Professional Documents
Culture Documents
When most North Americans think of for the television show “The World’s verely that the vessel was dead in the
Curacao, they think of it as a tropical is- Toughest Fixes,” which aired on the Na- water, unable to be steered, stranding the
land oasis, a place where they get away tional Geographic Channel. 22-member crew for several weeks. At the
from the everyday stress at work. But for time of the accident, the 623-ft-long
130 days, a group of dedicated commer- The Ship’s Accident freighter was less than a year old.
cial divers, welders, inspectors, and engi- Miami Diver, Inc., President Kevin Pe-
neers called it their workplace. It was the On January 21, 2009, the 56,000-ton ters was asked to develop a repair proce-
site for a job that demanded they work bulk carrier Sophia D was en route to dure for the damaged components. The
seven days a week, 12 to 14 hours per day, China, loaded with thousands of tons of vessel’s owner and the insurer accepted
with one day off during the entire job; a iron ore. Off the coast of Brazil, the ship the company’s proposal to perform the re-
job so challenging that part of it was filmed ran aground, damaging the rudder so se- pair of the rudder, the rudder horn, and
UWE W. ASCHEMEIER (uwaschemeier@terracon.com) is senior welding engineer, H. C. Nutting, a Terracon Co., Cincinnati, Ohio.
KEVIN S. PETERS is president, Miami Diver, Inc., a member of the Subsea Solutions Alliance, Miami, Fla.
38 MAY 2010
When a cargo ship ran aground, damaging its massive rudder,
a crew of commercial divers, welders, inspectors, and
engineers got to work on this tough repair
other affected components afloat. The forward holds, which would allow the
proposal specified the repair would take cofferdam to be trimmed 3 ft above the
place in Curacao, where Miami Diver has waterline.
a fully equipped facility. • Dewatering the cofferdam to enable the
Repairs could not be performed where evaluation of the damage to the rudder
the vessel was stranded because of the lo- horn and the aft peak tank. At the same
cation, which was several miles offshore, time, the rudder was to be transported
as well as poor weather conditions. In fact, by barge to the shipyard in Curacao for
the extent of the damage done to the ves- evaluation of the damage.
sel when it ran aground could not be de- • Qualifying and certifying the welding
termined on site. procedures and welders to be able to
The vessel was towed (Fig. 1) to Cura- weld on 1.75-in.-thick, high-tensile-
cao, Netherlands Antilles, in the strength steel. The repairs to the rud-
Caribbean Sea, just off the coast of der horn and other damaged compo-
Venezuela. It took 28 days to tow the ves- nents could not be performed until the
sel the 1000 miles from Brazil to Curacao. qualifications were completed.
• Cutting the rudder horn free from the
The Proposed Repair hull and intalling an 8-in. insert plate
to remove the “dog leg” so that the pin-
The proposal for performing the re- tle bushing could be realigned with the
pairs included the following: upper neck bushing.
• Divers removing the rudder blade un- • Cutting out and replacing the damaged
derwater. shell plating on the ship hull, as well as
• Transferring the weight of the rudder damaged frames and the longitudinal
from air chain hoists to lift bags and in the aft peak tank.
using two of the ship’s 35-ton cranes to • Cutting out and renewing the external
load the rudder blade onto the barge. rudder plating as well as replacing in-
• Building and installing a cofferdam ternal frames that were bent. After fi-
around the rudder horn in order to per- nalizing the repair to the internal
form the repairs in the dry. frames and the skin plate, the upper and
• Moving the cargo from the aft to the lower casting for the rudder stock and
pintle had to be line bored.
• Removing the cofferdam after the re-
pairs to the rudder horn and shell plat-
ing were complete, then reinstalling the
Diver-welders prepare to weld. rudder and rudder stock.
• Renewing the steering motor founda-
tion and remounting the steering gear
to the rudder stock
• Conducting sea trials.
WELDING JOURNAL 39
Fig. 1 — The Sophia D after it was towed into the
Caracas Bay in Curacao for repairs.
40 MAY 2010
Fig. 3 — The rudder hanging from the lift bags. Fig. 4 — The rudder in the shipyard.
Initial Evaluation
The first evaluation of the extent of the
damage revealed the following:
• Pintel shaft and rudder stock were un-
usable.
