Professional Documents
Culture Documents
Process planning is the key link for integrating design and manufacturing
Aggregate Planning
Forecast
Master Production
Schedule
Demand
Material Requirements
Planning
Individual Order
Scheduling
9/30/2019 CIM UNIT II (VM) 47
9/30/2019 CIM UNIT II (VM) 48
The main idea behind aggregate planning
Aggregate planning
Translates business plans into
rough labor schedules and
production plans
Costs Inventory
Production requirement
Ending Inventory
Ending Inventory 0 0 0 0 0 0
Workers required
Workers hired
Hiring cost
Layoff cost
Labor cost
Worker hours per month 176 152 168 168 176 160
Workers required 40 49 33 27 31 50
Workers hired 0 9 0 0 4 19
Shortage
3,495
cost
Inventory
798
cost
Outsourcing
44,160
Cost
Shortage
Hiring cost 6,400 3,495 Layoff Cost 3,250
cost
Inventory Outsourcing
Layoff cost 5,500 798 44,160
cost Cost
WHAT IF…
Disaggregation:
Aggregate Plan
Month Jan Feb Mar
Lawn Mower 200 300 400
Master Schedule
Push 100 100 100
Self-propelled 75 150 200
Riding 25 50 100
Total 200 300 400
Total of aggregate and
disaggregate products are not
9/30/2019 necessarily equal
CIM UNIT II (VM) 68
Master Schedule
The master schedule then is used as the basis for short term planning.
It says we need 75 push lawnmowers in January. But it does not say how we get it -
from production, or from inventory.
Inputs Outputs
Master
Forecast Projected inventory
scheduling
The key idea is: we have a forecast, but it turns into and actual
order when we receive a customer order.
Beginning
Inventory
JUNE JULY
64 1 2 3 4 5 6 7 8
Forecast 30 30 30 30 40 40 40 40
Customer Orders
(committed) 33 20 10 4 2
Projected on-hand
inventory 31 1 -29 Forecast is larger than
Customer orders in week 3
Suppose the economic production lot size for this product is 70 units.
The negative projected inventory of -29 in period 3 calls for production, 70 units
are produced, the projected inventory becomes 41.
64 June July
1 2 3 4 5 6 7 8
Forecast 30 30 30 30 40 40 40 40
Customer Orders 33 20 10 4 2
(committed)
Projected on 31 1 41 11 41 1 31 61
hand inventory
MPS 70 70 70 70
64 June July
1 2 3 4 5 6 7 8
Forecast 30 30 30 30 40 40 40 40
Customer Orders 33 20 10 4 2
(committed)
Projected on 31 1 41 11 41 1 31 61
hand inventory
MPS 70 70 70 70
ATP is only calculated for the first week and for weeks in which there is a MPS quantity.
(In this example: weeks 1, 3, 5, 7, 8)
64 June July
1 2 3 4 5 6 7 8
Forecast 30 30 30 30 40 40 40 40
Customer Orders (committed) 33 20 10 4 2
Projected on hand inventory 31 1 41 11 41 1 31 61
MPS 70 70 70 70
ATP 11 56 68 70 70
64 June July
1 2 3 4 5 6 7 8
Forecast 30 30 30 30 40 40 40 40
Customer Orders (committed) 33 20 10 4 2
Projected on hand inventory 31 1 41 11 41 1 31 61
MPS 70 70 70 70
ATP 11 56 68 70 70
64 June July
1 2 3 4 5 6 7 8
Forecast 30 30 30 30 40 40 40 40
Customer Orders (committed) 33 20 10 4 2
Projected on hand inventory 31 1 41 11 41 1 31 61
MPS 70 70 70 70
ATP 11 56 68 70 70
As additional orders are booked, they would be entered into the schedule.
Marketing can use updated ATP amounts to provide realistic delivery dates to customers
1 2 3 4 5 6 7 8 9 10 11 12
9/30/2019
Frozen Firm CIM UNIT
FullII (VM) Open 81
Assignment
Committed customer orders for the next four months are 80,
50, 30, and 10, respectively. Order size is 100 units.
Beginning inventory is 0.
Prepare MPS
Prepare ATP
Month
1 2 3 4
Forecast 70 70 70 70
Customer Orders
Inventory on hand
MPS
ATP
Month
1 2 3 4
Forecast 70 70 70 70
Customer Orders 80 50 30 10
Inventory on hand
MPS
ATP
Month
1 2 3 4
Forecast 70 70 70 70
Customer Orders 80 50 30 10
Inventory on hand 20
MPS 100
ATP
Month
1 2 3 4
Forecast 70 70 70 70
Customer Orders 80 50 30 10
Inventory on hand 20 50
MPS 100 100
ATP
Month
1 2 3 4
Forecast 70 70 70 70
Customer Orders 80 50 30 10
Inventory on hand 20 50 80
MPS 100 100 100
ATP
Month
1 2 3 4
Forecast 70 70 70 70
Customer Orders 80 50 30 10
Inventory on hand 20 50 80 10
MPS 100 100 100
ATP
Month
1 2 3 4
Forecast 70 70 70 70
Customer Orders 80 50 30 10
Inventory on hand 20 50 80 10
MPS 100 100 100
ATP 20
Month
1 2 3 4
Forecast 70 70 70 70
Customer Orders 80 50 30 10
Inventory on hand 20 50 80 10
MPS 100 100 100
ATP 20 50
Month
1 2 3 4
Forecast 70 70 70 70
Customer Orders 80 50 30 10
Inventory on hand 20 50 80 10
9/30/2019
MPS 100 CIM UNIT100
II (VM)
100 86
ATP 20 50 60
Material Requirement Planning (MRP)
Material Requirement Planning (MRP)
______________________________________
______________________________________
Key Outputs of MRP
• Calculate demand for component items
• Determine requirements for subassemblies, components, and raw material
• Determine when they are needed
• Generate work orders and purchase order
• Consider lead time
100 x 1 =
100 tabletops
100 tables
100 x 4 = 400 table legs
300 –
No. of tables
200 –
200 –
100 –
100 –
1 2 3 4 5
Week M T W Th F M T W Th F
Material
Requirements
Planning
(MRP)
Level 0
Clipboard
PERIOD
MPS ITEM 1 2 3 4 5
Clipboard 85 95 120 100 100
Lapdesk 0 50 0 50 0
Lapboard 75 120 47 20 17
Pencil Case 125 125 125 125 125
C(3) D(2)
LT=4 LT=2
Capacity
• Aggregate Planning • MRP
production • MPS • CRP
planning
• RCCP
• RRP
Capacity Capacity
Planning Planning
&
How EOQ Works
The Principles Behind EOQ: The Holding Costs
Interest
Obsolescence
Storage
How EOQ Works
The Principles Behind EOQ: The Procurement Costs
Total Cost
Formula
Taking the derivative of both sides of the equation and setting equal to
zero to find the minimum value of the function, one obtains:
How EOQ Works
The EOQ Formula
Holding Cost
Factor
Real Life Example:
R = Annual demand
C = Fixed ordering cost
P = Cost per case
F = Holding Cost Factor
Real Life Example:
R = 5200
C = $10 per order
P = $2
F = 20% of value of inventory
per year
Real Life Example:
R = 5200
2 (10) (5200)
C = $10 per order
EOQ =
P = $2 (2 )(.20)
F = 20% of value of inventory
per year
Real Life Example:
2 (10) (5200)
EOQ =
(2 )(.20)
Finance &
Accounting
Human
Resources