Minutes May 19, 2023

1. Calendola
a. 6/23 Matira
i. Completed
b. 10/43 Soralbo, 1/16 Curameng, /4 Janer, 9/3 Umali
i. May 31 Completion
ii. To give an earlier completion date for Umali
c. 4/17 Balaquot
i. May 19 Completion
d. Alvaro
i. June 6 completion
e. 11/3 Ursales
i. June 7 Completion
f. 6/20 Belino
i. Ongoing steeldeck
2. Antipolo
a. Celestis 1
i. Da Costa
1. May 24 Completion
ii. Calano
1. 2F slab
iii. Retaining Wall
1. Waiting for riprap along Celestis 2
b. Celestis 2
i. Perimeter fence and retaining wall
1. Concreting
ii. Riprap
1. Excavation
iii. Warehouse
1. Roofing
3. Biñan
a. Land development
i. Laguna water update in next presentation
ii. For subcontractors’ negotiation for perimeter fence
1. Labor materials
4. Action Items
a. Process in addressing issues
i. If there is difficulty in finding a solution, address concern to
the Office of the President
ii. Departments to coordinate with each other
iii. Hierarchy needed in when to address issues
b. Calendola
i. Give to marketing Memo of completion
1. At least 3 weeks lead time
2. After pouring of slab
ii. Open space
1. Checklist/timeline needed
2. Deadlines needed
a. P&D to coordinate deadline with Ge
b. Needed in order to start
c. Antipolo
i. Retaining wall on Celestis 1
1. Reduce depth of footing
2. Deadline needed
ii. Celestis 2 land development
1. Deadlines needed
d. Biñan
i. Plans for 3 blocks’ roads in order for it to be completed by end
of June
ii. To give deadlines
iii. Marketing and construction to coordinate whose units are for
completion and turnover (98 units)
e. Before technical meeting
i. Discuss concerns, so that a solution will already be given
during the meeting
f. Scheme for 2.5 hectares
g. Mancom checklist