• Upper and lower castings on the rud-
der blade were misaligned.
• Steering gear foundation was severely
damaged.
• Rudder horn was bent 8 in. starboard,
2 in. aft.
• Ship’s hull was fractured forward of the
gusset plate.
• Forward gusset plate was damaged.
• Internal frames in the aft peak tank
were damaged and fractured in the way
of the rudder horn connections.
• The ships’s shell plating, internal
frames, and the longitudinal member
in the aft peak tank were damaged.
WELDING JOURNAL 41
Fig. 6 — Welder Bruce Smythe at work building the 23,000-lb cof- Fig. 7 — Installing the cofferdam.
ferdam.
Fig. 8 — Joint preparation on the insert on the port side. Fig. 9 — Ceramic heating elements and insulation are shown in-
stalled at the joint to be welded.
out, internal plates were found to be The 23,000-lb cofferdam was built at ance Qualification Records (PQRs). After
buckled to a point that they needed to Miami Diver’s facilities in Curacao while the PQRs were qualified, five more
be cropped out and replaced. the vessel was being towed from Brazil. welders were tested in Curacao, with the
The 1.75-in.-thick plate mounted to the After the cofferdam was finished, it local DNV surveyor as witness.
bottom of the rudder was bent so badly (Fig. was transported to the vessel, lowered into In Miami, two welders welded identi-
5), it had to be trimmed approximately 1 in. the water, lifted up, and welded to the cal procedure qualification plates, which
overlapping the edge of the rudder skin be- ship’s hull — Fig. 7. Once installed, 30 were 1 in. thick, and 14 in. long per DNV
fore the rudder could be reinstalled onto tons of cargo had to be moved to the for- specifications. One welder welded quali-
the vessel. The plate helps with the steer- ward compartments allowing the ship to fication plates according to AWS D1.1,
ing of the vessel at slow speeds. trim the cofferdam 3 ft above the water- Structural Welding Code — Steel, on 1-in.-
line. The cofferdam was dewatered to en- thick material, in the 3G and 4G positions.
able evaluation of the damage to the rud- Time and passing the tests were cru-
Building and Installing the der horn and the aft peak tank. cial, since the welding procedure was the
Cofferdam foundation for the weld repair. Prepara-
tions and test runs were performed on
A marine engineer specifically de- Qualifying the Procedures Sundays.
signed a cofferdam for this job that would and the Welders The welding procedure qualification
displace 130 cubic yards of water. The cof- plates were welded in the 2G (horizontal)
ferdam was installed around the rudder Before any welding could be per- position. The root, filler passes, and cover
horn after the rudder was removed. The formed on the vessel, the welders had to passes were welded, and then the root was
approximately 15-ft-long, 13-ft-wide, and be qualified and the welding procedure backgouged and rewelded from the back-
14-ft-tall cofferdam was built out of ¼-in.- approved by Det Norske Veritas (DNV). side. The welding process was SMAW with
thick ASTM A36 steel, reinforced with 4 The tests were performed at Miami DNV-approved ESAB Atom Arc 1⁄8-in.
× 4 × 3⁄8-in. angles at the bottom and the Diver’s facility in Miami, Fla. The weld- 7018 electrodes.
sidewalls — Fig. 6. ing engineer wrote the necessary Perform- The rudder horn material was AH 36
42 MAY 2010
Fig. 10 — Two welders working simultaneously on the portside Fig. 11 — Inspector Mark Thury performing an ultrasonic
joint. inspection of a complete-joint-penetration weld.
DNV high-strength steel; the procedure tice in the United States, so DNV agreed the joint — Fig. 8. Run-off plates were
qualification was performed on high- to use material approved and stamped by welded at the ends of the welding joints.
strength, low-alloy (HSLA) material, the American Bureau of Shipping, an- Joint preparation was a single bevel
comparable to ASTM A572 Grade 50 other classification society. Riverfront groove weld with a 45-deg opening angle
HSLA steel. Steel, Cincinnati, Ohio, was able to locate on top. This allowed the lower part of the
Preheat and interpass temperatures the material needed in Houston, Tex. The joint to be used as a shelf. The root open-
were calculated from the chemical com- plates were transported by truck to Miami, ing was held at approximately ± 1⁄8 in.
