Professional Documents
Culture Documents
ARTES - Automatic Testing For The Undervoltage Dependent Directional Reactive Power Protection Function-Min
ARTES - Automatic Testing For The Undervoltage Dependent Directional Reactive Power Protection Function-Min
Protection Technology
Automatic Testing for the Undervoltage Dependent
Directional Reactive Power Protection Function
Prof. Dr.-Ing. Hendro Rijanto, Senior Engineer
Dip.-Ing. Alexander Bitz, Senior Product Manager for Protection Relay Testing
Over the past 10 years, regenerative, environmen- 1 Undervoltage dependent tion works. The secondary legislation to
directional reactive power protection the German Renewable Energy Sources
tally sustainable power plants have become incre-
For the safe operation of electrical pow- Act (EEG) requires that this type of Q-U
asingly important. Of all the available options, wind protection be installed [6]. The block
er systems with a high proportion of de-
turbine generator systems have been particularly centralized PGSs, it is necessary for in- diagram of the Q-U protection function
successful. According to the German Wind Energy is shown in Figure 1.
Institute, by the end of 2010 the number of wind
turbine generator systems operating in Germany
had reached 21,607, with a total power of 27,215
MW [1]. Since then, the average amount of power
produced per wind turbine generator system has
risen to slightly above 2 MW.
correctly. In this guideline a four year any type of pro-tection relay by setting
test cycle is recommended. the generator values manually.
the Q-U protection function starts.
· The start/operating time is to be 3 Test system
The ARTES testing software features
recorded. a wide range of convenient test mo-
• Determine the resetting ratio: The use of a fully automatic test sys- nitors which have been specially de-
· Before the Q-U protection function tem with appropriate testing software veloped for testing specific protection
operates, the voltages are to be in- substantially reduces the amount of functions. Undervoltage dependent
creased symmetrically again until time it takes to test the Q-U protection directional reactive power protection
the Q-U relay is reset. function. is included in the list of functions dis-
• Test the AND link: played under Functions/Configuration
· Apparent power is to be provided Figure 2 shows the ARTES 460 test set shown in Figure 4.
at a level which is sufficient for the whose technical specifications fulfil all The ARTES testing software features
directional operating character-istic the requirements needed in order to a wide range of convenient test mo-
of the reactive power to respond. test the Q-U protection function. The nitors which have been specially de-
The voltages are then to be decrea- test set is operated and controlled with veloped for testing specific protection
sed asymmetrically. Even when one the ARTES testing software. ARTES V4, functions. Undervoltage dependent
phase-to-earth voltage is decrea- the latest version of the software to be directional reactive power protection
sed to 0 V, the Q-U relay should not released, includes the QU-Monitor, a is included in the list of functions dis-
operate. test module which has been specially played under Functions/Configuration
• Test relay operation in specified di- designed for testing the Q-U protection shown in Figure 4.
rection of the reactive power function. This test monitor simplifies, Because it is very easy to adjust the
· The operating characteristic for the automates and significantly speeds up characteristic in the software, it is pos-
reactive power in relation to the ac- the test process. sible to test all the various different
tive power is to be tested. response characteristics for the Q-U
• Test the release current Figure 3 shows the ARTES V4 testing function which have been implemen-
· The size of the release current is to software with the new Microsoft Flu- ted by the anufacturers of protection
be ascertained. ent user interface. This interface pro- devices. Figure 5 shows the possible
It should also be mentioned that the vides fast access to all the functions characteristics of the reactive power
VDN guideline for digital protection of the testing software. The illustration as a function of the active power. As
systems [8] requires that installed pro- shows the VD-Monitor which is inclu- can be seen in the illustration, the follo
tection systems be tested at regular ded in the standard delivery package. wing options are taken into consideration:
intervals to ensure that they function This basic module can be used to test • Constant or minimum reactive
Figure 3: ARTES testing software V4.0 with the new Microsoft Fluent user interface Figure 4: Selection of different protection functions
2
Special Topic
Protection Technology
power vice is generally connected as shown In the other test modes, the settings
• Rising reactive power after release in Figure 8. The current transformer is listed below can be tested automati-
through minimum current usually earthed on the S1 side or line cally, taking into account the approp-
• 2-stage reactive power after re- side respectively. When the PGS pro- riate test conditions for the Q-U protec-
lease through minimum current duces active power, a negative active tion function.
