You are on page 1of 91

1- Name of work-- Construction of irrigation gul at village Meldhar .

Dallatok (Udiyarasain)
2- Scheme-- M.N.R.E.G.A
3- Block-- Rikhanikhal

LEAD STATEMENT

S.N. MATERIALS SOURCBY MOTOR ROAD BY MULE TOTAL DISTANCE

1 Cement Kotdwar 80 Km 3 83 Km

2 Course Sand Local 0 Km 3 3 Km

3 Fine Sand Local 0 Km 3 3 Km

4 20 mm S/B Local 0 Km 3 3 Km

5 40 mm S/B Local 0 Km 3 3 Km

6 Stone Local 0 Km 0 0 Km

J.E(M.N.R.E.G.A) B.D.O.
1- Name of work-- Construction of irrigation gul at village Meldhar .
Dallatok (Udiyarasain)
2- Scheme-- M.N.R.E.G.A
3- Block-- Rikhanikhal

1- CEMENT :- Cartage by motor road = 80 Km


1st to 5 Km as per schedule = 85.800 per MT
6th 10th Km 5 Km @ 6.60 = 33.00 per MT
11th to 20th Km 10 Km @ 5.50 = 55.00 per MT
21th to 30th Km 10 Km @ 4.55 = 45.50 per MT
31th to 40th Km 10 Km @ 3.85 = 38.50 per MT
41th to 50th Km 10 Km @ 3.85 = 38.50 per MT
Beyond 50 Km 45 Km @ 3.05 = 137.25 per MT
Cartage by mule = 3 Km
Up to 1/2 Km 0.5 Km @ 100.00 Per 1/2 Km 100.00 per MT
Beyond1/2Km 2.5 Km @ 45.00 Per 1/2 Km 225.00 per MT
Stacking charge = 18.00 per MT
Total Rs 776.55 Per MT
Or Rs 38.83 Per Bag
Less 10 % C.P.of 38.83 3.88275 Per Bag
Net Rs 34.94 Per Bag
Say Rs 35.00 Per Bag

2- Sand :- Cartage by motor road = 0 Km


1st to 5 Km as per schedule = 108.70 Per cum
0 Km @ 8.25 = 0.00 Per cum
0 Km @ 6.60 = 0.00 Per cum
0 Km @ 5.80 = 0.00 Per cum
0 Km @ 5.15 = 0.00 Per cum
0 Km @ 5.15 = 0.00 Per cum
0 Km @ 4.05 = 0.00 Per cum
Cartage by mule = 3 Km
Up to 1/2 Km 0.5 Km @ 10.00 Per 1/2 Km 160.00 Per cum
Beyond1/2Km 2.5 Km @ 4.50 Per 1/2 Km 360.00 Per cum
Stacking charge = 12.00 Per cum
Total Rs 640.70 Per cum
Less 10% C.P. (-) 64.07 Per cum
Net Rs 576.63 Per cum
Say Rs 577.00 Per cum
3- Stone ballast : -
Cartage by mule = 3 Km
Up to 1/2 Km 0.5 Km @ 10.00 Per 1/2 Km 160.00 Per cum
Beyond1/2Km 2.5 Km @ 4.50 Per 1/2 Km 360.00 Per cum
Stacking charge = 12.00 Per cum
Total Rs 532.00 Per cum
Less 10% C.P. (-) 53.20 Per cum
Net Rs 478.80 Per cum
Say Rs 479.00 Per cum
4- Stone :-
Cartage by mule = 0 Km
Up to 1/2 Km 0 Km @ 10.00 Per 1/2 Km 0.00 Per cum
Beyond1/2Km 0 Km @ 4.50 Per 1/2 Km 0.00 Per cum
Cartage by head load @Rs 51/cum for 3 chain 51.00 Per cum
Stacking charge = 12.00 Per cum
Total Rs 63.00 Per cum
Less 10% C.P. (-) 6.3 Per cum
Net Rs 56.70 Per cum
Say Rs 57.00 Per cum

COST OF MATERIAL AT SITE

S.N. MATERIAL S.I.NO. RATE CARTAGE TOTAL COST

1 Cement Market 260.00 35.00 295.00 Per Bag

2 20mm S/B 2(a) 410.00 479.00 889.00 Per cum

3 40mm S/B 2© 310.00 479.00 789.00 Per cum

4 Course Sand 38- 340.00 577.00 917.00 Per cum

5 Fine Sand 39- 300.00 577.00 877.00 Per cum

6 Stone 41(b) 220.00 57.00 277.00 Per cum


J.E(M.N.R.E.G.A) B.D.O.

1- Name of work-- Construction of irrigation gul at village Meldhar .


Dallatok (Udiyarasain)
2- Scheme-- M.N.R.E.G.A
3- Block-- Rikhanikhal
1- R/R dry walls in R/W,B/W and Kharinja i/c all for comp of work .
Rate as per S.I.No. 518 = Rs 350.00 Per cum
Less 10% C.P. Rs 35.00 Per cum
Net Rs 315.00 Per cum
Add cartage of stone Rs 277.00 Per cum
Total Rs 592.00 Per cum
Say Rs 592.00 Per cum
2- R/R stone masonry in 1:6 cement and sand mortor in R/W and B/W i/c supply of all.
Rate as per S.I.No 516 = Rs 360.00 Per cum
Less 10% C.P. Rs 36.00 Per cum
Net Rs 324.00 Per cum
Add cartage of stone Rs 277.00 Per cum
Cost of cement 1.41 bag @ 295.00 / bag =R 415.95 Per cum
Fine Sand 0.30 cum @ 877.00 / cum =R 263.10 Per cum
Total Rs 1280.05 Per cum
Say Rs 1280.00 Per cum
3- Laying of C.C. (1:3:6) in cement, sand and 20mm S/B i/c all .
(A) Materials -
Cement 4.41 bag @ 295.00 / bag =R 1300.95 Per cum
Course sand 0.45 cum @ 917.00 / cum =R 412.65 Per cum
20mm S/B 0.90 cum @ 889.00 / cum =R 800.10 Per cum
Total Rs 2513.70 Per cum
(B) Labour - (For 132 cft)
Mistri 0.166 nos @ 180.00 Per day = 29.88 Per132cft
Mason 2 nos @ 180.00 Per day = 360.00 Per132cft
Beldar 12 nos @ 100.00 Per day = 1200.00 Per132cft
Coolie 14 nos @ 100.00 Per day = 1400.00 Per132cft
Sundries 10.00x25= 250.00 Per132cft
Total Rs 3239.88 Per132cft
Or Rs 2454.45 % cft
Or Rs 867.30 Per cum

Total (A + B) =R 3381.00 Per cum


Say Rs 3381.00 Per cum
4- Excavation in foundation in R/W and B/W including supply of all
for completion of work.
Rate as per S.I. No. 165 (b) = Rs 40.00 / cum
Less 10 % C.P.of 40.00 4.00 / cum
Net Rs 36.00 / cum
Say Rs 36.00 / cum

5- 12mm thick plaster in 1:3 cement and sand mortor i/c supply of all for comp. of work .
(A) Materials :-
Cement 0.152 bags @ Rs 295.00 /bag= Rs 44.84 / sqm
Fine sand 0.015 cum @ Rs 877.00 /cum=Rs 13.16 / sqm
Total Rs 58.00 / sqm
(B) Labours - For 100 sqft
Mason 1.33 nos @ Rs 180.00 / day = Rs 239.94 % sqft
Beldar 0.50 nos @ Rs 100.00 / day = Rs 50.00 % sqft
Coolie 1.33 nos @ Rs 100.00 / day = Rs 133.30 % sqft
Bhisti 0.50 nos @ Rs 100.00 / day = Rs 50.00 % sqft
T$P etc L.S. 1.00 x 25 25.00 % sqft
less 10 %C.P.on Rs 498.24 49.824 % sqft
Total Rs 548.06 % sqft 59.00
(A+B) Total Rs 117.00 / sqm
Say Rs 117.00 / sqm

J.E(M.N.R.E.G.A) B.D.O.
1- Name of work-- Construction of irrigation gul at village Meldhar .
Dallatok (Udiyarasain)
2- Scheme-- M.N.R.E.G.A
3- Block-- Rikhanikhal

Detail of Measurement
S.N Item of work No L B H/D Qty
1- E/W in excavation in all Type
of soil including lead & lift
Etc-----
For wall 2 15.00 0.80 0.20 4.80
1 11.00 0.80 0.20 1.76
For Gul 17 15.00 0.70 0.20 35.70
1 12.00 0.70 0.20 1.68
Total .... 43.94 cum
2- R.R. dry stone masonry in
cluding s/o all material labou
r T&P etc----- work.
For wall 2 15.00 .70+.50/2 0.70 12.60
1 11.00 .70+.50/2 0.70 4.62
For Gul(Khadanja) 17 15.00 0.6 0.15 22.95
1 12.00 0.6 0.15 1.08
Total .... 41.25 cum
3- Laying c.c in 1:3:6 for Gul.
Foundation 17 15.00 0.60 0.10 15.30
1 12.00 0.60 0.10 0.72
Praphat 2X17 15.00 0.20 0.20 20.40
2X1 12.00 0.20 0.20 0.96
Total .... 37.38 cum
4- R.R. stone masonry 1:6 c/s 0 0 0 0 0.00
mortar------ work. L/W
5- Cement plaster in 1:3 C/S mortar
outer side 17 15.00 0.20 51.00
1 12.00 0.2 2.40
iner side 3X17 15.00 0.2 153.00
3X1 12.00 0.2 7.20
Total .... 213.60 sqm
6- Sign board & Photography.. L.S 1 job
7- R.C.C. pillar(1.95mx0.15mx0.12m) 4 job
J.E(M.N.R.E.G.A) B.D.O.

1- Name of work-- Construction of irrigation gul at village Meldhar .


Dallatok (Udiyarasain)
2- Scheme-- M.N.R.E.G.A
3- Block-- Rikhanikhal

Bill of Qty
S.N Item of Work Qty Unit Rate Amount

1- E/W in excavation in all Type


of soil including lead & lift
Etc----- 43.94 Cum 36.00 1581.84

2- R.R. dry stone masonry in


cluding s/o all material labou
r T&P etc----- work. 41.25 Cum 592.00 24420

3- Laying C.C. 1:3:6 cement


c.sand & 20mm stone ballast
including s/o all material
labour T&P etc------ work. 37.38 Cum 3381.00 126381.8

4- R.R. stone masonry 1:6 c/s 0 0 0 0


mortar------ work.
5- 12mm thick plaster 1:3 c/s
Mortar in wall including s/o
All material labour T&p 213.60 Sqm 117.00 24991.20

6- S/F of Sign Board & Photo Graphy L.S 2000.00


7- R.C.C. pillar(1.95mx0.15mx0.12m) L.S 2000.00
8- Tools & plant etc. L.S 1000.00
9- Site shed / Water arrangement L.S 1000.00

Total 183374.82
Say 183337.00
Sanction Cost Rs 183337.00

J.E(M.N.R.E.G.A) B.D.O.

SUMMARY OF ESTIMATED COST

S.N PARTICULARS AMOUNT

1 Constt. Of irrigation gul as per detailed estimate R #REF!

Total Rs #REF!

Say Rs ###

Sanctioned Rs ###

J.E.(M.N.R.G.A) B.D.O.
###

QNTTY.
DETAILS OF MEASUREMENT

S.N. ITEM OF WORK NO. L. B. H/D 30.00


1 E/W in excavation in 30.00
foundation in R/W, B/W
i/c supply of all. 1 50.00 1.00 0.60 108.00
2 R/R stone masonry Total 108.00 cum
in 1:6 cement and sand
mortor in R/W,B/W i/c all. 3 40.00 0.60 1.50 6.00
Total 6.00 cum
3 R/R dry walls in R/W,
B/W and Kharinja i/c all. 2 5.00 0.60 1.00 1 Job
Total

4 Making sign board . - - - L.S.

BILL OF QUANTITY

S.N. ITEM OF WORK QNTTY. UNIT RATE AMOUNT


1 E/W in excavation in
foundation in R/W, B/W
i/c supply of all. 30.00 cum 36.00 1080.00
2 R/R stone masonry
in 1:6 cement and sand
mortor in R/W,B/W i/c all. 108.00 cum 1280.00 ###
3 R/R dry walls in R/W,
B/W and Kharinja i/c all. 6.00 cum 592.00 3552

4 Making sign board . 1 Job L.S. 1000.00


Total Rs ###

J.E.,R.E.S. B.D.O.

###

SUMMARY OF ESTIMATED COST

S.N PARTICULARS AMOUNT

1 Constt. Of Protection wall as per detailed estimate Rs ###

Total Rs ###

Say Rs ###

J.E.,R.E.S. B.D.O.
1- Name of work-- Construction of Barat Ghar at Village Kotnalee .
2- Scheme-- Special Componenet Plan
3- Block-- Dugadda.

LEAD STATEMENT
S.N. MATERIALS SOURCE BY MOTOR ROAD BY MULE TOTAL DISTANCE

1 Cement Kotdwar 115 Km 2 117 Km

2 Mild steel Kotdwar 115 Km 2 117 Km

3 Bricks Kotdwar 115 Km 2 117 Km

4 Course Sand Local 35 Km 2 37 Km

5 Fine Sand Local 35 Km 2 37 Km

6 20 mm S/B Local 35 Km 2 37 Km

7 40 mm S/B Local 35 Km 2 37 Km

8 Stone Local 0 Km 1.5 1.5 Km

J.E.,R.E.S. B.D.O.
1- Name of work-- Construction of Barat Ghar at Village Kotnalee .
2- Scheme-- Special Componenet Plan
3- Block-- Rikhanikhal

CARTAGE OF MATERIALS
1- CEMENT :- Cartage by motor road = 115 Km
1st to 5 Km as per schedule = 85.80 per MT
6th 10th Km 5 Km @ 6.60 = 33.00 per MT
11th to 20th Km 10 Km @ 5.50 = 55.00 per MT
21th to 30th Km 10 Km @ 4.55 = 45.50 per MT
31th to 40th Km 10 Km @ 3.85 = 38.50 per MT
41th to 50th Km 10 Km @ 3.85 = 38.50 per MT
Beyond 50 Km 65 Km @ 3.05 = 198.25 per MT
Cartage by mule = 2 Km
Up to 1/2 Km 0.5 Km @ 100.00 Per 1/2 Km 100.00 per MT
Beyond1/2Km 1.5 Km @ 45.00 Per 1/2 Km 135.00 per MT
Stacking charge = 18.00 per MT
Total Rs 747.55 Per MT
Or Rs 37.38 Per Bag
Less 10 % C.P.of 37.38 3.73775 Per Bag
Net Rs 33.64 Per Bag
2- M.S.Tor Bar :- Say Rs 34.00 Per Bag
Cartage by motor road same as above Item no. 1 = Rs 494.55 per MT
Cartage by manual labour = 2 Km @Rs 320 per1/2 1280.00 per MT
Stacking charge = 18.00 per MT
Total Rs 1792.55 Per MT
Less 10 % C.P.of 1792.55 179.255 Per MT
Net Rs 1613.30 Per MT
Or Rs 161.33 Per qntl
Say Rs 161.00 Per qntl
3- Sand :- Cartage by motor road = 35 Km
1st to 5 Km as per schedule - - - - - - - = 108.70 Per cum
6th 10th Km 5 Km @ 8.25 = 41.25 Per cum
11th to 20th Km 10 Km @ 6.60 = 66.00 Per cum
21th to 30th Km 10 Km @ 5.80 = 58.00 Per cum
31th to 40th Km 5 Km @ 5.15 = 25.75 Per cum
0 Km @ 5.15 = 0.00 Per cum
0 Km @ 4.05 = 0.00 Per cum
Cartage by mule = 2 Km
Up to 1/2 Km 0.5 Km @ 10.00 Per 1/2 Km 160.00 Per cum
Beyond1/2Km 1.5 Km @ 4.50 Per 1/2 Km 216.00 Per cum
Stacking charge = 12.00 Per cum
Total Rs 687.70 Per cum
Less 10 % C.P.of 687.70 68.77 Per cum
Net Rs 618.93 Per cum
Say Rs 619.00 Per cum

J.E.,R.E.S. B.D.O.

