Material and Drawing Submittal Log

The document is a log sheet tracking the status of material, drawing, and document submittals for an upgrade building project. It includes 20 materials, 20 drawings, and 12 documents with information on submission date, revision status, discipline, and transmittal number. The majority of submittals are marked as submitted to the site authority for review and approval, while a few require revision and resubmission by specified dates.

Uploaded by

SARANGMUMBAI
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
55 views12 pages

Material and Drawing Submittal Log

The document is a log sheet tracking the status of material, drawing, and document submittals for an upgrade building project. It includes 20 materials, 20 drawings, and 12 documents with information on submission date, revision status, discipline, and transmittal number. The majority of submittals are marked as submitted to the site authority for review and approval, while a few require revision and resubmission by specified dates.

Uploaded by

SARANGMUMBAI
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

UPDATE SHEET FOR UPGRADE BUILDING FOR RISK MITIGATION -C.NO.

6601000236 - BI 10-01409
MATERIAL SUBMITTAL (MATERIAL LOG SHEET)
SUBMISSION 1ST 2ND 3RD STATUS OF
S.NO MATERIAL SUBMITTAL NO. DESCRIPTION VENDOR NAME Desipline Transmittal No. L.P.O. DATE
DATE M/D/Y REVISION REVISION REVISION SUBMITTAL

1 MMH-MAT-1409-0001

10

11

12

13

14

15
UPDATE SHEET FOR UPGRADE BUILDING FOR RISK MITIGATION -C.NO. 6601000236 - BI 10-01409
MATERIAL SUBMITTAL (MATERIAL LOG SHEET)
SUBMISSION 1ST 2ND 3RD STATUS OF
S.NO MATERIAL SUBMITTAL NO. DESCRIPTION VENDOR NAME Desipline Transmittal No. L.P.O. DATE
DATE M/D/Y REVISION REVISION REVISION SUBMITTAL

16

17

18

19

20
UPDATE SHEET FOR UPGRADE BUILDING FOR RISK MITIGATION -C.NO. 6601000236 - BI 10-01409
MATERIAL SUBMITTAL (MATERIAL LOG SHEET)
SUBMISSION 1ST 2ND 3RD STATUS OF
S.NO MATERIAL SUBMITTAL NO. DESCRIPTION VENDOR NAME Desipline Transmittal No. L.P.O. DATE
DATE M/D/Y REVISION REVISION REVISION SUBMITTAL
UPDATE SHEET FOR UPGRADE BUILDING FOR RISK MITIGATION -C.NO. 6601000236 - BI 10-01409
MATERIAL SUBMITTAL (MATERIAL LOG SHEET)
SUBMISSION 1ST 2ND 3RD STATUS OF
S.NO MATERIAL SUBMITTAL NO. DESCRIPTION VENDOR NAME Desipline Transmittal No. L.P.O. DATE
DATE M/D/Y REVISION REVISION REVISION SUBMITTAL
UPDATE SHEET FOR UPGRADE BUILDING FOR RISK MITIGATION -C.NO. 6601000236 - BI 10-01409
MATERIAL SUBMITTAL (MATERIAL LOG SHEET)
SUBMISSION 1ST 2ND 3RD STATUS OF
S.NO MATERIAL SUBMITTAL NO. DESCRIPTION VENDOR NAME Desipline Transmittal No. L.P.O. DATE
DATE M/D/Y REVISION REVISION REVISION SUBMITTAL
UPDATE SHEET FOR UPGRADE BUILDING FOR RISK MITIGATION -C.NO. 6601000236 - BI 10-01409
MATERIAL SUBMITTAL (MATERIAL LOG SHEET)
SUBMISSION 1ST 2ND 3RD STATUS OF
S.NO MATERIAL SUBMITTAL NO. DESCRIPTION VENDOR NAME Desipline Transmittal No. L.P.O. DATE
DATE M/D/Y REVISION REVISION REVISION SUBMITTAL
UPDATE SHEET FOR UPGRADE BUILDING FOR RISK MITIGATION -C.NO. 6601000236 - BI 10-01409
MATERIAL SUBMITTAL (MATERIAL LOG SHEET)
SUBMISSION 1ST 2ND 3RD STATUS OF
S.NO MATERIAL SUBMITTAL NO. DESCRIPTION VENDOR NAME Desipline Transmittal No. L.P.O. DATE
DATE M/D/Y REVISION REVISION REVISION SUBMITTAL
UPDATE SHEET FOR UPGRADE BUILDING FOR RISK MITIGATION-C.NO. 6601000236 - BI 10-01409
DRAWING SUBMITTAL (DRAWING LOG SHEET)
SUBMISSION 1ST 2ND 3RD STATUS OF
S.NO DRAWING SUBMITTAL NO. DESCRIPTION VENDOR NAME DATE M/D/Y REVISION REVISION REVISION SUBMITTAL DISCIPLINE Transmittal No.

