Current/Correction ID ID Stem content KEY Option A content Option B content Option C content Option D content Option E content Key Rationale (Old)
840609 1.9 A Project Manager realizes that sponsor expectations are NOT being met, specifically regarding project A Update the risk Develop a Develop a Create a work The Risk Register may have existing entries about
deliverables. register. stakeholder communications breakdown structure the potential for the sponsors expectations not
engagement plan. management plan. (WBS). being met that need updating. If there were no
To address this issue, which action should the Project Manager take? existing entries, then there will be new risks
No changes needed associated with any plan of action.
840610 2.10 A customer is contemplating adding new features to the project deliverable. B Gain approval from Ensure the change Gain approval from the Ensure key subject The Change control board is a formally chartered
the Project control board (CCB) project sponsor. matter experts group responsible for reviewing, evaluating,
Before a project team member starts working on these new features, what is a mandatory step? Manager. approves. (SMEs) approve. approving, deferring, or rejecting changes to the
project and for recording and communicating such
No changes needed decisions.
840611 2.3 A project is at the multi-functional planning phase. The Project Manager realizes that producing a complex D Mitigate Transfer Accept Avoid The risk to the project was posed by insufficient
application is not feasible with the current number of resources and decides to hire more resources for the resources. The risk was Avoided by hiring additional
production of the application. The Project Manager identifies temporary resources and signs a service level resources.
agreement (SLA) with them.
No changes needed What is the next step the Project Manager should take?
840613 2.11 After realizing that there are insufficient resources on a project that has an increasingly high workload, B Review the Revise the Escalate to the project Prepare an The Procurement Management Plan is where the
management outsources some major tasks to keep the project on schedule. communications procurement sponsor. organizational chart. process of documenting project procurement
management plan. management plan. decisions, specifying the approach and identifying
What should the Project Manager do in this scenario? potential sellers is captured. The key benefit of this
process is that it determines whether to acquire
goods and services from outside the project and, if
so, what to acquire as well as how and when to
Correction acquire it.
840614 2.11 A project has the following need: B Hold direct Conduct a bidder Ensure the Have each of the A bidder conference is a meeting between the
negotiations with conference with the procurement providers added to buyer and prospective sellers prior to proposal
900 resource hours must be outsourced. each provider. providers. management plan is the stakeholder submittal. They are used to ensure that all
sent to each provider. register. prospective bidders have a clear and common
Because of internal policies, all providers must be given the same information about the requirements. understanding of the procurement and no bidders
receive preferential treatment.
No changes needed Which action should the Project Manager take to ensure this?
840615 2.13 A company has a goal of increasing customer satisfaction within 4 months. A project is initiated to meet this goal. B Benchmarking Focus groups Facilitation Affinity diagram Focus Groups should be used to gather feedback
from actual customers. This ensures that any
The Project Manager needs to identify best practices. decisions are made off of real data rather than
assumptions.
What should the Project Manager utilize to accomplish this?
Current
840615 2.13 A company has a goal of increasing customer satisfaction within 4 months. A project is initiated to meet this goal. B Benchmarking Interviews Facilitation Affinity diagram Interviews should be used to gather feedback from
actual customers. This ensures that any decisions
The Project Manager needs to identify best practices. are made off of real data rather than assumptions.
Correction Which category of COQ should the Project Manager have used?
840617 2.3 A Project Manager is doing the following: A Creating a project Preparing a project Creating the project Preparing a risk The other options require a more detailed project
charter. scope statement. management plan. management plan. scope
-conducting a risk analysis based on a high-level scope, and
-using expert judgement to prepare a document.
Correction What is the Project Manager doing, based on the description of the activity?
840618 2.10 A project is started based on the approved scope. A Conduct a risk Enact the Perform Resolve the issue to Contact the customer The Risk Register exists for the project team and
analysis and update Integrated Change satisfy the customer. and negotiate for risk stakeholders to understand potential problems with
As the project design is being implemented, a team member says that the product will not meet the the project sponsor. Control process. acceptance. the project. Since the team member may not have
requirements in certain situations. Correcting the issue will not only cause an increase in scope and costs, but the all the answers, it is necessary to first perform a full
project will also miss the deadline. risk analysis and update the project sponsor before
making any decisions.
The project sponsors do not have additional funding to support the project.
Reference Considering this information, what should the Project Manager do?
840619 2.4 A Project Manager realizes that stakeholder interests will conflict on a project and decides to utilize a stakeholder A Produce a Convey the Gain consensus on Ensure that the Plan Stakeholder Engagement is the process of
engagement assessment matrix. stakeholder stakeholder project objectives by stakeholder register developing approaches to involve project
engagement plan. engagement plan. meeting with all is complete and stakeholders based on their needs, expectations,
The matrix pinpoints an influential stakeholder who is resistant to the project. The Project Manager needs to align stakeholders. updated. interests, and potential impact on the project. The
this stakeholder's expectations. key benefit is that it provides an actionable plan to
interact effectively with stakeholders.
No changes needed What should the Project Manager do to accomplish this goal?
840620 2.8 A medium-sized company is expanding into a new market. However, the company does not have previous B Prototypes Expert judgment Product analysis Create requirements Experts come with many lessons learned. Given the
experience in that market. traceability matrix increased risks of a new and potentially complex
market, using expert judgement is recommended.
A Project Manager needs to collect requirements.
Current What is the first action the Project Manager should take?
840626 2.17 Review the following project characteristics: B Rely on the Examine the Determine the Close all project Project closure guidelines or requirements will
communications organization's project potential impact of procurement contain the organization's procedures to follow.
-The project is in initiation. management plan closure guidelines. terminating the project processes.
-Due to lack of funding, the project gets terminated. to properly inform by performing a risk
-The Project Manager must close the project. all stakeholders. analysis.
Correction What is the first action the Project Manager should take?
840627 2.4 A project has the following characteristics: A Examine the project Present the project Request that the Ask the new The first version of the stakeholder engagement
charter with the schedule and the functional manager stakeholder to pair plan is developed after the initial stakeholder
-A functional manager is also a project stakeholder. new stakeholder specific, assigned briefs this new with a more community has been identified by the Identify
-The functional manager has time constraints and delegates project responsibilities to someone else on the and assess their tasks to the new stakeholder and ask experienced Stakeholder process. The stakeholder engagement
functional team. level of stakeholder. that they send them to stakeholder to learn plan is updated regularly to reflect changes to the
-The new stakeholder is not attending meetings. engagement. all relevant meetings. responsibilities. stakeholder community.
[**Note for PMI Manager: This clone can be used for security purposes to identify if the original item has been
disclosed to a brain dump site and widely used for cheating. You can begin your analysis by observing if a
significant amount of individuals are choosing "Transfer" -- the old key. You can use these numbers in an attempt
Current to determine who / how many people are cheating.**]
840629 2.3 A project is being planned in a remote area with limited access to vehicles and equipment. The Project Manager C Transfer Mitigate Accept Avoid Risk acceptance is a risk response strategy whereby
proposes that the company deliver all heavy equipment themselves despite the significant expense. The Project the project team decides to acknowledge this low
Manager will take full responsibility for this activity. risk and not take any action unless the risk occurs.
Current What is the first document the Project Manager should review?
840635 2.12 A project team collected sensitive client data early on in the project to help develop the project management B Statement of work Issue log Business case Risk register After a new issue is raised, the issue log should be
plan. The team is now working on deliverables for the project. (SOW) reviewed and updated, as needed, prior to taking
action
The compliance manager raises an issue of project non-compliance.
Correction What is the first document the Project Manager should review?
840636 2.10 A project is underway and is 50% completed. C Check with this Discuss the issue with Assess how the leave Refer to the resource The FIRST thing the Project Manager needs to do is
team member to the functional will impact the project. management plan. to understand what impact (if any) this absence will
An essential project team member requests 1.5 months leave for personal matters. see if the leave can manager and request have on the project.
be postponed. a replacement.
Correction What should the Project Manager do first?
840637 2.3 A Project Manager works for a company that is preparing to develop a new product. The new product will require C Develop detailed Focus on quality Focus on the Develop a competitor If you plan to deliver a product and do not possess
currently unavailable skills. project control assessment of high- analysis the skills required, this is a risk.
requirements level risks
Current To initiate this project, what should the Project Manager do?
840637 2.3 A Project Manager works for a company that is preparing to develop a new product. The new product will require C Develop detailed Focus on quality Document the risk in Develop a competitor If you plan to deliver a product and do not possess
currently unavailable skills. project control. the project charter. analysis. the skills required, this is a risk. The risk should be
requirements. documented in the project charter so it's impact can
To initiate this project, what should the Project Manager do? be analyzed before project initiation.
