These PM tasks are recommended to be done yearly


Estimated duration of PM in case no significant deviations are found: 3.0 h
x = Every time
# = As required
* = If instrument is equipped with this feature
w = is also performed in the service workshop
W! = Service Workshop only, final inspection
A = Always to be done during every instrument contact

Serial number:____________
Leica Biosystems Nussloch GmbH Initial:____________
TP_7.5.1-04_PM tasks_B
Heidelberger Straße 17-19
Page 1/143
69226 Nussloch, Germany
676478846.xls
not ok, still to

workshop
be repaired
repaired

Interval
PM tasks
not ok,

Pos.
(valid for instruments with new and old FSE Comment
ok

electronics)

1. Proactive Inspection List


A1 A Backup files to floppy disk
A2 A Check if the current software version is installed.
A3 A Check Run/Service log file entries (SW tool)
A4 A Check touchscreen functions / screen calibration
Visual check - conditions (line cables, switches and
A5 A
connectors)
Visual check - leakage (inner and outer area of the
A6 A
instrument)

A7 A Pressure / Vacuum / Vent test (refer to P/V/V table)


A8 A Fill / Drain test (refer to F/D table)
A9 A Check heater system
A10 A Check exhaust system and filter

2. PM tasks
3. Check Update and Handling
Download instrument data to disk (check off when
1 X w
done)
4. Vacuum and Pressure Test (record results in table)
Limit Value Before Service After Service Unit
+ 35 kPa kpa
2 X w Time to build up pressure to +35 kPa
< 20 sec sec

> + 30 kPa kpa


3 X w Remaining pressure after 4 minutes
4 min 4 min 4 min min

- 70 kPa kpa
4 X w Time to create vacuum to - 70 kPa
< 75 sec sec
> - 65 kPa kpa
5 X w Remaining vacuum after 4 minutes
4 min 4 min 4 min min

Serial number:____________
Leica Biosystems Nussloch GmbH Initial:____________
TP_7.5.1-04_PM tasks_B
Heidelberger Straße 17-19
Page 2/143
69226 Nussloch, Germany
676478846.xls
not ok, still to

workshop
be repaired
repaired

Interval
PM tasks
not ok,

Pos.
(valid for instruments with new and old FSE Comment
ok

electronics)

5. Check and Clean Reagent Cabinet


Interval
in month
6 X w Door, right -
7 X w Door, left -
8 X w Door Hinges -
9 X w Door Catch -
10 X w Carbon Filter 3
11 X w Wheels front -
12 X w Wheels rear -
13 X w Paint Work Condition (Mech. Damage) -
6. Check and Clean Reagent Bottles
14 X w Caps -
15 X w Air and Liquid Holes -
16 X w Reagent Bottle Shelves -
17 X w Bottle O-Ring 12
18 X w Bottle Connector Viton 12
7. Check and Clean Behind Rear Panel
19 X w Liquid Line Leakage and Wax Blockages -
20 X w Liquid and Air Lines for Deposit -
21 X w Air Lines Leaks and Wax Blockages -
22 X w Bottle Lock Clips -
23 X w Fresh Air Valve/Service Kit 48
24 X w Pressure Valve Service Kit 48
25 X w Vacuum Valve Service Kit 48
26 X w Condensate Service Kit 48
27 X w Air Pump Service Kit 48

Serial number:____________
Leica Biosystems Nussloch GmbH Initial:____________
TP_7.5.1-04_PM tasks_B
Heidelberger Straße 17-19
Page 3/143
69226 Nussloch, Germany
676478846.xls
not ok, still to

workshop
be repaired
repaired

Interval
PM tasks
not ok,

Pos.
(valid for instruments with new and old FSE Comment
ok

electronics)

8. Check and Clean Retort


28 X w Strainer -
29 X w Stirrer 24
30 X w Retort Lid Seal 24
31 X w Retort Lid Hinges -
32 X w Retort Reagent Valve 24
33 X w Retort Wax Valve 24
34 X w Retort Fill and Drain Valve and Reagent Hose 24
9. Check and Clean Wax Bath
35 X w Lid Seal 48
36 X w Strainer bath 1 & 2 -
37 X w Strainer wax bath 2 -
38 X w Lid Hinges -
39 X w Air Vent Line -
40 X w O-Ring on Wax drain Connector and Hose 12
41 X w Wax Drain Valve 24
42 X w Wax Valve I 24
43 X w Wax Valve II 24
44 X w Wax Valve III 24

