Procedure No. I-AGC-02M-001
Procedure Description:
SUPRESSED BY
2 MONTHS INSTRUMENT PM PROCEDURE
O & M Manual Ref. N/A
Frequency: 2 MONTHS
Checked By: Work Permit: Cold
Approved By: Shutdown (Y/N):
I: HSE Considerations:
Item Reference
HSE Consideration
No. Number
1 Ensure that all safety regulations are perfectly complied.
Ensure that the craft are wearing safety gears specially isolated gloves for (230 VAC
2
inst) & isolated safety shoe.
Obtain and fulfill the necessary work permits (HOT), and inform the operator before
3 starting the job.
The instrument tools shall be IS classified & isolated to prevent electric chock
4
(powered inst 230 VAC)
5 Consider continuous gas leak test around the area.
Confirm using P&ID / Logic diagram whether instrument is shut down item or not. If it
6 is shutdown item, proceed the procedure for override switch under acceptance from
operation and Instrument Maintenance Supervisor.
Manpower
Task Activity Description Duration
Qty Craft
No hr min
1 Notify the concerned department that analyzer will be checked.
Verify details of the loop sketch. Any documentation discrepancies are
2 to be investigated and corrected by the owning department and the loop
drawings updated with the corrections.
Perform a visual inspection of the Analyzer, wiring, connections, power
3 supply, controller etc… applicable to each installation. Ensure that all
connections are free of obstruction.
Complete the Danalyzer Maintenance Checklist (attach AGC CHECK
4 LIST) bi-monthly. Place the Sales Order No., date and time on the form
and file it.
Save a Chromatogram of the operating Analyzer on the PC with the
MON software. Pint configuration, calibration, and raw data reports and
5
file them with the Maintenance Check List. Also, upload the current
application to the PC with the MON software.
Check the Analog. output , if the there is a tolerance , calibrate as
6
follows :
Select “ Analog output “ under “ Application “ SUBMENU .select the
7
channel
8 Set zero = 0.0 and Full scale = 4
Page. 2 of 2
1 TECH
TOTAL ESTIMATED TIME & LABOR: 2 2 00
1 HLP
III: MaterialS: