Professional Documents
Culture Documents
• Project
• planned duration: 12 mos
• total budget: £100K
• .
• Status
• time elapsed: 6 mos
• spend so far: £64K
• .
• How far along are you?
• 50%? 64%?
• How are you doing?
Project Mgt in the dark
• It tells you how much you’ve spent
and compares it to the budget.
• Does it give an accurate picture of
£
where you are on the project? NO!
It doesn’t tell you if...
– you’re ahead or behind schedule
– you’re over or underspent
– you’ve spent money on the right
thing
– you’re getting value for money
• Accomplishment is (planned)
work that has been carried
out successfully.
• The budgeted cost of that
work quantifies the
accomplishment.
• This is called ‘earned value’
time
A bit more light…
• Project
• planned duration: 12 mos
• total budget: £100K
• produce 20 units
• Status
• time elapsed: 6 mos
• spend so far: £64K
• units produced: 8 complete, 2 partial
• How far along are you?
• 50%? 64%? >40%?
• How are you doing?
Basic definitions – answer three basic Q’s
• How much work • Budgeted Cost for Work
should be done? Scheduled (BCWS)
• plan
• schedule
• budget
• How much work is • Budgeted Cost for Work
done? Performed (BCWP)
• accomplishment
• How much did it cost? • Earned Value (EV)
• Actual Cost of Work
Performed (ACWP)
• actuals
Variance
£ • CV (Cost Variance)
– BCWP - ACWP
– earned value - actual cost
CV • SV (Schedule Variance)
SV – BCWP - BCWS
– earned value - planned
value
– 0 once all work completed
time
Performance Indices • CPI (Cost Performance
Index)
1.1
– BCWP/ACWP
1.0
– earned/actual
0.9
CPI
• SPI (Schedule
1.1
Performance Index)
– BCWP/BCWS
1.0
0.9
– earned/planned
SPI
0.8
– of diminishing value as
project progresses…
tends to 1
More definitions
– answering Q’s about the total job
• What was the total job • Budget At Completion (BAC)
supposed to cost?
• What do we now expect • Estimate To Completion (ETC)
will be needed to finish
the job? • Estimate At Completion (EAC)
• EAC = ACWP + ETC
• What do we now expect • often referred to as Latest
the total job to cost? Revised Estimate (LRE)
• How much do we now • VAC (Variance At Completion)
expect to eventually • VAC = BAC - EAC
underspend/overspend?
Earned Value Management tells you...
Where it’s Drill down
Know where you are
going right through the
and where it’s data to where
in terms of Where you the problem is
accomplishment going wrong
as well as how much
really are!
you’ve spent
EVM
10
Earned Value: Example
Actual Cost: what you Today
have actually spent to
this point in time.
Cost (Person-Hours)
Time (Date)
11
Earned Value: Example
Today
Over
Cost (Person-Hours)
Budget
Behind
Schedule
Time (Date)
12
Performance Indices
• Cost Performance Index
• CPI = BCWP/ACWP
• Schedule Performance Index
• SPI = BCWP/BCWS
• Analysis
• CPI > 1.0 → exceptional performance
• CPI < 1.0 → poor performance
• Similar for SPI
13
Earned Value Management Systems measure
progress
Progress = Movement Forward
to measure progress,
there must be a standard
against which the forward
movement may be
compared
15
EVM can provide answers to the
following questions:
• How much have we spent?
• How much did we get for our money?
• How much more will be have to spend to complete the
tasks we wanted to accomplish?
• How much longer will it take?
• How efficiently is the work being done?
• What has happened? (Why are we off schedule/cost?)
• What is happening? (What are the impacts?)
• What is going to happen? (What are we doing to fix it?)