Serial number:____________
Leica Biosystems Nussloch GmbH Initial:____________
TP_7.5.1-04_PM tasks_B
Heidelberger Straße 17-19
Page 4/143
69226 Nussloch, Germany
676478846.xls
not ok, still to

workshop
be repaired
repaired

Interval
PM tasks
not ok,

Pos.
(valid for instruments with new and old FSE Comment
ok

electronics)

10. Check and Clean Rotary Valve


45 X w Rotary Valve -
46 X w O-Ring, Swivel Seat 12
47 X w O-Ring, Selector Seat 12
11. Check Electronics
48 X w Check if the current software version is installed. -
49 # w Upgrade Help Files -
50 X w Check Main Fuses (value and condition) -
51 X w Check Alarms (Instrument, Remote, Local) -
52 X w Power Supply, PCB Assembly and Fans 60
53 X w Hard drive, configured 24
12. Miscellaneous
54 X w Clean external surfaces of ASP -
55 X w Ensure customer has spare Main fuses. -
56 X w Present / Explain PM Results/Report with Customer -
13. Additional Information
57 X w Dedicated power line installed? -
Does customer own a current valid User Manual?
58 X w -
If not, would customer like to purchase one?
14. Workshop only

Serial number:____________
Leica Biosystems Nussloch GmbH Initial:____________
TP_7.5.1-04_PM tasks_B
Heidelberger Straße 17-19
Page 5/143
69226 Nussloch, Germany
676478846.xls
Introduction show PM tasks

1. In the following PM task, only the fields highlighted in yellow can be filled out.
All other fields are blocked.

2. The column "Pos" is hyperlinked to show further information on the respective task.

3. To navigate click the green field.


filled out.

espective task.
Revision history back to PM tasks

Revision Date Cause


V 1.2 26-Oct-12 New document
V 1.3 03-Jul-13 Line 16 changed
Line 92,94,96,100 deleted
Line 21, 24-35 new
Renumbered Task Pos.
Deleted refernces to manual and IFU
Changed Leica Logo
Changed Value "Check and Clean Reagent Cabinet" interval 3 month
V 1.4 9/25/2014 added column "workshop"
added "w" and "W!" in Legend
added "Initial" in footer
added "Workshop only" section
formatted the document
V 1.5 8/5/2015 Pos. 51 added in PM tasks and description tabs
Original Pos. 51 - 57 adapted respectively
#VALUE! back to PM tasks

Backup files to floppy disk (stored in instrument)


#VALUE! back to PM tasks

Check if the current software version is installed.


#VALUE! back to PM tasks

Check Run/Service log file entries (SW tool)


#VALUE! back to PM tasks

Check touchscreen functions => If necessary - do a screen calibration


#VALUE! back to PM tasks

Visual check - conditions (line cables, switches and connectors)


#VALUE! back to PM tasks

Visual check - leakage (inner and outer area of the instrument)


#VALUE! back to PM tasks

Pressure / Vacuum / Vent test (refer to P/V/V table)


#VALUE! back to PM tasks

Fill / Drain test (refer to F/D table) =>


Mandatory testing of following reagent
stations: formalin, cleaning reagents
#VALUE! back to PM tasks

Check heater system


#VALUE! back to PM tasks

Check exhaust system and filter


Pos. 1 back to PM tasks

Download instrument data to disk (Check off when done)


Pos. 2 back to PM tasks

Time to build up pressure to +35 kPa


Pos. 3 back to PM tasks

Remaining pressure after 4 minutes


Pos. 4 back to PM tasks

Time to create vacuum to - 70 kPa


Pos. 5 back to PM tasks

Remaining vacuum after 4 minutes


Pos. 6 back to PM tasks

Door, right
Pos. 7 back to PM tasks

Door, left
Pos. 8 back to PM tasks

Door Hinges
Pos. 9 back to PM tasks

Door Catch
Pos. 10 back to PM tasks

Carbon Filter
Pos. 11 back to PM tasks

Wheels front
Pos. 12 back to PM tasks

Wheels rear
Pos. 13 back to PM tasks

Paint Work Condition (Mech. Damage)


