Professional Documents
Culture Documents
Prepared For
Asian Development Bank
Under
Power Transmission Corporation of Uttarakhand Ltd
(ADB FINANCIAL ASSISTANCE PROJECT, PFR-III)
Prepared by:
Vikas Sharma
Master of Social Work &
Master of Engineering
1.0 INTRODUCTION 5
1.1 Background 11
3.2 Seismicity 19
3.4.4 Economy 21
8.0 CONCLUSION 42
9.0 ANNEXURE
Annexure- 9.3 (a) Public consultation and awareness program (in English) 71
Annexure- 9.3 (b) Public consultation and awareness program (in Hindi) 72
Annexure- 9.4 Attendance Sheet of Public Consultation 73
Annexure- 9.5 Photographs of Public Consultation 75
ADMINISTRATIVE SETUP
2. Uttarakhand has inherited its present administrative set-up from its present
state Uttar Pradesh. The facts and figure about Uttarakhand are as follows-
Divisions 2
Districts 13
Tehsils 78
Development Blocks 95
Muncipal Areas 71
Nyay Panchayat 670
Gram Panchayat 7227
Villages 16826
Based on Year 2007 figure
Infrastructure
S. No. Items Year/ Period Number
1. Important Tourist Places 2006-2007 214
2. Developed Tourist Places 2006-2007 124
3. Tourist Rest Houses 2006-2007 174
4. No. of Beds in T.R.H. 2006-2007 6764
5. Rain Baseras 2006-2007 32
6. No. of Beds in Raien Basera 2006-2007 1610
7. No. of Hotels and Paying Guest Houses 2006-2007 2312
8. No. of Dharamshala 2006-2007 802
9. The proposed transmission system has been envisaged in consultation with CEA
and other beneficiary constituents for the reliable evacuation of more than 3000 MW
Power of Lata Tapovan NTPC (171 MW), Badrinath GMR Energy (140 MW), Vishnugad
NTPC (520 MW), Pipalkoti THDC (444 MW), Devsari SJVNL (330 MW), Langrasu
UJVNL (141 MW), Bawala Nandprayag UJVNL (300 MW), Srinagar P/H GVK (330
MW), Rambhara Lanco (76 MW), Phatabyung Lanco (76 MW), Singolibhatwari L&T
(99MW) and SHPs for further distribution among beneficiary states. Some units of these
projects are scheduled to be commissioned within 11th plan followed by subsequent
units at some intervals.
10. Transmission system for these projects is of a regional/ state level collaboration
as the power from these projects would be shared by Uttarakhand and other Northern
region states such as Delhi, Himanchal Pradesh, Punjab, Rajasthan, Haryana and Uttar
Pradesh. These will be connected through the proposed Intra-State transmission
system and through existing lines/interconnection to other regions. Techno-Economic
clearance of the proposed project has been obtained from Central Electricity Authority
(CEA) vide letter no. 12A/G/2006-SP&PA/39 dated 09/01/2007(enclosed) and proposal
has been examined by Ministry of Power, GoI and found in order vide letter no.
11/5/2004-IC dated 4th May, 2007(APPENDIX 1 and APPENDIX 2).
11. For the subject, sub-project 400 KV substation Srinagar, this IEE document is
prepared on the data contained in the Environmental and Social Impact Assessment
Report submitted by PTCUL on Feb 01, 2005. There is no change in the physical
parameters of the subject in relation to its design, location, land acquisition, forest land,
capacity etc. as mentioned in the report prepared earlier. This report depicts the details
of IEE for proposed new 400 KV sub-station at Srinagar for which the land has already
been identified and is in possession with PTCUL.
12. The EIA report describes the environment in the State of Uttarakhand, where the
proposed transmission project is to be located and various measures that will be taken
by PTCUL during design, construction and maintenance stages altogether to avoid and
wherever not possible to mitigate the effect on environment of various construction
activities.
Literacy : 83%
21. The Initial Environment Examination Report has been prepared by Power
Transmission Corporation of Uttarakhand Ltd. (PTCUL) to comply with the requirements
of ADB for its Power Sector Development Loan for the Transmission Improvement
project “Transmission system associated with Alaknanda basin projects more than 3000
MW HEP being constructed by NTPC, THDC, GVK, GMR and SHPs at
Chamoli/Pauri/Udhamsingh Nagar districts of Uttarakhand state by the year 2008-2009
to 2011-2012.
22. The IEE report describes the environment in the State of Uttarakhand, where the
proposed transmission project is to be located and various measures that will be taken
by PTCUL during design, construction and maintenance stages altogether to avoid and
wherever not possible to mitigate the effect on environment of various construction
activities.
2.2 Additional Justifications for the project
23. In addition to the above justification, the overall power scenario of Uttarakhand
as described below also justifies the construction of new substation. The total proposed
pooled power at 400 KV Srinagar S/s will be more than 3000 MW. This substation will
evacuate the pooled power of generators in Alaknanda Basin which are given below:
24. Lata Tapovan NTPC (171 MW), Badrinath GMR Energy (140 MW), Vishnugad
NTPC (520 MW), Pipalkoti THDC (444 MW), Devsari SJVNL (330 MW), Langrasu
UJVNL (141 MW), Bawala Nandprayag UJVNL (300 MW), Srinagar P/H GVK (330
MW), Rambhara Lanco (76 MW), Phatabyung Lanco (76 MW), Singolibhatwari L&T
(99MW) and SHPs.
Power Transmission Corporation of Uttarakhand Ltd.
ADB Financial Assistance Project, PFR-III [Updated in April 2010] Page 17
25. After the construction of new 400 KV substation at Srinagar, Srinagar will
become the pooled power hub. Presently Srinagar town and nearby areas are feed in
radial mode through single circuit 132 KV Rishikesh- Srinagar line. Whenever there is
any breakdown or shutdown in the line there is no alternate supply on EHV system.
400/220/132 KV sub-station Srinagar will be connected with existing 132 KV substation
Srinagar, the EHV system will strengthen and reliability of the supply to the Srinagar
town and its nearby areas will be more.
26. Similarly 400/220/132 KV sub-station Srinagar will be connected with 132 KV
sub-station Simli (Karanpryag) and 132 KV sub-station Satpuli (Pauri), the EHV system
will strengthen and reliability of the supply to the Simli and Satpuli sub-stations.
Reliability of the supply to the 132 KV sub-station Kotdwar, which is an industrial area,
will also increase as it will be connected to 400/220/132 KV sub-station Srinagar
through 132 KV sub-station Satpuli.
27. Reasons of forecasted generation and demand growth
i) Due to rapid growth of the hydro power generation sector, helped by the
Nation’s special attention to the growth of Uttarakhand.
ii) Due to rapid growth of the industrial sector, helped by the Nation’s special
attention to the growth of Uttarakhand.
iii) Higher consumption in the domestic sector due to development under Govt.
APDP scheme and increasing use of modem gadgets.
iv) Also, the Government of India (GOI) has envisaged 100% electrification of
villages by the end of 11th plan i.e. by 2012 and coverage of 100%
households by the 11th plan, i.e. by 2012. At present, about 5% of the
villages needs to be electrified.
28. There is urgent need of system up gradation, this need will be fulfilled by the
ADB under the program loan. The project will help in evacuation of upcoming power
generation, operational efficiency, quality of power and reliability of the system.
2.3 Implementation Plan
29. The proposed project involves construction of new 400 KV Sub-station. Since the
land has already been acquired for the purpose, hence the land acquisition problems
are not there. The activities for the development of land are already in progress. Tender
for procurement of equipments, erection of sub-station equipments, testing and
commissioning has already being initiated and technical evaluation has been done , the
project is expected to start by the end of 2008 The project is expected to take 24-26
months for completion.
Flora
33. Ferns: Over 120 species of fern grow in damp ravines, Covered rocks and tree
trunks. Fueli Ferns grow abundantly in the monsoon month of July, August and
September.
34. Tree: The hills abound wild cherry, wild Apple, Spindle Wood, Oak, Fig, Poplar,
Holly, Rhododendron, Masuri Berry, Dogwood, Horse Chestnut and hill tuna. At higher
altitudes, forests are crowded with Himalayan cypress, Deodar, Blue pine, Fir and Long
leafed pine.
