NO.

AKTIVITI MASA KOS


Penyediaan Bahan
Carbon Steel Pipe 6" Sch 40 100mm x 2unit
Sambungan v
Bahan Mentah Ukur Bahan- RM40.2+RM16+RM22=
1
Bevel Gauge 5Minit RM78.2
Measuring Tape

Kadar Pekerja: 1 Fitter, 1 Helper


2 2Jam RM12(2) + RM9(2)=RM42

Kadar Sewa Peralatan:


Machine Power/ BandSAW
Lathe Machine
Grinder 44Minit+38minit RM150+RM150+RM40+RM1
Mesin GMAW +6Minit+20Minit
3 Gas Co₂ 20+ RM3.42+
=108Minit(1Jam
Wire Filler ER70S-6 0.8m x 5KG 08Minit) +RM0.013=RM423.43

Kadar Penggunaan Elektrik


14.35sen+8.7sen+15.15sen+1
4 1Jam 08Minit 3.05sen=RM51.25
Bahan Gunahabis Lain: Grinder Cup Brush 1unit
Mata Grinder
5 Cutting 2unit RM2.50+RM5.60=RM8.1

Kerja Kimpalan
6 Proses:GMAW 4Jam
Kedudukan: 1G
7 Mesin GMAW
8 Wire Filler: Carbon Steel ER70S-6 Diameter 0.8x
RM2.31+RM5.50=RM7.81

9 Gas:CO₂
RM41
10 Kadar Pekerja: 1Welder
Welder(RM 13/Jam) 4Jam RM13x4=RM52

11 Kadar Penggunaan Elektrik


4Jam RM66.56

12 Bahan Gunahabis Lain: Mata Grinder Nipis 1unit RM2.80


13 Lain-lain Kos yang dikenalpasti:Headshield(RM10.79)
Safety Gloves(RM6.75) RM10.79+RM6.75+RM1+RM
4Jam 0.50=RM18.54
Welding Glass: Clear glass1unit , dark
glass1unit
Jumlah MASA dan KOS 4Jam RM683