Correction
840638 2.6 A Project Manager is uncertain about the duration of a new product and consults several groups B 23 days 25 days 27 days 30 days Using the PERT formula: [Pessimistic estimate +
of subject matter experts (SMEs). The first group advises that development can be finished in 25 days. The second 4(Average estimate) + Optimistic estimate]/6 = PERT
group identifies some risks that could make the duration up to 40 days. The third group proposes a new Estimate.
development method that can shorten the time to 10 days. Therefore, [10 + 4(25) + 40]/6 = 25.
Current What is the evaluation estimate for the duration for the new project?
840638 2.6 A Project Manager is uncertain about the project duration for a new product and consults several groups B 23 days 25 days 27 days 30 days Using the Triangular formula: [Pessimistic estimate
of subject matter experts (SMEs). The first group advises that it can be finished in 25 days. The second + Most likely estimate + Optimistic estimate]/3 =
group identifies some risks that could make the duration up to 40 days. The third group proposes a new method Therefore, [10 + 25 + 40]/3 = 75/3 = 25.
that can shorten the time to 10 days.
Correction Using the triangular estimating technique, what is the duration for the new project?
840639 2.6 A new product development project has the following characteristics: B Finish-to-start (FS) Finish-to-finish (FF) Start-to-start (SS) Start-to-finish (SF) While there is no DIRECT relationship between A
and B, both must be completed before C can start,
-There are three main tasks. so, of the choices, the only response that makes
-Task A must be delivered 4 weeks before task C starts. sense is FF
-Once task B is finished, task C will start.
No changes needed Which tool or technique can the Project Manager use for this task?
840642 2.7 A product passes 96% percent of the functional requirements defined in the scope. A customer is unwilling to C Assessed and Created the work Ensured that the Reviewed the Quality metrics are a description of a project or
accept the product since it did not pass 100%. evaluated the test breakdown structure quality metrics were requirements product attribute and how to measure it.
management plan. (WBS). defined. documentation.
A Project Manager is assessing what could have been done differently to avoid this.
Which estimating technique should the Project Manager use to obtain a precise cost estimate of the project?
Reference
840646 2.15 A project has the following characteristics: A Ensure that the Request that the Organize a meeting Continue with The FIRST thing the PM needs to do is to capture
issue log is updated finance department with the sponsor to planning, and this as an issue and communicate this to the other
-It is in the planning phase. and inform the provide a evaluate the situation acknowledge the stakeholders. Until then, no action can or should be
-A key stakeholder will be unavailable for 2.5 weeks during the project. other stakeholders. replacement during and identify impact the change taken.
the stakeholder's alternatives. may have on the
The Project Manager must decide what to do first, after learning about the key stakeholder's unavailability. absence. project schedule.
Current What is the next step that the Project Manager should take?
840652 2.5 A project is 7 months into execution. The Project Manager determines that the cost performance index (CPI) is A Issue a change Ask for additional Crash the project Utilize the Since the project is over budget and the trend
.80. request for cost re- resources. schedule. management reserve. analysis shows that this will continue, the best
baselining. course of action is to re-baseline the cost of the
According to a trend analysis, the CPI has a downward trend. project and manage to that.
Correction What is the next step that the Project Manager should take?
840653 2.3 A project is being implemented. A Anticipate risk Use forecasting Plan to use the Utilize methods such These new requirements may pose additional risks.
responses and methods. contingency reserve as earned value These risks need to be documented and appropriate
The research and development department communicates to the Project Manager that the product's modify the risk and update the risk management (EVM). responses need to be identified.
requirements have changed. These changes were not anticipated, may significantly influence potential sales register accordingly. mitigation plan.
numbers, and could impact project scope.
Current What is the appropriate action for the Project Manager to take?
840653 2.3 A project is being implemented. A Update the risk Use forecasting Plan to use the Utilize methods such These new requirements may pose additional risks.
register accordingly methods. contingency reserve as earned value These risks need to be documented and appropriate
The research and development department communicates to the Project Manager that the product's and identify risk and update the risk management (EVM). responses need to be identified.
requirements have changed. These changes were not anticipated, may significantly influence potential sales responses. mitigation plan.
numbers, and could impact project scope.
Correction What is the appropriate action for the Project Manager to take?
840654 2.5 A project has the following characteristics: B The project is ahead The project is behind The project is ahead of CV = EV - AC; 540-650 = -110
of schedule and schedule and over schedule and over The project is behind SV = EV - PV; 540-630 = -90.
-US$3 million budget under budget. budget. budget. schedule and under
-Planned cost of US$630,000 budget. Negative cost variance means over budget
-Actual cost of US$650,000 Negative schedule variance means behind schedule.
-Earned value of US$540,000
Current Which statement is true about the current status of the project?
840654 2.5 A project has the following characteristics: B The project is ahead The project is behind The project is ahead of The project is behind CV = EV - AC: 540 - 650 = -110
of schedule and schedule and over schedule and over schedule and under SV = EV - PV: 540 - 630 = -90
-US$3 million budget under budget. budget. budget. budget.
-Planned value of US$630,000 Negative cost variance means project is over budget
-Actual cost of US$650,000 Negative schedule variance means project is behind
-Earned value of US$540,000 schedule.
Correction Which statement is true about the current status of the project?
840655 1.5 A project is in the execution phase. C Build library Deliver workshops. Train the new team. Host a webinar. Develop Team is the process of improving
services. competences, team member interaction, and
Due to the demand for a quick turnaround time, the Project Manager needs to rapidly assign resources to build overall team environment to enhance project
the team and meet project requirements. performance. Training is a Tool & Technique of the
Develop Project Team process.
Current Which action should the Project Manager take next?
840655 1.5 A project is in the execution stage. C Build library Deliver workshops. Acquire and train the Host a webinar. Once the project team is established, the Project
services. new team. Manager can then start developing them. Develop
Due to a demand to complete the project quickly, the Project Manager needs to rapidly assign resources to build Team is the process of improving competences,
the team and meet project requirements. team member interaction, and overall team
environment to enhance project performance.
Which action should the Project Manager take next? Training is a Tool & Technique of the Develop
Correction Project Team process.
840656 3.2 A Project Manager leaves the company and is replaced. A Look over the Review the project Modify the project Revisit the project The Project Charter is one of the most important
project charter to diary and look schedule, adding a new budget to determine project documents. It defines many aspects of the
The new Project Manager wants to start guiding the team toward project success. identify goals and for notes made by activity related to the if extra time is project which are critical to the new Project
deliverables. the former Project knowledge transfer required. Manager's understanding of the project strategy, as
What should the new Project Manager do first? Manager. process. well as the tactical execution. Any other actions
before reading the official project charter will be
No changes needed made with a bias.
840657 3.2 A Project Manager receives the following for a new project: A Review and Put together the Build the project Ensure project The business case and project goals need to be
understand the project team and schedule and charter approval is understood first before a charter can be written.
-assumptions business case and assign project tasks. determine the critical obtained from the Building a team and a schedule come later in the
-restrictions project goals. path. sponsor. process.
-preliminary scope
No changes needed After receiving this information, what should the Project Manager do first?
840658 2.10 A Project Manager joins a project that has the following features: A Put any changes to Hold daily stand-ups Ask that all Disallow stakeholders Scope creep can be avoided by adherence to the
scope through the with all development development team from directly agreed upon change management process.
-Globally distributed team formal approval teams. leads prepare detailed interacting with the
-Budget that is fixed process. requirements. development team
-Very tight deadlines leads.
During planning, what should the Project Manager do to avoid any scope creep and keep the team focused on
Current delivering a product that meets requirements?
840658 2.10 A Project Manager joins a project that has the following features: C Ask that all Hold daily stand-ups Put any changes to Disallow stakeholders Scope creep can be avoided by adherence to the
development team with all development scope through the from directly agreed upon change management process.
-Globally distributed team leads prepare teams. formal approval interacting with the
-Budget that is fixed detailed process. development team
-Very tight deadlines requirements. leads.
During planning, what should the Project Manager do to avoid any scope creep and keep the team focused on
Correction delivering a product that meets requirements?
840659 2.2 A project is delayed. To obtain the desired quality level of the deliverables, a change is required. A Refer to the Provide a change Organize a meeting Review the The Monitoring of the communications process may
communications request to include with the project communications result in improved effectiveness of communication
First, the Project Manager issues a formal change request and communicates the change to all stakeholders. management and stakeholders' sponsor to better management plan, through additional and possibly amended
Then, the Project Manager learns that this communications approach did not meet stakeholders' expectations. stakeholder expectations in the understand follow it, and issue a communications plans and activities. Such iterations
engagement plans. project management stakeholders' status report. illustrate the continuous nature of the Project
What should the Project Manager do next? plan. expectations. Communications Management processes. Issues or
key performance indicators, risks, or conflicts may
trigger an immediate revision.