4- Stone Ballast 20mm 40 mm Same as item No 3- Rs 619.00 per Cum

5-Bricks :- Cartage by motor road = 115 Km


1st to 5 Km as per schedule = 108.70 Per cum
6th 10th Km 5 Km @ 8.25 = 41.25 Per cum
11th to 20th Km 10 Km @ 6.60 = 66.00 Per cum
21th to 30th Km 10 Km @ 5.80 = 58.00 Per cum
31th to 40th Km 10 Km @ 5.15 = 51.50 Per cum
41th to 50th Km 10 Km @ 5.15 = 51.50 Per cum
Beyond 50 Km 65 Km @ 4.05 = 263.25 Per cum
Cartage by mule = 2 Km
Up to 1/2 Km 0.5 Km @ 10.00 Per 1/2 Km 160.00 Per cum
Beyond1/2Km 1.5 Km @ 4.50 Per 1/2 Km 216.00 Per cum
Stacking charge = 12.00 Per cum
Total Rs 1028.20 Per cum

Less 10 % C.P.of 1028.20 102.82 Per cum


Net Rs 925.38 Per cum
Say Rs 925.00 Per cum
For thousand nos of brick =2.40x 925.00 = Rs 2220.00 %0 nos
Say Rs 2220.00 %0 nos

6- Stone :-
Cartage by mule = 1.5 Km
Up to 1/2 Km 0.5 Km @ 8.25 Per 1/2 Km 165.00 Per cum
Beyond1/2Km 1 Km @ 4.00 Per 1/2 Km 160.00 Per cum
Stacking charge = 10.00 Per cum
Total Rs 335.00 Per cum
Less 10 % C.P.of 335.00 33.50 Per cum
Net Rs 301.50 Per cum
Say Rs 302.00 Per cum

J.E.,R.E.S. B.D.O.
COST OF MATERIAL AT SITE

S.N. MATERIAL S.I. NO. RATE CARTAGE TOTAL COST

1 Cement Market 250.00 34.00 284.00

2 M.S. Tor Bar 20(b) 3850.00 161.00 4011.00

3 M.S.Angle, Flat Iron 20(a) 3950.00 161.00 4111.00

4 Bricks 1(a) 1900.00 2220.00 4120.00

5 20 mm stone ballast 2(a) 410.00 619.00 1029.00

6 40 mm stone ballast 2© 310.00 619.00 929.00

7 Course Sand 38 . 340.00 619.00 959.00

8 Fine Sand 39 . 300.00 619.00 919.00

9 Stone for building 41(a) 265.00 302.00 567.00

10 Stone for site development 41(b) 220.00 302.00 522.00

11 Paint As per market rate 180.00

12 Primer As per market rate 100.00

13 Snowsem As per market rate 35.00

14 Whiting As per market rate 5.00

15 Sal wood As per Van Nigam rate 30000.00


J.E.,R.E.S. B.D.O.

/ sqm

12mm thick plaster in 1:6 cement and sand mortor i/c supply of all for comp. of work .
(A) Materials :-
Cement 0.076 bags @ R 284.00 /bag= Rs 21.58
Fine sand 0.015 cum @ Rs 919.00 /cum=Rs 13.79
Total Rs 35.37
(B) Labours - For 100 sqft
Mason 1.33 nos @ Rs 180.00 / day = R 239.94 % sqft
Beldar 0.50 nos @ Rs 100.00 / day = R 50.00 % sqft
Coolie 1.33 nos @ Rs 100.00 / day = R 133.30 % sqft
Bhisti 0.50 nos @ Rs 100.00 / day = R 50.00 % sqft
T$P etc L.S. 1.00 x 25 25.00 % sqft
Add 0 %C.P.on Rs 498.24 0 % sqft
Total Rs 498.24 %sqft or Rs 53.63
(A+B) Total Rs 89.00
Say Rs 89.00
Earth and boulder filling in plinth including supply of all for comp of work.
Rate as per S.I. No. 161 = Rs 35.00 /cum
J.E.,R.E.S. B.D.O.

Painting or varnishing in two coats over one coat of primer including supply of all .
(A) Materials :-
Primer 0.075 bags @ R 100.00 /ltr = Rs 7.50
(B) Labours - For 650 sqft
Painter 1 nos @ Rs 180.00 / day = R 180.00 /650 sft
Coolie 1 nos @ Rs 100.00 / day = R 100.00 /650 sft
T$P etc L.S. 0.50 x 25 12.50 /650 sft
Add 0 %C.P.on Rs 292.50 0 /650 sft
Total Rs 292.50 /650 sft or 4.84
( c ) Paint 0.13 litr @ 180.00 /litr = Rs 23.40
(D) Labours - For 100 sqft
Painter 0.45 nos @ Rs 180.00 / day = R 81.00 % sqft
Coolie 0.45 nos @ Rs 100.00 / day = R 45.00 % sqft
T$P etc L.S. 0.20 x 25 5.00 % sqft

Add 0 %C.P.on Rs 131.00 0 % sqft


Total Rs 131.00 % sqft or 14.10
(A+B+C+D) Total Rs 49.84
Say Rs 50.00
White washing in three coats including supply of all for completion of work.
(A) Materials :-

White lime 0.32 Kg @ Rs 5.00 /ltr = Rs 1.60


(B) Labours - For 100 sqft
0.13 nos @ Rs 120.00 / day = R 15.96 % sqft
Helper 0.13 nos @ Rs 100.00 / day = R 13.30 % sqft
(B) Labours - For 1cwt
B/smith 1 nos @ Rs 180.00 / day = R 180.00 / cwt
1 nos @ Rs 100.00 / day = R 100.00 / cwt
Rivettor 0.25 nos @ Rs 180.00 / day = R 45.00 / cwt
Coolie 1 nos @ Rs 100.00 / day = R 100.00 / cwt
T$P etc L.S. 0.60 x 25 15.00 / cwt
Extra for hoisting and welding
4.9 x 25 122.5 / cwt
Add 0 %C.P.on Rs 562.50 0.00 / cwt
Total Rs 562.50 /cwt or Rs 1108.13
Total Rs 5321.90
Say Rs 5322.00
35 mm thick sal and sheesham wood fully panelled doors and window shutters i/c all .
(A) Materials :-
Sal wood Sal wood 0.0336 cum @ Rs 30000.00 /bag= Rs 1008.00
(B) Labours - For 24.75 sqft
Mistri 0.13 nos @ Rs 180.00 / day = R 22.50 /24.75 sqft
Carpent 2.00 nos @ Rs 180.00 / day = R 360.00 /24.75 sqft
Carpent 2.00 nos @ Rs 180.00 / day = R 360.00 /24.75 sqft
Beldar 1.00 nos @ Rs 100.00 / day = R 100.00 /24.75 sqft
Painter 0.25 nos @ Rs 180.00 / day = R 45.00 /24.75 sqft
T$P etc L.S. 0.50 x 25 12.50 /24.75 sqft
Add 0 %C.P.on Rs 900.00 0 /24.75 sqft
Total Rs 900.00 /24.75 sqft
Or Rs 3636.36364 %sqft or Rs 391.43
(A+B) Total Rs 1399.43
Say Rs 1399.00
S/F of oxidized iron fittings including supply of all for comp of work.
Rate as per market = Rs 100.00 / sqm
J.E.,R.E.S. B.D.O.
LABOUR RATE

S.N. LABOUR RATE

1 MISTRI 180.00 PER DAY

2 MASON 180.00 PER DAY

3 CARPENTER 180.00 PER DAY

4 BLACK SMITH 180.00 PER DAY

5 PAINTER 180.00 PER DAY

6 PLUMBER 180.00 PER DAY

7 BELDAR 100.00 PER DAY

8 COOLIE 100.00 PER DAY

9 CHAUKIDAR 100.00 PER DAY

10 BHISTI 100.00 PER DAY


11 HAMMER MAN 100.00 PER DAY
12 WHITE WASHER 120.00 PER DAY
13 HELPER 100.00 PER DAY
14 RIVETTOR 180.00 PER DAY
1- Name of work-- Construction of Barat Ghar at Village Kotnalee.
2- Scheme-- Special Component Plan
3- Block-- Rikhanikhal
ANALYSIS OF RATE
1- Excavation in foundation in all types of soil including supply of all
for completion of work.
Rate as per S.I. No. 165 (a) = Rs 35.00 / cum
Less 10 % C.P.of 35.00 3.50 / cum
Net Rs 31.50 / cum
Say Rs 32.00 / cum
2- C.C.(1:6:12) in foundation in cement, sand and 40 mm stone ballast i/c all .
(A) Materials :-
Cement 2.26 bags @ Rs 284.00 /bag= Rs 641.84 / cum
Fine sand 0.50 cum @ Rs 919.00 /cum=Rs 459.50 / cum
40mm S/B 1.00 cum @ Rs 929.00 /cum=Rs 929.00 / cum
Total Rs 2030.34 / cum
(B) Labours - For 100 cft
Mistri 0.125 nos @ Rs 180.00 / day = Rs 22.50 % cft
Mason 0.333 nos @ Rs 180.00 / day = Rs 59.94 % cft
Beldar 4 nos @ Rs 100.00 / day = Rs 400.00 % cft
Coolie 6 nos @ Rs 100.00 / day = Rs 600.00 % cft
Bhisti 1 nos @ Rs 100.00 / day = Rs 100.00 % cft
T$P etc L.S. 1.00 x 25 25.00 % cft
Add 0 %C.P.on Rs 1207.44 0 % cft
Total Rs 1207.44 %cft or Rs 426.66 / cum
(A+B) Total Rs 2457.00 / cum
Say Rs 2457.00 / cum

3 - R.R. stone masonry in 1:6 cement and sand mortor in foundation including supply of all .
(A) Materials :-
Cement 1.41 bags @ Rs 284.00 /bag= Rs 400.44 / cum
Fine sand 0.30 cum @ Rs 919.00 /cum=Rs 275.70 / cum
Stone 1.00 cum @ Rs 567.00 /cum=Rs 567.00 / cum
Total Rs 1243.14 / cum
(B) Labours - For 100 cft
Mason 4 nos @ Rs 180.00 / day = Rs 720.00 % cft
Beldar 3 nos @ Rs 100.00 / day = Rs 300.00 % cft
Coolie 2 nos @ Rs 100.00 / day = Rs 200.00 % cft
Bhisti 0.25 nos @ Rs 100.00 / day = Rs 25.00 % cft
T$P etc L.S. 0.50 x 25 12.50 % cft
Add 0 %C.P.on Rs 1257.50 0 % cft
Total Rs 1257.50 %cft or Rs 444.35 / cum
(A+B) Total Rs 1687.49 / cum
Say Rs 1687.00 / cum
J.E.,R.E.S. B.D.O.

4- R.R. stone masonry in 1:6 cement and sand mortor in super structure i/c supply of all .
Rate same as per above Item no. 3- = Rs 1687.49 / cum
Add for extra Labour required :-
Mason 0.5 nos @ Rs 180.00 / day = Rs 90.00 % cft
Coolie 1 nos @ Rs 100.00 / day = Rs 100.00 % cft
Scaffolding 0.75 x 25 18.75 % cft
Add 0 %C.P.on Rs 208.75 0 % cft
Total Rs 208.75 %cft or Rs 73.76 / cum
Total Rs 1761.25 / cum
Say Rs 1761.00 / cum

5- Brick masonry in 1:6 C/S mortor in plinth including supply of all for completion of work.
(A) Materials :-
Cement 1.25 bags @ Rs 284.00 /bag= Rs 355.00 / cum
Fine sand 0.27 cum @ Rs 919.00 /cum=Rs 248.13 / cum

Bricks 460.00 Nos @ Rs 4120.00 /cum=Rs 1895.20 / cum


Total Rs 2498.33 / cum
(B) Labours - For 100 cft
Mistri 0.17 nos @ Rs 180.00 / day = Rs 30.60 % cft
Mason 2 nos @ Rs 180.00 / day = Rs 360.00 % cft
Beldar 2 nos @ Rs 100.00 / day = Rs 200.00 % cft
Coolie 2 nos @ Rs 100.00 / day = Rs 200.00 % cft
T$P etc L.S. 0.70 x 25 17.50 % cft
Add 0 %C.P.on Rs 808.10 0 % cft
Total Rs 808.10 %cft or Rs 285.55 / cum
(A+B) Total Rs 2783.88 / cum
Say Rs 2784.00 / cum

6- Brick masonry in 1:6 C/S mortor in super structure i/c supply of all for completion of work.
Rate same as per above Item no. 5- = Rs 2783.88 / cum
Add for extra Labour required :-
Mason 1 nos @ Rs 180.00 / day = Rs 180.00 % cft
Coolie 1 nos @ Rs 100.00 / day = Rs 100.00 % cft
Scaffolding 1.50 x 25 37.50 % cft
Add 0 %C.P.on Rs 317.50 0 % cft
Total Rs 317.50 %cft or Rs 112.19 / cum
Total Rs 2896.07 / cum
Say Rs 2896.00 / cum

7- S/F of Angle Iron door chaukhat with iron shutter i/c all for comp of work. (1.00x2.00M)
Rate as per market = Rs 2500.00 /No.
8- S/F of Angle Iron window chaukhat with iron shutter grills i/c all for comp of work.
(0.90x1.20M) Rate as per market = Rs 2500.00 /No.
9- S/F of Angle Iron ventilator i/c supply of all for comp of work. (0.45x0.30M)
Rate as per market = Rs 250.00 /No.

J.E.,R.E.S. B.D.O.