35. Acacia Arabica (Babul): This tree and other of same genus yield a gum, which is
used as substitute for gum Arabic.
36. Egle Marmelos (Bel): The fruit is a specific in atonic diarrhea and dysentery.
37. Artemisia Vulgris (Pati) : It has stomachic and tonic properties and is given in
fevers.
38. Boenning Hausenia albiflora (Pisu-ghas): Exported and used as a medicine for
poultry.
39. Bauhinia Veriegata (Kachnar): The root in decoction is useful in dyspepsia and
flatulency, the flowers with sugar as gentle laxative, and the bark, flowers or root
triturated in rice-water as a cataplasm to promote suppuration.
Fauna
44. The valleys of Garhwal are quite rich in wild life and are excellent grounds for the
naturalist. Shielded from trigger-happy populace, animals and birds abound in the thick
forests.
45. Animals: The cat family is abundant in these mountains and would include the
Tiger, Panther, Civet cat, Leopard cat and Jungle Cat. Relatives of the domesticated
dog would include the Himalayan Silver Fox and the Jackal. Various species of deer
including the Musk Deer and the Barking Deer roam in the forest. Sambhar and Gural
as well as the Bear and the Porcupine can also be seen. The flying mammal, the Bat
too is common. Among the most adorable animals in this region are the Chipmunk, the
Rhesus Monkey and the Flying Squirrel.
46. Birds: Over 400 varieties of birds have been recorded in the Himalayan region.
The shore Bird- Musphekraa forest host, the Jewel Thrush, Black headed Oriole, Black
headed yellow Bulbul, Rosy Minivet, Laughing Thrush, Golden Backed Wood pecker
and the Blue fly Catcher, Wintering waterfowl include the Goosander, Brahminy Duck &
Green Shank, Grey headed Fishing Eagles may also be seen by the river edge. After
ascending over 5000 feet, the Woodpecker, Thrush & Warbler become more common,
between 8000-11000 feet, Grosbeak, Rock Thrush, Crested black Tit & red headed
Laughing Thrush are a plenty.
3.4 Human and economic development
47. This section discusses the baseline scenario of the socio-economic environment
in the study area. The issues discussed are population, education, employment,
community services and transportation. For assessing the baseline socio-economic
data, information from secondary data sources i.e. the 2001 Census data has been
considered.
Impact on Topography
Impact on Climate
Terrestrial Ecology
Wild Life
Aquatic Ecology
• Human Environment
• Waste Disposal
58. The impacts of the project activities on various environmental attributes are
discussed in subsequent sections.
4.2.1 Impact on Physical Resources
Impact on Topography
59. During the construction of the proposed project, the topography will change due
to leveling of the proposed uneven site. The permanent change would be the presence
of substation and associated structures on the leveled land. Cutting of trees (121 no) is
minimum and its approval from forest department has already been obtained and
amount has been deposited.
Impact on Climate
60. The project involves negligible deforestation and/or vegetation. Hence impact on
climate is not anticipated.
4.2.2 Impact on Environmental Resources
Impact on Air quality
61. During the construction phase, the activities would involve excavation, movement
of transporting vehicles along the haul road (through pucca roads, but are not
maintained). All these activities would give rise to emission of dust particles thereby
affecting air quality marginally at the site which although will be transitory in nature.
Sprinkling of water during excavation will reduce the dust emission to the greater extent.
62. The project will not have any negative impact on the air quality of the region
during the operation phase.
Impact on Noise Levels
63. During the construction, the major sources of noise pollution are movement of
vehicles transporting the construction material and equipment to the site. The major
work of the construction is expected to be carried out during the day time. The noise
produced during the construction will have negligible impact on the residents of
Villagers as they are too far more over the exposure for very short period.
64. During the operation phase of the project there will noise from the substation due
to transformers operation which will be felt only up to 15 to 50 m from the substation
A. Physical
Resources
B. Environment
al Resources
1. Air Quality Due to increase of dust Direct/Loca X Watering at construction site, During
project will have l/ limited bare soils, maintenance construction
marginal impact on air reversible of vehicles activity
quality.