1 MMH-DWG-1409-0001

10
UPDATE SHEET FOR UPGRADE BUILDING FOR RISK MITIGATION-C.NO. 6601000236 - BI 10-01409
DRAWING SUBMITTAL (DRAWING LOG SHEET)
SUBMISSION 1ST 2ND 3RD STATUS OF
S.NO DRAWING SUBMITTAL NO. DESCRIPTION VENDOR NAME DATE M/D/Y REVISION REVISION REVISION SUBMITTAL DISCIPLINE Transmittal No.

11

12

13

14

15

16

17

18

19

20
UPDATE SHEET FOR UPGRADE BUILDING FOR RISK MITIGATION -C.NO. 6601000236 - BI 10-01409
DOCUMENTS SUBMITTAL (DOCUMENT LOG SHEET)
DOCUMENTS SUBMISSION 1ST 2ND 3RD
S.NO DESCRIPTION STATUS OF SUBMITTAL DISCIPLINE TRANSMITTAL NO. REMARKS
SUBMITTAL NO. DATE M/D/Y REVISION REVISION REVISION

Revise & resubmit within


Hazard Identification Plan
1 HGP-2023-001 5/15/2023 Submitted to S.A MMH-01409-2023-0016 15/days
(HIP)
17/05/2023

Revise & resubmit within


Submitted to S.A MMH-01409-2023-0015
2 HGP-2023-002 Procurement Plan 5/15/2023 6/11/2023 15/days
Submitted to S.A MMH-01409-2023-0024
17/05/2023

3 HGP-2023-003 Quality Audit Schedule 5/10/2023 Submitted to S.A MMH-01409-2023-0013

Request Letter for no objection of Design


4 HGP-2023-004 4/13/2023 Approved MMH-01409-2023-0001
Office(Worley)

Proposed Key Personnels for Design


5 HGP-2023-005 4/25/2023 Submitted to S.A MMH-01409-2023-0002
Subcontractor(Worley)

6 HGP-2023-006 CV of Proposed QA-QC MANAGER - P.V. SARANG 4/27/2023 Submitted to S.A MMH-01409-2023-0003

CV of Proposed Procurement Manager-Narasimhan


7 HGP-2023-007 4/27/2023 Submitted to S.A MMH-01409-2023-0004
Ramanujam

CV of Proposed Document Controller-M. Shahzad


8 HGP-2023-008 4/29/2023 Submitted to S.A MMH-01409-2023-0005
Iqbal

9 HGP-2023-009 CV of Proposed Safety Supervisor-Shah Zaib 4/29/2023 Submitted to S.A Cancelled MMH-01409-2023-0006

10 HGP-2023-010 CONTRACTOR SITE SAFETY PROGRAM (CSSP) 4/30/2023 Submitted to S.A MMH-01409-2023-0007

11 HGP-2023-011 Project Quality Plan (PQP) 5/1/2023 Submitted to S.A MMH-01409-2023-0008

CV of Proposed Lead Instrumentation & Control


12 HGP-2023-012 5/3/2023 Submitted to S.A OUT-MMH-01409-2023-0009
Engineer Project Control Manager

13 HGP-2023-013 Proposed Project Organization Chart-M.M.H 5/8/2023 Submitted to S.A MMH-01409-2023-0010

14 HGP-2023-014 CV of Proposed Safety Manager-Shahid Raza 5/8/2023 Submitted to S.A MMH-01409-2023-0011

Impement S.A Comments


& resubmit within
15 HGP-2023-015 Saudization & Training Plan-M.M.H 5/9/2023 Submitted to S.A MMH-01409-2023-0012
15/days
28/05/2023

16 HGP-2023-016 Quality Management Report-QMR-001 5/10/2023 Submitted to S.A MMH-01409-2023-0014

REJECTED
Impement S.A Comments
17 HGP-2023-017 Subcontracting Plan 5/17/2023 Submitted to S.A MMH-01409-2023-0017 & resubmit within
10/days
28/05/2023

