4,796.00 14,047.48 P&M-006
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 9.135 1,501.00 13,711.64 P&M-023
(ii) 12 KL capacity hour 12.210 1,327.00 16,202.67 P&M-024
(iii) 6 KL capacity hour 24.390 1,005.00 24,511.95 P&M-025
Vibratory roller 12 tonne hour 2.184 2.184 2.184 2,562.00 5,595.41 5,595.41 5,595.41 P&M-022
c) Material
Cost of water (considering 5% additional moisture KL 39.375 39.375 39.375 16.00 630.00 630.00 630.00 M-191
required)
Compensation for earth taken from private land cum 450.000 450.000 450.000 45.00 20,250.00 20,250.00 20,250.00 M-093
@ 8% on @ 10% on @ 12% on 7,278.92 9,643.97 13,682.72
d) Overhead charges (a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on 9,826.54 10,608.37 12,770.54
e) Contractor's profit (a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 450 cum = a+b+c+d+e 108,091.93 116,692.07 140,475.96
Rate per cum = (a+b+c+d+e)/450 240.20 259.32 312.17
Say 240.00 259.00 312.00
3.19 305 Construction of Subgrade and Earthen Shoulders with
Material Deposited from Roadway Cutting
Unit = cum
Taking output = 450 cum
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 2.177 5,991.00 13,042.41 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.626 5,497.00 14,435.12 P&M-005
(iii) Motor grader 3.35 metre blade hour 2.929 4,796.00 14,047.48 P&M-006
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 9.135 1,501.00 13,711.64 P&M-023
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Motor grader for ripping & grading
(i) Motor grader 4.30 metre blade hour 3.487 5,991.00 20,888.92 P&M-004
(ii) Motor grader 3.70 metre blade hour 4.197 5,497.00 23,068.78 P&M-005
(iii) Motor grader 3.35 metre blade hour 4.497 4,796.00 21,569.46 P&M-006
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 5.650 1,501.00 8,480.65 P&M-023
(ii) 12 KL capacity hour 7.513 1,327.00 9,969.75 P&M-024
(iii) 6 KL capacity hour 15.027 1,005.00 15,102.14 P&M-025
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
c) Material
Cost of water (considering 5% additional moisture KL 24.000 24.000 24.000 16.00 384.00 384.00 384.00 M-191
required)
@ 8% on @ 10% on @ 12% on 2,721.67 3,768.98 4,958.74
d) Overhead charges (a+b+c) (a+b+c) (a+b+c)
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Unit = cum
Taking output = 250 cum
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Motor grader
(i) Motor grader 4.30 metre blade hour 1.680 5,991.00 10,065.52 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.027 5,497.00 11,140.16 P&M-005
(iii) Motor grader 3.35 metre blade hour 2.260 4,796.00 10,837.65 P&M-006
Hydraulic Excavator for reapplication
(i) 1.2 cum bucket capacity hour 2.804 3,420.00 9,590.48 P&M-007
(ii) 1.1 cum bucket capacity hour 3.230 3,074.00 9,927.51 P&M-008
(iii) 0.9 cum bucket capacity hour 4.515 2,782.00 12,560.71 P&M-009
Tipper
For transportation considering lead @ 1 km (20% of the
material needs to be transported)
(i) 18 cum capacity t.km 75.000 6.18 463.39 P&M-117
(ii) 14 cum capacity t.km 75.000 7.01 525.96 P&M-120
(iii) 10 cum capacity t.km 75.000 8.66 649.80 P&M-123
(i) Using by 18 cum capacity Tipper & 3.1 Cum capacity cum 50.000 92.72 4,636.12 P&M-129
Loader
(ii) Using by 14 cum capacity Tipper & 2.1 Cum capacity cum 50.000 92.81 4,640.63 P&M-130
Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 50.000 118.14 5,907.00 P&M-131
Loader
@ 8% on @ 10% on @ 12% on 2,023.34 2,677.05 3,658.96
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 2,731.50 2,944.75 3,415.03
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 250 sqm = a+b+c+d 30,046.55 32,392.25 37,565.35
Rate per sqm = (a+b+c+d)/250 120.19 129.57 150.26
Say 120.00 130.00 150.00
3.22 305 Stripping, Storing and Re-laying Top Soil from Borrow
Areas in Agriculture Fields.
Unit = cum
Taking output = 250 cum
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Motor grader
(i) Motor grader 4.30 metre blade hour 1.680 5,991.00 10,065.52 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.027 5,497.00 11,140.16 P&M-005
(iii) Motor grader 3.35 metre blade hour 2.260 4,796.00 10,837.65 P&M-006
Hydraulic Excavator for reapplication
(i) 1.2 cum bucket capacity hour 2.804 3,420.00 9,589.68 P&M-007
(ii) 1.1 cum bucket capacity hour 3.230 3,074.00 9,929.02 P&M-008
(iii) 0.9 cum bucket capacity hour 4.515 2,782.00 12,560.73 P&M-009
Tipper
For transportation
(i) 18 cum capacity t.km 250x1.6 x L2 6.18 2,471.40 P&M-117
(ii) 14 cum capacity t.km 250x1.6 x L2 7.01 2,805.12 P&M-120
(iii) 10 cum capacity t.km 250x1.6 x L2 8.66 3,465.60 P&M-123
For loading & unloading
(i) Using by 18 cum capacity Tipper & 3.1 Cum capacity cum 250.000 92.72 23,180.59 P&M-129
Loader
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
(ii) Using by 14 cum capacity Tipper & 2.1 Cum capacity cum 250.000 92.81 23,203.13 P&M-130
Loader
(iii) Using by 10 cum capacity Tipper & 1 Cum capacity cum 250.000 118.14 29,535.00 P&M-131
Loader
@ 8% on @ 10% on @ 12% on 3,667.47 4,761.36 6,832.22
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 4,951.09 5,237.50 6,376.74
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 250 sqm = a+b+c+d 54,461.95 57,612.48 70,144.14
Rate per sqm = (a+b+c+d)/250 217.85 230.45 280.58
Say 218.00 230.00 281.00
3.23 307 Turfing with Sods
Furnishing and laying of the live sods of perennial turf
forming grass on embankment slope, verges or other
locations shown on the drawing or as directed by the
engineer including preparation of ground, fetching of sods
and watering.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Mazdoor for preparation of ground and fetching of sods
b) Machinery
Water tanker including watering for 3 months
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 15.096 1,501.00 22,659.10 P&M-023
(ii) 12 KL capacity hour 20.138 1,327.00 26,723.13 P&M-024
(iii) 6 KL capacity hour 40.246 1,005.00 40,447.23 P&M-025
Tractor-trolley hour 1.000 1.000 1.000 1,876.50 1,876.50 1,876.50 1,876.50 P&M-026
c) Material
Farm yard manure @ 0.18 cum per 100 sqm at site of cum 0.180 0.180 0.180 300.00 54.00 54.00 54.00 M-168
work
Cost of water KL 12.000 12.000 12.000 16.00 192.00 192.00 192.00 M-191
@ 8% on @ 10% on @ 12% on 2,111.22 3,045.42 5,301.40
d) Overhead charges (a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on 2,850.14 3,349.96 4,947.97
e) Contractor's profit (a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 31,351.55 36,849.61 54,427.70
Rate per 100 sqm = (a+b+c+d+e)/100 313.52 368.50 544.28
Say 314.00 368.00 544.00
3.24 308 Seeding and Mulching
Unit = sqm
Taking output = 240 sqm
a) Labour
Mate day 0.400 0.400 0.400 617.00 246.80 246.80 246.80 L-12
Mazdoor day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-13
b) Machinery
Water tanker including watering for 3 months
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 106.613 1,501.00 160,026.11 P&M-023
(ii) 12 KL capacity hour 142.160 1,327.00 188,646.32 P&M-024
(iii) 6 KL capacity hour 284.291 1,005.00 285,712.46 P&M-025
Tractor-trolley hour 2.400 2.400 2.400 1,876.50 4,503.60 4,503.60 4,503.60 P&M-026
c) Material
Seeds kg 3.600 3.600 3.600 84.00 302.40 302.40 302.40 M-163
cum 0.430 0.430 0.430 300.00 129.00 129.00 129.00 M-168
Sludge/Farm yard manure @ 0.18 cum per 100 sqm
Bitumen Emulsion litre 55.200 55.200 55.200 47.66 2,630.96 2,630.96 2,630.96 M-077 /1000
Jute netting, open weave, 2.5 cm square opening sqm 264.000 264.000 264.000 56.00 14,784.00 14,784.00 14,784.00 M-120
Cost of water for 3 months KL 84.000 84.000 84.000 16.00 1,344.00 1,344.00 1,344.00 M-191
@ 8% on @ 10% on @ 12% on 15,126.57 21,770.23 37,772.21
d) Overhead charges (a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on 20,420.86 23,947.25 35,254.06
e) Contractor's profit (a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 240 sqm = a+b+c+d+e 224,629.51 263,419.76 387,794.69
Rate per sqm = (a+b+c+d+e)/240 935.96 1,097.58 1,615.81
Say 936.00 1,098.00 1,616.00
3.25 309 Surface Drains in Soil
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Unit = metre
Taking output = 10 metres 4 Cum
A Mechanical means
a) Labour
Mate day 0.010 0.010 0.010 617.00 6.17 6.17 6.17 L-12
Mazdoor for dressing of bed and side of drain day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
b) Machinery
Hydraulic Excavator 0.9 cum bucket capacity hour 0.090 0.090 0.090 2,782.00 250.38 250.38 250.38 P&M-009
Tractor-trolley
Tractor-trolley for transportation & for loading & Unloding hour 0.246 0.246 0.246 1,876.50 461.62 461.62 461.62 P&M-026
Time
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Machinery
Tractor-trolley
Tractor-trolley for transportation & for loading & Unloding hour 1.044 1.044 1.044 1,876.50 1,959.90 1,959.90 1,959.07 P&M-026
Time
Unit = metre
Taking output = 10 metres
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor for excavation and back filling day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
c) Material
metre 10.000 10.000 10.000 178.00 1,780.00 1,780.00 1,780.00 M-134
Perforated pipe of cement concrete, internal dia 100 mm
Crushed stone as per table 300-3 cum 2.400 2.400 2.400 1,215.07 2,916.17 2,916.17 2,916.17 M-011
d) Overhead charges @ 8% on (a+b+c) 459.51 574.39 689.27
e) Contractor's profit @ 10% on (a+b+c+d) 620.34 631.83 643.32
Cost for 10 metres = a+b+c+d+e 6,823.75 6,950.11 7,076.48
Rate per metre = (a+b+c+d+e)/10 682.37 695.01 707.65
Say 682.00 695.00 708.00
Note Type of pipe may be modified depending upon provision in
design.
b) Material
Crushed stone as per table 300-3 cum 1.350 1.350 1.350 1,215.07 1,640.35 1,640.35 1,640.35 M-011
@ 8% on @ 10% on @ 12% on 195.57 244.46 293.36
c) Overhead charges (a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on 264.02 268.91 273.80
d) Contractor's profit (a+b+c) (a+b+c) (a+b+c)
Cost for 10 metres = a+b+c+d 2,904.24 2,958.02 3,011.81
Rate per metre = (a+b+c+d)/10 290.42 295.80 301.18
Say 290.00 296.00 301.00
3.30 309 Underground Drain at Edge of Pavement
3.31 310
Preparation and Surface Treatment of Formation.
Unit = sqm
Taking output = 3500 sqm 525 Cum
a) Labour
Mate day 0.280 0.280 0.280 617.00 172.76 172.76 172.76 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
b) Machinery
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 4.590 1,501.00 6,889.59 P&M-023
(ii) 12 KL capacity hour 6.130 1,327.00 8,134.51 P&M-024
(iii) 6 KL capacity hour 12.230 1,005.00 12,291.15 P&M-025
Vibratory roller hour 2.549 2.549 2.549 2,562.00 6,529.37 6,529.37 6,529.37 P&M-022
c) Material
Cost of water KL 18.000 18.000 18.000 16.00 288.00 288.00 288.00 M-191
@ 8% on @ 10% on @ 12% on 1,401.17 1,875.95 2,749.94
d) Overhead charges (a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on 1,891.57 2,063.54 2,566.61
e) Contractor's profit (a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 3500 sqm = a+b+c+d+e 20,807.31 22,698.98 28,232.67
Rate per sqm = (a+b+c+d+e)/3500 5.94 6.49 8.07
Say 6.00 6.00 8.00
3.32 313 Construction of Rock fill Embankment with all lifts and lead
upto 5 Km
Unit = cum
Taking output = 500 cum
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Dozer
Dozer (240HP) hour 3.731 6,586.65 24,574.79 P&M-001
Dozer (175 HP) hour 4.808 5,087.25 24,459.50 P&M-002
Dozer (90 HP) hour 8.621 3,502.80 30,197.64 P&M-003
(iii) Motor grader 3.35 metre blade hour 2.929 4,796.00 14,047.48 P&M-006
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 11.911 1,501.00 17,878.41 P&M-023
(ii) 12 KL capacity hour 15.892 1,327.00 21,088.68 P&M-024
(iii) 6 KL capacity hour 31.783 1,005.00 31,941.92 P&M-025
Vibratory roller 12 tonne hour 2.184 2.184 2.184 2,562.00 5,595.41 5,595.41 5,595.41 P&M-022
c) Material
Cost of water (considering 5% additional moisture KL 51.300 51.300 51.300 16.00 820.80 820.80 820.80 M-191
required)
Compensation for earth taken from private land cum 67.500 67.500 67.500 45.00 3,037.50 3,037.50 3,037.50 M-093
@ 8% on @ 10% on @ 12% on 3,793.76 5,225.35 7,698.13
d) Overhead charges (a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on 5,121.58 5,747.89 7,184.92
e) Contractor's profit (a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 450 cum = a+b+c+d+e 56,337.34 63,226.75 79,034.09
Rate per cum = (a+b+c+d+e)/450 125.19 140.50 175.63
Say 125.00 141.00 176.00
Note
1.As flyash is available free of cost as waste material from
Thermal Plants, cost of material has not been added.
Unit = cum
Taking output = 400 cum 840 tonne 2.10
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Wet mix plant
(i) 250 tonne per hour hour 4.480 921.90 4,130.11 P&M-032
(ii) 200 tonne per hour hour 5.600 612.15 3,428.04 P&M-033
(iii) 100 tonne per hour hour 11.200 585.90 6,562.08 P&M-034
Electric generator
(i) 125 KVA hour 4.480 2,390.85 10,711.01 P&M-047
(ii) 100 KVA hour 5.600 2,041.20 11,430.72 P&M-048
(iii) 62.5 KVA hour 11.200 1,312.50 14,700.00 P&M-049
Front end loader
(i) 3.1 Cum Capacity hour 9.502 4,279.80 40,666.66 P&M-011
(ii) 2.1 Cum Capacity hour 14.047 2,640.75 37,094.62 P&M-012
(iii) 1 Cum Capacity hour 29.371 1,112.00 32,660.55 P&M-013
Tipper
For transportation
(i) 18 cum capacity t.km 840 x L1 6.18 155,698.20 P&M-117
(ii) 14 cum capacity t.km 840 x L1 7.01 176,722.56 P&M-120
(iii) 10 cum capacity t.km 840 x L1 8.66 218,332.80 P&M-123
For loading & unloading Time
(i) 18 cum capacity hour 4.480 2,883.30 12,917.18 P&M-014
(ii) 14 cum capacity hour 5.600 2,556.75 14,317.80 P&M-015
(iii) 10 cum capacity hour 11.200 2,274.30 25,472.16 P&M-016
Motor grader
(i) Motor grader 4.30 metre blade hour 3.226 5,991.00 19,326.97 P&M-004
(ii) Motor grader 3.70 metre blade hour 3.891 5,497.00 21,388.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 4.339 4,796.00 20,809.84 P&M-006
Vibratory roller hour 2.589 2.589 2.589 2,562.00 6,633.02 6,633.02 6,633.02 P&M-022
c) Material
Close graded Granular sub-base Material as per
table 400-1
For Grading-I Material
53 mm to 26.5 mm @27.5 per cent cum 148.077 148.077 148.077 1,887.12 279,439.38 279,439.38 279,439.38 M-028
26.5 mm to 9.5 mm @ 22.5 per cent cum 121.154 121.154 121.154 1,887.12 228,632.22 228,632.22 228,632.22 M-014
9.5 mm to 4.75 mm @ 10% cum 53.846 53.846 53.846 1,887.12 101,614.32 101,614.32 101,614.32 M-015
4.75 mm below @ 40 per cent cum 215.385 215.385 215.385 1,887.12 406,457.28 406,457.28 406,457.28 M-018
Cost of water KL 67.200 67.200 67.200 16.00 1,075.20 1,075.20 1,075.20 M-191
OR
For Grading-II Material
26.5 mm to 9.5 mm @ 35 per cent cum 188.462 188.462 188.462 1,887.12 355,650.12 355,650.12 355,650.12 M-014
9.5 mm to 4.75 mm @ 12.5 % cum 67.308 67.308 67.308 1,887.12 127,017.90 127,017.90 127,017.90 M-015
4.75 mm below @ 52.5 per cent cum 282.692 282.692 282.692 1,887.12 533,475.19 533,475.19 533,475.19 M-018
Cost of water KL 67.200 67.200 67.200 16.00 1,075.20 1,075.20 1,075.20 M-191
OR
For Grading-III Material
26.5 mm to 9.5 mm @ 68 per cent cum 366.154 366.154 366.154 1,887.12 690,977.38 690,977.38 690,977.38 M-014
9.5 mm to 4.75 mm @ 12 % cum 64.615 64.615 64.615 1,887.12 121,937.19 121,937.19 121,937.19 M-015
4.75 mm below @ 20 per cent cum 107.692 107.692 107.692 1,887.12 203,228.64 203,228.64 203,228.64 M-018
Cost of water KL 67.200 67.200 67.200 16.00 1,075.20 1,075.20 1,075.20 M-191
OR
For Grading-IV Material
26.5 mm to 9.5 mm @ 64 per cent cum 344.615 344.615 344.615 1,887.12 650,331.65 650,331.65 650,331.65 M-014
9.5 mm to 4.75 mm @ 11 % cum 59.231 59.231 59.231 1,887.12 111,775.75 111,775.75 111,775.75 M-015
4.75 mm below @ 25 per cent cum 134.615 134.615 134.615 1,887.12 254,035.80 254,035.80 254,035.80 M-018
Cost of water KL 67.200 67.200 67.200 16.00 1,075.20 1,075.20 1,075.20 M-191
OR
For Grading-V Material
53 mm to 26.5 mm @27.5 per cent cum 148.077 148.077 148.077 1,887.12 279,439.38 279,439.38 279,439.38 M-028
26.5 mm to 9.5 mm @ 22.5 per cent cum 121.154 121.154 121.154 1,887.12 228,632.22 228,632.22 228,632.22 M-014
9.5 mm to 4.75 mm @ 12.50 % cum 67.308 67.308 67.308 1,887.12 127,017.90 127,017.90 127,017.90 M-015
4.75 mm below @ 37.5 per cent cum 201.923 201.923 201.923 1,887.12 381,053.70 381,053.70 381,053.70 M-018
Cost of water KL 67.200 67.200 67.200 16.00 1,075.20 1,075.20 1,075.20 M-191
OR
For Grading-VI Material
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
53 mm to 26.5 mm @12.5 per cent cum 67.308 67.308 67.308 1,887.12 127,017.90 127,017.90 127,017.90 M-028
26.5 mm to 9.5 mm @22.5 per cent cum 121.154 121.154 121.154 1,887.12 228,632.22 228,632.22 228,632.22 M-014
9.5 mm to 4.75 mm @ 22.5 % cum 121.154 121.154 121.154 1,887.12 228,632.22 228,632.22 228,632.22 M-015
4.75 mm below @ 42.5 per cent cum 228.846 228.846 228.846 1,887.12 431,860.86 431,860.86 431,860.86 M-018
Cost of water KL 67.200 67.200 67.200 16.00 1,075.20 1,075.20 1,075.20 M-191
4.01A (i) Rate per cum for grading-I Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 101,474.25 128,936.06 161,221.86
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 136,990.24 141,829.67 150,473.73
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 400 cum = a+b+c+d+e 1,506,892.66 1,560,126.33 1,655,211.06
Rate per cum = (a+b+c+d+e)/400 3,767.23 3,900.32 4,138.03
Say 3,767.00 3,900.00 4,138.00
4.01A (ii) Rate per cum for grading-II Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 101,474.25 128,936.06 161,221.86
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 136,990.24 141,829.67 150,473.73
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 400 cum = a+b+c+d+e 1,506,892.66 1,560,126.33 1,655,211.06
Rate per cum = (a+b+c+d+e)/400 3,767.23 3,900.32 4,138.03
Say 3,767.00 3,900.00 4,138.00
4.01A (iii) Rate per cum for grading-III Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 101,474.25 128,936.06 161,221.86
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 136,990.24 141,829.67 150,473.73
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 400 cum = a+b+c+d+e 1,506,892.66 1,560,126.33 1,655,211.06
Rate per cum = (a+b+c+d+e)/400 3,767.23 3,900.32 4,138.03
Say 3,767.00 3,900.00 4,138.00
4.01A (iv) Rate per cum for grading-IV Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 101,474.25 128,936.06 161,221.86
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 136,990.24 141,829.67 150,473.73
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 400 cum = a+b+c+d+e 1,506,892.66 1,560,126.33 1,655,211.06
Rate per cum = (a+b+c+d+e)/400 3,767.23 3,900.32 4,138.03
Say 3,767.00 3,900.00 4,138.00
4.01A (v) Rate per cum for grading-V Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 101,474.25 128,936.06 161,221.86
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 136,990.24 141,829.67 150,473.73
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 400 cum = a+b+c+d+e 1,506,892.66 1,560,126.33 1,655,211.06
Rate per cum = (a+b+c+d+e)/400 3,767.23 3,900.32 4,138.03
Say 3,767.00 3,900.00 4,138.00
4.01A (vi) Rate per cum for grading-VI Material
d) Overhead charges @ 8% on @ 10% on @ 12% on 101,474.25 128,936.06 161,221.86
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 136,990.24 141,829.67 150,473.73
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 400 cum = a+b+c+d+e 1,506,892.66 1,560,126.33 1,655,211.06
Rate per cum = (a+b+c+d+e)/400 3,767.23 3,900.32 4,138.03
Say 3,767.00 3,900.00 4,138.00
Note Any one of the grading for material may be adopted
as per design
4.01 B By Mix in Place Method
Construction of granular sub-base by providing close
graded material, spreading in uniform layers with
motor grader on prepared surface, mixing by mix in
place method with front end loader at OMC, and
compacting with vibratory roller to achieve the
desired density, complete as per clause 401
Unit = cum
Taking output = 250 cum 525 tonne
a) Labour
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Machinery
Front end loader for mixing at stock pile location
Unit = cum
Taking output = 250 cum 525 tonne
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Front end loader for loading to Tipper
(i) 3.1 Cum Capacity hour 1.548 4,279.80 6,625.13 P&M-011
(ii) 2.1 Cum Capacity hour 2.283 2,640.75 6,028.83 P&M-012
(iii) 1 Cum Capacity hour 4.808 1,112.00 5,346.50 P&M-013
Tipper
For transportation
(i) 18 cum capacity t.km 525 x L1 6.18 97,311.38 P&M-117
(ii) 14 cum capacity t.km 525 x L1 7.01 110,451.60 P&M-120
(iii) 10 cum capacity t.km 525 x L1 8.66 136,458.00 P&M-123
For loading & unloading Time
(i) 18 cum capacity hour 1.548 2,883.30 4,463.35 P&M-014
(ii) 14 cum capacity hour 2.283 2,556.75 5,837.06 P&M-015
(iii) 10 cum capacity hour 4.808 2,274.30 10,934.83 P&M-016
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 3 km/hr )
A By Manual Means
a) Labour
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor for spraying lime day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 3,420.00 11,508.57 P&M-007
(ii) 1.1 cum bucket capacity hour 3.875 3,074.00 11,913.01 P&M-008
(iii) 0.9 cum bucket capacity hour 5.418 2,782.00 15,072.85 P&M-009
Tipper
For Transportation
(i) 18 cum capacity t.km 525 x L2 6.18 3,243.71 P&M-116
(ii) 14 cum capacity t.km 525 x L2 7.01 3,681.72 P&M-119
(iii) 10 cum capacity t.km 525 x L2 8.66 4,548.60 P&M-122
For loading & unloading Time
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
(i) 18 cum capacity hour 3.365 2,883.30 9,702.53 P&M-014
(ii) 14 cum capacity hour 3.875 2,556.75 9,908.45 P&M-015
(iii) 10 cum capacity hour 5.418 2,274.30 12,322.13 P&M-016
Tractor with ripper and rotavator attachments @ 250
cum per hour for mixing
P&M-026
hour 1.200 1.200 1.200 1,915.35 2,298.42 2,298.42 2,298.42 +P&M-027
+P&M-028
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
Water tanker (speed @ 20km/hr and return speed 23.007
@ 30 km/hr and spreading speed @ 2.5 km/hr )
By Mechanical Means
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 3,420.00 11,508.57 P&M-007
(ii) 1.1 cum bucket capacity hour 3.875 3,074.00 11,913.01 P&M-008
(iii) 0.9 cum bucket capacity hour 5.418 2,782.00 15,072.85 P&M-009
Tipper
For Transportation
(i) 18 cum capacity t.km 525 x L2 6.18 3,243.71 P&M-116
(ii) 14 cum capacity t.km 525 x L2 7.01 3,681.72 P&M-119
(iii) 10 cum capacity t.km 525 x L2 8.66 4,548.60 P&M-122
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2,883.30 9,702.53 P&M-014
(ii) 14 cum capacity hour 3.875 2,556.75 9,908.45 P&M-015
(iii) 10 cum capacity hour 5.418 2,274.30 12,322.13 P&M-016
Soil Stabilizer for mixing and pulverising with hour 2.667 2.667 2.667 26,741.40 71,310.40 71,310.40 71,310.40 P&M-085
capacity 1000 m2 per hour
Binder Spreader hour 2.667 2.667 2.667 8,300.25 22,134.00 22,134.00 22,134.00 P&M-086
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )
Unit = cum
Taking output = 300 cum 525 tonne
By Mechanical Means
a) Labour
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor for spraying lime day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 3,420.00 11,508.57 P&M-007
(ii) 1.1 cum bucket capacity hour 3.875 3,074.00 11,913.01 P&M-008
(iii) 0.9 cum bucket capacity hour 5.418 2,782.00 15,072.85 P&M-009
Tipper
For Transportation
(i) 18 cum capacity t.km 525 x L2 6.18 3,243.71 P&M-116
(ii) 14 cum capacity t.km 525 x L2 7.01 3,681.72 P&M-119
(iii) 10 cum capacity t.km 525 x L2 8.66 4,548.60 P&M-122
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2,883.30 9,702.53 P&M-014
(ii) 14 cum capacity hour 3.875 2,556.75 9,908.45 P&M-015
(iii) 10 cum capacity hour 5.418 2,274.30 12,322.13 P&M-016
Soil Stabilizer for mixing and pulverising with hour 2.667 2.667 2.667 26,741.40 71,310.40 71,310.40 71,310.40 P&M-085
capacity 1000 m2 per hour
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
Water tanker (speed @ 20km/hr and return speed
@ 30 km/hr and spreading speed @ 2.5 km/hr )
By Mechanical Means
Unit = cum
Taking output = 300 cum 525 tonne
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor for spraying lime day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 3,420.00 11,508.57 P&M-007
(ii) 1.1 cum bucket capacity hour 3.875 3,074.00 11,913.01 P&M-008
(iii) 0.9 cum bucket capacity hour 5.418 2,782.00 15,072.85 P&M-009
Tipper
For Transportation
(i) 18 cum capacity t.km 525 x L2 6.18 3,243.71 P&M-116
(ii) 14 cum capacity t.km 525 x L2 7.01 3,681.72 P&M-119
(iii) 10 cum capacity t.km 525 x L2 8.66 4,548.60 P&M-122
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2,883.30 9,702.53 P&M-014
(ii) 14 cum capacity hour 3.875 2,556.75 9,908.45 P&M-015
(iii) 10 cum capacity hour 5.418 2,274.30 12,322.13 P&M-016
Soil Stabilizer for mixing and pulverising with hour 2.667 2.667 2.667 26,741.40 71,310.40 71,310.40 71,310.40 P&M-085
capacity 1000 m2 per hour
Binder Spreader hour 2.667 2.667 2.667 8,300.25 22,134.00 22,134.00 22,134.00 P&M-086
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )
a) Labour
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor for spraying lime day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 3,420.00 11,508.57 P&M-007
(ii) 1.1 cum bucket capacity hour 3.875 3,074.00 11,913.01 P&M-008
(iii) 0.9 cum bucket capacity hour 5.418 2,782.00 15,072.85 P&M-009
Tipper
For Transportation
(i) 18 cum capacity t.km 525 x L2 6.18 3,243.71 P&M-116
(ii) 14 cum capacity t.km 525 x L2 7.01 3,681.72 P&M-119
(iii) 10 cum capacity t.km 525 x L2 8.66 4,548.60 P&M-122
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2,883.30 9,702.53 P&M-014
(ii) 14 cum capacity hour 3.875 2,556.75 9,908.45 P&M-015
(iii) 10 cum capacity hour 5.418 2,274.30 12,322.13 P&M-016
Soil Stabilizer for mixing and pulverising with hour 2.667 2.667 2.667 26,741.40 71,310.40 71,310.40 71,310.40 P&M-085
capacity 1000 m2 per hour
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )
A By Manual Means
P&M-026
Tractor with ripper and rotavator attachments @ 250
hour 1.200 1.200 1.200 1,915.35 2,298.42 2,298.42 2,298.42 +P&M-027
cum per hour for mixing
+P&M-028
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )
By Mechanical Means
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor for spraying lime day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 3,420.00 11,508.57 P&M-007
(ii) 1.1 cum bucket capacity hour 3.875 3,074.00 11,913.01 P&M-008
(iii) 0.9 cum bucket capacity hour 5.418 2,782.00 15,072.85 P&M-009
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L2 6.18 2,780.33 P&M-116
(ii) 14 cum capacity t.km 450 x L2 7.01 3,155.76 P&M-119
(iii) 10 cum capacity t.km 450 x L2 8.66 3,898.80 P&M-122
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2,883.30 9,702.53 P&M-014
(ii) 14 cum capacity hour 3.875 2,556.75 9,908.45 P&M-015
(iii) 10 cum capacity hour 5.418 2,274.30 12,322.13 P&M-016
Soil Stabilizer for mixing and pulverising with hour 2.667 2.667 2.667 26,741.40 71,310.40 71,310.40 71,310.40 P&M-085
capacity 1000 m2 per hour
Binder Spreader hour 2.667 2.667 2.667 8,300.25 22,134.00 22,134.00 22,134.00 P&M-086
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )
By Mechanical Means
a) Labour
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor for spraying lime day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 3,420.00 11,508.57 P&M-007
(ii) 1.1 cum bucket capacity hour 3.875 3,074.00 11,913.01 P&M-008
(iii) 0.9 cum bucket capacity hour 5.418 2,782.00 15,072.85 P&M-009
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L2 6.18 2,780.33 P&M-116
(ii) 14 cum capacity t.km 450 x L2 7.01 3,155.76 P&M-119
(iii) 10 cum capacity t.km 450 x L2 8.66 3,898.80 P&M-122
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2,883.30 9,702.53 P&M-014
(ii) 14 cum capacity hour 3.875 2,556.75 9,908.45 P&M-015
(iii) 10 cum capacity hour 5.418 2,274.30 12,322.13 P&M-016
Soil Stabilizer for mixing and pulverising with hour 2.667 2.667 2.667 26,741.40 71,310.40 71,310.40 71,310.40 P&M-085
capacity 1000 m2 per hour
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )
By Mechanical Means
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor for spraying lime day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 3,420.00 11,508.57 P&M-007
(ii) 1.1 cum bucket capacity hour 3.875 3,074.00 11,913.01 P&M-008
(iii) 0.9 cum bucket capacity hour 5.418 2,782.00 15,072.85 P&M-009
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L2 6.18 2,780.33 P&M-116
(ii) 14 cum capacity t.km 450 x L2 7.01 3,155.76 P&M-119
(iii) 10 cum capacity t.km 450 x L2 8.66 3,898.80 P&M-122
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2,883.30 9,702.53 P&M-014
(ii) 14 cum capacity hour 3.875 2,556.75 9,908.45 P&M-015
(iii) 10 cum capacity hour 5.418 2,274.30 12,322.13 P&M-016
Soil Stabilizer for mixing and pulverising with hour 2.667 2.667 2.667 26,741.40 71,310.40 71,310.40 71,310.40 P&M-085
capacity 1000 m2 per hour
Binder Spreader hour 2.667 2.667 2.667 8,300.25 22,134.00 22,134.00 22,134.00 P&M-086
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )
By Mechanical Means
a) Labour
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Skilled mazdoor for alignment and geometrics day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
Mazdoor for spraying lime day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 3.365 3,420.00 11,508.57 P&M-007
(ii) 1.1 cum bucket capacity hour 3.875 3,074.00 11,913.01 P&M-008
(iii) 0.9 cum bucket capacity hour 5.418 2,782.00 15,072.85 P&M-009
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L2 6.18 2,780.33 P&M-116
(ii) 14 cum capacity t.km 450 x L2 7.01 3,155.76 P&M-119
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
(iii) 10 cum capacity t.km 450 x L2 8.66 3,898.80 P&M-122
For loading & unloading Time
(i) 18 cum capacity hour 3.365 2,883.30 9,702.53 P&M-014
(ii) 14 cum capacity hour 3.875 2,556.75 9,908.45 P&M-015
(iii) 10 cum capacity hour 5.418 2,274.30 12,322.13 P&M-016
Soil Stabilizer for mixing and pulverising with hour 2.667 2.667 2.667 26,741.40 71,310.40 71,310.40 71,310.40 P&M-085
capacity 1000 m2 per hour
Motor Grader
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )
Unit = cum
Taking output = 300 cum 525 tonne
a) Labour
Mate day 0.480 0.480 0.480 617.00 296.16 296.16 296.16 L-12
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Mazdoor day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 7.852 3,420.00 26,853.33 P&M-007
(ii) 1.1 cum bucket capacity hour 9.043 3,074.00 27,797.02 P&M-008
(iii) 0.9 cum bucket capacity hour 12.642 2,782.00 35,169.98 P&M-009
Tipper
For Transportation of Soil
(i) 18 cum capacity t.km 525 x L2 6.18 3,243.71 P&M-116
(ii) 14 cum capacity t.km 525 x L2 7.01 3,681.72 P&M-119
(iii) 10 cum capacity t.km 525 x L2 8.66 4,548.60 P&M-122
For loading & unloading
(i) 18 cum capacity hour 7.852 2,883.30 22,639.24 P&M-014
(ii) 14 cum capacity hour 9.043 2,556.75 23,119.72 P&M-015
(iii) 10 cum capacity hour 12.642 2,274.30 28,751.64 P&M-016
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
P&M-026
Tractor with ripper and rotavator attachments @ 250
hour 1.200 1.200 1.200 1,915.35 2,298.42 2,298.42 2,298.42 +P&M-027
cum per hour for mixing
+P&M-028
c) Material
Lime at site tonne 15.750 15.75 15.75 3,753.00 59,109.75 59,109.75 59,109.75 M-190
Compensation for earth taken from private land cum 300.000 300.00 300.00 45.00 13,500.00 13,500.00 13,500.00 M-093
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Cost of water KL 52.500 52.5 52.50 16.00 840.00 840.00 840.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on 13,715.23 17,807.48 24,303.70
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 18,515.55 19,588.23 22,683.45
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 300 cum = a+b+c+d+e 203,671.10 215,470.53 249,518.00
Rate per cum= (a+b+c+d+e)/300 678.90 718.24 831.73
Say 679.00 718.00 832.00
4.06 403 Cement Treated Soil Sub Base/ Base
Providing, laying and spreading soil on a prepared
sub grade, pulverising, adding the designed quantity
of cement to the spread soil, mixing in place with
rotavator, grading with the motor grader and
compacting with the road roller at OMC to achieve
the desired unconfined compressive strength and to
form a layer of sub-base/base.
Unit = cum
Taking output = 300 cum 525 tonne
For 4 per cent quantity of cement by weight of soil
a) Labour
Mate day 0.480 0.480 0.480 617.00 296.16 296.16 296.16 L-12
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Mazdoor day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 7.852 3,420.00 26,853.33 P&M-007
(ii) 1.1 cum bucket capacity hour 9.043 3,074.00 27,797.02 P&M-008
(iii) 0.9 cum bucket capacity hour 12.642 2,782.00 35,169.98 P&M-009
Tipper
For Transportation of Soil
(i) 18 cum capacity t.km 525 x L2 6.18 3,243.71 P&M-116
(ii) 14 cum capacity t.km 525 x L2 7.01 3,681.72 P&M-119
(iii) 10 cum capacity t.km 525 x L2 8.66 4,548.60 P&M-122
For loading & unloading
(i) 18 cum capacity hour 7.852 2,883.30 22,639.24 P&M-014
(ii) 14 cum capacity hour 9.043 2,556.75 23,119.72 P&M-015
(iii) 10 cum capacity hour 12.642 2,274.30 28,751.64 P&M-016
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 2.419 5,991.00 14,494.35 P&M-004
(ii) Motor grader 3.70 metre blade hour 2.918 5,497.00 16,041.83 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.254 4,796.00 15,606.21 P&M-006
Vibratory roller hour 1.456 1.456 1.456 2,562.00 3,731.07 3,731.07 3,731.07 P&M-022
Tractor with ripper and rotavator attachments @ 250
cum per hour for mixing
P&M-026
hour 1.200 1.200 1.200 1,915.35 2,298.42 2,298.42 2,298.42 +P&M-027
+P&M-028
c) Material
Cement at site (@ 4 per cent of 525 tonne) tonne 21.000 21.000 21.000 4,940.00 103,740.00 103,740.00 103,740.00 M-081
Compensation for earth taken from private land cum 300.000 300.000 300.000 45.00 13,500.00 13,500.00 13,500.00 M-093
Cost of water KL 52.500 52.500 52.500 16.00 840.00 840.00 840.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on 17,285.65 22,270.51 29,659.33
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 23,335.62 24,497.56 27,682.04
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 300 cum = a+b+c+d+e 256,691.84 269,473.13 304,502.47
Rate per cum= (a+b+c+d+e)/300 855.64 898.24 1,015.01
Say 856.00 898.00 1,015.00
4.07 403 Cement Treated Crushed Rock or combination as
per clause 403 and table 400.4in Sub base/ Base
Unit = cum
Taking output = 250 cum 525 tonne
By Mechanical Means
a) Labour
Mate day 0.400 0.400 0.400 617.00 246.80 246.80 246.80 L-12
Skilled mazdoor for alignment and geometrics day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Mazdoor for spraying lime day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Front end loader for mixing at stock pile location
Unit = sqm
Taking output = 30 m x 7 m = 210 sqm
(i) 25mm deep furrow cutting
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Tractor-trolley hour 0.200 0.200 0.200 1,876.50 375.30 375.30 375.30 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on 115.82 144.77 173.72
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 156.35 159.25 162.14
(a+b+c) (a+b+c) (a+b+c)
Cost for 210 sqm= a+b+c+d 1,719.87 1,751.72 1,783.57
Rate per sqm =(a+b+c+d)/210 8.19 8.34 8.49
Say 8.00 8.00 8.00
(ii) 50mm deep furrow cutting
a) Labour
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Mazdoor day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
b) Machinery
Tractor-trolley hour 0.400 0.400 0.400 1,876.50 750.60 750.60 750.60 P&M-026
c) Overhead charges @ 8% on @ 10% on @ 12% on 231.63 289.54 347.45
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 312.70 318.49 324.28
(a+b+c) (a+b+c) (a+b+c)
Cost for 210 sqm= a+b+c+d 3,439.74 3,503.43 3,567.13
Rate per sqm =(a+b+c+d)/210 16.38 16.68 16.99
Say 16.00 17.00 17.00
4.10 404.3.2 Inverted Choke
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Construction of inverted choke by providing, laying,
spreading and compacting screening B type/ coarse
sand of specified grade in uniform layer on a
prepared surface with motor grader and compacting
with power roller etc
Unit = cum
Taking output = 600 cum
a) Labour
Mate day 0.920 0.920 0.920 617.00 567.64 567.64 567.64 L-12
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Mazdoor day 21.000 21.000 21.000 511.52 10,741.92 10,741.92 10,741.92 L-13
b) Machinery
Motor Grader
(i) Motor grader 4.30 metre blade hour 4.839 5,991.00 28,988.71 P&M-004
(ii) Motor grader 3.70 metre blade hour 5.837 5,497.00 32,083.66 P&M-005
(iii) Motor grader 3.35 metre blade hour 6.508 4,796.00 31,212.43 P&M-006
Vibratory roller 8-10 tonnes @ 60 cum per hour hour 6.000 6.000 6.000 2,562.00 15,372.00 15,372.00 15,372.00 P&M-022
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )
A By Manual Means
Unit = cum
Taking output = 360 Cum 756 tonne
a) Labour
Mate day 10.080 10.080 10.080 617.00 6,219.36 6,219.36 6,219.36 L-12
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Mazdoor day 250.000 250.000 250.000 511.52 127,880.00 127,880.00 127,880.00 L-13
b) Machinery
Vibratory roller hour 2.330 2.330 2.300 2,562.00 5,969.46 5,969.46 5,892.60 P&M-022
or
Smooth 3 wheeled steel roller @ 30cum/hour hour 4.660 4.660 4.600 417.00 1,943.22 1,943.22 1,918.20 P&M-019
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )
Aggregate
Grading-I 63 mm to 45 mm/Gradeing-II 53mm to cum 435.600 435.600 435.600 1,887.12 822,030.82 822,030.82 822,030.82 M-037
22.4mm@ 0.91cum per 10 sqm for compacted
thickness of 75 mm
Stone Screening
Type A 13.2 mm for grading-I @ 0.12 cum per 10 cum 57.600 57.600 57.600 1,887.12 108,698.29 108,698.29 108,698.29 M-041
sqm
OR
Crushable type such as Moorum or Gravel for cum 105.590 105.590 105.590 1,297.52 137,005.24 137,005.24 137,005.24 M-007
grading-I & II @ 0.22 cum per 10 sqm
OR
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Type B 11.2 mm for grading-II @ 0.18 cum per 10 cum 86.400 86.400 86.400 1,887.12 163,047.44 163,047.44 163,047.44 M-040
sqm
Binding material
Binding Material @ 0.06cum per 10 sqm for grading I cum 28.800 28.800 28.800 1,297.52 37,368.60 37,368.60 37,368.60 M-007
material
Cost of water KL 144.000 144.000 144.000 16.00 2,304.00 2,304.00 2,304.00 M-191
4.11 A (a) Using Scrining Crushable type such as Moorum or
(i) Gravel
d) Overhead charges @ 8% on @ 10% on @ 12% on 95,411.68 120,171.31 140,173.37
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 128,805.77 132,188.45 130,828.48
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 360 cum = a+b+c+d+e 1,416,863.46 1,454,072.90 1,439,113.30
Rate per cum = (a+b+c+d+e)/360 3,935.73 4,039.09 3,997.54
Say 3,936.00 4,039.00 3,998.00
OR
4.11 A (b) Using Scrining Type-A (13.2mm agg.)
(i)
d) Overhead charges @ 8% on @ 10% on @ 12% on 93,147.12 117,340.62 136,776.54
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 125,748.62 129,074.68 127,658.10
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 360 cum = a+b+c+d+e 1,383,234.80 1,419,821.49 1,404,239.13
Rate per cum = (a+b+c+d+e)/360 3,842.32 3,943.95 3,900.66
Say 3,842.00 3,944.00 3,901.00
OR
4.11 A (c) Using Scrining Type-B (11.2mm agg.)
(i)
d) Overhead charges @ 8% on @ 10% on @ 12% on 97,495.06 122,775.53 143,298.44
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 131,618.33 134,146.37 133,745.21
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 360 cum = a+b+c+d+e 1,447,801.59 1,484,677.24 1,471,197.28
Rate per cum = (a+b+c+d+e)/360 4,021.67 4,124.10 4,086.66
Say 4,022.00 4,124.00 4,087.00
4.11 A (ii) Grading-II
Aggregate
Grading-II 53 mm to 22.4 mm @ 0.91 cum per 10 cum 435.600 435.600 435.600 1,887.12 822,030.82 822,030.82 822,030.82 M-035
sqm for compacted thickness of 75 mm
Stone Screening
Type b 11.2 mm for grading-II@ 0.18 cum per 10 cum 86.400 86.400 86.400 1,887.12 163,047.44 163,047.44 163,047.44 M-040
sqm
OR
Crushable type such as Moorum or Gravel for cum 105.590 105.590 105.590 1,297.52 137,005.24 137,005.24 137,005.24 M-007
grading II &III @ 0.22 cum per 10 sqm
Binding material
Binding Material @ 0.06cum per 10 sqm for grading cum 28.800 28.800 28.800 1,297.52 37,368.60 37,368.60 37,368.60 M-007
II material
Cost of water KL 144.000 144.000 144.000 16.00 2,304.00 2,304.00 2,304.00 M-191
4.11 A (a) Using Scrining Crushable type such as Moorum or
(ii) Gravel
d) Overhead charges @ 8% on @ 10% on @ 12% on 95,411.68 120,171.31 140,173.37
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 128,805.77 132,188.45 130,828.48
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 360 cum = a+b+c+d+e 1,416,863.46 1,454,072.90 1,439,113.30
Rate per cum = (a+b+c+d+e)/360 3,935.73 4,039.09 3,997.54
Say 3,936.00 4,039.00 3,998.00
OR
4.11 A (b) Using Scrining Type-A (13.2mm agg.)
(ii)
d) Overhead charges @ 8% on (a+b+c) 97,495.06 122,775.53 143,298.44
e) Contractor's profit @ 10% on (a+b+c+d) 131,618.33 135,053.09 133,745.21
Aggregate
Grading-I 63 mm to 45/Grading-II 53 mm to 22.4mm cum 435.600 435.600 435.600 1,887.12 822,030.82 822,030.82 822,030.82 M-037
@ 0.91cum per 10 sqm for compacted thickness of
75 mm
Stone Screening
Type A 13.2 mm for grading-I @ 0.12 cum per 10 cum 57.600 57.600 57.600 1,887.12 108,698.29 108,698.29 108,698.29 M-041
sqm
OR
Crushable type such as Moorum or Gravel for cum 105.590 105.590 105.590 1,297.52 137,005.24 137,005.24 137,005.24 M-007
grading-I &II@ 0.22 cum per 10 sqm
OR
Type B 11.2mm for grading II @0.18 cum per 10sqm cum 86.400 86.400 86.400 1,887.12 163,047.44 163,047.44 163,047.44 M-040
Binding material
Binding Material @ 0.06cum per 10 sqm for grading I cum 28.800 28.800 28.800 1,297.52 37,368.60 37,368.60 37,368.60 M-007
material
Cost of water KL 144.000 144.000 144.000 16.00 2,304.00 2,304.00 2,304.00 M-191
4.11 B (a) Using Scrining Crushable type such as Moorum or
(i) Gravel
d) Overhead charges @ 8% on @ 10% on @ 12% on 88,923.65 111,997.43 137,701.70
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 120,046.92 123,197.17 128,521.59
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 360 cum = a+b+c+d+e 1,320,516.13 1,355,168.90 1,413,737.50
Rate per cum = (a+b+c+d+e)/360 3,668.10 3,764.36 3,927.05
Say 3,668.00 3,764.00 3,927.00
OR
4.11 B (b) Using Scrining Type-A (13.2mm agg.)
(i)
d) Overhead charges @ 8% on @ 10% on @ 12% on 86,659.09 109,166.73 134,304.87
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 116,989.77 120,083.41 125,351.21
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 360 cum = a+b+c+d+e 1,286,887.48 1,320,917.49 1,378,863.34
Rate per cum = (a+b+c+d+e)/360 3,574.69 3,669.22 3,830.18
Say 3,575.00 3,669.00 3,830.00
OR
4.11 B (c) Using Scrining Type-B (11.2mm agg.)
(i)
d) Overhead charges @ 8% on @ 10% on @ 12% on 91,007.02 114,601.65 140,826.77
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 122,859.48 126,061.81 131,438.32
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 360 cum = a+b+c+d+e 1,351,454.26 1,386,679.95 1,445,821.49
Rate per cum = (a+b+c+d+e)/360 3,754.04 3,851.89 4,016.17
Say 3,754.00 3,852.00 4,016.00
4.11 B (ii) Grading-II
Aggregate
Grading-II 53 mm to 22.4 mm @ 0.91 cum per 10 cum 435.600 435.600 435.600 1,887.12 822,030.82 822,030.82 822,030.82 M-035
sqm for compacted thickness of 75 mm
Stone Screening
Type B11.2 mm for grading-III @ 0.18 cum per 10 cum 86.400 86.400 86.400 1,887.12 163,047.44 163,047.44 163,047.44 M-040
sqm
OR
Crushable type such as Moorum or Gravel for cum 105.590 105.590 105.590 1,297.52 137,005.24 137,005.24 137,005.24 M-007
grading II &III @ 0.22 cum per 10 sqm
Binding material
Binding Material @ 0.06cum per 10 sqm for grading cum 28.800 28.800 28.800 1,297.52 37,368.60 37,368.60 37,368.60 M-007
II material
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Cost of water KL 144.000 144.000 144.000 16.00 2,304.00 2,304.00 2,304.00 M-191
4.11 B (a) Using Scrining Crushable type such as Moorum or
(ii) Gravel
d) Overhead charges @ 8% on @ 10% on @ 12% on 88,923.65 111,997.43 137,701.70
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 120,046.92 123,197.17 128,521.59
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 360 cum = a+b+c+d+e 1,320,516.13 1,355,168.90 1,413,737.50
Rate per cum = (a+b+c+d+e)/360 3,668.10 3,764.36 3,927.05
Say 3,668.00 3,764.00 3,927.00
OR
4.11 B (b) Using Scrining Type-A (13.2mm agg.)
(ii)
d) Overhead charges @ 8% on @ 10% on @ 12% on 91,007.02 113,758.78 140,826.77
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 122,859.48 125,977.53 131,438.32
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 360 cum = a+b+c+d+e 1,351,454.26 1,385,752.79 1,445,821.49
Rate per cum = (a+b+c+d+e)/360 3,754.04 3,849.31 4,016.17
Say 3,754.00 3,849.00 4,016.00
4.12 405 Crushed Cement Concrete Sub-base / Base
Breaking and crushing of material obtained by
breaking damaged cement concrete slabs to size
range not exceeding 75 mm as specified in table
400.9 transporting the aggregates obtained from
breaking of cement concrete slabs at a lead of L km.,
laying and compacting the same as sub base/ base
course, constructed as WBM to clause 404 except
the use of screening or binding Material.
Unit = cum
Taking output = 360 cum 720.000 Tonne
a) Labour
Mate day 4.160 4.160 4.160 617.00 2,566.72 2,566.72 2,566.72 L-12
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Mazdoor for crushing broken cement concrete day 102.000 102.000 102.000 511.52 52,175.04 52,175.04 52,175.04 L-13
pavement/slabs into aggregate
b) Machinery
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 2.903 5,991.00 17,393.23 P&M-004
(ii) Motor grader 3.70 metre blade hour 3.502 5,497.00 19,250.19 P&M-005
(iii) Motor grader 3.35 metre blade hour 3.905 4,796.00 18,727.46 P&M-006
Vibratory roller 8 - 10 tonne@ 60 cum per hour hour 6.000 6.000 6.000 2,562.00 15,372.00 15,372.00 15,372.00 P&M-022
or
Smooth 3 wheeled steel roller @ 30cum/hr. hour 12.000 12.000 12.000 - - - - P&M-019
Front end loader for loading to Tipper
(i) 3.1 Cum Capacity hour 2.229 4,279.80 9,540.11 P&M-011
(ii) 2.1 Cum Capacity hour 3.288 2,640.75 8,681.92 P&M-012
(iii) 1 Cum Capacity hour 6.923 1,112.00 7,698.46 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 720 x L 6.18 133,455.60 P&M-116
(ii) 14 cum capacity t.km 720 x L 7.01 151,476.48 P&M-119
(iii) 10 cum capacity t.km 720 x L 8.66 187,142.40 P&M-122
For loading & unloading time hour
(i) 18 cum capacity hour 2.229 2,883.30 6,426.88 P&M-014
(ii) 14 cum capacity hour 3.288 2,556.75 8,406.59 P&M-015
(iii) 10 cum capacity hour 6.923 2,274.30 15,744.98 P&M-016
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 3 km/hr )
Unit = sqm
Taking output = 7500 sqm
a) Labour
Mate day 0.560 0.560 0.560 617.00 345.52 345.52 345.52 L-12
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Mazdoor day 12.000 12.000 12.000 511.52 6,138.24 6,138.24 6,138.24 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.232 2.232 2.232 500.40 1,116.89 1,116.89 1,116.89 P&M-052
Hydraulic self propelled chips spreader hour 5.140 5.140 5.140 2,220.75 11,414.66 11,414.66 11,414.66 P&M-065
Front end loader 1 cum bucket capacity hour 6.000 6.000 6.000 1,112.00 6,672.00 6,672.00 6,672.00 P&M-013
Tipper 10 tonne capacity hour 6.000 6.000 6.000 1,731.45 10,388.70 10,388.70 10,388.70 P&M-017
Vibratory roller 8 -10 tonnes hour 5.140 5.140 5.140 2,562.00 13,168.68 13,168.68 13,168.68 P&M-022
Bitumen pressure distributor @ 1750 sqm per hour hour 4.280 4.280 4.280 1,729.35 7,401.62 7,401.62 7,401.62 P&M-053
c) Material
Crushed stone aggregate 11.2 mm size cum 97.500 97.500 97.500 1,887.12 183,994.50 183,994.50 183,994.50 M-040
Bitumen (60-70 grade) tonne 0.250 0.250 0.250 46,556.37 11,639.09 11,639.09 11,639.09 M-074
d) Overhead charges @ 8% on @ 10% on @ 12% on 20,272.91 25,341.14 30,409.36
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 27,368.43 27,875.25 28,382.07
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 7500 sqm = a+b+c+d+e 301,052.70 306,627.75 312,202.80
Rate per sqm = (a+b+c+d+e)/7500 40.14 40.88 41.63
Say 40.00 41.00 42.00
Note Though vibratory roller is required only for 3 hours as
per norms, the same is required to be available at
site for 6 hours to match with other machines. The
usage rates of vibratory roller may be multiplied with
a factor of 0.65.
Unit = cum
Taking output = 21 cum 46.2 tonne
a) Labour
Mate day 0.240 0.240 0.240 617.00 148.08 148.08 148.08 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
b) Machinery
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading speed @ 2.5 km/hr )
Unit = cum
Taking output = 21 cum 31.5 tonne
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 0.236 3,420.00 807.12 P&M-007
(ii) 1.1 cum bucket capacity hour 0.271 3,074.00 833.05 P&M-008
(iii) 0.9 cum bucket capacity hour 0.379 2,782.00 1,054.38 P&M-009
Tipper
For Transportation
(i) 18 cum capacity t.km 31.5 x L2 6.18 194.62 P&M-116
(ii) 14 cum capacity t.km 31.5 x L2 7.01 220.90 P&M-119
(iii) 10 cum capacity t.km 31.5 x L2 8.66 272.92 P&M-122
For loading & unloading time
(i) 18 cum capacity hour 0.236 2,883.30 680.46 P&M-014
(ii) 14 cum capacity hour 0.271 2,556.75 692.88 P&M-015
(iii) 10 cum capacity hour 0.379 2,274.30 861.96 P&M-016
Water tanker (speed @ 20km/hr and return speed
@ 30 km/hr and spreading speed @ 2.5 km/hr )
Unit = sqm
Taking output = 300 sqm
a) Labour
Mate day 1.360 1.360 1.360 617.00 839.12 839.12 839.12 L-12
Mason day 4.000 4.000 4.000 738.00 2,952.00 2,952.00 2,952.00 L-11
Mazdoor day 30.000 30.000 30.000 511.52 15,345.60 15,345.60 15,345.60 L-13
b) Machinery
Vibratory roller hour 0.750 0.750 0.750 2,562.00 1,921.50 1,921.50 1,921.50 P&M-022
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and spreading speed @ 2.5 km/hr )
Sand @ 0.45 cum/cum of concrete cum 3.380 3.380 3.380 1,994.03 6,739.82 6,739.82 6,739.82 M-005
Cement tonne 1.880 1.880 1.880 4,940.00 9,287.20 9,287.20 9,287.20 M-081
iii) For cement plaster 1:3
Sand cum 3.840 3.840 3.840 1,994.03 7,657.08 7,657.08 7,657.08 M-005
Cement tonne 1.830 1.830 1.830 4,940.00 9,040.20 9,040.20 9,040.20 M-081
iv) Pre-cast cement concrete tiles
Tiles size 300 x 300 mm and 25 mm thick each 3300.000 3300.000 3300.000 33.15 109,395.00 109,395.00 109,395.00 M-186
v) RCC pipes
Pipes 200 mm dia,2.5 m long for drainage metre 22.500 22.500 22.500 168.19 3,784.25 3,784.25 3,784.25 M-136
vi) Cost of water KL 12.000 12.000 12.000 16.00 192.00 192.00 192.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on 23,908.21 29,954.43 36,222.71
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 32,276.08 32,949.87 33,807.86
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 300 sqm = a+b+c+d+e 355,036.89 362,448.62 371,886.47
Rate per sqm = (a+b+c+d+e)/300 1,183.46 1,208.16 1,239.62
Say 1,183.00 1,208.00 1,240.00
4.20 410 Crusher Run Macadam Base
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Providing crushed stone aggregate, depositing on a
prepared surface by hauling vehicles, spreading and
mixing with a motor grader, watering and compacting
with a vibratory roller to clause 417 to form a layer of
sub-base/Base
Unit = cum
Taking output = 360 cum 720 tonne
A By Mix in Place Method
a) Labour
Mate day 0.480 0.480 0.480 617.00 296.16 296.16 296.16 L-12
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Mazdoor day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-13
b) Machinery
Tractor attached with rotavator @ 25 cum per hour
P&M-026
hour 12.000 12.000 12.000 1,915.35 22,984.20 22,984.20 22,984.20 +P&M-027
+P&M-028
Unit = cum
Taking output = 480 cum (720 tonne, density 1.50
t/cum)
Assumptions made
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Total mass taken for analysis = 720 t 720.00 Tonne
Lime + Flyash admixture @ 20 per cent = 0.2 x
720=144 t
Soil = 720 -144 = 576 t 576.00 Tonne
576 /1.6 = 360 cum 360.00 Cum
Lime + Flyash = 144 t 144.00 Tonne
Ratio Lime 4 : Flyash 16 49.40 Cum
Lime = 29 t 409.40 Cum
Flyash = 115 t
a) Labour
Mate day 0.280 0.280 0.280 617.00 172.76 172.76 172.76 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 4.038 3,420.00 13,810.29 P&M-007
(ii) 1.1 cum bucket capacity hour 4.650 3,074.00 14,295.61 P&M-008
(iii) 0.9 cum bucket capacity hour 6.502 2,782.00 18,087.42 P&M-009
Tipper
For transportation
(i) 18 cum capacity t.km 720 x L1 6.18 133,455.60 P&M-116
(ii) 14 cum capacity t.km 720 x L1 7.01 151,476.48 P&M-119
(iii) 10 cum capacity t.km 720 x L1 8.66 187,142.40 P&M-122
For Loading & unloading time
(i) 18 cum capacity hour 4.038 2,883.30 11,642.77 P&M-014
(ii) 14 cum capacity hour 4.650 2,556.75 11,888.89 P&M-015
(iii) 10 cum capacity hour 6.502 2,274.30 14,787.50 P&M-016
Tractor with disc harrows for pulverisation hour 6.000 6.000 6.000 1,876.50 11,259.00 11,259.00 11,259.00 P&M-026
Motor grader for grading
(i) Motor grader 4.30 metre blade hour 3.302 5,991.00 19,782.28 P&M-004
(ii) Motor grader 3.70 metre blade hour 3.982 5,497.00 21,889.05 P&M-005
(iii) Motor grader 3.35 metre blade hour 4.441 4,796.00 21,299.04 P&M-006
Vibratory roller hour 6.000 6.000 6.000 2,562.00 15,372.00 15,372.00 15,372.00 P&M-022
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and spreading speed @ 2.5 km/hr )
Cost of water (considering 5% additional moisture KL 43.200 43.200 43.200 16.00 691.20 691.20 691.20 M-191
required)
d) Overhead charges @ 8% on @ 10% on @ 12% on 28,058.11 37,442.22 51,097.93
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 37,878.44 41,186.45 47,691.41
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 480 cum = a+b+c+d+e 416,662.86 453,050.90 524,605.46
Rate per cum= (a+b+c+d+e)/480 868.05 943.86 1,092.93
Say 868.00 944.00 1,093.00
Note 1.Compensation for earth will vary from place to
place and will have to be assessed realistically as
per particular ground situation. In case earth is
available from Govt. land, compensation for earth
will not be required. The position is required to be
clearly stated in the cost estimate.
Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.083 2.083 2.083 500.40 1,042.33 1,042.33 1,042.33 P&M-052
Air compressor 250 cfm hour 2.083 2.083 2.083 614.25 1,279.48 1,279.48 1,279.48 P&M-029
Bitumen pressure distributor (Spraying width 4.5 m) P&M-053
hour 1.944 1.944 1.944 1,729.35 3,361.86 3,361.86 3,361.86
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 2.803 1,501.00 4,207.30 P&M-023
(ii) 12 KL capacity hour 3.727 1,327.00 4,945.73 P&M-024
(iii) 6 KL capacity hour 7.453 1,005.00 7,490.27 P&M-025
c) Material
SS1 grade Bitumen emulsion @ 0.85 kg per sqm tonne 4.900 4.900 4.900 47,662.37 233,545.62 233,545.62 233,545.62 M-077
Cost of water KL 10.500 10.500 10.500 16.00 168.00 168.00 168.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
19,574.16 24,541.54 29,755.19
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
26,425.12 26,995.70 27,771.51
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 7000 Sqm = a+b+c+d+e 290,676.27 296,952.66 305,486.66
Rate per Sqm = (a+b+c+d+e)/7000 41.53 42.42 43.64
Say 42.00 42.00 44.00
Note Bitumen primer has been provided @ 0.85 kg per sqm as
per clause 502.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and the actual quantity approved by the
Engineer after the preliminary trials referred to in clause
No. 502.4.3.
Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.083 2.083 2.083 500.40 1,042.50 1,042.50 1,042.50 P&M-052
Air compressor 250 cfm hour 2.083 2.083 2.083 614.25 1,279.69 1,279.69 1,279.69 P&M-029
Bitumen pressure distributor (Spraying width 4.5 m) hour 1.944 1.944 1.944 1,729.35 3,362.63 3,362.63 3,362.63 P&M-053
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity 0.073xL1+0.6 P&M-023
hour 1,501.00 4,207.30
13
(ii) 12 KL capacity 0.097xL1+0.81 P&M-024
hour 1,327.00 4,945.73
7
(iii) 6 KL capacity 0.194xL1+1.6 P&M-025
hour 1,005.00 7,490.27
33
c) Material
Cutback Bitumen MC 30 @ 0.6 kg per sqm tonne 4.200 4.200 4.200 46,556.37 195,536.76 195,536.76 195,536.76 M-076
Cost of water KL 10.500 10.500 10.500 16.00 168.00 168.00 168.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
16,533.54 20,740.77 25,194.27
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
22,320.28 22,814.85 23,514.65
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 7000 Sqm = a+b+c+d+e 245,523.10 250,963.32 258,661.15
Rate per Sqm = (a+b+c+d+e)/7000 35.07 35.85 36.95
Say 35.00 36.00 37.00
Note Bitumen primer has been provided @ 0.75 kg per sqm as
per clause 502.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and the actual quantity approved by the
Engineer after the preliminary trials referred to in clause
No. 502.4.3.
Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.083 2.083 2.083 500.40 1,042.33 1,042.33 1,042.33 P&M-052
Air compressor 250 cfm hour 2.083 2.083 2.083 614.25 1,279.48 1,279.48 1,279.48 P&M-029
Bitumen pressure distributor (Spraying width 4.5 m) hour 1.944 1.944 1.944 1,729.35 3,361.86 3,361.86 3,361.86 P&M-053
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity 0.073xL1+0.6 P&M-023
hour 1,501.00 4,207.30
13
(ii) 12 KL capacity 0.097xL1+0.81 P&M-024
hour 1,327.00 4,945.73
7
(iii) 6 KL capacity 0.194xL1+1.6 P&M-025
hour 1,005.00 7,490.27
33
c) Material
SS1 grade Bitumen emulsion @ 0.9 kg per sqm tonne 6.300 6.300 6.300 47,662.37 300,272.94 300,272.94 300,272.94 M-077
Cost of water KL 10.500 10.500 10.500 16.00 168.00 168.00 168.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
24,912.35 31,214.27 37,762.47
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
33,631.67 34,335.70 35,244.97
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 7000 Sqm = a+b+c+d+e 369,948.32 377,692.71 387,694.72
Rate per Sqm = (a+b+c+d+e)/7000 52.85 53.96 55.38
Say 53.00 54.00 55.00
Note Bitumen primer has been provided @ 1.05 kg per sqm as
per clause 502.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and the actual quantity approved by the
Engineer after the preliminary trials referred to in clause
No. 502.4.3.
Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.083 2.083 2.083 500.40 1,042.50 1,042.50 1,042.50 P&M-052
Air compressor 250 cfm hour 2.083 2.083 2.083 614.25 1,279.69 1,279.69 1,279.69 P&M-029
Bitumen pressure distributor (Spraying width 4.5 m) P&M-053
hour 1.944 1.944 1.944 1,729.35 3,362.63 3,362.63 3,362.63
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity 0.073xL1+0.6 P&M-023
hour 1,501.00 4,207.30
13
(ii) 12 KL capacity 0.097xL1+0.81 P&M-024
hour 1,327.00 4,945.73
7
(iii) 6 KL capacity 0.194xL1+1.6 P&M-025
hour 1,005.00 7,490.27
33
c) Material
Cutback Bitumen MC 70 @ 0.9 kg per sqm tonne 6.300 6.300 6.300 46,556.37 293,305.14 293,305.14 293,305.14 M-076
Cost of water KL 10.500 10.500 10.500 16.00 168.00 168.00 168.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
24,355.01 30,517.61 36,926.47
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
32,879.27 33,569.37 34,464.71
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 7000 Sqm = a+b+c+d+e 361,671.93 369,263.06 379,111.80
Rate per Sqm = (a+b+c+d+e)/7000 51.67 52.75 54.16
Say 52.00 53.00 54.00
Note Bitumen primer has been provided @ 1.05 kg per sqm as
per clause 502.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and the actual quantity approved by the
Engineer after the preliminary trials referred to in clause
No. 502.4.3.
Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.083 2.083 2.083 500.40 1,042.33 1,042.33 1,042.33 P&M-052
Air compressor 250 cfm hour 2.083 2.083 2.083 614.25 1,279.48 1,279.48 1,279.48 P&M-029
Emulsion Pressure Distributor (Spraying width 4.5 m) P&M-054
hour 1.944 1.944 1.944 1,112.00 2,161.73 2,161.73 2,161.73
c) Material
Bitumen emulsion @ 0.22 kg per sqm tonne 1.400 1.400 1.400 47,662.37 66,727.32 66,727.32 66,727.32 M-077
d) Overhead charges @ 8% on @ 10% on @ 12% on
5,782.66 7,228.33 8,673.99
(a+b+c) (a+b+c) (a+b+c)
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
e) Contractor's profit @ 10% on @ 10% on @ 10% on
7,806.59 7,951.16 8,095.73
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 7000 Sqm = a+b+c+d+e 85,872.52 87,462.75 89,052.98
Rate per Sqm = (a+b+c+d+e)/7000 12.27 12.49 12.72
Say 12.00 12.00 13.00
Note 1. Bitumen emulsion has been provided @ 0.25 kg per
sqm as per clause 503.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and actual quantity approved by the Engineer
after preliminary trials referred to in clause No. 503.4.3
5.02 503 (ii) Tack Coat on Granular surfaces treated with primer
Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.083 2.083 2.083 500.40 1,042.33 1,042.33 1,042.33 P&M-052
Air compressor 250 cfm hour 2.083 2.083 2.083 614.25 1,279.48 1,279.48 1,279.48 P&M-029
Emulsion Pressure Distributor (Spraying width 4.5 m) P&M-054
hour 1.944 1.944 1.944 1,112.00 2,161.73 2,161.73 2,161.73
c) Material
Bitumen emulsion @ 0.25 kg per sqm tonne 1.750 1.750 1.750 47,662.37 83,409.15 83,409.15 83,409.15 M-077
d) Overhead charges @ 8% on @ 10% on @ 12% on
7,117.21 8,896.51 10,675.81
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
9,608.23 9,786.16 9,964.09
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 7000 Sqm = a+b+c+d+e 105,690.53 107,647.76 109,604.99
Rate per Sqm = (a+b+c+d+e)/7000 15.10 15.38 15.66
Say 15.00 15.00 16.00
Note 1. Bitumen emulsion has been provided @ 0.275 kg per
sqm as per clause 503.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and actual quantity approved by the Engineer
after preliminary trials referred to in clause No. 503.4.3
Unit = sqm
Taking output = 7000 sqm
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.083 2.083 2.083 500.40 1,042.33 1,042.33 1,042.33 P&M-052
Air compressor 250 cfm hour 2.083 2.083 2.083 614.25 1,279.48 1,279.48 1,279.48 P&M-029
Emulsion Pressure Distributor (Spraying width 4.5 m) P&M-054
hour 1.944 1.944 1.944 1,112.00 2,161.73 2,161.73 2,161.73
c) Material
Bitumen emulsion @ 0.3 kg per sqm tonne 2.100 2.100 2.100 47,662.37 100,090.98 100,090.98 100,090.98 M-077
d) Overhead charges @ 8% on @ 10% on @ 12% on
8,451.75 10,564.69 12,677.63
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
11,409.87 11,621.16 11,832.46
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 7000 Sqm = a+b+c+d+e 125,508.54 127,832.78 130,157.01
Rate per Sqm = (a+b+c+d+e)/7000 17.93 18.26 18.59
Say 18.00 18.00 19.00
Note 1. Bitumen emulsion has been provided @ 0.325 kg per
sqm as per clause 503.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and actual quantity approved by the Engineer
after preliminary trials referred to in clause No. 503.4.3
Unit = cum
Taking output = 205 cum 451.00 tonnes
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Batch Type Hot Mix Plant
(i) HMP 200 TPH hour 3.007 14,634.90 44,007.14 P&M-035
(ii) HMP 160 TPH hour 3.758 10,338.30 38,851.33 P&M-036
(iii) HMP 120 TPH hour 5.011 8,372.70 41,955.60 P&M-037
Mechanical broom (2.1m sweeping width) hour 0.697 0.697 0.697 500.40 348.78 348.78 348.78 P&M-052
Air compressor 250 cfm hour 0.697 0.697 0.697 614.25 428.13 428.13 428.13 P&M-029
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.007 9,233.70 27,765.74 P&M-058
(ii) Paver (240HP) hour 3.758 9,233.70 34,700.24 P&M-058
(iii) Paver (174HP) hour 5.011 2,362.50 11,838.49 P&M-059
Electric generator
(i) 500 KVA hour 3.007 8,022.00 24,122.15 P&M-044
(ii) 400 KVA hour 3.758 6,470.10 24,314.64 P&M-045
(iii) 250 KVA hour 5.011 3,475.00 17,413.23 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 4.618 4,279.80 19,764.12 P&M-011
(ii) 2.1 Cum Capacity hour 6.826 2,640.75 18,025.76 P&M-012
(iii) 1 Cum Capacity hour 14.273 1,112.00 15,871.58 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 451 x L1 6.18 83,595.11 P&M-116
(ii) 14 cum capacity t.km 451 x L1 7.01 94,883.18 P&M-119
(iii) 10 cum capacity t.km 451 x L1 8.66 117,223.92 P&M-122
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.014 2,883.30 17,340.17 P&M-014
(ii) 14 cum capacity hour 7.516 2,556.75 19,216.53 P&M-015
(iii) 10 cum capacity hour 10.022 2,274.30 22,793.03 P&M-016
Smooth steel wheeled tandem roller for static and P&M-020
vibratory passaes hour 7.256 7.256 7.256 1,668.00 12,103.40 12,103.40 12,103.40
c) Material
i) Bitumen@ 3.3 per cent of mix tonne 14.883 14.883 14.883 46,556.37 692,898.47 692,898.47 692,898.47 M-074
weight of mix = 205 x 2.2 = 451 tonne
ii) Aggregate
Total weight of mix = 451.00 tonnes
Weight of bitumen = 14.88 tonnes
Weight of aggregate = 436.12 tonnes
Taking density of aggregate = 1.5 ton/cum
*Grading I ( 40 mm nominal size )
37.5 - 25 mm 15 per cent cum 43.612 43.612 43.612 1,887.12 82,301.21 82,301.21 82,301.21 M-048
25 - 10 mm 45 per cent cum 130.835 130.835 130.835 1,887.12 246,901.75 246,901.75 246,901.75 M-045
10 - 5 mm 25 per cent cum 72.686 72.686 72.686 1,887.12 137,167.43 137,167.43 137,167.43 M-039
5 mm and below15 per cent cum 14.537 14.537 14.537 1,887.12 27,433.11 27,433.11 27,433.11 M-029
* Any one of the alternative may be adopted as per
approved design
(i) for Grading I ( 40 mm nominal size )
d) Overhead charges @ 8% on @ 10% on @ 12% on
113,787.68 143,574.32 171,941.69
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
153,613.36 157,931.75 160,478.91
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Royalty of aggregate cum 247.133 247.133 247.133 - - - -
Cost for 205 cum = a+b+c+d+e 1,689,747.00 1,737,249.30 1,765,267.97
Rate per cum = (a+b+c+d+e)/205 8,242.67 8,474.39 8,611.06
Say 8,243.00 8,474.00 8,611.00
Note 1.Quantity of Bitumen has been taken for analysis
purpose. The actual quantity will depend upon job mix
formula.
2. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
Unit = cum
Taking output = 205 cum 451.00 tonnes
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Batch Type Hot Mix Plant
(i) HMP 200 TPH hour 3.007 14,634.90 44,002.27 P&M-035
(ii) HMP 160 TPH hour 3.758 10,338.30 38,854.78 P&M-036
(iii) HMP 120 TPH hour 5.011 8,372.70 41,956.53 P&M-037
Mechanical broom (2.1m sweeping width) hour 0.976 0.976 0.976 500.40 488.39 488.39 488.39 P&M-052
Air compressor 250 cfm hour 0.976 0.976 0.976 614.25 599.51 599.51 599.51 P&M-029
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.007 9,233.70 27,765.74 P&M-058
(ii) Paver (240HP) hour 3.758 9,233.70 34,700.24 P&M-058
(iii) Paver (174HP) hour 5.011 2,362.50 11,838.49 P&M-059
Electric generator
(i) 500 KVA hour 3.007 8,022.00 24,119.48 P&M-044
(ii) 400 KVA hour 3.758 6,470.10 24,316.79 P&M-045
(iii) 250 KVA hour 5.011 3,475.00 17,413.61 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.125 4,279.80 21,936.04 P&M-011
(ii) 2.1 Cum Capacity hour 7.577 2,640.75 20,008.43 P&M-012
(iii) 1 Cum Capacity hour 15.842 1,112.00 17,616.75 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 451 x L1 6.18 83,595.11 P&M-116
(ii) 14 cum capacity t.km 451 x L1 7.01 94,883.18 P&M-119
(iii) 10 cum capacity t.km 451 x L1 8.66 117,223.92 P&M-122
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.014 2,883.30 17,339.21 P&M-014
(ii) 14 cum capacity hour 7.516 2,556.75 19,217.39 P&M-015
(iii) 10 cum capacity hour 10.022 2,274.30 22,793.29 P&M-016
Smooth steel wheeled tandem roller for static and P&M-020
vibratory passaes hour 10.159 10.159 10.159 1,668.00 16,944.76 16,944.76 16,944.76
c) Material
i) Bitumen@ 3.4 per cent of mix tonne 15.334 15.334 15.334 46,556.37 713,895.39 713,895.39 713,895.39 M-074
weight of mix = 205 x 2.2 = 451 tonne
ii) Aggregate
Total weight of mix = 451.00 tonnes
Weight of bitumen = 15.33 tonnes
Weight of aggregate = 435.67 tonnes
Taking density of aggregate = 1.5 ton/cum
Grading II(19 mm nominal size)
25 - 10 mm 40 per cent cum 116.178 116.178 116.178 1,887.12 219,241.43 219,241.43 219,241.43 M-045
10 - 5 mm 40 per cent cum 116.178 116.178 116.178 1,887.12 219,241.43 219,241.43 219,241.43 M-039
5 mm and below 20 per cent cum 58.089 58.089 58.089 1,887.12 109,620.72 109,620.72 109,620.72 M-029
* Any one of the alternative may be adopted as per
approved design
(ii) for Grading II(19 mm nominal size)
d) Overhead charges @ 8% on @ 10% on @ 12% on
120,396.70 151,818.17 181,805.22
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
162,535.54 166,999.99 169,684.87
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Royalty of aggregate cum 232.355 232.355 232.355 - - - -
Cost for 205 cum = a+b+c+d+e 1,787,890.96 1,836,999.86 1,866,533.56
Rate per cum = (a+b+c+d+e)/205 8,721.42 8,960.97 9,105.04
Say 8,721.00 8,961.00 9,105.00
Note *1.Quantity of Bitumen has been taken for analysis
purpose. The actual quantity will depend upon job mix
formula.
2. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
Unit = cum
Taking output = 195 cum 450.45 tonnes 2.31
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.003 14,634.90 43,948.60 P&M-035
(ii) HMP 160 TPH hour 3.754 10,338.30 38,807.39 P&M-036
(iii) HMP 120 TPH hour 5.005 8,372.70 41,905.36 P&M-037
Mechanical broom (2.1m sweeping width) hour 0.663 0.663 0.663 500.40 331.90 331.90 331.90 P&M-052
Air compressor 250 cfm hour 0.663 0.663 0.663 614.25 407.41 407.41 407.41 P&M-029
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.003 9,233.70 27,728.80 P&M-058
(ii) Paver (240HP) hour 3.754 9,233.70 34,661.00 P&M-058
(iii) Paver (174HP) hour 5.005 2,362.50 11,824.31 P&M-059
Electric generator
(i) 500 KVA hour 3.003 8,022.00 24,090.07 P&M-044
(ii) 400 KVA hour 3.754 6,470.10 24,287.14 P&M-045
(iii) 250 KVA hour 5.005 3,475.00 17,392.38 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.138 4,279.80 21,990.96 P&M-011
(ii) 2.1 Cum Capacity hour 7.596 2,640.75 20,058.53 P&M-012
(iii) 1 Cum Capacity hour 15.882 1,112.00 17,660.86 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 450.45 x L1 6.18 83,493.16 P&M-116
(ii) 14 cum capacity t.km 450.45 x L1 7.01 94,767.47 P&M-119
(iii) 10 cum capacity t.km 450.45 x L1 8.66 117,080.96 P&M-122
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.006 2,883.30 17,317.10 P&M-014
(ii) 14 cum capacity hour 7.508 2,556.75 19,194.80 P&M-015
(iii) 10 cum capacity hour 10.010 2,274.30 22,765.74 P&M-016
Smooth steel wheeled tandem roller for static and P&M-020
vibratory passaes hour 9.663 9.663 9.663 1,668.00 16,118.19 16,118.19 16,118.19
c) Material
i) Bitumen@ 4 per cent of mix tonne 18.018 18.018 18.018 46,556.37 838,852.69 838,852.69 838,852.69 M-074
weight of mix = 195 x 2.31 = 450.450 tonne
ii) Aggregate
Total weight of mix = 450.45 tonnes
Weight of bitumen = 18.02 tonnes
Weight of aggregate = 432.43 tonnes
Taking density of aggregate = 1.5 ton/cum
Grading - I40 mm (Nominal Size)
37.5 - 25 mm 22 per cent cum 63.423 63.423 63.423 1,887.12 119,687.69 119,687.69 119,687.69 M-048
25 - 10 mm 13 per cent cum 37.477 37.477 37.477 1,887.12 70,724.54 70,724.54 70,724.54 M-045
10 -4.75 mm 19 per cent cum 54.775 54.775 54.775 1,887.12 103,366.64 103,366.64 103,366.64 M-039
4.75 mm and below 44 per cent cum 126.847 126.847 126.847 1,887.12 239,375.38 239,375.38 239,375.38 M-029
Filler @ 2 per cent of weight of aggregates. tonne 8.649 8.649 8.649 3,753.00 32,459.70 32,459.70 32,459.70 M-190
* Any one of the alternative may be adopted as per
approved design
Grading - I40 mm (Nominal Size)
d) Overhead charges @ 8% on @ 10% on @ 12% on
131,684.97 165,926.97 198,734.76
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
177,774.70 182,519.67 185,485.78
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Royalty of aggregate cum 227.748 227.748 227.748 - - - -
Cost for 195 cum = a+b+c+d+e 1,955,521.75 2,007,716.37 2,040,343.54
Rate per cum = (a+b+c+d+e)/195 10,028.32 10,295.98 10,463.30
Say 10,028.00 10,296.00 10,463.00
Note *1.Quantity of Bitumen has been taken for analysis
purpose. The actual quantity will depend upon job mix
formula.
2. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
Unit = cum
Taking output = 195 cum 450.45 tonnes 2.31
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.003 14,634.90 43,948.60 P&M-035
(ii) HMP 160 TPH hour 3.754 10,338.30 38,807.39 P&M-036
(iii) HMP 120 TPH hour 5.005 8,372.70 41,905.36 P&M-037
Mechanical broom (2.1m sweeping width) hour 0.663 0.663 0.663 500.40 331.90 331.90 331.90 P&M-052
Air compressor 250 cfm hour 0.663 0.663 0.663 614.25 407.41 407.41 407.41 P&M-029
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.003 9,233.70 27,728.80 P&M-058
(ii) Paver (240HP) hour 3.754 9,233.70 34,661.00 P&M-058
(iii) Paver (174HP) hour 5.005 2,362.50 11,824.31 P&M-059
Electric generator
(i) 500 KVA hour 3.003 8,022.00 24,090.07 P&M-044
(ii) 400 KVA hour 3.754 6,470.10 24,287.14 P&M-045
(iii) 250 KVA hour 5.005 3,475.00 17,392.38 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.112 4,279.80 21,876.40 P&M-011
(ii) 2.1 Cum Capacity hour 7.556 2,640.75 19,954.04 P&M-012
(iii) 1 Cum Capacity hour 15.799 1,112.00 17,568.85 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 450.45 x L1 6.18 83,493.16 P&M-116
(ii) 14 cum capacity t.km 450.45 x L1 7.01 94,767.47 P&M-119
(iii) 10 cum capacity t.km 450.45 x L1 8.66 117,080.96 P&M-122
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.006 2,883.30 17,317.10 P&M-014
(ii) 14 cum capacity hour 7.508 2,556.75 19,194.80 P&M-015
(iii) 10 cum capacity hour 10.010 2,274.30 22,765.74 P&M-016
Smooth steel wheeled tandem roller for static and P&M-020
vibratory passaes hour 9.663 9.663 9.663 1,668.00 16,118.19 16,118.19 16,118.19
c) Material
i) Bitumen@ 4.5 per cent of mix tonne 20.270 20.270 20.270 46,556.37 943,709.28 943,709.28 943,709.28 M-074
ii) Aggregate
Total weight of mix = 450.45 tonnes
Weight of bitumen = 20.27 tonnes
Weight of aggregate = 430.18 tonnes
Taking density of aggregate = 1.5 ton/cum
Grading - II19 mm (Nominal Size)
25 - 10 mm 30 per cent cum 86.036 86.036 86.036 1,887.12 162,360.43 162,360.43 162,360.43 M-045
10 - 5 mm 28 per cent cum 80.300 80.300 80.300 1,887.12 151,536.40 151,536.40 151,536.40 M-039
5 mm and below 40 per cent cum 114.715 114.715 114.715 1,887.12 216,480.57 216,480.57 216,480.57 M-029
Filler @ 2 per cent of weight of aggregates. cum 8.604 8.604 8.604 3,753.00 32,289.29 32,289.29 32,289.29 M-190
* Any one of the alternative may be adopted as per
approved design
Grading - II19 mm (Nominal Size)
d) Overhead charges @ 8% on @ 10% on @ 12% on
139,828.55 176,107.46 210,952.84
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
188,768.54 193,718.20 196,889.32
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Royalty of aggregate cum 289.654 289.654 289.654 - - - -
Cost for 195 cum = a+b+c+d+e 2,076,453.94 2,130,900.22 2,165,782.49
Rate per cum = (a+b+c+d+e)/195 10,648.48 10,927.69 11,106.58
Say 10,648.00 10,928.00 11,107.00
Note *1.Quantity of Bitumen has been taken for analysis
purpose. The actual quantity will depend upon job mix
formula.
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
2. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
Unit = cum
Taking output = 191 cum 450.76 tonnes 2.36
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.005 14,634.90 43,978.85 P&M-035
(ii) HMP 160 TPH hour 3.756 10,338.30 38,834.10 P&M-036
(iii) HMP 120 TPH hour 5.008 8,372.70 41,934.20 P&M-037
Mechanical broom (2.1m sweeping width) hour 1.137 1.137 1.137 500.40 568.91 568.91 568.91 P&M-052
Air compressor 250 cfm hour 1.137 1.137 1.137 614.25 698.34 698.34 698.34 P&M-029
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.005 9,233.70 27,747.88 P&M-058
(ii) Paver (240HP) hour 3.756 9,233.70 34,684.86 P&M-058
(iii) Paver (174HP) hour 5.008 2,362.50 11,832.45 P&M-059
Electric generator
(i) 500 KVA hour 3.005 8,022.00 24,106.64 P&M-044
(ii) 400 KVA hour 3.756 6,470.10 24,303.85 P&M-045
(iii) 250 KVA hour 5.008 3,475.00 17,404.34 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.078 4,279.80 21,731.06 P&M-011
(ii) 2.1 Cum Capacity hour 7.506 2,640.75 19,821.47 P&M-012
(iii) 1 Cum Capacity hour 15.694 1,112.00 17,452.13 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 450.76 x L1 6.18 83,550.62 P&M-116
(ii) 14 cum capacity t.km 450.76 x L1 7.01 94,832.69 P&M-119
(iii) 10 cum capacity t.km 450.76 x L1 8.66 117,161.54 P&M-122
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.010 2,883.30 17,329.02 P&M-014
(ii) 14 cum capacity hour 7.513 2,556.75 19,208.01 P&M-015
(iii) 10 cum capacity hour 10.017 2,274.30 22,781.41 P&M-016
Smooth steel wheeled tandem roller for static and P&M-020
vibratory passaes hour 11.831 11.831 11.831 1,668.00 19,734.45 19,734.45 19,734.45
Pnumetic Tyre roller hour 2.404 3.005 4.007 2,562.00 6,159.18 7,698.98 10,265.31 P&M-022
c) Material
i) Bitumen@ 5.2 per cent of mix tonne 23.440 23.440 23.440 46,556.37 1,091,281.34 1,091,281.34 1,091,281.34 M-074
ii) Aggregate
Total weight of mix = 450.76 tonnes
Weight of bitumen = 23.44 tonnes
Weight of aggregate = 427.32 tonnes
Taking density of aggregate = 1.5 ton/cum
* Grading - I-19 mm (Nominal Size)
20 - 10 mm 38 per cent cum 108.255 108.255 108.255 1,887.12 204,290.51 204,290.51 204,290.51 M-044
10 - 5 mm 17 per cent cum 48.430 48.430 48.430 1,887.12 91,393.37 91,393.37 91,393.37 M-039
5 mm and below 40 per cent cum 122.499 122.499 122.499 1,887.12 231,170.69 231,170.69 231,170.69 M-029
Filler @ 2 per cent of weight of aggregates. cum 8.546 8.546 8.546 3,753.00 32,073.14 32,073.14 32,073.14 M-190
* Any one of the alternative may be adopted as per
approved design
* Grading - I-19 mm (Nominal Size)
d) Overhead charges @ 8% on @ 10% on @ 12% on
152,158.66 191,676.40 229,945.37
(a+b+c) (a+b+c) (a+b+c)
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
e) Contractor's profit @ 10% on @ 10% on @ 10% on
205,414.19 210,844.04 214,615.68
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Royalty of aggregate cum 287.730 287.730 287.730 - - - -
Cost for 191 cum = a+b+c+d+e 2,259,556.12 2,319,284.39 2,360,772.43
Rate per cum = (a+b+c+d+e)/191 11,830.14 12,142.85 12,360.07
Say 11,830.00 12,143.00 12,360.00
Note *1.Quantity of Bitumen has been taken for analysis
purpose. The actual quantity will depend upon job mix
formula.
2. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
Unit = cum
Taking output = 191 cum 450.76 tonnes 2.36
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.005 14,634.90 43,978.85 P&M-035
(ii) HMP 160 TPH hour 3.756 10,338.30 38,834.10 P&M-036
(iii) HMP 120 TPH hour 5.008 8,372.70 41,934.20 P&M-037
Mechanical broom (2.1m sweeping width) hour 1.624 1.624 1.624 500.40 812.72 812.72 812.72 P&M-052
Air compressor 250 cfm hour 1.624 1.624 1.624 614.25 997.63 997.63 997.63 P&M-029
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.005 9,233.70 27,747.88 P&M-058
(ii) Paver (240HP) hour 3.756 9,233.70 34,684.86 P&M-058
(iii) Paver (174HP) hour 5.008 2,362.50 11,832.45 P&M-059
Electric generator
(i) 500 KVA hour 3.005 8,022.00 24,106.64 P&M-044
(ii) 400 KVA hour 3.756 6,470.10 24,303.85 P&M-045
(iii) 250 KVA hour 5.008 3,475.00 17,404.34 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.004 4,279.80 21,416.12 P&M-011
(ii) 2.1 Cum Capacity hour 7.378 2,640.75 19,483.45 P&M-012
(iii) 1 Cum Capacity hour 15.553 1,112.00 17,294.94 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 450.76 x L1 6.18 83,550.62 P&M-116
(ii) 14 cum capacity t.km 450.76 x L1 7.01 94,832.69 P&M-119
(iii) 10 cum capacity t.km 450.76 x L1 8.66 117,161.54 P&M-122
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.010 2,883.30 17,329.02 P&M-014
(ii) 14 cum capacity hour 7.513 2,556.75 19,208.01 P&M-015
(iii) 10 cum capacity hour 10.017 2,274.30 22,781.41 P&M-016
Smooth steel wheeled tandem roller for static and P&M-020
vibratory passaes hour 16.902 16.902 16.902 1,668.00 28,192.07 28,192.07 28,192.07
Pneumatic Tyre roller hour 2.404 3.005 4.007 2,562.00 6,159.18 7,698.98 10,265.31 P&M-022
c) Material
i) Bitumen@ 5.4 per cent of mix tonne 24.341 24.341 24.341 46,556.37 1,133,230.49 1,133,230.49 1,133,230.49 M-074
ii) Aggregate
Total weight of mix = 450.76 tonnes
Weight of bitumen = 24.34 tonnes
Weight of aggregate = 426.42 tonnes
Taking density of aggregate = 1.5 ton/cum
Grading - II-13 mm (Nominal Size)
13.2 - 10 mm 21 per cent cum 59.699 59.699 59.699 1,887.12 112,659.36 112,659.36 112,659.36 M-043
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
10 - 5 mm 17 per cent cum 48.327 48.327 48.327 1,887.12 91,199.00 91,199.00 91,199.00 M-039
5 mm and below 60 per cent cum 170.568 170.568 170.568 1,887.12 321,882.81 321,882.81 321,882.81 M-029
Filler @ 2 per cent of weight of aggregates. cum 8.528 8.528 8.528 3,753.00 32,005.58 32,005.58 32,005.58 M-190
* Any one of the alternative may be adopted as per
approved design
* Grading - I-19 mm (Nominal Size)
d) Overhead charges @ 8% on @ 10% on @ 12% on
156,114.98 196,619.49 235,898.77
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
210,755.22 216,281.44 220,172.19
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Royalty of aggregate cum 287.122 287.122 287.122 - - - -
Cost for 191 cum = a+b+c+d+e 2,318,307.45 2,379,095.79 2,421,894.08
Rate per cum = (a+b+c+d+e)/191 12,137.74 12,456.00 12,680.07
Say 12,138.00 12,456.00 12,680.00
Note *1.Quantity of Bitumen has been taken for analysis
purpose. The actual quantity will depend upon job mix
formula.
2. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
Unit = sqm
Taking output = 9000 sqm
5.06 Case -I :-19 mm nominal chipping size
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.679 2.679 2.679 500.40 1,340.36 1,340.36 1,340.36 P&M-052
Air compressor 250 cfm hour 2.679 2.679 2.679 614.25 1,645.31 1,645.31 1,645.31 P&M-029
Bitumen pressure distributor (Spraying width 4.5 m) P&M-053
hour 1.250 1.250 1.250 1,729.35 2,161.69 2,161.69 2,161.69
Hydraulic self propelled chip spreader hour 7.401 7.401 7.401 2,220.75 16,436.47 16,436.47 16,436.47 P&M-065
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 0.823 4,279.80 3,523.01 P&M-011
(ii) 2.1 Cum Capacity hour 1.216 2,640.75 3,211.72 P&M-012
(iii) 1 Cum Capacity hour 2.547 1,112.00 2,832.45 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 202.5 x L1 6.18 37,534.39 P&M-116
(ii) 14 cum capacity t.km 202.5 x L1 7.01 42,602.76 P&M-119
(iii) 10 cum capacity t.km 202.5 x L1 8.66 52,633.80 P&M-122
For loading & unloading time
(i) 18 cum capacity hour 8.224 2,883.30 23,713.66 P&M-014
(ii) 14 cum capacity hour 8.618 2,556.75 22,032.87 P&M-015
(iii) 10 cum capacity hour 9.948 2,274.30 22,625.84 P&M-016
Smooth steel wheeled tandem roller for static and P&M-020
vibratory passaes hour 5.973 5.973 5.973 1,668.00 9,963.17 9,963.17 9,963.17
Pnumetic Tyre roller hour 5.973 5.973 5.973 2,562.00 15,303.14 15,303.14 15,303.14 P&M-022
c) Material
Bitumen@ 1.20 kg per sqm tonne 10.800 10.800 10.800 46,556.37 502,808.81 502,808.81 502,808.81 M-074
Crushed stone chipping,19 mm nominal size @ 0.015 M-046
cum per sqm cum 135.000 135.000 135.000 1,887.12 254,761.62 254,761.62 254,761.62
d) Overhead charges @ 8% on @ 10% on @ 12% on
70,015.86 87,827.45 106,622.31
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
94,521.41 96,610.20 99,514.16
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 9000 sqm = a+b+c+d+e 1,039,735.50 1,062,712.19 1,094,655.74
Rate per sqm = (a+b+c+d+e)/9000 115.53 118.08 121.63
Say 116.00 118.00 122.00
5.06 509 Case - II 13 mm nominal size chipping
Unit = sqm
Taking output = 9000 sqm
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Machinery
Mechanical broom (2.1m sweeping width) hour 2.679 2.679 2.679 500.40 1,340.36 1,340.36 1,340.36 P&M-052
Air compressor 250 cfm hour 2.679 2.679 2.679 614.25 1,645.31 1,645.31 1,645.31 P&M-029
Bitumen pressure distributor (Spraying width 4.5 m) P&M-053
hour 1.250 1.250 1.250 1,729.35 2,161.69 2,161.69 2,161.69
Hydraulic self propelled chip spreader hour 7.401 7.401 7.401 2,220.75 16,436.47 16,436.47 16,436.47 P&M-065
Front end loader for loading
(i) 3.1 Cum Capacity hour 0.544 4,279.80 2,329.73 P&M-011
(ii) 2.1 Cum Capacity hour 0.804 2,640.75 2,122.03 P&M-012
(iii) 1 Cum Capacity hour 1.688 1,112.00 1,876.50 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 135 x L1 6.18 25,022.93 P&M-116
(ii) 14 cum capacity t.km 135 x L1 7.01 28,401.84 P&M-119
(iii) 10 cum capacity t.km 135 x L1 8.66 35,089.20 P&M-122
For loading & unloading time
(i) 18 cum capacity hour 7.946 2,883.30 22,909.75 P&M-014
(ii) 14 cum capacity hour 8.205 2,556.75 20,977.85 P&M-015
(iii) 10 cum capacity hour 9.089 2,274.30 20,670.69 P&M-016
Smooth steel wheeled tandem roller for static and P&M-020
vibratory passaes hour 3.982 3.982 3.982 1,668.00 6,642.11 6,642.11 6,642.11
Pnumetic Tyre roller hour 3.982 3.982 3.982 2,562.00 10,201.88 10,201.88 10,201.88 P&M-022
c) Material
Bitumen@ 1.20 kg per sqm tonne 9.000 9.000 9.000 46,556.37 419,007.34 419,007.34 419,007.34 M-074
Crushed stone chipping,13 mm nominal size @ 0.015 M-051
cum per sqm cum 90.000 90.000 90.000 1,887.12 169,841.08 169,841.08 169,841.08
d) Overhead charges @ 8% on @ 10% on @ 12% on
54,683.62 68,478.46 82,910.31
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
73,822.89 75,326.30 77,382.96
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 9000 sqm = a+b+c+d+e 812,051.78 828,589.34 851,212.52
Rate per sqm = (a+b+c+d+e)/9000 90.23 92.07 94.58
Say 90.00 92.00 95.00
Note 1.Where the proposed aggregate fails to pass the
stripping test, an approved adhesion agent may be added
to the binder as per clause 510.2.4. Alternatively, chips
may be pre-coated as per clause 510.2.5
Unit = cum
Taking output = 7860 sqm 47.16 cum
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 0.314 14,634.90 4,601.21 P&M-035
(ii) HMP 160 TPH hour 0.393 10,338.30 4,062.95 P&M-036
(iii) HMP 120 TPH hour 0.524 8,372.70 4,387.29 P&M-037
Mechanical broom (2.1m sweeping width) hour 2.339 2.339 2.339 500.40 1,170.58 1,170.58 1,170.58 P&M-052
Air compressor 250 cfm hour 2.339 2.339 2.339 614.25 1,436.91 1,436.91 1,436.91 P&M-029
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 0.314 9,233.70 2,903.08 P&M-058
(ii) Paver (240HP) hour 0.393 9,233.70 3,628.84 P&M-058
(iii) Paver (174HP) hour 0.524 2,362.50 1,237.95 P&M-059
Electric generator
(i) 500 KVA hour 0.314 8,022.00 2,522.12 P&M-044
(ii) 400 KVA hour 0.393 6,470.10 2,542.75 P&M-045
(iii) 250 KVA hour 0.524 3,475.00 1,820.90 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 0.832 4,279.80 3,560.79 P&M-011
(ii) 2.1 Cum Capacity hour 1.230 2,640.75 3,248.81 P&M-012
(iii) 1 Cum Capacity hour 2.572 1,112.00 2,860.47 P&M-013
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Tipper
For Transportation
(i) 18 cum capacity t.km 103.752 x L1 6.18 19,230.95 P&M-116
(ii) 14 cum capacity t.km 103.752 x L1 7.01 21,827.76 P&M-119
(iii) 10 cum capacity t.km 103.752 x L1 8.66 26,967.22 P&M-122
For loading & unloading time
(i) 18 cum capacity hour 0.629 2,883.30 1,813.02 P&M-014
(ii) 14 cum capacity hour 0.786 2,556.75 2,009.61 P&M-015
(iii) 10 cum capacity hour 1.048 2,274.30 2,383.47 P&M-016
Smooth steel wheeled tandem roller for static and P&M-020
vibratory passaes hour 2.087 2.087 2.087 1,668.00 3,480.47 3,480.47 3,480.47
c) Material
Bitumen@ 6.80 kg per 10 sqm tonne 5.345 5.345 5.345 46,556.37 248,834.49 248,834.49 248,834.49 M-074
Crushed stone chipping of 6.7 mm size defined as M-049
passing 11.2 mm sieve and retained on 2.36 mm sieve cum 47.160 47.160 47.160 1,887.12 88,996.73 88,996.73 88,996.73
applied @ 0.06 cum per 10 sqm
* Any one of the alternative may be adopted as per
approved design
d) Overhead charges @ 8% on @ 10% on @ 12% on
30,777.57 38,740.91 46,769.49
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
41,549.72 42,615.01 43,651.52
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 7860 Sqm = a+b+c+d+e 457,046.87 468,765.06 480,166.72
Rate per Sqm. = (a+b+c+d+e)/7860 58.15 59.64 61.09
Say 58.00 60.00 61.00
Unit = sqm
Taking output = 35 sqm 2.0125 tonnes
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-13
Mazdoor skilled day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
b) Machinery
Mechanical broom (2.1m sweeping width) hour 0.010 0.010 0.010 500.40 5.00 5.00 5.00 P&M-052
Air compressor 250 cfm hour 0.010 0.010 0.010 614.25 6.14 6.14 6.14 P&M-029
Mastic cooker 1 tonne capacity hour 3.000 3.000 3.000 1,042.50 3,127.50 3,127.50 3,127.50 P&M-056
Bitumen boiler 1500 litres capacity hour 3.000 3.000 3.000 743.40 2,230.20 2,230.20 2,230.20 P&M-055
Tractor for towing and positioning of mastic cooker and P&M-026
bitumen boiler hour 1.000 1.000 1.000 1,876.50 1,876.50 1,876.50 1,876.50
c) Material
Base mastic (without coarse aggregates) = 60 per cent
iii) Lime stone dust filler with calcium content not less M-190
than 80 per cent by weight @ 17.92 per cent by weight tonne 0.361 0.361 0.361 3,753.00 1,353.48 1,353.48 1,353.48
of mix = 2 x 17.92/100 = 0.36
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
iv) Coarse aggregates 6.3 mm to 13.2 mm @ 40 per cent M-042
by weight of mix = 2 x 40/100 = 0.8 MT = 0.8/1.456 = 0.55 cum 0.553 0.553 0.553 1,887.12 1,043.36 1,043.36 1,043.36
Unit = cum
Taking output = 120 Cum 276 tonnes
A (i) Using by Bituminous Macadam Grading-I
a) Labour
Mate day 0.280 0.280 0.280 617.00 172.76 172.76 172.76 L-12
Mazdoor day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
Mazdoor skilled day 3.000 3.000 3.000 565.73 1,697.19 1,697.19 1,697.19 L-15
b) Machinery
Milling Machine
Milling Machine with 2 meter Drum Width hour 5.926 11,982.60 71,008.89 P&M-083
Milling Machine with 1.3 meter Drum Width 9.117 8,006.25 72,992.98 P&M-082
Milling Machine with 1.2 meter Drum Width 9.877 5,592.30 55,235.15 P&M-081
Bitumen pressure distributor (Spraying width 4.5m) hour 0.667 0.667 0.667 1,729.35 1,152.90 1,152.90 1,152.90 P&M-053
Batch Type Hot Mix Plant
(i) HMP 200 TPH hour 1.840 14,634.90 26,928.22 P&M-035
(ii) HMP 160 TPH hour 2.300 10,338.30 23,778.09 P&M-036
(iii) HMP 120 TPH hour 3.067 8,372.70 25,676.28 P&M-037
Mechanical broom (2.1m sweeping width) hour 0.571 0.571 0.571 500.40 285.94 285.94 285.94 P&M-052
Air compressor 250 cfm hour 0.571 0.571 0.571 614.25 351.00 351.00 351.00 P&M-029
Paver Finisher hydrostatic with sensor control compatible
with the hot mix plant
(i) Paver (240HP) hour 1.840 9,233.70 16,990.01
(ii) Paver (240HP) hour 2.300 9,233.70 21,237.51
(iii) Paver (174HP) hour 3.067 2,362.50 7,245.00
Electric generator
(i) 500 KVA hour 1.840 8,022.00 14,760.48 P&M-044
(ii) 400 KVA hour 2.300 6,470.10 14,881.23 P&M-045
(iii) 250 KVA hour 3.067 3,475.00 10,656.67 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 1.868 4,279.80 7,994.67 P&M-011
(ii) 2.1 Cum Capacity hour 2.762 2,640.75 7,293.75 P&M-012
(iii) 1 Cum Capacity hour 5.775 1,112.00 6,421.80 P&M-013
Tipper
For Transportation Plant to Site
(i) 18 cum capacity t.km 276 x L1 7.51 62,171.16 P&M-117
(ii) 14 cum capacity t.km 276 x L1 8.52 70,566.30 P&M-120
(iii) 10 cum capacity t.km 276 x L1 10.53 87,181.50 P&M-123
Tipper for loading & unloading time
(i) 18 cum capacity hour 3.680 2,883.30 10,610.54 P&M-014
(ii) 14 cum capacity hour 4.600 2,556.75 11,761.05 P&M-015
(iii) 10 cum capacity hour 6.133 2,274.30 13,948.28 P&M-016
For Transportaion of Dismantle Material Site to Plant
For Transportation Plant to Site
(i) 18 cum capacity t.km 276 x L1 7.51 62,171.16 P&M-117
(ii) 14 cum capacity t.km 276 x L1 8.52 70,566.30 P&M-120
(iii) 10 cum capacity t.km 276 x L1 10.53 87,181.50 P&M-123
Tipper for loading
(i) 18 cum capacity hour 5.926 2,883.30 17,086.44 P&M-014
(ii) 14 cum capacity hour 9.117 2,556.75 23,309.89 P&M-015
(iii) 10 cum capacity hour 9.877 2,274.30 22,463.26 P&M-016
Smooth steel wheeled tandem roller for static and P&M-019
vibratory passaes hour 10.619 10.619 10.619 417.00 813.15 813.15 813.15
c) Material
i) Bitumen
A bitumen content is 3.3 per cent bitumen weight of mix.
For reclaimed material, fresh bitumen will be required to
the extent of 60 per cent of normal requirement.
Unit = sqm
Taking output = 10500 Sqm
(i) a) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 3.125 3.125 3.125 500.40 1,563.75 1,563.75 1,563.75 P&M-052
Air compressor 250 cfm hour 3.125 3.125 3.125 614.25 1,919.53 1,919.53 1,919.53 P&M-029
Bitumen pressure distributor (Spraying width 4.5 m) P&M-053
tonne 2.917 2.917 2.917 1,729.35 5,043.94 5,043.94 5,043.94
c) Material
Bitumen emulsion @ 0.75 kg per sqm tonne 7.880 7.880 7.880 47,662.37 375,579.48 375,579.48 375,579.48 M-077
d) Overhead charges @ 8% on @ 10% on @ 12% on
30,857.22 38,571.53 46,285.84
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
41,657.25 42,428.68 43,200.11
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10500 Sqm = a+b+c+d+e 458,229.78 466,715.52 475,201.25
Rate per Sqm = (a+b+c+d+e)/10500 43.64 44.45 45.26
Say 44.00 44.00 45.00
(ii) 1.In case it is decided by the engineer to blind the fog
spray, the following may be added
a) Labour
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Mazdoor for precoating of grit day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
b) Material
Crushed stone grit 3 mm size @ 3.75 kg per sqm cum 26.250 26.250 26.250 1,887.12 49,536.98 49,536.98 49,536.98 M-023
Bitumen emulsion for precoating grit @ 2 per cent of M-077
grit,39.38 x 0.02 tonne 0.790 0.790 0.790 47,662.37 37,653.27 37,653.27 37,653.27
Cost for 10500 Sqm = a+b 89,335.05 89,335.05 89,335.05
Cost per qm 8.508 8.508 8.508
c) Overhead charges @ 8% on @ 10% on @ 12% on
14,293.61 17,867.01 21,440.41
(a+b+c) (a+b+c) (a+b+c)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
19,296.37 19,653.71 20,011.05
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10500 Sqm = a+b+c+d 212,260.09 216,190.83 220,121.57
Rate per Sqm = (a+b+c+d)/10500 20.22 20.59 20.96
Say 20.00 21.00 21.00
5.15 518 Bituminous Cold Mix (Including Gravel Emulsion)
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Unit = cum
Taking output = 205 Cum 450 tonnes
(i) Using bitumen emulsion and 9.5 mm or 13.2 mm size
aggregate
Composition of mix (450 tonne) is assumed to be as
under:-
Bitumen Emulsion 8 percent By weight of total mix
Filler 2 per cent
Total aggregates 90 per cent
Proportion of aggregates
19 mm to 9.5 mm25 per cent
9.5 mm to 6 mm29 per cent
6 mm to 0.075 mm 36 per cent
a) Labour
Mate day 0.480 0.480 0.480 617.00 296.16 296.16 296.16 L-12
Mazdoor day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.000 14,634.90 43,904.70 P&M-035
(ii) HMP 160 TPH hour 3.750 10,338.30 38,768.63 P&M-036
(iii) HMP 120 TPH hour 5.000 8,372.70 41,863.50 P&M-037
Mechanical broom (2.1m sweeping width) hour 1.743 1.743 1.743 500.40 872.30 872.30 872.30 P&M-052
Air compressor 250 cfm hour 1.743 1.743 1.743 614.25 1,070.76 1,070.76 1,070.76 P&M-029
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.000 9,233.70 27,701.10 P&M-058
(ii) Paver (240HP) hour 3.750 9,233.70 34,626.38 P&M-058
(iii) Paver (174HP) hour 5.000 2,362.50 11,812.50 P&M-059
Electric generator
(i) 500 KVA hour 3.000 8,022.00 24,066.00 P&M-044
(ii) 400 KVA hour 3.750 6,470.10 24,262.88 P&M-045
(iii) 250 KVA hour 5.000 3,475.00 17,375.00 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 4.852 4,279.80 20,766.33 P&M-011
(ii) 2.1 Cum Capacity hour 6.923 2,640.75 18,282.12 P&M-012
(iii) 1 Cum Capacity hour 15.081 1,112.00 16,770.16 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L1 7.51 101,366.02 P&M-117
(ii) 14 cum capacity t.km 450 x L1 8.52 115,053.75 P&M-120
(iii) 10 cum capacity t.km 450 x L1 10.53 142,143.75 P&M-123
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.000 2,883.30 17,299.80 P&M-014
(ii) 14 cum capacity hour 7.500 2,556.75 19,175.63 P&M-015
(iii) 10 cum capacity hour 10.000 2,274.30 22,743.00 P&M-016
Smooth steel wheeled tandem roller for static and P&M-019
vibratory passaes hour 18.141 18.141 18.141 417.00 7,564.63 7,564.63 7,564.63
Pneumatic Tyre roller hour 2.569 3.000 4.000 2,562.00 6,581.58 7,686.00 10,248.00 P&M-022
c) Material
Bitumen emulsion @ 8 per cent tonne 36.000 36.000 36.000 47,662.37 1,715,845.36 1,715,845.36 1,715,845.36 M-077
Filler (lime)@ 2 per cent tonne 9.000 9.000 9.000 3,753.00 33,777.00 33,777.00 33,777.00 M-190
Aggregates size 19 to 9.5 mm - 450 x 0.25 x 1/1.5 cum 75.000 75.000 75.000 1,887.12 141,534.23 141,534.23 141,534.23 M-044
Aggregates size 9.5 to 6 mm - 450 x 0.29 x 1/1.5 cum 87.000 87.000 87.000 1,887.12 164,179.71 164,179.71 164,179.71 M-039
Aggregates size 6 to 0.075 mm - 450 x 0.36 x 1/1.5 M-029
cum 108.000 108.000 108.000 1,887.12 203,809.30 203,809.30 203,809.30
d) Overhead charges @ 8% on @ 10% on @ 12% on
201,363.54 253,321.41 304,597.76
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
271,840.78 278,653.55 284,291.24
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 205 cum = a+b+c+d+e 2,990,248.57 3,065,189.05 3,127,203.63
Rate per cum = (a+b+c+d+e)/205 14,586.58 14,952.14 15,254.65
Say 14,587.00 14,952.00 15,255.00
(Applicable to cases I to IV)
Note 1.Density of aggregates has been assumed 1.5 gms/cc
Unit = cum
Taking output = 205 Cum 450 tonnes
a) Labour
Mate day 0.480 0.480 0.480 617.00 296.16 296.16 296.16 L-12
Mazdoor day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.000 14,634.90 43,904.70 P&M-035
(ii) HMP 160 TPH hour 3.750 10,338.30 38,768.63 P&M-036
(iii) HMP 120 TPH hour 5.000 8,372.70 41,863.50 P&M-037
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.000 9,233.70 27,701.10 P&M-058
(ii) Paver (240HP) hour 3.750 9,233.70 34,626.38 P&M-058
(iii) Paver (174HP) hour 5.000 2,362.50 11,812.50 P&M-059
Electric generator
(i) 500 KVA hour 3.000 8,022.00 24,066.00 P&M-044
(ii) 400 KVA hour 3.750 6,470.10 24,262.88 P&M-045
(iii) 250 KVA hour 5.000 3,475.00 17,375.00 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.044 4,279.80 21,589.05 P&M-011
(ii) 2.1 Cum Capacity hour 7.441 2,640.75 19,648.50 P&M-012
(iii) 1 Cum Capacity hour 15.664 1,112.00 17,418.60 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L1 7.51 101,366.02 P&M-117
(ii) 14 cum capacity t.km 450 x L1 8.52 115,053.75 P&M-120
(iii) 10 cum capacity t.km 450 x L1 10.53 142,143.75 P&M-123
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.000 2,883.30 17,299.80 P&M-014
(ii) 14 cum capacity hour 7.500 2,556.75 19,175.63 P&M-015
(iii) 10 cum capacity hour 10.000 2,274.30 22,743.00 P&M-016
Smooth steel wheeled tandem roller for static and P&M-019
vibratory passaes hour 18.141 18.141 18.141 417.00 7,564.63 7,564.63 7,564.63
c) Material
Composition of mix (450 tonne) is assumed to be as
under:-
Density 2.20 tonne per cum
Weight450 tonne
Bitumen5 per cent
Filler2 per cent
Sand of size 4.75 to 0.075 mm 93 per cent
Bitumen@ 5 per cent tonne 22.500 22.500 22.500 46,556.37 1,047,518.35 1,047,518.35 1,047,518.35 M-074
Filler (lime)@ 2 per cent tonne 9.000 9.000 9.000 3,753.00 33,777.00 33,777.00 33,777.00 M-190
Sand of size 4.75 to 0.075 mm - 450 x 0.93 x 1/1.5 cum 288.620 288.620 288.620 1,994.03 575,517.23 575,517.23 575,517.23 M-004
d) Overhead charges @ 8% on @ 10% on @ 12% on
152,560.75 192,261.84 230,932.68
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
205,957.01 211,488.02 215,537.17
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 205 cum = a+b+c+d+e 2,265,527.07 2,326,368.27 2,370,908.85
Rate per cum = (a+b+c+d+e)/205 11,051.35 11,348.14 11,565.41
Say 11,051.00 11,348.00 11,565.00
Note 1. Tack coat will be measured and paid separately
Unit = sqm
Taking output = 10500 sqm
a) Labour
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Mazdoor day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 3.125 3.125 3.125 500.40 1,563.75 1,563.75 1,563.75 P&M-052
Air compressor 250 cfm hour 3.125 3.125 3.125 614.25 1,919.53 1,919.53 1,919.53 P&M-029
Bitumen pressure distributor (Spraying width 4.5 m) P&M-053
hour 2.917 2.917 2.917 1,729.35 5,043.94 5,043.94 5,043.94
Hydraulic Chip spreader hour 5.397 5.397 5.397 2,220.75 11,984.93 11,984.93 11,984.93 P&M-065
Smooth wheeled road roller 8-10 tonne hour 5.397 5.397 5.397 417.00 2,250.46 2,250.46 2,250.46 P&M-019
c) Material
Modified binder tonne 9.450 9.450 9.450 46,896.37 443,170.71 443,170.71 443,170.71 M-078
Crushed stone aggregates 5.6 mm size cum 105.000 105.000 105.000 1,887.12 198,147.93 198,147.93 198,147.93 M-049
d) Overhead charges @ 8% on @ 10% on @ 12% on
53,298.08 66,622.60 79,947.12
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
71,952.41 73,284.86 74,617.32
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10500 Sqm = a+b+c+d+e 791,476.54 806,133.51 820,790.48
Rate per Sqm = (a+b+c+d+e)/10500 75.38 76.77 78.17
Say 75.00 77.00 78.00
5.17 (ii) Stress absorbing membrane (SAM) with crack width 6
mm to 9 mm
Providing and laying of a stress absorbing membrane
over a cracked road surface, with crack width 6 to 9 mm
after cleaning with a mechanical broom, using modified
binder complying with IRC:SP: 53, sprayed at the rate of
11 kg per 10 sqm and spreading 11.2 mm crushed stone
aggregates @ 0.12 cum per 10 sqm, sweeping the
surface for uniform spread of aggregates and surface
finished to conform to clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Mazdoor day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 3.125 3.125 3.125 500.40 1,563.75 1,563.75 1,563.75 P&M-052
Air compressor 250 cfm hour 3.125 3.125 3.125 614.25 1,919.53 1,919.53 1,919.53 P&M-029
Bitumen pressure distributor (Spraying width 4.5 m) P&M-053
hour 2.917 2.917 2.917 1,729.35 5,043.94 5,043.94 5,043.94
Hydraulic Chip spreader hour 5.397 5.397 5.397 2,220.75 11,984.93 11,984.93 11,984.93 P&M-065
Smooth wheeled road roller 8-10 tonne hour 5.397 5.397 5.397 417.00 2,250.46 2,250.46 2,250.46 P&M-019
c) Material
Modified binder tonne 11.550 11.550 11.550 46,896.37 541,653.09 541,653.09 541,653.09 M-078
Crushed stone chipping 11.2 mm size cum 105.000 105.000 105.000 1,887.12 198,147.93 198,147.93 198,147.93 M-050
d) Overhead charges @ 8% on @ 10% on @ 12% on
61,176.67 76,470.84 91,765.01
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
82,588.51 84,117.93 85,647.34
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10500 Sqm = a+b+c+d+e 908,473.60 925,297.19 942,120.77
Rate per Sqm = (a+b+c+d+e)/10500 86.52 88.12 89.73
Say 87.00 88.00 90.00
5.17 (iii) Stress absorbing membrane (SAM) crack width above 9
mm and cracked area above 50 per cent
Unit = sqm
Taking output = 10500 sqm
a) Labour
Mate day 0.240 0.240 0.240 617.00 148.08 148.08 148.08 L-12
Mazdoor day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Machinery
Mechanical broom (2.1m sweeping width) hour 3.125 3.125 3.125 500.40 1,563.75 1,563.75 1,563.75 P&M-052
Air compressor 250 cfm hour 3.125 3.125 3.125 614.25 1,919.53 1,919.53 1,919.53 P&M-029
Bitumen pressure distributor (Spraying width 4.5 m) P&M-053
hour 2.917 2.917 2.917 1,729.35 5,043.94 5,043.94 5,043.94
Hydraulic Chip spreader hour 5.397 5.397 5.397 2,220.75 11,984.93 11,984.93 11,984.93 P&M-065
Smooth wheeled road roller 8-10 tonne hour 5.397 5.397 5.397 417.00 2,250.46 2,250.46 2,250.46 P&M-019
c) Material
Modified binder tonne 15.750 15.750 15.750 46,896.37 738,617.84 738,617.84 738,617.84 M-078
Crushed stone aggregates 11.2 mm size cum 126.000 126.000 126.000 1,887.12 237,777.51 237,777.51 237,777.51 M-050
d) Overhead charges @ 8% on @ 10% on @ 12% on
80,198.69 100,248.36 120,298.03
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
108,268.23 110,273.19 112,278.16
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10500 Sqm = a+b+c+d+e 1,190,950.50 1,213,005.14 1,235,059.77
Rate per Sqm = (a+b+c+d+e)/10500 113.42 115.52 117.62
Say 113.00 116.00 118.00
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Note In case 2nd coat is also required to be provided, material
provided for the 2nd coat shall be as per Table 500-43.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.280 0.280 0.280 617.00 172.76 172.76 172.76 L-12
Mazdoor day 5.000 5.000 5.000 511.52 2,557.60 2,557.60 2,557.60 L-13
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Machinery
Mechanical broom (2.1m sweeping width) hour 1.042 1.042 1.042 500.40 521.25 521.25 521.25 P&M-052
Air compressor 250 cfm hour 1.042 1.042 1.042 614.25 639.84 639.84 639.84 P&M-029
Bitumen pressure distributor (Spraying width 4.5 m) P&M-053
hour 0.972 0.972 0.972 1,729.35 1,681.31 1,681.31 1,681.31
Pneumatic roller hour 2.000 2.000 2.000 2,562.00 5,124.00 5,124.00 5,124.00 P&M-022
c) Material
Paving grade bitumen of 80 - 100 penetration @ 1.05 kg
per sqm tonne 3.680 3.680 3.680 48,006.37 176,663.45 176,663.45 176,663.45 M-075
Geotextile including 10 per cent for overlaps sqm 3850.000 3850.000 3850.000 62.55 240,817.50 240,817.50 240,817.50 M-107
d) Overhead charges @ 8% on @ 10% on @ 12% on
34,344.73 42,930.92 51,517.10
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
46,365.39 47,224.01 48,082.63
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 3500 Sqm = a+b+c+d+e 510,019.30 519,464.10 528,908.90
Rate per Sqm = (a+b+c+d+e)/3500 145.72 148.42 151.12
Say 146.00 148.00 151.00
NOTE As bitumen overlay construction shall follow closely the
fabric placement on the same day, an output of 3500 sqm
only has been considered for the analysis which will
cover a length of 500 m, of 7 m wide carriagway. This can
be conveniently overlaid by a bitumenious course in a
day
Unit = cum
Taking output 205 Cum 450 tonnes
(i) 75 mm thickness
a) Labour
Mate day 0.480 0.480 0.480 617.00 296.16 296.16 296.16 L-12
Mazdoor day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.000 14,634.90 43,904.70 P&M-035
(ii) HMP 160 TPH hour 3.750 10,338.30 38,768.63 P&M-036
(iii) HMP 120 TPH hour 5.000 8,372.70 41,863.50 P&M-037
Electric generator
(i) 500 KVA hour 3.000 8,022.00 24,066.00 P&M-044
(ii) 400 KVA hour 3.750 6,470.10 24,262.88 P&M-045
(iii) 250 KVA hour 5.000 3,475.00 17,375.00 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.400 4,279.80 23,110.92 P&M-011
(ii) 2.1 Cum Capacity hour 8.027 2,640.75 21,197.37 P&M-012
(iii) 1 Cum Capacity hour 16.500 1,112.00 18,348.00 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 450 x L1 7.51 101,366.02 P&M-117
(ii) 14 cum capacity t.km 450 x L1 8.52 115,053.75 P&M-120
(iii) 10 cum capacity t.km 450 x L1 10.53 142,143.75 P&M-123
For loading & unloading time
(i) 18 cum capacity hour 6.000 2,883.30 17,299.80 P&M-014
(ii) 14 cum capacity hour 7.500 2,556.75 19,175.63 P&M-015
(iii) 10 cum capacity hour 10.000 2,274.30 22,743.00 P&M-016
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.000 9,233.70 27,701.10 P&M-058
(ii) Paver (240HP) hour 3.750 9,233.70 34,626.38 P&M-058
(iii) Paver (174HP) hour 5.000 2,362.50 11,812.50 P&M-059
Smooth steel wheeled tandem roller for static and P&M-019
vibratory passaes hour 11.831 11.831 11.831 417.00 4,933.61 4,933.61 4,933.61
Pnumetic Tyre roller hour 2.400 3.000 4.000 2,562.00 6,148.80 7,686.00 10,248.00 P&M-022
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 1.442 1,501.00 2,164.44 P&M-023
(ii) 12 KL capacity hour 1.923 1,327.00 2,551.82 P&M-024
(iii) 6 KL capacity hour 3.816 1,005.00 3,835.08 P&M-025
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
c) Material
Bitumen emulsion @ 45 litres per tonne tonne 20.250 20.250 20.250 46,556.37 942,766.51 942,766.51 942,766.51 M-074
Crushed stone aggregates 40 mm nominal size cum 297.000 297.000 297.000 1,887.12 560,475.56 560,475.56 560,475.56 M-054
Cost of water KL 6.000 6.000 6.000 16.00 96.00 96.00 96.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
140,859.11 177,829.96 214,001.52
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
190,159.80 195,612.95 199,734.75
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 205 cum = a+b+c+d+e 2,091,757.83 2,151,742.49 2,197,082.23
Rate per cum = (a+b+c+d+e)/205 10,203.70 10,496.30 10,717.47
Say 10,204.00 10,496.00 10,717.00
Note (Case I to III)
1. These mixes are considered suitable for minor repair
work and temporary road surface improvement.