Proper maintenance of
equipments/ machineries so
the ambient noise standard is
met
3. Surface and Runoff from the Direct/Loca X Sedimentation ponds at the Before
Ground construction site l/ substations for waste water. construction
Water quality reversible activity
4. Soils and Soil erosion due to Direct/Loca X Stabilization of disturbed land. During and after
Geology construction activities. l/ Proper handling of construction the construction
reversible chemicals to avoid spillage. activity
C. Ecological
Resources
D. Human
Environment
6. Traffic and Traffic congestion due Direct/Local/ X Avoid high density areas, During
Transportatio to movement of reversible proper traffic signs at the construction
n construction vehicles construction site, ensuring phase
proper access roads
E Solid Waste Probability of Surface indirect/Loca X The wooden and metallic During
Disposal and ground pollution l/ reversible scrap will be collected and construction and
disposed off in compliance maintenance
with the Environmental
Protection Act, 1986, and
applicable regulations and
rules.
F Liquid (Oil) Probability of Surface indirect/Loca X The oil sludge should be During
waste and ground pollution l/ reversible separately stored in the construction and
Disposal containers and disposed off maintenance.
in compliance with the
Environmental Protection
Act, 1986, and applicable
regulations and rules.
EMSD
(Project in-
charge)
EMSD = Environmental Management and Social Department, EMP = environmental management plan, EMST =
Environmental management and Social Team, MOEF = Ministry of Environment and Forests, PIU = Project
Implementation Unit
88. During the construction and operation phase of this project, the monitoring of the
environmental aspects shall be done at the substation level by a competent officer under
guidance of the regional and corporate level offices. During the construction phase, the
prospective contractor should ensure that activities like handling of earth work, clearing
work, access road construction, putting proper traffic signals is done properly to have
minimum impact. This in turn should be monitored by the Engineer-in–Charge of the
individual substation. Preventive maintenance should be carried out to identify and
resolve problems related cooling oil, gaskets, circuit breakers, vibration measurements,
and other monitoring activities at regular intervals.
89. Monitoring of oil water separation and sanitary waste treatment should be done
periodically to avoid water pollution. Other environmental good practices include noise
abatement, maintaining hygienic conditions, maintenance of fire and safety equipment
etc. Clearing of grass should be done periodically and medium height tree plantation
around the substation wall should be done at the substation areas. Monitoring report
should be prepared once in six months with the corrective action plan for the problem
areas.
90. Overall the environmental good practices should be followed as per environmental
policy guidelines.
5.3 Environmental Management Plan
91. The main benefits of the environmental mitigation plan are (i) ensuring that
environmental standards are met during design, construction, and operation of the
project; (ii) providing offsets to negate project impacts especially ecological impacts, e.g.,
in the form of compensatory afforestation, greenbelt development and landscaping.
Without such expenditures, the project might generate large environmental impacts,
causing the biophysical environment in the area to deteriorate and indirectly depressing
the economies of local communities. No tree cutting is involved for the construction of the
substation at 400 Kv sub-station at Srinagar.
a. Summary EMP for the project components is provided in Table as Annexure- 8.
The compliance with the EMP has been prepared based upon optimum and
reasonable costs that are derived upon minimization of mitigation measures on a
“least-cost” basis.
b. The 400 KV substation project cost is 172.08 crores which includes the no land
cost, as it is government land. The EMP costs for the substation are given below
in Table 5.1 below:
92. The land has been provided by the State Government. There is no permanent or
temporary structure on the land, hence there is no resettlement. There is no tree on this
land hence no forest compensation is required.
6.0 PUBLIC INFORMATION AND CONSULTATION
93. Whenever a power transmission system is planned and put up for the
Government’s approval, a Gazette notification of the transmission scheme is made in the
state Gazette under section 29(II) of the Electricity (Supply) Act of 1948. The details of
the schemes including the locations ( villages/towns) through which it will pass should be
published in daily news papers of the area for information and to solicit comments, from
the public within stipulated period. This is to allay fears and apprehensions of people and
the objections or suggestions received, are considered in the location of the project.
