LEAD CHART

"Earthwork in ordinary soil for embankments lead up to 100 ft. (30 m) including ploughing and mixing with blade grade or disc
harrow or other suitable equipment & compaction by mechanical means at Optimum Moisture Content and dressing to design section
complete in all respects: 95% maximum modified AASHTO dry density” priced on Market Rate System 1st Bi-Annual-2022 (January
01 to June 30, 2022) for District. Lahore.

Earth Work Lead Upto 12 Km.


Sr. No Description RATE (RS/o% cft)
1 MRS BASE RATE 7448.3
2 LEAD UPTO 1/4 MILE (0.4 km) 3664.6
3 LEAD 1/4 MILE (0.4 km) TO ONE MILE (1.6 km) (12X40.6) 487.2
4 LEAD BEYOND ONE MILE (1.6 km) TO FIVE MILE (8 kM) (16X246.65) 3946.4
5 LEAD BEYOND FIVE MILES (5 km) TO SEVEN AND HALF MILES (12 km) (05 X228.60) 1143.0
Total Amount (RS/o %cft)= 16689.500

Rate Per Cft (Rs.) = 16.6895