Current
840659 2.2 A project is delayed. To obtain the desired quality level of the deliverables, a change is required. A Refer to the Provide a change Organize a meeting Review the The Monitoring of the communications and
communications request to include with the project communications stakeholder engagement processes may result in
First, the Project Manager issues a formal change request and communicates the change to all stakeholders. management and stakeholders' sponsor to better management plan, improved effectiveness of communication through
Then, the Project Manager learns that this communications approach did not meet stakeholders' expectations. stakeholder expectations in the understand follow it, and issue a additional and possibly amended communications
engagement plans. project management stakeholders' status report. plans and activities. Such iterations illustrate the
What should the Project Manager do next? plan. expectations. continuous nature of the Communications
Management and Stakeholder Engagement
processes. Issues or key performance indicators,
risks, or conflicts may trigger an immediate revision.
Correction
840660 2.10 A project sponsor asks the Project Manager to change production materials because these materials could cause A Follow the project Immediately End the current work Reject the change The impacts of the change to the project must be at
health problems to consumers. change control implement the and enact the change because the request least qualitatively assessed, and Optimizely
process and change and submit a control process. is outside of scope. quantitatively assessed, before submitted to the
What is an appropriate step for the Project Manager to take? thoroughly change request for Chance Control Board. A Change Control Board
investigate the formal relies on the Project Manager to provide all
matter. documentation. available information for effective decision making.
Current
840660 2.10 A project sponsor asks the Project Manager to change production materials because these materials could cause A Follow the perform Immediately End the current work Reject the change The impacts of the change to the project must be
health problems to consumers. integrated change implement the and enact the change because the request analyzed and understood before being submitted to
control process and change and submit a control process. is outside of scope. the Change Control Board. A Change Control Board
What is an appropriate step for the Project Manager to take? thoroughly change request for relies on the Project Manager to provide all
investigate the formal available information for effective decision making.
matter. documentation.
Correction
840661 2.10 A project is in the execution phase. A Confirm that all Hold a meeting with Organize a meeting Ensure all requested The team and Project Manager must follow the
team members and the board and project with team members to
changes are applied documented and agreed upon change management
Three necessary changes are brought to the attention of the team. The team members all have differing opinions stakeholders sponsor to address review the issues and
to the project and processes.
regarding how to implement the changes. understand and the issue. request changes where
communicate directly
follow the change needed. with all team
Current What should the Project Manager do? management plan. members.
840661 2.10 A team was in the execution stage of the project management plan when three necessary changes were brought B Hold a meeting with Confirm that all team Organize a meeting Ensure all requested The team and Project Manager must follow the
to their attention. The team members all have differing opinions regarding how to implement the changes. the board and members and with team members to changes are applied documented and agreed upon change management
project sponsor to stakeholders review the issues and to the project and processes.
What should the Project Manager do? address the issue. understand and request changes where communicate directly
follow the change needed. with all team
Correction management plan. members.
840662 2.17 After a project ends, the Project Manager and project team members are still being asked to do the following: A Complete the hand Review the Formally disband the Continue to fulfill the Project closure and hand-off will ensure knowledge
over of the project. acceptance criteria project team and find a requests as the transfer to production and/or operations.
-Evaluate new requirements and get acceptance. new project. product is still being
-Make minor modifications developed.
-Solve technical issues
The Project Manager wants to ensure the product or service developed by the project now has operational
support.
Risk
Probability
Impact
A 1 5
B 4 4
C 2 5
D 2 2
Based on the table, in what order should the project manager rank these risks for risk management purposes?
Current
840666 2.3 A project sponsor is risk averse and is therefore concerned about negative impacts on the project. To help with B B, A, D, C B, C, A, D B, A, C, D C, D, A, B C, D, A, B Risk severity is calculated by multiplying probability
this concern, the project team identifies four project risks and then evaluates both the probability of occurrence and impact. For example, Risk A has a probability of
and the impact of the risk if it occurs. The team uses a 1-5 scale, 1 being the lowest and 5 being the highest. 1 and an impact of 5: 1 x 5 = 5. The higher the
value, the higher the risk is rated.
Risk
Probability
Impact
A 1 5
B 4 4
C 2 5
D 2 2
Based on the table, in what order should the project manager rank these risks for risk management purposes?
Correction
840667 1.11 A Project Manager needs to successfully lead a project that has diverse, globally-dispersed team members. A Be aware of local Seek help from the Travel to each team Explore each team The Project Manager needs to be proactive and
customs, remain human resource member's geographic member's culture in- learn what he can while also maintaining flexibility.
What should the Project Manager do to develop cultural sensitivity? flexible when department to obtain location to gain depth for several
working with team formal training in this awareness of their weeks to be sensitive
members, and area. culture and meet face- to their needs.
recognize that to-face.
Current culture is learned.
840667 1.11 A Project Manager needs to successfully lead a project that has diverse, globally-dispersed team members. D Explore each team Seek help from the Travel to each team Be aware of local The Project Manager needs to be proactive and
member's culture in- human resource member's geographic customs, remain learn what he can while also maintaining flexibility.
What should the Project Manager do to develop cultural sensitivity? depth for several department to obtain location to gain flexible when working
weeks to be formal training in this awareness of their with team members,
sensitive to their area. culture and meet face- and recognize that
needs. to-face. culture is learned.
Correction
840668 1.8 On a project, three critical risks with a high-impact are identified. A 1. Check with the 1. Hire outside 1. Assume the risks. 1. Generate a The functional manager is the person who will be
functional manager resources. 2. Control these risks contingency reserve able to reschedule, reassign or replace resources.
The Project Manager must find a solution to address these risks immediately. regarding the 2. Assign these often to reduce to solve the potential
resources' resources to handle potential impact. schedule delay.
Three specific resources are required to address the risks; however, they are already committed to another availability. the tasks. 2. Mitigate the
project with critical deliverables. 2. Negotiate task possible impact.
crashing or
Which action should the Project Manager take? rescheduling with
the functional
No changes needed manager.
840669 1.5 Schedule performance issues are occurring on a project. After assessing the issue, the Project Manager A Implement training Request that the Advise the senior-level Design and conduct The PM must train the junior members and supply a
determines that the cause is the expertise levels of project resources. where necessary, senior-level resources resources, and replace training for the junior- checklist so that all are checking all and only what
and create a help the the junior-level level staff. they are supposed to be checking.
Specifically, a few of the senior-level resources check irrelevant details, and some inexperienced resources take checklist for all inexperienced resources.
too much time to complete tasks. team members. resources.
No changes needed What should the Project Manager do to ensure that the deliverables are realistic?
840674 2.7 During user testing a client agreed to a final product. A few days later the client is reconsidering their agreement A Review the project’s Refer to the project’s Review the Refer to the project's The definition of acceptance criteria may
acceptance criteria. quality management requirements project charter. significantly increase or decrease quality costs and,
What should the Project Manager do? plan. documentation. therefore, project costs. Satisfying all acceptance
criteria implies the needs of the stakeholders have
Current been met.
840674 2.7 During user testing a client agreed to a final product. A few days later the client is reconsidering their agreement. B Refer to the Review the project’s Review the Refer to the project's Satisfying all acceptance criteria implies the needs
project’s quality acceptance criteria. requirements project charter. of the stakeholders have been met.
What should the Project Manager do? management plan. documentation.
Correction
840675 2.3 Although the sponsor and project team say that the new project has an adequate budget and realistic schedule, A Engage in Ask the project Schedule a meeting
Execute the project The Project Manager needs to be proactive and to
the Project Manager worries that unplanned events could threaten the project’s success. identification of sponsor for additional with the functional
as planned, familiarize himself with the identified risks and their
project risks, then funding to cover manager to address
recognizing that mitigation strategies.
What should the Project Manager do first? assess those risks. project planning. the potential impact of
additional project
unplanned risks.
funds must be
requested at a later
No changes needed point in the project.
840676 2.12 A large project includes functional groups in four countries. It is close to completion, so the Project Manager must A The project sponsor The steering The functional The four managers Since the sponsor provided the resources for the
prepare the closeout documents. should be asked to committee should be managers from each from the four project, it is their responsibility to officially sign off
sign off. asked to sign off. group should be asked countries should be on the project deliverables.
No changes needed How should the Project Manager obtain appropriate signoff on the acceptance of project deliverables? to sign off. asked to sign off.
840677 2.7 A project has the following characteristics: A Use a cause-and- Modify the quality Request that the Reach out to the By understanding the root cause of the issue, the
effect diagram for management plan to project to undergo an project sponsor for Project Manager may avoid this type of problem
-A quality management plan is in place. root cause analysis. conform to project internal audit. their input. later on in this and other projects.
