Professional Documents
Culture Documents
1
Project Information Memorandum
2
Project Information Memorandum
3
Project Information Memorandum
4
Project Information Memorandum
Equivalent
Floating - - 21042 24830 27986 37245
Population
Total
469764 705748 902350 1069451 1198823 1595856
Population
5
Project Information Memorandum
6
Project Information Memorandum
Mercury (mg/l)
Copper (mg/l)
(mg/l)
Chromium
Chromium
Cadmium
S.
Arsenic
(mg/l)
(mg/l)
(mg/l)
(mg/l)
Hexa
Lead
Location
No.
Zinc
9 10 11 12 13 14 15 16
Paondhoi
1 <.01 <.01 <.01 <.01 <.01 0.2 0.1 <.001
(Upstream)
Paondhoi
2 <.01 <.01 <.01 <.01 <.01 0.2 0.1 <.001
(Downstream)
Dhamola
3 <.01 <.01 <.01 <.01 <.01 0.2 0.1 <.001
(Upstream)
Dhamola
4 <.01 <.01 <.01 <.01 <.01 0.2 0.1 <.001
(Downstream)
Dhamola
5 (Downstream <.01 <.01 <.01 <.01 <.01 0.2 0.1 <.001
after
Confluence)
Water quality of rivers deteriorates after entering the city due to discharge of wastewater from the
drains in the rivers.
7
Project Information Memorandum
Table-5
Coliform Count,
Coliform Count,
Total Alkalinity
TKN,mg/l
S
MPN/100
MPN/100
Chloride
Faeccal
Name
(mg/l)
(mg/l)
(mg/l)
(mg/l)
(mg/l)
COD
BOD
VOS
.
TSS
pH
of
N
Drain
o
Chilkan
a Nala
1 7.13 32 95.62 124 90 39.30 16000 9000 385.40 98.70
(Dhobi
Ghat)
Braj
2 Transpo 6.92 122 334.66 382 302 74.87 9000 3000 526.4 115.81
rt Nala
3 Taj Nala 8.04 120 360.64 462 392 11.23 8000 8000 470 119.75
Hathi
4 Gate 7.18 77 223.10 182 158 78.96 8000 7000 427.70 78.96
Nala
Dhobhi
Ghat
5 7.99 50 145.04 178 142 52.40 17000 14000 446.50 113.83
IPS
Drain
Gaddhe
waali
6 7.78 80 211.68 200 150 9.35 17000 5000 408.90 71.06
gali
drain
At Inlet
of
7 6.96 118 384 72 - -- 384 - - 16.4
existing
STP
The pH value ranged from 6.3 to 7.3. The BOD level ranged from 50 to 400 mg/l and COD level
ranged from 140 to 2850 mg/l. The BOD and COD level indicate that these drains are carrying
untreated sewage. The BOD level in drains near Janak Hotel indicates that the drain carries
contribution of septage as well from various septic tanks or leach pits constructed in various houses in
its catchment. The concentration of heavy metals in various drains was below detectable limits.
The city is partially sewered and mainly Interception and Diversion works and STP have been
provided in the city under Yamuna Action Plan-I (YAP-I) in the year 1998. The total length of sewer
is around 111 km. The summary of existing sewerage system is given in Table 6 below.
8
Project Information Memorandum
Most of the trunk sewers from these 4 zones are connected to the main trunk sewer of 1600 mm laid
under YAP-I.
a. 51 drains were tapped under YAP- I and connected with sewerage system to divert their flow to
the STP of 38 Mld (UASB) proposed at Praduman Nagar through 3 no. IPS constructed at:
Dal Mandi Intermediate Pumping Station (capacity 6.9 Mld) – 8 drains
Rakesh Theatre Intermediate Pumping Station (capacity 16.9 Mld) – 14 drains
Govind Nagar Intermediate Pumping Station (capacity 24 Mld) – 17 drains
The flow from these IPS is pumped to manholes located on the trunk sewers and is ultimately carried
by gravity to Main Pumping Station (MPS) (capacity 38MLD) located at Praduman Nagar STP,
intercepting 12 drains onway.