18 HGP-2023-018 RFI Drawing Number Request from iPlant (WORLEY) 5/17/2023 Submitted to S.A MMH-01409-2023-0018

Impement S.A Comments


& resubmit within
19 HGP-2023-019 Environmental Management Plan (EMP) 5/21/2023 Submitted to S.A MMH-01409-2023-0019
15/days
28/05/2023

20 HGP-2023-020 Environmental Management System (EMS) 5/21/2023 Submitted to S.A MMH-01409-2023-0020

21 HGP-2023-021 RFIs for Electrical & Instrumentation(WORLEY) 6/6/2023 Submitted to S.A MMH-01409-2023-0021

22 HGP-2023-022 Conducting the session of Project Risk Management-PRM 6/8/2023 Submitted to S.A MMH-01409-2023-0022

23 HGP-2023-023 Pre Inspection Meetings- PIM Procedure 6/10/2023 Submitted to S.A MMH-01409-2023-0023

24 HGP-2023-024 RFI-Instrument Tags Request(WORLEY) 6/12/2023 Submitted to S.A MMH-01409-2023-0025

25 HGP-2023-025 MMH-01409-2023-0026

26

27
UPDATE SHEET FOR UPGRADE BUILDING FOR RISK MITIGATION -C.NO. 6601000236 - BI 10-01409
DOCUMENTS SUBMITTAL (DOCUMENT LOG SHEET)
DOCUMENTS SUBMISSION 1ST 2ND 3RD
S.NO DESCRIPTION STATUS OF SUBMITTAL DISCIPLINE TRANSMITTAL NO. REMARKS
SUBMITTAL NO. DATE M/D/Y REVISION REVISION REVISION

Revise & resubmit within


Hazard Identification Plan 5/15/2023 Submitted to S.A MMH-01409-2023-0016
1 HGP-2023-001 15/days
(HIP) 6/14/2023 Submitted to S.A MMH-01409-2023-0028
17/05/2023

Submitted to S.A MMH-01409-2023-0015 Revise & resubmit within


2 HGP-2023-002 Procurement Plan 5/15/2023 6/11/2023 6/25/2023 Submitted to S.A MMH-01409-2023-0024 15/days
Submitted to S.A MMH-01409-2023-0035 17/05/2023

Submitted to S.A MMH-01409-2023-0013


3 HGP-2023-003 Quality Audit Schedule 5/10/2023 6/19/2023
Submitted to S.A MMH-01409-2023-0030

Request Letter for no objection of Design


4 HGP-2023-004 4/13/2023 Approved MMH-01409-2023-0001
Office(Worley)

Proposed Key Personnels for Design


5 HGP-2023-005 4/25/2023 Submitted to S.A MMH-01409-2023-0002
Subcontractor(Worley)

6 HGP-2023-006 CV of Proposed QA-QC MANAGER - P.V. SARANG 4/27/2023 Submitted to S.A MMH-01409-2023-0003

CV of Proposed Procurement Manager-Narasimhan


7 HGP-2023-007 4/27/2023 Submitted to S.A MMH-01409-2023-0004
Ramanujam

CV of Proposed Document Controller-M. Shahzad


8 HGP-2023-008 4/29/2023 Submitted to S.A MMH-01409-2023-0005
Iqbal

9 HGP-2023-009 CV of Proposed Safety Supervisor-Shah Zaib 4/29/2023 Submitted to S.A Cancelled MMH-01409-2023-0006

10 HGP-2023-010 CONTRACTOR SITE SAFETY PROGRAM (CSSP) 4/30/2023 Submitted to S.A MMH-01409-2023-0007

11 HGP-2023-011 Project Quality Plan (PQP) 5/1/2023 Submitted to S.A MMH-01409-2023-0008

CV of Proposed Lead Instrumentation & Control


12 HGP-2023-012 5/3/2023 Submitted to S.A MMH-01409-2023-0009
Engineer Project Control Manager

13 HGP-2023-013 Proposed Project Organization Chart-M.M.H 5/8/2023 Submitted to S.A MMH-01409-2023-0010

14 HGP-2023-014 CV of Proposed Safety Manager-Shahid Raza 5/8/2023 Submitted to S.A MMH-01409-2023-0011

Impement S.A Comments


Submitted to S.A MMH-01409-2023-0012 & resubmit within
15 HGP-2023-015 Saudization & Training Plan-M.M.H 5/9/2023 7/9/2023
Submitted to S.A MMH-01409-2023-0040 15/days
28/05/2023