-The quality management plan states that project deliverables must be reviewed, at a minimum, 1.5 weeks practices.
before the deadline.
-Four deliverables have missed this quality requirement.
Current To escalate the issue, what should the Project Manager do first?
840680 2.2 In response to slippage on some scheduled tasks, the Project Manager reprioritized a number of subsequent tasks C Refer to the change Review the Refer to the Review the risk The communications management plan is
in order to fix the problem. management plan. stakeholder communications management plan. developed to ensure that the appropriate messages
engagement plan. management plan. are communicated to stakeholders in various
The reprioritization did not put the project back on track, and now the Project Manager needs to escalate the formats and various means as defined by the
issue to project stakeholders. communication strategy.
Correction To escalate the issue, what should the Project Manager do first?
840681 2.7 A project is in the execution phase. B Control Statistical sampling Process audit Quality assurance Statistical sampling involves choosing part of a
procurement population of interest for inspection (for example,
Based on the originally approved blueprint, 1,000 products were developed. The project team randomly chooses selecting 10 engineering drawings at random from a
100 products to evaluate against the quality plan. list of 75). The sample is taken to measure controls
and verify quality. Sample frequency and sizes
What is the project team undertaking? should be determined during the Plan Quality
Current Management process.
840681 2.7 A project is in the execution stage. B Control Statistical sampling. Process audit. Quality assurance. Statistical sampling involves choosing part of a
procurement. population of interest for inspection (for example,
Based on the originally approved blueprint, 1,000 products were developed. The project team randomly chooses selecting 10 engineering drawings at random from a
100 products to evaluate against the quality plan. list of 75). The sample is taken to measure controls
and verify quality. Sample frequency and sizes
What is the project team undertaking? should be determined during the Plan Quality
Correction Management process.
840682 2.11 Because a deliverable does not meet the agreed-upon quality specifications, it is rejected by the customer. Team B Check the service Review the Check the internal Review the resource A contract is a mutually binding agreement that
members find that the deliverable does not meet expectations because there is a problem with vendor-provided level agreement procurement quality assurance management plan obligates the seller to provide the specified
parts. (SLA) established management plan reports. and document products, services, or results; obligates the buyer to
with the vendor. and contract lessons learned. compensate the seller; and represents a legal
The vendor says that they will not correct the problem. agreements. relationship that is subject to remedy in the courts.
No changes needed Before deciding on next steps, what should the Project Manager do?
840683 2.11 Several team members have been transferred to another project, so the Project Manager needs additional A Recommend a fixed Recommend a time Recommend a cost Recommend a firm A Fixed Price Incentive Fee Contract (FPIF) is a type
resource support from a new supplier. The Project Manager is concerned about the cost risk of using a new price incentive fee and material (TM) plus incentive fee fixed price (FFP) of contract where the buyer pays the seller a set
supplier at this stage of the project. (FPIF) contract. contract. (CPIF) contract. contract. amount (as defined by the contract), and the seller
can earn an additional amount if the seller meets
Now, the Project Manager needs to work with the procurement team to establish specifications and type of defined performance criteria.
contract to be used.
At which stage in the project should the Project Manager address this concern to optimize cost effectiveness?
Current
840777 1.2 All team members on a new project want to gain the customer's trust by delivering value as quickly as possible. C At the start of the Immediately after the During the next During the next The retrospective allows the team to learn about,
The Project Manager learns that one resource has worked with the sponsor on other projects. The resource team's performing first benefit retrospective resource improve and adapt their processes, so this would be
seems to be using personal influence, working with a project sponsor to increase the project's benefits stage. realization. ceremony. performance review. the event to address this concern.
realization.
At which stage in the project should the Project Manager address this concern to optimize cost effectiveness?
Correction
840778 3.1 A project team learns that there is a new compliance requirement from an international entity that may impact A Research the Address the Decline to address the Ensure that the The context of this scenario demands the Project
the baseline business case for the project. They learn this right after project charter is completed and the project requirement and requirement through issue, as the new requirement is Manager to influence the organization (sponsor)
sponsor has signed. possible the creation of a requirement is not part documented in the and recommend next steps after reviewing and
consequences, then quality management of the project's risk register, then ask understanding compliance requirements and
How should the Project Manager proceed? give the sponsor a plan. documented scope. for further guidance consequences.
recommendation. from all stakeholders.
Current
840778 3.1 A project team learns that there is a new compliance requirement from an international entity that may impact A Research the Address the Decline to address the Ensure that the The context of this scenario demands that the
the baseline business case for the project. They learn this right after project charter is completed and the project requirement and requirement through issue, as the new requirement is Project Manager influence the organization
sponsor has signed. possible the creation of a requirement is not part documented in the (sponsor), and recommend next steps after
consequences, then quality management of the project's risk register, then ask reviewing and understanding compliance
How should the Project Manager proceed? give the sponsor a plan. documented scope. for further guidance requirements and consequences.
recommendation. from all stakeholders.
Correction
840779 1.10 A team misunderstood one product functionality documented in an earlier stage of the project. During the B The functionality Schedule a meeting Ensure that the issue is Continue with the As the functionality has not been built the Project
current iteration, the functionality has not yet been developed, but a business representative has mentioned the was formally to discuss and addressed by current sprint, Manager should facilitate building common
deficiency. approved, so brainstorm the escalating it to the recognizing that the understanding and empowering the team to
initiate the change functionality with the project sponsor, who issue will be evaluate the impact of a possible change, this way
How should the Project Manager proceed? management project team and should discuss it with identified during the avoiding re-work.
process. business the representative. testing phase.
No changes needed representative.
840780 1.5 Some agile approaches have recently been added to an infrastructure company's predictive processes. The team A Provide team Speed up the project Gain the needed time Use burndown charts Training can be a great way to empower team
is not completing the planned story points, and the they are becoming passive. The Project Manager is concerned training, so the by reducing the for story point to evaluate team members to grow their skillsets. This would also
and wants to improve productivity. team can do a backlog. completion by adding performance. create consistency in story point estimation
better job of more iterations to the techniques.
What should the Project Manager do? estimating story project.
No changes needed points.
840781 2.1 During one daily standup meeting, team members indicate that they are having to engage in rework because B Try using a Kanban Request that team Request that the Engage in a process Rework can often caused by trying to do too much
there seems to be too much up-front work. board for reviews. members explicitly project owner to manage a in too little time. Timeboxing is a great technique to
implement time maximizes the product reduction in the choose an appropriate window of time dedicated to
Current How should the Project Manager respond to this concern? boxing. value. product backlog. a single focus.
840781 2.1 During one daily standup meeting, team members indicate that they are having to engage in rework because B Try using a Kanban Request that team Request that the Engage in a process Rework can often be caused by trying to do too
there seems to be too much up-front work. board for reviews. members explicitly project owner to manage a much in too little time. Timeboxing or spikes are
implement time maximizes the product reduction in the great techniques to choose an appropriate window
Correction How should the Project Manager respond to this concern? boxing or spikes. value. product backlog. of time dedicated to a single focus.
840782 1.6 A Project Manager from a traditional project management organization is assigned to an ongoing project. C Employ third-party Add additional Add cross-functional Where possible, Agile methodologies require "T" shaped team
Recently, the organization has started to use agile methodologies in its projects. The Project Manager hears that specialists to fill the resources via a internal resources. modify Gantt charts members. That is, individuals who are cross-
some team members feel like key subject matter expertise is missing and there is insufficient collaboration within knowledge gap. request to the to Kanban boards. functional and understand the importance and
the team. sponsor. value-add of collaboration across functional areas.
Correction How should the Project Manager respond to these team members' concerns?
840783 1.8 A contractor has sent an email request for urgent payment of their last installment on a project that is going C Negotiate payment Authorize the Act according to the Authorize payment Even an inexperienced Project Manager should
through a long execution stage with multiple contractors. terms through a payment by notifying agreed upon only after reviewing understand that terms and conditions should be
meeting with accounts payable and commitments in the forecast spend versus agreed before engaging a contractor to actually do
How should the Project Manager respond to this contractor's request? procurement and follow up to ensure it procurement actual spend to see if project work. The procurement plan holds all data
the contractor. was made. management plan. the actual status re contracts and is the single source to guide
Current allows it. payment activities
840783 1.8 A contractor has sent an email request for urgent payment of their last installment on a project that is going C Negotiate payment Authorize the Act according to the Authorize payment Even an inexperienced Project Manager should
through a long execution stage with multiple contractors. terms through a payment by notifying agreed upon only after reviewing understand that terms and conditions should be
meeting with accounts payable and commitments in the forecast spend versus agreed before engaging a contractor to actually do
How should the Project Manager respond to this contractor's request? procurement and follow up to ensure it procurement actual spend to see if project work. The procurement plan and the
the contractor. was made. management plan and the actual status agreement/contract holds all data reference
the signed allows it. contracts and are the sources to guide payment
Correction agreement/contract. activities
841220 2.1 A Project Manager for a construction firm meets with stakeholders. All stakeholders agree on a 20 month A Meet with key Add team members Refuse to modify the Identify agreed-upon If it is possible to reduce the requirements for a
lifecycle for a project. After work has begun, the Project Manager learns that stakeholders would like project stakeholders to to work more quickly time line, explaining tasks in the original project with the sponsor and key stakeholders, this
completion within no more than 16 months. discuss ways to just this one time in that scope creep project and assign is preferred over crashing, fast-tracking, change-
reduce some order to satisfy should be discouraged. additional duties as control, and other methods which will most likely
What should be the first step in the Project Manager’s response? project stakeholder needed to meet the increase risk and create issues with a shortened
requirements. requirements. new, shorter timeframe.
