Professional Documents
Culture Documents
Class 17
Process Equipment Sizing and Costing
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 215
SIZING
• Calculation of all physical attributes that allow a unique costing of this unit
- Capacity, Height - Pressure rating -Cross sectional area – Materials of construction
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 216
1
14-03-2023
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 217
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 218
2
14-03-2023
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 219
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 220
3
14-03-2023
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 221
Process design
(material and energy balances to determine the
quantities of material processed and the amount
of energy transferred)
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 222
4
14-03-2023
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 223
1. Equation Format
Simple convenient method of presenting cost data is by an equation (Capacity correlation):
Where
C1 = cost for equipment capacity S1
C2 = cost for equipment capacity S2
n = cost-capacity exponent that varies between 0.30 and 1.20 depending on the type of equipment
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 224
5
14-03-2023
Example:
Recently a cast iron leaf pressure filter with 100 ft2 was purchased for clarifying an inorganic liquid stream for
$15,000. In a similar application, the company will need a 450 ft2 cast iron leaf pressure filter. The size
exponent for this type filter is 0.6. Estimate the purchased price of the 450 ft2 unit.
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 225
6
14-03-2023
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 227
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 228
7
14-03-2023
Sizing
correlation
Installation factors
• provide separate accountings for the piping required, instrumentations, structural support, building,
electrical equipment, insulation etc..
• Independent of pressure, Temperature, material of construction etc..
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 229
• Purchased & delivered cost (uninstalled cost) = Base cost*Factor (P,T,MC etc) = BC*MFP
MFP: Material & Pressure correlation factor
• BC* Module Factor (MF) = BC + Installation cost including insulation, piping, electricity, building etc.
• Installed cost = Purchased & delivered cost (uninstalled cost) + Installation cost
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 230
8
14-03-2023
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 231
For example, a shell-and-tube heat exchanger cost developed for ASPEN plus may be estimated from the
following basic correlation equation:
where
CE = exchanger cost
CB = Base cost of a carbon steel, floating-heads exchanger, 150 psig design pressure
FD = Design-type cost factor if different from that in CB
FMC = material of construction cost factor
FP = design pressure cost factor
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 232
9
14-03-2023
Correlations for base cost, design type factor, material of construction factor, and design pressure factor
can be developed as secondary algorithms:
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 233
https://doi.org/10.3390/en14092665
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 234
10
14-03-2023
Update Factor:
It is necessary to bring the cost obtained from the above relationships (original cost) to the present time cost.
Cost Indexes:
• Cost indexes are used to perform an estimate of the actual cost of a process unit if the cost of the same unit,
referred to a past period, is known.
• It is generally not recommended to use cost indexes when the time interval is longer than 10 years.
• The cost index can also be used to extrapolate the present value of a process unit or a whole plant in the near
future (for instance at the expected time of purchase compared to the design time).
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 235
The most commonly used cost indexes in the process industry are:
Marshall & Swift (M&S): All industries and Process Industry (base 100 in 1926)
Nelson-Farrar: Refinery construction index (base 100 in 1946)
Chemical Engineering (CEPCI): Plant cost index (base 100 in 1959)
Vatavuk (VAPCCI): Air pollution Control (base 100 in 1994)
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 236
11
14-03-2023
Cost Indexes..
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 237
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 238
12
14-03-2023
Heuristics or rules of thumb may be used for a preliminary sizing and cost estimate.
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 239
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 240
13
14-03-2023
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 242
14
14-03-2023
Figure: Purchased cost of U-tube heat exchangers with 0.0254-m (1 -in.) OD tubes x 0.0254-m (1-
in.) square pitch and 4.88-m (16-ft) bundles operating at 1035 kPa (150 psia)
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 243
Figure: Purchased cost of fixed-tube-sheet heat exchangers with 0.019-m (|-in.) OD x 0.025-m (1-in.) square
pitch and 4.88- or 6.10-m (16- or 20-ft) bundles and carbon steel shell operating at 1035 kPa (150 psia)
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 244
15
14-03-2023
Figure: Purchased cost of floating-head heat exchangers with 0.019-m OD x 0.025-m (3/4 in. OD x 1in.)
square pitch and 4.88-m (16-ft) bundles of carbon-steel construction
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 245
“EQUIPMENT COSTS” accompanying Plant Design and Economics for Chemical Engineers, 5th edition, Peters,
Timmerhaus, and West
http://www.mhhe.com/engcs/chemical/peters/data/
Look for example similar to Heat Exchanger…and figure out sizing and costing
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 246
16
14-03-2023
• https://processdesign.mccormick.northwestern.edu/index.php/Equipment_sizing
• FluidFlow Equipment Sizing Handbook https://fluidflowinfo.com/wp-
content/uploads/2018/04/FluidFlow-Equipment-Sizing.pdf
• Chapter 4, Process Engineering Economics by James Riley Couper
• https://pressbooks.bccampus.ca/chbe220/chapter/purchased-equipment-pe-cost/
• Process Engineering Economics by James Riley Couper
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 247
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 248
17
14-03-2023
• Process synthesis and analysis Process Flowsheets as alternatives (set of case studies)
Estimate the optimum design conditions
selection of more profitable process alternative
• Every alternative is associated with costs cost information
• Cost diagram is an approach to summarize the cost information
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 249
Cost information:
Table form Cost diagram
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 250
18
14-03-2023
Cost information
Cost information:
For any process alternative:
Cost information
Cost information:
For any process alternative:
Operating cost summary ($/year)
Utility
Power $
Steam $
Fuel $
Water $
Total: $
Labor $
Supervision $
Taxes, insurance $
Repairs $
Miscellaneous $
Payroll charges $
Total: $
Catalyst $
Total: $
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 252
19
14-03-2023
Cost diagram
An alternating way of summarizing the most important processing cost in the pictorial form is to
put all the costs on the flowsheet called Cost diagram:
1. Annualized, installed cost inside the box of flow diagram Cost diagram provides visual picture:
2. Annual operating costs are attached to the stream arrows • on how the costs are distributed throughout the
process.
• Used to spot error and visualize/identify potential
3. Per unit annualized installed and operating cost improvements by flowsheet modification
• A system viewpoint
Cost information:
Table form Cost diagram
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 253
Cost diagram
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 254
20
14-03-2023
Cost diagram
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 255
Level 2
List of design decision during base-case design Level 3
development and associated decision change Numerous process
Level 4a
alternatives
Level 4b
Level 5
Process alternatives
Example: Process alternatives for the
HDA process
Cost diagram as tool to make some estimates of
economic importance of each process alternatives
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 256
21
14-03-2023
Preliminary designs
a) Used as a basis for determining whether further
work should be done on a proposed process.
Types of process design: b) Approximate process methods and approximate
1. Order of magnitude of design cost estimates are prepared.
2. Study of factored design c) Design details and the time spent on calculations
3. Preliminary designs are kept to a minimum.
4. Detailed-estimate designs Detailed-estimate designs
5. Final process designs a) This is done when preliminary design shows good prospect.
b) Here the cost-and-profit potential of the process is determined.
c) Exact specification are not given for the equipment.
d) Piping and layout work is minimized.
Final process designs
a) Undertaken if the detailed-estimate design indicates commercial success.
b) Complete specifications are presented for all components of the plat.
c) Accurate cost analysis based on quoted price is done.
d) Profit analysis and plant-wide controllability studies are done.
e) Includes detail documentation for immediate construction of project.
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 257
22