MATERIAL APPROVAL REQUEST
MAR No.: Rev. 0 0 Date: 0 8 0 2 2 0 2 5
Discipline Serial Number Day Month Year
Completion of Design & Build of Al Rawdah
Project Title : Client / Owner : Private Engineering Office (PEO)
BY & Academy Project
THE Contract Title / No. : C-P-20-05-DB-02 PMCS Consultant : GHD Global Pty Ltd.
APPLI Tadweer Trading, Contracting & Services
Prepared By : Contractor : UrbaCon Trading & Contracting
CANT W.L.L
PRQ Ref. No.:
Specification Ref.: SECTION 092900 Drawing Ref.: BOQ Ref.:
Discipline/s:
Architectural Civil/Structural Electrical Mechanical Landscape General
Infrastructure Audio / Video Instruments / Control Utilities IT Others:--------------
Item No. Material Description Notes
1 Supply & Installation of Aluminium Access Panel
Subcontractor: Tadweer Trading Contracting & Services W.L.L
Manufacturer / Supplier: Tadweer Trading Contracting & Services W.L.L Country of Origin: Qatar
Cost Impact: Yes No Time Impact: Yes No
Enclosure: Sample Data Sheet Catalogue
Specification Comparison Sheet Others ____________
For Contractor Signature
Technical Manager Project Director
Name Signature Date Name Signature Date
Mr. ALAA MAYYA Mr. TAREK ALKHATIB
Previous Submittal Revision Status (if applicable)
A- Approved B- Approved As Noted (refer footer)
C-Revise & Resubmit (refer footer) D-Rejected I-For Info Only
For PMCS Signature
Comments (refer to attached sheet for additional comments, If any)
Current Submittal Status:
A- Approved B- Approved As Noted (refer footer) C-Revise & Resubmit (refer footer) D-Rejected I-For Info Only
________________________ ________________________ ________________________
Project Manager Signature Date
For CLIENT REPRESENTATIVE Signature
______________________
________________________ ________________________
__
Project Manager Signature
Date
Corrections or Comments made relative to submittals during this review do not relieve the contractor from compliance with the requirements of contract drawings and specifications. This review is only respect of general
conformance with the design intent of the project and general compliance with the information given in the contract. The contractor remains ,responsible, among other things, for the project has design responsibility for
(if design forms part of Contract), for confirming and correlating all quantities and dimensions, selecting fabrication processes of construction, coordinating works with that trades, and performing work in a safe and
satisfactory manner, in accordance with the Contract.
DISTRIBUTION LIST
Originals Date Signature Copies Date Signature
Employer/Engineer PMCS
Contractor Others
Page 1 of 1 GHD- Material Approval Request
A-Approved | B- Approved as Noted (can proceed the work) | C-Revise & Resubmit (cannot proceed the work) | D-Rejected | I-For Information