Typical Spare/Consumable Parts


for Steam Turbine Startup

These instructions do not purport to cover all details or variations in equipment nor to provide for every possible
contingency to be met in connection with installation, operation or maintenance. Should further information be
desired or should particular problems arise which are not covered sufficiently for the purchaser's purposes the
matter should be referred to the GE Company.
© General Electric Company, 2010. GE Proprietary Information. All Rights Reserved.
Typical Spare/Consumable Partsfor Steam Turbine
GEK 116783 Startup

I. PURPOSE

The purpose of this document is to provide the general description of the spare parts and consumable ma-
terials that GE and GE suppliers ship to the site for steam turbine start up. Note that the spare parts and
consumable materials may vary depending on project scope. Information provided in this document is for
customer reference in the early stage of project execution.

The guidance and instruction presented in this document is generally applicable to steam turbines manu-
factured by General Electric. Since these product lines are evolving and new models are being introduced,
some turbine configurations may have additional or different spare part requirements than those described
in this document.

Commissioning and continuous operation activities may require additional spare parts not listed in this
document. These may be purchased separately. Contact the GE Project Manager for a project specific
spare parts list and quotation.

A typical consumables and spare parts list is provided in Table 1.

MLI Number Description Spare Part Name Purpose


Installation hardware
that can be re-used
Spanner Wrench,
Special Wrench for multiple unit
A10H Wrench box, Spanner
tools list installations. Typically
Socket,
1~2 each would be
shipped.
Thread Lubricants,
Material for one time
Adhesive sealants,
application of lubricants
A14H Kit Wrench and tools Coupling stud
and compounds during
lubricants, Grease,
assembly.
Eye bolt
Spare balance plugs and
Spare balancing weights Balance weight, screw weights are provided for
U190
and plugs and balance plugs field balance. Amount
varies by turbine type.
Protects the exhaust
hood and condenser
Atmospheric relief
CDDS Relief diaphragm against excessive steam
diaphragm
pressure. Typically ship
one set as spare.
For Change out of
lube oil filter elements
Lube Oil Tank /
Lube Oil Filter after system flush
PR01/PR20 Combined Lube and
Elements and commissioning.
Hydraulic Tank
Number and type vary
based on system design.

2 © General Electric Company, 2010. GE Proprietary Information. All Rights Reserved.


Typical Spare/Consumable Partsfor Steam Turbine Startup GEK 116783

For Change out of


High Pressure hydraulic oil elements
Combined lube and
Filter, Conditioning, after system flush
PR20/PR90 Hydraulic tank /
Particulate & Desiccant and commissioning.
Hydraulic Power Unit
Breather Elements Number and type vary
based on system design.
Depending on the type
of valve, the size and
quantity of gaskets and
Main stop and Reheat Gaskets, Rivets and
VV14/VV16 studs may vary. Studs
valves Studs
are used to replace
the start-up filter with
running filter.
Spare cover and gasket
would be provided with
PV21 LP Steam Strainer Spare Cover and gaskets
appropriate pressure
class.

© General Electric Company, 2010. GE Proprietary Information. All Rights Reserved. 3


Typical Spare/Consumable Partsfor Steam Turbine
GEK 116783 Startup

g
GE Energy
General Electric Company
www.gepower.com

4 © General Electric Company, 2010. GE Proprietary Information. All Rights Reserved.

You might also like