16 HGP-2023-016 Quality Management Report-QMR-001 5/10/2023 Submitted to S.A MMH-01409-2023-0014

REJECTED
Impement S.A Comments
Submitted to S.A MMH-01409-2023-0017
17 HGP-2023-017 Subcontracting Plan 5/17/2023 6/20/2023 & resubmit within
Submitted to S.A MMH-01409-2023-0034
10/days
28/05/2023

18 HGP-2023-018 RFI Drawing Number Request from iPlant (WORLEY) 5/17/2023 Submitted to S.A MMH-01409-2023-0018

Impement S.A Comments


Submitted to S.A MMH-01409-2023-0019 & resubmit within
19 HGP-2023-019 Environmental Management Plan (EMP) 5/21/2023 6/20/2023
Submitted to S.A MMH-01409-2023-0031 15/days
28/05/2023

20 HGP-2023-020 Environmental Management System (EMS) 5/21/2023 Submitted to S.A MMH-01409-2023-0020

21 HGP-2023-021 RFIs for Electrical & Instrumentation(WORLEY) 6/6/2023 Submitted to S.A MMH-01409-2023-0021

22 HGP-2023-022 Conducting the session of Project Risk Management-PRM 6/8/2023 Submitted to S.A MMH-01409-2023-0022

23 HGP-2023-023 Pre Inspection Meetings- PIM Procedure 6/10/2023 Submitted to S.A MMH-01409-2023-0023

24 HGP-2023-024 RFI-Instrument Tags Request(WORLEY) 6/12/2023 Submitted to S.A MMH-01409-2023-0025

25 HGP-2023-025 Final Inspection Disposition Procedure 6/13/2023 Submitted to S.A MMH-01409-2023-0026

26 HGP-2023-026 Proposed Work Permit Receiver 6/14/2023 Submitted to S.A MMH-01409-2023-0027

27 HGP-2023-027 Quality Management Report-QMR-002 6/15/2023 Submitted to S.A MMH-01409-2023-0029

CV of Proposed Procurement Quality Control Supervisor-


28 HGP-2023-028 6/20/2023 Submitted to S.A MMH-01409-2023-0032
PQCS-Robert M. Sanidad

29 HGP-2023-029 Contract Deliverables-DCL 6/20/2023 Submitted to S.A MMH-01409-2023-0033

30 HGP-2023-030 TCF Land Use Permit-LUP 6/21/2023 Submitted to S.A MMH-01409-2023-0036

31 HGP-2023-031 Scope Validation Log and Conflict Resolution Form 6/25/2023 Submitted to S.A MMH-01409-2023-0037

32 HGP-2023-032 RFI-Request for HVAC system DATA sheets 7/2/2023 Submitted to S.A MMH-01409-2023-0038

33 HGP-2023-033 RFI-Native files in the attached 7/5/2023 Submitted to S.A MMH-01409-2023-0039

34 HGP-2023-034 MMH-01409-2023-0041
UPDATE SHEET FOR UPGRADE BUILDING FOR RISK MITIGATION -C.NO. 6601000236 - BI 10-01409
LETTER SUBMITTAL (LETTER LOG SHEET)
SUBMISSION DATE
S.NO LETTER SUBMITTAL NO. DESCRIPTION 1ST REVISION 2ND REVISION 3RD REVISION STATUS OF SUBMITTAL DISCIPLINE TRANSMITTAL NO. REMARKS
M/D/Y

1 HGP-2023-001 MMH-Contractor Representative 2/26/2023 Submitted to S.A Info

2 HGP-2023-002 Bank Guarantee- Advance Payment 3/14/2023 Submitted to S.A Info

3 HGP-2023-003 Deign Office Mobilization 3/21/2023 Submitted to S.A Info

4 HGP-2023-004 Request Letter for no objection of Design Office 3/23/2023 Submitted to S.A Info

5 HGP-2023-005 Contract Deliverables-Corrective Action Plan 5/2/2023 Submitted to S.A Info

6 HGP-2023-006 Proposed Work Permit Receiver 6/14/2023 Submitted to S.A Info

SubContractor Worley Parson's Letter for Project Info


7 HGP-2023-007 6/25/2023 Submitted to S.A
Manager Annual Leave

8 HGP-2023-008

10

11

12

13

14

15

16

17

18

19

20

21
22
23
24
25
26
27
28
29
30
31
32