You are on page 1of 22

14-03-2023

Class 17
Process Equipment Sizing and Costing

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 215

Process Equipment Sizing and Costing for different process units

 Process Alternatives Synthesis (candidate flowsheet)


 Analysis (Preliminary mass and energy balances)
 SIZING (Sizes and capacities)
 COST ESTIMATION (Capital and operation)
 Economic Analysis (economic criteria)

SIZING
• Calculation of all physical attributes that allow a unique costing of this unit
- Capacity, Height - Pressure rating -Cross sectional area – Materials of construction

• Short-cut, approximate calculations (correlations)  Quick obtaining of sizing parameters

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 216

1
14-03-2023

Process Equipment Sizing and Costing for different process units

 Preliminary Equipment Sizing is done for equipment Capital Cost Estimation

The need for equipment sizing


• Before one can carry out capital cost estimates on process Equipment Types
equipment, the process engineer must carry out a preliminary • Towers
sizing of the equipment. • Heat Exchangers
• Although each process will have some unique pieces of • Instrumentation
equipment there are some general categories applicable to • Tanks
most designs. • Vessels
• Pumps
• Compressors
• Fired Heaters
• Others

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 217

Process Equipment Sizing and Costing for different process units

Types of Cost Estimates

Sl. No Type Remarks Accuracy

1 Order of Magnitude estimate. Extrapolate similar plant cost over 30%

2 Study Estimate. Knowledge of major pieces of equipment ± 30%

3 Preliminary Estimate. Enough for budget authorization ± 20%

4 Definitive Estimate. Based on basic Engineering and quotes ± 10%


from suppliers and contractors

5 Detailed Estimate Based on detailed engineering. ± 5%

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 218

2
14-03-2023

Process Equipment Sizing and Costing for different process units

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 219

Process Equipment Sizing and Costing for different process units


Types of Cost Estimates
• The first three types serve as a cost indicator at a very early stage of the project design stage
first look at project cost.
• The preparation of a preliminary estimate is done by an estimator based on his assessment of the
design, past cost estimates, in-house estimating information, and previous contracts and purchase
orders.
• Even with the advent of sophisticated estimating software it is sometimes simply easier to
manually approximate an equipment cost.
• Definitive and Detailed cost estimates are full-blown exercises that are undertaken to produce a
competitive bid submission or otherwise produce an accurate (plus or minus 10% or better) cost
estimate,

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 220

3
14-03-2023

Process Equipment Sizing and Costing for different process units

Table: Cost-Capacity Parameters a

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 221

Process Equipment Sizing and Costing for different process units

Process design
(material and energy balances to determine the
quantities of material processed and the amount
of energy transferred)

Preliminary equipment sizing


(Before equipment costs can be obtained, it is necessary to calculate
equipment sizes, specify operating temperatures and pressures as well
as materials of construction)

preliminary cost of equipment


f(equipment sizes, variation, operating temperatures and pressures and materials of construction)

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 222

4
14-03-2023

Process Equipment Sizing and Costing for different process units

Process Equipment Costing

Format for equipment cost-capacity data:


1. Equation Format
2. Graphical Presentation Format
3. Algorithm Format

 Size factor cost estimation


 Time factor cost estimation

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 223

Process Equipment Sizing and Costing for different process units

1. Equation Format
Simple convenient method of presenting cost data is by an equation (Capacity correlation):

Where
C1 = cost for equipment capacity S1
C2 = cost for equipment capacity S2
n = cost-capacity exponent that varies between 0.30 and 1.20 depending on the type of equipment

• The above equation is known as the six-tenths or 0.6 rule.


• This equation permits the user to obtain a cost for an equipment item of a different size when the
cost for given size is known.
• For most process equipment, the exponent (n) varies between 0.4 and 0.8 with an average value of
about 0.6 (When the exponent is unknown, this value may be used)

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 224

5
14-03-2023

Process Equipment Sizing and Costing for different process units

Typical equipment cost-capacity exponents (n)  Table: Cost-Capacity Exponents

Example:
Recently a cast iron leaf pressure filter with 100 ft2 was purchased for clarifying an inorganic liquid stream for
$15,000. In a similar application, the company will need a 450 ft2 cast iron leaf pressure filter. The size
exponent for this type filter is 0.6. Estimate the purchased price of the 450 ft2 unit.

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 225

Process Equipment Sizing and Costing for different process units

2. Graphical Presentation Format


Equipment cost data are presented in the literature by Guthrie, Hall et al., Hall et al., Peters and
Timmerhaus , Garrett, and Page as logarithmic plots of cost as a function of equipment capacity.

