RFI’s in QMIS has five (5) categories. The selection of the appropriate category by PID
Inspector is based on RFI inspection result of the issued RFI. These Categories are as follows:
1) Inspected and Accepted: PID Inspector shall select this category if the RFI was physically
inspected and accepted the inspection point. At this point the RFI is closed.
2) Job Not Ready: PID Inspector shall reject the issued RFI if the activity is not ready for
inspection. The RFI will be in closed status in QMIS and can be re-issued when the
activity is ready for inspection.
3) Violation: PID Inspector shall reject the issued RFI if inspection resulted in violation to
Saudi Aramco Standards, Procedures and International Code. The RFI will be in closed
status of QMIS and Surveillance LBE will be issued through create icon.
4) On Hold: PID Inspector may place the issued RFI “On Hold” status if there deficiency is
minor and can be rectified within few hours. System tracks how many hours per day the
RFI was on-hold.
5) Not Inspected and Accepted: PID Inspector shall select this category if he is not able to
attend the requested RFI due to urgent mandatory management matter but decided to
accept the RFI. The RFI is closed in this instance.
2) Pro-active: PID Inspector shall initiate a Pro-active logbook entry if the activity is on way
to violation or a potential violation may occur.
3) General Comments: PID Inspector shall initiate General comments to his regular
inspection or visit at the project.
1. Open Saudi Aramco Homepage and type “ID” to access Inspection Department Website
and select the QMIS V4.
Note:
Rejected RFI for Violation and Job-Not Ready will be automatically closed in a
system. However, Job-Not Ready status of RFI in a closed section can be re-
issued by selecting the “Initiator” role and click the Job Not Ready Menu to
re-issue the RFI.
5. Contractor to write the reply in comment section and click the submit
menu.
This guideline is for SAPMT role to work in QMIS process to respond to the
RFI and the surveillance logbook entry issued by the Project Inspection (PID)
Inspector. This element will be the records of contractor Quality Status and
for SAPMT monitoring purposes of contractor quality in relation to RFI and
Logbook Entry records.
2. Open Saudi Aramco Homepage and type “ID” to access Inspection Department Website
and select the QMIS V4.
Saudi Aramco: Company General Use
3. Log-in and Select the SAPMT Role.
4. After the Log-in, Select the Project and click the Surveillance Menu
5. Click the Logbook Entry Number to open the Surveillance logbook entry.
Saudi Aramco: Company General Use
6. This is the sample of SAPID Surveillance when SAPMT open the logbook entry
in a system.
7. SAPMT to write the reply in comment section and click the submit menu.
2. Open Saudi Aramco Homepage and type “ID” to access Inspection Department Website
and select the QMIS V4.
3. Log-in and Select the SAPMT Role.
8. After the response, the RFI will be transferred to the Replied Section of
QMIS.
1
2
Write the
3 4
surveillance LBE
5
6
7 Write the
surveillance LBE
10. This is the sample of surveillance (Violation) Log Book Entry. All the
required information provided.
To extend the ACD, click on Extend ACD – Select New ACD date – Write
the Comments – Click Save Changes.
14. When the extended ACD exceeded and failed to close in a target date,
the logbook entry will automatically transfer to “For Escalation” section. This
is the role of SAPID Field Supervisor to escalate the logbook entry.
Minor logbook Entry meet the ACD will be closed in normal process.
Minor logbook Entry requested the ACD extension and rectified within the
period will be closed in normal process.
Minor LBE failed to meet the extended ACD will be escalated to NCR if
agreed by Field Supervisor.
Moderate Logbook Entry will be automatically goes to “For Escalation
Section for SAPID Field Supervisor action to issue the Company NCR and
close the logbook entry.
Major Logbook Entry will be automatically goes to “For Escalation Section
for SAPID Field Supervisor action to issue the Worksheet (WS) and close
the logbook entry.
Field Supervisor shall always be included in all surveillance LBE for
escalation purposes.
Violation LBE classified as moderate or major shall be discussed first to
Supervisor before entering to QMIS.
Moderate violation + repeated will be escalated to Worksheet (WS)
Major violation + repeated will be escalated to Delinquent Worksheet
(DWS)
1. SAPID will receive a notification from his inbox for the RFI issued by the
contractor.
2. Open Saudi Aramco Homepage and type “ID” to access Inspection Department Website
and select the QMIS V4.
3. Log-in and Select the SAPID Role.
7. When the Inspection Completed and accepted, SAPID to reply the RFI by
Selecting the Accept & Close Menu – Enter the Closing Remarks – Then Click
the Submit Menu.
9. After Rejecting the RFI due to violation, the RFI will be in closed Status but
the “create” icon has to be click to issue the surveillance violation logbook
entry.
11. For The RFI in Hydro-test, click the RFI No. to open.
As Recap, SAPID Role for RFI Process will be at the following scenarios:
This guideline is for Project Inspection (SAPID) Field Supervisor role in QMIS process to
escalate the violation logbook entry according to the process of SAEP-381. Escalation
factors are due to Repeated Violation within six (6) months due to negligence, Violation
classified as moderate or major and Overdue of Agreed Completion Date (ACD).
1. Open Saudi Aramco Homepage and type “ID” to access Inspection Department Website
and select the QMIS V4.
2. Log-in and Select the Field Supervisor Role.
Click to
open
the LBE
1 2
Note: Surveillance Logbook Entry that was escalated to NCR will be automatically closed in
a system
1. Open Saudi Aramco Homepage and type “ID” to access Inspection Department Website
Go to Tracking List and select the QMIS V4.
2. Log-in and Select the PQM Role to open the PQM Menu.
a. Click the Project List to view all the projects added under your account.
b. Select the Project and click the inbox to open the RFI’s and Surveillance LBE.
d. For Supervisor Logbook entry rating, select the Surveillance menu to open the
logbook entries.
1 6
7
2
3 8
4 9
5
10
11
a. Go to PQM Menu and click “View/ Edit Users” to open the Project Data List and click the User’s list
to open the users data list.
1. Open Saudi Aramco Homepage and type “ID” to access Inspection Department Website
Go to Tracking List and select the QMIS V4.
4. When the specified project selected, click the “RFI Status Report” menu to see the
status of RFI’s in this project, or click the “Surveillance Status Report” menu for
surveillance logbook entry status:
RFI
Surv.
6. Sample of Surveillance Logbook Entry (LBE) status after the “Surveillance Status Report”
menu selected:
Note:
In surveillance status report, the category of surveillances such as Minor, Moderate and
Major are grouped together.
Surv.
RFI
8. For Surveillance, go for the following steps: Select the status – the category – click for
the date – select the discipline – click the Get Report menu.
3
4
1
2
3
5 4
Prepared By: Gilbert G. Curva – IPIU-GL: Checked By; G. Velasco – Field Supervisor-IPIU