Schedule Quality Checklist

1. Activity Attributes
1.1. All Activity IDs are structured 
1.2. Avoid Activities with Long Durations 
1.3. Ensure activities are assigned with correct Calendars 
1.4. % Complete Type is set properly 

2. Scheduling options
2.1. Uncheck “Use Expected Finish dates”. It should be OFF. 
2.2. “Retained logic” is ON 
2.3. Calculate Start-to-Start lag from “Early Start” 
2.4. Define Critical Activities as “total float less than or equal to “0h” 
2.5. Calculate float based on finish date of “each project” 
2.6. Computation of total float is set properly 
2.7. Calendar for scheduling relationship lag is predecessor activity calendar 

3. Log
3.1. No activities without predecessors 
3.2. No activities without successors 
3.3. No activities with constraints (only project end) 
3.4. No activities with invalid relationship 

4. Scheduling
4.1. Review activities with high total float 
4.2. Review activities with very early start dates 
4.3. Review high free float 

5. Critical Path

5.1. Practical Longest Path 


5.2. Percentage of critical activities is practical and reasonable 