From Govind Nagar IPS, sewage is pumped into trunk sewer of 1600 mm diameter, which flows to
the MPS at Praduman Nagar.
One STP of 38 Mld capacity based upon UASB technology has been constructed in Praduman Nagar,
Saharanpur under YAP-I. The STP is operational from 2002. Disposal of treated effluent is from
STP to Dhamola river.
c. The flow diagram of the works carried out under YAP- I is placed in Figure below.
9
Project Information Memorandum
10
Project Information Memorandum
11
Project Information Memorandum
12
Project Information Memorandum
Table 8: Works proposed under I&D scheme of 8 drains under State Sector
Description Details
Project area zones 2, 3 & 4
Works proposed
Sewers, 200 to 1100 mm, 200-250
152.815 km
mm AC, rest RCC NP3 & NP4
Sewer connecting chambers 4595 nos.
House connections 44904 nos.
MPS MPS of 6m. dia. at Zone-2
Rising main from MPS to STP 300 mm, 25 m, DI K7
STP 7 Mld (SBR)
Description Details
13
Project Information Memorandum
In Saharanpur, there are already 4 IPS, one MPS and one STP. Drains discharge their wastewater into
rivers Pandhoi and Dhamola. 51 drains were intercepted under YAP I. New I&D and STP works have
now been provided by dovetailing with the existing sewerage system and the following sewerage
works in progress,
a. I&D of 8 drains – The discharge from IPS of 5.7 Mld at Dhobi Ghat, would be pumped to the
proposed STP of capacity 7 Mld proposed under Smart City Sewerage Scheme.
Zone 3 and 4 – Under this scheme, 100.43 km sewers have been proposed. 32.46 Mld sewage
for the design year would be the proposed in new STP.
c. Sewerage scheme under AMRUT program – Zone 1, Sub Zone 1 - Under this scheme, 59.67
km sewers and IPS of 7 Mld in the campus of existing STP have been proposed. The
wastewater would be pumped to the proposed STP of capacity 135 Mld, on the site opposite
to existing STP.
I&D works of 51 drains were carried out under YAP I, out of which 4 drains were partially tapped.
The present discharge of these 51 drains has exceeded their design capacity. All drains will now
be fully tapped, out of which discharge of 34 drains would be taken through the existing I & D works.
The remaining 17 drains and 44 newly identified drains would now be tapped through proposed I&D
works with additional MPS and STP. Existing I&D works of 51 drains carried out under YAP I, will
be repaired and continue to work with wastewater tapping of 34 drains.
14
Project Information Memorandum
The wastewater from 61 drains will be intercepted in an inlet chamber provided with coarse
screen at each tapping arrangement to prevent the solid waste entering the sewer line. List of
drains are provided in table below-
15
Project Information Memorandum
Tentative
S.
Location Name of drain flow (in Drain Status
No.
