Professional Documents
Culture Documents
Lecture 7
Maintenance of Irrigation Canals,
Design of Lined Canals
1
Department of Civil Engineering
University of Engineering and Technology Peshawar
✓ Silting of canal
✓ Weed growth
2
Department of Civil Engineering
University of Engineering and Technology Peshawar
✓ Flushing
✓ Silt scouring fleet
✓ Bundle of thorny bushes
✓ Iron rakes
✓ Reduction of area of flow
✓ Stirring of silt by water jet
✓ Dredging
✓ Excavation
3
Department of Civil Engineering
University of Engineering and Technology Peshawar
✓ Flushing – Flushing of the canal with clear water will lift up deposited silt.
Absolutely clear water should be used for flushing but if this is not available then
the water which contains minimum quantity of silt should be used for flushing.
✓ Stirring of silt by water jet – A pump fitted with a pipe and nozzle is placed on a
barge. The high velocity jet is directed to the bed to stir the silt and prevent
silting.
✓ Excavation – The silt deposited in a channel is cleared off by manual labor. The
method is quite costly as it requires recurring expenditure. This method is
generally adopted for silt clearance in distributaries and minors. The silt must be
deposited clear off the channel so that it does not find its way back to the
channel.
4
Department of Civil Engineering
University of Engineering and Technology Peshawar
5
Department of Civil Engineering
University of Engineering and Technology Peshawar
6
Department of Civil Engineering
University of Engineering and Technology Peshawar
7
Department of Civil Engineering
University of Engineering and Technology Peshawar
8
Department of Civil Engineering
University of Engineering and Technology Peshawar
1) Breaching due to defective design and construction of the bank. The canal bank is
not strong enough to resist water pressure and a breach occurs.
2) Breaching due to exposure of saturation gradient. The soil particles on the outer
slope are dislodged and flown away along with the seeping water. A cavity is thus
formed in the bank which ultimately develops into a breach.
3) Breaching due to rush of water through rat holes or “Shories”.
4) Piping near downstream toe may ultimately cause subsidence of canal banks.
5) A willful cut in the canal bank either for unauthorized irrigation or for allowing
the flood water to get into canal to save an area from submergence.
9
Department of Civil Engineering
University of Engineering and Technology Peshawar
Closure of Banks
➢ Immediately after a breach occurs, the canal discharge
should be diverted to a nearby escape channel on the
upstream side or the canal should be closed from the
head to stop the outflow completely. Many a times it
is not possible to close the canal from head as the
irrigation of the area in between may suffer.
➢ In case of small minors and distributaries, a breach may be closed by dumping huge
quantities of earth instantaneously from both sides of the gap.
➢ In case of bigger canals such as a branch canal, the above procedure can not be
adopted, as the discharge from such a canal is huge and may completely wash off the
dumped soil.
10
Department of Civil Engineering
University of Engineering and Technology Peshawar
Closure of Banks
➢ In such a case, it is necessary to, first of all, reduce the flow through the breach.
This should be done by driving a double line of stakes or wooden piles (ballies) in
the opening of the breach.
➢ The space between the pile lines is filled with planks or bushes etc. The filler
material can be secured by placing sandbags on the top. If the breach is very
wide, another line of defense may be provided. This will reduce the inflow from
the breach.
➢ Collect a sufficient amount of earth on both sides of the gap. The earth collected
should either be from spoil bank nearby or from borrow pits. This earth material
is then dumped up instantaneously from both sides of the gap to form a ring
bund on outer side.
11
Department of Civil Engineering
University of Engineering and Technology Peshawar
Closure of Banks
12
Department of Civil Engineering
University of Engineering and Technology Peshawar
➢ The side slopes are so selected that they are nearly equal to the angle of repose
of the soil so that no earth pressure is imposed on the lining. The corners are
rounded off to improve the hydraulic efficiency.
➢ If the limiting velocity is taken as 1.8 m/s then the circular section can be adopted
only if the discharge is less than 85 cumecs.
13
Department of Civil Engineering
University of Engineering and Technology Peshawar
14
Department of Civil Engineering
University of Engineering and Technology Peshawar
15
Department of Civil Engineering
University of Engineering and Technology Peshawar
1 2 1 1.486 2 1
𝑉 = 𝑅3 𝑆 2 𝑉= 𝑅3𝑆 2
𝑁 MKS system 𝑁 FPS system
➢ Step # 4: For trapezoidal shaped channel, area of cross section A and wetted
perimeter P
𝐴 = 𝐵𝐷 + 𝐷2 (𝜃 + 𝑐𝑜𝑡𝜃) 𝑃 = 𝐵 + 2𝐷 (𝜃 + 𝑐𝑜𝑡𝜃)
Since A and P are known from Step # 3 and 4, the values of bed width B
and depth D can be computed.
𝐴 = 𝐷2 (𝜃 + 𝑐𝑜𝑡𝜃) 𝑃 = 2𝐷 (𝜃 + 𝑐𝑜𝑡𝜃)
17
Department of Civil Engineering
University of Engineering and Technology Peshawar
19
Department of Civil Engineering
University of Engineering and Technology Peshawar
➢ The properties of best hydraulic cross section for selected channels are given
below:
Trapezoidal, half of a 4Τ
3 D2 2 3D D/2 3 3D
hexagon
Rectangle, half of a
2D2 4D D/2 2D
square
Triangular, half of a 1Τ
D2 2 2D 4 2D 2D
square