Presently the public consultation is done as a part of social assessment separately to
ascertain the people’s reaction and the related issues are covered separately in the
social assessment report.
94. During the survey, public consultation has done to know the people’s perceptions
about the project and environmental problems. The purpose of the public consultation
includes the following:
96. The details of scheme including the locations (villages/towns) where the route
alignment of transmission line is proposed is published in daily news papers Amar Ujala,
Uttarakhand edition, Danik Jagran, Uttarakhand edition and Times of India , Delhi edition)
for information and to solicit comments from the public within stipulated period is given in
Annexure 9.1.
97. Information about the proposed project in English and Local language (Hindi) is
shared, which is given in Annexure 9.2 (a) & Annexure 9.2 (b).
98. Public Consultation and Awareness Program in English and Local language
(Hindi) for the proposed project is done based on certain questions, which is given in
Annexure 9.3 (a) & Annexure 9.3 (b).
100. General awareness was shared /imparted during the Public Consultation and
Awareness Program at the following villages:-
S. No. Name of Village Date No. of People
1 Khandukhal 20-08-2008 12
2 Benswada 20-08-2008 14
3 Dehalchori 20-08-2008 23
4 Maletha 21-08-2008 11
102. It is been evaluated form the impact matrix that the project will not have significant
negative environmental impacts and the project would help in improving the
socioeconomic conditions of this developing state. As the project falls in category B as
per the ADB’s guidelines, no detailed EIA study is required.
103. Based on the environmental assessment and surveys conducted for the project,
associated potential adverse environmental impacts can be mitigated to an acceptable
level by adequate implementation of the measures as stated in the IEE. Adequate
provisions should be made in the project to cover the environmental mitigation and
monitoring requirements, and their associated coasts.
104. As already mentioned, new 400 KV substation at Srinagar will evacuate the power
of under construction Hydro- electric power projects, improve operational efficiency
quality of power, reliability of the system and at the same time will reduce losses. The
transmission (400 KV Srinagar- Kashipur line) of power between the two regions
(Garhwal-Kumaon) will provide a tremendous boost to the economic and industrial
development of Uttarakhand state and will strengthen the power transmission due to
addition of this new substation at Srinagar. Overall, the major social and environmental
impacts associated with transmission project is limited to the construction period and can
be mitigated to an acceptable level by implementation of recommended measures and by
best engineering and environmental practices.
Na Area Popul Num Numb Popul Sex Popul Numb Lit Work Main Mar Non- Work Non Sche Perc Sch per
me (sq. ation ber er of ation ratio ation er of era ers work gin worke partici work dule ent edu ce
of Km.) of occup densit (famili age 6 literat cy and ers al rs patio ers d led nt
Tow hous ied y per es years es rat Non- wor n rate per Cast Trib
n e resid sq. per and age 6 e work ker (perc 1000 es es
hold ential km. 1000 above years ers s ent) work Pop Pop
s hous males and total ers ulati ulati
es ) abov work on on
e ers
Srin
agar 9.659 19861 3972 3938 159 962 14697 11916 83 5876 5236 640 13985 26.36 2671 3549 17.8 595 3.0
Srinagar 3 3 3 3 5 1 500
Name of Numb Numb Number Numb Numb Number Numb Scie Com Med Engi La adult Numb Numb
Town er of er of of er of er of of er of nce merc ical neer w literac er of er of
school school schools- school vocatio polytech colleg e ing y hostel seats
s- s- Second s- nal nics es cente s
Primar Middle ary Senior trainin offerin rs
y secon g g
dary instituti course
ons s in
Arts
Srinagar 3 5 2 8 3 1 1 1 1 1 1 1 0 4 NA
Important Drinking water Drinking water source Electricity (number of Road length (in km.)