10- R.C.C. (1:2:4) in plinth and lintel band etc. in cement, course sand and 20mm stone
ballast including supply of all for completion of work.
(A) Materials :-
Cement 6.62 bags @ Rs 284.00 /bag= Rs 1880.08 / cum
Course sand 0.45 cum @ Rs 959.00 /cum=Rs 431.55 / cum
20mm S/B 0.90 cum @ Rs 1029.00 /cum=Rs 926.10 / cum
Total Rs 3237.73 / cum
(B) Labours - For 100 cft
Mistri 0.1 nos @ Rs 180.00 / day = Rs 18.00 % cft
Mason 0.25 nos @ Rs 180.00 / day = Rs 45.00 % cft
Beldar 4 nos @ Rs 100.00 / day = Rs 400.00 % cft
Coolie 8 nos @ Rs 100.00 / day = Rs 800.00 % cft
Bhisti 2 nos @ Rs 100.00 / day = Rs 200.00 % cft
B/smith 2.1 nos @ Rs 180.00 / day = Rs 378.00 % cft
T$P etc L.S. 2.00 x 25 50.00 % cft
Add 0 %C.P.on Rs 1891.00 0 % cft
Binding wire 28 x 25 700 % cft
Shuttering 28 x 25 700 % cft
Total Rs 3291.00 %cft or Rs 1162.90 / cum
(A+B) Total Rs 4400.63 / cum
Say Rs 4401.00 / cum
11- R.C.C. (1:2:4) in slab including supply of all for completion of work.
Complete rate as per above Item no. 10- = Rs 4400.63 / cum
Add extra cost of centering and shuttering
= 0.40 x 35.31 x 25 = Rs 353.1 / cum
Total Rs 4753.73 / cum
Say Rs 4754.00 / cum
12- R.C.C. (1:2:4) in beam, columns including supply of all for completion of work.
Complete rate as per above Item no. 11- = Rs 4753.73 / cum
Add extra cost forordinary stone and balli support
= 1.00 x 35.31 x 25 = Rs 882.75 / cum
Total Rs 5636.48 / cum
Say Rs 5636.00 / cum
13- M.S. iron work as in reinforcement of R.C.C. work i/c supply of all for completion of work.
(A) Materials :-
M.S.bar i/c 5% wastage 1.05 qntl @ Rs 4011.00 /bag= Rs 4211.55 / qntl
(B) Labours - For 1 cwt
B/smith 1 nos @ Rs 180.00 / day = Rs 180.00 / cwt
Coolie 1.5 nos @ Rs 100.00 / day = Rs 150.00 / cwt
T$P etc L.S. 0.80 x 25 20.00 / cwt
Add 0 %C.P.on Rs 350.00 0 / cwt
Total Rs 350.00 /cwt or Rs 689.50 / qntl
Total Rs 4901.05 / qntl
Say Rs 4901.00 / qntl

J.E.,R.E.S. B.D.O.

14- 2.5 cm thick P.C.C. (1:2:4) in sills of door and windows in cement , course sand and
20 mm S/B including supply of all for completion of work .
(A) Materials :-
Cement 0.197 bags @ Rs 284.00 /bag= Rs 55.95 / sqm
Course sand 0.011 cum @ Rs 959.00 /cum=Rs 10.55 / sqm
20mm S/B 0.023 cum @ Rs 1029.00 /cum=Rs 23.67 / sqm
Total Rs 90.16 / sqm
(B) Labours - For 100 sqft
Mistri 0.13 nos @ Rs 180.00 / day = Rs 22.50 % sqft
Mason 1.00 nos @ Rs 180.00 / day = Rs 180.00 % sqft
Beldar 0.50 nos @ Rs 100.00 / day = Rs 50.00 % sqft
Coolie 0.50 nos @ Rs 100.00 / day = Rs 50.00 % sqft
Bhisti 0.25 nos @ Rs 100.00 / day = Rs 25.00 % sqft
T$P etc L.S. 1.25 x 25 31.25 % sqft
Add 0 %C.P.on Rs 358.75 0 % sqft
Total Rs 358.75 %sqft or Rs 38.62 / sqm
(A+B) Total Rs 128.78 / sqm
Say Rs 129.00 / sqm
15- 2.5 cm P.C.C.(1:2:4) in cement, sand and 20 mm S/B over 7.5 cm P.C.C. (1:6:12) in
cement, sand and 40 mm S/B in floor and apron including supply of all for comp of work.
Complete rate as per above Item no. -14- =Rs 128.78 / sqm
Base concrete of 1:6:12 ( Rate as per above item no. 2-
0.08 x 2457.00 = Rs 196.56 / sqm
Add 0 %C.P.on Rs 325.34 0.00 / sqm
Total Rs 325.34 / sqm
Say Rs 325.00 / sqm

/ sqm
/ sqm
/ sqm

/ sqm
/ sqm
/ sqm
dk;Z dk uke%&m0ek0fo0cjlwM+h esa d{kksa dk fuekZZ.k dk
/ sqm BILL OF QUANTITY

S.N. ITEM OF WORK QNTTY. UNIT RATE

1 E/W in excavation in foundation in all


types of soil i/c supply of all. 22.59 cum 32.00
/ sq 2 C.C.(1:6:12) in cement,sand and 40 mm.
/ sqm stone ballast i/c supply of all. 3.75 cum 2457.00
3 R/R stone masonry in 1:6 cement and
sand mortor in foundation i/c supply of all. 20.48 cum 1687.00
4 R.C.C.(1:2:4) in plinth and lintel band
i/c supply of all. 3.07 cum 4401.00

5 Brick masonry in 1:6 cement and sand


/ sqm mortor in super structure i/c all. 21.86 cum 2896.00
/ sq 6 S/F of Angle iron chaukhat for door with
/ sqm iron shutter i/c supply of all.(1.00x2.00M) 4 nos 2500.00
7 S/F of Angle iron chaukhat for window with
fixed grills and iron shutter i/c supply of all. 4 nos 2500.00

/ sq 8 R.C.C.(1:2:4) in beam columns i/c supply


of all for comp of work. 2.35 cum 5636.00
9 R.C.C.(1:2:4) in slab including supply
of all for comp of work. 10.44 cum 4754.00
T$P etc L.S. 0.20 x 25 5.00 % sqft
Add 0 %C.P.on Rs 5.00 0 % sqft
Total Rs 5.00 % sqft or 0.54 / sqm
(A+B ) Total Rs 2.14 / sqm
Say Rs 2.00 / sqm
20- R/R dry walls in R/W,B/W and Kharinja i/c all for comp of work .
Rate as per S.I.No. 518 = Rs 265.00 Per cum
Less 10% C.P. Rs 26.50 Per cum
Net Rs 238.50 Per cum
Add cartage of stone Rs 522.00 Per cum
Total Rs 760.50 Per cum 15
Say Rs 761.00 Per cum
21- R/R stone masonry in 1:6 cement and sand mortor in R/W and B/W i/c supply of all.
Rate as per S.I.No 516 = Rs 290.00 Per cum
Less 10% C.P. Rs 29.00 Per cum
Net Rs 261.00 Per cum
Add cartage of stone Rs 522.00 Per cum
Cost of cemen 1.41 bag @ 284.00 / bag =Rs 400.44 Per cum
Fine Sand 0.30 cum @ 919.00 / cum =Rs 275.70 Per cum
Total Rs 1459.14 Per cum
Say Rs 1459.00 Per cum

J.E.,R.E.S. B.D.O.

22- Mild steel or iron work such as in door, window chaukhats, grills i/c supply of all .
(A) Materials :-
M.S. i/c 2.5% wastage 1.025 qntl @ Rs 4111.00 /bag= Rs 4213.78 / qntl

S.N. PARTICULARS

1 Constt. Of Class room at High School Barsoodi as per detailed estimate


Rs

Total Rs
/ qntl
/ qntl Say Rs
/ qntl
Sanctioned Rs

/ sqm

J.E.,R.E.S. B.D.O.

/ sqm
/ sqm
/ sqm
Name of work :- Constt. Of Add.room at G.I.C. Kaindul Thangar.
Name of work :- Constt. Of Bahu Uddesheeya Bhawan at Khamana .

BILL OF QUANTITY

S.N. ITEM OF WORK QNTTY. UNIT RATE AMOUNT

1 E/W in excavation in foundation in all


types of soil i/c supply of all. 13.19 cum 32.00 422.08
2 C.C.(1:6:12) in cement,sand and 40 mm.
stone ballast i/c supply of all. 2.19 cum 2457.00 5380.83
3 R/R stone masonry in 1:6 cement and
sand mortor in foundation i/c supply of all. 13.38 cum 1687.00 22572.06
4 R.C.C.(1:2:4) in plinth and lintel band
i/c supply of all. 2.11 cum 4401.00 9286.11
5 Brick masonry in 1:6 cement and sand
mortor in super structure i/c all. 13.71 cum 2896.00 39704.16
6 S/F of Angle iron chaukhat for door with
iron shutter i/c supply of all.(1.00x2.00M) 2 nos 2500.00 5000.00
7 S/F of Angle iron chaukhat for window with
fixed grills and iron shutter i/c supply of all. 5 nos 2500.00 12500.00

8 S/F of Angle iron vent. i/c all. 4 nos 250.00 1000.00


9 R.C.C.(1:2:4) in beam columns i/c supply
of all for comp of work. 0.73 cum 5636.00 4114.28
10 R.C.C.(1:2:4) in slab including supply
of all for comp of work. 4.82 cum 4754.00 22914.28
11 M.S.Iron work in reinforcement i/c supply
of all for comp of work. 7.51 qntl 4901.00 36806.51
12 12 mm. thick plaster in (1:6) cement
and sand mortor i/c supply of all. 143.78 sqm 89.00 12796.42

13 E/B filling in plinth i/c all for comp. 8.85 cum 35.00 309.75
14 2.5 cm thick C.C.(1:2:4) over 7.5cm thick
C.C.(1:6:12) in floor i/c supply of all. 29.5 sqm 325.00 9587.50

15 White washing in three coat i/c supply of all. 173.28 sqm 2.00 346.56
16 Painting two coat over one priming coat
i/c supply of all. 19.88 sqm 50.00 994.00

17 Making sign board etc. 1 Job 1000.00 1000.00

Total Rs 184734.54
J.E.,R.E.S. B.D.O.

Name of work :- Constt. Of Bahu Uddesheeya Bhawan at Khamana .

SUMMARY OF ESTIMATED COST

S.N. PARTICULARS AMOUNT

1 Constt. Of Bahu Uddesheeya Bhawan as per detailed estimate


Rs 184734.54

Total Rs 184734.54

Say Rs 1,50,000.00

Sanctioned Rs 1,50,000.00

J.E.,R.E.S. B.D.O.
Name of work :- Constt. Of Barat Ghar at Nadda .

BILL OF QUANTITY

S.N. ITEM OF WORK QNTTY. UNIT RATE AMOUNT

1 E/W in excavation in foundation in all


types of soil i/c supply of all. 11.21 cum 32.00 358.72
2 C.C.(1:6:12) in cement,sand and 40 mm.
stone ballast i/c supply of all. 1.86 cum 2457.00 4570.02
3 R/R stone masonry in 1:6 cement and
sand mortor in foundation i/c supply of all. 7.84 cum 1687.00 13226.08
4 R.C.C.(1:2:4) in plinth and lintel band
i/c supply of all. 1.69 cum 4401.00 7437.69
5 Brick masonry in 1:6 cement and sand
mortor in super structure i/c all. 12.99 cum 2896.00 37619.04
6 S/F of Angle iron chaukhat for door with
iron shutter i/c supply of all.(1.00x2.00M) 2 nos 2500.00 5000.00
7 S/F of Angle iron chaukhat for window with
fixed grills and iron shutter i/c supply of all. 4 nos 2500.00 10000.00
8 R.C.C.(1:2:4) in beam columns i/c supply
of all for comp of work. 0.73 cum 5636.00 4114.28
9 R.C.C.(1:2:4) in slab including supply
of all for comp of work. 5.13 cum 4754.00 24388.02
10 M.S.Iron work in reinforcement i/c supply
of all for comp of work. 7.40 qntl 4901.00 36267.40
11 12 mm. thick plaster in (1:6) cement
and sand mortor i/c supply of all. 138.00 sqm 89.00 12282.00

12 E/B filling in plinth i/c all for comp. 10.50 cum 35.00 367.50
13 2.5 cm thick C.C.(1:2:4) over 7.5cm thick
C.C.(1:6:12) in floor i/c supply of all. 35.00 sqm 325.00 11375.00

14 White washing in three coat i/c supply of all. 173.00 sqm 2.00 346.00
15 Painting two coat over one priming coat
i/c supply of all. 16.64 sqm 50.00 832.00
16 R/R dry wall in R/W and B/W i/c supply
of all for comp of work. 5.40 cum 761.00 4109.4

17 Making sign board etc. 1 Job 1000.00 1000.00

Total Rs 173293.15
J.E.,R.E.S. B.D.O.

Name of work :- Constt. Of Barat Ghar at Nadda .

SUMMARY OF ESTIMATED COST

S.N. PARTICULARS AMOUNT

1 Constt. Of Barat Ghar at Nadda as per detailed estimate


Rs 173293.15

Total Rs 173293.15

Say Rs 1,40,000.00

Sanctioned Rs 1,40,000.00

J.E.,R.E.S. B.D.O.

14 S/F of Angel iron door / window


choukhat Frame including
cutting welding s/o all material
labour labour T&P etc
D 3 5.40 16.20
D1 4 4.95 19.80
W 12 4.20 50.40
V 2 2.10 4.20
C/S/D 1 8.40 8.40
S/W 1 5.40 5.40
H.F.D 82 0.30 24.60
Total 129.00
wt 129.00 x 3.00 387.00
For Grill 10mm Dai squar 108 1.20 129.60
132 0.90 129.60
24 1.80 43.20
18 2.40 43.20
9 1.80 16.20
18 0.90 16.20
Total 378.00
Wt 378.00 x0.78 kg/R.m 294.84
18mm Gauge B.C.G.I sheet shutter
3 1.2 2.1 7.56
4 0.75 2.1 6.30
Total 13.86
ZZ.k dk;Z A 387.00 +294.84+135.82 Total 8.17
1- Name of work-- Construction of Barat Ghar at Village Kotnalee.
2- Scheme-- Special Componenet plan
3- Block-- RikhaniKhal
AMOUNT

Abstract of Cost
### S.N Item of work Qty unit Rate Amount
1 Excavation in foundation
### in all Type of soil-------E/I 69.37 Cum 32.00 2219.76

### 2 Laying C.C. 1:6:12 in base con


crete including s/o all Material
### Labour T&P etc-- 8.56 Cum 2457.00 21034.99

### 3 R.R. stone masonry 1:6


cement sand mortar in foun
### dation including s/o all materi
al labour T&P etc--- work. 32.07 Cum 1687.00 54100.40
###

4 R.C.C. work 1:2:4 in plinth


### bends including s/o all mater
ial labour T&P etc---work. 3.52 Cum 4401.00 15511.41
###
10 M.S.Iron work in reinforcement i/c supply
of all for comp of work. 15.56 qntl 4901.00 76259.56
11 12 mm. thick plaster in (1:6) cement
and sand mortor i/c supply of all. 208.26 sqm 89.00 18535.14

12 E/B filling in plinth i/c all for comp. 20.27 cum 35.00 709.45
13 2.5 cm thick C.C.(1:2:4) over 7.5cm thick
C.C.(1:6:12) in floor i/c supply of all. 85.04 sqm 325.00 27638.00

