The following details are the methods of construction for the Dismantling of 4 units Alkane tank at East
Yard.
1. Mobilization
a. Positioning of Crane shall be in proper position and will operate by competent operator with
NCII certificate and competent rigger, ensure that the equipment has also certificate of
maintenance.
b. Use Manlift or scissor lift for the manpower to cut the plate and ensure that the area for the
positioning of Scissor lift is levelled.
g. During lifting time crane position should follow the required distance from high voltage
electrical power.
a. Ensure that the lifting eye are properly installed on the top plate
b. Ensure that the lifting cable are connected to the lifting eye.
c. Cutting of the plate start at the top edge of the Tank
d. Ensure during cutting of plate there is no personnel inside the tank.
e. Provide tagging for every cut plate.
f. Provide drawing for every tank with proper tagging system.
g. After completing cutting, lift the cut plate down slowly to the proper place.
h. Provide proper support for before cutting the plate base on given cutting list.
i. Ensure that during lifting the area is cordon off.
j. Provide fire extinguisher during cutting.
k. Provide fire blanket if needed.
l. Observe and execute safety during lifting of MS Plate.
m. The fire hose is already available at the site during cutting.
a. Ensure that the lifting eye are properly installed on the top plate
b. Ensure that the lifting cable are connected to the lifting eye.
c. The roof plate will be divided into two since the maximum capacity of the crane when fully
extended at the height of 11.90m is only 2.52 tons, whereas the total weight of the roof
plate is 3.24 tons.
d. An 8layer scaffolding will be used to install the shell support inside the tank.
e. Cutting of the plate start at the top edge of the Tank.
f. Ensure during cutting of plate there is no personnel inside the tank.
g. Provide tagging for every cut plate.
h. Provide drawing for every tank with proper tagging system.
i. After completing cutting, lift the cut plate down slowly to the proper place.
j. Provide proper support for before cutting the plate base on given cutting list.
k. Ensure that during lifting the area is cordon off.
l. Provide fire extinguisher during cutting.
m. Provide fire blanket if needed.
n. Observe and execute safety during lifting of MS Plate.
o. The fire hose is already available at the site during cutting.