sources capacity in liters connections)
Name Tap Well Tank Tube Ov Ser Rive Pres Do Indu Co Road Oth Surf Un Fire Dist
of wate water water well/ erh vic r sure mes stria mm lightin ers aced surfa Tot fighting anc
Town r hand ead e infilt tank tic l erci g road ced al service e( in
- tan res ratio al (point road roa s- km)
pum k erv n s) d Name
p oir gall len of
ery gth neares
t place
where
availab
le ( if
not
availab
le in
the
town
Srinag DN DN DN DN DN DN Srinag
ar √ NA √ √ A √ √ √ A A A DNA A DNA DNA A ar 11
Note: (i) NA for Not Available, (ii) DNA for Data Not Available, (iii) √ for Available
Name of Annual income of Annual expenditure Most important Most important Most important
Town the town 2007-2008 of the town 2007- commodities commodities commodities
2008 imported exported manufactured
Note: (i) NA for Not Available, (ii) DNA for Data Not Available, (iii) √ for Available
Two most prevalent systems of sewerage Number of latrines Two most prevalent methods of disposal of night
soil
Name Sew Ope Box Sky Cess Pit Oth Water Servi Oth Head Bask Whee Septi Sewe pit Oth
of er n surfa drains pool System ers borne ce ers load et l c r age syste ers
Town surfa ce method barro tank m
ce drain ws
drain s
s
Srinaga DN DN
r NA √ NA NA NA √ DNA DNA DNA A No No √ √ No √ A
Note: (i) NA for Not Available, (ii) DNA for Data Not Available, (iii) √ for Available
Involuntary Social Compensation paid for RAP implementation Consultation with PTCUL Prior to
resettlement or inequities temporary/ permanent loss affected parties— construction
land acquisition of productive land as per once in a quarter Phase
LAA & its process
Encroachment Loss of Avoid encroachment by Sub-station location Consultation with PTCUL Part of detailed
into precious precious careful site and alignment (distance to nearest local authorities— siting and
ecological ecological selection designated ecological once alignment
areas values/ protection area) survey/design
damage to
precious
species
Noise related Nuisance to Substations designed to Noise levels Noise levels to be PTCUL, Part of detailed
neighbouring ensure noise will not be a specified in tender equipment
properties nuisance. documents—once design
PTCUL Part of
detailed equipment
design
Designing Impact on Appropriate mitigation Ground condition for Part of detailed PTCUL Part of detailed
drainage pattern groundwater measures to be adopted flow of drain water design survey alignment
and nearby in the design itself to survey and
agricultural avoid accidental hazards design
field in the drainage system
Escape of Environmenta Transformers designed with Equipment Tender document PTCUL Part of detailed
polluting l oil spill containment specifications to mention equipment
materials pollution systems, and purpose-built with respect to specifications— design
oil, lubricant and fuel potential pollutants once /drawings
storage system, complete
With spill cleanup
equipment.
Substations to include Substation sewage Tender document PTCUL
drainage and sewage design to mention detailed
disposal systems to avoid specifications—
offsite land and water once
Power Transmission Corporation of Uttarakhand Ltd.
ADB Financial Assistance Project, PFR-III [Updated in April 2010] Page 54
Project activity Potential Proposed mitigation Parameter to be Measurement and Institutional Implementation
/stage impact measure monitored frequency responsibility Schedule
pollution.