14 White washing in three coat i/c supply of all. 289.66 sqm 2.00 579.32
Painting two coat over one priming coat
i/c supply of all. 24.64 sqm 50.00 1232.00
16 Making sign board etc. 1 Job 1000.00 1000.00
Total Rs 217588.04

J.E.,R.E.S. B.D.O.

dk;Z dk uke%&m0ek0fo0cjlwM+h esa d{kksa dk fuekZZ.k dk;Z A


SUMMARY OF ESTIMATED COST
base concrete including s/o
AMOUNT all material labour T&P -- 154.28 Sqm 325.00 50142.17

13 white washing 3coat with one


coat of primer-------- work. 428.86 Sqm 2.00 857.72
###
14 S/F of Angel iron door / window
choukhat Frame including
### cutting welding s/o all material
labour labour T&P etc 8.17 Qtl 5322.00 43480.74
3,00,000.00 Total Rs 348378.33

3,00,000.00
BILL OF QUANTITY

S.N. ITEM OF WORK QNTTY. UNIT RATE AMOUNT

1 E/W in excavation in foundation in all


types of soil i/c supply of all. 11.43 cum 32.00 365.76
2 C.C.(1:6:12) in cement,sand and 40 mm.
stone ballast i/c supply of all. 1.90 cum 2457.00 4668.30
3 R/R stone masonry in 1:6 cement and
sand mortor in foundation i/c supply of all. 6.93 cum 1687.00 11690.91
4 R.C.C.(1:2:4) in plinth and lintel band
i/c supply of all. 1.17 cum 4401.00 5149.17
5 Brick masonry in 1:6 cement and sand
mortor in super structure i/c all. 9.96 cum 2896.00 28844.16
6 S/F of Angle iron chaukhat for door with
iron shutter i/c supply of all.(1.00x2.00M) 2 nos 2500.00 5000.00
7 S/F of Angle iron chaukhat for window with
fixed grills and iron shutter i/c supply of all. 2 nos 3500.00 7000.00
(1.50x1.20M)
8 S/F of Angle iron vent. i/c all.(1.00x0.60M) 2 nos 500.00 1000.00
9 R.C.C.(1:2:4) in beam columns i/c supply
of all for comp of work. 0.81 cum 5636.00 4565.16
10 R.C.C.(1:2:4) in slab including supply
of all for comp of work. 4.99 cum 4754.00 23722.46
11 M.S.Iron work in reinforcement i/c supply
of all for comp of work. 6.83 qntl 4901.00 33473.83
12 12 mm. thick plaster in (1:6) cement
and sand mortor i/c supply of all. 103.20 sqm 89.00 9184.80

13 E/B filling in plinth i/c all for comp. 9.90 cum 35.00 346.50
14 2.5 cm thick C.C.(1:2:4) over 7.5cm thick
C.C.(1:6:12) in floor i/c supply of all. 41.50 sqm 325.00 13487.50

15 White washing in three coat i/c supply of all. 144.70 sqm 2.00 289.40
16 Painting two coat over one priming coat
i/c supply of all. 22.50 sqm 50.00 1125.00

17 R/R dry walls in R/W,B/W i/c all . 9.00 cum 761.00 6849

18 Making sign board etc. 1 Job 1000.00 1000.00

Total Rs 157761.95

J.E.,R.E.S. B.D.O.

Name of work :- Constt. Of Add.room at G.I.C. Kaindul Thangar.

SUMMARY OF ESTIMATED COST

S.N. PARTICULARS AMOUNT

1 Constt. Of Add.room at G.I.C. Kaindul Thangar as per detailed estimate


Rs 157761.95

Total Rs 157761.95

Say Rs 1,40,000.00

Sanctioned Rs 1,40,000.00

J.E.,R.E.S. B.D.O.
Name of work :- Beautification of Balkunwari Tok at village Khand .

BILL OF QUANTITY

S.N. ITEM OF WORK QNTTY. UNIT RATE AMOUNT

1 E/W in excavation in foundation in all


types of soil i/c supply of all. 4.70 cum 32.00 150.40
2 C.C.(1:6:12) in cement,sand and 40 mm.
stone ballast i/c supply of all. 0.74 cum 2457.00 1818.18
3 R/R stone masonry in 1:6 cement and
sand mortor in foundation i/c supply of all. 4.99 cum 1687.00 8418.13
4 Brick masonry in 1:6 cement and sand
mortor in super structure i/c all. 4.14 cum 2896.00 11989.44
5 R.C.C.(1:2:4) in beam columns i/c supply
of all for comp of work. 3.11 cum 5636.00 17527.96
6 R.C.C.(1:2:4) in slab including supply
of all for comp of work. 3.24 cum 4754.00 15402.96
7 M.S.Iron work in reinforcement i/c supply
of all for comp of work. 6.23 qntl 4901.00 30533.23
8 12 mm. thick plaster in (1:6) cement
and sand mortor i/c supply of all. 52.92 sqm 89.00 4709.88
9 2.5 cm thick C.C.(1:2:4) over 7.5cm thick
C.C.(1:6:12) in floor i/c supply of all. 22.99 sqm 325.00 7471.75

10 S/F of M.S. iron gate i/c supply of all . 1 No. L.S. 1000.00
11 White washing in three coat and
painting two coat over one priming coat
i/c supply of all. 1 Job L.S. 1000.00

12 R/R dry walls in R/W,B/W i/c all . 5.40 cum 761.00 4109.40

13 Making sign board etc. 1 Job 1000.00 1000.00

Total Rs 105131.33

J.E.,R.E.S. B.D.O.

Name of work :- Beautification of Balkunwari Tok at village Khand .

SUMMARY OF ESTIMATED COST

S.N. PARTICULARS AMOUNT

1 Beautification of Balkunwari Tok at Khand as per detailed estimate.


Rs 105131.33

Total Rs 105131.33

Say Rs 1,00,000.00

Sanctioned Rs 1,00,000.00

J.E.,R.E.S. B.D.O.
Name of work :- Constt. Of Laboratory at Govt. Inter College
Mahadev Chatti .
BILL OF QUANTITY

S.N. ITEM OF WORK QNTTY. UNIT RATE AMOUNT

1 E/W in excavation in foundation in all


types of soil i/c supply of all. 49.12 cum 32.00 1571.84
2 C.C.(1:6:12) in cement,sand and 40 mm.
stone ballast i/c supply of all. 8.17 cum 2457.00 20073.69
3 R/R stone masonry in 1:6 cement and
sand mortor in foundation i/c supply of all. 40.02 cum 1687.00 67513.74
4 R.C.C.(1:2:4) in plinth and lintel band
i/c supply of all. 4.61 cum 4401.00 20288.61
5 Brick masonry in 1:6 cement and sand
mortor in super structure i/c all. 36.9 cum 2896.00 106862.40
6 Mild steel or iron work such as in door,
window chaukhats, grills i/c supply of all . 3.30 qntl 5322.00 17562.60
7 R.C.C.(1:2:4) in beam columns i/c supply
of all for comp of work. 2.89 cum 5636.00 16288.04
8 R.C.C.(1:2:4) in slab including supply
of all for comp of work. 18.66 cum 4754.00 88709.64
9 M.S.Iron work in reinforcement i/c supply
of all for comp of work. 25.66 qntl 4901.00 125759.66
10 12 mm. thick plaster in (1:6) cement
and sand mortor i/c supply of all. 373.86 sqm 89.00 33273.54
11 E/B filling in plinth i/c all for comp. 27.99 cum 35.00 979.65
12 2.5 cm thick C.C.(1:2:4) over 7.5cm thick
C.C.(1:6:12) in floor i/c supply of all. 113.19 sqm 325.00 36786.75
13 2.5 cm thick P.C.C (1:2:4) in sills of door
and window i/c all. 6.12 129.00 789.48
14 35 mm thick sal and sheesham wood fully
panelled doors and window shutters i/c all . 15.69 1399.00 21950.31

15 S/F of oxidized iron fittings i/c all . 15.69 100.00 1569.00

16 White washing in three coat i/c supply of all. 487.05 sqm 2.00 974.10
17 Painting two coat over one priming coat
i/c supply of all. 45.15 sqm 50.00 2257.50
18 R/R dry wall in R/W, B/W i/c all . 10.20 761.00 7762.20
19 R/R (1:6) cement $ sand in R/W, B/W i/c all 10.20 1459.00 14881.80
20 Internal electrification of building i/c all . 1 Job 10000 10000.00
21 Making sign board etc. 1 Job 1000.00 1000.00

Total Rs 596854.55

J.E.,R.E.S. B.D.O.

Name of work :- Constt. Of Laboratory at Govt. Inter College


Mahadev Chatti .
SUMMARY OF ESTIMATED COST

S.N. PARTICULARS AMOUNT

1 Constt. Of Laboratory as per detailed estimate


Rs 596854.55

Total Rs 596854.55

Say Rs 5,45,000.00

Sanctioned Rs 5,45,000.00

J.E.,R.E.S. B.D.O.
1- Name of work-- Construction of Barat Ghar at Village Kotnalee.
2- Scheme-- Special Componenet plan
3- Block-- RikhaniKhal

Detail of Measurement
S.N Item of work No L B H/d Qty Unit
1 Excavation in foundation
in all Type of soil-------E/I
L/W 2 6.98 0.75 0.90 9.42 Cum
1 3.52 0.75 0.90 2.38 Cum
2 5.48 0.75 0.90 7.40 Cum
1 5.94 0.75 0.90 4.01 Cum
S/W 2 3.98 0.75 0.90 5.37 Cum
2 3.08 0.75 0.90 4.16 Cum
2 3.48 0.75 0.90 4.70 Cum
2 7.48 0.75 0.90 10.10 Cum
2 1.77 0.75 0.90 2.39 Cum
1 2.14 0.75 0.90 1.44 Cum
S/T 1 3.00 3.00 2.00 18.00 Cum
Total 69.37 Cum
2 Laying C.C. 1:6:12 in base con
crete including s/o all Material
Labour T&P etc-- 2 6.98 0.75 0.15 1.57 Cum
1 3.52 0.75 0.15 0.40 Cum
2 5.48 0.75 0.15 1.23 Cum
1 5.94 0.75 0.15 0.67 Cum
2 3.98 0.75 0.15 0.90 Cum
2 3.08 0.75 0.15 0.69 Cum
2 3.48 0.75 0.15 0.78 Cum
2 7.48 0.75 0.15 1.68 Cum
2 1.77 0.75 0.15 0.40 Cum
1 2.14 0.75 0.15 0.24 Cum
Total 8.56 Cum
3 R.R. stone masonry 1:6
cement sand mortar in foun
dation including s/o all materi
al labour T&P etc--- work.
2 6.88 0.65 0.30 2.68 Cum
1 3.42 0.65 0.30 0.67 Cum
2 5.38 0.65 0.30 2.10 Cum
1 5.84 0.65 0.30 1.14 Cum
2 3.88 0.65 0.30 1.51 Cum
2 3.18 0.65 0.30 1.24 Cum
2 3.58 0.65 0.30 1.40 Cum
2 7.58 0.65 0.30 2.96 Cum
2 1.87 0.65 0.30 0.73 Cum
1 2.24 0.65 0.30 0.44 Cum
1 3.72 0.65 0.45 1.09 Cum
Total 15.95 Cum

B.F 15.95 Cum


2 5.18 0.45 0.60 2.80 Cum
1 5.64 0.45 0.60 1.52 Cum
2 3.68 0.45 0.60 1.99 Cum
2 3.38 0.45 0.60 1.83 Cum
2 3.78 0.45 0.60 2.04 Cum
2 7.78 0.45 0.60 4.20 Cum
2 2.01 0.45 0.60 1.09 Cum
1 2.44 0.45 0.60 0.66 Cum
Total 32.07 Cum
4 R.C.C. work 1:2:4 in plinth
bends including s/o all mater
ial labour T&P etc---work. 4 6.46 0.23 0.10 0.59 Cum
2 3.00 0.23 0.10 0.14 Cum
4 4.96 0.23 0.10 0.46 Cum

2 5.42 0.23 0.10 0.25 Cum


4 3.46 0.23 0.10 0.32 Cum
4 3.60 0.23 0.10 0.33 Cum
4 4.00 0.23 0.10 0.37 Cum
4 8.00 0.23 0.10 0.74 Cum
4 2.29 0.23 0.10 0.21 Cum
2 2.66 0.23 0.10 0.12 Cum
Total 3.52 Cum
5 M100 B/W 1:6 cement sand
Mortar in supper structure
including s/o all material
Labour T&P etc--- work.
2 6.46 0.23 3.20 9.51 Cum
1 3.00 0.23 3.00 2.07 Cum
2 4.96 0.23 3.20 7.30 Cum
2 3.46 0.23 3.00 4.77 Cum
2 3.60 0.23 3.20 5.30 Cum
2 4.00 0.23 3.00 5.52 Cum
2 8.00 0.23 3.20 11.78 Cum
2 2.29 0.23 3.00 3.16 Cum
1 2.66 0.23 3.00 1.84 Cum
3 1.20 0.23 2.10 1.74 Cum
4 0.75 0.23 2.10 1.45 Cum
Total 54.43 Cum

Deduction opening 1 1.80 0.23 2.40 0.99 Cum


1 0.90 0.23 1.80 0.37 Cum
12 0.90 0.23 1.20 2.98 Cum
Total 4.35 Cum
Net Qty 54.43 -4.35 50.08 Cum

6 R.C.C. work 1:2:4 for Coulms


including C/S s/o all material
labour T&P etc---- work. 8 0.23 0.35 4.20 2.70 Cum

7 R.C.C. work 1:2:4 for Beams


including C/S s/o all material
labour T&P etc---- work. 1 4.06 0.23 0.30 0.28 Cum
2 4.96 0.23 0.30 0.68 Cum
1 3.46 0.23 0.30 0.24 Cum
Total 1.20 Cum
8 R.C.C. work 1:2:4 for Slab
including C/S s/o all material
labour T&P etc---- work. 1 8.30 3.46 0.10 2.87 Cum
1 7.10 4.66 0.10 3.31 Cum
1 9.10 5.56 0.10 5.06 Cum
12 1.10 0.45 0.06 0.36 Cum
Total 11.60 Cum
9 M.S. iron work such as reinfor
cement 1/c supply all material
labour T&P wastages
R.C.C. qty ( 3.52+2.70+1.20+11.60) x 78.50 x1.25
100 18.66 Qtl
10 12mm thick plaster 1:6 cement
sand mortar in wall including
s/o all material labour T&P--
2 6.00 3.20 38.40 Sqm
2 3.60 3.20 23.04 Sqm
2 4.00 3.00 24.00 Sqm
2 8.00 3.20 51.20 Sqm
2 4.50 3.20 28.80 Sqm
4 0.90 2.40 8.64 Sqm
4 1.20 2.40 11.52 Sqm
4 0.90 2.40 8.64 Sqm
4 1.20 2.40 11.52 Sqm
2 6.23 4.05 50.46 Sqm
2 4.06 4.05 32.89 Sqm
1 3.23 3.00 9.69 Sqm
2 8.46 4.05 34.26 Sqm
2 4.96 4.05 40.18 Sqm
2 0.90 3.00 5.40 Sqm
1 3.46 3.00 10.38 Sqm
1 6.00 3.20 19.20 Sqm
1 8.00 4.50 36.00 Sqm
1 4.00 3.00 12.00 Sqm
Total 456.22 Sqm
Deduction D 3 1.20 2.10 7.56 Sqm
D1 4 0.75 2.10 6.30 Sqm
W 12 0.90 1.20 12.96 Sqm
V 2 0.60 0.45 0.54 Sqm
Total 27.36 Sqm
Net Qty 456.22 -27.36 428.86 Sqm
11 Earth & Boulder Filling under
Floor --------- work. 1 6.00 3.60 0.45 9.72 Cum
1 4.00 3.00 0.45 5.40 Cum
1 8.00 4.50 0.45 16.20 Cum
4 0.90 1.20 0.45 1.94 Cum
1 0.90 1.00 0.45 0.41 Cum
2 15.00 2.50 0.45 33.75 Cum
2 10.50 3.00 0.45 28.35 Cum
Total 95.77 Cum
12 2.50 cm thick C.C floor 1:2:4
over 7.50 cm thick C.C. 1:6:12
base concrete including s/o
all material labour T&P -- 1 6.00 3.60 21.60 Sqm
1 4.00 3.00 12.00 Sqm
1 8.00 4.50 36.00 Sqm
4 0.90 1.20 4.32 Sqm
1 0.90 1.00 0.90 Sqm
1 9.46 2.66 25.16 Sqm
2 22.00 0.45 19.80 Sqm
1 15.00 0.90 13.50 Sqm
2 10.50 1.00 21.00 Sqm
Total 154.28 Sqm
13 white washing 3coat with one
coat of primer-------- work. Same as item no 10 428.86 Sqm

