ACTIVITIES START

1 st floor column part 1


PT slab 2nd floor part 1

1 st floor column part 2


PT slab 2nd floor part 2

2 nd floor column part 1


PT slab 3 rd floor part 1

2 nd floor column part 2


PT slab 3 rd floor part 2

ceiling spray plaster BSM


Light weight concrete water tank
Block work GF 23 July 2020

FROM

Threading
Columns
Scaffolding
Concrete Casting

Strand Cutting
Strand Pushing
Chairs
Ducting
Anchors
Stressing
Grouting
PT SLAB Tape Fixing
House Keeping
MEP Box
Marking
Concrete Casting
Patching
Curing
Burlap Spreading
House Keeping
Ceiling Spray Plaster Access Making
Scaffolding

Site Preparation
Block Work
Material Shifting

GRP / Water tank Preparation


Cover block making

Also needed in daily


FINISH M CP SF H SC
25 June 2020
04 July 2020

29 June 2020
07 July 2020

12 July 2020
18 July 2020

15 July 2020
23 July 2020

23 June 2020
20 July 2020
23 August 2020

FROM 22-6-2020 UP TO 23-07-2020

B1 GF 1st / part 1 1st / part 2 2nd / part 1 2nd / part 2

12 12 12
24 24 24
14 14 14

24 24
36 27
24 18
36 24
16 12
24 24 24 24
18 24 18 24 18
6 6
3 3
6 6
12 12
25 25
12 12 12 12
14 14 14
2 2 2
40 40
8 8
18 18

12 16
18 160

20
6 6

116 260 0 120 320 283

Also needed in daily basis 4 labors for safety & 6 labors for general hous keeping
3rd / part1 3 rd / part 2

12 12 60
24 24 120
14 14 70
250
24 24 96
36 27 126
24 18 84
36 24 120
16 12 56
24 24 144
24 12 138
6 6 24
3 3 12
6 6 24
12 12 48
25 25 100
12 12 72
14 14 56
2 2 8
1108
80
16
36
132
28
178
206
20
6 6 24
44
320 277 1696
26 days
65.2307692308
need 66 Labor /day