Equipment Contaminatio Substations constructed Substation design to Base height as per PTCUL Part of detailed
submerged n of receptors above the high flood level account for HFL flood design - once substation
under flood (land, water) (HFL) by raising the (elevation with layout and
foundation pad. respect to HFL design
elevation) /drawings
Explosions/Fire Hazards to Design of Substations to Substation design Tender document PTCUL Part of detailed
life include modern fire control compliance with fire to mention detailed substation
systems/firewalls. prevention and specifications - layout and
control codes once design
/drawings
Rainwater Positive - - Part of detailed PTCUL Part of detailed
Harvesting Impact design survey substation
design
Uncontrolled Soil loss, Need for access tracks Design basis and Incorporating good PTCUL Part of detailed
erosion/ silt downstream minimised, use of existing construction design and substation
runoff siltation; roads. procedures construction design
(suspended solids in management
receiving waters; practices – once for
area re-vegetated in each site
m2; amount of bunds
constructed [length in
meter, area in m2, or
volume in m3])
Construction-Phase
Physical Disturbed Construction activities on Time period of • Crop disturbance- PTCUL / Construction
Construction nearby land timed to avoid available field crop post harvest Supervision Period
farming disturbance on the nearby Crops – once Consultant/
activities field crops (within 1 month
Contractor
of harvest wherever
possible)
Felled trees Disposal of cleared Use or intended use Amount of ground PTCUL/ Construction
and other vegetation as approved by of vegetation as disturbance - once Supervision Period
cleared or the statutory authorities approved by the per site Consultant/
pruned (area cleared in m2) statutory authorities Contractor
vegetation to
be disposed
of as
authorized by
the statutory
bodies
Site clearance Vegetation Tree clearances for Ground disturbance Amount of ground PTCUL/ Construction
easement establishment to during vegetation disturbance - every Supervision Period
only involve cutting trees off clearance (area, m2) 2 weeks Consultant/
at ground level or pruning Contractor
as appropriate, with tree
stumps and roots left in
place and ground cover left
undisturbed
Wood/ Loss of Construction workers Illegal wood Complaints by local PTCUL Construction
vegetation vegetation prohibited from harvesting /vegetation people or other /Supervision Period
harvesting and wood in the project area harvesting (area in evidence of illegal Consultant/
deforestation during their employment m2, number of harvesting - every 2 Contractor
(apart from locally incidents reported) weeks
employed staff continuing
current legal activities).
Surplus Runoff to Excess fill from tower Location and amount Appropriate fill PTCUL Construction
earthwork/soil cause foundation excavation (m3)of fill disposal disposal /Supervision Period
Construction disposed of next to roads or locations—every 2 Consultant/
period water around houses, in weeks Contractor
pollution, solid agreement with the local
waste community or landowner.
disposal Soil excavated from Soil disposal Acceptable soil Construction
Sub-station construction locations and volume disposal sites— Period
(m3) 1. every 2 weeks
Encroachment Loss of • Use existing access Usage of existing Complaints PTCUL/ Construction
into farmland agricultural roads wherever possible utilities received by local Supervision Period
productivity • Ensure existing irrigation Status of facilities people /authorities - Consultant/
facilities are maintained (earthwork in m3) every 2 weeks
in working condition
• Protect /preserve topsoil
and reinstate after
construction completed
• Repair /reinstate
damaged bunds etc after
construction completed
Social Compensation for
Implementation of Consultation with Contractor Construction
inequities temporary loss in
Crop compensation affected parties – Period
agricultural production (amount paid, dates, once in a quarter
etc.)
Uncontrolled Soil loss, Need for access tracks Design basis and Incorporating good PTCUL Construction
erosion/silt downstream minimised, use of existing construction design and Contractor Period
runoff siltation; roads procedures construction through
Limit site clearing to work (suspended solids in management contract
areas receiving waters; practices—once for provisions
Equipment Contaminatio Equipment stored at secure Store room level to Store room level as IA (PTCUL) Construction
submerged n of place above the high flood be above HFL per flood design— Period
under flood receptors level (HFL) (elevation difference once
(land, in meters)
water)
Inadequate Loss of land Existing borrow sites will be Contract clauses Incorporating good IA (Contractor Construction
siting of borrow values used to source aggregates, Construction through Period
areas therefore, no need to management contract
develop new sources of practices—once for provisions
aggregates each site
Public Information
General public is hereby informed that construction of Extra High Voltage, 400KV Substation at
Srinagar, District Pauri is proposed with the financial assistance of Asian Development Bank. The
purpose is to evacuate the power from the various Hydro Electric power houses under construction/
proposal nearby.
1. Sate of Uttarakhand will progress by leaps and bounce due to more power generated , as the
state will get free 12% of the generated electric power as well as the transmission charges by
transmitting the electric power. Thus the state will get more revenue and more electric power.
You all will get uninterrupted electric power supply due to this more power generated. The extra
revenue generated will be used in various development activities of state, which will increase
your living standards.
2. Construction of this substation will generate local employment, as large number of unskilled
labors (men/women) will be required at the time of construction activities. Completion period of
this project will be around 2-3 years. Local employment which you get during this period will
increase your living standards.
