1. Activity Attributes
1.1. All Activity IDs are structured
1.2. Avoid Activities with Long Durations
1.3. Ensure activities are assigned with correct Calendars
1.4. % Complete Type is set properly
2. Scheduling options
2.1. Uncheck “Use Expected Finish dates”. It should be OFF.
2.2. “Retained logic” is ON
2.3. Calculate Start-to-Start lag from “Early Start”
2.4. Define Critical Activities as “total float less than or equal to “0h”
2.5. Calculate float based on finish date of “each project”
2.6. Computation of total float is set properly
2.7. Calendar for scheduling relationship lag is predecessor activity calendar
3. Log
3.1. No activities without predecessors
3.2. No activities without successors
3.3. No activities with constraints (only project end)
3.4. No activities with invalid relationship
4. Scheduling
4.1. Review activities with high total float
4.2. Review activities with very early start dates
4.3. Review high free float
5. Critical Path