OVER VIEW

INTRODUCTION
PLG OF RUNWAY WKS
DESIGN OF PAVEMENT AND STRENGTHENING
TYPES & CAUSES OF DEFECTS
IMP POLICY GUIDELINES ISSUED AND VALUE ADDNS
 RUNWAY RESURFACING WORKS
MAINT STRATEGY AND PREVENTIVE METHODS.
QA AND QC
CONCLUSION.
INTRODUCTION
TYPES OF PAVEMENTS
 RIGID PAVEMENTS
 FLEXIBLE PAVEMENTS
NEW CONSTRUCTIONS.
REHAB/REPAIRS OF EXISTING DISTRESSED
PAVEMENTS.
STRENGTHENING OF EXISTING PAVEMENTS
 PRIMARILY NECESSITATED BY CHANGE IN TFC
PATTERN
LAY OUT OF A TYPICAL AIRFIELD SGA
ORA

RIGID ENDS

PTT

DISPERSAL
AY
W
N
R U
SE
CO AIN
ND M LTT
AR
YR
DISPERSAL UN
WA
Y
N
I O
RT
PO
LE
IB
L EX
F
AL DISPERSAL
T R
C EN
ORP PTT - PARALLEL TAXI TR
LTT - LINK TAXI TR
RIGID ENDS
ORA - OP READINESS PLATFORM
ORA - OVER RUN AREA
ORA
SGA - SOFT GRND ARRESTER
SGA
1. Pavement Cross Section

FLEXIBLE PAVEMENT

100 mm Grade II DAC in two layers with


elastomeric PMB40/70 with min 75 %
elastic recovery(Min Marshal Stability-1400
KG)
150mm DBM Grade II in two layers with
VG-30(Min Marshal Stability-900 KG

150 mm WMM

200 mm GSB
COMPACTED SUB GRADE TO 98 %
DENSITY AT OMC

TYPICAL X-SECTION FLEXIBLE PAVEMENT


RIGID PAVEMENT
300mm PQC with minimum flexural strength of
45 Kg/cm2 using non circular synthetic fibre @.25%
by wt of cement

150mm DLC M-15

150 mm WMM

200 mm GSB
COMPACTED SUB GRADE TO 98 %
DENSITY AT OMC

400 µ POLYTHENE FILM OVER 10 MM


SAND CUSHION

TYPICAL X-SECTION RIGID PAVEMENT


COMMON DISTRESS IN CONCRETE PAVEMENTS

 DURABILITY OF CONCRETE
 SEMICIRCULAR HAIRLINE CRACKS CLOSELY SPACED
INCREASING FROM EDGES/JOINTS
 SCALING
 DUE TO HIGH WATER CONTENT IN MIXES
 DIRTY AGGREGATES
 SHRINKAGE CRACKS
 SHORT & RANDOM SPACING IN LONGITUDNAL &
TRANSVERSE DIRECTIONS
 WARPING CRACKS
 LONGITUDNAL CRACKS AT CENTRE OF SLAB
 CONTRACTION CRACKS 7
COMMON DISTRESS IN FLEXIBLE PAVEMENTS

 ALLIGATOR CRACKING/MAP CRACKING


 INDICATES EXECESSIVE MOVEMENT OF UNDERLYING LAYERS/FATIGUE
OF SURFACE
 MAY / MAYNOT BE PROGRESSIVE
 RUTS
 DUE TO CONSOLIDATION OF ANY PAVING LAYER
 SHEAR FAILURE
 NOTICED AT EDGES. OCCURES DUE TO LACK OF COHESION/INTERNAL
FRICTION BETWEEN LAYERS
 LONGITUDNAL CRACKS
 DUE TO FROST HEAVE/ VOLUME CHANGE IN SUBGRADE
 FROST HEAVE
 BLEEDING
 REFLECTION CRACKING 8
TRANSVERSE CRACKS9
10
RADIAL CRACKS
11
CORNER CRACKS
CORNER CRACKS 12
CORNER CRACKS. TEMP STRESSES, UNEQUAL EXPANSION
SHRINKAGE CRACKS 13
SHRINKAGE CRACKS 14
SCALING 15
BLEEDING