PTCUL Department needs your co-operation for successful completion of this project. Let us
together contribute for the prosperity of the state.
Thank You.
By-
lkoZtfud
fud lwpuk
loZlk/kkj.k dks lwfpr fd;k tkrk gS fd Jhuxj] ftyk ikSM+h esa 400 ds0oh0 ds miLFkku dk fuekZ.k
,f”k;u MoyieSaV cSad dh foRrh; lgk;rk ls fd;k tkuk izLrkfor gSA bl miLFkku ds fuekZ.k ls
vkl&ikl cuus okys fo|qr x`gksa ds mRiknu dh fudklh dh tk,xhA
vki lHkh dks fuEu fcUnqvksa ls voxr djkuk gS %&
1- fo|qr mRiknu vf/kd gksus ls mRrjk[k.M jkT; dk vR;kf/kd fodkl gksxk D;ksafd fo|qr mRiknu
dk 12 izfr”kr fgLlk jkT; dks eq¶r izkIr gksxk rFkk fo|qr ds ikjs’k.k ls ikjs’k.k “kqYd izkIr
gksxkA bl izdkj mRrjk[k.M jkT; dks jktLo ,oa fo|qr nksuksa izkIr gksxsaA vf/kd fo|qr izkIr gksus
ij vki lHkh dks fujUrj fo|qr feysxhA jkT; dk jktLo vki lHkh ds fy, fofHkUu fodkl
;kstukvksa esa mi;ksxh gksxk rFkk lHkh dk thou rj c<+sxkA
2- fo|qr ykbZuksa ds fuekZ.k ds nkSjku LFkkuh; fuokfl;ksa dks jkstxkj izkIr gksxk D;ksafd vdq”ky
Jfed ¼iq:’k ,oa efgyk½ dh fuekZ.k dk;Z ds nkSjku vR;f/kd vko”;drk gksxhA ;g ifj;kstuk
yxHkx rhu lky esa iwjh gksxhA bl vof/k esa izR;{k ,oa vizR;{k jkstxkj izkIr gksus ls vki lHkh
dk thou Lrj c<+sxkA
mijksDr ifj;kstuk ds lQy fuekZ.k gsrq foHkkx ¼fiVdqy½ dks vki lHkh dk lg;ksx pkfg,A vkbZ;s
vki vkSj ge feydj jkT; dh [kq”kgkyh esa viuk ;ksxnku nsaA
/kU;okn
}kjk%
miegkizcU/kd ikoj Vªkalfe”ku dkjiks
dkjiksjs”ku vkQ
,0Mh0ch0 ifj;kstuk dk;Z mRrjk[k.M fy0
ÅtkZ Hkou ifjlj ¼mRrjk[k.M ljdkj dk miØe½
dkaoyh jksM] nsgjknwu&248001
Qksu ua0&0135&2761587
Following General Knowledge was shared /imparted during the Public Consultation and Awareness Program.
(2) How this will benefit you personally society and state as a whole?
(4) What are the disadvantages and how these can be mitigated?
(5) Considering all the positive & negative factors, should the project be implemented or not?
tutkx:drk ,oa fopkj foe”kZ dk;ZØe ds vUrZxr fuEufyf[kr lkekU; Kku dk vnku&iznku fd;k
x;kA
1- D;k vki ifj;kstuk ls ifjfpr gSa \
2- ;g fdl izdkj vkidks O;fDrxr :i ls] lekt ,oa jkT; dks ykHkkfUor djsxk \
4- ifj;kstuk ds fuekZ.k ls D;k uqdlku gSa ,oa muds izHkko dks fdl izdkj de fd;k tk ldrk gS \
5- lHkh ldkjkRed ,oa udkjkRed igyqvksa@rF;ksa dks /;ku esa j[krs gq;s D;k ifj;kstuk dk fuekZ.k
miegkizcU/kd
,0Mh0ch0 ifj;kstuk dk;Z
ÅtkZ Hkou ifjlj
dkaoyh jksM] nsgjknwu&248001
Qksu ua0&0135&2761587
DELCHAURI
DELCHAURI
DELCHAURI
DELCHAURI
DELCHAURI