16
Five Basic Elements
BCWS Budgeted Cost of Work Scheduled
17
5 Basic Performance Data
Questions & Answers
QUESTION ANSWER ACRONYM
19
Budget at Completion (BAC)
BAC
$
$
$ $
$
$
$
time
20
Formulas
• Cost variance • Cost variance in
BCWP – ACWP percentage
BCWP – ACWP x 100
BCWP
• Schedule variance in
• Schedule variance percent
BCWP – BCWS BCWP – BCWS x 100
BCWS
WORK
SCHEDULE PERFORMANCE INDEX: = ACCOMPLISHED
WORK
SPI = schedule efficiency with which work has been SCHEDULED
WORK
accomplished
BCWP ACCOMPLISHED $1500
(The rate at which work is being accomplished)
= BCWS = WORK = $2000 = .75
SCHEDULED 23
Budget at Complete (BAC), Estimate at Complete (EAC)
and Variance at Complete (VAC)
Schedule
BAC = Sum of BCWS
Delay
(Planned cost of all work) EAC
VAC
BAC = $5,000
BAC
EAC(kr)* = ACWP plus estimated to ETC
complete (ETC)
(Actual cost to date plus expected cost
to finish all work) $
EAC = $7,000
VAC = BAC-EAC
VAC = $5,000-$7,000
VAC = -$2,000
TIME
* EAC(kr) = Contractor EAC 24
How to answer the question: “Have we
done what we said we’d do?”
• % complete estimating % of
Budget spent % of work done
% of time elapsed
• subjective, incomplete
25
EVA Integrates All Three
26
PV – Planned Value or Budgeted Cost of Work
Scheduled
120000
100000
80000
60000 BCWS
40000
20000
Nov-03
Jan-03
Jun-03
Jul-03
Feb-03
Aug-03
Sep-03
Dec-03
Mar-03
Apr-03
May-03
Oct-03
27
Earned Value Definitions (cont.)
Cost incurred to accomplish the work that has been done to date.
28
ACWP - Actual Cost of Work Performed
120000
100000
80000
56000 BCWP
60000
ACWP
49000
40000
20000
Nov-03
Jan-03
Jun-03
Jul-03
Feb-03
Aug-03
Sep-03
Dec-03
Mar-03
Apr-03
May-03
Oct-03
29
Earned Value Definitions (cont.)
30
EV- Earned Value or Budgeted Cost of Work
Performed
120000
100000
80000
55000 BCWP
60000
49000 BCWS
40000
20000
Nov-03
Jan-03
Jun-03
Jul-03
Feb-03
Aug-03
Sep-03
Dec-03
Mar-03
Apr-03
May-03
Oct-03
31
The Whole Story
120000
100000
80000
56000 BCWS
60000 BCWP
55000
49000 ACWP
40000
20000
Nov-03
Jan-03
Jun-03
Jul-03
Feb-03
Apr-03
May-03
Aug-03
Sep-03
Dec-03
Oct-03
Mar-03
32
Some Derived Metrics
33
Schedule Variance & Cost Variance
34
Some More Derived Metrics
35
Performance Metrics
SPI: EV/PV
49,000/55,000 = 0.891
CPI: EV/AC
49,000/56000 = 0.875
36
Making Projections
120000
103865
100000 102000
90882
80000
Today BCWS
60000 BCWP
ACWP
40000
20000
Nov-03
Jan-03
Jun-03
Jul-03
Feb-03
Apr-03
May-03
Aug-03
Sep-03
Dec-03
Oct-03
Mar-03
37
Estimate to Complete
140000
120000 116,571
100000 102000
Today BCWS
80000
BCWP
60000
ACWP
40000
20000
0
3
3
03
03
04
3
-03
v-0
l-0
n-0
n-0
ar-
p-
ar-
ay
Ju
No
Se
Ja
Ja
M
M
M
38
Shortcomings of Earned Value
39
EVM Trend Analysis: Cumulative
At Complete
Time Now Risk Variance
Prog
Budget
Management Reserve
ACWP
Schedule Slip
Resources
(Actual
Cost)
Cost BCWS
400 Variance (Planned
Value)
BCWP Schedule
(Earned Variance
300
Value)
200
100
Time
▲
J F M A M J J A
Approx. Time Variance
Planned Resource Consumption
Program
Budget $M
40
Management Reserve
35
30
25
Resources
20 BCWS
(Planned Value)
15 Time-Phased Plan
for Consumption
10 of Resources
▲
J F M A M J J A S O N D
Time
Unfavorable Cost Performance
At Complete
Variance
Time Now
Prog
Budget
Management Reserve
ACWP
$ Resources
(Actual
Cost)
Cost BCWS
400 Variance (Planned
Value)
BCWP
(Earned
300
Value)
200
100
Time
▲
J F M A M J J A