GROUP ASSIGNMENT
(Learning Activities)
Chur Yi Yu
2229537 2B/22 13
Kazuhiro
Content Page
Learning Activities Page No.
Group Assignment (10%) and PowerPoint Presentation (10%) -
Group Activity 1:
Preparation of incident investigation and report
Instructions: Use the incident reporting form attached to conduct the incident 1-4
investigation and report to company management based on the incident case
provided in the template.
Group Activity 2:
Assessing WSH hazards and risks
Instructions: Based on the incident case in the template, each group is required to
assess the risk and compile a detail report of Risk Assessment (RA).
Group Activity 3:
Preparation of WSH Inspection
Instructions: Based on the scene of formwork construction in a construction site, list
down the unsafe acts or unsafe conditions, according to the numbering on the
locations, in the table provided.
Group Activity 4:
WSH Video (10%)
Instructions: Let your creative entries be an inspiration to others on the importance of
taking care of your health and safety in the workplace!
Do include the theme in your Short Video or animation:
“Take Time to Take Care of your Safety and Health”
Official (Closed), Non-Sensitive
Use the incident reporting form attached to conduct the incident investigation and report to company
management based on the following incident case. Complete the accident investigation report (Make
any assumption if necessary).
Additional Information
Contractor Address:
ABC Contractor
No 8 Defu Lane Singapore 785201
Tel: 6894 8944
Page 1
Official (Closed), Non-Sensitive
Age: 25
Sex: Male
(If any):
Page 2
Official (Closed), Non-Sensitive
Description of Accident
In this incident, a worker was found dead on the ground floor of a construction site.
Preliminary investigations revealed that the worker was carrying out plastering works at the
balcony area within a unit on the 17 th storey. The worker was found without any fall
protection equipment and it was suspected that the worker fell from the edge of the balcony
and landed on the ground. The guardrails that were installed were dislodged at one end.
A similar incident had occurred earlier this year. A worker carrying out plastering work on
the external wall of an air conditioning ledge fell to his death from the 9 th floor of a building.
Figure 1: Worker fell from the 17th storey balcony while carrying out plastering work.
1. The worker did not go for Work at Height (WAH) WSH Training.
2. Workers did not use Personal Protective Equipment.
3. Guardrails were dislodged at one end.
4. Unsafe Work environment
5. Lack of Safe Work Procedure (SWP).
6. Lack of proper supervision.
Provide ONE Root Cause of the accident and justify with reason.
The Worker does not have adequate training when working at a height. The worker does not know the
importance of PPE when working at height. Thus, neglecting the importance of PPE. The worker also
does not know the dangers of working at height and what preventive measures they can do.
Page 3
Official (Closed), Non-Sensitive
Page 4
Official (Closed), Non-Sensitive
Page 5
Official (Closed), Non-Sensitive
Location Hazard
(by numberings) (One unsafe Act Or unsafe One Control Measure
Condition)
1 Slip, Trip, Fall (STF). Ensure good housekeeping to prevent accidents
from happening.
2 Poor housekeeping Objects may fall onto workers or they might slip
and get injured. It is important to ensure good
housekeeping in the work site.
3 Dust might go into the Clean work areas using a vacuum cleaner rather
worker’s eye when sweeping than brushing.
the dust using a brush
8 Possible danger of object Ensure that workers should not stand directly
falling onto the worker above any objects and their surrounding area
should be clear, including areas that they cannot
see.
Page 6