Flowchart for Large

Distributed Generation
Connections Quote accepted

Your appointed Commercial If further negotiations with


Contracts Manager/Connection affected third parties do not
Manager will contact you to provide an acceptable resolution
discuss the connections process your connection may have to be
and schedule any meetings redesigned and requoted

You will be required to enter


into a Connection Agreement
with us

If a new substation is to be adopted


we will require to purchase or lease
Type of quote
the substation site in addition to any
accepted
wayleaves required.

Please note that we will be unable to


Non-Contestable Works are energise the substation until the land
works which are necessary for the purchase/lease documentation is
provision of a connection that only we complete.
can provide, usually the final connection
to our existing network. For details on this process please
see our Land Rights information.
Contestable Works are works Non-Contestable All Works
which can be provided by third parties
such as Independent Connection
Providers (ICPs) or Independent
Distribution Network Operators (IDNOs). If you accept our “All Works”
quote our Wayleaves Officer will
negotiate the wayleave/servitude/
easement with the third party and
Your allocated Connection apply for any statutory consents
For further details on your connection You will need to appoint an ICP Manager will contact you to
choices please see to build the Contestable Works required.
discuss your project and arrange
our You Have a Choice information. a site visit, if required If you accept the ”Non-Contestable”
element of our quote your ICP will
(Within 7 days for LV) obtain the necessary land rights and
(Within 10 days for HV) consents and will send the final
(Within 15 days for EHV)
Low Voltage – not more than 1kV. documentation to us for completion.
High Voltage – more than 1KV but not
more than 22kV. Please note that simple wayleaves
Extra High Voltage – More than 22kV can take 12 to 16 weeks to complete.
but not more than 72kV.
For further information please
see our Wayleave Guide.

Any excavations required in the public


highway require notice to be given be
given to the Local Roads Authority and
other utility companies. Are any of Yes
Wayleave(s)/servitude(s)/
the works on third
easement(s) will be required
If you accept our “All Works” quote we party land?
will notify the relevant parties. If you
have appointed an ICP to carry out the
Contestable Works they will notify the
relevant parties.
No
The following periods of notice are Yes Agreement No
required: reached with third
party/parties?
- 3 days for minor works (works with a
planned duration of three days or less.
- 10 days for standard works (works
with a planned duration of between four
and ten days).
- 3 months for major works (works ICP/ IDNO constructs the We construct all the works
requiring a temporary traffic order or with Contestable Works to the agreed required for your
a planned duration of 11 days or more). design connection

Your IDNO will arrange and Are the We will arrange and send Please note that SHEP/SEPD cannot
send you your Meter Point No Contestable Works Yes you your Meter Point install your electricity meter.
Administration Number to be adopted Administration Number
(MPAN) by us? (MPAN) For further information on how
to get your meters connected
please see our MPAN guide.

For competition in connections


please see our For ICPs and IDNOs
information.
We may contact you to obtain the
following additional technical
To access our specifications, network
information:
information and GIS please see our
secure Online documentation, which
1. Required installation date
requires an account login.
2. Current Transformer (CT) Ratio
3. Supply Voltage
4. Cut Out
For further details on our network 5. Earthing Type
adoption process please see our
Network Adoption Flowchart. Once this information is received it will
be passed to our Distribution Billing
Income Team who will raise
a request for our CT Fitter to
You register your MPAN with your install the CT's.
preferred electricity provider

(Please allow 28 days for registration)

You notify your preferred electricity


You notify us of the
provider of your scheduled
energisation date you require
connection date
(10 days notice for LV)
(20 days notice for HV)
(Normally 10 days notice is required)

Your preferred electricity provider If we request to witness the test


We carry out the witness/
will arrange for your meter to be you will be required to give us details
commissioning tests
installed of the scope, time and date of
testing at least 15 days before
commissioning.

We do the final connection

You are now


connected

Inveralmond House, 200 Dunkeld Road, Perth PH1 3AQ ssen.co.uk


Scottish and Southern Electricity Networks is a trading name of: Scottish and Southern Energy Power Distribution Limited Registered in Scotland No. SC213459; Scottish Hydro Electric Transmission plc
Registered in Scotland No. SC213461; Scottish Hydro Electric Power Distribution plc Registered in Scotland No. SC213460; (all having their Registered Offices at Inveralmond House 200 Dunkeld Road
Perth PH1 3AQ); and Southern Electric Power Distribution plc Registered in England & Wales No. 04094290 having its Registered Office at 55 Vastern Road Reading Berkshire RG1 8BU which are
members of the SSE Group www.ssen.co.uk

You might also like