Figure: Compressors cost-capacity plot.


14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 226

6
14-03-2023

Process Equipment Sizing and Costing for different process units

• If possible, before using any cost-capacity data, it is


advisable to determine how the data were obtained and
correlated.
• The data accuracy may be high over a very narrow range of
capacity, usually in the middle of the range.

Economy of scale: Figure: Variations of n in a cost-capacity plot.


• The economy of scale is reflected in the exponent.
• If the n < 1.0  there is an economy of scale.
• As n approaches the value of 1  the economy of scale disappears.
• An n >1.0  a negative economy of scale and multiple equipment units should be used.

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 227

Process Equipment Sizing and Costing for different process units


3. Algorithm Format: Cost correlation based
• More convenient way to display cost-capacity data
• Readily adaptable in computer cost-estimating programs.
• Cost data may be represented by using an equation with equation modifiers to account for pressure,
temperature, materials of construction, equipment design type, etc.

Cost correlation equation for purchased cost:


Chilton’s Correlation (1949)
Guthrie's correlation (1968)   Douglas Book  Appendix E.2
..
..
Peter and Timmerhaus  Commercial software (Aspen etc.)

In-house cost & Installation correlation

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 228

7
14-03-2023

Process Equipment Sizing and Costing for different process units


3. Algorithm Format: Cost correlation based

Sizing

correlation

Purchased cost Installed cost

Need another set of factors  Installation factors

 Installation factors
• provide separate accountings for the piping required, instrumentations, structural support, building,
electrical equipment, insulation etc..
• Independent of pressure, Temperature, material of construction etc..

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 229

Process Equipment Sizing and Costing for different process units


3. Algorithm Format: Cost correlation based

• Purchased & delivered cost (uninstalled cost) = Base cost*Factor (P,T,MC etc) = BC*MFP
MFP: Material & Pressure correlation factor

• BC* Module Factor (MF) = BC + Installation cost including insulation, piping, electricity, building etc.

• Installation cost including insulation, piping, electricity, building etc. =BC*MF - BC

• Installed cost = Purchased & delivered cost (uninstalled cost) + Installation cost

• Installed cost = (BC*MF – BC) +BC*MFP = BC (MF +MPF-1)


Guthrie's correlation
• Updated Installed cost/bare module cost (BMC) = Installed cost *Update Factor  Douglas Book 
Appendix E.2
Note:
• Module Factor (MF) is also called Installation Factor (IF)
• Installed cost is also called capital cost/investment for a process equipment

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 230

8
14-03-2023

3. Algorithm Format: Cost correlation based

The total Installed equipment cost = ~ 4 * total purchased cost

Module Factor (MF) / Installation Factor (IF)

Different for kinds of processing equipments:


• Distillation column, Pressure vessels, pumps and instruments  4
• Heat exchanger  3.5
• Compressor  2.5 Hand’s Factor
• Fire heater  2
• Miscellaneous equipment  2.5

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 231

Process Equipment Sizing and Costing for different process units


3. Algorithm Format: Cost correlation based

 Peter and Timmerhaus  Commercial software (Aspen etc.)

For example, a shell-and-tube heat exchanger cost developed for ASPEN plus may be estimated from the
following basic correlation equation:

CE =1.218 CB * FD * FMC * FP (1.218  updated time to time)

where
CE = exchanger cost
CB = Base cost of a carbon steel, floating-heads exchanger, 150 psig design pressure
FD = Design-type cost factor if different from that in CB
FMC = material of construction cost factor
FP = design pressure cost factor

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 232

9
14-03-2023

Process Equipment Sizing and Costing for different process units


3. Algorithm Format…

Correlations for base cost, design type factor, material of construction factor, and design pressure factor
can be developed as secondary algorithms:

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 233

Process Equipment Sizing and Costing for different process units

In-house cost & Installation correlation:


• Called Company cost correlation
• These are frequently developed by using purchase repository, vendor’s quotation and recent construction costs.
• Must always be used when available

Read following article to have better understanding

https://doi.org/10.3390/en14092665

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 234

10
14-03-2023

Process Equipment Sizing and Costing for different process units

Update Factor:
It is necessary to bring the cost obtained from the above relationships (original cost) to the present time cost.

• Original 𝑰𝒏𝒔𝒕𝒂𝒍𝒍𝒆𝒅 𝒄𝒐𝒔𝒕 are presented as of a specific date.