position provided by mill certificates and then flown to Curacao. After alignment of the inserts was con-
based on ISO/TR 17844:2004, Welding — firmed, ceramic heating elements and in-
Comparison of Standardized Methods for Rudder Horn sulation pads were installed to maintain
the Avoidance of Cold Cracks. the preheat temperature and to reduce
The preheat temperature was calcu- Since the rudder horn was bent 8 in. the cooling rate of the finished welds —
lated to 225°F, with a maximum interpass starboard and 2 in. aft, it was cut from the Fig. 9. After approximately two hours the
temperature of 400°F. Temperatures dur- vessel at approximately 12 in. below the 225°F preheat temperature was achieved
ing the tests were verified with heat- hull penetration. An approximately 8-in.- and the root could be welded. Preheat and
indicating crayons. tall section was removed. During the cut- minimum interpass temperatures were
The DNV surveyor witnessed the ting operation, the lower, 25-ton portion maintained during the welding operation
welding of the qualification tests. The of the horn was supported vertically by six for a distance not less than 3 in. in all di-
welds passed the visual inspection and 15-ton load-rated turnbuckles. For side rections from the point of welding.
were brought to a local metallurgical lab, alignment, four 10-ton chain hoists were The two upper joints on the port and
accredited by the classification societies. placed forward and aft at the port and starboard side were welded first. The root
The following laboratory tests were starboard sides between the hull plating passes on the upper weld joints were
performed: and the lower casting at an approximately welded simultaneously by two welders,
• Radiography 30-deg angle. each working on one side. They worked
• Round tensile test (weld metal) The rough cut was ground smooth, and in a predetermined welding sequence,
• Tensile test (flat specimen transverse to a 45-deg bevel was prepared at the upper staring from the center to the outside.
the weld) part of the rudder horn plating. For the Four welders working at the same time,
• Charpy V-notch tests at –20°C with the lower part of the joint, the 8-in.-tall plate two on each side (Fig. 10), welded the fill
notch location in weld metal, weld in- insert needed to be prepared with a 45- and cover passes. Welding was accom-
terface, HAZ + 2 mm, and HAZ + 5 deg bevel. plished in two 12-h shifts.
mm An 8-in.-tall plate insert was installed The welders started in the center of the
• Transverse side bend tests to remove the “dog leg” so that the pintle joint, moving outward. The challenge was
• Hardness measurements (Rockwell A) bushing could be realigned with the upper to convince the welders they weren’t in a
• Macro section test. neck bushing. race, and each welder had to weld at the
Test results were available one week The rudder horn nose plate was found same speed. It took 35 passes and approx-
after the plates were delivered to the lab. to be cracked and had to be cropped out imately 24 hours to fill each of the 12-ft-
The results were positive. and replaced. The thickness of the steel long joints.
for the rudder horn plating and the nose After welding the outsides of the in-
Material plate was 1.75 in. sert plates and the front section, the rud-
der horn nose and the root sides of the
All materials, including the electrodes Joint Preparation welds needed to be gouged out and re-
and the steel, had to be certified. The steel welded from the inside. This posed a bur-
had to meet certain criteria, and had to The 8-in.-tall plate insert on the port den on the welders, since they had to sit
be approved and stamped by DNV. Det and starboard sides, as well as the nose in- inside the rudder horn, with preheat tem-
Norske Veritas approved and stamped sert plate, were tacked in place and strong- peratures still applied. After welding the
plate proved difficult to find on short no- backs were welded onto the backside of root from the inside of the rudder horn,
WELDING JOURNAL 43
which had had to be cut out to remove and
reinstall the rudder stock and steering gear
foundation, needed to be re-installed.
Weld Inspection
Mark Thury of Intnerational Inspec-
tions, Inc., a third-party inspection agency
based in California, performed all the in-
spections, including weld inspection.
Det Norske Veritas required 100% vi-
sual inspection of all welds, magnetic par-
ticle testing on root passes of all welds on
insert plates, and ultrasonic inspection of
all complete-joint-penetration welds —
Fig. 11. In addition, leak testing had to be
performed on all watertight compart-
ments. After Thury passed the inspected
items, the DNV surveyor performed a
verification inspection.
44 MAY 2010