You are on page 1of 1

Appendix 7.

NATIONAL HIGHWAYS AUTHORITY OF INDIA


“Consultancy Services for preparation of Report on Physical Condition of the National
Highway stretch on Toll Operate Transfer (TOT) Model.
CULVERT INSPECTION SHEET

Date : 10.08.2021 Weather: Sunny


HIGHWAY / ROAD SECTION : Eastern Peripheral Expressway
CHAINAGE : 10+840 Plan of the Structure
COORDINATES : 715567 3198745
STRUCTURE NO. :

1. CULVERT DETAILS
Type/Structure : Box Distance between Cells : -
No. of Cells : 1 Floor Details : -
Size : 3 Skew : No
Overall Width (m) : 67 Box Thickness : 0.4
Structural Condition : Good Bearing Details : -
Elevation of Structure
Direction of Flow :
(Sketch)
Depth of Stagnant Water from Invert :
2. HEADWALL/RETURN WALL DETAILS
Parapet height from road
Type/Structure
: RCC top 0.25(LHS),0.2(RHS)
Shape : Rectangular At inlet : -
Structural Condition : Good At outlet : -
At inlet : - Length : 4.0(LHS),3.5(RHS)
At outlet : -
3. WIDENING
Preferred side and reason : -
Details of Services : -
Details of Widening already carried out : -

4. INLET/OUTLET CONDITION INLET OUTLET


Scour : No
Sediment Deposits : No
Undergrowth / Other Blockages : No
Details of Protection works
Existing / Required
5. FLOOD LEVELS
Physical signs of flood
-
levels/overtopping :
Local inquiry : -
Annual flood levels : -
Max flood levels : -
Engineering’s estimate of hydraulic
-
adequacy :

6. REMARKS : New Culvert

7. RECOMMENDATIONS :