No changes needed timeline.
841221 1.7 During an iteration, a project team encounters problems that may cause a delay in task completion. Another B Insist that the Work with the Increase the iteration Ask team members to May cause a delay does not mean the task
team within the same project needs the task to be completed on time in order to meet their schedule. project team work a product owner to length, and add perform to the best completion will be delayed, To improve probability
bit harder to reprioritize the additional resources to of their abilities of success, reprioritizing the backlog may improve
What can the Project Manager do to resolve this problem? complete on time, iteration backlog, so the project team, so during the iteration, the probability for success more than the other
in order to avoid that it does not delay that they can meet the and engage in a options.
delaying the work work by other teams. appropriate deadlines. retrospective after
of other teams. completion of the
No changes needed iteration.
841222 1.1 Certain key stakeholders are dissatisfied with how a key feature of a project has been developed. They express B Gather the project Identify the reasons Create a list of the pros Add a neutral party, Identifying the source of conflict is a key initial step
their dissatisfaction during an iteration review meeting. team for a why there are issues and cons of the such as the project in conflict management.
brainstorming with the feature, situation to define the sponsor, to function
What should the Project Manager do first to resolve this issue? session and identify then address the impact of the conflict. as a negotiator with
Current a solution. issue. stakeholders.
841222 1.1 Certain key stakeholders are dissatisfied with how a key feature of a project has been developed. They express B Gather the project Identify the reasons Create a list of the pros Add a neutral party, Working with the customer in identifying the source
their dissatisfaction during an iteration review meeting. team for a why there are issues and cons of the such as the project of dissatisfaction with the feature is a good first
brainstorming with the feature, situation to define the sponsor, to function step. This also helps with resolving conflict
What should the Project Manager do first to resolve this issue? session and identify then address the impact of the conflict. as a negotiator with between the team and stakeholders.
Correction a solution. issue. stakeholders.
841223 1.6 During a technical project, a well-liked project member is reassigned to a different project. The team has B Notify the project Employ coaching Add a resource with Notify the change PM should know how to handle key personnel
expressed disapproval regarding the reassignment. sponsor regarding tools and techniques the same skills to control board (CCB) changes and keep the team motivated and
the team’s to increase team replace the key team and discuss possible productive.
What action can help mitigate the team's disapproval? disapproval, and motivation. member. ways to resolve the
brainstorm a issue.
Current response.
841223 1.6 During a technical project, a well-liked project member is reassigned to a different project. The team has B Notify the project Employ leadership Add a resource with Notify the change The PM should know how to handle key personnel
expressed disapproval regarding the reassignment. sponsor regarding and emotional the same skills to control board (CCB) changes and keep the team motivated and
the team’s intelligence tools and replace the key team and discuss possible productive.
What action can help mitigate the team's disapproval? disapproval, and techniques to inspire member. ways to resolve the
brainstorm a the team to continue issue.
Correction response. working.
841258 1.1 A key team member is unhappy with the overall approach documented in a project management plan. The D Continue with the Continue with the Remember that a Make a short Conflict should be addressed in private, first, to
member surprises the Project Manager with negative comments about the approach during a weekly status meeting, and scheduled agenda project should not go
comment to better understand the concern being raised.
meeting during the execution phase of the project. ensure that the items after reminding forward when key acknowledge the Exploring the concern after the meeting gives the
concerns are added the team member of team members are inteam member’s PM an opportunity to verify the concern and
How should the Project Manager address the team member’s concerns? to the risk register expected meeting disagreement, and use
concerns, continue determine needed next steps without disrupting the
after the meeting is etiquette. Then, the meeting to discuss
with the meeting, and meeting with all meeting attendees.
finished. solicit feedback about the member’s meet with the
the etiquette concerns. member in private to
expectations. discuss their
Current concerns.
841258 1.1 During the execution of a project, a key team member is concerned with the overall approach documented in the D Continue with the Continue with the Remember that a Make a short Conflict should be addressed in private in order to
project management plan. The member surprises the Project Manager with negative comments about the meeting, and scheduled agenda project should not go comment to better understand the concern being raised.
approach during a weekly status meeting. ensure that the items after reminding forward when key acknowledge the Exploring the concern, after the meeting, gives the
concerns are added the team member of team members are in team members' PM an opportunity to verify it and determine next
How should the Project Manager address the team member’s concerns? to the risk register expected meeting disagreement, and use concerns, continue steps without disrupting the meeting with all
after the meeting is etiquette. Then, the meeting to discuss with the meeting, and meeting attendees.
finished. solicit feedback about the members' meet with the
the etiquette concerns. member in private to
expectations. discuss their
Correction concerns.
841263 1.7 A Project Manager is faced with an updated schedule that requires delivering a business result under a far more C Let the project Ensure that upper Ask the technical Work with a third- Per Agile manifesto, it values individual and
aggressive timeline. The project’s technical resource manager has worked with the Project Manager on previous sponsor know that management is resource manager party vendor to interactions over processes and tools. Thus, it is best
projects. Still, a team member indicates that the company does not have technical resources that could be added an issue with a aware of the lack of about the availability quickly acquire the to meet with the resource manager to understand
to the project to meet the new timeline. technical resource needed resources of technical resources needed resource. the real situation rather than informing sponsor first
may put the project which may put the which might be the false alarm.
Current What should be the Project Manager's next step? at risk. project at risk.
841263 1.7 A Project Manager is faced with an updated schedule that requires delivering a business result under a far more C Let the project Ensure that upper Ask the technical Work with a third- Per the Agile Manifesto, it values individuals and
aggressive timeline. The project’s technical resource manager has worked with the Project Manager on previous sponsor know that management is resource manager party vendor to interactions over processes and tools. Thus, it is best
projects. Still, a team member indicates that the company does not have technical resources that could be added an issue with a aware of the lack of about the availability quickly acquire the to meet with the resource manager to understand
to the project to meet the new timeline. technical resource needed resources of technical resources. needed resource. the real situation rather than informing sponsor
may put the project which may put the first.
Correction What should be the Project Manager's next step? at risk. project at risk.
841274 2.3 A Project Manager has been asked to conduct a risk analysis that is based on a high-level scope. As part of the this A Creating the project Preparing the scope Creating a project Documenting the risk Expert judgment is one of the tools and techniques
analysis, the Project Manager must use expert judgment to prepare a document. charter statement document management plan management plan for developing the project charter.
Current
841277 1.2 A projects’ daily standups are long, often lasting more than two hours. The project team uses the standup D Invite department Request shorter Insert a new team Coach team members With Agile, it is important for teams to know how to
meetings for extended discussions about solutions to project obstacles. managers to discussion time member who will that they have the implement the daily standup. The Project Manager
participate in the during each standup, manage obstacles and opportunity to should coach the team in how a daily stand-up
What should the Project Manager do to improve the daily standup meetings? team members’ leaving more time for meetings to discuss shorten all standup meeting is run and what is discussed. Teams run
discussions in order working. possible solutions. meetings and their own standups and when run well, they can be
to identify solutions improve their very useful. Daily stand-ups are typically 10-15 mins
in a business-like method for and three questions are answered: 1) What did you
manner. identifying solutions. do since the last stand-up?, 2) What will you do
today?, 3) Are there any impediments or
roadblocks? Separate meetings are held to discuss
the blockers and the solution.
Correction
843081 1.6 A new resource is assigned to fill in for a resource who is leaving. The new resource will be working on a small B Assess the new Meet with the new Privately ask the Meet with the A) No - This is not the best use of time, and unfairly
project that is critical to a larger program milestone. Unfortunately, there is a rumor that the new resource may resource’s resource to discuss program management functional manager makes presumptions on the candidate.
be a problem, due to a lack of skills. communication their skills and then officer (PMO) to assign of the new resource B) Yes - This is the best answer. Without seeing
skills to evaluate determine how they a different resource to discuss the rumor performance first-hand, there is no available proof
How should the program manager respond to this rumor? their ability to can contribute to the with better skills. and see if it is true. to the hearsay.
perform acceptably project. C) No - This assumes that hearsay is fact, which may
as part of the create a strained relationship between the Project
project team. Manager and functional manager.
