You are on page 1of 2

PROJECT Report No:

CLIENT
(Partner (Client Logo)
Logo) INSPECTION TEST REPORT Date:
Checks of Electrical Equipment
Ready for Precommissioning

Subcontractor: ITR-EW-04A
Reference QCP No: QCP phase:

Test Notification n°: Notification Date:

Equipment: ELECTRICAL EQUIPMENT Type: LV SWITCHBOARD Equipment Tag:

Equipment Designation: System Tag:

Manufacturer: Model: P&ID No.:

Voltage Ratio: Nominal Frequency: Nominal Power:

Data Sheet No.: Drawing No.:

Checks Description C NC NA
Check the equipment, verifying the compliance with the project documentation in last revision: P&I D, drawings,
1. specifications, standards, etc.

2. Check that the tag of the equipment is correct and appropriate.

3. Check that the equipment is complete of all accessories and instrumentation.

4. Check the elevation and planarity of switchgear basement and panel fixation.

5. Check installation and fixing of all internals are according to construction drawings.

6. Check the correct mechanical functioning of switchgear components, in particular breakers and isolators.
Check the installation and connection of all ancillaries (voltage and current transformers, dischargers on incoming
7.
lines, etc.).
Check the power connection of the switchgear (the Mechanical Completion certificates of all cables/Bus-ducts are
8.
filled-in and signed).
Check the tightness of bolts by means of a suitable torque wrench on each one of the connecting joints of the bus-
9.
bars.
Check the completeness and integrity of the switchboard Bus-bars (including insulating coating) and relevant isolated
10.
supports.
Check the auxiliary connections of the switchboard (the Mechanical Completion certificates of all auxiliary cables are
11.
filled-in and signed).
12. Check that there are no damages/deformations.

13. Check that the internal and external painting is in satisfactory condition and does not need to be touched-up.

14. Check that the internal and external cleaning is in satisfactory.

15. Check the opening and closing of all compartment/drawer doors. The keys of all locks are available.
Check the cable entries (they shall be sealed as described in design drawings, all openings foreseen for future uses
16.
are properly plugged).
Check that the earthing system is connected to earthing network and that the terminal on the equipment is well
17.
tightened.
18. Measure the insulation resistance of current transformers (see next page).

19. Check that Eventual defects/abnormalities have been entered in the Project Punch List.

20. Check that the final documentation for QCP has been completed and signed off.

21. Check that all modifications have been highlighted on the “Master Copy” drawings (as built).

P.1/2 Mod. ITR-EW-04A/0


PROJECT Report No:
CLIENT
(Partner (Client Logo)
Logo) INSPECTION TEST REPORT Date:
Checks of Electrical Equipment
Ready for Precommissioning

22. Measure insulation resistance of bus-bars. Ambient Temperature: …....ºC

Insulation Resistance of bus-bars (Ohm)


Bus-bars Deviation
UΣT,V,W VΣT,U,W WΣT,U,V
I

II

III

IV
Note: The insulation resistance of bus-bars is measured by means of a Megger applying a voltage ……..…..Vcc for one minute. All other bus-bars
shall be short-circuited and connected to Plant earthing network.
Remarks:

C = Conformance; NC = Non Conformance; NA = Not Applicable;


Conform
Test Instrument Used:

Not Conform – Report n°: Tag n°:

INSPECTORS SUBCONTRACTOR CONTRACTOR CLIENT AUTHORITY (if any)

Name:
Signature:
Date:
The information included in this document and any attachments are confidential and may also be privileged. Document and any attachments are property of ABB
SpA.: theirs reproduction, circulation and use without prior consent are forbidden.

P.2/2 Mod. ITR-EW-04A/0

You might also like