16
ALLEGATOR CRACKS

17
EXCESSIVE MOVEMENT OF UNDERLYING LAYERS
PLG OF RUNWAY RESURF
WKS

18
PLG OF RUNWAY RESURF WKS
 BD STAGE

 OVER ALL PLG OF ALL AC MVRE AREA BY AOC/STN


CDR IN CONSULTATION WITH OP STAFF KEEPING
FUTURE STRATEGIC AND TACTICAL PLAN

 ASSESSMENT OF PRESENT CONDITION

 WORKING OUT OVERALL SCOPE OF WK

 PHASING OF WK

 BRIEFING OF BD MEMBERS BY AOC/STN CDR


19
PLG OF RUNWAY RESURF WKS
ACTION BY STN AUTH

 FINALISATION OF SCOPE

 PREP OF SKETCH SHOWING PROPOSED


SCOPE OF WK
 FWD OF MET, TRAFFIC AND AC
CHARACTERISTICS DULY VETTED BY AIR
HQ/COMD OPS BRANCH TO DESIGN SUB DTE
OF E-IN-C BRANCH

20
PLG OF RUNWAY RESURF WKS

ACTION BY ENGINEERING AUTH

 PCN EVAL, CONDITION SVY, SOIL DATA TO


DESIGN SUB DTE OF E-IN-C BR BY CE
CONCERNED

 PREP OF DESIGN BY DESIGN SUB DTE

 PREP OF AE/RIC FOR BOO

 SCRUTINY OF AE/BP
21
PLG OF RUNWAY RESURF WKS

 POST ADM APPROVAL

 PREP OF TENDER DOCU BY CE CONCERNED.

 TENDER PRESENTATION BY CE TO DGW AT


E-IN-C BR

 FINALISATION OF TENDER

 PRESENTATION BY CONTRACTOR TO DGW


WITH COMPLETE EXEC PGME PRIOR TO
COMMENCEMENT OF WK 22
PLG OF RUNWAY RESURF WKS
 EXEC
SITE HANDING OVER
LABOUR CAMP AND SITE OFFICE
MTRL STK AND BP/HMP SITE
PMG
QA/QC

 FLYING DURING WK
 TAKING OVER COMPLETED WK
23
PAST LEGACY
 USE TRADITIONAL MTRL
JOINT FILLING
BITUMEN
CRACK PROPAGATION
 USE OF LOW CAPACITY PLANT & MACHINERY
CONCRETE WEIGH BATCHERS & MIXERS
PLATFORM/NEEDLE VIBRATORS
MANUAL PAVING, PAINTING ETC
 LTD CAPABILITY OF CONTRACTORS
 UNTRAINED EXECUTIVES
24
LATEST POLICY OF AIRFORCE

 MIN 5 TO 6 RW RESURFACING WKS PER YR


 THROUGH CCS ROUTE

 THROUGH AMWP ROUTE

 REF AIRCRAFT FOR DESIGN OF PAVEMENTS


 SU-30 – FIGHTERS
 IL-76/78 – TRANSPORT AIRCRAFT

 HEAVIEST CIVIL AIRCRAFT

25
LATEST POLICY OF AIRFORCE
 AWACS OPS AT SELECTED AIRFDS
 EXTN TO 3000 MTRS

 REMOVAL OF SGA

 ORA – SAME PCN AS RUNWAY

 NEW PTT- MIN 45 MTR WIDTH

 PROVN OF SUBWAYS

 PROVN OF RAPID EXIT TAXI TRACK

 FRICTION TESTING & RUBBER REMOVAL.