R.M
R.M
R.M
R.M
R.M
R.M
R.M
R.M
Kg
R.M
R.M
R.M
R.M
R.M
R.M
R.M
Kg

Sqm
Sqm
Sqm
Qtl

mount

5 M100 B/W 1:6 cement sand


Mortar in supper structure
including s/o all material
Labour T&P etc--- work. 50.08 Cum 2896.00 145031.68

6 R.C.C. work 1:2:4 for Coulms


including C/S s/o all material
labour T&P etc---- work. 2.70 Cum 5636.00 15244.25

7 R.C.C. work 1:2:4 for Beams


including C/S s/o all material
labour T&P etc---- work. 1.20 CUM 5636.00 6782.14
8 R.C.C. work 1:2:4 for Slab
including C/S s/o all material
labour T&P etc---- work. 11.60 Cum 4754.00 55129.29

9 M.S. iron work such as reinfor


cement 1/c supply all material
labour T&P wastages 18.66 Qtl 4901.00 91452.66

10 12mm thick plaster 1:6 cement


sand mortar in wall including
s/o all material labour T&P-- 428.86 Sqm 89.00 38168.54

11 Earth & Boulder Filling under


Floor --------- work. 95.77 Cum 35.00 3351.92
dk;Z A
12 2.50 cm thick C.C floor 1:2:4
over 7.50 cm thick C.C. 1:6:12
1- Name of work-- Construction of Barat Ghar at Village Kotnalee.
2- Scheme--Special Componenet plan
3- Block-- RikhaniKhal

Summary of Cost
S.N Sub Head Amount
1 Estimate for the Construction of Barat Ghar
at Village Kotanalee as per Detail Estimate
Rs 5,41,140.01
Say Rs Rs 5,41,000-00
Name of work :- Constt. Of Panchayati Angan at Dunwa
Gram Sabha Haja .
LEAD STATEMENT

S.N. MATERIALS SOURCE BY MOTOR ROAD BY MULE TOTAL DISTANCE

1 Cement V.Nagar 55 Km 0.5 55.5 Km

2 Course Sand River 50 Km 0.5 50.5 Km

3 Fine Sand River 50 Km 0.5 50.5 Km

4 20 mm S/B Local 0 Km 2.5 2.5 Km

5 40 mm S/B Local 0 Km 2.5 2.5 Km

6 Stone Local 0 Km 2 2 Km

J.E.,R.E.S. B.D.O.
Name of work :- Constt. Of Panchayati Angan at Dunwa
Gram Sabha Haja .
CARTAGE OF MATERIALS

1- CEMENT :- Cartage by motor road = 55 Km


1st to 5 Km as per schedule = 68.60 per MT
6th 10th Km 5 Km @ 5.25 = 26.25 per MT
11th to 20th Km 10 Km @ 4.00 = 40.00 per MT
21th to 30th Km 10 Km @ 3.30 = 33.00 per MT
31th to 40th Km 10 Km @ 3.00 = 30.00 per MT
41th to 50th Km 10 Km @ 2.80 = 28.00 per MT
Beyond 50 Km 5 Km @ 2.25 = 11.25 per MT
Cartage by mule = 0.5 Km
Up to 1/2 Km 0.5 Km @ 100.00 Per 1/2 Km 100.00 per MT
Beyond1/2Km 0 Km @ 40.00 Per 1/2 Km 0.00 per MT
Stacking charge = 13.00 per MT
Total Rs 350.10 Per MT
Or Rs 17.51 Per Bag
Less 10% C.P. (-) 1.7505 Per Bag
Net Rs 15.75 Per Bag
Say Rs 16.00 Per Bag

2- Sand :- Cartage by motor road = 50 Km


1st to 5 Km as per schedule = 88.00 Per cum
6th 10th Km 5 Km @ 7.00 = 35.00 Per cum
11th to 20th Km 10 Km @ 5.40 = 54.00 Per cum
21th to 30th Km 10 Km @ 4.70 = 47.00 Per cum
31th to 40th Km 10 Km @ 4.00 = 40.00 Per cum
41th to 50th Km 10 Km @ 4.00 = 40.00 Per cum
0 Km @ 3.50 = 0.00 Per cum
Cartage by mule = 0.5 Km
Up to 1/2 Km 0.5 Km @ 10.00 Per 1/2 Km 160.00 Per cum
Beyond1/2Km 0 Km @ 4.00 Per 1/2 Km 0.00 Per cum
Stacking charge = 13.00 Per cum
Total Rs 477.00 Per cum
Less 10% C.P. (-) 47.7 Per cum
Net Rs 429.30 Per cum
Say Rs 429.00 Per cum

J.E.,R.E.S. B.D.O.
Name of work :- Constt. Of Panchayati Angan at Dunwa
Gram Sabha Haja .
3- Stone ballast : -
Cartage by mule = 2.5 Km
Up to 1/2 Km 0.5 Km @ 10.00 Per 1/2 Km 160.00 Per cum
Beyond1/2Km 2 Km @ 4.00 Per 1/2 Km 256.00 Per cum
Stacking charge = 13.00 Per cum
Total Rs 429.00 Per cum
Less 10% C.P. (-) 42.90 Per cum
Net Rs 386.10 Per cum
Say Rs 386.00 Per cum
4- Stone :-
Cartage by mule = 2 Km
Up to 1/2 Km 0.5 Km @ 10.00 Per 1/2 Km 200.00 Per cum
Beyond1/2Km 1.5 Km @ 4.00 Per 1/2 Km 240.00 Per cum
Stacking charge = 13.00 Per cum
Total Rs 453.00 Per cum
Less 10% C.P. (-) 45.3 Per cum
Net Rs 407.70 Per cum
Say Rs 408.00 Per cum

COST OF MATERIAL AT SITE

S.N. MATERIAL S.I.NO. RATE CARTAGE TOTAL COST

1 Cement 9. 230.00 16.00 246.00 Per Bag

2 20mm S/B 2(a) 450.00 386.00 836.00 Per cum

3 40mm S/B 2© 360.00 386.00 746.00 Per cum

4 Course Sand 38- 330.00 429.00 759.00 Per cum

5 Fine Sand 39- 300.00 429.00 729.00 Per cum

6 Stone 41(b) 0.00 408.00 408.00 Per cum

J.E.,R.E.S. B.D.O.
Name of work :- Constt. Of Panchayati Angan at Dunwa
Gram Sabha Haja .
ANALYSIS OF RATE

1- R/R dry walls in R/W,B/W and Kharinja i/c all for comp of work .
Rate as per S.I.No. 518 = Rs 200.00 Per cum
Less 10% C.P. Rs 20.00 Per cum
Net Rs 180.00 Per cum
Add cartage of stone Rs 408.00 Per cum
Total Rs 588.00 Per cum
Say Rs 588.00 Per cum
2- R/R stone masonry in 1:6 cement and sand mortor in R/W and B/W i/c supply of all.
Rate as per S.I.No. 516 = Rs 280.00 Per cum
Less 10% C.P. Rs 28.00 Per cum
Net Rs 252.00 Per cum
Add cartage of stone Rs 408.00 Per cum
Cost of cement 1.41 bag @ 246.00 / bag =Rs 346.86 Per cum
Fine Sand 0.30 cum @ 729.00 / cum =Rs 218.70 Per cum
Total Rs 1225.56 Per cum
Say Rs 1226.00 Per cum

3- Laying of C.C. road slab (1:2:4) in cement, sand and 40mm S/B i/c all .

Rate as per schedule = Rs 2650.00 /cum


Add cartage of cement 6.62 bag @Rs 16.00 /bag = Rs 105.92 /cum
Add difference in cost of cement (230.00 -180.00 = Rs 50.00)
6.62 bag @Rs 50.00 /bag = Rs 331.00 /cum
Add difference in cost of sand (330.00 -300.00 = Rs 30.00)
0.45 cum @Rs 30.00 /cum = Rs 13.50 /cum
Add difference in cost of S/B (360.00 -290.00 = Rs 70.00)
0.90 cum @Rs 70.00 /cum = Rs 63.00 /cum

Total Rs 3163.42 /cum

Say Rs 3163.00 /cum

4- Excavation in foundation in R/W and B/W including supply of all


for completion of work.
Rate as per S.I. No. 165 (b) = Rs 26.00 / cum
Less 10 % C.P.of 26.00 2.60 / cum
Net Rs 23.40 / cum
Say Rs 23.00 / cum
5- E/W in cutting in soil with earth mixed boulders including supply of all .
Rate as per S.I. No. 157 = Rs 20.00 / cum
Less 10 % C.P.of 20.00 2.00 / cum
Net Rs 18.00 / cum
Say Rs 18.00 / cum

J.E.,R.E.S. B.D.O.

Name of work :- Constt. Of Panchayati Angan at Dunwa


Gram Sabha Haja .

DETAILS OF MEASUREMENT

S.N. ITEM OF WORK NO. L. B. H/D QNTTY.


1 R/R dry walls in R/W,
B/W and Kharinja i/c all.
R/W - 1 5.00 0.60 0.60 1.80
Kharinja- 6 20.00 1.00 0.15 18.00
Total 19.80
2 Laying of C.C. road
slab(1:2:4) i/c supply of
all for comp. of work .
5 20.00 1.00 0.10 10.00
1 12.00 1.00 0.10 1.20
Total 11.20
3 Making sign board . - - - L.S. 1 Job

BILL OF QUANTITY

S.N. ITEM OF WORK QNTTY. UNIT RATE AMOUNT


1 R/R dry walls in R/W,
B/W and Kharinja i/c all. 19.80 cum 588.00 11642.40

2 Laying of C.C. road


slab(1:2:4) i/c supply of
all for comp. of work . 11.20 cum 3163.00 35425.60

3 Making sign board . 1 Job L.S. 1000.00

Total Rs 48068.00
Say Rs 48068.00

J.E.,R.E.S. B.D.O.
Name of work :- Constt. Of Panchayati Angan at Dunwa
Gram Sabha Haja .

SUMMARY OF ESTIMATED COST

S.N PARTICULARS AMOUNT

1 Constt. Of C.C. road as per detailed estimate Rs 48068.00

Total Rs 48068.00

Say Rs 50000.00

Sanctioned Rs 50000.00

J.E.,R.E.S. B.D.O.
Name of work :- Constt. Of Panchayati Angan at Dunwa
Gram Sabha Haja .

DETAILS OF MEASUREMENT

S.N. ITEM OF WORK NO. L. B. H/D QNTTY.


1 R/R dry walls in R/W,
B/W and Kharinja i/c all.
Kharinja- 5 15.00 1.00 0.15 11.25
Total 11.25
2 Laying of C.C. road
slab(1:2:4) i/c supply of
all for comp. of work .
5 15.00 1.00 0.10 7.50
Total 7.50
3 Making sign board . - - - L.S. 1 Job

BILL OF QUANTITY

S.N. ITEM OF WORK QNTTY. UNIT RATE AMOUNT


1 R/R dry walls in R/W,
B/W and Kharinja i/c all. 11.25 cum 588.00 6615.00

2 Laying of C.C. road


slab(1:2:4) i/c supply of
all for comp. of work . 7.50 cum 3163.00 23722.50

3 Making sign board . 1 Job L.S. 1000.00

Total Rs 31337.50
J.E.,R.E.S. B.D.O.

Name of work :- Constt. Of Panchayati Angan at Dunwa


Gram Sabha Haja .

SUMMARY OF ESTIMATED COST

S.N PARTICULARS AMOUNT

1 Constt. Of C.C. road as per detailed estimate Rs 31337.50

Total Rs 31337.50

Say Rs 35000.00

Sanctioned Rs 35000.00

J.E.,R.E.S. B.D.O.
Name of work :- Constt. Of Panchayati Angan at Dunwa
Gram Sabha Haja .

DETAILS OF MEASUREMENT

S.N. ITEM OF WORK NO. L. B. H/D QNTTY.


1 E/W in cutting in soil with
earth mixed boulders
i/c supply of all .
In Angan 1 5.00 4.00 0.30 6.00
2 E/W in excavation in Total 6.00 cum
foundation in R/W, B/W
i/c supply of all.
In Parapet - 2 5.00 0.45 0.30 1.35
3 R/R stone masonry Total 1.35 cum
in 1:6 cement and sand
mortor in R/W,B/W i/c all.
In Parapet - 2 5.00 0.45 0.45 2.03
R/W - 1 3.00 0.45 0.60 0.81
4 R/R dry walls in R/W, Total 2.84 cum
B/W and Kharinja i/c all.
Making sign board .
In Kharinja - 1 6.00 5.00 0.15 4.50
5 Laying of C.C. road Total 4.50 cum
slab(1:2:4) i/c supply of
all for comp. of work .
In Angan 1 10.00 8.00 0.10 8.00
Total 8.00 cum
J.E.,R.E.S. B.D.O.

Name of work :- Constt. Of Panchayati Angan at Dunwa


Gram Sabha Haja .
BILL OF QUANTITY

S.N. ITEM OF WORK QNTTY. UNIT RATE AMOUNT


1 E/W in cutting in soil with
earth mixed boulders
i/c supply of all . 6.00 cum 18.00 108.00

2 E/W in excavation in
foundation in R/W, B/W
i/c supply of all. 1.35 cum 23.00 31.05

3 R/R stone masonry


in 1:6 cement and sand
mortor in R/W,B/W i/c all. 2.84 cum 1226.00 3475.71

4 R/R dry walls in R/W,


B/W and Kharinja i/c all.
Making sign board . 4.50 cum 588.00 2646.00

5 Laying of C.C. road


slab(1:2:4) i/c supply of
all for comp. of work . 8.00 cum 3163.00 25304.00

Total Rs 31564.76
J.E.,R.E.S. B.D.O.

