K.

P E s t i m a t e M k II

Gulf Of Thailand- 2007


Start Date MM/DD/YYYY 8/13/2007 21:00 Start KP 0
Todays Date MM/DD/YYYY 9/9/2007 7:35 Current KP 384825 178925 <- Insert KP on current pipeline
Total Days 26.440972222222 Total KP 604800
Total Hours 634.58333333333 Remaining 219975

Time Distance
Extra Days 1

Total Distance Achieved = 384825


Average Speed = (mtrs/hr) 606.421536
Total Days 43
Days Remaining 15

Finish Date 9/25/2007 10:19

Dale Naughton June 2007