MLD)
1 Jamshednai 0.06 Already tapped
2 Jawahar nagar Bansal publisher 0.4 Already tapped
3 Jawahar nagar khurana niwas* 0.64 To be retapped
4 Swami dental clinic* 0.5 To be retapped
5 Near Janak hotel* 1 To be retapped
6 Braj Transport* 8.73 To be retapped
7 Khumranpulmandike pass* 0.75 To be retapped
Paondhoi
8 left side Sharab theka ke samne* 0.73 To be retapped
9 drains Natraj drycleaners* 0.45 To be retapped
10 Sabji mandi pull 0.72 Already tapped
11 Rajdhani plywood 0.58 Already tapped
12 State bank of patiala, Puljogian 0.45 Already tapped
13 Near Jai general store ,link road 0.3 Already tapped
Ram tirath school Drain (left side of
14 0.58 To be tapped
Paondhoi)*
15 Kotwali nalla* 0.45 To be tapped
16 Chilkana nalla (Dhobi ghat) * 17.41 To be retapped
Paondhoi right side from from
17 3.57 To be tapped
Dhobighat IPS*
18 Kalyani sales 0.06 Already tapped
19 Agarwal Daramshala-1* 0.15 To be retapped
20 Agarwal Daramshala-2* 0.7 To be retapped
21 Baghat singh chowk ke samne* 0.25 To be retapped
Paondhoi
22 right side Kumranpul riksaw stand* 0.5 To be retapped
23 drains Dalmandi Pumping station* 0.44 To be retapped
24 Ansari road near Dr. neha clinic* 0.29 To be tapped
25 Machhli bajar* 0.61 To be retapped
26 Jogiyan pul near ganpati cellphone* 0.58 To be retapped
27 Ashu sharma 0.25 Already tapped
28 Near taj nalla* 0.13 To be tapped
29 Hanuman mandir Near 0.2 Already tapped
30 Janta colony* 0.04 To be tapped
31 Numaish camp V shape nalla* 0.7 To be tapped
32 Dhamola Dukhibagh* 0.06 To be tapped
left side
33 Shanti nagar-1* 0.02 To be tapped
before
34 confluence Shanti nagar-2* 0.26 To be tapped
35 Bijlighar nalla* 0.7 To be tapped
36 Beribagh drain* 0.5 To be tapped
16
Project Information Memorandum
17
Project Information Memorandum
It is proposed to lay the interceptor sewers along both the banks of rivers Pandhoi and Dhamola, to
intercept remaining 17 drains of YAP I and 44 new drains = 61 drains, before falling into rivers and
divert the same to the proposed STP. Size of sewers vary from 300 mm to 800 mm diameter before
confluence of the two rivers. After confluence, a trunk sewer of size 1200 to 1600mm diameter has
been proposed up to the MPS, which will also carry the discharge of zone-3 & 4, received from
1100mm dia. gravity trunk sewer to be laid under ongoing Smart City scheme.
18
Project Information Memorandum
7 1200 610
8 1400 1,050
9 1600 2,380
Total 16,000
19
Project Information Memorandum
Trenchless:- .
Tentative length and diameter of pipes to be laid with trenchless technology are as follows:
River Crossing
S.No. Location Approx. diameter Approx. length
1 Paondhoi left side to Confluence 800/1200 mm 80 m
2 Dhamola left side to Confluence 300/500 mm 120 m
3 Dhamola right side to Confluence 500/800 mm 100 m
4 Dhamola right side to STP 1400/1600 mm 80 m
If Trenchless length will exceed from above then the rates of Trenchless will be considered as
per Trenchless Society of India or equivalent SOR as approved by EA (UPJN-R).
6.4 Design Periods
The base year of the project has been taken as 2023, intermediate year as 2038 and ultimate
year as 2053. Design periods of various components are given in below
Table 15: Design period of various components
20
Project Information Memorandum
S. Construction
Package Commercial Operations
Completion O&M Period
No. Date (COD)
Date (CCD)
1 Single Package 21 months from 24 months from Effective From COD to End of
Effective Date Date - with 3 months of Concession
Trial Operations after CCD
The details of each Facility, their grouping in the Package is presented below.
Facility Capacity
Package Part of Details
Name (Average)
Saharanpur STP
Saharanpur STP 135 MLD
Facilities
Saharanpur Saharanpur
Saharanpur MPS 172.3 MLD & 50
Saharanpur STP Facilities Associate
with rising Main meter Rising main
and I&D Project Infrastructure
Saharanpur 61 nos. of tapping
Nalla Tapping
Associate and 16 Kms
and Sewer
Infrastructure Sewer
21
Project Information Memorandum
B) Trial Operations Period (Article 7): Upon receiving the relevant Construction Completion
Certificate, the Concessionaire shall commence the Trial Operations of the Facilities to determine
whether the KPIs are met on a continuous basis, and is fit for the commercial operations. To
achieve successful Trial Operations, the Facilities need to achieve KPIs for 20 consecutive days
prior to the relevant Scheduled COD.