Name of work :- Constt. Of Panchayati Angan at Dunwa


Gram Sabha Haja .

SUMMARY OF ESTIMATED COST

S.N PARTICULARS AMOUNT

1 Constt. Of Panchayati Angan as per detailed estimate


Rs 31564.76
Total Rs 31564.76

Say Rs 32000.00

J.E.,R.E.S. B.D.O.
Name of work :- Constt. Of Hauj at Kheda Ghauna at village Haja.

LEAD STATEMENT

S.N. MATERIALS SOURCE BY MOTOR ROAD BY MULE TOTAL DISTANCE

1 Cement Vikas Nagar 55 Km 5 60 Km

2 Mild steel Vikas Nagar 55 Km 5 60 Km

3 Bricks Vikas Nagar 55 Km 5 60 Km

4 Course Sand Local 0 Km 5 5 Km

5 Fine Sand Local 0 Km 5 5 Km

6 20 mm S/B Local 0 Km 2 2 Km

7 40 mm S/B Local 0 Km 2 2 Km

8 Stone Local 0 Km 2 2 Km

J.E.,R.E.S. B.D.O.
Name of work :- Constt. Of Hauj at Kheda Ghauna at village Haja.

CARTAGE OF MATERIALS
1- CEMENT :- Cartage by motor road = 55 Km
1st to 5 Km as per schedule = = 68.60 per MT
6th 10th Km 5 Km @ 5.25 = 26.25 per MT
11th to 20th Km 10 Km @ 4.00 = 40.00 per MT
21th to 30th Km 10 Km @ 3.30 = 33.00 per MT
31th to 40th Km 10 Km @ 3.00 = 30.00 per MT
41th to 50th Km 10 Km @ 2.80 = 28.00 per MT
Beyond 50 Km 5 Km @ 2.25 = 11.25 per MT
Cartage by mule = 5 Km
Up to 1/2 Km 0.5 Km @ 100.00 Per 1/2 Km 100.00 per MT
Beyond1/2Km 4.5 Km @ 40.00 Per 1/2 Km 360.00 per MT
Stacking charge = 13.00 per MT
Total Rs 710.10 Per MT
Or Rs 35.51 Per Bag
Less 10 % C.P.of 35.51 3.5505 Per Bag
Net Rs 31.95 Per Bag
2- M.S.Tor Bar :- Say Rs 32.00 Per Bag
Cartage by motor road same as above Item no. 1 = Rs 237.10 per MT
Cartage by manual labour = 5 Km @Rs 300 per1/2 3000.00 per MT
Stacking charge = 13.00 per MT
Total Rs 3250.10 Per MT
Less 10 % C.P.of 3250.10 325.01 Per MT
Net Rs 2925.09 Per MT
Or Rs 292.51 Per qntl
Say Rs 293.00 Per qntl
3- Sand :- Cartage by motor road = 0 Km
1st to 5 Km as per schedule - - - - - - - = 0.00 Per cum
0 Km @ 7.00 = 0.00 Per cum
0 Km @ 5.40 = 0.00 Per cum
0 Km @ 4.70 = 0.00 Per cum
0 Km @ 4.00 = 0.00 Per cum
0 Km @ 4.00 = 0.00 Per cum
0 Km @ 3.50 = 0.00 Per cum
Cartage by mule = 5 Km
Up to 1/2 Km 0.5 Km @ 10.00 Per 1/2 Km 160.00 Per cum
Beyond1/2Km 4.5 Km @ 4.00 Per 1/2 Km 576.00 Per cum
Stacking charge = 13.00 Per cum
Total Rs 749.00 Per cum
Less 10 % C.P.of 749.00 74.9 Per cum
Net Rs 674.10 Per cum
Say Rs 674.00 Per cum

J.E.,R.E.S. B.D.O.
Name of work :- Constt. Of Hauj at Kheda Ghauna at village Haja.

4- Bricks :- Cartage by motor road = 55 Km


1st to 5 Km as per schedule = = 88.00 Per cum
6th 10th Km 5 Km @ 7.00 = 35.00 Per cum
11th to 20th Km 10 Km @ 5.40 = 54.00 Per cum
21th to 30th Km 10 Km @ 4.70 = 47.00 Per cum
31th to 40th Km 10 Km @ 4.00 = 40.00 Per cum
41th to 50th Km 10 Km @ 4.00 = 40.00 Per cum
Beyond 50 Km 5 Km @ 3.50 = 17.50 Per cum
Cartage by mule = 5 Km
Up to 1/2 Km 0.5 Km @ 10.00 Per 1/2 Km 160.00 Per cum
Beyond1/2Km 4.5 Km @ 4.00 Per 1/2 Km 576.00 Per cum
Stacking charge = 13.00 Per cum
Total Rs 1070.50 Per cum
Less 10 % C.P.of 1070.50 107.05 Per cum
Net Rs 963.45 Per cum
Say Rs 963.00 Per cum
For thousand nos of brick =2.40x 963.00 = Rs 2311.20 %0 nos
Say Rs 2311.00 %0 nos
5- Stone ballast : -
Cartage by mule = 2 Km
Up to 1/2 Km 0.5 Km @ 10.00 Per 1/2 Km 160.00 Per cum
Beyond1/2Km 1.5 Km @ 4.00 Per 1/2 Km 192.00 Per cum
Stacking charge = 13.00 Per cum
Total Rs 365.00 Per cum
Less 10 % C.P.of 365.00 36.50 Per cum
Net Rs 328.50 Per cum
Say Rs 329.00 Per cum
6- Stone :-
Cartage by mule = 2 Km
Up to 1/2 Km 0.5 Km @ 10.00 Per 1/2 Km 200.00 Per cum
Beyond1/2Km 1.5 Km @ 4.00 Per 1/2 Km 240.00 Per cum
Stacking charge = 13.00 Per cum
Total Rs 453.00 Per cum
Less 10 % C.P.of 453.00 45.30 Per cum
Net Rs 407.70 Per cum
Say Rs 408.00 Per cum

J.E.,R.E.S. B.D.O.
Name of work :- Constt. Of Hauj at Kheda Ghauna at village Haja.

COST OF MATERIAL AT SITE

S.N. MATERIAL S.I. NO. RATE CARTAGE TOTAL COST

1 Cement 9. 230.00 32.00 262.00

2 M.S. Tor Bar 20(b) 2650.00 293.00 2943.00

3 M.S.Angle, Flat Iron 20(a) 3300.00 293.00 3593.00

4 Bricks 1(a) 2450.00 2311.00 4761.00

5 20 mm stone ballast 2(a) 450.00 329.00 779.00

6 40 mm stone ballast 2© 360.00 329.00 689.00

7 Course Sand 38 . 330.00 674.00 1004.00

8 Fine Sand 39 . 300.00 674.00 974.00

9 Stone for building 41(a) 260.00 408.00 668.00

10 Stone for site development 41(b) 225.00 408.00 633.00

11 Paint As per market rate 180.00

12 Primer As per market rate 100.00

13 Snowsem As per market rate 35.00

14 Whiting As per market rate 5.00

15 Sal wood As per Van Nigam rate 30000.00


J.E.,R.E.S. B.D.O.
LABOUR RATE

S.N. LABOUR RATE

1 MISTRI 180.00 PER DAY

2 MASON 180.00 PER DAY

3 CARPENTER 180.00 PER DAY

4 BLACK SMITH 180.00 PER DAY

5 PAINTER 180.00 PER DAY

6 PLUMBER 180.00 PER DAY

7 BELDAR 100.00 PER DAY

8 COOLIE 100.00 PER DAY

9 CHAUKIDAR 100.00 PER DAY

10 BHISTI 100.00 PER DAY


11 HAMMER MAN 100.00 PER DAY
12 WHITE WASHER 120.00 PER DAY
13 HELPER 100.00 PER DAY
14 RIVETTOR 180.00 PER DAY
Name of work :- Constt. Of Hauj at Kheda Ghauna at village Haja.

ANALYSIS OF RATE

1- Excavation in foundation in all types of soil including supply of all


for completion of work.
Rate as per S.I. No. 165 (a) = Rs 35.00 / cum
Less 10 % C.P.of 35.00 3.50 / cum
Net Rs 31.50 / cum
Say Rs 32.00 / cum

2- C.C.(1:6:12) in foundation in cement, sand and 40 mm stone ballast i/c all .


(A) Materials :-
Cement 2.26 bags @ Rs 262.00 /bag= Rs 592.12 / cum
Fine sand 0.50 cum @ Rs 974.00 /cum=Rs 487.00 / cum
40mm S/B 1.00 cum @ Rs 689.00 /cum=Rs 689.00 / cum
Total Rs 1768.12 / cum
(B) Labours - For 100 cft
Mistri 0.125 nos @ Rs 180.00 / day = Rs 22.50 % cft
Mason 0.333 nos @ Rs 180.00 / day = Rs 59.94 % cft
Beldar 4 nos @ Rs 100.00 / day = Rs 400.00 % cft
Coolie 6 nos @ Rs 100.00 / day = Rs 600.00 % cft
Bhisti 1 nos @ Rs 100.00 / day = Rs 100.00 % cft
T$P etc L.S. 1.00 x 20 20.00 % cft
Add 0 %C.P.on Rs 1202.44 0 % cft
Total Rs 1202.44 %cft or Rs 424.89 / cum
(A+B) Total Rs 2193.01 / cum
Say Rs 2193.00 / cum

3 - R.R. stone masonry in 1:6 cement and sand mortor in foundation including supply of all .
(A) Materials :-
Cement 1.41 bags @ Rs 262.00 /bag= Rs 369.42 / cum
Fine sand 0.30 cum @ Rs 974.00 /cum=Rs 292.20 / cum
Stone 1.00 cum @ Rs 668.00 /cum=Rs 668.00 / cum
Total Rs 1329.62 / cum
(B) Labours - For 100 cft
Mason 4 nos @ Rs 180.00 / day = Rs 720.00 % cft
Beldar 3 nos @ Rs 100.00 / day = Rs 300.00 % cft
Coolie 2 nos @ Rs 100.00 / day = Rs 200.00 % cft
Bhisti 0.25 nos @ Rs 100.00 / day = Rs 25.00 % cft
T$P etc L.S. 0.50 x 20 10.00 % cft
Add 0 %C.P.on Rs 1255.00 0 % cft
Total Rs 1255.00 %cft or Rs 443.46 / cum
(A+B) Total Rs 1773.08 / cum
Say Rs 1773.00 / cum
J.E.,R.E.S. B.D.O.

4- R.R. stone masonry in 1:6 cement and sand mortor in super structure i/c supply of all .
Rate same as per above Item no. 3- = Rs 1773.08 / cum
Add for extra Labour required :-
Mason 0.5 nos @ Rs 180.00 / day = Rs 90.00 % cft
Coolie 1 nos @ Rs 100.00 / day = Rs 100.00 % cft
Scaffolding 0.75 x 20 15.00 % cft
Add 0 %C.P.on Rs 205.00 0 % cft
Total Rs 205.00 %cft or Rs 72.44 / cum
Total Rs 1845.52 / cum
Say Rs 1846.00 / cum

5- Brick masonry in 1:6 C/S mortor in plinth including supply of all for completion of work.
(A) Materials :-
Cement 1.25 bags @ Rs 262.00 /bag= Rs 327.50 / cum
Fine sand 0.27 cum @ Rs 974.00 /cum=Rs 262.98 / cum
Bricks 460.00 Nos @ Rs 4761.00 /cum=Rs 2190.06 / cum
Total Rs 2780.54 / cum
(B) Labours - For 100 cft
Mistri 0.17 nos @ Rs 180.00 / day = Rs 30.60 % cft
Mason 2 nos @ Rs 180.00 / day = Rs 360.00 % cft
Beldar 2 nos @ Rs 100.00 / day = Rs 200.00 % cft
Coolie 2 nos @ Rs 100.00 / day = Rs 200.00 % cft
T$P etc L.S. 0.70 x 20 14.00 % cft
Add 0 %C.P.on Rs 804.60 0 % cft
Total Rs 804.60 %cft or Rs 284.31 / cum
(A+B) Total Rs 3064.85 / cum
Say Rs 3065.00 / cum

6- Brick masonry in 1:6 C/S mortor in super structure i/c supply of all for completion of work.
Rate same as per above Item no. 5- = Rs 3064.85 / cum
Add for extra Labour required :-
Mason 1 nos @ Rs 180.00 / day = Rs 180.00 % cft
Coolie 1 nos @ Rs 100.00 / day = Rs 100.00 % cft
Scaffolding 1.50 x 20 30.00 % cft
Add 0 %C.P.on Rs 310.00 0 % cft
Total Rs 310.00 %cft or Rs 109.54 / cum
Total Rs 3174.39 / cum
Say Rs 3174.00 / cum

7- S/F of Angle Iron door chaukhat with iron shutter i/c all for comp of work. (1.00x2.00M)
Rate as per market = Rs 2500.00 /No.
8- S/F of Angle Iron window chaukhat with iron shutter grills i/c all for comp of work.
(0.90x1.20M) Rate as per market = Rs 2500.00 /No.
9- S/F of Angle Iron ventilator i/c supply of all for comp of work. (0.45x0.30M)
Rate as per market = Rs 250.00 /No.
J.E.,R.E.S. B.D.O.

10- R.C.C. (1:2:4) in plinth and lintel band etc. in cement, course sand and 20mm stone
ballast including supply of all for completion of work.
(A) Materials :-
Cement 6.62 bags @ Rs 262.00 /bag= Rs 1734.44 / cum
Course sand 0.45 cum @ Rs 1004.00 /cum=Rs 451.80 / cum
20mm S/B 0.90 cum @ Rs 779.00 /cum=Rs 701.10 / cum
Total Rs 2887.34 / cum
(B) Labours - For 100 cft
Mistri 0.1 nos @ Rs 180.00 / day = Rs 18.00 % cft
Mason 0.25 nos @ Rs 180.00 / day = Rs 45.00 % cft
Beldar 4 nos @ Rs 100.00 / day = Rs 400.00 % cft
Coolie 8 nos @ Rs 100.00 / day = Rs 800.00 % cft
Bhisti 2 nos @ Rs 100.00 / day = Rs 200.00 % cft
B/smith 2.1 nos @ Rs 180.00 / day = Rs 378.00 % cft
T$P etc L.S. 2.00 x 25 50.00 % cft
Add 0 %C.P.on Rs 1891.00 0 % cft
Binding wire 28 x 25 700 % cft
Shuttering 28 x 25 700 % cft
Total Rs 3291.00 %cft or Rs 1162.90 / cum
(A+B) Total Rs 4050.24 / cum
Say Rs 4050.00 / cum
11- R.C.C. (1:2:4) in slab including supply of all for completion of work.
Complete rate as per above Item no. 10- = Rs 4050.24 / cum
Add extra cost of centering and shuttering
= 0.40 x 35.31 x 25 = Rs 353.1 / cum
Total Rs 4403.34 / cum
Say Rs 4403.00 / cum
12- R.C.C. (1:2:4) in beam, columns including supply of all for completion of work.
Complete rate as per above Item no. 11- = Rs 4403.34 / cum
Add extra cost forordinary stone and balli support
= 1.00 x 35.31 x 25 = Rs 882.75 / cum
Total Rs 5286.09 / cum
Say Rs 5286.00 / cum
13- M.S. iron work as in reinforcement of R.C.C. work i/c supply of all for completion of work.
(A) Materials :-
M.S.bar i/c 5% wastage 1.05 qntl @ Rs 2943.00 /bag= Rs 3090.15 / qntl
(B) Labours - For 1 cwt
B/smith 1 nos @ Rs 180.00 / day = Rs 180.00 / cwt
Coolie 1.5 nos @ Rs 100.00 / day = Rs 150.00 / cwt
T$P etc L.S. 0.80 x 20 16.00 / cwt
Add 0 %C.P.on Rs 346.00 0 / cwt
Total Rs 346.00 /cwt or Rs 681.62 / qntl
Total Rs 3771.77 / qntl
Say Rs 3772.00 / qntl

J.E.,R.E.S. B.D.O.