D) No - While this may give solace to the Project
Current Manager, this is inappropriate and unwarranted.
843081 1.6 A new resource is assigned to fill in for a resource who is leaving. The new resource will be working on a small B Assess the new Meet with the new Privately ask the Meet with the A) No - This is not the best use of time, and unfairly
project that is critical to a larger program milestone. Unfortunately, there is a rumor that the new resource may resource’s resource to discuss project management functional manager makes presumptions on the candidate.
be a problem, due to a lack of skills. communication their skills and then office (PMO) to assign of the new resource B) Yes - This is the best answer. Without seeing
skills to evaluate determine how they a different resource to discuss the rumor performance first-hand, there is no available proof
How should the Project Manager respond to this rumor? their ability to can contribute to the with better skills. and see if it is true. to the hearsay.
perform acceptably project. C) No - This assumes that hearsay is fact, which may
as part of the create a strained relationship between the Project
project team. Manager and functional manager.
D) No - While this may give solace to the Project
Correction Manager, this is inappropriate and unwarranted.
843083 1.7 A team member could not be reached by email or phone during the week that they were absent. The team B Add a new resource Discuss the situation Require that the team Ask the functional Key Rationale
member had not notified anyone on the team prior to their absence. Due to the absence, several successor who can complete with the team member complete the manager for A) No - This is premature and will most likely take
activities are behind schedule, impacting the project’s critical path. the work package in member, and work work package more additional support on longer than attempting to rectify the situation.
a professional with them to identify quickly when they the project, including B) Yes - A Project Manager also has the ability to be
How should the Project Manager respond to this situation? manner. a workable solution. return. assignment of a new a coach. Servant Leadership encourages listening
resource. and serving, and therefore it may be possible to
compromise with the team member.
C) No - This does not address the situation and is in
direct contradiction to the coaching role of a Project
Manager.
D) No - This does not address the situation directly
and offsets blame to a third party.
Current
843083 1.7 A team member has been absent for a week without providing notification and could not be reached by email or B Add a new resource Discuss the situation Require that the team Ask the functional A) No - This is premature and will most likely take
phone. Due to the absence, several successor activities are behind schedule, impacting the project’s critical path. who can complete with the team member complete the manager for longer than attempting to rectify the situation.
the work package in member, and work work package more additional support on B) Yes - A Project Manager also has the ability to be
How should the Project Manager respond to this situation? a professional with them to identify quickly when they the project, including a coach. Servant Leadership encourages listening
manner. a workable solution. return. assignment of a new and serving, and therefore it may be possible to
resource. compromise with the team member.
C) No - This does not address the situation and is in
direct contradiction to the coaching role of a Project
Manager.
D) No - This does not address the situation directly
and offsets blame to a third party.
Correction
843770 2.6 A Project Manager is uncertain about the duration of a new product and consults several groups B 20 Days 40 Days 60 Days 30 Days Using 3 point, PERT, or average delivers an estimate
of subject matter experts (SMEs). The first group advises that development can be finished in 40 days. The second of 40
group identifies some risks that could make the duration up to 60 days. The third group proposes a new
development method that can shorten the time to 20 days.
Current What is the estimated development duration for the new product?
843770 2.6 A Project Manager is uncertain about the duration of a project for a new product and consults several groups B 20 Days 40 Days 60 Days 30 Days Using 3 point estimating: Triangular Estimate =
of subject matter experts (SMEs). The first group advises that development can be finished in 40 days. The second (Optimistic + Most Likely + Pessimistic)/3 = (20 + 40
group identifies some risks that could make the duration up to 60 days. The third group proposes a new + 60)/3 = 120/3 = 40 days
development method that can shorten the time to 20 days.
Beta Estimate = (Optimistic + (4 X Most Likely) +
What is the estimated development duration for the new product? Pessimistic)/6 = (20 + (4*40) + 60)/6 = 240/6 = 40
Correction days"
843772 2.6 A Project Manager is uncertain about the duration of a new product and consults several groups B 28 Days 30 Days 32 Days 36 Days Using 3 point, PERT, or average delivers an estimate
of subject matter experts (SMEs). The first group advises that development can be finished in 29 days. The second of 40
group identifies some risks that could make the duration up to 46 days. The third group proposes a new
development method that can shorten the time to 18 days.
Current What is the estimated development duration for the new product?
843772 2.6 A Project Manager is uncertain about the duration of a new project and consults several groups B 28 Days 31 Days 32 Days 36 Days Using a Triangular Estimate = (Optimistic + Most
of subject matter experts (SMEs). The first group advises that development can be finished in 29 days. The second Likely + Pessimistic)/3 = (18 + 29 + 46)/3 = 93/3 = 31
group identifies some risks that could make the duration up to 46 days. The third group proposes a new days
development method that can shorten the time to 18 days.
Using the Triangular estimation technique, what is the estimated development duration for the new product?
Correction
843775 2.6 A Project Manager is uncertain about the duration of a new product development project and consults several B 12 Days 16 Days 18 Days 20 Days PERT Estimate = (Optimistic + (4 X Most Likely) +
groups of subject matter experts (SMEs). The first group advises that development can be finished in 14 days. The Pessimistic)/6 = (8 + (4*14) + 32)/6 = 16 days
second group identifies some risks that could make the duration up to 32 days. The third group proposes a new
development method that can shorten the time to 8 days.
Current What is the estimated development duration for the new product?
843775 2.6 A Project Manager is uncertain about the duration of a new product development project and consults several B 12 Days 16 Days 14 Days 20 Days Using the Beta Estimate = (Optimistic + (4 X Most
groups of subject matter experts (SMEs). The first group advises that development can be finished in 14 days. The Likely) + Pessimistic)/6 = (8 + (4*14) + 32)/6 = 96/6 =
second group identifies some risks that could make the duration up to 32 days. The third group proposes a new 16 days
development method that can shorten the time to 8 days.
Correction What is the estimated development duration for the new product using the Beta estimation technique?
843783 2.2 A product passes 99% percent of the functional requirements defined in the scope. A customer is unwilling to C Properly evaluated Produced the work Defined and Verified the Quality metrics are a description of a project or
accept the product since it did not pass 100%. the test breakdown structure communicated the requirements product attribute and how to measure it.
management plan (WBS) quality metrics documentation
A Project Manager is assessing what could have done differently to avoid this.
Which type of communication should the Project Manager use first when contacting the vendor about this issue?
Current
844400 1.1 A project is utilizing a third-party contractor. A Face-to-face Phone Contractual Letter Email Face-to-face interaction is usually the most effective
way to build the trusting relationships that are
A member of the contractor's team raises an issue with a member of the project team. The two individuals are needed to manage a project. Once relationships are
not able to work out a solution. established, virtual interaction can be used to
maintain the relationship.
The Project Manager is aware of the disagreement.
Which type of communication should the Project Manager use first when contacting the vendor about this issue?
Correction
844429 2.5 A software vendor is behind on a key project deliverable. A Evaluate alternative Remove the current Ask the vendor to meet Accept the cost The first step is analysis and evaluation of alternate
software vendors vendor and have the to discuss legal issues overrun and update options. After that, specific and appropriate action
There is a 21% buffer in the budget for cost overruns. that can help new vendor send a regarding the the project schedule. can be taken.
project deliverables contract. slippage.
The Project Manager needs to mitigate the issue. despite resource
constraints.
Which action should the Project Manager take next?
Correction
844441 1.6 A project needs a specialized resource. A resource that fits the needs of the project is identified, and can work D Ask the existing Place a limit on the Put the project on hold Request that the The globalization of projects has promoted the need
onsite, but lives in another country. The visa process was expected to take weeks but is now taking months. team to work project's scope. by an equivalent resource work for virtual teams that work on the same project, but
overtime. duration. virtually. are not collocated.
What should the Project Manager do?
No Changes Needed
844443 2.9 To determine which product to create, a project feasibility study was conducted. However, a change request was A Perform the change Do not accept the Review a detailed Review a feasibility After a change request has been approved, it should
recently approved to develop another product that contradicts the original requirements. request. change request. report of the data study of the new be executed. If the new requirements did not
analysis. product. contradict the original ones, a change request would
Data specialists conducted an analysis before the change request was approved. likely not be needed in the first place.
No Changes Needed After receiving this information, what is the first step the Project Manager should take?