Unit = cum
Taking output = 191 cum 450.76 tonnes
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.005 14,634.90 43,978.85 P&M-035
(ii) HMP 160 TPH hour 3.756 10,338.30 38,834.10 P&M-036
(iii) HMP 120 TPH hour 5.008 8,372.70 41,934.20 P&M-037
Mechanical broom (2.1m sweeping width) hour 1.137 1.137 1.137 500.40 568.91 568.91 568.91 P&M-052
Air compressor 250 cfm hour 1.137 1.137 1.137 614.25 698.34 698.34 698.34 P&M-029
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.005 9,233.70 27,747.88 P&M-058
(ii) Paver (240HP) hour 3.756 9,233.70 34,684.86 P&M-058
(iii) Paver (174HP) hour 5.008 2,362.50 11,832.45 P&M-059
Electric generator
(i) 500 KVA hour 3.005 8,022.00 24,106.64 P&M-044
(ii) 400 KVA hour 3.756 6,470.10 24,303.85 P&M-045
(iii) 250 KVA hour 5.008 3,475.00 17,404.34 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 5.078 4,279.80 21,731.00 P&M-011
(ii) 2.1 Cum Capacity hour 7.506 2,640.75 19,821.41 P&M-012
(iii) 1 Cum Capacity hour 15.694 1,112.00 17,452.08 P&M-013
Tipper
For Transportation Mix
(i) 18 cum capacity t.km 450.76 x L1 7.51 101,537.21 P&M-117
(ii) 14 cum capacity t.km 450.76 x L1 8.52 115,248.06 P&M-120
(iii) 10 cum capacity t.km 450.76 x L1 10.53 142,383.82 P&M-123
Loading & unloading time for Mix
(i) 18 cum capacity hour 6.010 2,883.30 17,329.02 P&M-014
(ii) 14 cum capacity hour 7.513 2,556.75 19,208.01 P&M-015
(iii) 10 cum capacity hour 10.017 2,274.30 22,781.41 P&M-016
B
Bituminous Concrete Grading 2 Using Waste Plastic
Providing and laying bituminous concrete with higher
capacity batch type hot mix plant using crushed
aggregates of specified grading, premixed with
bituminous binder @ 5.4 per cent of mix and filler,
transporting the hot mix to work site, laying with a
hydrostatic paver finisher with sensor control to the
required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the
desired compaction as per MORTH specification clause
No. 507 complete in all respects
Unit = cum
Taking output = 191 cum 450.76 tonnes
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
b) Machinery
Hot Mix Plant
(i) HMP 200 TPH hour 3.005 14,634.90 43,978.85 P&M-035
(ii) HMP 160 TPH hour 3.756 10,338.30 38,834.10 P&M-036
(iii) HMP 120 TPH hour 5.008 8,372.70 41,934.20 P&M-037
Mechanical broom (2.1m sweeping width) hour 1.624 1.624 1.624 500.40 812.72 812.72 812.72 P&M-052
Air compressor 250 cfm hour 1.624 1.624 1.624 614.25 997.63 997.63 997.63 P&M-029
Paver finisher hydrostatic with sensor control compatable
with the hot mix plant
(i) Paver (240HP) hour 3.005 9,233.70 27,747.88 P&M-058
(ii) Paver (240HP) hour 3.756 9,233.70 34,684.86 P&M-058
(iii) Paver (174HP) hour 5.008 2,362.50 11,832.45 P&M-059
Electric generator
(i) 500 KVA hour 3.005 8,022.00 24,106.64 P&M-044
(ii) 400 KVA hour 3.756 6,470.10 24,303.85 P&M-045
(iii) 250 KVA hour 5.008 3,475.00 17,404.34 P&M-046
Front end loader for feeding the plant
(i) 3.1 Cum Capacity hour 4.993 4,279.80 21,370.87 P&M-011
(ii) 2.1 Cum Capacity hour 7.362 2,640.75 19,441.48 P&M-012
(iii) 1 Cum Capacity hour 15.520 1,112.00 17,258.37 P&M-013
Tipper
For Transportation
(i) 18 cum capacity t.km 450.76 x L1 7.51 101,537.21 P&M-117
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
(ii) 14 cum capacity t.km 450.76 x L1 8.52 115,248.06 P&M-120
(iii) 10 cum capacity t.km 450.76 x L1 10.53 142,383.82 P&M-123
Tipper for loading & unloading time
(i) 18 cum capacity hour 6.010 2,883.30 17,329.02 P&M-014
(ii) 14 cum capacity hour 7.513 2,556.75 19,208.01 P&M-015
(iii) 10 cum capacity hour 10.017 2,274.30 22,781.41 P&M-016
Smooth steel wheeled tandem roller for static and P&M-019
vibratory passaes hour 16.902 16.902 16.902 417.00 7,048.02 7,048.02 7,048.02
Pneumatic Tyre roller hour 2.404 3.005 4.007 2,562.00 6,159.18 7,698.98 10,265.31 P&M-022
Shredding Machine hour 1.298 1.298 1.298 416.00 540.05 540.05 540.05 P&M-79001
c) Material
i) Bitumen@ 4.97 per cent of mix tonne 22.394 22.394 22.394 46,556.37 1,042,572.05 1,042,572.05 1,042,572.05 M-074
ii) Plastic @ 8 per cent of Bitumen tonne 1.947 1.947 1.947 5,000.00 9,736.42 9,736.42 9,736.42
iii) Aggregate
Total weight of mix = 450.76 tonnes
Weight of bitumen = 22.39 tonnes
Weight of Plastic = 1.95 tonnes
Weight of aggregate = 426.42 tonnes
Taking density of aggregate = 1.5 ton/cum
Grading - II-13 mm (Nominal Size)
13.2 - 10 mm 21 per cent cum 59.699 99.498 99.498 1,887.12 112,658.71 187,764.52 187,764.52 M-043
10 - 5 mm 17 per cent cum 48.327 65.384 65.384 1,887.12 91,199.91 123,388.11 123,388.11 M-039
5 mm and below 60 per cent cum 170.568 113.712 113.712 1,887.12 321,882.03 214,588.02 214,588.02 M-029
Filler @ 2 per cent of weight of aggregates. tonnes 8.528 8.528 8.528 3,753.00 32,007.01 32,007.01 32,007.01 M-081
* Any one of the alternative may be adopted as per
approved design
* Grading - I-19 mm (Nominal Size)
d) Overhead charges @ 8% on @ 10% on @ 12% on
149,428.28 188,504.31 226,738.04
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
201,728.17 207,354.74 211,622.17
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 191 cum = a+b+c+d+e 2,219,009.91 2,280,902.19 2,327,843.90
Rate per cum = (a+b+c+d+e)/191 11,617.85 11,941.90 12,187.66
Say 11,618.00 11,942.00 12,188.00
Note *1.Quantity of Bitumen & Plastic have been taken for
analysis purpose. The actual quantity will depend upon
job mix formula.
2. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
Unit = cum
Taking output 450 cum
990 tonne
a) Labour
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Mazdoor day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
b) Machinery
Paver with electronic sensor
(i) Paver Finisher Concrete with 300 HP Motor hour 2.045 28,108.50 57,494.66 P&M-060
(ii) Paver Finisher Concrete with 241 HP Motor 3.000 18,201.75 54,605.25 P&M-061
(iii) Paver Finisher Concrete with 118 HP Motor 5.625 4,517.10 25,408.69 P&M-062
Vibratory roller 8-10 t capacity hour 2.045 3.000 5.625 2,562.00 5,240.45 7,686.00 14,411.25 P&M-022
Tipper
For Transportation
(i) 18 cum capacity t.km 990 x L1 6.18 183,501.45 P&M-116
(ii) 14 cum capacity t.km 990 x L1 7.01 208,280.16 P&M-119
(iii) 10 cum capacity t.km 990 x L1 8.66 257,320.80 P&M-122
For loading & unloading Time
(i) 18 cum capacity hour 4.545 2,883.30 13,104.60 P&M-014
(ii) 14 cum capacity hour 5.500 2,556.75 14,062.13 P&M-015
(iii) 10 cum capacity hour 10.625 2,274.30 24,164.44 P&M-016
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 1.509xL1+7.
1,501.00 78,825.02 P&M-023
245
(ii) 12 KL capacity hour 2.013xL1+9.6
1,327.00 92,956.35 P&M-024
6
(iii) 6 KL capacity hour 4.025xL1+1
1,005.00 140,770.35 P&M-025
9.32
c) Material
Concrete from sub-analysis of concrete Rate
(i) Using Batching Plant 240 Cum Capacity Sub-
Analysis of
cum 450.000 3,500.00 1,575,000.00
Concrete -
20.18 A
(ii) Using Batching Plant 240 Cum Capacity Sub-
Analysis of
cum 450.000 3,500.00 1,575,000.00
Concrete -
20.18 A
(iii) Using Batching Plant 120 Cum Capacity Sub-
Analysis of
cum 450.000 3,530.00 1,588,500.00
Concrete -
20.18 C
Cost of water (Curing) KL 217.350 217.350 217.350 16.00 3,477.60 3,477.60 3,477.60 M-191
Unit = cum
Taking output = 900 Cum 2070 Tonne
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.893 0.893 0.893 500.40 446.79 446.79 446.79 P&M-052
Air compressor 250 cfm hour 0.893 0.893 0.893 614.25 548.44 548.44 548.44 P&M-029
Paver with electronic sensor
(i) Paver Finisher Concrete with 300 HP Motor hour 4.091 28,108.50 114,991.87 P&M-060
(ii) Paver Finisher Concrete with 241 HP Motor 6.000 18,201.75 109,210.50 P&M-061
(iii) Paver Finisher Concrete with 118 HP Motor 11.250 4,517.10 50,817.38 P&M-062
Transit truck agitator
For Transportation Transit truck agitator 6 cum capacity t.km 2070 x L1 2070 x L1 2070 x L1 13.41 832,812.75 832,812.75 832,812.75 P&M-128
For unloding time hour 4.091 6.000 11.250 2,413.95 9,875.47 14,483.70 27,156.94 P&M-067
Concrete joint cutting machine hour 101.587 101.587 101.587 1,251.00 127,085.71 127,085.71 127,085.71 P&M-098
Texturing machine
Texturing machine (TCM) - upto 18 m hour 4.091 4,830.00 19,759.53 P&M-063
Texturing machine (TCM) - upto 18 m 6.000 4,830.00 28,980.00 P&M-063
Texturing machine (TCM) - upto 9 m 11.250 3,807.30 42,832.13 P&M-064
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 114.180 1,501.00 171,384.18 P&M-023
(ii) 12 KL capacity hour 152.250 1,327.00 202,035.75 P&M-024
(iii) 6 KL capacity hour 304.500 1,005.00 306,022.50 P&M-025
c) Material
Concrete from sub-analysis of concrete Rate
Sub-
Analysis of
(i) Using Batching Plant 240 Cum Capacity cum 900.000 5,083.00 4,574,700.00
Concrete -
20.19 A
Sub-
Analysis of
(ii) Using Batching Plant 240 Cum Capacity cum 900.000 5,083.00 4,574,700.00
Concrete -
20.19 A
Sub-
Analysis of
(iii) Using Batching Plant 120 Cum Capacity cum 900.000 5,126.00 4,613,400.00
Concrete -
20.19 C
36 mm mild steel dowel bars of grade S 240 tonne 9.170 9.170 9.170 63,806.54 585,106.01 585,106.01 585,106.01 M-125
12 mm deformed steel tie bars of grade S 415 tonne 1.051 1.051 1.051 46,496.54 48,867.87 48,867.87 48,867.87 M-083
Separation Membrane of impermeable plastic sheeting 125 sqm
micron thick (including 5% Overlap) 3150.000 3150.000 3150.000 16.68 52,542.00 52,542.00 52,542.00 M-165
Joint sealant kg 609.524 609.524 609.524 37.53 22,875.43 22,875.43 22,875.43 M-119
Sealant primer kg 100.003 100.003 100.003 37.53 3,753.11 3,753.11 3,753.11 M-119
Plastic sheath,1.25 mm thick for dowel bars sqm 155.735 155.735 155.735 41.70 6,494.15 6,494.15 6,494.15 M-137
Curing compound Liter 600.000 600.000 600.000 41.70 25,020.00 25,020.00 25,020.00 M-091
Cost of water (Curing) KL 472.500 472.500 472.500 16.00 7,560.00 7,560.00 7,560.00 M-191
Add 1 per cent of material for cost of miscellaneous materials
like tarpauline, Hessian cloth, metal cap, cotton / compressible
sponge and cradle for dowel bars, work bridges for men to
approach concrete surface without walking over it, cutting
53,269.19 53,269.19 53,656.19
blades and bites, minor equipments like scabbling machine,
threads, ropes, guide wires and any other unforeseen items.
Unit = cum
Taking output 450 cum
990 tonne
a) Labour
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Mazdoor day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
b) Machinery
Paver with electronic sensor
(i) Paver Finisher Concrete with 300 HP Motor hour 2.045 28,108.50 57,494.66 P&M-060
(ii) Paver Finisher Concrete with 241 HP Motor 3.000 18,201.75 54,605.25 P&M-061
(iii) Paver Finisher Concrete with 118 HP Motor 5.625 4,517.10 25,408.69 P&M-062
Vibratory roller 8-10 t capacity hour 2.045 3.000 5.625 903.50 1,848.07 2,710.50 5,082.19 P&M-018
Tipper
For Transportation
(i) 18 cum capacity t.km 990 x L1 7.51 223,005.23 P&M-117
(ii) 14 cum capacity t.km 990 x L1 8.52 253,118.25 P&M-120
(iii) 10 cum capacity t.km 990 x L1 10.53 312,716.25 P&M-123
For loading & unloading Time
(i) 18 cum capacity hour 4.545 2,883.30 13,105.91 P&M-014
(ii) 14 cum capacity hour 5.500 2,556.75 14,062.13 P&M-015
(iii) 10 cum capacity hour 10.625 2,274.30 24,164.44 P&M-016
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 52.515 1,501.00 78,825.02 P&M-023
(ii) 12 KL capacity hour 70.050 1,327.00 92,956.35 P&M-024
(iii) 6 KL capacity hour 140.070 1,005.00 140,770.35 P&M-025
c) Material
Concrete from sub-analysis of concrete Rate
Sub-
Analysis of
(i) Using Batching Plant 240 Cum Capacity cum 450.000 3,399.00 1,529,550.00
Concrete -
20.18 B
Sub-
Analysis of
(ii) Using Batching Plant 240 Cum Capacity cum 450.000 3,399.00 1,529,550.00
Concrete -
20.18 B
Sub-
Analysis of
(iii) Using Batching Plant 120 Cum Capacity cum 450.000 3,428.00 1,542,600.00
Concrete -
20.18 D
Cost of water (Curing) KL 217.350 217.350 217.350 16.00 3,477.60 3,477.60 3,477.60 M-191
Unit = cum
Taking output = 900 Cum 2070 Tonne
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.893 0.893 0.893 500.40 446.79 446.79 446.79 P&M-052
Air compressor 250 cfm hour 0.893 0.893 0.893 614.25 548.44 548.44 548.44 P&M-029
Paver with electronic sensor
(i) Paver Finisher Concrete with 300 HP Motor hour 4.091 28,108.50 114,989.32 P&M-060
(ii) Paver Finisher Concrete with 241 HP Motor 6.000 18,201.75 109,210.50 P&M-061
(iii) Paver Finisher Concrete with 118 HP Motor 11.250 4,517.10 50,817.38 P&M-062
Transit truck agitator
For Transportation Transit truck agitator 6 cum capacity t.km 2070 x L1 2070 x L1 2070 x L1 13.41 832,812.75 832,812.75 832,812.75 P&M-128
For Unloding time hour 4.091 6.000 11.250 2,413.95 9,875.25 14,483.70 27,156.94 P&M-067
Concrete joint cutting machine . hour 101.587 101.587 101.587 511.35 51,946.67 51,946.67 51,946.67 P&M-075
Texturing machine . hour 4.091 6.000 11.250 4,830.00 19,759.09 28,980.00 54,337.50 P&M-063
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 114.180 1,501.00 171,384.18 P&M-023
(ii) 12 KL capacity hour 152.250 1,327.00 202,035.75 P&M-024
(iii) 6 KL capacity hour 304.500 1,005.00 306,022.50 P&M-025
c) Material
Concrete from sub-analysis of concrete Rate
Sub-
Analysis of
(i) Using Batching Plant 240 Cum Capacity cum 900.000 4,664.00 4,197,600.00
Concrete -
20.19 B
Sub-
Analysis of
(ii) Using Batching Plant 240 Cum Capacity cum 900.000 4,664.00 4,197,600.00
Concrete -
20.19 B
(iii) Using Batching Plant 120 Cum Capacity cum Sub-
Analysis of
900.000 4,650.00 4,185,000.00
Concrete -
20.19 D
36 mm mild steel dowel bars of grade S 240 tonne 9.170 9.170 9.170 63,806.54 585,106.01 585,106.01 585,106.01 M-125
12 mm deformed steel tie bars of grade S 415 tonne 1.051 1.051 1.051 46,496.54 48,867.87 48,867.87 48,867.87 M-083
Separation Membrane of impermeable plastic sheeting 125 sqm
micron thick (including 5% Overlap) 3150.000 3150.000 3150.000 16.68 52,542.00 52,542.00 52,542.00 M-165
Joint sealant kg 609.524 609.524 609.524 37.53 22,875.43 22,875.43 22,875.43 M-119
Sealant primer kg 100.003 100.003 100.003 208.50 20,850.60 20,850.60 20,850.60 M-097
Plastic sheath,1.25 mm thick for dowel bars sqm 155.735 155.735 155.735 41.70 6,494.15 6,494.15 6,494.15 M-137
Curing compound Liter 600.000 600.000 600.000 41.70 25,020.00 25,020.00 25,020.00 M-091
Cost of water (Curing) KL 472.500 472.500 472.500 16.00 7,560.00 7,560.00 7,560.00 M-191
Add 1 per cent of material for cost of miscellaneous materials
like tarpauline, Hessian cloth, metal cap, cotton / compressible
sponge and cradle for dowel bars, work bridges for men to
approach concrete surface without walking over it, cutting
61,748.48 62,135.50 62,845.74
blades and bites, minor equipments like scabbling machine,
threads, ropes, guide wires and any other unforeseen items.
Unit = cum
Taking output = 900 Cum 2070 Tonne
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.893 0.893 0.893 500.40 446.79 446.79 446.79 P&M-052
Air compressor 250 cfm hour 0.893 0.893 0.893 614.25 548.44 548.44 548.44 P&M-029
Paver with electronic sensor
(i) Paver Finisher Concrete with 300 HP Motor hour 4.091 28,108.50 114,989.32 P&M-060
(ii) Paver Finisher Concrete with 241 HP Motor 6.000 18,201.75 109,210.50 P&M-061
(iii) Paver Finisher Concrete with 118 HP Motor 11.250 4,517.10 50,817.38 P&M-062
Transit truck agitator
For Transportation Transit truck agitator 6 cum capacity t.km 2070 x L1 2070 x L1 2070 x L1 13.41 832,812.75 832,812.75 832,812.75 P&M-128
For Unloding time hour 4.091 6.000 11.250 2,413.95 9,875.25 14,483.70 27,156.94 P&M-067
Concrete joint cutting machine . hour 320.000 320.000 320.000 511.35 163,632.00 163,632.00 163,632.00 P&M-075
Texturing machine .
Texturing machine (TCm)- upto 18m hour 4.091 4,830.00 19,759.09 P&M-063
Texturing machine (TCm)- upto 18m hour 6.000 4,830.00 28,980.00 P&M-063
Texturing machine (TCm)- upto 9m hour 11.250 3,807.30 42,832.13 P&M-064
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 57.105 1,501.00 85,714.61 P&M-023
(ii) 12 KL capacity hour 76.140 1,327.00 101,037.78 P&M-024
(iii) 6 KL capacity hour 152.250 1,005.00 153,011.25 P&M-025
c) Material
Concrete from sub-analysis of concrete Rate
Sub-
Analysis of
(i) Using Batching Plant 240 Cum Capacity cum 900.000 5,083.00 4,574,700.00
Concrete -
20.19 A
Sub-
Analysis of
(ii) Using Batching Plant 240 Cum Capacity cum 900.000 5,083.00 4,574,700.00
Concrete -
20.19 A
(iii) Using Batching Plant 120 Cum Capacity cum Sub-
Analysis of
900.000 5,126.00 4,613,400.00
Concrete -
20.19 C
Joint sealant kg 609.524 609.524 609.524 37.53 22,875.43 22,875.43 22,875.43 M-119
Sealant primer kg 100.003 100.003 100.003 208.50 20,850.60 20,850.60 20,850.60 M-097
Fiber Reinforcement @9.25 kg Per Cum tonne 8.325 8.325 8.325 46,496.54 387,083.73 387,083.73 387,083.73 M-225
Curing compound Liter 600.000 600.000 600.000 41.70 25,020.00 25,020.00 25,020.00 M-091
Cost of water (Curing) KL 472.500 472.500 472.500 16.00 7,560.00 7,560.00 7,560.00 M-191
Add 1 per cent of material for cost of miscellaneous materials
like tarpauline, Hessian cloth, metal cap, cotton / compressible
sponge and cradle for dowel bars, work bridges for men to
approach concrete surface without walking over it, cutting
62,720.37 62,954.11 63,542.17
blades and bites, minor equipments like scabbling machine,
threads, ropes, guide wires and any other unforeseen items.
Unit = cum
Taking output = 900 Cum 2070 Tonne
a) Labour
Mate day 0.440 0.440 0.440 617.00 271.48 271.48 271.48 L-12
Mazdoor skilled day 5.000 5.000 5.000 565.73 2,828.65 2,828.65 2,828.65 L-15
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.893 0.893 0.893 500.40 446.79 446.79 446.79 P&M-052
Air compressor 250 cfm hour 0.893 0.893 0.893 614.25 548.44 548.44 548.44 P&M-029
Paver with electronic sensor
(i) Paver Finisher Concrete with 300 HP Motor hour 4.091 28,108.50 114,989.32 P&M-060
(ii) Paver Finisher Concrete with 241 HP Motor 6.000 18,201.75 109,210.50 P&M-061
(iii) Paver Finisher Concrete with 118 HP Motor 11.250 4,517.10 50,817.38 P&M-062
Transit truck agitator
For Transportation Transit truck agitator 6 cum capacity t.km 2070 x L1 2070 x L1 2070 x L1 13.41 832,812.75 832,812.75 832,812.75 P&M-128
For Unloding time hour 4.091 6.000 11.250 2,413.95 9,875.25 14,483.70 27,156.94 P&M-067
Concrete joint cutting machine . hour 320.000 320.000 320.000 511.35 163,632.00 163,632.00 163,632.00 P&M-075
Texturing machine .
Texturing machine (TCm)- upto 18m hour 4.091 4,830.00 19,759.09 P&M-063
Texturing machine (TCm)- upto 18m hour 6.000 4,830.00 28,980.00 P&M-063
Texturing machine (TCm)- upto 9m hour 11.250 3,807.30 42,832.13 P&M-064
Water tanker ( speed @ 20km/hr and return speed @ 30
km/hr and spreading speed @ 2.5 km/hr )
(i) 16 KL capacity hour 57.105 1,501.00 85,714.61 P&M-023
(ii) 12 KL capacity hour 76.140 1,327.00 101,037.78 P&M-024
(iii) 6 KL capacity hour 152.250 1,005.00 153,011.25 P&M-025
c) Material
Concrete from sub-analysis of concrete Rate
Sub-
Analysis of
(i) Using Batching Plant 240 Cum Capacity cum 900.000 4,664.00 4,197,600.00
Concrete -
20.19 B
Sub-
Analysis of
(ii) Using Batching Plant 240 Cum Capacity cum 900.000 4,664.00 4,197,600.00
Concrete -
20.19 B
(iii) Using Batching Plant 120 Cum Capacity cum Sub-
Analysis of
900.000 4,650.00 4,185,000.00
Concrete -
20.19 D
Joint sealant kg 609.524 609.524 609.524 37.53 22,875.43 22,875.43 22,875.43 M-119
Sealant primer kg 100.003 100.003 100.003 208.50 20,850.60 20,850.60 20,850.60 M-097
Fiber Reinforcement @9.25 kg Per Cum tonne 8.325 8.325 8.325 46,496.54 387,083.73 387,083.73 387,083.73 M-225
Curing compound Liter 600.000 600.000 600.000 41.70 25,020.00 25,020.00 25,020.00 M-091
Cost of water (Curing) KL 472.500 472.500 472.500 16.00 7,560.00 7,560.00 7,560.00 M-191
Add 1 per cent of material for cost of miscellaneous materials
like tarpauline, Hessian cloth, metal cap, cotton / compressible
sponge and cradle for dowel bars, work bridges for men to
approach concrete surface without walking over it, cutting
58,949.37 59,183.11 59,258.17
blades and bites, minor equipments like scabbling machine,
threads, ropes, guide wires and any other unforeseen items.
Unit = sqm
Taking output = 2800 sqm
a) Labour
Mate day 0.800 0.800 0.800 617.00 493.60 493.60 493.60 L-12
Mazdoor day 20.000 20.000 20.000 511.52 10,230.40 10,230.40 10,230.40 L-13
b) Machinery
Mechanical broom (2.1m sweeping width) hour 0.833 2.240 2.240 500.40 416.83 1,120.90 1,120.90 P&M-052
Pneumatic roller 14 tonnes 2000 sqm per hour hour 1.400 1.400 1.400 2,562.00 3,586.80 3,586.80 3,586.80 P&M-022
Bitumen pressure distributor (Spraying width 4.5 m)
hour 0.778 0.778 0.778 1,729.35 1,345.05 1,345.05 1,345.05 P&M-053
c) Material
Paving Fabric sqm 2940.0 2940.0 2940.0 80.73 237,359.43 237,359.43 237,359.43 M-132
Paving Bitumen 80-100 tonne 2.800 2.800 2.800 48,006.37 134,417.84 134,417.84 134,417.84 M-075
c) Overhead charges @ 8% on @ 10% on @ 12% on
31,028.00 38,855.40 46,626.48
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
41,887.79 42,740.94 43,518.05
(a+b+c) (a+b+c) (a+b+c)
Cost for 2800 sqm = a+b+c+d+e 460,765.74 470,150.36 478,698.55
Rate per sqm =(a+b+c+d+e)/2800 164.56 167.91 170.96
Say 165.00 168.00 171.00
7.3 703 Laying Boulder Apron in Crates of Synthetic Geogrids
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Unit = cum
Taking output = 3 cum
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor skilled day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
Mazdoor day 1.500 1.500 1.500 511.52 767.28 767.28 767.28 L-13
b) Material
Geo grids sqm 21.000 21.000 21.000 236.00 4,956.00 4,956.00 4,956.00 M-104
Connectors/ Staples each 50.000 50.000 50.000 6.95 347.50 347.50 347.50 M-086
Polymer braids metre 20.000 20.000 20.000 205.00 4,100.00 4,100.00 4,100.00 M-139
Stones with minimum size of 200 mm cum 3.450 3.450 3.450 1,994.63 6,881.48 6,881.48 6,881.48 M-003
Stones spall for filling voids cum 0.450 0.450 0.450 1,679.81 755.92 755.92 755.92 M-008
c) Overhead charges @ 8% on @ 10% on @ 12% on
1,451.23 1,814.04 2,176.85
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,959.16 1,995.44 2,031.72
(a+b+c) (a+b+c) (a+b+c)
Cost for 3 cum = a+b+c+d 21,550.79 21,949.88 22,348.97
Rate per cum = (a+b+c+d)/ 3 7,183.60 7,316.63 7,449.66
Say 7,184.00 7,317.00 7,450.00
7.4 3100 Reinforced Earth Structures
Reinforced earth Structures have four main
components as under:
a) Excavation for foundation, foundation concrete
and cement concrete grooved seating in the
foundation for facing elements (facia material).
or
2.Copper Strips metre 472.500 472.500 472.500 1.00 472.50 472.50 472.50 M-154
Add 5 per cent of the cost of reinforcing elements
strip towards accessories like tie-strips, nuts and bolts
and loops/lugs for joining reinforcing elements with 47.25 47.25 47.25
the facia pannels, overlaps heat bonding or extension
or
3.Aluminium Strips metre 472.500 472.500 472.500 1.00 472.50 472.50 472.50 M-158
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Add 5 per cent of the cost of reinforcing elements
strip towards accessories like tie-strips, nuts and bolts
and loops/lugs for joining reinforcing elements with 47.25 47.25 47.25
the facia pannels, overlaps heat bonding or extension
or
4.Stainless steel strips metre 472.500 472.500 472.500 1.00 472.50 472.50 472.50 M-157
Add 5 per cent of the cost of reinforcing elements
strip towards accessories like tie-strips, nuts and bolts
and loops/lugs for joining reinforcing elements with 47.25 47.25 47.25
the facia pannels, overlaps heat bonding or extension
or
5.Glass reinforced polymer/fibre reinforced
polymer/polymeric strips metre 472.500 472.500 472.500 1.00 495.00 495.00 495.00 M-156
Add 5 per cent of the cost of reinforcing elements
strip towards accessories like tie-strips, nuts and bolts
and loops/lugs for joining reinforcing elements with 49.50 49.50 49.50
the facia pannels, overlaps heat bonding or extension
Unit = sqm
Taking output 300 sqm
a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Mazdoor skilled day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Material
Synthetic Geogrids as per clause 3100 and approved
design and specifications including 5% wastage. sqm 315.000 315.000 315.000 182.60 57,519.00 57,519.00 57,519.00 M-183
Unit = Sqm
Taking output 300 Sqm
a) Labour
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Mazdoor (Skilled ) day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Material
Bi-Axial Extruded GeoGrids of Minimum Tensile
Strength 15 kN/m in the longitudinal and transverse sqm 300.00 300.00 300.00 1.00 300.00 300.00 300.00 M-286
direction
Add 10 % of the cost of reinforcing elements
(synthetic geogrids) for wastage and accessories like
tie-strips, nuts and bolts and loops/lugs for joining
reinforcing elements with the facia pannels, overlaps
and other protective elements for synthetic geogrids 30.00 30.00 30.00
and all other activities required to complete the item in
all respect including taxes and transportation.
7.5 703 (ii) Supplying & laying of bi-axial extruded high modulus
polypropylene geogrid conforming to MORT&H
specification for base/sub-base reinforcement having
minimum tensile strength 20kN/m in the longitudinal
and transverse direction, with 7kN/m and 14kN/m
tensile strength at 2% and 5% strain respectively in
the longitudinal and transverse direction, junction
efficiency not less than 95% and with 38mm X 38mm
mesh opening.
Unit = Sqm
Taking output 300 Sqm
a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Mazdoor (Skilled ) day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Material
Bi-Axial Extruded GeoGrids of Minimum Tensile
Strength 20 kN/m in the longitudinal and transverse sqm 300.00 300.00 300.00 1.00 300.00 300.00 300.00 M-287
direction
Add 10 % of the cost of reinforcing elements
(synthetic geogrids) for wastage and accessories like
tie-strips, nuts and bolts and loops/lugs for joining
reinforcing elements with the facia pannels, overlaps
and other protective elements for synthetic geogrids 30.00 30.00 30.00
and all other activities required to complete the item in
all respect including taxes and transportation.
7.5 703 (iii) Supplying & laying of bi-axial extruded high modulus
polypropylene geogrid conforming to MORT&H
specification for base/sub-base reinforcement having
minimum tensile strength 30kN/m in the longitudinal
and transverse direction, with 10.5kN/m and 21kN/m
tensile strength at 2% and 5% strain respectively in
the longitudinal and transverse direction, junction
efficiency not less than 95% and with 38mm X 38mm
mesh opening.
7.5 703 (iv) Supplying & laying of bi-axial extruded high modulus
polypropylene geogrid coforming to MORT&H
specification for base/sub-base reinforcement having
minimum tensile strength 40kN/m in the longitudinal
and transverse direction, with 14kN/m and 28kN/m
tensile strength at 2% and 5% strain respectively in
the longitudinal and transverse direction, junction
efficiency not less than 95% and with 38mm X 38mm
mesh opening.
Unit = Sqm
Taking output 300 Sqm
a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Mazdoor (Skilled ) day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Material
Bi-Axial Extruded GeoGrids of Minimum Tensile
Strength 40 kN/m in the longitudinal and transverse sqm 300.00 300.00 300.00 1.00 300.00 300.00 300.00 M-289
direction
Add 10 % of the cost of reinforcing elements
(synthetic geogrids) for wastage and accessories like
tie-strips, nuts and bolts and loops/lugs for joining
reinforcing elements with the facia pannels, overlaps
and other protective elements for synthetic geogrids 30.00 30.00 30.00
and all other activities required to complete the item in
all respect including taxes and transportation.
Unit = Sqm
Taking output 300 Sqm
a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Mazdoor (Skilled ) day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Material
Geosynthetic Drainage Composite (tensile strength of
18 kN/ m) sqm 300.00 300.00 300.00 175.00 52,500.00 52,500.00 52,500.00 M-290
Add 10 per cent of the cost of synthetic Composits for
wastage and accessories for joining sheets with the
facia pannels, overlaps and other protective elements
for synthetic Composits and other miscelleneus
5,250.00 5,250.00 5,250.00
activities required to complete the item in all respect
including transpotarion & takes.
Unit = Sqm
Taking output 300 Sqm
a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Mazdoor (Skilled ) day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Material
Geosynthetic Drainage Composite (tensile strength of
13.5 kN/ m) sqm 300.00 300.00 300.00 150.00 45,000.00 45,000.00 45,000.00 M-291
Add 10 per cent of the cost of synthetic Composits for
wastage and accessories for joining sheets with the
facia pannels, overlaps and other protective elements
for synthetic Composits and other miscelleneus
4,500.00 4,500.00 4,500.00
activities required to complete the item in all respect
including transpotarion & takes.
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mazdoor for filling, watering, ramming etc. day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
Mazdoor (Skilled) day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
b) Material
Filter media of stone aggregate conforming to clause cum M-011
2504.2.2. of MoRTH specifications. 12.000 12.000 12.000 1,215.07 14,580.87 14,580.87 14,580.87
c) Machinery
Water Tanker of 6 KL capacity hour 0.060 0.060 0.060 1,005.00 60.30 60.30 60.30 P&M-025
d) Overhead charges @ 8% on @ 10% on @ 12% on
1,518.80 1,898.50 2,278.20
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
2,050.38 2,088.35 2,126.32
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Unit = Sqm
Taking output 300 Sqm
a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Mazdoor (Skilled ) day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Material
Geosynthetic Drainage Composite (tensile strength of sqm 300.00 300.00 300.00 M-290
18 kN/ m) 175.00 52,500.00 52,500.00 52,500.00
Add 10 per cent of the cost of synthetic Composits for
wastage and accessories for joining sheets with the
facia pannels, overlaps and other protective elements
for synthetic Composits and other miscelleneus
5,250.00 5,250.00 5,250.00
activities required to complete the item in all respect
including transpotarion & takes.
Unit = Sqm
Taking output 300 Sqm
a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Mazdoor (Skilled ) day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Material
Geosynthetic Drainage Composite (tensile strength of sqm 300.00 300.00 300.00 M-290
13.5 kN/ m) 150.00 45,000.00 45,000.00 45,000.00
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Add 10 per cent of the cost of synthetic Composits for
wastage and accessories for joining sheets with the
facia pannels, overlaps and other protective elements
for synthetic Composits and other miscelleneus
4,500.00 4,500.00 4,500.00
activities required to complete the item in all respect
including transpotarion & takes.
Unit = Sqm
Taking output 100 Sqm
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Mazdoor for preparation of ground and laying of the day 1.000 1.000 1.000 L-13
Geocell 511.52 511.52 511.52 511.52
Mazdoor (Skilled ) day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
b) Material
Geocell sqm 100.00 100.00 100.00 80.00 8,000.00 8,000.00 8,000.00 M-290
Add 10 per cent of the cost of Geocell for wastage,
overlaps and accessories for anchoring with the
ground, other protective elements for Geocell and
other miscelleneus activities required to complete the 800.00 800.00 800.00
item in all respect including transpotarion & takes.
Unit = Sqm
Taking output 100 Sqm
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Mazdoor for preparation of ground and laying of the day 1.000 1.000 1.000 L-13
Geocell 511.52 511.52 511.52 511.52
Mazdoor (Skilled ) day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
b) Material
Geosynthetics mat sqm 100.00 100.00 100.00 50.00 5,000.00 5,000.00 5,000.00 M-290
Add 10 per cent of the cost of Geosynthetics mat for
wastage, overlaps and accessories for anchoring with
the ground, other protective elements for
Geosynthetics mat and other miscelleneus activities
500.00 500.00 500.00
required to complete the item in all respect including
transpotarion & takes.
Unit = Sqm
Taking output 100 Sqm
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Mazdoor for preparation of ground and laying of the day 1.000 1.000 1.000 L-13
Geocell 511.52 511.52 511.52 511.52
Mazdoor (Skilled ) day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
b) Material
Natural geotextile sqm 100.00 100.00 100.00 25.00 2,500.00 2,500.00 2,500.00 M-290
Sub-Analysis
Concrete from sub-analysis of concrete Rate cum 11.610 11.610 11.610 4,176.00 48,483.36 48,483.36 48,483.36 of Concrete -
20.21
Cost of water KL 1.602 1.602 1.602 16.00 25.63 25.63 25.63 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
5,798.52 7,256.24 8,739.74
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
7,828.00 7,981.87 8,157.09
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Sub-Analysis
Concrete from sub-analysis of concrete Rate cum 12.600 12.600 12.600 4,518.00 56,926.80 56,926.80 56,926.80 of Concrete -
20.2
Cost of water KL 6.086 6.086 6.086 16.00 97.37 97.37 97.37 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
7,408.03 9,291.76 11,286.79
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
10,000.84 10,220.94 10,534.33
(a+b+c+d) (a+b+c+d) (a+b+c+d)
0.025xL1+0.
(iii) 6 KL capacity hour 1,005.00 854.25 P&M-025
1
c) Material
Sub-Analysis
Concrete from sub-analysis of concrete Rate cum 9.675 9.675 9.675 4,176.00 40,402.80 40,402.80 40,402.80 of Concrete -
20.2
Cost of water KL 1.335 1.335 1.335 16.00 21.36 21.36 21.36 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
5,022.11 6,283.14 7,569.02
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
6,779.84 6,911.45 7,064.42
(a+b+c+d) (a+b+c+d) (a+b+c+d)
0.134xL1+0.
(iii) 6 KL capacity hour 1,005.00 4,140.60 P&M-025
1
c) Material
Sub-Analysis
Concrete from sub-analysis of concrete Rate cum 15.000 15.000 15.000 4,518.00 67,770.00 67,770.00 67,770.00 of Concrete -
20.21
Cost of water KL 7.245 7.245 7.245 16.00 115.92 115.92 115.92 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
8,325.02 10,446.11 12,696.21
(a+b+c) (a+b+c) (a+b+c)
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
11,238.78 11,490.72 11,849.80
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Unit = Each
Taking output = one traffic sign
i) Excavation for foundation cum 0.122 223.00 27.21
Item No. -
cum 0.122 227.00 27.69
9.01 A - (I)
cum 0.122 231.00 28.18
ii) Cement concrete M25 grade cum 0.122 8,734.00 1,061.18 Item No. -
cum 0.122 8,942.00 1,086.45 9.06 E, case -
cum 0.122 9,266.00 1,125.82 II
iii) Painting angle iron post two coats sqm 1.414 93.00 131.48
Item No. -
sqm 1.414 95.00 134.30
8.09
sqm 1.414 97.00 137.13
a) Labour (For fixing at site)
Mate day 0.010 0.010 0.010 617.00 6.17 6.17 6.17 L-12
Mazdoor day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
b) Material
Mild Steel 'L' Angle Back Support Frame 25 x 25 x 3mm kg 2.200 2.200 2.200 63.81 140.37 140.37 140.37 M-181/1000
c) Machinery
Tractor-trolley hour 0.010 0.010 0.010 1,876.50 18.77 18.77 18.77 P&M-026
( ii ) 90 cm equilateral triangle
d) Overhead charges @ 8% on @ 10% on @ 12% on
343.79 429.74 515.69
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
464.12 472.72 481.31
(a+b+c+d) (a+b+c+d) (a+b+c+d)
( v ) 120 cm circular
d) Overhead charges @ 8% on @ 10% on @ 12% on
820.40 1,025.50 1,230.60
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
1,107.54 1,128.05 1,148.56
(a+b+c+d) (a+b+c+d) (a+b+c+d)
(vi) 90 cm circular
d) Overhead charges @ 8% on @ 10% on @ 12% on
518.15 647.69 777.23
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
699.50 712.46 725.41
(a+b+c+d) (a+b+c+d) (a+b+c+d)
(viii) 60 cm circular
d) Overhead charges @ 8% on @ 10% on @ 12% on
302.26 377.82 453.39
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
408.05 415.61 423.16
(a+b+c+d) (a+b+c+d) (a+b+c+d)
( ix ) 90 cm x 75 cm rectangular
d) Overhead charges @ 8% on @ 10% on @ 12% on
541.87 677.33 812.80
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
731.52 745.07 758.61
(a+b+c+d) (a+b+c+d) (a+b+c+d)
( x ) 80 mm x 60 mm rectangular
d) Overhead charges @ 8% on @ 10% on @ 12% on
422.75 528.44 634.13
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
570.72 581.28 591.85
(a+b+c+d) (a+b+c+d) (a+b+c+d)
(xi) 60 cm x 50 cm rectangular
d) Overhead charges @ 8% on @ 10% on @ 12% on
312.80 391.00 469.20
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
422.28 430.10 437.92
(a+b+c+d) (a+b+c+d) (a+b+c+d)
(xiii ) 60 cm x 60 cm square
d) Overhead charges @ 8% on @ 10% on @ 12% on
349.45 436.81 524.18
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
471.76 480.49 489.23
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Unit = sqm
Taking output = 0.9 sqm
i) Excavation for foundation cum 0.122 223.00 27.21
Item No. -
cum 0.122 227.00 27.69
9.01 A - (I)
cum 0.122 231.00 28.18
ii) Cement concrete M25 grade cum 0.122 8,734.00 1,061.18 Item No. -
cum 0.122 8,942.00 1,086.45 9.06 E, case -
cum 0.122 9,266.00 1,125.82 II
iii) Painting angle iron post two coats sqm 1.414 93.00 131.48
Item No. -
sqm 1.414 95.00 134.30
8.09
sqm 1.414 97.00 137.13
a) Labour (For fixing at site)
Mate day 0.008 0.008 0.008 617.00 4.94 4.94 4.94 L-12
Mazdoor day 0.200 0.200 0.200 511.52 102.30 102.30 102.30 L-13
b) Material
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
Mild Steel 'L' Angle Back Support Frame 35 x 35 x 3mm kg 6.080 6.080 6.080 63.81 387.94 387.94 387.94 M-181/1000
Unit = sqm
Taking output = 1.5 sqm
i) Excavation for foundation cum 0.243 223.00 54.19
Item No. -
cum 0.243 227.00 55.16
9.01 A - (I)
cum 0.243 231.00 56.13
ii) Cement concrete M25 grade cum 0.243 8,734.00 2,122.36 Item No. -
cum 0.243 8,942.00 2,172.91 9.06 E, case -
cum 0.243 9,266.00 2,251.64 II
iii) Painting angle iron post two coats sqm 2.827 93.00 262.91
Item No. -
sqm 2.827 95.00 268.57
8.09
sqm 2.827 97.00 274.22
a) Labour (For fixing at site)
Mate day 0.012 0.012 0.012 617.00 7.40 7.40 7.40 L-12
Mazdoor day 0.300 0.300 0.300 511.52 153.46 153.46 153.46 L-13
b) Material
Mild Steel 'L' Angle Back Support Frame 40 x 40 x 5 mm kg 14.400 14.400 14.400 63.81 918.81 918.81 918.81 M-181/1000
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.028 0.028 0.028 617.00 17.28 17.28 17.28 L-12
Painter day 0.500 0.500 0.500 679.00 339.50 339.50 339.50 L-18
Mazdoor day 0.200 0.200 0.200 511.52 102.30 102.30 102.30 L-13
b) Material
Paint ready mixed of approved brand. Litre 1.500 1.500 1.500 235.22 352.83 352.83 352.83 M-130
Add @ 1 per cent on cost of material for scaffolding 3.53 3.53 3.53
Cost for 6 Nos. 5th km stone = a+b+c+ d+e +f+g+h +i 41,308.68 42,132.29 43,235.25
Add 10 per cent cost of material for installation 1,146.75 1,146.75 1,146.75
c) Overhead charges @ 8% on @ 10% on @ 12% on
1,052.04 1,315.05 1,578.05
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,420.25 1,446.55 1,472.85
(a+b+c) (a+b+c) (a+b+c)
Cost for 30 Nos. delineators = (a+b+ c+d) 15,622.73 15,912.04 16,201.35
Rate per delineators = (a+b+c+d) /30 520.76 530.40 540.05
Say 521.00 530.00 540.00
In case of soft ground, a proper foundation may be
provided as per approved design. In case foundation is
Note required to be provided, the items of excavation and
foundation concrete are required to be measured and
paid separately.
8.16 806 Boundary pillar
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
Unit = Each
Taking output = 57 Nos.
a) M-15 grade of concrete cum 1.250 7,682.00 9,602.50
Item No. -
cum 1.250 7,870.00 9,837.50
9.06 Case II
cum 1.250 8,176.00 10,220.00
b) Steel reinforcement @ 5 kg per sqm kg 79.800 60.87 4,857.11
Item No. -
kg 79.800 62.08 4,954.14
9.07 / 1000
kg 79.800 63.39 5,058.60
c) Excavation in soil for foundation cum 10.720 223.00 2,390.56
Item No. -
cum 10.720 227.00 2,433.44
9.01 A(i)
cum 10.720 231.00 2,476.32
e) Lettering on km post (average 30 letters of 10 cm per cm
2280.000 1.60 3,648.00
height each) per letter
per cm Item No. -
2280.000 1.60 3,648.00
per letter 8.03
per cm
2280.000 1.60 3,648.00
per letter
Transportation and fixing
e) Labour
Mate day 0.570 0.570 0.570 617.00 351.69 351.69 351.69 L-12
Mazdoor day 14.250 14.250 14.250 511.52 7,289.16 7,289.16 7,289.16 L-13
f) Machinery
Tractor-trolley hour 6.000 6.000 6.000 1,876.50 11,259.00 11,259.00 11,259.00 P&M-026
g) Material
Stone spall cum 11.970 11.970 11.970 1,679.81 20,107.36 20,107.36 20,107.36 M-008
h) Overhead charges @ 8% on @ 10% on @ 12% on
3,120.58 3,900.72 4,680.87
(e+f+g) (e+f+g) (e+f+g)
i) Contractor's profit
@ 10% on @ 10% on @ 10% on
4,212.78 4,290.79 4,368.81
(e+f+g+h) (e+f+g+h) (e+f+g+h)
Rate for each boundary pillar = (a+b+c+d+e+ f+g+h+i)/57 1,172.61 1,194.24 1,218.59
Say 1,173.00 1,194.00 1,219.00
In case of soft ground, a proper foundation may be
provided as per approved design. In case foundation is
Note required to be provided, the items of excavation and
foundation concrete are required to be measured and
paid separately.
8.17 808 G.I Barbed Wire Fencing 1.2 Metre High
Add for drilling holes @ 2 per cent of cost of channels 126.80 126.80 126.80
c) Machinery
Tractor-trolley hour 0.040 0.040 0.040 1,876.50 75.06 75.06 75.06 P&M-026
d) Overhead charges @ 8% on @ 10% on @ 12% on
1,092.12 1,092.12 1,092.12
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
1,474.37 1,474.37 1,474.37
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Spacer 150 x 75 x 5 mm channel 0.546 m long,3 Nos kg 26.860 26.860 26.860 63.81 1,713.84 1,713.84 1,713.84 M-181/1000
Nuts and bolts kg 30.000 30.000 30.000 64.83 1,944.81 1,944.81 1,944.81 M-129
Add 15 per cent of the cost of material for fabrication,
2,281.40 2,281.40 2,281.40
nuts, bolts and washers etc.)
d) Overhead charges @ 8% on @ 10% on @ 12% on
1,487.67 1,859.59 2,231.51
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
2,008.36 2,045.55 2,082.74
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Suggest
8.25 Flexible Crash Barrier, Wire Rope Safety Barrier
ive
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
iv) Steel wire rope 40 mm, including 7.50 per cent extra
kg 65.000 65.000 65.000 44.78 2,910.86 2,910.86 2,910.86 M-179
for fixing at ends 15 x 4 x 1.075 @ 1 kg per m
c) Painting
Applying 2 coats of painting on exposed surface sqm 16.500 93.00 1,534.50
Item No. -
sqm 16.500 95.00 1,567.50
8.09
sqm 16.500 97.00 1,600.50
d) Machinery
Tractor-trolley hour 0.250 0.250 0.250 1,876.50 469.13 469.13 469.13 P&M-026
e) Overhead charges
@ 8% on @ 10% on @ 12% on
2,703.53 3,379.41 4,055.29
(a+b+d) (a+b+d) (a+b+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
3,649.76 3,717.35 3,784.94
(a+b+d+e) (a+b+d+e) (a+b+d+e)
Unit = Each
Taking output = one light
a) Labour
Mate day 0.030 0.030 0.030 617.00 18.51 18.51 18.51 L-12
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
Electrician day 0.250 0.250 0.250 738.00 184.50 184.50 184.50 L-02
b) Material
i) Steel circular hollow pole of standard specification for
street lighting to mount light at 10 m height above road each 1.000 1.000 1.000 15,000.00 15,000.00 15,000.00 15,000.00 M-172
level
ii) Sodium vapour lamp each 1.000 1.000 1.000 4,210.00 4,210.00 4,210.00 4,210.00 M-169
Add 5 per cent of cost of material for holder, electric
960.50 960.50 960.50
cable, insulation, ladder, scaffolding etc .
c) Painting
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
For Fixing in Median
sqm 5.750 93.00 534.75
Providing two coats of alluminium paint over steel circular Item No. -
sqm 5.750 95.00 546.25
hollow pipe with overhang on both sides 8.09
sqm 5.750 97.00 557.75
For fixing in Footpath
sqm 4.630 93.00 430.59
Providing two coats of alluminium paint over steel circular Item No. -
sqm 4.630 95.00 439.85
hollow pipe with overhang on one side 8.09
sqm 4.630 97.00 449.11
(i) For Fixing in Median
d) Overhead charges @ 8% on @ 10% on @ 12% on
1,650.34 2,062.93 2,475.51
(a+b) (a+b) (a+b)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
2,227.96 2,269.22 2,310.48
(a+b+d) (a+b+d) (a+b+d)
Rate per light for fixing in Median= a+b+c+d+e 25,042.32 25,507.67 25,973.01
Say 25,042.00 25,508.00 25,973.00
(ii) For fixing in Footpath
Rate per light for Fixing in Footpath = a+b+c+d+e 24,938.16 25,401.27 25,864.37
Say 24,938.00 25,401.00 25,864.00
Suggest
8.28 Lighting on Bridges
ive
Unit = Each
Taking output = one light
a) Labour
Mate day 0.020 0.020 0.020 617.00 12.34 12.34 12.34 L-12
Mazdoor day 0.400 0.400 0.400 511.52 204.61 204.61 204.61 L-13
Electrician day 0.200 0.200 0.200 738.00 147.60 147.60 147.60 L-02
b) Material
ii) Sodium vapour lamp 70 watt each 1.000 1.000 1.000 4,210.00 4,210.00 4,210.00 4,210.00 M-169
Add 1 per cent of cost of material for holder, electric
142.10 142.10 142.10
cable, insulation, ladder, scaffolding etc
c) Painting
sqm 2.760 93.00 256.68
Providing two coats of alluminium paint over steel circular Item No. -
sqm 2.760 95.00 262.20
hollow pipe 8.09
sqm 2.760 97.00 267.72
d) Overhead charges @ 8% on @ 10% on @ 12% on
1,177.33 1,471.66 1,766.00
(a+b) (a+b) (a+b)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
1,589.40 1,618.83 1,648.26
(a+b+d) (a+b+d) (a+b+d)
Suggest
8.29 Cable Duct Across the Road
ive
Sub-Analysis
Cement mortar 1:2 for joints (15.05B) cum 0.020 0.020 0.020 5,695.00 113.90 113.90 113.90 of Concrete -
20.01 B
d) Machinery
Tractor-trolley hour 0.500 0.500 0.500 1,876.50 938.25 938.25 938.25 P&M-026
e) Overhead charges
@ 8% on @ 10% on @ 12% on
5,053.70 6,317.13 7,580.55
(b+c+d) (b+c+d) (b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
6,822.50 6,948.84 7,075.18
(b+c+d+e) (b+c+d+e) (b+c+d+e)
Sub-Analysis
Cement mortar 1:2 for joints cum 0.040 0.040 0.040 5,695.00 227.80 227.80 227.80 of Concrete -
20.01 B
d) Machinery
Tractor-trolley hour 1.000 1.000 1.000 1,876.50 1,876.50 1,876.50 1,876.50 P&M-026
e) Overhead charges
@ 8% on @ 10% on @ 12% on
10,095.60 12,619.50 15,143.40
(b+c+d) (b+c+d) (b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
10,903.25 13,881.45 16,960.60
(b+c+d+e) (b+c+d+e) (b+c+d+e)
Sub-Analysis
Cement mortar 1:2 for joints cum 0.060 0.060 0.060 5,695.00 341.70 341.70 341.70 of Concrete -
20.01 B
d) Machinery
Tractor-trolley hour 1.500 1.500 1.500 1,876.50 2,814.75 2,814.75 2,814.75 P&M-026
e) Overhead charges
@ 8% on @ 10% on @ 12% on
15,172.92 18,966.15 22,759.38
(b+c+d) (b+c+d) (b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
20,483.44 20,862.76 21,242.08
(b+c+d+e) (b+c+d+e) (b+c+d+e)
Suggest
8.30 Highway Patrolling and Traffic Aid Post
ive
It is proposed to locate one Traffic Aid Post every 50-60
km of the highway.