14- 2.5 cm thick P.C.C. (1:2:4) in sills of door and windows in cement , course sand and
20 mm S/B including supply of all for completion of work .
(A) Materials :-
Cement 0.197 bags @ Rs 262.00 /bag= Rs 51.61 / sqm
Course sand 0.011 cum @ Rs 1004.00 /cum=Rs 11.04 / sqm
20mm S/B 0.023 cum @ Rs 779.00 /cum=Rs 17.92 / sqm
Total Rs 80.58 / sqm
(B) Labours - For 100 sqft
Mistri 0.13 nos @ Rs 180.00 / day = Rs 22.50 % sqft
Mason 1.00 nos @ Rs 180.00 / day = Rs 180.00 % sqft
Beldar 0.50 nos @ Rs 100.00 / day = Rs 50.00 % sqft
Coolie 0.50 nos @ Rs 100.00 / day = Rs 50.00 % sqft
Bhisti 0.25 nos @ Rs 100.00 / day = Rs 25.00 % sqft
T$P etc L.S. 1.25 x 20 25.00 % sqft
Add 0 %C.P.on Rs 352.50 0 % sqft
Total Rs 352.50 %sqft or Rs 37.94 / sqm
(A+B) Total Rs 118.52 / sqm
Say Rs 119.00 / sqm
15- 2.5 cm P.C.C.(1:2:4) in cement, sand and 20 mm S/B over 7.5 cm P.C.C. (1:6:12) in
cement, sand and 40 mm S/B in floor and apron including supply of all for comp of work.
Complete rate as per above Item no. -14- =Rs 118.52 / sqm
Base concrete of 1:6:12 ( Rate as per above item no. 2-
0.08 x 2193.00 = Rs 175.44 / sqm
Add 0 %C.P.on Rs 293.96 0.00 / sqm
Total Rs 293.96 / sqm
Say Rs 294.00 / sqm
16- 12mm thick plaster in 1:6 cement and sand mortor i/c supply of all for comp. of work .
(A) Materials :-
Cement 0.076 bags @ Rs 262.00 /bag= Rs 19.91 / sqm
Fine sand 0.015 cum @ Rs 974.00 /cum=Rs 14.61 / sqm
Total Rs 34.52 / sqm
(B) Labours - For 100 sqft
Mason 1.33 nos @ Rs 180.00 / day = Rs 239.94 % sqft
Beldar 0.50 nos @ Rs 100.00 / day = Rs 50.00 % sqft
Coolie 1.33 nos @ Rs 100.00 / day = Rs 133.30 % sqft
Bhisti 0.50 nos @ Rs 100.00 / day = Rs 50.00 % sqft
T$P etc L.S. 1.00 x 20 20.00 % sqft
Add 0 %C.P.on Rs 493.24 0 % sqft
Total Rs 493.24 %sqft or Rs 53.09 / sqm
(A+B) Total Rs 87.62 / sqm
Say Rs 88.00 / sqm
17- Earth and boulder filling in plinth including supply of all for comp of work.
Rate as per S.I. No. 161 = Rs 20.00 /cum
J.E.,R.E.S. B.D.O.

18- Painting or varnishing in two coats over one coat of primer including supply of all .
(A) Materials :-
Primer 0.075 bags @ Rs 100.00 /ltr = Rs 7.50 / sqm
(B) Labours - For 650 sqft
Painter 1 nos @ Rs 180.00 / day = Rs 180.00 /650 sft
Coolie 1 nos @ Rs 100.00 / day = Rs 100.00 /650 sft
T$P etc L.S. 0.50 x 20 10.00 /650 sft
Add 0 %C.P.on Rs 290.00 0 /650 sft
Total Rs 290.00 /650 sft or 4.80 / sqm
( c ) Paint 0.13 litr @ 180.00 /litr = Rs 23.40 / sqm
(D) Labours - For 100 sqft
Painter 0.45 nos @ Rs 180.00 / day = Rs 81.00 % sqft
Coolie 0.45 nos @ Rs 100.00 / day = Rs 45.00 % sqft
T$P etc L.S. 0.20 x 20 4.00 % sqft
Add 0 %C.P.on Rs 130.00 0 % sqft
Total Rs 130.00 % sqft or 13.99 / sqm
(A+B+C+D) Total Rs 49.70 / sqm
Say Rs 50.00 / sqm
19- White washing in three coats including supply of all for completion of work.
(A) Materials :-
White lime 0.32 Kg @ Rs 5.00 /ltr = Rs 1.60 / sqm
(B) Labours - For 100 sqft
White washer 0.13 nos @ Rs 120.00 / day = Rs 15.96 % sqft
Helper 0.13 nos @ Rs 100.00 / day = Rs 13.30 % sqft
T$P etc L.S. 0.20 x 20 4.00 % sqft
Add 0 %C.P.on Rs 33.26 0 % sqft
Total Rs 33.26 % sqft or 3.58 / sqm
(A+B ) Total Rs 5.18 / sqm
Say Rs 5.00 / sqm
20- R/R dry walls in R/W,B/W and Kharinja i/c all for comp of work .
Rate as per S.I.No. 518 = Rs 225.00 Per cum
Less 10% C.P. Rs 22.50 Per cum
Net Rs 202.50 Per cum
Add cartage of stone Rs 633.00 Per cum
Total Rs 835.50 Per cum
Say Rs 836.00 Per cum
21- R/R stone masonry in 1:6 cement and sand mortor in R/W and B/W i/c supply of all.
Rate as per S.I.No 516 = Rs 325.00 Per cum
Less 10% C.P. Rs 32.50 Per cum
Net Rs 292.50 Per cum
Add cartage of stone Rs 633.00 Per cum
Cost of cemen 1.41 bag @ 262.00 / bag =Rs 369.42 Per cum
Fine Sand 0.30 cum @ 974.00 / cum =Rs 292.20 Per cum
Total Rs 1587.12 Per cum
Say Rs 1587.00 Per cum

J.E.,R.E.S. B.D.O.

22- Mild steel or iron work such as in door, window chaukhats, grills i/c supply of all .
(A) Materials :-
M.S. i/c 2.5% wastage 1.025 qntl @ Rs 3593.00 /bag= Rs 3682.83 / qntl
(B) Labours - For 1cwt
B/smith 1 nos @ Rs 180.00 / day = Rs 180.00 / cwt
Hammer man 1 nos @ Rs 100.00 / day = Rs 100.00 / cwt
Rivettor 0.25 nos @ Rs 180.00 / day = Rs 45.00 / cwt
Coolie 1 nos @ Rs 100.00 / day = Rs 100.00 / cwt
T$P etc L.S. 0.60 x 20 12.00 / cwt
Extra for hoisting and welding
4.9 x 20 98 / cwt
Add 0 %C.P.on Rs 535.00 0.00 / cwt
Total Rs 535.00 /cwt or Rs 1053.95 / qntl
Total Rs 4736.78 / qntl
Say Rs 4737.00 / qntl
23- 35 mm thick sal and sheesham wood fully panelled doors and window shutters i/c all .
(A) Materials :-
Sal wood 0.0336 cum @ Rs 30000.00 /bag= Rs 1008.00 / sqm
(B) Labours - For 24.75 sqft
Mistri 0.13 nos @ Rs 180.00 / day = Rs 22.50 /24.75 sqft
Carpente 2.00 nos @ Rs 180.00 / day = Rs 360.00 /24.75 sqft
Carpente 2.00 nos @ Rs 180.00 / day = Rs 360.00 /24.75 sqft
Beldar 1.00 nos @ Rs 100.00 / day = Rs 100.00 /24.75 sqft
Painter 0.25 nos @ Rs 180.00 / day = Rs 45.00 /24.75 sqft
T$P etc L.S. 0.50 x 20 10.00 /24.75 sqft
Add 0 %C.P.on Rs 897.50 0 /24.75 sqft
Total Rs 897.50 /24.75 sqft
Or Rs 3626.2626 %sqft or Rs 390.34 / sqm
(A+B) Total Rs 1398.34 / sqm
Say Rs 1398.00 / sqm
24- S/F of oxidized iron fittings including supply of all for comp of work.
Rate as per schedule = Rs 150.00 / sqm
J.E.,R.E.S. B.D.O.
Name of work :- Constt. Of Toilet

BILL OF QUANTITY

S.N. ITEM OF WORK QNTTY. UNIT RATE AMOUNT

1 E/W in excavation in foundation in all


types of soil i/c supply of all. Err:522 cum 32.00 Err:522
2 C.C.(1:6:12) in cement,sand and 40 mm.
stone ballast i/c supply of all. 1.49 cum 2193.00 3256.61
3 R/R stone masonry in 1:6 cement and
sand mortor in foundation i/c supply of all. 0.00 cum 1773.00 0.00
4 R/R stone masonry in 1:6 cement and
sand mortor in super structure i/c all. Err:522 cum 1846.00 Err:522
5 S/F of Angle iron chaukhat for door with
iron shutter i/c supply of all.(0.75x1.80M) 2 nos 2500.00 5000.00

6
S/F of Angle iron vent. i/c all. 0 nos 250.00 0.00
7R.C.C.(1:2:4) in slab including supply
of all for comp of work. Err:522 cum 4403.00 Err:522
8 M.S.Iron work in reinforcement i/c supply
of all for comp of work. 2.05 qntl 3772.00 7732.60
9 12 mm. thick plaster in (1:6) cement
and sand mortor i/c supply of all. 38.97 sqm 88.00 3429.36
10 2.5 cm thick C.C.(1:2:4) over 7.5cm thick
C.C.(1:6:12) in floor i/c supply of all. 3.33 sqm 294.00 979.02

11 White washing in three coat i/c supply of all. 1.00 sqm 5.00 5.00
12 Painting two coat over one priming coat
i/c supply of all. 0 sqm 50.00 0.00

13 Making sign board etc. 1 Job 1000.00 1000.00

Total Rs Err:522
J.E.,R.E.S. B.D.O.

Name of work :- Constt. Of Toilet

SUMMARY OF ESTIMATED COST

S.N. PARTICULARS AMOUNT

1 Constt. Of Toilet as per detailed estimate


Rs Err:522

Total Rs Err:522

Say Rs 1,50,000.00

Sanctioned Rs 1,50,000.00

J.E.,R.E.S. B.D.O.
Name of work :- Constt. Of Barat Ghar at Nadda .

BILL OF QUANTITY

S.N. ITEM OF WORK QNTTY. UNIT RATE AMOUNT

1 E/W in excavation in foundation in all


types of soil i/c supply of all. 11.21 cum 32.00 358.72
2 C.C.(1:6:12) in cement,sand and 40 mm.
stone ballast i/c supply of all. 1.86 cum 2193.00 4078.98
3 R/R stone masonry in 1:6 cement and
sand mortor in foundation i/c supply of all. 7.84 cum 1773.00 13900.32
4 R.C.C.(1:2:4) in plinth and lintel band
i/c supply of all. 1.69 cum 4050.00 6844.50
5 Brick masonry in 1:6 cement and sand
mortor in super structure i/c all. 12.99 cum 3174.00 41230.26
6 S/F of Angle iron chaukhat for door with
iron shutter i/c supply of all.(1.00x2.00M) 2 nos 2500.00 5000.00
7 S/F of Angle iron chaukhat for window with
fixed grills and iron shutter i/c supply of all. 4 nos 2500.00 10000.00
8 R.C.C.(1:2:4) in beam columns i/c supply
of all for comp of work. 0.73 cum 5286.00 3858.78
9 R.C.C.(1:2:4) in slab including supply
of all for comp of work. 5.13 cum 4403.00 22587.39
10 M.S.Iron work in reinforcement i/c supply
of all for comp of work. 7.40 qntl 3772.00 27912.80
11 12 mm. thick plaster in (1:6) cement
and sand mortor i/c supply of all. 138.00 sqm 88.00 12144.00

12 E/B filling in plinth i/c all for comp. 10.50 cum 20.00 210.00
13 2.5 cm thick C.C.(1:2:4) over 7.5cm thick
C.C.(1:6:12) in floor i/c supply of all. 35.00 sqm 294.00 10290.00

14 White washing in three coat i/c supply of all. 173.00 sqm 5.00 865.00
15 Painting two coat over one priming coat
i/c supply of all. 16.64 sqm 50.00 832.00
16 R/R dry wall in R/W and B/W i/c supply
of all for comp of work. 5.40 cum 836.00 4514.4

17 Making sign board etc. 1 Job 1000.00 1000.00

Total Rs 165627.15
J.E.,R.E.S. B.D.O.

Name of work :- Constt. Of Barat Ghar at Nadda .

