Professional Documents
Culture Documents
Note: Only tasks that are 100% complete will be counted as complete.
Example: The project started on 2/19/01. Today is 2/22/01 (C.O.B.), and we are going to sample
the project based upon the information provided in the project schedule above.
Baseline_Duration Actual_Work Actual_Start Actual_Finish Resource_Names
5 days 68 hrs 2/19/2001 NA
2 days 29 hrs 2/19/2001 2/20/2001 Mike,John
1 day 19 hrs 2/20/2001 2/21/2001 Mike,John
0.5 days 10 hrs 2/22/2002 2/22/2001 Mike[50%],John[50%]
1 day 10 hrs 2/22/2001 NA Mike,John
0.5 days 0 hrs NA NA Mike[50%],John[50%]
oing to sample
Predecessors
2
3
4
5
CV - Calculating Cost Variance CV = BCWP - ACWP SV - Calculating Schedule Variance SV = BCWP - BCWS
Enter the number of estimated effort hours Task 2 32 estimated hrs Enter the number of estimated effort hours Task 2 32 estimated hrs
of task completed as of current sampling Task 3 16 estimated hrs of task completed as of current sampling Task 3 16 estimated hrs
date in this cell Task 4 4 estimated hrs date in this cell Task 4 4 estimated hrs
52.00 estimated hrs BCWP = $3,120.00 52.00 estimated hrs BCWP = $3,120.00
Enter the number of actual effort Task 2 29 actual hrs Enter the number of estimated effort Task 2 32 estimated hrs
hours of task completed as of current Task 3 19 actual hrs hours of task scheduled be completed as Task 3 16 estimated hrs
sampling date in this cell Task 4 10 actual hrs of current sampling date in this cell Task 4 4 estimated hrs
58.00 actual hrs ACWP = $3,480.00 52.00 estimated hrs BCWS = $3,120.00
CPI - Cost Performance Index CPI = BCWP / ACWP SPI - Schedule Performance Index SPI = BCWP / BCWS
Enter the number of estimated effort hours Task 2 32 estimated hrs Enter the number of estimated effort hours Task 2 32 estimated hrs
of task completed as of current sampling Task 3 16 estimated hrs of task completed as of current sampling Task 3 16 estimated hrs
date in this cell Task 4 4 estimated hrs date in this cell Task 4 4 estimated hrs
52.00 estimated hrs BCWP = $3,120.00 52.00 estimated hrs BCWP = $3,120.00
Enter the number of actual effort Task 2 29 actual hrs Enter the number of estimated effort Task 2 32 estimated hrs
hours of task completed as of current Task 3 19 actual hrs hours of task scheduled to be completed as Task 3 16 estimated hrs
sampling date in this cell Task 4 10 actual hrs of current sampling date in this cell Task 4 4 estimated hrs
58.00 actual hrs ACWP = $3,480.00 52.00 estimated hrs BCWS = $3,120.00
CPI = 0.90 A value of less than one SPI = 1.00 A value of less than one
is unfavorable is unfavorable
This project is on schedule (SV=0) and (SPI=1), however your actual costs are exceeding your estimated costs (CV = $360.00)
and your Cost Performance Index is unfavorable (CPI=.90) which means you're spending money faster than estimated to reach your scheduled dates.
At this rate you are going to run out of money before you reach project completion.
End Result = keep your resume current!