The organisation and financial aspect are required to be
finalised in consultation with administrative and traffic
authorities .
Suggest Items Related to Underpass/ Subway/ Overhead Bridge/
8.31
ive Overhead Foot Bridge
Suggest
8.32 Traffic Control System and Communication System
ive
Unit = sqm
Taking output = 20sqm
a) Labour
Mate day 0.070 0.070 0.070 617.00 43.19 43.19 43.19 L-12
Mazdoor day 1.500 1.500 1.500 511.52 767.28 767.28 767.28 L-13
Blacksmith day 0.250 0.250 0.250 738.00 184.50 184.50 184.50 L-02
b) Material
Scrap tyres of size 900 x 20 each 80.000 80.000 80.000 130.00 10,400.00 10,400.00 10,400.00 M-162
20 mm steel wire rope kg 150.000 150.000 150.000 44.78 6,717.38 6,717.38 6,717.38 M-178
Add 1 per cent of cost of wire rope for clamps etc. 67.17 67.17 67.17
c) Machinery
Tractor-trolley hour 3.000 3.000 3.000 1,876.50 5,629.50 5,629.50 5,629.50 P&M-026
d) Overhead charges @ 8% on @ 10% on @ 12% on
1,904.72 2,380.90 2,857.08
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
2,571.37 2,618.99 2,666.61
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Unit = sqm
Taking output = 20sqm
a) Labour
Mate day 0.130 0.130 0.130 617.00 80.21 80.21 80.21 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Blacksmith day 0.250 0.250 0.250 738.00 184.50 184.50 184.50 L-02
b) Material
Plastic barrels each 50.000 50.000 50.000 150.00 7,500.00 7,500.00 7,500.00 M-173
or
Steel barrels each 50.000 50.000 50.000 252.00 12,600.00 12,600.00 12,600.00 M-173
Sand cum 8.000 8.000 8.000 1,994.03 15,952.25 15,952.25 15,952.25 M-004
20 mm steel wire rope kg 15.000 15.000 15.000 44.78 671.74 671.74 671.74 M-178
Add 1 per cent of cost of wire rope for clamps etc. 6.72 6.72 6.72
c) Machinery
Tractor-trolley hour 2.000 2.000 2.000 1,876.50 3,753.00 3,753.00 3,753.00 P&M-026
d) Overhead charges @ 8% on @ 10% on @ 12% on
2,374.64 2,968.30 3,561.96
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
3,205.76 3,265.13 3,324.49
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Unit = Nos
Taking output = 50Nos
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Material
Poly carbonate or ABS body and shall support a load of
13.635 Kg tested in accordance to ASTM D 4280 with
each 50.000 50.000 50.000 169.19 8,459.50 8,459.50 8,459.50 M-062
height not exceeding 20mm and width/length not
exceeding 130mm
Add 10 per cent of cost of material for fixing and
845.95 845.95 845.95
installation
c) Overhead charges @ 8% on @ 10% on @ 12% on
787.33 984.17 1,181.00
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,062.90 1,082.58 1,102.26
(a+b+c) (a+b+c) (a+b+c)
Cost for 50 studs = a+b+c+d 11,691.88 11,908.40 12,124.91
Rate per studs = (a+b+c+d)/50 233.84 238.17 242.50
Say 234.00 238.00 242.00
Suggest
8.36 Traffic Cone
ive
C Lawn
Providing a lawn planted with grass and its maintenance
The rate per sqm of premix carpet and road marking may
be adopted from chapter 5 & 8 respectively for the
quantities calculated from approved drawings
Suggest
8.39 Policeman Umbrella
ive
Unit = each
Taking output = one number
Earthwork cum
Cement Concrete cum
brick masonry or cum
stone masonry cum
Painting sqm 2.500 93.00 232.50
Item No. -
sqm 2.500 95.00 237.50
8.09
sqm 2.500 97.00 242.50
a) Labour
Mate day 0.090 0.090 0.090 617.00 55.53 55.53 55.53 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
Blacksmith (Ist class) day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-02
Welder day 0.250 0.250 0.250 738.00 184.50 184.50 184.50 L-02
b) Material
Steel pipe 100 mm dia metre 3.500 3.500 3.500 337.05 1,179.68 1,179.68 1,179.68 M-177
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
Steel pipe 25 mm dia metre 10.000 10.000 10.000 129.80 1,298.01 1,298.01 1,298.01 M-175
CGI sheets (0.8 mm) kg 8.000 8.000 8.000 62.55 500.40 500.40 500.40 M-082
Add 25 per cent of cost of material for fabrication 744.52 744.52 744.52
Add 2 per cent of cost of material for welding
59.56 59.56 59.56
consumables, J-hooks, washers etc.
c) Machinery
Tractor-trolley hour 0.500 0.500 0.500 1,876.50 938.25 938.25 938.25 P&M-026
d) Overhead charges @ 8% on @ 10% on @ 12% on
496.80 621.00 745.20
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit
@ 10% on @ 10% on @ 10% on
670.68 683.10 695.52
(a+b+c+d) (a+b+c+d) (a+b+c+d)
suggesti
8.40 High Mast Pole Lighting at Interchanges and Flyovers
ve
Unit = each
Taking output = one sign post
Following types of signs are required to be fixed in
construction zones for safety of traffic
a) Diversion one km ahead
b) Traffic sign ahead
c) Road ahead closed
d) Men at work
e) Road narrow
f) Single file traffic
g) Right lane diverted
h) Left lane diverted
i) Right lane closed
j) Left lane closed
k) Median closed
l) Diversion to other carriageway
m) Traffic signal ahead
n) Two way traffic
o) Un - even road
p) Slippery road
q) Loose chippings
r) Dual carriageway ends
s) Diversion
t) Do not enter
u) Road closed
v) Stop
w) Slow
x) One way
y) Give way
z) Overtaking prohibited
aa) Speed limit
bb) Weight limit
cc) Height and length limit
dd) No stopping or standing
ee) Any other warning or regulatory safety sign as per
site requirement and consistent with IRC:SP:55 and
IRC:67
The rate for traffic signs are already worked out and
given elsewhere in this chapter. The same may be
adopted.
suggesti
8.43 Portable Barricade in Construction Zone
ve
Unit = each
Taking output = one steel portable barricade
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
Painter day 0.500 0.500 0.500 679.00 339.50 339.50 339.50 L-18
Welder day 0.250 0.250 0.250 738.00 184.50 184.50 184.50 L-02
b) Material
Angle iron 45 x 45 x 5 mm kg 25.000 25.000 25.000 63.81 1,595.16 1,595.16 1,595.16 M-181 /1000
MS sheet 300 mm wide,2.5 m long and 2.6 mm thick kg 15.000 15.000 15.000 63.81 957.10 957.10 957.10 M-181 /1000
Paint litre 0.500 0.500 0.500 235.22 117.61 117.61 117.61 M-130
Add 2 per cent of cost of steel for welding consumables,
51.05 51.05 51.05
nuts & bolts and drilling holes
c) Overhead charges @ 8% on @ 10% on @ 12% on
271.80 339.75 407.70
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
293.54 373.72 456.62
(a+b+c) (a+b+c) (a+b+c)
Rate per barricade = a+b+c+d 3,962.82 4,110.95 4,261.80
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
Say 3,963.00 4,111.00 4,262.00
suggesti
8.44 Permanent Type Barricade in Construction Zone
ve
A With steel components
Unit = each
Taking output = one barricade
a) Labour
Mate day 0.048 0.048 0.048 617.00 29.62 29.62 29.62 L-12
Mazdoor day 0.300 0.300 0.300 511.52 153.46 153.46 153.46 L-13
Painter day 0.600 0.600 0.600 679.00 407.40 407.40 407.40 L-18
Welder day 0.300 0.300 0.300 738.00 221.40 221.40 221.40 L-02
b) Material
Angle iron 50 x 50 x 5 mm,2 m long,2 Nos. kg 15.000 15.000 15.000 63.81 957.10 957.10 957.10 M-181 /1000
MS sheet of 12 SWG,3 Nos of 200 mm width and 4 m
kg 50.000 50.000 50.000 63.81 3,190.33 3,190.33 3,190.33 M-181 /1000
length
Paint litre 1.000 1.000 1.000 235.22 235.22 235.22 235.22 M-130
Add 1 per cent of cost of steel for welding consumables,
82.95 82.95 82.95
nuts & bolts and drilling holes
c) Overhead charges @ 8% on @ 10% on @ 12% on
422.20 527.75 633.30
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
569.97 580.52 591.08
(a+b+c) (a+b+c) (a+b+c)
Rate per barricade = a+b+c+d 6,269.63 6,385.73 6,501.84
Say 6,270.00 6,386.00 6,502.00
8.44 B With wooden components
Unit = each
Taking output = one barricade
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Mazdoor day 0.300 0.300 0.300 511.52 153.46 153.46 153.46 L-13
Painter day 0.600 0.600 0.600 679.00 407.40 407.40 407.40 L-18
Carpenter day 0.600 0.600 0.600 738.00 442.80 442.80 442.80 L-04
b) Material
Timber cum 0.180 0.180 0.180 2,500.00 450.00 450.00 450.00 M-187
Add 1 per cent of cost of timber for nuts & bolts, nails,
4.50 4.50 4.50
etc.
c) Overhead charges @ 8% on @ 10% on @ 12% on
119.61 149.52 179.42
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
161.48 164.47 167.46
(a+b+c) (a+b+c) (a+b+c)
Rate per barricade = a+b+c+d 1,776.27 1,809.16 1,842.06
Say 1,776.00 1,809.00 1,842.00
8.44 C With bricks
Construction of a permanent type barricade made with
brick work in mud mortar, 1.5 m high, 4 m long, 600 mm
thick, plastered with cement mortar 1:6, painted with
yellow and white strips
Unit = each
Taking output = one barricade
a) Labour
Mate day 0.240 0.240 0.240 617.00 148.08 148.08 148.08 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Painter day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-18
Mason day 2.000 2.000 2.000 738.00 1,476.00 1,476.00 1,476.00 L-11
b) Material
Brick each 1800.000 1800.000 1800.000 3.50 6,300.00 6,300.00 6,300.00 M-079
Cement kg 22.000 22.000 22.000 4.94 108.68 108.68 108.68 M-081 /1000
Sand cum 0.090 0.090 0.090 1,994.03 179.46 179.46 179.46 M-005
Paint litre 1.250 1.250 1.250 235.22 294.03 294.03 294.03 M-130
c) Overhead charges @ 8% on @ 10% on @ 12% on
857.58 1,071.98 1,286.38
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,157.74 1,179.18 1,200.62
(a+b+c) (a+b+c) (a+b+c)
Rate per barricade = a+b+c+d 12,735.13 12,970.97 13,206.80
Say 12,735.00 12,971.00 13,207.00
suggesti
8.45 Drum Delineator in Construction Zone
ve
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
Unit = each
Taking output = one drum delineator
a) Labour
Mate day 0.020 0.020 0.020 617.00 12.34 12.34 12.34 L-12
Mazdoor day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
Painter day 0.250 0.250 0.250 679.00 169.75 169.75 169.75 L-18
b) Material
Steel drum 300 mm dia 1.2 m high/empty bitumen drum each 1.000 1.000 1.000 252.00 252.00 252.00 252.00 M-173
Paint litre 0.500 0.500 0.500 235.22 117.61 117.61 117.61 M-130
c) Overhead charges @ 8% on @ 10% on @ 12% on
54.37 67.96 81.55
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
73.39 74.75 76.11
(a+b+c) (a+b+c) (a+b+c)
Rate per drum delineator = a+b+c+d 807.34 822.29 837.24
Say 807.00 822.00 837.00
suggesti
8.46 Water Filled Barricades Work zone sheeting
ve
Unit = each
Taking output = one drum delineator
a) Labour
Mate day 0.010 0.010 0.010 617.00 6.17 6.17 6.17 L-12
Mazdoor day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
b) Material
Water Filled Barricades Work zone sheeting each 1.000 1.000 1.000 2,500.00 2,500.00 2,500.00 2,500.00 M-238
c) Overhead charges @ 8% on @ 10% on @ 12% on
210.72 263.41 316.09
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
284.48 289.75 295.01
(a+b+c) (a+b+c) (a+b+c)
Rate per drum delineator = a+b+c+d 3,129.25 3,187.20 3,245.15
Say 3,129.00 3,187.00 3,245.00
suggesti
8.47 Tubular Marker/ Spring post 450 mm
ve
Unit = each
Taking output = one drum delineator
a) Labour
Mate day 0.010 0.010 0.010 617.00 6.17 6.17 6.17 L-12
Mazdoor day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
b) Material
Tubular Marker/ Spring post 450 mm each 1.000 1.000 1.000 350.00 350.00 350.00 350.00 M-237
c) Overhead charges @ 8% on @ 10% on @ 12% on
38.72 48.41 58.09
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
52.28 53.25 54.21
(a+b+c) (a+b+c) (a+b+c)
Rate per drum delineator = a+b+c+d 575.05 585.70 596.35
Say 575.00 586.00 596.00
suggesti
8.48 Tubular Marker/ Spring post 700 mm
ve
Unit = each
Taking output = one drum delineator
a) Labour
Mate day 0.010 0.010 0.010 617.00 6.17 6.17 6.17 L-12
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project Input ref.
Specification Project Project Project
Mazdoor day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
b) Material
Tubular Marker/ Spring post 700 mm each 1.000 1.000 1.000 375.00 375.00 375.00 375.00 M-236
c) Overhead charges @ 8% on @ 10% on @ 12% on
40.72 50.91 61.09
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
54.98 56.00 57.01
(a+b+c) (a+b+c) (a+b+c)
Rate per drum delineator = a+b+c+d 604.75 615.95 627.15
Say 605.00 616.00 627.00
suggesti
8.49 Flagman
ve
Unit = each
Taking output = one flagman
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Material
Flag of red color cloth 600 x 600 mm each 1.000 1.000 1.000 118.00 118.00 118.00 118.00 M-099
Wooden staff for fastening of flag 25 mm dia, one m long each 1.000 1.000 1.000 16.00 16.00 16.00 16.00 M-198
c) Overhead charges @ 8% on @ 10% on @ 12% on
53.62 67.02 80.42
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
72.38 73.72 75.06
(a+b+c) (a+b+c) (a+b+c)
Rate per flagman = a+b+c+d 796.20 810.94 825.69
Say 796.00 811.00 826.00
Video Management Software with atleast 150 VMS Lic. Nos. 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-260
Facility Monitoring System Controller Software Nos. 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-261
Server & Database license Nos. 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-262
Antivirus license Nos. 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-263
C PTZ Closed Circuit Television System
PTZ Camera (including CCTV Controller) Set 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-264
Solar System with UPS, battery & 12m Pole & Cabinet Set 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-265
Uninterruptible Power Supply (UPS) For TMC (30 KVA) Set 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-277
Power Distribution Board (Essential & Critical Supply) Set 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-278
H Meteorological Observation System (MOS)
MOS sensor Equipment (including MOS Controller) Set 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-279
Cabinet Nos. 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-280
Pole Nos. 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-281
Steel fence for protection Set 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-282
I Digital Transmission System (DTS)
24 Core Armoured OFC + all accessories Km 1.000 1.000 1.00 29.00 29.00 29.00 29.00 M-283
40 mm PLB HDPE duct as per latest TSEC specifications
Km 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-284
+ all accessories
Trenching of 1.8 meters, Laying & Backfilling for PLB
Km 1.000 1.000 1.00 1.00 1.00 1.00 1.00 M-285
HDPE duct
Overhead and contractor profit will be add separately on
Note
Item no 8.50 .
Civil works required to be executed for these
installations, pricing may be done as per rates in relevant
chapters for quantities derived approved design and
drawing.)
suggesti Fiber Reinforced Cement Concrete new jersey crash
8.51
ve barrier
I Ordinary soil
Unit = cum
Taking output = 10 cum
Manual Means
A (i) Depth upto 3 m
a) Labour
Mate day 0.140 0.140 0.140 617.00 86.38 86.38 86.38 L-12
Mazdoor day 3.500 3.500 3.500 511.52 1,790.32 1,790.32 1,790.32 L-13
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 187.670 187.670 187.670
b) Overhead charges @ 10% on
@ 8% on (a) @ 12% on (a) 150.14 187.67 225.20
(a)
c) Contractor's profit @ 10% on @ 10% on @ 10% on
202.68 206.44 210.19
(a+b) (a+b) (a+b)
Cost for 10 cum = a+b+c 2,229.52 2,270.81 2,312.09
Rate per cum = (a+b+c)/10 222.95 227.08 231.21
Say 223.00 227.00 231.00
Note
1. Cost of dewatering may be added where required
upto, 10 per cent of labour cost Assessment for
dewatering shall be made as per site conditions.
c) Material
Explosives (Blasting Material) kg 3.500 3.500 3.500 81.90 286.65 286.65 286.65 M-215
Detonator electric each 14.000 14.000 14.000 21.00 294.00 294.00 294.00 M-217
d) Overhead charges @ 8% on @ 10% on @ 12% on
473.72 592.14 710.57
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
639.52 651.36 663.20
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10 cum = a+b+c+d+e 7,034.67 7,164.94 7,295.21
Rate per cum = (a+b+c+d+e)/10 703.47 716.49 729.52
Say 703.00 716.00 730.00
Note Cost of dewatering @ 10 per cent of (a+b) may be
added, where required Assessment for dewatering
shall be made as per site conditions.
9.01 301 & 302 III Hard Rock ( requiring blasting )
Carrying out excavation in hard rock to achieve a
specified slope of the rock face by controlled use of
explosives and blasting accessories in properly aligned
and spaced drill holes, collection of the excavated rock
by a dozer, loading in tipper by a front end loader and
disposing of the material with all lifts and lead upto
1000 m, all as specified in clause No. 303
B Mechanical Means
Unit = cum
Taking output = 120 cum
a) Labour
Mate day 0.210 0.210 0.210 617.00 129.57 129.57 129.57 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Driller day 2.000 2.000 2.000 558.00 1,116.00 1,116.00 1,116.00 L-06
Blaster day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-03
b) Machinery
Air compressor hour 6.000 6.000 6.000 614.25 3,685.50 3,685.50 3,685.50 P&M-029
Jack Hammer for drilling holes (@ 4.5 m per hour) P&M-078
hour 24.000 24.000 24.000 11.55 277.20 277.20 277.20
Jack Hammer (consider 5% of the volume for dressing) P&M-010
hour 1.024 1.024 1.024 206.00 210.94 210.94 210.94
Hydraulic Excavator
Excavator for excavation
(i) 1.2 cum bucket capacity hour 1.024 3,420.00 3,502.08 P&M-007
(ii) 1.1 cum bucket capacity hour 1.024 3,074.00 3,147.78 P&M-008
(iii) 0.9 cum bucket capacity hour 1.024 2,782.00 2,848.77 P&M-009
For loading
(i) 1.2 cum bucket capacity hour 2.094 3,420.00 7,160.89 P&M-007
(ii) 1.1 cum bucket capacity hour 2.411 3,074.00 7,412.54 P&M-008
(iii) 0.9 cum bucket capacity hour 3.371 2,782.00 9,378.66 P&M-009
Tipper
For transportation considering lead @ 1 km
(i) 18 cum capacity t-km 180.000 7.51 1,351.55 P&M-117
(ii) 14 cum capacity t-km 180.000 8.52 1,534.05 P&M-120
(iii) 10 cum capacity t-km 180.000 10.53 1,895.25 P&M-123
For loading & unloading time
(i) 18 cum capacity hour 2.094 2,883.30 6,037.13 P&M-014
(ii) 14 cum capacity hour 2.411 2,556.75 6,165.26 P&M-015
(iii) 10 cum capacity hour 3.371 2,274.30 7,667.11 P&M-016
c) Materials
Small dia.Explosive at 0.40 kg / cum for 120 cum ( 120 M-215
x 0.40 )
Explosive at 0.20 kg / cum for secondary blast @ 5%of kg 48.000 48.000 48.000 81.90 3,931.20 3,931.20 3,931.20
the total volume ( 120 x 0.2x5% )
Electric detonators at 1 per hole for main blast holes M-217
(21x3+20*2)=103 nos no 69.000 69.000 69.000 21.00 1,449.00 1,449.00 1,449.00
Ordinary detonators @ 1 per hole for 10 secondary M-216
holes( required for 5% of the total quantity @ 0.6 m per no 7.000 7.000 7.000 21.00 147.00 147.00 147.00
hole for I cum )
Detonating fuse coil m 213.000 213.000 213.000 19.00 4,047.00 4,047.00 4,047.00 M-218
d) Overhead charges @ 8% on @ 10% on @ 12% on
2,776.60 3,491.55 4,613.48
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
3,748.41 3,840.70 4,305.91
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 120 cum = a+b+c+d+e 41,232.51 42,247.73 47,365.03
Rate per cum = (a+b+c+d+e)/120 343.60 352.06 394.71
Say 344.00 352.00 395.00
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mason day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-10
Mazdoor day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
b) Material
Plain cement concrete 1:3:6 nominal mix using Sub-
batching plant (Rate as sub-analysis) Analysis of
cum 15.000 15.000 15.000 4,238.00 63,570.00 63,570.00 63,570.00 Concrete -
20.02
Water KL 3.240 3.240 3.240 16.00 51.84 51.84 51.84 M-191
c) Machinery
Plate Compactor hour 1.000 1.000 1.000 597.45 597.45 597.45 597.45 P&M-079
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading @ 30 mins per trip )
Unit = metre
Taking output = 12.5 metres ( 5 pipes of 2.5 m length
each )
A 1000 mm dia
a) Labour
Mate day 0.100 0.100 0.100 617.00 61.70 61.70 61.70 L-12
Mason day 0.500 0.500 0.500 679.00 339.50 339.50 339.50 L-10
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Material
Sand at site cum 0.070 0.070 0.070 1,994.03 139.58 139.58 139.58 M-005
Cement at site tonne 0.050 0.050 0.050 4,940.00 247.00 247.00 247.00 M-081
RCC pipe NP-4 /prestressed concrete pipe including M-148
collar at site metre 12.500 12.500 12.500 5,925.00 74,062.50 74,062.50 74,062.50
Granular material passing 5.6 mm sieve for bedding M-009
cum 4.500 4.500 4.500 1,887.12 8,492.05 8,492.05 8,492.05
c) Machinery
Light Crane 3 tonnes capacity for placing of Hume P&M-102
pipe hour 2.083 2.083 2.083 1,083.60 2,257.50 2,257.50 2,257.50
d) Overhead charges @ 8% on @ 10% on @ 12% on
6,929.83 8,662.29 10,394.75
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
9,355.27 9,528.52 9,701.76
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 12.5 metres = a+b+c+d 102,907.98 104,813.68 106,719.38
Rate per metre = (a+b+c+d)/12.5 8,232.64 8,385.09 8,537.55
Say 8,233.00 8,385.00 8,538.00
Note 1. In case of cement craddle bedding, quantity of PCC
M15 is to be calculated as per design and priced
separately and added .
2. The rate analysis does not include excavation,
cement /masonry works in head walls, backfilling,
protection works and parapet walls. The same are to
be calculated as per approved design and drawings
and priced separately on rates available under
respective sections
Unit = metre
Taking output = 12.5 metres ( 10 pipes of 2.5 m length
each in two rows.)
A 1000 mm dia
a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mason day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-10
Mazdoor day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
b) Material
Sand at site cum 0.140 0.140 0.140 1,994.03 279.16 279.16 279.16 M-005
Cement at site tonne 0.100 0.100 0.100 4,940.00 494.00 494.00 494.00 M-081
RCC pipe NP-4/prestressed concrete pipe including M-148
collar at site metre 25.000 25.000 25.000 5,925.00 148,125.00 148,125.00 148,125.00
Granular material passing 5.6 mm sieve for bedding M-009
cum 12.500 12.500 12.500 1,887.12 23,589.04 23,589.04 23,589.04
c) Machinery
Light Crane 3 tonnes capacity for handling Hume pipe P&M-102
hour 4.167 4.167 4.167 1,083.60 4,515.00 4,515.00 4,515.00
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
d) Overhead charges @ 8% on @ 10% on @ 12% on
14,388.05 17,985.07 21,582.08
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
19,423.87 19,783.58 20,143.28
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 12.5 metres = a+b+c+d 213,662.61 217,619.33 221,576.04
Rate per metre = (a+b+c+d)/12.5 17,093.01 17,409.55 17,726.08
Say 17,093.00 17,410.00 17,726.00
Note 1. In case of cement craddle bedding, quantity of PCC
M15 is to be calculated as per design and priced
separately and added .
2. The rate analysis does not include excavation,
cement /masonry works in head walls, backfilling,
protection works and parapet walls. The same are to
be calculated as per approved design and drawings
and priced separately on rates available under
respective sections
Unit = cum
Taking output = 15 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis) Sub-
Analysis of
cum 15.000 15.000 15.000 4,176.00 62,640.00 62,640.00 62,640.00 Concrete -
20.03
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne- P&M-128
37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19
km
For unloading hour 0.833 0.833 0.833 2,413.95 2,010.82 2,010.82 2,010.82 P&M-067
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.055xL1+0.3 P&M-023
hour 1,501.00 2,968.98
28
(ii) 12 KL capacity 0.073xL1+0.4 P&M-024
hour 1,327.00 3,487.36
38
(iii) 6 KL capacity 0.146xL1+0.8 P&M-025
hour 1,005.00 5,281.28
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 5879.000 5914.000 6033.000
d) Formwork @ 10 per cent on cost of concrete i.e.
cost of material, labour and machinery 8,817.81 8,869.65 9,049.04
Unit = MT
Taking output = 8 MT
a) Material
MS bars including 5 per cent overlaps and wastage M-083
tonne 8.400 8.400 8.400 46,496.54 390,570.97 390,570.97 390,570.97
Binding wire Kg 48.000 48.000 48.000 66.72 3,202.56 3,202.56 3,202.56 M-072
b) Labour for straightening, cutting, bending, shifting
to site, tying and placing in position
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Blacksmith day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-20
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
c) Machinery
Cutting Machine & Bending Machine hour 5.333 5.333 5.333 528.15 2,816.62 2,816.62 2,816.62 P&M-076
Electric generator 15 KVA hour 5.333 5.333 5.333 425.25 2,267.86 2,267.86 2,267.86 P&M-051
Tipper
Tipper for Transportation
(i) 18 cum capacity t.km 8xL 6.18 1,482.84 P&M-116
(ii) 14 cum capacity t.km 8xL 7.01 1,683.07 P&M-119
(iii) 10 cum capacity t.km 8xL 8.66 2,079.36 P&M-122
Loading & Unloading Time hour
(i) 18 cum capacity hour 1.000 2,883.30 2,883.30 P&M-014
(ii) 14 cum capacity hour 1.280 2,556.75 3,272.64 P&M-015
(iii) 10 cum capacity hour 1.778 2,274.30 4,043.20 P&M-016
Light weight Crane
At cutting bending yard hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102
At site hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102
Per MT Basic Cost of Labour, Material & Machinery
(a+b+c) 51234.000 51308.000 51454.000
Unit = cum
Taking output = 10 cum 10 Cum 12 tonne
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Hydraulic Excavator
(i) 1.2 cum bucket capacity hour 0.007 3,420.00 23.94 P&M-007
(ii) 1.1 cum bucket capacity hour 0.008 3,074.00 24.59 P&M-008
(iii) 0.9 cum bucket capacity hour 0.012 2,782.00 33.38 P&M-009
Tipper
For transportation to dumping yard considering
lead @ 1km
(i) 18 cum capacity t.km 12 x L2 6.18 74.14 P&M-116
(ii) 14 cum capacity t.km 12 x L2 7.01 84.15 P&M-119
(iii) 10 cum capacity t.km 12 x L2 8.66 103.97 P&M-122
For loading & unloading
(i) 18 cum capacity hour 0.007 2,883.30 20.18 P&M-014
(ii) 14 cum capacity hour 0.008 2,556.75 20.45 P&M-015
(iii) 10 cum capacity hour 0.012 2,274.30 27.29 P&M-016
Plate compactor hour 0.500 0.500 0.500 597.45 298.73 298.73 298.73 P&M-079
d) Overhead charges @ 8% on @ 10% on @ 12% on 119.15 150.03 184.29
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 160.85 165.04 172.01
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10 cum = a+b+c+d 1,769.40 1,815.39 1,892.07
Rate per cum = (a+b+c+d)/10 176.94 181.54 189.21
Say 177.00 182.00 189.00
Note Only 75 per cent of fresh material has been
provided as 25 per cent can be retrieved at site
from earth that is flown down the slope in the form
of slurry and deposited at the foot of there in cuts
Crushed stone aggregates nominal size 13.2mm 348,174.21 348,174.21 348,174.21 M-051
cum 184.500 184.500 184.500 1,887.12
Crushed stone aggregates nominal size 11.2mm 174,087.11 174,087.11 174,087.11 M-050
cum 92.250 92.250 92.250 1,887.12
Bitumen 80/100 tonne 14.970 14.970 14.970 48,006.37 718,655.37 718,655.37 718,655.37 M-075
Bitumen emulsion for tack coat including vertical 117,249.43 117,249.43 117,249.43 M-077
sides of pot hole. tonne 2.460 2.460 2.460 47,662.37
d) Overhead charges @ 8% on @ 10% on @ 12% on 125,905.65 157,771.32 191,047.01
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on 169,972.62 173,548.46 178,310.54
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10250 sqm = a+b+c+d+e 1,869,698.86 1,909,033.03 1,961,415.96
Rate per sqm = (a+b+c+d+e)/10250 182.41 186.25 191.36
Say 182.00 186.00 191.00
10.05 3004.2 Filling Pot-holes and Patch Repairs with
Bituminous concrete, 40mm.
Removal of all failed material, trimming of
completed excavation to provide firm vertical faces,
cleaning of surface, painting of tack coat on the
sides and base of excavation as per clause 503,
back filling the pot holes with hot bituminous
material as per clause 504, compacting, trimming
and finishing the surface to form a smooth
continuous surface, all as per clause 3004.2
Unit = Sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Material
Stone crusher dust finer than 3mm with not more 11,794.52 11,794.52 11,794.52 M-020
than 10 per cent passing 0.075 sieve. cum 6.250 6.250 6.250 1,887.12
c) Overhead charges @ 8% on @ 10% on @ 12% on 1,029.35 1,286.69 1,544.03
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 1,389.63 1,415.36 1,441.09
(a+b+c) (a+b+c) (a+b+c)
Cost for 3500sqm = a+b+c+d 15,285.90 15,568.97 15,852.04
Rate per meter = (a+b+c+d)/3500 4.37 4.45 4.53
Say 4.00 4.00 5.00
10.8 (A) Fog Seal
3004.3.2 sqm
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Dozer 175 HP hour 1.670 1.670 1.670 5,087.25 8,495.71 8,495.71 8,495.71 P&M-002
c) Overhead charges @ 8% on @ 10% on @ 12% on 722.55 903.19 1,083.83
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 975.45 993.51 1,011.57
(a+b+c) (a+b+c) (a+b+c)
Cost for 100 cum = a+b+c+d 10,729.91 10,928.61 11,127.31
Rate per cum = (a+b+c+d)/100 107.30 109.29 111.27
Say 107.00 109.00 111.00
Note Land Slide clearance involves pushing of loose
earth slided on the road surface from hill face on
the valley side. Since no cutting of original ground
is involved, the output of dozer has been taken as
60 cum per hour for soil, ordinary rock and blasted
hard rock. However, if there are objection to
disposing of earth on valley side, additional
resources for its disposal shall be considered as
per site conditions.
Unit = cum
Taking output = 5000 cum
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Dozer 175 HP hour 5.880 5.880 5.880 5,087.25 29,913.03 29,913.03 29,913.03 P&M-002
c) Overhead charges @ 8% on @ 10% on @ 12% on 2,478.83 3,098.54 3,718.25
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on 3,346.43 3,408.40 3,470.37
(a+b+c) (a+b+c) (a+b+c)
Cost for 5000 cum = a+b+c+d 36,810.69 37,492.37 38,174.05
Rate per cum = (a+b+c+d)/5000 7.36 7.50 7.63
Say 7.00 7.00 8.00
Note i) Labour provided will not be cutting the snow.
They will be guiding the dozer operator on the
alignment of the road as entire surface gets
covered with snow and the edges of the road are
not visible and for changing the blade angle. Also
they will keep a watch on the hill side for any
eventuality of avalanches, slide etc
Quantity Amount (Rs.)
Ref.to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium Small
(Rs.) Large Project ref.
Specification Project Project Project Project Project
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Blacksmith day 0.500 0.500 0.500 738.00 369.00 369.00 369.00 L-02
Mazdoor day 1.500 1.500 1.500 511.52 767.28 767.28 767.28 L-13
b) Machinery
Tractor-trolley hour 0.100 0.100 0.100 1,876.50 187.65 187.65 187.65 P&M-026
c) Material
Corrugated sheet,3 mm thick, "Thrie" beam section
kg 72.940 72.940 72.940 72.28 5,272.10 5,272.10 5,272.10 M-089
railing,4.5 m in length
Channel post 150 x 75 x 5 mm, 2 m long,3 Nos @
kg 98.400 98.400 98.400 63.81 6,278.56 6,278.56 6,278.56 M-181/1000
16.4 kg per metre
Spacer 150 x 75 x 5 mm channel 0.546 m long,3
kg 26.860 26.860 26.860 63.81 1,713.84 1,713.84 1,713.84 M-181/1000
Nos
Nuts and bolts kg 30.000 30.000 30.000 64.83 1,944.81 1,944.81 1,944.81 M-129
Add 15 per cent of the cost of material for
2,281.40 2,281.40 2,281.40
fabrication, nuts, bolts and washers etc.)
Credit for salvage value of dismantled material kg 166.010 166.010 166.010 -26.47 -4,394.62 -4,394.62 -4,394.62
d) Overhead charges @ 8% on @ 10% on @ 12% on
1,509.12 1,886.40 2,263.68
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
2,037.31 2,075.04 2,112.77
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 4.5 metre = a+b+c+d+e 18,015.82 18,430.83 18,845.84
Rate per metre= (a+b+c+d+e)/4.5 4,003.52 4,095.74 4,187.96
Say 4,004.00 4,096.00 4,188.00
10.17 Network Survey Vehicle (NSV) attached with SUV
Unit = sqm
Taking output = 100 sqm
(i) In rows 15 cm apart in either direction
a) Labour
Mate day 0.070 0.070 0.070 617.00 43.19 43.19 43.19 L-12
Mazdoor for grassing day 0.750 0.750 0.750 511.52 383.64 383.64 383.64 L-13
Mazdoor for maintenance for 30 days day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Water tanker6 KL capacity hour 0.500 0.500 0.500 1,005.00 502.50 502.50 502.50 P&M-025
c) Material
Doob grass kg 100.000 100.000 100.000 34.75 3,475.00 3,475.00 3,475.00 M-111
d) Overhead charges @ 8% on @ 10% on @ 12% on
393.27 491.59 589.90
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
530.91 540.74 550.58
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 5,840.03 5,948.18 6,056.33
Rate per sqm= (a+b+c+d+e)/100 58.40 59.48 60.56
Say 58.00 59.00 61.00
11.2 (ii) In rows 7.5 cm apart in either direction
a) Labour
Mate day 0.090 0.090 0.090 617.00 55.53 55.53 55.53 L-12
Mazdoor for grassing. day 1.250 1.250 1.250 511.52 639.40 639.40 639.40 L-13
for maintenance for 30 days day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Water tanker6 KL capacity hour 0.750 0.750 0.750 1,005.00 753.75 753.75 753.75 P&M-025
c) Material
Doob grass kg 200.000 200.000 200.000 34.75 6,950.00 6,950.00 6,950.00 M-111
d) Overhead charges @ 8% on @ 10% on @ 12% on
712.82 891.02 1,069.22
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
962.30 980.12 997.94
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 10,585.32 10,781.34 10,977.37
Rate per sqm = (a+b+c+d+e)/100 105.85 107.81 109.77
Say 106.00 108.00 110.00
Note In the case of horticulture one mate has been
provided for every 10 mazdoors as maintenance of
grass and plants require more care.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Mazdoor for preparation of ground day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
Mali for fetching doobs grass roots and grassing at L-09
15 cm apart day 1.000 1.000 1.000 511.52 511.52 511.52 511.52
b) Machinery
Water tanker6 KL capacity hour 0.500 0.500 0.500 1,005.00 502.50 502.50 502.50 P&M-025
Tractor with tipper hour 0.010 0.010 0.010 1,876.50 18.77 18.77 18.77 P&M-026
c) Material
Supply of farm yard manure at site of work cum 0.180 0.180 0.180 300.00 54.00 54.00 54.00 M-168
Fine grass kg 100.000 100.000 100.000 34.75 3,475.00 3,475.00 3,475.00 M-112
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
d) Overhead charges @ 8% on @ 10% on @ 12% on
388.37 485.46 582.55
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
524.29 534.00 543.71
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 5,767.22 5,874.02 5,980.82
Rate per sqm = (a+b+c+d+e)/100 57.67 58.74 59.81
Say 58.00 59.00 60.00
11.4 307 Maintenance of Lawns or Turfing of Slopes
Maintenance of lawns or Turfing of slopes (rough
grassing) for a period of one year including
watering etc
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.400 0.400 0.400 617.00 246.80 246.80 246.80 L-12
Mali day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-09
b) Machinery
Water tanker6 KL capacity hour 15.000 15.000 15.000 1,005.00 15,075.00 15,075.00 15,075.00 P&M-025
c) Material
Cost of water KL 90.000 90.000 90.000 16.00 1,440.00 1,440.00 1,440.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
1,750.16 2,187.70 2,625.24
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
2,362.72 2,406.47 2,450.22
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 25,989.88 26,471.17 26,952.46
Rate per sqm = (a+b+c+d+e)/100 259.90 264.71 269.52
Say 260.00 265.00 270.00
11.5 307 Turfing Lawns with Fine Grassing including
Ploughing, Dressing
Turfing lawns with fine grassing including
ploughing, dressing including breaking of clods,
removal of rubbish, dressing and supplying doobs
grass roots at 10 cm apart, including supplying and
spreading of farm yard manure at rate of0.6 cum
per 100 sqm
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.100 0.100 0.100 617.00 61.70 61.70 61.70 L-12
Mazdoor for preparation of ground day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
Mali for fetching doobs grass roots hedges and L-09
grassing at 10 cm apart day 1.500 1.500 1.500 511.52 767.28 767.28 767.28
b) Machinery
Water tanker6 KL capacity hour 0.500 0.500 0.500 1,005.00 502.50 502.50 502.50 P&M-025
Tractor with tiller hour 0.010 0.010 0.010 1,876.50 18.77 18.77 18.77 P&M-026
c) Material
Supply of farm yard manure at site of work @ 0.6 M-168
cum per 100 sqm cum 0.600 0.600 0.600 300.00 180.00 180.00 180.00
Fine grass kg 100.000 100.000 100.000 34.75 3,475.00 3,475.00 3,475.00 M-112
d) Overhead charges @ 8% on @ 10% on @ 12% on
441.34 551.68 662.01
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
595.81 606.84 617.88
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 6,553.92 6,675.29 6,796.65
Rate per sqm = (a+b+c+d+e)/100 65.54 66.75 67.97
Say 66.00 67.00 68.00
11.6 307 Maintenance of Lawns with Fine Grassing for the
First Year
Maintenance of lawns with fine grassing for the first
year including watering etc
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.400 0.400 0.400 617.00 246.80 246.80 246.80 L-12
Mali day 10.000 10.000 10.000 511.52 5,115.20 5,115.20 5,115.20 L-09
b) Machinery
Water tanker6 KL capacity hour 20.000 20.000 20.000 1,005.00 20,100.00 20,100.00 20,100.00 P&M-025
c) Material
Cost of water KL 60.000 60.000 60.000 16.00 960.00 960.00 960.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
2,113.76 2,642.20 3,170.64
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
2,853.58 2,906.42 2,959.26
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 31,389.34 31,970.62 32,551.90
Rate per sqm = (a+b+c+d+e)/100 313.89 319.71 325.52
Say 314.00 320.00 326.00
11.7 307 Planting and Maintaining of Permanent Hedges
Unit = Each
Taking output = 10 trees
a) Labour
Mate day 0.680 0.680 0.680 617.00 419.56 419.56 419.56 L-12
Mazdoor for planting day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
Mazdoor for maintenance for one year day 15.000 15.000 15.000 511.52 7,672.80 7,672.80 7,672.80 L-13
b) Machinery
Water tanker6 KL capacity hour 2.000 2.000 2.000 1,005.00 2,010.00 2,010.00 2,010.00 P&M-025
c) Material
Sapling 2 m high 25 mm dia each 10.000 10.000 10.000 300.00 3,000.00 3,000.00 3,000.00 M-161
Farm yard manure cum 0.940 0.940 0.940 300.00 282.00 282.00 282.00 M-168
Pesticide kg 0.500 0.500 0.500 222.40 111.20 111.20 111.20 M-135
Cost of water KL 12.000 12.000 12.000 16.00 192.00 192.00 192.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
1,176.85 1,471.06 1,765.27
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
1,588.74 1,618.17 1,647.59
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10 trees = a+b+c+d+e 17,476.19 17,799.83 18,123.46
Rate per trees = (a+b+c+d+e)/10 1,747.62 1,779.98 1,812.35
Say 1,748.00 1,780.00 1,812.00
11.10 308
Renovation Lawns including, Weeding, Forking the
Ground, Top Dressing with Forked Soil
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Machinery
Water tanker6 KL capacity hour 0.500 0.500 0.500 1,005.00 502.50 502.50 502.50 P&M-025
c) Material
Cost of water KL 3.000 3.000 3.000 16.00 48.00 48.00 48.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
172.73 215.91 259.09
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
233.18 237.50 241.82
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 2,565.01 2,612.51 2,660.01
Rate per sqm = (a+b+c+d+e) 25.65 26.13 26.60
Say 26.00 26.00 27.00
11.11 308.2
Supply at Site Well Decayed Farm Yard Manure
Supply at site of work well decayed farm yard
manure, from any available source, approved by
the engineer in charge including screening and
stacking
Unit = cum
Taking output = one cum
a) Material
a) Cost of well decayed farm yard manure duly M-168
screened, loading, carriage, unloading and cum 1.000 1.000 1.000 300.00 300.00 300.00 300.00
stacking at site
b) Overhead charges @ 10% on @ 12% on
@ 8% on (a) 24.00 30.00 36.00
(a) (a)
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
c) Contractor's profit @ 10% on @ 10% on @ 10% on
32.40 33.00 33.60
(a+b) (a+b) (a+b)
Rate per cum = (a+b+c) 356.40 363.00 369.60
Say 356.00 363.00 370.00
11.12 308.20 Supply at Site of Work/ Store-Deoiled Neem Cake
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.020 0.020 0.020 617.00 12.34 12.34 12.34 L-12
Mason day 0.250 0.250 0.250 738.00 184.50 184.50 184.50 L-11
Mazdoor day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
b) Material
Brick 2nd class including carriage each 230.000 230.000 230.000 3.50 805.00 805.00 805.00 M-079
Cement mortar 1:6 Sub-
Analysis of
cum 0.025 0.025 0.025 4,588.00 114.70 114.70 114.70 Concrete -
20.01 D
c) Overhead charges @ 8% on @ 10% on @ 12% on
99.55 124.44 149.33
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
134.40 136.89 139.38
(a+b+c) (a+b+c) (a+b+c)
Rate per tree Guard = a+b+c+d 1,478.37 1,505.75 1,533.13
Say 1,478.00 1,506.00 1,533.00
11.15 New Edging with 2nd Class Bricks, Laid Dry Lengthwise
Unit = Metre
Taking output= 10 metres
a) Labour
Mate day 0.004 0.004 0.004 617.00 2.47 2.47 2.47 L-12
Mason day 0.050 0.050 0.050 738.00 36.90 36.90 36.90 L-11
Mazdoor day 0.050 0.050 0.050 511.52 25.58 25.58 25.58 L-13
b) Material
Brick 2nd class including carriage each 50.000 50.000 50.000 3.50 175.00 175.00 175.00 M-079
c) Overhead charges @ 8% on @ 10% on @ 12% on
19.20 23.99 28.79
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
25.91 26.39 26.87
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 metre = a+b+c+d 285.05 290.33 295.61
Rate per metre = (a+b+c+d)/10 28.51 29.03 29.56
Say 29.00 29.00 30.00
11.16 New Making Tree Guard 53 cm dia and 1.3 m High as
per Design from Empty Bitumen Drums
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Making tree guard 53 cm dia and 1.3 m high as per
design from empty bitumen drum, slit suitably to
permit sun and air, (supplied by the department at
stock issue rate) including providing and fixing 2
nos MS sheet rings 50 x 0.5 mm with rivets,
complete in all respect
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.009 0.009 0.009 617.00 5.43 5.43 5.43 L-12
Blacksmith day 0.150 0.150 0.150 738.00 110.70 110.70 110.70 L-02
Mazdoor day 0.070 0.070 0.070 511.52 35.81 35.81 35.81 L-13
b) Material
Empty bitumen drum each 1.000 1.000 1.000 252.00 252.00 252.00 252.00 M-173
MS sheet 50 x 0.5 mm M-181 /
kg 0.650 0.650 0.650 63.81 41.47 41.47 41.47 1000
Rivets 6 mm dia and 10 mm in length each 22.000 22.000 22.000 6.00 132.00 132.00 132.00 M-159
d) Overhead charges @ 8% on @ 10% on @ 12% on
46.19 57.74 69.29
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
62.36 63.52 64.67
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate for each tree guard = a+b+c+d 685.96 698.67 711.37
Say 686.00 699.00 711.00
11.17 New Making Tree Guard 53 cm dia and 2 Metre High as
per Design from Empty Bitumen Drums
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.016 0.016 0.016 617.00 9.87 9.87 9.87 L-12
Blacksmith day 0.200 0.200 0.200 738.00 147.60 147.60 147.60 L-02
Mazdoor day 0.200 0.200 0.200 511.52 102.30 102.30 102.30 L-13
b) Material
Empty bitumen drum each 1.500 1.500 1.500 252.00 378.00 378.00 378.00 M-173
MS sheet50 x 0.5 mm M-181 /
kg 0.650 0.650 0.650 63.81 41.47 41.47 41.47 1000
Rivets 6 mm dia and 10 mm in length each 50.000 50.000 50.000 6.00 300.00 300.00 300.00 M-159
MS plate30 x 3 mm M-181 /
kg 1.300 1.300 1.300 63.81 82.95 82.95 82.95 1000
c) Overhead charges @ 8% on @ 10% on @ 12% on
84.98 106.22 127.46
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
114.72 116.84 118.97
(a+b+c) (a+b+c) (a+b+c)
Rate for each tree guard = a+b+c+d 1,261.89 1,285.26 1,308.63
Say 1,262.00 1,285.00 1,309.00
11.18 New Wrought Iron and Mild Steel Welded Work
Wrought iron and mild steel welded work (using
angles, square bars, tees and channel grills,
grating frames, gates and tree guards of any size
and design etc. including cost of screens and
welding rods or bolts and nuts complete fixed in
position but without the cost of excavation and
concrete for fixing which will be paid separately
Unit = quintal
Taking output = one quintal
a) Labour
Mate day 0.180 0.180 0.180 617.00 111.06 111.06 111.06 L-12
Blacksmith/ welder for cutting to design and shape L-02
and jointing day 2.000 2.000 2.000 738.00 1,476.00 1,476.00 1,476.00
Mazdoor for fixing and helper for Blacksmith/welder L-13
day 2.500 2.500 2.500 511.52 1,278.80 1,278.80 1,278.80
b) Material
Angle, tees, channels etc quintal 1.050 1.050 1.050 6,380.65 6,699.69 6,699.69 6,699.69 M-181 / 10
Deduct the cost of scrap M-181 / 10/3
quintal 0.050 0.050 0.050 -2,126.88 -106.34 -106.34 -106.34
Add 5 per cent of cost of material for welding rods
and other welding accessories 334.98 334.98 334.98
c) Overhead charges @ 8% on @ 10% on @ 12% on
783.53 979.42 1,175.30
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,057.77 1,077.36 1,096.95
(a+b+c) (a+b+c) (a+b+c)
Rate per quintal = a+b+c+d 11,635.49 11,850.97 12,066.44
Say 11,635.00 11,851.00 12,066.00
11.19 New Tree Guard with MS Iron
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Providing and fixing MS iron tree guard 60 cm dia
and 2 metre high above ground level formed of 4
Nos (25 x 6 mm) and 8 Nos (25 x 3 mm) vertical
MS riveted to 3 Nos (25 x 6 mm) iron rings in two
halves, bolted together with 8 mm dia and 30 mm
long bolts including painting two coats with paint of
approved brand over a coat of priming, complete in
all respects.
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.020 0.020 0.020 617.00 12.34 12.34 12.34 L-12
Blacksmith day 0.250 0.250 0.250 738.00 184.50 184.50 184.50 L-02
Mazdoor day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
b) Material
MS iron 25 x 6 mm M-181 /1000
kg 19.200 19.200 19.200 63.81 1,225.09 1,225.09 1,225.09
MS iron 25 x 3 mm M-181 /
kg 9.600 9.600 9.600 63.81 612.54 612.54 612.54 1000
Add 5 per cent of cost of material for riveting,
bolting and welding accessories 91.88 91.88 91.88
c) Machinery
Tractor-trolley hour 0.040 0.040 0.040 1,876.50 75.06 75.06 75.06 P&M-026
d) Painting
Painting two coats including priming sqm 1.770 93.00 164.61
Item No. -
sqm 1.770 95.00 168.15
8.09
sqm 1.770 97.00 171.69
e) Overhead charges @ 8% on @ 10% on @ 12% on
186.34 232.93 279.51
(a+b+c) (a+b+c) (a+b+c)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
251.56 256.22 260.88
(a+b+c+e) (a+b+c+e) (a+b+c+e)
Rate per tree guard =a+b+c+d+e+f 2,931.81 2,986.59 3,041.38
Say 2,932.00 2,987.00 3,041.00
Note 1 The items of excavation and concreting to be
measured and paid separately as per design .
Unit = Each
Taking output = one
a) Labour
Mate day 0.030 0.030 0.030 617.00 18.51 18.51 18.51 L-12
Blacksmith day 0.250 0.250 0.250 738.00 184.50 184.50 184.50 L-02
Welder day 0.250 0.250 0.250 738.00 184.50 184.50 184.50 L-02
Mazdoor day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
b) Material
MS angle 30 x 30 x 3 mm M-181 /
kg 13.500 13.500 13.500 63.81 861.39 861.39 861.39 1000
MS iron 25 x 3 mm M-181 /
kg 18.000 18.000 18.000 63.81 1,148.52 1,148.52 1,148.52 1000
Steel wire 3 mm dia kg 6.000 6.000 6.000 66.72 400.32 400.32 400.32 M-194
Add 5 per cent of cost of material for riveting,
bolting and welding accessories 120.51 120.51 120.51
c) Machinery
Tractor-trolley hour 0.040 0.040 0.040 1,876.50 75.06 75.06 75.06 P&M-026
d) Painting
Painting two coats including priming sqm 1.500 93.00 139.50
Item No. -
sqm 1.500 95.00 142.50
8.09
sqm 1.500 97.00 145.50
e) Overhead charges @ 8% on @ 10% on @ 12% on
249.69 312.12 374.54
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit
@ 10% on @ 10% on @ 10% on
337.09 343.33 349.57
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Unit = Hectare
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Taking output = one hectare
a) Labour
i) Planting
Mate day 1.000 1.000 1.000 617.00 617.00 617.00 617.00 L-12
Mazdoor day 25.000 25.000 25.000 511.52 12,788.00 12,788.00 12,788.00 L-13
ii) For Maintenance for one year
Mate day 5.000 5.000 5.000 617.00 3,085.00 3,085.00 3,085.00 L-12
Mazdoor day 50.000 50.000 50.000 511.52 25,576.00 25,576.00 25,576.00 L-13
b) Machinery
Dozer 80 HP @ 1000 sqm/hour hour 10.000 10.000 10.000 3,502.80 35,028.00 35,028.00 35,028.00 P&M-003
Water tanker6 KL capacity (for planting) hour 3.000 3.000 3.000 1,005.00 3,015.00 3,015.00 3,015.00 P&M-025
Water tanker6 KL capacity (for maintenance) hour 25.000 25.000 25.000 1,005.00 25,125.00 25,125.00 25,125.00 P&M-025
c) Material
Sapling 1 to 1.5 m high 2 cm dia stem M-161 x 0.8
each 290.000 290.000 290.000 240.00 69,600.00 69,600.00 69,600.00
Add 10 per cent of sapling M-161 x 0.8
each 29.000 29.000 29.000 240.00 6,960.00 6,960.00 6,960.00
Decayed farm yard/sludge manure (planting) cum 60.900 60.900 60.900 300.00 18,270.00 18,270.00 18,270.00 M-168
Decayed farm yard/sludge manure (maintenance) M-168
cum 4.000 4.000 4.000 300.00 1,200.00 1,200.00 1,200.00
Pesticides for planting kg 0.500 0.500 0.500 222.40 111.20 111.20 111.20 M-135
Pesticides for maintenance kg 1.500 1.500 1.500 222.40 333.60 333.60 333.60 M-135
Cost of water KL 18.000 18.000 18.000 16.00 288.00 288.00 288.00 M-191
d) Overhead charges @ 8% on @ 10% on @ 12% on
16,159.74 20,199.68 24,239.62
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
21,815.65 22,219.65 22,623.64
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per hectare = a+b+c+d+e 239,972.20 244,416.13 248,860.06
Say 239,972.00 244,416.00 248,860.00
Note Cost of fencing to be provided as per size of plot
and approved design, measured and paid
separately
11.22 New Rain Water Harvesting Constructing rain water
harvesting
Unit = Number
Taking output = 10 Number
a) Material
cum 230.213 152.00 34,992.38 Item No.-
Excavation 12.01 (Rate taken from Item No.-12.01
cum 230.213 158.00 36,373.65 12.01 (I)
(I) B (iii) )
cum 230.213 194.00 44,661.32 B(iii)
cum 61.819 6,061.00 374,684.96
Brick Wall (2.5 meter) (Rate taken from Item No. - Item No.-
cum 61.819 6,098.00 376,972.26
12.05) 12.05
cum 61.819 6,249.00 386,306.93
cum 98.910 5,030.63 497,579.61
Brick Wall (Without Mortar -4 meter) (Rate taken Item No.-
cum 98.910 5,061.34 500,617.14
from Item No.-12.05 x 83%) 12.05
cum 98.910 5,186.67 513,013.53
cum 5.193 8,966.00 46,560.44
RCC M20 for Slab (Rate taken from Item No.12.08 Item No.-
cum 5.193 9,014.00 46,809.70
C, Case-II) 12.08C(ii)
cum 5.193 9,178.00 47,661.35
MT 0.415 68,094.00 28,259.01
Item No.-
Reinforcement (Rate taken from Item No.-12.42) MT 0.415 68,191.00 28,299.27
12.42
MT 0.415 68,383.00 28,378.95
b) Filter Material (Size from 75- 100 mm) cum 225.020 225.020 225.020 1,215.07 273,415.64 273,415.64 273,415.64 M-011
c) Add 1 per cent of the cost of (a+b) for other
miscelleneus (i.e Pipe etc) activities required to 12,554.92 12,624.88 12,934.38
complete the item in all respect.
@ 10% on @ 12% on
d) Overhead charges @ 8% on (b) 21,873.25 27,341.56 32,809.88
(b) (b)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 29,528.89 30,075.72 30,622.55
(b+d) (b+d) (b+d)
Cost for 10 Nos. = a+b+c+d+e 1,319,449.09 1,332,529.82 1,369,804.52
Rate per No. = (a+b+c+d+e)/10 131,944.91 133,252.98 136,980.45
Say 131,945.00 133,253.00 136,980.00
CHAPTER-12
FOUNDATIONS
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
12.01 304 Excavation for Structures
Earth work in excavation of foundation of structures
as per drawing and technical specification,
including setting out, construction of shoring and
bracing, removal of stumps and other deleterious
matter, dressing of sides and bottom and
backfilling with approved material.
I Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means
(i) Depth upto 3 m
a) Labour
Mate day 0.140 0.140 0.140 617.00 86.38 86.38 86.38 L-12
Mazdoor day 3.500 3.500 3.500 511.52 1,790.32 1,790.32 1,790.32 L-13
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 187.670 187.670 187.670
b) Overhead charges @ 20% on (a) @ 20% on (a) @ 20% on (a) 375.34 375.34 375.34
c) Contractor's profit @ 10% on @ 10% on @ 10% on
225.20 225.20 225.20
(a+b) (a+b) (a+b)
Cost for 10 cum = a+b+c 2,477.24 2,477.24 2,477.24
Rate per cum = (a+b+c)/10 247.72 247.72 247.72
Say 248.00 248.00 248.00
Note 1. Cost of dewatering may be added where
required upto, 10 per cent of labour cost
Assessment for dewatering shall be made as per
site conditions.
2.The excavated earth can be used partially for
backfilling of foundation pit and partly for road work
except for marshy soil. Hence cost of disposal has
not been added except for marshy soil. This
remark is common to all cases of item 12.1
excluding marshy soil.
a) Labour
Mate/Supervisor day 0.180 0.180 0.180 617.00 111.06 111.06 111.06 L-12
Mazdoor day 4.500 4.500 4.500 511.52 2,301.84 2,301.84 2,301.84 L-13
b) Overhead charges @ 20% on (a) @ 20% on (a) @ 20% on (a) 482.58 482.58 482.58
c) Contractor's profit @ 10% on @ 10% on @ 10% on
289.55 289.55 289.55
(a+b) (a+b) (a+b)
Cost for 10 cum = a+b+c 3,185.03 3,185.03 3,185.03
Rate per cum = (a+b+c)/10 318.50 318.50 318.50
Say 319.00 319.00 319.00
Note Cost of dewatering may be added where required
upto 15 per cent of labour cost. Assessment for
dewatering shall be done as per actual ground
conditions.
12.01 (I) A (iii) Depth above 6 m
a) Labour
Mate/Supervisor day 0.240 0.240 0.240 617.00 148.08 148.08 148.08 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
b) Overhead charges @ 20% on (a) @ 20% on (a) @ 20% on (a) 643.44 643.44 643.44
c) Contractor's profit @ 10% on @ 10% on @ 10% on
386.06 386.06 386.06
(a+b) (a+b) (a+b)
Cost for 10 cum = a+b+c 4,246.70 4,246.70 4,246.70
Rate per cum = (a+b+c)/10 424.67 424.67 424.67
Say 425.00 425.00 425.00
Note 1. Cost of dewatering may be added where
required upto 20 per cent of labour cost.
Assessment for dewatering shall be made as per
site conditions..
12.01 (I) B Mechanical Means
Depth upto 3 m
Unit = cum
Taking output = 330 cum
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Hydraulic Excavator
For excavation
(i) 1.2 cum bucket capacity hour 4.627 3,420.00 15,824.29 P&M-007
(ii) 1.1 cum bucket capacity hour 5.329 3,074.00 16,380.39 P&M-008
(iii) 0.9 cum bucket capacity hour 7.450 2,782.00 20,725.16 P&M-009
For backfilling (considering 60% of the excavated
material)
(i) 1.2 cum bucket capacity hour 2.776 3,420.00 9,494.57 P&M-007
(ii) 1.1 cum bucket capacity hour 3.197 3,074.00 9,828.23 P&M-008
(iii) 0.9 cum bucket capacity hour 4.470 2,782.00 12,435.10 P&M-009
Tipper for transportation of excess material to
dumping yard considering lead @ 1 km
(i) 18 cum capacity t-km 198.000 6.18 1,223.34 P&M-116
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
(ii) 14 cum capacity t-km 198.000 7.01 1,388.53 P&M-119
(iii) 10 cum capacity t-km 198.000 8.66 1,715.47 P&M-122
c) Overhead charges @ 20% on @ 20% on @ 20% on
6,166.36 6,377.35 7,833.07
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
3,699.82 3,826.41 4,699.84
(a+b+c) (a+b+c) (a+b+c)
Cost for 330 cum = a+b+c+d 40,697.98 42,090.51 51,698.24
Rate per cum = (a+b+c+d)/330 123.33 127.55 156.66
Say 123.00 128.00 157.00
Note Cost of dewatering upto 5 per cent of (a+b) may
be added, where required. Assessment for
dewatering shall be made as per site conditions..
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Hydraulic Excavator
For excavation
(i) 1.2 cum bucket capacity hour 4.674 3,420.00 15,984.13 P&M-007
(ii) 1.1 cum bucket capacity hour 5.383 3,074.00 16,545.84 P&M-008
(iii) 0.9 cum bucket capacity hour 7.525 2,782.00 20,934.51 P&M-009
For backfilling (considering 60% of the excavated
material)
(i) 1.2 cum bucket capacity hour 2.804 3,420.00 9,590.48 P&M-007
(ii) 1.1 cum bucket capacity hour 3.230 3,074.00 9,927.51 P&M-008
(iii) 0.9 cum bucket capacity hour 4.515 2,782.00 12,560.71 P&M-009
Tipper for transportation of excess material to
dumping yard considering lead @ 1 km
(i) 18 cum capacity t-km 180.000 6.18 1,112.13 P&M-116
(ii) 14 cum capacity t-km 180.000 7.01 1,262.30 P&M-119
(iii) 10 cum capacity t-km 180.000 8.66 1,559.52 P&M-122
Unit = cum
Taking output = 270 cum
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
b) Machinery
Hydraulic Excavator
For excavation
(i) 1.2 cum bucket capacity hour 4.732 3,420.00 16,183.93 P&M-007
(ii) 1.1 cum bucket capacity hour 5.450 3,074.00 16,752.67 P&M-008
(iii) 0.9 cum bucket capacity hour 7.619 2,782.00 21,196.19 P&M-009
For backfilling (considering 60% of the excavated
material)
(i) 1.2 cum bucket capacity hour 2.839 3,420.00 9,710.36 P&M-007
(ii) 1.1 cum bucket capacity hour 3.270 3,074.00 10,051.60 P&M-008
(iii) 0.9 cum bucket capacity hour 4.571 2,782.00 12,717.71 P&M-009
Tipper for transportation of excess material to
dumping yard considering lead @ 1 km
(i) 18 cum capacity t-km 162.000 6.18 1,000.92 P&M-116
(ii) 14 cum capacity t-km 162.000 7.01 1,136.07 P&M-119
(iii) 10 cum capacity t-km 162.000 8.66 1,403.57 P&M-122
c) Overhead charges @ 20% on @ 20% on @ 20% on
6,236.96 6,445.99 7,921.41
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
3,742.18 3,867.59 4,752.85
(a+b+c) (a+b+c) (a+b+c)
Cost for 270 cum = a+b+c+d 41,163.94 42,543.52 52,281.34
Rate per cum = (a+b+c+d)/270 152.46 157.57 193.63
Say 152.00 158.00 194.00
Note 1. Cost of dewatering upto 10 per cent of (a+b)
may be added, where required. Assessment for
dewatering shall be made as per site conditions..
A Manual Means
Unit = cum
Taking output = 120 cum
a) Labour
Mate day 0.210 0.210 0.210 617.00 129.57 129.57 129.57 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Driller day 2.000 2.000 2.000 558.00 1,116.00 1,116.00 1,116.00 L-06
Blaster day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-03
b) Machinery
Air compressor hour 6.000 6.000 6.000 614.25 3,685.50 3,685.50 3,685.50 P&M-029
Jack Hammer for drilling holes (@ 4.5 m per hour)
hour 24.000 24.000 24.000 11.55 277.20 277.20 277.20 P&M-078
Jack Hammer (consider 5% of the volume for
dressing) hour 1.024 1.205 1.280 206.00 210.94 248.17 263.68 P&M-010
Hydraulic Excavator
Excavator for excavation
(i) 1.2 cum bucket capacity hour 1.024 3,420.00 3,502.08 P&M-007
(ii) 1.1 cum bucket capacity hour 1.205 3,074.00 3,703.27 P&M-008
(iii) 0.9 cum bucket capacity hour 1.280 2,782.00 3,560.96 P&M-009
For loading
(i) 1.2 cum bucket capacity hour 2.094 3,420.00 7,160.89 P&M-007
(ii) 1.1 cum bucket capacity hour 2.411 3,074.00 7,412.54 P&M-008
(iii) 0.9 cum bucket capacity hour 3.371 2,782.00 9,378.66 P&M-009
Tipper
For transportation considering lead @ 1 km
(i) 18 cum capacity t-km 180.000 6.18 1,112.13 P&M-116
(ii) 14 cum capacity t-km 180.000 7.01 1,262.30 P&M-119
(iii) 10 cum capacity t-km 180.000 8.66 1,559.52 P&M-122
For loading & unloading time
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
(i) 18 cum capacity hour 2.094 2,883.30 6,037.13 P&M-014
(ii) 14 cum capacity hour 2.411 2,556.75 6,165.26 P&M-015
(iii) 10 cum capacity hour 3.371 2,274.30 7,667.11 P&M-016
c) Materials
Small dia.Explosive at 0.40 kg / cum for 120 cum M-215
( 120 x 0.40 )
Explosive at 0.20 kg / cum for secondary blast @ kg 49.200 49.200 49.200 81.90 4,029.48 4,029.48 4,029.48
5%of the total volume ( 120 x 0.2x5% )
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mason day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-10
Mazdoor day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
b) Material
Plain cement concrete 1:3:6 nominal mix using
batching plant (Rate as sub-analysis) Sub-Analysis
cum 15.000 15.000 15.000 4,238.00 63,570.00 63,570.00 63,570.00 of Concrete -
20.02
(i) 16 KL capacity
hour 0.023xL1+0.135 1,501.00 1,238.33 P&M-023
(ii) 12 KL capacity hour 0.03xL1+0.18 1,327.00 1,433.16 P&M-024
(iii) 6 KL capacity hour 0.06xL1+0.36 1,005.00 2,170.80 P&M-025
d) Overhead charges @ 20% on @ 20% on @ 20% on
13,982.94 14,021.91 14,169.43
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
8,389.76 8,413.14 8,501.66
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 15 cum = a+b+c+d+e 92,287.40 92,544.58 93,518.26
Rate per cum = (a+b+c+d+e)/15 6,152.49 6,169.64 6,234.55
Say 6,152.00 6,170.00 6,235.00
Note Vibrator is a part of minor T & P which is already
included in overhead charges of the contractor.
Water for curing KL 2.415 2.415 2.415 16.00 38.64 38.64 38.64 M-191
b) Labour
Mate day 0.480 0.480 0.480 617.00 296.16 296.16 296.16 L-12
Mason day 4.000 4.000 4.000 679.00 2,716.00 2,716.00 2,716.00 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Water tanker (speed @ 20km/hr and return speed
@ 30 km/hr and spreading @ 30 mins per trip )
(i) 16 KL capacity
hour 0.017xL1+0.101 1,501.00 917.11 P&M-023
(ii) 12 KL capacity
hour 0.022xL1+0.134 1,327.00 1,053.64 P&M-024
(iii) 6 KL capacity
hour 0.045xL1+0.268 1,005.00 1,626.09 P&M-025
c) Overhead charges @ 20% on @ 20% on @ 20% on
4,592.01 4,619.32 4,733.81
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
2,755.21 2,771.59 2,840.29
(a+b+c) (a+b+c) (a+b+c)
Cost for 5 cum = a+b+c+d 30,307.29 30,487.51 31,243.15
Rate per cum (a+b+c+d)/5 6,061.46 6,097.50 6,248.63
Say 6,061.00 6,098.00 6,249.00
Unit = 1 cum
Taking output = 1 cum
Cement mortar 1:3 (Rate as sub-analysis) Sub-Analysis
of Concrete -
Cum 1.000 1.000 1.000 5,125.00 5,125.00 5,125.00 5,125.00 20.01 (A)
a) Material
Stone cum 5.500 5.500 5.500 933.45 5,133.98 5,133.98 5,133.98 M-170
Through and bond stone each 35.000 35.000 35.000 59.77 2,091.95 2,091.95 2,091.95 M-184
(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as sub-analysis)
Sub-Analysis
cum 1.500 1.500 1.500 5,125.00 7,687.50 7,687.50 7,687.50 of Concrete -
20.01 (A)
b) Labour
Mate day 0.660 0.660 0.660 617.00 407.22 407.22 407.22 L-12
Mason day 7.500 7.500 7.500 679.00 5,092.50 5,092.50 5,092.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Overhead charges @ 20% on @ 20% on @ 20% on
5,003.37 5,003.37 5,003.37
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
3,002.02 3,002.02 3,002.02
(a+b+c) (a+b+c) (a+b+c)
Cost for 5 cum = a+b+c+d 33,022.21 33,022.21 33,022.21
Rate per cum (a+b+c+d)/5 6,604.44 6,604.44 6,604.44
Say 6,604.00 6,604.00 6,604.00
(B) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.500 5.500 5.500 611.60 3,363.80 3,363.80 3,363.80 M-147
Through and bond stone each 35.000 35.000 35.000 59.77 2,091.95 2,091.95 2,091.95 M-184
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in sub-analysis)
Sub-Analysis
cum 1.550 1.550 1.550 5,125.00 7,943.75 7,943.75 7,943.75 of Concrete -
20.01 (A)
b) Labour
Mate day 0.600 0.600 0.600 617.00 370.20 370.20 370.20 L-12
Mason day 6.000 6.000 6.000 679.00 4,074.00 4,074.00 4,074.00 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Overhead charges @ 20% on @ 20% on @ 20% on
4,489.48 4,489.48 4,489.48
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
2,693.69 2,693.69 2,693.69
(a+b+c) (a+b+c) (a+b+c)
Cost for 5 cum = a+b+c+d 29,630.54 29,630.54 29,630.54
Rate per cum (a+b+c+d)/5 5,926.11 5,926.11 5,926.11
Say 5,926.00 5,926.00 5,926.00
Note The labour already considered in cement mortar
has been taken into account while proposing
labour for masonry works.
12.08 1500, Plain/Reinforced Cement Concrete in Open
1700 & Foundation complete as per Drawing and
2100 Technical Specifications.
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
A PCC Grade M15
Case I PCC Grade M15 using batching plant & Concrete
pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,176.00 125,280.00 125,280.00 125,280.00 of Concrete -
20.03
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity
hour 0.109xL1+0.656 1,501.00 5,892.93 P&M-023
(ii) 12 KL capacity
hour 0.146xL1+0.875 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity hour 0.292xL1+1.75 1,005.00 10,562.55 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 5594.000 5630.000 5749.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 6,711.82 6,755.03 6,898.60
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity
hour 0.055xL1+0.328 1,501.00 2,968.98 P&M-023
(ii) 12 KL capacity
hour 0.073xL1+0.438 1,327.00 3,487.36 P&M-024
(iii) 6 KL capacity
hour 0.146xL1+0.875 1,005.00 5,281.28 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 5879.000 5914.000 6033.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 3,527.16 3,547.89 3,619.65
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity
hour 0.109xL1+0.656 1,501.00 5,892.93 P&M-023
(ii) 12 KL capacity
hour 0.146xL1+0.875 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity
hour 0.292xL1+1.750 1,005.00 10,562.55 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 5936.000 5972.000 6091.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 7,122.22 7,165.43 7,309.00
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity
hour 0.055xL1+0.328 1,501.00 2,968.98 P&M-023
(ii) 12 KL capacity
hour 0.073xL1+0.438 1,327.00 3,487.36 P&M-024
(iii) 6 KL capacity
hour 0.146xL1+0.875 1,005.00 5,281.28 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6221.000 6256.000 6375.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 3,732.36 3,753.09 3,824.85
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity
hour 0.109xL1+0.656 1,501.00 5,892.93 P&M-023
(ii) 12 KL capacity
hour 0.146xL1+0.875 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity hour 0.292xL1+1.75 1,005.00 10,562.55 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6229.000 6265.000 6384.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 7,473.66 7,516.88 7,660.45
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.420 0.420 0.420 617.00 259.14 259.14 259.14 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity
hour 0.055xL1+0.328 1,501.00 2,968.98 P&M-023
(ii) 12 KL capacity
hour 0.073xL1+0.438 1,327.00 3,487.36 P&M-024
(iii) 6 KL capacity
hour 0.146xL1+0.875 1,005.00 5,281.28 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6532.000 6566.000 6686.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 3,918.80 3,939.54 4,011.30
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity
hour 0.109xL1+0.656 1,501.00 5,892.93 P&M-023
(ii) 12 KL capacity
hour 0.146xL1+0.875 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity hour 0.292xL1+1.75 1,005.00 10,562.55 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6211.000 6247.000 6366.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 7,452.22 7,495.43 7,639.00
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity
hour 0.055xL1+0.328 1,501.00 2,968.98 P&M-023
(ii) 12 KL capacity
hour 0.073xL1+0.438 1,327.00 3,487.36 P&M-024
(iii) 6 KL capacity
hour 0.146xL1+0.875 1,005.00 5,281.28 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6496.000 6531.000 6650.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 3,897.36 3,918.09 3,989.85
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity
hour 0.109xL1+0.656 1,501.00 5,892.93 P&M-023
(ii) 12 KL capacity
hour 0.146xL1+0.875 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity hour 0.292xL1+1.75 1,005.00 10,562.55 P&M-025
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6381.000 6417.000 6536.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 7,656.06 7,699.28 7,842.85
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.420 0.420 0.420 617.00 259.14 259.14 259.14 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity
hour 0.055xL1+0.328 1,501.00 2,968.98 P&M-023
(ii) 12 KL capacity
hour 0.073xL1+0.438 1,327.00 3,487.36 P&M-024
(iii) 6 KL capacity
hour 0.146xL1+0.875 1,005.00 5,281.28 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6684.000 6718.000 6838.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 4,010.00 4,030.74 4,102.50
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity
hour 0.109xL1+0.656 1,501.00 5,892.93 P&M-023
(ii) 12 KL capacity
hour 0.146xL1+0.875 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity hour 0.292xL1+1.75 1,005.00 10,562.55 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6237.000 6273.000 6392.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 7,483.42 7,526.63 7,670.20
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity
hour 0.055xL1+0.328 1,501.00 2,968.98 P&M-023
(ii) 12 KL capacity
hour 0.073xL1+0.438 1,327.00 3,487.36 P&M-024
(iii) 6 KL capacity
hour 0.146xL1+0.875 1,005.00 5,281.28 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6522.000 6557.000 6676.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 3,912.96 3,933.69 4,005.45
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity
hour 0.109xL1+0.656 1,501.00 5,892.93 P&M-023
(ii) 12 KL capacity
hour 0.146xL1+0.875 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity hour 0.292xL1+1.75 1,005.00 10,562.55 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6468.000 6504.000 6623.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 7,760.46 7,803.68 7,947.25
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.420 0.420 0.420 617.00 259.14 259.14 259.14 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity
hour 0.055xL1+0.328 1,501.00 2,968.98 P&M-023
(ii) 12 KL capacity
hour 0.073xL1+0.438 1,327.00 3,487.36 P&M-024
(iii) 6 KL capacity
hour 0.146xL1+0.875 1,005.00 5,281.28 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6771.000 6805.000 6925.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 4,062.20 4,082.94 4,154.70
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity
hour 0.109xL1+0.656 1,501.00 5,892.93 P&M-023
(ii) 12 KL capacity
hour 0.146xL1+0.875 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity hour 0.292xL1+1.75 1,005.00 10,562.55 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6622.000 6658.000 6777.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 7,945.26 7,988.48 8,132.05
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
For pouring and placing
Mate day 0.420 0.420 0.420 617.00 259.14 259.14 259.14 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity
hour 0.055xL1+0.328 1,501.00 2,968.98 P&M-023
(ii) 12 KL capacity
hour 0.073xL1+0.438 1,327.00 3,487.36 P&M-024
(iii) 6 KL capacity
hour 0.146xL1+0.875 1,005.00 5,281.28 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6925.000 6959.000 7079.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 4,154.60 4,175.34 4,247.10
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity
hour 0.109xL1+0.656 1,501.00 5,892.93 P&M-023
(ii) 12 KL capacity
hour 0.146xL1+0.875 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity hour 0.292xL1+1.75 1,005.00 10,562.55 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6955.000 6991.000 7110.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 8,344.86 8,388.08 8,531.65
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.420 0.420 0.420 617.00 259.14 259.14 259.14 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity
hour 0.055xL1+0.328 1,501.00 2,968.98 P&M-023
(ii) 12 KL capacity
hour 0.073xL1+0.438 1,327.00 3,487.36 P&M-024
(iii) 6 KL capacity
hour 0.146xL1+0.875 1,005.00 5,281.28 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 7258.000 7292.000 7412.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 4,354.40 4,375.14 4,446.90
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity
hour 0.109xL1+0.656 1,501.00 5,892.93 P&M-023
(ii) 12 KL capacity
hour 0.146xL1+0.875 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity hour 0.292xL1+1.75 1,005.00 10,562.55 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 7099.000 7135.000 7254.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 8,517.66 8,560.88 8,704.45
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.420 0.420 0.420 617.00 259.14 259.14 259.14 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity
hour 0.055xL1+0.328 1,501.00 2,968.98 P&M-023
(ii) 12 KL capacity
hour 0.073xL1+0.438 1,327.00 3,487.36 P&M-024
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
(iii) 6 KL capacity
hour 0.146xL1+0.875 1,005.00 5,281.28 P&M-025
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 7402.000 7436.000 7556.000
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 4,440.80 4,461.54 4,533.30
b) Labour
For pouring and placing
Mate day 0.133 0.133 0.133 617.00 82.06 82.06 82.06 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 20 per cent on cost of concrete
i.e. cost of material, labour and machinery 34,520.77 34,520.77 34,520.77
b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 20 per cent on cost of concrete
i.e. cost of material, labour and machinery 18,029.22 18,029.22 18,029.22
b) Labour
For pouring and placing
Mate day 0.133 0.133 0.133 617.00 82.06 82.06 82.06 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 20 per cent on cost of concrete
i.e. cost of material, labour and machinery 36,992.77 36,992.77 36,992.77
b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 20 per cent on cost of concrete
i.e. cost of material, labour and machinery 19,265.22 19,265.22 19,265.22
b) Labour
For pouring and placing
Mate day 0.133 0.133 0.133 617.00 82.06 82.06 82.06 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 20 per cent on cost of concrete
i.e. cost of material, labour and machinery 37,514.77 37,514.77 37,514.77
b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 20 per cent on cost of concrete
i.e. cost of material, labour and machinery 19,526.22 19,526.22 19,526.22
b) Labour
For pouring and placing
Mate day 0.133 0.133 0.133 617.00 82.06 82.06 82.06 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 20 per cent on cost of concrete
i.e. cost of material, labour and machinery 38,438.77 38,438.77 38,438.77
b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 20 per cent on cost of concrete
i.e. cost of material, labour and machinery 19,988.22 19,988.22 19,988.22
b) Labour
For pouring and placing
Mate day 0.133 0.133 0.133 617.00 82.06 82.06 82.06 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 20 per cent on cost of concrete
i.e. cost of material, labour and machinery 40,436.77 40,436.77 40,436.77
b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 20 per cent on cost of concrete
i.e. cost of material, labour and machinery 20,987.22 20,987.22 20,987.22
b) Labour
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
For pouring and placing
Mate day 0.093 0.093 0.093 617.00 57.38 57.38 57.38 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 16,135.76 16,135.76 16,135.76
b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 8,479.11 8,479.11 8,479.11
b) Labour
For pouring and placing
Mate day 0.093 0.093 0.093 617.00 57.38 57.38 57.38 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 17,161.76 17,161.76 17,161.76
b) Labour
For pouring and placing
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 8,992.11 8,992.11 8,992.11
b) Labour
For pouring and placing
Mate day 0.133 0.133 0.133 617.00 82.06 82.06 82.06 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 17,260.38 17,260.38 17,260.38
b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 9,014.61 9,014.61 9,014.61
b) Labour
For pouring and placing
Mate day 0.093 0.093 0.093 617.00 57.38 57.38 57.38 L-12
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 17,986.76 17,986.76 17,986.76
b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 9,404.61 9,404.61 9,404.61
b) Labour
For pouring and placing
Mate day 0.133 0.133 0.133 617.00 82.06 82.06 82.06 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 18,496.38 18,496.38 18,496.38
b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 9,632.61 9,632.61 9,632.61
b) Labour
For pouring and placing
Mate day 0.093 0.093 0.093 617.00 57.38 57.38 57.38 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 18,064.76 18,064.76 18,064.76
b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 9,443.61 9,443.61 9,443.61
b) Labour
For pouring and placing
Mate day 0.133 0.133 0.133 617.00 82.06 82.06 82.06 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 18,757.38 18,757.38 18,757.38
b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 9,763.11 9,763.11 9,763.11
b) Labour
For pouring and placing
Mate day 0.133 0.133 0.133 617.00 82.06 82.06 82.06 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 19,219.38 19,219.38 19,219.38
b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 9,994.11 9,994.11 9,994.11
b) Labour
For pouring and placing
Mate day 0.133 0.133 0.133 617.00 82.06 82.06 82.06 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 20,218.38 20,218.38 20,218.38
b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 10,493.61 10,493.61 10,493.61
b) Labour
For pouring and placing
Mate day 0.093 0.093 0.093 617.00 57.38 57.38 57.38 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Hydra Crane for holding tremie pipe hour 0.650 0.650 0.650 1,083.60 704.34 704.34 704.34 P&M-102
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 5745.000 5745.000 5745.000
Add 5 per cent of cost of material and labour
towards cost of forming sump, protective bunds,
chiselling and making arrangements for under 8,616.10 8,616.10 8,616.10
water concreting with tremie pipe..
b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Hydra Crane for holding tremie pipe hour 0.833 0.833 0.833 1,083.60 903.00 903.00 903.00 P&M-102
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6055.000 6055.000 6055.000
Add 5 per cent of cost of material and labour
towards cost of forming sump, protective bunds,
chiselling and making arrangements for under 4,541.20 4,541.20 4,541.20
water concreting with tremie pipe..
b) Labour
For pouring and placing
Mate day 0.093 0.093 0.093 617.00 57.38 57.38 57.38 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Hydra Crane for holding tremie pipe hour 0.650 0.650 0.650 1,083.60 704.34 704.34 704.34 P&M-102
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6020.000 6020.000 6020.000
Add 5 per cent of cost of material and labour
towards cost of forming sump, protective bunds,
chiselling and making arrangements for under 9,028.60 9,028.60 9,028.60
water concreting with tremie pipe..
b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Hydra Crane for holding tremie pipe hour 0.833 0.833 0.833 1,083.60 903.00 903.00 903.00 P&M-102
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6330.000 6330.000 6330.000
Add 5 per cent of cost of material and labour
towards cost of forming sump, protective bunds,
chiselling and making arrangements for under 4,747.45 4,747.45 4,747.45
water concreting with tremie pipe..
b) Labour
For pouring and placing
Mate day 0.093 0.093 0.093 617.00 57.38 57.38 57.38 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Hydra Crane for holding tremie pipe hour 0.650 0.650 0.650 1,083.60 704.34 704.34 704.34 P&M-102
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6046.000 6046.000 6046.000
Add 5 per cent of cost of material and labour
towards cost of forming sump, protective bunds,
chiselling and making arrangements for under 9,067.60 9,067.60 9,067.60
water concreting with tremie pipe..
b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Hydra Crane for holding tremie pipe hour 0.833 0.833 0.833 1,083.60 903.00 903.00 903.00 P&M-102
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6356.000 6356.000 6356.000
Add 5 per cent of cost of material and labour
towards cost of forming sump, protective bunds,
chiselling and making arrangements for under 4,766.95 4,766.95 4,766.95
water concreting with tremie pipe..
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
d) Overhead charges @ 20% on @ 20% on @ 20% on
20,021.21 20,021.21 20,021.21
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
12,012.73 12,012.73 12,012.73
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 15 cum = a+b+c+d+e 132,139.98 132,139.98 132,139.98
Rate per cum = (a+b+c+d+e)/15 8,809.33 8,809.33 8,809.33
Say 8,809.00 8,809.00 8,809.00
12.11 C (iv) PCC Grade M35
Case I PCC Grade M35 using batching plant & Concrete
pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 5,102.00 153,060.00 153,060.00 153,060.00 of Concrete -
20.1
b) Labour
For pouring and placing
Mate day 0.093 0.093 0.093 617.00 57.38 57.38 57.38 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Hydra Crane for holding tremie pipe hour 0.650 0.650 0.650 1,083.60 704.34 704.34 704.34 P&M-102
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6329.000 6329.000 6329.000
Add 5 per cent of cost of material and labour
towards cost of forming sump, protective bunds,
chiselling and making arrangements for under 9,492.10 9,492.10 9,492.10
water concreting with tremie pipe..
b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Hydra Crane for holding tremie pipe hour 0.833 0.833 0.833 1,083.60 903.00 903.00 903.00 P&M-102
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c) 6639.000 6639.000 6639.000
Add 5 per cent of cost of material and labour
towards cost of forming sump, protective bunds,
chiselling and making arrangements for under 4,979.20 4,979.20 4,979.20
water concreting with tremie pipe..
12.11 D Case I PCC Grade M20 using batching plant & Concrete
(i) pump
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 5,745.00 5,745.00 5,745.00
12.11 C (i)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,149.00 1,149.00 1,149.00
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
689.40 689.40 689.40
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 7,583.40 7,583.40 7,583.40
Say 7,583.00 7,583.00 7,583.00
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
12.11 D Case II PCC Grade M20 using batching plant & manual
(i) placing
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 6,055.00 6,055.00 6,055.00
12.11 C (i)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,211.00 1,211.00 1,211.00
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
726.60 726.60 726.60
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 7,992.60 7,992.60 7,992.60
Say 7,993.00 7,993.00 7,993.00
12.11 D (ii) Grade M25 PCC
Same as in bottom plug concrete, excluding cost of
forming sump, protective bunds, chiseling etc.
12.11 D Case I PCC Grade M25 using batching plant & Concrete
(ii) pump
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 6,020.00 6,020.00 6,020.00
12.11 C (ii)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,204.00 1,204.00 1,204.00
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
722.40 722.40 722.40
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 7,946.40 7,946.40 7,946.40
Say 7,946.00 7,946.00 7,946.00
12.11 D Case II PCC Grade M25 using batching plant & manual
(ii) placing
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 6,330.00 6,330.00 6,330.00
12.11 C (ii)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,266.00 1,266.00 1,266.00
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
759.60 759.60 759.60
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 8,355.60 8,355.60 8,355.60
Say 8,356.00 8,356.00 8,356.00
'12.11 D (iii) Grade M30 PCC
12.11 D Case I PCC Grade M30 using batching plant & Concrete
(iii) pump
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 6,046.00 6,046.00 6,046.00
12.11 C (iii)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,209.20 1,209.20 1,209.20
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
725.52 725.52 725.52
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 7,980.72 7,980.72 7,980.72
Say 7,981.00 7,981.00 7,981.00
12.11 D Case II PCC Grade M30 using batching plant & manual
(iii) placing
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 6,356.00 6,356.00 6,356.00
12.11 C (iii)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,271.20 1,271.20 1,271.20
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
762.72 762.72 762.72
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 8,389.92 8,389.92 8,389.92
Say 8,390.00 8,390.00 8,390.00
12.11 E Top plug
(i) Grade M15 PCC
Same as Item 12.8(a) excluding formwork
12.11 E Case I PCC Grade M15 using batching plant & Concrete
(i) pump
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 5,594.00 5,630.00 5,749.00
12.08 (A)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,118.80 1,126.00 1,149.80
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
671.28 675.60 689.88
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 7,384.08 7,431.60 7,588.68
Say 7,384.00 7,432.00 7,589.00
12.11 E Case II PCC Grade M15 using batching plant & manual
(i) placing
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 5,879.00 5,914.00 6,033.00
12.08 (A)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,175.80 1,182.80 1,206.60
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
705.48 709.68 723.96
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 7,760.28 7,806.48 7,963.56
Say 7,760.00 7,806.00 7,964.00
12.11 E (ii) Grade M20 PCC
Same as Item 12.8(b) excluding formwork
12.11 E Case I PCC Grade M20 using batching plant & Concrete
(ii) pump
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 5,936.00 5,972.00 6,091.00
12.08 (B)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,187.20 1,194.40 1,218.20
(a+b+c) (a+b+c) (a+b+c)
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
e) Contractor's profit @ 10% on @ 10% on @ 10% on
712.32 716.64 730.92
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 7,835.52 7,883.04 8,040.12
Say 7,836.00 7,883.00 8,040.00
12.11 E Case II PCC Grade M20 using batching plant & manual
(ii) placing
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 6,221.00 6,256.00 6,375.00
12.08 (B)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,244.20 1,251.20 1,275.00
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
746.52 750.72 765.00
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 8,211.72 8,257.92 8,415.00
Say 8,212.00 8,258.00 8,415.00
12.11 E (iii) Grade M25 PCC
Same as Item 12.8 (d) excluding formwork
12.11 E Case I PCC Grade M25 using batching plant & Concrete
(iii) pump
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 6,211.00 6,247.00 6,366.00
12.08 (D)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,242.20 1,249.40 1,273.20
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
745.32 749.64 763.92
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 8,198.52 8,246.04 8,403.12
Say 8,199.00 8,246.00 8,403.00
12.11 E Case II PCC Grade M25 using batching plant & manual
(iii) placing
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 6,496.00 6,531.00 6,650.00
12.08 (D)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,299.20 1,306.20 1,330.00
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
779.52 783.72 798.00
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 8,574.72 8,620.92 8,778.00
Say 8,575.00 8,621.00 8,778.00
12.11 E (iv) Grade M30 PCC
Same as Item 12.8(f) excluding formwork
12.11 E Case I PCC Grade M30 using batching plant & Concrete
(iv) pump
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 6,237.00 6,273.00 6,273.00
12.08 (F)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,247.40 1,254.60 1,254.60
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
748.44 752.76 752.76
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 8,232.84 8,280.36 8,280.36
Say 8,233.00 8,280.00 8,280.00
12.11 E Case II PCC Grade M30 using batching plant & manual
(iv) placing
Per Cum Basic Cost of Labour, Material & Item No. -
Machinery (a+b+c) 6,522.00 6,557.00 6,676.00
12.08 (F)
d) Overhead charges @ 20% on @ 20% on @ 20% on
1,304.40 1,311.40 1,335.20
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
782.64 786.84 801.12
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum = (a+b+c+d+e) 8,609.04 8,655.24 8,812.32
Say 8,609.00 8,655.00 8,812.00
12.11 F Well cap
(i) RCC Grade M20
Case I RCC Grade M20 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 30.000 30.000 30.000 4,533.00 135,990.00 135,990.00 135,990.00 of Concrete -
20.05
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.152 0.152 617.00 94.40 93.78 93.78 L-12
Mason day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-11
Mazdoor day 2.325 2.300 2.300 511.52 1,189.28 1,176.50 1,176.50 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity
hour 0.109xL1+0.656 1,501.00 5,892.93 P&M-023
(ii) 12 KL capacity
hour 0.146xL1+0.875 1,327.00 6,973.39 P&M-024
(iii) 6 KL capacity hour 0.292xL1+1.75 1,005.00 10,562.55 P&M-025
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 7,945.26 7,988.48 8,132.05
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-11
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Unit - 1 cum
Taking output = 5 cum
a) Material
M35 grade RCC corbel provided for supporting of Cum 8.000 6,622.00 52,976.00
Item No. -
equipment (Dimensions as per ground conditions). Cum 8.000 6,658.00 53,264.00
12.08 H
Rate may be adopted vide Item 12.8 (H) Cum 8.000 6,777.00 54,216.00
HYSD bar reinforcement in corbel tonne 0.480 0.480 0.480 46,496.54 22,318.34 22,318.34 22,318.34 M-083
Blasting material
Explosives Kg 1.500 1.500 1.500 81.90 122.85 122.85 122.85 M-215
Electric detonators each 6.000 6.000 6.000 21.00 126.00 126.00 126.00 M-217
b) Labour
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Mate day 1.880 1.880 1.880 617.00 1,159.96 1,159.96 1,159.96 L-12
Driller day 1.000 1.000 1.000 558.00 558.00 558.00 558.00 L-06
Blaster day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-03
Mazdoor (for cutting, blasting, cleaning, removal of
Material etc.) day 30.000 30.000 30.000 511.52 15,345.60 15,345.60 15,345.60 L-13
Mazdoor (Skilled) (for fixation and removal of
adopter for air lock, carrying out mechanical and
electrical operations and repairs and other skilled day 10.000 10.000 10.000 565.73 5,657.30 5,657.30 5,657.30 L-15
jobs.)
Diver day 4.000 4.000 4.000 738.00 2,952.00 2,952.00 2,952.00 L-07
Medical Officer day 0.500 0.500 0.500 1,077.25 538.63 538.63 538.63 L-16
Para medical personnel day 1.000 1.000 1.000 622.72 622.72 622.72 622.72 L-19
c) Machinery
(i) Induction, deinduction and erection of plant and
equipment including all components and
accessories for pneumatic method of well sinking. hour 6.000 6.000 6.000 10,073.70 60,442.20 60,442.20 60,442.20 P&M-113
Unit = 1 MT
Taking output = 1 MT
a) Material
i) Structural steel including 5 per cent wastage
tonne 1.050 1.050 1.050 63,806.54 66,996.87 66,996.87 66,996.87 M-181
b) Labour
Mate day 0.800 0.800 0.800 617.00 493.60 493.60 493.60 L-12
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Fitter day 4.000 4.000 4.000 738.00 2,952.00 2,952.00 2,952.00 L-08
Blacksmith day 4.000 4.000 4.000 679.00 2,716.00 2,716.00 2,716.00 L-01
Welder day 4.000 4.000 4.000 738.00 2,952.00 2,952.00 2,952.00 L-02
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
Electrodes, cutting gas and other consumables @
5 per cent on cost a (a) above. 3,349.84 3,349.84 3,349.84
c) Machinery
Hydra Crane of capacity 10T for lifting shifting hour 8.000 8.000 8.000 1,240.05 9,920.40 9,920.40 9,920.40 P&M-104
Pile diameter-750 mm
Unit = meter
Taking output = 25 m
a) Materials
RCC Grade M35 (including additional concreteing
of 1m for pile head ) cum 11.486 9,089.00 104,400.33
Item No. -
Rate for concrete may be adopted same as for pile cum 11.486 9,139.00 104,974.65
12.11 F (iv)
vide item no. 12.11 F (iv) cum 11.486 9,303.00 106,858.43
Concrete
Bentonite to be cast with a tremie pipe 200mm dia. kg 574.500 574.500 574.500 4.31 2,476.10 2,476.10 2,476.10 M-071
b) Machinery (for boring and construction)
Hire and running charges of hydraulic piling rig with
power unit and complete accessories including
shifting from one bore location to another. hour 6.000 6.000 6.000 19,747.35 118,484.10 118,484.10 118,484.10 P&M-071
Pile diameter-1000 mm
Unit = meter
Taking output = 25 m
a)
RCC Materials
Grade M35 (including additional concreteing
of 1m for pile head ) cum 20.420 9,089.00 185,600.58
Item No. -
Rate for concrete may be adopted same as for pile cum 20.420 9,139.00 186,621.60
12.11 F (iv)
vide item no. 12.11 F (iv) cum 20.420 9,303.00 189,970.54
Concrete
Bentonite to be cast with a tremie pipe 200mm dia. kg 1021.018 1021.018 1021.018 4.31 4,400.59 4,400.59 4,400.59 M-071
b) Machinery( for boring and construction )
A Pile diameter-1200 mm
Unit = meter
Taking output = 25 m
a)
RCC Materials
Grade M35 (including additional concreteing
of 1m for pile head ) cum 29.405 9,089.00 267,264.84
Item No. -
Rate for concrete may be adopted same as for pile cum 29.405 9,139.00 268,735.10
12.11 F (iv)
vide item no. 12.11 F (iv) cum 29.405 9,303.00 273,557.57
Concrete
Bentonite to be cast with a tremie pipe 200mm dia. kg 1470.265 1470.265 1470.265 4.31 6,336.84 6,336.84 6,336.84 M-071
b) Machinery( for boring and construction )
12.29 1100 & Driven cast-in-place vertical M35 grade R.C.C. Pile
1700 excluding Reinforcement complete as per Drawing
and & Technical Specification
12.30 1100 & Driven precast vertical M35 grade R.C.C. Piles
1700 excluding Reinforcement complete as per Drawing
and & Technical Specification
Pile Diameter = 500 mm
Unit = Running Meter
Taking output = 60 m
a) Materials
RCC Grade M35 cum 11.780 9,089.00 107,068.42
Item No. -
(Rate for concrete may be adopted same as for cum 11.780 9,139.00 107,657.42
12.11 F (iv)
pile vide item no. 12.11 F (iv)) cum 11.780 9,303.00 109,589.34
b ) Material Pile shoes
a) C.I Shoes Kg 240.000 240.000 240.000 69.50 16,680.00 16,680.00 16,680.00 M-080
b) M.S. shoes Kg 105.000 105.000 105.000 50.00 5,250.00 5,250.00 5,250.00 M-124
c) Steel helmet and cushion block on top of pile
head during driving. Kg 30.000 30.000 30.000 135.00 4,050.00 4,050.00 4,050.00 M-174
c) Machinery
Crane20 t capacity hour 6.000 6.000 6.000 1,584.45 9,506.70 9,506.70 9,506.70 P&M-106
Vibrating Pile driving hammer complete with power
unit and accessories. hour 6.000 6.000 6.000 18,571.35 111,428.10 111,428.10 111,428.10 P&M-115
d) Labour
Mate/Supervisor day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Add 1 per cent of (a+b+c) for carriage of piles
from casting yard to work site and stacking, and
other imponderables during installation. 2,555.92 2,561.81 2,581.13
12.31 1100 & Driven precast vertical M35 grade R.C.C. Piles
1700 excluding Reinforcement complete as per Drawing
and & Technical Specification
Pile Diameter = 750 mm
Unit = Running Meter
Taking output = 50 m
a) Materials
RCC Grade M35 cum 22.080 9,089.00 200,685.12
Item No. -
(Rate for concrete may be adopted same as for cum 22.080 9,139.00 201,789.12
12.11 F (iv)
pile vide item no. 12.11 F (iv)) cum 22.080 9,303.00 205,410.24
b ) Material Pile shoes
a) C.I. shoes Kg 160.000 160.000 160.000 69.50 11,120.00 11,120.00 11,120.00 M-080
b) M.S. shoes Kg 70.000 70.000 70.000 50.00 3,500.00 3,500.00 3,500.00 M-124
c) Steel helmet and cushion block on top of pile
head during driving. Kg 40.000 40.000 40.000 135.00 5,400.00 5,400.00 5,400.00 M-174
c) Machinery
Crane 35 T capacity hour 6.000 6.000 6.000 2,394.00 14,364.00 14,364.00 14,364.00 P&M-107
Vibrating Pile driving hammer complete with power
unit and accessories. hour 6.000 6.000 6.000 18,571.35 111,428.10 111,428.10 111,428.10 P&M-115
d) Labour
Mate/Supervisor day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Mazdoor day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
Add 1 per cent of (a+b+c) for carriage of piles
from casting yard to work site and stacking, and
other imponderables during installation. 3,486.42 3,497.46 3,533.67
12.32 1100 & Driven precast vertical M35 grade R.C.C. Piles
1700 excluding Reinforcement complete as per Drawing
and & Technical Specification
Pile Diameter = 1000 mm
Unit = Running Meter
Taking output = 40 m
a) Materials
RCC Grade M35 cum 31.400 9,089.00 285,394.60
Item No. -
(Rate for concrete may be adopted same as for cum 31.400 9,139.00 286,964.60
12.11 F (iv)
pile vide item no. 12.11 F (iv))
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H RCC Grade M35 Description Unit For Large For Medium For Small Large Medium Small
(Rs.) InputNo.
Item ref.-
Specification (Rate for concrete may be adopted same as for Project Project Project Project Project Project
12.11 F (iv)
pile vide item no. 12.11 F (iv)) cum 31.400 9,303.00 292,114.20
b ) Material Pile shoes
a) C.I. shoes for the pile Kg 160.000 160.000 160.000 69.50 11,120.00 11,120.00 11,120.00 M-080
b) M.S. shoes @ 35 Kg per pile of 15 m Kg 70.000 70.000 70.000 50.00 3,500.00 3,500.00 3,500.00 M-124
c) Steel helmet and cushion block on top of pile
head during driving. Kg 50.000 50.000 50.000 135.00 6,750.00 6,750.00 6,750.00 M-174
c) Machinery
Crane 50 t capacity. hour 6.000 6.000 6.000 6,580.35 39,482.10 39,482.10 39,482.10 P&M-100
Vibrating Pile driving hammer complete with power
unit and accessories. hour 6.000 6.000 6.000 18,571.35 111,428.10 111,428.10 111,428.10 P&M-115
d) Labour
Mate/Supervisor day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 5.000 5.000 5.000 511.52 2,557.60 2,557.60 2,557.60 L-13
Add 1 per cent of (a+b+c) for carriage of piles
from casting yard to work site and stacking, and
other imponderables during installation. 4,603.56 4,619.26 4,670.75
b) Labour
For pouring and placing
Mate day 0.146 0.146 0.146 617.00 90.08 90.08 90.08 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 2.650 2.650 2.650 511.52 1,355.53 1,355.53 1,355.53 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 150 x L1 150 x L1 150 x L1 13.41 60,348.75 60,348.75 60,348.75 P&M-128
For unloading hour 1.300 1.300 1.300 2,413.95 3,138.14 3,138.14 3,138.14 P&M-067
Hydraulic Boom placer pump hour 1.300 1.300 1.300 4,401.60 5,722.08 5,722.08 5,722.08 P&M-069
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 13,734.90 13,734.90 13,734.90
b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 150 x L1 150 x L1 150 x L1 13.41 60,348.75 60,348.75 60,348.75 P&M-128
For unloading hour 3.333 3.333 3.333 2,413.95 8,046.50 8,046.50 8,046.50 P&M-067
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 13,817.10 13,817.10 13,817.10
b) Labour
For pouring and placing
Mate day 0.146 0.146 0.146 617.00 90.08 90.08 90.08 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 2.650 2.650 2.650 511.52 1,355.53 1,355.53 1,355.53 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 150 x L1 150 x L1 150 x L1 13.41 60,348.75 60,348.75 60,348.75 P&M-128
For unloading hour 1.300 1.300 1.300 2,413.95 3,138.14 3,138.14 3,138.14 P&M-067
Hydraulic Boom placer pump hour 1.300 1.300 1.300 4,401.60 5,722.08 5,722.08 5,722.08 P&M-069
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 14,723.70 14,723.70 14,723.70
b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 150 x L1 150 x L1 150 x L1 13.41 60,348.75 60,348.75 60,348.75 P&M-128
For unloading hour 3.333 3.333 3.333 2,413.95 8,046.50 8,046.50 8,046.50 P&M-067
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 14,805.90 14,805.90 14,805.90
b) Labour
For pouring and placing
Mate day 0.146 0.146 0.146 617.00 90.08 90.08 90.08 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 2.650 2.650 2.650 511.52 1,355.53 1,355.53 1,355.53 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 150 x L1 150 x L1 150 x L1 13.41 60,348.75 60,348.75 60,348.75 P&M-128
For unloading hour 1.300 1.300 1.300 2,413.95 3,138.14 3,138.14 3,138.14 P&M-067
Hydraulic Boom placer pump hour 1.300 1.300 1.300 4,401.60 5,722.08 5,722.08 5,722.08 P&M-069
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 14,932.50 14,932.50 14,932.50
b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-11
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 150 x L1 150 x L1 150 x L1 13.41 60,348.75 60,348.75 60,348.75 P&M-128
For unloading hour 3.333 3.333 3.333 2,413.95 8,046.50 8,046.50 8,046.50 P&M-067
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 15,014.70 15,014.70 15,014.70
Sub-Analysis
Per Cum Basic Cost (Rate as in sub-analysis) cum 60.000 60.000 60.000 5,186.00 311,160.00 311,160.00 311,160.00 of Concrete -
20.11
b) Labour
For pouring and placing
Mate day 0.146 0.146 0.146 617.00 90.08 90.08 90.08 L-12
Mason day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-10
Mazdoor day 2.650 2.650 2.650 511.52 1,355.53 1,355.53 1,355.53 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 150 x L1 150 x L1 150 x L1 13.41 60,348.75 60,348.75 60,348.75 P&M-128
For unloading hour 1.300 1.300 1.300 2,413.95 3,138.14 3,138.14 3,138.14 P&M-067
Hydraulic Boom placer pump hour 1.300 1.300 1.300 4,401.60 5,722.08 5,722.08 5,722.08 P&M-069
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 15,299.74 15,299.74 15,299.74
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
e) Overhead charges @ 20% on @ 20% on @ 20% on
79,558.66 79,558.66 79,558.66
(a+b+c+d) (a+b+c+d) (a+b+c+d)
f) Contractor's profit @ 10% on @ 10% on @ 10% on
47,735.20 47,735.20 47,735.20
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 60 cum = a+b+c+d+e+f 525,087.18 525,087.18 525,087.18
Rate per cum = (a+b+c+d+e+f)/60 8,751.45 8,751.45 8,751.45
Say 8,751.00 8,751.00 8,751.00
Case II RCC Grade M35 using batching plant & manual
placing
Unit = cum
Taking output = 60 cum
a) Material
Per Cum Basic Cost (Rate as in sub-analysis)
Sub-Analysis
cum 60.000 60.000 60.000 5,186.00 311,160.00 311,160.00 311,160.00 of Concrete -
20.11
b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 150 x L1 150 x L1 150 x L1 13.41 60,348.75 60,348.75 60,348.75 P&M-128
For unloading hour 3.333 3.333 3.333 2,413.95 8,046.50 8,046.50 8,046.50 P&M-067
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 15,381.94 15,381.94 15,381.94
b) Labour
For pouring and placing
Mate day 0.146 0.146 0.146 617.00 90.08 90.08 90.08 L-12
Mason day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-10
Mazdoor day 2.650 2.650 2.650 511.52 1,355.53 1,355.53 1,355.53 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 150 x L1 150 x L1 150 x L1 13.41 60,348.75 60,348.75 60,348.75 P&M-128
For unloading hour 1.300 1.300 1.300 2,413.95 3,138.14 3,138.14 3,138.14 P&M-067
Hydraulic Boom placer pump hour 1.300 1.300 1.300 4,401.60 5,722.08 5,722.08 5,722.08 P&M-069
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 16,098.94 16,098.94 16,098.94
b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 150 x L1 150 x L1 150 x L1 13.41 60,348.75 60,348.75 60,348.75 P&M-128
For unloading hour 3.333 3.333 3.333 2,413.95 8,045.70 8,045.70 8,045.70 P&M-067
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 16,181.11 16,181.11 16,181.11
b) Labour
For pouring and placing
Mate day 0.146 0.146 0.146 617.00 90.08 90.08 90.08 L-12
Mason day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-10
Mazdoor day 2.650 2.650 2.650 511.52 1,355.53 1,355.53 1,355.53 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 150 x L1 150 x L1 150 x L1 13.41 60,348.75 60,348.75 60,348.75 P&M-128
For unloading hour 1.300 1.300 1.300 2,413.95 3,138.14 3,138.14 3,138.14 P&M-067
Hydraulic Boom placer pump hour 1.300 1.300 1.300 4,401.60 5,722.08 5,722.08 5,722.08 P&M-069
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 16,444.54 16,444.54 16,444.54
b) Labour
For pouring and placing
Mate day 0.360 0.360 0.360 617.00 222.12 222.12 222.12 L-12
Mason day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 150 x L1 150 x L1 150 x L1 13.41 60,348.75 60,348.75 60,348.75 P&M-128
For unloading hour 3.333 3.333 3.333 2,413.95 8,046.50 8,046.50 8,046.50 P&M-067
d) Formwork @ 4 per cent on cost of concrete
i.e. cost of material, labour and machinery 16,526.74 16,526.74 16,526.74
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Unit = MT
Taking output = 8 MT
a) Material
MS bars including 5 per cent overlaps and
wastage tonne 8.400 8.400 8.400 46,496.54 390,570.97 390,570.97 390,570.97 M-083
Binding wire Kg 48.000 48.000 48.000 66.72 3,202.56 3,202.56 3,202.56 M-072
b) Labour for straightening, cutting, bending,
shifting to site, tying and placing in position
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Blacksmith day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-01
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
c) Machinery
Cutting Machine hour 5.333 5.333 5.333 528.15 2,816.80 2,816.80 2,816.80 P&M-076
Bending Machine hour 5.333 5.333 5.333 528.15 2,816.80 2,816.80 2,816.80 P&M-076
Electric generator 15 KVA hour 5.333 5.333 5.333 425.25 2,268.00 2,268.00 2,268.00 P&M-051
Tipper
Tipper for Transportation
(i) 18 cum capacity t.km 8 x L1 6.18 1,482.84 P&M-116
(ii) 14 cum capacity t.km 8 x L1 7.01 1,683.07 P&M-119
(iii) 10 cum capacity t.km 8 x L1 8.66 2,079.36 P&M-122
Loading & Unloading Time hour
(i) 18 cum capacity hour 1.000 2,883.30 2,883.30 P&M-014
(ii) 14 cum capacity hour 1.280 2,556.75 3,272.64 P&M-015
(iii) 10 cum capacity hour 1.778 2,274.30 4,043.20 P&M-016
Light weight Crane
At cutting bending yard hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102
At site hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102
Reference to Quantity Amount (Rs.)
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) Input ref.
Specification Project Project Project Project Project Project
Per MT Basic Cost of Labour, Material &
51586.000 51660.000 51806.000
Machinery (a+b+c)
Unit = MT
Taking output = 8 MT
a) Material
MS bars including 5 per cent overlaps and
wastage tonne 8.400 8.400 8.400 63,806.54 535,974.97 535,974.97 535,974.97 M-125
Binding wire Kg 48.000 48.000 48.000 66.72 3,202.56 3,202.56 3,202.56 M-072
b) Labour for straightening, cutting, bending,
shifting to site, tying and placing in position
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Blacksmith day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-01
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
c) Machinery
Cutting Machine hour 5.333 5.333 5.333 528.15 2,816.80 2,816.80 2,816.80 P&M-076
Bending Machine hour 5.333 5.333 5.333 528.15 2,816.80 2,816.80 2,816.80 P&M-076
Electric generator 15 KVA hour 5.333 5.333 5.333 425.25 2,268.00 2,268.00 2,268.00 P&M-051
Tipper
Tipper for Transportation
(i) 18 cum capacity t.km 8 x L1 6.18 1,482.84 P&M-116
(ii) 14 cum capacity t.km 8 x L1 7.01 1,683.07 P&M-119
(iii) 10 cum capacity t.km 8 x L1 8.66 2,079.36 P&M-122
Loading & Unloading Time hour
(i) 18 cum capacity hour 1.000 2,883.30 2,883.30 P&M-014
(ii) 14 cum capacity hour 1.280 2,556.75 3,272.64 P&M-015
(iii) 10 cum capacity hour 1.778 2,274.30 4,043.20 P&M-016
Light weight Crane
At cutting bending yard hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102
At site hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102
Per MT Basic Cost of Labour, Material &
69762.000 69836.000 69982.000
Machinery (a+b+c)
Unit = cum
Taking output = 1 cum
a) Material
Bricks Ist class each 500.000 500.000 500.000 3.50 1,750.00 1,750.00 1,750.00 M-079
Sub-Analysis of
Cement mortar 1:3 (Rate as sub-analysis) cum 0.240 0.240 0.240 5,125.00 1,230.00 1,230.00 1,230.00 Concrete -
20.01 (A)
Water for curing KL 0.483 0.483 0.483 16.00 7.73 7.73 7.73 M-191
b) Labour
Mate day 0.064 0.064 0.064 617.00 39.49 39.49 39.49 L-12
Mason day 0.800 0.800 0.800 679.00 543.20 543.20 543.20 L-10
Mazdoor day 0.800 0.800 0.800 511.52 409.22 409.22 409.22 L-13
Add for scaffolding @ 5 per cent of cost of material
198.98 198.98 198.98
and labour
c) Machinery
P&M-023
(i) 16 KL capacity hour 0.003XL1+0.02 1,501.00 165.11
0.004XL1+0.02 P&M-024
(ii) 12 KL capacity hour 1,327.00 195.07
7
0.009XL1+0.05 P&M-025
(iii) 6 KL capacity hour 1,005.00 325.62
4
@ 20% on @ 20% on @ 20% on
d) Overhead charges 868.74 874.74 900.85
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 521.25 524.84 540.51
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum (a+b+c+d+e) 5,733.72 5,773.26 5,945.59
Say 5,734.00 5,773.00 5,946.00
13.02 1300 &
2200 Pointing with cement mortar (1:3 ) on brick work in
substructure as per Technical Specifications
Unit = sqm
Taking output = 10 sqm
a) Material
Sub-Analysis of
Cement mortar 1:3 (Rate as sub-analysis) cum 0.030 0.030 0.030 5,125.00 153.75 153.75 153.75 Concrete -
20.01 (A)
b) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mason day 0.500 0.500 0.500 679.00 339.50 339.50 339.50 L-10
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
@ 20% on @ 20% on @ 20% on
c) Overhead charges 154.74 154.74 154.74
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 92.84 92.84 92.84
(a+b+c) (a+b+c) (a+b+c)
Rate per 10 sqm (a+b+c+d) 1,021.27 1,021.27 1,021.27
Rate per sqm =(a+b+c+d+e)/10 102.13 102.13 102.13
Say 102.00 102.00 102.00
Note Scaffolding is already included in item 13.1
13.03 1300 &
2200 Plastering with cement mortar (1:3 ) on brick work
in sub-structure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Sub-Analysis of
Cement mortar 1:3 (Rate as sub-analysis) cum 0.144 0.144 0.144 5,125.00 738.00 738.00 738.00 Concrete -
20.01 (A)
Water for curing KL 0.139 0.139 0.139 16.00 2.23 2.23 2.23 M-191
b) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mason day 0.500 0.500 0.500 679.00 339.50 339.50 339.50 L-11
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
c) Machinery
0.001XL1+0.00 P&M-023
(i) 16 KL capacity hour 1,501.00 54.04
6
0.001XL1+0.00 P&M-024
(ii) 12 KL capacity hour 1,327.00 50.43
8
0.003XL1+0.01 P&M-025
(iii) 6 KL capacity hour 1,005.00 105.53
5
13.04 1400 & Stone masonry work in cement mortar 1:3 for
2200 substructure complete as per drawing and
Technical Specifications
A Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.000 1.000 1.000 1,472.59 1,472.59 1,472.59 1,472.59 M-001
Through and bond stone No 7.000 7.000 7.000 59.77 418.39 418.39 418.39 M-184
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Sub-Analysis of
Cement mortar 1:3 (Rate as sub-analysis) cum 0.330 0.330 0.330 5,125.00 1,691.25 1,691.25 1,691.25 Concrete -
20.01 (A)
Water for curing KL 0.966 0.966 0.966 16.00 15.46 15.46 15.46 M-191
b) Labour
Mate day 0.096 0.096 0.096 617.00 59.23 59.23 59.23 L-12
Mason day 1.200 1.200 1.200 679.00 814.80 814.80 814.80 L-10
Mazdoor day 1.200 1.200 1.200 511.52 613.82 613.82 613.82 L-13
Add for scaffolding @ 5 per cent of cost of a)
254.28 254.28 254.28
Material and b) Labour
c) Machinery
P&M-023
(i) 16 KL capacity hour 0.007XL1+0.04 1,501.00 375.25
0.009XL1+0.05 P&M-024
(ii) 12 KL capacity hour 1,327.00 429.95
4
0.018XL1+0.10 P&M-025
(iii) 6 KL capacity hour 1,005.00 650.24
7
@ 20% on @ 20% on @ 20% on
d) Overhead charges 1,143.01 1,153.95 1,198.01
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 685.81 692.37 718.81
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum (a+b+c+d) 7,543.89 7,616.09 7,906.87
Say 7,544.00 7,616.00 7,907.00
13.04 B Coursed rubble masonry (first sort )
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.100 1.100 1.100 1,472.59 1,619.85 1,619.85 1,619.85 M-001
Through and bond stone each 7.000 7.000 7.000 59.77 418.39 418.39 418.39 M-184
(7 no.x 0.24 m x 0.24 m x 0.39 m = 0.16 cum)
Sub-Analysis of
Cement mortar 1:3 (Rate as sub-analysis) cum 0.300 0.300 0.300 5,125.00 1,537.50 1,537.50 1,537.50 Concrete -
20.01 (A)
Water for curing KL 0.966 0.966 0.966 16.00 15.46 15.46 15.46 M-191
b) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.500 1.500 1.500 511.52 767.28 767.28 767.28 L-13
Add for scaffolding @ 5 per cent of cost of material
272.55 272.55 272.55
and labour
c) Machinery
P&M-023
(i) 16 KL capacity hour 0.007XL1+0.04 1,501.00 375.25
0.009XL1+0.05 P&M-024
(ii) 12 KL capacity hour 1,327.00 429.95
4
0.018XL1+0.10 P&M-025
(iii) 6 KL capacity hour 1,005.00 650.24
7
@ 20% on @ 20% on @ 20% on
d) Overhead charges 1,219.76 1,230.70 1,274.76
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 731.86 738.42 764.86
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum (a+b+c+d) 8,050.44 8,122.64 8,413.42
Say 8,050.00 8,123.00 8,413.00
13.04 C Ashlar masonry ( first sort )
Plain ashlar
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.110 1.110 1.110 1,472.59 1,634.58 1,634.58 1,634.58 M-001
Through and bond stone each 7.000 7.000 7.000 59.77 418.39 418.39 418.39 M-184
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Sub-Analysis of
Cement mortar 1:3 (Rate as sub-analysis) cum 0.330 0.330 0.330 5,125.00 1,691.25 1,691.25 1,691.25 Concrete -
20.01 (A)
Water for curing KL 0.966 0.966 0.966 16.00 15.46 15.46 15.46 M-191
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
b) Labour for masonry work
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mason day 2.500 2.500 2.500 679.00 1,697.50 1,697.50 1,697.50 L-10
Mazdoor day 2.500 2.500 2.500 511.52 1,278.80 1,278.80 1,278.80 L-13
Add for scaffolding @ 5 per cent of cost of a)
342.97 342.97 342.97
Material and b) Labour
c) Machinery
P&M-023
(i) 16 KL capacity hour 0.007XL1+0.04 1,501.00 375.25
0.009XL1+0.05 P&M-024
(ii) 12 KL capacity hour 1,327.00 429.95
4
0.018XL1+0.10 P&M-025
(iii) 6 KL capacity hour 1,005.00 650.24
7
@ 20% on @ 20% on @ 20% on
d) Overhead charges 1,515.52 1,526.46 1,570.52
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 909.31 915.87 942.31
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum (a+b+c+d) 10,002.42 10,074.62 10,365.40
Say 10,002.00 10,075.00 10,365.00
Note The labour already considered in the cement
mortar have been taken into account while
providing these categories in the stone masonry
works.