SUMMARY OF ESTIMATED COST

S.N. PARTICULARS AMOUNT

1 Constt. Of Barat Ghar at Nadda as per detailed estimate


Rs 165627.15

Total Rs 165627.15

Say Rs 1,40,000.00

Sanctioned Rs 1,40,000.00

J.E.,R.E.S. B.D.O.
dk;Z dk uke%&m0ek0fo0cjlwM+h esa d{kksa dk fuekZZ.k dk;Z A

BILL OF QUANTITY

S.N. ITEM OF WORK QNTTY. UNIT RATE AMOUNT

1 E/W in excavation in foundation in all


types of soil i/c supply of all. 22.59 cum 32.00 722.88
2 C.C.(1:6:12) in cement,sand and 40 mm.
stone ballast i/c supply of all. 3.75 cum 2193.00 8223.75
3 R/R stone masonry in 1:6 cement and
sand mortor in foundation i/c supply of all. 20.48 cum 1773.00 36311.04
4 R.C.C.(1:2:4) in plinth and lintel band
i/c supply of all. 3.07 cum 4050.00 12433.50
5 Brick masonry in 1:6 cement and sand
mortor in super structure i/c all. 21.86 cum 3174.00 69383.64
6 S/F of Angle iron chaukhat for door with
iron shutter i/c supply of all.(1.00x2.00M) 4 nos 2500.00 10000.00
7 S/F of Angle iron chaukhat for window with
fixed grills and iron shutter i/c supply of all. 4 nos 2500.00 10000.00
8 R.C.C.(1:2:4) in beam columns i/c supply
of all for comp of work. 2.35 cum 5286.00 12422.10
9 R.C.C.(1:2:4) in slab including supply
of all for comp of work. 10.44 cum 4403.00 45967.32
10 M.S.Iron work in reinforcement i/c supply
of all for comp of work. 15.56 qntl 3772.00 58692.32
11 12 mm. thick plaster in (1:6) cement
and sand mortor i/c supply of all. 208.26 sqm 88.00 18326.88

12 E/B filling in plinth i/c all for comp. 20.27 cum 20.00 405.40
13 2.5 cm thick C.C.(1:2:4) over 7.5cm thick
C.C.(1:6:12) in floor i/c supply of all. 85.04 sqm 294.00 25001.76

14 White washing in three coat i/c supply of all. 289.66 sqm 5.00 1448.30
15 Painting two coat over one priming coat
i/c supply of all. 24.64 sqm 50.00 1232.00
16 Making sign board etc. 1 Job 1000.00 1000.00

Total Rs 311570.89
J.E.,R.E.S. B.D.O.

dk;Z dk uke%&m0ek0fo0cjlwM+h esa d{kksa dk fuekZZ.k dk;Z A

SUMMARY OF ESTIMATED COST

S.N. PARTICULARS AMOUNT

1 Constt. Of Class room at High School Barsoodi as per detailed estimate


Rs 311570.89

Total Rs 311570.89

Say Rs 3,00,000.00

Sanctioned Rs 3,00,000.00

J.E.,R.E.S. B.D.O.
Name of work :- Constt. Of Add.room at G.I.C. Kaindul Thangar.

BILL OF QUANTITY

S.N. ITEM OF WORK QNTTY. UNIT RATE AMOUNT

1 E/W in excavation in foundation in all


types of soil i/c supply of all. 11.43 cum 32.00 365.76
2 C.C.(1:6:12) in cement,sand and 40 mm.
stone ballast i/c supply of all. 1.90 cum 2193.00 4166.70
3 R/R stone masonry in 1:6 cement and
sand mortor in foundation i/c supply of all. 6.93 cum 1773.00 12286.89
4 R.C.C.(1:2:4) in plinth and lintel band
i/c supply of all. 1.17 cum 4050.00 4738.50
5 Brick masonry in 1:6 cement and sand
mortor in super structure i/c all. 9.96 cum 3174.00 31613.04
6 S/F of Angle iron chaukhat for door with
iron shutter i/c supply of all.(1.00x2.00M) 2 nos 2500.00 5000.00
7 S/F of Angle iron chaukhat for window with
fixed grills and iron shutter i/c supply of all. 2 nos 3500.00 7000.00
(1.50x1.20M)
8 S/F of Angle iron vent. i/c all.(1.00x0.60M) 2 nos 500.00 1000.00
9 R.C.C.(1:2:4) in beam columns i/c supply
of all for comp of work. 0.81 cum 5286.00 4281.66
10 R.C.C.(1:2:4) in slab including supply
of all for comp of work. 4.99 cum 4403.00 21970.97
11 M.S.Iron work in reinforcement i/c supply
of all for comp of work. 6.83 qntl 3772.00 25762.76
12 12 mm. thick plaster in (1:6) cement
and sand mortor i/c supply of all. 103.20 sqm 88.00 9081.60

13 E/B filling in plinth i/c all for comp. 9.90 cum 20.00 198.00
14 2.5 cm thick C.C.(1:2:4) over 7.5cm thick
C.C.(1:6:12) in floor i/c supply of all. 41.50 sqm 294.00 12201.00

15 White washing in three coat i/c supply of all. 144.70 sqm 5.00 723.50
16 Painting two coat over one priming coat
i/c supply of all. 22.50 sqm 50.00 1125.00
17 R/R dry walls in R/W,B/W i/c all . 9.00 cum 836.00 7524

18 Making sign board etc. 1 Job 1000.00 1000.00

Total Rs 150039.38

J.E.,R.E.S. B.D.O.

Name of work :- Constt. Of Add.room at G.I.C. Kaindul Thangar.

SUMMARY OF ESTIMATED COST

S.N. PARTICULARS AMOUNT

1 Constt. Of Add.room at G.I.C. Kaindul Thangar as per detailed estimate


Rs 150039.38

Total Rs 150039.38

Say Rs 1,40,000.00

Sanctioned Rs 1,40,000.00

J.E.,R.E.S. B.D.O.
Name of work :- Beautification of Balkunwari Tok at village Khand .

BILL OF QUANTITY

S.N. ITEM OF WORK QNTTY. UNIT RATE AMOUNT

1 E/W in excavation in foundation in all


types of soil i/c supply of all. 4.70 cum 32.00 150.40
2 C.C.(1:6:12) in cement,sand and 40 mm.
stone ballast i/c supply of all. 0.74 cum 2193.00 1622.82
3 R/R stone masonry in 1:6 cement and
sand mortor in foundation i/c supply of all. 4.99 cum 1773.00 8847.27
4 Brick masonry in 1:6 cement and sand
mortor in super structure i/c all. 4.14 cum 3174.00 13140.36
5 R.C.C.(1:2:4) in beam columns i/c supply
of all for comp of work. 3.11 cum 5286.00 16439.46
6 R.C.C.(1:2:4) in slab including supply
of all for comp of work. 3.24 cum 4403.00 14265.72
7 M.S.Iron work in reinforcement i/c supply
of all for comp of work. 6.23 qntl 3772.00 23499.56
8 12 mm. thick plaster in (1:6) cement
and sand mortor i/c supply of all. 52.92 sqm 88.00 4656.96
9 2.5 cm thick C.C.(1:2:4) over 7.5cm thick
C.C.(1:6:12) in floor i/c supply of all. 22.99 sqm 294.00 6759.06

10 S/F of M.S. iron gate i/c supply of all . 1 No. L.S. 1000.00
11 White washing in three coat and
painting two coat over one priming coat
i/c supply of all. 1 Job L.S. 1000.00

12 R/R dry walls in R/W,B/W i/c all . 5.40 cum 836.00 4514.40

13 Making sign board etc. 1 Job 1000.00 1000.00


Total Rs 96896.01

J.E.,R.E.S. B.D.O.

Name of work :- Beautification of Balkunwari Tok at village Khand .

SUMMARY OF ESTIMATED COST

S.N. PARTICULARS AMOUNT

1 Beautification of Balkunwari Tok at Khand as per detailed estimate.


Rs 96896.01

Total Rs 96896.01

Say Rs 1,00,000.00

Sanctioned Rs 1,00,000.00

J.E.,R.E.S. B.D.O.
Name of work :- Constt. Of Laboratory at Govt. Inter College
Mahadev Chatti .
BILL OF QUANTITY

S.N. ITEM OF WORK QNTTY. UNIT RATE AMOUNT

1 E/W in excavation in foundation in all


types of soil i/c supply of all. 49.12 cum 32.00 1571.84
2 C.C.(1:6:12) in cement,sand and 40 mm.
stone ballast i/c supply of all. 8.17 cum 2193.00 17916.81
3 R/R stone masonry in 1:6 cement and
sand mortor in foundation i/c supply of all. 40.02 cum 1773.00 70955.46
4 R.C.C.(1:2:4) in plinth and lintel band
i/c supply of all. 4.61 cum 4050.00 18670.50
5 Brick masonry in 1:6 cement and sand
mortor in super structure i/c all. 36.9 cum 3174.00 117120.60
6 Mild steel or iron work such as in door,
window chaukhats, grills i/c supply of all . 3.30 qntl 4737.00 15632.10
7 R.C.C.(1:2:4) in beam columns i/c supply
of all for comp of work. 2.89 cum 5286.00 15276.54
8 R.C.C.(1:2:4) in slab including supply
of all for comp of work. 18.66 cum 4403.00 82159.98
9 M.S.Iron work in reinforcement i/c supply
of all for comp of work. 25.66 qntl 3772.00 96789.52
10 12 mm. thick plaster in (1:6) cement
and sand mortor i/c supply of all. 373.86 sqm 88.00 32899.68

11 E/B filling in plinth i/c all for comp. 27.99 cum 20.00 559.80
12 2.5 cm thick C.C.(1:2:4) over 7.5cm thick
C.C.(1:6:12) in floor i/c supply of all. 113.19 sqm 294.00 33277.86
13 2.5 cm thick P.C.C (1:2:4) in sills of door
and window i/c all. 6.12 119.00 728.28
14 35 mm thick sal and sheesham wood fully
panelled doors and window shutters i/c all . 15.69 1398.00 21934.62

15 S/F of oxidized iron fittings i/c all . 15.69 150.00 2353.50

16 White washing in three coat i/c supply of all. 487.05 sqm 5.00 2435.25
17 Painting two coat over one priming coat
i/c supply of all. 45.15 sqm 50.00 2257.50
18 R/R dry wall in R/W, B/W i/c all . 10.20 836.00 8527.20
19 R/R (1:6) cement $ sand in R/W, B/W i/c all 10.20 1587.00 16187.40
20 Internal electrification of building i/c all . 1 Job 10000 10000.00
21 Making sign board etc. 1 Job 1000.00 1000.00

Total Rs 568254.44

J.E.,R.E.S. B.D.O.

Name of work :- Constt. Of Laboratory at Govt. Inter College


Mahadev Chatti .
SUMMARY OF ESTIMATED COST

S.N. PARTICULARS AMOUNT

1 Constt. Of Laboratory as per detailed estimate


Rs 568254.44

Total Rs 568254.44

Say Rs 5,45,000.00

Sanctioned Rs 5,45,000.00

J.E.,R.E.S. B.D.O.
Name of work :- Beautification of Balkunwari Tok at village Khand .

BILL OF QUANTITY

S.N. ITEM OF WORK QNTTY. UNIT RATE AMOUNT

1 E/W in excavation in foundation in all


types of soil i/c supply of all. 4.70 cum 0.00 0.00
2 C.C.(1:6:12) in cement,sand and 40 mm.
stone ballast i/c supply of all. 0.74 cum 0.00 0.00
3 R/R stone masonry in 1:6 cement and
sand mortor in foundation i/c supply of all. 4.99 cum 0.00 0.00
4 Brick masonry in 1:6 cement and sand
mortor in super structure i/c all. 4.14 cum 0.00 0.00
5 R.C.C.(1:2:4) in beam columns i/c supply
of all for comp of work. 3.11 cum 0.00 0.00
6 R.C.C.(1:2:4) in slab including supply
of all for comp of work. 3.24 cum 0.00 0.00
7 M.S.Iron work in reinforcement i/c supply
of all for comp of work. 6.23 qntl 0.00 0.00
8 12 mm. thick plaster in (1:6) cement
and sand mortor i/c supply of all. 52.92 sqm 0.00 0.00
9 2.5 cm thick C.C.(1:2:4) over 7.5cm thick
C.C.(1:6:12) in floor i/c supply of all. 22.99 sqm 0.00 0.00

10 S/F of M.S. iron gate i/c supply of all . 1 No. L.S. 1000.00
11 White washing in three coat and
painting two coat over one priming coat
i/c supply of all. 1 Job L.S. 1000.00

12 R/R dry walls in R/W,B/W i/c all . 5.40 cum 0.00 0.00

13 Making sign board etc. 1 Job 1000.00 1000.00

Total Rs 3000.00

J.E.,R.E.S. B.D.O.

Name of work :- Beautification of Balkunwari Tok at village Khand .

SUMMARY OF ESTIMATED COST

S.N. PARTICULARS AMOUNT

1 Beautification of Balkunwari Tok at Khand as per detailed estimate.


Rs 3000.00

Total Rs 3000.00

Say Rs 1,00,000.00

Sanctioned Rs 1,00,000.00

J.E.,R.E.S. B.D.O.
Name of work :- Constt of w/c and Bath at Village Purankot--

DETAILS OF MEASUREMENT
S.N. ITEM OF WORK NO. L B H/D QNTTY.
1 E/W in excavation in foundation in all
types of soil i/c supply of all.
In Septic Tank - 1 4.50 3.50 1.80 28.35 Cum
Total Err:522 cum

2 R.R. stone masonry 1:6 cement sand


Fopundation For S.T ----------work. 2 3.50 0.45 1.80 5.67 cum
2 2.40 0.45 1.80 3.89 cum
Total 9.56 cum

3 R.C.C. work 1:2:4 in S.T Slab 1 4.50 3.30 0.10 1.49 Cum

4 C.C. Black Masonry 1:3:6 plaster 1:3


sand mortor in super structure i/c all.
In W.C. - L/W - 2 2.60 0.30 2.10 3.28 cum
S/W - 3 0.90 0.30 2.10 1.70 cum
Total 4.98 cum
Deduct - Door - 2 0.75 0.30 1.80 0.81 cum
Total Err:522 cum

Net masonry = 4.98 - ### = Err:522 cum

5 S/F of Angle iron chaukhat for door with


iron shutter i/c supply of all.(0.75x1.80M) 2 - - - 2 No.

7 R.C.C.(1:2:4) in slab including supply


of all for comp of work.
Over Toilet - 1 3.05 1.95 0.10 0.59 Cum
Total Err:522 cum
8 M.S.Iron work in reinforcement i/c supply
of all for comp of work.
1.25% of R.C,.C. - = 2.08 0.783 = 2.05 Qntl
9 12 mm. thick plaster in (1:6) cement
and sand mortor i/c supply of all.
Outer side - L/W - 2 2.60 - 2.10 10.92
S/W - 2 1.50 - 2.10 6.30
Inner side - L/W - 4 1.85 - 2.10 15.54
S/W - 4 0.90 - 2.10 7.56
Total 40.32 sqm
Deduct - Door - 1 0.75 - 1.80 1.35 sqm
Net Plaster = 40.32 - 1.35 38.97 sqm
10 2.5 cm thick C.C.(1:2:4) in floor 2 1.85 0.90 - 3.33 sqm

11 S/F of White Glazed W/C Sheet 1 1.00 No


k dk;Z A
k dk;Z A
CONSTRUCTION OF TOILET

0.10 M

2.40 M

0.45 0.45

G L
0.60 M 0.60 M 0.45 0.10 M

0.75 M 0.75 M 0.10

TOILET 1.50 M

SCHEDULE -
DOOR - 0.75 x 1.80 M
VENTILATOR 0.45 x 0.30 M
0.10 M

SEPTIC TANK
SECTIONAL ELEVATION

1.00 M
1.90 1.50 M
0.45 0.45 0.45 0.45 1.90 M
1.00 M

1.00 M

D
1.90 M 2.40 M

TOILET SEPTIC TANK

PLAN
CONSTRUCTION OF ONE ROOM

0.10 M

3.00 M

0.23
P L
0.10 M
0.45 0.30 M
G L
0.60 0.30 M

0.75 0.30 M

0.20 M
0.90
SECTIONAL ELEVATION

W W
0.23

0.23 6.00 M 0.23

4.46 M

4.00 M

0.23
D
W
6.46 M
PLAN

SCHEDULE
DOOR 1.00 X 2.00 M
WINDOW 0.90 X 1.20 M

You might also like