• They are adjusted through the use of cost indexes that are based upon constant dollars in a base year and actual dollars
in a specified year.
• Projections of cost data into the near future have to take into account not only inflation rates but also short-term
estimates of what an index might be.
𝑃𝑟𝑒𝑠𝑒𝑛𝑡 𝑐𝑜𝑠𝑡 𝐼𝑛𝑑𝑒𝑥
𝑷𝒓𝒆𝒔𝒆𝒏𝒕 𝒄𝒐𝒔𝒕 / 𝑼𝒑𝒅𝒂𝒕𝒆𝒅 𝑰𝒏𝒔𝒕𝒂𝒍𝒍𝒆𝒅 𝒄𝒐𝒔𝒕/ BMC UF =
𝑶𝒓𝒊𝒈𝒊𝒏𝒂𝒍 𝑰𝒏𝒔𝒕𝒂𝒍𝒍𝒆𝒅 𝒄𝒐𝒔𝒕 ∗ Update Factor (UF) 𝑂𝑟𝑖𝑔𝑖𝑎𝑙 𝑐𝑜𝑠𝑡 𝑖𝑛𝑑𝑒𝑥

Cost Indexes:

• Cost indexes are used to perform an estimate of the actual cost of a process unit if the cost of the same unit,
referred to a past period, is known.
• It is generally not recommended to use cost indexes when the time interval is longer than 10 years.
• The cost index can also be used to extrapolate the present value of a process unit or a whole plant in the near
future (for instance at the expected time of purchase compared to the design time).

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 235

Process Equipment Sizing and Costing for different process units


Cost Indexes
• Many cost indexes are published on a regular basis.

The most commonly used cost indexes in the process industry are:
 Marshall & Swift (M&S): All industries and Process Industry (base 100 in 1926)
 Nelson-Farrar: Refinery construction index (base 100 in 1946)
 Chemical Engineering (CEPCI): Plant cost index (base 100 in 1959)
 Vatavuk (VAPCCI): Air pollution Control (base 100 in 1994)

Indexes apply only to labor and materials in specialized fields:


 Bureau of Labor Statistics (BLS)
 Mining and Metallurgical Index
 EPA–STP Treatment Plant Index
 OFJ–Morgan Pipeline Index
 Foreign Indexes
 Company Indexes

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 236

11
14-03-2023

Process Equipment Sizing and Costing for different process units

Cost Indexes..

Table: Cost Index

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 237

Process Equipment Sizing and Costing for different process units

Example: cost of purchase equipment

An oil at a rate of 490,000 lb/hr is to be heated from 100 to 170 F with


145,000 lb/hr of kerosene at initially at 390 F from another plant unit.
The oil stream enters at 20 psig and the kerosene stream at 25 psig.
The physical properties are:
Oil 0.85 sp. gr.; 3.5 cP at 135 F; 0.49 sp.ht.
Kerosene 0.82 sp.gr.; 0.4 cP; 0.61 sp.ht.

Estimate the cost of an all carbon steel exchanger in late 2001.


Assume a counter flow shell-and-tube heat exchanger.

Figure: Shell-and-Tube Heat Exchanger

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 238

12
14-03-2023

Process Equipment Sizing and Costing for different process units

Heuristics or rules of thumb may be used for a preliminary sizing and cost estimate.

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 239

Process Equipment Sizing and Costing for different process units

Table: Cost Index

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 240

13
14-03-2023

Figure: Purchased cost of double-pipe heat exchangers


14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 241

Figure: Purchased cost of multiple-pipe heat exchangers

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 242

14
14-03-2023

Figure: Purchased cost of U-tube heat exchangers with 0.0254-m (1 -in.) OD tubes x 0.0254-m (1-
in.) square pitch and 4.88-m (16-ft) bundles operating at 1035 kPa (150 psia)
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 243

Figure: Purchased cost of fixed-tube-sheet heat exchangers with 0.019-m (|-in.) OD x 0.025-m (1-in.) square
pitch and 4.88- or 6.10-m (16- or 20-ft) bundles and carbon steel shell operating at 1035 kPa (150 psia)

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 244

15
14-03-2023

Figure: Purchased cost of floating-head heat exchangers with 0.019-m OD x 0.025-m (3/4 in. OD x 1in.)
square pitch and 4.88-m (16-ft) bundles of carbon-steel construction
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 245

Process Equipment Sizing and Costing for different process units

“EQUIPMENT COSTS” accompanying Plant Design and Economics for Chemical Engineers, 5th edition, Peters,
Timmerhaus, and West 
http://www.mhhe.com/engcs/chemical/peters/data/