• 3-stage reactive power after re- power value must be displayed. • V test: test the starting value of the
lease through minimum current The ARTES 460 test system is to be undervoltage setting
connected up appropriately and the • I test: test the starting value of the
By way of example, Figure 6 shows the earthing of the device under test is to minimum current setting
equivalent circuit diagram with the in- be defined on the line side. When an • Q test: test the starting value of the
strument transformers and their trans- apparent power value with positive reactive power
formation ratios. The test values which active and reactive power is set, the • φ test: test the angle of the reactive
are needed in order to carry out a func- sign prefixing the active and reactive power direction
tion test (undervoltage, reactivepower power on the display of the protection The starting and reset values are de-
and minimum current) are calculated device must be negative. termined using pulse ramps. All the
automatically taking the instrument The „series“ and „sequence“ test mo- parameters required for the test, such
transformer data into account. des are then used to test the accuracy as start and end values, pulse width,
FA range of different test modes are of the operating characteristic of the angle between current and voltage,
available for configuring the test steps reactive power as a function of the ac- number of steps, pause values etc.,
needed. Test definitions based on dif- tive power. Test points can be defined are defined in a dedicated area of the
ferent test modes can be grouped to- freely in accordance with the type of workspace. The values can be given in
gether in one test plan and carried out operating characteristic implemented relation to the rated value or as abso-
automatically. Figure 7 by the manufacturer of the Q-U protec- lute values. No conversion is required.
tion function. When a test is started, The reset values are also determined
First use the „manual“ test mode to the test points are dealt with one by automatically and the corresponding
check that the protection device is one and evaluated according to the reset ratios identified.
connected correctly. The protection de- reaction of the Q-U protection function. In „V test“ mode, it is also possible
Bild 7: several
Test modes for
automatic testing
the Q-U-protection function
3
Special Topic
Protection Technology
to select fault loops, enabling phase- Sources Act (EEG) requires this type of nungsnetz“, guideline for generating
selective fault types to be reproduced. Q-U protection. In order to reduce the plants‘ connection to and parallel ope-
This makes it possible not only to de- amount of time it takes to test the Q-U ration with the medium voltage net-
termine the starting value of the U< protection function, considering the work, June 2008 [English translation:
function but also to determine the logi- large numbers of wind turbine genera- Generating plants connected to the
cal AND-link, as required above, in one tor systems, an automatic test system medium-voltage network]
and the same test step. is required.
[5] VDE/FNN: Lastenheft Blindleis-
In „φ test“ mode it is possible to test An automatic test for the Q-U protec-
tungsrichtungs-Unterspannungs-
the reactive power range in both a tion function is already a component
schutz (Q-U-Schutz), February 2010
clockwise and anti-clockwise direction. of the ARTES V4.0 testing software.
As a result, the starting behaviour can This testing software is backwards [6] Verordnung zu Systemdienstleis-
be determined in the 4 quadrants of compatible with earlier versions of the tungen (Systemdienstleistungsverord-
the Cartesian coordinates. Once the ARTES testing software. The various nung – SDLWindV) under the Rene-
automatic test has been completed, test modes for the test steps required wable Energy Sources Act 2009, May
the test report generated by the ARTES can be grouped together to form a test 2009 [English translation: Ordinance
testing software can be submitted for plan for automatic execution of the Q-U on System Services by Wind Energy
assessment within the certification protection function test. Test plans can Plants (System Service Ordinance –
process for the wind turbine genera- be defined appropriately and saved for SDLWindV)]
tor system. The results are presented the repeat tests which should be car-
[7] J. Möller: Anforderung an die
both graphically and numerically. The ried out at least every 4 years.
Schutzprüfprotokoll des Entkupp-
test steps defined for the test can be
lungsschutz, 23.01.2011, www.moe-
saved in a test plan together with the 5 References: service.com
test results, allowing the behaviour of
Q-U protection functions to be compa- [1] J.P. Molly: Status der Windener- [8] VDN: VDN – Richtlinie für digita-
red again when the test is repeated la- gienutzung in Deutschland – Stand le Schutzsysteme, Berlin, November
ter at appropriate regular maintenance 31.12.2010, DEWI GmbH, www.dewi. 2003
intervals. de
[9] KoCoS: ARTES II Automatische
[2] H. Hartenbach, H. Rijanto, J. Möl- Prüfsysteme, www.kocos.com
4 Summary ler: Automatic certification testing of
the system automatics of wind power
For the safe operation of electrical po-
plants, paper 0418, CIRED 2011
wer systems with a high proportion of
decentralized PGSs, it is necessary for [3] VDN: Transmission Code 2007,
individual power PGUs to contribute to Netz- und Systemregeln der deutschen
power grid support. The equipment for Übertragungsnetzbetreiber, version
appropriately decoupling the PGS from 1.1, August 2007 [English translation:
the electrical power system which is Network and System Rules of the Ger-
required for this purpose is known as man Transmission System Operators]
Q-U protection. The secondary legisla-
[4] BDEW: Technische Richtlinie „Er-
tion to the German Renewable Energy
zeugungsanlagen am Mittelspan-