C) O&M Period (Article 8): From their respective COD to the End of Concession, the
Concessionaire will be required to operate and maintain the Facilities, such that the Facilities
meet the key performance indicators specified in the Concession Agreement.
9.0 Payments
The payments for the Facilities shall be based on a Hybrid Annuity Model, wherein 40% of the
project cost shall be reimbursed to the Concessionaire during the Construction period. The balance
construction cost, along with interest, will be made as quarterly payments (Capex Annuity) during the
O&M period. Additionally, the Concessionaire will also receive indexed O&M charges based on his
quote and reimbursable power charges for operating and maintaining the Facilities, as quarterly
payments during the O&M Period.
A brief overview of the timeline and payments for the three STP Facilities is given in the table below
for better understanding. Kindly note that the details below are indicative and the Concessionaire may
refer to Article 9 of the Concession Agreement for the exact details.
10.0 Package Facilities
What? Design, Finance, Construct, Operate and Maintain, and Transfer the
STP Facilities as per the Concession Agreement
Project Details Where? At Dhamola river Saharanpur
How? Using any suitable technology, subject to satisfaction of the
Qualification Criteria set out in this RFP
Construction 21 months; from Effective Date (ED) till 40% of Bid Project Cost, in eight
Period Construction Completion Date (CCD) equal instalments upon achieving
each Payment Milestone certificate;
after accounting for Delay Liquidated
Damages, if any;
Trial Operations 3 months; from Construction Completion Bonus upon early achievement of
Period Date (CCD) till Scheduled COD Construction Completion Date, if
any;
From the Commercial Operations Date Quarterly payments of:
O&M Period
(COD) of the STP Facility, till End of (1) Capex Annuity - 60% of
Concession; (means the date occurring Completion Cost (indexed Bid
after the expiry of 15 years from the Project Cost), along with interest;
Saharanpur (New) Package COD; (2) Indexed O&M charges for the
STP Facilities, based on number
of days of operation.
- (3) Power charges for STP subject to
a cap of Allowable Guaranteed
Energy Consumption.
(4) after accounting for Availability
Liquidated Damages,
Performance Liquidated Damages
22
Project Information Memorandum
23
Project Information Memorandum
The Saharanpur (New) STP 135 MLD is proposed on the land opposite to Existing STP across the
river Dhamola. The existing STP of 38 MLD capacity is based on UASB followed by waste
stabilization pond technology. Approximately total 4.50 Ha land is in possession of Uttar Pradesh Jal
Nigam (UPJN) for the Proposed STP site for the construction of Saharanpur STP.
The proposed new STP land is low lying area and has large potholes due to carrying of soil by the
local people. The land filling and leveling of site shall be with in the scope of project, no additional
cost will be given. The approach road to site is from the residential area for which alternate route has
to be constructed as per the scope of the works.
Approach road from Existing STP of length 250 m and 5.5 m width between the polishing ponds of
existing STP to be constructed along with a box culvert of 20 m length and suitable depth as per flow
and 300 m approach road from entry gate of existing STP to polishing ponds
24
Project Information Memorandum
25
Project Information Memorandum
The other relevant data is provided as listed in the Table below. Please note that the designs and
drawings in Annexure are indicative only and the Bidders are required to undertake their own due
diligence and prepare their own designs and drawings for the purpose of the Bid and the Project.
S.No. Drawings
3 Topographic Survey 1
4 Topographic Survey 2
5 Topographic Survey 3
13 Staff Quarter
26
Project Information Memorandum
27
Project Information Memorandum
28
Project Information Memorandum
29