13.05 1500, Plain/Reinforced cement concrete in sub-structure
1700 & complete as per drawing and Technical
2200 Specifications
A PCC Grade M15
(p) Height upto 5m
PCC Grade M15 using batching plant & Concrete
pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 4,176.00 125,280.00 125,280.00 125,280.00 Concrete -
20.03
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 10 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 10.000 19,140.16 19,248.21 19,607.12
Formwork
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 11.8 per cent on cost of concrete i.e. cost
of material, labour and machinery (a+b+c) for 11.800 22,585.39 22,712.88 23,136.40
Formwork
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 10 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 10.000 19,401.16 19,509.21 19,868.12
Formwork
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 14 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 14.000 27,161.62 27,312.89 27,815.37
Formwork
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 11 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 11.000 11.000 11.000 21,849.48 21,968.33 22,363.13
Formwork
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 13 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 13.000 25,822.11 25,962.57 26,429.16
Formwork
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 10 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 10.000 10.000 10.000 20,862.16 20,970.21 21,329.12
Formwork
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 11 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 11.000 11.000 11.000 22,948.38 23,067.23 23,462.03
Formwork
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 13 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 13.000 13.000 13.000 27,120.81 27,261.27 27,727.86
Formwork
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 10 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 10.000 10.000 10.000 21,294.16 21,402.21 21,761.12
Formwork
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 11 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 11.000 11.000 11.000 23,423.58 23,542.43 23,937.23
Formwork
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 13 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 13.000 13.000 13.000 27,682.41 27,822.87 28,289.46
Formwork
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 10 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 10.000 10.000 10.000 23,031.16 23,139.21 23,498.12
Formwork
@ 20% on @ 20% on @ 20% on
e) Overhead charges 50,668.55 50,906.25 51,695.87
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 30,401.13 30,543.75 31,017.52
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 30 cum = a+b+c+d+e+f 334,412.43 335,981.26 341,192.73
Rate per cum = (a+b+c+d+e+f)/30 11,147.08 11,199.38 11,373.09
Say 11,147.00 11,199.00 11,373.00
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
13.05 K (q) Height 5m to 10m
For height, upto 10m, add 1.4 per cent of cost as
above excluding formwork. For cost of formwork
add 11 per cent of cost of material, labour and
machinery .
RCC Grade M50 using batching plant transit mixer
& Concrete pump
Unit = cum
Taking output = 30 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 30.000 30.000 30.000 6,242.00 187,260.00 187,260.00 187,260.00 Concrete -
20.14
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
tonne- P&M-128
For transportation (6 cum Capacity) 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38
km
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 11 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 11.000 11.000 11.000 25,334.28 25,453.13 25,847.93
Formwork
0.109XL1+0.65 P&M-023
(i) 16 KL capacity hour 1,501.00 5,892.93
6
0.146XL1+0.87 P&M-024
(ii) 12 KL capacity hour 1,327.00 6,973.39
5
P&M-025
(iii) 6 KL capacity hour 0.292XL1+1.75 1,005.00 10,562.55
d) Formwork
Add @ 13 per cent on cost of concrete i.e. cost of
material, labour and machinery (a+b+c) for 13.000 13.000 13.000 29,940.51 30,080.97 30,547.56
Formwork
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Blacksmith day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-20
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
c) Machinery
Cutting Machine hour 6.667 6.667 6.667 528.15 3,521.00 3,521.00 3,521.00 P&M-076
Bending Machine hour 6.667 6.667 6.667 528.15 3,521.00 3,521.00 3,521.00 P&M-076
Electric generator 15 KVA hour 6.667 6.667 6.667 425.25 2,835.00 2,835.00 2,835.00 P&M-051
Tipper
Tipper for Transportation
(i) 18 cum capacity t.km 8 x L1 6.18 1,482.84 P&M-116
(ii) 14 cum capacity t.km 8 x L1 7.01 1,683.07 P&M-119
(iii) 10 cum capacity t.km 8 x L1 8.66 2,079.36 P&M-122
Loading & Unloading Time hour
(i) 18 cum capacity hour 1.000 2,883.30 2,883.30 P&M-014
(ii) 14 cum capacity hour 1.280 2,556.75 3,272.64 P&M-015
(iii) 10 cum capacity hour 1.778 2,274.30 4,043.71 P&M-016
Light weight Crane
At cutting bending yard hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102
At site hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Blacksmith day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-20
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
c) Machinery
Cutting Machine hour 6.667 6.667 6.667 528.15 3,521.00 3,521.00 3,521.00 P&M-076
Bending Machine hour 6.667 6.667 6.667 528.15 3,521.00 3,521.00 3,521.00 P&M-076
Electric generator 15 KVA hour 6.667 6.667 6.667 425.25 2,835.00 2,835.00 2,835.00 P&M-051
Tipper
Tipper for Transportation
(i) 18 cum capacity t.km 8 x L1 6.18 1,482.84 P&M-116
(ii) 14 cum capacity t.km 8 x L1 7.01 1,683.07 P&M-119
(iii) 10 cum capacity t.km 8 x L1 8.66 2,079.36 P&M-122
Loading & Unloading Time hour
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
(i) 18 cum capacity hour 1.000 2,883.30 2,883.30 P&M-014
(ii) 14 cum capacity hour 1.280 2,556.75 3,272.64 P&M-015
(iii) 10 cum capacity hour 1.778 2,274.30 4,043.71 P&M-016
Light weight Crane
At cutting bending yard hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102
At site hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102
Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including wastage @ 5 per M-056
metre 31.500 31.500 31.500 59.13 1,862.60 1,862.60 1,862.60
cent )
Average length of weep hole is taken as one metre
for the purpose of estimating.
MS clamp each. 30.000 30.000 30.000 41.70 1,251.00 1,251.00 1,251.00 M-122
collar for AC pipe (average) taking 10% of above M-056/10
each. 10.000 10.000 10.000 5.91 59.13 59.13 59.13
pipe rate
Sub-Analysis of
Cement mortar 1:3 (Rate as sub-analysis) cum 0.050 0.050 0.050 5,125.00 256.25 256.25 256.25 Concrete -
20.01 (A)
b) Labour
Mate day 0.030 0.030 0.030 617.00 18.51 18.51 18.51 L-12
Mason day 0.500 0.500 0.500 679.00 339.50 339.50 339.50 L-10
Mazdoor day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
@ 20% on @ 20% on @ 20% on
c) Overhead charges 782.97 782.97 782.97
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 469.78 469.78 469.78
(a+b+c) (a+b+c) (a+b+c)
Cost for 30 m = a+b+c+d 5,167.62 5,167.62 5,167.62
Rate per m (a+b+c+d)/30 172.25 172.25 172.25
Say 172.00 172.00 172.00
Note 1. In case of stone masonry, the size of the weep
hole shall be 150 mm x 80 mm or circular with 150
mm diameter.
13.09 710.1.4.of Back filling behind abutment, wing wall and return
IRC:78 & wall complete as per drawing and Technical
2200 Specification
Unit = cum
Taking output = 10 cum
A Granular material
a) Labour
Mate day 0.280 0.280 0.280 617.00 172.76 172.76 172.76 L-12
Mazdoor day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
b) Material
Granular material cum 12.000 12.000 12.000 1,887.12 22,645.48 22,645.48 22,645.48 M-009
c) Machinery
Plate compactor/power rammer hour 2.500 2.500 2.500 597.45 1,493.63 1,493.63 1,493.63 P&M-079
Water Tanker hour 0.050 0.050 0.050 1,005.00 50.25 50.25 50.25 P&M-025
@ 20% on @ 20% on @ 20% on
d) Overhead charges 5,588.55 5,588.55 5,588.55
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 3,353.13 3,353.13 3,353.13
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Unit = cum
Taking output = 10 cum.
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mazdoor for filling, watering, ramming etc. day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
Mazdoor (Skilled) day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
b) Material
Filter media of stone aggregate conforming to M-011
cum 12.000 12.000 12.000 1,215.07 14,580.87 14,580.87 14,580.87
clause 2504.2.2. of MoRTH specifications.
c) Machinery
Water Tanker of 6 KL capacity hour 0.060 0.060 0.060 1,005.00 60.30 60.30 60.30 P&M-025
@ 20% on @ 20% on @ 20% on
d) Overhead charges 3,797.00 3,797.00 3,797.00
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 2,278.20 2,278.20 2,278.20
(a+b+c+d) (a+b+c+d) (a+b+c+d)
cost for 10 cum of Fiter Media = a+b+c+d+e 25,060.18 25,060.18 25,060.18
Rate per cum = (a+b+c+d+e)/10 2,506.02 2,506.02 2,506.02
Say 2,506.00 2,506.00 2,506.00
13.11 704
Unit = Sqm
Taking output 300 Sqm
a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Mazdoor (Skilled ) day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Material
Geosynthetic Drainage Composite sqm 300.000 300.000 300.000 175.00 52,500.00 52,500.00 52,500.00 M-290
Unit = Sqm
Taking output 300 Sqm
a) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Mazdoor (Skilled ) day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
b) Material
Geosynthetic Drainage Composite sqm 300.000 300.000 300.000 150.00 45,000.00 45,000.00 45,000.00 M-291
13.13 2000,
1000 & Supplying, fitting and fixing in position true to line
2200 and level cast steel rocker bearing conforming to
IRC: 83(Pt.-1) section IX and clause 2003 of
MoRTH specifications complete including all
accessories as per drawing and Technical
Specifications.
cost for 250 tonnes capacity bearing = a+b+c+d 75,303.37 75,303.37 75,303.37
Rate per tonne capacity = (a+b+c+d)/250 301.21 301.21 301.21
Say 301.00 301.00 301.00
13.14 2000 ,
1000 & Supplying, fitting and fixing in position true to line
2200 and level forged steel roller bearing conforming to
IRC: 83(Pt.-1) section IX and clause 2003 of
MoRTH specifications complete including all
accessories as per drawing and Technical
Specifications.
cost for 250 tonnes capacity bearing = a+b+c+d 114,430.12 114,430.12 114,430.12
Rate per tonne capacity = (a+b+c+d)/250 457.72 457.72 457.72
Say 458.00 458.00 458.00
13.15 2000 &
Supplying, fitting and fixing in position true to line
2200
and level sliding plate bearing with PTFE surface
sliding on stainless steel complete including all
accessories as per drawing and Technical
Specifications and BS: 5400, section 9.1 & 9.2 (for
PTFE) and clause 2004 of MoRTH
Specifications.
Unit: one tonne capacity
Considering a 80 tonne capacity bearing for this
analysis
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
Mazdoor (Skilled) day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
b) Material
PTFE sliding plate bearing assembly of 80 tonnes M-069
design load capacity duly painted complete with all
each. 1.000 1.000 1.000 34,788.00 34,788.00 34,788.00 34,788.00
its components as per drawing and Technical
Specifications
Add 1 per cent for foundation anchorage bolts and
347.88 347.88 347.88
consumables.
@ 20% on @ 20% on @ 20% on
c) Overhead charges 7,193.46 7,193.46 7,193.46
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 4,316.07 4,316.07 4,316.07
(a+b+c) (a+b+c) (a+b+c)
cost for 250 tonnes capacity bearing = a+b+c+d 47,000.12 47,000.12 47,000.12
Rate per tonne capacity = (a+b+c+d)/250 188.00 188.00 188.00
Say 188.00 188.00 188.00
13.19 Protection to substructure by using coal tar epoxy
Trailer 30 tonne capacity for transporting to site Hrs 2+L/15 2+L/15 2+L/15 2,883.30 11,533.20 11,533.20 11,533.20 P&M-014
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 120.000 120.000 4,533.00 543,960.00 543,960.00 543,960.00
Concrete - 20.05
Water for curing Kl 63.000 63.000 63.000 16.00 1,008.00 1,008.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.192 0.192 0.192 617.00 118.46 118.46 118.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 3.300 3.300 3.300 511.52 1,688.02 1,688.02 1,688.02 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L1 lead in tonne-
300 x L 300 x L 300 x L 13.41 120,697.50 120,697.50 120,697.50 P&M-128
Kilometer km
For unloading hour 2.600 2.600 2.600 2,413.95 6,276.27 6,276.27 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 2.600 2.600 4,401.60 11,444.16 11,444.16 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
0.438XL1+2.62
(i) 16 KL capacity hour 1,501.00 23,663.27 P&M-023
5
0.583XL1+3.50
(ii) 12 KL capacity hour 1,327.00 27,853.73 P&M-024
0
1.167XL1+7.00
(iii) 6 KL capacity hour 1,005.00 42,220.05 P&M-025
0
Basic Cost of Labour, Material & Machinery (a+b+c)
709,875.00 714,065.00 728,431.00
for 120 cum
For formwork and staging add the following:
14.01 A (i) For solid slab super-structure, 20-30 per cent of
(a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
709,875.00 714,065.00 728,431.00
for 120 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.000 141,975.00 142,813.00 145,686.20
d) Formwork and staging 25 per cent of (a+b+c) 25.000 177,468.75 178,516.25 182,107.75
d) Formwork and staging 30 per cent of (a+b+c) 30.000 212,962.50 214,219.50 218,529.30
d) Formwork and staging 25 per cent of (a+b+c) 25.000 177,468.75 178,516.25 182,107.75
d) Formwork and staging 30 per cent of (a+b+c) 30.000 212,962.50 214,219.50 218,529.30
d) Formwork and staging 35 per cent of (a+b+c) 35.000 248,456.25 249,922.75 254,950.85
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 120.000 120.000 4,945.00 593,400.00 593,400.00 593,400.00
Concrete - 20.07
Water for curing Kl 63.000 63.000 63.000 16.00 1,008.00 1,008.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.192 0.192 0.192 617.00 118.46 118.46 118.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 3.300 3.300 3.300 511.52 1,688.02 1,688.02 1,688.02 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-
300 x L 300 x L 301 x L 13.41 120,697.50 120,697.50 120,697.50 P&M-128
Kilometer km
For unloading hour 2.600 2.600 2.600 2,413.95 6,276.27 6,276.27 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 2.600 2.600 4,401.60 11,444.16 11,444.16 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
0.438XL1+2.62
(i) 16 KL capacity hour 1,501.00 23,663.27 P&M-023
5
0.583XL1+3.50
(ii) 12 KL capacity hour 1,327.00 27,853.73 P&M-024
0
1.167XL1+7.00
(iii) 6 KL capacity hour 1,005.00 42,220.05 P&M-025
0
Basic Cost of Labour, Material & Machinery (a+b+c)
759,315.00 763,505.00 777,871.00
for 120 Cum
For formwork and staging add the following:
14.01B (i) For solid slab super-structure, 20-30 per cent of
(a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
759,315.00 763,505.00 777,871.00
for 120 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.000 151,863.00 152,701.00 155,574.20
d) Formwork and staging 25 per cent of (a+b+c) 25.000 189,828.75 190,876.25 194,467.75
d) Formwork and staging 30 per cent of (a+b+c) 30.000 227,794.50 229,051.50 233,361.30
d) Formwork and staging 25 per cent of (a+b+c) 25.000 189,828.75 190,876.25 194,467.75
d) Formwork and staging 30 per cent of (a+b+c) 30.000 227,794.50 229,051.50 233,361.30
d) Formwork and staging 35 per cent of (a+b+c) 35.000 265,760.25 267,226.75 272,254.85
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 120.000 120.000 5,032.00 603,840.00 603,840.00 603,840.00
Concrete - 20.09
Water for curing Kl 63.000 63.000 63.000 16.00 1,008.00 1,008.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.192 0.192 0.192 617.00 118.46 118.46 118.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 3.300 3.300 3.300 511.52 1,688.02 1,688.02 1,688.02 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-
300 x L 300 x L 301 x L 13.41 120,697.50 120,697.50 120,697.50 P&M-128
Kilometer km
For unloading hour 2.600 2.600 2.600 2,413.95 6,276.27 6,276.27 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 2.600 2.600 4,401.60 11,444.16 11,444.16 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
0.438XL1+2.62
(i) 16 KL capacity hour 1,501.00 23,663.27 P&M-023
5
0.583XL1+3.50
(ii) 12 KL capacity hour 1,327.00 27,853.73 P&M-024
0
1.167XL1+7.00
(iii) 6 KL capacity hour 1,005.00 42,220.05 P&M-025
0
Basic Cost of Labour, Material & Machinery (a+b+c)
769,754.18 773,944.64 788,310.96
for 120 Cum
For formwork and staging add the following:
14.01C (i) For solid slab super-structure, 20-30 per cent of
(a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
769,754.18 773,944.64 788,310.96
for 120 cum
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
d) Formwork and staging 20 per cent of (a+b+c) 20.000 153,950.84 154,788.93 157,662.19
d) Formwork and staging 25 per cent of (a+b+c) 25.000 192,438.54 193,486.16 197,077.74
d) Formwork and staging 30 per cent of (a+b+c) 30.000 230,926.25 232,183.39 236,493.29
d) Formwork and staging 25 per cent of (a+b+c) 25.000 192,438.54 193,486.16 197,077.74
d) Formwork and staging 30 per cent of (a+b+c) 30.000 230,926.25 232,183.39 236,493.29
d) Formwork and staging 35 per cent of (a+b+c) 35.000 269,413.96 270,880.62 275,908.84
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 120.000 120.000 5,186.00 622,320.00 622,320.00 622,320.00
Concrete - 20.11
Water for curing Kl 63.000 63.000 63.000 16.00 1,008.00 1,008.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.192 0.192 0.192 617.00 118.46 118.46 118.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Mazdoor day 3.300 3.300 3.300 511.52 1,688.02 1,688.02 1,688.02 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-
300 x L 300 x L 300 x L 13.41 120,697.50 120,697.50 120,697.50 P&M-128
Kilometer km
For unloading hour 2.600 2.600 2.600 2,413.95 6,276.27 6,276.27 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 2.600 2.600 4,401.60 11,444.16 11,444.16 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
0.438XL1+2.62
(i) 16 KL capacity hour 1,501.00 23,663.27 P&M-023
5
0.583XL1+3.50
(ii) 12 KL capacity hour 1,327.00 27,853.73 P&M-024
0
1.167XL1+7.00
(iii) 6 KL capacity hour 1,005.00 42,220.05 P&M-025
0
Basic Cost of Labour, Material & Machinery (a+b+c)
788,235.00 792,425.00 806,791.00
for 120 Cum
For formwork and staging add the following:
14.01D (i) For solid slab super-structure, 18-28 per cent of
(a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
788,235.00 792,425.00 806,791.00
for 120 cum
d) Formwork and staging 18 per cent of (a+b+c) 18.000 141,882.30 142,636.50 145,222.38
d) Formwork and staging 23 per cent of (a+b+c) 23.000 181,294.05 182,257.75 185,561.93
d) Formwork and staging 28 per cent of (a+b+c) 28.000 220,705.80 221,879.00 225,901.48
d) Formwork and staging 23 per cent of (a+b+c) 23.000 181,294.05 182,257.75 185,561.93
d) Formwork and staging 28 per cent of (a+b+c) 28.000 220,705.80 221,879.00 225,901.48
d) Formwork and staging 33 per cent of (a+b+c) 33.000 260,117.55 261,500.25 266,241.03
d) Formwork and staging 38 per cent of (a+b+c) 38.000 299,529.30 301,121.50 306,580.58
d) Formwork and staging 48 per cent of (a+b+c) 48.000 378,352.80 380,364.00 387,259.68
d) Formwork and staging 58 per cent of (a+b+c) 58.000 457,176.30 459,606.50 467,938.78
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 120.000 120.000 5,519.00 662,280.00 662,280.00 662,280.00
Concrete - 20.12
Water for curing Kl 63.000 63.000 63.000 16.00 1,008.00 1,008.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.192 0.192 0.192 617.00 118.46 118.46 118.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 3.300 3.300 3.300 511.52 1,688.02 1,688.02 1,688.02 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-
300 x L 300 x L 300 x L 13.41 120,697.50 120,697.50 120,697.50 P&M-128
Kilometer km
For unloading hour 2.600 2.600 2.600 2,413.95 6,276.27 6,276.27 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 2.600 2.600 4,401.60 11,444.16 11,444.16 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
0.438XL1+2.62
(i) 16 KL capacity hour 1,501.00 23,663.27 P&M-023
5
0.583XL1+3.50
(ii) 12 KL capacity hour 1,327.00 27,853.73 P&M-024
0
1.167XL1+7.00
(iii) 6 KL capacity hour 1,005.00 42,220.05 P&M-025
0
Basic Cost of Labour, Material & Machinery (a+b+c)
828,195.00 832,385.00 846,751.00
for 120 Cum
For formwork and staging add the following:
14.01E (i) For solid/voided slab super-structure, 18-28 per cent
of (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
828,195.00 832,385.00 846,751.00
for 120 cum
d) Formwork and staging 18 per cent of (a+b+c) 18.000 149,075.10 149,829.30 152,415.18
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
@ 20% on @ 20% on @ 20% on
e) Overhead charges 195,454.02 196,442.86 199,833.24
(a+b+c+d) (a+b+c+d) (a+b+c+d)
@ 10% on @ 10% on @ 10% on
f) Contractor's profit 117,272.41 117,865.72 119,899.94
(a+b+c+d+e) (a+b+c+d+e) (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f 1,289,996.53 1,296,522.88 1,318,899.36
Rate per cum = (a+b+c+d+e+f)/120 10,749.97 10,804.36 10,990.83
Say 10,750.00 10,804.00 10,991.00
14.01E (q)
(i) Height 5m to 10m
d) Formwork and staging 23 per cent of (a+b+c) 23.000 190,484.85 191,448.55 194,752.73
d) Formwork and staging 28 per cent of (a+b+c) 28.000 231,894.60 233,067.80 237,090.28
d) Formwork and staging 23 per cent of (a+b+c) 23.000 190,484.85 191,448.55 194,752.73
d) Formwork and staging 28 per cent of (a+b+c) 28.000 231,894.60 233,067.80 237,090.28
d) Formwork and staging 33 per cent of (a+b+c) 33.000 273,304.35 274,687.05 279,427.83
d) Formwork and staging 38 per cent of (a+b+c) 38.000 314,714.10 316,306.30 321,765.38
d) Formwork and staging 48 per cent of (a+b+c) 48.000 397,533.60 399,544.80 406,440.48
d) Formwork and staging 58 per cent of (a+b+c) 58.000 480,353.10 482,783.30 491,115.58
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 120.000 120.000 5,663.00 679,560.00 679,560.00 679,560.00
Concrete - 20.13
Water for curing Kl 63.000 63.000 63.000 16.00 1,008.00 1,008.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.192 0.192 0.192 617.00 118.46 118.46 118.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 3.300 3.300 3.300 511.52 1,688.02 1,688.02 1,688.02 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-
300 x L 300 x L 300 x L 13.41 120,697.50 120,697.50 120,697.50 P&M-128
Kilometer km
For unloading hour 2.600 2.600 2.600 2,413.95 6,276.27 6,276.27 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 2.600 2.600 4,401.60 11,444.16 11,444.16 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
0.438XL1+2.62
(i) 16 KL capacity hour 1,501.00 23,663.27 P&M-023
5
0.583XL1+3.50
(ii) 12 KL capacity hour 1,327.00 27,853.73 P&M-024
0
1.167XL1+7.00
(iii) 6 KL capacity hour 1,005.00 42,220.05 P&M-025
0
Basic Cost of Labour, Material & Machinery (a+b+c)
845,475.00 849,665.00 864,031.00
for 120 Cum
For formwork and staging add the following:
14.01F (i) For solid slab/voided slab super-structure, 16-26 per
cent of cost of concrete (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
845,475.00 849,665.00 864,031.00
for 120 cum
d) Formwork and staging 16 per cent of (a+b+c) 16.000 135,276.00 135,946.40 138,244.96
d) Formwork and staging 21 per cent of (a+b+c) 21.000 177,549.75 178,429.65 181,446.51
d) Formwork and staging 26 per cent of (a+b+c) 26.000 219,823.50 220,912.90 224,648.06
d) Formwork and staging 21 per cent of (a+b+c) 21.000 177,549.75 178,429.65 181,446.51
d) Formwork and staging 26 per cent of (a+b+c) 26.000 219,823.50 220,912.90 224,648.06
d) Formwork and staging 31 per cent of (a+b+c) 31.000 262,097.25 263,396.15 267,849.61
d) Formwork and staging 36 per cent of (a+b+c) 36.000 304,371.00 305,879.40 311,051.16
d) Formwork and staging 46 per cent of (a+b+c) 46.000 388,918.50 390,845.90 397,454.26
d) Formwork and staging 56 per cent of (a+b+c) 56.000 473,466.00 475,812.40 483,857.36
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 120.000 120.000 6,242.00 749,040.00 749,040.00 749,040.00
Concrete - 20.14
Water for curing Kl 63.000 63.000 63.000 16.00 1,008.00 1,008.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.192 0.192 0.192 617.00 118.46 118.46 118.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 3.300 3.300 3.300 511.52 1,688.02 1,688.02 1,688.02 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-
300 x L 300 x L 300 x L 13.41 120,697.50 120,697.50 120,697.50 P&M-128
Kilometer km
For unloading hour 2.600 2.600 2.600 2,413.95 6,276.27 6,276.27 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 2.600 2.600 4,401.60 11,444.16 11,444.16 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
0.438XL1+2.62
(i) 16 KL capacity hour 1,501.00 23,663.27 P&M-023
5
0.583XL1+3.50
(ii) 12 KL capacity hour 1,327.00 27,853.73 P&M-024
0
1.167XL1+7.00
(iii) 6 KL capacity hour 1,005.00 42,220.05 P&M-025
0
Basic Cost of Labour, Material & Machinery (a+b+c)
914,955.00 919,145.00 933,511.00
for 120 Cum
For formwork and staging add the following:
14.01G (i) For cast-in-situ box girder, segmental construction
and balanced cantilever, 35-55 per cent of cost of
concrete
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
914,955.00 919,145.00 933,511.00
for 120 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.000 320,234.25 321,700.75 326,728.85
d) Formwork and staging 45 per cent of (a+b+c) 45.000 411,729.75 413,615.25 420,079.95
d) Formwork and staging 55 per cent of (a+b+c) 55.000 503,225.25 505,529.75 513,431.05
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 120.000 120.000 6,321.00 758,520.00 758,520.00 758,520.00
Concrete - 20.15
Water for curing Kl 63.000 63.000 63.000 16.00 1,008.00 1,008.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.192 0.192 0.192 617.00 118.46 118.46 118.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 3.300 3.300 3.300 511.52 1,688.02 1,688.02 1,688.02 L-13
c) Machinery
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-
300 x L 300 x L 300 x L 13.41 120,697.50 120,697.50 120,697.50 P&M-128
Kilometer km
For unloading hour 2.600 2.600 2.600 2,413.95 6,276.27 6,276.27 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 2.600 2.600 4,401.60 11,444.16 11,444.16 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
0.438XL1+2.62
(i) 16 KL capacity hour 1,501.00 23,663.27 P&M-023
5
0.583XL1+3.50
(ii) 12 KL capacity hour 1,327.00 27,853.73 P&M-024
0
1.167XL1+7.00
(iii) 6 KL capacity hour 1,005.00 42,220.05 P&M-025
0
Basic Cost of Labour, Material & Machinery (a+b+c)
924,435.00 928,625.00 942,991.00
for 120 Cum
For formwork and staging add the following:
14.01H (i) For cast-in-situ box girder, segmental construction
and balanced cantilever, 35-55 per cent of cost of
concrete
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
924,435.00 928,625.00 942,991.00
for 120 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.000 323,552.25 325,018.75 330,046.85
d) Formwork and staging 45 per cent of (a+b+c) 45.000 415,995.75 417,881.25 424,345.95
d) Formwork and staging 55 per cent of (a+b+c) 55.000 508,439.25 510,743.75 518,645.05
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 120.000 120.000 6,511.00 781,320.00 781,320.00 781,320.00
Concrete - 20.16
Water for curing Kl 63.000 63.000 63.000 16.00 1,008.00 1,008.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.192 0.192 0.192 617.00 118.46 118.46 118.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 3.300 3.300 3.300 511.52 1,688.02 1,688.02 1,688.02 L-13
c) Machinery
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-
300 x L 300 x L 300 x L 13.41 120,697.50 120,697.50 120,697.50 P&M-128
Kilometer km
For unloading hour 2.600 2.600 2.600 2,413.95 6,276.27 6,276.27 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 2.600 2.600 4,401.60 11,444.16 11,444.16 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
0.438XL1+2.62
(i) 16 KL capacity hour 1,501.00 23,663.27 P&M-023
5
0.583XL1+3.50
(ii) 12 KL capacity hour 1,327.00 27,853.73 P&M-024
0
1.167XL1+7.00
(iii) 6 KL capacity hour 1,005.00 42,220.05 P&M-025
0
Basic Cost of Labour, Material & Machinery (a+b+c)
947,235.00 951,425.00 965,791.00
for 120 Cum
For formwork and staging add the following:
14.01H (i) For cast-in-situ box girder, segmental construction
and balanced cantilever, 35-55 per cent of cost of
concrete
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
947,235.00 951,425.00 965,791.00
for 120 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.000 331,532.25 332,998.75 338,026.85
d) Formwork and staging 45 per cent of (a+b+c) 45.000 426,255.75 428,141.25 434,605.95
d) Formwork and staging 55 per cent of (a+b+c) 55.000 520,979.25 523,283.75 531,185.05
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 120.000 120.000 6,552.00 786,240.00 786,240.00 786,240.00
Concrete - 20.17
Water for curing Kl 63.000 63.000 63.000 16.00 1,008.00 1,008.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.192 0.192 0.192 617.00 118.46 118.46 118.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 3.300 3.300 3.300 511.52 1,688.02 1,688.02 1,688.02 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in tonne-
300 x L 300 x L 300 x L 13.41 120,697.50 120,697.50 120,697.50 P&M-128
Kilometer km
For unloading hour 2.600 2.600 2.600 2,413.95 6,276.27 6,276.27 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 2.600 2.600 4,401.60 11,444.16 11,444.16 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @
30 km/hr and 30 mins for unloading )
0.438XL1+2.62
(i) 16 KL capacity hour 1,501.00 23,663.27 P&M-023
5
0.583XL1+3.50
(ii) 12 KL capacity hour 1,327.00 27,853.73 P&M-024
0
1.167XL1+7.00
(iii) 6 KL capacity hour 1,005.00 42,220.05 P&M-025
0
Basic Cost of Labour, Material & Machinery (a+b+c)
952,155.00 956,345.00 970,711.00
for 120 Cum
For formwork and staging add the following:
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
14.01 (i) For cast-in-situ box girder, segmental construction
and balanced cantilever, 35-55 per cent of cost of
concrete
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
952,155.00 956,345.00 970,711.00
for 120 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.000 333,254.25 334,720.75 339,748.85
d) Formwork and staging 45 per cent of (a+b+c) 45.000 428,469.75 430,355.25 436,819.95
d) Formwork and staging 55 per cent of (a+b+c) 55.000 523,685.25 525,989.75 533,891.05
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Blacksmith day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-01
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
c) Machinery
Cutting Machine hour 8.000 8.000 8.000 528.15 4,225.20 4,225.20 4,225.20 P&M-076
Bending Machine hour 8.000 8.000 8.000 528.15 4,225.20 4,225.20 4,225.20 P&M-076
Electric generator 15 KVA hour 8.000 8.000 8.000 425.25 3,402.00 3,402.00 3,402.00 P&M-051
Tipper
Tipper for Transportation
(i) 18 cum capacity t.km 8xL 6.18 1,482.84 P&M-116
(ii) 14 cum capacity t.km 8xL 7.01 1,683.07 P&M-119
(iii) 10 cum capacity t.km 8xL 8.66 2,079.36 P&M-122
Loading & Unloading Time hour
(i) 18 cum capacity hour 1.000 2,883.30 2,883.30 P&M-014
(ii) 14 cum capacity hour 1.280 2,556.75 3,272.64 P&M-015
(iii) 10 cum capacity hour 1.778 2,274.30 4,043.20 P&M-016
Light weight Crane
At cutting bending yard hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
At site hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102
Basic Cost of Labour, Material & Machinery (a+b) for
52080.000 52154.000 52300.000
1 MT
b) Labour
i) For making and fixing cables, anchorages
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Blacksmith day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-01
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
ii) For prestressing
Mate/Supervisor day 0.050 0.050 0.050 617.00 30.85 30.85 30.85 L-12
Prestressing operator / Fitter day 0.250 0.250 0.250 738.00 184.50 184.50 184.50 L-08
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
iii) For grouting
Mate/Supervisor day 0.050 0.050 0.050 617.00 30.85 30.85 30.85 L-12
Mason day 0.250 0.250 0.250 679.00 169.75 169.75 169.75 L-10
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
c) Machinery
Stressing jack with pump hour 2.500 2.500 2.500 559.65 1,399.13 1,399.13 1,399.13 P&M-109
Grouting pump with agitator hour 1.000 1.000 1.000 798.00 798.00 798.00 798.00 P&M-096
Generator 33 KVA. hour 3.500 3.500 3.500 753.90 2,638.65 2,638.65 2,638.65 P&M-050
@ 20% on @ 20% on @ 20% on
d) Overhead charges 8,571.49 8,571.49 8,571.49
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 5,142.89 5,142.89 5,142.89
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 0.377 MT (a+b+c+d+e) 56,571.84 56,571.84 56,571.84
Rate per MT = (a+b+c+d+e)/0.377 150,057.94 150,057.94 150,057.94
Say 150,058.00 150,058.00 150,058.00
Note Cost of HT steel has been taken for delivery at site.
Hence carriage has not been considered.
14.04 2702
Providing and laying Cement concrete wearing coat
M-30 grade including reinforcement complete as per
drawing and Technical Specifications
Unit = 1 cum
Taking output = 1 cum
a) Material
cum 1.000 6,414.62 6,414.62
Cement concrete M30 Grade Refer relevant item of Item No. - 14.01
cum 1.000 6,449.54 6,449.54
concrete in Item 14.1 excluding formwork C
cum 1.000 6,569.26 6,569.26
tonne 0.075 52,080.00 3,906.00
HYSD bar reinforcement Rate as per item No
tonne 0.075 52,154.00 3,911.55 Item No. - 14.02
14.2(Excluding OH & CP)
tonne 0.075 52,300.00 3,922.50
b) Labour
Mazdoor for cleaning deck slab concrete surface. day 0.150 0.150 0.150 511.52 76.73 76.73 76.73 L-13
Unit = sqm
Taking output = 72.46 sqm (2 tonnes)(0.869 cum)
assuming a density of 2.3 tonnes/cum.
a) Labour
Mate day 0.490 0.490 0.490 617.00 302.33 302.33 302.33 L-12
Mazdoor day 11.000 11.000 11.000 511.52 5,626.72 5,626.72 5,626.72 L-13
Mazdoor (Skilled) day 1.250 1.250 1.250 565.73 707.16 707.16 707.16 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.060 0.060 0.060 500.40 30.02 30.02 30.02 P&M-052
Air compressor 250 cfm hour 0.060 0.060 0.060 614.25 36.86 36.86 36.86 P&M-029
Mastic cooker 1 tonne capacity hour 6.000 6.000 6.000 1,042.50 6,255.00 6,255.00 6,255.00 P&M-056
Bitumen boiler 1500 litres capacity hour 6.000 6.000 6.000 743.40 4,460.40 4,460.40 4,460.40 P&M-055
Tractor for towing and positioning of mastic cooker
hour 1.000 1.000 1.000 1,876.50 1,876.50 1,876.50 1,876.50 P&M-026
and bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60 per
cent
Coarse aggregate(3.35mm to 9.5 mm size) = 40 per
cent .
Proportion of material required for mastic asphalt with
coarse aggregates (based on mix design done by
CRRI for a specific case)
i) Bitumen 80/100 or 60/70 or 30/40 @ 10.2 per cent
tonne 0.204 0.204 0.204 44,020.00 8,980.08 8,980.08 8,980.08 M-327
by weight of mix. 2 x 10.2/100 = 0.204
ii) Crusher stone dust @ 31.9 per cent by weight of
mix = 2 x 31.9/100 = 0.638 tonnes = 0.638/1.625 = cum 0.390 0.390 0.390 1,887.12 735.98 735.98 735.98 M-020
0.39
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m
a) Material
Cement concreteM30 Grade Refer relevant item of cum 4.092 6,414.62 26,248.62
Item No. - 14.01
concrete in Item 14.1(C) by using batching plant, cum 4.092 6,449.54 26,391.51
C
excluding formwork i.e. per cum basic cost (a+b+c) cum 4.092 6,569.26 26,881.40
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
b) Overhead charges @ 20% on (a) @ 20% on (a) @ 20% on (a) 15,248.15 15,293.10 15,427.64
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m.
a) Material
Cement concreteM30 Grade Refer relevant item of cum 4.092 6,414.62 26,248.62
Item No. - 14.01
concrete in Item 14.1(C) by using batching plant, cum 4.092 6,449.54 26,391.51
C
excluding formwork i.e. per cum basic cost (a+b+c) cum 4.092 6,569.26 26,881.40
Add 12 per cent of above cost for form work. 3,149.83 3,166.98 3,225.77
tonne 0.865 52,080.00 45,049.20
HYSD bar reinforcement Rate as per item No
tonne 0.865 52,154.00 45,113.21 Item No. - 14.02
14.2(Excluding OH & CP)
tonne 0.865 52,300.00 45,239.50
refer MoRTH SD / 202.
b) Overhead charges @ 20% on (a) @ 20% on (a) @ 20% on (a) 14,889.53 14,934.34 15,069.33
Unit = 1 RM
Taking output = 2 x 50 m span = 100 m
a) Material:
1) ISMC 100 = 2.806 x 1.05 = 2.946 MT tonne 2.946 2.946 2.946 63,806.54 187,974.08 187,974.08 187,974.08 M-181
2) MS Flat = 0.964 x 1.05 = 1.012 MT tonne 1.012 1.012 1.012 63,806.54 64,572.22 64,572.22 64,572.22 M-181
3) MS bars = 0.17 x 1.05 = 0.180 MT tonne 0.180 0.180 0.180 63,806.54 11,485.18 11,485.18 11,485.18 M-125
4) MS bolts, nuts and washers tonne 0.150 0.150 0.150 64.83 9.72 9.72 9.72 M-129
b) Overhead charges @ 20% on (a) @ 20% on (a) @ 20% on (a) 1,118.80 1,126.00 1,149.80
c) Overhead charges @ 20% on (a) @ 20% on (a) @ 20% on (a) 1,175.80 1,182.80 1,206.60
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concreteM30 Grade Refer relevant item of cum 1.000 6,468.00 6,468.00
concrete in item 12.8(G)by using batching plant, Item No. - 12.08
cum 1.000 6,504.00 6,504.00
excluding formwork i.e. per cum basic cost. (a+b+c) G
(Excluding OH & CP). cum 1.000 6,623.00 6,623.00
( Refer relevant item of concrete in item No. 13.8 (G)
except that form work may be added at the rate of 2
129.36 130.08 132.46
per cent of cost against 3.5 per cent provided in the
foundation concrete.
tonne 0.050 52,080.00 2,604.00
HYSD bar reinforcement Rate as per item No
tonne 0.050 52,154.00 2,607.70 Item No. - 14.02
14.02(Excluding OH & CP)
tonne 0.050 52,300.00 2,615.00
b) Overhead charges @ 20% on (a) @ 20% on (a) @ 20% on (a) 1,840.27 1,326.82 1,351.09
Unit = 1 cum
Taking output = 1 cum
Grade of concrete - M40
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 1.000 1.000 1.000 5,519.00 5,519.00 5,519.00 5,519.00
Concrete - 20.12
Water for curing Kl 0.525 0.525 0.525 16.00 8.40 8.40 8.40 M-191
HYSD steel . tonne 0.100 0.100 0.100 46,496.54 4,649.65 4,649.65 4,649.65 M-083
HT strand with 5 per cent as wastage and extra
tonne 0.060 0.060 0.060 63,806.54 3,828.39 3,828.39 3,828.39 M-118
length for anchoring
LDO for steam curing Litre 37.000 37.000 37.000 83.00 3,071.00 3,071.00 3,071.00 M-121
Add consumables such as binding wire, foam,
packing tape, shuttering oil, HDPE pipe for
170.76 170.76 170.76
unbonding of strand, bolt & nuts etc @ 1 per cent of
material cost
b) Labour
the rates at Sl. No. i), ii), iii) & iv) shall be added
14.18 2600 Asphaltic Plug joint
Cost for 12 m Modular strip/box seal joint = (a+b+c+d) 134,075.52 134,075.52 134,075.52
Rate per m = (a+b+c+d)/12 11,172.96 11,172.96 11,172.96
Say 11,173.00 11,173.00 11,173.00
Note 1. The installation shall be done by the manufacturer
or his authorised representative to the satisfaction of
the Engineer.
2. The concreting for joining the expansion joint
assembly with the deck has not been included in this
analysis as the same is catered in the quantities of
RCC deck.
3. The anchoring bars of the expansion joint
assembly shall be welded to the main reinforcement
of the deck.
14.23 2600 Modular Strip / Box Seal Joint
Cost for 12 m Modular strip/box seal joint = (a+b+c+d) 134,330.40 134,330.40 134,330.40
Rate per m = (a+b+c+d)/12 11,194.20 11,194.20 11,194.20
Say 11,194.00 11,194.00 11,194.00
Note 1. The installation shall be done by the manufacturer
or his authorised representative to the satisfaction of
the Engineer.
2. The concreting for joining the expansion joint
assembly with the deck has not been included in this
analysis as the same is catered in the quantities of
RCC deck.
3. The anchoring bars of the expansion joint
assembly shall be welded to the main reinforcement
of the deck.
Painting with synthetic enamel paint bridge No. and
14.24
span arrangements
Painting two coats after filling the surface with
synthetic enamel paint bridge No. and span
arrangements as per as directed by Engineer.
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
Unit = Nos.
Taking output = 1 Nos.
a) Labour
Mate day 0.006 0.006 0.006 617.00 3.70 3.70 3.70 L-12
Painter day 0.100 0.100 0.100 679.00 67.90 67.90 67.90 L-18
Mazdoor day 0.050 0.050 0.050 511.52 25.58 25.58 25.58 L-13
b) Material
Paint conforming to requirement of clause 803.3. Litre 0.300 0.300 0.300 172.36 51.71 51.71 51.71 M-131
Per Sqm Basic Cost of Labour & Material (a+b) 157.302 157.302 157.302
Corrosion Inhibiting Admixture @ 3 kg per cubic Meter kg 300.000 300.000 300.000 70.00 21,000.00 21,000.00 21,000.00
b) Overhead charges @ 20% on (a) @ 20% on (a) @ 20% on (a) 4,200.00 4,200.00 4,200.00
Unit = MT
Taking output = 17.135 MT
a) Material
Structural steel in plates, angles, etc including 5 per
tonne 17.992 17.992 17.992 63,806.54 1,148,007.35 1,148,007.35 1,148,007.35 M-181
cent wastage
Nuts & bolts Kg 180.000 180.000 180.000 64.83 11,668.86 11,668.86 11,668.86 M-129
b) Labour
(for cutting, bending, making holes, joining, welding
and erecting in position)
Mate day 21.097 21.097 21.097 617.00 13,016.85 13,016.85 13,016.85 L-12
Fitter day 77.108 77.108 77.108 738.00 56,905.70 56,905.70 56,905.70 L-08
Blacksmith day 77.108 77.108 77.108 679.00 52,356.33 52,356.33 52,356.33 L-20
Welder day 77.108 77.108 77.108 738.00 56,905.70 56,905.70 56,905.70 L-02
Painter I Class day 32.385 32.385 32.385 679.00 21,989.42 21,989.42 21,989.42 L-18
Mazdoor day 263.708 263.708 263.708 511.52 134,891.92 134,891.92 134,891.92 L-13
Electrodes, cutting gas and other consumables @ 10
115,967.62 115,967.62 115,967.62
per cent of cost of (a) above
c) Machinery
Mobile hydraulic cran 10 tonne capacity (for
Hrs 68.540 68.540 68.540 1,240.05 84,993.03 84,993.03 84,993.03 P&M-104
fabrication)
Crane 35 tonne capacity (For loading & unloading @
Hrs 4.000 4.000 4.000 2,394.00 9,576.00 9,576.00 9,576.00 P&M-107
1hr for each operation)
Crane 35 tonne capacity (Forlifting and placing in
Hrs 4.000 4.000 4.000 2,394.00 9,576.00 9,576.00 9,576.00 P&M-107
position @ 2 hr)
Trailer 30 tonne capacity for transporting to site Hrs 4+L/15 4+L/15 4+L/15 2,883.30 17,299.80 17,299.80 17,299.80 P&M-014
Applying two coats primer before painting of truss
lits 899.588 899.588 899.588 288.00 259,081.34 259,081.34 259,081.34 M-145
and girder (42sqm/tonne)
Painting of Truss and Girder lits 899.588 899.588 899.588 180.70 162,555.55 162,555.55 162,555.55 M-058
Sundries @5% of above 107,739.57 107,739.57 107,739.57
Basic Cost of Labour, Material & Machinery (a+b+c)
132042.000 132042.000 132042.000
for 1 MT
Reference to Quantity Amount (Rs.)
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project ref.
Specification Project Project Project Project
I Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means
(i) Depth upto 3 m
a) Labour
Mate day 0.140 0.140 0.140 617.00 86.38 86.38 86.38 L-12
Mazdoor day 3.500 3.500 3.500 511.52 1,790.32 1,790.32 1,790.32 L-13
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 187.670 187.670 187.670
b) Overhead charges @ 20% on @ 20% on
@ 20% on (a) 375.34 375.34 375.34
(a) (a)
c) Contractor's profit @ 10% on @ 10% on @ 10% on
225.20 225.20 225.20
(a+b) (a+b) (a+b)
Cost for 10 cum = a+b+c 2,477.24 2,477.24 2,477.24
Rate per cum = (a+b+c)/10 247.72 247.72 247.72
Say 248.00 248.00 248.00
Note 1. Cost of dewatering may be added where required upto, 10 per cent of labour cost Assessment for dewatering shall be made as per site conditions.
2.The excavated earth can be used partially for backfilling of foundation pit and partly for road work except for marshy soil. Hence cost of disposal has not been added except for
marshy soil. This remark is common to all cases of item 12.1 excluding marshy soil.
3.The cost of shoring and shuttering, where needed, may be added @ 1 per cent on cost of excavation for open foundation.
15.01 A (ii) Depth 3 m to 6 m
(I)
a) Labour
Mate/Supervisor day 0.180 0.180 0.180 617.00 111.06 111.06 111.06 L-12
Mazdoor day 4.500 4.500 4.500 511.52 2,301.84 2,301.84 2,301.84 L-13
b) Overhead charges @ 20% on @ 20% on
@ 20% on (a) 482.58 482.58 482.58
(a) (a)
c) Contractor's profit @ 10% on @ 10% on @ 10% on
289.55 289.55 289.55
(a+b) (a+b) (a+b)
Cost for 10 cum = a+b+c 3,185.03 3,185.03 3,185.03
Rate per cum = (a+b+c)/10 318.50 318.50 318.50
Say 319.00 319.00 319.00
Note Cost of dewatering may be added where required upto 15 per cent of labour cost. Assessment for dewatering shall be done as per actual ground conditions.
15.01 A (iii) Depth above 6 m
(I)
a) Labour
Mate/Supervisor day 0.240 0.240 0.240 617.00 148.08 148.08 148.08 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
b) Overhead charges @ 20% on @ 20% on
@ 20% on (a) 643.44 643.44 643.44
(a) (a)
c) Contractor's profit @ 10% on @ 10% on @ 10% on
386.06 386.06 386.06
(a+b) (a+b) (a+b)
Cost for 10 cum = a+b+c 4,246.70 4,246.70 4,246.70
Rate per cum = (a+b+c)/10 424.67 424.67 424.67
Say 425.00 425.00 425.00
Note 1. Cost of dewatering may be added where required
upto 20 per cent of labour cost. Assessment for
dewatering shall be made as per site conditions..
A Manual Means
Unit = cum
Taking output = 120 cum
a) Labour
Mate day 0.210 0.210 0.210 617.00 129.57 129.57 129.57 L-12
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
Driller day 2.000 2.000 2.000 558.00 1,116.00 1,116.00 1,116.00 L-06
Blaster day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-03
b) Machinery
Air compressor hour 6.000 6.000 6.000 614.25 3,685.50 3,685.50 3,685.50 P&M-029
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Unit = cum
Taking out put = 1 cum
PCC-15 nominal mix. Rate may be taken as per item Item No. -
Say 8,121.00 8,168.00 8,347.00
15.11. 15.11
15.03 304 Sand Filling in Foundation Trenches as per Drawing
& Technical Specification
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
b) Machinery
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading @ 30 mins per trip )
Water for curing KL 2.415 2.415 2.415 16.00 38.64 38.64 38.64 M-191
b) Labour
Mate day 0.480 0.480 0.480 617.00 296.16 296.16 296.16 L-12
Mason day 4.000 4.000 4.000 679.00 2,716.00 2,716.00 2,716.00 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Water tanker (speed @ 20km/hr and return speed @
30 km/hr and spreading @ 30 mins per trip )
a) Material
Stone cum 5.500 5.500 5.500 933.45 5,133.98 5,133.98 5,133.98 M-170
Through and bond stone each 35.000 35.000 35.000 59.77 2,091.95 2,091.95 2,091.95 M-184
(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as sub-analysis)
Sub-Analysis
cum 1.500 1.500 1.500 5,125.00 7,687.50 7,687.50 7,687.50 of Concrete -
20.01 (A)
b) Labour
Mate day 0.660 0.660 0.660 617.00 407.22 407.22 407.22 L-12
Mason day 7.500 7.500 7.500 679.00 5,092.50 5,092.50 5,092.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Overhead charges @ 20% on @ 20% on @ 20% on
5,003.37 5,003.37 5,003.37
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
3,002.02 3,002.02 3,002.02
(a+b+c) (a+b+c) (a+b+c)
Cost for 5 cum = a+b+c+d 33,022.21 33,022.21 33,022.21
Rate per cum (a+b+c+d)/5 6,604.44 6,604.44 6,604.44
Say 6,604.00 6,604.00 6,604.00
1404.3 (B) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone cum 5.500 5.500 5.500 611.60 3,363.80 3,363.80 3,363.80 M-147
Through and bond stone each 35.000 35.000 35.000 59.77 2,091.95 2,091.95 2,091.95 M-184
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in sub-analysis)
Sub-Analysis
cum 1.550 1.550 1.550 5,125.00 7,943.75 7,943.75 7,943.75 of Concrete -
20.01 (A)
b) Labour
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Mate day 0.600 0.600 0.600 617.00 370.20 370.20 370.20 L-12
Mason day 6.000 6.000 6.000 679.00 4,074.00 4,074.00 4,074.00 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Overhead charges @ 20% on @ 20% on @ 20% on
4,489.48 4,489.48 4,489.48
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
2,693.69 2,693.69 2,693.69
(a+b+c) (a+b+c) (a+b+c)
Cost for 5 cum = a+b+c+d 29,630.54 29,630.54 29,630.54
Rate per cum (a+b+c+d)/5 5,926.11 5,926.11 5,926.11
Say 5,926.00 5,926.00 5,926.00
Note The labour already considered in cement mortar has
been taken into account while proposing labour for
masonry works.
15.07 1300 Brick Masonry Work in Cement Mortar 1:3 in Sub-
structure complete excluding Pointing and Plastering,
as per Drawing and Technical Specifications.
Unit = cum
Taking output = 1 cum
a) Material
Bricks Ist class each 500.000 500.000 500.000 3.50 1,750.00 1,750.00 1,750.00 M-079
Cement mortar 1:3 (Rate as sub-analysis)
Sub-Analysis
cum 0.240 0.240 0.240 5,125.00 1,230.00 1,230.00 1,230.00 of Concrete -
20.01 (A)
Water for curing KL 0.483 0.483 0.483 16.00 7.73 7.73 7.73 M-191
b) Labour
Mate day 0.064 0.064 0.064 617.00 39.49 39.49 39.49 L-12
Mason day 0.800 0.800 0.800 679.00 543.20 543.20 543.20 L-10
Mazdoor day 0.800 0.800 0.800 511.52 409.22 409.22 409.22 L-13
Add for scaffolding @ 5 Percent of cost of material
and labour 198.98 198.98 198.98
c) Machinery
Unit = sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as sub-analysis)
Sub-Analysis
cum 0.030 0.030 0.030 5,125.00 153.75 153.75 153.75 of Concrete -
20.01 (A)
b) Labour
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mason day 0.500 0.500 0.500 679.00 339.50 339.50 339.50 L-10
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
c) Overhead charges @ 20% on @ 20% on @ 20% on
154.74 154.74 154.74
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
92.84 92.84 92.84
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm = a+b+c+d 1,021.27 1,021.27 1,021.27
Rate per sqm (a+b+c+d)/10 102.13 102.13 102.13
Say 102.00 102.00 102.00
15.09 1300
Plastering with cement mortar (1:3 ) on brick work in
sub-structure as per Technical Specification
Unit = sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as sub-analysis)
Sub-Analysis
cum 0.144 0.144 0.144 5,125.00 738.00 738.00 738.00 of Concrete -
20.01 (A)
Water for curing KL 0.139 0.139 0.139 16.00 2.22 2.22 2.22 M-191
b) Labour
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mason day 0.500 0.500 0.500 679.00 339.50 339.50 339.50 L-10
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
Add for scaffolding @ 5 Percent of cost of material
and labour 68.01 68.01 68.01
c) Machinery
Water for curing KL 0.966 0.966 0.966 16.00 15.46 15.46 15.46 M-191
b) Labour
Mate day 0.096 0.096 0.096 617.00 59.23 59.23 59.23 L-12
Mason day 1.200 1.200 1.200 679.00 814.80 814.80 814.80 L-10
Mazdoor day 1.200 1.200 1.200 511.52 613.82 613.82 613.82 L-13
Add for scaffolding @ 5 Percent of cost of material
and labour 211.23 211.23 211.23
c) Machinery
Water for curing KL 0.966 0.966 0.966 16.00 15.46 15.46 15.46 M-191
b) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.500 1.500 1.500 511.52 767.28 767.28 767.28 L-13
Add for scaffolding @ 5 Percent of cost of material
and labour 250.59 250.59 250.59
c) Machinery
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Water for curing KL 0.966 0.966 0.966 16.00 15.46 15.46 15.46 M-191
b) Labour
Mate day 0.200 0.200 0.200 617.00 123.40 123.40 123.40 L-12
Mason day 2.500 2.500 2.500 679.00 1,697.50 1,697.50 1,697.50 L-10
Mazdoor day 2.500 2.500 2.500 511.52 1,278.80 1,278.80 1,278.80 L-13
Add for scaffolding @ 5 Percent of cost of material
and labour 312.58 312.58 312.58
c) Machinery
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.
hour 1,501.00 5,892.93 P&M-023
656
(ii) 12 KL capacity 0.143xL1+0.8
hour 1,327.00 6,853.96 P&M-024
75
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.055xL1+0.
hour 1,501.00 2,968.98 P&M-023
328
(ii) 12 KL capacity 0.073xL1+0.4
hour 1,327.00 3,487.36 P&M-024
38
(iii) 6 KL capacity 0.146xL1+0.
hour 1,005.00 5,281.28 P&M-025
875
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 5879.000 5914.000 6033.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 8,817.89 8,869.73 9,049.12
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.
hour 1,501.00 5,892.93 P&M-023
656
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.055xL1+0.
hour 1,501.00 2,968.98 P&M-023
328
(ii) 12 KL capacity 0.073xL1+0.4
hour 1,327.00 3,487.36 P&M-024
38
(iii) 6 KL capacity 0.146xL1+0.
hour 1,005.00 5,281.28 P&M-025
875
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6221.000 6256.000 6375.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 9,330.89 9,382.73 9,562.12
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.420 0.420 0.420 617.00 259.14 259.14 259.14 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.055xL1+0.
hour 1,501.00 2,968.98 P&M-023
328
(ii) 12 KL capacity 0.073xL1+0.4
hour 1,327.00 3,487.36 P&M-024
38
(iii) 6 KL capacity 0.146xL1+0.
hour 1,005.00 5,281.28 P&M-025
875
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6272.000 6306.000 6426.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 9,407.01 9,458.85 9,638.24
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.055xL1+0.
hour 1,501.00 2,968.98 P&M-023
328
(ii) 12 KL capacity 0.073xL1+0.4
hour 1,327.00 3,487.36 P&M-024
38
(iii) 6 KL capacity 0.146xL1+0.
hour 1,005.00 5,281.28 P&M-025
875
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6496.000 6531.000 6650.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 9,743.39 9,795.23 9,974.62
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.
hour 1,501.00 5,892.93 P&M-023
656
(ii) 12 KL capacity 0.146xL1+0.8
hour 1,327.00 6,973.39 P&M-024
75
(iii) 6 KL capacity 0.292xL1+1.
hour 1,005.00 10,562.55 P&M-025
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6381.000 6417.000 6536.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 19,140.16 19,248.21 19,607.12
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.420 0.420 0.420 617.00 259.14 259.14 259.14 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.055xL1+0.
hour 1,501.00 2,968.98 P&M-023
328
(ii) 12 KL capacity 0.073xL1+0.4
hour 1,327.00 3,487.36 P&M-024
38
(iii) 6 KL capacity 0.146xL1+0.
hour 1,005.00 5,281.28 P&M-025
875
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6684.000 6718.000 6838.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 10,025.01 10,076.85 10,256.24
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.113 0.113 0.113 617.00 69.72 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 1.325 1.325 1.325 511.52 677.76 677.76 677.76 L-13
c) Machinery
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.380 0.380 0.380 617.00 234.46 234.46 234.46 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.055xL1+0.
hour 1,501.00 2,968.98 P&M-023
328
(ii) 12 KL capacity 0.073xL1+0.4
hour 1,327.00 3,487.36 P&M-024
38
(iii) 6 KL capacity 0.146xL1+0.
hour 1,005.00 5,281.28 P&M-025
875
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6522.000 6557.000 6676.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 9,782.39 9,834.23 10,013.62
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.
hour 1,501.00 5,892.93 P&M-023
656
(ii) 12 KL capacity 0.146xL1+0.8
hour 1,327.00 6,973.39 P&M-024
75
(iii) 6 KL capacity 0.292xL1+1.
hour 1,005.00 10,562.55 P&M-025
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6468.000 6504.000 6623.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 19,401.16 19,509.21 19,868.12
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.420 0.420 0.420 617.00 259.14 259.14 259.14 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.055xL1+0.
hour 1,501.00 2,968.98 P&M-023
328
(ii) 12 KL capacity 0.073xL1+0.4
hour 1,327.00 3,487.36 P&M-024
38
(iii) 6 KL capacity 0.146xL1+0.
hour 1,005.00 5,281.28 P&M-025
875
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 7448.000 7486.000 7617.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 10,155.51 10,207.35 10,386.74
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.
hour 1,501.00 5,892.93 P&M-023
656
(ii) 12 KL capacity 0.146xL1+0.8
hour 1,327.00 6,973.39 P&M-024
75
(iii) 6 KL capacity 0.292xL1+1.
hour 1,005.00 10,562.55 P&M-025
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6622.000 6658.000 6777.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 19,863.16 19,971.21 20,330.12
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.420 0.420 0.420 617.00 259.14 259.14 259.14 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.055xL1+0.
hour 1,501.00 2,968.98 P&M-023
328
(ii) 12 KL capacity 0.073xL1+0.4
hour 1,327.00 3,487.36 P&M-024
38
(iii) 6 KL capacity 0.146xL1+0.
hour 1,005.00 5,281.28 P&M-025
875
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6925.000 6959.000 7079.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 10,386.51 10,438.35 10,617.74
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.
hour 1,501.00 5,892.93 P&M-023
656
(ii) 12 KL capacity 0.146xL1+0.8
hour 1,327.00 6,973.39 P&M-024
75
(iii) 6 KL capacity 0.292xL1+1.
hour 1,005.00 10,562.55 P&M-025
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6955.000 6991.000 7110.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 20,862.16 20,970.21 21,329.12
Water for curing Kl 7.875 7.875 7.875 16.00 126.00 126.00 126.00 M-191
b) Labour
For pouring and placing
Mate day 0.420 0.420 0.420 617.00 259.14 259.14 259.14 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 9.000 9.000 9.000 511.52 4,603.68 4,603.68 4,603.68 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 37.5 x L1 37.5 x L1 37.5 x L1 13.41 15,087.19 15,087.19 15,087.19 P&M-128
For unloading hour 0.833 0.833 0.833 2,413.95 2,011.63 2,011.63 2,011.63 P&M-067
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.104xL1+0.
hour 1,501.00 5,621.25 P&M-023
625
(ii) 12 KL capacity 0.139xL1+0.8
hour 1,327.00 6,638.98 P&M-024
33
(iii) 6 KL capacity 0.278xL1+1.
hour 1,005.00 10,057.04 P&M-025
667
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 7435.000 7503.000 7730.000
d) Formwork @ 10 per cent on cost of concrete
i.e. cost of material, labour and machinery 11,151.24 11,253.01 11,594.82
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.
hour 1,501.00 5,892.93 P&M-023
656
(ii) 12 KL capacity 0.146xL1+0.8
hour 1,327.00 6,973.39 P&M-024
75
(iii) 6 KL capacity 0.292xL1+1.
hour 1,005.00 10,562.55 P&M-025
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 5969.000 6005.000 6124.000
d) Formwork @ 25 per cent on cost of concrete
i.e. cost of material, labour and machinery 44,760.40 45,030.51 45,927.80
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.
hour 1,501.00 5,892.93 P&M-023
656
(ii) 12 KL capacity 0.146xL1+0.8
hour 1,327.00 6,973.39 P&M-024
75
(iii) 6 KL capacity 0.292xL1+1.
hour 1,005.00 10,562.55 P&M-025
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6381.000 6417.000 6536.000
d) Formwork @ 25 per cent on cost of concrete
i.e. cost of material, labour and machinery 47,850.40 48,120.51 49,017.80
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.113 0.113 617.00 94.40 69.72 69.72 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 1.325 1.325 511.52 1,189.28 677.76 677.76 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.
hour 1,501.00 5,892.93 P&M-023
656
(ii) 12 KL capacity 0.146xL1+0.8
hour 1,327.00 6,973.39 P&M-024
75
(iii) 6 KL capacity 0.292xL1+1.
hour 1,005.00 10,562.55 P&M-025
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6468.000 6486.000 6605.000
d) Formwork @ 25 per cent on cost of concrete
i.e. cost of material, labour and machinery 48,502.90 48,638.96 49,536.25
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.
hour 1,501.00 5,892.93 P&M-023
656
(ii) 12 KL capacity 0.146xL1+0.8
hour 1,327.00 6,973.39 P&M-024
75
(iii) 6 KL capacity 0.292xL1+1.
hour 1,005.00 10,562.55 P&M-025
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6622.000 6658.000 6777.000
d) Formwork @ 25 per cent on cost of concrete
i.e. cost of material, labour and machinery 49,657.90 49,928.01 50,825.30
Water for curing Kl 15.750 15.750 15.750 16.00 252.00 252.00 252.00 M-191
b) Labour
For pouring and placing
Mate day 0.153 0.153 0.153 617.00 94.40 94.40 94.40 L-12
Mason day 1.500 1.500 1.500 679.00 1,018.50 1,018.50 1,018.50 L-10
Mazdoor day 2.325 2.325 2.325 511.52 1,189.28 1,189.28 1,189.28 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) tonne-km 75 x L1 75 x L1 75 x L1 13.41 30,174.38 30,174.38 30,174.38 P&M-128
For unloading hour 0.650 0.650 0.650 2,413.95 1,569.07 1,569.07 1,569.07 P&M-067
Hydraulic Boom placer pump hour 0.650 0.650 0.650 4,401.60 2,861.04 2,861.04 2,861.04 P&M-069
Water tanker ( speed @ 20km/hr and return speed
@ 30 km/hr and 30 mins for unloading )
(i) 16 KL capacity 0.109xL1+0.
hour 1,501.00 5,892.93 P&M-023
656
(ii) 12 KL capacity 0.146xL1+0.8
hour 1,327.00 6,973.39 P&M-024
75
(iii) 6 KL capacity 0.292xL1+1.
hour 1,005.00 10,562.55 P&M-025
75
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) 6955.000 6991.000 7110.000
d) Formwork @ 25 per cent on cost of concrete
i.e. cost of material, labour and machinery 52,155.40 52,425.51 53,322.80
Unit = MT
Taking output = 8 MT
a) Material
MS bars including 5 per cent overlaps and wastage
tonne 8.400 8.400 8.400 46,496.54 390,570.97 390,570.97 390,570.97 M-083
Binding wire Kg 48.000 48.000 48.000 66.72 3,202.56 3,202.56 3,202.56 M-072
b) Labour for straightening, cutting, bending,
shifting to site, tying and placing in position
Mate day 0.160 0.160 0.160 617.00 98.72 98.72 98.72 L-12
Blacksmith day 1.000 1.000 1.000 679.00 679.00 679.00 679.00 L-01
Mazdoor day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
c) Machinery
Cutting Machine hour 5.333 5.333 5.333 528.15 2,816.80 2,816.80 2,816.80 P&M-076
Bending Machine hour 5.333 5.333 5.333 528.15 2,816.80 2,816.80 2,816.80 P&M-076
Electric generator 15 KVA hour 5.333 5.333 5.333 425.25 2,268.00 2,268.00 2,268.00 P&M-051
Tipper
Tipper for Transportation
(i) 18 cum capacity t.km 8 x L1 6.18 1,482.84 P&M-116
(ii) 14 cum capacity t.km 8 x L1 7.01 1,683.07 P&M-119
(iii) 10 cum capacity t.km 8 x L1 8.66 2,079.36 P&M-122
Loading & Unloading Time hour
(i) 18 cum capacity hour 1.000 2,883.30 2,883.30 P&M-014
(ii) 14 cum capacity hour 1.280 2,556.75 3,272.64 P&M-015
(iii) 10 cum capacity hour 1.778 2,274.30 4,043.20 P&M-016
Light weight Crane
At cutting bending yard hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102
At site hour 2.000 2.000 2.000 1,083.60 2,167.20 2,167.20 2,167.20 P&M-102
Per MT Basic Cost of Labour, Material & Machinery
51586.000 51660.000 51806.000
(a+b+c)
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including wastage @ 5 per M-056
cent ) metre 31.500 31.500 31.500 59.13 1,862.60 1,862.60 1,862.60
Average length of weep hole is taken as one metre
for the purpose of estimating.
MS clamp each. 30.000 30.000 30.000 41.70 1,251.00 1,251.00 1,251.00 M-122
collar for AC pipe (average) taking 10% of above M-056/10
pipe rate each. 10.000 10.000 10.000 5.91 59.13 59.13 59.13
Cement mortar 1:3 (Rate as sub-analysis) Sub-Analysis
of Concrete -
cum 0.050 0.050 0.050 5,125.00 256.25 256.25 256.25 20.01 (A)
b) Labour
Mate day 0.030 0.030 0.030 617.00 18.51 18.51 18.51 L-12
Mason day 0.500 0.500 0.500 679.00 339.50 339.50 339.50 L-10
Mazdoor day 0.250 0.250 0.250 511.52 127.88 127.88 127.88 L-13
c) Overhead charges @ 20% on @ 20% on @ 20% on
782.97 782.97 782.97
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
469.78 469.78 469.78
(a+b+c) (a+b+c) (a+b+c)
Cost for 30 Nos.= a+b+c+d 5,167.62 5,167.62 5,167.62
Rate per No. (a+b+c+d)/30 172.25 172.25 172.25
Say 172.00 172.00 172.00
15.15 2700 PCC M15 Grade leveling course below approach
slab complete as per drawing and Technical
specification
Unit = 1 cum
Taking output = 1 cum
Material
Case I PCC Grade M15 using batching plant & Concrete
pump
cum 1.000 5,594.00 5,594.00 Item No. -
Concrete, Rate as per item No. 15.11 (A), Case-I
cum 1.000 5,626.00 5,626.00 15.11 A
excluding formworks
cum 1.000 5,749.00 5,749.00 Case-I
c) Overhead charges @ 20% on @ 20% on
@ 20% on (a) 1,118.80 1,125.20 1,149.80
(a) (a)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
671.28 675.12 689.88
(a+b) (a+b) (a+b)
Rate per cum Say 7,384.00 7,426.00 7,589.00
Case II PCC Grade M15 using batching plant & manual
placing
cum 1.000 5,879.00 5,879.00 Item No. -
Concrete, Rate as per item No. 15.11 (A), Case-II
1.000 5,914.00 5,914.00 15.11 A
excluding formworks
1.000 6,033.00 6,033.00 Case-II
c) Overhead charges @ 20% on @ 20% on
@ 20% on (a) 1,175.80 1,182.80 1,206.60
(a) (a)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
705.48 709.68 723.96
(a+b) (a+b) (a+b)
Rate per cum Say 7,760.00 7,806.00 7,964.00
15.16 1500,1600 Reinforced cement concrete approach slab including
,1700 & reinforcement and formwork complete as per drawing
2704 and Technical specification
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concrete M30 Grade Refer relevant item of cum 1.000 6,468.00 6,468.00 Item No. -
concrete in item 15.11(G)by using batching plant, 15.11 G Case
cum 1.000 6,504.00 6,504.00
excluding formwork i.e. per cum basic cost (a+b+c) 1
(Excluding OH & CP) cum 1.000 6,623.00 6,623.00
Added at the rate of 2 Percent of cost 129.36 130.08 132.46
tonne 0.050 51,586.00 2,579.30
HYSD bar reinforcement Rate as per item No 15.13 Item No. -
tonne 0.050 51,660.00 2,583.00
(Excluding OH & CP) 15.13
tonne 0.050 51,806.00 2,590.30
b) Overhead charges @ 20% on @ 20% on
@ 20% on (a) 1,835.33 1,843.42 1,869.15
(a) (a)
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Unit = 1 cum
Taking output = 1 cum
a) Material
cum 1.000 6,468.00 6,468.00
Cement concrete M30 Grade Refer relevant item of Item No. -
cum 1.000 6,486.00 6,486.00
concrete in Item 15.12 (C) excluding formwork 15.12 C
cum 1.000 6,605.00 6,605.00
tonne 0.075 51,586.00 3,868.95
HYSD bar reinforcement Rate as per item No 15.13 Item No. -
tonne 0.075 51,660.00 3,874.50
(Excluding OH & CP) 15.13
tonne 0.075 51,806.00 3,885.45
b) Labour
Mazdoor for cleaning deck slab concrete surface. L-13
day 0.150 0.150 0.150 511.52 76.73 76.73 76.73
c) Overhead charges @ 20% on @ 20% on @ 20% on
2,082.74 2,087.45 2,113.44
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
1,249.64 1,252.47 1,268.06
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per cum (a+b+c+d) 13,746.05 13,777.14 13,948.67
Say 13,746.00 13,777.00 13,949.00
15.19 516 & Mastic Asphalt
2702
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Unit = sqm
Taking output = 72.46 sqm (2 tonnes)(0.869 cum)
assuming a density of 2.3 tonnes/cum.
a) Labour
Mate day 0.490 0.490 0.490 617.00 302.33 302.33 302.33 L-12
Mazdoor day 11.000 11.000 11.000 511.52 5,626.72 5,626.72 5,626.72 L-13
Mazdoor (Skilled) day 1.250 1.250 1.250 565.73 707.16 707.16 707.16 L-15
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.060 0.060 0.060 500.40 30.02 30.02 30.02 P&M-052
Air compressor 250 cfm hour 0.060 0.060 0.060 614.25 36.86 36.86 36.86 P&M-029
Mastic cooker 1 tonne capacity hour 6.000 6.000 6.000 1,042.50 6,255.00 6,255.00 6,255.00 P&M-056
Bitumen boiler 1500 litres capacity hour 6.000 6.000 6.000 743.40 4,460.40 4,460.40 4,460.40 P&M-055
Tractor for towing and positioning of mastic cooker P&M-026
and bitumen boiler hour 1.000 1.000 1.000 1,876.50 1,876.50 1,876.50 1,876.50
c) Material
Base mastic (without coarse aggregates) = 60 per
cent
Coarse aggregate(3.35mm to 9.5 mm size) = 40 per
cent .
Proportion of material required for mastic asphalt
with coarse aggregates (based on mix design done
by CRRI for a specific case)
i) Bitumen 80/100 or 60/70 or 30/40 @ 10.2 per cent M-327
by weight of mix. 2 x 10.2/100 = 0.204 tonne 0.204 0.204 0.204 44,020.00 8,980.08 8,980.08 8,980.08
ii) Crusher stone dust @ 31.9 per cent by weight of M-020
mix = 2 x 31.9/100 = 0.638 tonnes = 0.638/1.625 = cum 0.390 0.390 0.390 1,887.12 735.98 735.98 735.98
0.39
iii) Lime stone dust filler with calcium carbonate M-190
content not less than 80 per cent by weight @ 17.92
per cent by weight of mix = 2 x 17.92/100 = 0.36 tonne 0.360 0.360 0.360 3,753.00 1,351.08 1,351.08 1,351.08
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.020 0.020 0.020 617.00 12.34 12.34 12.34 L-12
Painter day 0.250 0.250 0.250 679.00 169.75 169.75 169.75 L-18
Mazdoor (Skilled) day 0.250 0.250 0.250 565.73 141.43 141.43 141.43 L-15
b) Material
Water based paint of approved quality for cement M-192
concrete surface Litres 5.000 5.000 5.000 97.30 486.50 486.50 486.50
c) Overhead charges @ 20% on @ 20% on @ 20% on
162.00 162.00 162.00
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
97.20 97.20 97.20
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm (a+b+c+d) 1,069.23 1,069.23 1,069.23
Rate per sqm (a+b+c+d)/10 106.92 106.92 106.92
Say 107.00 107.00 107.00
15.22 2605 Filler joint
(i) Providing & fixing 2 mm thick corrugated copper
plate in expansion joint complete as per drawing &
Technical Specification.
Unit = Running meter
Taking output = 12 m
a) Labour
Cutting, bending, carrying & fixing etc.
Mate day 0.040 0.040 0.040 617.00 24.68 24.68 24.68 L-12
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
Mazdoor (Skilled) day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
b) Material
Copper plate - 12m long x 250 mm wide kg 55.000 55.000 55.000 389.20 21,406.00 21,406.00 21,406.00 M-087
Area = 12 x 0.25 = 3 sqm
Weight = 3 x 0.002 x 8900 = 53.4 kg
Wastage @ 2.5 per cent = 1.33 kg/54.73 kg say = 55
kg.
c) Overhead charges @ 20% on @ 20% on @ 20% on
4,393.86 4,393.86 4,393.86
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
2,636.32 2,636.32 2,636.32
(a+b+c) (a+b+c) (a+b+c)
Cost for 12 m = (a+b+c+d) 28,999.48 28,999.48 28,999.48
Rate per m = (a+b+c+d)/12 2,416.62 2,416.62 2,416.62
Say 2,417.00 2,417.00 2,417.00
15.22 (ii) Providing & fixing 20 mm thick compressible fibre
board in expansion joint complete as per drawing &
Technical Specification.
Unit = Running meter
Taking output = 12 m
a) Labour
For carrying, placing & fixing.
Mate day 0.008 0.008 0.008 617.00 4.94 4.94 4.94 L-12
Mazdoor day 0.100 0.100 0.100 511.52 51.15 51.15 51.15 L-13
Mazdoor (Skilled) day 0.100 0.100 0.100 565.73 56.57 56.57 56.57 L-15
b) Material
20 mm thick compressible fibre board 12 m long x 25 M-085
cm deep. sqm 3.000 3.000 3.000 735.00 2,205.00 2,205.00 2,205.00
Area = 12 x 0.25 = 3 sqm
c) Overhead charges @ 20% on @ 20% on @ 20% on
463.53 463.53 463.53
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
278.12 278.12 278.12
(a+b+c) (a+b+c) (a+b+c)
Cost for 12 m = (a+b+c+d) 3,059.31 3,059.31 3,059.31
Rate per m = (a+b+c+d)/12 254.94 254.94 254.94
Say 255.00 255.00 255.00
15.22 (iii) Providing and fixing in position 20 mm thick
premoulded joint filler in expansion joint for fixed
ends of simply supported spans not exceeding 10 m
to cater for a horizontal movement upto 20 mm,
covered with sealant complete as per drawing and
technical specifications.
a) Labour
Mate day 0.024 0.024 0.024 617.00 14.81 14.81 14.81 L-12
Mazdoor day 0.500 0.500 0.500 511.52 255.76 255.76 255.76 L-13
Mazdoor (Skilled) day 0.100 0.100 0.100 565.73 56.57 56.57 56.57 L-15
b) Material
Sand cum 0.012 0.012 0.012 1,994.03 23.93 23.93 23.93 M-005
Volume 12 x 0.1 x 0.01 = 0.012 cum
Weight 0.012 x 1400 = 16.8kg
Bitumen cum 0.001 0.001 0.001 46,556.37 46.56 46.56 46.56 M-074
16.8 x 0.06 = 1 kg
c) Overhead charges @ 20% on @ 20% on @ 20% on
79.53 79.53 79.53
(a+b) (a+b) (a+b)
d) Contractor's profit @ 10% on @ 10% on @ 10% on
47.72 47.72 47.72
(a+b+c) (a+b+c) (a+b+c)
Cost for 12 m = (a+b+c+d) 524.87 524.87 524.87
Rate per m = (a+b+c+d)/12 43.74 43.74 43.74
Say 44.00 44.00 44.00
Note For arriving at the final rate of filler joints per m
length and per cm depth of joint filling compound,
the rates at Sl. No. i), ii), iii) & iv) shall be added
15.23 710.1.4.of Back filling behind abutment, wing wall and return
IRC:78 & wall complete as per drawing and Technical
2200 Specification
Unit = cum
Taking output = 10 cum
A Granular material
a) Labour
Mate day 0.280 0.280 0.280 617.00 172.76 172.76 172.76 L-12
Mazdoor day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
b) Material
Granular material cum 12.000 12.000 12.000 1,887.12 22,645.48 22,645.48 22,645.48 M-009
c) Machinery
Plate compactor/power rammer hour 2.500 2.500 2.500 597.45 1,493.63 1,493.63 1,493.63 P&M-079
Water Tanker hour 0.050 0.050 0.050 1,005.00 50.25 50.25 50.25 P&M-025
d) Overhead charges @ 20% on @ 20% on @ 20% on
5,588.55 5,588.55 5,588.55
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
3,353.13 3,353.13 3,353.13
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10 cum of granular backfill = a+b+c+d+e
36,884.43 36,884.43 36,884.43
Rate per cum = (a+b+c+d+e)/10 3,688.44 3,688.44 3,688.44
Say 3,688.00 3,688.00 3,688.00
15.23 B Sandy material
a) Labour
Mate day 0.280 0.280 0.280 617.00 172.76 172.76 172.76 L-12
Mazdoor for filling, watering, ramming etc. day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
b) Material
Sand cum 12.000 12.000 12.000 1,544.03 18,528.37 18,528.37 18,528.37 M-006
c) Machinery
Plate compactor/power rammer hour 2.500 2.500 2.500 597.45 1,493.63 1,493.63 1,493.63 P&M-079
Water Tanker hour 0.060 0.060 0.060 1,005.00 60.30 60.30 60.30 P&M-025
d) Overhead charges @ 20% on @ 20% on @ 20% on
4,767.14 4,767.14 4,767.14
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
2,860.28 2,860.28 2,860.28
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10 cum of sandy backfill = a+b+c+d+e 31,463.12 31,463.12 31,463.12
Rate per cum = (a+b+c+d+e)/10 3,146.31 3,146.31 3,146.31
Say 3,146.00 3,146.00 3,146.00
Quantity Amount (Rs.)
Reference to
Rate Remarks/
Sr No MORT&H Description Unit For Large For Medium For Small Medium
(Rs.) Large Project Small Project Input ref.
Specification Project Project Project Project
Unit = cum
Taking output = 10 cum.
a) Labour
Mate day 0.320 0.320 0.320 617.00 197.44 197.44 197.44 L-12
Mazdoor for filling, watering, ramming etc. day 7.000 7.000 7.000 511.52 3,580.64 3,580.64 3,580.64 L-13
Mazdoor (Skilled) day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
b) Material
Filter media of stone aggregate conforming to clause M-011
2504.2.2. of MoRTH specifications. cum 12.000 12.000 12.000 1,215.07 14,580.87 14,580.87 14,580.87
c) Machinery
Water Tanker of 6 KL capacity hour 0.060 0.060 0.060 1,005.00 60.30 60.30 60.30 P&M-025
d) Overhead charges @ 20% on @ 20% on @ 20% on
3,797.00 3,797.00 3,797.00
(a+b+c) (a+b+c) (a+b+c)
e) Contractor's profit @ 10% on @ 10% on @ 10% on
2,278.20 2,278.20 2,278.20
(a+b+c+d) (a+b+c+d) (a+b+c+d)
cost for 10 cum of Fiter Media = a+b+c+d+e 25,060.18 25,060.18 25,060.18
Rate per cum = (a+b+c+d+e)/10 2,506.02 2,506.02 2,506.02
Say 2,506.00 2,506.00 2,506.00
15.25 Painting with synthetic enamel paint bridge No. and
span arrangements
Painting two coats after filling the surface with
synthetic enamel paint bridge No. and span
arrangements as per as directed by Engineer.
Unit = Nos.
Taking output = 1 Nos.
a) Labour
Mate day 0.006 0.006 0.006 617.00 3.70 3.70 3.70 L-12
Painter day 0.100 0.100 0.100 679.00 67.90 67.90 67.90 L-18
Mazdoor day 0.050 0.050 0.050 511.52 25.58 25.58 25.58 L-13
b) Material
M-131
Paint conforming to requirement of clause 803.3. Litre 0.300 0.300 0.300 172.36 51.71 51.71 51.71
16.01 2503
Providing and laying boulders apron on river bed for
protection against scour with stone boulders weighing
not less than 40 kg each complete as per drawing and
Technical specification.
A Stone/Boulder
Unit = cum
Taking output = 1 cum
a) Material
Stone weighing not less than 40kg cum 1.000 1.000 1.000 1,994.63 1,994.63 1,994.63 1,994.63 M-003
Stone spalls of minimum 25 mm size cum 0.200 0.200 0.200 1,679.81 335.96 335.96 335.96 M-008
b) Labour
Mate day 0.044 0.044 0.044 617.00 27.15 27.15 27.15 L-12
Mason day 0.350 0.350 0.350 679.00 237.65 237.65 237.65 L-10
Mazdoor day 0.750 0.750 0.750 511.52 383.64 383.64 383.64 L-13
@ 20% on @ 20% on @ 20% on
c) Overhead charges 595.81 595.81 595.81
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 357.48 357.48 357.48
(a+b+c) (a+b+c) (a+b+c)
Rate per cum = (a+b+c+d) 3,932.32 3,932.32 3,932.32
Say 3,932.00 3,932.00 3,932.00
16.04 B Cement Concrete Blocks of size 0.3x0.3 x0.3 m cast
in cement concrete of Grade M15
Unit = cum
Taking output = 1 cum
cum 1.000 8,070.00 8,070.00
Concrete Grade M15 Rate as per item No. 12.08 (A, Item No. -
cum 1.000 8,118.00 8,118.00
Case-II) including OH & CP 12.08 A
cum 1.000 8,282.00 8,282.00
Add 2 per cent of cost to account for nominal surface
reinforcement and filling of granular material in 161.40 162.36 165.64
recesses between blocks.
Rate per cum 8,231.40 8,280.36 8,447.64
Say 8,231.00 8,280.00 8,448.00
16.05 2504 Providing and laying Filter material underneath
pitching in slopes complete as per drawing and
Technical specification
Unit = cum
Taking output = 1 cum
a) Material
Graded stone aggregate of required size cum 1.200 1.200 1.200 1,215.07 1,458.09 1,458.09 1,458.09 M-011
b) Labour
Mate day 0.050 0.050 0.050 617.00 30.85 30.85 30.85 L-12
Mazdoor (Skilled) day 0.250 0.250 0.250 565.73 141.43 141.43 141.43 L-15
Mazdoor * day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
@ 20% on @ 20% on @ 20% on
c) Overhead charges 428.38 428.38 428.38
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 257.03 257.03 257.03
(a+b+c) (a+b+c) (a+b+c)
Rate per cum = (a+b+c+d) 2,827.29 2,827.29 2,827.29
Say 2,827.00 2,827.00 2,827.00
Includes Mazdoor required for trimming of slope to
proper profile and preparation of bed.
16.06 700 &
2504 Geotextile Filter
Unit = sqm
Taking output = 10 sqm.
a) Labour
Mate day 0.016 0.016 0.016 617.00 9.87 9.87 9.87 L-12
Mazdoor day 0.300 0.300 0.300 511.52 153.46 153.46 153.46 L-13
Mazdoor (Skilled) day 0.100 0.100 0.100 565.73 56.57 56.57 56.57 L-15
Quantity Amount (Rs.)
Reference to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) ref.
Specification Project Project Project Project Project Project
b) Material
Permeable synthetic geotextile including 5 per cent M301
sqm 11.000 11.000 11.000 1.00 11.00 11.00 11.00
for overlap and wastage
@ 20% on @ 20% on @ 20% on
c) Overhead charges 46.18 46.18 46.18
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 27.71 27.71 27.71
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm = a+b+c+d 304.79 304.79 304.79
Rate per sqm = (a+b+c+d)/10 30.48 30.48 30.48
Say 30.00 30.00 30.00
16.07 2504.4 Toe protection
b) Add for cement concrete bedding (M15 Nominal cum 0.333 7,678.00 2,559.33
mix) vide Item 12.8 (A) excluding OH & CP . Quantity
Item No. -
shall be adopted as per design (Assume Rubble stone cum 0.333 7,728.00 2,576.00
12.08 A
Flooring thickness 300mm and cement concrete
bedding thickness 100mm) cum 0.333 7,892.00 2,630.67
Add 1 per cent of cost to account for excavation for
32.43 32.59 33.14
preparation of bed.
c) Material
Stone cum 1.000 1.000 1.000 1,994.63 1,994.63 1,994.63 1,994.63 M-003
Stone Spalls cum 0.200 0.200 0.200 1,679.81 335.96 335.96 335.96 M-008
d) Labour
Mate day 0.106 0.106 0.106 617.00 65.40 65.40 65.40 L-12
Mason day 0.665 0.665 0.665 679.00 451.54 451.54 451.54 L-10
L-13
Mazdoor (for laying stones, filling of quarry spalls) day 1.995 1.995 1.995 511.52 1,020.48 1,020.48 1,020.48
Unit = cum
Quantity Amount (Rs.)
Reference to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) ref.
Specification Project Project Project Project Project Project
Unit = cum
Taking Output = 1 cum
a) Material
Stone cum 1.000 1.000 1.000 1,994.63 1,994.63 1,994.63 1,994.63 M-003
Stone Spalls cum 0.200 0.200 0.200 1,679.81 335.96 335.96 335.96 M-008
b) Labour
Mate day 0.050 0.050 0.050 617.00 30.85 30.85 30.85 L-12
Mason day 0.250 0.250 0.250 679.00 169.75 169.75 169.75 L-10
Mazdoor day 1.000 1.000 1.000 511.52 511.52 511.52 511.52 L-13
Add 1 per cent of cost of (a+b) for trimming and
30.43 30.43 30.43
preparation of bed.
@ 20% on @ 20% on @ 20% on
c) Overhead charges 614.63 614.63 614.63
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 368.78 368.78 368.78
(a+b+c) (a+b+c) (a+b+c)
Rate per cum = (a+b+c+d) 4,056.55 4,056.55 4,056.55
Say 4,057.00 4,057.00 4,057.00
16.12 2503.3 Gabian Structure for Retaining Earth
Unit = cum
Taking output = 7 x 3 x 0.6 = 12.60 cum
a) Labour
Mate day 0.280 0.280 0.280 617.00 172.76 172.76 172.76 L-12
Mazdoor day 5.000 5.000 5.000 511.52 2,557.60 2,557.60 2,557.60 L-13
Mazdoor (Skilled) day 2.000 2.000 2.000 565.73 1,131.46 1,131.46 1,131.46 L-15
Quantity Amount (Rs.)
Reference to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) ref.
Specification Project Project Project Project Project Project
b) Material
Galvanised steel wire crates of mesh size 100 mm x M-102
100 mm woven with 4mm dia. GI wire in rolls of sqm 61.000 61.000 61.000 19.00 1,159.00 1,159.00 1,159.00
required size.
Stone boulders with least dimension of 200 mm cum 12.600 12.600 12.600 1,994.63 25,132.35 25,132.35 25,132.35 M-003
Stone spalls of minimum size 25 mm cum 2.520 2.520 2.520 1,679.81 4,233.13 4,233.13 4,233.13 M-008
@ 20% on @ 20% on @ 20% on
c) Overhead charges 6,877.26 6,877.26 6,877.26
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 4,126.36 4,126.36 4,126.36
(a+b+c) (a+b+c) (a+b+c)
Cost for 12.60 cum (a+b+c+d) 45,389.91 45,389.91 45,389.91
Rate per cum (a+b+c+d)/12.60 3,602.37 3,602.37 3,602.37
Say 3,602.00 3,602.00 3,602.00
Note Readymade woven wire crate rolls have been
considered in the rate analysis. In case readymade
rolls are not available, GI wire 4mm dia. @ 32 kg per
10 sqm may be provided. In that case 2 per cent of
the cost of GI wire may be added for weaving the wire
crates.
16.13 2503.3 Gabian Structure for Erosion Control, River Training
Works and Protection works
Unit = cum
Taking output = 2 x 1 x 0.3 x 10 Nos. = 6.00 cum
a) Labour
Mate day 0.140 0.140 0.140 617.00 86.38 86.38 86.38 L-12
Mazdoor day 2.500 2.500 2.500 511.52 1,278.80 1,278.80 1,278.80 L-13
Mazdoor (Skilled) day 1.000 1.000 1.000 565.73 565.73 565.73 565.73 L-15
b) Material
Galvanised steel wire crates of mesh size 100 mm x M-102
100 mm woven with 4mm dia. GI wire in rolls of sqm 65.000 65.000 65.000 19.00 1,235.00 1,235.00 1,235.00
required size to cover 6.00 cum.
Stone boulders with least dimension of 200 mm cum 6.000 6.000 6.000 1,994.63 11,967.78 11,967.78 11,967.78 M-003
Stone spalls of minimum size 25 mm cum 1.200 1.200 1.200 1,679.81 2,015.78 2,015.78 2,015.78 M-008
@ 20% on @ 20% on @ 20% on
c) Overhead charges 3,429.89 3,429.89 3,429.89
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 2,057.94 2,057.94 2,057.94
(a+b+c) (a+b+c) (a+b+c)
Cost for 6.00 cum (a+b+c+d) 22,637.30 22,637.30 22,637.30
Rate per cum (a+b+c+d)/6.00 3,772.88 3,772.88 3,772.88
Say 3,773.00 3,773.00 3,773.00
Note Readymade woven wire crate rolls have been
considered in the rate analysis. In case readymade
rolls are not available, GI wire 4mm dia. @ 32 kg per
10 sqm may be provided. In that case 2 per cent of
the cost of GI wire may be added for weaving the wire
crates.
Quantity Amount (Rs.)
Reference to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small Large Medium Small
(Rs.) ref.
Specification Project Project Project Project Project Project
16.14 2503
Unit = cum
Taking output = 2 x 1 x 1 m = 2 cum
a) Material
Crates made of Mesh type 10x12 (D=100 mm) Zn M-102
sqm 11.000 11.000 11.000 19.00 209.00 209.00 209.00
coated. (Mesh wire diameter 3.00 mm).
Surface area required = 11.00 sqm.
Stone boulder with least dimension 200mm cum 2.000 2.000 2.000 1,994.63 3,989.26 3,989.26 3,989.26 M-003
b) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mason (for plain stone work) 2nd class day 0.500 0.500 0.500 679.00 339.50 339.50 339.50 L-10
Mazdoor * day 1.500 1.500 1.500 511.52 767.28 767.28 767.28 L-13
@ 20% on @ 20% on @ 20% on
c) Overhead charges 1,070.88 1,070.88 1,070.88
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 642.53 642.53 642.53
(a+b+c) (a+b+c) (a+b+c)
Cost for 2.00 cum (a+b+c+d) 7,067.81 7,067.81 7,067.81
Rate per cum (a+b+c+d)/2 3,533.90 3,533.90 3,533.90
Say 3,534.00 3,534.00 3,534.00
Unit = Sqm
Taking output = 60 Sqm
a) Labour
Mate day 0.096 0.096 0.096 617.00 59.23 59.23 59.23 L-12
Mazdoor day 1.800 1.800 1.800 511.52 920.74 920.74 920.74 L-13
Mazdoor (skilled) day 0.600 0.600 0.600 565.73 339.44 339.44 339.44 L-15
b) Machinery
Transit truck agitator
For Transportation Transit truck agitator 6 cum P&M-128
t.km 13.800 x L 13.800 x L 13.800 x L 13.41 5,552.09 5,552.09 5,552.09
capacity
Unloding time hour 0.130 0.130 0.130 2,413.95 313.81 313.81 313.81 P&M-067
Concrete Pump hour 0.130 0.130 0.130 1,341.90 174.45 174.45 174.45 P&M-068
c) Materials
Item No. -
PCC M30 Grade Refer relevant item of concrete in 12.08 F
Item 12.8 (F) by using batching plant, excluding cum 6.000 6.000 6.000 6,237.00 37,422.00 37,638.00 38,352.00
formwork i.e. per cum basic cost (a+b+c)
Fabric Form mattress with 30% shrinkage sqm 78.000 78.000 78.000 62.55 4,878.90 4,878.90 4,878.90 M-108
Non-Woven Geotextile to be placed under concrete
filled fabric form including 15 per cent for overlap and sqm 9.000 9.000 9.000 62.55 562.95 562.95 562.95 M-107
shrinkage
@ 20% on @ 20% on @ 20% on
d) Overhead charges 10,044.72 10,087.92 10,230.72
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 6,026.83 6,052.75 6,138.43
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 60 sqm = a+b+c+d+e 66,295.15 66,580.27 67,522.75
Rate per sqm = (a+b+c+d+e)/60 1,104.92 1,109.67 1,125.38
Say 1,105.00 1,110.00 1,125.00
CHAPTER-17
REPAIR AND REHABILITATION
Quantity Amount (Rs.)
Reference to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project ref.
Specification Project Project Project
17.01 2811
Removal of existing cement concrete wearing coat
including its disposal complete as per Technical
Specification without causing any detrimental effect
to any part of the bridge structure and removal of
dismantled material with all lifts and lead upto 1000
m
Tractor-trolley. hour 0.500 0.500 0.500 1,876.50 938.25 938.25 938.25 P&M-026
@ 30% on @ 30% on @ 30% on
c) Overhead charges 630.08 630.08 630.08
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 273.03 273.03 273.03
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm = (a+d+c+d) 3,003.36 3,003.36 3,003.36
Rate per sqm = (a+b+c+d)/10 300.34 300.34 300.34
Say 300.00 300.00 300.00
17.02 2811
Removal of existing asphaltic wearing coat
comprising of 50 mm thick asphaltic concert laid
over 12 mm thick mastic asphalt including disposal
with all lift and lead upto 1000 m.
Unit = Sq m
Taking output = 10 sqm
a) Labour
Mate day 0.030 0.030 0.030 617.00 18.51 18.51 18.51 L-12
Mazdoor day 0.750 0.750 0.750 511.52 383.64 383.64 383.64 L-13
b) Machinery
P&M-15001
Air Compressor 250 cfm with pneumatic breaker. hour 0.750 0.750 0.750 625.80 469.35 469.35 469.35
+ P&M45001
Tractor-trolley. hour 0.400 0.400 0.400 1,876.50 750.60 750.60 750.60 P&M-026
@ 30% on @ 30% on @ 30% on
c) Overhead charges 486.63 486.63 486.63
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 210.87 210.87 210.87
(a+b+c) (a+b+c) (a+b+c)
Cost for 10 sqm = (a+d+c+d) 2,319.60 2,319.60 2,319.60
Rate per sqm = (a+b+c+d)/10 231.96 231.96 231.96
Say 232.00 232.00 232.00
17.03 2807 Guniting concrete surface with cement mortar
applied with compressor after cleaning surface and
spraying with epoxy complete as per Technical
Specification
Unit = Sq m
Taking output = 1 sqm
Assuming thickness 25 mm
a) Material
Cement kg 16.000 16.000 16.000 4.94 79.04 79.04 79.04 M-081/1000
Graded sand cum 0.040 0.040 0.040 1,994.03 79.76 79.76 79.76 M-005
Wire mesh 50mm x 50mm size of 3mm wire kg 2.000 2.000 2.000 66.72 133.44 133.44 133.44 M-194
Epoxy kg 0.670 0.670 0.670 764.50 512.22 512.22 512.22 M-095
Accelerator compound for guniting @ 4 per cent of
kg 0.640 0.640 0.640 125.00 80.00 80.00 80.00 M-227
weight of cement
Add 2 per cent of cost of material for
miscellaneous consumables like nozzles, wire 17.69 17.69 17.69
brush, cotton waste etc.
b) Labour
Mate day 0.007 0.007 0.007 617.00 4.32 4.32 4.32 L-12
Mason day 0.040 0.040 0.040 679.00 27.16 27.16 27.16 L-10
Mazdoor day 0.140 0.140 0.140 511.52 71.61 71.61 71.61 L-13
c) Machinery
Compressor with guniting equipment along with
hour 0.100 0.100 0.100 614.25 61.43 61.43 61.43 P&M-029
accessories
@ 30% on @ 30% on @ 30% on
d) Overhead charges 320.00 320.00 320.00
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 138.67 138.67 138.67
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Rate per sqm = (a+b+c+d+e) 1,525.33 1,525.33 1,525.33
Say 1,525.00 1,525.00 1,525.00
Quantity Amount (Rs.)
Reference to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project ref.
Specification Project Project Project
17.04 2800
Providing and inserting nipples with approved
fixing compound after drilling holes for grouting as
per Technical Specifications including subsequent
cutting/removal and sealing of the hole as
necessary of nipples after completion of grouting
with Cement/Epoxy
Unit = Number
Taking output = 1 No.
a) Material
Nipples each 1.000 1.000 1.000 26.41 26.41 26.41 26.41 M-128
Cement, fixing compound and consumables @ 15
3.96 3.96 3.96
per cent of cost of nipple
b) Labour
Mate day 0.006 0.006 0.006 617.00 3.70 3.70 3.70 L-12
Mazdoor (Skilled) labour for drilling day 0.080 0.080 0.080 565.73 45.26 45.26 45.26 L-15
Mazdoor (Skilled) labour for fixing nipple and
day 0.080 0.080 0.080 565.73 45.26 45.26 45.26 L-15
sealing inlets
Mazdoor for cutting and removing of nipples day 0.040 0.040 0.040 511.52 20.46 20.46 20.46 L-13
Add 10 per cent of labour cost for drilling holes etc 11.47 11.47 11.47
Unit = sqm
Taking output = 10 sqm for an average thickness of
25mm.
a) Labour
Mate day 0.060 0.060 0.060 617.00 37.02 37.02 37.02 L-12
Quantity Amount (Rs.)
Reference to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project ref.
Specification Project Project Project
Mazdoor (Skilled) day 0.750 0.750 0.750 565.73 424.30 424.30 424.30 L-15
Mazdoor day 0.750 0.750 0.750 511.52 383.64 383.64 383.64 L-13
b) Material
c) Machinery
Grout pump with agitator and accessories hour 2.000 2.000 2.000 798.00 1,596.00 1,596.00 1,596.00 P&M-096
@ 30% on @ 30% on @ 30% on
d) Overhead charges 4,606.79 4,606.79 4,606.79
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 1,996.27 1,996.27 1,996.27
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 10 sqm = a+b+c+d+e 21,959.02 21,959.02 21,959.02
Rate per sqm = (a+b+c+d+e)/10 2,195.90 2,195.90 2,195.90
Say 2,196.00 2,196.00 2,196.00
Note
This item is a proprietory item available in market
as pre-packed polymer concrete and is required to
be applied as per instructions of the manufacturer.
unit: sqm
Quantity Amount (Rs.)
Reference to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project ref.
Specification Project Project Project
Span assumed: 25 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 1 MT
Assume 12.7mm dia. Strand in 12T13 system.
Weight-9.42 kg/m of cable.
a) Material
Quantity Amount (Rs.)
Reference to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project ref.
Specification Project Project Project
Span assumed: 50 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 3.10 MT
Assume 12.7mm dia. Strand in 19T13 system.
Weight-14.73 kg/m of cable.
a) Material
HTS strand including 5 per cent wastage and extra
tonne 3.100 3.100 3.100 63,806.54 197,800.29 197,800.29 197,800.29 M-118
length for jacking
HDPE pipes 90mm dia including 5 per cent
metre 224.000 224.000 224.000 252.00 56,448.00 56,448.00 56,448.00 M-114
wastage
Cement for grouting tonne 1.010 1.010 1.010 4,940.00 4,989.40 4,989.40 4,989.40 M-081
Tube anchorage set complete with bearing plate,
each 8.000 8.000 8.000 48.45 387.58 387.58 387.58 M-189
permanent wedges etc
Epoxy kg 10.000 10.000 10.000 764.50 7,645.00 7,645.00 7,645.00 M-095
MS plates for deviator (where deviator blocks are
tonne 7.000 7.000 7.000 63,806.54 446,645.81 446,645.81 446,645.81 M-181
not provided)
Add 20 per cent cost of material for other
materials like lead sheet, sleeves, deviator fixtures 142,783.22 142,783.22 142,783.22
etc.
b) Labour
i) For making holes in the structure .
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor Semi-skilled) day 8.000 8.000 8.000 617.00 4,936.00 4,936.00 4,936.00 L-14
Mazdoor day 8.000 8.000 8.000 511.52 4,092.16 4,092.16 4,092.16 L-13
ii) For making and fixing anchorages for cables and
placement of cables .
Mate day 1.280 1.280 1.280 617.00 789.76 789.76 789.76 L-12
Blacksmith day 7.000 7.000 7.000 738.00 5,166.00 5,166.00 5,166.00 L-02
Mazdoor day 25.000 25.000 25.000 511.52 12,788.00 12,788.00 12,788.00 L-13
iii) For prestressing
Mate/Supervisor day 0.200 0.200 0.200 617.00 123.40 123.40 L-12
Fitter day 1.000 1.000 1.000 738.00 738.00 738.00 738.00 L-08
Quantity Amount (Rs.)
Reference to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project ref.
Specification Project Project Project
Mazdoor day 4.000 4.000 4.000 511.52 2,046.08 2,046.08 2,046.08 L-13
iv) For grouting
Mate/Supervisor day 0.260 0.260 0.260 617.00 160.42 160.42 160.42 L-12
Mason day 1.500 1.500 1.500 738.00 1,107.00 1,107.00 1,107.00 L-11
Mazdoor day 5.000 5.000 5.000 511.52 2,557.60 2,557.60 2,557.60 L-13
c) Machinery
Stressing jack with pump hour 7.000 7.000 7.000 559.65 3,917.55 3,917.55 3,917.55 P&M-109
Grouting pump with agitator hour 3.000 3.000 3.000 798.00 2,394.00 2,394.00 2,394.00 M-110
@ 30% on @ 30% on @ 30% on
d) Overhead charges 269,269.39 269,269.39 269,232.37
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 116,683.40 116,683.40 116,667.36
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 3.10 MT = a+b+c+d+e 1,283,517.41 1,283,517.41 1,283,340.95
Rate per MT = (a+b+c+d+e)/3.10 414,037.87 414,037.87 413,980.95
Say 414,038.00 414,038.00 413,981.00
17.14 2812
Providing external prestressing with high tensile
steel wires/strands including drilling for passage of
prestessing steel, all accessories for stressing and
stressing operation and grouting complete as per
drawing and Technical Specification
Mazdoor day 12.000 12.000 12.000 511.52 6,138.24 6,138.24 6,138.24 L-13
b) Machinery
i) Hire charges for jack of 40 tonne lifting capacity.
Day 3.000 3.000 3.000 378.00 1,134.00 1,134.00 1,134.00 P&M-114
(Lifting of span)
c) Material
Wooden packing cum 0.150 0.150 0.150 1,659.00 248.85 248.85 248.85 M-197
Cost of bearing. (Replacement of bearing) each 3.000 3.000 3.000 55,660.00 166,980.00 166,980.00 166,980.00 M-065
@ 30% on @ 30% on @ 30% on
d) Overhead charges 53,147.67 53,147.67 53,147.67
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 23,030.66 23,030.66 23,030.66
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost of repair of 3 bearings = a+b+c+d 253,337.21 253,337.21 253,337.21
Rate of repair per bearing = (a+b+c+d)/3 84,445.74 84,445.74 84,445.74
Say 84,446.00 84,446.00 84,446.00
Note The work entails replacement of all the bearings on
one side of the span.
17.16 2811 Rectification of Bearings as per Technical
Specifications
Unit = 1 No
Taking output = 3 No.
a) Labour
i) Mate day 0.640 0.640 0.640 617.00 394.88 394.88 394.88 L-12
ii) Mazdoor (Skilled) day 4.000 4.000 4.000 565.73 2,262.92 2,262.92 2,262.92 L-15
iii) Mazdoor day 12.000 12.000 12.000 511.52 6,138.24 6,138.24 6,138.24 L-13
b) Machinery
i) Hire charges for jack of 40 tonne lifting capacity.
Day 3.000 3.000 3.000 378.00 1,134.00 1,134.00 1,134.00 P&M-114
(Lifting of span)
c) Material
Cost of parts to be replaced for 3 bearings. each 3.000 3.000 3.000 630.00 1,890.00 1,890.00 1,890.00 M-064
Wooden packing cum 0.150 0.150 0.150 1,659.00 248.85 248.85 248.85 M-197
@ 30% on @ 30% on @ 30% on
d) Overhead charges 3,620.67 3,620.67 3,620.67
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 1,568.96 1,568.96 1,568.96
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost of repair of 3 bearings = a+b+c+d 17,258.51 17,258.51 17,258.51
Rate of repair per bearing = (a+b+c+d)/3 5,752.84 5,752.84 5,752.84
Say 5,753.00 5,753.00 5,753.00
Note The rectification of 3 bearings included in this
analysis are on the same side of the span.
17.17 Replacement of Expansion Joints complete as per
drawings
Unit -1 RM
Taking output = 12 RM
a) Material
Epoxy for bonding new concrete to old concrete @
kg 9.600 9.600 9.600 764.50 7,339.20 7,339.20 7,339.20 M-095
0.8 kg/sqm
cum 3.600 7,697.54 27,711.15
M-30 grade cement concrete excluding OH & CP Item No. -
cum 3.600 7,739.45 27,862.01
(Rate as per items 14.01 C (i) (p) 14.01 C (i)(p)
cum 3.600 7,883.11 28,379.19
b) Labour
Removal of old expansion joint including breaking
of concrete, cutting of lugs and shifting of broken
material etc.
Mate day 0.260 0.260 0.260 617.00 160.42 160.42 160.42 L-12
Mazdoor day 6.000 6.000 6.000 511.52 3,069.12 3,069.12 3,069.12 L-13
Mazdoor (Skilled) day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
@ 30% on @ 30% on @ 30% on
c) Overhead charges 11,568.83 11,614.08 11,769.24
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
d) Contractor's profit 5,013.16 5,032.77 5,100.00
(a+b+c) (a+b+c) (a+b+c)
Cost for replacement of 12 RM = a+b+c+d 55,144.74 55,360.47 56,100.04
Rate per RM = (a+b+c+d)/12 4,595.40 4,613.37 4,675.00
Say 4,595.00 4,613.00 4,675.00
Note
The rate for the installation of new expansion joints
may be taken from the chapter on superstructure.
Broken concrete will have to be replaced which has
been included in this analysis.
b) Machinery
Tractor-trolley for disposal of dismantled material hour 1.000 1.000 1.000 1,876.50 1,876.50 1,876.50 1,876.50 P&M-026
b) Material
cum 0.300 7,697.54 2,309.26
M-30 grade cement concrete excluding OH & CP Item No. -
cum 0.300 7,739.45 2,321.83
(Rate as per items 14.01 C (i) (p) 14.01 C (i)(p)
cum 0.300 7,883.11 2,364.93
This may be priced based on the rate given the
chapter of superstructure.
@ 30% on @ 30% on @ 30% on
c) Overhead charges 853.64 857.41 870.34
(a+b) (a+b) (a+b)
Quantity Amount (Rs.)
Reference to
Rate Remarks/ Input
Sr No MORT&H Description Unit For Large For Medium For Small (Rs.) Large Project Medium Project Small Project ref.
Specification Project Project Project
Unit = cum
Taking output = 60 cum
a) Labour
Mate day 0.040 617.00 24.68 L-12
Mazdoor day 1.000 511.52 511.52 L-13
b) Machinery
Excavator 1.1 cum bucket capacity hour 8.214 3,074.00 25,249.54 P&M-008
Jack Hammer hour 8.214 206.00 1,692.06 P&M-010
Loading & unloading charges for disposed of grabbed material cum 72.000 118.14 8,506.08 P&M-131
Tipper
(Using 10 cumcum
by 10 capacity for Tipper
capacity transportation
& 1 Cumtocapacity
dumpingLoader)
yard
t-km 120.000 10.53 1,263.50 P&M-123
considering lead @ 1km
c) Overhead charges @ 25% on (a+b) 9,311.85
d) Contractor's profit @ 10% on (a+b+c) 4,655.92
Cost for 60 cum = a+b+c+d 51,215.15
Rate per cum = (a+b+c+d)/60 853.59
say 854.00
18.02 303 & 304 Excavation in Hard Rock (blasting prohibited)
Excavation for Portal in Hard Rock (blasting prohibited) with
hydraulic
Unit = cumexcavator including cutting and loading in tippers,
trimming bottom and side slopes, in accordance with requirements
Taking output = 50 cum
of lines, grades and cross sections, and and disposal of excavated
a) Labour
materials including all lifts and lead upto 1000m
Mate day 0.040 617.00 24.68 L-12
Mazdoor day 1.000 511.52 511.52 L-13
b) Machinery
Excavator 1.1 cum bucket capacity hour 10.039 3,074.00 30,860.55 P&M-008
Jack Hammer hour 10.039 206.00 2,068.08 P&M-010
Loading & unloading charges for disposed of grabbed material cum 60.000 118.14 7,088.40 P&M-131
(Using
Tipper 10by 10
cumcum capacity
capacity for Tipper & 1 Cumtocapacity
transportation dumpingLoader)
yard t-km 100.000 10.53 1,052.92 P&M-123
considering
Credit lead @ 1km
for excavated rock found suitable for use @ 50 per cent of cum 30.000 319.70 -9,591.00 M-090
excavated
c) Overhead quantity
charges @ 25% on (a+b) 8,003.79
d) Contractor's profit @ 10% on (a+b+c) 4,001.89
Cost for 50 cum = a+b+c+d 44,020.82
Rate per cum = (a+b+c+d)/50 880.42
say 880.00
18.03 304 Excavation in Soil using Hydraulic Excavator and Tippers with
Disposal
Excavationupto
for1000
portalmetres.
in soil with hydraulic excavator including
cutting and loading in tippers, trimming bottom and side slopes, in
accordance with requirements of lines, grades and cross sections,
and and disposal of excavated materials including all lifts and
lead upto 1000m
Unit = cum
Taking output = 350 cum
a) Labour
Mate day 0.040 617.00 24.68 L-12
Mazdoor day 1.000 511.52 511.52 L-13
b) Machinery
Excavator 1.1 cum bucket capacity hour 5.024 3,074.00 15,442.79 P&M-008
Loading & unloading charges for disposed of grabbed material hour 5.024 2,274.30 11,425.35 P&M-016
(Using 10
Tipper by 10
cumcum capacity
capacity for Tipper & 1 Cumtocapacity
transportation dumpingLoader)
yard t-km 525.000 10.53 5,527.81 P&M-123
considering
c) Overhead leadcharges
@ 1km @ 25% on (a+b) 8,233.04
d) Contractor's profit @ 10% on (a+b+c) 4,116.52
Cost for 350 cum = a+b+c+d 45,281.71
Rate per cum = (a+b+c+d)/350 129.38
say 129.00
18.04 Drill steel with Drill jumboo
Excavation for tunnel by using drilling & blasting methods in all
types of rock including cost of all materials,machinery, labour,
scaling excavated surface, marking, ventilation, lighting, drainage,
removing and hauling the excavated muck outside tunnel upto
specified dump area and all other ancillary operations etc.