26
LATEST POLICY OF E-IN-C’s BRANCH
 EXEC TO BE COMPLETED IN ONE YEAR/SEASON.
 WINDOWS FOR OP OF MIL / CIV AIRCRAFT.
 NO DILUTION IN PRE QUALIFICATION CRITERIA.
 MODEL TENDER TO BE FOLLOWED.
 ACTIONS AT PRE A/A STG
 FRESH PCN EVAL, IF REQD.
 DESIGN BASED ON AC DATA & SOIL DATA.
 AEs BASED ON ACTUAL DESIGN.

27
LATEST POLICY OF E-IN-C’s BRANCH
 ACTIONS AT PRE CONTRACT STG
 PRESENTATION BY CE BEFORE TENDER
ISSUE. CHAIRED BY DGW

 CE, DIR (CONTRACT), CWE/GE


 DDGW (AIR), DDGW (DES), DDGW (PPC), JT DG
(CONTRACT), DIRECTOR (PAVEMENT)
 REP OF ACAS (WKS)/AIR COMD

 PRESENTATION BY CONTRACTOR BEFORE


COMMENCEMENT OF WK (CE IS PRESENT).

 TRG OF EXEC – SEMT WG, ON GOING WK,


SOFTWARE TOOLS. 28
POLICY ON PCN EVALUATION
•ACN – PCN REPORTING AS PER ICAO STDS.

• THE PCN (STRENGTH OF PAVEMENT) EVAL AT


AN INTERVAL OF SEVEN YEARS or WHEN A
CHANGE IS ANTICIPATED IN THE TYPE OF
AIRCRAFTS & NO OF DEPARTURES.

•RESURFACING PLAN :- IS A FALLOUT OF PCN


EVAL
• FUNCTIONAL OVERLAY
• STRUCTURAL OVERLAY
29
VALUE ADDITIONS IN RECENT PAST
 REVISION OF SSR (PAVEMENT PORTION).
 ISSUE OF MODEL TENDER.
 ONE WEEK TRG OF NEWLY POSTED GEs AT SEMT.
 OFFRS TRAINED ON PROJECT MGT COURSE BASED
ON PRIMAVERA.
 PLANT CAPACITY AND VINTAGE (NOT OLDER THAN
THREE YRS) FOR PAVEMENT WKS BEING SPECIFIED AT
DESIGN STAGE.
 SURVEY WITH TOTAL STATION.
 PRESENTATION BY CE BEFORE ISSUE OF
TENDER OF RUNWAY WKS TO ENSURE ADHERENCE TO
DESIGN SPECIFICATIONS
30
VALUE ADDITIONS IN RECENT PAST
 MODERNISATION OF SEMT LAB.
 REVISION OF E-IN-C’S TIs (1987) - UNDER PROG
 REVISED TI NO 09/2009 ON FLEXIBLE PAVEMENT :ISSUED
 TI 10/2011 ON RIGID PAVEMENT REVISED: ISSUED.
 USE OF GLASS GRIDS (POLICY ISSUED) -31 JAN 08
 USE OF JOINT SEALANTS (POLICY ISSUED)-01 JUL 08
 UNINTERRUPTED FLYING DURING OVERLAY WKS.
 NO OUTSOURCING OF PAVEMENT EVAL AND DESIGN.
 SOP ON ENHANCEMENT OF QUALITY OF - 21 MAY 07
RUNWAY CONSTRUCTION (POLICY ISSUED)
 AIRFIELD PAVEMENT MANNUAL (PUBLISHED)- 05 JUL 07

31
PCN EVALUATION

 NON DESTRUCTIVE METHOD OF PAVEMENT


EVALUATION AS PER ICAO NORMS.
 USE OF FWD/HWD
 PREVIOUS METHOD OF LCN WAS CUMBERSOME.
BASED ON EVALUATION ON THE POINT OF FAILURE.
 DEFINITION
 PCN IS THE ACN LOAD OF THE CRITICAL AIRCRAFT THAT
CONSUMES THE TOTAL STRUCTURAL PAVEMENT LIFE IN A
CERTAIN PERIOD OF TIME
 INPUTS
 EXISTING / FORECASTED TFC
 AIRCRAFT CHARACTERISTICS
 PAVEMENT DESIGN 32
 ENGINEERING EXPERIENCE
PCN EVALUATION