844521 2.10 A Project Manager recently joined a new project. A Ensure that any Ensure that daily Ensure that the Following the formal approval process is the best
changes to scope go stand-ups occur, with development team Ensure that way to control unnecessary project changes.
This project has the following characteristics: through the formal all development leads generate detailed stakeholders do not
approval process. teams. requirements. directly interact with
-Deadlines that are tight the development
-Global team that works virtually team leads.
-Fixed budget
The Project Manager is in the planning phase, and wants to avoid scope creep and keep the team focused on
delivering a product that meets requirements.
The Project Manager is in the planning stage, and wants to avoid scope creep and keep the team focused on
delivering a product that meets requirements.
B
4
2
C
3
3
D
2
2
No Changes Needed Based on the table, in what order should the Project Manager rank these risks for risk management purposes?
844595 2.17 A project is completed, but the Project Manager and project team members are being asked to do the following: A Execute the project Procure project Contact the project Since the product is At project close, the final product, service, or result
hand off. acceptance. team, dismiss them still under can be transitioned to a production support team.
-Troubleshoot and resolve technical issues from the project, and development,
-Evaluate new requirements find a new project. continue to fulfill the
-Make minor adjustments requests.
The Project Manager needs to ensure that the product developed by the project now has operational support.
Current
844595 2.17 A project is completed, but the Project Manager and project team members are being asked to do the following: D Since the product is Procure project Contact the project Execute the project In the Close project or phase process, the final
still under acceptance. team, dismiss them hand off. product, service, or result is transitioned to the
-Troubleshoot and resolve technical issues development, from the project, and production support team. Documentation should
-Evaluate new requirements continue to fulfill find a new project. be signed by the receiving group, agreeing to accept
-Make minor adjustments the requests. the final product, service, or result. Once signed,
the owner is responsible for changes, adjustments
The Project Manager needs to ensure that the product developed by the project now has operational support. and resolving technical issues.
Correction
844596 2.7 A project has the following characteristics: B The project team is The project team is The project team is The project team is Statistical sampling involves choosing part of a
performing utilizing statistical conducting audits. undertaking a quality population of interest for inspection. The sample is
-It is in the execution phase. inspections. sampling. control measure. taken to measure controls and verify quality.
-500 products have been developed based on the originally-approved blueprint.
-The project team randomly selected 50 products to evaluate against the quality plan.
Current What should the Project Manager do before presenting this new risk information?
844632 2.3 Four new risks for a project are identified while the Project Manager is preparing the monthly project status D Review the risk Review the Refer to the risk Add risks to the risk The first step would be to update the risk register
report. report and lessons organizational management plan and register, analyze and then analyze the new risks. This information
learned repository. process assets and the risk report. them for impact to can then be presented to stakeholders who will help
These four risks could affect vital key milestones. risk register. the project and determine a response plan for each risk.
identify response
Correction What should the Project Manager do before presenting this new risk information? plans.
844633 2.12 A project that is nearing completion has the following characteristics: A Seek the project Contact the steering Seek sign off from the Contact managers The project charter determines who will sign off on
sponsor's sign off. committee for sign director of the Project from the five the project, but of the given options, the sponsor is
-It is very large. off. Manager's business countries involved in the best answer due to their role.
-It contains functional groups in five different countries. unit. the project for sign
-Closeout documents are being prepared. off.
Correction Which document should be part of the first step in responding to the warning?
844815 2.5 The Project Manager learns that one team member needs to complete a critical task that is outside of the project, A Schedule a meeting Replace the team Notify the project Notify the team The resource management plan is used to help
resulting in a scheduling risk for the project. with the team member with a new sponsor, documenting member’s manager determine how resources allocated to agreed-upon
member’s manager resource from the conflict caused by of project needs, and risk responses will be coordinated with other
How can the Project Manager eliminate this risk? to negotiate for another department. the member’s require the release of project resources. This will provide guidance as to
additional time to manager. the member until the how the Project Manager can negotiate with the
complete the other project activity is resource's manager.
task. completed.
Current
844815 2.5 The Project Manager learns that one team member needs to complete a critical task that is outside of the project, B Replace the team Schedule a meeting Notify the project Notify the team The resource management plan is used to help
resulting in a scheduling risk for the project. member with a new with the team sponsor, documenting member’s manager determine how resources allocated to agreed-upon
resource from member’s manager the conflict caused by of project needs, and activities will be coordinated with other project
How can the Project Manager eliminate this risk? another to negotiate for the member’s require the release of resources. This will provide guidance as to how the
department. additional time to manager. the member until the Project Manager can negotiate with the resource's
complete the other project activity is manager.
task. completed.
Correction
844816 1.2 Successful project leaders nurture team members’ skills and knowledge, and keep members motivated A Be assertive, and Promote team Schedule daily sessions Create a team reward The primary goal of a Project Manager in relation to
throughout the project. stand up for the challenges by where team members for each successfully- the project team is to ensure that the team has the
team’s needs, delegating project can voice concerns and completed task. time and resources to do their job and to remove
Which action helps to promote successful project leadership? concerns, and tasks. receive a response. any barriers they may encounter. By standing up for
beliefs. the team's beliefs the Project Manager is
demonstrating their support for the team.
No Changes Needed
844818 2.7 The project is overseen by a senior Project Manager. When a new Project Manager is added to the project, the A Obtain established Schedule a meeting Schedule a meeting Postpone the The new Project Manager needs to consult with the
sponsor asks the new Project Manager to develop the quality management plan. quality processes with the customer to with the sponsor to development of the senior Project Manager to find out what practices
and plans from the collect requirements obtain benchmarking quality management and processes are already in place.
How should the new Project Manager proceed? senior Project and obtain samples and cost- plan by submitting a
Manager. Then, ask benchmarking benefit analyses change request. Only
them for guidance samples. proceed when quality
in selecting the metrics and quality
appropriate checklists have been
standards created.
Current
844818 2.7 The project is overseen by a senior Project Manager. When a new Project Manager is added to the project, the D Postpone the Schedule a meeting Schedule a meeting Obtain established The new Project Manager needs to consult with the
sponsor asks the new Project Manager to develop the quality management plan. development of the with the customer to with the sponsor to quality processes and senior Project Manager to find out what practices
quality collect requirements obtain benchmarking plans from the senior and processes are already in place.
How should the new Project Manager proceed? management plan and obtain samples and cost- Project Manager.
by submitting a benchmarking benefit analyses. Then, ask them for
change request. samples. guidance in selecting
Only proceed when the appropriate
quality metrics and standards.
quality checklists
have been created.
Correction
844819 2.12 Two users complain during the project’s user acceptance stage, saying that their expectations were not met. A Stakeholder Risk assessments. Conflict management A professional Managing stakeholder engagement helps to ensure
feedback. techniques. relationship with the that stakeholders clearly understand the project
What could the Project Manager use to avoid this issue in the future? users. goals, objectives, benefits, and risks for the project,
as well as how their contribution will enhance
project success. Listening to their feedback is an
important part of this engagement.
Correction
844820 2.3 A new project sponsor asks for a project team that includes resources working in three different time zones and A Overall project risks Key stakeholder list High-level Resource Having a dispersed project team does not come
locations. The project sponsor did not consider the implications of this requirement, and believes that the request requirements management plan without risks. These risks need to be identified in
will save costs while creating the ideal project team. the risk log for the project.
Current Where should the Project Manager document this request in the project charter?
844820 2.3 A new project sponsor asks for a project team that includes resources working in three different time zones and B Key stakeholder list. Overall project risks. High-level Resource Having a dispersed project team does not come
locations. The project sponsor did not consider the implications of this requirement, and believes that the request requirements. management plan. without risks. These risks need to be identified in
will save costs while creating the ideal project team. the risk log for the project.
Correction Where should the Project Manager document this request in the project charter?
844943 2.2 As a result of multiple regulatory changes, a governmental agency is added as a key stakeholder on a complex A Meet with the new Identify needed Review the stakeholder Check with the Meetings are used to develop an understanding of
project. The Project Manager wants to develop an understanding of this new stakeholder and identify any new stakeholders. changes to the engagement plan. project sponsor significant project stakeholders. They can take the
high-level risks that may result from the change. assumption log. regarding the form of facilitation workshops, small group guided
benefits management discussions, and virtual groups using electronics or
What should the Project Manager do? plan. social media technologies to share ideas and
Current analyze data.
844943 2.2 As a result of multiple regulatory changes, a governmental agency is added as a key stakeholder on a complex C Review the Identify needed Meet with the new Check with the Meetings are used to develop an understanding of
project. The Project Manager wants to develop an understanding of this new stakeholder and identify any new stakeholder changes to the stakeholders. project sponsor significant project stakeholders. They can take the
high-level risks that may result from the change. engagement plan. assumption log. regarding the form of facilitation workshops, small group guided
benefits management discussions, and virtual groups using electronics or
What should the Project Manager do? plan. social media technologies to share ideas and
Correction analyze data.