Unit = cum
Taking output = 480 Cum
a) Labour
Mate day 0.320 617.00 197.44 L-12
Mazdoor day 6.000 511.52 3,069.12 L-13
Mazdoor (Skilled) day 2.000 565.73 1,131.46 L-15
b) Machinery
Three boom Hydraulic Drill Jumbo hour 25.067 12,007.80 300,995.52 P&M-092
Excavator for Scaling hour 2.000 3,074.00 6,148.00 P&M-008
Tipper 10 cum capacity for transportation tonne.km 480 x 2 x L 10.53 28,800.00 P&M-123
Loading & unloading charges(Using by 10 cum capacity Tipper & cum 576.000 118.14 68,048.64 P&M-131
1Dozer
Cum (175
capacity
HP)Loader) hour 9.600 5,087.25 48,837.60 P&M-002
c) Materials
Explosives Kg 576.000 81.90 47,174.40 M-215
Delay Detonators Nos. 228.000 21.00 4,788.00 M-216
Electric Detonators Nos. 35.000 21.00 735.00 M-217
Detonation fuse coil Meter 50.000 19.00 950.00 M-218
3.7 m long extension rod Nos 1.043 10,000.00 10,434.78 M-219
Difter rod Nos 0.505 15,000.00 7,578.95 M-221
R32 shank adapter Nos 1.043 13,000.00 13,565.22 M-222
45 mm Button Bit Nos 3.692 3,000.00 11,076.92 M-223
18.05 305
Dewatering tunnel by pumping out water collected by natural
drainage inside tunnel including
Dewatering in tunnel by pumping out water collected by natural
drainage
Unit = cuminside tunnel including providing sump wherever
necessary, cost of all materials, machinery, labour, Taking
drainage and =
output 20000 Hour
all other ancillary operations etc., complete.
a) Labour
Mate day 100.000 617.00 61,700.00 L-12
Mazdoor day 2500.000 511.52 1,278,800.00 L-13
b) Machinery
Water Pump 10 HP hour 20000.000 328.65 6,573,000.00 P&M-097
c) Materials
GI Pipe 100 mm Dia Meter 500.000 496.00 248,000.00 M-239
Flange Kg. 41.667 1.00 41.67 M-241
Nut & Bolt Kg. 133.333 64.83 8,643.60 M-129
Bracket Kg. 1125.000 1.00 1,125.00 M-241
Credit for salvage value of GI Pipe @ 20 per cent Meter 100.000 -496.00 -49,600.00 M-239
Unit = cum
Taking output = 26 Tonne
a) Labour
Mate day 0.800 617.00 493.60 L-12
Mazdoor day 10.000 511.52 5,115.20 L-13
Mazdoor(Semi Skilled) day 5.000 617.00 3,085.00 L-14
Welder day 5.000 738.00 3,690.00 L-02
b) Machinery
Rotating Telehandlers hour 37.180 1,207.50 44,894.85 P&M-094
c) Materials
ISMB 350 Tonne 20.732 63,806.54 1,322,818.14 M-181
(Including
MS Channel0.25%
ISMCWastage)
75 Tonne 3.830 63,806.54 244,350.35 M-181
(Including
MS 0.25%
Plate 200 Wastage)
x 200 x 12 mm Tonne 1.504 63,806.54 95,949.09 M-181
(Including 0.25%(MWastage)
Nuts and bolts 16X40) Kg 151.200 64.83 9,801.84 M-129
Add 40 per cent of cost of a+b+c towards of Fabrication,
Erection,Temporary fixture, Handling of material, final matching 692,079.23
and field welding etc.
Unit = cum
Taking output = 120 Cum
a) Labour
Mate day 0.320 617.00 197.44 L-12
Mazdoor day 8.000 511.52 4,092.16 L-13
b) Machinery
Batching Plant of capacity 120 cum/hour hour 1.333 4,104.45 5,472.60 P&M-039
Generator 250 KVA hour 1.333 3,475.00 4,633.33 P&M-046
Loader 3.1 cum capacity hour 1.333 4,279.80 5,706.40 P&M-011
Transit truck agitator
For transportation (6 cum Capacity) tonne.km 300 x L 13.41 120,697.50 P&M-128
For loading & unloading hour 11.333 2,413.95 27,358.10 P&M-067
Shotcrete Machine @ 12 cum/hour hour 10.000 1,830.15 18,301.50 P&M-095
Compressor 500 cfm hour 10.000 2,752.05 27,520.50 P&M-030
c) Materials
Cement Tonne 49.440 4,940.00 244,233.60 M-081
Sand Cum 86.850 1,994.03 173,181.59 M-004
10 mm to 4.76 mm Aggregate Cum 52.080 1,887.12 98,281.37 M-039
Steel Fiber Tonne 6.120 46,496.54 284,558.85 M-225
Admixture @ 0.4 % of Cement Kg 197.760 167.49 33,121.93 M-182
Microsilica @ 6 % of Cement Kg 2966.400 32.00 94,924.80 M-226
Accelerator @ 4.5 % of Cement Kg 2224.800 125.00 278,100.00 M-227
Add 20 per cent of cost of a+b+c for Wastage due to rebound. 284,076.34
d) Overhead charges @ 25% on (a+b+c) 426,114.50
e) Contractor's profit @ 10% on (a+b+c+d) 213,057.25
Cost for 120 Cum = a+b+c+d+e 2,343,629.78
Rate per Cum = (a+b+c+d+e)/120 19,530.25
say 19,530.00
Unit = cum
Taking output = 120 Cum
a) Labour
Mate day 0.320 617.00 197.44 L-12
Mazdoor day 8.000 511.52 4,092.16 L-13
b) Machinery
Batching Plant of capacity 120 cum/hour hour 1.333 4,104.45 5,472.60 P&M-039
Generator 250 KVA hour 1.333 3,475.00 4,633.33 P&M-046
Loader 3.1 cum capacity hour 1.333 4,279.80 5,706.40 P&M-011
Transit truck agitator
For transportation (6 cum Capacity) tonne.km 300 x L 13.41 120,697.50 P&M-128
For loading & unloading hour 11.333 2,413.95 27,358.10 P&M-067
Shotcrete Machine @ 12 cum/hour hour 10.000 1,830.15 18,301.50 P&M-095
Compressor 500 cfm hour 10.000 2,752.05 27,520.50 P&M-030
c) Materials
Cement Tonne 49.440 4,940.00 244,233.60 M-081
Sand Cum 86.850 1,994.03 173,181.59 M-004
10 mm to 4.76 mm Aggregate Cum 52.080 1,887.12 98,281.37 M-039
Wiremesh (Including 10% for lapping) Sqm 1320.000 40.58 53,565.60 M-228
Admixture @ 0.4 % of Cement Kg 197.760 167.49 33,121.93 M-182
Microsilica @ 6 % of Cement Kg 2966.400 32.00 94,924.80 M-226
Accelerator @ 4.5 % of Cement Kg 2224.800 125.00 278,100.00 M-227
Add 20 per cent of cost of a+b+c for Wastage due to rebound. 237,877.69
d) Overhead charges @ 25% on (a+b+c) 356,816.53
e) Contractor's profit @ 10% on (a+b+c+d) 178,408.26
Cost for 120 Cum = a+b+c+d+e 1,962,490.91
Rate per Cum = (a+b+c+d+e)/120 16,354.09
say 16,354.00
18.09 2806 & Providing and fixing 25 mm diameter 3 meter long steel rock bolts
3200 including drilling 45 mm dia holes, plate, nuts, cement grout, cost
of all materials, machinery, labour, ventilation, lighting, drainage
and all other ancillary operations etc. complete as per Drawing
and Technical Specifications.
Unit = cum
Taking output = 155 Nos.
a) Labour
Mate day 0.480 617.00 296.16 L-12
Mazdoor day 8.000 511.52 4,092.16 L-13
Mason (IInd class) day 4.000 679.00 2,716.00 L-10
b) Machinery
Single boom Hydraulic Drill Jumbo hour 25.833 5,420.10 140,019.25 P&M-090
c) Materials
3.7 m long extension rod Nos 1.011 10,000.00 10,108.70 M-219
R32 shank adapter Nos 1.011 13,000.00 13,141.30 M-222
45 mm dia cross bit Nos 3.577 3,000.00 10,730.77 M-223
25 mm Tor Steel (Including 2.5% Wastage) Tonne 1.927 46,496.54 89,587.52 M-083
Add 15 per cent of cost of a+b+c towards of cutting ,making tip, 40,603.78
Threading,
d) Overheadnut , charges
plate,grouting
@ 25%and bit sharpening etc..
on (a+b+c) 77,823.91
e) Contractor's profit @ 10% on (a+b+c+d) 38,911.96
Cost for 155 Nos = a+b+c+d+e 428,031.51
Rate per Number = (a+b+c+d+e)/155 2,761.49
say 2,761.00
18.10 2806 & Providing and fixing 32 mm diameter 7 meter long steel rock bolts
3200 including drilling 51 mm dia holes, plate, nuts, cement grout, cost
of all materials, machinery, labour, ventilation, lighting, drainage
and all other ancillary operations etc. complete as per Drawing
and Technical Specifications.
Unit = cum
Taking output = 70 Nos.
a) Labour
Mate day 0.600 617.00 370.20 L-12
Mazdoor day 10.000 511.52 5,115.20 L-13
Mason (IInd class) day 5.000 679.00 3,395.00 L-10
b) Machinery
Single Boom Hydraulic hour 17.500 5,420.10 94,851.75 P&M-090
c) Materials
3.7 m long extension rod Nos 1.065 10,000.00 10,652.17 M-219
R32 shank adapter Nos 1.065 13,000.00 13,847.83 M-222
32 mm coupling sleeve Nos 1.065 12,000.00 12,782.61 M-220
51 mm dia button bit Nos 3.769 5,000.00 18,846.15 M-224
32 mm Tor Steel (Including 2.5% Wastage) Tonne 3.237 46,496.54 150,514.38 M-083
Add 15 per cent of cost of a+b+c towards of cutting ,making tip, 46,556.29
Threading, nut , plate, grouting and bit sharpening etc..
d) Overhead charges @ 25% on (a+b+c) 89,232.90
e) Contractor's profit @ 10% on (a+b+c+d) 44,616.45
Cost for 70 Nos = a+b+c+d+e 490,780.93
Rate per Number = (a+b+c+d+e)/70 7,011.16
say 7,011.00
Unit = cum
Taking output = 1.5 Tonne
a) Labour
Mate day 0.080 617.00 49.36 L-12
Mazdoor day 2.000 511.52 1,023.04 L-13
b) Machinery
Grouting machine @ 25 Bags Per Hours hour 1.200 798.00 957.60 P&M-096
Pump 10 HP hour 1.200 -
Single Boom Hydraulic hour 1.250 5,420.10 6,775.13 P&M-090
c) Materials
Cement Including 1% Wastage) Tonne 1.515 4,940.00 7,484.10 M-081
Cost of water (Water/Cement Ratio - 0.4) KL 0.606 16.00 9.70 M-191
3.7 m long extension rod Nos 0.076 10,000.00 760.87 M-219
R32 shank adapter Nos 0.076 13,000.00 989.13 M-222
32 mm coupling sleeve Nos 0.076 12,000.00 913.04 M-220
51 mm dia cross bit Nos 0.269 5,000.00 1,346.15 M-224
Add 5 per cent of cost of a+b+c towards of cutting ,making tip, 1,015.41
Threading, nut , plate, grouting and bit sharpening etc..
d) Overhead charges @ 25% on (a+b+c) 5,330.88
e) Contractor's profit @ 10% on (a+b+c+d) 2,665.44
Cost for 1.5 Tonne = a+b+c+d+e 29,319.85
Rate per Tonne = (a+b+c+d+e)/1.5 19,546.56
say 19,547.00
18.12 1700 Furnishing and Placing Reinforced cement concrete in Tunnel
18.12A 1700 A Work as per M20
RCC Grade drawing and Technical Specification
Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 4,533.00 543,960.00
Concrete - 20.05
Water for curing Kl 63.000 16.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.232 617.00 143.14 L-12
Mason day 1.500 738.00 1,107.00 L-11
Mazdoor day 4.300 511.52 2,199.54 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in Kilometer tonne-km 300 x L 13.41 120,697.50 P&M-128
For unloading hour 2.600 2,413.95 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 4,401.60 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @ 30 km/hr
and
(i) 1230KLmins for unloading )
capacity hour 20.990 1,501.00 31,505.99 P&M-023
Basic Cost of Labour, Material & Machinery (a+b+c) for 120
d) Formwork and staging 40 per cent of (a+b+c) cum 40.000 287,336.64
e) Overhead charges @ 25% on (a+b+c+d) 251,419.56
f) Contractor's profit @ 10% on (a+b+c+d+e) 125,709.78
Cost for 120 cum = a+b+c+d+e+f 1,382,807.58
Rate per cum = (a+b+c+d+e+f)/120 11,523.40
say 11,523.00
18.12B 1700 B RCC Grade M25
Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 4,945.00 593,400.00
Concrete - 20.07
Water for curing Kl 63.000 16.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.232 617.00 143.14 L-12
Mason day 1.500 738.00 1,107.00 L-11
Mazdoor day 4.300 511.52 2,199.54 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in Kilometer tonne-km 300 x L 13.41 120,697.50 P&M-128
For unloading hour 2.600 2,413.95 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 4,401.60 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @ 30 km/hr
and
(i) 1230KLmins for unloading )
capacity hour 20.990 1,501.00 31,505.99 P&M-023
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 Cum
d) Formwork and staging 40 per cent of (a+b+c) 40.000 307,112.64
e) Overhead charges @ 25% on (a+b+c+d) 268,723.56
f) Contractor's profit @ 10% on (a+b+c+d+e) 134,361.78
Cost for 120 cum = a+b+c+d+e+f 1,477,979.58
Rate per cum = (a+b+c+d+e+f)/120 12,316.50
say 12,316.00
18.12C 1700 C RCC Grade M 30
Using Batching Plant, Transit Mixer and Concrete Pump.
Unit = cum
Taking output = 120 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 5,032.00 603,840.00
Concrete - 20.09
Water for curing Kl 63.000 16.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.232 617.00 143.14 L-12
Mason day 1.500 738.00 1,107.00 L-11
Mazdoor day 4.300 511.52 2,199.54 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in Kilometer tonne-km 300 x L 13.41 120,697.50 P&M-128
For unloading hour 2.600 2,413.95 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 4,401.60 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @ 30 km/hr
and
(i) 1230KLmins for unloading )
capacity hour 20.990 1,501.00 31,505.99 P&M-023
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 Cum
d) Formwork and staging 40 per cent of (a+b+c) 40.000 311,288.64
e) Overhead charges @ 25% on (a+b+c+d) 272,377.56
f) Contractor's profit @ 10% on (a+b+c+d+e) 136,188.78
Cost for 120 cum = a+b+c+d+e+f 1,498,076.58
Rate per cum = (a+b+c+d+e+f)/120 12,483.97
say 12,484.00
18.12D 1700 D RCC Grade M35
Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum 120 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 5,186.00 622,320.00
Concrete - 20.11
Water for curing Kl 63.000 16.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.232 617.00 143.14 L-12
Mason day 1.500 738.00 1,107.00 L-11
Mazdoor day 4.300 511.52 2,199.54 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in Kilometer tonne-km 300 x L 13.41 120,697.50 P&M-128
For unloading hour 2.600 2,413.95 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 4,401.60 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @ 30 km/hr
and
(i) 1230KLmins for unloading )
capacity hour 20.990 1,501.00 31,505.99 P&M-023
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 Cum
d) Formwork and staging 40 per cent of (a+b+c) 40.000 318,680.64
e) Overhead charges @ 25% on (a+b+c+d) 278,845.56
f) Contractor's profit @ 10% on (a+b+c+d+e) 139,422.78
Cost for 120 cum = a+b+c+d+e+f 1,533,650.58
Rate per cum = (a+b+c+d+e+f)/120 12,780.42
say 12,780.00
18.12E 1700 E RCC Grade M-40
Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum 120 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 5,519.00 662,280.00
Concrete - 20.12
Water for curing Kl 63.000 16.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.232 617.00 143.14 L-12
Mason day 1.500 738.00 1,107.00 L-11
Mazdoor day 4.300 511.52 2,199.54 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in Kilometer tonne-km 300 x L 13.41 120,697.50 P&M-128
For unloading hour 2.600 2,413.95 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 4,401.60 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @ 30 km/hr
and
(i) 1230KLmins for unloading )
capacity hour 20.990 1,501.00 31,505.99 P&M-023
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 Cum
d) Formwork and staging 40 per cent of (a+b+c) 40.000 334,664.64
e) Overhead charges @ 25% on (a+b+c+d) 292,831.56
f) Contractor's profit @ 10% on (a+b+c+d+e) 146,415.78
Cost for 15 cum = a+b+c+d+e+f 1,610,573.58
Rate per cum = (a+b+c+d+e+f)/120 13,421.45
say 13,421.00
18.12F 1700 F RCC Grade M-45
Unit = 1 cum
Taking output = 120 cum 120 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 5,663.00 679,560.00
Concrete - 20.13
Water for curing Kl 63.000 16.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.232 617.00 143.14 L-12
Mason day 1.500 738.00 1,107.00 L-11
Mazdoor day 4.300 511.52 2,199.54 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in Kilometer tonne-km 300 x L 13.41 120,697.50 P&M-128
For unloading hour 2.600 2,413.95 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 4,401.60 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @ 30 km/hr
and
(i) 1230KLmins for unloading )
capacity hour 20.990 1,501.00 31,505.99 P&M-023
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 Cum
d) Formwork and staging 40 per cent of (a+b+c) 40.000 341,576.64
e) Overhead charges @ 25% on (a+b+c+d) 298,879.56
f) Contractor's profit @ 10% on (a+b+c+d+e) 149,439.78
Cost for 120 cum = a+b+c+d+e+f 1,643,837.58
Rate per cum = (a+b+c+d+e+f)/120 13,698.65
say 13,699.00
18.12G 1700 G RCC Grade M-50
Unit = 1 cum
Taking output = 120 cum 120 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 6,242.00 749,040.00
Concrete - 20.14
Water for curing Kl 63.000 16.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.232 617.00 143.14 L-12
Mason day 1.500 738.00 1,107.00 L-11
Mazdoor day 4.300 511.52 2,199.54 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in Kilometer tonne-km 300 x L 13.41 120,697.50 P&M-128
For unloading hour 2.600 2,413.95 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 4,401.60 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @ 30 km/hr
and
(i) 1230KLmins for unloading )
capacity hour 20.990 1,501.00 31,505.99 P&M-023
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 Cum
d) Formwork and staging 40 per cent of (a+b+c) 40.000 369,368.64
e) Overhead charges @ 25% on (a+b+c+d) 323,197.56
f) Contractor's profit @ 10% on (a+b+c+d+e) 161,598.78
Cost for 120 cum = a+b+c+d+e+f 1,777,586.58
Rate per cum = (a+b+c+d+e+f)/120 14,813.22
say 14,813.00
18.12H 1700 H RCC Grade M- 55
Unit = 1 cum
Taking output = 120 cum 120 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 6,321.00 758,520.00
Concrete - 20.15
Water for curing Kl 63.000 16.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.232 617.00 143.14 L-12
Mason day 1.500 738.00 1,107.00 L-11
Mazdoor day 4.300 511.52 2,199.54 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in Kilometer tonne-km 300 x L 13.41 120,697.50 P&M-128
For unloading hour 2.600 2,413.95 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 4,401.60 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @ 30 km/hr
and
(i) 1630KLmins for unloading )
capacity hour 20.990 1,501.00 31,505.99 P&M-023
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 Cum
d) Formwork and staging 40 per cent of (a+b+c) 40.000 373,160.64
e) Overhead charges @ 25% on (a+b+c+d) 326,515.56
f) Contractor's profit @ 10% on (a+b+c+d+e) 163,257.78
Cost for 120 cum = a+b+c+d+e+f 1,795,835.58
Rate per cum = (a+b+c+d+e+f)/120 14,965.30
say 14,965.00
18.12 I 1700 I RCC Grade M- 60
Unit = 1 cum
Taking output = 120 cum 120 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost cum 120.000 6,511.00 781,320.00
Concrete - 20.16
(Rate
Water as forincuring
sub-analysis of concrete) Kl 63.000 16.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.232 617.00 143.14 L-12
Mason day 1.500 738.00 1,107.00 L-11
Mazdoor day 4.300 511.52 2,199.54 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in Kilometer tonne-km 300 x L 13.41 120,697.50 P&M-128
For unloading hour 2.600 2,413.95 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 4,401.60 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @ 30 km/hr
and
(i) 1230KLmins for unloading )
capacity hour 20.990 1,327.00 27,853.73 P&M-024
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 Cum
d) Formwork and staging 40 per cent of (a+b+c) 40.000 380,819.74
e) Overhead charges @ 25% on (a+b+c+d) 333,217.27
f) Contractor's profit @ 10% on (a+b+c+d+e) 166,608.63
Cost for 120 cum = a+b+c+d+e+f 1,832,694.98
Rate per cum = (a+b+c+d+e+f)/120 15,272.46
18.12J 1700 J RCC Grade M- 65 15,272.00
Unit = 1 cum
Taking output = 120 cum 120 cum
a) Material
Sub-Analysis of
Per Cum Basic Cost (Rate as in sub-analysis) cum 120.000 6,552.00 786,240.00
Concrete - 20.17
Water for curing Kl 63.000 16.00 1,008.00 M-191
b) Labour
For pouring and placing
Mate day 0.232 617.00 143.14 L-12
Mason day 1.500 738.00 1,107.00 L-11
Mazdoor day 4.300 511.52 2,199.54 L-13
c) Machinery
Transit truck agitator
For transportation (6 cum Capacity) , L - lead in Kilometer tonne-km 300 x L 13.41 120,697.50 P&M-128
For unloading hour 2.600 2,413.95 6,276.27 P&M-067
Hydraulic Boom placer pump hour 2.600 4,401.60 11,444.16 P&M-069
Water tanker ( speed @ 20km/hr and return speed @ 30 km/hr
and
(i) 1230KLmins for unloading )
capacity hour 20.990 1,327.00 27,853.73 P&M-024
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 Cum
d) Formwork and staging 40 per cent of (a+b+c) 40.000 382,787.74
e) Overhead charges @ 25% on (a+b+c+d) 334,939.27
f) Contractor's profit @ 10% on (a+b+c+d+e) 167,469.63
Cost for 120 cum = a+b+c+d+e+f 1,842,165.98
Rate per cum = (a+b+c+d+e+f)/120 15,351.38
say 15,351.00
18.13 1600 Supplying, fitting and placing HYSD bar reinforcement in Tunnel
Work
Unit =complete
MT as per drawing and technical specifications
Taking output = 8 MT
a) Material
MS bars including 5 per cent overlaps and wastage tonne 8.400 46,496.54 390,570.97 M-083
Binding wire Kg 48.000 66.72 3,202.56 M-072
b) Labour for straightening, cutting, bending, shifting to site,
tying
Mate and placing in position day 0.160 617.00 98.72 L-12
Blacksmith day 1.000 738.00 738.00 L-02
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Cutting Machine hour 8.000 528.15 4,225.20 P&M-076
Bending Machine hour 8.000 528.15 4,225.20 P&M-076
Electric generator 15 KVA hour 8.000 425.25 3,402.00 P&M-051
Tipper
Tipper for Transportation
(i) 14 cum capacity t.km 8xL 8.52 2,045.40 P&M-120
Loading & Unloading Time hour
(i) 14 cum capacity hour 2.000 2,556.75 5,113.50 P&M-015
Light weight Crane
At cutting bending yard hour 2.000 1,083.60 2,167.20 P&M-102
At site hour 2.000 1,083.60 2,167.20 P&M-102
Basic Cost of Labour, Material & Machinery (a+b) for 8 MT
Unit = Rm
Taking output = 1Rm
a) Labour
Mate day 0.016 0.016 0.016 617.00 9.87 9.87 9.87 L-12
Mazdoor skilled day 0.100 0.100 0.100 565.73 56.57 56.57 56.57 L-15
Mazdoor day 0.300 0.300 0.300 511.52 153.46 153.46 153.46 L-13
b) Machinery
Water tanker 6 KL capacity hour 0.008 0.008 0.008 1,005.00 8.38 8.38 8.38 P&M-025
c) Materials
Bamboos ( For Horizontal Beam) Rm 4.000 4.000 4.000 17.75 71.00 71.00 71.00 M-229
Live Stake Stump / Bamboos (Vertical) Rm 1.500 1.500 1.500 1.00 1.50 1.50 1.50 M-230
Live Stake Stump / Bamboos (Horizontal) Rm 1.000 1.000 1.000 1.00 1.00 1.00 1.00 M-230
Binding Material Rm 2.000 2.000 2.000 1.00 2.00 2.00 2.00 M-235
Cost of Water KL 0.050 0.050 0.050 16.00 0.80 0.80 0.80 M-191
Grass Kg 1.500 1.500 1.500 34.75 52.13 52.13 52.13 M-112
@ 8% on @ 10% on @ 12% on
d) Overhead charges 28.54 35.67 42.80
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 38.52 39.24 39.95
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 1 RM = a+b+c+d+e 423.76 431.61 439.46
Rate per cum = (a+b+c+d+e) 423.76 431.61 439.46
Say 424.00 432.00 439.00
Unit = Rm
Taking output = 10 Rm
a) Labour
Mate day 0.100 0.100 0.100 617.00 61.70 61.70 61.70 L-12
Mazdoor skilled day 0.500 0.500 0.500 565.73 282.87 282.87 282.87 L-15
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Tractor-trolley hour 1.000 1.000 1.000 1,876.50 1,876.50 1,876.50 1,876.50 P&M-026
c) Material
Hard wood sticks Nr 8.000 8.000 8.000 100.00 800.00 800.00 800.00 M-231
Binding Material Rm 5.000 5.000 5.000 1.00 5.00 5.00 5.00 M-235
@ 8% on @ 10% on @ 12% on
d) Overhead charges 323.93 404.91 485.89
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 437.30 445.40 453.50
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 1 M = a+b+c+d+e 4,810.34 4,899.42 4,988.50
Rate per Rm = (a+b+c+d+e)/10 481.03 489.94 498.85
Say 481.00 490.00 499.00
Construction and laying of brush Layers across the slope
19.04 complete as per drawing and additional Technical
specification.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor for preparation of ground day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Machinery
Water tanker including watering for 3 months hour 2.000 2.000 2.000 1,005.00 2,010.00 2,010.00 2,010.00 P&M-025
Tractor-trolley hour 0.500 0.500 0.500 1,876.50 938.25 938.25 938.25 P&M-026
c) Material
Live Sods (.6m Length) Nr 1000.000 1000.000 1000.000 1.00 1,000.00 1,000.00 1,000.00 M-232
Farm yard manure @ 0.18 cum per 100 sqm at site of
cum 0.180 0.180 0.180 300.00 54.00 54.00 54.00 M-168
work
Cost of water KL 12.000 12.000 12.000 16.00 192.00 192.00 192.00 M-191
Grass Kg 100.000 100.000 100.000 34.75 3,475.00 3,475.00 3,475.00 M-112
@ 8% on @ 10% on @ 12% on
d) Overhead charges 742.23 927.79 1,113.34
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 1,002.01 1,020.56 1,039.12
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 11,022.09 11,226.20 11,430.31
Rate per sqm = (a+b+c+d+e)/100 110.22 112.26 114.30
Say 110.00 112.00 114.00
Construction of vegetative Palisades in Rills using hard
19.05 wood cutting complete as per drawing and additional
Technical specification.
Unit = Rm
Taking output = 2 Rm
a) Labour
Mate day 0.012 0.012 0.012 617.00 7.40 7.40 7.40 L-12
Mazdoor skilled day 0.100 0.100 0.100 565.73 56.57 56.57 56.57 L-15
Mazdoor day 0.200 0.200 0.200 511.52 102.30 102.30 102.30 L-13
b) Machinery
Tractor-trolley hour 0.250 0.250 0.250 1,876.50 469.13 469.13 469.13 P&M-026
c) Material
Horizontal Live Sods (2M Length) Nr 2.000 2.000 2.000 1.00 2.00 2.00 2.00 M-233
Vertical Live Sods (2 M Length) Nr 40.000 40.000 40.000 1.00 40.00 40.00 40.00 M-233
Cost of water KL 0.100 0.100 0.100 16.00 1.60 1.60 1.60 M-191
Binding Material Rm 5.000 5.000 5.000 1.00 5.00 5.00 5.00 M-235
@ 8% on @ 10% on @ 12% on
d) Overhead charges 54.72 68.40 82.08
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 73.87 75.24 76.61
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 2 M = a+b+c+d+e 812.60 827.65 842.70
Rate per Rm = (a+b+c+d+e)/2 406.30 413.82 421.35
Say 406.00 414.00 421.00
Laying of Palisades in Slopes complete as per drawing
19.06
and additional Technical specification.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 0.120 0.120 617.00 74.04 74.04 74.04 L-12
Mazdoor for preparation of ground day 3.000 3.000 3.000 511.52 1,534.56 1,534.56 1,534.56 L-13
b) Machinery
Water tanker including watering for 3 months hour 2.000 2.000 2.000 1,005.00 2,010.00 2,010.00 2,010.00 P&M-025
Tractor-trolley hour 0.500 0.500 0.500 1,876.50 938.25 938.25 938.25 P&M-026
c) Material
Live Sods (.6m Length) Nr 1000.000 1000.000 1000.000 1.00 1,000.00 1,000.00 1,000.00 M-232
Farm yard manure @ 0.18 cum per 100 sqm at site of
cum 0.180 0.180 0.180 300.00 54.00 54.00 54.00 M-168
work
Cost of water KL 12.000 12.000 12.000 16.00 192.00 192.00 192.00 M-191
Grass Kg 100.000 100.000 100.000 34.75 3,475.00 3,475.00 3,475.00 M-112
@ 8% on @ 10% on @ 12% on
d) Overhead charges 742.23 927.79 1,113.34
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 1,002.01 1,020.56 1,039.12
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e 11,022.09 11,226.20 11,430.31
Rate per sqm = (a+b+c+d+e)/100 110.22 112.26 114.30
Say 110.00 112.00 114.00
Unit = KL
Taking output = 6KL
a) Labour
Mate day 0.008 0.008 0.008 617.00 4.94 4.94 4.94 L-12
Mazdoor day 0.200 0.200 0.200 511.52 102.30 102.30 102.30 L-13
b) Machinery
Water tanker 6 KL capacity hour 0.750 0.750 0.750 1,005.00 753.75 753.75 753.75 P&M-025
c) Materials
Cost of Water KL 6.000 6.000 6.000 16.00 96.00 96.00 96.00 M-191
@ 8% on @ 10% on @ 12% on
d) Overhead charges 76.56 95.70 114.84
(a+b+c) (a+b+c) (a+b+c)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit 103.35 105.27 107.18
(a+b+c+d) (a+b+c+d) (a+b+c+d)
Cost for 6 KL = a+b+c+d+e 1,136.90 1,157.96 1,179.01
Cost per KL = (a+b+c+d+e) 189.48 192.99 196.50
Say 189.00 193.00 197.00
Unit = Number
Taking output = One Number
a) Cost of Water Quality Monitoring Nos. 1.000 1.000 1.000 2,700.00 2,700.00 2,700.00 2,700.00
@ 10% on @ 12% on
b) Overhead charges @ 8% on (a) 216.00 270.00 324.00
(a) (a)
@ 10% on @ 10% on @ 10% on
c) Contractor's profit 291.60 297.00 302.40
(a+b) (a+b) (a+b)
Rate per Number = a+b+c 3,207.60 3,267.00 3,326.40
Say 3,208.00 3,267.00 3,326.00
Unit = Number
Taking output = One Number
a) Cost of Soil Quality Monitoring Nos. 1.000 1.000 1.000 6,000.00 6,000.00 6,000.00 6,000.00
@ 10% on @ 12% on
b) Overhead charges @ 8% on (a) 480.00 600.00 720.00
(a) (a)
@ 10% on @ 10% on @ 10% on
c) Contractor's profit 648.00 660.00 672.00
(a+b) (a+b) (a+b)
Rate per Number = a+b+c 7,128.00 7,260.00 7,392.00
Say 7,128.00 7,260.00 7,392.00
Unit = Number
Taking output = One Number
Cost of Ambient Air Quality Nos. 1.000 1.000 1.000 2,500.00 2,500.00 2,500.00 2,500.00
@ 10% on @ 12% on
b) Overhead charges @ 8% on (a) 200.00 250.00 300.00
(a) (a)
@ 10% on @ 10% on @ 10% on
c) Contractor's profit 270.00 275.00 280.00
(a+b) (a+b) (a+b)
Rate per Number = a+b+c 2,970.00 3,025.00 3,080.00
Say 2,970.00 3,025.00 3,080.00
@ 10% on @ 12% on
b) Overhead charges @ 8% on (a) 160.00 200.00 240.00
(a) (a)
@ 10% on @ 10% on @ 10% on
c) Contractor's profit 216.00 220.00 224.00
(a+b) (a+b) (a+b)
Rate per Number = a+b+c 2,376.00 2,420.00 2,464.00
Say 2,376.00 2,420.00 2,464.00
Unit = Number
Taking output = One Number
(ii) Consent to Operate (CTO) Nos. 1.000 1.000 1.000 100,000.00 100,000.00 100,000.00 100,000.00
@ 10% on @ 12% on
b) Overhead charges @ 8% on (a) 8,000.00 10,000.00 12,000.00
(a) (a)
@ 10% on @ 10% on @ 10% on
c) Contractor's profit 10,800.00 11,000.00 11,200.00
(a+b) (a+b) (a+b)
Rate per Number = a+b+c 118,800.00 121,000.00 123,200.00
Say 118,800.00 121,000.00 123,200.00
@ 10% on @ 12% on
b) Overhead charges @ 8% on (a) 960.00 1,200.00 1,440.00
(a) (a)
@ 10% on @ 10% on @ 10% on
c) Contractor's profit 1,296.00 1,320.00 1,344.00
(a+b) (a+b) (a+b)
Rate per Number = a+b+c 14,256.00 14,520.00 14,784.00
Say 14,256.00 14,520.00 14,784.00
Unit = Number
Taking output = One Number
(ii) compliance submission for Consent to Operate (CTO) Nos. 1.000 1.000 1.000 12,000.00 12,000.00 12,000.00 12,000.00
@ 10% on @ 12% on
b) Overhead charges @ 8% on (a) 960.00 1,200.00 1,440.00
(a) (a)
@ 10% on @ 10% on @ 10% on
c) Contractor's profit 1,296.00 1,320.00 1,344.00
(a+b) (a+b) (a+b)
Rate per Number = a+b+c 14,256.00 14,520.00 14,784.00
Say 14,256.00 14,520.00 14,784.00
Unit = Number
Taking output = One Number
Cost of Workshop Nos. 1.000 1.000 1.000 25,000.00 25,000.00 25,000.00 25,000.00
@ 10% on @ 12% on
b) Overhead charges @ 8% on (a) 2,000.00 2,500.00 3,000.00
(a) (a)
@ 10% on @ 10% on @ 10% on
c) Contractor's profit 2,700.00 2,750.00 2,800.00
(a+b) (a+b) (a+b)
Rate per Number = a+b+c 29,700.00 30,250.00 30,800.00
Say 29,700.00 30,250.00 30,800.00
19.16 Pollution prevention
Silt fencing on eirther side of the streams and rivers
including erection and maintenance for entire construction
phase.
Unit = Rm
Taking output = 100 Rm
a) Labour
Mate day 0.080 0.080 0.080 617.00 49.36 49.36 49.36 L-12
Mazdoor day 2.000 2.000 2.000 511.52 1,023.04 1,023.04 1,023.04 L-13
b) Machinery
Tractor-trolley for transportation hour 2.000 2.000 2.000 1,876.50 3,753.00 3,753.00 3,753.00 P&M-026
c) Material
Silt Fence Sheet Sqm 100.000 100.000 100.000 250.00 25,000.00 25,000.00 25,000.00 P&M-026
Hard wood sticks Nos. 34.000 34.000 34.000 100.00 3,400.00 3,400.00 3,400.00 P&M-026
@ 8% on @ 10% on @ 12% on
d) Overhead charges @ on (a+b+c) 2,658.03 3,322.54 3,987.05
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit @ on (a+b+c+d) 3,588.34 3,654.79 3,721.24
(a+b+c) (a+b+c) (a+b+c)
Cost for 100 Rm = a+b+c+d+e 39,471.78 40,202.73 40,933.69
Rate per Rm = (a+b+c+d+e)/100 394.72 402.03 409.34
Say 395.00 402.00 409.00
Road Safety Audit during Construction Period &
19.17 IRC-SP-88
Maintenance Period
Unit = Km
19.17 A Upto 50.00 Kilometer
a) Experts/Key Personnel
Sr. Road Safety/Auditor/ Team leader Month 4.000 4.000 4.000 100,000.00 400,000.00 400,000.00 400,000.00 M312
Traffic Planner Month 6.000 6.000 6.000 75,000.00 450,000.00 450,000.00 450,000.00 M313
b) Boarding & Loading
Boarding & Loading and Per Diem for Site Visits. days 90.000 90.000 90.000 3,500.00 315,000.00 315,000.00 315,000.00 M314
No. of
Transportation at site and Head Office 20.000 20.000 20.000 1,200.00 24,000.00 24,000.00 24,000.00 M315
trip
Duty travel to Site days 90.000 90.000 90.000 2,000.00 180,000.00 180,000.00 180,000.00 M316
c) Reports and Documents Cost
No.of
Submission of GAP report 5.000 5.000 5.000 7,000.00 35,000.00 35,000.00 35,000.00 M318
Copies
No.of
Submission of audit report of work zone safety 5.000 5.000 5.000 15,000.00 75,000.00 75,000.00 75,000.00 M320
Copies
No.of
workshop report. 5.000 5.000 5.000 4,500.00 22,500.00 22,500.00 22,500.00 M321
Copies
No.of
Final Safety report 5.000 5.000 5.000 25,000.00 125,000.00 125,000.00 125,000.00 M322
Copies
@ 8% on @ 10% on @ 12% on
d) Overhead charges @ on (a+b+c) 148,412.00 185,515.00 222,618.00
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit @ on (a+b+c+d) 200,356.20 204,066.50 207,776.80
(a+b+c) (a+b+c) (a+b+c)
Rate for Upto 50.00 Kilometer = a+b+c+d+e 2,203,918.20 2,244,731.50 2,285,544.80
Say 2,203,918.00 2,244,732.00 2,285,545.00
19.17 B Between 50.00 Km. to 100.00 Km.
a) Experts/Key Personnel
Sr. Road Safety/Auditor/ Team leader Month 6.000 6.000 6.000 100,000.00 600,000.00 600,000.00 600,000.00 M312
Traffic Planner Month 8.000 8.000 8.000 75,000.00 600,000.00 600,000.00 600,000.00 M313
b) Boarding & Loading
Boarding & Loading and Per Diem for Site Visits. days 126.000 126.000 126.000 3,500.00 441,000.00 441,000.00 441,000.00 M314
No. of
Transportation at site and Head Office 20.000 20.000 20.000 1,200.00 24,000.00 24,000.00 24,000.00 M315
trip
Duty travel to Site days 126.000 126.000 126.000 2,000.00 252,000.00 252,000.00 252,000.00 M316
c) Reports and Documents Cost
No.of
Submission of GAP report 5.000 5.000 5.000 7,000.00 35,000.00 35,000.00 35,000.00 M318
Copies
No.of
Submission of audit report of work zone safety 5.000 5.000 5.000 15,000.00 75,000.00 75,000.00 75,000.00 M320
Copies
No.of
workshop report. 5.000 5.000 5.000 4,500.00 22,500.00 22,500.00 22,500.00 M321
Copies
No.of
Final Safety report 5.000 5.000 5.000 25,000.00 125,000.00 125,000.00 125,000.00 M322
Copies
@ 8% on @ 10% on @ 12% on
d) Overhead charges @ on (a+b+c) 196,636.00 245,795.00 294,954.00
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit @ on (a+b+c+d) 265,458.60 270,374.50 275,290.40
(a+b+c) (a+b+c) (a+b+c)
Rate for 50.00 to 100.00 Kilometer = a+b+c+d+e 2,920,044.60 2,974,119.50 3,028,194.40
Say 2,920,045.00 2,974,120.00 3,028,194.00
19.17 C More than 100 Km.
a) Experts/Key Personnel
Sr. Road Safety/Auditor/ Team leader Month 8.000 8.000 8.000 100,000.00 800,000.00 800,000.00 800,000.00 M312
Traffic Planner Month 10.000 10.000 10.000 75,000.00 750,000.00 750,000.00 750,000.00 M313
b) Boarding & Loading
Boarding & Loading and Per Diem for Site Visits. days 162.000 162.000 162.000 3,500.00 567,000.00 567,000.00 567,000.00 M314
No. of
Transportation at site and Head Office 20.000 20.000 20.000 1,200.00 24,000.00 24,000.00 24,000.00 M315
trip
Duty travel to Site days 162.000 162.000 162.000 2,000.00 324,000.00 324,000.00 324,000.00 M316
c) Reports and Documents Cost
No.of
Submission of GAP report 5.000 5.000 5.000 7,000.00 35,000.00 35,000.00 35,000.00 M318
Copies
No.of
Submission of audit report of work zone safety 5.000 5.000 5.000 15,000.00 75,000.00 75,000.00 75,000.00 M320
Copies
No.of
workshop report. 5.000 5.000 5.000 4,500.00 22,500.00 22,500.00 22,500.00 M321
Copies
No.of
Final Safety report 5.000 5.000 5.000 25,000.00 125,000.00 125,000.00 125,000.00 M322
Copies
Add 10 percent of cost of a+b+c as Miscellaneous work 278,250.00 278,250.00 278,250.00
@ 8% on @ 10% on @ 12% on
d) Overhead charges @ on (a+b+c) 244,860.00 306,075.00 367,290.00
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit @ on (a+b+c+d) 330,561.00 336,682.50 342,804.00
(a+b+c) (a+b+c) (a+b+c)
Rate for More than 100.00 Kilometer = a+b+c+d+e 3,636,171.00 3,703,507.50 3,770,844.00
Say 3,636,171.00 3,703,508.00 3,770,844.00
19.18 IRC-SP-88 Road Safety Audit during Maintenance Period
Unit = Km
19.18 A Upto 50.00 Kilometer
a) Experts/Key Personnel
Sr. Road Safety/Auditor/ Team leader Month 2.000 2.000 2.000 100,000.00 200,000.00 200,000.00 200,000.00 M312
Traffic Planner Month 3.000 3.000 3.000 75,000.00 225,000.00 225,000.00 225,000.00 M313
b) Boarding & Loading
Boarding & Loading and Per Diem for Site Visits. days 45.000 45.000 45.000 3,500.00 157,500.00 157,500.00 157,500.00 M314
No. of
Transportation at site and Head Office 20.000 20.000 20.000 1,200.00 24,000.00 24,000.00 24,000.00 M315
trip
Duty travel to Site days 45.000 45.000 45.000 2,000.00 90,000.00 90,000.00 90,000.00 M316
c) Reports and Documents Cost
No.of
Submission of GAP report 5.000 5.000 5.000 7,000.00 35,000.00 35,000.00 35,000.00 M318
Copies
No.of
workshop report. 5.000 5.000 5.000 4,500.00 22,500.00 22,500.00 22,500.00 M321
Copies
No.of
Final Safety report 5.000 5.000 5.000 25,000.00 125,000.00 125,000.00 125,000.00 M322
Copies
@ 8% on @ 10% on @ 12% on
d) Overhead charges @ on (a+b+c) 89,232.00 111,540.00 133,848.00
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit @ on (a+b+c+d) 120,463.20 122,694.00 124,924.80
(a+b+c) (a+b+c) (a+b+c)
Rate for Upto 50.00 Kilometer = a+b+c+d+e 1,325,095.20 1,349,634.00 1,374,172.80
Say 1,325,095.00 1,349,634.00 1,374,173.00
19.18 B Between 50.00 Km. to 100.00 Km.
a) Experts/Key Personnel
Sr. Road Safety/Auditor/ Team leader Month 3.000 3.000 3.000 100,000.00 300,000.00 300,000.00 300,000.00 M312
Traffic Planner Month 4.000 4.000 4.000 75,000.00 300,000.00 300,000.00 300,000.00 M313
b) Boarding & Loading
Boarding & Loading and Per Diem for Site Visits. days 45.000 45.000 45.000 3,500.00 157,500.00 157,500.00 157,500.00 M314
No. of
Transportation at site and Head Office 20.000 20.000 20.000 1,200.00 24,000.00 24,000.00 24,000.00 M315
trip
Duty travel to Site days 45.000 45.000 45.000 2,000.00 90,000.00 90,000.00 90,000.00 M316
c) Reports and Documents Cost
No.of
Submission of GAP report 5.000 5.000 5.000 7,000.00 35,000.00 35,000.00 35,000.00 M318
Copies
No.of
Final Safety report 5.000 5.000 5.000 25,000.00 125,000.00 125,000.00 125,000.00 M322
Copies
@ 8% on @ 10% on @ 12% on
d) Overhead charges @ on (a+b+c) 104,632.00 130,790.00 156,948.00
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit @ on (a+b+c+d) 141,253.20 143,869.00 146,484.80
(a+b+c) (a+b+c) (a+b+c)
Rate for 50.00 to 100.00 Kilometer = a+b+c+d+e 1,553,785.20 1,582,559.00 1,611,332.80
Say 1,553,785.00 1,582,559.00 1,611,333.00
19.18 C More than 100 Km.
a) Experts/Key Personnel
Sr. Road Safety/Auditor/ Team leader Month 4.000 4.000 4.000 100,000.00 400,000.00 400,000.00 400,000.00 M312
Traffic Planner Month 5.000 5.000 5.000 75,000.00 375,000.00 375,000.00 375,000.00 M313
b) Boarding & Loading
Boarding & Loading and Per Diem for Site Visits. days 45.000 45.000 45.000 3,500.00 157,500.00 157,500.00 157,500.00 M314
No. of
Transportation at site and Head Office 20.000 20.000 20.000 1,200.00 24,000.00 24,000.00 24,000.00 M315
trip
Duty travel to Site days 45.000 45.000 45.000 2,000.00 90,000.00 90,000.00 90,000.00 M316
c) Reports and Documents Cost
No.of
Submission of GAP report 5.000 5.000 5.000 7,000.00 35,000.00 35,000.00 35,000.00 M318
Copies
No.of
workshop report. 5.000 5.000 5.000 4,500.00 22,500.00 22,500.00 22,500.00 M321
Copies
No.of
Final Safety report 5.000 5.000 5.000 25,000.00 125,000.00 125,000.00 125,000.00 M322
Copies
@ 8% on @ 10% on @ 12% on
d) Overhead charges @ on (a+b+c) 120,032.00 150,040.00 180,048.00
(a+b) (a+b) (a+b)
@ 10% on @ 10% on @ 10% on
e) Contractor's profit @ on (a+b+c+d) 162,043.20 165,044.00 168,044.80
(a+b+c) (a+b+c) (a+b+c)
Rate for More than 100.00 Kilometer = a+b+c+d+e 1,782,475.20 1,815,484.00 1,848,492.80
Say 1,782,475.00 1,815,484.00 1,848,493.00
SUB-ANALYSIS OF CONCRETE / MORTAR RATE
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
20.01 (A) Cement Mortar 1:3 (1 cement : 3 sand)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.510 4,940.00 2,519.40 M-081
Coarse sand cum 1.050 1,994.03 2,093.73 M-005
Cost of water KL 0.255 16.00 4.08 M-191
b) Labour
Mate day 0.036 617.00 22.21 L-12
Mazdoor day 0.900 511.52 460.37 L-13
c) Machinery
Water tanker 12 KL capacity ( speed @
20km/hr and return speed @ 30 km/hr and hour 0.019 1,327.00 25.21 P&M-024
30 mins for unloading )
Rate per cum = (a+b+c) 5,125.00
20.01 (B) Cement Mortar1:2 (1cement :2 sand)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.672 4,940.00 3,319.68 M-081
Coarse sand cum 0.930 1,994.03 1,854.45 M-005
Cost of water KL 0.336 16.00 5.38 M-191
b) Labour
Mate day 0.036 617.00 22.21 L-12
Mazdoor day 0.900 511.52 460.37 L-13
c) Machinery
Water tanker 12 KL capacity ( speed @
20km/hr and return speed @ 30 km/hr and hour 0.025 1,327.00 33.18 P&M-024
30 mins for unloading )
Rate per cum = (a+b+c) 5,695.00
20.01 (C) Cement Mortar1:4 (1cement :4 sand)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.403 4,940.00 1,990.82 M-081
Coarse sand cum 1.120 1,994.03 2,233.31 M-005
Cost of water KL 0.202 16.00 3.22 M-191
b) Labour
Mate day 0.036 617.00 22.21 L-12
Mazdoor day 0.900 511.52 460.37 L-13
c) Machinery
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
Water tanker 12 KL capacity ( speed @
20km/hr and return speed @ 30 km/hr and hour 0.015 1,327.00 19.91 P&M-024
30 mins for unloading )
Rate per cum = (a+b+c) 4,730.00
20.01 (D) Cement Mortar1:6 (1cement :6 sand)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement tonne 0.288 4,940.00 1,422.72 M-081
Coarse sand cum 1.337 1,994.03 2,666.02 M-005
Cost of water KL 0.144 16.00 2.30 M-191
b) Labour
Mate day 0.036 617.00 22.21 L-12
Mazdoor day 0.900 511.52 460.37 L-13
c) Machinery
Water tanker 12 KL capacity ( speed @
20km/hr and return speed @ 30 km/hr and hour 0.011 1,327.00 14.60 P&M-024
30 mins for unloading )
Rate per cum = (a+b+c) 4,588.00
Unit = cum
Taking output = 360 Cum
a) Material
Cement tonne 99.000 4,940.00 489,060.00 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
40 mm Aggregate cum 194.400 1,887.12 366,856.73 M-054
20 mm Aggregate cum 97.200 1,887.12 183,428.37 M-052
10 mm Aggregate cum 32.400 1,887.12 61,142.79 M-050
Cost of water (Water/Cement Ratio - 0.4)
KL 39.600 16.00 633.60 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Unit = cum
Taking output = 360 Cum
a) Material
Cement tonne 123.840 4,940.00 611,769.60 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
40 mm Aggregate cum 129.600 1,887.12 244,571.15 M-054
20 mm Aggregate cum 129.600 1,887.12 244,571.15 M-052
10 mm Aggregate cum 64.800 1,887.12 122,285.58 M-050
Cost of water (Water/Cement Ratio - 0.4)
KL 49.536 16.00 792.58 M-191
b) Labour
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Unit : cum
Taking output = 360 Cum
a) Material
Cement tonne 124.980 4,940.00 617,401.20 M-081
Coarse Sand cum 162.000 1,994.03 323,033.02 M-004
20 mm Aggregate cum 194.400 1,887.12 366,856.73 M-052
10 mm Aggregate cum 129.600 1,887.12 244,571.15 M-050
Cost of water KL 49.992 16.00 799.87 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,144.38 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 4,533.00
20.06 PCC Grade M25 Using Batching Plant
Unit : cum
Taking output = 360 Cum
a) Material
Cement tonne 143.850 4,940.00 710,619.00 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
40 mm Aggregate cum 129.600 1,887.12 244,571.15 M-054
20 mm Aggregate cum 129.600 1,887.12 244,571.15 M-052
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
10 mm Aggregate cum 64.800 1,887.12 122,285.58 M-050
Cost of water KL 57.540 16.00 920.64 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,144.38 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 4,793.00
20.07 RCC Grade M25 Using Batching Plant
Unit: cum
Taking output = 360 Cum
a) Material
Cement tonne 145.140 4,940.00 716,991.60 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
20 mm Aggregate cum 194.400 1,887.12 366,856.73 M-052
10 mm Aggregate cum 129.600 1,887.12 244,571.15 M-050
Admixture @ 0.2 % of Cement Kg 290.280 167.49 48,617.69 M-182
Cost of water KL 58.056 16.00 928.90 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 4,945.00
20.08 PCC Grade M30 Using Batching Plant
Unit : cum
Taking output = 360 Cum
a) Material
Cement tonne 145.800 4,940.00 720,252.00 M-081
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
40 mm Aggregate cum 129.600 1,887.12 244,571.15 M-054
20 mm Aggregate cum 129.600 1,887.12 244,571.15 M-052
10 mm Aggregate cum 64.800 1,887.12 122,285.58 M-050
Cost of water KL 58.320 16.00 933.12 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 4,819.00
20.09 RCC Grade M30 Using Batching Plant
Unit = cum
Taking output = 360 Cum
a) Material
Cement tonne 146.400 4,940.00 723,216.00 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
20 mm Aggregate cum 194.400 1,887.12 366,856.73 M-052
10 mm Aggregate cum 129.600 1,887.12 244,571.15 M-050
Admixture @ 0.3 % of Cement Kg 439.200 167.49 73,559.63 M-182
Cost of water KL 58.560 16.00 936.96 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 5,032.00
20.10 PCC Grade M35 Using Batching Plant
Unit : cum
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
Taking output = 360 Cum
a) Material
Cement tonne 150.840 4,940.00 745,149.60 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
20 mm Aggregate cum 194.400 1,887.12 366,856.73 M-052
10 mm Aggregate cum 129.600 1,887.12 244,571.15 M-050
Admixture @ 0.3 % of Cement Kg 452.520 167.49 75,790.54 M-182
Cost of water KL 60.336 16.00 965.38 M-191
b) Labour
Mate day 0.160 617.00 965.38 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 5,102.00
20.11 RCC Grade M35 Using Batching Plant
Unit ; cum
Taking output = 360 Cum
a) Material
Cement tonne 151.920 4,940.00 750,484.80 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
20 mm Aggregate cum 194.400 1,887.12 366,856.73 M-052
10 mm Aggregate cum 129.600 1,887.12 244,571.15 M-050
Admixture @ 0.4 % of Cement Kg 607.680 167.49 101,777.59 M-182
Cost of water KL 60.768 16.00 972.29 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 5,186.00
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
Unit ; cum
Taking output = 360 Cum
a) Material
Cement tonne 154.800 4,940.00 764,712.00 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
20 mm Aggregate cum 194.400 1,887.12 366,856.73 M-052
10 mm Aggregate cum 129.600 1,887.12 244,571.15 M-050
Admixture @ 0.8 % of Cement Kg 1238.400 167.49 207,414.04 M-182
Cost of water KL 61.920 16.00 990.72 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 5,519.00
20.13 RCC Grade M45 Using Batching Plant
Unit ; cum
Taking output = 360 Cum
a) Material
Cement tonne 154.800 4,940.00 764,712.00 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
20 mm Aggregate cum 194.400 1,887.12 366,856.73 M-052
10 mm Aggregate cum 129.600 1,887.12 244,571.15 M-050
Admixture @ 1 % of Cement Kg 1548.000 167.49 259,267.55 M-182
Cost of water KL 61.920 16.00 990.72 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 5,663.00
20.14 RCC Grade M50 Using Batching Plant
Unit ; cum
Taking output = 360 Cum
a) Material
Cement tonne 154.800 4,940.00 764,712.00 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
20 mm Aggregate cum 194.400 1,887.12 366,856.73 M-052
10 mm Aggregate cum 129.600 1,887.12 244,571.15 M-050
Admixture @ 0.8 % of Cement Kg 1238.400 167.49 207,414.04 M-182
Silica Fume @ 5% of Cement Kg 7740.000 33.60 260,064.00 M-199
Cost of water KL 61.920 16.00 990.72 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 6,242.00
20.15 RCC Grade M55 Using Batching Plant
Unit ; cum
Taking output = 360 Cum
a) Material
Cement tonne 158.400 4,940.00 782,496.00 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
20 mm Aggregate cum 194.400 1,887.12 366,856.73 M-052
10 mm Aggregate cum 129.600 1,887.12 244,571.15 M-050
Admixture @ 1 % of Cement Kg 1267.200 167.49 212,237.63 M-182
Silica Fume @ 5% of Cement Kg 7920.000 33.60 266,112.00 M-199
Cost of water KL 63.360 16.00 1,013.76 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 6,321.00
20.16 RCC Grade M60 Using Batching Plant
Unit ; cum
Taking output = 360 Cum
a) Material
Cement tonne 160.200 4,940.00 791,388.00 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
20 mm Aggregate cum 194.400 1,887.12 366,856.73 M-052
10 mm Aggregate cum 129.600 1,887.12 244,571.15 M-050
Admixture @ 1 % of Cement Kg 1281.600 167.49 214,649.42 M-182
Silica Fume @ 6% of Cement Kg 9612.000 33.60 322,963.20 M-199
Cost of water KL 64.080 16.00 1,025.28 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 6,511.00
20.17 RCC Grade M65 Using Batching Plant
Unit ; cum
Taking output = 360 Cum
a) Material
Cement tonne 162.000 4,940.00 800,280.00 M-081
Coarse sand cum 162.000 1,994.03 323,033.02 M-004
20 mm Aggregate cum 194.400 1,887.12 366,856.73 M-052
10 mm Aggregate cum 129.600 1,887.12 244,571.15 M-050
Admixture @ 1 % of Cement Kg 1296.000 167.49 217,061.21 M-182
Silica Fume @ 6% of Cement Kg 9720.000 33.60 326,592.00 M-199
Ref. to
Rate Amount Remarks/
Sr No MORT&H Description Unit Quantity
(Rs.) (Rs.) Input ref.)
Spec.
Cost of water KL 64.800 16.00 1,036.80 M-191
b) Labour
Mate day 0.160 617.00 98.72 L-12
Skilled Mazdoor day 1.000 565.73 565.73 L-15
Mazdoor day 3.000 511.52 1,534.56 L-13
c) Machinery
Batching Plant of capacity 120 cum/hour
hour 4.000 4,104.45 16,417.80 P&M-039
Generator 250 KVA hour 4.000 3,475.00 13,900.00 P&M-046
Loader 3.1 cum capacity hour 8.679 4,279.80 37,142.55 P&M-011
Transit truck agitator
For loading & Unloding time hour 4.000 2,413.95 9,655.80 P&M-067
Per Cum Basic Cost of Labour, Material &
Machinery (a+b+c)/360 6,552.00
20.18 A DLC Using Batching Plant-240 cum
capacity Plant
Unit = cum
Taking output = 450 Cum
a) Material
Cement @ 150 kg/cum of concrete tonne 67.500 4,940.00 333,450.00 M-081
Coarse Sand as per IS: 383 @ 0.45
cum/cum of concrete cum 202.500 1,994.03 403,791.28 M-004
Crushed stone coarse aggregate of 25 mm
and 12.5 mm nominal sizes graded as per
table 600-1 @ 0.90 cum/cum of concrete cum 405.000 1,887.12 764,284.86 M-045
conforming to clause 602.2.6.
Unit ; cum
Taking output = 900 Cum
a) Material
Cement tonne 306.000 4,940.00 1,511,640.00 M-081
Fly ash conforming to IS: 3812 (Part-I) tonne 93.000 204.70 19,037.30 M-010
Coarse sand as per IS :383 and confirming
to clause 602.2.4 @0.45 cum/cum of cum 364.500 1,994.03 726,824.30 M-004
concrete
Crushed stone coarse aggregate of 25mm
and 12.5mm nominal size @0.90 cum/cum
of concrete confirming to clause 602.2.4 cum 810.000 1,887.12 1,528,569.72 M-045
Unit ; cum
Taking output = 900 Cum
a) Material
Cement tonne 306.000 4,940.00 1,511,640.00 M-081
Fly ash conforming to IS: 3812 (Part-I) tonne 93.000 204.70 19,037.30 M-010
Coarse sand as per IS :383 and confirming
to clause 602.2.4 @0.45 cum/cum of cum 364.500 1,994.03 726,824.30 M-004
concrete
Crushed stone coarse aggregate of 25mm
and 12.5mm nominal size @0.90 cum/cum
of concrete confirming to clause 602.2.4 cum 810.000 1,887.12 1,528,569.72 M-045