 FORMAT
 N/R/C/X/T
 N : PCN
 R : TYPE OF PAVEMENT
 SUBGRADE CATEGORY
 TYRE PRESSURE
 TECHNICAL EVALUATION
 PCN IS A METHOD OF EVALUATING A CONSTRUCTED PAVEMENT.
PAVEMENT CANNOT BE DESIGNED TO A SPECIFIC VALUE OF PCN.

33
QUALITY CONTROL

 CONCRETE MIX DESIGN & JOB MIX FORMULA FROM


SEMT , CRRI, IITs.
 BITUMEN & CEMENT TO BE PROCURED FROM MAIN
MANUFACTURER AS SPECIFIED IN THE CONTRACT.
 SITE LAB TO BE ESTABLISHED BY THE CONTRACTOR
WITH FACILITES FOR CARRYING OUT BASIC TESTS ON
BITUMEN, CEMENT & AGGREGATES .
 USE OF BATCH MIXING PLANTS, MIXERS, HMP & PAVERS
 ROLLING OF FLEXIBLE PAVEMENT USING TANDEM
VIBRATORY ROLLERS, PNEUMATIC ROLLERS & STATIC
ROLLERS

34
QUALITY CONTROL

 CONCRETE MIX DESIGN & JOB MIX FORMULA FROM


SEMT , CRRI, IITs.
 BITUMEN & CEMENT TO BE PROCURED FROM MAIN
MANUFACTURER AS SPECIFIED IN THE CONTRACT.
 SITE LAB TO BE ESTABLISHED BY THE CONTRACTOR
WITH FACILITES FOR CARRYING OUT BASIC TESTS ON
BITUMEN, CEMENT & AGGREGATES .
 USE OF BATCH MIXING PLANTS, MIXERS, HMP & PAVERS
 ROLLING OF FLEXIBLE PAVEMENT USING TANDEM
VIBRATORY ROLLERS, PNEUMATIC ROLLERS & STATIC
ROLLERS

35
TEMPERATURE REQUIREMENTS
STAGE OF WORK INDICATED TEMP WITH INDICATED TEMP WITH
VG 30 BITUMEN PMB

BINDER AT MIXING 150 – 165º C 170 – 180º C

MIX AT MIXING PLANT 150 – 165º C 165 – 180º C

MIX AT LAYING SITE 140 – 160º C 155 – 175º C

ROLLING AT LAYING SITE Min 100º C Min 115º C

36
IMPORTANT PARAMETERS

 CALIFORNIA BEARING RATIO (CBR)


 TEST FOR FINDING OUT QUALITY OF SUBGRADE
MTRL . EXPRESSED AS RATIO OF THE LOAD REQUIRED
FOR A STANDARD PLUNGER TO PENETRATE THE TEST
MTRL TO THAT OF A STANDARD MTRL.

 MODULUS OF SUBGRADE REACTION ‘k’ value


 COMPUTED BY STUDYING THE SETTLEMENT OF A 30”
DIA PLATE UNDER 10 PSI LOAD

37
GLASGRID INCREASES SERVICE
LIFE OF ASPHALT OVERLAYS

38
JOINT FILLING IN PROGRESS

CLEANING OF JOINTS FIXING OF BAKER ROD

APPLICATION OF PRIMER FILLING OF SEALENT


FINISHED JOINT

40
WELL MIXED FIBRE

41
ELASTOMERIC CONCRETE
 FOR QUICK AND ECONOMICAL REPAIR OF CONCRETE
PAVEMENTS
 PAVEMENT CAN BE USED AFTER 75 MINUITES.
 PATCHES CAN BE REPAIRED IN ANY SHAPE.

42
THANK YOU