844956 1.2 A Project Manager is having difficulty obtaining consistent input from stakeholders, and needs their input to D Use political Institute checklist Research effective Make use of effective Facilitation is the ability to effectively guide a group
identify strategic and operational assumptions and constraints. awareness policies. meeting management facilitation event to a successful decision, solution, or
techniques. techniques. techniques. conclusion. A facilitator ensures that there is
How can the Project Manager improve stakeholder input? effective participation, that participants achieve a
mutual understanding, that all contributions are
considered, that conclusions or results have full buy-
in according to the decision process established for
the project, and that the actions and agreements
achieved are appropriately dealt with afterward.
No Changes Needed
844991 2.11 A project involves six different companies, and the project sponsor is a global organization. At the midpoint of the A Update the Revise the project Update the Revise the project The stakeholder engagement plan is updated to
project, the Project Manager is informed that one stakeholder is experiencing difficulties and cannot provide stakeholder charter. stakeholder register. management plan. reflect any processes, procedures, tools, or
their former level of involvement. engagement plan. techniques that affect the engagement of
stakeholders in project decisions and execution.
No Changes Needed Which action should the Project Manager perform?
844992 3.1 A company’s products will be affected by a new law that might be passed in the next four months. A new product A 1. Discuss risks with 1. Update the risk 1. Move forward with This new law can have a profound effect on the
launch is starting, and should be completed within three months. If the proposed law is passed, the new product the sponsor and key management plan. the project and project
1. Warn the sponsor project. It will certainly lead to new potential risks,
will not meet the new requirements. stakeholders. 2. Move ahead with planning. and key stakeholders new assumptions and a possible charter change.
2. Using the results project planning. 2. Meet all deadlines,
about the
How should the Project Manager address to this potential problem? of the discussion, ensuring that the implications of the
update the product will be possible law.
assumption log and complete prior to 2. Advise them to put
project charter. potential change in the
the project on hold
law. until the legislation is
Current passed.
844992 3.1 A company’s products will be affected by a new law that might be passed in the next four months. A new product B 1. Update the risk 1. Discuss risks with 1. Move forward with 1. Warn the sponsor This new law can have a profound effect on the
launch is starting, and should be completed within three months. If the proposed law is passed, the new product management plan. the sponsor and key the project and project and key stakeholders project. It will certainly lead to new potential risks,
will not meet the new requirements. 2. Move ahead with stakeholders. planning. about the new assumptions and a possible charter change.
project planning. 2. Using the results of 2. Meet all deadlines, implications of the
How should the Project Manager address this potential problem? the discussion, ensuring that the possible law.
update the product will be 2. Advise them to put
assumption log and complete prior to the project on hold
project charter. potential change in the until the legislation is
Correction law. passed.
844995 2.3 An approved change was implemented to manage a risk. Three months later, the Project Manager finds that the A Confirm that an Review the Update the risk Evaluate new risks, Project work should be continuously monitored for
change did not yield the desired result. In fact, the change led to adverse consequences. implemented risk assumption log to information to the and update the new, changing, and outdated individual project risks
response is revisit or change lessons learned probability and and for changes in the level of overall project risk by
What should the Project Manager do to avoid this issue in the future? effective. current assumptions. register. impact matrix. applying the Monitor Risks process. The Monitor
Risks process uses performance information
generated during project execution to determine if
the response was effective.
Current
844995 2.3 An approved change was implemented to manage a risk. Three months later, the Project Manager finds that the C Update the risk Review the Confirm that an Evaluate new risks, Project work should be continuously monitored for
change did not yield the desired result. In fact, the change led to adverse consequences. information to the assumption log to implemented risk and update the new, changing, and outdated individual project risks
lessons learned revisit or change response is effective. probability and and for changes in the level of overall project risk by
What should the Project Manager do to avoid this issue in the future? register. current assumptions. impact matrix. applying the Monitor Risks process. The Monitor
Risks process uses performance information
generated during project execution to determine if
the response was effective.
Correction
844999 2.3 A Project Manager overhears a conversation in a cafeteria. The speaker says that a possible union action will A Inform relevant Ask stakeholders for
Set up an information Meet with union The Project Manager needs to proactively approach
occur within the next two weeks. stakeholders and additional session for the project members and the this. By updating the risk register and by
update the risk information team, letting them union leader to communicating this development to the appropriate
The Project Manager knows that any union action will affect the project team, and at this stage of the project, any register with the regarding the know of possible resolve this conflict. stakeholders, they will be achieving this.
project delays will cause substantial harm to both budget and schedule. Earlier, the probability of a union action new risk. likelihood of the disciplinary sanctions
was considered minimal. Thus, it was unanticipated. union action, then act
for those who
on what is heard. participate in the union
Current What should the Project Manager do? action.
844999 2.3 A Project Manager overhears a conversation in the company's cafeteria. The speaker says that a possible union A Inform relevant Ask stakeholders for Set up an information Meet with union The Project Manager needs to proactively approach
action will occur within the next two weeks. stakeholders and additional session for the project members and the this. By updating the risk register and by
update the risk information team, letting them union leader to communicating this development to the appropriate
The Project Manager knows that any union action will affect the project team, and at this stage of the project, any register with the regarding the know of possible resolve this conflict. stakeholders, they will be achieving this.
project delays will cause substantial harm to both budget and schedule. Earlier, the probability of a union action new risk. likelihood of the disciplinary sanctions
was considered minimal. Thus, it was unanticipated. union action, then act for those who
on what is heard. participate in the union
Correction What should the Project Manager do? action.
845000 2.15 While reviewing the issues log, the Project Manager notices that tasks assigned to two team members are quite a A Work with the Document the issue, Tell the team members The Project Manager needs to be proactive and
bit behind schedule. relevant team escalate to the who are behind Notify the responsible review the activities with the team and to identify
members to review project sponsor, and schedule that they team members of the resolution strategies.
What should be done? the delayed tasks ask for how they should explain why need to complete the
and decide on would like it resolved. tasks were delayed and overdue tasks quickly
strategies for how they will get back in order to avoid
resolution. on schedule. introducing extra
project risks.
Current
845000 2.15 While reviewing the issues log, the Project Manager notices that tasks assigned to two team members are quite a D Notify the Document the issue, Tell the team members Work with the The Project Manager needs to be proactive and
bit behind schedule. responsible team escalate to the who are behind relevant team review the activities with the team members and to
members of the project sponsor, and schedule that they members to review identify resolution strategies.
What should be done? need to complete ask for how they should explain why the delayed tasks and
the overdue tasks would like it resolved. tasks were delayed and decide on strategies
quickly in order to how they will get back for resolution.
avoid introducing on schedule.
Correction extra project risks.
84500 2.3 A project sponsor is risk averse and is therefore concerned about negative impacts on the project. To help with C B, A, D, C B, C, A, D D, C, B, A Probability * Impact provides the risk ranking from
this concern, the project team identifies four project risks and then evaluates both the probability of occurrence C, D, A, B highest to lowest.
and the impact of the risk if it occurs. The team uses a 1-5 scale, 1 being the lowest and 5 being the highest. A = 2*3 = 6
B = 2*5 = 10
Risk C = 3*4 = 12
Probability D = 4*4 = 16
Impact
Therefore the risks should be ranked in the
A following order: D, C, B, A
2
3
B
2
5
C
3
4
D
4
4
Current Based on the table, in what order should the Project Manager rank these risks for risk management purposes?
T 2.3 A project sponsor is risk averse and is therefore concerned about negative impacts on the project. To help with C B, A, D, C B, C, A, D A, D, B, C C, D, A, B Probability * Impact provides the risk ranking from
this concern, the project team identifies four project risks and then evaluates both the probability of occurrence highest to lowest.
and the impact of the risk if it occurs. The team uses a 1-5 scale, 1 being the lowest and 5 being the highest. A = 4*4 = 16
B = 2*5 = 10
Risk C = 2*3 = 6
Probability D = 3*4 = 12
Impact
Therefore the risks should be ranked in the
A following order: A, D, B, C
4
4
B
2
5
C
2
3
D
3
4
Correction Based on the table, in what order should the Project Manager rank these risks for risk management purposes?
1.1 A Project Manager has put together a project team. During initial meetings, the Project Manager observes that C Storming Norming Forming Performing The Forming phase is where the team members
team members are getting to know each other, feeling excited and positive about the project, and have not been meet and learn about the project and their formal
told the specific details of the project. roles and responsibilities. Team members tend to be
independent and not as open in this phase.
No Changes Needed In what phase of development is the team?