– Budgeted Cost for Work Scheduled (BCWS): (Planned Value PV) – The amount you budget for a task between its start date and today Example: Math: • You expected a task to take 10 days and cost $1,000 (Total Budget/total duration) *day you are on • Today is day 3 (1,000/10)*3 • The BCWS on day 3= $300
– Budgeted Cost for Work Performed (BCWP): (Earned Value EV)
– The percentage of the task budget that corresponds to the task’s completion status – Also known as Earned Value Math: Example: Total Budget*Percent Complete • The $1,000 task is only 10% complete on day 3 1,000*10% • The BCWP = $100
– Actual Cost for Work Performed (ACWP): Actual Cost (AC)
– The actual cost of the task so far Example: • You have spent $500 of your $1,000 by day 3 • The ACWP = $500
Acronym Variance Calculations
CV Cost Variance BCWP — ACWP SV Schedule Variance BCWP — BCWS CVP Cost Variance Percentage CV BCWP • divides cost variance by budgeted cost • negative value means a cost overrun
SVP Schedule Variance Percentage SV BCWS
• divides schedule variance by budgeted cost to date • negative value means the work is behind schedule EAC Estimate at Completion (Original Cost ACWP) ÷ BCWP • Recalculates the cost or completion date based on performance to date