L&T Construction, Water International BU

Monthly Activity Plan


Document No: IM-WI-20-D Revision No: 00 Date: 09/09/2020 Page 1 of 2

Identity of the Project or Site/Cluster/HO : Reinforcement of Ad Dakhiliyah Water Transmission System Phase - II
Job No. (For Project/Site only) : LE200287
EHS Head/BU EHS Coordinators/CEHSM/EHSM (TF)/EHSO : Balasubramaniam
For the Month of : February Year: 2023
SUNDAY MONDAY TUESDAY WEDNESDAY THURSDAY FRIDAY SATURDAY
26-02-2023 27-02-2023 28-02-2023 01-02-2023 02-02-2023 03.02.2023 04-02-2023
Inspection of Compound wall Preparation of Fire extinguisher Inspection of full body Inspection of lifting
working @ height piping alignment MAP for the next inspection harness & PFAS on Off Day tools & tackles
activities work inspection month site store & PPE
Frontline supervisors’ Inspection Inspection of form
Housekeeping trainings. work & scaffolding
SST – Campaigns SST – working at inspection
Workmen wellness height
awareness program Weekly noise & SST – Lifting Safety SST – Chemical safety
environmental
monitoring reports

05-02-2023 06-02-2023 07-02-2023 08-02-2023 09-02-2023 10.02.2023 11-02-2023


Inspection of P&M Ladder inspection Joint inspection Inspection of first aid Safety supervisor’s Carrying out site
Equipment with client & box with site medic & development program Off Day specific mock drill
Electrical safety consultant occupational health Inspection of form
SST –Crane inspection inspection for Housekeeping work & mobile
operators Weekly noise & workmen Campaigns scaffoldings
SST – Earth environmental
moving equipment monitoring reports Internal EHS walk DG inspection
operators down. SST – go green drive
SST – Electrical waste minimization SST – Grinding
safety SST – health
awareness

Realize the Vision of “Zero Harm” by Improving EHS Performance through meaningful Engagement of Workforce
Sensitivity: LNT Construction Internal Use EHS Department – HQ, WI BU © Larsen and Toubro Limited, Construction. All Rights Reserved.
L&T Construction, Water International BU
Monthly Activity Plan
Document No: IM-WI-20-D Revision No: 00 Date: 09/09/2020 Page 2 of 2

12-02-2023 13-02-2023 14-02-2023 15-02-2023 16-02-2023 17.02.2023 18-02-2023


Environment Inspection of Inspection of low Inspection of site store Housekeeping Inspection of shutdown
inspection checklist overhead line hook tools & & peripheral areas Campaigns Off Day work areas
safety tackles lifting gears Access egress SST – welders
Inspection of arrangements on inspection on site & SST – Training for
isolation & valve pipeline Weekly noise & excavation trenches peripheral area
chambers environmental workmen on manual
SST – Manual monitoring reports SST – Excavation & handling topic
handling Trenching
SST – semiskilled
SST – Confined
workmen
space

19-02-2023 20-02-2023 21-02-2023 22-02-2023 23-02-2023 24.02.2023 25-02-2023


Preparation of Inspection of open Mobile scaffolding EHS report Evaluation of Sub Preparation of monthly
COSHH trenches & shoring inspection preparation of contractors. Off Day reports for HQ
assessment for box inspection consultant
newly received along with site Weekly noise & Client HSE Reporting
materials engineers environmental SST – Scaffolders Inspection of of SST – Pipe fit-up &
monitoring reports locations & ogc areas Welding

SST – Steel fitters SST – falling SST – Excavation SST – Fire safety
objects. safety

Balasubramaniam
DATE: 24/02/2023 ______________________________________________________
SIGNATURE OF EHS Head/BU EHS Coordinators/CEHSM/EHSM (TF)/EHSO

Realize the Vision of “Zero Harm” by Improving EHS Performance through meaningful Engagement of Workforce