Pos. 14 back to PM tasks

Caps
Pos. 15 back to PM tasks

Air and Liqid Holes


Pos. 16 back to PM tasks

Reagent Bottle Shelves


Pos. 17 back to PM tasks

Bottle O-Ring
Pos. 18 back to PM tasks

Bottle Connector Viton


Pos. 19 back to PM tasks

Liquid Line Leakage and Wax Blockages


Pos. 20 back to PM tasks

Liquid and Air Lines for Deposit


Pos. 21 back to PM tasks

Air Lines Leaks and Wax Blockages


Pos. 22 back to PM tasks

Bottle Lock Clips


Pos. 23 back to PM tasks

Air Valve/Service Kit


Notice, kits from different air valve manufactures
Pos. 24 back to PM tasks

Pressure Valve Service Kit

Notice, kits from different air valve manufactures


Pos. 25 back to PM tasks

Vacuum Valve Service Kit

Notice, kits from different air valve manufactures


Pos. 26 back to PM tasks

Condensate Service Kit

Notice, kits from different air valve manufactures


Pos. 27 back to PM tasks

Air Pump Service Kit

Notice, kits from different pump valve manufactures


Pos. 28 back to PM tasks

Strainer
Pos. 29 back to PM tasks

Stirrer

Notice, different design


Pos. 30 back to PM tasks

Retort Lid Seal, additional grease


Pos. 31 back to PM tasks

Lid Hinges
Pos. 32 back to PM tasks

Retort Reagent Valve


Pos. 33 back to PM tasks

Retort Wax Valve


Pos. 34 back to PM tasks

Retort Fill and Drain Valve and Reagent Hose


Pos. 35 back to PM tasks

Lid Seal
Pos. 36 back to PM tasks

Strainer bath 1&3


Pos. 37 back to PM tasks

Strainer wax bath 2


Pos. 38 back to PM tasks

Lid Hinges
Pos. 39 back to PM tasks

Air Vent Line


Pos. 40 back to PM tasks

O-Ring on Wax Drain Connector


Pos. 41 back to PM tasks

Wax Drain Valve


Pos. 42 back to PM tasks

Wax Valve I
Pos. 43 back to PM tasks

Wax Valve II
Pos. 44 back to PM tasks

Wax Valve III


Pos. 45 back to PM tasks

Rotary Valve

Notice, different design


Pos. 46 back to PM tasks

O-Ring, Swivel Seat

Notice, different design


Pos. 47 back to PM tasks

O-Ring, Selector Seat

Notice, different design


Pos. 48 back to PM tasks

Check if the current software version is installed. Upgrade, if required.


Pos. 49 back to PM tasks

Upgrade Help Files, if required.


Pos. 50 back to PM tasks

Check Main Fuses (value and condition)


Pos. 51 back to PM tasks

Alarms => check functionality

Contacts on the test plug 1 Common Terminal for A and B

2 Terminal A

3 Terminal B

Test:
Opened contact Closed contact
State before testing
(measured value µ Ohm) (measured value ~ 0,0 Ohm)

- Remote Alarm Use top socket for testing Use top socket for testing
- Local Alarm Use lower socket for testing Use lower socket for testing

Position the
1. multimeter
measuring probes

2. Press alarm button

- Buzzer for Instrument alarm (speaker)


- Local alarm for lower socket test
- Remote alarm for top socket test

Result measured for


3. ~ 0,0 Ohm µ Ohm
approx. 2 sec
(only for Local and Remote alarm)
Pos. 52 back to PM tasks

Power Supply, PCB Assembly and Fans => check functionality and remove dust
Pos. 53 back to PM tasks

Hard drive, configured

Notice, different design


Pos. 54 back to PM tasks

Clean external surfaces of ASP300


Pos. 55 back to PM tasks

Ensure customer has spare main fuses.


Pos. 56 back to PM tasks

Present / Explain PM Results/Report with Customer


Pos. 57 back to PM tasks

Dedicated power line installed?


Pos. 57 back to PM tasks

Does customer own a current valid User Manual?


If not, would customer like to purchase one?