Look for example similar to Heat Exchanger…and figure out sizing and costing

Equipment Costs  Cost Information for a designed process

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 246

16
14-03-2023

Process Equipment Sizing

• https://processdesign.mccormick.northwestern.edu/index.php/Equipment_sizing
• FluidFlow Equipment Sizing Handbook https://fluidflowinfo.com/wp-
content/uploads/2018/04/FluidFlow-Equipment-Sizing.pdf
• Chapter 4, Process Engineering Economics by James Riley Couper
• https://pressbooks.bccampus.ca/chbe220/chapter/purchased-equipment-pe-cost/
• Process Engineering Economics by James Riley Couper

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 247

Cost diagram and


Screening of process alternatives

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 248

17
14-03-2023

Cost diagram and screening of process alternatives

Base case design  process alternatives  detailed cost analysis

• Process synthesis and analysis  Process Flowsheets as alternatives (set of case studies)
 Estimate the optimum design conditions
 selection of more profitable process alternative
• Every alternative is associated with costs  cost information
• Cost diagram is an approach to summarize the cost information

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 249

Cost diagram and screening of process alternatives


 Cost information:
• Summery of cost information related to equipments and operation
• Table of equipment cots coded to flowsheet
• Cost grouping
• Table for equipments of similar type Total Capitol Cost
• Table for operating costs  Total Operating Cost
• Provide investment/installed cost summary and operating cost summary for process
alternatives
• Process alternative screening

Cost information:
Table form Cost diagram

• Constrained to look at • A system viewpoint: look at


individual piece of equipment the total system
• Conventional approach of • Modern approach of cost
cost allocation allocation

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 250

18
14-03-2023

Cost information
 Cost information:
For any process alternative:

Pumps Capital cost Exchanger Capital cost


Investment/installed cost summary ($)
P1 x$ E1 x$
Reactor $ P2 y$ E2 y$
Furnaces $ P3 z$
Compressor $ Spare E11 $
Pumps $ Total: $ Total: $
Exchanger $
Trays $ Compressor Capital cost
Towers $ C1 x$
Total: $ C2 y$
Total: $

Costs of smaller items are neglected during screening alternatives.


Cost lumping is also done to develop expression for total cost associated with a process step.
14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 251

Cost information
 Cost information:
For any process alternative:
Operating cost summary ($/year)
Utility
Power $
Steam $
Fuel $
Water $
Total: $
Labor $
Supervision $
Taxes, insurance $
Repairs $
Miscellaneous $
Payroll charges $
Total: $
Catalyst $
Total: $

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 252

19
14-03-2023

Cost diagram

An alternating way of summarizing the most important processing cost in the pictorial form is to
put all the costs on the flowsheet  called Cost diagram:

1. Annualized, installed cost  inside the box of flow diagram Cost diagram provides visual picture:
2. Annual operating costs are  attached to the stream arrows • on how the costs are distributed throughout the
process.
• Used to spot error and visualize/identify potential
3. Per unit annualized installed and operating cost improvements by flowsheet modification
• A system viewpoint

Cost information:
Table form Cost diagram

• Constrained to look at • A system viewpoint: look at


individual piece of equipment the total system
• Conventional approach of • Modern approach of cost
cost allocation allocation

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 253

Cost diagram

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 254

20
14-03-2023

Cost diagram

Figure: Cost diagram of Dehydrogenation of isopropanol to produce


acetone.

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 255

Quick screening of process alternatives

Using Cost diagram, quick screening of process alternatives is possible:

Hierarchical Approach of process design


(systematic procedure for developing a process design)

Level 2
List of design decision during base-case design Level 3
development and associated decision change Numerous process
Level 4a
alternatives
Level 4b
Level 5
Process alternatives
Example: Process alternatives for the
HDA process
Cost diagram as tool to make some estimates of
economic importance of each process alternatives

Quick screening of process alternatives

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 256

21
14-03-2023

Preliminary designs
a) Used as a basis for determining whether further
work should be done on a proposed process.
Types of process design: b) Approximate process methods and approximate
1. Order of magnitude of design cost estimates are prepared.
2. Study of factored design c) Design details and the time spent on calculations
3. Preliminary designs are kept to a minimum.
4. Detailed-estimate designs Detailed-estimate designs
5. Final process designs a) This is done when preliminary design shows good prospect.
b) Here the cost-and-profit potential of the process is determined.
c) Exact specification are not given for the equipment.
d) Piping and layout work is minimized.
Final process designs
a) Undertaken if the detailed-estimate design indicates commercial success.
b) Complete specifications are presented for all components of the plat.
c) Accurate cost analysis based on quoted price is done.
d) Profit analysis and plant-wide controllability studies are done.
e) Includes detail documentation for immediate construction of project.

14-03-2023 CL 306 Process Engineering & Economics, Dr. Sumit kumar IITG 257

22

You might also like