Safety/Personnel Observations
All equipment inspected and working condition observed. Check power cords and hydraulic
hoses. Every day before use must be inspected.
Overall Observed, LOTO tags Need to be completed, was discussed and Corrected
All crews and individuals observed committed to HSE Program. Good use of PPE and
keeping hands out of pinch points.
Heat and humidity major concern of workforce. Heat up to 104 Degrees today
Comments: Safety Cones are being set up for drop zone in proper locations, good jobs.
Field Images
S
Tower I-6 JSCA good and complete
Tower I-6 Inspection on lifting bags
or in good Condition
Tower I-6 back side of JSCA
Tower I-6 inspection of lifting bags
in good condition.
Tower I-6 confined space log must be
complete before entering.
Tower I-6 Photo of proper
extracting practices for working in
the blade for confined space.
Tower K-1 JSCA Need to have tower #
Tower K-1 need to have correct day,
Issue was corrected.
Tower K-1 wire out of box in
the Lift.
End of Report
Tower K-1 equipment should
not have power cord
underneath